AH1-069 Phase I Study Report

v1.00 released 2025-10-29 21:01

Jerome – Mohicanville 69 kV

10.2 MW Capacity / 17.0 MW Energy

Introduction

This Phase I System Impact Study Report (PH1) has been prepared in accordance with the PJM Open Access Transmission Tariff, Part VII, Subpart D, sections 307 and 308 for New Service Requests (projects) in Transition Cycle 2. The Project Developer/Eligible Customer (developer) is JR ME LLC, and the Transmission Provider (TP) is PJM Interconnection, LLC (PJM). The interconnected Transmission Owner (TO) is American Transmission Systems, Incorporated.

Preface

The Phase I System Impact Study is conducted on an aggregate basis within a New Services Request’s Cycle, and results are provided in both (i) a single Cycle executive summary format and (ii) an individual project-level basis. The Phase I System Impact Study Results (for both the executive summary and individual reports) will be publicly available on PJM’s website. Developers must obtain the results from the website.

In accordance with PJM Manual 14H, section 4.3, PJM takes the following actions during the Phase I System Impact Study:
  1. PJM studies each New Service Request on a summer peak, winter peak and light load RTEP base case study. The case year is dependent on the new services cycle under study. PJM will identify the base case year to be used in the study of a specific cycle on its website.
  2. PJM will only perform load flow analysis during the Phase I System Impact Study.
  3. In Phase I of the Cycle, PJM conducts an Affected System screen to identify any New Service Request with Affected System impacts and provides each Affected System Operator with a list of New Service Request in the Cycle with potential impacts to their respective system.
  4. PJM will create both the short circuit and stability base cases to be used in the Phase II System Impact Study.
  5. The Phase I System Impact Study results will be publicly available on PJM’s website. Project Developers and Eligible Customers must obtain the results from the website.
The Transmission Owner takes the following actions during the Phase I System Impact Study:
  1. Identify required Interconnection Facilities to accommodate the New Service Request.
  2. Identify required Network Upgrades to mitigate system violations from the Phase I System Impact Study.
  3. Provide planning-level preliminary estimates of Interconnection Facilities and Network Upgrades including scope, cost and elapsed time to complete the work.

Decision Point I Requirements

At the close of Phase I System Impact Study, PJM will initiate Decision Point I (DP1). During DP1, the Project Developer will have 30 days to decide whether to proceed with their project. If the Project Developer elects to proceed, they should provide the elements defined in the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 309.A.1. Additional information on these elements is available in PJM Manual 14H sections 4.4, 6, and 7.

Allowable project modifications at Decision Point I are defined in PJM Open Access Transmission Tariff, Part VII, Subpart D, section 309.B. Additional information regarding allowable project modifications can be found in PJM Manual 14H, section 9.8.

General

The Project Developer has proposed a Solar generating facility located in the American Transmission Systems, Incorporated zone — Ashland County, Ohio. The installed facilities will have a total capability of 17.0 MW with 10.2 MW of this output being recognized by PJM as Capacity.

Project Information
New Service Request Number:
AH1-069
Project Name:
Jerome – Mohicanville 69 kV
Project Developer Name:
JR ME LLC
State:
Ohio
County:
Ashland
Transmission Owner:
American Transmission Systems, Incorporated
MFO:
17.0
MWE:
17.0
MWC:
10.2
Fuel Type:
Solar
Basecase Study Year:
2028

Physical Interconnection Facility Study

Physical Interconnection Facilities Study is not performed as part of the Phase I System Impact Study. Physical Interconnection Facilities Study will commence in the Phase II System Impact Study.

Point of Interconnection

AH1-069 will interconnect on the American Transmission Systems, Incorporated transmission system by tapping the Mohican - Brookside 69 kV line between Mohicanville and Jerome. AH1-069 is uprated by AH1-070. Both projects are in Transition Cycle 2 and will share costs for the required Transmission Owner Interconnection Facilities and physical interconnection Network Upgrades

Cost Summary

The table below shows a summary of the total cost estimates for this New Service Request project. In the Phase I SIS, the costs shown are subject to change as a result of a facility study performed by the TO during the Phase II or Phase III System Impact Study.

Based on the Phase I SIS results, the AH1-069 project has the following allocation of costs for interconnection. The cost contribution towards Readiness Deposit are also shown below.

Cost Summary
DescriptionCost Allocated to AH1-069Cost Subject to Readiness*
Transmission Owner Interconnection Facilities (TOIF)$403,522$0
Other Scope$29,200$0
Option To Build Oversight$0$0
Physical Interconnection Network Upgrades
Stand Alone Network Upgrades$6,452,552$6,452,552
Network Upgrades$592,184$592,184
System Reliability Network Upgrades
Steady State Thermal & Voltage (SP & LL)$0$0
Transient Stability$0$0
Short Circuit$0$0
Transmission Owner Analysis
SubRegional$0$0
Distribution$0$0
Affected System Reinforcements
AFS - PJM Violatons$0$0
AFS - Non-PJM Violations$0$0
Total$7,477,458$7,044,736

* Contributes to calculation for Readiness Deposit #2 (RD2). See Readiness Deposit section of report for additional detail.

Definitions

Transmission Owner Interconnection Facilities: Facilities that are owned, controlled, operated and maintained by the Transmission Owner on the Transmission Owner’s side of the Point of Change of Ownership to the Point of Interconnection, including any modifications, additions or upgrades made to such facilities and equipment, that are necessary to physically and electrically interconnect the Generating Facility with the Transmission System or interconnected distribution facilities.

Stand Alone Network Upgrades: Network Upgrades, which are not part of an Affected System, which a Project Developer may construct without affecting day-to-day operations (e.g. taking a transmission outage) of the Transmission System during their construction.

Network Upgrades: Modifications or additions to transmission-related facilities that are integrated with and support the Transmission Provider’s overall Transmission System for the general benefit of all users of such Transmission System. Network Upgrades have no impact or potential impact on the Transmission System until the final tie-in is complete.

Notes

Note 1: PJM Open Access Transmission Tariff (OATT), Part VII, Subpart D, section 307.5 outlines cost allocation rules. The rules are further clarified in PJM Manual 14H, section 4.2.6. PJM shall identify the New Service Requests in the Cycle contributing to the need for the required Network Upgrades within the Cycle. All New Service Requests that contribute to the need for a Network Upgrade will receive cost allocation for that upgrade pursuant to each New Service Request’s contribution to the reliability violation identified on the transmission system in accordance with PJM Manuals.

Note 2: There will be no inter-Cycle cost allocation for Interconnection Facilities or Network Upgrades identified in the System Impact Study costs identified in a Cycle; all such costs shall be allocated to New Service Requests in that Cycle.

Note 3: For Project Developers with System Reinforcements listed: If this project presents cost allocation to a System Reinforcement indicates $0, then please be aware that as changes to the interconnection process occur, such as other projects withdrawing, reducing in size, etc, the cost responsibilities can change and a cost allocation may be assigned to this project. In addition, although this project presents cost allocation to a System Reinforcement is presently $0, this project may need this system reinforcement completed to be deliverable to the PJM system. If this project desires to come into service prior to completion of the system reinforcement, the Project Developer will need to request PJM to perform an interim deliverability study to determine if they would be deliverable for all or a portion of their output for each delivery year until the system reinforcement is complete.

Readiness Deposit

Per Tariff Part VII, Subpart D, section 309 (Decision Point I) A.1.a.i and PJM Manual 14H, section 6.2, Readiness Deposit #2 (RD2) are funds committed by the Project Developer or Eligible Customer based upon the applicable contribution to Network Upgrades as defined below. Readiness Deposits are not used to fund studies nor to offset Security.

During Decision Point I (DP1), the Project Developer or Eligible Customer is required to submit Readiness Deposit #2, which is calculated as 10% of cost allocation for required Phase I Network Upgrades minus Readiness Deposit #1.

Note 1: “Network Upgrades” referred to in the calculation include both (i) the Physical Interconnection Network Upgrades and (ii) the System Reliability Network Upgrades as shown in the Cost Summary table.

Note 2: Readiness Deposit #1 (RD1) = ($4,000 * Project Size (MW))

Note 3: Readiness Deposit #2 (RD2) = 10% of cost allocation for required Network Upgrades minus RD1. Readiness Deposit #2 (RD2) can be zero, but may not be a negative number.

Readiness Deposit #2 Due for Project AH1-069

Readiness Deposit #2 has been calculated for the project based on the Phase I System Impact Study results and is shown in the table below. This Readiness Deposit #2 must be provided at Decision Point I through either a wire transfer or letter of credit per Manual 14H, Section 6.2.

Readiness Deposit
Project ID10% of cost allocation for Phase I Network UpgradesReadiness Deposit #1 Received (RD1)Readiness Deposit #2 (RD2) for AH1-069 Project due at DP1
ABA - B
AH1-069$704,474$68,000$636,474

Note: Failure to provide an acceptable form of Readiness Deposit #2 by the end of Decision Point I will result in withdrawal and termination of the New Service Request.

For additional detail regarding Readiness Deposit Refunds, reference PJM Manual 14H, section 6.2.1. The Readiness Deposit Letter of Credit template can be found here.

Transmission Owner Scope of Work

The total preliminary cost estimate for the Transmission Owner scope of work (including TOIF and Physical Interconnection Network Upgrades) is given in the table below. These costs do not include CIAC Tax Gross-up.

Transmission Owner Interconnection Facilities
RTEP IDDescriptionTotal Cost ($USD)Allocated Cost ($USD)
(Pending)Integrate Interconnection Facilities protection and controls to the Transmission Owner system.$61,320 $30,660 (See Note 1)
(Pending)Construction of (1) span of conductor between the new Interconnection substation takeoff structure and Developer owned dead end structure.$745,724 $372,862 (See Note 1)
Stand-Alone Network Upgrades
RTEP IDDescriptionTotal Cost ($USD)Allocated Cost ($USD)
(Pending)ADSS fiber to new interconnection substation.$803,000 $401,500 (See Note 1)
(Pending)Construct a new 69 kV 3-breaker ring bus Interconnection substation.$12,102,104 $6,051,052 (See Note 1)
Network Upgrades
RTEP IDDescriptionTotal Cost ($USD)Allocated Cost ($USD)
(Pending)Revise relay settings at Mohicanville substation as required.$51,100 $25,550 (See Note 1)
(Pending)Revise relay settings at Mohican substation as required.$51,100 $25,550 (See Note 1)
(Pending)Revise relay settings at Jerome substation as required.$51,100 $25,550 (See Note 1)
(Pending)Revise relay settings at Brookside substation as required.$51,100 $25,550 (See Note 1)
(Pending)Cut the existing 138kV line and Loop in the new Interconnection substation.$979,968 $489,984 (See Note 1)
Physical Interconnection
RTEP IDDescriptionTotal Cost ($USD)Allocated Cost ($USD)
(Pending)Install 138 kV revenue metering within new Interconnection substation.$58,400 $29,200 (See Note 1)

Based on the scope of work for the Interconnection Facilities, it is expected to take 36 month(s) after the signing of a Generator Interconnection Agreement (as this is a FERC connection) and construction kickoff call to complete the installation of the physical connection work. This assumes that there will be no environmental issues with any of the new properties associated with this project, that there will be no delays in acquiring the necessary permits for implementing the defined interconnection work, and that all system outages will be allowed when requested.

The schedule for any required Network Impact Reinforcements will be more clearly identified in the Phase II and Phase III System Impact Studies.

Note 1: A Common Use Upgrade is a Network Upgrade that is needed for the interconnection of Generating Facilities or Merchant Transmission Facilities of more than one Project Developer or Eligible Customer and which is the shared responsibility of each Project Developer or Eligible Customer. If multiple Project Developers request to connect to the same interconnection substation, the Transmission Owner will determine the cost to accommodate all the requests at the substation. The cost for the interconnection will be allocated in proportion to the number of required terminations into the substation.

Transmission Owner Analysis

FE performed an analysis of its underlying transmission system <100 kV system. New Service Request Project AH1-069 did not contribute to any overloads on the FE transmission <100 kV system.

 

Developer Requirements

The developer is responsible for all design and construction related activities on the developer’s side of the Point of Change in Ownership. FirstEnergy interconnection requirements can be found here.

To the extent that these Applicable Technical Requirements and Standards may conflict with the terms and conditions of the Tariff, the Tariff shall control.

Revenue Metering and SCADA Requirements

PJM Requirements
The developer will be required to install equipment necessary to provide Revenue Metering (KWH, KVARH) and real time data (KW, KVAR) for their generating Resource. See PJM Manual 01, PJM Manual 14D, and PJM Tariff Part IX, Subpart B, Appendix 2, section 8.
Meteorological Data Reporting Requirement
The solar generation facility shall provide the Transmission Provider with site-specific meteorological data including:
  • Temperature (degrees Fahrenheit)
  • Atmospheric Pressure (hectopascals)
  • Irradiance
  • Forced outage data
Transmission Owner Requirements
The Project Developer will be required to comply with all interconnected Transmission Owner’s revenue metering requirements located at the following link: PJM - Transmission Owner Engineering & Construction Standards.

Summer Peak Analysis

The New Service Request AH1-069 was evaluated as a 17.0 MW (10.2 MW Capacity) injection in the ATSI area.

AH1-069 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 17.0 MW (17.0 MW under study).

Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.

StudyAreaFacility DescriptionContingency NameContingency TypeDC|ACFinal Cycle LoadingRating (MVA)Rating TypeMVA to MitigateMW ContributionDetails
GD2ATSI
02BEAVER-02CARLIL 345.0 kV Ckt 1 line
ATSI_P7-1_OEC-345-002_SRT-A
TowerAC109.31 %1745.0B1907.450.8
GD2ATSI
02BEAVER-02LAKEAVE 345.0 kV Ckt 2 line
ATSI_P2-3_OEC-345-002_SRT-A
BreakerAC174.17 %1878.0B3270.930.91

Details for 02BEAVER-02CARLIL 345.0 kV Ckt 1 line l/o ATSI_P7-1_OEC-345-002_SRT-A


Base Case Flowgate

Area:ATSI
Facility Description:
02BEAVER-02CARLIL 345.0 kV Ckt 1 line
Contingency Name:
ATSI_P7-1_OEC-345-002_SRT-A
Contingency Type:Tower
DC|AC:AC
Final Cycle Loading:109.31 %
Rating:1745.0 MVA
Rating Type:B
MVA to Mitigate:1907.45
MW Contribution:0.8
Bus #Bus NameTypeMW Contribution
23856402BAYSG1
50/50
1.196
23867002DVBSG1
50/50
10.407
23906402RICHG1
Adder
1.189
23917202WLORG-3
50/50
1.553
23917302WLORG-4
50/50
1.519
23917402WLORG-5
50/50
1.527
23920202STRYCT
Adder
1.608
23929302BS-PKR
50/50
2.106
247604X1-042
Adder
0.22
247620Y3-023
Adder
0.218
247643Z2-116 C
Solar/Wind Harmer
0.032
24191202EL_AA1-006
Adder
0.297
24441205WTRV SLR C
Solar/Wind Harmer
0.07
24695305TIMB G C
Solar/Wind Harmer
2.781
24189802OREGON_CT1
50/50
2.254
24189902OREGON_CT2
50/50
2.208
24190002OREGON_ST1
50/50
2.971
247607V1-011 GEN
Solar/Wind Harmer
2.098
23857102WLORG-A
50/50
9.096
23857202WLORG-B
50/50
9.372
247521TR3_G114
Solar/Wind Harmer
1.636
254304AE2-114 C
Solar/Wind Helper
0.104
254305AE2-115 C
Solar/Wind Helper
0.104
241982AE2-343 S C
Solar/Wind Helper
0.109
203947AF1-006 C
Solar/Wind Helper
0.283
270191TR4_S_V150
Solar/Wind Harmer
1.46
23906502RICHG2&3
Adder
1.187
23906502RICHG2&3
Adder
1.187
203979AG1-198 GEN
Solar/Wind Helper
0.147
203980AG1-197 GEN
Solar/Wind Helper
0.188
203860AG1-193 C
Solar/Wind Helper
0.116
203835AF1-098 GEN
Solar/Wind Helper
0.992
203830AF1-094 GEN
Solar/Wind Helper
0.245
270302AB2-170 GEN
Solar/Wind Harmer
3.966
270317AD1-130_GEN
Solar/Wind Harmer
1.52
241886AC2-103 GEN2
Solar/Wind Harmer
14.419
241885AC2-103 GEN1
Solar/Wind Harmer
14.419
241801AE1-079 GEN
Solar/Wind Helper
0.122
270404AC1-167 GEN
Solar/Wind Harmer
0.641
270428AC2-015 C
Solar/Wind Harmer
4.415
241847AF2-150_GEN
Solar/Wind Harmer
2.294
270435AC2-044 GEN
Solar/Wind Harmer
1.044
270489AE1-102 GEN1
Solar/Wind Harmer
0.679
246936BC-WTG1
Solar/Wind Harmer
2.043
246937BC-WTG2
Solar/Wind Harmer
2.043
246938BC-WTG3
Solar/Wind Harmer
2.078
241808AF1-120 C
Solar/Wind Harmer
1.077
241996AE2-282_GEN
Solar/Wind Harmer
1.931
241813AF1-122_GEN
Solar/Wind Harmer
2.935
241960AC2-195 GEN
Solar/Wind Harmer
1.215
23917502WLORG-6
50/50
0.764
241832AE2-181_GEN
Solar/Wind Harmer
1.75
241967AE2-285_GEN
Solar/Wind Helper
0.314
241997AF1-093 GEN
Solar/Wind Helper
0.121
241807AE2-176_GEN
Solar/Wind Harmer
6.057
241840AF1-064_GEN
Solar/Wind Harmer
1.274
241858AF1-205_GEN
Solar/Wind Harmer
4.928
270297AD1-101 GEN
Solar/Wind Harmer
1.75
270377AD1-106 GEN
Solar/Wind Harmer
3.082
270258AD1-119 GEN
Solar/Wind Harmer
1.565
270449AD2-020 GEN
Solar/Wind Harmer
1.385
241985AE1-237 GEN
Solar/Wind Helper
0.122
270216AD2-079_GEN
Solar/Wind Harmer
0.283
270588AE1-091_GEN
Solar/Wind Harmer
6.591
270499AE1-146 GEN
Solar/Wind Harmer
2.343
270505AE1-170 C O1
Solar/Wind Harmer
7.249
270007AE1-245 C
Solar/Wind Harmer
3.147
270541AE2-072 C
Solar/Wind Harmer
3.99
270043AE2-236 GEN
Solar/Wind Harmer
2.394
270063AE2-323 C
Solar/Wind Harmer
1.038
254303AC2-168 GEN
Solar/Wind Helper
0.071
270578AF1-285 GEN2
Solar/Wind Harmer
0.204
270578AF1-285 GEN2
Solar/Wind Harmer
0.531
270391AF1-285 GEN3
Solar/Wind Harmer
0.204
270391AF1-285 GEN3
Solar/Wind Harmer
0.531
270361_3
Solar/Wind Harmer
8.521
270575GUS2 35KV
Solar/Wind Harmer
10.039
270526AF1-158 GEN
Solar/Wind Harmer
2.042
270462AD2-086
Solar/Wind Harmer
3.299
270485AE1-090_GEN
Solar/Wind Harmer
0.287
270044AE2-322 C
Solar/Wind Harmer
0.769
23917102WLORG-2
50/50
1.505
972211AH1-690 GEN
50/50
238.133
241966AE1-183 GEN
Solar/Wind Helper
0.121
24639705ELKHART HY
Adder
0.072
24642205MAYFLWER
Adder
0.299
247522W1-056 GEN
Solar/Wind Harmer
1.589
270491AE1-102 GEN2
Solar/Wind Harmer
0.679
942801AE2-298 GEN
Solar/Wind Harmer
0.797
942871AE2-306 GEN
Solar/Wind Harmer
0.398
943021AE2-325 GEN
Solar/Wind Harmer
1.799
944161AF1-084 GEN
Solar/Wind Harmer
1.106
944231AF1-091 GEN
Solar/Wind Harmer
2.19
945111AF1-176 GEN
Solar/Wind Harmer
8.634
945111AF1-176 GEN
Solar/Wind Harmer
2.737
945411AF1-206 GEN
Solar/Wind Harmer
7.213
945641AF1-229 GEN
Solar/Wind Harmer
3.229
959331AF2-224 GEN
Solar/Wind Harmer
4.645
959441AF2-235 GEN
Solar/Wind Helper
0.115
960681AF2-359 GEN
Solar/Wind Harmer
1.625
960841AF2-375 GEN
Solar/Wind Harmer
3.749
960981AF2-389 GEN
Solar/Wind Harmer
0.728
961051AF2-396 GEN
Solar/Wind Harmer
7.783
961051AF2-396 GEN
Solar/Wind Harmer
3.62
961961AG1-039 GEN
Solar/Wind Harmer
1.583
961971AG1-040 GEN
Solar/Wind Helper
0.251
962101AG1-054 GEN
Solar/Wind Helper
0.304
962511AG1-100 GEN
Solar/Wind Helper
0.255
963791AG1-232 GEN
Solar/Wind Harmer
5.807
966831AG1-554 GEN
Solar/Wind Harmer
0.704
970031AG2-029 GEN
Solar/Wind Harmer
14.083
970065AG2-057 GEN
Solar/Wind Harmer
0.459
970179AG2-119 GEN
Solar/Wind Harmer
3.495
970217AG2-149 GEN
Solar/Wind Harmer
22.552
970515AG2-329 GEN
Solar/Wind Harmer
10.227
970611AG2-400 GEN
Solar/Wind Harmer
4.645
970817AG2-515 GEN
Solar/Wind Harmer
13.044
970905AG2-564 GEN
Solar/Wind Harmer
3.497
971201AH1-060 GEN
Solar/Wind Harmer
0.917
971231AH1-075 GEN
Solar/Wind Harmer
0.399
971549AH1-272 GEN
Solar/Wind Harmer
11.155
971567AH1-282 GEN
Solar/Wind Harmer
8.024
971677AH1-339 GEN
Solar/Wind Harmer
6.773
971769AH1-391 GEN
Solar/Wind Harmer
4.471
971771AH1-392 GEN
Solar/Wind Harmer
4.129
971989AH1-539 GEN
Solar/Wind Harmer
7.613
972253AH1-711 GEN
Adder
43.699
24441505OLIV SLR
Solar/Wind Harmer
0.06
270223U2-072_GEN1
Solar/Wind Harmer
0.868
270224U2-072_GEN2
Solar/Wind Harmer
0.868
270227U2-072_GEN3
Solar/Wind Harmer
0.868
270228U2-072_GEN4
Solar/Wind Harmer
0.868
270231U2-072_GEN5
Solar/Wind Harmer
0.868
270246TR4_N_V150
Solar/Wind Harmer
0.414
270247TR4_N_V136
Solar/Wind Harmer
0.414
957071AF2-004 GEN
50/50
12.095
957111AF2-005 GEN
50/50
1.467
957201AF2-014 GEN
Solar/Wind Harmer
2.368
957891AF2-083 GEN
Solar/Wind Harmer
1.625
958091AF2-103 GEN
Solar/Wind Harmer
0.086
958321AF2-126 GEN
Solar/Wind Harmer
1.366
965011AG1-365 GEN
Solar/Wind Harmer
4.645
965021AG1-366 GEN
Solar/Wind Harmer
1.08
965041AG1-368 GEN
Solar/Wind Harmer
4.881
965051AG1-369 GEN
Solar/Wind Harmer
2.43
965421AG1-410 GEN
Solar/Wind Harmer
15.499
965681AG1-436 GEN
Solar/Wind Harmer
5.376
965791AG1-447 GEN
Solar/Wind Harmer
2.75
966311AG1-500 GEN
50/50
141.29
966321AG1-501 GEN
50/50
1.834
972301AH1-735 GEN
Adder
5.944
970159AG2-109 GEN
Solar/Wind Harmer
3.418
971219AH1-069 GEN
Solar/Wind Harmer
0.796
971221AH1-070 GEN
Solar/Wind Harmer
0.796
990142J1224
External Queue
11.235392570495605
990527J1329
External Queue
1.536989450454712
991177J1571 G
External Queue
13.065269470214844
CBM West 1LTFEXP_CBM-W1->PJM
CBM
79.335
CBM West 2LTFEXP_CBM-W2->PJM
CBM
33.236
CBM South 1LTFEXP_CBM-S1->PJM
CBM
7.4
CBM South 2LTFEXP_CBM-S2->PJM
CBM
1.536
NYPJM->LTFIMP_NY
CLTF
1.797
LGEELTFEXP_LGEE->PJM
CLTF
1.709
WECLTFEXP_WEC->PJM
CLTF
1.408
CPLELTFEXP_CPLE->PJM
CLTF
0.14
TVALTFEXP_TVA->PJM
CLTF
1.857
MECLTFEXP_MEC->PJM
CLTF
5.472
LAGNLTFEXP_LAGN->PJM
CLTF
4.111
SIGELTFEXP_SIGE->PJM
CLTF
0.142
AG2-052LTFEXP_AG2-052->PJM
LTF
0.091
AH1-155LTFEXP_AH1-155->PJM
LTF
0.136

Details for 02BEAVER-02LAKEAVE 345.0 kV Ckt 2 line l/o ATSI_P2-3_OEC-345-002_SRT-A


Base Case Flowgate

Area:ATSI
Facility Description:
02BEAVER-02LAKEAVE 345.0 kV Ckt 2 line
Contingency Name:
ATSI_P2-3_OEC-345-002_SRT-A
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:174.17 %
Rating:1878.0 MVA
Rating Type:B
MVA to Mitigate:3270.93
MW Contribution:0.91
Bus #Bus NameTypeMW Contribution
23856402BAYSG1
50/50
1.489
23867002DVBSG1
50/50
13.011
23906402RICHG1
Adder
1.491
23917202WLORG-3
50/50
1.953
23917302WLORG-4
50/50
1.91
23917402WLORG-5
50/50
1.92
23920202STRYCT
Adder
2.011
23929302BS-PKR
50/50
2.62
24729505KEY G4
Adder
3.179
247604X1-042
Adder
0.282
247620Y3-023
Adder
0.281
247643Z2-116 C
Solar/Wind Harmer
0.042
20083426SW_E13_K22
Solar/Wind Helper
0.025
20084626FORWARD
Solar/Wind Helper
0.17
20088826HIGHLAND
Solar/Wind Helper
0.435
20088926STNY CRK
Solar/Wind Helper
0.38
20092526R32
Solar/Wind Helper
0.563
20094526CT_V3-030
Solar/Wind Helper
0.243
20334926Z1-069 C
Solar/Wind Helper
0.837
24191202EL_AA1-006
Adder
0.36
24441205WTRV SLR C
Solar/Wind Harmer
0.089
274675JOLIET 29;7U
Adder
15.345
274675JOLIET 29;7U
Adder
14.797
274676JOLIET 29;8U
Adder
15.345
274676JOLIET 29;8U
Adder
14.797
274682WAUKEGAN ;7U
Adder
8.816
274682WAUKEGAN ;7U
Adder
8.816
274683WAUKEGAN ;8U
Adder
10.328
274683WAUKEGAN ;8U
Adder
8.706
274687WILL CNTY;4U
Adder
14.004
274687WILL CNTY;4U
Adder
14.004
274693ROCKY RD ;1P
Adder
5.407
274695ROCKY RD ;2P
Adder
5.46
274696ROCKY RD ;4P
Adder
5.589
274697ROCKY RD ;3P
Adder
1.483
274723RIVER EC ;12
Adder
9.215
274724RIVER EC ;11
Adder
9.105
274728ELWOOD EC;5P
Adder
8.208
274729ELWOOD EC;1P
Adder
8.208
274730ELWOOD EC;6P
Adder
8.208
274731ELWOOD EC;2P
Adder
8.208
274732ELWOOD EC;7P
Adder
8.208
274733ELWOOD EC;3P
Adder
8.208
274734ELWOOD EC;8P
Adder
8.208
274735ELWOOD EC;4P
Adder
8.208
274736ELWOOD EC;9P
Adder
8.208
274752CRETE EC ;2U
Adder
2.532
274753CRETE EC ;3U
Adder
2.532
274754CRETE EC ;4U
Adder
2.532
274771LINCOLN ;2U
Adder
3.125
274772LINCOLN ;3U
Adder
3.125
274773LINCOLN ;4U
Adder
3.125
274774LINCOLN ;5U
Adder
3.125
274775LINCOLN ;6U
Adder
3.125
274776LINCOLN ;7U
Adder
3.125
274777LINCOLN ;8U
Adder
3.125
274800UNIV PARK;3U
Adder
2.944
274801UNIV PARK;4U
Adder
2.944
274802UNIV PARK;5U
Adder
2.953
274803UNIV PARK;6U
Adder
2.953
274822ROCKFORD ;11
Adder
9.424
274823ROCKFORD ;21
Adder
9.356
274826FISK ;BP
Adder
5.536
274827FISK ;RP
Adder
3.924
274888KELLY CRK;1U
Solar/Wind Harmer
2.977
276164X3-005 C
Solar/Wind Harmer
0.358
25326509SID D
Adder
0.633
20088626ARWF_N39
Solar/Wind Helper
0.584
20091526CHSTN_FL
Solar/Wind Helper
0.29
20303426NA_O38_P22
Solar/Wind Helper
0.479
274674JOLIET 9 ;6U
Adder
7.687
274674JOLIET 9 ;6U
Adder
7.687
274828WAUKEGAN ;BP
Adder
5.414
24695305TIMB G C
Solar/Wind Harmer
3.562
274760LEE CO EC;1U
Adder
4.416
24189802OREGON_CT1
50/50
2.816
24189902OREGON_CT2
50/50
2.76
24190002OREGON_ST1
50/50
3.713
247607V1-011 GEN
Solar/Wind Harmer
2.681
23857102WLORG-A
Adder
8.207
23857202WLORG-B
Adder
8.455
247521TR3_G114
Solar/Wind Harmer
2.099
254304AE2-114 C
Solar/Wind Helper
0.138
254305AE2-115 C
Solar/Wind Helper
0.138
235058AG1-386 C
Solar/Wind Helper
0.205
241982AE2-343 S C
Solar/Wind Helper
0.145
203940AF1-140 C
Solar/Wind Helper
0.192
203946AE2-131 C
Solar/Wind Helper
0.258
203947AF1-006 C
Solar/Wind Helper
0.516
203952AE2-129 C
Solar/Wind Helper
0.257
203954AE2-126 C
Solar/Wind Helper
0.282
270191TR4_S_V150
Solar/Wind Harmer
1.873
23906502RICHG2&3
Adder
1.489
23906502RICHG2&3
Adder
1.489
20090526Q36
Solar/Wind Helper
0.548
274761LEE CO EC;2U
Adder
2.885
274764LEE CO EC;5U
Adder
4.426
274765LEE CO EC;6U
Adder
4.426
274805UNIV PK N;1U
Adder
2.569
274807UNIV PK N;3U
Adder
2.581
274808UNIV PK N;4U
Adder
2.553
238217AF1-153 C O1
Solar/Wind Helper
0.144
238206AE2-263_GEN
Solar/Wind Helper
0.502
238202AE2-262_GEN
Solar/Wind Helper
0.528
276772AC2-154 GEN
Solar/Wind Harmer
1.406
276776AD2-060 GEN
Solar/Wind Harmer
0.213
276806AD2-047 C O1
Solar/Wind Harmer
5.394
276893AG1-478 C
Solar/Wind Harmer
0.209
276897AD1-100 C
Solar/Wind Harmer
14.503
274744AC1-111 GEN8
Adder
2.761
274745AC1-111 GEN9
Adder
2.761
274746AC1-111 G10
Adder
2.761
203979AG1-198 GEN
Solar/Wind Helper
0.261
203980AG1-197 GEN
Solar/Wind Helper
0.336
203860AG1-193 C
Solar/Wind Helper
0.199
203846AF2-130 C
Solar/Wind Helper
0.325
203835AF1-098 GEN
Solar/Wind Helper
1.778
203830AF1-094 GEN
Solar/Wind Helper
0.435
203818AF1-086 GEN
Solar/Wind Helper
0.912
203854AF2-039 C
Solar/Wind Helper
0.18
203855AF2-088 C
Solar/Wind Helper
0.087
203961AE2-224 GEN
Solar/Wind Helper
1.164
203804AE2-113_GEN
Solar/Wind Helper
1.128
203993AD2-133_GEN1
Solar/Wind Helper
0.548
270302AB2-170 GEN
Solar/Wind Harmer
5.097
270317AD1-130_GEN
Solar/Wind Harmer
1.954
241886AC2-103 GEN2
Solar/Wind Harmer
18.089
241885AC2-103 GEN1
Solar/Wind Harmer
18.089
241801AE1-079 GEN
Solar/Wind Helper
0.162
270404AC1-167 GEN
Solar/Wind Harmer
0.816
270428AC2-015 C
Solar/Wind Harmer
5.418
241847AF2-150_GEN
Solar/Wind Harmer
2.847
270435AC2-044 GEN
Solar/Wind Harmer
1.336
270489AE1-102 GEN1
Solar/Wind Harmer
0.868
246936BC-WTG1
Solar/Wind Harmer
2.614
246937BC-WTG2
Solar/Wind Harmer
2.614
246938BC-WTG3
Solar/Wind Harmer
2.659
241808AF1-120 C
Solar/Wind Harmer
1.346
241996AE2-282_GEN
Solar/Wind Harmer
2.414
241813AF1-122_GEN
Solar/Wind Harmer
3.682
241960AC2-195 GEN
Solar/Wind Harmer
1.533
241832AE2-181_GEN
Solar/Wind Harmer
2.188
241967AE2-285_GEN
Solar/Wind Helper
0.417
241997AF1-093 GEN
Solar/Wind Helper
0.16
241807AE2-176_GEN
Solar/Wind Harmer
7.368
241840AF1-064_GEN
Solar/Wind Harmer
1.592
241858AF1-205_GEN
Solar/Wind Harmer
6.156
270297AD1-101 GEN
Solar/Wind Harmer
2.22
270377AD1-106 GEN
Solar/Wind Harmer
3.918
270258AD1-119 GEN
Solar/Wind Harmer
1.996
270449AD2-020 GEN
Solar/Wind Harmer
1.777
241985AE1-237 GEN
Solar/Wind Helper
0.162
270216AD2-079_GEN
Solar/Wind Harmer
0.363
270588AE1-091_GEN
Solar/Wind Harmer
8.353
270499AE1-146 GEN
Solar/Wind Harmer
2.926
270505AE1-170 C O1
Solar/Wind Harmer
9.313
270007AE1-245 C
Solar/Wind Harmer
4.022
270541AE2-072 C
Solar/Wind Harmer
5.011
270024AE2-089 GEN
Solar/Wind Harmer
2.366
270043AE2-236 GEN
Solar/Wind Harmer
3.089
270063AE2-323 C
Solar/Wind Harmer
1.334
270536AF1-215 GEN2
Solar/Wind Harmer
2.387
270535AF1-215 GEN1
Solar/Wind Harmer
2.387
270055AF2-134 C O1
Solar/Wind Harmer
1.591
254303AC2-168 GEN
Solar/Wind Helper
0.093
203853AF1-134 C O1
Solar/Wind Helper
0.264
270578AF1-285 GEN2
Solar/Wind Harmer
0.264
270578AF1-285 GEN2
Solar/Wind Harmer
0.685
270391AF1-285 GEN3
Solar/Wind Harmer
0.264
270391AF1-285 GEN3
Solar/Wind Harmer
0.685
270361_3
Solar/Wind Harmer
10.624
270575GUS2 35KV
Solar/Wind Harmer
12.516
270526AF1-158 GEN
Solar/Wind Harmer
2.631
270462AD2-086
Solar/Wind Harmer
4.24
270485AE1-090_GEN
Solar/Wind Harmer
0.369
270071AF1-092 GEN
Solar/Wind Harmer
7.858
270044AE2-322 C
Solar/Wind Harmer
0.979
23917102WLORG-2
50/50
1.892
274751CRETE EC ;1U
Adder
2.532
274770LINCOLN ;1U
Adder
3.125
972211AH1-690 GEN
50/50
297.552
972235AH1-702 GEN1
Adder
1.208
972236AH1-702 GEN2
Adder
1.051
200917MEHOOPANY_G
Solar/Wind Helper
1.091
241966AE1-183 GEN
Solar/Wind Helper
0.16
24639705ELKHART HY
Adder
0.093
24642205MAYFLWER
Adder
0.384
247522W1-056 GEN
Solar/Wind Harmer
1.996
270491AE1-102 GEN2
Solar/Wind Harmer
0.868
274887GEN-1.85
Solar/Wind Harmer
2.688
939351AE1-166 GEN
Solar/Wind Harmer
2.963
942221AE2-234 GEN
Solar/Wind Harmer
0.373
942801AE2-298 GEN
Solar/Wind Harmer
1.019
942871AE2-306 GEN
Solar/Wind Harmer
0.514
943021AE2-325 GEN
Solar/Wind Harmer
2.309
944161AF1-084 GEN
Solar/Wind Harmer
1.419
944231AF1-091 GEN
Solar/Wind Harmer
2.791
945111AF1-176 GEN
Solar/Wind Harmer
11.092
945111AF1-176 GEN
Solar/Wind Harmer
3.515
945411AF1-206 GEN
Solar/Wind Harmer
9.015
945641AF1-229 GEN
Solar/Wind Harmer
4.044
946071AF1-272 GEN
Solar/Wind Helper
1.356
946381AF1-302 GEN
Solar/Wind Helper
0.136
959141AF2-205 GEN
Solar/Wind Harmer
3.076
959331AF2-224 GEN
Solar/Wind Harmer
5.975
959441AF2-235 GEN
Solar/Wind Helper
0.196
959471AF2-238 GEN
Solar/Wind Helper
0.26
960591AF2-350 GEN
Solar/Wind Harmer
5.042
960681AF2-359 GEN
Solar/Wind Harmer
2.098
960841AF2-375 GEN
Solar/Wind Harmer
4.677
960981AF2-389 GEN
Solar/Wind Harmer
0.936
961051AF2-396 GEN
Solar/Wind Harmer
9.992
961051AF2-396 GEN
Solar/Wind Harmer
4.648
961961AG1-039 GEN
Solar/Wind Harmer
1.964
961971AG1-040 GEN
Solar/Wind Helper
0.451
962101AG1-054 GEN
Solar/Wind Helper
0.402
962511AG1-100 GEN
Solar/Wind Helper
0.462
963791AG1-232 GEN
Solar/Wind Harmer
7.497
966831AG1-554 GEN
Solar/Wind Harmer
0.892
970031AG2-029 GEN
Solar/Wind Harmer
18.113
970065AG2-057 GEN
Solar/Wind Harmer
0.575
970179AG2-119 GEN
Solar/Wind Harmer
4.411
970217AG2-149 GEN
Solar/Wind Harmer
28.273
970245AG2-165 GEN
Solar/Wind Harmer
8.906
970321AG2-212 GEN
Solar/Wind Harmer
8.906
970349AG2-230 GEN
Solar/Wind Harmer
8.3
970373AG2-245 GEN
Solar/Wind Harmer
11.24
970513AG2-328 GEN
Solar/Wind Harmer
8.906
970515AG2-329 GEN
Solar/Wind Harmer
12.822
970517AG2-330 GEN
Solar/Wind Harmer
8.078
970611AG2-400 GEN
Solar/Wind Harmer
5.975
970707AG2-453 GEN
Solar/Wind Harmer
13.981
970817AG2-515 GEN
Solar/Wind Harmer
16.3
970833AG2-524 GEN
Solar/Wind Harmer
1.943
970833AG2-524 GEN
Solar/Wind Harmer
0.904
970905AG2-564 GEN
Solar/Wind Harmer
4.278
970941AG2-585 GEN
Solar/Wind Harmer
6.303
971201AH1-060 GEN
Solar/Wind Harmer
1.151
971231AH1-075 GEN
Solar/Wind Harmer
0.508
971347AH1-153 GEN
Solar/Wind Harmer
8.3
971549AH1-272 GEN
Solar/Wind Harmer
14.209
971567AH1-282 GEN
Solar/Wind Harmer
10.136
971605AH1-302 GEN
Solar/Wind Harmer
4.401
971617AH1-308 GEN
Solar/Wind Harmer
2.93
971677AH1-339 GEN
Solar/Wind Harmer
8.462
971769AH1-391 GEN
Solar/Wind Harmer
5.763
971771AH1-392 GEN
Solar/Wind Harmer
5.317
971917AH1-482 GEN
Solar/Wind Harmer
4.678
971989AH1-539 GEN
Solar/Wind Harmer
9.641
972037AH1-567 GEN1
Adder
0.093
972038AH1-567 GEN2
Adder
0.184
972181SS23-001
Solar/Wind Harmer
3.073
972207SS24-0001
Solar/Wind Harmer
11.112
972227AH1-698 GEN1
Adder
1.311
972228AH1-698 GEN2
Adder
1.862
972231SS25-0005
Solar/Wind Harmer
4.917
972253AH1-711 GEN
Adder
54.605
972259AH1-714 GEN
Adder
9.55
20398826ARMNA MT
Solar/Wind Helper
0.849
24441505OLIV SLR
Solar/Wind Harmer
0.077
270223U2-072_GEN1
Solar/Wind Harmer
1.12
270224U2-072_GEN2
Solar/Wind Harmer
1.12
270227U2-072_GEN3
Solar/Wind Harmer
1.12
270228U2-072_GEN4
Solar/Wind Harmer
1.12
270231U2-072_GEN5
Solar/Wind Harmer
1.12
270246TR4_N_V150
Solar/Wind Harmer
0.531
270247TR4_N_V136
Solar/Wind Harmer
0.531
276843GEN-1.7
Solar/Wind Harmer
0.289
940581AE2-045 GEN
Solar/Wind Harmer
5.147
941231AE2-117 GEN
Solar/Wind Helper
0.227
941421AE2-139 GEN
Solar/Wind Helper
1.203
941551AE2-152 GEN
Solar/Wind Harmer
2.266
957071AF2-004 GEN
50/50
15.205
957111AF2-005 GEN
Adder
1.324
957201AF2-014 GEN
Solar/Wind Harmer
3.029
957891AF2-083 GEN
Solar/Wind Harmer
2.088
958011AF2-095 GEN
Solar/Wind Harmer
7.261
958091AF2-103 GEN
Solar/Wind Harmer
0.109
958321AF2-126 GEN
Solar/Wind Harmer
1.707
958381AF2-132 GEN
Solar/Wind Harmer
4.687
958391AF2-133 GEN
Solar/Wind Harmer
4.646
964201AG1-281 GEN
Solar/Wind Helper
0.234
964391AG1-301 GEN
Solar/Wind Helper
0.226
964401AG1-302 GEN
Solar/Wind Harmer
4.687
964861AG1-349 GEN
Solar/Wind Harmer
4.054
965011AG1-365 GEN
Solar/Wind Harmer
5.975
965021AG1-366 GEN
Solar/Wind Harmer
1.39
965041AG1-368 GEN
Solar/Wind Harmer
6.263
965051AG1-369 GEN
Solar/Wind Harmer
3.117
965421AG1-410 GEN
Solar/Wind Harmer
19.836
965681AG1-436 GEN
Solar/Wind Harmer
6.942
965791AG1-447 GEN
Solar/Wind Harmer
3.552
966311AG1-500 GEN
50/50
177.624
966321AG1-501 GEN
Adder
1.655
972301AH1-735 GEN
Adder
7.456
970159AG2-109 GEN
Solar/Wind Harmer
3.924
971219AH1-069 GEN
Solar/Wind Harmer
0.907
971221AH1-070 GEN
Solar/Wind Harmer
0.907
274811UNIV PK N;7U
Adder
2.564
274812UNIV PK N;8U
Adder
2.564
274814UNIV PK N;0U
Adder
2.586
990142J1224
External Queue
13.827776908874512
990527J1329
External Queue
1.891624927520752
991177J1571 G
External Queue
16.072763442993164
991182J1586 G
External Queue
25.886547088623047
CBM West 1LTFEXP_CBM-W1->PJM
CBM
101.376
CBM West 2LTFEXP_CBM-W2->PJM
CBM
44.143
CBM South 1LTFEXP_CBM-S1->PJM
CBM
9.995
CBM South 2LTFEXP_CBM-S2->PJM
CBM
2.427
NYPJM->LTFIMP_NY
CLTF
2.552
LGEELTFEXP_LGEE->PJM
CLTF
2.281
WECLTFEXP_WEC->PJM
CLTF
1.831
CPLELTFEXP_CPLE->PJM
CLTF
0.342
TVALTFEXP_TVA->PJM
CLTF
2.517
MECLTFEXP_MEC->PJM
CLTF
7.157
LAGNLTFEXP_LAGN->PJM
CLTF
5.524
SIGELTFEXP_SIGE->PJM
CLTF
0.189
AG2-052LTFEXP_AG2-052->PJM
LTF
0.118
AH1-155LTFEXP_AH1-155->PJM
LTF
0.177
CONTINGENCY 'ATSI_P7-1_OEC-345-002_SRT-A'
 DISCONNECT BRANCH FROM BUS 238569 TO BUS 239725 CKT 1   /*02BEAVER     345.0 - 02LAKEAVE    345.0
 DISCONNECT BRANCH FROM BUS 238569 TO BUS 239725 CKT 2   /*02BEAVER     345.0 - 02LAKEAVE    345.0
END
CONTINGENCY 'ATSI_P2-3_OEC-345-002_SRT-A'
 DISCONNECT BRANCH FROM BUS 238569 TO BUS 238607 CKT 1   /*02BEAVER     345.0 - 02CARLIL     345.0
 DISCONNECT BRANCH FROM BUS 238569 TO BUS 239725 CKT 1   /*02BEAVER     345.0 - 02LAKEAVE    345.0
END
238569 to 238607 ckt 1
238569 to 239725 ckt 2

Winter Peak Analysis

The New Service Request AH1-069 was evaluated as a 17.0 MW (10.2 MW Capacity) injection in the ATSI area.

AH1-069 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 17.0 MW (17.0 MW under study).

Note: The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for single or N-1 contingencies and multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.

(No impacts were found for this analysis)

Light Load Analysis

The New Service Request AH1-069 was evaluated as a 17.0 MW injection

AH1-069 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 17.0 MW (17.0 MW under study).

Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.

(No impacts were found for this analysis)

Short Circuit Analysis

Short Circuit analysis is not performed as part of the Phase I System Impact Study. Short Circuit analysis will commence in the Phase II System Impact Study.

Stability Analysis

Stability Analysis is Not Required.

Reactive Power Analysis

Reactive Power Analysis was not performed. This project is responsible for meeting all applicable power factor requirements.

Steady-State Voltage Analysis

Steady State Voltage Analysis is Not Required.

New Service Request Dependencies

The New Service Requests below are listed in one or more dispatch for the overloads identified in this report. These projects contribute to the loading of the overloaded facilities identified in this report. The percent overload of a facility and cost allocation you may have towards a particular reinforcement could vary depending on the action of other projects. The status of each project at the time of the analysis is presented in the table. This list may change as other projects withdraw or modify their requests. This table is valid for load flow analyses only.

New Service Requests Dependencies
Project IDProject NameStatus
AB2-170East Lima-Marysville 345kVIn Service
AC1-111Aurora 138kVIn Service
AC1-167Mark Center 69kVUnder Construction
AC2-015Chatfield-Howard 138kVPartially in Service - Under Construction
AC2-044Maddox Creek 345kVSuspended
AC2-103Beaver-Davis Besse 345 kV IEngineering & Procurement
AC2-154Davis Creek 138kVEngineering & Procurement
AC2-168Clinton 23kVIn Service
AC2-195Galion-Roberts South 138 kVUnder Construction
AD1-100Loretto-Wilton 345 kV & Braidwood-Davis Creek 345 kVUnder Construction
AD1-101Continental 69 kVIn Service
AD1-106North Waldo-Wild Creek 138 kVSuspended
AD1-119Payne 69 kVIn Service
AD1-130Hardin Switch 345 kVIn Service
AD2-020Valley 138 kVEngineering & Procurement
AD2-047Davis Creek 138 kVSuspended
AD2-060Davis Creek 138kVEngineering & Procurement
AD2-079Capitol Ave 34.5kVIn Service
AD2-086Hardin Switch 345 kVIn Service
AD2-133Eagle Valley 115kVIn Service
AE1-079Maysville-Sharon 69 kVUnder Construction
AE1-090Hardin Switch 345 kVIn Service
AE1-091West Newton-Lynn 138 kVSuspended
AE1-102Maddox Creek 345 kVSuspended
AE1-146Ebersole #2-Fostoria Central 138 kVUnder Construction
AE1-166Loretto-Wilton 345 kV & Braidwood-Davis Creek 345 kVEngineering & Procurement
AE1-170Kenzie Creek-Colby 138 kVSuspended
AE1-183Maysville-McDowell 69 kVEngineering & Procurement
AE1-237Andover (Maysville) 69kV IUnder Construction
AE1-245Haviland 138 kVUnder Construction
AE2-045Olive-Reynolds 345 kVEngineering & Procurement
AE2-072East Leipsic-Richland 138 kVIn Service
AE2-089Pennville-Adams 138 kVEngineering & Procurement
AE2-113Farmers Valley-Ridgeway 115 kVUnder Construction
AE2-114Midland 23 kV IIn Service
AE2-115Midland 23 kV IIIn Service
AE2-117ABW Tap-Alexandria 46 kVSuspended
AE2-126Dubois-Curwensville 34.5 kVIn Service
AE2-129Philipsburg-Clarence 34.5 kVIn Service
AE2-131Philipsburg-Karthaus 34.5Under Construction
AE2-139East Towanda-Grover 230 kVEngineering & Procurement
AE2-152Loretto-Wilton 345 kV & Braidwood-Davis Creek 345 kVEngineering & Procurement
AE2-176Groton 138 kV SolarIn Service
AE2-181Snyder 69kVUnder Construction
AE2-224Bear Rock-Johnstown 230 kVIn Service
AE2-234Liberty Center-Buckeye Tap 69 kVEngineering & Procurement
AE2-236Columbia-Northeast 138 kVSuspended
AE2-262Moshannon-Milesburg 230 kVEngineering & Procurement
AE2-263Moshannon-Milesburg 230 kV IIEngineering & Procurement
AE2-282East Fayette 138 kVIn Service
AE2-285Maysville 69 kVEngineering & Procurement
AE2-298Cavett Switch - West Van Wert 69 kVEngineering & Procurement
AE2-306Gunn Road 345 kVUnder Construction
AE2-322Mark Center 69 kVUnder Construction
AE2-323Twin Branch-Guardian 138 kVUnder Construction
AE2-325Valley 138 kVActive
AE2-343Andover (Maysville) 69 kV IIUnder Construction
AF1-006Fairview East 34.5 kVIn Service
AF1-064Weston 69 kVUnder Construction
AF1-084Hartford-Almena 69 kVEngineering & Procurement
AF1-086Madera-Westover South 115 kVUnder Construction
AF1-091Varner - Sowers 138 kVEngineering & Procurement
AF1-092Huntington Jct. 138 kVSuspended
AF1-093Henderson-Stoneboro 69 kVEngineering & Procurement
AF1-094Union City-Cambridge Springs 34.5 kVEngineering & Procurement
AF1-098Four Mile Jct-Corry East 115 kVEngineering & Procurement
AF1-120East Fayette 2 138 kVIn Service
AF1-122Cardington-Liberty 69 kVSuspended
AF1-134Philipsburg-Madera 34.5 kVEngineering & Procurement
AF1-140Claysburg 23 kVEngineering & Procurement
AF1-153Motion-Ridgeway 46 kVSuspended
AF1-158Edison-Gravel Pit 138 kVIn Service
AF1-176Corey 138 kVActive
AF1-205Napoleon Muni 138 kVSuspended
AF1-206East Fayette 138 kVEngineering & Procurement
AF1-215Olive-Reynolds 345 kVIn Service
AF1-229Galion-South Berwick 345 kVEngineering & Procurement
AF1-272Lucerne 115 kVEngineering & Procurement
AF1-285Gunn Road 345 kVUnder Construction
AF1-302Brookville-Squab Hollow 138 kVEngineering & Procurement
AF2-004Beaver 345 kVEngineering & Procurement
AF2-005Beaver 138 kVEngineering & Procurement
AF2-014Maddox Creek 345 kVEngineering & Procurement
AF2-039Shawville-Clearfield 34.5 kVEngineering & Procurement
AF2-083Kenzie Creek-Stone Lake 69 kVUnder Construction
AF2-088Shawville-Clearfield 34.5 kV IIEngineering & Procurement
AF2-095Davis Creek 138 kVActive
AF2-103Haviland 138 kVIn Service
AF2-126Weston 69 kV IIActive
AF2-130Cobalt Corners 34.5 kVIn Service
AF2-132Reynolds-Olive #1 345 kVUnder Construction
AF2-133Reynolds-Olive #2 345 kVUnder Construction
AF2-134Olive-Reynolds #2 345 kVIn Service
AF2-150Galion 138 kVUnder Construction
AF2-205Olive-Reynolds #2 345 kVEngineering & Procurement
AF2-224Allen 345 kVEngineering & Procurement
AF2-235Titusville-Oil Creek 34.5 kVWithdrawn
AF2-238Mansfield-South Troy 34.5 kVEngineering & Procurement
AF2-350Kensington 138 kVActive
AF2-359Olive-University Park 345 kVEngineering & Procurement
AF2-375Ebersole-Fostoria 138 kVEngineering & Procurement
AF2-389Kenzie Creek-Stone Lake 69 kVWithdrawn
AF2-396Stinger 138 kVActive
AG1-039Galion 138 kV IIUnder Construction
AG1-040Morgan Street-Mount Hope 34.5 kVEngineering & Procurement
AG1-054Potter-Harlan 69 kVEngineering & Procurement
AG1-100Venango-Saegertown 34.5 kVEngineering & Procurement
AG1-193Utica Junction 34.5 kVSuspended
AG1-197Morgan Street-Cochranton 34.5 kVSuspended
AG1-198Union City 34.5 kVUnder Construction
AG1-232Magley 138 kVEngineering & Procurement
AG1-281Claysburg-HCR Tap 46 kVEngineering & Procurement
AG1-301Miller REC-Warrior Ridge 46 kVEngineering & Procurement
AG1-302Olive-Reynolds #1 345 kVUnder Construction
AG1-349Olive-Reynolds #2 345 kVEngineering & Procurement
AG1-365Allen 345 kVEngineering & Procurement
AG1-366Allen 345 kVEngineering & Procurement
AG1-368Tillman 138 kVEngineering & Procurement
AG1-369Logtown 138 kVEngineering & Procurement
AG1-386Smith-Francis Junction 25 kVIn Service
AG1-410Maddox Creek-RP Mone 345 kVActive
AG1-436Olive-University Park 345 kVActive
AG1-447Olive-University Park 345 kVActive
AG1-478Wilmington 34.5 kVEngineering & Procurement
AG1-500Beaver 345 kVEngineering & Procurement
AG1-501Beaver 138 kVEngineering & Procurement
AG1-554South Kenton 138 kVEngineering & Procurement
AG2-029Forest G. Hipple-Collingwood 345 kVActive
AG2-057Cardington-Liberty 69 kV IIActive
AG2-109Fitchville-New London 69 kVActive
AG2-119Galion-Roberts South 138 kV IIActive
AG2-149Galion-South Berwick 345 kVActive
AG2-165Dumont-Greentown 765 kVActive
AG2-212Dumont-Greentown 765 kVActive
AG2-230Dumont 345 kVActive
AG2-245Olive - Reynolds #1 345 kVActive
AG2-328Dumont - Greentown 765 kVActive
AG2-329S Berwick - Galion 345 kVActive
AG2-330Dumont - Greentown 765 kVActive
AG2-400Allen 345 kVActive
AG2-453Lasalle - Plano 345 kVActive
AG2-515Midway 345 kV IIIActive
AG2-524LaSalle Station - Mazon 138 kVActive
AG2-564Sulphur Springs 138 kVActive
AG2-585Kensington 138kVActive
AH1-060Cardington-Liberty 69 kV IIIActive
AH1-070Jerome – Mohicanville 69 kVActive
AH1-075North Waldo - Wild Creek 138 kVActive
AH1-153Dumont 345 kVActive
AH1-272Argenta - Twin Branch 345 kVActive
AH1-282Galion - Ohio Central 345 kVActive
AH1-302Olive - Reynolds 345 kVActive
AH1-308Pennville - Adams 138 kVActive
AH1-339West Crawford 69 kVActive
AH1-391Olive 138 kVActive
AH1-392Gravel Pit-Kankakee 138 kVActive
AH1-482Olive - Reynolds #2 345 kVActive
AH1-539South Kenton 138 kVActive
AH1-567University Park 138 kVActive
AH1-690Bay Shore - Lallendorf 345 kVActive
AH1-698Braidwood 345 kVActive
AH1-702Byron 345 kVActive
AH1-711Lemoyne 345 kVActive
AH1-714Lasalle 345 kVActive
AH1-735Richland 138 kVActive
U2-072East Lima-Marysville 345kVIn Service
V1-011Haviland 138kVIn Service
W1-056Ada-Dunkirk 69kVIn Service
X1-042WatervlietIn Service
X3-005Wildwood 12kVIn Service
Y3-023Country Side 12kVIn Service
Z2-116Twin Branch 12.47kVIn Service

Affected System - PJM Identified Violations

As part of PJM's analysis, PJM evaluated the potential impacts on tie line facilities between PJM and an affected system entity, which were identified per PJM planning analysis criteria. This upgrade may be required on the affected system portion of the tie line along with cost allocation of such upgrade if applicable, in coordination with the affected system. Depending on the affected system, this project may not be contingent on upgrade based on PJM planning analysis criteria, but may be contingent on this upgrade based on the Affected System Operator's planning criteria, provided in the Affected Systems Study Section, herein.

Midcontinent Independent System Operator, Inc. (MISO)No Impact
New York Independent System Operator (NYISO)No Impact
Tennessee Valley Authority (TVA)No Impact
Louisville Gas & Electric (LG&E)No Impact
Duke Energy Carolinas (DUKE)No Impact
Duke Energy Progress – East (CPLE)No Impact
Duke Energy Progress – West (CPLW)No Impact

Affected System - Non-PJM Identified Violations

In Phase I of the Cycle, PJM conducts an Affected System screen to identify any New Service Request with potential Affected System impacts. PJM initiates coordination with each Affected System Operator by providing a list of New Service Requests in the Cycle with potential impacts to their respective system. If the Affected System Operator indicates an Affected System Study is required, PJM will notify the Project Developer or Eligible Customer of the need for an Affected System Study. See below if any Affected System Operator requires a study for this project:

Midcontinent Independent System Operator, Inc. (MISO)Not required
New York Independent System Operator (NYISO)Not required
Tennessee Valley Authority (TVA)Not required
Louisville Gas & Electric (LG&E)Not required
Duke Energy Carolinas (DUKE)Not required
Duke Energy Progress – East (CPLE)Not required
Duke Energy Progress – West (CPLW)Not required

System Reinforcements

No cost allocated system reinforcements were identified for this project in the Phase I System Impact Study load flow analysis.

Shown below are the details of the cost allocated, contingent, eliminated, topology and potential aggregate contributor reinforcements for this project. Please refer to the System Reinforcement table above and the information below for more detail.


System Reinforcement
Type
Load Flow
TO
ATSI
RTEP ID / TO ID
(Pending) / TC2-ATSI-004.a
Title
Upgrade D120 and D125 disconnect switches at Beaver substation
Description
Upgrade D120 and D125 disconnect switches at Beaver substation
Total Cost ($USD)
$929,516
Allocated Cost ($USD)
$0
Time Estimate
22 Months

Potential Aggregate Contributor

Note: Based on PJM cost allocation criteria, AH1-069 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AH1-069 could receive cost allocation. Although AH1-069 may not presently have cost responsibility for this upgrade, AH1-069 is a potential Aggregate Pool Contributor.

FacilityContingency
02BEAVER-02CARLIL 345.0 kV Ckt 1 line(Any)

System Reinforcement
Type
Load Flow
TO
ATSI
RTEP ID / TO ID
(Pending) / TC2-ATSI-004.b
Title
Upgrade (1) 3000 SAC 169 line drop at Beaver
Description
Upgrade (1) 3000 SAC 169 line drop at Beaver
Total Cost ($USD)
$263,169
Allocated Cost ($USD)
$0
Time Estimate
12 Months

Potential Aggregate Contributor

Note: Based on PJM cost allocation criteria, AH1-069 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AH1-069 could receive cost allocation. Although AH1-069 may not presently have cost responsibility for this upgrade, AH1-069 is a potential Aggregate Pool Contributor.

FacilityContingency
02BEAVER-02CARLIL 345.0 kV Ckt 1 line(Any)

System Reinforcement
Type
Load Flow
TO
ATSI
RTEP ID / TO ID
(Pending) / TC2-ATSI-004.c
Title
Reconductor (possible rebuild) 18.22 miles of 954 ACSR 48/7 transmission line and (3) line drops at Beaver on the Beaver - Carlisle Ckt 1 345 kV
Description
Reconductor (possible rebuild) 18.22 miles of 954 ACSR 48/7 transmission line and (3) line drops at Beaver on the Beaver - Carlisle Ckt 1 345 kV using dual (2) 795 26/7 "Drake ACSS
Total Cost ($USD)
$109,211,408
Allocated Cost ($USD)
$0
Time Estimate
63 Months

Potential Aggregate Contributor

Note: Based on PJM cost allocation criteria, AH1-069 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AH1-069 could receive cost allocation. Although AH1-069 may not presently have cost responsibility for this upgrade, AH1-069 is a potential Aggregate Pool Contributor.

FacilityContingency
02BEAVER-02CARLIL 345.0 kV Ckt 1 line(Any)

System Reinforcement
Type
Load Flow
TO
ATSI
RTEP ID / TO ID
(Pending) / TC2-ATSI-004.d
Title
Upgrade (1) 3500 SAC 127 D120-to-B121 breaker lead at Beaver
Description
Upgrade (1) 3500 SAC 127 D120-to-B121 breaker lead at Beaver
Total Cost ($USD)
$265,209
Allocated Cost ($USD)
$0
Time Estimate
12 Months

Potential Aggregate Contributor

Note: Based on PJM cost allocation criteria, AH1-069 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AH1-069 could receive cost allocation. Although AH1-069 may not presently have cost responsibility for this upgrade, AH1-069 is a potential Aggregate Pool Contributor.

FacilityContingency
02BEAVER-02CARLIL 345.0 kV Ckt 1 line(Any)

System Reinforcement: n9227.0
Type
Load Flow
TO
ATSI
RTEP ID / TO ID
n9227.0 / TC1-ATSI-001.b
Title
Upgrade T-line drops, overhead substation conductor and TL reconductor
Description
Reconductor (possible rebuild) of 8.12 miles of dual transmission line and (2) single conductor line drops at Beaver on the Beaver-Lake Ave Ckt 2 345 kV line using triple (3) 1113 54/19 ""Finch"" ACSS"
Total Cost ($USD)
$48,873,856
Allocated Cost ($USD)
$0
Time Estimate
37 Months

Potential Aggregate Contributor

Note: Based on PJM cost allocation criteria, AH1-069 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AH1-069 could receive cost allocation. Although AH1-069 may not presently have cost responsibility for this upgrade, AH1-069 is a potential Aggregate Pool Contributor.

FacilityContingency
02BEAVER-02LAKEAVE 345.0 kV Ckt 2 line(Any)

System Reinforcement
Type
Load Flow
TO
ATSI
RTEP ID / TO ID
(Pending) / TC2-ATSI-021.a
Title
Upgrade (4) circuit breakers at Beaver and Lake Ave (B:3,4,216,219)
Description
Upgrade (4) circuit breakers at Beaver and Lake Ave (B:3,4,216,219)
Total Cost ($USD)
$7,786,809
Allocated Cost ($USD)
$0
Time Estimate
56 Months

Potential Aggregate Contributor

Note: Based on PJM cost allocation criteria, AH1-069 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AH1-069 could receive cost allocation. Although AH1-069 may not presently have cost responsibility for this upgrade, AH1-069 is a potential Aggregate Pool Contributor.

FacilityContingency
02BEAVER-02LAKEAVE 345.0 kV Ckt 2 line(Any)

System Reinforcement
Type
Load Flow
TO
ATSI
RTEP ID / TO ID
(Pending) / TC2-ATSI-021.b
Title
Upgrade 1590 AAC B3, B4, B216 and B219 breaker leads at Beaver and Lake Ave
Description
Upgrade 1590 AAC B3, B4, B216 and B219 breaker leads at Beaver and Lake Ave
Total Cost ($USD)
$305,540
Allocated Cost ($USD)
$0
Time Estimate
12 Months

Potential Aggregate Contributor

Note: Based on PJM cost allocation criteria, AH1-069 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AH1-069 could receive cost allocation. Although AH1-069 may not presently have cost responsibility for this upgrade, AH1-069 is a potential Aggregate Pool Contributor.

FacilityContingency
02BEAVER-02LAKEAVE 345.0 kV Ckt 2 line(Any)

System Reinforcement
Type
Load Flow
TO
ATSI
RTEP ID / TO ID
(Pending) / TC2-ATSI-021.c
Title
Upgrade the (3) B216, B219 and B4 1500 CTs
Description
Upgrade the (3) B216, B219 and B4 1500 CTs
Total Cost ($USD)
$853,850
Allocated Cost ($USD)
$0
Time Estimate
16 Months

Potential Aggregate Contributor

Note: Based on PJM cost allocation criteria, AH1-069 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AH1-069 could receive cost allocation. Although AH1-069 may not presently have cost responsibility for this upgrade, AH1-069 is a potential Aggregate Pool Contributor.

FacilityContingency
02BEAVER-02LAKEAVE 345.0 kV Ckt 2 line(Any)

System Reinforcement
Type
Load Flow
TO
ATSI
RTEP ID / TO ID
(Pending) / TC2-ATSI-021.d
Title
Upgrade (3) 1590 line drops at Beaver and Lake Ave
Description
Upgrade (3) 1590 line drops at Beaver and Lake Ave
Total Cost ($USD)
$690,685
Allocated Cost ($USD)
$0
Time Estimate
12 Months

Potential Aggregate Contributor

Note: Based on PJM cost allocation criteria, AH1-069 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AH1-069 could receive cost allocation. Although AH1-069 may not presently have cost responsibility for this upgrade, AH1-069 is a potential Aggregate Pool Contributor.

FacilityContingency
02BEAVER-02LAKEAVE 345.0 kV Ckt 2 line(Any)

System Reinforcement
Type
Load Flow
TO
ATSI
RTEP ID / TO ID
(Pending) / TC2-ATSI-021.e
Title
Upgrade the (1) B219 1200 CT to PVD at Beaver
Description
Upgrade the (1) B219 1200 CT to PVD at Beaver
Total Cost ($USD)
$349,952
Allocated Cost ($USD)
$0
Time Estimate
16 Months

Potential Aggregate Contributor

Note: Based on PJM cost allocation criteria, AH1-069 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AH1-069 could receive cost allocation. Although AH1-069 may not presently have cost responsibility for this upgrade, AH1-069 is a potential Aggregate Pool Contributor.

FacilityContingency
02BEAVER-02LAKEAVE 345.0 kV Ckt 2 line(Any)

System Reinforcement
Type
Load Flow
TO
ATSI
RTEP ID / TO ID
(Pending) / TC2-ATSI-021.f
Title
Upgrade the (1) B216 relay thermal at Beaver
Description
Upgrade the (1) B216 relay thermal at Beaver
Total Cost ($USD)
$509,895
Allocated Cost ($USD)
$0
Time Estimate
18 Months

Potential Aggregate Contributor

Note: Based on PJM cost allocation criteria, AH1-069 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AH1-069 could receive cost allocation. Although AH1-069 may not presently have cost responsibility for this upgrade, AH1-069 is a potential Aggregate Pool Contributor.

FacilityContingency
02BEAVER-02LAKEAVE 345.0 kV Ckt 2 line(Any)

System Reinforcement
Type
Load Flow
TO
ATSI
RTEP ID / TO ID
(Pending) / TC2-ATSI-021.g
Title
Upgrade (1) 4.00 SPS.AL PIPE at Beaver
Description
Upgrade (1) 4.00 SPS.AL PIPE at Beaver
Total Cost ($USD)
$178,089
Allocated Cost ($USD)
$0
Time Estimate
12 Months

Potential Aggregate Contributor

Note: Based on PJM cost allocation criteria, AH1-069 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AH1-069 could receive cost allocation. Although AH1-069 may not presently have cost responsibility for this upgrade, AH1-069 is a potential Aggregate Pool Contributor.

FacilityContingency
02BEAVER-02LAKEAVE 345.0 kV Ckt 2 line(Any)

System Reinforcement
Type
Load Flow
TO
ATSI
RTEP ID / TO ID
(Pending) / TC2-ATSI-021.h
Title
Upgrade (9) disconnect switches at Beaver and Lake Ave (D: 19,20,21,22, 212,215,217,218,220)
Description
Upgrade (9) disconnect switches at Beaver and Lake Ave (D: 19,20,21,22, 212,215,217,218,220)
Total Cost ($USD)
$3,850,794
Allocated Cost ($USD)
$0
Time Estimate
39 Months

Potential Aggregate Contributor

Note: Based on PJM cost allocation criteria, AH1-069 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AH1-069 could receive cost allocation. Although AH1-069 may not presently have cost responsibility for this upgrade, AH1-069 is a potential Aggregate Pool Contributor.

FacilityContingency
02BEAVER-02LAKEAVE 345.0 kV Ckt 2 line(Any)

System Reinforcement
Type
Load Flow
TO
ATSI
RTEP ID / TO ID
(Pending) / TC2-ATSI-021.i
Title
Upgrade the (2) B3 SEL411L impedance relays at Lake Ave
Description
Upgrade the (2) B3 SEL411L impedance relays at Lake Ave
Total Cost ($USD)
$509,895
Allocated Cost ($USD)
$0
Time Estimate
18 Months

Potential Aggregate Contributor

Note: Based on PJM cost allocation criteria, AH1-069 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AH1-069 could receive cost allocation. Although AH1-069 may not presently have cost responsibility for this upgrade, AH1-069 is a potential Aggregate Pool Contributor.

FacilityContingency
02BEAVER-02LAKEAVE 345.0 kV Ckt 2 line(Any)

System Reinforcement
Type
Load Flow
TO
ATSI
RTEP ID / TO ID
(Pending) / TC2-ATSI-021.j
Title
Upgrade (2) 2.50 SPS.AL PIPE SCCIR at Beaver
Description
Upgrade (2) 2.50 SPS.AL PIPE SCCIR at Beaver
Total Cost ($USD)
$173,391
Allocated Cost ($USD)
$0
Time Estimate
12 Months

Potential Aggregate Contributor

Note: Based on PJM cost allocation criteria, AH1-069 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AH1-069 could receive cost allocation. Although AH1-069 may not presently have cost responsibility for this upgrade, AH1-069 is a potential Aggregate Pool Contributor.

FacilityContingency
02BEAVER-02LAKEAVE 345.0 kV Ckt 2 line(Any)

System Reinforcement
Type
Load Flow
TO
ATSI
RTEP ID / TO ID
(Pending) / TC2-ATSI-021.k
Title
Upgrade the (15) B216, B219, B3 and B4 2000 CTs at Beaver and Lake Ave
Description
Upgrade the (15) B216, B219, B3 and B4 2000 CTs at Beaver and Lake Ave
Total Cost ($USD)
$2,701,212
Allocated Cost ($USD)
$0
Time Estimate
17 Months

Potential Aggregate Contributor

Note: Based on PJM cost allocation criteria, AH1-069 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AH1-069 could receive cost allocation. Although AH1-069 may not presently have cost responsibility for this upgrade, AH1-069 is a potential Aggregate Pool Contributor.

FacilityContingency
02BEAVER-02LAKEAVE 345.0 kV Ckt 2 line(Any)

System Reinforcement
Type
Load Flow
TO
ATSI
RTEP ID / TO ID
(Pending) / TC2-ATSI-021.l
Title
Upgrade the (2) B216 SEL411L impedance relays at Lake Ave
Description
Upgrade the (2) B216 SEL411L impedance relays at Lake Ave
Total Cost ($USD)
$509,895
Allocated Cost ($USD)
$0
Time Estimate
18 Months

Potential Aggregate Contributor

Note: Based on PJM cost allocation criteria, AH1-069 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AH1-069 could receive cost allocation. Although AH1-069 may not presently have cost responsibility for this upgrade, AH1-069 is a potential Aggregate Pool Contributor.

FacilityContingency
02BEAVER-02LAKEAVE 345.0 kV Ckt 2 line(Any)

System Reinforcement
Type
Load Flow
TO
ATSI
RTEP ID / TO ID
(Pending) / TC2-ATSI-021.m
Title
Upgrade (8) 5.00 SPS.AL PIPE SCCIR at Beaver
Description
Upgrade (8) 5.00 SPS.AL PIPE SCCIR at Beaver
Total Cost ($USD)
$250,039
Allocated Cost ($USD)
$0
Time Estimate
12 Months

Potential Aggregate Contributor

Note: Based on PJM cost allocation criteria, AH1-069 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AH1-069 could receive cost allocation. Although AH1-069 may not presently have cost responsibility for this upgrade, AH1-069 is a potential Aggregate Pool Contributor.

FacilityContingency
02BEAVER-02LAKEAVE 345.0 kV Ckt 2 line(Any)

Attachments

AH1-069 One Line Diagram

AH1-069 One Line Diagram.pdf
The state in which the generator or merchant transmission facility is located.
The Transmission Owner of the facility where the New Service Request project interconnects to the transmission system.
Winter load flow analysis will be performed starting in Transition Cycle 2.