AG2-238 Phase I Study Report

v1.00 released 2025-10-29 20:58

Earleys 230 kV

0.0 MW Capacity / 0.0 MW Energy

Introduction

This Phase I System Impact Study Report (PH1) has been prepared in accordance with the PJM Open Access Transmission Tariff, Part VII, Subpart D, sections 307 and 308 for New Service Requests (projects) in Transition Cycle 2. The Project Developer/Eligible Customer (developer) is Aulander Holloman Solar, LLC, and the Transmission Provider (TP) is PJM Interconnection, LLC (PJM). The interconnected Transmission Owner (TO) is Virginia Electric and Power Company (d/b/a Dominion Energy Virginia).

Preface

The Phase I System Impact Study is conducted on an aggregate basis within a New Services Request’s Cycle, and results are provided in both (i) a single Cycle executive summary format and (ii) an individual project-level basis. The Phase I System Impact Study Results (for both the executive summary and individual reports) will be publicly available on PJM’s website. Developers must obtain the results from the website.

In accordance with PJM Manual 14H, section 4.3, PJM takes the following actions during the Phase I System Impact Study:
  1. PJM studies each New Service Request on a summer peak, winter peak and light load RTEP base case study. The case year is dependent on the new services cycle under study. PJM will identify the base case year to be used in the study of a specific cycle on its website.
  2. PJM will only perform load flow analysis during the Phase I System Impact Study.
  3. In Phase I of the Cycle, PJM conducts an Affected System screen to identify any New Service Request with Affected System impacts and provides each Affected System Operator with a list of New Service Request in the Cycle with potential impacts to their respective system.
  4. PJM will create both the short circuit and stability base cases to be used in the Phase II System Impact Study.
  5. The Phase I System Impact Study results will be publicly available on PJM’s website. Project Developers and Eligible Customers must obtain the results from the website.
The Transmission Owner takes the following actions during the Phase I System Impact Study:
  1. Identify required Interconnection Facilities to accommodate the New Service Request.
  2. Identify required Network Upgrades to mitigate system violations from the Phase I System Impact Study.
  3. Provide planning-level preliminary estimates of Interconnection Facilities and Network Upgrades including scope, cost and elapsed time to complete the work.

Decision Point I Requirements

At the close of Phase I System Impact Study, PJM will initiate Decision Point I (DP1). During DP1, the Project Developer will have 30 days to decide whether to proceed with their project. If the Project Developer elects to proceed, they should provide the elements defined in the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 309.A.1. Additional information on these elements is available in PJM Manual 14H sections 4.4, 6, and 7.

Allowable project modifications at Decision Point I are defined in PJM Open Access Transmission Tariff, Part VII, Subpart D, section 309.B. Additional information regarding allowable project modifications can be found in PJM Manual 14H, section 9.8.

General

The Project Developer has proposed an uprate to a planned/existing Solar facility located in the Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) zone — Hertford County, North Carolina. This project is an increase to the developer’s AA1-065/AE1-035 project(s), which will share the same Point of Interconnection. The AG2-238 project is a 0.0 MW uprate (0.0 MW Capacity uprate) to the previous project(s). The total installed facilities will have a capability of 99.9 MW with 67.0 MW of this output being recognized by PJM as Capacity.

Project Information
New Service Request Number:
AG2-238
Project Name:
Earleys 230 kV
Project Developer Name:
Aulander Holloman Solar, LLC
State:
North Carolina
County:
Hertford
Transmission Owner:
Virginia Electric and Power Company (d/b/a Dominion Energy Virginia)
MFO:
99.9
MWE:
0.0
MWC:
0.0
Battery Storage Specification:
200.0 MWh, 4.0-hr class
Grid Charging:
Yes
Fuel Type:
Storage
Basecase Study Year:
2028

Physical Interconnection Facility Study

Physical Interconnection Facilities Study is not performed as part of the Phase I System Impact Study. Physical Interconnection Facilities Study will commence in the Phase II System Impact Study.

Point of Interconnection

AG2-238 will interconnect on the Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) transmission system as an uprate to AA1-065 and AE1-035 sharing the POI and Attachment Facilities.

Cost Summary

The table below shows a summary of the total cost estimates for this New Service Request project. In the Phase I SIS, the costs shown are subject to change as a result of a facility study performed by the TO during the Phase II or Phase III System Impact Study.

Based on the Phase I SIS results, the AG2-238 project has the following allocation of costs for interconnection. The cost contribution towards Readiness Deposit are also shown below.

Cost Summary
DescriptionCost Allocated to AG2-238Cost Subject to Readiness*
Transmission Owner Interconnection Facilities (TOIF)$0$0
Other Scope$0$0
Option To Build Oversight$0$0
Physical Interconnection Network Upgrades
Stand Alone Network Upgrades$0$0
Network Upgrades$0$0
System Reliability Network Upgrades
Steady State Thermal & Voltage (SP & LL)$0$0
Transient Stability$0$0
Short Circuit$0$0
Transmission Owner Analysis
SubRegional$0$0
Distribution$0$0
Affected System Reinforcements
AFS - PJM Violatons$0$0
AFS - Non-PJM Violations$0$0
Total$0$0

* Contributes to calculation for Readiness Deposit #2 (RD2). See Readiness Deposit section of report for additional detail.

Definitions

Transmission Owner Interconnection Facilities: Facilities that are owned, controlled, operated and maintained by the Transmission Owner on the Transmission Owner’s side of the Point of Change of Ownership to the Point of Interconnection, including any modifications, additions or upgrades made to such facilities and equipment, that are necessary to physically and electrically interconnect the Generating Facility with the Transmission System or interconnected distribution facilities.

Stand Alone Network Upgrades: Network Upgrades, which are not part of an Affected System, which a Project Developer may construct without affecting day-to-day operations (e.g. taking a transmission outage) of the Transmission System during their construction.

Network Upgrades: Modifications or additions to transmission-related facilities that are integrated with and support the Transmission Provider’s overall Transmission System for the general benefit of all users of such Transmission System. Network Upgrades have no impact or potential impact on the Transmission System until the final tie-in is complete.

Notes

Note 1: PJM Open Access Transmission Tariff (OATT), Part VII, Subpart D, section 307.5 outlines cost allocation rules. The rules are further clarified in PJM Manual 14H, section 4.2.6. PJM shall identify the New Service Requests in the Cycle contributing to the need for the required Network Upgrades within the Cycle. All New Service Requests that contribute to the need for a Network Upgrade will receive cost allocation for that upgrade pursuant to each New Service Request’s contribution to the reliability violation identified on the transmission system in accordance with PJM Manuals.

Note 2: There will be no inter-Cycle cost allocation for Interconnection Facilities or Network Upgrades identified in the System Impact Study costs identified in a Cycle; all such costs shall be allocated to New Service Requests in that Cycle.

Note 3: For Project Developers with System Reinforcements listed: If this project presents cost allocation to a System Reinforcement indicates $0, then please be aware that as changes to the interconnection process occur, such as other projects withdrawing, reducing in size, etc, the cost responsibilities can change and a cost allocation may be assigned to this project. In addition, although this project presents cost allocation to a System Reinforcement is presently $0, this project may need this system reinforcement completed to be deliverable to the PJM system. If this project desires to come into service prior to completion of the system reinforcement, the Project Developer will need to request PJM to perform an interim deliverability study to determine if they would be deliverable for all or a portion of their output for each delivery year until the system reinforcement is complete.

Readiness Deposit

Per Tariff Part VII, Subpart D, section 309 (Decision Point I) A.1.a.i and PJM Manual 14H, section 6.2, Readiness Deposit #2 (RD2) are funds committed by the Project Developer or Eligible Customer based upon the applicable contribution to Network Upgrades as defined below. Readiness Deposits are not used to fund studies nor to offset Security.

During Decision Point I (DP1), the Project Developer or Eligible Customer is required to submit Readiness Deposit #2, which is calculated as 10% of cost allocation for required Phase I Network Upgrades minus Readiness Deposit #1.

Note 1: “Network Upgrades” referred to in the calculation include both (i) the Physical Interconnection Network Upgrades and (ii) the System Reliability Network Upgrades as shown in the Cost Summary table.

Note 2: Readiness Deposit #1 (RD1) = ($4,000 * Project Size (MW))

Note 3: Readiness Deposit #2 (RD2) = 10% of cost allocation for required Network Upgrades minus RD1. Readiness Deposit #2 (RD2) can be zero, but may not be a negative number.

Readiness Deposit #2 Due for Project AG2-238

Readiness Deposit #2 has been calculated for the project based on the Phase I System Impact Study results and is shown in the table below. This Readiness Deposit #2 must be provided at Decision Point I through either a wire transfer or letter of credit per Manual 14H, Section 6.2.

Readiness Deposit
Project ID10% of cost allocation for Phase I Network UpgradesReadiness Deposit #1 Received (RD1)Readiness Deposit #2 (RD2) for AG2-238 Project due at DP1
ABA - B
AG2-238$0$200,000$0

Note: Failure to provide an acceptable form of Readiness Deposit #2 by the end of Decision Point I will result in withdrawal and termination of the New Service Request.

For additional detail regarding Readiness Deposit Refunds, reference PJM Manual 14H, section 6.2.1. The Readiness Deposit Letter of Credit template can be found here.

Transmission Owner Scope of Work

The total preliminary cost estimate for the Transmission Owner scope of work (including TOIF and Physical Interconnection Network Upgrades) is given in the table below. These costs do not include CIAC Tax Gross-up.

Transmission Owner Interconnection Facilities
RTEP IDDescriptionTotal Cost ($USD)Allocated Cost ($USD)
(Pending)AG2-238 is sharing a POI and the TOIF with AA1-065 and AE1-035, so there are no associated interconnection costs for this project.$0 $0

Based on the scope of work for the Interconnection Facilities, it is expected to take a range of 46 to 50 month(s) after the signing of a Generator Interconnection Agreement (as this is a FERC connection) and construction kickoff call to complete the installation of the physical connection work. This assumes that there will be no environmental issues with any of the new properties associated with this project, that there will be no delays in acquiring the necessary permits for implementing the defined interconnection work, and that all system outages will be allowed when requested.

The schedule for any required Network Impact Reinforcements will be more clearly identified in the Phase II and Phase III System Impact Studies.

Transmission Owner Analysis

PJM performed a power flow analysis of the transmission system using a 2028 load flow model and the results were verified by Dominion.

 

Developer Requirements

The developer is responsible for all design and construction related activities on the developer’s side of the Point of Change in Ownership. Dominion interconnection requirements can be found here.

To the extent that these Applicable Technical Requirements and Standards may conflict with the terms and conditions of the Tariff, the Tariff shall control.

Revenue Metering and SCADA Requirements

PJM Requirements
The developer will be required to install equipment necessary to provide Revenue Metering (KWH, KVARH) and real time data (KW, KVAR) for their generating Resource. See PJM Manual 01, PJM Manual 14D, and PJM Tariff Part IX, Subpart B, Appendix 2, section 8.
Transmission Owner Requirements
The Project Developer will be required to comply with all interconnected Transmission Owner’s revenue metering requirements located at the following link: PJM - Transmission Owner Engineering & Construction Standards.

Summer Peak Analysis

The New Service Request AG2-238 was evaluated as a 0.0 MW (0.0 MW Capacity) injection in the Dominion area.

AG2-238 was evaluated as part of a plant. The plant consists of AG2-238. The total Energy output of the plant was evaluated at its maximum seasonal capability of 99.9 MW (0.0 MW under study).

Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.

(No impacts were found for this analysis)

Winter Peak Analysis

The New Service Request AG2-238 was evaluated as a 0.0 MW (0.0 MW Capacity) injection in the Dominion area.

AG2-238 was evaluated as part of a plant. The plant consists of AG2-238. The total Energy output of the plant was evaluated at its maximum seasonal capability of 99.9 MW (0.0 MW under study).

Note: The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for single or N-1 contingencies and multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.

(No impacts were found for this analysis)

Light Load Analysis

The New Service Request AG2-238 was evaluated as a 0.0 MW injection and 50.0 MW withdrawal in the Dominion area.

AG2-238 was evaluated as part of a plant. The plant consists of AG2-238. The total Energy output of the plant was evaluated at its maximum seasonal capability of 99.9 MW (46.27 MW under study).

Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.

StudyAreaFacility DescriptionContingency NameContingency TypeDC|ACFinal Cycle LoadingRating (MVA)Rating TypeMVA to MitigateMW ContributionDetails
GD2CPLE/DVP
3BTLEBRO-3ROCKYMT115T 115.0 kV Ckt 1 line
DVP_P7-1: LN 2058-2181_SRT-A
TowerAC110.6 %313.0B346.173.21

Details for 3BTLEBRO-3ROCKYMT115T 115.0 kV Ckt 1 line l/o DVP_P7-1: LN 2058-2181_SRT-A


Base Case Flowgate

Area:CPLE/DVP
Facility Description:
3BTLEBRO-3ROCKYMT115T 115.0 kV Ckt 1 line
Contingency Name:
DVP_P7-1: LN 2058-2181_SRT-A
Contingency Type:Tower
DC|AC:AC
Final Cycle Loading:110.6 %
Rating:313.0 MVA
Rating Type:B
MVA to Mitigate:346.17
MW Contribution:3.21
Bus #Bus NameTypeMW Contribution
3147043LAWRENC
Solar/Wind Harmer
0.101
316317KELFORD C
Solar/Wind Harmer
0.154
3156081AA2-088 GEN
Solar/Wind Harmer
0
316011AB1-132 GEN
Solar/Wind Harmer
-1.065
316463AE2-346 GEN
Solar/Wind Harmer
-0.223
316065AD1-022 GEN
Solar/Wind Harmer
2.678
3145513AHOSKIE
Solar/Wind Harmer
0.253
3145513AHOSKIE
Solar/Wind Harmer
0.253
3145746EVERETS
Solar/Wind Harmer
0.698
3145746EVERETS
Solar/Wind Harmer
0.175
3145746EVERETS
Solar/Wind Harmer
0.175
3145746EVERETS
Solar/Wind Harmer
0.175
3145746EVERETS
Solar/Wind Harmer
0.175
3145746EVERETS
Solar/Wind Harmer
0.175
3145746EVERETS
Solar/Wind Harmer
0.175
3145746EVERETS
Solar/Wind Harmer
0.175
3146206CASHIE
Solar/Wind Harmer
0.174
3146206CASHIE
Solar/Wind Harmer
0.174
3146206CASHIE
Solar/Wind Harmer
0.174
3142666NORTHAMPTON
Solar/Wind Harmer
0.3
3142666NORTHAMPTON
Solar/Wind Harmer
0.3
3142666NORTHAMPTON
Solar/Wind Harmer
0.3
3142666NORTHAMPTON
Solar/Wind Harmer
0.3
3142666NORTHAMPTON
Solar/Wind Harmer
0.18
3156021HOLLOMANSOL
Solar/Wind Harmer
-0.299
315652AC1-086 GEN
Solar/Wind Harmer
11.295
316359AB2-059 GEN
Solar/Wind Harmer
0
316263AC1-034 GEN
Solar/Wind Harmer
18.042
316140AB2-099
Solar/Wind Harmer
-0.093
3145543BTLEBRO
Solar/Wind Harmer
1.274
3145543BTLEBRO
Solar/Wind Harmer
1.274
3145543BTLEBRO
Solar/Wind Harmer
1.274
3145543BTLEBRO
Solar/Wind Harmer
1.019
3145593CAROLNA
Solar/Wind Harmer
0.3
3145593CAROLNA
Solar/Wind Harmer
0.3
3145593CAROLNA
Solar/Wind Harmer
0.084
3145683EARLEYS
Solar/Wind Harmer
0.519
3145683EARLEYS
Solar/Wind Harmer
0.26
3145683EARLEYS
Solar/Wind Harmer
0.26
3145683EARLEYS
Solar/Wind Harmer
0.26
3137643SOCKMAN
Solar/Wind Harmer
1.123
3138543CONSLDL
Solar/Wind Harmer
0.75
3142053HEARTS
Solar/Wind Harmer
0.477
3145453TOT5
Solar/Wind Harmer
0.136
3145493TOT1
Solar/Wind Harmer
0.434
3145493TOT1
Solar/Wind Harmer
0.226
3145573BETHELC
Solar/Wind Harmer
0.434
3145573BETHELC
Solar/Wind Harmer
0.434
3145603CNETO
Solar/Wind Harmer
0.09
3145783HORNRTN
Solar/Wind Harmer
1.459
3145783HORNRTN
Solar/Wind Harmer
1.167
3145783HORNRTN
Solar/Wind Harmer
0.365
3145783HORNRTN
Solar/Wind Harmer
0.365
3145783HORNRTN
Solar/Wind Harmer
0.146
3145796HORNRTN
Solar/Wind Harmer
1.413
3145796HORNRTN
Solar/Wind Harmer
1.166
3145796HORNRTN
Solar/Wind Harmer
1.13
3145796HORNRTN
Solar/Wind Harmer
1.06
3145796HORNRTN
Solar/Wind Harmer
0.353
3145796HORNRTN
Solar/Wind Harmer
0.353
3145796HORNRTN
Solar/Wind Harmer
0.141
3145823KELFORD
Solar/Wind Harmer
0.406
3145823KELFORD
Solar/Wind Harmer
0.406
3145893MURPHYS
Solar/Wind Harmer
0.934
3145893MURPHYS
Solar/Wind Harmer
0.747
3145893MURPHYS
Solar/Wind Harmer
0.63
3145893MURPHYS
Solar/Wind Harmer
0.42
3145893MURPHYS
Solar/Wind Harmer
0.233
3145893MURPHYS
Solar/Wind Harmer
0.233
3145893MURPHYS
Solar/Wind Harmer
0.233
3145893MURPHYS
Solar/Wind Harmer
0.187
3145933PARMELE
Solar/Wind Harmer
0.344
3145933PARMELE
Solar/Wind Harmer
0.172
3145933PARMELE
Solar/Wind Harmer
0.172
3145963POPLR C
Solar/Wind Harmer
0.164
3145963POPLR C
Solar/Wind Harmer
0.164
3146033SCOT NK
Solar/Wind Harmer
2.207
3146043SEABORD
Solar/Wind Harmer
0.264
3146073TAR RVR
Solar/Wind Harmer
0.434
3146083TARBORO
Solar/Wind Harmer
0.434
3146083TARBORO
Solar/Wind Harmer
0.434
3146173TUNIS
Solar/Wind Harmer
0.246
3146173TUNIS
Solar/Wind Harmer
0.246
3146173TUNIS
Solar/Wind Harmer
0.246
3146173TUNIS
Solar/Wind Harmer
0.246
3146233WITAKRS
Solar/Wind Harmer
4.447
3146233WITAKRS
Solar/Wind Harmer
2.682
3146233WITAKRS
Solar/Wind Harmer
0.76
3146263WOODLND
Solar/Wind Harmer
0.271
3146263WOODLND
Solar/Wind Harmer
0.271
3146293MARTNCO
Solar/Wind Harmer
0.036
316318V4-068
Solar/Wind Harmer
0
960081AF2-299 GEN
Solar/Wind Harmer
0.792
961601AG1-000A GEN
Solar/Wind Harmer
8.4
961601AG1-000A GEN
Solar/Wind Harmer
11.587
961671AG1-007 GEN
Solar/Wind Harmer
0.815
961681AG1-008 GEN
Solar/Wind Harmer
5.979
961941AG1-037 GEN
Solar/Wind Harmer
0.144
962331AG1-082 GEN
Solar/Wind Harmer
1.013
962331AG1-082 GEN
Solar/Wind Harmer
0.59
962571AG1-106 GEN
Solar/Wind Harmer
0.886
966801AG1-551 GEN
Solar/Wind Harmer
0.687
966811AG1-552 GEN
Solar/Wind Harmer
1.081
970181AG2-120 GEN
Solar/Wind Harmer
0.736
970601AG2-382 GEN
Solar/Wind Harmer
2.439
970831AG2-522 GEN
Solar/Wind Harmer
1.472
971547AH1-271 GEN
Solar/Wind Harmer
1.394
957521AF2-046 GEN
Solar/Wind Harmer
5.979
957861AF2-080 GEN
Solar/Wind Harmer
4.399
965291AG1-394 GEN
Solar/Wind Harmer
0.628
971795AH1-408 GEN
Solar/Wind Harmer
4.433
970359AG2-237 GEN
Solar/Wind Harmer
9.963
970361AG2-238 GEN
Solar/Wind Harmer
3.207
971263AH1-091 GEN
Solar/Wind Harmer
0.94
G-007ALTFEXP_G-007A->PJM
CMTX
0.124
VFTLTFEXP_VFT->PJM
CMTX
0.313
NYPJM->LTFIMP_NY
CLTF
0.014
GibsonPJM->LTFIMP_GIBSON
CLTF
0
HAMLETPJM->LTFIMP_HAMLET
CLTF
1.672
CATAWBAPJM->LTFIMP_CATAWBA
CLTF
0.841
PRAIRIEPJM->LTFIMP_PRAIRIE
CLTF
2.912
TRIMBLEPJM->LTFIMP_TRIMBLE
CLTF
0.536
CALDErWOODPJM->LTFIMP_CALDERWOOD
CLTF
0
CHEOAHPJM->LTFIMP_CHEOAH
CLTF
0
BlueGrassPJM->LTFIMP_BlueG
CLTF
1.684
MDUPJM->LTFIMP_MDU
CLTF
0
CONTINGENCY 'DVP_P7-1: LN 2058-2181_SRT-A'
 OPEN BRANCH FROM BUS 304222 TO BUS 313845 CKT 1   /*6ROCKYMT230T 230.0 - 6HATHAWAY    230.0
 OPEN BRANCH FROM BUS 304226 TO BUS 314591 CKT 1   /*6PA-RMOUNT#4 230.0 - 6NASH        230.0
 OPEN BRANCH FROM BUS 313844 TO BUS 313845 CKT 2   /*3HATHAWAY    115.0 - 6HATHAWAY    230.0
 OPEN BRANCH FROM BUS 313845 TO BUS 314591 CKT 1   /*6HATHAWAY    230.0 - 6NASH        230.0
 OPEN BUS 304226                                   /*6PA-RMOUNT#4 230.0
 OPEN BUS 314591                                   /*6NASH        230.0
END
314554 to 304223 ckt 1

Short Circuit Analysis

Short Circuit analysis is not performed as part of the Phase I System Impact Study. Short Circuit analysis will commence in the Phase II System Impact Study.

Stability Analysis

Stability analysis is not performed as part of the Phase I System Impact Study. Stability analysis will commence in the Phase II System Impact Study.

Reactive Power Analysis

Reactive Power analysis is not performed as part of the Phase I System Impact Study. Reactive Power analysis will commence in the Phase II System Impact Study.

Steady-State Voltage Analysis

Steady State Voltage Analysis is Not Required.

New Service Request Dependencies

The New Service Requests below are listed in one or more dispatch for the overloads identified in this report. These projects contribute to the loading of the overloaded facilities identified in this report. The percent overload of a facility and cost allocation you may have towards a particular reinforcement could vary depending on the action of other projects. The status of each project at the time of the analysis is presented in the table. This list may change as other projects withdraw or modify their requests. This table is valid for load flow analyses only.

New Service Requests Dependencies
Project IDProject NameStatus
AB1-132Thelma 230kVIn Service
AB2-059Benson-Dunbar 115kVIn Service
AB2-099Ahoskie 34.5kVIn Service
AC1-034Heartsease DP - Mayo Dunbar 115kVSuspended
AC1-086Thelma 230kVSuspended
AD1-022Cashie-Trowbridge 230 kVEngineering & Procurement
AE2-346Ahoskie 34.5 kVIn Service
AF2-046Tunis-Mapleton 115 kVActive
AF2-080Chinquapin-Everetts 230 kVActive
AF2-299Fields 34.5 kVActive
AG1-007Tar River 12.5 kVEngineering & Procurement
AG1-008Tunis-Mapleton 115 kVActive
AG1-037Ahoskie 34.5 kVEngineering & Procurement
AG1-082Ahoskie 34.5 kVActive
AG1-106Thelma 230 kVActive
AG1-394Boykins 34.5 kVActive
AG1-551Parmele 34.5 kVActive
AG1-552Carolina 34.5 kVActive
AG2-120Everetts 34.5 kVActive
AG2-237Thelma 230kVActive
AG2-382Cashie 230 kVActive
AG2-522Five Forks DP 115 kVActive
AH1-091Ahoskie 34.5kVActive
AH1-271Cashie 230 kVActive
AH1-408Freeman DP – Lawrenceville 115 kVActive
V4-068Murphy's 34.5kVIn Service

Affected System - PJM Identified Violations

As part of PJM's analysis, PJM evaluated the potential impacts on tie line facilities between PJM and an affected system entity, which were identified per PJM planning analysis criteria. This upgrade may be required on the affected system portion of the tie line along with cost allocation of such upgrade if applicable, in coordination with the affected system. Depending on the affected system, this project may not be contingent on upgrade based on PJM planning analysis criteria, but may be contingent on this upgrade based on the Affected System Operator's planning criteria, provided in the Affected Systems Study Section, herein.

Midcontinent Independent System Operator, Inc. (MISO)No Impact
New York Independent System Operator (NYISO)No Impact
Tennessee Valley Authority (TVA)No Impact
Louisville Gas & Electric (LG&E)No Impact
Duke Energy Carolinas (DUKE)No Impact
Duke Energy Progress – East (CPLE)No Impact
Duke Energy Progress – West (CPLW)No Impact

Affected System - Non-PJM Identified Violations

In Phase I of the Cycle, PJM conducts an Affected System screen to identify any New Service Request with potential Affected System impacts. PJM initiates coordination with each Affected System Operator by providing a list of New Service Requests in the Cycle with potential impacts to their respective system. If the Affected System Operator indicates an Affected System Study is required, PJM will notify the Project Developer or Eligible Customer of the need for an Affected System Study. See below if any Affected System Operator requires a study for this project:

Midcontinent Independent System Operator, Inc. (MISO)Not required
New York Independent System Operator (NYISO)Not required
Tennessee Valley Authority (TVA)Not required
Louisville Gas & Electric (LG&E)Not required
Duke Energy Carolinas (DUKE)Study Pending
Duke Energy Progress – East (CPLE)Not required
Duke Energy Progress – West (CPLW)Not required

System Reinforcements

No cost allocated system reinforcements were identified for this project in the Phase I System Impact Study load flow analysis.

Shown below are the details of the cost allocated, contingent, eliminated, topology and potential aggregate contributor reinforcements for this project. Please refer to the System Reinforcement table above and the information below for more detail.


System Reinforcement
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
(Pending)
Title
Dominion facility ratings: 379/390/449 MVA Winter | 372/384/441 MVA LL | 342/352/405 MVA Summer.
Description
Dominion facility ratings: 379/390/449 MVA Winter | 372/384/441 MVA LL | 342/352/405 MVA Summer.
Total Cost ($USD)
$0
Allocated Cost ($USD)
$0
Time Estimate
TBD

Note: This reinforcement is fictitious and will not be cost allocated to projects. It is listed for information purposes only.

FacilityContingency
3ROCKYMT115T-3BTLEBRO 115.0 kV Ckt 1 line(Any)

Attachments

AG2-238 One Line Diagram

AG2-238 One Line Diagram.pdf
The state in which the generator or merchant transmission facility is located.
The Transmission Owner of the facility where the New Service Request project interconnects to the transmission system.
Winter load flow analysis will be performed starting in Transition Cycle 2.