AG2-532 Phase I Study Report
v1.00 released 2025-10-29 20:14
Pohatcong-Newburgh Tap 34.5 kV
0.0 MW Capacity / 20.0 MW Energy
Introduction
This Phase I System Impact Study Report (PH1) has been prepared in accordance with the PJM Open Access Transmission Tariff, Part VII, Subpart D, sections 307 and 308 for New Service Requests (projects) in Transition Cycle 2. The Project Developer/Eligible Customer (developer) is V20 Mansfield LLC, and the Transmission Provider (TP) is PJM Interconnection, LLC (PJM). The interconnected Transmission Owner (TO) is Jersey Central Power & Light Company.
Preface
The Phase I System Impact Study is conducted on an aggregate basis within a New Services Request’s Cycle, and results are provided in both (i) a single Cycle executive summary format and (ii) an individual project-level basis. The Phase I System Impact Study Results (for both the executive summary and individual reports) will be publicly available on PJM’s website. Developers must obtain the results from the website.
In accordance with PJM Manual 14H, section 4.3, PJM takes the following actions during the Phase I System Impact Study:
- PJM studies each New Service Request on a summer peak, winter peak and light load RTEP base case study. The case year is dependent on the new services cycle under study. PJM will identify the base case year to be used in the study of a specific cycle on its website.
- PJM will only perform load flow analysis during the Phase I System Impact Study.
- In Phase I of the Cycle, PJM conducts an Affected System screen to identify any New Service Request with Affected System impacts and provides each Affected System Operator with a list of New Service Request in the Cycle with potential impacts to their respective system.
- PJM will create both the short circuit and stability base cases to be used in the Phase II System Impact Study.
- The Phase I System Impact Study results will be publicly available on PJM’s website. Project Developers and Eligible Customers must obtain the results from the website.
The Transmission Owner takes the following actions during the Phase I System Impact Study:
- Identify required Interconnection Facilities to accommodate the New Service Request.
- Identify required Network Upgrades to mitigate system violations from the Phase I System Impact Study.
- Provide planning-level preliminary estimates of Interconnection Facilities and Network Upgrades including scope, cost and elapsed time to complete the work.
Decision Point I Requirements
At the close of Phase I System Impact Study, PJM will initiate Decision Point I (DP1). During DP1, the Project Developer will have 30 days to decide whether to proceed with their project. If the Project Developer elects to proceed, they should provide the elements defined in the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 309.A.1. Additional information on these elements is available in PJM Manual 14H sections 4.4, 6, and 7.
Allowable project modifications at Decision Point I are defined in PJM Open Access Transmission Tariff, Part VII, Subpart D, section 309.B. Additional information regarding allowable project modifications can be found in PJM Manual 14H, section 9.8.
General
The Project Developer has proposed a Storage facility located in the Jersey Central Power & Light Company zone — Warren County, New Jersey. The installed facilities will have a total capability of 20.0 MW with 0.0 MW of this output being recognized by PJM as Capacity.Project Information
Physical Interconnection Facility Study
Physical Interconnection Facilities Study is not performed as part of the Phase I System Impact Study. Physical Interconnection Facilities Study will commence in the Phase II System Impact Study.
Point of Interconnection
AG2-532 will interconnect on the Jersey Central Power & Light Company distribution system tapping the Pohatcong – Newburgh 34.5 kv line Q719-5 ckt.
Cost Summary
The table below shows a summary of the total cost estimates for this New Service Request project. In the Phase I SIS, the costs shown are subject to change as a result of a facility study performed by the TO during the Phase II or Phase III System Impact Study.
Based on the Phase I SIS results, the AG2-532 project has the following allocation of costs for interconnection. The cost contribution towards Readiness Deposit are also shown below.
| Cost Summary | |||
|---|---|---|---|
| Description | Cost Allocated to AG2-532 | Cost Subject to Readiness* | |
| Transmission Owner Interconnection Facilities (TOIF) | $925,715 | $0 | |
| Other Scope | $57,200 | $0 | |
| Option To Build Oversight | $0 | $0 | |
| Physical Interconnection Network Upgrades | |||
| Stand Alone Network Upgrades | $1,074,135 | $1,074,135 | |
| Network Upgrades | $150,150 | $150,150 | |
| System Reliability Network Upgrades | |||
| Steady State Thermal & Voltage (SP & LL) | $0 | $0 | |
| Transient Stability | $0 | $0 | |
| Short Circuit | $0 | $0 | |
| Transmission Owner Analysis | |||
| SubRegional | $39,796,796 | $39,796,796 | |
| Distribution | $0 | $0 | |
| Affected System Reinforcements | |||
| AFS - PJM Violatons | $0 | $0 | |
| AFS - Non-PJM Violations | $0 | $0 | |
| Total | $42,003,996 | $41,021,081 | |
* Contributes to calculation for Readiness Deposit #2 (RD2). See Readiness Deposit section of report for additional detail.
Definitions
Transmission Owner Interconnection Facilities: Facilities that are owned, controlled, operated and maintained by the Transmission Owner on the Transmission Owner’s side of the Point of Change of Ownership to the Point of Interconnection, including any modifications, additions or upgrades made to such facilities and equipment, that are necessary to physically and electrically interconnect the Generating Facility with the Transmission System or interconnected distribution facilities.
Stand Alone Network Upgrades: Network Upgrades, which are not part of an Affected System, which a Project Developer may construct without affecting day-to-day operations (e.g. taking a transmission outage) of the Transmission System during their construction.
Network Upgrades: Modifications or additions to transmission-related facilities that are integrated with and support the Transmission Provider’s overall Transmission System for the general benefit of all users of such Transmission System. Network Upgrades have no impact or potential impact on the Transmission System until the final tie-in is complete.
Notes
Note 1: PJM Open Access Transmission Tariff (OATT), Part VII, Subpart D, section 307.5 outlines cost allocation rules. The rules are further clarified in PJM Manual 14H, section 4.2.6. PJM shall identify the New Service Requests in the Cycle contributing to the need for the required Network Upgrades within the Cycle. All New Service Requests that contribute to the need for a Network Upgrade will receive cost allocation for that upgrade pursuant to each New Service Request’s contribution to the reliability violation identified on the transmission system in accordance with PJM Manuals.
Note 2: There will be no inter-Cycle cost allocation for Interconnection Facilities or Network Upgrades identified in the System Impact Study costs identified in a Cycle; all such costs shall be allocated to New Service Requests in that Cycle.
Note 3: For Project Developers with System Reinforcements listed: If this project presents cost allocation to a System Reinforcement indicates $0, then please be aware that as changes to the interconnection process occur, such as other projects withdrawing, reducing in size, etc, the cost responsibilities can change and a cost allocation may be assigned to this project. In addition, although this project presents cost allocation to a System Reinforcement is presently $0, this project may need this system reinforcement completed to be deliverable to the PJM system. If this project desires to come into service prior to completion of the system reinforcement, the Project Developer will need to request PJM to perform an interim deliverability study to determine if they would be deliverable for all or a portion of their output for each delivery year until the system reinforcement is complete.
Readiness Deposit
Per Tariff Part VII, Subpart D, section 309 (Decision Point I) A.1.a.i and PJM Manual 14H, section 6.2, Readiness Deposit #2 (RD2) are funds committed by the Project Developer or Eligible Customer based upon the applicable contribution to Network Upgrades as defined below. Readiness Deposits are not used to fund studies nor to offset Security.
During Decision Point I (DP1), the Project Developer or Eligible Customer is required to submit Readiness Deposit #2, which is calculated as 10% of cost allocation for required Phase I Network Upgrades minus Readiness Deposit #1.
Note 1: “Network Upgrades” referred to in the calculation include both (i) the Physical Interconnection Network Upgrades and (ii) the System Reliability Network Upgrades as shown in the Cost Summary table.
Note 2: Readiness Deposit #1 (RD1) = ($4,000 * Project Size (MW))
Note 3: Readiness Deposit #2 (RD2) = 10% of cost allocation for required Network Upgrades minus RD1. Readiness Deposit #2 (RD2) can be zero, but may not be a negative number.
Readiness Deposit #2 Due for Project AG2-532
Readiness Deposit #2 has been calculated for the project based on the Phase I System Impact Study results and is shown in the table below. This Readiness Deposit #2 must be provided at Decision Point I through either a wire transfer or letter of credit per Manual 14H, Section 6.2.
| Readiness Deposit | |||
|---|---|---|---|
| Project ID | 10% of cost allocation for Phase I Network Upgrades | Readiness Deposit #1 Received (RD1) | Readiness Deposit #2 (RD2) for AG2-532 Project due at DP1 |
| A | B | A - B | |
| AG2-532 | $4,102,108 | $80,000 | $4,022,108 |
Note: Failure to provide an acceptable form of Readiness Deposit #2 by the end of Decision Point I will result in withdrawal and termination of the New Service Request.
For additional detail regarding Readiness Deposit Refunds, reference PJM Manual 14H, section 6.2.1. The Readiness Deposit Letter of Credit template can be found here.
Transmission Owner Scope of Work
The total preliminary cost estimate for the Transmission Owner scope of work (including TOIF and Physical Interconnection Network Upgrades) is given in the table below. These costs do not include CIAC Tax Gross-up.
| Transmission Owner Interconnection Facilities | |||
|---|---|---|---|
| RTEP ID | Description | Total Cost ($USD) | Allocated Cost ($USD) |
| (Pending) | Tap the existing Pohatcong Mountain-Washington 34.5 kV line (Q719). Install one (1) SCADA controlled tap switch and extend the tap by one (1) span to the project developer's facilities. | $865,655 | $865,655 |
| (Pending) | Integrate interconnection facilities protection and controls to the Transmission Owner system. | $60,060 | $60,060 |
| Stand-Alone Network Upgrades | |||
|---|---|---|---|
| RTEP ID | Description | Total Cost ($USD) | Allocated Cost ($USD) |
| (Pending) | Install (2) 34.5 kV line switches on the Pohatcong Mountain-Washington 34.5 kV Line (Q719). | $1,074,135 | $1,074,135 |
| Network Upgrades | |||
|---|---|---|---|
| RTEP ID | Description | Total Cost ($USD) | Allocated Cost ($USD) |
| (Pending) | Revise relay settings at Pohatcong Mountain substation as required. | $50,050 | $50,050 |
| (Pending) | Revise relay settings at Newburgh substation as required. | $50,050 | $50,050 |
| (Pending) | Revise relay settings at Washington substation as required. | $50,050 | $50,050 |
| Physical Interconnection | |||
|---|---|---|---|
| RTEP ID | Description | Total Cost ($USD) | Allocated Cost ($USD) |
| (Pending) | Install 34.5 kV revenue metering | $57,200 | $57,200 |
Based on the scope of work for the Interconnection Facilities, it is expected to take 23 month(s) after the signing of a Generator Interconnection Agreement (as this is a FERC connection) and construction kickoff call to complete the installation of the physical connection work. This assumes that there will be no environmental issues with any of the new properties associated with this project, that there will be no delays in acquiring the necessary permits for implementing the defined interconnection work, and that all system outages will be allowed when requested.
The schedule for any required Network Impact Reinforcements will be more clearly identified in the Phase II and Phase III System Impact Studies.
Transmission Owner Analysis
There were no network impacts to Distribution facilities identified by the Transmission Owner.
The Transmission Owner identified network impacts to Sub-Regional facilities as follows:
| Overloaded Element | Contingency | Rating [MVA] | Final Cycle Loading % | Contribution [MW] |
|---|---|---|---|---|
| 206212 28CHESTER 34.5 - 207529 AG1-191 TAP 34.5 CKT 1 | JC_P1-3_JCN-230-028_SRT-A (Charging) CONTINGENCY 'JC_P1-3_JCN-230-028_SRT-A' /* POHATCONG 230/34.5 KV BANK 1 DISCONNECT BRANCH FROM BUS 206247 TO BUS 206219 CKT 1 /* 28POHATCNG 230 28POHATCNG 35 END | 47.0 | 167.55 % | 6.54 |
| 206216 28FLANDERS 34.5 - 206663 28NET R TP 34.5 CKT 1 | JC_P1-3_JCN-230-028_SRT-A (Charging) CONTINGENCY 'JC_P1-3_JCN-230-028_SRT-A' /* POHATCONG 230/34.5 KV BANK 1 DISCONNECT BRANCH FROM BUS 206247 TO BUS 206219 CKT 1 /* 28POHATCNG 230 28POHATCNG 35 END | 50.0 | 149.97 % | 5.1 |
| 206219 28POHATCNG 34.5 - 970848 AG2-533 TP 34.5 CKT 1 | JC_P1-2_JCN-230-019_SRT-SL (Discharging/Charging) CONTINGENCY 'JC_P1-2_JCN-230-019_SRT-SL' /* POHATCONG - WEST WHARTON (A2001) 230 KV DISCONNECT BRANCH FROM BUS 206247 TO BUS 206374 CKT 1 /* 28POHATCNG 230 28ELASTMLD 230 DISCONNECT BRANCH FROM BUS 206374 TO BUS 206377 CKT 1 /* 28ELASTMLD 230 28DOTWHART 230 DISCONNECT BRANCH FROM BUS 206377 TO BUS 206255 CKT ZL /* 28DOTWHART 230 28W WHRTN 230 REMOVE LOAD C FROM BUS 206374 /* 28ELASTMLD 230 REMOVE LOAD C FROM BUS 206377 /* 28DOTWHART 230 SET PRECONTRATING 650 BRANCH FROM BUS 206228 TO BUS 206255 CKT 1 /* 28CHESTER 230 - 28W WHRTN 230 RATEA DERATE H2034 SET POSTCONTRATING 813 BRANCH FROM BUS 206228 TO BUS 206255 CKT 1/* 28CHESTER 230 - 28W WHRTN 230 RATEB DERATE H2034 SET PRECONTRATING 218 BRANCH FROM BUS 206254 TO BUS 206255 CKT 3 /* 28W WHARTN 115.00 28W WHRTN 230.00 RATEA DERATE WW#3 SET POSTCONTRATING 263 BRANCH FROM BUS 206254 TO BUS 206255 CKT 3/* 28W WHARTN 115.00 28W WHRTN 230.00 RATEB DERATE WW#3 END | 50.0 | 107.14 % | 2.56 |
| 206219 28POHATCNG 34.5 - 970850 AG2-534 TP 34.5 CKT 1 | JC_P1-2_JCN-230-019_SRT-SL (Discharging/Charging) CONTINGENCY 'JC_P1-2_JCN-230-019_SRT-SL' /* POHATCONG - WEST WHARTON (A2001) 230 KV DISCONNECT BRANCH FROM BUS 206247 TO BUS 206374 CKT 1 /* 28POHATCNG 230 28ELASTMLD 230 DISCONNECT BRANCH FROM BUS 206374 TO BUS 206377 CKT 1 /* 28ELASTMLD 230 28DOTWHART 230 DISCONNECT BRANCH FROM BUS 206377 TO BUS 206255 CKT ZL /* 28DOTWHART 230 28W WHRTN 230 REMOVE LOAD C FROM BUS 206374 /* 28ELASTMLD 230 REMOVE LOAD C FROM BUS 206377 /* 28DOTWHART 230 SET PRECONTRATING 650 BRANCH FROM BUS 206228 TO BUS 206255 CKT 1 /* 28CHESTER 230 - 28W WHRTN 230 RATEA DERATE H2034 SET POSTCONTRATING 813 BRANCH FROM BUS 206228 TO BUS 206255 CKT 1/* 28CHESTER 230 - 28W WHRTN 230 RATEB DERATE H2034 SET PRECONTRATING 218 BRANCH FROM BUS 206254 TO BUS 206255 CKT 3 /* 28W WHARTN 115.00 28W WHRTN 230.00 RATEA DERATE WW#3 SET POSTCONTRATING 263 BRANCH FROM BUS 206254 TO BUS 206255 CKT 3/* 28W WHARTN 115.00 28W WHRTN 230.00 RATEB DERATE WW#3 END | 48.0 | 130.57 % | 1.97 |
| 206660 28NEWBRG E 34.5 - 970848 AG2-533 TP 34.5 CKT 1 | JC_P1-3_JCN-230-028_SRT-A (Charging) CONTINGENCY 'JC_P1-3_JCN-230-028_SRT-A' /* POHATCONG 230/34.5 KV BANK 1 DISCONNECT BRANCH FROM BUS 206247 TO BUS 206219 CKT 1 /* 28POHATCNG 230 28POHATCNG 35 END | 50.0 | 146.68 % | 6.54 |
| 206662 28SAXTON F 34.5 - 206661 28PANTHER 34.5 CKT 1 | JC_P1-2_JCN-230-014_SRT-A (Charging) CONTINGENCY 'JC_P1-2_JCN-230-014_SRT-A' /* KITTATINY - POHATCONG (L2012) 230 KV & POHAT BK 1 DISCONNECT BRANCH FROM BUS 206242 TO BUS 206247 CKT 1 /* 28KITATINY 230 28POHATCNG 230 DISCONNECT BRANCH FROM BUS 206247 TO BUS 206219 CKT 1 /* 28POHATCNG 230 28POHATCNG 35 END | 48.0 | 129.08 % | 5.06 |
| 206663 28NET R TP 34.5 - 206662 28SAXTON F 34.5 CKT 1 | JC_P1-2_JCN-230-014_SRT-A (Charging) CONTINGENCY 'JC_P1-2_JCN-230-014_SRT-A' /* KITTATINY - POHATCONG (L2012) 230 KV & POHAT BK 1 DISCONNECT BRANCH FROM BUS 206242 TO BUS 206247 CKT 1 /* 28KITATINY 230 28POHATCNG 230 DISCONNECT BRANCH FROM BUS 206247 TO BUS 206219 CKT 1 /* 28POHATCNG 230 28POHATCNG 35 END | 48.0 | 129.08 % | 5.06 |
| 206668 28COOKE CO 34.5 - 206678 28NWBRG TP 34.5 CKT 1 | JC_P1-2_JCN-230-014_SRT-A (Injection/Charging) CONTINGENCY 'JC_P1-2_JCN-230-014_SRT-A' /* KITTATINY - POHATCONG (L2012) 230 KV & POHAT BK 1 DISCONNECT BRANCH FROM BUS 206242 TO BUS 206247 CKT 1 /* 28KITATINY 230 28POHATCNG 230 DISCONNECT BRANCH FROM BUS 206247 TO BUS 206219 CKT 1 /* 28POHATCNG 230 28POHATCNG 35 END | 53.0 | 133.68 % | 8.4 |
| 206672 28MOBIL CH 34.5 - 206673 28PORT MUR 34.5 CKT 1 | JC_P1-2_JCN-230-014_SRT-A (Injection/Charging) CONTINGENCY 'JC_P1-2_JCN-230-014_SRT-A' /* KITTATINY - POHATCONG (L2012) 230 KV & POHAT BK 1 DISCONNECT BRANCH FROM BUS 206242 TO BUS 206247 CKT 1 /* 28KITATINY 230 28POHATCNG 230 DISCONNECT BRANCH FROM BUS 206247 TO BUS 206219 CKT 1 /* 28POHATCNG 230 28POHATCNG 35 END | 53.0 | 157.21 % | 8.4 |
| 206673 28PORT MUR 34.5 - 206668 28COOKE CO 34.5 CKT 1 | JC_P1-2_JCN-230-014_SRT-A (Injection/Charging) CONTINGENCY 'JC_P1-2_JCN-230-014_SRT-A' /* KITTATINY - POHATCONG (L2012) 230 KV & POHAT BK 1 DISCONNECT BRANCH FROM BUS 206242 TO BUS 206247 CKT 1 /* 28KITATINY 230 28POHATCNG 230 DISCONNECT BRANCH FROM BUS 206247 TO BUS 206219 CKT 1 /* 28POHATCNG 230 28POHATCNG 35 END | 53.0 | 140.26 % | 8.4 |
| 206675 28WASHNTON 34.5 - 206776 28PVGCS 34.5 CKT 1 | JC_P1-2_JCN-230-014_SRT-A (Injection/Charging) CONTINGENCY 'JC_P1-2_JCN-230-014_SRT-A' /* KITTATINY - POHATCONG (L2012) 230 KV & POHAT BK 1 DISCONNECT BRANCH FROM BUS 206242 TO BUS 206247 CKT 1 /* 28KITATINY 230 28POHATCNG 230 DISCONNECT BRANCH FROM BUS 206247 TO BUS 206219 CKT 1 /* 28POHATCNG 230 28POHATCNG 35 END | 47.0 | 177.17 % | 8.4 |
| 206678 28NWBRG TP 34.5 - 206219 28POHATCNG 34.5 CKT 1 | JC_P1-2_JCN-230-014_SRT-A (Injection/Charging) CONTINGENCY 'JC_P1-2_JCN-230-014_SRT-A' /* KITTATINY - POHATCONG (L2012) 230 KV & POHAT BK 1 DISCONNECT BRANCH FROM BUS 206242 TO BUS 206247 CKT 1 /* 28KITATINY 230 28POHATCNG 230 DISCONNECT BRANCH FROM BUS 206247 TO BUS 206219 CKT 1 /* 28POHATCNG 230 28POHATCNG 35 END | 50.0 | 104.04 % | 11.59 |
| 206679 28M&M R+ 34.5 - 206792 28HACKETHOSP 34.5 CKT 1 | JC_P1-2_JCN-230-019_SRT-SL CONTINGENCY 'JC_P1-2_JCN-230-019_SRT-SL' /* POHATCONG - WEST WHARTON (A2001) 230 KV DISCONNECT BRANCH FROM BUS 206247 TO BUS 206374 CKT 1 /* 28POHATCNG 230 28ELASTMLD 230 DISCONNECT BRANCH FROM BUS 206374 TO BUS 206377 CKT 1 /* 28ELASTMLD 230 28DOTWHART 230 DISCONNECT BRANCH FROM BUS 206377 TO BUS 206255 CKT ZL /* 28DOTWHART 230 28W WHRTN 230 REMOVE LOAD C FROM BUS 206374 /* 28ELASTMLD 230 REMOVE LOAD C FROM BUS 206377 /* 28DOTWHART 230 SET PRECONTRATING 650 BRANCH FROM BUS 206228 TO BUS 206255 CKT 1 /* 28CHESTER 230 - 28W WHRTN 230 RATEA DERATE H2034 SET POSTCONTRATING 813 BRANCH FROM BUS 206228 TO BUS 206255 CKT 1/* 28CHESTER 230 - 28W WHRTN 230 RATEB DERATE H2034 SET PRECONTRATING 218 BRANCH FROM BUS 206254 TO BUS 206255 CKT 3 /* 28W WHARTN 115.00 28W WHRTN 230.00 RATEA DERATE WW#3 SET POSTCONTRATING 263 BRANCH FROM BUS 206254 TO BUS 206255 CKT 3/* 28W WHARTN 115.00 28W WHRTN 230.00 RATEB DERATE WW#3 END | 48.0 | 100.23 % | 1.97 |
| 206748 28DL_W4-046 34.5 - 206672 28MOBIL CH 34.5 CKT 1 | JC_P1-2_JCN-230-014_SRT-A (Injection/Charging) CONTINGENCY 'JC_P1-2_JCN-230-014_SRT-A' /* KITTATINY - POHATCONG (L2012) 230 KV & POHAT BK 1 DISCONNECT BRANCH FROM BUS 206242 TO BUS 206247 CKT 1 /* 28KITATINY 230 28POHATCNG 230 DISCONNECT BRANCH FROM BUS 206247 TO BUS 206219 CKT 1 /* 28POHATCNG 230 28POHATCNG 35 END | 53.0 | 157.96 % | 8.4 |
| 206776 28PVGCS 34.5 - 206748 28DL_W4-046 34.5 CKT 1 | JC_P1-2_JCN-230-014_SRT-A (Injection/Charging) CONTINGENCY 'JC_P1-2_JCN-230-014_SRT-A' /* KITTATINY - POHATCONG (L2012) 230 KV & POHAT BK 1 DISCONNECT BRANCH FROM BUS 206242 TO BUS 206247 CKT 1 /* 28KITATINY 230 28POHATCNG 230 DISCONNECT BRANCH FROM BUS 206247 TO BUS 206219 CKT 1 /* 28POHATCNG 230 28POHATCNG 35 END | 53.0 | 149.49 % | 8.4 |
| 207529 AG1-191 TAP 34.5 - 206660 28NEWBRG E 34.5 CKT 1 | JC_P1-3_JCN-230-028_SRT-A (Charging) CONTINGENCY 'JC_P1-3_JCN-230-028_SRT-A' /* POHATCONG 230/34.5 KV BANK 1 DISCONNECT BRANCH FROM BUS 206247 TO BUS 206219 CKT 1 /* 28POHATCNG 230 28POHATCNG 35 END | 47.0 | 185.76 % | 6.54 |
| 970848 AG2-533 TP 34.5 - 206219 28POHATCNG 34.5 CKT 1 | JC_P1-3_JCN-230-028_SRT-A (Discharging/Charging) CONTINGENCY 'JC_P1-3_JCN-230-028_SRT-A' /* POHATCONG 230/34.5 KV BANK 1 DISCONNECT BRANCH FROM BUS 206247 TO BUS 206219 CKT 1 /* 28POHATCNG 230 28POHATCNG 35 END | 50.0 | 127.16 % | 6.54 |
| 970850 AG2-534 TP 34.5 - 206655 28HCKTWN S 34.5 CKT 1 | JC_P1-2_JCN-230-019_SRT-SL CONTINGENCY 'JC_P1-2_JCN-230-019_SRT-SL' /* POHATCONG - WEST WHARTON (A2001) 230 KV DISCONNECT BRANCH FROM BUS 206247 TO BUS 206374 CKT 1 /* 28POHATCNG 230 28ELASTMLD 230 DISCONNECT BRANCH FROM BUS 206374 TO BUS 206377 CKT 1 /* 28ELASTMLD 230 28DOTWHART 230 DISCONNECT BRANCH FROM BUS 206377 TO BUS 206255 CKT ZL /* 28DOTWHART 230 28W WHRTN 230 REMOVE LOAD C FROM BUS 206374 /* 28ELASTMLD 230 REMOVE LOAD C FROM BUS 206377 /* 28DOTWHART 230 SET PRECONTRATING 650 BRANCH FROM BUS 206228 TO BUS 206255 CKT 1 /* 28CHESTER 230 - 28W WHRTN 230 RATEA DERATE H2034 SET POSTCONTRATING 813 BRANCH FROM BUS 206228 TO BUS 206255 CKT 1/* 28CHESTER 230 - 28W WHRTN 230 RATEB DERATE H2034 SET PRECONTRATING 218 BRANCH FROM BUS 206254 TO BUS 206255 CKT 3 /* 28W WHARTN 115.00 28W WHRTN 230.00 RATEA DERATE WW#3 SET POSTCONTRATING 263 BRANCH FROM BUS 206254 TO BUS 206255 CKT 3/* 28W WHARTN 115.00 28W WHRTN 230.00 RATEB DERATE WW#3 END | 48.0 | 105.59 % | 1.97 |
| TO | RTEP ID / TO ID | Category | Title | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|---|---|---|
| JCPL | (Pending) / TC2-JCP-L04.a | SubRegional | Reconductor (Possible Rebuild) ~0.7 miles of the Chester - AG1-191 34.5 kV Line including (1) T-line drop at Chester | 6.5 MW | 21.2% | $913,942 |
| JCPL | (Pending) / TC2-JCP-L04.b | SubRegional | Replace (2) 750Amp Breaker leads at Chester | 6.5 MW | 21.2% | $32,166 |
| JCPL | (Pending) / TC2-JCP-L07.a | SubRegional | Replace (1) Misc 1250 Amp 34.5 kV CU UGS-34 [324ft of Underground riser] | 5.1 MW | 21.3% | $134,634 |
| JCPL | (Pending) / TC2-JCP-L07.b | SubRegional | Reconductor (Possible Rebuild) ~2.9 miles of the Flanders - Bud Lake Sw Pt (R772) 34.5 kV Line | 5.1 MW | 21.3% | $2,958,595 |
| JCPL | (Pending) / TC2-JCP-L07.c | SubRegional | Replace (1) KD-10 Z3 relay at Flanders | 5.1 MW | 21.3% | $108,398 |
| JCPL | (Pending) / TC2-JCP-L01.a | SubRegional | Replace 34.5 kV 397.5 SCCIR 26/7 (B-66599) Substation Conductor at Pohatcong | 9.1 MW | 16.1% | $24,543 |
| JCPL | (Pending) / TC2-JCP-L01.b | SubRegional | Reconductor (Possible Rebuild) ~1.3 miles of the Pohatcong Mountain - AG2-533 34.5 kV Line | 9.1 MW | 16.1% | $1,087,481 |
| JCPL | (Pending) / TC2-JCP-L01.c | SubRegional | Replace (1) 6 Amp KD-4 (0.73-21.2 OHM) Relay | 9.1 MW | 16.1% | $82,343 |
| JCPL | (Pending) / TC2-JCP-L06.a | SubRegional | Replace (1) 5 Amp KD-4 (0.75-20 OHM) Relay at Pohatcong | 3.9 MW | 11.9% | $60,752 |
| JCPL | (Pending) / TC2-JCP-L06.b | SubRegional | Replace (1) 34.5 kV substation conductor at Pohatcong | 3.9 MW | 11.9% | $75,697 |
| JCPL | (Pending) / TC2-JCP-L06.c | SubRegional | Reconductor (Possible Rebuild) ~1.3 miles of Pohatcong Mountain - AG2-534 (R722) 34.5 kV Line | 2.0 MW | 8.7% | $583,621 |
| JCPL | (Pending) / TC2-JCP-L02 | SubRegional | Reconductor (Possible Rebuild) ~1.7 miles of the AG2-533 - Newburgh 34.5 kV Line | 6.5 MW | 21.2% | $1,723,003 |
| JCPL | (Pending) / TC2-JC-L16 | SubRegional | Reconductor (Possible Rebuild) 1.7 miles of the Flanders - Pohatcong Mountain 34.5 KV Line (Saxton Falls Tap - Panther Valley Sw Pt Line section) | 5.1 MW | 21.1% | $1,728,787 |
| JCPL | (Pending) / TC2-JC-L17 | SubRegional | Reconductor (Possible Rebuild) 4.2 miles of the Flanders - Pohatcong Mountain 34.5 KV Line (Bud Lake Sw Pt - Saxton Falls Tap Line section) | 5.1 MW | 21.1% | $4,507,633 |
| JCPL | (Pending) / TC2-JC-L18 | SubRegional | Reconductor (Possible Rebuild) 3.1 miles of the Pohatcong Mountain - Washington 34.5 KV Line (Cooke Color Tap - Port Murray Line section) | 8.4 MW | 30.8% | $4,795,031 |
| JCPL | (Pending) / TC2-JCP-L11 | SubRegional | Reconductor (Possible Rebuild) ~1.2 miles of the Port Murray - Mobil Chem(Q719) 34.5 kV Line | 8.4 MW | 30.8% | $1,927,053 |
| JCPL | (Pending) / TC2-JCP-L12 | SubRegional | Reconductor (Possible Rebuild) ~2.7 miles of the Cooke Color Tap - Port Murray (Q719) 34.5 kV Line | 8.4 MW | 30.8% | $4,296,626 |
| JCPL | (Pending) / TC2-JCP-L13.a | SubRegional | Replace (1) 6.5 Amp GCx17A Relay Thermal at Washington | 8.4 MW | 30.8% | $156,833 |
| JCPL | (Pending) / TC2-JCP-L13.b | SubRegional | Reconductor (Possible Rebuild) ~0.31 miles of the PVGCS T - Washington (Q719) 34.5 kV Line | 8.4 MW | 30.8% | $693,990 |
| JCPL | (Pending) / TC2-JCP-L13.c | SubRegional | Replace (1) 10 Amp Meter and (1) 10 Amp Relay Thermal [MCTI-39] at Washington | 8.4 MW | 30.8% | $156,833 |
| JCPL | (Pending) / TC2-JCP-L13.d | SubRegional | Replace (2) 1200 Amp Current Transformers at Washington | 8.4 MW | 30.8% | $124,178 |
| JCPL | (Pending) / TC2-JCP-L13.e | SubRegional | Replace (1) 11.1 Ohm Relay and (1) 14.53 Ohm Relay at Washington | 8.4 MW | 30.8% | $156,833 |
| JCPL | (Pending) / TC2-JCP-L13.f | SubRegional | Replace (1) 4.72 Ohm Relay at Washington | 8.4 MW | 30.8% | $156,833 |
| JCPL | (Pending) / TC2-JC-L19 | SubRegional | Replace sub conductor at Pohatcong Mountain | 11.6 MW | 38.0% | $96,487 |
| JCPL | (Pending) / TC2-JC-L20 | SubRegional | Reconductor (Possible Rebuild) 1.6 miles of the Flanders - Pohatcong Mountain 34.5 KV Line (Hackettstown Hosp Tap - Hackettstown Tap Line section) | 2.0 MW | 19.0% | $1,481,045 |
| JCPL | (Pending) / TC2-JCP-L14 | SubRegional | Reconductor (Possible Rebuild) ~0.4 miles of the Mobil Chem - Domin LN Solar T (Q719) 34.5 kV Line | 8.4 MW | 30.8% | $947,561 |
| JCPL | (Pending) / TC2-JCP-L15 | SubRegional | Reconductor (Possible Rebuild) ~2.6 miles of the Domin LN Solar T - PVGCS T (Q719) 34.5 kV Line | 8.4 MW | 30.8% | $3,887,217 |
| JCPL | (Pending) / TC2-JCP-L03 | SubRegional | Reconductor (Possible Rebuild) ~6.9 miles of the Newburgh - AG1-191 34.5 kV Line | 6.5 MW | 21.2% | $6,898,678 |
| Grand Total: | $39,796,793 | |||||
System Reinforcement
- TO
- JCPL
- RTEP ID / TO ID
- (Pending) / TC2-JCP-L04.a
- Category
- SubRegional
- Title
- Reconductor (Possible Rebuild) ~0.7 miles of the Chester - AG1-191 34.5 kV Line including (1) T-line drop at Chester
- Description
- New ratings: 56/73/83 MVA SN/SE/SLD
- Total Cost
- $4,318,266
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
| AG2-532 | 6.5 MW | 21.2% | $913,942 |
| AG2-533 | 9.1 MW | 29.6% | $1,277,786 |
| AG2-534 | 7.3 MW | 23.6% | $1,019,116 |
| AG2-535 | 7.9 MW | 25.6% | $1,107,421 |
System Reinforcement
- TO
- JCPL
- RTEP ID / TO ID
- (Pending) / TC2-JCP-L04.b
- Category
- SubRegional
- Title
- Replace (2) 750Amp Breaker leads at Chester
- Description
- New ratings: 82/84/87 MVA SN/SE/SLD
- Total Cost
- $151,980
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
| AG2-532 | 6.5 MW | 21.2% | $32,166 |
| AG2-533 | 9.1 MW | 29.6% | $44,971 |
| AG2-534 | 7.3 MW | 23.6% | $35,867 |
| AG2-535 | 7.9 MW | 25.6% | $38,975 |
System Reinforcement
- TO
- JCPL
- RTEP ID / TO ID
- (Pending) / TC2-JCP-L07.a
- Category
- SubRegional
- Title
- Replace (1) Misc 1250 Amp 34.5 kV CU UGS-34 [324ft of Underground riser]
- Description
- New ratings: 55/67/75 MVA SN/SE/SLD
- Total Cost
- $633,306
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
| AG2-532 | 5.1 MW | 21.3% | $134,634 |
| AG2-533 | 5.5 MW | 22.9% | $145,193 |
| AG2-534 | 7.2 MW | 30.2% | $191,391 |
| AG2-535 | 6.1 MW | 25.6% | $162,088 |
System Reinforcement
- TO
- JCPL
- RTEP ID / TO ID
- (Pending) / TC2-JCP-L07.b
- Category
- SubRegional
- Title
- Reconductor (Possible Rebuild) ~2.9 miles of the Flanders - Bud Lake Sw Pt (R772) 34.5 kV Line
- Description
- New ratings: 66/69/71 MVA SN/SE/SLD
- Total Cost
- $13,916,998
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
| AG2-532 | 5.1 MW | 21.3% | $2,958,595 |
| AG2-533 | 5.5 MW | 22.9% | $3,190,641 |
| AG2-534 | 7.2 MW | 30.2% | $4,205,846 |
| AG2-535 | 6.1 MW | 25.6% | $3,561,916 |
System Reinforcement
- TO
- JCPL
- RTEP ID / TO ID
- (Pending) / TC2-JCP-L07.c
- Category
- SubRegional
- Title
- Replace (1) KD-10 Z3 relay at Flanders
- Description
- New ratings: 66/79/83 MVA SN/SE/SLD
- Total Cost
- $509,895
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
| AG2-532 | 5.1 MW | 21.3% | $108,398 |
| AG2-533 | 5.5 MW | 22.9% | $116,900 |
| AG2-534 | 7.2 MW | 30.2% | $154,095 |
| AG2-535 | 6.1 MW | 25.6% | $130,503 |
System Reinforcement
- TO
- JCPL
- RTEP ID / TO ID
- (Pending) / TC2-JCP-L01.a
- Category
- SubRegional
- Title
- Replace 34.5 kV 397.5 SCCIR 26/7 (B-66599) Substation Conductor at Pohatcong
- Description
- New ratings: 44/53/60 MVA SN/SE/SLD
- Total Cost
- $151,980
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
| AG2-532 | 9.1 MW | 16.1% | $24,543 |
| AG2-533 | 26.0 MW | 46.2% | $70,259 |
| AG2-534 | 10.2 MW | 18.0% | $27,375 |
| AG2-535 | 11.1 MW | 19.6% | $29,803 |
System Reinforcement
- TO
- JCPL
- RTEP ID / TO ID
- (Pending) / TC2-JCP-L01.b
- Category
- SubRegional
- Title
- Reconductor (Possible Rebuild) ~1.3 miles of the Pohatcong Mountain - AG2-533 34.5 kV Line
- Description
- New ratings: 55/57/63 MVA SN/SE/SLD
- Total Cost
- $6,734,018
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
| AG2-532 | 9.1 MW | 16.1% | $1,087,481 |
| AG2-533 | 26.0 MW | 46.2% | $3,113,064 |
| AG2-534 | 10.2 MW | 18.0% | $1,212,960 |
| AG2-535 | 11.1 MW | 19.6% | $1,320,513 |
System Reinforcement
- TO
- JCPL
- RTEP ID / TO ID
- (Pending) / TC2-JCP-L01.c
- Category
- SubRegional
- Title
- Replace (1) 6 Amp KD-4 (0.73-21.2 OHM) Relay
- Description
- New ratings: 55/67/75 MVA SN/SE/SLD
- Total Cost
- $509,895
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
| AG2-532 | 9.1 MW | 16.1% | $82,343 |
| AG2-533 | 26.0 MW | 46.2% | $235,719 |
| AG2-534 | 10.2 MW | 18.0% | $91,844 |
| AG2-535 | 11.1 MW | 19.6% | $99,988 |
System Reinforcement
- TO
- JCPL
- RTEP ID / TO ID
- (Pending) / TC2-JCP-L06.a
- Category
- SubRegional
- Title
- Replace (1) 5 Amp KD-4 (0.75-20 OHM) Relay at Pohatcong
- Description
- New ratings: 42/50/52 MVA SN/SE/SLD
- Total Cost
- $509,895
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
| AG2-532 | 3.9 MW | 11.9% | $60,752 |
| AG2-533 | 4.3 MW | 13.0% | $66,413 |
| AG2-534 | 20.0 MW | 60.5% | $308,420 |
| AG2-535 | 4.8 MW | 14.6% | $74,310 |
System Reinforcement
- TO
- JCPL
- RTEP ID / TO ID
- (Pending) / TC2-JCP-L06.b
- Category
- SubRegional
- Title
- Replace (1) 34.5 kV substation conductor at Pohatcong
- Description
- New ratings: 44/53/60 MVA SN/SE/SLD
- Total Cost
- $635,328
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
| AG2-532 | 3.9 MW | 11.9% | $75,697 |
| AG2-533 | 4.3 MW | 13.0% | $82,750 |
| AG2-534 | 20.0 MW | 60.5% | $384,291 |
| AG2-535 | 4.8 MW | 14.6% | $92,590 |
System Reinforcement
- TO
- JCPL
- RTEP ID / TO ID
- (Pending) / TC2-JCP-L06.c
- Category
- SubRegional
- Title
- Reconductor (Possible Rebuild) ~1.3 miles of Pohatcong Mountain - AG2-534 (R722) 34.5 kV Line
- Description
- New ratings: 66/76/82 MVA SN/SE/SLD
- Total Cost
- $6,734,018
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
| AG2-532 | 2.0 MW | 8.7% | $583,621 |
| AG2-533 | 2.1 MW | 9.5% | $637,270 |
| AG2-534 | 16.2 MW | 71.3% | $4,798,792 |
| AG2-535 | 2.4 MW | 10.6% | $714,335 |
System Reinforcement
- TO
- JCPL
- RTEP ID / TO ID
- (Pending) / TC2-JCP-L02
- Category
- SubRegional
- Title
- Reconductor (Possible Rebuild) ~1.7 miles of the AG2-533 - Newburgh 34.5 kV Line
- Description
- New ratings: 77/94/106 MVA SN/SE/SLD
- Total Cost
- $8,140,795
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
| AG2-532 | 6.5 MW | 21.2% | $1,723,003 |
| AG2-533 | 9.1 MW | 29.6% | $2,407,989 |
| AG2-534 | 7.3 MW | 23.6% | $1,920,595 |
| AG2-535 | 7.9 MW | 25.7% | $2,089,207 |
System Reinforcement
- TO
- JCPL
- RTEP ID / TO ID
- (Pending) / TC2-JC-L16
- Category
- SubRegional
- Title
- Reconductor (Possible Rebuild) 1.7 miles of the Flanders - Pohatcong Mountain 34.5 KV Line (Saxton Falls Tap - Panther Valley Sw Pt Line section)
- Description
- New ratings: 70/85/95 MVA SN/SE/SLD
- Total Cost
- $8,192,945
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
| AG2-532 | 5.1 MW | 21.1% | $1,728,787 |
| AG2-533 | 5.5 MW | 23.0% | $1,885,949 |
| AG2-534 | 7.2 MW | 30.2% | $2,477,016 |
| AG2-535 | 6.2 MW | 25.6% | $2,101,193 |
System Reinforcement
- TO
- JCPL
- RTEP ID / TO ID
- (Pending) / TC2-JC-L17
- Category
- SubRegional
- Title
- Reconductor (Possible Rebuild) 4.2 miles of the Flanders - Pohatcong Mountain 34.5 KV Line (Bud Lake Sw Pt - Saxton Falls Tap Line section)
- Description
- New ratings: 70/85/95 MVA SN/SE/SLD
- Total Cost
- $21,362,263
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
| AG2-532 | 5.1 MW | 21.1% | $4,507,633 |
| AG2-533 | 5.5 MW | 23.0% | $4,917,418 |
| AG2-534 | 7.2 MW | 30.2% | $6,458,566 |
| AG2-535 | 6.2 MW | 25.6% | $5,478,645 |
System Reinforcement
- TO
- JCPL
- RTEP ID / TO ID
- (Pending) / TC2-JC-L18
- Category
- SubRegional
- Title
- Reconductor (Possible Rebuild) 3.1 miles of the Pohatcong Mountain - Washington 34.5 KV Line (Cooke Color Tap - Port Murray Line section)
- Description
- New ratings: 70/85/95 MVA SN/SE/SLD
- Total Cost
- $15,588,670
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
| AG2-532 | 8.4 MW | 30.8% | $4,795,031 |
| AG2-533 | 5.3 MW | 19.5% | $3,047,027 |
| AG2-534 | 5.5 MW | 20.0% | $3,116,057 |
| AG2-535 | 5.9 MW | 21.7% | $3,387,043 |
| AH1-257 | 2.2 MW | 8.0% | $1,243,513 |
System Reinforcement
- TO
- JCPL
- RTEP ID / TO ID
- (Pending) / TC2-JCP-L11
- Category
- SubRegional
- Title
- Reconductor (Possible Rebuild) ~1.2 miles of the Port Murray - Mobil Chem(Q719) 34.5 kV Line
- Description
- New ratings: 82/100/113 MVA SN/SE/SLD
- Total Cost
- $6,265,216
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
| AG2-532 | 8.4 MW | 30.8% | $1,927,053 |
| AG2-533 | 5.3 MW | 19.5% | $1,224,472 |
| AG2-534 | 5.5 MW | 20.0% | $1,252,447 |
| AG2-535 | 5.9 MW | 21.7% | $1,361,365 |
| AH1-257 | 2.2 MW | 8.0% | $499,878 |
System Reinforcement
- TO
- JCPL
- RTEP ID / TO ID
- (Pending) / TC2-JCP-L12
- Category
- SubRegional
- Title
- Reconductor (Possible Rebuild) ~2.7 miles of the Cooke Color Tap - Port Murray (Q719) 34.5 kV Line
- Description
- New ratings: 70/85/95 MVA SN/SE/SLD
- Total Cost
- $13,969,148
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
| AG2-532 | 8.4 MW | 30.8% | $4,296,626 |
| AG2-533 | 5.3 MW | 19.5% | $2,730,127 |
| AG2-534 | 5.5 MW | 20.0% | $2,792,500 |
| AG2-535 | 5.9 MW | 21.7% | $3,035,349 |
| AH1-257 | 2.2 MW | 8.0% | $1,114,546 |
System Reinforcement
- TO
- JCPL
- RTEP ID / TO ID
- (Pending) / TC2-JCP-L13.a
- Category
- SubRegional
- Title
- Replace (1) 6.5 Amp GCx17A Relay Thermal at Washington
- Description
- New ratings: 44/53/60 MVA SN/SE/SLD
- Total Cost
- $509,895
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
| AG2-532 | 8.4 MW | 30.8% | $156,833 |
| AG2-533 | 5.3 MW | 19.5% | $99,654 |
| AG2-534 | 5.5 MW | 20.0% | $101,930 |
| AG2-535 | 5.9 MW | 21.7% | $110,795 |
| AH1-257 | 2.2 MW | 8.0% | $40,683 |
System Reinforcement
- TO
- JCPL
- RTEP ID / TO ID
- (Pending) / TC2-JCP-L13.b
- Category
- SubRegional
- Title
- Reconductor (Possible Rebuild) ~0.31 miles of the PVGCS T - Washington (Q719) 34.5 kV Line
- Description
- New ratings: 58/72/78 MVA SN/SE/SLD
- Total Cost
- $2,256,294
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
| AG2-532 | 8.4 MW | 30.8% | $693,990 |
| AG2-533 | 5.3 MW | 19.5% | $440,970 |
| AG2-534 | 5.5 MW | 20.0% | $451,044 |
| AG2-535 | 5.9 MW | 21.7% | $490,269 |
| AH1-257 | 2.2 MW | 8.0% | $180,021 |
System Reinforcement
- TO
- JCPL
- RTEP ID / TO ID
- (Pending) / TC2-JCP-L13.c
- Category
- SubRegional
- Title
- Replace (1) 10 Amp Meter and (1) 10 Amp Relay Thermal [MCTI-39] at Washington
- Description
- New ratings: 58/74/78 MVA SN/SE/SLD
- Total Cost
- $509,895
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
| AG2-532 | 8.4 MW | 30.8% | $156,833 |
| AG2-533 | 5.3 MW | 19.5% | $99,654 |
| AG2-534 | 5.5 MW | 20.0% | $101,930 |
| AG2-535 | 5.9 MW | 21.7% | $110,795 |
| AH1-257 | 2.2 MW | 8.0% | $40,683 |
System Reinforcement
- TO
- JCPL
- RTEP ID / TO ID
- (Pending) / TC2-JCP-L13.d
- Category
- SubRegional
- Title
- Replace (2) 1200 Amp Current Transformers at Washington
- Description
- New ratings: 74/75/78 MVA SN/SE/SLD
- Total Cost
- $403,725
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
| AG2-532 | 8.4 MW | 30.8% | $124,178 |
| AG2-533 | 5.3 MW | 19.5% | $78,904 |
| AG2-534 | 5.5 MW | 20.0% | $80,707 |
| AG2-535 | 5.9 MW | 21.7% | $87,725 |
| AH1-257 | 2.2 MW | 8.0% | $32,212 |
System Reinforcement
- TO
- JCPL
- RTEP ID / TO ID
- (Pending) / TC2-JCP-L13.e
- Category
- SubRegional
- Title
- Replace (1) 11.1 Ohm Relay and (1) 14.53 Ohm Relay at Washington
- Description
- New ratings: 74/83/86 MVA SN/SE/SLD
- Total Cost
- $509,895
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
| AG2-532 | 8.4 MW | 30.8% | $156,833 |
| AG2-533 | 5.3 MW | 19.5% | $99,654 |
| AG2-534 | 5.5 MW | 20.0% | $101,930 |
| AG2-535 | 5.9 MW | 21.7% | $110,795 |
| AH1-257 | 2.2 MW | 8.0% | $40,683 |
System Reinforcement
- TO
- JCPL
- RTEP ID / TO ID
- (Pending) / TC2-JCP-L13.f
- Category
- SubRegional
- Title
- Replace (1) 4.72 Ohm Relay at Washington
- Description
- New ratings: 74/90/103 MVA SN/SE/SLD
- Total Cost
- $509,895
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
| AG2-532 | 8.4 MW | 30.8% | $156,833 |
| AG2-533 | 5.3 MW | 19.5% | $99,654 |
| AG2-534 | 5.5 MW | 20.0% | $101,930 |
| AG2-535 | 5.9 MW | 21.7% | $110,795 |
| AH1-257 | 2.2 MW | 8.0% | $40,683 |
System Reinforcement
- TO
- JCPL
- RTEP ID / TO ID
- (Pending) / TC2-JC-L19
- Category
- SubRegional
- Title
- Replace sub conductor at Pohatcong Mountain
- Description
- New ratings: 44/53/60 MVA SN/SE/SLD
- Total Cost
- $253,989
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
| AG2-532 | 11.6 MW | 38.0% | $96,487 |
| AG2-533 | 5.3 MW | 17.5% | $44,456 |
| AG2-534 | 5.5 MW | 17.9% | $45,471 |
| AG2-535 | 5.9 MW | 19.5% | $49,426 |
| AH1-257 | 2.2 MW | 7.1% | $18,149 |
System Reinforcement
- TO
- JCPL
- RTEP ID / TO ID
- (Pending) / TC2-JC-L20
- Category
- SubRegional
- Title
- Reconductor (Possible Rebuild) 1.6 miles of the Flanders - Pohatcong Mountain 34.5 KV Line (Hackettstown Hosp Tap - Hackettstown Tap Line section)
- Description
- New ratings: 55/67/75 MVA SN/SE/SLD
- Total Cost
- $7,776,800
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
| AG2-532 | 2.0 MW | 19.0% | $1,481,045 |
| AG2-533 | 2.2 MW | 20.8% | $1,620,950 |
| AG2-534 | 3.8 MW | 36.8% | $2,863,553 |
| AG2-535 | 2.4 MW | 23.3% | $1,811,252 |
System Reinforcement
- TO
- JCPL
- RTEP ID / TO ID
- (Pending) / TC2-JCP-L14
- Category
- SubRegional
- Title
- Reconductor (Possible Rebuild) ~0.4 miles of the Mobil Chem - Domin LN Solar T (Q719) 34.5 kV Line
- Description
- New ratings: 82/100/113 MVA SN/SE/SLD
- Total Cost
- $3,080,702
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
| AG2-532 | 8.4 MW | 30.8% | $947,561 |
| AG2-533 | 5.3 MW | 19.5% | $602,092 |
| AG2-534 | 5.5 MW | 20.0% | $615,847 |
| AG2-535 | 5.9 MW | 21.7% | $669,404 |
| AH1-257 | 2.2 MW | 8.0% | $245,798 |
System Reinforcement
- TO
- JCPL
- RTEP ID / TO ID
- (Pending) / TC2-JCP-L15
- Category
- SubRegional
- Title
- Reconductor (Possible Rebuild) ~2.6 miles of the Domin LN Solar T - PVGCS T (Q719) 34.5 kV Line
- Description
- New ratings: 77/94/106 MVA SN/SE/SLD
- Total Cost
- $12,638,082
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
| AG2-532 | 8.4 MW | 30.8% | $3,887,217 |
| AG2-533 | 5.3 MW | 19.5% | $2,469,983 |
| AG2-534 | 5.5 MW | 20.0% | $2,526,414 |
| AG2-535 | 5.9 MW | 21.7% | $2,746,122 |
| AH1-257 | 2.2 MW | 8.0% | $1,008,345 |
System Reinforcement
- TO
- JCPL
- RTEP ID / TO ID
- (Pending) / TC2-JCP-L03
- Category
- SubRegional
- Title
- Reconductor (Possible Rebuild) ~6.9 miles of the Newburgh - AG1-191 34.5 kV Line
- Description
- New ratings: 82/103/119 MVA SN/SE/SLD
- Total Cost
- $32,594,670
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
| AG2-532 | 6.5 MW | 21.2% | $6,898,678 |
| AG2-533 | 9.1 MW | 29.6% | $9,641,271 |
| AG2-534 | 7.3 MW | 23.6% | $7,689,810 |
| AG2-535 | 7.9 MW | 25.7% | $8,364,910 |
Developer Requirements
The developer is responsible for all design and construction related activities on the developer’s side of the Point of Change in Ownership. FirstEnergy interconnection requirements can be found here.
To the extent that these Applicable Technical Requirements and Standards may conflict with the terms and conditions of the Tariff, the Tariff shall control.
Revenue Metering and SCADA Requirements
The developer will be required to install equipment necessary to provide Revenue Metering (KWH, KVARH) and real time data (KW, KVAR) for their generating Resource. See PJM Manual 01, PJM Manual 14D, and PJM Tariff Part IX, Subpart B, Appendix 2, section 8.Transmission Owner Requirements
The Project Developer will be required to comply with all interconnected Transmission Owner’s revenue metering requirements located at the following link: PJM - Transmission Owner Engineering & Construction Standards.
Summer Peak Analysis
The New Service Request AG2-532 was evaluated as a 20.0 MW (0.0 MW Capacity) injection in the JCPL area.
AG2-532 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 20.0 MW (20.0 MW under study).
Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.
(No impacts were found for this analysis)
Winter Peak Analysis
The New Service Request AG2-532 was evaluated as a 20.0 MW (0.0 MW Capacity) injection in the JCPL area.
AG2-532 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 20.0 MW (20.0 MW under study).
Note: The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for single or N-1 contingencies and multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.
| Study | Area | Facility Description | Contingency Name | Contingency Type | DC|AC | Final Cycle Loading | Rating (MVA) | Rating Type | MVA to Mitigate | MW Contribution | |
|---|---|---|---|---|---|---|---|---|---|---|---|
| IPD | PJM | PCHBTM1S-CNASTONE 500.0 kV Ckt 1 line | AP_P1-2_PE-500-3835T_SRT-A | Single | AC | 117.9 % | 3700.0 | B | 4362.39 | 5.02 | |
| IPD | PJM | PCHBTM1S-CNASTONE 500.0 kV Ckt 1 line | AP_P2-3_PE-500-019E_SRT-W | Breaker | AC | 117.87 % | 3700.0 | B | 4361.04 | 5.02 | |
| IPD | PJM | PCHBTM1S-CNASTONE 500.0 kV Ckt 1 line | AP_P2-3_PE-500-019B_SRT-A | Breaker | AC | 113.85 % | 3700.0 | B | 4212.51 | 4.69 | |
| IPD | PJM | PCHBTM1S-CNASTONE 500.0 kV Ckt 1 line | PECO_P1-2_5007_SRT-A/* $ CHESCO $ PECO_P1-2_5007 $ L | Single | AC | 108.99 % | 3700.0 | B | 4032.58 | 4.05 |
Light Load Analysis
The New Service Request AG2-532 was evaluated as a 20.0 MW injection and 20.0 MW withdrawal in the JCPL area.
AG2-532 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 20.0 MW (20.0 MW under study).
Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.
(No impacts were found for this analysis)
Short Circuit Analysis
Short Circuit analysis is not performed as part of the Phase I System Impact Study. Short Circuit analysis will commence in the Phase II System Impact Study.
Stability Analysis
Stability analysis is not performed as part of the Phase I System Impact Study. Stability analysis will commence in the Phase II System Impact Study.
Reactive Power Analysis
Reactive Power analysis is not performed as part of the Phase I System Impact Study. Reactive Power analysis will commence in the Phase II System Impact Study.
Steady-State Voltage Analysis
Steady State Voltage Analysis is Not Required.
New Service Request Dependencies
The New Service Requests below are listed in one or more dispatch for the overloads identified in this report. These projects contribute to the loading of the overloaded facilities identified in this report. The percent overload of a facility and cost allocation you may have towards a particular reinforcement could vary depending on the action of other projects. The status of each project at the time of the analysis is presented in the table. This list may change as other projects withdraw or modify their requests. This table is valid for load flow analyses only.
| New Service Requests Dependencies | ||
|---|---|---|
| Project ID | Project Name | Status |
Affected System - PJM Identified Violations
As part of PJM's analysis, PJM evaluated the potential impacts on tie line facilities between PJM and an affected system entity, which were identified per PJM planning analysis criteria. This upgrade may be required on the affected system portion of the tie line along with cost allocation of such upgrade if applicable, in coordination with the affected system. Depending on the affected system, this project may not be contingent on upgrade based on PJM planning analysis criteria, but may be contingent on this upgrade based on the Affected System Operator's planning criteria, provided in the Affected Systems Study Section, herein.
Affected System - Non-PJM Identified Violations
In Phase I of the Cycle, PJM conducts an Affected System screen to identify any New Service Request with potential Affected System impacts. PJM initiates coordination with each Affected System Operator by providing a list of New Service Requests in the Cycle with potential impacts to their respective system. If the Affected System Operator indicates an Affected System Study is required, PJM will notify the Project Developer or Eligible Customer of the need for an Affected System Study. See below if any Affected System Operator requires a study for this project:
System Reinforcements
No cost allocated system reinforcements were identified for this project in the Phase I System Impact Study load flow analysis.
Shown below are the details of the cost allocated, contingent, eliminated, topology and potential aggregate contributor reinforcements for this project. Please refer to the System Reinforcement table above and the information below for more detail.
System Reinforcement: b3737.50
- Type
- Load Flow
- TO
- PECO
- RTEP ID / TO ID
- b3737.50
- Title
- Bring the Peach Bottom-Delta Power Plant 500 kV line “in and out” of North Delta
- Description
- Bring the Peach Bottom-Delta Power Plant 500 kV line “in and out” of North Delta by constructing a new Peach Bottom-North Delta 500 kV (0.3 miles) cut-in and cut-out lines.
- Cost Information
- Time Estimate
- Jun 01 2029
Not Contingent Note: AG2-532 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-532 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.
| Facility | Contingency | |
|---|---|---|
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) |
System Reinforcement: b3780.11
- Type
- Load Flow
- TO
- PEPCO
- RTEP ID / TO ID
- b3780.11
- Title
- Brighton Statcom and Capacitor (Projected ISD 12/31/2028)
- Description
- Brighton Statcom and capacitor New STATCOM rating: 350 MVAR New capacitor rating: 350 MVAR
- Cost Information
- Time Estimate
- Dec 31 2028
Not Contingent Note: AG2-532 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-532 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.
| Facility | Contingency | |
|---|---|---|
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) |
System Reinforcement: b3780.5
- Type
- Load Flow
- TO
- BGE
- RTEP ID / TO ID
- b3780.5
- Title
- Build Solley Road substation + Statcom (Projected ISD 12/31/2028)
- Description
- Build Solley Road substation + Statcom. New STATCOM rating: 350 MVAR Add 4x 230 kV breakers bays.
- Cost Information
- Time Estimate
- Dec 31 2028
Not Contingent Note: AG2-532 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-532 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.
| Facility | Contingency | |
|---|---|---|
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) |
System Reinforcement: b3800.26
- Type
- Load Flow
- TO
- BGE
- RTEP ID / TO ID
- b3800.26
- Title
- Build High Ridge 500 kV substation - Three bay breaker and half configuration (Projected ISD 12/31/2030)
- Description
- None
- Cost Information
- Time Estimate
- Dec 31 2030
Not Contingent Note: AG2-532 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-532 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.
| Facility | Contingency | |
|---|---|---|
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) |
System Reinforcement: b3800.27
- Type
- Load Flow
- TO
- BGE
- RTEP ID / TO ID
- b3800.27
- Title
- High Ridge 500 kV substation (cut into Brighton-Waugh Chapel 500 kV line) - Waugh Chapel side (Projected ISD 12/31/2030)
- Description
- None
- Cost Information
- Time Estimate
- Dec 31 2030
Not Contingent Note: AG2-532 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-532 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.
| Facility | Contingency | |
|---|---|---|
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) |
System Reinforcement: b3800.29
- Type
- Load Flow
- TO
- BGE
- RTEP ID / TO ID
- b3800.29
- Title
- High Ridge termination for the North Delta-High Ridge 500 kV line (Projected ISD 12/31/2030)
- Description
- None
- Cost Information
- Time Estimate
- Dec 31 2030
Not Contingent Note: AG2-532 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-532 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.
| Facility | Contingency | |
|---|---|---|
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) |
System Reinforcement: b3800.30
- Type
- Load Flow
- TO
- BGE
- RTEP ID / TO ID
- b3800.30
- Title
- High Ridge - Install two 500/230 kV transformers (Projected ISD 12/31/2030)
- Description
- None
- Cost Information
- Time Estimate
- Dec 31 2030
Not Contingent Note: AG2-532 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-532 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.
| Facility | Contingency | |
|---|---|---|
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) |
System Reinforcement: b3800.31
- Type
- Load Flow
- TO
- PECO
- RTEP ID / TO ID
- b3800.31
- Title
- Build new North Delta-High Ridge 500 kV line - PECO Portion (Projected ISD 12/1/2030)
- Description
- None
- Cost Information
- Time Estimate
- Dec 01 2030
Not Contingent Note: AG2-532 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-532 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.
| Facility | Contingency | |
|---|---|---|
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) |
System Reinforcement: b3800.32
- Type
- Load Flow
- TO
- BGE
- RTEP ID / TO ID
- b3800.32
- Title
- Build new North Delta-High Ridge 500 kV line - BGE Portion (Projected ISD 12/31/2030)
- Description
- Build new North Delta-High Ridge 500 kV line. (~59 miles)
- Cost Information
- Time Estimate
- Dec 31 2030
Not Contingent Note: AG2-532 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-532 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.
| Facility | Contingency | |
|---|---|---|
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) |
System Reinforcement: b3800.44
- Type
- Load Flow
- TO
- PECO
- RTEP ID / TO ID
- b3800.44
- Title
- North Delta termination for the North Delta-High Ridge 500 line (PECO work).
- Description
- None
- Cost Information
- Time Estimate
- Dec 01 2030
Not Contingent Note: AG2-532 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-532 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.
| Facility | Contingency | |
|---|---|---|
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) |
System Reinforcement: b3800.48
- Type
- Load Flow
- TO
- PECO
- RTEP ID / TO ID
- b3800.48
- Title
- North Delta termination for the North Delta-High Ridge 500 line (Transource work).
- Description
- None
- Cost Information
- Time Estimate
- Dec 15 2030
Not Contingent Note: AG2-532 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-532 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.
| Facility | Contingency | |
|---|---|---|
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) |
System Reinforcement: b3800.49
- Type
- Load Flow
- TO
- PECO
- RTEP ID / TO ID
- b3800.49
- Title
- North Delta 500 kV termination for the Calpine generator (Calpine/Transource work).
- Description
- None
- Cost Information
- Time Estimate
- Oct 06 2027
Not Contingent Note: AG2-532 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-532 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.
| Facility | Contingency | |
|---|---|---|
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) |
System Reinforcement: b3780.13
- Type
- Load Flow
- TO
- BGE
- RTEP ID / TO ID
- b3780.13
- Title
- Batavia Road to Riverside 230 kV reconductor
- Description
- Batavia Road to Riverside 230 kV reconductor New rating: 1941 MVA SN / 2181 MVA SE
- Cost Information
- Time Estimate
- Dec 31 2027
Not Contingent Note: AG2-532 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-532 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.
| Facility | Contingency | |
|---|---|---|
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) |
System Reinforcement: b3800.36
- Type
- Load Flow
- TO
- BGE
- RTEP ID / TO ID
- b3800.36
- Title
- Rebuild 5012 (existing Peach Bottom-Conastone) (new North Delta-Graceton BGE) 500 kV (Projected ISD 12/31/2030)
- Description
- Rebuild 5012 (existing Peach Bottom-Conastone) (new North Delta-Graceton BGE) 500 kV line on single circuit structures within existing ROW and cut into North Delta 500 kV and Gracetone 500 kV stations.
- Cost Information
- Time Estimate
- Dec 31 2030
Not Contingent Note: AG2-532 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-532 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.
| Facility | Contingency | |
|---|---|---|
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) |
System Reinforcement: b3800.33
- Type
- Load Flow
- TO
- BGE
- RTEP ID / TO ID
- b3800.33
- Title
- Replace terminal equipment limitations at Brighton 500 kV - on the existing Brighton-Waugh Chapel 500 kV (5053) or new Brighton-High Ridge 500 kV.
- Description
- None
- Cost Information
- Time Estimate
- Dec 31 2030
Not Contingent Note: AG2-532 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-532 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.
| Facility | Contingency | |
|---|---|---|
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) |
System Reinforcement: b3780.1
- Type
- Load Flow
- TO
- PECO
- RTEP ID / TO ID
- b3780.1
- Title
- Peach Bottom North upgrades – substation work (Projected ISD 12/31/2028)
- Description
- Add 3x 500 kV breakers to form a breaker-and-a-half bay.
- Cost Information
- Time Estimate
- Dec 31 2028
Not Contingent Note: AG2-532 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-532 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.
| Facility | Contingency | |
|---|---|---|
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) |
System Reinforcement: b3780.15
- Type
- Load Flow
- TO
- PECO
- RTEP ID / TO ID
- b3780.15
- Title
- Cut in 5012 Peach Bottom-Conastone 500 kV line into North Delta 500/230 kV sub
- Description
- Cut in 5012 Peach Bottom-Conastone 500 kV line into North Delta 500/230 kV substation by rebuilding 5012 between new terminal at Peach Bottom South and North Delta on single circuit structures and terminating at North Delta.
- Cost Information
- Time Estimate
- Dec 31 2028
Not Contingent Note: AG2-532 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-532 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.
| Facility | Contingency | |
|---|---|---|
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) |
System Reinforcement: b3780.17
- Type
- Load Flow
- TO
- PECO
- RTEP ID / TO ID
- b3780.17
- Title
- Cut in 5012 Peach Bottom-Conastone 500 kV line into North Delta 500/230 kV sub (Transource)
- Description
- Cut in 5012 Peach Bottom-Conastone 500 kV line into North Delta 500/230 kV substation by rebuilding 5012 between new terminal at Peach Bottom South and North Delta on single circuit structures and terminating at North Delta (Transource Scope).
- Cost Information
- Time Estimate
- May 31 2028
Not Contingent Note: AG2-532 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-532 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.
| Facility | Contingency | |
|---|---|---|
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) |
System Reinforcement: b3780.8
- Type
- Load Flow
- TO
- BGE
- RTEP ID / TO ID
- b3780.8
- Title
- Graceton 500 kV substation expansion (Projected ISD 12/31/2028)
- Description
- Add 3x 500 kV breaker bays, 2x 500/230 kV auto transformer, 1x 500 kV caps
- Cost Information
- Time Estimate
- Dec 31 2028
Not Contingent Note: AG2-532 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-532 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.
| Facility | Contingency | |
|---|---|---|
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) |
System Reinforcement: b3800.34
- Type
- Load Flow
- TO
- BGE
- RTEP ID / TO ID
- b3800.34
- Title
- Rebuild 5012 (existing Peach Bottom-Conastone) (new Graceton-Conastone) 500 kV and cut into North Delta 500kV (Projected ISD 12/31/2030)
- Description
- Rebuild 5012 (existing Peach Bottom-Conastone) (new Graceton-Conastone) 500 kV line on single circuit structures within existing ROW and cut into North Delta 500 kV and Gracetone 500 kV stations.
- Cost Information
- Time Estimate
- Dec 31 2030
Not Contingent Note: AG2-532 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-532 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.
| Facility | Contingency | |
|---|---|---|
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) |
System Reinforcement: b3800.35
- Type
- Load Flow
- TO
- PECO
- RTEP ID / TO ID
- b3800.35
- Title
- Rebuild 5012 (existing Peach Bottom-Conastone) (new North Delta-Graceton PECO) 500 kV (Projected ISD 12/1/2030)
- Description
- Rebuild 5012 (existing Peach Bottom-Conastone) (new North Delta-Graceton PECO) 500 kV line on single circuit structures within existing ROW and cut into North Delta 500 kV and Gracetone 500 kV stations.
- Cost Information
- Time Estimate
- Dec 01 2030
Not Contingent Note: AG2-532 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-532 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.
| Facility | Contingency | |
|---|---|---|
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) |
System Reinforcement: b3800.37
- Type
- Load Flow
- TO
- BGE
- RTEP ID / TO ID
- b3800.37
- Title
- Replace terminal equipment limitations at Conastone 500 kV - on the (existing Peach Bottom-Conastone) or (new Graceton-Conastone) 500 kV line (Projected ISD 12/31/2030)
- Description
- None
- Cost Information
- Time Estimate
- Dec 31 2030
Not Contingent Note: AG2-532 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-532 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.
| Facility | Contingency | |
|---|---|---|
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) |
System Reinforcement: b3780.14
- Type
- Load Flow
- TO
- PECO
- RTEP ID / TO ID
- b3780.14
- Title
- Reconfigure Cooper transmission feeds by establishing new Cooper-North Delta 230 kV line and rerouting existing transmissions lines by Cooper.
- Description
- None
- Cost Information
- Time Estimate
- Dec 31 2028
Not Contingent Note: AG2-532 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-532 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.
| Facility | Contingency | |
|---|---|---|
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) |
System Reinforcement: b3780.16
- Type
- Load Flow
- TO
- PECO
- RTEP ID / TO ID
- b3780.16
- Title
- Terminate new Cooper-North Delta 230 kV line (Transource Scope) at North Delta 230 kV
- Description
- None
- Cost Information
- Time Estimate
- Oct 15 2028
Not Contingent Note: AG2-532 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-532 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.
| Facility | Contingency | |
|---|---|---|
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) |
System Reinforcement: b3780.6
- Type
- Load Flow
- TO
- BGE
- RTEP ID / TO ID
- b3780.6
- Title
- Build Granite substation + Statcom (Projected ISD 12/31/2028)
- Description
- Build Granite substation + Statcom. New STATCOM rating: 350 MVAR. Add 4x 230 kV breaker bays.
- Cost Information
- Time Estimate
- Dec 31 2028
Not Contingent Note: AG2-532 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-532 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.
| Facility | Contingency | |
|---|---|---|
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) |
System Reinforcement: b3780.7
- Type
- Load Flow
- TO
- BGE
- RTEP ID / TO ID
- b3780.7
- Title
- Build new Batavia Road substation (Projected ISD 12/31/2028)
- Description
- Build Batavia Road substation. Add 4 x 230kV breaker bays
- Cost Information
- Time Estimate
- Dec 31 2028
Not Contingent Note: AG2-532 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-532 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.
| Facility | Contingency | |
|---|---|---|
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) |
System Reinforcement: b3780.9
- Type
- Load Flow
- TO
- BGE
- RTEP ID / TO ID
- b3780.9
- Title
- Graceton to Batavia Road 230 kV double circuit pole line (Projected ISD 12/31/2028)
- Description
- Graceton to Batavia Road 230 kV double circuit pole line New rating: 1331 MVA SN/ 1594 MVA SE
- Cost Information
- Time Estimate
- Dec 31 2028
Not Contingent Note: AG2-532 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-532 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.
| Facility | Contingency | |
|---|---|---|
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) |
System Reinforcement: b3800.28
- Type
- Load Flow
- TO
- BGE
- RTEP ID / TO ID
- b3800.28
- Title
- High Ridge 500 kV substation (cut into Brighton-Waugh Chapel 500 kV line) -Brighton side (Projected ISD 12/31/2030)
- Description
- None
- Cost Information
- Time Estimate
- Dec 31 2030
Not Contingent Note: AG2-532 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-532 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.
| Facility | Contingency | |
|---|---|---|
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) |
System Reinforcement: b3737.47
- Type
- Load Flow
- TO
- PECO
- RTEP ID / TO ID
- b3737.47
- Title
- Build New North Delta 500 kV substation (Four bay breaker and half configuration)
- Description
- Build New North Delta 500 kV substation (four bay breaker and half configuration) - the substation will include 12 - 500kV breakers and one 500/230 kV transformer, will allow the termination of six - 500 kV lines
- Cost Information
- Time Estimate
- Oct 15 2027
Not Contingent Note: AG2-532 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-532 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.
| Facility | Contingency | |
|---|---|---|
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) |
System Reinforcement: b3800.50
- Type
- Load Flow
- TO
- PECO
- RTEP ID / TO ID
- b3800.50
- Title
- North Delta 500 kV termination for the Rock Springs 500 kV line (5034/5014 line) (Transource work).
- Description
- Loops in the 500kV line from Peach Bottom to Rock Springs into the new North Delta (Bramah) sub
- Cost Information
- Time Estimate
- Jan 23 2028
Not Contingent Note: AG2-532 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-532 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.
| Facility | Contingency | |
|---|---|---|
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) |
System Reinforcement: b3800.42
- Type
- Load Flow
- TO
- PECO
- RTEP ID / TO ID
- b3800.42
- Title
- Peach Bottom 500kV North bus upgrade (Projected ISD 12/1/2030)
- Description
- Peach Bottom 500kV North bus upgrade - Replace 11 – Instances of strain bus conductor used for breaker drops or CT drops, 7 – 500 kV disconnect switches, 7 – Free Standing CTs, 1 – 500 kV breaker, 2 – Breaker relays or meters.
- Cost Information
- Time Estimate
- Dec 01 2030
Not Contingent Note: AG2-532 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-532 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.
| Facility | Contingency | |
|---|---|---|
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) |
System Reinforcement: b3800.52
- Type
- Load Flow
- TO
- PECO
- RTEP ID / TO ID
- b3800.52
- Title
- Reconfigure Peach Bottom North and South 500 kV yards (Projected ISD 12/1/2030)
- Description
- Reconfigure Peach Bottom North and South yards to allow for termination of 500 kV lines from Peach Bottom to North Delta. North Delta 500 kV termination for the new Peach Bottom-North Delta 500 kV line.
- Cost Information
- Time Estimate
- Dec 01 2030
Not Contingent Note: AG2-532 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-532 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.
| Facility | Contingency | |
|---|---|---|
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) |
System Reinforcement: b3780.2
- Type
- Load Flow
- TO
- PECO
- RTEP ID / TO ID
- b3780.2
- Title
- Peach Bottom to Graceton (PECO Portion) – New 500kV Line
- Description
- Peach Bottom to Graceton (PECO Portion) – New 500kV Line. New rating: 4503 MVA SN/ 5022 MVA SE. This is a baseline identified for the announced Brandon Shores deactivation.
- Cost Information
- Time Estimate
- Dec 31 2028
Not Contingent Note: AG2-532 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-532 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.
| Facility | Contingency | |
|---|---|---|
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) |
System Reinforcement: b3780.4
- Type
- Load Flow
- TO
- BGE
- RTEP ID / TO ID
- b3780.4
- Title
- Peach Bottom to Graceton (BGE Portion) – New 500kV Line
- Description
- New rating: 4503 MVA SN/ 5022 MVA SE. This is a baseline identified for the announced Brandon Shores deactivation.
- Cost Information
- Time Estimate
- Dec 31 2028
Not Contingent Note: AG2-532 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-532 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.
| Facility | Contingency | |
|---|---|---|
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) |
System Reinforcement: b3800.45
- Type
- Load Flow
- TO
- PECO
- RTEP ID / TO ID
- b3800.45
- Title
- North Delta 500 kV termination for the Rock Springs 500 kV line (5034/5014 line) (PECO work).
- Description
- Loops in the 500kV line from Peach Bottom to Rock Springs into the new North Delta (Bramah) sub
- Cost Information
- Time Estimate
- Dec 01 2030
Not Contingent Note: AG2-532 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-532 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.
| Facility | Contingency | |
|---|---|---|
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) |
System Reinforcement: b3800.46
- Type
- Load Flow
- TO
- PEPCO
- RTEP ID / TO ID
- b3800.46
- Title
- North Delta 500 kV termination for the new Peach Bottom-North Delta 500 kV line (PECO work).
- Description
- Loops in the 500kV line from Peach Bottom to Rock Springs into the new North Delta (Bramah) sub
- Cost Information
- Time Estimate
- Dec 01 2030
Not Contingent Note: AG2-532 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-532 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.
| Facility | Contingency | |
|---|---|---|
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) |
System Reinforcement: b3800.47
- Type
- Load Flow
- TO
- PECO
- RTEP ID / TO ID
- b3800.47
- Title
- Build new Peach Bottom South-North Delta 500 kV line (Projected ISD 12/1/2030)
- Description
- Build new Peach Bottom South-North Delta 500 kV line – cut in to Peach Bottom tie No. 1 and extending line to North Delta (~1.25 miles new ROW).
- Cost Information
- Time Estimate
- Dec 01 2030
Not Contingent Note: AG2-532 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-532 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.
| Facility | Contingency | |
|---|---|---|
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) |
System Reinforcement: b3800.51
- Type
- Load Flow
- TO
- PECO
- RTEP ID / TO ID
- b3800.51
- Title
- North Delta 500 kV termination for the new Peach Bottom-North Delta 500 kV line (Transource work).
- Description
- Loops in the 500kV line from Peach Bottom to Rock Springs into the new North Delta (Bramah) sub
- Cost Information
- Time Estimate
- May 31 2028
Not Contingent Note: AG2-532 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-532 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.
| Facility | Contingency | |
|---|---|---|
| CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line | (Any) |