AG2-535 Phase I Study Report

v1.00 released 2025-10-29 19:50

Hackettstown-Pohatcong J738-1 34.5 kV II

0.0 MW Capacity / 20.0 MW Energy

Introduction

This Phase I System Impact Study Report (PH1) has been prepared in accordance with the PJM Open Access Transmission Tariff, Part VII, Subpart D, sections 307 and 308 for New Service Requests (projects) in Transition Cycle 2. The Project Developer/Eligible Customer (developer) is Mansfield 3 LLC, and the Transmission Provider (TP) is PJM Interconnection, LLC (PJM). The interconnected Transmission Owner (TO) is Jersey Central Power & Light Company.

Preface

The Phase I System Impact Study is conducted on an aggregate basis within a New Services Request’s Cycle, and results are provided in both (i) a single Cycle executive summary format and (ii) an individual project-level basis. The Phase I System Impact Study Results (for both the executive summary and individual reports) will be publicly available on PJM’s website. Developers must obtain the results from the website.

In accordance with PJM Manual 14H, section 4.3, PJM takes the following actions during the Phase I System Impact Study:
  1. PJM studies each New Service Request on a summer peak, winter peak and light load RTEP base case study. The case year is dependent on the new services cycle under study. PJM will identify the base case year to be used in the study of a specific cycle on its website.
  2. PJM will only perform load flow analysis during the Phase I System Impact Study.
  3. In Phase I of the Cycle, PJM conducts an Affected System screen to identify any New Service Request with Affected System impacts and provides each Affected System Operator with a list of New Service Request in the Cycle with potential impacts to their respective system.
  4. PJM will create both the short circuit and stability base cases to be used in the Phase II System Impact Study.
  5. The Phase I System Impact Study results will be publicly available on PJM’s website. Project Developers and Eligible Customers must obtain the results from the website.
The Transmission Owner takes the following actions during the Phase I System Impact Study:
  1. Identify required Interconnection Facilities to accommodate the New Service Request.
  2. Identify required Network Upgrades to mitigate system violations from the Phase I System Impact Study.
  3. Provide planning-level preliminary estimates of Interconnection Facilities and Network Upgrades including scope, cost and elapsed time to complete the work.

Decision Point I Requirements

At the close of Phase I System Impact Study, PJM will initiate Decision Point I (DP1). During DP1, the Project Developer will have 30 days to decide whether to proceed with their project. If the Project Developer elects to proceed, they should provide the elements defined in the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 309.A.1. Additional information on these elements is available in PJM Manual 14H sections 4.4, 6, and 7.

Allowable project modifications at Decision Point I are defined in PJM Open Access Transmission Tariff, Part VII, Subpart D, section 309.B. Additional information regarding allowable project modifications can be found in PJM Manual 14H, section 9.8.

General

The Project Developer has proposed an uprate to a planned/existing Storage facility located in the Jersey Central Power & Light Company zone — Warren County, New Jersey. This project is an increase to the developer’s AF1-328 project(s), which will share the same Point of Interconnection. The AG2-535 project is a 20.0 MW uprate (0.0 MW Capacity uprate) to the previous project(s). The total installed facilities will have a capability of 40.0 MW with 0.0 MW of this output being recognized by PJM as Capacity.

Project Information
New Service Request Number:
AG2-535
Project Name:
Hackettstown-Pohatcong J738-1 34.5 kV II
Project Developer Name:
Mansfield 3 LLC
State:
New Jersey
County:
Warren
Transmission Owner:
Jersey Central Power & Light Company
MFO:
40.0
MWE:
20.0
MWC:
0.0
Battery Storage Specification:
20.0 MWh, 1.0-hr class
Grid Charging:
Yes
Fuel Type:
Storage
Basecase Study Year:
2028

Physical Interconnection Facility Study

Physical Interconnection Facilities Study is not performed as part of the Phase I System Impact Study. Physical Interconnection Facilities Study will commence in the Phase II System Impact Study.

Point of Interconnection

AG2-535 will interconnect on the Jersey Central Power & Light Company distribution system tapping the Hackettstown - Pohatcong 34.5 kV (J738-1 ckt).

Cost Summary

The table below shows a summary of the total cost estimates for this New Service Request project. In the Phase I SIS, the costs shown are subject to change as a result of a facility study performed by the TO during the Phase II or Phase III System Impact Study.

Based on the Phase I SIS results, the AG2-535 project has the following allocation of costs for interconnection. The cost contribution towards Readiness Deposit are also shown below.

Cost Summary
DescriptionCost Allocated to AG2-535Cost Subject to Readiness*
Transmission Owner Interconnection Facilities (TOIF)$823,627$0
Other Scope$59,600$0
Option To Build Oversight$0$0
Physical Interconnection Network Upgrades
Stand Alone Network Upgrades$11,588,672$11,588,672
Network Upgrades$993,663$993,663
System Reliability Network Upgrades
Steady State Thermal & Voltage (SP & LL)$0$0
Transient Stability$0$0
Short Circuit$0$0
Transmission Owner Analysis
SubRegional$46,472,286$46,472,286
Distribution$0$0
Affected System Reinforcements
AFS - PJM Violatons$0$0
AFS - Non-PJM Violations$0$0
Total$59,937,848$59,054,621

* Contributes to calculation for Readiness Deposit #2 (RD2). See Readiness Deposit section of report for additional detail.

Definitions

Transmission Owner Interconnection Facilities: Facilities that are owned, controlled, operated and maintained by the Transmission Owner on the Transmission Owner’s side of the Point of Change of Ownership to the Point of Interconnection, including any modifications, additions or upgrades made to such facilities and equipment, that are necessary to physically and electrically interconnect the Generating Facility with the Transmission System or interconnected distribution facilities.

Stand Alone Network Upgrades: Network Upgrades, which are not part of an Affected System, which a Project Developer may construct without affecting day-to-day operations (e.g. taking a transmission outage) of the Transmission System during their construction.

Network Upgrades: Modifications or additions to transmission-related facilities that are integrated with and support the Transmission Provider’s overall Transmission System for the general benefit of all users of such Transmission System. Network Upgrades have no impact or potential impact on the Transmission System until the final tie-in is complete.

Notes

Note 1: PJM Open Access Transmission Tariff (OATT), Part VII, Subpart D, section 307.5 outlines cost allocation rules. The rules are further clarified in PJM Manual 14H, section 4.2.6. PJM shall identify the New Service Requests in the Cycle contributing to the need for the required Network Upgrades within the Cycle. All New Service Requests that contribute to the need for a Network Upgrade will receive cost allocation for that upgrade pursuant to each New Service Request’s contribution to the reliability violation identified on the transmission system in accordance with PJM Manuals.

Note 2: There will be no inter-Cycle cost allocation for Interconnection Facilities or Network Upgrades identified in the System Impact Study costs identified in a Cycle; all such costs shall be allocated to New Service Requests in that Cycle.

Note 3: For Project Developers with System Reinforcements listed: If this project presents cost allocation to a System Reinforcement indicates $0, then please be aware that as changes to the interconnection process occur, such as other projects withdrawing, reducing in size, etc, the cost responsibilities can change and a cost allocation may be assigned to this project. In addition, although this project presents cost allocation to a System Reinforcement is presently $0, this project may need this system reinforcement completed to be deliverable to the PJM system. If this project desires to come into service prior to completion of the system reinforcement, the Project Developer will need to request PJM to perform an interim deliverability study to determine if they would be deliverable for all or a portion of their output for each delivery year until the system reinforcement is complete.

Readiness Deposit

Per Tariff Part VII, Subpart D, section 309 (Decision Point I) A.1.a.i and PJM Manual 14H, section 6.2, Readiness Deposit #2 (RD2) are funds committed by the Project Developer or Eligible Customer based upon the applicable contribution to Network Upgrades as defined below. Readiness Deposits are not used to fund studies nor to offset Security.

During Decision Point I (DP1), the Project Developer or Eligible Customer is required to submit Readiness Deposit #2, which is calculated as 10% of cost allocation for required Phase I Network Upgrades minus Readiness Deposit #1.

Note 1: “Network Upgrades” referred to in the calculation include both (i) the Physical Interconnection Network Upgrades and (ii) the System Reliability Network Upgrades as shown in the Cost Summary table.

Note 2: Readiness Deposit #1 (RD1) = ($4,000 * Project Size (MW))

Note 3: Readiness Deposit #2 (RD2) = 10% of cost allocation for required Network Upgrades minus RD1. Readiness Deposit #2 (RD2) can be zero, but may not be a negative number.

Readiness Deposit #2 Due for Project AG2-535

Readiness Deposit #2 has been calculated for the project based on the Phase I System Impact Study results and is shown in the table below. This Readiness Deposit #2 must be provided at Decision Point I through either a wire transfer or letter of credit per Manual 14H, Section 6.2.

Readiness Deposit
Project ID10% of cost allocation for Phase I Network UpgradesReadiness Deposit #1 Received (RD1)Readiness Deposit #2 (RD2) for AG2-535 Project due at DP1
ABA - B
AG2-535$5,905,462$80,000$5,825,462

Note: Failure to provide an acceptable form of Readiness Deposit #2 by the end of Decision Point I will result in withdrawal and termination of the New Service Request.

For additional detail regarding Readiness Deposit Refunds, reference PJM Manual 14H, section 6.2.1. The Readiness Deposit Letter of Credit template can be found here.

Transmission Owner Scope of Work

The total preliminary cost estimate for the Transmission Owner scope of work (including TOIF and Physical Interconnection Network Upgrades) is given in the table below. These costs do not include CIAC Tax Gross-up.

Transmission Owner Interconnection Facilities
RTEP IDDescriptionTotal Cost ($USD)Allocated Cost ($USD)
(Pending)Integrate interconnection facilities protection and controls to the Transmission Owner system.$62,580 $62,580
(Pending)Construction of one (1) span of conductor between the new interconnection substation takeoff structure and developer owned dead end structure.$761,047 $761,047
Stand-Alone Network Upgrades
RTEP IDDescriptionTotal Cost ($USD)Allocated Cost ($USD)
(Pending)Construct a new 34.5 kV 3-breaker ring bus interconnection substation.$10,098,672 $10,098,672
(Pending)Extend fiber to new interconnection substation.$1,490,000 $1,490,000
Network Upgrades
RTEP IDDescriptionTotal Cost ($USD)Allocated Cost ($USD)
(Pending)Cut the existing 34.5 kV line and loop in the new interconnection substation.$889,363 $889,363
(Pending)Revise relay settings at Hackettstown substation as required.$52,150 $52,150
(Pending)Revise relay settings at Pohatcong Mountain substation as required.$52,150 $52,150
Physical Interconnection
RTEP IDDescriptionTotal Cost ($USD)Allocated Cost ($USD)
(Pending)Install 34.5 kV revenue metering within new interconnection substation.$59,600 $59,600

Based on the scope of work for the Interconnection Facilities, it is expected to take 40 month(s) after the signing of a Generator Interconnection Agreement (as this is a FERC connection) and construction kickoff call to complete the installation of the physical connection work. This assumes that there will be no environmental issues with any of the new properties associated with this project, that there will be no delays in acquiring the necessary permits for implementing the defined interconnection work, and that all system outages will be allowed when requested.

The schedule for any required Network Impact Reinforcements will be more clearly identified in the Phase II and Phase III System Impact Studies.

Transmission Owner Analysis

Transmission Owner Identified Network Impacts

There were no network impacts to Distribution facilities identified by the Transmission Owner.

The Transmission Owner identified network impacts to Sub-Regional facilities as follows:

Transmission Owner Identified System Reinforcements on Sub-Regional Facilities
Overloaded ElementContingencyRating [MVA]Final Cycle Loading %Contribution [MW]
206212 28CHESTER 34.5 - 207529 AG1-191 TAP 34.5 CKT 1 JC_P1-3_JCN-230-028_SRT-A (Charging)
CONTINGENCY 'JC_P1-3_JCN-230-028_SRT-A'  /* POHATCONG 230/34.5 KV BANK 1

  DISCONNECT BRANCH FROM BUS 206247 TO BUS 206219 CKT 1            /* 28POHATCNG 230 28POHATCNG 35

END
47.0167.55 %7.92
206216 28FLANDERS 34.5 - 206663 28NET R TP 34.5 CKT 1 JC_P1-3_JCN-230-028_SRT-A (Charging)
CONTINGENCY 'JC_P1-3_JCN-230-028_SRT-A'  /* POHATCONG 230/34.5 KV BANK 1

  DISCONNECT BRANCH FROM BUS 206247 TO BUS 206219 CKT 1            /* 28POHATCNG 230 28POHATCNG 35

END
50.0149.97 %6.14
206219 28POHATCNG 34.5 - 207524 AF1-328 TAP 34.5 CKT 1 Base Case (Charging) 44.0127.8 %20.0
206219 28POHATCNG 34.5 - 970848 AG2-533 TP 34.5 CKT 1 JC_P1-2_JCN-230-019_SRT-SL (Discharging/Charging)
CONTINGENCY 'JC_P1-2_JCN-230-019_SRT-SL'  /* POHATCONG - WEST WHARTON (A2001) 230 KV

  DISCONNECT BRANCH FROM BUS 206247 TO BUS 206374 CKT 1            /* 28POHATCNG 230 28ELASTMLD 230

  DISCONNECT BRANCH FROM BUS 206374 TO BUS 206377 CKT 1            /* 28ELASTMLD 230 28DOTWHART 230

  DISCONNECT BRANCH FROM BUS 206377 TO BUS 206255 CKT ZL           /* 28DOTWHART 230 28W WHRTN 230

  REMOVE LOAD C FROM BUS 206374                                    /* 28ELASTMLD 230

  REMOVE LOAD C FROM BUS 206377                                    /* 28DOTWHART 230

  SET PRECONTRATING 650 BRANCH FROM BUS 206228 TO BUS 206255 CKT 1 /* 28CHESTER 230 - 28W WHRTN 230 RATEA DERATE H2034

  SET POSTCONTRATING 813 BRANCH FROM BUS 206228 TO BUS 206255 CKT 1/* 28CHESTER 230 - 28W WHRTN 230 RATEB DERATE H2034

  SET PRECONTRATING 218 BRANCH FROM BUS 206254 TO BUS 206255 CKT 3 /* 28W WHARTN 115.00 28W WHRTN 230.00 RATEA DERATE WW#3

  SET POSTCONTRATING 263 BRANCH FROM BUS 206254 TO BUS 206255 CKT 3/* 28W WHARTN 115.00 28W WHRTN 230.00 RATEB DERATE WW#3

END
50.0107.14 %3.12
206219 28POHATCNG 34.5 - 970850 AG2-534 TP 34.5 CKT 1 JC_P1-2_JCN-230-019_SRT-SL (Discharging/Charging)
CONTINGENCY 'JC_P1-2_JCN-230-019_SRT-SL'  /* POHATCONG - WEST WHARTON (A2001) 230 KV

  DISCONNECT BRANCH FROM BUS 206247 TO BUS 206374 CKT 1            /* 28POHATCNG 230 28ELASTMLD 230

  DISCONNECT BRANCH FROM BUS 206374 TO BUS 206377 CKT 1            /* 28ELASTMLD 230 28DOTWHART 230

  DISCONNECT BRANCH FROM BUS 206377 TO BUS 206255 CKT ZL           /* 28DOTWHART 230 28W WHRTN 230

  REMOVE LOAD C FROM BUS 206374                                    /* 28ELASTMLD 230

  REMOVE LOAD C FROM BUS 206377                                    /* 28DOTWHART 230

  SET PRECONTRATING 650 BRANCH FROM BUS 206228 TO BUS 206255 CKT 1 /* 28CHESTER 230 - 28W WHRTN 230 RATEA DERATE H2034

  SET POSTCONTRATING 813 BRANCH FROM BUS 206228 TO BUS 206255 CKT 1/* 28CHESTER 230 - 28W WHRTN 230 RATEB DERATE H2034

  SET PRECONTRATING 218 BRANCH FROM BUS 206254 TO BUS 206255 CKT 3 /* 28W WHARTN 115.00 28W WHRTN 230.00 RATEA DERATE WW#3

  SET POSTCONTRATING 263 BRANCH FROM BUS 206254 TO BUS 206255 CKT 3/* 28W WHARTN 115.00 28W WHRTN 230.00 RATEB DERATE WW#3

END
48.0130.57 %2.41
206660 28NEWBRG E 34.5 - 970848 AG2-533 TP 34.5 CKT 1 JC_P1-3_JCN-230-028_SRT-A (Charging)
CONTINGENCY 'JC_P1-3_JCN-230-028_SRT-A'  /* POHATCONG 230/34.5 KV BANK 1

  DISCONNECT BRANCH FROM BUS 206247 TO BUS 206219 CKT 1            /* 28POHATCNG 230 28POHATCNG 35

END
50.0146.68 %7.93
206662 28SAXTON F 34.5 - 206661 28PANTHER 34.5 CKT 1 JC_P1-2_JCN-230-014_SRT-A (Charging)
CONTINGENCY 'JC_P1-2_JCN-230-014_SRT-A'  /* KITTATINY - POHATCONG (L2012) 230 KV & POHAT BK 1

  DISCONNECT BRANCH FROM BUS 206242 TO BUS 206247 CKT 1            /* 28KITATINY 230 28POHATCNG 230

  DISCONNECT BRANCH FROM BUS 206247 TO BUS 206219 CKT 1            /* 28POHATCNG 230 28POHATCNG 35

END
48.0129.08 %6.15
206663 28NET R TP 34.5 - 206662 28SAXTON F 34.5 CKT 1 JC_P1-2_JCN-230-014_SRT-A (Charging)
CONTINGENCY 'JC_P1-2_JCN-230-014_SRT-A'  /* KITTATINY - POHATCONG (L2012) 230 KV & POHAT BK 1

  DISCONNECT BRANCH FROM BUS 206242 TO BUS 206247 CKT 1            /* 28KITATINY 230 28POHATCNG 230

  DISCONNECT BRANCH FROM BUS 206247 TO BUS 206219 CKT 1            /* 28POHATCNG 230 28POHATCNG 35

END
48.0129.08 %6.15
206668 28COOKE CO 34.5 - 206678 28NWBRG TP 34.5 CKT 1 JC_P1-2_JCN-230-014_SRT-A (Injection/Charging)
CONTINGENCY 'JC_P1-2_JCN-230-014_SRT-A'  /* KITTATINY - POHATCONG (L2012) 230 KV & POHAT BK 1

  DISCONNECT BRANCH FROM BUS 206242 TO BUS 206247 CKT 1            /* 28KITATINY 230 28POHATCNG 230

  DISCONNECT BRANCH FROM BUS 206247 TO BUS 206219 CKT 1            /* 28POHATCNG 230 28POHATCNG 35

END
53.0133.68 %5.94
206672 28MOBIL CH 34.5 - 206673 28PORT MUR 34.5 CKT 1 JC_P1-2_JCN-230-014_SRT-A (Injection/Charging)
CONTINGENCY 'JC_P1-2_JCN-230-014_SRT-A'  /* KITTATINY - POHATCONG (L2012) 230 KV & POHAT BK 1

  DISCONNECT BRANCH FROM BUS 206242 TO BUS 206247 CKT 1            /* 28KITATINY 230 28POHATCNG 230

  DISCONNECT BRANCH FROM BUS 206247 TO BUS 206219 CKT 1            /* 28POHATCNG 230 28POHATCNG 35

END
53.0157.21 %5.94
206673 28PORT MUR 34.5 - 206668 28COOKE CO 34.5 CKT 1 JC_P1-2_JCN-230-014_SRT-A (Injection/Charging)
CONTINGENCY 'JC_P1-2_JCN-230-014_SRT-A'  /* KITTATINY - POHATCONG (L2012) 230 KV & POHAT BK 1

  DISCONNECT BRANCH FROM BUS 206242 TO BUS 206247 CKT 1            /* 28KITATINY 230 28POHATCNG 230

  DISCONNECT BRANCH FROM BUS 206247 TO BUS 206219 CKT 1            /* 28POHATCNG 230 28POHATCNG 35

END
53.0140.26 %5.94
206675 28WASHNTON 34.5 - 206776 28PVGCS 34.5 CKT 1 JC_P1-2_JCN-230-014_SRT-A (Injection/Charging)
CONTINGENCY 'JC_P1-2_JCN-230-014_SRT-A'  /* KITTATINY - POHATCONG (L2012) 230 KV & POHAT BK 1

  DISCONNECT BRANCH FROM BUS 206242 TO BUS 206247 CKT 1            /* 28KITATINY 230 28POHATCNG 230

  DISCONNECT BRANCH FROM BUS 206247 TO BUS 206219 CKT 1            /* 28POHATCNG 230 28POHATCNG 35

END
47.0177.17 %5.94
206678 28NWBRG TP 34.5 - 206219 28POHATCNG 34.5 CKT 1 JC_P1-2_JCN-230-014_SRT-A (Injection/Charging)
CONTINGENCY 'JC_P1-2_JCN-230-014_SRT-A'  /* KITTATINY - POHATCONG (L2012) 230 KV & POHAT BK 1

  DISCONNECT BRANCH FROM BUS 206242 TO BUS 206247 CKT 1            /* 28KITATINY 230 28POHATCNG 230

  DISCONNECT BRANCH FROM BUS 206247 TO BUS 206219 CKT 1            /* 28POHATCNG 230 28POHATCNG 35

END
50.0104.04 %5.94
206679 28M&M R+ 34.5 - 206792 28HACKETHOSP 34.5 CKT 1 JC_P1-2_JCN-230-019_SRT-SL
CONTINGENCY 'JC_P1-2_JCN-230-019_SRT-SL'  /* POHATCONG - WEST WHARTON (A2001) 230 KV

  DISCONNECT BRANCH FROM BUS 206247 TO BUS 206374 CKT 1            /* 28POHATCNG 230 28ELASTMLD 230

  DISCONNECT BRANCH FROM BUS 206374 TO BUS 206377 CKT 1            /* 28ELASTMLD 230 28DOTWHART 230

  DISCONNECT BRANCH FROM BUS 206377 TO BUS 206255 CKT ZL           /* 28DOTWHART 230 28W WHRTN 230

  REMOVE LOAD C FROM BUS 206374                                    /* 28ELASTMLD 230

  REMOVE LOAD C FROM BUS 206377                                    /* 28DOTWHART 230

  SET PRECONTRATING 650 BRANCH FROM BUS 206228 TO BUS 206255 CKT 1 /* 28CHESTER 230 - 28W WHRTN 230 RATEA DERATE H2034

  SET POSTCONTRATING 813 BRANCH FROM BUS 206228 TO BUS 206255 CKT 1/* 28CHESTER 230 - 28W WHRTN 230 RATEB DERATE H2034

  SET PRECONTRATING 218 BRANCH FROM BUS 206254 TO BUS 206255 CKT 3 /* 28W WHARTN 115.00 28W WHRTN 230.00 RATEA DERATE WW#3

  SET POSTCONTRATING 263 BRANCH FROM BUS 206254 TO BUS 206255 CKT 3/* 28W WHARTN 115.00 28W WHRTN 230.00 RATEB DERATE WW#3

END
48.0100.23 %2.41
206748 28DL_W4-046 34.5 - 206672 28MOBIL CH 34.5 CKT 1 JC_P1-2_JCN-230-014_SRT-A (Injection/Charging)
CONTINGENCY 'JC_P1-2_JCN-230-014_SRT-A'  /* KITTATINY - POHATCONG (L2012) 230 KV & POHAT BK 1

  DISCONNECT BRANCH FROM BUS 206242 TO BUS 206247 CKT 1            /* 28KITATINY 230 28POHATCNG 230

  DISCONNECT BRANCH FROM BUS 206247 TO BUS 206219 CKT 1            /* 28POHATCNG 230 28POHATCNG 35

END
53.0157.96 %5.94
206776 28PVGCS 34.5 - 206748 28DL_W4-046 34.5 CKT 1 JC_P1-2_JCN-230-014_SRT-A (Injection/Charging)
CONTINGENCY 'JC_P1-2_JCN-230-014_SRT-A'  /* KITTATINY - POHATCONG (L2012) 230 KV & POHAT BK 1

  DISCONNECT BRANCH FROM BUS 206242 TO BUS 206247 CKT 1            /* 28KITATINY 230 28POHATCNG 230

  DISCONNECT BRANCH FROM BUS 206247 TO BUS 206219 CKT 1            /* 28POHATCNG 230 28POHATCNG 35

END
53.0149.49 %5.94
207529 AG1-191 TAP 34.5 - 206660 28NEWBRG E 34.5 CKT 1 JC_P1-3_JCN-230-028_SRT-A (Charging)
CONTINGENCY 'JC_P1-3_JCN-230-028_SRT-A'  /* POHATCONG 230/34.5 KV BANK 1

  DISCONNECT BRANCH FROM BUS 206247 TO BUS 206219 CKT 1            /* 28POHATCNG 230 28POHATCNG 35

END
47.0185.76 %7.93
970848 AG2-533 TP 34.5 - 206219 28POHATCNG 34.5 CKT 1 JC_P1-3_JCN-230-028_SRT-A (Discharging/Charging)
CONTINGENCY 'JC_P1-3_JCN-230-028_SRT-A'  /* POHATCONG 230/34.5 KV BANK 1

  DISCONNECT BRANCH FROM BUS 206247 TO BUS 206219 CKT 1            /* 28POHATCNG 230 28POHATCNG 35

END
50.0127.16 %7.93
970850 AG2-534 TP 34.5 - 206655 28HCKTWN S 34.5 CKT 1 JC_P1-2_JCN-230-019_SRT-SL
CONTINGENCY 'JC_P1-2_JCN-230-019_SRT-SL'  /* POHATCONG - WEST WHARTON (A2001) 230 KV

  DISCONNECT BRANCH FROM BUS 206247 TO BUS 206374 CKT 1            /* 28POHATCNG 230 28ELASTMLD 230

  DISCONNECT BRANCH FROM BUS 206374 TO BUS 206377 CKT 1            /* 28ELASTMLD 230 28DOTWHART 230

  DISCONNECT BRANCH FROM BUS 206377 TO BUS 206255 CKT ZL           /* 28DOTWHART 230 28W WHRTN 230

  REMOVE LOAD C FROM BUS 206374                                    /* 28ELASTMLD 230

  REMOVE LOAD C FROM BUS 206377                                    /* 28DOTWHART 230

  SET PRECONTRATING 650 BRANCH FROM BUS 206228 TO BUS 206255 CKT 1 /* 28CHESTER 230 - 28W WHRTN 230 RATEA DERATE H2034

  SET POSTCONTRATING 813 BRANCH FROM BUS 206228 TO BUS 206255 CKT 1/* 28CHESTER 230 - 28W WHRTN 230 RATEB DERATE H2034

  SET PRECONTRATING 218 BRANCH FROM BUS 206254 TO BUS 206255 CKT 3 /* 28W WHARTN 115.00 28W WHRTN 230.00 RATEA DERATE WW#3

  SET POSTCONTRATING 263 BRANCH FROM BUS 206254 TO BUS 206255 CKT 3/* 28W WHARTN 115.00 28W WHRTN 230.00 RATEB DERATE WW#3

END
48.0105.59 %2.41
Transmission Owner Identified System Reinforcements
AG2-535 Transmission Owner Identified System Reinforcements Cost Breakdown:
TORTEP ID / TO IDCategoryTitleMW ImpactPercent AllocationAllocated Cost ($USD)
JCPL(Pending) / TC2-JCP-L04.aSubRegionalReconductor (Possible Rebuild) ~0.7 miles of the Chester - AG1-191 34.5 kV Line including (1) T-line drop at Chester7.9 MW25.6%$1,107,421
JCPL(Pending) / TC2-JCP-L04.bSubRegionalReplace (2) 750Amp Breaker leads at Chester7.9 MW25.6%$38,975
JCPL(Pending) / TC2-JCP-L07.aSubRegionalReplace (1) Misc 1250 Amp 34.5 kV CU UGS-34 [324ft of Underground riser]6.1 MW25.6%$162,088
JCPL(Pending) / TC2-JCP-L07.bSubRegionalReconductor (Possible Rebuild) ~2.9 miles of the Flanders - Bud Lake Sw Pt (R772) 34.5 kV Line6.1 MW25.6%$3,561,916
JCPL(Pending) / TC2-JCP-L07.cSubRegionalReplace (1) KD-10 Z3 relay at Flanders6.1 MW25.6%$130,503
JCPL(Pending) / TC2-JCP-L05.aSubRegionalReplace (1) 5 Amp KD-4 Relay at Pohatcong20.0 MW100.0%$509,895
JCPL(Pending) / TC2-JCP-L05.bSubRegionalReconductor (Possible Rebuild) ~1.25 miles of the Pohatcong Mountain - AF1-328 (J738) 34.5 kV Line20.0 MW100.0%$6,514,858
JCPL(Pending) / TC2-JCP-L01.aSubRegionalReplace 34.5 kV 397.5 SCCIR 26/7 (B-66599) Substation Conductor at Pohatcong11.1 MW19.6%$29,803
JCPL(Pending) / TC2-JCP-L01.bSubRegionalReconductor (Possible Rebuild) ~1.3 miles of the Pohatcong Mountain - AG2-533 34.5 kV Line11.1 MW19.6%$1,320,513
JCPL(Pending) / TC2-JCP-L01.cSubRegionalReplace (1) 6 Amp KD-4 (0.73-21.2 OHM) Relay11.1 MW19.6%$99,988
JCPL(Pending) / TC2-JCP-L06.aSubRegionalReplace (1) 5 Amp KD-4 (0.75-20 OHM) Relay at Pohatcong4.8 MW14.6%$74,310
JCPL(Pending) / TC2-JCP-L06.bSubRegionalReplace (1) 34.5 kV substation conductor at Pohatcong4.8 MW14.6%$92,590
JCPL(Pending) / TC2-JCP-L06.cSubRegionalReconductor (Possible Rebuild) ~1.3 miles of Pohatcong Mountain - AG2-534 (R722) 34.5 kV Line2.4 MW10.6%$714,335
JCPL(Pending) / TC2-JCP-L02SubRegionalReconductor (Possible Rebuild) ~1.7 miles of the AG2-533 - Newburgh 34.5 kV Line7.9 MW25.7%$2,089,207
JCPL(Pending) / TC2-JC-L16SubRegionalReconductor (Possible Rebuild) 1.7 miles of the Flanders - Pohatcong Mountain 34.5 KV Line (Saxton Falls Tap - Panther Valley Sw Pt Line section)6.2 MW25.6%$2,101,193
JCPL(Pending) / TC2-JC-L17SubRegionalReconductor (Possible Rebuild) 4.2 miles of the Flanders - Pohatcong Mountain 34.5 KV Line (Bud Lake Sw Pt - Saxton Falls Tap Line section)6.2 MW25.6%$5,478,645
JCPL(Pending) / TC2-JC-L18SubRegionalReconductor (Possible Rebuild) 3.1 miles of the Pohatcong Mountain - Washington 34.5 KV Line (Cooke Color Tap - Port Murray Line section)5.9 MW21.7%$3,387,043
JCPL(Pending) / TC2-JCP-L11SubRegionalReconductor (Possible Rebuild) ~1.2 miles of the Port Murray - Mobil Chem(Q719) 34.5 kV Line5.9 MW21.7%$1,361,365
JCPL(Pending) / TC2-JCP-L12SubRegionalReconductor (Possible Rebuild) ~2.7 miles of the Cooke Color Tap - Port Murray (Q719) 34.5 kV Line5.9 MW21.7%$3,035,349
JCPL(Pending) / TC2-JCP-L13.aSubRegionalReplace (1) 6.5 Amp GCx17A Relay Thermal at Washington5.9 MW21.7%$110,795
JCPL(Pending) / TC2-JCP-L13.bSubRegionalReconductor (Possible Rebuild) ~0.31 miles of the PVGCS T - Washington (Q719) 34.5 kV Line5.9 MW21.7%$490,269
JCPL(Pending) / TC2-JCP-L13.cSubRegionalReplace (1) 10 Amp Meter and (1) 10 Amp Relay Thermal [MCTI-39] at Washington5.9 MW21.7%$110,795
JCPL(Pending) / TC2-JCP-L13.dSubRegionalReplace (2) 1200 Amp Current Transformers at Washington5.9 MW21.7%$87,725
JCPL(Pending) / TC2-JCP-L13.eSubRegionalReplace (1) 11.1 Ohm Relay and (1) 14.53 Ohm Relay at Washington5.9 MW21.7%$110,795
JCPL(Pending) / TC2-JCP-L13.fSubRegionalReplace (1) 4.72 Ohm Relay at Washington5.9 MW21.7%$110,795
JCPL(Pending) / TC2-JC-L19SubRegionalReplace sub conductor at Pohatcong Mountain5.9 MW19.5%$49,426
JCPL(Pending) / TC2-JC-L20SubRegionalReconductor (Possible Rebuild) 1.6 miles of the Flanders - Pohatcong Mountain 34.5 KV Line (Hackettstown Hosp Tap - Hackettstown Tap Line section)2.4 MW23.3%$1,811,252
JCPL(Pending) / TC2-JCP-L14SubRegionalReconductor (Possible Rebuild) ~0.4 miles of the Mobil Chem - Domin LN Solar T (Q719) 34.5 kV Line5.9 MW21.7%$669,404
JCPL(Pending) / TC2-JCP-L15SubRegionalReconductor (Possible Rebuild) ~2.6 miles of the Domin LN Solar T - PVGCS T (Q719) 34.5 kV Line5.9 MW21.7%$2,746,122
JCPL(Pending) / TC2-JCP-L03SubRegionalReconductor (Possible Rebuild) ~6.9 miles of the Newburgh - AG1-191 34.5 kV Line7.9 MW25.7%$8,364,910
Grand Total:$46,472,285

System Reinforcement
TO
JCPL
RTEP ID / TO ID
(Pending) / TC2-JCP-L04.a
Category
SubRegional
Title
Reconductor (Possible Rebuild) ~0.7 miles of the Chester - AG1-191 34.5 kV Line including (1) T-line drop at Chester
Description
New ratings: 56/73/83 MVA SN/SE/SLD
Total Cost
$4,318,266
Contributor
Cost Allocation
ProjectMW ImpactPercent AllocationAllocated Cost ($USD)
AG2-5326.5 MW21.2%$913,942
AG2-5339.1 MW29.6%$1,277,786
AG2-5347.3 MW23.6%$1,019,116
AG2-5357.9 MW25.6%$1,107,421

System Reinforcement
TO
JCPL
RTEP ID / TO ID
(Pending) / TC2-JCP-L04.b
Category
SubRegional
Title
Replace (2) 750Amp Breaker leads at Chester
Description
New ratings: 82/84/87 MVA SN/SE/SLD
Total Cost
$151,980
Contributor
Cost Allocation
ProjectMW ImpactPercent AllocationAllocated Cost ($USD)
AG2-5326.5 MW21.2%$32,166
AG2-5339.1 MW29.6%$44,971
AG2-5347.3 MW23.6%$35,867
AG2-5357.9 MW25.6%$38,975

System Reinforcement
TO
JCPL
RTEP ID / TO ID
(Pending) / TC2-JCP-L07.a
Category
SubRegional
Title
Replace (1) Misc 1250 Amp 34.5 kV CU UGS-34 [324ft of Underground riser]
Description
New ratings: 55/67/75 MVA SN/SE/SLD
Total Cost
$633,306
Contributor
Cost Allocation
ProjectMW ImpactPercent AllocationAllocated Cost ($USD)
AG2-5325.1 MW21.3%$134,634
AG2-5335.5 MW22.9%$145,193
AG2-5347.2 MW30.2%$191,391
AG2-5356.1 MW25.6%$162,088

System Reinforcement
TO
JCPL
RTEP ID / TO ID
(Pending) / TC2-JCP-L07.b
Category
SubRegional
Title
Reconductor (Possible Rebuild) ~2.9 miles of the Flanders - Bud Lake Sw Pt (R772) 34.5 kV Line
Description
New ratings: 66/69/71 MVA SN/SE/SLD
Total Cost
$13,916,998
Contributor
Cost Allocation
ProjectMW ImpactPercent AllocationAllocated Cost ($USD)
AG2-5325.1 MW21.3%$2,958,595
AG2-5335.5 MW22.9%$3,190,641
AG2-5347.2 MW30.2%$4,205,846
AG2-5356.1 MW25.6%$3,561,916

System Reinforcement
TO
JCPL
RTEP ID / TO ID
(Pending) / TC2-JCP-L07.c
Category
SubRegional
Title
Replace (1) KD-10 Z3 relay at Flanders
Description
New ratings: 66/79/83 MVA SN/SE/SLD
Total Cost
$509,895
Contributor
Cost Allocation
ProjectMW ImpactPercent AllocationAllocated Cost ($USD)
AG2-5325.1 MW21.3%$108,398
AG2-5335.5 MW22.9%$116,900
AG2-5347.2 MW30.2%$154,095
AG2-5356.1 MW25.6%$130,503

System Reinforcement
TO
JCPL
RTEP ID / TO ID
(Pending) / TC2-JCP-L05.a
Category
SubRegional
Title
Replace (1) 5 Amp KD-4 Relay at Pohatcong
Description
New ratings: 44/53/60 MVA SN/SE/SLD
Total Cost
$509,895
Contributor
Cost Allocation
ProjectMW ImpactPercent AllocationAllocated Cost ($USD)
AG2-53520.0 MW100.0%$509,895

System Reinforcement
TO
JCPL
RTEP ID / TO ID
(Pending) / TC2-JCP-L05.b
Category
SubRegional
Title
Reconductor (Possible Rebuild) ~1.25 miles of the Pohatcong Mountain - AF1-328 (J738) 34.5 kV Line
Description
New ratings: 67/72/74 MVA SN/SE/SLD
Total Cost
$6,514,858
Contributor
Cost Allocation
ProjectMW ImpactPercent AllocationAllocated Cost ($USD)
AG2-53520.0 MW100.0%$6,514,858

System Reinforcement
TO
JCPL
RTEP ID / TO ID
(Pending) / TC2-JCP-L01.a
Category
SubRegional
Title
Replace 34.5 kV 397.5 SCCIR 26/7 (B-66599) Substation Conductor at Pohatcong
Description
New ratings: 44/53/60 MVA SN/SE/SLD
Total Cost
$151,980
Contributor
Cost Allocation
ProjectMW ImpactPercent AllocationAllocated Cost ($USD)
AG2-5329.1 MW16.1%$24,543
AG2-53326.0 MW46.2%$70,259
AG2-53410.2 MW18.0%$27,375
AG2-53511.1 MW19.6%$29,803

System Reinforcement
TO
JCPL
RTEP ID / TO ID
(Pending) / TC2-JCP-L01.b
Category
SubRegional
Title
Reconductor (Possible Rebuild) ~1.3 miles of the Pohatcong Mountain - AG2-533 34.5 kV Line
Description
New ratings: 55/57/63 MVA SN/SE/SLD
Total Cost
$6,734,018
Contributor
Cost Allocation
ProjectMW ImpactPercent AllocationAllocated Cost ($USD)
AG2-5329.1 MW16.1%$1,087,481
AG2-53326.0 MW46.2%$3,113,064
AG2-53410.2 MW18.0%$1,212,960
AG2-53511.1 MW19.6%$1,320,513

System Reinforcement
TO
JCPL
RTEP ID / TO ID
(Pending) / TC2-JCP-L01.c
Category
SubRegional
Title
Replace (1) 6 Amp KD-4 (0.73-21.2 OHM) Relay
Description
New ratings: 55/67/75 MVA SN/SE/SLD
Total Cost
$509,895
Contributor
Cost Allocation
ProjectMW ImpactPercent AllocationAllocated Cost ($USD)
AG2-5329.1 MW16.1%$82,343
AG2-53326.0 MW46.2%$235,719
AG2-53410.2 MW18.0%$91,844
AG2-53511.1 MW19.6%$99,988

System Reinforcement
TO
JCPL
RTEP ID / TO ID
(Pending) / TC2-JCP-L06.a
Category
SubRegional
Title
Replace (1) 5 Amp KD-4 (0.75-20 OHM) Relay at Pohatcong
Description
New ratings: 42/50/52 MVA SN/SE/SLD
Total Cost
$509,895
Contributor
Cost Allocation
ProjectMW ImpactPercent AllocationAllocated Cost ($USD)
AG2-5323.9 MW11.9%$60,752
AG2-5334.3 MW13.0%$66,413
AG2-53420.0 MW60.5%$308,420
AG2-5354.8 MW14.6%$74,310

System Reinforcement
TO
JCPL
RTEP ID / TO ID
(Pending) / TC2-JCP-L06.b
Category
SubRegional
Title
Replace (1) 34.5 kV substation conductor at Pohatcong
Description
New ratings: 44/53/60 MVA SN/SE/SLD
Total Cost
$635,328
Contributor
Cost Allocation
ProjectMW ImpactPercent AllocationAllocated Cost ($USD)
AG2-5323.9 MW11.9%$75,697
AG2-5334.3 MW13.0%$82,750
AG2-53420.0 MW60.5%$384,291
AG2-5354.8 MW14.6%$92,590

System Reinforcement
TO
JCPL
RTEP ID / TO ID
(Pending) / TC2-JCP-L06.c
Category
SubRegional
Title
Reconductor (Possible Rebuild) ~1.3 miles of Pohatcong Mountain - AG2-534 (R722) 34.5 kV Line
Description
New ratings: 66/76/82 MVA SN/SE/SLD
Total Cost
$6,734,018
Contributor
Cost Allocation
ProjectMW ImpactPercent AllocationAllocated Cost ($USD)
AG2-5322.0 MW8.7%$583,621
AG2-5332.1 MW9.5%$637,270
AG2-53416.2 MW71.3%$4,798,792
AG2-5352.4 MW10.6%$714,335

System Reinforcement
TO
JCPL
RTEP ID / TO ID
(Pending) / TC2-JCP-L02
Category
SubRegional
Title
Reconductor (Possible Rebuild) ~1.7 miles of the AG2-533 - Newburgh 34.5 kV Line
Description
New ratings: 77/94/106 MVA SN/SE/SLD
Total Cost
$8,140,795
Contributor
Cost Allocation
ProjectMW ImpactPercent AllocationAllocated Cost ($USD)
AG2-5326.5 MW21.2%$1,723,003
AG2-5339.1 MW29.6%$2,407,989
AG2-5347.3 MW23.6%$1,920,595
AG2-5357.9 MW25.7%$2,089,207

System Reinforcement
TO
JCPL
RTEP ID / TO ID
(Pending) / TC2-JC-L16
Category
SubRegional
Title
Reconductor (Possible Rebuild) 1.7 miles of the Flanders - Pohatcong Mountain 34.5 KV Line (Saxton Falls Tap - Panther Valley Sw Pt Line section)
Description
New ratings: 70/85/95 MVA SN/SE/SLD
Total Cost
$8,192,945
Contributor
Cost Allocation
ProjectMW ImpactPercent AllocationAllocated Cost ($USD)
AG2-5325.1 MW21.1%$1,728,787
AG2-5335.5 MW23.0%$1,885,949
AG2-5347.2 MW30.2%$2,477,016
AG2-5356.2 MW25.6%$2,101,193

System Reinforcement
TO
JCPL
RTEP ID / TO ID
(Pending) / TC2-JC-L17
Category
SubRegional
Title
Reconductor (Possible Rebuild) 4.2 miles of the Flanders - Pohatcong Mountain 34.5 KV Line (Bud Lake Sw Pt - Saxton Falls Tap Line section)
Description
New ratings: 70/85/95 MVA SN/SE/SLD
Total Cost
$21,362,263
Contributor
Cost Allocation
ProjectMW ImpactPercent AllocationAllocated Cost ($USD)
AG2-5325.1 MW21.1%$4,507,633
AG2-5335.5 MW23.0%$4,917,418
AG2-5347.2 MW30.2%$6,458,566
AG2-5356.2 MW25.6%$5,478,645

System Reinforcement
TO
JCPL
RTEP ID / TO ID
(Pending) / TC2-JC-L18
Category
SubRegional
Title
Reconductor (Possible Rebuild) 3.1 miles of the Pohatcong Mountain - Washington 34.5 KV Line (Cooke Color Tap - Port Murray Line section)
Description
New ratings: 70/85/95 MVA SN/SE/SLD
Total Cost
$15,588,670
Contributor
Cost Allocation
ProjectMW ImpactPercent AllocationAllocated Cost ($USD)
AG2-5328.4 MW30.8%$4,795,031
AG2-5335.3 MW19.5%$3,047,027
AG2-5345.5 MW20.0%$3,116,057
AG2-5355.9 MW21.7%$3,387,043
AH1-2572.2 MW8.0%$1,243,513

System Reinforcement
TO
JCPL
RTEP ID / TO ID
(Pending) / TC2-JCP-L11
Category
SubRegional
Title
Reconductor (Possible Rebuild) ~1.2 miles of the Port Murray - Mobil Chem(Q719) 34.5 kV Line
Description
New ratings: 82/100/113 MVA SN/SE/SLD
Total Cost
$6,265,216
Contributor
Cost Allocation
ProjectMW ImpactPercent AllocationAllocated Cost ($USD)
AG2-5328.4 MW30.8%$1,927,053
AG2-5335.3 MW19.5%$1,224,472
AG2-5345.5 MW20.0%$1,252,447
AG2-5355.9 MW21.7%$1,361,365
AH1-2572.2 MW8.0%$499,878

System Reinforcement
TO
JCPL
RTEP ID / TO ID
(Pending) / TC2-JCP-L12
Category
SubRegional
Title
Reconductor (Possible Rebuild) ~2.7 miles of the Cooke Color Tap - Port Murray (Q719) 34.5 kV Line
Description
New ratings: 70/85/95 MVA SN/SE/SLD
Total Cost
$13,969,148
Contributor
Cost Allocation
ProjectMW ImpactPercent AllocationAllocated Cost ($USD)
AG2-5328.4 MW30.8%$4,296,626
AG2-5335.3 MW19.5%$2,730,127
AG2-5345.5 MW20.0%$2,792,500
AG2-5355.9 MW21.7%$3,035,349
AH1-2572.2 MW8.0%$1,114,546

System Reinforcement
TO
JCPL
RTEP ID / TO ID
(Pending) / TC2-JCP-L13.a
Category
SubRegional
Title
Replace (1) 6.5 Amp GCx17A Relay Thermal at Washington
Description
New ratings: 44/53/60 MVA SN/SE/SLD
Total Cost
$509,895
Contributor
Cost Allocation
ProjectMW ImpactPercent AllocationAllocated Cost ($USD)
AG2-5328.4 MW30.8%$156,833
AG2-5335.3 MW19.5%$99,654
AG2-5345.5 MW20.0%$101,930
AG2-5355.9 MW21.7%$110,795
AH1-2572.2 MW8.0%$40,683

System Reinforcement
TO
JCPL
RTEP ID / TO ID
(Pending) / TC2-JCP-L13.b
Category
SubRegional
Title
Reconductor (Possible Rebuild) ~0.31 miles of the PVGCS T - Washington (Q719) 34.5 kV Line
Description
New ratings: 58/72/78 MVA SN/SE/SLD
Total Cost
$2,256,294
Contributor
Cost Allocation
ProjectMW ImpactPercent AllocationAllocated Cost ($USD)
AG2-5328.4 MW30.8%$693,990
AG2-5335.3 MW19.5%$440,970
AG2-5345.5 MW20.0%$451,044
AG2-5355.9 MW21.7%$490,269
AH1-2572.2 MW8.0%$180,021

System Reinforcement
TO
JCPL
RTEP ID / TO ID
(Pending) / TC2-JCP-L13.c
Category
SubRegional
Title
Replace (1) 10 Amp Meter and (1) 10 Amp Relay Thermal [MCTI-39] at Washington
Description
New ratings: 58/74/78 MVA SN/SE/SLD
Total Cost
$509,895
Contributor
Cost Allocation
ProjectMW ImpactPercent AllocationAllocated Cost ($USD)
AG2-5328.4 MW30.8%$156,833
AG2-5335.3 MW19.5%$99,654
AG2-5345.5 MW20.0%$101,930
AG2-5355.9 MW21.7%$110,795
AH1-2572.2 MW8.0%$40,683

System Reinforcement
TO
JCPL
RTEP ID / TO ID
(Pending) / TC2-JCP-L13.d
Category
SubRegional
Title
Replace (2) 1200 Amp Current Transformers at Washington
Description
New ratings: 74/75/78 MVA SN/SE/SLD
Total Cost
$403,725
Contributor
Cost Allocation
ProjectMW ImpactPercent AllocationAllocated Cost ($USD)
AG2-5328.4 MW30.8%$124,178
AG2-5335.3 MW19.5%$78,904
AG2-5345.5 MW20.0%$80,707
AG2-5355.9 MW21.7%$87,725
AH1-2572.2 MW8.0%$32,212

System Reinforcement
TO
JCPL
RTEP ID / TO ID
(Pending) / TC2-JCP-L13.e
Category
SubRegional
Title
Replace (1) 11.1 Ohm Relay and (1) 14.53 Ohm Relay at Washington
Description
New ratings: 74/83/86 MVA SN/SE/SLD
Total Cost
$509,895
Contributor
Cost Allocation
ProjectMW ImpactPercent AllocationAllocated Cost ($USD)
AG2-5328.4 MW30.8%$156,833
AG2-5335.3 MW19.5%$99,654
AG2-5345.5 MW20.0%$101,930
AG2-5355.9 MW21.7%$110,795
AH1-2572.2 MW8.0%$40,683

System Reinforcement
TO
JCPL
RTEP ID / TO ID
(Pending) / TC2-JCP-L13.f
Category
SubRegional
Title
Replace (1) 4.72 Ohm Relay at Washington
Description
New ratings: 74/90/103 MVA SN/SE/SLD
Total Cost
$509,895
Contributor
Cost Allocation
ProjectMW ImpactPercent AllocationAllocated Cost ($USD)
AG2-5328.4 MW30.8%$156,833
AG2-5335.3 MW19.5%$99,654
AG2-5345.5 MW20.0%$101,930
AG2-5355.9 MW21.7%$110,795
AH1-2572.2 MW8.0%$40,683

System Reinforcement
TO
JCPL
RTEP ID / TO ID
(Pending) / TC2-JC-L19
Category
SubRegional
Title
Replace sub conductor at Pohatcong Mountain
Description
New ratings: 44/53/60 MVA SN/SE/SLD
Total Cost
$253,989
Contributor
Cost Allocation
ProjectMW ImpactPercent AllocationAllocated Cost ($USD)
AG2-53211.6 MW38.0%$96,487
AG2-5335.3 MW17.5%$44,456
AG2-5345.5 MW17.9%$45,471
AG2-5355.9 MW19.5%$49,426
AH1-2572.2 MW7.1%$18,149

System Reinforcement
TO
JCPL
RTEP ID / TO ID
(Pending) / TC2-JC-L20
Category
SubRegional
Title
Reconductor (Possible Rebuild) 1.6 miles of the Flanders - Pohatcong Mountain 34.5 KV Line (Hackettstown Hosp Tap - Hackettstown Tap Line section)
Description
New ratings: 55/67/75 MVA SN/SE/SLD
Total Cost
$7,776,800
Contributor
Cost Allocation
ProjectMW ImpactPercent AllocationAllocated Cost ($USD)
AG2-5322.0 MW19.0%$1,481,045
AG2-5332.2 MW20.8%$1,620,950
AG2-5343.8 MW36.8%$2,863,553
AG2-5352.4 MW23.3%$1,811,252

System Reinforcement
TO
JCPL
RTEP ID / TO ID
(Pending) / TC2-JCP-L14
Category
SubRegional
Title
Reconductor (Possible Rebuild) ~0.4 miles of the Mobil Chem - Domin LN Solar T (Q719) 34.5 kV Line
Description
New ratings: 82/100/113 MVA SN/SE/SLD
Total Cost
$3,080,702
Contributor
Cost Allocation
ProjectMW ImpactPercent AllocationAllocated Cost ($USD)
AG2-5328.4 MW30.8%$947,561
AG2-5335.3 MW19.5%$602,092
AG2-5345.5 MW20.0%$615,847
AG2-5355.9 MW21.7%$669,404
AH1-2572.2 MW8.0%$245,798

System Reinforcement
TO
JCPL
RTEP ID / TO ID
(Pending) / TC2-JCP-L15
Category
SubRegional
Title
Reconductor (Possible Rebuild) ~2.6 miles of the Domin LN Solar T - PVGCS T (Q719) 34.5 kV Line
Description
New ratings: 77/94/106 MVA SN/SE/SLD
Total Cost
$12,638,082
Contributor
Cost Allocation
ProjectMW ImpactPercent AllocationAllocated Cost ($USD)
AG2-5328.4 MW30.8%$3,887,217
AG2-5335.3 MW19.5%$2,469,983
AG2-5345.5 MW20.0%$2,526,414
AG2-5355.9 MW21.7%$2,746,122
AH1-2572.2 MW8.0%$1,008,345

System Reinforcement
TO
JCPL
RTEP ID / TO ID
(Pending) / TC2-JCP-L03
Category
SubRegional
Title
Reconductor (Possible Rebuild) ~6.9 miles of the Newburgh - AG1-191 34.5 kV Line
Description
New ratings: 82/103/119 MVA SN/SE/SLD
Total Cost
$32,594,670
Contributor
Cost Allocation
ProjectMW ImpactPercent AllocationAllocated Cost ($USD)
AG2-5326.5 MW21.2%$6,898,678
AG2-5339.1 MW29.6%$9,641,271
AG2-5347.3 MW23.6%$7,689,810
AG2-5357.9 MW25.7%$8,364,910

Developer Requirements

The developer is responsible for all design and construction related activities on the developer’s side of the Point of Change in Ownership. FirstEnergy interconnection requirements can be found here.

To the extent that these Applicable Technical Requirements and Standards may conflict with the terms and conditions of the Tariff, the Tariff shall control.

Revenue Metering and SCADA Requirements

PJM Requirements
The developer will be required to install equipment necessary to provide Revenue Metering (KWH, KVARH) and real time data (KW, KVAR) for their generating Resource. See PJM Manual 01, PJM Manual 14D, and PJM Tariff Part IX, Subpart B, Appendix 2, section 8.
Transmission Owner Requirements
The Project Developer will be required to comply with all interconnected Transmission Owner’s revenue metering requirements located at the following link: PJM - Transmission Owner Engineering & Construction Standards.

Summer Peak Analysis

The New Service Request AG2-535 was evaluated as a 20.0 MW (0.0 MW Capacity) injection in the JCPL area.

AG2-535 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 40.0 MW (20.0 MW under study).

Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.

(No impacts were found for this analysis)

Winter Peak Analysis

The New Service Request AG2-535 was evaluated as a 20.0 MW (0.0 MW Capacity) injection in the JCPL area.

AG2-535 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 40.0 MW (20.0 MW under study).

Note: The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for single or N-1 contingencies and multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.

StudyAreaFacility DescriptionContingency NameContingency TypeDC|ACFinal Cycle LoadingRating (MVA)Rating TypeMVA to MitigateMW ContributionDetails
IPDPJM
PCHBTM1S-CNASTONE 500.0 kV Ckt 1 line
AP_P1-2_PE-500-3835T_SRT-A
SingleAC118.1 %3700.0B4369.615.03
IPDPJM
PCHBTM1S-CNASTONE 500.0 kV Ckt 1 line
AP_P2-3_PE-500-019E_SRT-W
BreakerAC118.06 %3700.0B4368.285.03
IPDPJM
PCHBTM1S-CNASTONE 500.0 kV Ckt 1 line
AP_P2-3_PE-500-019B_SRT-A
BreakerAC114.03 %3700.0B4219.184.7
IPDPJM
PCHBTM1S-CNASTONE 500.0 kV Ckt 1 line
PECO_P1-2_5007_SRT-A/* $ CHESCO $ PECO_P1-2_5007 $ L
SingleAC109.15 %3700.0B4038.394.07

Details for [AG2-535] PCHBTM1S-CNASTONE 500.0 kV Ckt 1 line l/o AP_P1-2_PE-500-3835T_SRT-A


Base Case Flowgate

Area:PJM
Facility Description:
PCHBTM1S-CNASTONE 500.0 kV Ckt 1 line
Contingency Name:
AP_P1-2_PE-500-3835T_SRT-A
Contingency Type:Single
DC|AC:AC
Final Cycle Loading:118.1 %
Rating:3700.0 MVA
Rating Type:B
MVA to Mitigate:4369.61
MW Contribution:5.03
IPD Plant:AG2-535
Bus #Bus NameTypeMW Contribution
970853AG2-535 GEN
PJM_IPD_GROUP
5.03

Details for [AG2-535] PCHBTM1S-CNASTONE 500.0 kV Ckt 1 line l/o AP_P2-3_PE-500-019E_SRT-W


Base Case Flowgate

Area:PJM
Facility Description:
PCHBTM1S-CNASTONE 500.0 kV Ckt 1 line
Contingency Name:
AP_P2-3_PE-500-019E_SRT-W
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:118.06 %
Rating:3700.0 MVA
Rating Type:B
MVA to Mitigate:4368.28
MW Contribution:5.03
IPD Plant:AG2-535
Bus #Bus NameTypeMW Contribution
970853AG2-535 GEN
PJM_IPD_GROUP
5.032

Details for [AG2-535] PCHBTM1S-CNASTONE 500.0 kV Ckt 1 line l/o AP_P2-3_PE-500-019B_SRT-A


Base Case Flowgate

Area:PJM
Facility Description:
PCHBTM1S-CNASTONE 500.0 kV Ckt 1 line
Contingency Name:
AP_P2-3_PE-500-019B_SRT-A
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:114.03 %
Rating:3700.0 MVA
Rating Type:B
MVA to Mitigate:4219.18
MW Contribution:4.7
IPD Plant:AG2-535
Bus #Bus NameTypeMW Contribution
970853AG2-535 GEN
PJM_IPD_GROUP
4.7

Details for [AG2-535] PCHBTM1S-CNASTONE 500.0 kV Ckt 1 line l/o PECO_P1-2_5007_SRT-A/* $ CHESCO $ PECO_P1-2_5007 $ L


Base Case Flowgate

Area:PJM
Facility Description:
PCHBTM1S-CNASTONE 500.0 kV Ckt 1 line
Contingency Name:
PECO_P1-2_5007_SRT-A/* $ CHESCO $ PECO_P1-2_5007 $ L
Contingency Type:Single
DC|AC:AC
Final Cycle Loading:109.15 %
Rating:3700.0 MVA
Rating Type:B
MVA to Mitigate:4038.39
MW Contribution:4.07
IPD Plant:AG2-535
Bus #Bus NameTypeMW Contribution
970853AG2-535 GEN
PJM_IPD_GROUP
4.069
CONTINGENCY 'AP_P1-2_PE-500-3835T_SRT-A'
 DISCONNECT BRANCH FROM BUS 270095 TO BUS 235105 CKT 1   /*CHAN         500.0 - 01DOUBS      500.0
END
CONTINGENCY 'AP_P2-3_PE-500-019E_SRT-W'
 DISCONNECT BRANCH FROM BUS 235105 TO BUS 235459 CKT 1   /*01DOUBS      500.0 - 01DOUBS      230.0
 DISCONNECT BRANCH FROM BUS 235105 TO BUS 235459 CKT 3   /*01DOUBS      500.0 - 01DOUBS      230.0
 DISCONNECT BRANCH FROM BUS 270095 TO BUS 235105 CKT 1   /*CHAN         500.0 - 01DOUBS      500.0
 REMOVE SWSHUNT FROM BUS 235105 BLOCK 1 STEP 2           /*01DOUBS      500.0
END
CONTINGENCY 'AP_P2-3_PE-500-019B_SRT-A'
 DISCONNECT BRANCH FROM BUS 235105 TO BUS 200003 CKT 1   /*01DOUBS      500.0 - BRIGHTON     500.0
 DISCONNECT BRANCH FROM BUS 270095 TO BUS 235105 CKT 1   /*CHAN         500.0 - 01DOUBS      500.0
END
CONTINGENCY 'PECO_P1-2_5007_SRT-A
 TRIP BRANCH FROM BUS 200066 TO BUS 270095 CKT 1   /*PCHBTM1N     500.0 - CHAN         500.0
END
200064 to 200004 ckt 1

Light Load Analysis

The New Service Request AG2-535 was evaluated as a 20.0 MW injection and 20.0 MW withdrawal in the JCPL area.

AG2-535 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 40.0 MW (20.0 MW under study).

Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.

(No impacts were found for this analysis)

Short Circuit Analysis

Short Circuit analysis is not performed as part of the Phase I System Impact Study. Short Circuit analysis will commence in the Phase II System Impact Study.

Stability Analysis

Stability analysis is not performed as part of the Phase I System Impact Study. Stability analysis will commence in the Phase II System Impact Study.

Reactive Power Analysis

Reactive Power analysis is not performed as part of the Phase I System Impact Study. Reactive Power analysis will commence in the Phase II System Impact Study.

Steady-State Voltage Analysis

Steady State Voltage Analysis is Not Required.

New Service Request Dependencies

The New Service Requests below are listed in one or more dispatch for the overloads identified in this report. These projects contribute to the loading of the overloaded facilities identified in this report. The percent overload of a facility and cost allocation you may have towards a particular reinforcement could vary depending on the action of other projects. The status of each project at the time of the analysis is presented in the table. This list may change as other projects withdraw or modify their requests. This table is valid for load flow analyses only.

New Service Requests Dependencies
Project IDProject NameStatus

Affected System - PJM Identified Violations

As part of PJM's analysis, PJM evaluated the potential impacts on tie line facilities between PJM and an affected system entity, which were identified per PJM planning analysis criteria. This upgrade may be required on the affected system portion of the tie line along with cost allocation of such upgrade if applicable, in coordination with the affected system. Depending on the affected system, this project may not be contingent on upgrade based on PJM planning analysis criteria, but may be contingent on this upgrade based on the Affected System Operator's planning criteria, provided in the Affected Systems Study Section, herein.

Midcontinent Independent System Operator, Inc. (MISO)No Impact
New York Independent System Operator (NYISO)No Impact
Tennessee Valley Authority (TVA)No Impact
Louisville Gas & Electric (LG&E)No Impact
Duke Energy Carolinas (DUKE)No Impact
Duke Energy Progress – East (CPLE)No Impact
Duke Energy Progress – West (CPLW)No Impact

Affected System - Non-PJM Identified Violations

In Phase I of the Cycle, PJM conducts an Affected System screen to identify any New Service Request with potential Affected System impacts. PJM initiates coordination with each Affected System Operator by providing a list of New Service Requests in the Cycle with potential impacts to their respective system. If the Affected System Operator indicates an Affected System Study is required, PJM will notify the Project Developer or Eligible Customer of the need for an Affected System Study. See below if any Affected System Operator requires a study for this project:

Midcontinent Independent System Operator, Inc. (MISO)Not required
New York Independent System Operator (NYISO)Not required
Tennessee Valley Authority (TVA)Not required
Louisville Gas & Electric (LG&E)Not required
Duke Energy Carolinas (DUKE)Not required
Duke Energy Progress – East (CPLE)Not required
Duke Energy Progress – West (CPLW)Not required

System Reinforcements

No cost allocated system reinforcements were identified for this project in the Phase I System Impact Study load flow analysis.

Shown below are the details of the cost allocated, contingent, eliminated, topology and potential aggregate contributor reinforcements for this project. Please refer to the System Reinforcement table above and the information below for more detail.


System Reinforcement: b3800.37
Type
Load Flow
TO
BGE
RTEP ID / TO ID
b3800.37
Title
Replace terminal equipment limitations at Conastone 500 kV - on the (existing Peach Bottom-Conastone) or (new Graceton-Conastone) 500 kV line (Projected ISD 12/31/2030)
Description
None
Cost Information
Time Estimate
Dec 31 2030

Not Contingent

Note: AG2-535 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-535 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

FacilityContingency
CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line(Any)

System Reinforcement: b3800.42
Type
Load Flow
TO
PECO
RTEP ID / TO ID
b3800.42
Title
Peach Bottom 500kV North bus upgrade (Projected ISD 12/1/2030)
Description
Peach Bottom 500kV North bus upgrade - Replace 11 – Instances of strain bus conductor used for breaker drops or CT drops, 7 – 500 kV disconnect switches, 7 – Free Standing CTs, 1 – 500 kV breaker, 2 – Breaker relays or meters.
Cost Information
Time Estimate
Dec 01 2030

Not Contingent

Note: AG2-535 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-535 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

FacilityContingency
CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line(Any)

System Reinforcement: b3780.1
Type
Load Flow
TO
PECO
RTEP ID / TO ID
b3780.1
Title
Peach Bottom North upgrades – substation work (Projected ISD 12/31/2028)
Description
Add 3x 500 kV breakers to form a breaker-and-a-half bay.
Cost Information
Time Estimate
Dec 31 2028

Not Contingent

Note: AG2-535 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-535 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

FacilityContingency
CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line(Any)

System Reinforcement: b3780.6
Type
Load Flow
TO
BGE
RTEP ID / TO ID
b3780.6
Title
Build Granite substation + Statcom (Projected ISD 12/31/2028)
Description
Build Granite substation + Statcom. New STATCOM rating: 350 MVAR. Add 4x 230 kV breaker bays.
Cost Information
Time Estimate
Dec 31 2028

Not Contingent

Note: AG2-535 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-535 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

FacilityContingency
CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line(Any)

System Reinforcement: b3780.9
Type
Load Flow
TO
BGE
RTEP ID / TO ID
b3780.9
Title
Graceton to Batavia Road 230 kV double circuit pole line (Projected ISD 12/31/2028)
Description
Graceton to Batavia Road 230 kV double circuit pole line New rating: 1331 MVA SN/ 1594 MVA SE
Cost Information
Time Estimate
Dec 31 2028

Not Contingent

Note: AG2-535 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-535 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

FacilityContingency
CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line(Any)

System Reinforcement: b3800.35
Type
Load Flow
TO
PECO
RTEP ID / TO ID
b3800.35
Title
Rebuild 5012 (existing Peach Bottom-Conastone) (new North Delta-Graceton PECO) 500 kV (Projected ISD 12/1/2030)
Description
Rebuild 5012 (existing Peach Bottom-Conastone) (new North Delta-Graceton PECO) 500 kV line on single circuit structures within existing ROW and cut into North Delta 500 kV and Gracetone 500 kV stations.
Cost Information
Time Estimate
Dec 01 2030

Not Contingent

Note: AG2-535 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-535 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

FacilityContingency
CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line(Any)

System Reinforcement: b3800.48
Type
Load Flow
TO
PECO
RTEP ID / TO ID
b3800.48
Title
North Delta termination for the North Delta-High Ridge 500 line (Transource work).
Description
None
Cost Information
Time Estimate
Dec 15 2030

Not Contingent

Note: AG2-535 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-535 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

FacilityContingency
CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line(Any)

System Reinforcement: b3800.32
Type
Load Flow
TO
BGE
RTEP ID / TO ID
b3800.32
Title
Build new North Delta-High Ridge 500 kV line - BGE Portion (Projected ISD 12/31/2030)
Description
Build new North Delta-High Ridge 500 kV line. (~59 miles)
Cost Information
Time Estimate
Dec 31 2030

Not Contingent

Note: AG2-535 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-535 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

FacilityContingency
CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line(Any)

System Reinforcement: b3800.36
Type
Load Flow
TO
BGE
RTEP ID / TO ID
b3800.36
Title
Rebuild 5012 (existing Peach Bottom-Conastone) (new North Delta-Graceton BGE) 500 kV (Projected ISD 12/31/2030)
Description
Rebuild 5012 (existing Peach Bottom-Conastone) (new North Delta-Graceton BGE) 500 kV line on single circuit structures within existing ROW and cut into North Delta 500 kV and Gracetone 500 kV stations.
Cost Information
Time Estimate
Dec 31 2030

Not Contingent

Note: AG2-535 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-535 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

FacilityContingency
CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line(Any)

System Reinforcement: b3800.26
Type
Load Flow
TO
BGE
RTEP ID / TO ID
b3800.26
Title
Build High Ridge 500 kV substation - Three bay breaker and half configuration (Projected ISD 12/31/2030)
Description
None
Cost Information
Time Estimate
Dec 31 2030

Not Contingent

Note: AG2-535 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-535 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

FacilityContingency
CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line(Any)

System Reinforcement: b3800.46
Type
Load Flow
TO
PEPCO
RTEP ID / TO ID
b3800.46
Title
North Delta 500 kV termination for the new Peach Bottom-North Delta 500 kV line (PECO work).
Description
Loops in the 500kV line from Peach Bottom to Rock Springs into the new North Delta (Bramah) sub
Cost Information
Time Estimate
Dec 01 2030

Not Contingent

Note: AG2-535 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-535 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

FacilityContingency
CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line(Any)

System Reinforcement: b3780.16
Type
Load Flow
TO
PECO
RTEP ID / TO ID
b3780.16
Title
Terminate new Cooper-North Delta 230 kV line (Transource Scope) at North Delta 230 kV
Description
None
Cost Information
Time Estimate
Oct 15 2028

Not Contingent

Note: AG2-535 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-535 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

FacilityContingency
CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line(Any)

System Reinforcement: b3800.31
Type
Load Flow
TO
PECO
RTEP ID / TO ID
b3800.31
Title
Build new North Delta-High Ridge 500 kV line - PECO Portion (Projected ISD 12/1/2030)
Description
None
Cost Information
Time Estimate
Dec 01 2030

Not Contingent

Note: AG2-535 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-535 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

FacilityContingency
CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line(Any)

System Reinforcement: b3800.30
Type
Load Flow
TO
BGE
RTEP ID / TO ID
b3800.30
Title
High Ridge - Install two 500/230 kV transformers (Projected ISD 12/31/2030)
Description
None
Cost Information
Time Estimate
Dec 31 2030

Not Contingent

Note: AG2-535 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-535 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

FacilityContingency
CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line(Any)

System Reinforcement: b3780.17
Type
Load Flow
TO
PECO
RTEP ID / TO ID
b3780.17
Title
Cut in 5012 Peach Bottom-Conastone 500 kV line into North Delta 500/230 kV sub (Transource)
Description
Cut in 5012 Peach Bottom-Conastone 500 kV line into North Delta 500/230 kV substation by rebuilding 5012 between new terminal at Peach Bottom South and North Delta on single circuit structures and terminating at North Delta (Transource Scope).
Cost Information
Time Estimate
May 31 2028

Not Contingent

Note: AG2-535 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-535 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

FacilityContingency
CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line(Any)

System Reinforcement: b3800.49
Type
Load Flow
TO
PECO
RTEP ID / TO ID
b3800.49
Title
North Delta 500 kV termination for the Calpine generator (Calpine/Transource work).
Description
None
Cost Information
Time Estimate
Oct 06 2027

Not Contingent

Note: AG2-535 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-535 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

FacilityContingency
CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line(Any)

System Reinforcement: b3800.45
Type
Load Flow
TO
PECO
RTEP ID / TO ID
b3800.45
Title
North Delta 500 kV termination for the Rock Springs 500 kV line (5034/5014 line) (PECO work).
Description
Loops in the 500kV line from Peach Bottom to Rock Springs into the new North Delta (Bramah) sub
Cost Information
Time Estimate
Dec 01 2030

Not Contingent

Note: AG2-535 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-535 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

FacilityContingency
CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line(Any)

System Reinforcement: b3780.13
Type
Load Flow
TO
BGE
RTEP ID / TO ID
b3780.13
Title
Batavia Road to Riverside 230 kV reconductor
Description
Batavia Road to Riverside 230 kV reconductor New rating: 1941 MVA SN / 2181 MVA SE
Cost Information
Time Estimate
Dec 31 2027

Not Contingent

Note: AG2-535 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-535 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

FacilityContingency
CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line(Any)

System Reinforcement: b3800.52
Type
Load Flow
TO
PECO
RTEP ID / TO ID
b3800.52
Title
Reconfigure Peach Bottom North and South 500 kV yards (Projected ISD 12/1/2030)
Description
Reconfigure Peach Bottom North and South yards to allow for termination of 500 kV lines from Peach Bottom to North Delta. North Delta 500 kV termination for the new Peach Bottom-North Delta 500 kV line.
Cost Information
Time Estimate
Dec 01 2030

Not Contingent

Note: AG2-535 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-535 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

FacilityContingency
CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line(Any)

System Reinforcement: b3780.8
Type
Load Flow
TO
BGE
RTEP ID / TO ID
b3780.8
Title
Graceton 500 kV substation expansion (Projected ISD 12/31/2028)
Description
Add 3x 500 kV breaker bays, 2x 500/230 kV auto transformer, 1x 500 kV caps
Cost Information
Time Estimate
Dec 31 2028

Not Contingent

Note: AG2-535 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-535 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

FacilityContingency
CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line(Any)

System Reinforcement: b3800.47
Type
Load Flow
TO
PECO
RTEP ID / TO ID
b3800.47
Title
Build new Peach Bottom South-North Delta 500 kV line (Projected ISD 12/1/2030)
Description
Build new Peach Bottom South-North Delta 500 kV line – cut in to Peach Bottom tie No. 1 and extending line to North Delta (~1.25 miles new ROW).
Cost Information
Time Estimate
Dec 01 2030

Not Contingent

Note: AG2-535 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-535 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

FacilityContingency
CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line(Any)

System Reinforcement: b3780.11
Type
Load Flow
TO
PEPCO
RTEP ID / TO ID
b3780.11
Title
Brighton Statcom and Capacitor (Projected ISD 12/31/2028)
Description
Brighton Statcom and capacitor New STATCOM rating: 350 MVAR New capacitor rating: 350 MVAR
Cost Information
Time Estimate
Dec 31 2028

Not Contingent

Note: AG2-535 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-535 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

FacilityContingency
CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line(Any)

System Reinforcement: b3800.29
Type
Load Flow
TO
BGE
RTEP ID / TO ID
b3800.29
Title
High Ridge termination for the North Delta-High Ridge 500 kV line (Projected ISD 12/31/2030)
Description
None
Cost Information
Time Estimate
Dec 31 2030

Not Contingent

Note: AG2-535 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-535 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

FacilityContingency
CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line(Any)

System Reinforcement: b3737.50
Type
Load Flow
TO
PECO
RTEP ID / TO ID
b3737.50
Title
Bring the Peach Bottom-Delta Power Plant 500 kV line “in and out” of North Delta
Description
Bring the Peach Bottom-Delta Power Plant 500 kV line “in and out” of North Delta by constructing a new Peach Bottom-North Delta 500 kV (0.3 miles) cut-in and cut-out lines.
Cost Information
Time Estimate
Jun 01 2029

Not Contingent

Note: AG2-535 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-535 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

FacilityContingency
CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line(Any)

System Reinforcement: b3780.7
Type
Load Flow
TO
BGE
RTEP ID / TO ID
b3780.7
Title
Build new Batavia Road substation (Projected ISD 12/31/2028)
Description
Build Batavia Road substation. Add 4 x 230kV breaker bays
Cost Information
Time Estimate
Dec 31 2028

Not Contingent

Note: AG2-535 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-535 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

FacilityContingency
CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line(Any)

System Reinforcement: b3800.34
Type
Load Flow
TO
BGE
RTEP ID / TO ID
b3800.34
Title
Rebuild 5012 (existing Peach Bottom-Conastone) (new Graceton-Conastone) 500 kV and cut into North Delta 500kV (Projected ISD 12/31/2030)
Description
Rebuild 5012 (existing Peach Bottom-Conastone) (new Graceton-Conastone) 500 kV line on single circuit structures within existing ROW and cut into North Delta 500 kV and Gracetone 500 kV stations.
Cost Information
Time Estimate
Dec 31 2030

Not Contingent

Note: AG2-535 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-535 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

FacilityContingency
CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line(Any)

System Reinforcement: b3800.27
Type
Load Flow
TO
BGE
RTEP ID / TO ID
b3800.27
Title
High Ridge 500 kV substation (cut into Brighton-Waugh Chapel 500 kV line) - Waugh Chapel side (Projected ISD 12/31/2030)
Description
None
Cost Information
Time Estimate
Dec 31 2030

Not Contingent

Note: AG2-535 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-535 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

FacilityContingency
CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line(Any)

System Reinforcement: b3780.14
Type
Load Flow
TO
PECO
RTEP ID / TO ID
b3780.14
Title
Reconfigure Cooper transmission feeds by establishing new Cooper-North Delta 230 kV line and rerouting existing transmissions lines by Cooper.
Description
None
Cost Information
Time Estimate
Dec 31 2028

Not Contingent

Note: AG2-535 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-535 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

FacilityContingency
CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line(Any)

System Reinforcement: b3780.5
Type
Load Flow
TO
BGE
RTEP ID / TO ID
b3780.5
Title
Build Solley Road substation + Statcom (Projected ISD 12/31/2028)
Description
Build Solley Road substation + Statcom. New STATCOM rating: 350 MVAR Add 4x 230 kV breakers bays.
Cost Information
Time Estimate
Dec 31 2028

Not Contingent

Note: AG2-535 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-535 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

FacilityContingency
CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line(Any)

System Reinforcement: b3800.50
Type
Load Flow
TO
PECO
RTEP ID / TO ID
b3800.50
Title
North Delta 500 kV termination for the Rock Springs 500 kV line (5034/5014 line) (Transource work).
Description
Loops in the 500kV line from Peach Bottom to Rock Springs into the new North Delta (Bramah) sub
Cost Information
Time Estimate
Jan 23 2028

Not Contingent

Note: AG2-535 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-535 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

FacilityContingency
CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line(Any)

System Reinforcement: b3800.51
Type
Load Flow
TO
PECO
RTEP ID / TO ID
b3800.51
Title
North Delta 500 kV termination for the new Peach Bottom-North Delta 500 kV line (Transource work).
Description
Loops in the 500kV line from Peach Bottom to Rock Springs into the new North Delta (Bramah) sub
Cost Information
Time Estimate
May 31 2028

Not Contingent

Note: AG2-535 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-535 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

FacilityContingency
CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line(Any)

System Reinforcement: b3780.15
Type
Load Flow
TO
PECO
RTEP ID / TO ID
b3780.15
Title
Cut in 5012 Peach Bottom-Conastone 500 kV line into North Delta 500/230 kV sub
Description
Cut in 5012 Peach Bottom-Conastone 500 kV line into North Delta 500/230 kV substation by rebuilding 5012 between new terminal at Peach Bottom South and North Delta on single circuit structures and terminating at North Delta.
Cost Information
Time Estimate
Dec 31 2028

Not Contingent

Note: AG2-535 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-535 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

FacilityContingency
CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line(Any)

System Reinforcement: b3800.28
Type
Load Flow
TO
BGE
RTEP ID / TO ID
b3800.28
Title
High Ridge 500 kV substation (cut into Brighton-Waugh Chapel 500 kV line) -Brighton side (Projected ISD 12/31/2030)
Description
None
Cost Information
Time Estimate
Dec 31 2030

Not Contingent

Note: AG2-535 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-535 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

FacilityContingency
CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line(Any)

System Reinforcement: b3737.47
Type
Load Flow
TO
PECO
RTEP ID / TO ID
b3737.47
Title
Build New North Delta 500 kV substation (Four bay breaker and half configuration)
Description
Build New North Delta 500 kV substation (four bay breaker and half configuration) - the substation will include 12 - 500kV breakers and one 500/230 kV transformer, will allow the termination of six - 500 kV lines
Cost Information
Time Estimate
Oct 15 2027

Not Contingent

Note: AG2-535 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-535 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

FacilityContingency
CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line(Any)

System Reinforcement: b3800.44
Type
Load Flow
TO
PECO
RTEP ID / TO ID
b3800.44
Title
North Delta termination for the North Delta-High Ridge 500 line (PECO work).
Description
None
Cost Information
Time Estimate
Dec 01 2030

Not Contingent

Note: AG2-535 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-535 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

FacilityContingency
CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line(Any)

System Reinforcement: b3800.33
Type
Load Flow
TO
BGE
RTEP ID / TO ID
b3800.33
Title
Replace terminal equipment limitations at Brighton 500 kV - on the existing Brighton-Waugh Chapel 500 kV (5053) or new Brighton-High Ridge 500 kV.
Description
None
Cost Information
Time Estimate
Dec 31 2030

Not Contingent

Note: AG2-535 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-535 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

FacilityContingency
CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line(Any)

System Reinforcement: b3780.2
Type
Load Flow
TO
PECO
RTEP ID / TO ID
b3780.2
Title
Peach Bottom to Graceton (PECO Portion) – New 500kV Line
Description
Peach Bottom to Graceton (PECO Portion) – New 500kV Line. New rating: 4503 MVA SN/ 5022 MVA SE. This is a baseline identified for the announced Brandon Shores deactivation.
Cost Information
Time Estimate
Dec 31 2028

Not Contingent

Note: AG2-535 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-535 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

FacilityContingency
CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line(Any)

System Reinforcement: b3780.4
Type
Load Flow
TO
BGE
RTEP ID / TO ID
b3780.4
Title
Peach Bottom to Graceton (BGE Portion) – New 500kV Line
Description
New rating: 4503 MVA SN/ 5022 MVA SE. This is a baseline identified for the announced Brandon Shores deactivation.
Cost Information
Time Estimate
Dec 31 2028

Not Contingent

Note: AG2-535 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-535 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

FacilityContingency
CNASTONE-PCHBTM1S 500.0 kV Ckt 1 line(Any)

Attachments

AG2-535 One Line Diagram

AG2-535 One Line Diagram.pdf
The state in which the generator or merchant transmission facility is located.
The Transmission Owner of the facility where the New Service Request project interconnects to the transmission system.
Winter load flow analysis will be performed starting in Transition Cycle 2.