AH1-051 Phase I Study Report
v1.00 released 2025-10-29 21:20
Eclipse-Piney 115 kV II
18.0 MW Capacity / 30.0 MW Energy
Introduction
This Phase I System Impact Study Report (PH1) has been prepared in accordance with the PJM Open Access Transmission Tariff, Part VII, Subpart D, sections 307 and 308 for New Service Requests (projects) in Transition Cycle 2. The Project Developer/Eligible Customer (developer) is Deal Solar LLC, and the Transmission Provider (TP) is PJM Interconnection, LLC (PJM). The interconnected Transmission Owner (TO) is Mid-Atlantic Interstate Transmission, LLC.
Preface
The Phase I System Impact Study is conducted on an aggregate basis within a New Services Request’s Cycle, and results are provided in both (i) a single Cycle executive summary format and (ii) an individual project-level basis. The Phase I System Impact Study Results (for both the executive summary and individual reports) will be publicly available on PJM’s website. Developers must obtain the results from the website.
In accordance with PJM Manual 14H, section 4.3, PJM takes the following actions during the Phase I System Impact Study:
- PJM studies each New Service Request on a summer peak, winter peak and light load RTEP base case study. The case year is dependent on the new services cycle under study. PJM will identify the base case year to be used in the study of a specific cycle on its website.
- PJM will only perform load flow analysis during the Phase I System Impact Study.
- In Phase I of the Cycle, PJM conducts an Affected System screen to identify any New Service Request with Affected System impacts and provides each Affected System Operator with a list of New Service Request in the Cycle with potential impacts to their respective system.
- PJM will create both the short circuit and stability base cases to be used in the Phase II System Impact Study.
- The Phase I System Impact Study results will be publicly available on PJM’s website. Project Developers and Eligible Customers must obtain the results from the website.
The Transmission Owner takes the following actions during the Phase I System Impact Study:
- Identify required Interconnection Facilities to accommodate the New Service Request.
- Identify required Network Upgrades to mitigate system violations from the Phase I System Impact Study.
- Provide planning-level preliminary estimates of Interconnection Facilities and Network Upgrades including scope, cost and elapsed time to complete the work.
Decision Point I Requirements
At the close of Phase I System Impact Study, PJM will initiate Decision Point I (DP1). During DP1, the Project Developer will have 30 days to decide whether to proceed with their project. If the Project Developer elects to proceed, they should provide the elements defined in the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 309.A.1. Additional information on these elements is available in PJM Manual 14H sections 4.4, 6, and 7.
Allowable project modifications at Decision Point I are defined in PJM Open Access Transmission Tariff, Part VII, Subpart D, section 309.B. Additional information regarding allowable project modifications can be found in PJM Manual 14H, section 9.8.
General
The Project Developer has proposed an uprate to a planned/existing Solar facility located in the Mid-Atlantic Interstate Transmission, LLC zone — Venango County, Pennsylvania. This project is an increase to the developer’s AH1-050 project(s), which will share the same Point of Interconnection. The AH1-051 project is a 30.0 MW uprate (18.0 MW Capacity uprate) to the previous project(s). The total installed facilities will have a capability of 80.0 MW with 48.0 MW of this output being recognized by PJM as Capacity.Project Information
Physical Interconnection Facility Study
Physical Interconnection Facilities Study is not performed as part of the Phase I System Impact Study. Physical Interconnection Facilities Study will commence in the Phase II System Impact Study.
Point of Interconnection
AH1-051 will interconnect on the Mid-Atlantic Interstate Transmission, LLC transmission system by tapping the Eclipse - Piney 115 kV line as an uprate to AH1-050. AH1-051 is uprated by AH1-158. All three projects are in Transition Cycle 2 and will share costs for the required Transmission Owner Interconnection Facilities and physical interconnection Network Upgrades
Cost Summary
The table below shows a summary of the total cost estimates for this New Service Request project. In the Phase I SIS, the costs shown are subject to change as a result of a facility study performed by the TO during the Phase II or Phase III System Impact Study.
Based on the Phase I SIS results, the AH1-051 project has the following allocation of costs for interconnection. The cost contribution towards Readiness Deposit are also shown below.
| Cost Summary | |||
|---|---|---|---|
| Description | Cost Allocated to AH1-051 | Cost Subject to Readiness* | |
| Transmission Owner Interconnection Facilities (TOIF) | $274,542 | $0 | |
| Other Scope | $19,867 | $0 | |
| Option To Build Oversight | $0 | $0 | |
| Physical Interconnection Network Upgrades | |||
| Stand Alone Network Upgrades | $4,906,044 | $4,906,044 | |
| Network Upgrades | $577,192 | $577,192 | |
| System Reliability Network Upgrades | |||
| Steady State Thermal & Voltage (SP & LL) | $7,619,826 | $7,619,826 | |
| Transient Stability | $0 | $0 | |
| Short Circuit | $0 | $0 | |
| Transmission Owner Analysis | |||
| SubRegional | $0 | $0 | |
| Distribution | $0 | $0 | |
| Affected System Reinforcements | |||
| AFS - PJM Violatons | $0 | $0 | |
| AFS - Non-PJM Violations | $0 | $0 | |
| Total | $13,397,470 | $13,103,061 | |
* Contributes to calculation for Readiness Deposit #2 (RD2). See Readiness Deposit section of report for additional detail.
Definitions
Transmission Owner Interconnection Facilities: Facilities that are owned, controlled, operated and maintained by the Transmission Owner on the Transmission Owner’s side of the Point of Change of Ownership to the Point of Interconnection, including any modifications, additions or upgrades made to such facilities and equipment, that are necessary to physically and electrically interconnect the Generating Facility with the Transmission System or interconnected distribution facilities.
Stand Alone Network Upgrades: Network Upgrades, which are not part of an Affected System, which a Project Developer may construct without affecting day-to-day operations (e.g. taking a transmission outage) of the Transmission System during their construction.
Network Upgrades: Modifications or additions to transmission-related facilities that are integrated with and support the Transmission Provider’s overall Transmission System for the general benefit of all users of such Transmission System. Network Upgrades have no impact or potential impact on the Transmission System until the final tie-in is complete.
Notes
Note 1: PJM Open Access Transmission Tariff (OATT), Part VII, Subpart D, section 307.5 outlines cost allocation rules. The rules are further clarified in PJM Manual 14H, section 4.2.6. PJM shall identify the New Service Requests in the Cycle contributing to the need for the required Network Upgrades within the Cycle. All New Service Requests that contribute to the need for a Network Upgrade will receive cost allocation for that upgrade pursuant to each New Service Request’s contribution to the reliability violation identified on the transmission system in accordance with PJM Manuals.
Note 2: There will be no inter-Cycle cost allocation for Interconnection Facilities or Network Upgrades identified in the System Impact Study costs identified in a Cycle; all such costs shall be allocated to New Service Requests in that Cycle.
Note 3: For Project Developers with System Reinforcements listed: If this project presents cost allocation to a System Reinforcement indicates $0, then please be aware that as changes to the interconnection process occur, such as other projects withdrawing, reducing in size, etc, the cost responsibilities can change and a cost allocation may be assigned to this project. In addition, although this project presents cost allocation to a System Reinforcement is presently $0, this project may need this system reinforcement completed to be deliverable to the PJM system. If this project desires to come into service prior to completion of the system reinforcement, the Project Developer will need to request PJM to perform an interim deliverability study to determine if they would be deliverable for all or a portion of their output for each delivery year until the system reinforcement is complete.
Readiness Deposit
Per Tariff Part VII, Subpart D, section 309 (Decision Point I) A.1.a.i and PJM Manual 14H, section 6.2, Readiness Deposit #2 (RD2) are funds committed by the Project Developer or Eligible Customer based upon the applicable contribution to Network Upgrades as defined below. Readiness Deposits are not used to fund studies nor to offset Security.
During Decision Point I (DP1), the Project Developer or Eligible Customer is required to submit Readiness Deposit #2, which is calculated as 10% of cost allocation for required Phase I Network Upgrades minus Readiness Deposit #1.
Note 1: “Network Upgrades” referred to in the calculation include both (i) the Physical Interconnection Network Upgrades and (ii) the System Reliability Network Upgrades as shown in the Cost Summary table.
Note 2: Readiness Deposit #1 (RD1) = ($4,000 * Project Size (MW))
Note 3: Readiness Deposit #2 (RD2) = 10% of cost allocation for required Network Upgrades minus RD1. Readiness Deposit #2 (RD2) can be zero, but may not be a negative number.
Readiness Deposit #2 Due for Project AH1-051
Readiness Deposit #2 has been calculated for the project based on the Phase I System Impact Study results and is shown in the table below. This Readiness Deposit #2 must be provided at Decision Point I through either a wire transfer or letter of credit per Manual 14H, Section 6.2.
| Readiness Deposit | |||
|---|---|---|---|
| Project ID | 10% of cost allocation for Phase I Network Upgrades | Readiness Deposit #1 Received (RD1) | Readiness Deposit #2 (RD2) for AH1-051 Project due at DP1 |
| A | B | A - B | |
| AH1-051 | $1,310,306 | $120,000 | $1,190,306 |
Note: Failure to provide an acceptable form of Readiness Deposit #2 by the end of Decision Point I will result in withdrawal and termination of the New Service Request.
For additional detail regarding Readiness Deposit Refunds, reference PJM Manual 14H, section 6.2.1. The Readiness Deposit Letter of Credit template can be found here.
Transmission Owner Scope of Work
The total preliminary cost estimate for the Transmission Owner scope of work (including TOIF and Physical Interconnection Network Upgrades) is given in the table below. These costs do not include CIAC Tax Gross-up.
| Transmission Owner Interconnection Facilities | |||
|---|---|---|---|
| RTEP ID | Description | Total Cost ($USD) | Allocated Cost ($USD) |
| (Pending) | Integrate Interconnection Facilities protection and controls to the Transmission Owner system. | $62,580 | $20,860 (See Note 1) |
| (Pending) | Construction of (1) span of conductor between the new Interconnection substation takeoff structure and Developer owned dead end structure. | $761,047 | $253,682 (See Note 1) |
| Stand-Alone Network Upgrades | |||
|---|---|---|---|
| RTEP ID | Description | Total Cost ($USD) | Allocated Cost ($USD) |
| (Pending) | Construct a new 115 kV 3-breaker ring bus Interconnection substation. | $13,228,131 | $4,409,377 (See Note 1) |
| (Pending) | ADSS fiber to new interconnection substation. | $1,490,000 | $496,667 (See Note 1) |
| Network Upgrades | |||
|---|---|---|---|
| RTEP ID | Description | Total Cost ($USD) | Allocated Cost ($USD) |
| (Pending) | Revise relay settings at Eclipse substation as required. | $52,150 | $17,383 (See Note 1) |
| (Pending) | Revise relay settings at Piney substation as required. | $52,150 | $17,383 (See Note 1) |
| (Pending) | Cut the existing 115kV line and Loop in the new Interconnection substation. | $1,627,275 | $542,425 (See Note 1) |
| Physical Interconnection | |||
|---|---|---|---|
| RTEP ID | Description | Total Cost ($USD) | Allocated Cost ($USD) |
| (Pending) | Install 115 kV revenue metering within new Interconnection substation. | $59,600 | $19,867 (See Note 1) |
Based on the scope of work for the Interconnection Facilities, it is expected to take 41 month(s) after the signing of a Generator Interconnection Agreement (as this is a FERC connection) and construction kickoff call to complete the installation of the physical connection work. This assumes that there will be no environmental issues with any of the new properties associated with this project, that there will be no delays in acquiring the necessary permits for implementing the defined interconnection work, and that all system outages will be allowed when requested.
The schedule for any required Network Impact Reinforcements will be more clearly identified in the Phase II and Phase III System Impact Studies.
Note 1: A Common Use Upgrade is a Network Upgrade that is needed for the interconnection of Generating Facilities or Merchant Transmission Facilities of more than one Project Developer or Eligible Customer and which is the shared responsibility of each Project Developer or Eligible Customer. If multiple Project Developers request to connect to the same interconnection substation, the Transmission Owner will determine the cost to accommodate all the requests at the substation. The cost for the interconnection will be allocated in proportion to the number of required terminations into the substation.
Transmission Owner Analysis
FE performed an analysis of its underlying transmission system <100 kV. New Service Request Project AH1-051 did not contribute to any overloads on the FE transmission <100 kV system.
Developer Requirements
The developer is responsible for all design and construction related activities on the developer’s side of the Point of Change in Ownership. FirstEnergy interconnection requirements can be found here.
To the extent that these Applicable Technical Requirements and Standards may conflict with the terms and conditions of the Tariff, the Tariff shall control.
Revenue Metering and SCADA Requirements
The developer will be required to install equipment necessary to provide Revenue Metering (KWH, KVARH) and real time data (KW, KVAR) for their generating Resource. See PJM Manual 01, PJM Manual 14D, and PJM Tariff Part IX, Subpart B, Appendix 2, section 8.Meteorological Data Reporting Requirement
The solar generation facility shall provide the Transmission Provider with site-specific meteorological data including:Transmission Owner Requirements
- Temperature (degrees Fahrenheit)
- Atmospheric Pressure (hectopascals)
- Irradiance
- Forced outage data
The Project Developer will be required to comply with all interconnected Transmission Owner’s revenue metering requirements located at the following link: PJM - Transmission Owner Engineering & Construction Standards.
Summer Peak Analysis
The New Service Request AH1-051 was evaluated as a 30.0 MW (18.0 MW Capacity) injection in the PENELEC area.
AH1-051 was evaluated as part of a plant. The plant consists of AH1-158, AH1-050, AH1-051. The total Energy output of the plant was evaluated at its maximum seasonal capability of 80.0 MW (89.07 MW under study).
Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.
| Study | Area | Facility Description | Contingency Name | Contingency Type | DC|AC | Final Cycle Loading | Rating (MVA) | Rating Type | MVA to Mitigate | MW Contribution | |
|---|---|---|---|---|---|---|---|---|---|---|---|
| GD2 | AP | 01AL&D6T-01AL 4J 138.0 kV Ckt 1 line | AP_P2-3_WP-138-171A_SRT-A | Breaker | AC | 150.5 % | 151.0 | B | 227.25 | 1.83 | |
| GD2 | AP | 01AL&D6T-01AL 4J 138.0 kV Ckt 1 line | AP_P2-2_WP-138-054A_SRT-A | Bus | AC | 149.99 % | 151.0 | B | 226.48 | 1.82 | |
| GD2 | AP | 01AL&D6T-01AL 4J 138.0 kV Ckt 1 line | ATSI_P2-3_CEI-345-041D_SRT-A | Breaker | AC | 142.46 % | 151.0 | B | 215.11 | 1.77 | |
| GD2 | AP | 01AL&D6T-01AL 4J 138.0 kV Ckt 1 line | ATSI_P2-3_CEI-345-041E_SRT-A | Breaker | AC | 142.46 % | 151.0 | B | 215.11 | 1.77 | |
| GD2 | AP | 01AL&D6T-01AL 4J 138.0 kV Ckt 1 line | PN_P2-3_PN-230-0347-3-DRTF-013_SRT-SL | Breaker | AC | 138.88 % | 151.0 | B | 209.7 | 1.55 | |
| GD2 | AP | 01AL&D6T-01AL 4J 138.0 kV Ckt 1 line | PN_P2-3_PN-230-0347-3_SRT-A | Breaker | AC | 138.88 % | 151.0 | B | 209.7 | 1.55 | |
| GD2 | AP | 01AL&D6T-01AL 4J 138.0 kV Ckt 1 line | AP_P1-3_WP-138-053A_SRT-A | Single | AC | 121.3 % | 151.0 | B | 183.16 | 1.57 | |
| GD2 | AP | 01AL&D6T-01AL 4J 138.0 kV Ckt 1 line | AP_P7-1_WPP-138-051A_SRT-A | Tower | AC | 104.58 % | 151.0 | B | 157.92 | 1.55 | |
| GD2 | AP | 01AL&D6T-01AL 4J 138.0 kV Ckt 1 line | AP_P2-2_WP-138-055_SRT-A | Bus | AC | 104.36 % | 151.0 | B | 157.58 | 1.5 | |
| GD2 | AP | 01ARMSTR-01KITTAN 138.0 kV Ckt 1 line | AP_P2-2_WP-138-058_SRT-A | Bus | AC | 157.77 % | 209.0 | B | 329.75 | 1.79 | |
| GD2 | AP | 01ARMSTR-01KITTAN 138.0 kV Ckt 1 line | AP_P2-3_WP-138-194T_SRT-A | Breaker | AC | 140.36 % | 209.0 | B | 293.36 | 1.81 | |
| GD2 | AP | 01ARMSTR-01KITTAN 138.0 kV Ckt 1 line | PN_P2-3_PN-230-0347-3-DRTF-013_SRT-SL | Breaker | AC | 127.91 % | 209.0 | B | 267.34 | 1.67 | |
| GD2 | AP | 01ARMSTR-01KITTAN 138.0 kV Ckt 1 line | PN_P2-3_PN-230-0347-3_SRT-A | Breaker | AC | 127.91 % | 209.0 | B | 267.34 | 1.67 | |
| GD2 | AP | 01ARMSTR-01KITTAN 138.0 kV Ckt 1 line | PN_P2-3_PN-230-0347-4_SRT-A | Breaker | AC | 127.2 % | 209.0 | B | 265.86 | 1.67 | |
| GD2 | AP | 01ARMSTR-01KITTAN 138.0 kV Ckt 1 line | ATSI_P2-3_CEI-345-041D_SRT-A | Breaker | AC | 121.14 % | 209.0 | B | 253.19 | 1.87 | |
| GD2 | AP | 01ARMSTR-01KITTAN 138.0 kV Ckt 1 line | AP_P7-1_WPP-138-051A_SRT-A | Tower | AC | 108.44 % | 209.0 | B | 226.63 | 1.57 | |
| GD2 | AP | 01COLMBGPN-01KISKIV 138.0 kV Ckt 1 line | PN_P2-3_PN-230-0347-4_SRT-A | Breaker | AC | 181.73 % | 151.0 | B | 274.41 | 1.82 | |
| GD2 | AP | 01COLMBGPN-01KISKIV 138.0 kV Ckt 1 line | PN_P2-3_PN-230-0347-3_SRT-A | Breaker | AC | 179.52 % | 151.0 | B | 271.07 | 1.82 | |
| GD2 | AP | 01COLMBGPN-01KISKIV 138.0 kV Ckt 1 line | PN_P2-3_PN-230-0347-3-DRTF-013_SRT-SL | Breaker | AC | 179.52 % | 151.0 | B | 271.07 | 1.82 | |
| GD2 | AP | 01COLMBGPN-01KISKIV 138.0 kV Ckt 1 line | AP_P2-3_WP-138-177_A_SRT-A | Breaker | AC | 168.0 % | 151.0 | B | 253.68 | 1.99 | |
| GD2 | AP | 01COLMBGPN-01KISKIV 138.0 kV Ckt 1 line | ATSI_P2-3_CEI-345-041D_SRT-A | Breaker | AC | 164.29 % | 151.0 | B | 248.08 | 2.0 | |
| GD2 | AP | 01COLMBGPN-01KISKIV 138.0 kV Ckt 1 line | AP_P7-1_WPP-138-054_SRT-A | Tower | AC | 149.48 % | 151.0 | B | 225.72 | 1.69 | |
| GD2 | AP | 01COLMBGPN-01KISKIV 138.0 kV Ckt 1 line | AP_P1-2_WP-138-087_SRT-A | Single | AC | 143.83 % | 151.0 | B | 217.18 | 1.71 | |
| GD2 | AP | 01COLMBGPN-01KISKIV 138.0 kV Ckt 1 line | AP_P1-2_WP-138-103_SRT-A | Single | AC | 133.67 % | 151.0 | B | 201.84 | 1.74 | |
| GD2 | AP | 01COLMBGPN-01KISKIV 138.0 kV Ckt 1 line | AP_P2-2_WP-138-057_SRT-A | Bus | AC | 131.28 % | 151.0 | B | 198.24 | 1.74 | |
| GD2 | AP | 01COLMBGPN-01KISKIV 138.0 kV Ckt 1 line | PN_P2-2_PN-345-002T-DRT-003_SRT-A | Bus | AC | 124.22 % | 151.0 | B | 187.57 | 1.58 | |
| GD2 | AP | 01COLMBGPN-01KISKIV 138.0 kV Ckt 1 line | AP_P7-1_WPP-138-067_SRT-A | Tower | AC | 118.35 % | 151.0 | B | 178.72 | 1.8 | |
| GD2 | AP | 01GAR RN-01COLMBGPN 138.0 kV Ckt 1 line | PN_P2-3_PN-230-0347-4_SRT-A | Breaker | AC | 183.35 % | 151.0 | B | 276.86 | 1.82 | |
| GD2 | AP | 01GAR RN-01COLMBGPN 138.0 kV Ckt 1 line | PN_P2-3_PN-230-0347-3-DRTF-013_SRT-SL | Breaker | AC | 181.14 % | 151.0 | B | 273.52 | 1.82 | |
| GD2 | AP | 01GAR RN-01COLMBGPN 138.0 kV Ckt 1 line | PN_P2-3_PN-230-0347-3_SRT-A | Breaker | AC | 181.14 % | 151.0 | B | 273.52 | 1.82 | |
| GD2 | AP | 01GAR RN-01COLMBGPN 138.0 kV Ckt 1 line | AP_P2-3_WP-138-177_A_SRT-A | Breaker | AC | 168.97 % | 151.0 | B | 255.15 | 1.99 | |
| GD2 | AP | 01GAR RN-01COLMBGPN 138.0 kV Ckt 1 line | ATSI_P2-3_CEI-345-041D_SRT-A | Breaker | AC | 165.68 % | 151.0 | B | 250.18 | 2.0 | |
| GD2 | AP | 01GAR RN-01COLMBGPN 138.0 kV Ckt 1 line | AP_P7-1_WPP-138-054_SRT-A | Tower | AC | 150.85 % | 151.0 | B | 227.78 | 1.69 | |
| GD2 | AP | 01GAR RN-01COLMBGPN 138.0 kV Ckt 1 line | AP_P1-2_WP-138-087_SRT-A | Single | AC | 144.37 % | 151.0 | B | 218.0 | 1.71 | |
| GD2 | AP | 01GAR RN-01COLMBGPN 138.0 kV Ckt 1 line | AP_P1-2_WP-138-103_SRT-A | Single | AC | 134.03 % | 151.0 | B | 202.39 | 1.74 | |
| GD2 | AP | 01GAR RN-01COLMBGPN 138.0 kV Ckt 1 line | AP_P2-2_WP-138-057_SRT-A | Bus | AC | 132.4 % | 151.0 | B | 199.92 | 1.74 | |
| GD2 | AP | 01GAR RN-01COLMBGPN 138.0 kV Ckt 1 line | PN_P2-2_PN-345-002T_SRT-A | Bus | AC | 125.54 % | 151.0 | B | 189.57 | 1.58 | |
| GD2 | AP | 01GAR RN-01COLMBGPN 138.0 kV Ckt 1 line | AP_P7-1_WPP-138-067_SRT-A | Tower | AC | 119.71 % | 151.0 | B | 180.75 | 1.8 | |
| GD2 | AP | 01KARNSC-01BUTLER 138.0 kV Ckt 1 line | ATSI_P2-3_CEI-345-041D_SRT-A | Breaker | AC | 142.81 % | 192.0 | B | 274.2 | 2.83 | |
| GD2 | AP | 01KARNSC-01BUTLER 138.0 kV Ckt 1 line | ATSI_P2-3_CEI-345-041E_SRT-A | Breaker | AC | 142.81 % | 192.0 | B | 274.2 | 2.83 | |
| GD2 | AP | 01KARNSC-01BUTLER 138.0 kV Ckt 1 line | PN_P2-3_PN-230-0347-3_SRT-A | Breaker | AC | 131.54 % | 192.0 | B | 252.56 | 2.52 | |
| GD2 | AP | 01KARNSC-01BUTLER 138.0 kV Ckt 1 line | PN_P2-3_PN-230-0347-3-DRTF-013_SRT-SL | Breaker | AC | 131.54 % | 192.0 | B | 252.56 | 2.52 | |
| GD2 | AP | 01KARNSC-01BUTLER 138.0 kV Ckt 1 line | PN_P2-3_PN-230-0347-4_SRT-A | Breaker | AC | 131.08 % | 192.0 | B | 251.67 | 2.52 | |
| GD2 | AP | 01KARNSC-01BUTLER 138.0 kV Ckt 1 line | AP_P7-1_WPP-138-053A_SRT-A | Tower | AC | 128.11 % | 192.0 | B | 245.97 | 2.74 | |
| GD2 | AP | 01KARNSC-01BUTLER 138.0 kV Ckt 1 line | AP_P2-2_WP-230-005T_SRT-A | Bus | AC | 105.32 % | 192.0 | B | 202.22 | 2.27 | |
| GD2 | AP | 01KARNSC-01BUTLER 138.0 kV Ckt 1 line | AP_P7-1_WPP-138-051A_SRT-A | Tower | AC | 100.95 % | 192.0 | B | 193.82 | 2.44 | |
| GD2 | AP | 01KISSNG-01KARNSC 138.0 kV Ckt 1 line | ATSI_P2-3_CEI-345-041D_SRT-A | Breaker | AC | 119.89 % | 268.0 | B | 321.31 | 2.98 | |
| GD2 | AP | 01KISSNG-01KARNSC 138.0 kV Ckt 1 line | ATSI_P2-3_CEI-345-041E_SRT-A | Breaker | AC | 119.89 % | 268.0 | B | 321.31 | 2.98 | |
| GD2 | AP | 01KISSNG-01KARNSC 138.0 kV Ckt 1 line | PN_P2-3_PN-230-0347-4_SRT-A | Breaker | AC | 109.92 % | 268.0 | B | 294.6 | 2.66 | |
| GD2 | AP | 01KISSNG-01KARNSC 138.0 kV Ckt 1 line | PN_P2-3_PN-230-0347-3-DRTF-013_SRT-SL | Breaker | AC | 108.63 % | 268.0 | B | 291.14 | 2.65 | |
| GD2 | AP | 01KISSNG-01KARNSC 138.0 kV Ckt 1 line | PN_P2-3_PN-230-0347-3_SRT-A | Breaker | AC | 108.63 % | 268.0 | B | 291.14 | 2.65 | |
| GD2 | AP | 01KISSNG-01KARNSC 138.0 kV Ckt 1 line | AP_P7-1_WPP-138-053A_SRT-A | Tower | AC | 107.72 % | 268.0 | B | 288.7 | 2.87 | |
| GD2 | AP | 01KITTAN-01AL&D6T 138.0 kV Ckt 1 line | AP_P2-3_WP-138-171A_SRT-A | Breaker | AC | 148.95 % | 151.0 | B | 224.92 | 1.83 | |
| GD2 | AP | 01KITTAN-01AL&D6T 138.0 kV Ckt 1 line | AP_P2-2_WP-138-054A_SRT-A | Bus | AC | 148.43 % | 151.0 | B | 224.13 | 1.82 | |
| GD2 | AP | 01KITTAN-01AL&D6T 138.0 kV Ckt 1 line | ATSI_P2-3_CEI-345-041D_SRT-A | Breaker | AC | 141.31 % | 151.0 | B | 213.37 | 1.77 | |
| GD2 | AP | 01KITTAN-01AL&D6T 138.0 kV Ckt 1 line | ATSI_P2-3_CEI-345-041E_SRT-A | Breaker | AC | 141.31 % | 151.0 | B | 213.37 | 1.77 | |
| GD2 | AP | 01KITTAN-01AL&D6T 138.0 kV Ckt 1 line | PN_P2-3_PN-230-0347-3-DRTF-013_SRT-SL | Breaker | AC | 137.47 % | 151.0 | B | 207.58 | 1.55 | |
| GD2 | AP | 01KITTAN-01AL&D6T 138.0 kV Ckt 1 line | PN_P2-3_PN-230-0347-3_SRT-A | Breaker | AC | 137.47 % | 151.0 | B | 207.58 | 1.55 | |
| GD2 | AP | 01KITTAN-01AL&D6T 138.0 kV Ckt 1 line | AP_P1-3_WP-138-053A_SRT-A | Single | AC | 119.95 % | 151.0 | B | 181.13 | 1.57 | |
| GD2 | AP | 01KITTAN-01AL&D6T 138.0 kV Ckt 1 line | AP_P7-1_WPP-138-051A_SRT-A | Tower | AC | 104.78 % | 151.0 | B | 158.22 | 1.55 | |
| GD2 | AP | 01KITTAN-01AL&D6T 138.0 kV Ckt 1 line | AP_P2-2_WP-138-055_SRT-A | Bus | AC | 102.82 % | 151.0 | B | 155.25 | 1.5 | |
| GD2 | AP/PENELEC | 01SHINGL-26LEWISTWN 230.0 kV Ckt 1 line | PN_P2-3_PN-230-0310-B_SRT-A | Breaker | AC | 134.58 % | 612.0 | B | 823.64 | 1.38 | |
| GD2 | AP/PENELEC | 01SHINGL-26LEWISTWN 230.0 kV Ckt 1 line | PN_P2-3_PN-230-0310-A_SRT-A | Breaker | AC | 134.58 % | 612.0 | B | 823.6 | 1.38 | |
| GD2 | AP/PENELEC | 01SHINGL-26LEWISTWN 230.0 kV Ckt 1 line | PN_P2-3_PN-230-0014-01_SRT-A | Breaker | AC | 134.57 % | 612.0 | B | 823.56 | 1.38 | |
| GD2 | AP/PENELEC | 01SHINGL-26LEWISTWN 230.0 kV Ckt 1 line | PN_P2-3_PN-230-0014-02_SRT-A | Breaker | AC | 133.52 % | 612.0 | B | 817.12 | 1.38 | |
| GD2 | AP/PENELEC | 01SHINGL-26LEWISTWN 230.0 kV Ckt 1 line | PN_P2-3_PN-230-0310-C_SRT-A | Breaker | AC | 132.54 % | 612.0 | B | 811.17 | 1.36 | |
| GD2 | AP/PENELEC | 01SHINGL-26LEWISTWN 230.0 kV Ckt 1 line | PN_P2-2_PN-345-1185-2_SRT-A | Bus | AC | 123.1 % | 612.0 | B | 753.36 | 1.29 | |
| GD2 | AP/PENELEC | 01SHINGL-26LEWISTWN 230.0 kV Ckt 1 line | AP_P7-1_WPP-138-053A_SRT-A | Tower | AC | 119.03 % | 612.0 | B | 728.44 | 1.39 | |
| GD2 | AP/PENELEC | 01SHINGL-26LEWISTWN 230.0 kV Ckt 1 line | PN_P2-2_PN-230-009_SRT-A | Bus | AC | 118.05 % | 612.0 | B | 722.47 | 1.19 | |
| GD2 | AP/PENELEC | 01SHINGL-26LEWISTWN 230.0 kV Ckt 1 line | AP_P7-1_WPP-138-020T_SRT-A | Tower | AC | 117.04 % | 612.0 | B | 716.26 | 1.19 | |
| GD2 | AP/PENELEC | 01SHINGL-26LEWISTWN 230.0 kV Ckt 1 line | PN_P2-2_PN-115-022_SRT-A | Bus | AC | 116.81 % | 612.0 | B | 714.9 | 1.16 | |
| GD2 | AP/PENELEC | 01SHINGL-26LEWISTWN 230.0 kV Ckt 1 line | PL_08_P22_102799_SRT-A | Bus | AC | 116.7 % | 612.0 | B | 714.18 | 1.24 | |
| GD2 | AP/PENELEC | 01SHINGL-26LEWISTWN 230.0 kV Ckt 1 line | PN_P2-2_PN-115-059B_SRT-A | Bus | AC | 116.57 % | 612.0 | B | 713.39 | 1.25 | |
| GD2 | AP/PENELEC | 01SHINGL-26LEWISTWN 230.0 kV Ckt 1 line | PN_P1-2_PN-230-020A_SRT-A | Single | AC | 113.22 % | 612.0 | B | 692.91 | 1.19 | |
| GD2 | AP/PENELEC | 01SHINGL-26LEWISTWN 230.0 kV Ckt 1 line | Base Case | Single | AC | 111.67 % | 512.0 | A | 571.73 | 1.07 | |
| GD2 | AP/PENELEC | 01SHINGL-26LEWISTWN 230.0 kV Ckt 1 line | PN_P1-2_PN-230-019_SRT-A | Single | AC | 111.12 % | 612.0 | B | 680.04 | 1.17 | |
| GD2 | PENELEC/PJM | 26CONEMAGH-CONEM-GH 230.0/500.0 kV Ckt 3 transformer | PN_P2-3_PN-230-0252-C_SRT-A | Breaker | AC | 106.31 % | 1001.0 | B | 1064.17 | 3.03 | |
| GD2 | PENELEC/PJM | 26CONEMAGH-CONEM-GH 230.0/500.0 kV Ckt 3 transformer | PN_P2-3_PN-230-0252-B_SRT-A | Breaker | AC | 106.31 % | 1001.0 | B | 1064.17 | 3.03 | |
| GD2 | PENELEC/PJM | 26CONEMAGH-CONEM-GH 230.0/500.0 kV Ckt 3 transformer | PN_P2-3_PN-230-0252-A_SRT-A | Breaker | AC | 106.31 % | 1001.0 | B | 1064.16 | 3.03 | |
| GD2 | PENELEC/PJM | 26CONEMAGH-CONEM-GH 230.0/500.0 kV Ckt 3 transformer | PN_P2-3_PN-230-0201A-20_SRT-A | Breaker | AC | 104.94 % | 1001.0 | B | 1050.42 | 3.04 | |
| GD2 | PENELEC/PJM | 26CONEMAGH-CONEM-GH 230.0/500.0 kV Ckt 3 transformer | PN_P2-3_PN-230-0183-208_SRT-A | Breaker | AC | 103.22 % | 1001.0 | B | 1033.26 | 2.78 | |
| GD2 | PENELEC | 26HOMER CT _-26HOMER CT 230.0 kV Ckt S line | PN_P2-2_PN-230-001T_SRT-A | Bus | AC | 133.05 % | 827.0 | B | 1100.29 | 3.62 | |
| GD2 | PENELEC | 26HOMER CT _-26HOMER CT 230.0 kV Ckt S line | PN_P2-3_PN-230-0183-210_SRT-A | Breaker | AC | 133.04 % | 827.0 | B | 1100.25 | 3.62 | |
| GD2 | PENELEC | 26HOMER CT _-26HOMER CT 230.0 kV Ckt S line | PN_P2-2_PN-345-001T-DRT-001_SRT-A | Bus | AC | 131.95 % | 827.0 | B | 1091.2 | 3.62 | |
| GD2 | PENELEC | 26HOMER CT _-26HOMER CT 230.0 kV Ckt S line | PN_P2-2_PN-345-001T_SRT-A | Bus | AC | 131.95 % | 827.0 | B | 1091.2 | 3.62 | |
| GD2 | PENELEC | 26HOMER CT _-26HOMER CT 230.0 kV Ckt S line | PN_P2-3_PN-230-0183-207_SRT-A | Breaker | AC | 129.11 % | 827.0 | B | 1067.77 | 3.61 | |
| GD2 | PENELEC | 26HOMER CT _-26HOMER CT 230.0 kV Ckt S line | ATSI_P2-3_CEI-345-041E_SRT-A | Breaker | AC | 128.09 % | 827.0 | B | 1059.33 | 4.38 | |
| GD2 | PENELEC | 26HOMER CT _-26HOMER CT 230.0 kV Ckt S line | AP_P2-2_WP-138-059_SRT-A | Bus | AC | 121.05 % | 827.0 | B | 1001.09 | 2.55 | |
| GD2 | PENELEC | 26HOMER CT _-26HOMER CT 230.0 kV Ckt S line | AP_P2-2_WP-230-005T_SRT-A | Bus | AC | 115.4 % | 827.0 | B | 954.32 | 3.04 | |
| GD2 | PENELEC | 26HOMER CT _-26HOMER CT 230.0 kV Ckt S line | Base Case | Single | AC | 113.83 % | 647.0 | A | 736.47 | 2.48 | |
| GD2 | PENELEC | 26HOMER CT _-26HOMER CT 230.0 kV Ckt S line | AP_P7-1_WPP-138-053A_SRT-A | Tower | AC | 113.78 % | 827.0 | B | 940.96 | 3.47 | |
| GD2 | PENELEC | 26HOMER CT _-26HOMER CT 230.0 kV Ckt S line | PN_P1-3_DRT-230-003-DRT_SRT-SL | Single | AC | 112.55 % | 827.0 | B | 930.83 | 3.12 | |
| GD2 | PENELEC | 26HOMER CT _-26HOMER CT 230.0 kV Ckt S line | AP_P7-1_WPP-138-051A_SRT-A | Tower | AC | 108.7 % | 827.0 | B | 898.94 | 3.14 | |
| GD2 | PENELEC | 26HOMER CT _-26HOMER CT 230.0 kV Ckt S line | AP_P1-3_WP-345-001_SRT-A | Single | AC | 104.64 % | 827.0 | B | 865.39 | 2.21 | |
| GD2 | PENELEC | 26HOMER CT-26SHELOCTA 230.0 kV Ckt 1 line | PN_P2-3_PN-230-0347-2_SRT-A | Breaker | AC | 132.2 % | 980.0 | B | 1295.55 | 3.24 | |
| GD2 | PENELEC | 26HOMER CT-26SHELOCTA 230.0 kV Ckt 1 line | PN_P2-3_PN-500-003JT_SRT-A | Breaker | AC | 131.02 % | 980.0 | B | 1284.02 | 3.26 | |
| GD2 | PENELEC | 26HOMER CT-26SHELOCTA 230.0 kV Ckt 1 line | PN_P2-2_PN-500-001T_SRT-A | Bus | AC | 131.02 % | 980.0 | B | 1284.02 | 3.26 | |
| GD2 | PENELEC | 26HOMER CT-26SHELOCTA 230.0 kV Ckt 1 line | PN_P2-3_PN-230-0347-A_SRT-A | Breaker | AC | 131.01 % | 980.0 | B | 1283.85 | 3.25 | |
| GD2 | PENELEC | 26HOMER CT-26SHELOCTA 230.0 kV Ckt 1 line | ATSI_P2-3_CEI-345-041D_SRT-A | Breaker | AC | 121.6 % | 980.0 | B | 1191.64 | 3.65 | |
| GD2 | PENELEC | 26HOMER CT-26SHELOCTA 230.0 kV Ckt 1 line | ATSI_P2-3_CEI-345-041E_SRT-A | Breaker | AC | 121.6 % | 980.0 | B | 1191.64 | 3.65 | |
| GD2 | PENELEC | 26HOMER CT-26SHELOCTA 230.0 kV Ckt 1 line | AP_P2-2_WP-138-059_SRT-A | Bus | AC | 112.4 % | 980.0 | B | 1101.51 | 2.19 | |
| GD2 | PENELEC | 26HOMER CT-26SHELOCTA 230.0 kV Ckt 1 line | PN_P2-2_PN-115-016A_SRT-A | Bus | AC | 109.01 % | 980.0 | B | 1068.29 | 2.48 | |
| GD2 | PENELEC | 26HOMER CT-26SHELOCTA 230.0 kV Ckt 1 line | AP_P7-1_WPP-138-053A_SRT-A | Tower | AC | 108.9 % | 980.0 | B | 1067.2 | 2.87 | |
| GD2 | PENELEC | 26HOMER CT-26SHELOCTA 230.0 kV Ckt 1 line | AP_P2-2_MP-138-100_SRT-A | Bus | AC | 108.04 % | 980.0 | B | 1058.75 | 2.5 | |
| GD2 | PENELEC | 26HOMER CT-26SHELOCTA 230.0 kV Ckt 1 line | AP_P2-2_WP-500-DRT18_SRT-A | Bus | AC | 106.12 % | 980.0 | B | 1040.01 | 2.41 | |
| GD2 | PENELEC | 26HOMER CT-26SHELOCTA 230.0 kV Ckt 1 line | PN_P1-2_PN-230-025_SRT-A | Single | AC | 105.44 % | 980.0 | B | 1033.27 | 2.81 | |
| GD2 | PENELEC | 26HOMER CT-26SHELOCTA 230.0 kV Ckt 1 line | PN_P1-3_PN-500-003_SRT-A | Single | AC | 105.43 % | 980.0 | B | 1033.25 | 2.81 | |
| GD2 | PENELEC | 26HOMER CT-26SHELOCTA 230.0 kV Ckt 1 line | AP_P7-1_WPP-138-051A_SRT-A | Tower | AC | 104.72 % | 980.0 | B | 1026.22 | 2.62 | |
| GD2 | PENELEC | 26HOMER CT-26SHELOCTA 230.0 kV Ckt 1 line | Base Case | Single | AC | 100.25 % | 809.0 | A | 811.02 | 2.08 | |
| GD2 | PENELEC | 26HOMER CY-26HOMER CT _ 345.0/230.0 kV Ckt S transformer | PN_P2-2_PN-230-001T_SRT-A | Bus | AC | 132.97 % | 827.0 | B | 1099.7 | 3.62 | |
| GD2 | PENELEC | 26HOMER CY-26HOMER CT _ 345.0/230.0 kV Ckt S transformer | PN_P2-3_PN-230-0183-210_SRT-A | Breaker | AC | 132.97 % | 827.0 | B | 1099.66 | 3.62 | |
| GD2 | PENELEC | 26HOMER CY-26HOMER CT _ 345.0/230.0 kV Ckt S transformer | PN_P2-2_PN-345-001T_SRT-A | Bus | AC | 131.9 % | 827.0 | B | 1090.83 | 3.62 | |
| GD2 | PENELEC | 26HOMER CY-26HOMER CT _ 345.0/230.0 kV Ckt S transformer | PN_P2-2_PN-345-001T-DRT-001_SRT-A | Bus | AC | 131.9 % | 827.0 | B | 1090.83 | 3.62 | |
| GD2 | PENELEC | 26HOMER CY-26HOMER CT _ 345.0/230.0 kV Ckt S transformer | PN_P2-3_PN-230-0183-207_SRT-A | Breaker | AC | 129.01 % | 827.0 | B | 1066.94 | 3.61 | |
| GD2 | PENELEC | 26HOMER CY-26HOMER CT _ 345.0/230.0 kV Ckt S transformer | ATSI_P2-3_CEI-345-041E_SRT-A | Breaker | AC | 128.09 % | 827.0 | B | 1059.31 | 4.38 | |
| GD2 | PENELEC | 26HOMER CY-26HOMER CT _ 345.0/230.0 kV Ckt S transformer | AP_P2-2_WP-138-059_SRT-A | Bus | AC | 121.08 % | 827.0 | B | 1001.36 | 2.55 | |
| GD2 | PENELEC | 26HOMER CY-26HOMER CT _ 345.0/230.0 kV Ckt S transformer | AP_P2-2_WP-230-005T_SRT-A | Bus | AC | 115.44 % | 827.0 | B | 954.65 | 3.04 | |
| GD2 | PENELEC | 26HOMER CY-26HOMER CT _ 345.0/230.0 kV Ckt S transformer | Base Case | Single | AC | 113.82 % | 647.0 | A | 736.42 | 2.48 | |
| GD2 | PENELEC | 26HOMER CY-26HOMER CT _ 345.0/230.0 kV Ckt S transformer | AP_P7-1_WPP-138-053A_SRT-A | Tower | AC | 113.78 % | 827.0 | B | 940.95 | 3.47 | |
| GD2 | PENELEC | 26HOMER CY-26HOMER CT _ 345.0/230.0 kV Ckt S transformer | PN_P1-3_DRT-230-003-DRT_SRT-SL | Single | AC | 112.51 % | 827.0 | B | 930.45 | 3.12 | |
| GD2 | PENELEC | 26HOMER CY-26HOMER CT _ 345.0/230.0 kV Ckt S transformer | AP_P7-1_WPP-138-051A_SRT-A | Tower | AC | 108.69 % | 827.0 | B | 898.89 | 3.14 | |
| GD2 | PENELEC | 26HOMER CY-26HOMER CT _ 345.0/230.0 kV Ckt S transformer | AP_P1-3_WP-345-001_SRT-A | Single | AC | 104.67 % | 827.0 | B | 865.66 | 2.21 | |
| GD2 | PENELEC | 26KEYSTONE-KEYSTONE _3 230.0 kV Ckt 4 line | PN_P2-3_PN-500-DRT27_SRT-SL | Breaker | AC | 118.81 % | 639.0 | B | 759.23 | 2.2 | |
| GD2 | PENELEC | 26KEYSTONE-KEYSTONE _3 230.0 kV Ckt 4 line | PN_P2-3_PN-500-004-DRT-003_SRT-SL | Breaker | AC | 118.81 % | 639.0 | B | 759.23 | 2.2 | |
| GD2 | PENELEC | 26KEYSTONE-KEYSTONE _3 230.0 kV Ckt 4 line | PN_P2-3_PN-500-DRT26_SRT-SL | Breaker | AC | 118.75 % | 639.0 | B | 758.81 | 2.2 | |
| GD2 | PENELEC | 26KEYSTONE-KEYSTONE _3 230.0 kV Ckt 4 line | PN_P2-3_PN-500-004-DRT-004_SRT-SL | Breaker | AC | 118.75 % | 639.0 | B | 758.8 | 2.2 | |
| GD2 | PENELEC | 26KEYSTONE-KEYSTONE _3 230.0 kV Ckt 4 line | PN_P2-2_PN-500-004A-DRT_SRT-SL | Bus | AC | 112.01 % | 639.0 | B | 715.77 | 2.2 | |
| GD2 | PENELEC | 26KEYSTONE-KEYSTONE _3 230.0 kV Ckt 4 line | PN_P2-3_PN-500-DRT33_SRT-SL | Breaker | AC | 111.27 % | 639.0 | B | 711.02 | 2.06 | |
| GD2 | PENELEC/PL | 26LEWISTWN-JUNI 230.0 kV Ckt 1 line | PN_P2-3_PN-115-0331-A_SRT-A | Breaker | AC | 156.72 % | 618.0 | B | 968.54 | 1.6 | |
| GD2 | PENELEC/PL | 26LEWISTWN-JUNI 230.0 kV Ckt 1 line | PN_P2-3_PN-115-0331-B_SRT-A | Breaker | AC | 156.7 % | 618.0 | B | 968.43 | 1.6 | |
| GD2 | PENELEC/PL | 26LEWISTWN-JUNI 230.0 kV Ckt 1 line | PN_P2-3_PN-500-DRT31_SRT-SL | Breaker | AC | 155.32 % | 618.0 | B | 959.88 | 1.6 | |
| GD2 | PENELEC/PL | 26LEWISTWN-JUNI 230.0 kV Ckt 1 line | PN_P2-3_PN-500-004-DRT-008_SRT-SL | Breaker | AC | 155.32 % | 618.0 | B | 959.88 | 1.6 | |
| GD2 | PENELEC/PL | 26LEWISTWN-JUNI 230.0 kV Ckt 1 line | PN_P2-3_PN-115-0331-D_SRT-A | Breaker | AC | 154.64 % | 618.0 | B | 955.66 | 1.6 | |
| GD2 | PENELEC/PL | 26LEWISTWN-JUNI 230.0 kV Ckt 1 line | PN_P2-2_PN-115-030_SRT-A | Bus | AC | 149.64 % | 618.0 | B | 924.75 | 1.61 | |
| GD2 | PENELEC/PL | 26LEWISTWN-JUNI 230.0 kV Ckt 1 line | PN_P2-2_PN-115-031_SRT-A | Bus | AC | 144.8 % | 618.0 | B | 894.87 | 1.57 | |
| GD2 | PENELEC/PL | 26LEWISTWN-JUNI 230.0 kV Ckt 1 line | PN_P2-2_PN-500-001T_SRT-A | Bus | AC | 142.79 % | 618.0 | B | 882.46 | 1.67 | |
| GD2 | PENELEC/PL | 26LEWISTWN-JUNI 230.0 kV Ckt 1 line | AP_P2-2_WP-138-074_SRT-A | Bus | AC | 136.41 % | 618.0 | B | 843.02 | 1.48 | |
| GD2 | PENELEC/PL | 26LEWISTWN-JUNI 230.0 kV Ckt 1 line | PL_08_P22_102799_SRT-A | Bus | AC | 136.19 % | 618.0 | B | 841.64 | 1.44 | |
| GD2 | PENELEC/PL | 26LEWISTWN-JUNI 230.0 kV Ckt 1 line | PL_48_P71_102649_SRT-A | Tower | AC | 135.55 % | 618.0 | B | 837.69 | 1.44 | |
| GD2 | PENELEC/PL | 26LEWISTWN-JUNI 230.0 kV Ckt 1 line | PECO_P7-1_220-9091_SRT-A/* $ BUCKS $ PECO_P7-1_220-9091 $ DCT | Tower | AC | 135.09 % | 618.0 | B | 834.83 | 1.44 | |
| GD2 | PENELEC/PL | 26LEWISTWN-JUNI 230.0 kV Ckt 1 line | Base Case | Single | AC | 131.72 % | 493.0 | A | 649.4 | 1.25 | |
| GD2 | PENELEC/PL | 26LEWISTWN-JUNI 230.0 kV Ckt 1 line | PN_P1-2_PN-115-094_A_SRT-A | Single | AC | 127.45 % | 618.0 | B | 787.65 | 1.38 | |
| GD2 | PENELEC/PL | 26LEWISTWN-JUNI 230.0 kV Ckt 1 line | PL_10_P12_000085_SRT-A | Single | AC | 127.27 % | 618.0 | B | 786.5 | 1.33 | |
| GD2 | AP/PENELEC | 26SHAWVL 2-01SHINGL 230.0 kV Ckt 1 line | AP_P2-3_WP-230-450T_SRT-A | Breaker | AC | 106.33 % | 587.0 | B | 624.15 | 1.08 | |
| GD2 | AP/PENELEC | 26SHAWVL 2-01SHINGL 230.0 kV Ckt 1 line | AP_P2-3_WP-230-449T_SRT-A | Breaker | AC | 106.27 % | 587.0 | B | 623.82 | 1.08 | |
| GD2 | PENELEC | 26SHELOCTA-26KEYSTONE 230.0 kV Ckt 1 line | PN_P2-3_PN-230-0347-2_SRT-A | Breaker | AC | 133.95 % | 980.0 | B | 1312.71 | 3.85 | |
| GD2 | PENELEC | 26SHELOCTA-26KEYSTONE 230.0 kV Ckt 1 line | PN_P2-3_PN-500-003JT_SRT-A | Breaker | AC | 133.46 % | 980.0 | B | 1307.88 | 3.86 | |
| GD2 | PENELEC | 26SHELOCTA-26KEYSTONE 230.0 kV Ckt 1 line | PN_P2-2_PN-500-001T_SRT-A | Bus | AC | 133.46 % | 980.0 | B | 1307.88 | 3.86 | |
| GD2 | PENELEC | 26SHELOCTA-26KEYSTONE 230.0 kV Ckt 1 line | PN_P2-3_PN-230-0347-A_SRT-A | Breaker | AC | 133.4 % | 980.0 | B | 1307.34 | 3.86 | |
| GD2 | PENELEC | 26SHELOCTA-26KEYSTONE 230.0 kV Ckt 1 line | ATSI_P2-3_CEI-345-041E_SRT-A | Breaker | AC | 122.69 % | 980.0 | B | 1202.4 | 4.26 | |
| GD2 | PENELEC | 26SHELOCTA-26KEYSTONE 230.0 kV Ckt 1 line | ATSI_P2-3_CEI-345-041D_SRT-A | Breaker | AC | 122.69 % | 980.0 | B | 1202.4 | 4.26 | |
| GD2 | PENELEC | 26SHELOCTA-26KEYSTONE 230.0 kV Ckt 1 line | AP_P2-2_WP-138-033T_SRT-A | Bus | AC | 110.79 % | 980.0 | B | 1085.77 | 3.15 | |
| GD2 | PENELEC | 26SHELOCTA-26KEYSTONE 230.0 kV Ckt 1 line | AP_P2-2_WP-138-059_SRT-A | Bus | AC | 110.5 % | 980.0 | B | 1082.93 | 2.79 | |
| GD2 | PENELEC | 26SHELOCTA-26KEYSTONE 230.0 kV Ckt 1 line | AP_P2-2_MP-138-100_SRT-A | Bus | AC | 108.43 % | 980.0 | B | 1062.61 | 3.07 | |
| GD2 | PENELEC | 26SHELOCTA-26KEYSTONE 230.0 kV Ckt 1 line | AP_P2-2_WP-138-036_SRT-A | Bus | AC | 108.01 % | 980.0 | B | 1058.48 | 3.1 | |
| GD2 | PENELEC | 26SHELOCTA-26KEYSTONE 230.0 kV Ckt 1 line | AP_P7-1_WPP-138-053A_SRT-A | Tower | AC | 107.82 % | 980.0 | B | 1056.6 | 3.38 | |
| GD2 | PENELEC | 26SHELOCTA-26KEYSTONE 230.0 kV Ckt 1 line | AP_P7-1_WPP-138-083_SRT-A | Tower | AC | 105.56 % | 980.0 | B | 1034.46 | 3.1 | |
| GD2 | PENELEC | 26SHELOCTA-26KEYSTONE 230.0 kV Ckt 1 line | PN_P1-2_PN-230-025_SRT-A | Single | AC | 104.25 % | 980.0 | B | 1021.65 | 3.33 | |
| GD2 | PENELEC | 26SHELOCTA-26KEYSTONE 230.0 kV Ckt 1 line | PN_P1-3_PN-500-003_SRT-A | Single | AC | 104.25 % | 980.0 | B | 1021.63 | 3.33 | |
| GD2 | PENELEC/PJM | KEYSTONE _3-KEYSTONE 230.0/500.0 kV Ckt 4 transformer | PN_P2-3_PN-500-DRT27_SRT-SL | Breaker | AC | 119.18 % | 639.0 | B | 761.59 | 2.2 | |
| GD2 | PENELEC/PJM | KEYSTONE _3-KEYSTONE 230.0/500.0 kV Ckt 4 transformer | PN_P2-3_PN-500-004-DRT-003_SRT-SL | Breaker | AC | 119.18 % | 639.0 | B | 761.58 | 2.2 | |
| GD2 | PENELEC/PJM | KEYSTONE _3-KEYSTONE 230.0/500.0 kV Ckt 4 transformer | PN_P2-3_PN-500-DRT26_SRT-SL | Breaker | AC | 119.09 % | 639.0 | B | 761.0 | 2.2 | |
| GD2 | PENELEC/PJM | KEYSTONE _3-KEYSTONE 230.0/500.0 kV Ckt 4 transformer | PN_P2-3_PN-500-004-DRT-004_SRT-SL | Breaker | AC | 119.09 % | 639.0 | B | 760.99 | 2.2 | |
| GD2 | PENELEC/PJM | KEYSTONE _3-KEYSTONE 230.0/500.0 kV Ckt 4 transformer | PN_P2-2_PN-500-004A-DRT_SRT-SL | Bus | AC | 112.2 % | 639.0 | B | 716.99 | 2.2 | |
| GD2 | PENELEC/PJM | KEYSTONE _3-KEYSTONE 230.0/500.0 kV Ckt 4 transformer | PN_P2-3_PN-500-DRT33_SRT-SL | Breaker | AC | 111.54 % | 639.0 | B | 712.74 | 2.06 |
Winter Peak Analysis
The New Service Request AH1-051 was evaluated as a 30.0 MW (18.0 MW Capacity) injection in the PENELEC area.
AH1-051 was evaluated as part of a plant. The plant consists of AH1-158, AH1-050, AH1-051. The total Energy output of the plant was evaluated at its maximum seasonal capability of 80.0 MW (110.0 MW under study).
Note: The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for single or N-1 contingencies and multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.
(No impacts were found for this analysis)
Light Load Analysis
The New Service Request AH1-051 was evaluated as a 30.0 MW injection
AH1-051 was evaluated as part of a plant. The plant consists of AH1-158, AH1-050, AH1-051. The total Energy output of the plant was evaluated at its maximum seasonal capability of 80.0 MW (110.0 MW under study).
Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.
| Study | Area | Facility Description | Contingency Name | Contingency Type | DC|AC | Final Cycle Loading | Rating (MVA) | Rating Type | MVA to Mitigate | MW Contribution | |
|---|---|---|---|---|---|---|---|---|---|---|---|
| GD2 | AP | 01AL&D6T-01AL 4J 138.0 kV Ckt 1 line | AP_P1-3_WP-138-053A_SRT-A | Single | AC | 114.75 % | 151.0 | B | 173.27 | 1.41 | |
| GD2 | AP | 01COLMBGPN-01KISKIV 138.0 kV Ckt 1 line | PN_P2-3_PN-230-0347-3-DRTF-013_SRT-SL | Breaker | AC | 152.48 % | 151.0 | B | 230.25 | 1.41 | |
| GD2 | AP | 01COLMBGPN-01KISKIV 138.0 kV Ckt 1 line | PN_P2-3_PN-230-0347-3_SRT-A | Breaker | AC | 152.48 % | 151.0 | B | 230.25 | 1.41 | |
| GD2 | AP | 01COLMBGPN-01KISKIV 138.0 kV Ckt 1 line | PN_P2-3_PN-230-0347-4_SRT-A | Breaker | AC | 152.27 % | 151.0 | B | 229.93 | 1.41 | |
| GD2 | AP | 01COLMBGPN-01KISKIV 138.0 kV Ckt 1 line | AP_P1-2_WP-138-087_SRT-A | Single | AC | 123.04 % | 151.0 | B | 185.79 | 1.53 | |
| GD2 | AP | 01COLMBGPN-01KISKIV 138.0 kV Ckt 1 line | AP_P1-2_WP-138-103_SRT-A | Single | AC | 122.49 % | 151.0 | B | 184.97 | 1.56 | |
| GD2 | AP | 01GAR RN-01COLMBGPN 138.0 kV Ckt 1 line | PN_P2-3_PN-230-0347-3_SRT-A | Breaker | AC | 154.09 % | 151.0 | B | 232.67 | 1.41 | |
| GD2 | AP | 01GAR RN-01COLMBGPN 138.0 kV Ckt 1 line | PN_P2-3_PN-230-0347-3-DRTF-013_SRT-SL | Breaker | AC | 154.09 % | 151.0 | B | 232.67 | 1.41 | |
| GD2 | AP | 01GAR RN-01COLMBGPN 138.0 kV Ckt 1 line | PN_P2-3_PN-230-0347-4_SRT-A | Breaker | AC | 153.87 % | 151.0 | B | 232.34 | 1.41 | |
| GD2 | AP | 01GAR RN-01COLMBGPN 138.0 kV Ckt 1 line | AP_P1-2_WP-138-087_SRT-A | Single | AC | 124.67 % | 151.0 | B | 188.25 | 1.53 | |
| GD2 | AP | 01GAR RN-01COLMBGPN 138.0 kV Ckt 1 line | AP_P1-2_WP-138-103_SRT-A | Single | AC | 124.12 % | 151.0 | B | 187.43 | 1.56 | |
| GD2 | AP | 01KITTAN-01AL&D6T 138.0 kV Ckt 1 line | AP_P1-3_WP-138-053A_SRT-A | Single | AC | 113.72 % | 151.0 | B | 171.71 | 1.41 | |
| GD2 | PENELEC | 26HOMER CT _-26HOMER CT 230.0 kV Ckt S line | PN_P2-3_PN-230-0183-210_SRT-A | Breaker | AC | 127.46 % | 824.0 | B | 1050.25 | 1.27 | |
| GD2 | PENELEC | 26HOMER CT _-26HOMER CT 230.0 kV Ckt S line | PN_P2-2_PN-230-001T_SRT-A | Bus | AC | 127.46 % | 824.0 | B | 1050.25 | 1.27 | |
| GD2 | PENELEC | 26HOMER CT _-26HOMER CT 230.0 kV Ckt S line | Base Case | Single | AC | 127.41 % | 647.0 | A | 824.37 | 1.57 | |
| GD2 | PENELEC | 26HOMER CT _-26HOMER CT 230.0 kV Ckt S line | PN_P2-2_PN-345-001T-DRT-001_SRT-A | Bus | AC | 126.35 % | 824.0 | B | 1041.16 | 1.27 | |
| GD2 | PENELEC | 26HOMER CT _-26HOMER CT 230.0 kV Ckt S line | PN_P2-2_PN-345-001T_SRT-A | Bus | AC | 126.35 % | 824.0 | B | 1041.16 | 1.27 | |
| GD2 | PENELEC | 26HOMER CT _-26HOMER CT 230.0 kV Ckt S line | PN_P1-3_DRT-230-003-DRT_SRT-SL | Single | AC | 126.18 % | 824.0 | B | 1039.69 | 1.98 | |
| GD2 | PENELEC | 26HOMER CT _-26HOMER CT 230.0 kV Ckt S line | PN_P2-3_PN-345-0183-307-DRT-010_SRT-A | Breaker | AC | 126.02 % | 824.0 | B | 1038.38 | 2.9 | |
| GD2 | PENELEC | 26HOMER CT _-26HOMER CT 230.0 kV Ckt S line | PN_P2-3_PN-345-0183-308_SRT-A | Breaker | AC | 126.02 % | 824.0 | B | 1038.38 | 2.9 | |
| GD2 | PENELEC | 26HOMER CT _-26HOMER CT 230.0 kV Ckt S line | AP_P1-3_WP-345-001_SRT-A | Single | AC | 112.45 % | 824.0 | B | 926.56 | 1.98 | |
| GD2 | PENELEC | 26HOMER CT _-26HOMER CT 230.0 kV Ckt S line | PN_P7-1_PN-230-002A_SRT-A | Tower | AC | 106.29 % | 824.0 | B | 875.84 | 2.2 | |
| GD2 | PENELEC | 26HOMER CT _-26HOMER CT 230.0 kV Ckt S line | AP_P7-1_WPP-138-053A_SRT-A | Tower | AC | 106.03 % | 824.0 | B | 873.67 | 2.68 | |
| GD2 | PENELEC | 26HOMER CT _-26HOMER CT 230.0 kV Ckt S line | AP_P2-2_WP-230-005T_SRT-A | Bus | AC | 104.37 % | 824.0 | B | 860.0 | 1.06 | |
| GD2 | PENELEC | 26HOMER CY-26HOMER CT _ 345.0/230.0 kV Ckt S transformer | Base Case | Single | AC | 127.59 % | 647.0 | A | 825.5 | 1.57 | |
| GD2 | PENELEC | 26HOMER CY-26HOMER CT _ 345.0/230.0 kV Ckt S transformer | PN_P2-3_PN-230-0183-210_SRT-A | Breaker | AC | 127.54 % | 824.0 | B | 1050.96 | 1.27 | |
| GD2 | PENELEC | 26HOMER CY-26HOMER CT _ 345.0/230.0 kV Ckt S transformer | PN_P2-2_PN-230-001T_SRT-A | Bus | AC | 127.54 % | 824.0 | B | 1050.96 | 1.27 | |
| GD2 | PENELEC | 26HOMER CY-26HOMER CT _ 345.0/230.0 kV Ckt S transformer | PN_P2-2_PN-345-001T-DRT-001_SRT-A | Bus | AC | 126.48 % | 824.0 | B | 1042.23 | 1.27 | |
| GD2 | PENELEC | 26HOMER CY-26HOMER CT _ 345.0/230.0 kV Ckt S transformer | PN_P2-2_PN-345-001T_SRT-A | Bus | AC | 126.48 % | 824.0 | B | 1042.23 | 1.27 | |
| GD2 | PENELEC | 26HOMER CY-26HOMER CT _ 345.0/230.0 kV Ckt S transformer | PN_P1-3_DRT-230-003-DRT_SRT-SL | Single | AC | 126.3 % | 824.0 | B | 1040.75 | 1.98 | |
| GD2 | PENELEC | 26HOMER CY-26HOMER CT _ 345.0/230.0 kV Ckt S transformer | PN_P2-3_PN-345-0183-308_SRT-A | Breaker | AC | 126.18 % | 824.0 | B | 1039.72 | 2.9 | |
| GD2 | PENELEC | 26HOMER CY-26HOMER CT _ 345.0/230.0 kV Ckt S transformer | PN_P2-3_PN-345-0183-307-DRT-010_SRT-A | Breaker | AC | 126.18 % | 824.0 | B | 1039.72 | 2.9 | |
| GD2 | PENELEC | 26HOMER CY-26HOMER CT _ 345.0/230.0 kV Ckt S transformer | AP_P1-3_WP-345-001_SRT-A | Single | AC | 112.66 % | 824.0 | B | 928.33 | 1.98 | |
| GD2 | PENELEC | 26HOMER CY-26HOMER CT _ 345.0/230.0 kV Ckt S transformer | PN_P7-1_PN-230-002A_SRT-A | Tower | AC | 106.46 % | 824.0 | B | 877.19 | 2.2 | |
| GD2 | PENELEC | 26HOMER CY-26HOMER CT _ 345.0/230.0 kV Ckt S transformer | AP_P7-1_WPP-138-053A_SRT-A | Tower | AC | 106.2 % | 824.0 | B | 875.06 | 2.68 | |
| GD2 | PENELEC | 26HOMER CY-26HOMER CT _ 345.0/230.0 kV Ckt S transformer | AP_P2-2_WP-230-005T_SRT-A | Bus | AC | 104.53 % | 824.0 | B | 861.35 | 1.06 |
Short Circuit Analysis
Short Circuit analysis is not performed as part of the Phase I System Impact Study. Short Circuit analysis will commence in the Phase II System Impact Study.
Stability Analysis
Stability analysis is not performed as part of the Phase I System Impact Study. Stability analysis will commence in the Phase II System Impact Study.
Reactive Power Analysis
Reactive Power analysis is not performed as part of the Phase I System Impact Study. Reactive Power analysis will commence in the Phase II System Impact Study.
Steady-State Voltage Analysis
Steady State Voltage Analysis is Not Required.
New Service Request Dependencies
The New Service Requests below are listed in one or more dispatch for the overloads identified in this report. These projects contribute to the loading of the overloaded facilities identified in this report. The percent overload of a facility and cost allocation you may have towards a particular reinforcement could vary depending on the action of other projects. The status of each project at the time of the analysis is presented in the table. This list may change as other projects withdraw or modify their requests. This table is valid for load flow analyses only.
| New Service Requests Dependencies | ||
|---|---|---|
| Project ID | Project Name | Status |
| AA2-133 | Wyalusing 34.5kV | In Service |
| AD2-062 | Roxbury-Greene 138 kV | Suspended |
| AD2-133 | Eagle Valley 115kV | In Service |
| AE1-071 | Shade Gap-Roxbury 115 kV | In Service |
| AE1-123 | Emlenton 34.5 kV | In Service |
| AE2-001 | Nittany-Zion 46 kV | Suspended |
| AE2-042 | Milton 69 kV | In Service |
| AE2-059 | Derry Tap-Derry Bus 69 kV | In Service |
| AE2-060 | Mifflintown Bus-Mifflintown Tap 69 kV | In Service |
| AE2-074 | Potter 46 kV | Under Construction |
| AE2-113 | Farmers Valley-Ridgeway 115 kV | Under Construction |
| AE2-117 | ABW Tap-Alexandria 46 kV | Suspended |
| AE2-118 | ABW Tap-Williamsburg 46 kV | Suspended |
| AE2-125 | Stahlstown-Ligonier 25 kV | In Service |
| AE2-126 | Dubois-Curwensville 34.5 kV | In Service |
| AE2-129 | Philipsburg-Clarence 34.5 kV | In Service |
| AE2-131 | Philipsburg-Karthaus 34.5 | Under Construction |
| AE2-133 | Penns Tap-Richfield Tie 69 kV | In Service |
| AE2-139 | East Towanda-Grover 230 kV | Engineering & Procurement |
| AE2-224 | Bear Rock-Johnstown 230 kV | In Service |
| AE2-248 | Fillmore-Thompson Farm 46 kV | Suspended |
| AE2-262 | Moshannon-Milesburg 230 kV | Engineering & Procurement |
| AE2-263 | Moshannon-Milesburg 230 kV II | Engineering & Procurement |
| AE2-316 | Brookville-Squab Hollow 138 kV | Under Construction |
| AE2-344 | Edinboro South-Venango Junction 115 kV | Suspended |
| AF1-006 | Fairview East 34.5 kV | In Service |
| AF1-039 | Listonburg-Highpoint 24.9 kV | In Service |
| AF1-086 | Madera-Westover South 115 kV | Under Construction |
| AF1-094 | Union City-Cambridge Springs 34.5 kV | Engineering & Procurement |
| AF1-098 | Four Mile Jct-Corry East 115 kV | Engineering & Procurement |
| AF1-106 | East Sayre 34.5 kV | Withdrawn |
| AF1-134 | Philipsburg-Madera 34.5 kV | Engineering & Procurement |
| AF1-140 | Claysburg 23 kV | Engineering & Procurement |
| AF1-143 | Lick Run 115 kV | Engineering & Procurement |
| AF1-153 | Motion-Ridgeway 46 kV | Suspended |
| AF1-167 | West Freedom-C&K Coal 25 kV | Suspended |
| AF1-240 | Timblin 34.5 kV | Active |
| AF1-272 | Lucerne 115 kV | Engineering & Procurement |
| AF1-287 | Edinboro South 34.5 kV II | Suspended |
| AF1-302 | Brookville-Squab Hollow 138 kV | Engineering & Procurement |
| AF1-321 | Hooversville 115 kV I | Suspended |
| AF1-333 | Laurelton-Mifflinburg 69 kV | Engineering & Procurement |
| AF1-337 | Laurelton-Mifflinburg 69 kV | Engineering & Procurement |
| AF1-338 | Laurelton-Mifflinburg 69 kV | Engineering & Procurement |
| AF1-339 | Laurelton-Mifflinburg 69 kV | Engineering & Procurement |
| AF2-001 | Hooversville 115 kV II | Suspended |
| AF2-002 | Hooversville 115 kV III | Suspended |
| AF2-010 | Union City-Titusville 115 kV | Active |
| AF2-039 | Shawville-Clearfield 34.5 kV | Engineering & Procurement |
| AF2-050 | Bear Rock-Johnstown 230 kV | Active |
| AF2-088 | Shawville-Clearfield 34.5 kV II | Engineering & Procurement |
| AF2-092 | Snake Spring-Bedford Area 23 kV | Suspended |
| AF2-130 | Cobalt Corners 34.5 kV | In Service |
| AF2-165 | Clark Summit-Emlenton 34.5 kV | In Service |
| AF2-166 | Emlenton 34.5 kV | Withdrawn |
| AF2-221 | Scalp Level 22.9 kV | Suspended |
| AF2-229 | Roxbury 23 kV | Engineering & Procurement |
| AF2-233 | Penns-Richfield Tie #1 69 kV | Engineering & Procurement |
| AF2-234 | Sunbury Yard #1-Richfield Tie #2 69 kV | Engineering & Procurement |
| AF2-235 | Titusville-Oil Creek 34.5 kV | Withdrawn |
| AF2-238 | Mansfield-South Troy 34.5 kV | Engineering & Procurement |
| AF2-294 | Thompson 34.5 kV | Suspended |
| AF2-296 | Madera 34.5 kV | Active |
| AF2-361 | Mifflintown Tap 69 kV | Engineering & Procurement |
| AG1-040 | Morgan Street-Mount Hope 34.5 kV | Engineering & Procurement |
| AG1-041 | Osterburg-Bedford North 23 kV | Withdrawn |
| AG1-090 | Philipsburg 115 kV | Active |
| AG1-100 | Venango-Saegertown 34.5 kV | Engineering & Procurement |
| AG1-140 | Union City 34.5 kV | Suspended |
| AG1-193 | Utica Junction 34.5 kV | Suspended |
| AG1-197 | Morgan Street-Cochranton 34.5 kV | Suspended |
| AG1-198 | Union City 34.5 kV | Under Construction |
| AG1-253 | Erie East-Union City 34.5 kV | Suspended |
| AG1-259 | Sunbury-Dalmatia 69 kV | Engineering & Procurement |
| AG1-260 | Sunbury-Dalmatia 69 kV | Engineering & Procurement |
| AG1-281 | Claysburg-HCR Tap 46 kV | Engineering & Procurement |
| AG1-301 | Miller REC-Warrior Ridge 46 kV | Engineering & Procurement |
| AG1-377 | Philipsburg 115 kV | Active |
| AG1-378 | Philipsburg 115 kV | Active |
| AG1-514 | Springdale CT III 138 kV | Withdrawn |
| AG1-548 | Erie South-Union City 115 kV | Active |
| AG2-090 | Scalp Level 23 kV IV | Active |
| AG2-091 | Scalp Level 23 kV V | Active |
| AG2-176 | Geneva 115 kV | Active |
| AG2-200 | North Warren–Russell 34.5 kV | Active |
| AG2-206 | Tennessee Gas-East Towanda 115 kV | Active |
| AG2-220 | East Towanda-South Troy 115 kV | Active |
| AG2-221 | South Troy - North Towanda 34.5 kV | Active |
| AG2-327 | Tennessee Gas-East Towanda 115 kV | Active |
| AG2-356 | South Troy - Canton 34.5 kV | Active |
| AG2-411 | Statler Hill 115 kV | Active |
| AG2-418 | Blain 115 kV | Active |
| AG2-420 | Eclipse #2 34.5 kV | Active |
| AG2-429 | Burma - Armstrong 138 kV | Active |
| AG2-438 | Union City 34.5 kV | Active |
| AG2-439 | Oxbow 34.5 kV | Active |
| AG2-456 | Pierce Brook-Lewis Run 230 kV | Active |
| AG2-457 | Pierce Brook - Lewis Run 230 kV | Active |
| AG2-561 | Glory - Glen Campbell 34.5 kV | Active |
| AG2-654 | Craigsville - Leards Crossing 12 kV | Active |
| AH1-005 | East Towanda-South Troy 115 kV II | Active |
| AH1-050 | Eclipse-Piney 115 kV | Active |
| AH1-102 | Seward-Glory 115 kV | Active |
| AH1-140 | Vasco 138 kV | Active |
| AH1-158 | Eclipse-Piney 115 kV III | Active |
| AH1-201 | Allegheny-New Baltimore 115kV | Active |
| AH1-203 | Allegheny-Somerset 115 kV | Active |
| AH1-205 | Allegheny-New Baltimore 115kV | Active |
| AH1-212 | Bethlehem - Lilly 46 kV | Active |
| AH1-268 | Seward-Glory 115 kV II | Active |
| AH1-313 | Moshannon-Milesburg 230 kV VII | Active |
| AH1-357 | Pierce Brook-Lewis Run 230kV | Active |
| AH1-358 | Pierce Brook-Lewis Run 230kV | Active |
| AH1-359 | Pierce Brook - Lewis Run 230 kV | Active |
| AH1-360 | Pierce Brook - Lewis Run 230 kV | Active |
| AH1-452 | Clementine-Clementine Jct. 25 kV | Active |
| AH1-460 | Hooversville - Scalp Level 115 kV | Active |
| AH1-490 | Venango Junction 34.5 kV | Active |
| AH1-491 | Union City 34.5 kV | Active |
| AH1-587 | Farmers Valley – Ridgeway 115 kV | Active |
| AH1-588 | Lewis Run - Pierce Brook 230 kV | Active |
| AH1-589 | Lewis Run - Pierce Brook 230 kV | Active |
| AH1-667 | Philipsburg-Shawville 34.5 kV | Active |
| AH1-720 | East Towanda 230 kV | Active |
| AH1-746 | Madera - Westover South 115 kV | Active |
| Y1-033 | Penn Mar-Rock Wood 115kV | In Service |
Affected System - PJM Identified Violations
As part of PJM's analysis, PJM evaluated the potential impacts on tie line facilities between PJM and an affected system entity, which were identified per PJM planning analysis criteria. This upgrade may be required on the affected system portion of the tie line along with cost allocation of such upgrade if applicable, in coordination with the affected system. Depending on the affected system, this project may not be contingent on upgrade based on PJM planning analysis criteria, but may be contingent on this upgrade based on the Affected System Operator's planning criteria, provided in the Affected Systems Study Section, herein.
Affected System - Non-PJM Identified Violations
In Phase I of the Cycle, PJM conducts an Affected System screen to identify any New Service Request with potential Affected System impacts. PJM initiates coordination with each Affected System Operator by providing a list of New Service Requests in the Cycle with potential impacts to their respective system. If the Affected System Operator indicates an Affected System Study is required, PJM will notify the Project Developer or Eligible Customer of the need for an Affected System Study. See below if any Affected System Operator requires a study for this project:
System Reinforcements
Based on the Phase I analysis results, this project may have a cost responsibility for the following System Reinforcements:
| TO | RTEP ID | Title | Allocated Cost ($USD) |
|---|---|---|---|
| APS | (Pending) / TC1-PH1-076 | Reconductor Butler - Karns City 138 kV line. | $1,444,041 |
| PENELEC | n6817.1 | Rebuild 24.59 miles of the Lewistown-Juniata 230kV transmission line | $1,202,132 |
| APS | (Pending) / TC1-APS-002.d | Rebuild 11.6 miles of 556.5 ACSR of the Armstrong - Kittanning 138 kV line | $903,998 |
| APS | n6183 | Rebuild 10.4 miles of 4/0 CU from Columbia Big Pine - Garretts Run Jct 138 kV (99 spans). | $825,404 |
| APS | n7164.1 | Reconductor (Possible Rebuild) ~7.5 miles of the Karns City to Kissinger Jct 138kV line | $731,414 |
| APS | n7166.2 | Reconductor 7.6 miles of 4/0 CU from All Dam 6 Tap to structure 84 (66 spans) | $707,428 |
| APS | n7165.2 | Reconductor All Dam 6 - Kittanning 138kV line | $566,372 |
| APS | n7171.1 | Rebuild approximately 4.0 miles of 4/0 CU on the Kiski Valley to Columbia Big Pine 138kV line. | $340,886 |
| PENELEC | n8281 | Replace the Keystone #4 500/230 kV transformer with a larger unit and install a high side breaker | $335,706 |
| PENELEC | (Pending) / TC2-PN-011 | Replace 500/230 kV Conemaugh #3 Transformer | $301,709 |
| PPL | n6818 | Rebuild PPL's ~0.9 miles LEWI-JUNI 230kV Line with a summer normal rating of at least 3000 Amps. | $35,283 |
| APS | (Pending) / TC2-APS-026.a | Replace (4) 10 Amp Meters & (3) 10 Amp Relays at Kittanning | $29,917 |
| APS | n7166.1 | Replace 4/0 CU line exit at All Dam 6 Tap. | $24,840 |
| PENELEC | n9127.0 / TC1-PN-003.g | Replace disconnect switches and leads at Shelocta Substation (Keystone-Shelocta 230kV line terminal) | $18,878 |
| PENELEC | n9118.0 / TC1-PN-001.g | Replace disconnect switches and leads at Shelocta Substation (Homer City-Shelocta 230kV line terminal) | $18,109 |
| APS | (Pending) / TC2-APS-031.b | Replace 138 kV T-line drops at Karns City | $16,136 |
| APS | (Pending) / TC1-APS-002.c | Replace/Upgrade (3) 138 kV T-Line Drops at Armstrong | $14,109 |
| PENELEC | n9125.0 / TC1-PN-003.f | Replace disconnect switches at Keystone Substation (Keystone-Shelocta 230kV line terminal) | $13,283 |
| PENELEC | n9117.0 / TC1-PN-001.f | Replace disconnect switches at Homer City Substation (Homer City-Shelocta 230kV line terminal) | $12,742 |
| APS | n9241.0 / TC1-APS-002.b | Replace 8 Amp ITH(50FD) relay at Kittanning | $12,155 |
| PENELEC | n9124.0 / TC1-PN-003.e | Replace bus conductor at Keystone Substation (Keystone-Shelocta 230kV line terminal) | $11,694 |
| APS | n7165.1 | Replace T-line drops at All Dam 6 | $11,511 |
| PENELEC | (Pending) / TC2-PN-005.a | Replace Sub conductor at Shelocta Substation (Homer City-Shelocta 230kV line terminal) | $8,832 |
| APS | n9240.0 / TC1-APS-002.a | Replace GE 800 Amp Wave Trap at Kittanning | $8,691 |
| APS | (Pending) / TC2-APS-026.b | Replace WHSE 1200 Amp Wave Trap at Armstrong | $8,691 |
| APS | (Pending) / TC2-APS-031.a | Upgrade (2) 138 kV Breaker Leads at Karns City | $5,111 |
| PENELEC | (Pending) / TC2-PN-007.b | Replace line drops at Keystone Substation (Keystone-Shelocta 230kV line terminal) | $2,786 |
| PENELEC | n9121.0 / TC1-PN-003.d | Replace line drops at Keystone Substation (Keystone-Shelocta 230kV line terminal) | $2,729 |
| PENELEC | n9120.0 / TC1-PN-003.c | Replace substation conductor at Keystone substation (Keystone-Shelocta 230kV line terminal) | $1,987 |
| PENELEC | n9126.0 / TC1-PN-003.h | Replace breaker leads at Keystone Substation (Keystone-Shelocta 230kV line terminal) | $1,617 |
| PENELEC | (Pending) / TC2-PN-007.a | Adjust relay settings at Keystone and Shelocta | $1,096 |
| PENELEC | (Pending) / TC2-PN-005.b | Adjust Relays at Shelocta Substation (Homer City-Shelocta 230kV line terminal) | $537 |
| Grand Total: | $7,619,824 | ||
Shown below are the details of the cost allocated, contingent, eliminated, topology and potential aggregate contributor reinforcements for this project. Please refer to the System Reinforcement table above and the information below for more detail.
System Reinforcement
- Type
- Load Flow
- TO
- APS
- RTEP ID / TO ID
- (Pending) / TC1-PH1-076
- Title
- Reconductor Butler - Karns City 138 kV line.
- Description
- Reconductor (Possible Rebuild) ~15.6 miles on the Butler - Karns City 138 kV line.
- Total Cost ($USD)
- $51,840,579
- Allocated Cost ($USD)
- $1,444,041
- Time Estimate
- 30 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 01BUTLER-01KARNSC 138.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-176 | 13.1 MW | 12.9% | $6,681,371 |
AG2-429 | 12.5 MW | 12.3% | $6,391,032 |
AG2-456 | 5.0 MW | 4.9% | $2,532,941 |
AG2-457 | 5.0 MW | 4.9% | $2,532,941 |
AH1-050 | 4.7 MW | 4.6% | $2,406,396 |
AH1-051 | 2.8 MW | 2.8% | $1,444,041 |
AH1-102 | 3.6 MW | 3.5% | $1,818,574 |
AH1-158 | 3.3 MW | 3.2% | $1,678,762 |
AH1-268 | 1.5 MW | 1.5% | $774,067 |
AH1-313 | 5.2 MW | 5.1% | $2,646,729 |
AH1-357 | 1.2 MW | 1.2% | $633,235 |
AH1-358 | 1.4 MW | 1.4% | $736,308 |
AH1-359 | 1.2 MW | 1.2% | $633,235 |
AH1-360 | 1.4 MW | 1.4% | $736,308 |
AH1-587 | 12.4 MW | 12.2% | $6,337,964 |
AH1-588 | 14.9 MW | 14.7% | $7,598,312 |
AH1-589 | 12.3 MW | 12.1% | $6,258,364 |
System Reinforcement: n6817.1
- Type
- Load Flow
- TO
- PENELEC
- RTEP ID / TO ID
- n6817.1
- Title
- Rebuild 24.59 miles of the Lewistown-Juniata 230kV transmission line
- Description
- Total Cost ($USD)
- $122,656,404
- Allocated Cost ($USD)
- $1,202,132
- Time Estimate
- 81 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 26LEWISTWN-JUNI 230.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-176 | 8.7 MW | 5.1% | $6,270,835 |
AG2-418 | 14.0 MW | 8.2% | $10,085,515 |
AG2-456 | 8.0 MW | 4.7% | $5,741,839 |
AG2-457 | 8.0 MW | 4.7% | $5,741,839 |
AH1-050 | 2.8 MW | 1.6% | $2,002,833 |
AH1-051 | 1.7 MW | 1.0% | $1,202,132 |
AH1-102 | 6.9 MW | 4.0% | $4,938,255 |
AH1-158 | 1.9 MW | 1.1% | $1,397,443 |
AH1-203 | 6.5 MW | 3.8% | $4,704,748 |
AH1-268 | 2.9 MW | 1.7% | $2,101,569 |
AH1-313 | 26.0 MW | 15.3% | $18,769,262 |
AH1-357 | 2.0 MW | 1.2% | $1,435,640 |
AH1-358 | 2.3 MW | 1.4% | $1,669,148 |
AH1-359 | 2.0 MW | 1.2% | $1,435,640 |
AH1-360 | 2.3 MW | 1.4% | $1,669,148 |
AH1-460 | 6.4 MW | 3.8% | $4,608,894 |
AH1-587 | 24.2 MW | 14.2% | $17,466,952 |
AH1-588 | 23.9 MW | 14.0% | $17,226,238 |
AH1-589 | 19.7 MW | 11.6% | $14,188,475 |
System Reinforcement
- Type
- Load Flow
- TO
- APS
- RTEP ID / TO ID
- (Pending) / TC1-APS-002.d
- Title
- Rebuild 11.6 miles of 556.5 ACSR of the Armstrong - Kittanning 138 kV line
- Description
- Rebuild 11.6 miles of 556.5 ACSR of the Armstrong - Kittanning 138 kV line using 795.0 KCMIL 26/7 STR ACSR. This upgrade is scoped and estimated as a line rebuild. During the network upgrade facility study process, FirstEnergy will make a final determination on whether a full rebuild is required or if only a reconductor is required.
- Total Cost ($USD)
- $37,921,495
- Allocated Cost ($USD)
- $903,998
- Time Estimate
- 28 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 01ARMSTR-01KITTAN 138.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-176 | 9.5 MW | 12.6% | $4,768,689 |
AG2-429 | 7.4 MW | 9.8% | $3,716,379 |
AG2-456 | 4.7 MW | 6.2% | $2,347,771 |
AG2-457 | 4.7 MW | 6.2% | $2,347,771 |
AH1-050 | 3.0 MW | 4.0% | $1,506,831 |
AH1-051 | 1.8 MW | 2.4% | $903,998 |
AH1-158 | 2.1 MW | 2.8% | $1,051,301 |
AH1-357 | 1.2 MW | 1.5% | $587,195 |
AH1-358 | 1.4 MW | 1.8% | $682,538 |
AH1-359 | 1.2 MW | 1.5% | $587,195 |
AH1-360 | 1.4 MW | 1.8% | $682,538 |
AH1-587 | 11.7 MW | 15.5% | $5,893,642 |
AH1-588 | 14.0 MW | 18.6% | $7,043,817 |
AH1-589 | 11.5 MW | 15.3% | $5,801,829 |
System Reinforcement: n6183
- Type
- Load Flow
- TO
- APS
- RTEP ID / TO ID
- n6183
- Title
- Rebuild 10.4 miles of 4/0 CU from Columbia Big Pine - Garretts Run Jct 138 kV (99 spans).
- Description
- Rebuild 10.4 miles of 4/0 CU from Columbia Big Pine - Garretts Run Jct 138 kV (99 spans) using 954 kcmil 45/7 STR ACSR.
- Total Cost ($USD)
- $36,946,687
- Allocated Cost ($USD)
- $825,404
- Time Estimate
- 26 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 01COLMBGPN-01GAR RN 138.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-176 | 9.1 MW | 11.2% | $4,121,135 |
AG2-429 | 9.3 MW | 11.4% | $4,194,031 |
AG2-456 | 5.1 MW | 6.2% | $2,308,687 |
AG2-457 | 5.1 MW | 6.2% | $2,308,687 |
AH1-050 | 3.0 MW | 3.7% | $1,375,976 |
AH1-051 | 1.8 MW | 2.2% | $825,404 |
AH1-158 | 2.6 MW | 3.2% | $1,178,114 |
AH1-357 | 1.3 MW | 1.6% | $577,285 |
AH1-358 | 1.5 MW | 1.8% | $671,009 |
AH1-359 | 1.3 MW | 1.6% | $577,285 |
AH1-360 | 1.5 MW | 1.8% | $671,009 |
AH1-587 | 12.2 MW | 14.9% | $5,506,619 |
AH1-588 | 15.3 MW | 18.7% | $6,926,513 |
AH1-589 | 12.6 MW | 15.4% | $5,704,933 |
System Reinforcement: n7164.1
- Type
- Load Flow
- TO
- APS
- RTEP ID / TO ID
- n7164.1
- Title
- Reconductor (Possible Rebuild) ~7.5 miles of the Karns City to Kissinger Jct 138kV line
- Description
- Reconductor (Possible Rebuild) ~7.5 miles of the Karns City to Kissinger Jct 138kV line This project is a pre-req for TC2-APS-031.a.
- Total Cost ($USD)
- $26,275,973
- Allocated Cost ($USD)
- $731,414
- Time Estimate
- 23 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 01KARNSC-01KISSNG 138.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-176 | 13.8 MW | 12.9% | $3,384,815 |
AG2-429 | 13.2 MW | 12.3% | $3,236,913 |
AG2-456 | 5.2 MW | 4.9% | $1,284,022 |
AG2-457 | 5.2 MW | 4.9% | $1,284,022 |
AH1-050 | 5.0 MW | 4.6% | $1,219,269 |
AH1-051 | 3.0 MW | 2.8% | $731,414 |
AH1-102 | 3.8 MW | 3.5% | $923,466 |
AH1-158 | 3.5 MW | 3.2% | $850,619 |
AH1-268 | 1.6 MW | 1.5% | $392,933 |
AH1-313 | 5.5 MW | 5.1% | $1,342,153 |
AH1-357 | 1.3 MW | 1.2% | $321,067 |
AH1-358 | 1.5 MW | 1.4% | $373,311 |
AH1-359 | 1.3 MW | 1.2% | $321,067 |
AH1-360 | 1.5 MW | 1.4% | $373,311 |
AH1-587 | 13.1 MW | 12.2% | $3,212,631 |
AH1-588 | 15.7 MW | 14.7% | $3,852,066 |
AH1-589 | 12.9 MW | 12.1% | $3,172,896 |
System Reinforcement: n7166.2
- Type
- Load Flow
- TO
- APS
- RTEP ID / TO ID
- n7166.2
- Title
- Reconductor 7.6 miles of 4/0 CU from All Dam 6 Tap to structure 84 (66 spans)
- Description
- Total Cost ($USD)
- $26,284,067
- Allocated Cost ($USD)
- $707,428
- Time Estimate
- 23 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 01AL 4J-01AL&D6T 138.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-176 | 8.1 MW | 11.8% | $3,107,204 |
AG2-429 | 10.0 MW | 14.6% | $3,841,262 |
AG2-456 | 3.8 MW | 5.6% | $1,481,624 |
AG2-457 | 3.8 MW | 5.6% | $1,481,624 |
AH1-050 | 3.1 MW | 4.5% | $1,179,433 |
AH1-051 | 1.8 MW | 2.7% | $707,428 |
AH1-158 | 2.6 MW | 3.8% | $1,004,602 |
AH1-357 | 1.0 MW | 1.4% | $370,503 |
AH1-358 | 1.1 MW | 1.6% | $430,709 |
AH1-359 | 1.0 MW | 1.4% | $370,503 |
AH1-360 | 1.1 MW | 1.6% | $430,709 |
AH1-587 | 9.8 MW | 14.4% | $3,772,565 |
AH1-588 | 11.5 MW | 16.9% | $4,444,873 |
AH1-589 | 9.5 MW | 13.9% | $3,661,028 |
System Reinforcement: n7165.2
- Type
- Load Flow
- TO
- APS
- RTEP ID / TO ID
- n7165.2
- Title
- Reconductor All Dam 6 - Kittanning 138kV line
- Description
- Reconductor (Possible Rebuild) ~6 miles of the All Dam 6 - Kittanning 138kV line
- Total Cost ($USD)
- $21,034,523
- Allocated Cost ($USD)
- $566,372
- Time Estimate
- 22 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 01AL&D6T-01KITTAN 138.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-176 | 8.1 MW | 11.8% | $2,486,603 |
AG2-429 | 10.0 MW | 14.6% | $3,073,666 |
AG2-456 | 3.8 MW | 5.6% | $1,185,861 |
AG2-457 | 3.8 MW | 5.6% | $1,185,861 |
AH1-050 | 3.1 MW | 4.5% | $943,748 |
AH1-051 | 1.8 MW | 2.7% | $566,372 |
AH1-158 | 2.6 MW | 3.8% | $803,853 |
AH1-357 | 1.0 MW | 1.4% | $296,465 |
AH1-358 | 1.1 MW | 1.6% | $344,641 |
AH1-359 | 1.0 MW | 1.4% | $296,465 |
AH1-360 | 1.1 MW | 1.6% | $344,641 |
AH1-587 | 9.8 MW | 14.4% | $3,019,314 |
AH1-588 | 11.5 MW | 16.9% | $3,557,275 |
AH1-589 | 9.5 MW | 13.9% | $2,929,757 |
System Reinforcement: n7171.1
- Type
- Load Flow
- TO
- APS
- RTEP ID / TO ID
- n7171.1
- Title
- Rebuild approximately 4.0 miles of 4/0 CU on the Kiski Valley to Columbia Big Pine 138kV line.
- Description
- Rebuild approximately 4.0 miles of 4/0 CU on the Kiski Valley to Columbia Big Pine 138kV line using 954 KCMIL 45/7 STR ACSR.
- Total Cost ($USD)
- $15,258,720
- Allocated Cost ($USD)
- $340,886
- Time Estimate
- 20 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 01KISKIV-01COLMBGPN 138.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-176 | 9.1 MW | 11.2% | $1,702,000 |
AG2-429 | 9.3 MW | 11.4% | $1,732,105 |
AG2-456 | 5.1 MW | 6.2% | $953,471 |
AG2-457 | 5.1 MW | 6.2% | $953,471 |
AH1-050 | 3.0 MW | 3.7% | $568,268 |
AH1-051 | 1.8 MW | 2.2% | $340,886 |
AH1-158 | 2.6 MW | 3.2% | $486,553 |
AH1-357 | 1.3 MW | 1.6% | $238,415 |
AH1-358 | 1.5 MW | 1.8% | $277,122 |
AH1-359 | 1.3 MW | 1.6% | $238,415 |
AH1-360 | 1.5 MW | 1.8% | $277,122 |
AH1-587 | 12.2 MW | 14.9% | $2,274,195 |
AH1-588 | 15.3 MW | 18.7% | $2,860,601 |
AH1-589 | 12.6 MW | 15.4% | $2,356,097 |
System Reinforcement: n8281
- Type
- Load Flow
- TO
- PENELEC
- RTEP ID / TO ID
- n8281
- Title
- Replace the Keystone #4 500/230 kV transformer with a larger unit and install a high side breaker
- Description
- Replace the #4 500/230 kV transformer with a larger unit and install a high side breaker. Install a 230-20 kV transformer and high side breaker to serve load currently fed from existing transformer tertiary. Estimated Summer Ratings: 910/1086/1141 MVA
- Total Cost ($USD)
- $31,322,503
- Allocated Cost ($USD)
- $335,706
- Time Estimate
- 67 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 26KEYSTONE-KEYSTONE _3 230.0 kV Ckt 4 line | (Any) | |
| KEYSTONE-KEYSTONE _3 500.0/230.0 kV Ckt 4 transformer | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-176 | 24.1 MW | 5.9% | $1,841,952 |
AG2-411 | 20.6 MW | 5.0% | $1,572,439 |
AG2-429 | 14.0 MW | 3.4% | $1,071,784 |
AG2-456 | 18.8 MW | 4.6% | $1,437,300 |
AG2-457 | 18.8 MW | 4.6% | $1,437,300 |
AH1-050 | 7.3 MW | 1.8% | $559,511 |
AH1-051 | 4.4 MW | 1.1% | $335,706 |
AH1-102 | 25.5 MW | 6.2% | $1,948,656 |
AH1-140 | 20.1 MW | 4.9% | $1,537,125 |
AH1-158 | 5.1 MW | 1.2% | $390,434 |
AH1-201 | 9.5 MW | 2.3% | $724,153 |
AH1-203 | 20.7 MW | 5.1% | $1,583,446 |
AH1-205 | 4.4 MW | 1.1% | $336,776 |
AH1-268 | 10.8 MW | 2.6% | $829,329 |
AH1-313 | 16.2 MW | 4.0% | $1,237,650 |
AH1-357 | 4.7 MW | 1.1% | $359,401 |
AH1-358 | 5.5 MW | 1.3% | $417,798 |
AH1-359 | 4.7 MW | 1.1% | $359,401 |
AH1-360 | 5.5 MW | 1.3% | $417,798 |
AH1-460 | 21.5 MW | 5.3% | $1,644,441 |
AH1-587 | 44.7 MW | 10.9% | $3,416,378 |
AH1-588 | 56.4 MW | 13.8% | $4,312,053 |
AH1-589 | 46.5 MW | 11.3% | $3,551,669 |
System Reinforcement
- Type
- Load Flow
- TO
- PENELEC
- RTEP ID / TO ID
- (Pending) / TC2-PN-011
- Title
- Replace 500/230 kV Conemaugh #3 Transformer
- Description
- Replace 500/230 kV Conemaugh #3 Transformer
- Total Cost ($USD)
- $28,558,871
- Allocated Cost ($USD)
- $301,709
- Time Estimate
- 66 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| CONEM-GH-26CONEMAGH 500.0/230.0 kV Ckt 3 transformer | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-176 | 16.5 MW | 5.8% | $1,644,796 |
AG2-411 | 17.1 MW | 6.0% | $1,706,593 |
AG2-456 | 12.5 MW | 4.4% | $1,248,996 |
AG2-457 | 12.5 MW | 4.4% | $1,248,996 |
AH1-050 | 5.0 MW | 1.8% | $502,748 |
AH1-051 | 3.0 MW | 1.1% | $301,709 |
AH1-102 | 21.4 MW | 7.5% | $2,135,683 |
AH1-140 | 13.8 MW | 4.8% | $1,379,567 |
AH1-158 | 3.5 MW | 1.2% | $350,748 |
AH1-201 | 8.0 MW | 2.8% | $801,866 |
AH1-203 | 17.5 MW | 6.1% | $1,748,356 |
AH1-205 | 3.7 MW | 1.3% | $372,975 |
AH1-268 | 9.1 MW | 3.2% | $908,914 |
AH1-313 | 11.9 MW | 4.1% | $1,183,213 |
AH1-357 | 3.1 MW | 1.1% | $312,274 |
AH1-358 | 3.6 MW | 1.3% | $363,107 |
AH1-359 | 3.1 MW | 1.1% | $312,274 |
AH1-360 | 3.6 MW | 1.3% | $363,107 |
AH1-460 | 18.3 MW | 6.4% | $1,826,300 |
AH1-587 | 30.2 MW | 10.6% | $3,013,300 |
AH1-588 | 37.6 MW | 13.1% | $3,747,089 |
AH1-589 | 31.0 MW | 10.8% | $3,086,260 |
System Reinforcement: n6818
- Type
- Load Flow
- TO
- PPL
- RTEP ID / TO ID
- n6818
- Title
- Rebuild PPL's ~0.9 miles LEWI-JUNI 230kV Line with a summer normal rating of at least 3000 Amps.
- Description
- The FE portion of the line is rated at 546/666 MVA SN/SE. The PPL portion is limiting, which requires n6818. Reinforcement scope no longer includes any substation scope as Juniata 230kV substation is being rebuilt under S0945.1. Actual PPL facility ratings after upgrade: 1245/1431 MVA SN/SE (FE facilities are more limiting)
- Total Cost ($USD)
- $3,600,000
- Allocated Cost ($USD)
- $35,283
- Time Estimate
- 24 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 26LEWISTWN-JUNI 230.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-176 | 8.7 MW | 5.1% | $184,051 |
AG2-418 | 14.0 MW | 8.2% | $296,013 |
AG2-456 | 8.0 MW | 4.7% | $168,525 |
AG2-457 | 8.0 MW | 4.7% | $168,525 |
AH1-050 | 2.8 MW | 1.6% | $58,784 |
AH1-051 | 1.7 MW | 1.0% | $35,283 |
AH1-102 | 6.9 MW | 4.0% | $144,939 |
AH1-158 | 1.9 MW | 1.1% | $41,015 |
AH1-203 | 6.5 MW | 3.8% | $138,086 |
AH1-268 | 2.9 MW | 1.7% | $61,682 |
AH1-313 | 26.0 MW | 15.3% | $550,883 |
AH1-357 | 2.0 MW | 1.2% | $42,136 |
AH1-358 | 2.3 MW | 1.4% | $48,990 |
AH1-359 | 2.0 MW | 1.2% | $42,136 |
AH1-360 | 2.3 MW | 1.4% | $48,990 |
AH1-460 | 6.4 MW | 3.8% | $135,272 |
AH1-587 | 24.2 MW | 14.2% | $512,660 |
AH1-588 | 23.9 MW | 14.0% | $505,595 |
AH1-589 | 19.7 MW | 11.6% | $416,436 |
System Reinforcement
- Type
- Load Flow
- TO
- APS
- RTEP ID / TO ID
- (Pending) / TC2-APS-026.a
- Title
- Replace (4) 10 Amp Meters & (3) 10 Amp Relays at Kittanning
- Description
- Replace (4) 10 Amp Meters & (3) 10 Amp Relays at Kittanning
- Total Cost ($USD)
- $1,254,982
- Allocated Cost ($USD)
- $29,917
- Time Estimate
- 20 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 01ARMSTR-01KITTAN 138.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-176 | 9.5 MW | 12.6% | $157,816 |
AG2-429 | 7.4 MW | 9.8% | $122,991 |
AG2-456 | 4.7 MW | 6.2% | $77,698 |
AG2-457 | 4.7 MW | 6.2% | $77,698 |
AH1-050 | 3.0 MW | 4.0% | $49,867 |
AH1-051 | 1.8 MW | 2.4% | $29,917 |
AH1-158 | 2.1 MW | 2.8% | $34,792 |
AH1-357 | 1.2 MW | 1.5% | $19,433 |
AH1-358 | 1.4 MW | 1.8% | $22,588 |
AH1-359 | 1.2 MW | 1.5% | $19,433 |
AH1-360 | 1.4 MW | 1.8% | $22,588 |
AH1-587 | 11.7 MW | 15.5% | $195,045 |
AH1-588 | 14.0 MW | 18.6% | $233,110 |
AH1-589 | 11.5 MW | 15.3% | $192,007 |
System Reinforcement: n7166.1
- Type
- Load Flow
- TO
- APS
- RTEP ID / TO ID
- n7166.1
- Title
- Replace 4/0 CU line exit at All Dam 6 Tap.
- Description
- Replace 4/0 CU line exit at All Dam 6 Tap on the 01AL&D6T - 01AL 4J
- Total Cost ($USD)
- $922,908
- Allocated Cost ($USD)
- $24,840
- Time Estimate
- 18 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 01AL 4J-01AL&D6T 138.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-176 | 8.1 MW | 11.8% | $109,103 |
AG2-429 | 10.0 MW | 14.6% | $134,878 |
AG2-456 | 3.8 MW | 5.6% | $52,024 |
AG2-457 | 3.8 MW | 5.6% | $52,024 |
AH1-050 | 3.1 MW | 4.5% | $41,413 |
AH1-051 | 1.8 MW | 2.7% | $24,840 |
AH1-158 | 2.6 MW | 3.8% | $35,274 |
AH1-357 | 1.0 MW | 1.4% | $13,009 |
AH1-358 | 1.1 MW | 1.6% | $15,123 |
AH1-359 | 1.0 MW | 1.4% | $13,009 |
AH1-360 | 1.1 MW | 1.6% | $15,123 |
AH1-587 | 9.8 MW | 14.4% | $132,465 |
AH1-588 | 11.5 MW | 16.9% | $156,072 |
AH1-589 | 9.5 MW | 13.9% | $128,549 |
System Reinforcement: n9127.0
- Type
- Load Flow
- TO
- PENELEC
- RTEP ID / TO ID
- n9127.0 / TC1-PN-003.g
- Title
- Replace disconnect switches and leads at Shelocta Substation (Keystone-Shelocta 230kV line terminal)
- Description
- Note: Due to shared breaker arrangements, this cost is split 50/50 with TC1-PN-001.g (Homer City-Shelocta 230kV line) terminal)
- Total Cost ($USD)
- $1,783,345
- Allocated Cost ($USD)
- $18,878
- Time Estimate
- 26 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 26SHELOCTA-26KEYSTONE 230.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-176 | 21.1 MW | 5.8% | $103,254 |
AG2-411 | 19.1 MW | 5.2% | $93,548 |
AG2-429 | 12.3 MW | 3.4% | $60,324 |
AG2-456 | 16.3 MW | 4.5% | $79,716 |
AG2-457 | 16.3 MW | 4.5% | $79,716 |
AH1-050 | 6.4 MW | 1.8% | $31,460 |
AH1-051 | 3.9 MW | 1.1% | $18,878 |
AH1-102 | 23.7 MW | 6.5% | $116,272 |
AH1-140 | 17.9 MW | 4.9% | $87,654 |
AH1-158 | 4.5 MW | 1.2% | $21,950 |
AH1-201 | 8.9 MW | 2.4% | $43,435 |
AH1-203 | 19.4 MW | 5.3% | $94,856 |
AH1-205 | 4.1 MW | 1.1% | $20,201 |
AH1-268 | 10.1 MW | 2.8% | $49,481 |
AH1-313 | 14.5 MW | 4.0% | $71,054 |
AH1-357 | 4.1 MW | 1.1% | $19,932 |
AH1-358 | 4.7 MW | 1.3% | $23,175 |
AH1-359 | 4.1 MW | 1.1% | $19,932 |
AH1-360 | 4.7 MW | 1.3% | $23,175 |
AH1-460 | 20.2 MW | 5.5% | $98,741 |
AH1-587 | 38.9 MW | 10.7% | $190,471 |
AH1-588 | 48.8 MW | 13.4% | $239,149 |
AH1-589 | 40.2 MW | 11.0% | $196,973 |
System Reinforcement: n9118.0
- Type
- Load Flow
- TO
- PENELEC
- RTEP ID / TO ID
- n9118.0 / TC1-PN-001.g
- Title
- Replace disconnect switches and leads at Shelocta Substation (Homer City-Shelocta 230kV line terminal)
- Description
- Note: Due to shared breaker arrangements, this cost is split 50/50 with TC1-PN-003.g (Keystone-Shelocta 230kV line terminal)
- Total Cost ($USD)
- $1,783,345
- Allocated Cost ($USD)
- $18,109
- Time Estimate
- 26 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 26HOMER CT-26SHELOCTA 230.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-176 | 19.8 MW | 6.2% | $110,525 |
AG2-411 | 17.6 MW | 5.5% | $98,262 |
AG2-429 | 10.7 MW | 3.4% | $59,973 |
AG2-456 | 16.0 MW | 5.0% | $89,540 |
AG2-457 | 16.0 MW | 5.0% | $89,540 |
AH1-050 | 5.4 MW | 1.7% | $30,177 |
AH1-051 | 3.2 MW | 1.0% | $18,109 |
AH1-102 | 16.1 MW | 5.0% | $89,932 |
AH1-158 | 3.8 MW | 1.2% | $21,058 |
AH1-201 | 8.1 MW | 2.5% | $45,277 |
AH1-203 | 17.7 MW | 5.5% | $98,945 |
AH1-205 | 3.8 MW | 1.2% | $21,058 |
AH1-268 | 6.8 MW | 2.1% | $38,272 |
AH1-313 | 13.0 MW | 4.1% | $72,824 |
AH1-357 | 4.0 MW | 1.3% | $22,384 |
AH1-358 | 4.7 MW | 1.5% | $26,026 |
AH1-359 | 4.0 MW | 1.3% | $22,384 |
AH1-360 | 4.7 MW | 1.5% | $26,026 |
AH1-460 | 18.5 MW | 5.8% | $103,342 |
AH1-587 | 37.5 MW | 11.8% | $209,834 |
AH1-588 | 48.0 MW | 15.1% | $268,616 |
AH1-589 | 39.5 MW | 12.4% | $221,241 |
System Reinforcement
- Type
- Load Flow
- TO
- APS
- RTEP ID / TO ID
- (Pending) / TC2-APS-031.b
- Title
- Replace 138 kV T-line drops at Karns City
- Description
- Replace (3) 138 kV T-line drops at Karns City
- Total Cost ($USD)
- $579,701
- Allocated Cost ($USD)
- $16,136
- Time Estimate
- 13 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 01KARNSC-01KISSNG 138.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-176 | 13.8 MW | 12.9% | $74,676 |
AG2-429 | 13.2 MW | 12.3% | $71,413 |
AG2-456 | 5.2 MW | 4.9% | $28,328 |
AG2-457 | 5.2 MW | 4.9% | $28,328 |
AH1-050 | 5.0 MW | 4.6% | $26,900 |
AH1-051 | 3.0 MW | 2.8% | $16,136 |
AH1-102 | 3.8 MW | 3.5% | $20,374 |
AH1-158 | 3.5 MW | 3.2% | $18,766 |
AH1-268 | 1.6 MW | 1.5% | $8,669 |
AH1-313 | 5.5 MW | 5.1% | $29,611 |
AH1-357 | 1.3 MW | 1.2% | $7,083 |
AH1-358 | 1.5 MW | 1.4% | $8,236 |
AH1-359 | 1.3 MW | 1.2% | $7,083 |
AH1-360 | 1.5 MW | 1.4% | $8,236 |
AH1-587 | 13.1 MW | 12.2% | $70,877 |
AH1-588 | 15.7 MW | 14.7% | $84,984 |
AH1-589 | 12.9 MW | 12.1% | $70,000 |
System Reinforcement
- Type
- Load Flow
- TO
- APS
- RTEP ID / TO ID
- (Pending) / TC1-APS-002.c
- Title
- Replace/Upgrade (3) 138 kV T-Line Drops at Armstrong
- Description
- Upgrade Line drops at Armstrong using 795.0 KCMIL 26/7 STR ACSR
- Total Cost ($USD)
- $591,863
- Allocated Cost ($USD)
- $14,109
- Time Estimate
- 13 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 01ARMSTR-01KITTAN 138.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-176 | 9.5 MW | 12.6% | $74,428 |
AG2-429 | 7.4 MW | 9.8% | $58,004 |
AG2-456 | 4.7 MW | 6.2% | $36,643 |
AG2-457 | 4.7 MW | 6.2% | $36,643 |
AH1-050 | 3.0 MW | 4.0% | $23,518 |
AH1-051 | 1.8 MW | 2.4% | $14,109 |
AH1-158 | 2.1 MW | 2.8% | $16,408 |
AH1-357 | 1.2 MW | 1.5% | $9,165 |
AH1-358 | 1.4 MW | 1.8% | $10,653 |
AH1-359 | 1.2 MW | 1.5% | $9,165 |
AH1-360 | 1.4 MW | 1.8% | $10,653 |
AH1-587 | 11.7 MW | 15.5% | $91,986 |
AH1-588 | 14.0 MW | 18.6% | $109,937 |
AH1-589 | 11.5 MW | 15.3% | $90,553 |
System Reinforcement: n9125.0
- Type
- Load Flow
- TO
- PENELEC
- RTEP ID / TO ID
- n9125.0 / TC1-PN-003.f
- Title
- Replace disconnect switches at Keystone Substation (Keystone-Shelocta 230kV line terminal)
- Description
- None
- Total Cost ($USD)
- $1,254,762
- Allocated Cost ($USD)
- $13,283
- Time Estimate
- 24 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 26SHELOCTA-26KEYSTONE 230.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-176 | 21.1 MW | 5.8% | $72,649 |
AG2-411 | 19.1 MW | 5.2% | $65,820 |
AG2-429 | 12.3 MW | 3.4% | $42,444 |
AG2-456 | 16.3 MW | 4.5% | $56,088 |
AG2-457 | 16.3 MW | 4.5% | $56,088 |
AH1-050 | 6.4 MW | 1.8% | $22,135 |
AH1-051 | 3.9 MW | 1.1% | $13,283 |
AH1-102 | 23.7 MW | 6.5% | $81,809 |
AH1-140 | 17.9 MW | 4.9% | $61,673 |
AH1-158 | 4.5 MW | 1.2% | $15,444 |
AH1-201 | 8.9 MW | 2.4% | $30,561 |
AH1-203 | 19.4 MW | 5.3% | $66,741 |
AH1-205 | 4.1 MW | 1.1% | $14,213 |
AH1-268 | 10.1 MW | 2.8% | $34,815 |
AH1-313 | 14.5 MW | 4.0% | $49,993 |
AH1-357 | 4.1 MW | 1.1% | $14,024 |
AH1-358 | 4.7 MW | 1.3% | $16,306 |
AH1-359 | 4.1 MW | 1.1% | $14,024 |
AH1-360 | 4.7 MW | 1.3% | $16,306 |
AH1-460 | 20.2 MW | 5.5% | $69,474 |
AH1-587 | 38.9 MW | 10.7% | $134,016 |
AH1-588 | 48.8 MW | 13.4% | $168,265 |
AH1-589 | 40.2 MW | 11.0% | $138,590 |
System Reinforcement: n9117.0
- Type
- Load Flow
- TO
- PENELEC
- RTEP ID / TO ID
- n9117.0 / TC1-PN-001.f
- Title
- Replace disconnect switches at Homer City Substation (Homer City-Shelocta 230kV line terminal)
- Description
- Total Cost ($USD)
- $1,254,760
- Allocated Cost ($USD)
- $12,742
- Time Estimate
- 24 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 26HOMER CT-26SHELOCTA 230.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-176 | 19.8 MW | 6.2% | $77,766 |
AG2-411 | 17.6 MW | 5.5% | $69,137 |
AG2-429 | 10.7 MW | 3.4% | $42,197 |
AG2-456 | 16.0 MW | 5.0% | $63,001 |
AG2-457 | 16.0 MW | 5.0% | $63,001 |
AH1-050 | 5.4 MW | 1.7% | $21,232 |
AH1-051 | 3.2 MW | 1.0% | $12,742 |
AH1-102 | 16.1 MW | 5.0% | $63,276 |
AH1-158 | 3.8 MW | 1.2% | $14,816 |
AH1-201 | 8.1 MW | 2.5% | $31,857 |
AH1-203 | 17.7 MW | 5.5% | $69,617 |
AH1-205 | 3.8 MW | 1.2% | $14,816 |
AH1-268 | 6.8 MW | 2.1% | $26,928 |
AH1-313 | 13.0 MW | 4.1% | $51,239 |
AH1-357 | 4.0 MW | 1.3% | $15,749 |
AH1-358 | 4.7 MW | 1.5% | $18,312 |
AH1-359 | 4.0 MW | 1.3% | $15,749 |
AH1-360 | 4.7 MW | 1.5% | $18,312 |
AH1-460 | 18.5 MW | 5.8% | $72,711 |
AH1-587 | 37.5 MW | 11.8% | $147,639 |
AH1-588 | 48.0 MW | 15.1% | $188,998 |
AH1-589 | 39.5 MW | 12.4% | $155,665 |
System Reinforcement: n9241.0
- Type
- Load Flow
- TO
- APS
- RTEP ID / TO ID
- n9241.0 / TC1-APS-002.b
- Title
- Replace 8 Amp ITH(50FD) relay at Kittanning
- Description
- Replace 8 Amp ITH(50FD) relay at Kittanning
- Total Cost ($USD)
- $509,895
- Allocated Cost ($USD)
- $12,155
- Time Estimate
- 18 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 01ARMSTR-01KITTAN 138.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-176 | 9.5 MW | 12.6% | $64,120 |
AG2-429 | 7.4 MW | 9.8% | $49,971 |
AG2-456 | 4.7 MW | 6.2% | $31,568 |
AG2-457 | 4.7 MW | 6.2% | $31,568 |
AH1-050 | 3.0 MW | 4.0% | $20,261 |
AH1-051 | 1.8 MW | 2.4% | $12,155 |
AH1-158 | 2.1 MW | 2.8% | $14,136 |
AH1-357 | 1.2 MW | 1.5% | $7,895 |
AH1-358 | 1.4 MW | 1.8% | $9,177 |
AH1-359 | 1.2 MW | 1.5% | $7,895 |
AH1-360 | 1.4 MW | 1.8% | $9,177 |
AH1-587 | 11.7 MW | 15.5% | $79,246 |
AH1-588 | 14.0 MW | 18.6% | $94,712 |
AH1-589 | 11.5 MW | 15.3% | $78,012 |
System Reinforcement: n9124.0
- Type
- Load Flow
- TO
- PENELEC
- RTEP ID / TO ID
- n9124.0 / TC1-PN-003.e
- Title
- Replace bus conductor at Keystone Substation (Keystone-Shelocta 230kV line terminal)
- Description
- None
- Total Cost ($USD)
- $1,104,686
- Allocated Cost ($USD)
- $11,694
- Time Estimate
- 13 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 26SHELOCTA-26KEYSTONE 230.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-176 | 21.1 MW | 5.8% | $63,960 |
AG2-411 | 19.1 MW | 5.2% | $57,948 |
AG2-429 | 12.3 MW | 3.4% | $37,367 |
AG2-456 | 16.3 MW | 4.5% | $49,380 |
AG2-457 | 16.3 MW | 4.5% | $49,380 |
AH1-050 | 6.4 MW | 1.8% | $19,488 |
AH1-051 | 3.9 MW | 1.1% | $11,694 |
AH1-102 | 23.7 MW | 6.5% | $72,024 |
AH1-140 | 17.9 MW | 4.9% | $54,297 |
AH1-158 | 4.5 MW | 1.2% | $13,597 |
AH1-201 | 8.9 MW | 2.4% | $26,906 |
AH1-203 | 19.4 MW | 5.3% | $58,758 |
AH1-205 | 4.1 MW | 1.1% | $12,513 |
AH1-268 | 10.1 MW | 2.8% | $30,651 |
AH1-313 | 14.5 MW | 4.0% | $44,014 |
AH1-357 | 4.1 MW | 1.1% | $12,346 |
AH1-358 | 4.7 MW | 1.3% | $14,356 |
AH1-359 | 4.1 MW | 1.1% | $12,346 |
AH1-360 | 4.7 MW | 1.3% | $14,356 |
AH1-460 | 20.2 MW | 5.5% | $61,165 |
AH1-587 | 38.9 MW | 10.7% | $117,987 |
AH1-588 | 48.8 MW | 13.4% | $148,140 |
AH1-589 | 40.2 MW | 11.0% | $122,014 |
System Reinforcement: n7165.1
- Type
- Load Flow
- TO
- APS
- RTEP ID / TO ID
- n7165.1
- Title
- Replace T-line drops at All Dam 6
- Description
- Replace (2) T-line drops at All Dam 6
- Total Cost ($USD)
- $427,516
- Allocated Cost ($USD)
- $11,511
- Time Estimate
- 12 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 01AL&D6T-01KITTAN 138.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-176 | 8.1 MW | 11.8% | $50,539 |
AG2-429 | 10.0 MW | 14.6% | $62,471 |
AG2-456 | 3.8 MW | 5.6% | $24,102 |
AG2-457 | 3.8 MW | 5.6% | $24,102 |
AH1-050 | 3.1 MW | 4.5% | $19,181 |
AH1-051 | 1.8 MW | 2.7% | $11,511 |
AH1-158 | 2.6 MW | 3.8% | $16,338 |
AH1-357 | 1.0 MW | 1.4% | $6,026 |
AH1-358 | 1.1 MW | 1.6% | $7,005 |
AH1-359 | 1.0 MW | 1.4% | $6,026 |
AH1-360 | 1.1 MW | 1.6% | $7,005 |
AH1-587 | 9.8 MW | 14.4% | $61,366 |
AH1-588 | 11.5 MW | 16.9% | $72,300 |
AH1-589 | 9.5 MW | 13.9% | $59,546 |
System Reinforcement
- Type
- Load Flow
- TO
- PENELEC
- RTEP ID / TO ID
- (Pending) / TC2-PN-005.a
- Title
- Replace Sub conductor at Shelocta Substation (Homer City-Shelocta 230kV line terminal)
- Description
- Total Cost ($USD)
- $869,783
- Allocated Cost ($USD)
- $8,832
- Time Estimate
- 13 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 26HOMER CT-26SHELOCTA 230.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-176 | 19.8 MW | 6.2% | $53,906 |
AG2-411 | 17.6 MW | 5.5% | $47,925 |
AG2-429 | 10.7 MW | 3.4% | $29,251 |
AG2-456 | 16.0 MW | 5.0% | $43,671 |
AG2-457 | 16.0 MW | 5.0% | $43,671 |
AH1-050 | 5.4 MW | 1.7% | $14,718 |
AH1-051 | 3.2 MW | 1.0% | $8,832 |
AH1-102 | 16.1 MW | 5.0% | $43,862 |
AH1-158 | 3.8 MW | 1.2% | $10,270 |
AH1-201 | 8.1 MW | 2.5% | $22,083 |
AH1-203 | 17.7 MW | 5.5% | $48,258 |
AH1-205 | 3.8 MW | 1.2% | $10,270 |
AH1-268 | 6.8 MW | 2.1% | $18,666 |
AH1-313 | 13.0 MW | 4.1% | $35,518 |
AH1-357 | 4.0 MW | 1.3% | $10,917 |
AH1-358 | 4.7 MW | 1.5% | $12,693 |
AH1-359 | 4.0 MW | 1.3% | $10,917 |
AH1-360 | 4.7 MW | 1.5% | $12,693 |
AH1-460 | 18.5 MW | 5.8% | $50,403 |
AH1-587 | 37.5 MW | 11.8% | $102,341 |
AH1-588 | 48.0 MW | 15.1% | $131,011 |
AH1-589 | 39.5 MW | 12.4% | $107,905 |
System Reinforcement: n9240.0
- Type
- Load Flow
- TO
- APS
- RTEP ID / TO ID
- n9240.0 / TC1-APS-002.a
- Title
- Replace GE 800 Amp Wave Trap at Kittanning
- Description
- Replace GE 800 Amp Wave Trap at Kittanning
- Total Cost ($USD)
- $364,562
- Allocated Cost ($USD)
- $8,691
- Time Estimate
- 17 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 01ARMSTR-01KITTAN 138.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-176 | 9.5 MW | 12.6% | $45,844 |
AG2-429 | 7.4 MW | 9.8% | $35,728 |
AG2-456 | 4.7 MW | 6.2% | $22,571 |
AG2-457 | 4.7 MW | 6.2% | $22,571 |
AH1-050 | 3.0 MW | 4.0% | $14,486 |
AH1-051 | 1.8 MW | 2.4% | $8,691 |
AH1-158 | 2.1 MW | 2.8% | $10,107 |
AH1-357 | 1.2 MW | 1.5% | $5,645 |
AH1-358 | 1.4 MW | 1.8% | $6,562 |
AH1-359 | 1.2 MW | 1.5% | $5,645 |
AH1-360 | 1.4 MW | 1.8% | $6,562 |
AH1-587 | 11.7 MW | 15.5% | $56,659 |
AH1-588 | 14.0 MW | 18.6% | $67,716 |
AH1-589 | 11.5 MW | 15.3% | $55,776 |
System Reinforcement
- Type
- Load Flow
- TO
- APS
- RTEP ID / TO ID
- (Pending) / TC2-APS-026.b
- Title
- Replace WHSE 1200 Amp Wave Trap at Armstrong
- Description
- Replace WHSE 1200 Amp Wave Trap at Armstrong
- Total Cost ($USD)
- $364,562
- Allocated Cost ($USD)
- $8,691
- Time Estimate
- 18 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 01ARMSTR-01KITTAN 138.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-176 | 9.5 MW | 12.6% | $45,844 |
AG2-429 | 7.4 MW | 9.8% | $35,728 |
AG2-456 | 4.7 MW | 6.2% | $22,571 |
AG2-457 | 4.7 MW | 6.2% | $22,571 |
AH1-050 | 3.0 MW | 4.0% | $14,486 |
AH1-051 | 1.8 MW | 2.4% | $8,691 |
AH1-158 | 2.1 MW | 2.8% | $10,107 |
AH1-357 | 1.2 MW | 1.5% | $5,645 |
AH1-358 | 1.4 MW | 1.8% | $6,562 |
AH1-359 | 1.2 MW | 1.5% | $5,645 |
AH1-360 | 1.4 MW | 1.8% | $6,562 |
AH1-587 | 11.7 MW | 15.5% | $56,659 |
AH1-588 | 14.0 MW | 18.6% | $67,716 |
AH1-589 | 11.5 MW | 15.3% | $55,776 |
System Reinforcement
- Type
- Load Flow
- TO
- APS
- RTEP ID / TO ID
- (Pending) / TC2-APS-031.a
- Title
- Upgrade (2) 138 kV Breaker Leads at Karns City
- Description
- Upgrade (2) 138 kV Breaker Leads at Karns City This project has a pre-req of n7164.1.
- Total Cost ($USD)
- $183,598
- Allocated Cost ($USD)
- $5,111
- Time Estimate
- 13 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 01KARNSC-01KISSNG 138.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-176 | 13.8 MW | 12.9% | $23,651 |
AG2-429 | 13.2 MW | 12.3% | $22,617 |
AG2-456 | 5.2 MW | 4.9% | $8,972 |
AG2-457 | 5.2 MW | 4.9% | $8,972 |
AH1-050 | 5.0 MW | 4.6% | $8,519 |
AH1-051 | 3.0 MW | 2.8% | $5,111 |
AH1-102 | 3.8 MW | 3.5% | $6,453 |
AH1-158 | 3.5 MW | 3.2% | $5,944 |
AH1-268 | 1.6 MW | 1.5% | $2,746 |
AH1-313 | 5.5 MW | 5.1% | $9,378 |
AH1-357 | 1.3 MW | 1.2% | $2,243 |
AH1-358 | 1.5 MW | 1.4% | $2,608 |
AH1-359 | 1.3 MW | 1.2% | $2,243 |
AH1-360 | 1.5 MW | 1.4% | $2,608 |
AH1-587 | 13.1 MW | 12.2% | $22,448 |
AH1-588 | 15.7 MW | 14.7% | $26,916 |
AH1-589 | 12.9 MW | 12.1% | $22,170 |
System Reinforcement
- Type
- Load Flow
- TO
- PENELEC
- RTEP ID / TO ID
- (Pending) / TC2-PN-007.b
- Title
- Replace line drops at Keystone Substation (Keystone-Shelocta 230kV line terminal)
- Description
- Total Cost ($USD)
- $263,169
- Allocated Cost ($USD)
- $2,786
- Time Estimate
- 12 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 26SHELOCTA-26KEYSTONE 230.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-176 | 21.1 MW | 5.8% | $15,237 |
AG2-411 | 19.1 MW | 5.2% | $13,805 |
AG2-429 | 12.3 MW | 3.4% | $8,902 |
AG2-456 | 16.3 MW | 4.5% | $11,764 |
AG2-457 | 16.3 MW | 4.5% | $11,764 |
AH1-050 | 6.4 MW | 1.8% | $4,643 |
AH1-051 | 3.9 MW | 1.1% | $2,786 |
AH1-102 | 23.7 MW | 6.5% | $17,158 |
AH1-140 | 17.9 MW | 4.9% | $12,935 |
AH1-158 | 4.5 MW | 1.2% | $3,239 |
AH1-201 | 8.9 MW | 2.4% | $6,410 |
AH1-203 | 19.4 MW | 5.3% | $13,998 |
AH1-205 | 4.1 MW | 1.1% | $2,981 |
AH1-268 | 10.1 MW | 2.8% | $7,302 |
AH1-313 | 14.5 MW | 4.0% | $10,485 |
AH1-357 | 4.1 MW | 1.1% | $2,941 |
AH1-358 | 4.7 MW | 1.3% | $3,420 |
AH1-359 | 4.1 MW | 1.1% | $2,941 |
AH1-360 | 4.7 MW | 1.3% | $3,420 |
AH1-460 | 20.2 MW | 5.5% | $14,571 |
AH1-587 | 38.9 MW | 10.7% | $28,108 |
AH1-588 | 48.8 MW | 13.4% | $35,291 |
AH1-589 | 40.2 MW | 11.0% | $29,067 |
System Reinforcement: n9121.0
- Type
- Load Flow
- TO
- PENELEC
- RTEP ID / TO ID
- n9121.0 / TC1-PN-003.d
- Title
- Replace line drops at Keystone Substation (Keystone-Shelocta 230kV line terminal)
- Description
- Total Cost ($USD)
- $257,762
- Allocated Cost ($USD)
- $2,729
- Time Estimate
- 11 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 26SHELOCTA-26KEYSTONE 230.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-176 | 21.1 MW | 5.8% | $14,924 |
AG2-411 | 19.1 MW | 5.2% | $13,521 |
AG2-429 | 12.3 MW | 3.4% | $8,719 |
AG2-456 | 16.3 MW | 4.5% | $11,522 |
AG2-457 | 16.3 MW | 4.5% | $11,522 |
AH1-050 | 6.4 MW | 1.8% | $4,547 |
AH1-051 | 3.9 MW | 1.1% | $2,729 |
AH1-102 | 23.7 MW | 6.5% | $16,806 |
AH1-140 | 17.9 MW | 4.9% | $12,669 |
AH1-158 | 4.5 MW | 1.2% | $3,173 |
AH1-201 | 8.9 MW | 2.4% | $6,278 |
AH1-203 | 19.4 MW | 5.3% | $13,710 |
AH1-205 | 4.1 MW | 1.1% | $2,920 |
AH1-268 | 10.1 MW | 2.8% | $7,152 |
AH1-313 | 14.5 MW | 4.0% | $10,270 |
AH1-357 | 4.1 MW | 1.1% | $2,881 |
AH1-358 | 4.7 MW | 1.3% | $3,350 |
AH1-359 | 4.1 MW | 1.1% | $2,881 |
AH1-360 | 4.7 MW | 1.3% | $3,350 |
AH1-460 | 20.2 MW | 5.5% | $14,272 |
AH1-587 | 38.9 MW | 10.7% | $27,530 |
AH1-588 | 48.8 MW | 13.4% | $34,566 |
AH1-589 | 40.2 MW | 11.0% | $28,470 |
System Reinforcement: n9120.0
- Type
- Load Flow
- TO
- PENELEC
- RTEP ID / TO ID
- n9120.0 / TC1-PN-003.c
- Title
- Replace substation conductor at Keystone substation (Keystone-Shelocta 230kV line terminal)
- Description
- Total Cost ($USD)
- $187,749
- Allocated Cost ($USD)
- $1,987
- Time Estimate
- 12 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 26SHELOCTA-26KEYSTONE 230.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-176 | 21.1 MW | 5.8% | $10,870 |
AG2-411 | 19.1 MW | 5.2% | $9,849 |
AG2-429 | 12.3 MW | 3.4% | $6,351 |
AG2-456 | 16.3 MW | 4.5% | $8,392 |
AG2-457 | 16.3 MW | 4.5% | $8,392 |
AH1-050 | 6.4 MW | 1.8% | $3,312 |
AH1-051 | 3.9 MW | 1.1% | $1,987 |
AH1-102 | 23.7 MW | 6.5% | $12,241 |
AH1-140 | 17.9 MW | 4.9% | $9,228 |
AH1-158 | 4.5 MW | 1.2% | $2,311 |
AH1-201 | 8.9 MW | 2.4% | $4,573 |
AH1-203 | 19.4 MW | 5.3% | $9,986 |
AH1-205 | 4.1 MW | 1.1% | $2,127 |
AH1-268 | 10.1 MW | 2.8% | $5,209 |
AH1-313 | 14.5 MW | 4.0% | $7,480 |
AH1-357 | 4.1 MW | 1.1% | $2,098 |
AH1-358 | 4.7 MW | 1.3% | $2,440 |
AH1-359 | 4.1 MW | 1.1% | $2,098 |
AH1-360 | 4.7 MW | 1.3% | $2,440 |
AH1-460 | 20.2 MW | 5.5% | $10,395 |
AH1-587 | 38.9 MW | 10.7% | $20,053 |
AH1-588 | 48.8 MW | 13.4% | $25,177 |
AH1-589 | 40.2 MW | 11.0% | $20,737 |
System Reinforcement: n9126.0
- Type
- Load Flow
- TO
- PENELEC
- RTEP ID / TO ID
- n9126.0 / TC1-PN-003.h
- Title
- Replace breaker leads at Keystone Substation (Keystone-Shelocta 230kV line terminal)
- Description
- None
- Total Cost ($USD)
- $152,770
- Allocated Cost ($USD)
- $1,617
- Time Estimate
- 12 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 26SHELOCTA-26KEYSTONE 230.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-176 | 21.1 MW | 5.8% | $8,845 |
AG2-411 | 19.1 MW | 5.2% | $8,014 |
AG2-429 | 12.3 MW | 3.4% | $5,168 |
AG2-456 | 16.3 MW | 4.5% | $6,829 |
AG2-457 | 16.3 MW | 4.5% | $6,829 |
AH1-050 | 6.4 MW | 1.8% | $2,695 |
AH1-051 | 3.9 MW | 1.1% | $1,617 |
AH1-102 | 23.7 MW | 6.5% | $9,960 |
AH1-140 | 17.9 MW | 4.9% | $7,509 |
AH1-158 | 4.5 MW | 1.2% | $1,880 |
AH1-201 | 8.9 MW | 2.4% | $3,721 |
AH1-203 | 19.4 MW | 5.3% | $8,126 |
AH1-205 | 4.1 MW | 1.1% | $1,731 |
AH1-268 | 10.1 MW | 2.8% | $4,239 |
AH1-313 | 14.5 MW | 4.0% | $6,087 |
AH1-357 | 4.1 MW | 1.1% | $1,707 |
AH1-358 | 4.7 MW | 1.3% | $1,985 |
AH1-359 | 4.1 MW | 1.1% | $1,707 |
AH1-360 | 4.7 MW | 1.3% | $1,985 |
AH1-460 | 20.2 MW | 5.5% | $8,459 |
AH1-587 | 38.9 MW | 10.7% | $16,317 |
AH1-588 | 48.8 MW | 13.4% | $20,487 |
AH1-589 | 40.2 MW | 11.0% | $16,874 |
System Reinforcement
- Type
- Load Flow
- TO
- PENELEC
- RTEP ID / TO ID
- (Pending) / TC2-PN-007.a
- Title
- Adjust relay settings at Keystone and Shelocta
- Description
- Total Cost ($USD)
- $103,523
- Allocated Cost ($USD)
- $1,096
- Time Estimate
- 11 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 26SHELOCTA-26KEYSTONE 230.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-176 | 21.1 MW | 5.8% | $5,994 |
AG2-411 | 19.1 MW | 5.2% | $5,430 |
AG2-429 | 12.3 MW | 3.4% | $3,502 |
AG2-456 | 16.3 MW | 4.5% | $4,628 |
AG2-457 | 16.3 MW | 4.5% | $4,628 |
AH1-050 | 6.4 MW | 1.8% | $1,826 |
AH1-051 | 3.9 MW | 1.1% | $1,096 |
AH1-102 | 23.7 MW | 6.5% | $6,750 |
AH1-140 | 17.9 MW | 4.9% | $5,088 |
AH1-158 | 4.5 MW | 1.2% | $1,274 |
AH1-201 | 8.9 MW | 2.4% | $2,521 |
AH1-203 | 19.4 MW | 5.3% | $5,506 |
AH1-205 | 4.1 MW | 1.1% | $1,173 |
AH1-268 | 10.1 MW | 2.8% | $2,872 |
AH1-313 | 14.5 MW | 4.0% | $4,125 |
AH1-357 | 4.1 MW | 1.1% | $1,157 |
AH1-358 | 4.7 MW | 1.3% | $1,345 |
AH1-359 | 4.1 MW | 1.1% | $1,157 |
AH1-360 | 4.7 MW | 1.3% | $1,345 |
AH1-460 | 20.2 MW | 5.5% | $5,732 |
AH1-587 | 38.9 MW | 10.7% | $11,057 |
AH1-588 | 48.8 MW | 13.4% | $13,883 |
AH1-589 | 40.2 MW | 11.0% | $11,434 |
System Reinforcement
- Type
- Load Flow
- TO
- PENELEC
- RTEP ID / TO ID
- (Pending) / TC2-PN-005.b
- Title
- Adjust Relays at Shelocta Substation (Homer City-Shelocta 230kV line terminal)
- Description
- Total Cost ($USD)
- $52,848
- Allocated Cost ($USD)
- $537
- Time Estimate
- 12 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 26HOMER CT-26SHELOCTA 230.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-176 | 19.8 MW | 6.2% | $3,275 |
AG2-411 | 17.6 MW | 5.5% | $2,912 |
AG2-429 | 10.7 MW | 3.4% | $1,777 |
AG2-456 | 16.0 MW | 5.0% | $2,653 |
AG2-457 | 16.0 MW | 5.0% | $2,653 |
AH1-050 | 5.4 MW | 1.7% | $894 |
AH1-051 | 3.2 MW | 1.0% | $537 |
AH1-102 | 16.1 MW | 5.0% | $2,665 |
AH1-158 | 3.8 MW | 1.2% | $624 |
AH1-201 | 8.1 MW | 2.5% | $1,342 |
AH1-203 | 17.7 MW | 5.5% | $2,932 |
AH1-205 | 3.8 MW | 1.2% | $624 |
AH1-268 | 6.8 MW | 2.1% | $1,134 |
AH1-313 | 13.0 MW | 4.1% | $2,158 |
AH1-357 | 4.0 MW | 1.3% | $663 |
AH1-358 | 4.7 MW | 1.5% | $771 |
AH1-359 | 4.0 MW | 1.3% | $663 |
AH1-360 | 4.7 MW | 1.5% | $771 |
AH1-460 | 18.5 MW | 5.8% | $3,062 |
AH1-587 | 37.5 MW | 11.8% | $6,218 |
AH1-588 | 48.0 MW | 15.1% | $7,960 |
AH1-589 | 39.5 MW | 12.4% | $6,556 |
System Reinforcement: n9116.0
- Type
- Load Flow
- TO
- PENELEC
- RTEP ID / TO ID
- n9116.0 / TC1-PN-001.d
- Title
- Rebuild approximately 11 miles of the Homer City-Shelocta 230 kV line with double bundled 795 kcmil 26/7 ACSS conductor
- Description
- Rebuild the Homer City – Shelocta 230 kV Line, approximately 11 miles, with double bunded 795 kcmil 26/7 ACSS conductor. Terminate new conductor at Homer City substation. Terminate new conductor at Shelocta substation.
- Total Cost ($USD)
- $39,312,233
- Allocated Cost ($USD)
- $0
- Time Estimate
- 31 Months
Potential Aggregate Contributor Note: Based on PJM cost allocation criteria, AH1-051 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AH1-051 could receive cost allocation. Although AH1-051 may not presently have cost responsibility for this upgrade, AH1-051 is a potential Aggregate Pool Contributor.
| Facility | Contingency | |
|---|---|---|
| 26HOMER CT-26SHELOCTA 230.0 kV Ckt 1 line | (Any) |
System Reinforcement: n9225.0
- Type
- Load Flow
- TO
- PENELEC
- RTEP ID / TO ID
- n9225.0 / TC1-PN-001.e
- Title
- Replace 230 kV substation conductor and line drops at Shelocta substation for the Homer City-Shelocta 230 kV line terminal
- Description
- Replace 230 kV substation conductor and line drops at Shelocta substation for the Homer City-Shelocta 230 kV line terminal
- Total Cost ($USD)
- $107,569
- Allocated Cost ($USD)
- $0
- Time Estimate
- 13 Months
Potential Aggregate Contributor Note: Based on PJM cost allocation criteria, AH1-051 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AH1-051 could receive cost allocation. Although AH1-051 may not presently have cost responsibility for this upgrade, AH1-051 is a potential Aggregate Pool Contributor.
| Facility | Contingency | |
|---|---|---|
| 26HOMER CT-26SHELOCTA 230.0 kV Ckt 1 line | (Any) |
System Reinforcement: s3335.1
- Type
- Load Flow
- TO
- PENELEC
- RTEP ID / TO ID
- s3335.1 / PN-2024-007
- Title
- Replace Homer City South 345/230-23kV Transformer (Projected ISD 6/1/2027)
- Description
- Replace the South 345/230-23kV Transformer and associated equipment with: - One(1) 345/230kV Transformer with three single-phase units - Replace 345 kV circuit switcher, disconnects, circuit breaker, and substation conductor Transformer Ratings: - Before Proposed Solution: 649/836/793/984 MVA (SN/SLTE/WN/WLTE) - After Proposed Solution: 913/1147/1201/1376 MVA (SN/SLTE/WN/WLTE)
- Cost Information
- Time Estimate
- Jun 01 2027
Not Contingent Note: AH1-051 contributes to the loading of an overloaded facility that is being mitigated by a planned supplemental project. AH1-051 is not contingent on this supplemental project as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.
| Facility | Contingency | |
|---|---|---|
| 26HOMER CT-26HOMER CT _ 230.0 kV Ckt S line | (Any) | |
| 26HOMER CY-26HOMER CT _ 345.0/230.0 kV Ckt S transformer | (Any) |
System Reinforcement
- Type
- Load Flow
- TO
- APS
- RTEP ID / TO ID
- (Pending) / TC2-APS-034.f
- Title
- Replace Breaker Leads at Shingletown
- Description
- Replace (2) 230 kV Breaker Leads (Bus side and Line side) at Shingletown This project has a pre-req of TC2-APS-034.e
- Total Cost ($USD)
- $214,619
- Allocated Cost ($USD)
- $0
- Time Estimate
- 12 Months
Potential Aggregate Contributor Note: Based on PJM cost allocation criteria, AH1-051 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AH1-051 could receive cost allocation. Although AH1-051 may not presently have cost responsibility for this upgrade, AH1-051 is a potential Aggregate Pool Contributor.
| Facility | Contingency | |
|---|---|---|
| 26LEWISTWN-01SHINGL 230.0 kV Ckt 1 line | (Any) |
System Reinforcement
- Type
- Load Flow
- TO
- APS
- RTEP ID / TO ID
- (Pending) / TC2-APS-034.g
- Title
- Replace/Update SEL-421 Relay at Shingletown
- Description
- Replace/Update (1) SEL-421 Relay at Shingletown This project has a pre-req of TC2-APS-034.f
- Total Cost ($USD)
- $509,895
- Allocated Cost ($USD)
- $0
- Time Estimate
- 18 Months
Potential Aggregate Contributor Note: Based on PJM cost allocation criteria, AH1-051 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AH1-051 could receive cost allocation. Although AH1-051 may not presently have cost responsibility for this upgrade, AH1-051 is a potential Aggregate Pool Contributor.
| Facility | Contingency | |
|---|---|---|
| 26LEWISTWN-01SHINGL 230.0 kV Ckt 1 line | (Any) |
System Reinforcement
- Type
- Load Flow
- TO
- APS
- RTEP ID / TO ID
- (Pending) / TC2-PN-002.b
- Title
- Replace/Update SEL-421 Relays at Lewistown
- Description
- Replace/Update (2) SEL-421 Relays at Lewistown
- Total Cost ($USD)
- $176,953
- Allocated Cost ($USD)
- $0
- Time Estimate
- 12 Months
Potential Aggregate Contributor Note: Based on PJM cost allocation criteria, AH1-051 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AH1-051 could receive cost allocation. Although AH1-051 may not presently have cost responsibility for this upgrade, AH1-051 is a potential Aggregate Pool Contributor.
| Facility | Contingency | |
|---|---|---|
| 26LEWISTWN-01SHINGL 230.0 kV Ckt 1 line | (Any) |
System Reinforcement
- Type
- Load Flow
- TO
- APS
- RTEP ID / TO ID
- (Pending) / TC2-APS-034.h
- Title
- Replace/Update SEL-421 Relay at Shingletown
- Description
- Replace/Update (1) SEL-421 Relay at Shingletown This project has a pre-req of TC2-APS-034.g
- Total Cost ($USD)
- $509,895
- Allocated Cost ($USD)
- $0
- Time Estimate
- 18 Months
Potential Aggregate Contributor Note: Based on PJM cost allocation criteria, AH1-051 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AH1-051 could receive cost allocation. Although AH1-051 may not presently have cost responsibility for this upgrade, AH1-051 is a potential Aggregate Pool Contributor.
| Facility | Contingency | |
|---|---|---|
| 26LEWISTWN-01SHINGL 230.0 kV Ckt 1 line | (Any) |
System Reinforcement
- Type
- Load Flow
- TO
- APS
- RTEP ID / TO ID
- (Pending) / TC2-APS-034.a
- Title
- Replace Bus Riser and Bus Side Disc Leads at Shingletown
- Description
- Replace (1) 230 kV Bus Riser and (1) 230 kV Bus Side Disc Leads at Shingletown
- Total Cost ($USD)
- $427,516
- Allocated Cost ($USD)
- $0
- Time Estimate
- 13 Months
Potential Aggregate Contributor Note: Based on PJM cost allocation criteria, AH1-051 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AH1-051 could receive cost allocation. Although AH1-051 may not presently have cost responsibility for this upgrade, AH1-051 is a potential Aggregate Pool Contributor.
| Facility | Contingency | |
|---|---|---|
| 26LEWISTWN-01SHINGL 230.0 kV Ckt 1 line | (Any) |
System Reinforcement
- Type
- Load Flow
- TO
- APS
- RTEP ID / TO ID
- (Pending) / TC2-APS-034.b
- Title
- Replace Bus Riser at Shingletown
- Description
- Replace (1) 230 kV Bus Riser at Shingletown This project has pre-req TC2-APS-034.a
- Total Cost ($USD)
- $263,169
- Allocated Cost ($USD)
- $0
- Time Estimate
- 12 Months
Potential Aggregate Contributor Note: Based on PJM cost allocation criteria, AH1-051 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AH1-051 could receive cost allocation. Although AH1-051 may not presently have cost responsibility for this upgrade, AH1-051 is a potential Aggregate Pool Contributor.
| Facility | Contingency | |
|---|---|---|
| 26LEWISTWN-01SHINGL 230.0 kV Ckt 1 line | (Any) |
System Reinforcement
- Type
- Load Flow
- TO
- APS
- RTEP ID / TO ID
- (Pending) / TC2-PN-002.a
- Title
- Reconductor Shingletown - Lewistown 230kV line [PN Side]
- Description
- Reconductor (Possible Rebuild) ~11.7 miles of Shingletown - Lewistown 230kV line [PN Side]
- Total Cost ($USD)
- $58,911,069
- Allocated Cost ($USD)
- $0
- Time Estimate
- 49 Months
Potential Aggregate Contributor Note: Based on PJM cost allocation criteria, AH1-051 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AH1-051 could receive cost allocation. Although AH1-051 may not presently have cost responsibility for this upgrade, AH1-051 is a potential Aggregate Pool Contributor.
| Facility | Contingency | |
|---|---|---|
| 26LEWISTWN-01SHINGL 230.0 kV Ckt 1 line | (Any) |
System Reinforcement
- Type
- Load Flow
- TO
- APS
- RTEP ID / TO ID
- (Pending) / TC2-APS-034.c
- Title
- Reconductor Shingletown - Lewistown 230kV line including T-line drop at Shingletown
- Description
- Reconductor (Possible Rebuild) ~14.4 miles of Shingletown - Lewistown 230kV line [APS Side] including T-line drop at Shingletown This project has a pre-req of TC2-APS-034.b
- Total Cost ($USD)
- $73,419,183
- Allocated Cost ($USD)
- $0
- Time Estimate
- 55 Months
Potential Aggregate Contributor Note: Based on PJM cost allocation criteria, AH1-051 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AH1-051 could receive cost allocation. Although AH1-051 may not presently have cost responsibility for this upgrade, AH1-051 is a potential Aggregate Pool Contributor.
| Facility | Contingency | |
|---|---|---|
| 26LEWISTWN-01SHINGL 230.0 kV Ckt 1 line | (Any) |
System Reinforcement
- Type
- Load Flow
- TO
- APS
- RTEP ID / TO ID
- (Pending) / TC2-APS-034.d
- Title
- Replace Disc Switches at Shingletown
- Description
- Replace (2) 1200 Amp 230 kV Disc Switches (LWT_BUS & LWT_LINE) at Shingletown This project has a pre-req of TC2-APS-034.c
- Total Cost ($USD)
- $711,556
- Allocated Cost ($USD)
- $0
- Time Estimate
- 22 Months
Potential Aggregate Contributor Note: Based on PJM cost allocation criteria, AH1-051 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AH1-051 could receive cost allocation. Although AH1-051 may not presently have cost responsibility for this upgrade, AH1-051 is a potential Aggregate Pool Contributor.
| Facility | Contingency | |
|---|---|---|
| 26LEWISTWN-01SHINGL 230.0 kV Ckt 1 line | (Any) |
System Reinforcement
- Type
- Load Flow
- TO
- APS
- RTEP ID / TO ID
- (Pending) / TC2-APS-034.i
- Title
- Replace Circuit Breaker at Shingletown
- Description
- Replace (1) 230 kV Circuit Breaker at Shingletown This project has a pre-req of TC2-APS-034.h
- Total Cost ($USD)
- $1,621,562
- Allocated Cost ($USD)
- $0
- Time Estimate
- 45 Months
Potential Aggregate Contributor Note: Based on PJM cost allocation criteria, AH1-051 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AH1-051 could receive cost allocation. Although AH1-051 may not presently have cost responsibility for this upgrade, AH1-051 is a potential Aggregate Pool Contributor.
| Facility | Contingency | |
|---|---|---|
| 26LEWISTWN-01SHINGL 230.0 kV Ckt 1 line | (Any) |
System Reinforcement
- Type
- Load Flow
- TO
- APS
- RTEP ID / TO ID
- (Pending) / TC2-APS-034.e
- Title
- Replace Current Transformers at Shingletown
- Description
- Replace (3) 1200 Amp 230 kV Current Transformers at Shingletown This project has a pre-req of TC2-APS-034.d
- Total Cost ($USD)
- $1,563,362
- Allocated Cost ($USD)
- $0
- Time Estimate
- 22 Months
Potential Aggregate Contributor Note: Based on PJM cost allocation criteria, AH1-051 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AH1-051 could receive cost allocation. Although AH1-051 may not presently have cost responsibility for this upgrade, AH1-051 is a potential Aggregate Pool Contributor.
| Facility | Contingency | |
|---|---|---|
| 26LEWISTWN-01SHINGL 230.0 kV Ckt 1 line | (Any) |
System Reinforcement: s0945.1
- Type
- Load Flow
- TO
- PPL
- RTEP ID / TO ID
- s0945.1
- Title
- Rebuild the Juniata 230/69 kV Substation
- Description
- None
- Cost Information
- Time Estimate
- Dec 31 2025
Not Contingent Note: AH1-051 contributes to the loading of an overloaded facility that is being mitigated by a planned supplemental project. AH1-051 is not contingent on this supplemental project as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.
| Facility | Contingency | |
|---|---|---|
| 26LEWISTWN-JUNI 230.0 kV Ckt 1 line | (Any) |
System Reinforcement
- Type
- Load Flow
- TO
- PENELEC
- RTEP ID / TO ID
- (Pending) / TC2-PN-001.a
- Title
- Replace 230 kV bus conductor at Shawville
- Description
- Replace 230 kV bus conductor at Shawville
- Total Cost ($USD)
- $696,930
- Allocated Cost ($USD)
- $0
- Time Estimate
- 13 Months
Potential Aggregate Contributor Note: Based on PJM cost allocation criteria, AH1-051 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AH1-051 could receive cost allocation. Although AH1-051 may not presently have cost responsibility for this upgrade, AH1-051 is a potential Aggregate Pool Contributor.
| Facility | Contingency | |
|---|---|---|
| 26SHAWVL 2-01SHINGL 230.0 kV Ckt 1 line | (Any) |
System Reinforcement
- Type
- Load Flow
- TO
- APS
- RTEP ID / TO ID
- (Pending) / TC2-APS-020.a
- Title
- Replace Bus Risers at Shingletown substation
- Description
- Replace (2) Bus Risers at Shingletown substation There is a pre-req for this project TC2-PN-001.a (FE-East Penelec project)
- Total Cost ($USD)
- $591,863
- Allocated Cost ($USD)
- $0
- Time Estimate
- 13 Months
Potential Aggregate Contributor Note: Based on PJM cost allocation criteria, AH1-051 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AH1-051 could receive cost allocation. Although AH1-051 may not presently have cost responsibility for this upgrade, AH1-051 is a potential Aggregate Pool Contributor.
| Facility | Contingency | |
|---|---|---|
| 26SHAWVL 2-01SHINGL 230.0 kV Ckt 1 line | (Any) |
System Reinforcement: n9119.0
- Type
- Load Flow
- TO
- PENELEC
- RTEP ID / TO ID
- n9119.0 / TC1-PN-003.b
- Title
- Reconductor/Rebuild the Shelocta – Keystone 230 kV Line, approximately 2.5 miles, with 1272 kcmil 45/7 ACSR 2-conductor
- Description
- Reconductor/Rebuild the Shelocta – Keystone 230 kV Line, approximately 2.5 miles, with 1272 kcmil 45/7 ACSR 2-conductor. Terminate new conductor at Keystone substation. Terminate new conductor at Shelocta substation.
- Total Cost ($USD)
- $9,533,592
- Allocated Cost ($USD)
- $0
- Time Estimate
- 23 Months
Potential Aggregate Contributor Note: Based on PJM cost allocation criteria, AH1-051 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AH1-051 could receive cost allocation. Although AH1-051 may not presently have cost responsibility for this upgrade, AH1-051 is a potential Aggregate Pool Contributor.
| Facility | Contingency | |
|---|---|---|
| 26SHELOCTA-26KEYSTONE 230.0 kV Ckt 1 line | (Any) |