AH1-690 Phase I Study Report
v1.00 released 2025-10-29 21:50
Bay Shore - Lallendorf 345 kV
1440.0 MW Capacity / 1475.0 MW Energy
Introduction
This Phase I System Impact Study Report (PH1) has been prepared in accordance with the PJM Open Access Transmission Tariff, Part VII, Subpart D, sections 307 and 308 for New Service Requests (projects) in Transition Cycle 2. The Project Developer/Eligible Customer (developer) is CPV Oregon, LLC, and the Transmission Provider (TP) is PJM Interconnection, LLC (PJM). The interconnected Transmission Owner (TO) is American Transmission Systems, Incorporated.
Preface
The Phase I System Impact Study is conducted on an aggregate basis within a New Services Request’s Cycle, and results are provided in both (i) a single Cycle executive summary format and (ii) an individual project-level basis. The Phase I System Impact Study Results (for both the executive summary and individual reports) will be publicly available on PJM’s website. Developers must obtain the results from the website.
In accordance with PJM Manual 14H, section 4.3, PJM takes the following actions during the Phase I System Impact Study:
- PJM studies each New Service Request on a summer peak, winter peak and light load RTEP base case study. The case year is dependent on the new services cycle under study. PJM will identify the base case year to be used in the study of a specific cycle on its website.
- PJM will only perform load flow analysis during the Phase I System Impact Study.
- In Phase I of the Cycle, PJM conducts an Affected System screen to identify any New Service Request with Affected System impacts and provides each Affected System Operator with a list of New Service Request in the Cycle with potential impacts to their respective system.
- PJM will create both the short circuit and stability base cases to be used in the Phase II System Impact Study.
- The Phase I System Impact Study results will be publicly available on PJM’s website. Project Developers and Eligible Customers must obtain the results from the website.
The Transmission Owner takes the following actions during the Phase I System Impact Study:
- Identify required Interconnection Facilities to accommodate the New Service Request.
- Identify required Network Upgrades to mitigate system violations from the Phase I System Impact Study.
- Provide planning-level preliminary estimates of Interconnection Facilities and Network Upgrades including scope, cost and elapsed time to complete the work.
Decision Point I Requirements
At the close of Phase I System Impact Study, PJM will initiate Decision Point I (DP1). During DP1, the Project Developer will have 30 days to decide whether to proceed with their project. If the Project Developer elects to proceed, they should provide the elements defined in the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 309.A.1. Additional information on these elements is available in PJM Manual 14H sections 4.4, 6, and 7.
Allowable project modifications at Decision Point I are defined in PJM Open Access Transmission Tariff, Part VII, Subpart D, section 309.B. Additional information regarding allowable project modifications can be found in PJM Manual 14H, section 9.8.
General
The Project Developer has proposed a Natural Gas generating facility located in the American Transmission Systems, Incorporated zone — Lucas County, Ohio. The installed facilities will have a total capability of 1475.0 MW with 1440.0 MW of this output being recognized by PJM as Capacity.Project Information
Physical Interconnection Facility Study
Physical Interconnection Facilities Study is not performed as part of the Phase I System Impact Study. Physical Interconnection Facilities Study will commence in the Phase II System Impact Study.
Point of Interconnection
AH1-690 will interconnect on the American Transmission Systems, Incorporated transmission system by tapping the BayShore - Lallendorf 345 kV 1 and 2 lines.
Cost Summary
The table below shows a summary of the total cost estimates for this New Service Request project. In the Phase I SIS, the costs shown are subject to change as a result of a facility study performed by the TO during the Phase II or Phase III System Impact Study.
Based on the Phase I SIS results, the AH1-690 project has the following allocation of costs for interconnection. The cost contribution towards Readiness Deposit are also shown below.
| Cost Summary | |||
|---|---|---|---|
| Description | Cost Allocated to AH1-690 | Cost Subject to Readiness* | |
| Transmission Owner Interconnection Facilities (TOIF) | $843,231 | $0 | |
| Other Scope | $60,800 | $0 | |
| Option To Build Oversight | $0 | $0 | |
| Physical Interconnection Network Upgrades | |||
| Stand Alone Network Upgrades | $32,872,665 | $32,872,665 | |
| Network Upgrades | $7,999,870 | $7,999,870 | |
| System Reliability Network Upgrades | |||
| Steady State Thermal & Voltage (SP & LL) | $1,232,419,113 | $1,232,419,113 | |
| Transient Stability | $0 | $0 | |
| Short Circuit | $0 | $0 | |
| Transmission Owner Analysis | |||
| SubRegional | $17,528,776 | $17,528,776 | |
| Distribution | $3,936,000 | $0 | |
| Affected System Reinforcements | |||
| AFS - PJM Violatons | $0 | $0 | |
| AFS - Non-PJM Violations | $0 | $0 | |
| Total | $1,295,660,455 | $1,290,820,424 | |
* Contributes to calculation for Readiness Deposit #2 (RD2). See Readiness Deposit section of report for additional detail.
Definitions
Transmission Owner Interconnection Facilities: Facilities that are owned, controlled, operated and maintained by the Transmission Owner on the Transmission Owner’s side of the Point of Change of Ownership to the Point of Interconnection, including any modifications, additions or upgrades made to such facilities and equipment, that are necessary to physically and electrically interconnect the Generating Facility with the Transmission System or interconnected distribution facilities.
Stand Alone Network Upgrades: Network Upgrades, which are not part of an Affected System, which a Project Developer may construct without affecting day-to-day operations (e.g. taking a transmission outage) of the Transmission System during their construction.
Network Upgrades: Modifications or additions to transmission-related facilities that are integrated with and support the Transmission Provider’s overall Transmission System for the general benefit of all users of such Transmission System. Network Upgrades have no impact or potential impact on the Transmission System until the final tie-in is complete.
Notes
Note 1: PJM Open Access Transmission Tariff (OATT), Part VII, Subpart D, section 307.5 outlines cost allocation rules. The rules are further clarified in PJM Manual 14H, section 4.2.6. PJM shall identify the New Service Requests in the Cycle contributing to the need for the required Network Upgrades within the Cycle. All New Service Requests that contribute to the need for a Network Upgrade will receive cost allocation for that upgrade pursuant to each New Service Request’s contribution to the reliability violation identified on the transmission system in accordance with PJM Manuals.
Note 2: There will be no inter-Cycle cost allocation for Interconnection Facilities or Network Upgrades identified in the System Impact Study costs identified in a Cycle; all such costs shall be allocated to New Service Requests in that Cycle.
Note 3: For Project Developers with System Reinforcements listed: If this project presents cost allocation to a System Reinforcement indicates $0, then please be aware that as changes to the interconnection process occur, such as other projects withdrawing, reducing in size, etc, the cost responsibilities can change and a cost allocation may be assigned to this project. In addition, although this project presents cost allocation to a System Reinforcement is presently $0, this project may need this system reinforcement completed to be deliverable to the PJM system. If this project desires to come into service prior to completion of the system reinforcement, the Project Developer will need to request PJM to perform an interim deliverability study to determine if they would be deliverable for all or a portion of their output for each delivery year until the system reinforcement is complete.
Readiness Deposit
Per Tariff Part VII, Subpart D, section 309 (Decision Point I) A.1.a.i and PJM Manual 14H, section 6.2, Readiness Deposit #2 (RD2) are funds committed by the Project Developer or Eligible Customer based upon the applicable contribution to Network Upgrades as defined below. Readiness Deposits are not used to fund studies nor to offset Security.
During Decision Point I (DP1), the Project Developer or Eligible Customer is required to submit Readiness Deposit #2, which is calculated as 10% of cost allocation for required Phase I Network Upgrades minus Readiness Deposit #1.
Note 1: “Network Upgrades” referred to in the calculation include both (i) the Physical Interconnection Network Upgrades and (ii) the System Reliability Network Upgrades as shown in the Cost Summary table.
Note 2: Readiness Deposit #1 (RD1) = ($4,000 * Project Size (MW))
Note 3: Readiness Deposit #2 (RD2) = 10% of cost allocation for required Network Upgrades minus RD1. Readiness Deposit #2 (RD2) can be zero, but may not be a negative number.
Readiness Deposit #2 Due for Project AH1-690
Readiness Deposit #2 has been calculated for the project based on the Phase I System Impact Study results and is shown in the table below. This Readiness Deposit #2 must be provided at Decision Point I through either a wire transfer or letter of credit per Manual 14H, Section 6.2.
| Readiness Deposit | |||
|---|---|---|---|
| Project ID | 10% of cost allocation for Phase I Network Upgrades | Readiness Deposit #1 Received (RD1) | Readiness Deposit #2 (RD2) for AH1-690 Project due at DP1 |
| A | B | A - B | |
| AH1-690 | $129,082,042 | $5,900,000 | $123,182,042 |
Note: Failure to provide an acceptable form of Readiness Deposit #2 by the end of Decision Point I will result in withdrawal and termination of the New Service Request.
For additional detail regarding Readiness Deposit Refunds, reference PJM Manual 14H, section 6.2.1. The Readiness Deposit Letter of Credit template can be found here.
Transmission Owner Scope of Work
The total preliminary cost estimate for the Transmission Owner scope of work (including TOIF and Physical Interconnection Network Upgrades) is given in the table below. These costs do not include CIAC Tax Gross-up.
| Transmission Owner Interconnection Facilities | |||
|---|---|---|---|
| RTEP ID | Description | Total Cost ($USD) | Allocated Cost ($USD) |
| (Pending) | Integrate Interconnection Facilities protection and controls to the Transmission Owner system. | $63,840 | $63,840 |
| (Pending) | Construction of (1) span of conductor between the new Interconnection substation takeoff structure and Developer owned dead end structure. | $779,391 | $779,391 |
| Stand-Alone Network Upgrades | |||
|---|---|---|---|
| RTEP ID | Description | Total Cost ($USD) | Allocated Cost ($USD) |
| (Pending) | Construct a new 345 kV 5-breaker ring bus Interconnection substation. | $32,796,665 | $32,796,665 |
| (Pending) | ADSS fiber to new interconnection substation. | $76,000 | $76,000 |
| Network Upgrades | |||
|---|---|---|---|
| RTEP ID | Description | Total Cost ($USD) | Allocated Cost ($USD) |
| (Pending) | Cut the existing Bayshore-Lallendorf No.1 345kV line and Loop in the new Interconnection substation. | $3,946,735 | $3,946,735 |
| (Pending) | Revise relay settings at Bayshore substation as required. | $53,200 | $53,200 |
| (Pending) | Revise relay settings at Lallendorf substation as required. | $53,200 | $53,200 |
| (Pending) | Cut the existing Bayshore-Lallendorf No.1 345kV line and loop in the new interconnection substation. | $3,946,735 | $3,946,735 |
| Physical Interconnection | |||
|---|---|---|---|
| RTEP ID | Description | Total Cost ($USD) | Allocated Cost ($USD) |
| (Pending) | Install 345 kV revenue metering within new Interconnection substation. | $60,800 | $60,800 |
Based on the scope of work for the Interconnection Facilities, it is expected to take 55 month(s) after the signing of a Generator Interconnection Agreement (as this is a FERC connection) and construction kickoff call to complete the installation of the physical connection work. This assumes that there will be no environmental issues with any of the new properties associated with this project, that there will be no delays in acquiring the necessary permits for implementing the defined interconnection work, and that all system outages will be allowed when requested.
The schedule for any required Network Impact Reinforcements will be more clearly identified in the Phase II and Phase III System Impact Studies.
Transmission Owner Analysis
The Transmission Owner identified network impacts to Distribution facilities as follows:
| Overloaded Element | Contingency | Rating [MVA] | Final Cycle Loading % | Contribution [MW] |
|---|---|---|---|---|
| 245749 05FNDCTREQ 1.0 - 245747 05FINDLAY C 34.5 CKT 1 | AEP_P7-1_#17590___SRT-A CONTINGENCY 'AEP_P7-1_#17590___SRT-A' OPEN BRANCH FROM BUS 288663 TO BUS 288672 CKT 1 / 288663 05FIN DATAZ 138 288672 05N.FINDLAY2 138 1 OPEN BRANCH FROM BUS 288663 TO BUS 288664 CKT Z / 288663 05FIN DATAZ 138 288664 05FIN DATA 138 Z OPEN BRANCH FROM BUS 247172 TO BUS 288663 CKT 1 / 247172 05EBERSO 138 288663 05FIN DATAZ 138 1 OPEN BRANCH FROM BUS 247172 TO BUS 247893 CKT 1 / 247172 05EBERSO 138 247893 05FLAG CITY 138 1 OPEN BRANCH FROM BUS 243057 TO BUS 247893 CKT 1 / 243057 05NEW LIBR1 138 247893 05FLAG CITY 138 1 END | 45.0 | 111.45 % | 7.02 |
The Transmission Owner identified network impacts to Sub-Regional facilities as follows:
| Overloaded Element | Contingency | Rating [MVA] | Final Cycle Loading % | Contribution [MW] |
|---|---|---|---|---|
| 239713 02NOVA 69.0 - 239167 02WELLNG 69.0 CKT 1 | ATSI_P1-2_OEC-345-809_SRT-A | 33.0 | 159.11 % | 7.44 |
| 240865 02GRNSPR 69.0 - 240851 02CLYDE 69.0 CKT 0 | ATSI_P1-2_OEC-345-810_SRT-A | 58.0 | 101.57 % | 5.99 |
| 245715 05U SANDSK 69.0 - 247379 05NEVADA SS 69.0 CKT 1 | ATSI_P7-1_TE-345-027A_SRT-A CONTINGENCY 'ATSI_P7-1_TE-345-027A_SRT-A' /* DB - AD1-103 & DB - HAYES 345 DISCONNECT BRANCH FROM BUS 238654 TO BUS 241877 CKT 1 /* 02DAV-BE 345 AD1-103 345 DISCONNECT BRANCH FROM BUS 238654 TO BUS 239289 CKT 1 /* 02DAV-BE 345 02HAYES 345 END | 31.0 | 120.02 % | 2.31 |
| 245715 05U SANDSK 69.0 - 247379 05NEVADA SS 69.0 CKT 1 | AEP_P4_#13372_05N WALDO 69.0_A_SRT-A CONTINGENCY 'AEP_P4_#13372_05N WALDO 69.0_A_SRT-A' OPEN BRANCH FROM BUS 242963 TO BUS 243011 CKT 1 / 242963 05HEDDSS 138 243011 05FULTON 138 1 OPEN BRANCH FROM BUS 242963 TO BUS 243153 CKT 1 / 242963 05HEDDSS 138 243153 05WMTVER 138 1 OPEN BRANCH FROM BUS 242963 TO BUS 245540 CKT 1 / 242963 05HEDDSS 138 245540 05BLOOMFLD8 138 1 REMOVE LOAD D1 FROM BUS 243011 / 243011 05FULTON 138 D1 REMOVE LOAD T1 FROM BUS 245540 / 245540 05BLOOMFLD8 138 T1 OPEN BRANCH FROM BUS 243011 TO BUS 243148 CKT 1 / 243011 05FULTON 138 243148 05WINDFL 138 1 OPEN BRANCH FROM BUS 243048 TO BUS 243148 CKT 1 / 243048 05N WALD 138 243148 05WINDFL 138 1 REMOVE LOAD T1 FROM BUS 243148 / 243148 05WINDFL 138 T1 OPEN BRANCH FROM BUS 243048 TO BUS 270372 CKT 1 / 243048 05N WALD 138 270372 AD1-106 TAP 138 1 OPEN BRANCH FROM BUS 243048 TO BUS 245708 CKT 1 / 243048 05N WALD 138 245708 05N WALDO 69.0 1 OPEN BRANCH FROM BUS 245708 TO BUS 245716 CKT 1 / 245708 05N WALDO 69.0 245716 05WALDO 69.0 1 REMOVE LOAD D1 FROM BUS 245716 / 245716 05WALDO 69.0 D1 REMOVE SWSHUNT FROM BUS 245716 / 245716 05WALDO 69.0 OPEN BRANCH FROM BUS 245716 TO BUS 247032 CKT 1 / 245716 05WALDO 69.0 247032 05UNCAPHSS 69.0 1 REMOVE LOAD D1 FROM BUS 247032 / 247032 05UNCAPHSS 69.0 D1 OPEN BRANCH FROM BUS 245711 TO BUS 247032 CKT 1 / 245711 05S MORRAL 69.0 247032 05UNCAPHSS 69.0 1 /* OPEN BRANCH FROM BUS 972046 TO BUS 247032 CKT 1 / 972046 AH1-572 TP 69.0 247032 05UNCAPHSS 69.0 1 /* Withdrawn REMOVE LOAD D1 FROM BUS 245711 / 245711 05S MORRAL 69.0 D1 OPEN BRANCH FROM BUS 245710 TO BUS 245711 CKT 1 / 245710 05RIDGEDALEZ69.0 245711 05S MORRAL 69.0 1 OPEN BRANCH FROM BUS 245710 TO BUS 290079 CKT Z1 / 245710 05RIDGEDALEZ69.0 290079 05GOODNOW SS69.0 Z1 OPEN BRANCH FROM BUS 245391 TO BUS 245710 CKT 1 / 245391 05RIDGEDALE869.0 245710 05RIDGEDALEZ69.0 1 OPEN BRANCH FROM BUS 245699 TO BUS 290079 CKT 1 / 245699 05HARPSTER P69.0 290079 05GOODNOW SS69.0 1 REMOVE LOAD T1 FROM BUS 245391 / 245391 05RIDGEDALE869.0 T1 REMOVE LOAD C1 FROM BUS 245699 / 245699 05HARPSTER P69.0 C1 OPEN BRANCH FROM BUS 245699 TO BUS 245701 CKT 1 / 245699 05HARPSTER P69.0 245701 05HARPSTER 69.0 1 END | 31.0 | 119.56 % | 1.84 |
| 245715 05U SANDSK 69.0 - 247379 05NEVADA SS 69.0 CKT 1 | AEP_P2-2_#14773_05N WALDO 69.0_1_SRT-A CONTINGENCY 'AEP_P2-2_#14773_05N WALDO 69.0_1_SRT-A' /Waldo - La Rue line tapped by AD1-106 & AG2-595 OPEN BRANCH FROM BUS 243048 TO BUS 245708 CKT 1 / 243048 05N WALD 138 245708 05N WALDO 69.0 1 OPEN BRANCH FROM BUS 245708 TO BUS 245716 CKT 1 / 245708 05N WALDO 69.0 245716 05WALDO 69.0 1 OPEN BRANCH FROM BUS 243048 TO BUS 270372 CKT 1 / 243048 05N WALD 138 270372 AD1-106 TAP 138 1 OPEN BRANCH FROM BUS 243048 TO BUS 243148 CKT 1 / 243048 05N WALD 138 243148 05WINDFL 138 1 OPEN BRANCH FROM BUS 243011 TO BUS 243148 CKT 1 / 243011 05FULTON 138 243148 05WINDFL 138 1 OPEN BRANCH FROM BUS 242963 TO BUS 243011 CKT 1 / 242963 05HEDDSS 138 243011 05FULTON 138 1 OPEN BRANCH FROM BUS 242963 TO BUS 245540 CKT 1 / 242963 05HEDDSS 138 245540 05BLOOMFLD8 138 1 OPEN BRANCH FROM BUS 242963 TO BUS 243153 CKT 1 / 242963 05HEDDSS 138 243153 05WMTVER 138 1 REMOVE LOAD D2 FROM BUS 245708 / 245708 05N WALDO 69.0 D2 END | 31.0 | 114.3 % | 1.84 |
| 245715 05U SANDSK 69.0 - 247379 05NEVADA SS 69.0 CKT 1 | AEP_P2-2_#17157_05E.TIFFIN 69.0_1_SRT-A CONTINGENCY 'AEP_P2-2_#17157_05E.TIFFIN 69.0_1_SRT-A' OPEN BRANCH FROM BUS 243032 TO BUS 245630 CKT 1 / 243032 05E.TIFFIN 69.0 245630 05S TIFFIN 69.0 1 OPEN BRANCH FROM BUS 243032 TO BUS 290149 CKT 1 / 243032 05E.TIFFIN 69.0 290149 05MOUSEY SS 69.0 1 REMOVE LOAD D1 FROM BUS 243032 / 243032 05E.TIFFIN 69.0 D1 END | 31.0 | 109.62 % | 1.56 |
| 247379 05NEVADA SS 69.0 - 245687 05BROK SWR 69.0 CKT 1 | ATSI_P7-1_TE-345-027A_SRT-A CONTINGENCY 'ATSI_P7-1_TE-345-027A_SRT-A' /* DB - AD1-103 & DB - HAYES 345 DISCONNECT BRANCH FROM BUS 238654 TO BUS 241877 CKT 1 /* 02DAV-BE 345 AD1-103 345 DISCONNECT BRANCH FROM BUS 238654 TO BUS 239289 CKT 1 /* 02DAV-BE 345 02HAYES 345 END | 31.0 | 115.85 % | 2.31 |
| 247379 05NEVADA SS 69.0 - 245687 05BROK SWR 69.0 CKT 1 | AEP_P4_#13372_05N WALDO 69.0_A_SRT-A CONTINGENCY 'AEP_P4_#13372_05N WALDO 69.0_A_SRT-A' OPEN BRANCH FROM BUS 242963 TO BUS 243011 CKT 1 / 242963 05HEDDSS 138 243011 05FULTON 138 1 OPEN BRANCH FROM BUS 242963 TO BUS 243153 CKT 1 / 242963 05HEDDSS 138 243153 05WMTVER 138 1 OPEN BRANCH FROM BUS 242963 TO BUS 245540 CKT 1 / 242963 05HEDDSS 138 245540 05BLOOMFLD8 138 1 REMOVE LOAD D1 FROM BUS 243011 / 243011 05FULTON 138 D1 REMOVE LOAD T1 FROM BUS 245540 / 245540 05BLOOMFLD8 138 T1 OPEN BRANCH FROM BUS 243011 TO BUS 243148 CKT 1 / 243011 05FULTON 138 243148 05WINDFL 138 1 OPEN BRANCH FROM BUS 243048 TO BUS 243148 CKT 1 / 243048 05N WALD 138 243148 05WINDFL 138 1 REMOVE LOAD T1 FROM BUS 243148 / 243148 05WINDFL 138 T1 OPEN BRANCH FROM BUS 243048 TO BUS 270372 CKT 1 / 243048 05N WALD 138 270372 AD1-106 TAP 138 1 OPEN BRANCH FROM BUS 243048 TO BUS 245708 CKT 1 / 243048 05N WALD 138 245708 05N WALDO 69.0 1 OPEN BRANCH FROM BUS 245708 TO BUS 245716 CKT 1 / 245708 05N WALDO 69.0 245716 05WALDO 69.0 1 REMOVE LOAD D1 FROM BUS 245716 / 245716 05WALDO 69.0 D1 REMOVE SWSHUNT FROM BUS 245716 / 245716 05WALDO 69.0 OPEN BRANCH FROM BUS 245716 TO BUS 247032 CKT 1 / 245716 05WALDO 69.0 247032 05UNCAPHSS 69.0 1 REMOVE LOAD D1 FROM BUS 247032 / 247032 05UNCAPHSS 69.0 D1 OPEN BRANCH FROM BUS 245711 TO BUS 247032 CKT 1 / 245711 05S MORRAL 69.0 247032 05UNCAPHSS 69.0 1 /* OPEN BRANCH FROM BUS 972046 TO BUS 247032 CKT 1 / 972046 AH1-572 TP 69.0 247032 05UNCAPHSS 69.0 1 /* Withdrawn REMOVE LOAD D1 FROM BUS 245711 / 245711 05S MORRAL 69.0 D1 OPEN BRANCH FROM BUS 245710 TO BUS 245711 CKT 1 / 245710 05RIDGEDALEZ69.0 245711 05S MORRAL 69.0 1 OPEN BRANCH FROM BUS 245710 TO BUS 290079 CKT Z1 / 245710 05RIDGEDALEZ69.0 290079 05GOODNOW SS69.0 Z1 OPEN BRANCH FROM BUS 245391 TO BUS 245710 CKT 1 / 245391 05RIDGEDALE869.0 245710 05RIDGEDALEZ69.0 1 OPEN BRANCH FROM BUS 245699 TO BUS 290079 CKT 1 / 245699 05HARPSTER P69.0 290079 05GOODNOW SS69.0 1 REMOVE LOAD T1 FROM BUS 245391 / 245391 05RIDGEDALE869.0 T1 REMOVE LOAD C1 FROM BUS 245699 / 245699 05HARPSTER P69.0 C1 OPEN BRANCH FROM BUS 245699 TO BUS 245701 CKT 1 / 245699 05HARPSTER P69.0 245701 05HARPSTER 69.0 1 END | 31.0 | 115.59 % | 1.84 |
| 247379 05NEVADA SS 69.0 - 245687 05BROK SWR 69.0 CKT 1 | AEP_P2-2_#14773_05N WALDO 69.0_1_SRT-A CONTINGENCY 'AEP_P2-2_#14773_05N WALDO 69.0_1_SRT-A' /Waldo - La Rue line tapped by AD1-106 & AG2-595 OPEN BRANCH FROM BUS 243048 TO BUS 245708 CKT 1 / 243048 05N WALD 138 245708 05N WALDO 69.0 1 OPEN BRANCH FROM BUS 245708 TO BUS 245716 CKT 1 / 245708 05N WALDO 69.0 245716 05WALDO 69.0 1 OPEN BRANCH FROM BUS 243048 TO BUS 270372 CKT 1 / 243048 05N WALD 138 270372 AD1-106 TAP 138 1 OPEN BRANCH FROM BUS 243048 TO BUS 243148 CKT 1 / 243048 05N WALD 138 243148 05WINDFL 138 1 OPEN BRANCH FROM BUS 243011 TO BUS 243148 CKT 1 / 243011 05FULTON 138 243148 05WINDFL 138 1 OPEN BRANCH FROM BUS 242963 TO BUS 243011 CKT 1 / 242963 05HEDDSS 138 243011 05FULTON 138 1 OPEN BRANCH FROM BUS 242963 TO BUS 245540 CKT 1 / 242963 05HEDDSS 138 245540 05BLOOMFLD8 138 1 OPEN BRANCH FROM BUS 242963 TO BUS 243153 CKT 1 / 242963 05HEDDSS 138 243153 05WMTVER 138 1 REMOVE LOAD D2 FROM BUS 245708 / 245708 05N WALDO 69.0 D2 END | 31.0 | 110.49 % | 1.84 |
| TO | RTEP ID / TO ID | Category | Title | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|---|---|---|
| ATSI | (Pending) / TC2-ATSI-L06 | SubRegional | Reconductor/rebuild 4.8 miles between Greensprings Tap and Clyde Tap | 6.0 MW | 100.0% | $17,380,145 |
| AEP | (Pending) / TC2-AEP-149 | Distribution | At Findlay Center TR#1 138/34.5kV 45MVA needs to be replaced with a 138/34.5kV 90MVA bank | 7.0 MW | 100.0% | $3,936,000 |
| ATSI | (Pending) / TC2-ATSI-L02 | SubRegional | Upgrade (1) 4A overcurrent relay for breaker B41 at Wellington | 7.4 MW | 29.1% | $148,631 |
| Grand Total: | $21,464,776 | |||||
System Reinforcement
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-L06
- Category
- SubRegional
- Title
- Reconductor/rebuild 4.8 miles between Greensprings Tap and Clyde Tap
- Description
- Reconductor (possible rebuild) 4.8 miles of 4/0 CU 19 transmission line between Greensprings Tap and Clyde Tap on the Bellevue - West Fremont 69kV line using one (1) 795 26/7 "Drake ACSS New ratings to be 164/206/237 MVA
- Total Cost
- $17,380,145
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
| AH1-690 | 6.0 MW | 100.0% | $17,380,145 |
System Reinforcement
- TO
- AEP
- RTEP ID / TO ID
- (Pending) / TC2-AEP-190
- Category
- SubRegional
- Title
- Nevada - Sands: ~11.2 miles of 69kV single circuit needs rebuilt.
- Description
- Nevada - Sands: ~11.2 miles of 69kV single circuit needs rebuilt. Existing conductor 1-4/0 COPPER 19 75/75 °C
- Total Cost
- $35,840,000
System Reinforcement
- TO
- AEP
- RTEP ID / TO ID
- (Pending) / TC2-AEP-149
- Category
- Distribution
- Title
- At Findlay Center TR#1 138/34.5kV 45MVA needs to be replaced with a 138/34.5kV 90MVA bank
- Description
- At Findlay Center TR#1 138/34.5kV 45MVA needs to be replaced with a 138/34.5kV 90MVA bank
- Total Cost
- $3,936,000
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
| AH1-690 | 7.0 MW | 100.0% | $3,936,000 |
System Reinforcement
- TO
- AEP
- RTEP ID / TO ID
- (Pending) / TC2-AEP-193
- Category
- SubRegional
- Title
- Nevada - Brok: ~3 miles of 69kV single circuit needs rebuilt.
- Description
- Nevada - Brok: ~3 miles of 69kV single circuit needs rebuilt.
- Total Cost
- $9,600,000
System Reinforcement
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-L02
- Category
- SubRegional
- Title
- Upgrade (1) 4A overcurrent relay for breaker B41 at Wellington
- Description
- Upgrade (1) 4A overcurrent relay for breaker B41 at Wellington New ratings to be 55/69/80 MVA
- Total Cost
- $509,895
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
| AG2-109 | 18.1 MW | 70.9% | $361,264 |
| AH1-690 | 7.4 MW | 29.1% | $148,631 |
Developer Requirements
The developer is responsible for all design and construction related activities on the developer’s side of the Point of Change in Ownership. FirstEnergy interconnection requirements can be found here.
To the extent that these Applicable Technical Requirements and Standards may conflict with the terms and conditions of the Tariff, the Tariff shall control.
Revenue Metering and SCADA Requirements
The developer will be required to install equipment necessary to provide Revenue Metering (KWH, KVARH) and real time data (KW, KVAR) for their generating Resource. See PJM Manual 01, PJM Manual 14D, and PJM Tariff Part IX, Subpart B, Appendix 2, section 8.Transmission Owner Requirements
The Project Developer will be required to comply with all interconnected Transmission Owner’s revenue metering requirements located at the following link: PJM - Transmission Owner Engineering & Construction Standards.
Summer Peak Analysis
The New Service Request AH1-690 was evaluated as a 1475.0 MW (1440.0 MW Capacity) injection in the ATSI area.
AH1-690 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 1475.0 MW (1475.0 MW under study).
Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.
| Study | Area | Facility Description | Contingency Name | Contingency Type | DC|AC | Final Cycle Loading | Rating (MVA) | Rating Type | MVA to Mitigate | MW Contribution | |
|---|---|---|---|---|---|---|---|---|---|---|---|
| GD2 | ATSI | 02ASQ-11-02AVQ1 138.0 kV Ckt 1 line | ATSI_P7-1_OEC-345-001_SRT-A | Tower | AC | 102.13 % | 332.0 | B | 339.07 | 45.19 | |
| GD2 | ATSI | 02AVERY-02SHNROK 138.0 kV Ckt 1 line | ATSI_P7-1_TE-345-030_SRT-A | Tower | AC | 135.2 % | 282.0 | B | 381.27 | 58.35 | |
| GD2 | ATSI | 02AVERY-02SHNROK 138.0 kV Ckt 1 line | ATSI_P7-1_TE-345-031_SRT-A | Tower | AC | 132.18 % | 282.0 | B | 372.74 | 58.38 | |
| GD2 | ATSI | 02BAY SH-02DAV-BE 345.0 kV Ckt 1 line | ATSI_P2-3_TE-345-008B_SRT-SL | Breaker | AC | 168.3 % | 1683.0 | B | 2832.52 | 441.81 | |
| GD2 | ATSI | 02BAY SH-02DAV-BE 345.0 kV Ckt 1 line | ATSI_P2-3_TE-345-013_SRT-SL | Breaker | AC | 146.58 % | 1683.0 | B | 2466.99 | 445.14 | |
| GD2 | ATSI | 02BAY SH-02DAV-BE 345.0 kV Ckt 1 line | ATSI_P2-3_TE-345-014_SRT-A | Breaker | AC | 146.58 % | 1683.0 | B | 2466.97 | 445.15 | |
| GD2 | ATSI | 02BAY SH-02DAV-BE 345.0 kV Ckt 1 line | ATSI_P2-3_TE-345-009_SRT-A | Breaker | AC | 146.4 % | 1683.0 | B | 2463.99 | 445.37 | |
| GD2 | ATSI | 02BAY SH-02DAV-BE 345.0 kV Ckt 1 line | ATSI_P1-2_TE-345-602_SRT-A | Single | AC | 142.52 % | 1683.0 | B | 2398.59 | 445.37 | |
| GD2 | ATSI | 02BEAVER-02CARLIL 345.0 kV Ckt 1 line | ATSI_P7-1_OEC-345-002_SRT-A | Tower | AC | 109.31 % | 1745.0 | B | 1907.45 | 238.13 | |
| GD2 | ATSI | 02BEAVER-02JONSON 138.0 kV Ckt 1 line | ATSI_P7-1_OEC-345-002_SRT-A | Tower | AC | 122.44 % | 282.0 | B | 345.29 | 41.55 | |
| GD2 | ATSI | 02BEAVER-02LAKEAVE 345.0 kV Ckt 1 line | ATSI_P2-3_OEC-345-901_SRT-SL | Breaker | AC | 113.76 % | 1720.0 | B | 1956.7 | 209.15 | |
| GD2 | ATSI | 02BEAVER-02LAKEAVE 345.0 kV Ckt 1 line | ATSI_P2-3_OEC-345-007A_SRT-SL | Breaker | AC | 104.78 % | 1878.0 | B | 1967.82 | 212.09 | |
| GD2 | ATSI | 02BEAVER-02LAKEAVE 345.0 kV Ckt 1 line | ATSI_P2-3_OEC-345-031_SRT-A | Breaker | AC | 100.84 % | 1878.0 | B | 1893.72 | 206.56 | |
| GD2 | ATSI | 02BEAVER-02LAKEAVE 345.0 kV Ckt 2 line | ATSI_P2-3_OEC-345-002_SRT-A | Breaker | AC | 174.17 % | 1878.0 | B | 3270.93 | 297.55 | |
| GD2 | ATSI | 02BEAVER-02LAKEAVE 345.0 kV Ckt 2 line | ATSI_P2-3_OEC-345-003_SRT-SL | Breaker | AC | 104.76 % | 1878.0 | B | 1967.48 | 210.31 | |
| GD2 | ATSI | 02BEAVER-02LAKEAVE 345.0 kV Ckt 2 line | ATSI_P2-3_OEC-345-028_SRT-A | Breaker | AC | 101.37 % | 1878.0 | B | 1903.65 | 207.62 | |
| GD2 | ATSI | 02BRWELL-02FORD 138.0 kV Ckt 1 line | ATSI_P7-1_TE-345-030_SRT-A | Tower | AC | 170.25 % | 230.0 | B | 391.56 | 60.94 | |
| GD2 | ATSI | 02BRWELL-02FORD 138.0 kV Ckt 1 line | ATSI_P7-1_TE-345-031_SRT-A | Tower | AC | 166.37 % | 230.0 | B | 382.65 | 60.97 | |
| GD2 | ATSI | 02DAV-BE-02HAYES 345.0 kV Ckt 1 line | ATSI_P2-3_OEC-345-005_SRT-A | Breaker | AC | 149.08 % | 1892.0 | B | 2820.59 | 306.57 | |
| GD2 | ATSI | 02DAV-BE-02HAYES 345.0 kV Ckt 1 line | ATSI_P2-3_OEC-345-006_SRT-SL | Breaker | AC | 146.41 % | 1892.0 | B | 2770.12 | 307.32 | |
| GD2 | ATSI | 02DAV-BE-02HAYES 345.0 kV Ckt 1 line | ATSI_P2-3_TE-345-010A_SRT-SL | Breaker | AC | 144.5 % | 1892.0 | B | 2733.88 | 307.27 | |
| GD2 | ATSI | 02DAV-BE-02HAYES 345.0 kV Ckt 1 line | ATSI_P1-2_OEC-345-825_SRT-A | Single | AC | 136.86 % | 1892.0 | B | 2589.31 | 307.1 | |
| GD2 | ATSI | 02DAV-BE-02HAYES 345.0 kV Ckt 1 line | ATSI_P1-2_OEC-345-824_SRT-A | Single | AC | 136.39 % | 1892.0 | B | 2580.58 | 307.27 | |
| GD2 | ATSI | 02DAV-BE-AC2-103 TAP 345.0 kV Ckt 1 line | ATSI_P2-3_OEC-345-1152-F1_SRT-A | Breaker | AC | 155.03 % | 1646.0 | B | 2551.84 | 290.29 | |
| GD2 | ATSI | 02DAV-BE-AC2-103 TAP 345.0 kV Ckt 1 line | ATSI_P2-3_OEC-345-1152-12_SRT-A | Breaker | AC | 155.03 % | 1646.0 | B | 2551.84 | 290.29 | |
| GD2 | ATSI | 02DAV-BE-AC2-103 TAP 345.0 kV Ckt 1 line | ATSI_P2-3_TE-345-010B2_SRT-SL | Breaker | AC | 153.46 % | 1646.0 | B | 2525.94 | 287.75 | |
| GD2 | ATSI | 02DAV-BE-AC2-103 TAP 345.0 kV Ckt 1 line | ATSI_P2-3_TE-345-010B1_SRT-SL | Breaker | AC | 153.46 % | 1646.0 | B | 2525.94 | 287.75 | |
| GD2 | ATSI | 02DAV-BE-AC2-103 TAP 345.0 kV Ckt 1 line | ATSI_P2-3_OEC-345-1152-3_SRT-A | Breaker | AC | 151.55 % | 1646.0 | B | 2494.57 | 280.32 | |
| GD2 | ATSI | 02DAV-BE-AC2-103 TAP 345.0 kV Ckt 1 line | ATSI_P1-2_OEC-345-810_SRT-A | Single | AC | 136.64 % | 1646.0 | B | 2249.01 | 287.75 | |
| GD2 | ATSI | 02DAV-BE-AC2-103 TAP 345.0 kV Ckt 1 line | ATSI_P1-2_OEC-345-809_SRT-A | Single | AC | 128.94 % | 1646.0 | B | 2122.34 | 275.12 | |
| GD2 | ATSI | 02DUALR+-02ROBERT 138.0 kV Ckt 1 line | AEP_P4_#8396_05OHIOCT 345_M_SRT-A | Breaker | AC | 108.55 % | 209.0 | B | 226.88 | 23.04 | |
| GD2 | ATSI | 02DUALR+-02ROBERT 138.0 kV Ckt 1 line | AEP_P4_#16815_05OHIOCT 345_M2_SRT-A | Breaker | AC | 108.52 % | 209.0 | B | 226.81 | 23.04 | |
| GD2 | ATSI | 02DUALR+-02ROBERT 138.0 kV Ckt 1 line | ATSI_P2-3_OES-138-020_SRT-SL | Breaker | AC | 105.07 % | 209.0 | B | 219.59 | 20.84 | |
| GD2 | ATSI | 02FWLSQ2-02PV Q2 138.0 kV Ckt 1 line | ATSI_P2-3_CEI-345-025_BDR_A_SRT-SL | Breaker | AC | 113.1 % | 132.0 | B | 149.29 | 28.95 | |
| GD2 | ATSI | 02FWLSQ2-02PV Q2 138.0 kV Ckt 1 line | ATSI_P7-1_CEI-345-010_SRT-A | Tower | AC | 109.05 % | 132.0 | B | 143.95 | 29.47 | |
| GD2 | ATSI | 02FWLSQ2-02PV Q2 138.0 kV Ckt 1 line | ATSI_P1-2_CEI-345-701_SRT-A | Single | AC | 106.07 % | 132.0 | B | 140.01 | 30.05 | |
| GD2 | ATSI | 02FWLSQ2-02PV Q2 138.0 kV Ckt 1 line | ATSI_P2-3_CEI-345-002H_SRT-SL | Breaker | AC | 106.07 % | 132.0 | B | 140.01 | 30.05 | |
| GD2 | ATSI | 02FWLSQ2-02PV Q2 138.0 kV Ckt 1 line | ATSI_P2-3_CEI-345-018_BDR_A_SRT-SL | Breaker | AC | 105.53 % | 132.0 | B | 139.3 | 30.09 | |
| GD2 | ATSI | 02FWLSQ2-02PV Q2 138.0 kV Ckt 1 line | ATSI_P7-1_CEI-345-002_SRT-A | Tower | AC | 104.56 % | 132.0 | B | 138.02 | 29.83 | |
| GD2 | ATSI | 02FWLSQ2-02PV Q2 138.0 kV Ckt 1 line | ATSI_P2-3_CEI-345-002I_SRT-A | Breaker | AC | 104.53 % | 132.0 | B | 137.98 | 29.83 | |
| GD2 | ATSI | 02GALION-02GALION 345.0/138.0 kV Ckt 3 transformer | ATSI_P2-3_OES-138-021_SRT-SL | Breaker | AC | 103.25 % | 417.0 | B | 430.54 | 40.09 | |
| GD2 | ATSI | 02GALION-02GALION 345.0/138.0 kV Ckt 4 transformer | ATSI_P2-3_OES-138-018_SRT-SL | Breaker | AC | 104.79 % | 411.0 | B | 430.69 | 40.11 | |
| GD2 | ATSI | 02GRNFLD-02N DEPT 138.0 kV Ckt 1 line | ATSI_P7-1_TE-345-030_SRT-A | Tower | AC | 157.88 % | 242.0 | B | 382.07 | 60.94 | |
| GD2 | ATSI | 02GRNFLD-02N DEPT 138.0 kV Ckt 1 line | ATSI_P7-1_TE-345-031_SRT-A | Tower | AC | 154.19 % | 242.0 | B | 373.15 | 60.97 | |
| GD2 | ATSI | 02GRNFLD-02NASA 138.0 kV Ckt 1 line | ATSI_P7-1_TE-345-030_SRT-A | Tower | AC | 179.06 % | 192.0 | B | 343.8 | 54.56 | |
| GD2 | ATSI | 02GRNFLD-02NASA 138.0 kV Ckt 1 line | ATSI_P7-1_TE-345-031_SRT-A | Tower | AC | 177.37 % | 192.0 | B | 340.55 | 54.59 | |
| GD2 | ATSI | 02HAYES-02AVERY 138.0 kV Ckt 1 line | ATSI_P7-1_TE-345-030_SRT-A | Tower | AC | 123.09 % | 339.0 | B | 417.27 | 60.6 | |
| GD2 | ATSI | 02HAYES-02AVERY 138.0 kV Ckt 1 line | ATSI_P7-1_TE-345-031_SRT-A | Tower | AC | 120.42 % | 339.0 | B | 408.21 | 60.63 | |
| GD2 | ATSI | 02HAYES-02BEAVER 345.0 kV Ckt 1 line | ATSI_P2-3_OEC-345-005_SRT-A | Breaker | AC | 146.75 % | 1878.0 | B | 2755.89 | 288.19 | |
| GD2 | ATSI | 02HAYES-02BEAVER 345.0 kV Ckt 1 line | ATSI_P2-3_OEC-345-006_SRT-SL | Breaker | AC | 144.08 % | 1878.0 | B | 2705.74 | 289.62 | |
| GD2 | ATSI | 02HAYES-02BEAVER 345.0 kV Ckt 1 line | ATSI_P2-3_TE-345-010A_SRT-SL | Breaker | AC | 142.21 % | 1878.0 | B | 2670.76 | 288.97 | |
| GD2 | ATSI | 02HAYES-02BEAVER 345.0 kV Ckt 1 line | ATSI_P1-2_OEC-345-825_SRT-A | Single | AC | 136.05 % | 1878.0 | B | 2554.95 | 288.81 | |
| GD2 | ATSI | 02HAYES-02BEAVER 345.0 kV Ckt 1 line | ATSI_P1-2_OEC-345-824_SRT-A | Single | AC | 135.68 % | 1878.0 | B | 2548.09 | 288.97 | |
| GD2 | ATSI | 02LAKVEW-02GRNFLD 138.0 kV Ckt 1 line | ATSI_P7-1_TE-345-027A_SRT-A | Tower | AC | 175.39 % | 352.0 | B | 617.37 | 89.7 | |
| IPD | ATSI | 02LAKVEW-02GRNFLD 138.0 kV Ckt 1 line | ATSI_P7-1_TE-345-027A_SRT-A | Tower | AC | 126.45 % | 352.0 | B | 445.09 | 95.19 | |
| GD2 | AEP/ATSI | 02LALLENDORF-05FOSTOR 345.0 kV Ckt 1 line | ATSI_P7-1_TE-345-021_SRT-A-1 | Tower | AC | 124.85 % | 1409.0 | B | 1759.15 | 788.05 | |
| IPD | AEP/ATSI | 02LALLENDORF-05FOSTOR 345.0 kV Ckt 1 line | ATSI_P7-1_TE-345-021_SRT-A-1 | Tower | AC | 110.58 % | 1409.0 | B | 1558.11 | 788.05 | |
| GD2 | ATSI | 02LEMOYN-02DAV-BE 345.0 kV Ckt 1 line | ATSI_P2-3_TE-345-007_SRT-SL | Breaker | AC | 137.87 % | 1878.0 | B | 2589.19 | 230.61 | |
| GD2 | ATSI | 02LEMOYN-02DAV-BE 345.0 kV Ckt 1 line | ATSI_P2-3_TE-345-004_SRT-A | Breaker | AC | 118.2 % | 1878.0 | B | 2219.8 | 234.32 | |
| GD2 | ATSI | 02LEMOYN-02DAV-BE 345.0 kV Ckt 1 line | ATSI_P2-3_TE-345-005_SRT-SL | Breaker | AC | 118.2 % | 1878.0 | B | 2219.73 | 234.28 | |
| GD2 | ATSI | 02LEMOYN-02DAV-BE 345.0 kV Ckt 1 line | ATSI_P2-3_TE-345-006_SRT-SL | Breaker | AC | 118.2 % | 1878.0 | B | 2219.73 | 234.28 | |
| GD2 | ATSI | 02LEMOYN-02DAV-BE 345.0 kV Ckt 1 line | ATSI_P1-2_TE-345-601_SRT-A | Single | AC | 113.99 % | 1878.0 | B | 2140.73 | 234.28 | |
| GD2 | ATSI | 02LEMOYN-02DAV-BE 345.0 kV Ckt 1 line | ATSI_P7-1_TE-345-021_SRT-A-1 | Tower | AC | 109.02 % | 1878.0 | B | 2047.43 | 211.68 | |
| GD2 | ATSI | 02N DEPT-02BRWELL 138.0 kV Ckt 1 line | ATSI_P7-1_TE-345-030_SRT-A | Tower | AC | 171.21 % | 230.0 | B | 393.79 | 60.94 | |
| GD2 | ATSI | 02N DEPT-02BRWELL 138.0 kV Ckt 1 line | ATSI_P7-1_TE-345-031_SRT-A | Tower | AC | 167.34 % | 230.0 | B | 384.88 | 60.97 | |
| GD2 | ATSI | 02NASA-02BEAVER 138.0 kV Ckt 1 line | ATSI_P7-1_TE-345-030_SRT-A | Tower | AC | 178.12 % | 192.0 | B | 341.99 | 54.56 | |
| GD2 | ATSI | 02NASA-02BEAVER 138.0 kV Ckt 1 line | ATSI_P7-1_TE-345-031_SRT-A | Tower | AC | 176.43 % | 192.0 | B | 338.74 | 54.59 | |
| GD2 | ATSI | 02OAKPOINT-02BEAVER 138.0 kV Ckt 1 line | ATSI_P7-1_TE-345-030_SRT-A | Tower | AC | 108.86 % | 314.0 | B | 341.82 | 66.07 | |
| GD2 | ATSI | 02OAKPOINT-02BEAVER 138.0 kV Ckt 1 line | ATSI_P7-1_TE-345-031_SRT-A | Tower | AC | 106.41 % | 314.0 | B | 334.12 | 66.1 | |
| GD2 | ATSI | 02OTTAWA-02LAKVEW 138.0 kV Ckt 1 line | ATSI_P7-1_TE-345-027A_SRT-A | Tower | AC | 115.82 % | 516.0 | B | 597.63 | 89.7 | |
| GD2 | AEP/ATSI | 02W.FREM-05FRMNT 138.0 kV Ckt 1 line | AEP_P4_#17249_05FOSTOR 345_A1_SRT-A | Breaker | AC | 108.84 % | 380.0 | B | 413.58 | 97.56 | |
| GD2 | AEP | 05BOKESCRK-05MARYSV 345.0 kV Ckt 1 line | AEP_P4_#7445_05MARYSV 765_B_SRT-A | Breaker | AC | 117.99 % | 1302.0 | B | 1536.23 | 87.56 | |
| GD2 | AEP | 05BOKESCRK-05MARYSV 345.0 kV Ckt 1 line | AEP_P4_#7441_05SORENS 765_J1_SRT-A | Breaker | AC | 110.86 % | 1302.0 | B | 1443.45 | 94.17 | |
| GD2 | AEP | 05BOKESCRK-05MARYSV 345.0 kV Ckt 1 line | AEP_P4_#8075_05MARYSV 765_A2_SRT-A | Breaker | AC | 104.12 % | 1302.0 | B | 1355.58 | 74.51 | |
| GD2 | AEP | 05BOKESCRK-05MARYSV 345.0 kV Ckt 1 line | AEP_P4_#7446_05MARYSV 765_B2_SRT-A | Breaker | AC | 103.45 % | 1302.0 | B | 1346.92 | 81.32 | |
| GD2 | AEP | 05BOXWD-05CLIFFR 138.0 kV Ckt 1 line | DVP_P4-2: 547T566_SRT-S | Breaker | AC | 158.21 % | 167.0 | B | 264.21 | 9.05 | |
| GD2 | AEP | 05BOXWD-05CLIFFR 138.0 kV Ckt 1 line | DVP_P4-2: 56602_SRT-A | Breaker | AC | 156.66 % | 167.0 | B | 261.62 | 9.06 | |
| GD2 | AEP | 05BOXWD-05CLIFFR 138.0 kV Ckt 1 line | AEP_P4_#7422_05CLOVRD 500_EE2_SRT-A | Breaker | AC | 156.47 % | 167.0 | B | 261.31 | 9.06 | |
| GD2 | AEP | 05BOXWD-05CLIFFR 138.0 kV Ckt 1 line | AEP_P1-2_#7422_16_SRT-A | Single | AC | 144.17 % | 167.0 | B | 240.77 | 9.06 | |
| GD2 | AEP | 05CLIFFR-05COLLEEN SS 138.0 kV Ckt 1 line | DVP_P4-2: 547T566_SRT-S | Breaker | AC | 161.25 % | 167.0 | B | 269.29 | 9.05 | |
| GD2 | AEP | 05CLIFFR-05COLLEEN SS 138.0 kV Ckt 1 line | DVP_P4-2: 56602_SRT-A | Breaker | AC | 159.7 % | 167.0 | B | 266.7 | 9.06 | |
| GD2 | AEP | 05CLIFFR-05COLLEEN SS 138.0 kV Ckt 1 line | AEP_P4_#7422_05CLOVRD 500_EE2_SRT-A | Breaker | AC | 159.52 % | 167.0 | B | 266.4 | 9.06 | |
| GD2 | AEP | 05CLIFFR-05COLLEEN SS 138.0 kV Ckt 1 line | AEP_P1-2_#7422_16_SRT-A | Single | AC | 145.35 % | 167.0 | B | 242.73 | 9.06 | |
| GD2 | AEP | 05COLLEEN SS-05JAMES RIVR 138.0 kV Ckt 1 line | DVP_P4-2: 547T566_SRT-S | Breaker | AC | 159.14 % | 167.0 | B | 265.76 | 9.05 | |
| GD2 | AEP | 05COLLEEN SS-05JAMES RIVR 138.0 kV Ckt 1 line | DVP_P4-2: 56602_SRT-A | Breaker | AC | 157.59 % | 167.0 | B | 263.18 | 9.06 | |
| GD2 | AEP | 05COLLEEN SS-05JAMES RIVR 138.0 kV Ckt 1 line | AEP_P4_#7422_05CLOVRD 500_EE2_SRT-A | Breaker | AC | 157.41 % | 167.0 | B | 262.87 | 9.06 | |
| GD2 | AEP | 05COLLEEN SS-05JAMES RIVR 138.0 kV Ckt 1 line | AEP_P1-2_#7422_16_SRT-A | Single | AC | 143.23 % | 167.0 | B | 239.2 | 9.06 | |
| GD2 | AEP | 05E LIMA-05SW LIM 345.0 kV Ckt 1 line | AEP_P4_#6497_05MARYSV 345_J2_SRT-A | Breaker | AC | 112.9 % | 971.0 | B | 1096.25 | 115.56 | |
| GD2 | AEP | 05E LIMA-05SW LIM 345.0 kV Ckt 1 line | AEP_P4_#17564_05BOKESCRK 345_CB2_SRT-A | Breaker | AC | 105.18 % | 971.0 | B | 1021.28 | 115.99 | |
| GD2 | AEP | 05E LIMA-05SW LIM 345.0 kV Ckt 1 line | AEP_P4_#16659_05GUNN RD SW 345_M2_SRT-A | Breaker | AC | 104.18 % | 971.0 | B | 1011.61 | 116.09 | |
| GD2 | AEP | 05E LIMA-05SW LIM 345.0 kV Ckt 1 line | AEP_P2-2_#16655_05GUNN RD SW 345_2_SRT-A | Bus | AC | 104.17 % | 971.0 | B | 1011.54 | 116.09 | |
| GD2 | AEP | 05GUNN RD SW-05BOKESCRK 345.0 kV Ckt 1 line | AEP_P4_#7445_05MARYSV 765_B_SRT-A | Breaker | AC | 101.83 % | 1301.0 | B | 1324.81 | 89.12 | |
| GD2 | AEP | 05JAMES RIVR-05SOAPSTONE 138.0 kV Ckt 1 line | DVP_P4-2: 547T566_SRT-S | Breaker | AC | 156.86 % | 167.0 | B | 261.96 | 9.05 | |
| GD2 | AEP | 05JAMES RIVR-05SOAPSTONE 138.0 kV Ckt 1 line | DVP_P4-2: 56602_SRT-A | Breaker | AC | 155.32 % | 167.0 | B | 259.38 | 9.06 | |
| GD2 | AEP | 05JAMES RIVR-05SOAPSTONE 138.0 kV Ckt 1 line | AEP_P4_#7422_05CLOVRD 500_EE2_SRT-A | Breaker | AC | 155.13 % | 167.0 | B | 259.07 | 9.06 | |
| GD2 | AEP | 05JAMES RIVR-05SOAPSTONE 138.0 kV Ckt 1 line | AEP_P1-2_#7422_16_SRT-A | Single | AC | 140.96 % | 167.0 | B | 235.41 | 9.06 | |
| GD2 | AEP | 05SCOTSV-AE1-108 POI 138.0 kV Ckt 1 line | DVP_P4-2: 547T566_SRT-S | Breaker | AC | 150.94 % | 167.0 | B | 252.07 | 9.05 | |
| GD2 | AEP | 05SCOTSV-AE1-108 POI 138.0 kV Ckt 1 line | DVP_P4-2: 56602_SRT-A | Breaker | AC | 149.39 % | 167.0 | B | 249.49 | 9.06 | |
| GD2 | AEP | 05SCOTSV-AE1-108 POI 138.0 kV Ckt 1 line | AEP_P4_#7422_05CLOVRD 500_EE2_SRT-A | Breaker | AC | 149.21 % | 167.0 | B | 249.18 | 9.06 | |
| GD2 | AEP | 05SCOTSV-AE1-108 POI 138.0 kV Ckt 1 line | AEP_P1-2_#7422_16_SRT-A | Single | AC | 135.04 % | 167.0 | B | 225.52 | 9.06 | |
| GD2 | AEP | 05SOAPSTONE-05SCOTSV 138.0 kV Ckt 1 line | DVP_P4-2: 547T566_SRT-S | Breaker | AC | 154.46 % | 167.0 | B | 257.95 | 9.05 | |
| GD2 | AEP | 05SOAPSTONE-05SCOTSV 138.0 kV Ckt 1 line | DVP_P4-2: 56602_SRT-A | Breaker | AC | 152.91 % | 167.0 | B | 255.37 | 9.06 | |
| GD2 | AEP | 05SOAPSTONE-05SCOTSV 138.0 kV Ckt 1 line | AEP_P4_#7422_05CLOVRD 500_EE2_SRT-A | Breaker | AC | 152.74 % | 167.0 | B | 255.07 | 9.06 | |
| GD2 | AEP | 05SOAPSTONE-05SCOTSV 138.0 kV Ckt 1 line | AEP_P1-2_#7422_16_SRT-A | Single | AC | 138.56 % | 167.0 | B | 231.4 | 9.06 | |
| GD2 | AEP | 05WOLFCK-05W.WATERT 138.0 kV Ckt 1 line | AEP_P4_#37_05MOUNTN 765_B1_SRT-A | Breaker | AC | 103.4 % | 255.0 | B | 263.67 | 15.52 | |
| GD2 | AEP | 05WOLFCK-05W.WATERT 138.0 kV Ckt 1 line | AEP_P4_#2942_05KAMMER 765_PP_SRT-A | Breaker | AC | 102.5 % | 255.0 | B | 261.36 | 15.53 | |
| GD2 | AEP | 05WOLFCK-05W.WATERT 138.0 kV Ckt 1 line | AP_P2-3_MP-500-021_SRT-SL | Breaker | AC | 102.45 % | 255.0 | B | 261.25 | 14.96 | |
| GD2 | CPLE/DVP | 6PERSON230 T-AC2-100 TAP 230.0 kV Ckt 1 line | DVP_P1-2: LN 570_SRT-A-3 | Single | AC | 182.88 % | 508.54 | B | 930.03 | 28.67 | |
| GD2 | CPLE/DVP | 6PERSON230 T-AC2-100 TAP 230.0 kV Ckt 1 line | DVP_P1-2: LN 570_SRT-A-2 | Single | AC | 178.67 % | 508.54 | B | 908.59 | 28.67 | |
| GD2 | AEP | AC2-015 TAP-05HOWARD1 138.0 kV Ckt 1 line | AEP_P4_#7105_05MELMOR 138_B2_SRT-A | Breaker | AC | 102.18 % | 183.0 | B | 186.99 | 26.1 | |
| GD2 | ATSI | AC2-103 TAP-02BEAVER 345.0 kV Ckt 1 line | ATSI_P2-3_OEC-345-009_SRT-SL | Breaker | AC | 165.39 % | 1499.0 | B | 2479.15 | 275.94 | |
| GD2 | ATSI | AC2-103 TAP-02BEAVER 345.0 kV Ckt 1 line | ATSI_P2-3_OEC-345-1152-F1_SRT-A | Breaker | AC | 145.45 % | 1798.0 | B | 2615.26 | 289.96 | |
| GD2 | ATSI | AC2-103 TAP-02BEAVER 345.0 kV Ckt 1 line | ATSI_P2-3_OEC-345-1152-12_SRT-A | Breaker | AC | 145.45 % | 1798.0 | B | 2615.26 | 289.96 | |
| GD2 | ATSI | AC2-103 TAP-02BEAVER 345.0 kV Ckt 1 line | ATSI_P2-3_OEC-345-1152-3_SRT-A | Breaker | AC | 142.16 % | 1798.0 | B | 2556.01 | 279.99 | |
| GD2 | ATSI | AC2-103 TAP-02BEAVER 345.0 kV Ckt 1 line | ATSI_P2-3_TE-345-010B1_SRT-SL | Breaker | AC | 141.11 % | 1798.0 | B | 2537.18 | 287.42 | |
| GD2 | ATSI | AC2-103 TAP-02BEAVER 345.0 kV Ckt 1 line | ATSI_P1-2_OEC-345-810_SRT-A | Single | AC | 123.08 % | 1798.0 | B | 2212.91 | 287.42 | |
| GD2 | ATSI | AC2-103 TAP-02BEAVER 345.0 kV Ckt 1 line | ATSI_P1-2_OEC-345-809_SRT-A | Single | AC | 117.76 % | 1798.0 | B | 2117.36 | 274.79 | |
| GD2 | AEP/DVP | AE1-108 POI-4BREMO 138.0 kV Ckt 1 line | DVP_P4-2: 547T566_SRT-S | Breaker | AC | 195.0 % | 167.0 | B | 325.65 | 8.44 | |
| GD2 | AEP/DVP | AE1-108 POI-4BREMO 138.0 kV Ckt 1 line | DVP_P4-2: 56602_SRT-A | Breaker | AC | 193.53 % | 167.0 | B | 323.2 | 8.45 | |
| GD2 | AEP/DVP | AE1-108 POI-4BREMO 138.0 kV Ckt 1 line | AEP_P4_#7422_05CLOVRD 500_EE2_SRT-A | Breaker | AC | 193.36 % | 167.0 | B | 322.91 | 8.45 | |
| GD2 | AEP/DVP | AE1-108 POI-4BREMO 138.0 kV Ckt 1 line | AEP_P1-2_#7422_16_SRT-A | Single | AC | 192.44 % | 156.98 | B | 302.1 | 8.45 | |
| GD2 | AEP | AE2-072 TAP-05E.LEIPSIC2 138.0 kV Ckt 1 line | AEP_P4_#17249_05FOSTOR 345_A1_SRT-A | Breaker | AC | 116.88 % | 223.0 | B | 260.64 | 30.96 | |
| GD2 | AEP | AE2-072 TAP-05E.LEIPSIC2 138.0 kV Ckt 1 line | AEP_P4_#10098_05LCKWRD 138_A_SRT-A | Breaker | AC | 109.73 % | 223.0 | B | 244.7 | 19.24 | |
| GD2 | AEP | AE2-072 TAP-05E.LEIPSIC2 138.0 kV Ckt 1 line | AEP_P2-2_#5123_05LCKWRD 138_1_SRT-A | Bus | AC | 109.65 % | 223.0 | B | 244.53 | 19.27 | |
| GD2 | AEP | AE2-072 TAP-05E.LEIPSIC2 138.0 kV Ckt 1 line | AEP_P4_#5123_05LCKWRD 138_B_SRT-A | Breaker | AC | 109.65 % | 223.0 | B | 244.51 | 19.27 | |
| GD2 | AEP | AE2-072 TAP-05E.LEIPSIC2 138.0 kV Ckt 1 line | ATSI_P7-1_TE-345-027A_SRT-A | Tower | AC | 105.2 % | 223.0 | B | 234.6 | 13.4 | |
| GD2 | AEP | AE2-072 TAP-05E.LEIPSIC2 138.0 kV Ckt 1 line | ATSI_P7-1_TE-345-030_SRT-A | Tower | AC | 103.28 % | 223.0 | B | 230.31 | 12.53 | |
| GD2 | AEP | AE2-072 TAP-05E.LEIPSIC2 138.0 kV Ckt 1 line | AEP_P2-2_#744_05FOSTOR 345_2_SRT-A | Bus | AC | 100.96 % | 223.0 | B | 225.14 | 12.11 | |
| GD2 | AEP/ATSI | AG2-148 TP-02GALION 345.0 kV Ckt 1 line | ATSI_P7-1_TE-345-027A_SRT-A | Tower | AC | 106.19 % | 1308.0 | B | 1388.99 | 228.6 | |
| GD2 | AEP/ATSI | AG2-148 TP-02GALION 345.0 kV Ckt 1 line | ATSI_P7-1_TE-345-030_SRT-A | Tower | AC | 105.3 % | 1308.0 | B | 1377.33 | 222.24 | |
| GD2 | ATSI | AH1-690 TP-02BAY SH 345.0 kV Ckt 2 line | ATSI_P1-2_TE-345-606_SRT-A-1 | Single | AC | 102.39 % | 1774.0 | B | 1816.36 | 717.96 | |
| GD2 | ATSI | AH1-690 TP-02BAY SH 345.0 kV Ckt 2 line | ATSI_P2-3_TE-345-002_SRT-SL | Breaker | AC | 101.27 % | 1720.0 | B | 1741.77 | 686.08 | |
| GD2 | NYISO/PENELEC | N.WAV115-26E.SAYRE 115.0 kV Ckt 1 line | PN_P1-1_PN-230-018_SRT-A | Single | AC | 139.93 % | 128.0 | B | 179.12 | 7.01 | |
| GD2 | NYISO/PENELEC | N.WAV115-26E.SAYRE 115.0 kV Ckt 1 line | PN_P1-1_PN-230-017_SRT-A | Single | AC | 139.93 % | 128.0 | B | 179.12 | 7.01 | |
| GD2 | NYISO/PENELEC | N.WAV115-26E.SAYRE 115.0 kV Ckt 1 line | PN_P2-2_PN-345-1154-W_SRT-A | Bus | AC | 124.81 % | 128.0 | B | 159.76 | 7.85 | |
| GD2 | NYISO/PENELEC | N.WAV115-26E.SAYRE 115.0 kV Ckt 1 line | Base Case | Single | AC | 116.38 % | 114.0 | A | 132.68 | 7.01 | |
| GD2 | NYISO/PENELEC | N.WAV115-26E.SAYRE 115.0 kV Ckt 1 line | AP_P2-2_WP-230-001T_SRT-A | Bus | AC | 113.06 % | 128.0 | B | 144.71 | 7.6 |
Winter Peak Analysis
The New Service Request AH1-690 was evaluated as a 1475.0 MW (1440.0 MW Capacity) injection in the ATSI area.
AH1-690 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 1475.0 MW (1475.0 MW under study).
Note: The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for single or N-1 contingencies and multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.
(No impacts were found for this analysis)
Light Load Analysis
The New Service Request AH1-690 was evaluated as a 1475.0 MW injection
AH1-690 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 1475.0 MW (1475.0 MW under study).
Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.
| Study | Area | Facility Description | Contingency Name | Contingency Type | DC|AC | Final Cycle Loading | Rating (MVA) | Rating Type | MVA to Mitigate | MW Contribution | |
|---|---|---|---|---|---|---|---|---|---|---|---|
| GD2 | AEP/ATSI | 02LALLENDORF-05FOSTOR 345.0 kV Ckt 1 line | ATSI_P7-1_TE-345-021_SRT-A-1 | Tower | AC | 112.05 % | 1409.0 | B | 1578.76 | 647.24 | |
| IPD | AEP/ATSI | 02LALLENDORF-05FOSTOR 345.0 kV Ckt 1 line | ATSI_P7-1_TE-345-021_SRT-A-1 | Tower | AC | 101.19 % | 1409.0 | B | 1425.72 | 787.57 | |
| GD2 | AEP | 05BOKESCRK-05MARYSV 345.0 kV Ckt 1 line | Base Case | Single | AC | 124.29 % | 897.0 | A | 1114.89 | 35.6 | |
| GD2 | AEP | 05BOKESCRK-05MARYSV 345.0 kV Ckt 1 line | AEP_P1-2_#7441_100545_SRT-A | Single | AC | 111.91 % | 1301.0 | B | 1455.99 | 53.82 | |
| GD2 | AEP | 05E LIMA-05SW LIM 345.0 kV Ckt 1 line | AEP_P1-2_#6497_SRT-A | Single | AC | 113.95 % | 971.0 | B | 1106.49 | 62.8 | |
| GD2 | AEP | 05E LIMA-05SW LIM 345.0 kV Ckt 1 line | AEP_P1-2_#17561_SRT-A | Single | AC | 108.46 % | 971.0 | B | 1053.1 | 63.33 | |
| GD2 | AEP | 05GUNN RD SW-05BOKESCRK 345.0 kV Ckt 1 line | Base Case | Single | AC | 108.04 % | 897.0 | A | 969.16 | 36.79 |
Short Circuit Analysis
Short Circuit analysis is not performed as part of the Phase I System Impact Study. Short Circuit analysis will commence in the Phase II System Impact Study.
Stability Analysis
Stability analysis is not performed as part of the Phase I System Impact Study. Stability analysis will commence in the Phase II System Impact Study.
Reactive Power Analysis
Reactive Power analysis is not performed as part of the Phase I System Impact Study. Reactive Power analysis will commence in the Phase II System Impact Study.
Steady-State Voltage Analysis
Steady State Voltage Analysis is Not Required.
New Service Request Dependencies
The New Service Requests below are listed in one or more dispatch for the overloads identified in this report. These projects contribute to the loading of the overloaded facilities identified in this report. The percent overload of a facility and cost allocation you may have towards a particular reinforcement could vary depending on the action of other projects. The status of each project at the time of the analysis is presented in the table. This list may change as other projects withdraw or modify their requests. This table is valid for load flow analyses only.
| New Service Requests Dependencies | ||
|---|---|---|
| Project ID | Project Name | Status |
| AA1-018 | Powerton-Goodings Grove | In Service |
| AA1-050 | Tarboro-Everetts 230kV | In Service |
| AA1-139 | Hickory-Shawboro 230kV | In Service |
| AB1-006 | Meadow Lake 345kV | In Service |
| AB1-027 | Old Church 34.5 KV | In Service |
| AB1-081 | Anaconda-Mayo Dunbar 115kV | In Service |
| AB2-022 | Elizabeth City 34.5kV | In Service |
| AB2-025 | Sapony 34.5kV | In Service |
| AB2-026 | Powhatan 34.5kV | In Service |
| AB2-045 | Buckingham 34.5kV | In Service |
| AB2-059 | Benson-Dunbar 115kV | In Service |
| AB2-060 | Chase City-Lunenburg 115kV | In Service |
| AB2-070 | Mt. Pulaski-Brokaw | In Service |
| AB2-077 | Buggs Island-Chase City 115kV | In Service |
| AB2-078 | Buggs Island-Chase City 115kV | In Service |
| AB2-079 | Buggs Island-Chase City 115kV | In Service |
| AB2-134 | Hopewell-Surry 230kV | In Service |
| AB2-170 | East Lima-Marysville 345kV | In Service |
| AB2-190 | Hopewell-Surry 230kV | In Service |
| AC1-027 | Pendleton 34.5kV | In Service |
| AC1-033 | Kewanee 138 kV | In Service |
| AC1-034 | Heartsease DP - Mayo Dunbar 115kV | Suspended |
| AC1-036 | Twittys Creek 34.5kV | In Service |
| AC1-042 | Altavista-Mt. Airy 69kV | In Service |
| AC1-053 | Lanesville-Brokaw | Partially in Service - Under Construction |
| AC1-054 | Kerr Dam–Eatons Ferry 115 kV | In Service |
| AC1-075 | Perth-Hickory Grove 115kV | In Service |
| AC1-078 | Beatty-London 138kV | In Service |
| AC1-105 | Halifax-Mt. Laurel 115kV | In Service |
| AC1-111 | Aurora 138kV | In Service |
| AC1-122 | Smith Mountain-Candler's Mountain 138kV | In Service |
| AC1-145 | Gretna DP 69 kV | In Service |
| AC1-147 | Grassfield 34.5kV | In Service |
| AC1-161 | Septa 500kV | In Service |
| AC1-167 | Mark Center 69kV | Under Construction |
| AC1-168 | Kewanee-Streator | Suspended |
| AC1-214 | Crescent Ridge | In Service |
| AC1-221 | Halifax-Person 230kV | In Service |
| AC1-222 | Crystal Hill-Halifax 115kV | In Service |
| AC2-012 | Grassfield-Great Bridge 115kV | In Service |
| AC2-015 | Chatfield-Howard 138kV | Partially in Service - Under Construction |
| AC2-044 | Maddox Creek 345kV | Suspended |
| AC2-100 | Halifax-Person 230kV | In Service |
| AC2-103 | Beaver-Davis Besse 345 kV I | Engineering & Procurement |
| AC2-137 | Elko 34.5kV | In Service |
| AC2-138 | Northern Neck 34.5kV | In Service |
| AC2-141 | Septa 500kV | Engineering & Procurement |
| AC2-154 | Davis Creek 138kV | Engineering & Procurement |
| AC2-165 | Bremo-Powhatan 230kV | Suspended |
| AC2-168 | Clinton 23kV | In Service |
| AC2-176 | Jay 138 kV | In Service |
| AC2-195 | Galion-Roberts South 138 kV | Under Construction |
| AD1-013 | Twombly Road 138kV | Engineering & Procurement |
| AD1-017 | Smith Mountain-Bearskin 138 kV | In Service |
| AD1-025 | Hopewell-Surry 230 kV | Under Construction |
| AD1-033 | Fentress-Landstown 230 kV | In Service |
| AD1-041 | Harmony Village-Shackleford 115 kV | In Service |
| AD1-063 | Harmony Village 34.5 kV | In Service |
| AD1-082 | Bakers Pond-Ivor 115kV | In Service |
| AD1-087 | Clover-Sedge Hill 230 kV | In Service |
| AD1-100 | Loretto-Wilton 345 kV & Braidwood-Davis Creek 345 kV | Under Construction |
| AD1-101 | Continental 69 kV | In Service |
| AD1-106 | North Waldo-Wild Creek 138 kV | Suspended |
| AD1-119 | Payne 69 kV | In Service |
| AD1-130 | Hardin Switch 345 kV | In Service |
| AD1-140 | Greene-Clark 138 kV | Engineering & Procurement |
| AD1-144 | Kings Fork 34.5 kV | In Service |
| AD1-152 | Clover-Sedge Hill 230 kV | In Service |
| AD2-020 | Valley 138 kV | Engineering & Procurement |
| AD2-030 | Wan 34.5 kV | In Service |
| AD2-031 | Martinsville-Wilmington 69 kV | In Service |
| AD2-033 | Chase City-Lunenburg 115 kV | Under Construction |
| AD2-038 | Powerton-Nevada 345 kV | Under Construction |
| AD2-047 | Davis Creek 138 kV | Suspended |
| AD2-060 | Davis Creek 138kV | Engineering & Procurement |
| AD2-066 | Mazon-Crescent Ridge 138 kV | Engineering & Procurement |
| AD2-067 | Centerburg 138kV | Engineering & Procurement |
| AD2-071 | Strawton-Deer Creek 138 kV | Suspended |
| AD2-074 | Garner DP-Lancaster 115 kV | Engineering & Procurement |
| AD2-079 | Capitol Ave 34.5kV | In Service |
| AD2-085 | Myrtle-Windsor DP 115kV | Engineering & Procurement |
| AD2-086 | Hardin Switch 345 kV | In Service |
| AD2-091 | Hardin Tap 345kV | Suspended |
| AD2-092 | Marysville 345kV | Under Construction |
| AD2-093 | Marysville 345kV | Under Construction |
| AD2-096 | Marysville 345kV | Suspended |
| AD2-133 | Eagle Valley 115kV | In Service |
| AD2-134 | Shady Oaks | Partially in Service - Under Construction |
| AD2-160 | Hickory-Moyock 230kV | In Service |
| AD2-163 | Broadview-Tangy 138 kV | In Service |
| AD2-172 | Lena 138kV | In Service |
| AD2-202 | Clover-Sedge Hill 230kV | In Service |
| AE1-072 | Shawboro-Sligo 230 kV | Under Construction |
| AE1-074 | Winterpock 34.5 kV | Under Construction |
| AE1-075 | Powhatan 34.5 kV | In Service |
| AE1-079 | Maysville-Sharon 69 kV | Under Construction |
| AE1-090 | Hardin Switch 345 kV | In Service |
| AE1-091 | West Newton-Lynn 138 kV | Suspended |
| AE1-100 | Axton 138 kV | In Service |
| AE1-102 | Maddox Creek 345 kV | Suspended |
| AE1-108 | Bremo-Scottsville 138 kV | Engineering & Procurement |
| AE1-113 | Mole Creek 345 kV | Engineering & Procurement |
| AE1-114 | Maryland-Lancaster 138 kV | Active |
| AE1-146 | Ebersole #2-Fostoria Central 138 kV | Under Construction |
| AE1-155 | Garner-Northern Neck 115 kV | In Service |
| AE1-162 | Smithfield 34.5 kV | In Service |
| AE1-163 | Powerton-Nevada 345 kV | Engineering & Procurement |
| AE1-166 | Loretto-Wilton 345 kV & Braidwood-Davis Creek 345 kV | Engineering & Procurement |
| AE1-170 | Kenzie Creek-Colby 138 kV | Suspended |
| AE1-172 | Loretto-Wilton Center | Active |
| AE1-175 | Light Foot 34.5 kV | In Service |
| AE1-183 | Maysville-McDowell 69 kV | Engineering & Procurement |
| AE1-190 | Harmony Village-Shackleford 115 kV | Partially in Service - Under Construction |
| AE1-191 | Harmony Village-Shackleford 115 kV | Partially in Service - Under Construction |
| AE1-205 | McLean 345 kV | Engineering & Procurement |
| AE1-207 | Mississinewa-Gaston 138 kV | Suspended |
| AE1-208 | Delaware-Van Buren 138 kV | Suspended |
| AE1-209 | Desoto 345 kV | Suspended |
| AE1-210 | Desoto 345 kV | Suspended |
| AE1-237 | Andover (Maysville) 69kV I | Under Construction |
| AE1-245 | Haviland 138 kV | Under Construction |
| AE1-250 | Smith Mountain-E. Danville 138 kV | Engineering & Procurement |
| AE2-035 | Lena 138 kV | In Service |
| AE2-045 | Olive-Reynolds 345 kV | Engineering & Procurement |
| AE2-047 | Ridgeway-Solite 69 kV | Engineering & Procurement |
| AE2-072 | East Leipsic-Richland 138 kV | In Service |
| AE2-089 | Pennville-Adams 138 kV | Engineering & Procurement |
| AE2-092 | Kidds Store-Sherwood 115 kV | Engineering & Procurement |
| AE2-113 | Farmers Valley-Ridgeway 115 kV | Under Construction |
| AE2-114 | Midland 23 kV I | In Service |
| AE2-115 | Midland 23 kV II | In Service |
| AE2-117 | ABW Tap-Alexandria 46 kV | Suspended |
| AE2-126 | Dubois-Curwensville 34.5 kV | In Service |
| AE2-129 | Philipsburg-Clarence 34.5 kV | In Service |
| AE2-131 | Philipsburg-Karthaus 34.5 | Under Construction |
| AE2-139 | East Towanda-Grover 230 kV | Engineering & Procurement |
| AE2-140 | Axton-Danville 138 kV | Suspended |
| AE2-148 | Beatty-Greene 345 kV | In Service |
| AE2-152 | Loretto-Wilton 345 kV & Braidwood-Davis Creek 345 kV | Engineering & Procurement |
| AE2-166 | Stockton 138 kV | Suspended |
| AE2-169 | Delaware-Van Buren 138 kV | Suspended |
| AE2-172 | Mississinewa-Gaston 138 kV | Suspended |
| AE2-173 | McLean 345 kV | Active |
| AE2-176 | Groton 138 kV Solar | In Service |
| AE2-181 | Snyder 69kV | Under Construction |
| AE2-185 | Gladys DP-Stonemill Switching Station 69 kV | Active |
| AE2-187 | Shockoe DP-Chatham 69 kV | Active |
| AE2-206 | East Sidney-Quincy 138 kV | In Service |
| AE2-212 | Harrowgate 34 kV | Engineering & Procurement |
| AE2-214 | Cole 345 kV | Engineering & Procurement |
| AE2-216 | Hardin Switch 345 kV | Engineering & Procurement |
| AE2-219 | Bluff Point-Randolph 138 kV | Suspended |
| AE2-221 | Clinton-Stuart 345 kV | Under Construction |
| AE2-223 | McLean 345 kV | Active |
| AE2-224 | Bear Rock-Johnstown 230 kV | In Service |
| AE2-234 | Liberty Center-Buckeye Tap 69 kV | Engineering & Procurement |
| AE2-236 | Columbia-Northeast 138 kV | Suspended |
| AE2-253 | Hickory-Moyock 230 kV | In Service |
| AE2-255 | Molecreek 345 kV | Engineering & Procurement |
| AE2-259 | Curdsville-Willis Mtn 115 kV | Engineering & Procurement |
| AE2-262 | Moshannon-Milesburg 230 kV | Engineering & Procurement |
| AE2-263 | Moshannon-Milesburg 230 kV II | Engineering & Procurement |
| AE2-281 | Powerton-Nevada 345 kV | Engineering & Procurement |
| AE2-282 | East Fayette 138 kV | In Service |
| AE2-283 | Gladys-Stone Mill 69 kV | Active |
| AE2-285 | Maysville 69 kV | Engineering & Procurement |
| AE2-298 | Cavett Switch - West Van Wert 69 kV | Engineering & Procurement |
| AE2-306 | Gunn Road 345 kV | Under Construction |
| AE2-321 | Belvidere-Marengo 138 kV | Active |
| AE2-322 | Mark Center 69 kV | Under Construction |
| AE2-323 | Twin Branch-Guardian 138 kV | Under Construction |
| AE2-325 | Valley 138 kV | Active |
| AE2-341 | Sandwich-Plano 138 kV | Active |
| AE2-342 | Woodstock 69 kV | Engineering & Procurement |
| AE2-343 | Andover (Maysville) 69 kV II | Under Construction |
| AF1-006 | Fairview East 34.5 kV | In Service |
| AF1-030 | Sandwich-Plano 138 kV | Active |
| AF1-032 | Suffolk 34.5 kV | In Service |
| AF1-042 | Garner DP-Lancaster 115 kV | Engineering & Procurement |
| AF1-049 | Berry Hill 138 kV | Under Construction |
| AF1-058 | Welco 34.5 kV | In Service |
| AF1-064 | Weston 69 kV | Under Construction |
| AF1-078 | East Sidney-Quincy 138 kV | In Service |
| AF1-084 | Hartford-Almena 69 kV | Engineering & Procurement |
| AF1-086 | Madera-Westover South 115 kV | Under Construction |
| AF1-088 | Sullivan 345 kV | Active |
| AF1-091 | Varner - Sowers 138 kV | Engineering & Procurement |
| AF1-092 | Huntington Jct. 138 kV | Suspended |
| AF1-093 | Henderson-Stoneboro 69 kV | Engineering & Procurement |
| AF1-094 | Union City-Cambridge Springs 34.5 kV | Engineering & Procurement |
| AF1-098 | Four Mile Jct-Corry East 115 kV | Engineering & Procurement |
| AF1-118 | Sorenson-Desoto 345 kV | Engineering & Procurement |
| AF1-119 | Keystone-Desoto 345 kV | Engineering & Procurement |
| AF1-120 | East Fayette 2 138 kV | In Service |
| AF1-122 | Cardington-Liberty 69 kV | Suspended |
| AF1-134 | Philipsburg-Madera 34.5 kV | Engineering & Procurement |
| AF1-140 | Claysburg 23 kV | Engineering & Procurement |
| AF1-153 | Motion-Ridgeway 46 kV | Suspended |
| AF1-158 | Edison-Gravel Pit 138 kV | In Service |
| AF1-176 | Corey 138 kV | Active |
| AF1-202 | Keystone-Desoto 345 kV | Under Construction |
| AF1-205 | Napoleon Muni 138 kV | Suspended |
| AF1-206 | East Fayette 138 kV | Engineering & Procurement |
| AF1-207 | Reynolds-Olive #1 345 kV | Engineering & Procurement |
| AF1-215 | Olive-Reynolds 345 kV | In Service |
| AF1-223 | Keystone-Desoto 345 kV | Under Construction |
| AF1-227 | Marysville – Gunn Road 345 kV | In Service |
| AF1-229 | Galion-South Berwick 345 kV | Engineering & Procurement |
| AF1-268 | Desoto-Jay 138 kV | Engineering & Procurement |
| AF1-272 | Lucerne 115 kV | Engineering & Procurement |
| AF1-275 | Cole 345 kV | Engineering & Procurement |
| AF1-285 | Gunn Road 345 kV | Under Construction |
| AF1-291 | Tyler 34.5 kV | Engineering & Procurement |
| AF1-296 | Garden Plain 138 kV | Active |
| AF1-302 | Brookville-Squab Hollow 138 kV | Engineering & Procurement |
| AF1-322 | Meadow Lake 345 kV | Engineering & Procurement |
| AF1-331 | Twombley Road | Engineering & Procurement |
| AF2-004 | Beaver 345 kV | Engineering & Procurement |
| AF2-005 | Beaver 138 kV | Engineering & Procurement |
| AF2-008 | Sullivan 345 kV | Active |
| AF2-014 | Maddox Creek 345 kV | Engineering & Procurement |
| AF2-039 | Shawville-Clearfield 34.5 kV | Engineering & Procurement |
| AF2-041 | Nelson-Electric Junction 345 kV | Active |
| AF2-043 | Suffolk 34.5 kV | In Service |
| AF2-054 | Wan 34.5 kV | In Service |
| AF2-068 | Jay 138 kV | Active |
| AF2-069 | Crescent Ridge 138 kV | Active |
| AF2-077 | White Marsh 34.5 kV | In Service |
| AF2-078 | Reynolds-Olive #1 345 kV | Engineering & Procurement |
| AF2-083 | Kenzie Creek-Stone Lake 69 kV | Under Construction |
| AF2-088 | Shawville-Clearfield 34.5 kV II | Engineering & Procurement |
| AF2-095 | Davis Creek 138 kV | Active |
| AF2-103 | Haviland 138 kV | In Service |
| AF2-107 | Clifford 138 kV | Engineering & Procurement |
| AF2-122 | Kirk 138 kV | Under Construction |
| AF2-126 | Weston 69 kV II | Active |
| AF2-130 | Cobalt Corners 34.5 kV | In Service |
| AF2-132 | Reynolds-Olive #1 345 kV | Under Construction |
| AF2-133 | Reynolds-Olive #2 345 kV | Under Construction |
| AF2-134 | Olive-Reynolds #2 345 kV | In Service |
| AF2-142 | Nevada 345 kV | Active |
| AF2-143 | Powerton-Nevada 345 kV | Active |
| AF2-144 | Powhatan 34.5 kV | In Service |
| AF2-150 | Galion 138 kV | Under Construction |
| AF2-173 | Desoto 345 kV | Active |
| AF2-177 | Sorenson-DeSoto #2 345 kV | Active |
| AF2-187 | Brookside-Cloverdale 138 kV | Engineering & Procurement |
| AF2-199 | Nelson-Electric Junction 345 kV | Active |
| AF2-200 | Nelson-Electric Junction 345 kV | Active |
| AF2-205 | Olive-Reynolds #2 345 kV | Engineering & Procurement |
| AF2-224 | Allen 345 kV | Engineering & Procurement |
| AF2-225 | McLean 345 kV | Active |
| AF2-235 | Titusville-Oil Creek 34.5 kV | Withdrawn |
| AF2-238 | Mansfield-South Troy 34.5 kV | Engineering & Procurement |
| AF2-252 | Blue Mound 345 kV | Engineering & Procurement |
| AF2-294 | Thompson 34.5 kV | Suspended |
| AF2-335 | Delaware-Royerton 138 kV | Active |
| AF2-350 | Kensington 138 kV | Active |
| AF2-352 | Blue Mound 345 kV | Engineering & Procurement |
| AF2-359 | Olive-University Park 345 kV | Engineering & Procurement |
| AF2-375 | Ebersole-Fostoria 138 kV | Engineering & Procurement |
| AF2-376 | Timber Switch 138 kV | Active |
| AF2-377 | Logtown 138 kV | Engineering & Procurement |
| AF2-388 | Keystone-Desoto 345 kV | Active |
| AF2-389 | Kenzie Creek-Stone Lake 69 kV | Withdrawn |
| AF2-392 | Nelson-Dixon 138 kV | Active |
| AF2-396 | Stinger 138 kV | Active |
| AG1-007 | Tar River 12.5 kV | Engineering & Procurement |
| AG1-039 | Galion 138 kV II | Under Construction |
| AG1-040 | Morgan Street-Mount Hope 34.5 kV | Engineering & Procurement |
| AG1-047 | Jay 138 kV | Engineering & Procurement |
| AG1-054 | Potter-Harlan 69 kV | Engineering & Procurement |
| AG1-100 | Venango-Saegertown 34.5 kV | Engineering & Procurement |
| AG1-118 | Sugar Grove-Waterman 138kV | Active |
| AG1-124 | Gladstone 138 kV | Active |
| AG1-127 | Crego Rd 138 kV | Active |
| AG1-145 | Lightfoot 34.5 kV | In Service |
| AG1-193 | Utica Junction 34.5 kV | Suspended |
| AG1-197 | Morgan Street-Cochranton 34.5 kV | Suspended |
| AG1-198 | Union City 34.5 kV | Under Construction |
| AG1-207 | Vandalia 69 kV | Engineering & Procurement |
| AG1-226 | Dequine-Eugene 345 kV | Active |
| AG1-232 | Magley 138 kV | Engineering & Procurement |
| AG1-236 | Lanesville-Brokaw 345 kV | Active |
| AG1-237 | Dequine-Eugene 345 kV | Engineering & Procurement |
| AG1-281 | Claysburg-HCR Tap 46 kV | Engineering & Procurement |
| AG1-282 | Dunnsville 34.5 kV | Engineering & Procurement |
| AG1-301 | Miller REC-Warrior Ridge 46 kV | Engineering & Procurement |
| AG1-302 | Olive-Reynolds #1 345 kV | Under Construction |
| AG1-324 | Jay-Desoto 138 kV | Engineering & Procurement |
| AG1-349 | Olive-Reynolds #2 345 kV | Engineering & Procurement |
| AG1-365 | Allen 345 kV | Engineering & Procurement |
| AG1-366 | Allen 345 kV | Engineering & Procurement |
| AG1-367 | DeSoto 345 kV | Active |
| AG1-368 | Tillman 138 kV | Engineering & Procurement |
| AG1-369 | Logtown 138 kV | Engineering & Procurement |
| AG1-374 | Blue Mound 345 kV | Active |
| AG1-375 | Sorenson-Desoto 345 kV | Active |
| AG1-386 | Smith-Francis Junction 25 kV | In Service |
| AG1-410 | Maddox Creek-RP Mone 345 kV | Active |
| AG1-411 | Maddox Creek-RP Mone 345 kV | Active |
| AG1-433 | Keystone-DeSoto 345 kV | Active |
| AG1-436 | Olive-University Park 345 kV | Active |
| AG1-447 | Olive-University Park 345 kV | Active |
| AG1-462 | Cordova 345 kV | Active |
| AG1-478 | Wilmington 34.5 kV | Engineering & Procurement |
| AG1-494 | Boxwood-Riverville 138 kV | Active |
| AG1-500 | Beaver 345 kV | Engineering & Procurement |
| AG1-501 | Beaver 138 kV | Engineering & Procurement |
| AG1-554 | South Kenton 138 kV | Engineering & Procurement |
| AG1-555 | Dequine 345 kV | Engineering & Procurement |
| AG2-029 | Forest G. Hipple-Collingwood 345 kV | Active |
| AG2-057 | Cardington-Liberty 69 kV II | Active |
| AG2-068 | Heritage - Wake 500 kV | Active |
| AG2-069 | Heritage - Wake 500 kV | Active |
| AG2-085 | Delaware-Royerton 138 kV | Active |
| AG2-106 | Marysville-Flatlick 765 kV | Active |
| AG2-107 | Marysville-Flatlick 765 kV | Active |
| AG2-109 | Fitchville-New London 69 kV | Active |
| AG2-114 | Dresden-Pontiac Midpoint 345 kV | Active |
| AG2-119 | Galion-Roberts South 138 kV II | Active |
| AG2-149 | Galion-South Berwick 345 kV | Active |
| AG2-152 | Banister-Bear Skin 138 kV | Active |
| AG2-162 | Jefferson-Greentown 765 kV | Active |
| AG2-163 | Dequine-Eugene 345 kV | Active |
| AG2-164 | Jefferson-Greentown 765 kV | Active |
| AG2-165 | Dumont-Greentown 765 kV | Active |
| AG2-191 | Mississinewa 138 kV | Active |
| AG2-192 | Mississinewa 138 kV | Active |
| AG2-212 | Dumont-Greentown 765 kV | Active |
| AG2-216 | East Sidney-Quincy 138 kV | Active |
| AG2-219 | Jefferson-Greentown 765 kV | Active |
| AG2-230 | Dumont 345 kV | Active |
| AG2-245 | Olive - Reynolds #1 345 kV | Active |
| AG2-272 | Berry Hill 138 kV | Active |
| AG2-328 | Dumont - Greentown 765 kV | Active |
| AG2-329 | S Berwick - Galion 345 kV | Active |
| AG2-330 | Dumont - Greentown 765 kV | Active |
| AG2-331 | Jefferson-Greentown 765 kV | Active |
| AG2-363 | Powerton 345 kV | Active |
| AG2-364 | Powerton 345 kV | Active |
| AG2-369 | Heritage - Wake 500 kV | Active |
| AG2-370 | Tillman 138 kV | Active |
| AG2-400 | Allen 345 kV | Active |
| AG2-402 | Allen 345 kV | Active |
| AG2-405 | Continental 69 kV | Active |
| AG2-406 | Payne 69 kV | Active |
| AG2-408 | Allen 345 kV | Active |
| AG2-449 | Jefferson-Greentown 765 kV | Active |
| AG2-453 | Lasalle - Plano 345 kV | Active |
| AG2-456 | Pierce Brook-Lewis Run 230 kV | Active |
| AG2-457 | Pierce Brook - Lewis Run 230 kV | Active |
| AG2-491 | Meadow Lake 345 kV | Active |
| AG2-515 | Midway 345 kV III | Active |
| AG2-516 | Pecatonica 138kV | Active |
| AG2-519 | Royerton - Desoto 138 kV | Active |
| AG2-524 | LaSalle Station - Mazon 138 kV | Active |
| AG2-550 | Bluff Point - Randolph 138 kV | Active |
| AG2-551 | Bluff Point - Randolph 138 kV | Active |
| AG2-564 | Sulphur Springs 138 kV | Active |
| AG2-570 | Heritage - Wake 500 kV | Active |
| AG2-571 | Heritage - Wake 500 kV | Active |
| AG2-575 | Crego Rd. 138 kV | Active |
| AG2-582 | Flint Run 500 kV | Active |
| AG2-585 | Kensington 138kV | Active |
| AG2-660 | Nelson-Electric Junction 345 kV | Active |
| AH1-044 | Nelson - Electric Junction 345 kV | Active |
| AH1-047 | Marengo - Belvidere 138 kV | Active |
| AH1-060 | Cardington-Liberty 69 kV III | Active |
| AH1-069 | Jerome – Mohicanville 69 kV | Active |
| AH1-070 | Jerome – Mohicanville 69 kV | Active |
| AH1-075 | North Waldo - Wild Creek 138 kV | Active |
| AH1-146 | White Rock - Wayne 345 kV | Active |
| AH1-147 | White Rock - Wayne 345 kV | Active |
| AH1-150 | Nelson-Electric Junction 345 kV | Active |
| AH1-151 | Nelson-Electric Junction 345 kV | Active |
| AH1-153 | Dumont 345 kV | Active |
| AH1-164 | Oak Level - Tank Hill 138 kV | Active |
| AH1-196 | Prairie 345 kV | Active |
| AH1-234 | Wempletown - Paddock 345 kV | Active |
| AH1-272 | Argenta - Twin Branch 345 kV | Active |
| AH1-282 | Galion - Ohio Central 345 kV | Active |
| AH1-285 | Sandwich 138 kV | Active |
| AH1-302 | Olive - Reynolds 345 kV | Active |
| AH1-304 | Delaware-Van Buren 138 kV | Active |
| AH1-305 | Olive - Reynolds 345 kV | Active |
| AH1-306 | Mississinewa-Gaston 138 kV | Active |
| AH1-308 | Pennville - Adams 138 kV | Active |
| AH1-309 | Kenzie Creek-Colby 138 kV | Active |
| AH1-311 | Heartsease DP - Mayo Dunbar 115kV | Active |
| AH1-314 | East Danville 138 kV | Active |
| AH1-327 | Hardin Switch 345 kV | Active |
| AH1-338 | McGirr Rd - Ritchie Road 138kV | Active |
| AH1-339 | West Crawford 69 kV | Active |
| AH1-341 | Stillman - Dixon 138KV | Active |
| AH1-357 | Pierce Brook-Lewis Run 230kV | Active |
| AH1-358 | Pierce Brook-Lewis Run 230kV | Active |
| AH1-359 | Pierce Brook - Lewis Run 230 kV | Active |
| AH1-360 | Pierce Brook - Lewis Run 230 kV | Active |
| AH1-391 | Olive 138 kV | Active |
| AH1-392 | Gravel Pit-Kankakee 138 kV | Active |
| AH1-482 | Olive - Reynolds #2 345 kV | Active |
| AH1-535 | Nagel - Cane River 230 kV | Active |
| AH1-539 | South Kenton 138 kV | Active |
| AH1-541 | Chestnut 345 kV | Active |
| AH1-543 | Mulberry – Tazewell 345 kV | Active |
| AH1-567 | University Park 138 kV | Active |
| AH1-588 | Lewis Run - Pierce Brook 230 kV | Active |
| AH1-589 | Lewis Run - Pierce Brook 230 kV | Active |
| AH1-670 | Blue Mound-Chestnut 345 kV | Active |
| AH1-680 | Sammis - South Canton 345 kV | Active |
| AH1-698 | Braidwood 345 kV | Active |
| AH1-702 | Byron 345 kV | Active |
| AH1-711 | Lemoyne 345 kV | Active |
| AH1-714 | Lasalle 345 kV | Active |
| AH1-718 | Nelson 345 kV | Active |
| AH1-721 | Laurel-Cooper 161 kV | Active |
| AH1-735 | Richland 138 kV | Active |
| U2-072 | East Lima-Marysville 345kV | In Service |
| V1-011 | Haviland 138kV | In Service |
| V4-073 | Yankee 12.5kV | In Service |
| W1-056 | Ada-Dunkirk 69kV | In Service |
| W2-048 | Brokaw-Lanesville | In Service |
| W4-005 | Blue Mound-Latham | In Service |
| X1-042 | Watervliet | In Service |
| X2-022 | Brokaw-Lanesville | In Service |
| X3-005 | Wildwood 12kV | In Service |
| Y1-086 | Morgans Corner | In Service |
| Y3-023 | Country Side 12kV | In Service |
| Y3-024 | Bluff Point 12kV | In Service |
| Z2-044 | Whitakers 34.5kV | In Service |
| Z2-087 | Pontiac MidPoint-Brokaw 345kV | In Service |
| Z2-115 | Deer Creek 12.47kV | In Service |
| Z2-116 | Twin Branch 12.47kV | In Service |
Affected System - PJM Identified Violations
As part of PJM's analysis, PJM evaluated the potential impacts on tie line facilities between PJM and an affected system entity, which were identified per PJM planning analysis criteria. This upgrade may be required on the affected system portion of the tie line along with cost allocation of such upgrade if applicable, in coordination with the affected system. Depending on the affected system, this project may not be contingent on upgrade based on PJM planning analysis criteria, but may be contingent on this upgrade based on the Affected System Operator's planning criteria, provided in the Affected Systems Study Section, herein.
No cost allocated AFS Tie Line reinforcements were identified for this project in the Phase I System Impact Study load flow analysis.
System Reinforcement
- Type
- Load Flow
- TO
- NYISO
- RTEP ID / TO ID
- (Pending) / NYISO_CY17_13387
- Title
- East Sayre-North Waverly 115kV line upgrade - NYSEG (NYISO CY17 driven upgrade)
- Description
- North Waverly terminal equipment upgrades and a line reconductor of the NYSEG portion of the East Sayre – North Waverly 115kV line. (Install approximately twenty-six (26) new steel pole structures, one (1) 795 kcmil (26/7) ACSR conductor, and 36 Fiber OPGW). Final expected SUM ratings with both NYSEG & Penelec work complete = 218/251 MVA SN/SE. NYSEG uses LTE for Rate B, not STE like FirstEnergy. The earliest projected in-service date for this project is in 2026, but that timeframe may shift to complete the terminal equipment work at North Waverly. The final trip setting for the line will be updated during engineering and construction, but it must meet at least 176 MVA. Note: NYISO customers Q387, Q421, Q505 require an upgrade on the East Sayre-North Waverly 115 kV line as part of the CY17 study. NYSEG will complete work at North Waverly substation and the line reconductor/rebuild. FirstEnergy will complete work at East Sayre substation. Per NYISO, the rating that must be achieved for CY17 is 176/176/176 MVA Summer Normal/LTE/STE. NYSEG confirmed the new line ratings for the NYISO side (218/251/282 MVA Summer Normal/LTE/STE; 265/291/318 MVA Winter Normal/LTE/STE), but the East Sayre terminal needs to be upgraded since it is limiting. NYSEG uses LTE for Rate B, not STE like FirstEnergy.
- Total Cost ($USD)
- $10,525,000
- Allocated Cost ($USD)
- $0
- Time Estimate
- 32 Months
Info Note: AH1-690 contributes to the loading of an overloaded tie line facility between PJM and an affected system entity, which was identified per PJM planning analysis criteria. This upgrade may be required on the affected system portion of the tie line and will be confirmed in subsequent study phases, along with cost allocation of such upgrade if applicable, in coordination with the affected system.
| Facility | Contingency | |
|---|---|---|
| N.WAV115-26E.SAYRE 115.0 kV Ckt 1 line | (Any) |
No cost allocated AFS Tie Line reinforcements were identified for this project in the Phase I System Impact Study load flow analysis.
System Reinforcement
- Type
- Load Flow
- TO
- CPLE
- RTEP ID / TO ID
- (Pending) / TC2-CPLE-0001
- Title
- Person - VP Hendrick 230kV Line (Existing Line Uprate)
- Description
- Currently no costs since there is already a DEP project to reconductor to upgrade this line. This is the estimated ISD for the current project CPLE is developing. The Person - Hendrick 230 kV line will be reconductored with bundled 795 ACSS/TW and will have a rating 1195MVA.
- Total Cost ($USD)
- $0
- Allocated Cost ($USD)
- $0
- Time Estimate
- 0 to 48 Months
Info Note: AH1-690 contributes to the loading of an overloaded tie line facility between PJM and an affected system entity, which was identified per PJM planning analysis criteria. This upgrade may be required on the affected system portion of the tie line and will be confirmed in subsequent study phases, along with cost allocation of such upgrade if applicable, in coordination with the affected system.
| Facility | Contingency | |
|---|---|---|
| 6PERSON230 T-AC2-100 TAP 230.0 kV Ckt 1 line | (Any) |
Affected System - Non-PJM Identified Violations
In Phase I of the Cycle, PJM conducts an Affected System screen to identify any New Service Request with potential Affected System impacts. PJM initiates coordination with each Affected System Operator by providing a list of New Service Requests in the Cycle with potential impacts to their respective system. If the Affected System Operator indicates an Affected System Study is required, PJM will notify the Project Developer or Eligible Customer of the need for an Affected System Study. See below if any Affected System Operator requires a study for this project:
System Reinforcements
Based on the Phase I analysis results, this project may have a cost responsibility for the following System Reinforcements:
| TO | RTEP ID | Title | Allocated Cost ($USD) |
|---|---|---|---|
| ATSI | (Pending) / TC2-ATSI-006.a | Reconductor (possible rebuild) 30.25 miles of 954 ACSR 48/7 transmission line and line drops (line drops at Davis Besse) on the Davis Besse-Hayes 345 kV line | $128,073,552 |
| ATSI | (Pending) / TC2-ATSI-014.a | Reconductor (possible rebuild) 29.61 miles of transmission line and line drops ( line drops at Hayes) on the Beaver - Hayes Ckt 1 345 kV line | $122,797,286 |
| ATSI | (Pending) / TC2-ATSI-020.d | Reconductor (possible rebuild) 29.61 miles of transmission line and (4) line drops beginning at Beaver towards Davis Besse on the Beaver - Davis Besse Ckt 1 345 kV line | $106,455,624 |
| ATSI | (Pending) / TC2-ATSI-002.d | Reconductor (possible rebuild) 345kV 20.75 miles of transmission line and line drops at both remote ends | $89,885,811 |
| ATSI | (Pending) / TC2-ATSI-004.c | Reconductor (possible rebuild) 18.22 miles of 954 ACSR 48/7 transmission line and (3) line drops at Beaver on the Beaver - Carlisle Ckt 1 345 kV | $85,440,891 |
| ATSI | (Pending) / TC2-ATSI-008.f | Reconductor (possible rebuild) 18.7 miles of 954 ACSR 48/7 on the Davis Besse - AC2-103 TAP 345kV | $82,891,012 |
| ATSI | (Pending) / TC2-ATSI-015.a | Reconductor (possible rebuild) 21.68 miles of transmission line and (1) line drop (line drop at Lemoyne) on the Davis Besse - Lemoyne 345 kV | $68,126,768 |
| ATSI | (Pending) / TC2-ATSI-008.c | Reconductor (possible rebuild) 15.6 miles of 954 ACSR 45/7 on the Davis Besse - AC2-103 Tap 345 kV line | $68,030,782 |
| AEP | (Pending) / AEP-TC2-18700 | 05GUNN RD SW 345.0 kV to 05BOKESCRK 345.0 kV ckt 1- Rebuild | $43,588,025 |
| ATSI | (Pending) / TC2-ATSI-003 | Reconductor (possible rebuild) 12.19 miles of transmission line on the Beaver- Johnson Ckt 1 138kV | $42,140,488 |
| AEP | (Pending) / AEP-TC2-18681 | 05E LIMA 345.0 kV to 05SW LIM 345.0 kV ckt 1 - Rebuild | $40,254,475 |
| AEP | (Pending) / AEP-TC2-18647 | 05JAMES RIVR 138.0 kV to 05SOAPSTONE 138.0 kV ckt 1 - Rebuild | $40,000,000 |
| AEP | (Pending) / AEP-TC2-18671 | 05SOAPSTONE 138.0 kV to 05SCOTSV 138.0 kV ckt 1 - Rebuild | $40,000,000 |
| ATSI | (Pending) / TC2-ATSI-005.d | Reconductor (possible rebuild) 8.37 miles of 954 ACSR 48/7 transmission line on the Beaver - Lake Avenue Ckt 1 345 kV | $39,274,455 |
| ATSI | n9227.0 / TC1-ATSI-001.b | Upgrade T-line drops, overhead substation conductor and TL reconductor | $35,718,003 |
| ATSI | (Pending) / TC2-ATSI-016.c | Reconductor (possible rebuild) 10.46 miles of transmission line on the Ottawa-Lakeview 138 kV Q-121 line | $30,769,431 |
| AEP | (Pending) / AEP-TC2-18630 | 05BOXWD 138.0 kV to 05CLIFFR 138.0 kV ckt 1 - Rebuild | $21,800,000 |
| AEP | (Pending) / AEP-TC2-18636 | 05COLLEEN SS 138.0 kV to 05JAMES RIVR 138.0 kV ckt 1 - Rebuild | $18,000,000 |
| AEP | (Pending) / AEP-TC2-18665 | 05CLIFFR 138.0 kV to 05COLLEEN SS 138.0 kV ckt 1 - Rebuild | $14,700,000 |
| AEP | n6525.3 / AEPO0026f | Rebuild 7 miles of 138 kV line between Fremont Center and First Energy's We [...] fact that they own a portion of the line conductor that limits the branch. | $10,781,492 |
| ATSI | (Pending) / TC2-ATSI-001 | Reconductor (possible rebuild) 1.98 miles of 795 ACSR 36/1 transmission line and 795 ACSR 36/1 line drops on the Avon-Astor T11 Ckt Q11 138 kV line | $7,382,665 |
| ATSI | (Pending) / TC2-ATSI-002.g | Upgrade (2) 345kV circuit breakers at Bayshore and (2) at Davis Besse | $5,756,196 |
| ATSI | (Pending) / TC2-ATSI-021.a | Upgrade (4) circuit breakers at Beaver and Lake Ave (B:3,4,216,219) | $5,690,758 |
| ATSI | (Pending) / TC2-ATSI-014.d | Upgrade (4) circuit breakers at Beaver and Hayes (B88, B115, B3, B6) | $5,541,172 |
| AEP | (Pending) / AEP-TC2-18733 | 05BOKESCRK 345kV to 05MARYSV 345kV ckt 1 - Reconductor | $4,507,618 |
| AEP | (Pending) / AEP-TC2-18702 | 05SCOTSV 138.0 kV to AE1-108 POI 138.0 kV ckt 1 - Rebuild | $3,800,000 |
| ATSI | (Pending) / TC2-ATSI-015.c | Upgrade (2) 3000A CBs at Davis Besse and (1) 3000A CB at Lemoyne | $3,403,380 |
| ATSI | n6511 | Reconductor the 0.8 miles of transmission line between West Fremont-Fremont [...] section of limiting conductor and provide estimates for their replacement. | $3,347,779 |
| ATSI | (Pending) / TC2-ATSI-006.j | Upgrade (6) disconnect switches at Davis Besse (D27,28,29,30,34625,37) and (5) disconnect switches at Hayes (D20,19,16,13,14) | $3,221,706 |
| ATSI | (Pending) / TC2-ATSI-021.h | Upgrade (9) disconnect switches at Beaver and Lake Ave (D: 19,20,21,22, 212,215,217,218,220) | $2,814,238 |
| ATSI | (Pending) / TC2-ATSI-002.m | Upgrade (7) 3000A disconnect switches (D34545:N,S, D3454:W,E, A34673, D34561C, and 34623)and (2) B34545 impedance relays at Bayshore and Davis Besse | $2,809,622 |
| ATSI | (Pending) / TC2-ATSI-006.g | Upgrade B66 and B67 circuit breakers at Davis Besse substation | $2,771,525 |
| ATSI | (Pending) / TC2-ATSI-006.d | Upgrade (2) B18 & B12 345 kV Ciruit Breakers at Hayes | $2,771,525 |
| ATSI | (Pending) / TC2-ATSI-014.k | Upgrade (9) 3000A disconnect switches at Beaver and Hayes (D:74,92,93,116,4,5,7,8,11) | $2,768,527 |
| ATSI | (Pending) / TC2-ATSI-020.a | Upgrade B185 and B182 circuit breakers at Beaver | $2,748,721 |
| ATSI | (Pending) / TC2-ATSI-015.i | Upgrade (10) 3000A bus and line side disconnect switches at Davis Besse and Lemoyne (34624, A34604, D345:63A,63B,64D,64C,01N,01S,02W,02E) | $2,256,287 |
| ATSI | (Pending) / TC2-ATSI-021.k | Upgrade the (15) B216, B219, B3 and B4 2000 CTs at Beaver and Lake Ave | $1,974,100 |
| ATSI | (Pending) / TC2-ATSI-008.h | Upgrade Circuit Breaker 34564 at Davis Besse | $1,533,593 |
| ATSI | (Pending) / TC2-ATSI-008.l | Upgrade Circuit Breaker B65 at Davis Besse | $1,533,593 |
| ATSI | (Pending) / TC2-ATSI-015.g | Upgrade (2) B34501 and B34502 relay thermals at Lemoyne and (3) 34563 relay and meter thermals at Davis Besse | $1,220,083 |
| ATSI | (Pending) / TC2-ATSI-020.b | Upgrade (4) disconnect switches at Beaver (D186,184,181,183) | $1,211,059 |
| ATSI | (Pending) / TC2-ATSI-015.d | Upgrade (12) dual 1590 ACSR SCCIR at Davis Besse and Lemoyne | $1,182,159 |
| ATSI | (Pending) / TC2-ATSI-015.f | Upgrade the B34502 CB at Lemoyne | $1,180,945 |
| ATSI | (Pending) / TC2-ATSI-005.a | Upgrade (3) disconnect switches at Beaver (D:120,166,165) | $1,056,291 |
| ATSI | (Pending) / TC2-ATSI-002.b | Upgrade (3) 345kV bus and line side disconnect switches at Davis Besse substation at Davis Besse | $978,827 |
| ATSI | (Pending) / TC2-ATSI-017 | Upgrade (2) 2000A bus and line side disconnect switches at Bayshore | $948,616 |
| ATSI | (Pending) / TC2-ATSI-002.f | Upgrade (2) 345kV Wave Traps at Bayshore and (2) at Davis Besse | $898,671 |
| ATSI | (Pending) / TC2-ATSI-020.g | Upgrade (2) B185 and B182 revenue meter CTs at Beaver | $896,798 |
| ATSI | (Pending) / TC2-ATSI-006.e | Upgrade (2) B12 and B18 CTs at Hayes | $895,933 |
| ATSI | (Pending) / TC2-ATSI-014.h | Upgrade the B88 and B115 CTs at Beaver | $878,624 |
| ATSI | (Pending) / TC2-ATSI-006.c | Upgrade (2) Wave Traps at Davis Besse and (2) Wave Traps at Hayes | $865,394 |
| ATSI | (Pending) / TC2-ATSI-002.a | Upgrade (4) 1024.5 ACAR 24/13 sub conductors at Davis Besse | $812,704 |
| ATSI | (Pending) / TC2-ATSI-002.k | Upgrade the B34545 and 34562 (4) Meter and (2) Relay Thermals at Bayshore and Davis Besse | $738,363 |
| ATSI | (Pending) / TC2-ATSI-004.a | Upgrade D120 and D125 disconnect switches at Beaver substation | $727,201 |
| ATSI | (Pending) / TC2-ATSI-006.i | Upgrade (2) 9.6 Ohms impedance relays at Hayes and (2) 12.9 Ohms impedance relays at Davis Besse | $725,939 |
| ATSI | (Pending) / TC2-ATSI-008.a | Upgrade D41 and D42 disconnect switches at Davis Besse | $717,344 |
| ATSI | (Pending) / TC2-ATSI-014.j | Upgrade the B88 and B3 impedance relays at Beaver and Hayes | $711,914 |
| ATSI | (Pending) / TC2-ATSI-006.k | Upgrade (1) 1590 AACSR Phase A/C line drop at Davis Besse substation and (3) Phase 3 "B-B", Phase 1&2 "C-C", and shared node to wave trap line drops at Hayes | $637,420 |
| ATSI | (Pending) / TC2-ATSI-005.b | Upgrade (4) 954 ACSR 45/7 overhead line and line drops at Beaver Substation | $635,147 |
| ATSI | (Pending) / TC2-ATSI-021.c | Upgrade the (3) B216, B219 and B4 1500 CTs | $624,011 |
| ATSI | (Pending) / TC2-ATSI-015.b | Upgrade (4) L300 wavetraps at Davis Besse and Lemoyne | $611,784 |
| ATSI | (Pending) / TC2-ATSI-006.h | Upgrade B66 (1) meter and (1) relay thermals and B67 (1) meter thermal at Davis Besse substation | $606,826 |
| ATSI | (Pending) / TC2-ATSI-010 | Upgrade 4/0 CU sub conductor at FOWLES substation | $591,862 |
| ATSI | (Pending) / TC2-ATSI-015.e | Upgrade (2) 8.6 Ohm impedance relays at Davis Besse and (2) 7.8 Ohm impedance relays at Lemoyne | $582,117 |
| ATSI | (Pending) / TC2-ATSI-008.i | Upgrade (4) 1590 ACSR 45/7 sub conductors at Davis Besse | $560,559 |
| ATSI | (Pending) / TC2-ATSI-015.h | Upgrade (12) 4.00 SPS.AL PIPE at Lemoyne | $548,730 |
| ATSI | (Pending) / TC2-ATSI-016.b | Upgrade the standalone CT at Ottawa | $537,901 |
| ATSI | (Pending) / TC2-ATSI-002.i | Upgrade B34544 CT at BAYSHORE | $526,591 |
| ATSI | (Pending) / TC2-ATSI-014.c | Upgrade (2) L3000 wavetraps at Beaver and Hayes | $509,000 |
| ATSI | (Pending) / TC2-ATSI-014.f | Upgrade the B6 CT at Hayes | $507,727 |
| ATSI | (Pending) / TC2-ATSI-021.d | Upgrade (3) 1590 line drops at Beaver and Lake Ave | $504,767 |
| ATSI | (Pending) / TC2-ATSI-008.g | Upgrade (2) Wave Traps at Davis Besse | $460,035 |
| ATSI | (Pending) / TC2-ATSI-020.e | Upgrade (2) L3000 wavetraps at Beaver | $438,140 |
| ATSI | (Pending) / TC2-ATSI-023.a | Upgrade (2) line drop strands, one into Greenfield and one into Lakeview | $421,055 |
| ATSI | (Pending) / TC2-ATSI-016.a | Upgrade (1) line drop into Lakeview and (1) line drop into Ottawa | $421,055 |
| ATSI | (Pending) / TC2-ATSI-014.g | Upgrade (3) 1590 AAC line drops at Beaver (line drop to WT, Phase 1&3 "B-B", and SHARED NODE TO: WT, PH 2 / 5" AL, PH 1&3) | $413,179 |
| ATSI | (Pending) / TC2-ATSI.023.b | Upgrade the B242 relay thermal | $407,901 |
| ATSI | (Pending) / TC2-ATSI-008.m | Upgrade (2) B65 Meter Thermals at Davis Besse | $377,973 |
| ATSI | (Pending) / TC2-ATSI-008.j | Upgrade (2) 13.03 Ohm B65 Impedance Relays at Davis Besse | $377,973 |
| ATSI | (Pending) / TC2-ATSI-008.k | Upgrade (2) 6.65 Ohm B65 Impedance Relays at Davis Besse | $377,973 |
| ATSI | (Pending) / TC2-ATSI-021.f | Upgrade the (1) B216 relay thermal at Beaver | $372,642 |
| ATSI | (Pending) / TC2-ATSI-021.i | Upgrade the (2) B3 SEL411L impedance relays at Lake Ave | $372,642 |
| ATSI | (Pending) / TC2-ATSI-021.l | Upgrade the (2) B216 SEL411L impedance relays at Lake Ave | $372,642 |
| ATSI | (Pending) / TC2-ATSI-020.i | Upgrade B182 relay thermal at Beaver | $363,320 |
| ATSI | (Pending) / TC2-ATSI-020.f | Upgrade (2) B182 impedance relays at Beaver (SEL-321: Z2-BU & Z2-PR) | $363,320 |
| ATSI | (Pending) / TC2-ATSI-020.j | Upgrade (2) B182 impedance relays at Beaver (SEL-321: Z4-BU & Z4-PR) | $363,320 |
| ATSI | (Pending) / TC2-ATSI-014.i | Upgrade the 10A B115 relay and B88 meter thermal at Beaver | $355,957 |
| AEP | n6525.2 / AEPO0026d | Replace three Sub Cond 1590 AAC 61 Str at Fremont | $308,043 |
| ATSI | (Pending) / TC2-ATSI-019 | Upgrade phase 2 wave trap at Galion | $291,889 |
| ATSI | (Pending) / TC2-ATSI-002.j | Upgrade (1) 1590 ACSR 45/7 sub conductor at Davis Besse | $291,159 |
| ATSI | (Pending) / TC2-ATSI-016.d | Upgrade 795 ACSR B6 and B145 breaker leads and shared and (2) shared node subconductors at Lakeview | $269,825 |
| ATSI | (Pending) / TC2-ATSI-021.e | Upgrade the (1) B219 1200 CT to PVD at Beaver | $255,752 |
| ATSI | (Pending) / TC2-ATSI-020.h | Upgrade the B185 CT to PVD at Beaver | $249,354 |
| ATSI | (Pending) / TC2-ATSI-021.b | Upgrade 1590 AAC B3, B4, B216 and B219 breaker leads at Beaver and Lake Ave | $223,295 |
| ATSI | (Pending) / TC2-ATSI-006.f | Upgrade (10) 1590 ACSR sub conductor (B66 and B67 breaker leads, wave trap subconductor, Overheadline-34625) at Davis Besse and B12 breaker leads at Hayes | $217,221 |
| ATSI | (Pending) / TC2-ATSI-004.d | Upgrade (1) 3500 SAC 127 D120-to-B121 breaker lead at Beaver | $207,485 |
| ATSI | (Pending) / TC2-ATSI-004.b | Upgrade (1) 3000 SAC 169 line drop at Beaver | $205,889 |
| AEP | n9674.0 / AEPO0026b | Replace 1200 A Switch at Fremont | $205,362 |
| ATSI | (Pending) / TC2-ATSI-006.b | Upgrade 3500 SAC 127 OVERHEAD PIPE to disc sw. 34625 at Davis Besse and B18 breaker leads at Hayes | $202,209 |
| ATSI | (Pending) / TC2-ATSI-002.l | Upgrade (5) 4.00 SPS AL PIPE 61 sub conductors at BAYSHORE on the Bayshore - Davis Besse 345kV line | $195,449 |
| ATSI | (Pending) / TC2-ATSI-008.d | Upgrade (2) 3500 SAC 127 line drops at Davis Besse | $195,081 |
| ATSI | (Pending) / TC2-ATSI-008.b | Upgrade (1) 1024 ACAR 6E550-52-1 "A" line drop at Davis Besse | $195,081 |
| ATSI | (Pending) / TC2-ATSI-002.c | Upgrade 345kV 1033.5 AAC 61 sub conductors at Davis Besse substation at Davis Besse | $190,544 |
| ATSI | (Pending) / TC2-ATSI-002.e | Upgrade 345kV 3500 SAC 127 sub conductor at Davis Besse | $190,544 |
| ATSI | (Pending) / TC2-ATSI-021.m | Upgrade (8) 5.00 SPS.AL PIPE SCCIR at Beaver | $182,734 |
| ATSI | (Pending) / TC2-ATSI.023.c | Upgrade the (2) B96 and (2) B7 breaker leads at Lakeview and the (1) B242 to D241 lead at Greenfield | $175,138 |
| ATSI | (Pending) / TC2-ATSI-002.h | Upgrade (8) 1590 AAC 61 sub conductor at BAYSHORE | $156,064 |
| ATSI | (Pending) / TC2-ATSI-005c | Upgrade 3500 SAC 127 B161 (2) breaker leads and (1) B121-to-D120 breaker lead at Beaver | $149,954 |
| ATSI | (Pending) / TC2-ATSI-008.e | Upgrade 3500 SAC B65 breaker leads and subconductor (D42 to wave trap) at Davis Besse | $146,470 |
| ATSI | (Pending) / TC2-ATSI-020.c | Upgrade 3000 AAC B185 and B185 breaker leads at Beaver | $133,565 |
| ATSI | (Pending) / TC2-ATSI-021.g | Upgrade (1) 4.00 SPS.AL PIPE at Beaver | $130,151 |
| AEP | n9669.0 / AEPO0027e | Replace Sub cond 397.5 ACSR 26/7 at Howard | $130,000 |
| ATSI | (Pending) / TC2-ATSI-021.j | Upgrade (2) 2.50 SPS.AL PIPE SCCIR at Beaver | $126,718 |
| Dominion | (Pending) / TC2-PH1-DOM-2043 | Wreck and rebuild 0.93 miles of 230 kV Line 2241 between Hendrick and Persons with (2) 768.2 ACSS/TW (20/7) "MAUMEE" at 250 degrees C. Dominion portion of line only. | $123,688 |
| AEP | n9675.0 / AEPO0035a | Sag Study will be required on ACSR ~ 954 ~ 45/7, 18.3 miles line between South Berwick and Galion . | $107,857 |
| ATSI | (Pending) / TC2-ATSI-014.b | Upgrade 3500 SAC (2) B3 and (2) B6 breaker leads at Hayes | $106,511 |
| ATSI | (Pending) / TC2-ATSI-014.e | Upgrade the 1590 AAC (2) B88 and (2) B15 breaker leads at Beaver | $106,511 |
| AEP | (Pending) / AEP-TC2-18731 | 05WOLFCK 138kV to 05W.WATERT 138kV ckt 1 - Replace Equipment | $100,000 |
| AEP | n9676.0 / AEPO0033a | Sag Study will be required on 19.2 miles line between Fostoria and Lallen [...] tudy : S/N: 1409MVA S/E: 1887MVA.Rebuild/Reconductor, cost : $ 38.4 million | $99,840 |
| AEP | (Pending) / AEPAPRJV002 | Perform sag study on 397 ACSR between Clifford and Boxwood (13.7 miles) | $82,200 |
| AEP | n8383 | A sag study will be required on the 3.65 miles of ACSR ~ 397.5 ~ 30/7 ~ LARK~ Conductor to determine what mitigation | $78,000 |
| AEP | n8386 | A sag study will be required on the ~4.0 miles of ACSR ~ 397.5 ~ 30/7 ~ LARK~ Conductor to determine what mitigation | $78,000 |
| AEP | (Pending) / AEPAPRJV006_2 | Sag Study 397 ACSR between James River and Soapstone ~10 miles | $60,000 |
| Grand Total: | $1,232,419,117 | ||
Shown below are the details of the cost allocated, contingent, eliminated, topology and potential aggregate contributor reinforcements for this project. Please refer to the System Reinforcement table above and the information below for more detail.
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-006.a
- Title
- Reconductor (possible rebuild) 30.25 miles of 954 ACSR 48/7 transmission line and line drops (line drops at Davis Besse) on the Davis Besse-Hayes 345 kV line
- Description
- Reconductor (possible rebuild) 30.25 miles of 954 ACSR 48/7 transmission line and line drops (line drops at Davis Besse) on the Davis Besse-Hayes 345 kV line using dual (2) 1590 54/19 "Falcon" ACSS
- Total Cost ($USD)
- $179,916,169
- Allocated Cost ($USD)
- $128,073,552
- Time Estimate
- 90 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02DAV-BE-02HAYES 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-149 | 22.4 MW | 5.2% | $9,354,606 |
AG2-165 | 8.1 MW | 1.9% | $3,373,039 |
AG2-212 | 8.1 MW | 1.9% | $3,373,039 |
AG2-328 | 8.1 MW | 1.9% | $3,373,039 |
AG2-660 | 1.0 MW | 0.2% | $427,374 |
AH1-044 | 6.1 MW | 1.4% | $2,563,827 |
AH1-150 | 6.1 MW | 1.4% | $2,563,827 |
AH1-151 | 6.1 MW | 1.4% | $2,563,827 |
AH1-690 | 306.6 MW | 71.2% | $128,073,552 |
AH1-711 | 58.0 MW | 13.5% | $24,250,037 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-014.a
- Title
- Reconductor (possible rebuild) 29.61 miles of transmission line and line drops ( line drops at Hayes) on the Beaver - Hayes Ckt 1 345 kV line
- Description
- Reconductor (possible rebuild) 29.61 miles of transmission line and line drops ( line drops at Hayes) on the Beaver - Hayes Ckt 1 345 kV line using dual (2) 954 54/7 "Cardinal" ACSS
- Total Cost ($USD)
- $175,902,477
- Allocated Cost ($USD)
- $122,797,286
- Time Estimate
- 90 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02BEAVER-02HAYES 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-149 | 24.0 MW | 5.8% | $10,237,972 |
AG2-165 | 8.3 MW | 2.0% | $3,519,183 |
AG2-212 | 8.3 MW | 2.0% | $3,519,183 |
AG2-328 | 8.3 MW | 2.0% | $3,519,183 |
AG2-660 | 1.0 MW | 0.3% | $446,130 |
AH1-044 | 6.3 MW | 1.5% | $2,675,499 |
AH1-150 | 6.3 MW | 1.5% | $2,675,499 |
AH1-151 | 6.3 MW | 1.5% | $2,675,499 |
AH1-690 | 288.2 MW | 69.8% | $122,797,286 |
AH1-711 | 55.9 MW | 13.6% | $23,837,042 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-020.d
- Title
- Reconductor (possible rebuild) 29.61 miles of transmission line and (4) line drops beginning at Beaver towards Davis Besse on the Beaver - Davis Besse Ckt 1 345 kV line
- Description
- Reconductor (possible rebuild) 29.61 miles of transmission line and (4) line drops beginning at Beaver towards Davis Besse on the Beaver - Davis Besse Ckt 1 345 kV line using dual (2) 1590 54/19 "Falcon" ACSS
- Total Cost ($USD)
- $149,403,319
- Allocated Cost ($USD)
- $106,455,624
- Time Estimate
- 82 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02BEAVER-AC2-103 TAP 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-029 | 15.9 MW | 3.9% | $5,835,961 |
AG2-149 | 22.1 MW | 5.4% | $8,125,408 |
AG2-165 | 7.9 MW | 1.9% | $2,891,547 |
AG2-212 | 7.9 MW | 1.9% | $2,891,547 |
AG2-328 | 7.9 MW | 1.9% | $2,891,547 |
AH1-690 | 290.0 MW | 71.3% | $106,455,624 |
AH1-711 | 55.3 MW | 13.6% | $20,311,685 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-002.d
- Title
- Reconductor (possible rebuild) 345kV 20.75 miles of transmission line and line drops at both remote ends
- Description
- Reconductor (possible rebuild) 345kV 20.75 miles of transmission line and line drops at both remote ends using dual (2) 1590 54/19 "Falcon" ACSS
- Total Cost ($USD)
- $121,594,776
- Allocated Cost ($USD)
- $89,885,811
- Time Estimate
- 71 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02BAY SH-02DAV-BE 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-029 | 18.3 MW | 3.1% | $3,726,804 |
AG2-149 | 24.2 MW | 4.0% | $4,914,548 |
AG2-165 | 9.0 MW | 1.5% | $1,840,616 |
AG2-212 | 9.0 MW | 1.5% | $1,840,616 |
AG2-328 | 9.0 MW | 1.5% | $1,840,616 |
AG2-363 | 10.7 MW | 1.8% | $2,168,781 |
AG2-364 | 7.1 MW | 1.2% | $1,445,922 |
AG2-660 | 1.2 MW | 0.2% | $241,903 |
AH1-044 | 7.1 MW | 1.2% | $1,451,212 |
AH1-150 | 7.1 MW | 1.2% | $1,451,212 |
AH1-151 | 7.1 MW | 1.2% | $1,451,212 |
AH1-690 | 441.8 MW | 73.9% | $89,885,811 |
AH1-711 | 45.9 MW | 7.7% | $9,335,525 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-004.c
- Title
- Reconductor (possible rebuild) 18.22 miles of 954 ACSR 48/7 transmission line and (3) line drops at Beaver on the Beaver - Carlisle Ckt 1 345 kV
- Description
- Reconductor (possible rebuild) 18.22 miles of 954 ACSR 48/7 transmission line and (3) line drops at Beaver on the Beaver - Carlisle Ckt 1 345 kV using dual (2) 795 26/7 "Drake ACSS
- Total Cost ($USD)
- $109,211,408
- Allocated Cost ($USD)
- $85,440,891
- Time Estimate
- 63 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02BEAVER-02CARLIL 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-149 | 22.6 MW | 7.4% | $8,091,541 |
AH1-690 | 238.1 MW | 78.2% | $85,440,891 |
AH1-711 | 43.7 MW | 14.4% | $15,678,976 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-008.f
- Title
- Reconductor (possible rebuild) 18.7 miles of 954 ACSR 48/7 on the Davis Besse - AC2-103 TAP 345kV
- Description
- Reconductor (possible rebuild) 18.7 miles of 954 ACSR 48/7 on the Davis Besse - AC2-103 TAP 345kV using dual (2) 1272 54/19 "Pheasant" ACSS
- Total Cost ($USD)
- $111,822,087
- Allocated Cost ($USD)
- $82,891,012
- Time Estimate
- 64 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02DAV-BE-AC2-103 TAP 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-149 | 22.2 MW | 5.7% | $6,337,596 |
AG2-165 | 7.9 MW | 2.0% | $2,258,920 |
AG2-212 | 7.9 MW | 2.0% | $2,258,920 |
AG2-328 | 7.9 MW | 2.0% | $2,258,920 |
AH1-690 | 290.3 MW | 74.1% | $82,891,012 |
AH1-711 | 55.4 MW | 14.1% | $15,816,720 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-015.a
- Title
- Reconductor (possible rebuild) 21.68 miles of transmission line and (1) line drop (line drop at Lemoyne) on the Davis Besse - Lemoyne 345 kV
- Description
- Reconductor (possible rebuild) 21.68 miles of transmission line and (1) line drop (line drop at Lemoyne) on the Davis Besse - Lemoyne 345 kV using dual (2) 1272 54/19 "Pheasant" ACSS
- Total Cost ($USD)
- $126,131,949
- Allocated Cost ($USD)
- $68,126,768
- Time Estimate
- 73 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02DAV-BE-02LEMOYN 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-029 | 19.4 MW | 4.5% | $5,726,959 |
AG2-149 | 26.0 MW | 6.1% | $7,692,075 |
AG2-165 | 9.2 MW | 2.2% | $2,716,066 |
AG2-212 | 9.2 MW | 2.2% | $2,716,066 |
AG2-328 | 9.2 MW | 2.2% | $2,716,066 |
AG2-515 | 20.4 MW | 4.8% | $6,022,672 |
AG2-660 | 1.2 MW | 0.3% | $356,864 |
AH1-044 | 7.3 MW | 1.7% | $2,142,071 |
AH1-150 | 7.3 MW | 1.7% | $2,142,071 |
AH1-151 | 7.3 MW | 1.7% | $2,142,071 |
AH1-690 | 230.6 MW | 54.0% | $68,126,768 |
AH1-711 | 80.0 MW | 18.7% | $23,632,200 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-008.c
- Title
- Reconductor (possible rebuild) 15.6 miles of 954 ACSR 45/7 on the Davis Besse - AC2-103 Tap 345 kV line
- Description
- Reconductor (possible rebuild) 15.6 miles of 954 ACSR 45/7 on the Davis Besse - AC2-103 Tap 345 kV line using dual (2) 1272 54/19 "Pheasant" ACSS
- Total Cost ($USD)
- $91,775,258
- Allocated Cost ($USD)
- $68,030,782
- Time Estimate
- 57 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02DAV-BE-AC2-103 TAP 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-149 | 22.2 MW | 5.7% | $5,201,428 |
AG2-165 | 7.9 MW | 2.0% | $1,853,953 |
AG2-212 | 7.9 MW | 2.0% | $1,853,953 |
AG2-328 | 7.9 MW | 2.0% | $1,853,953 |
AH1-690 | 290.3 MW | 74.1% | $68,030,782 |
AH1-711 | 55.4 MW | 14.1% | $12,981,188 |
System Reinforcement
- Type
- Load Flow
- TO
- AEP
- RTEP ID / TO ID
- (Pending) / AEP-TC2-18700
- Title
- 05GUNN RD SW 345.0 kV to 05BOKESCRK 345.0 kV ckt 1- Rebuild
- Description
- AEP owned line, 16.54 miles of 345kV single circuit with PE conductor (1-1275 ACSR/PE 54/19) needs to be rebuilt
- Total Cost ($USD)
- $66,000,000
- Allocated Cost ($USD)
- $43,588,025
- Time Estimate
- 24 to 36 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 05GUNN RD SW-05BOKESCRK 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-029 | 15.7 MW | 11.7% | $7,690,422 |
AH1-539 | 10.9 MW | 8.0% | $5,308,563 |
AH1-690 | 89.1 MW | 66.0% | $43,588,025 |
AH1-711 | 19.2 MW | 14.3% | $9,412,990 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-003
- Title
- Reconductor (possible rebuild) 12.19 miles of transmission line on the Beaver- Johnson Ckt 1 138kV
- Description
- Reconductor (possible rebuild) 12.19 miles of transmission line on the Beaver- Johnson Ckt 1 138kV using single (1) 1272 45/7 "Bittern" ACSR
- Total Cost ($USD)
- $42,140,488
- Allocated Cost ($USD)
- $42,140,488
- Time Estimate
- 27 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02BEAVER-02JONSON 138.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AH1-690 | 41.5 MW | 100.0% | $42,140,488 |
System Reinforcement
- Type
- Load Flow
- TO
- AEP
- RTEP ID / TO ID
- (Pending) / AEP-TC2-18681
- Title
- 05E LIMA 345.0 kV to 05SW LIM 345.0 kV ckt 1 - Rebuild
- Description
- AEP owned line, ~14.66 miles (total 21.97 miles) of 345kV single circuit needs to be rebuilt. Existing conductor is 1-1414 ACSR/PE 62/19 & 1-1708.8 ACSR/AE 66/19
- Total Cost ($USD)
- $58,640,000
- Allocated Cost ($USD)
- $40,254,475
- Time Estimate
- 24 to 36 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 05E LIMA-05SW LIM 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-149 | 17.4 MW | 10.4% | $6,072,657 |
AH1-539 | 10.5 MW | 6.2% | $3,662,823 |
AH1-690 | 115.6 MW | 68.6% | $40,254,475 |
AH1-711 | 24.8 MW | 14.8% | $8,650,044 |
System Reinforcement
- Type
- Load Flow
- TO
- AEP
- RTEP ID / TO ID
- (Pending) / AEP-TC2-18647
- Title
- 05JAMES RIVR 138.0 kV to 05SOAPSTONE 138.0 kV ckt 1 - Rebuild
- Description
- Rebuild ~10 miles of 138 kV line between James River and Soapstone
- Total Cost ($USD)
- $40,000,000
- Allocated Cost ($USD)
- $40,000,000
- Time Estimate
- 24 to 48 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 05JAMES RIVR-05SOAPSTONE 138.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AH1-690 | 9.1 MW | 100.0% | $40,000,000 |
System Reinforcement
- Type
- Load Flow
- TO
- AEP
- RTEP ID / TO ID
- (Pending) / AEP-TC2-18671
- Title
- 05SOAPSTONE 138.0 kV to 05SCOTSV 138.0 kV ckt 1 - Rebuild
- Description
- Rebuild ~10.2 miles of 138 kV line between Soapstone and Scottsville
- Total Cost ($USD)
- $40,000,000
- Allocated Cost ($USD)
- $40,000,000
- Time Estimate
- 32 to 48 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 05SCOTSV-05SOAPSTONE 138.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AH1-690 | 9.1 MW | 100.0% | $40,000,000 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-005.d
- Title
- Reconductor (possible rebuild) 8.37 miles of 954 ACSR 48/7 transmission line on the Beaver - Lake Avenue Ckt 1 345 kV
- Description
- Reconductor (possible rebuild) 8.37 miles of 954 ACSR 48/7 transmission line on the Beaver - Lake Avenue Ckt 1 345 kV using dual (2) 954 54/7 "Cardinal" ACSS
- Total Cost ($USD)
- $50,053,445
- Allocated Cost ($USD)
- $39,274,455
- Time Estimate
- 38 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02BEAVER-02LAKEAVE 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-149 | 19.4 MW | 7.2% | $3,585,590 |
AH1-690 | 212.1 MW | 78.5% | $39,274,455 |
AH1-711 | 38.8 MW | 14.4% | $7,193,400 |
System Reinforcement: n9227.0
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- n9227.0 / TC1-ATSI-001.b
- Title
- Upgrade T-line drops, overhead substation conductor and TL reconductor
- Description
- Reconductor (possible rebuild) of 8.12 miles of dual transmission line and (2) single conductor line drops at Beaver on the Beaver-Lake Ave Ckt 2 345 kV line using triple (3) 1113 54/19 ""Finch"" ACSS"
- Total Cost ($USD)
- $48,873,856
- Allocated Cost ($USD)
- $35,718,003
- Time Estimate
- 37 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02BEAVER-02LAKEAVE 345.0 kV Ckt 2 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-149 | 28.3 MW | 6.9% | $3,393,878 |
AG2-165 | 8.9 MW | 2.2% | $1,069,072 |
AG2-212 | 8.9 MW | 2.2% | $1,069,072 |
AG2-328 | 8.9 MW | 2.2% | $1,069,072 |
AH1-690 | 297.6 MW | 73.1% | $35,718,003 |
AH1-711 | 54.6 MW | 13.4% | $6,554,759 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-016.c
- Title
- Reconductor (possible rebuild) 10.46 miles of transmission line on the Ottawa-Lakeview 138 kV Q-121 line
- Description
- Reconductor (possible rebuild) 10.46 miles of transmission line on the Ottawa-Lakeview 138 kV Q-121 line
- Total Cost ($USD)
- $38,463,247
- Allocated Cost ($USD)
- $30,769,431
- Time Estimate
- 25 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02LAKVEW-02OTTAWA 138.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-515 | 5.4 MW | 4.8% | $1,860,168 |
AH1-690 | 89.7 MW | 80.0% | $30,769,431 |
AH1-711 | 17.0 MW | 15.2% | $5,833,648 |
System Reinforcement
- Type
- Load Flow
- TO
- AEP
- RTEP ID / TO ID
- (Pending) / AEP-TC2-18630
- Title
- 05BOXWD 138.0 kV to 05CLIFFR 138.0 kV ckt 1 - Rebuild
- Description
- Rebuild ~5.3 miles of 138 kV line between Boxwood (specifically Structure 265-1) and Clifford (line is 1949 vintage); Replace 795 AAC station conductor at Boxwood; Replace 795 AAC station conductor at Clifford
- Total Cost ($USD)
- $21,800,000
- Allocated Cost ($USD)
- $21,800,000
- Time Estimate
- 24 to 36 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 05BOXWD-05CLIFFR 138.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AH1-690 | 9.1 MW | 100.0% | $21,800,000 |
System Reinforcement
- Type
- Load Flow
- TO
- AEP
- RTEP ID / TO ID
- (Pending) / AEP-TC2-18636
- Title
- 05COLLEEN SS 138.0 kV to 05JAMES RIVR 138.0 kV ckt 1 - Rebuild
- Description
- Rebuild ~4.5 miles of 138 kV line between Colleen and James River
- Total Cost ($USD)
- $18,000,000
- Allocated Cost ($USD)
- $18,000,000
- Time Estimate
- 24 to 48 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 05COLLEEN SS-05JAMES RIVR 138.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AH1-690 | 9.1 MW | 100.0% | $18,000,000 |
System Reinforcement
- Type
- Load Flow
- TO
- AEP
- RTEP ID / TO ID
- (Pending) / AEP-TC2-18665
- Title
- 05CLIFFR 138.0 kV to 05COLLEEN SS 138.0 kV ckt 1 - Rebuild
- Description
- Rebuild ~3.6 miles of 138 kV line between Clifford and Colleen (line is 1949 vintage); Replace 795 AAC station conductor at Clifford
- Total Cost ($USD)
- $14,700,000
- Allocated Cost ($USD)
- $14,700,000
- Time Estimate
- 24 to 36 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 05CLIFFR-05COLLEEN SS 138.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AH1-690 | 9.1 MW | 100.0% | $14,700,000 |
System Reinforcement: n6525.3
- Type
- Load Flow
- TO
- AEP
- RTEP ID / TO ID
- n6525.3 / AEPO0026f
- Title
- Rebuild 7 miles of 138 kV line between Fremont Center and First Energy's We [...] fact that they own a portion of the line conductor that limits the branch.
- Description
- Rebuild 7 miles of 138 kV line between Fremont Center and First Energy's West Fremont station with a bundled 795 ACSR conductor (Replacing ACSR ~ 1033.5 ~ 45/7 ~ ORTOLAN conductor). First Energy will need to be consulted due to the fact that they own a portion of the line conductor that limits the branch.
- Total Cost ($USD)
- $13,650,000
- Allocated Cost ($USD)
- $10,781,492
- Time Estimate
- 24 to 36 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02W.FREM-05FRMNT 138.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-515 | 6.0 MW | 4.8% | $659,940 |
AH1-690 | 97.6 MW | 79.0% | $10,781,492 |
AH1-711 | 20.0 MW | 16.2% | $2,208,568 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-001
- Title
- Reconductor (possible rebuild) 1.98 miles of 795 ACSR 36/1 transmission line and 795 ACSR 36/1 line drops on the Avon-Astor T11 Ckt Q11 138 kV line
- Description
- Reconductor (possible rebuild) 1.98 miles of 795 ACSR 36/1 transmission line and 795 ACSR 36/1 line drops on the Avon-Astor T11 Ckt Q11 138 kV line using single (1) 1590 45/7 "Lapwing" ACSR
- Total Cost ($USD)
- $7,382,665
- Allocated Cost ($USD)
- $7,382,665
- Time Estimate
- 18 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02ASQ-11-02AVQ1 138.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AH1-690 | 45.2 MW | 100.0% | $7,382,665 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-002.g
- Title
- Upgrade (2) 345kV circuit breakers at Bayshore and (2) at Davis Besse
- Description
- Upgrade (2) 345kV circuit breakers at Bayshore and (2) at Davis Besse
- Total Cost ($USD)
- $7,786,806
- Allocated Cost ($USD)
- $5,756,196
- Time Estimate
- 60 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02BAY SH-02DAV-BE 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-029 | 18.3 MW | 3.1% | $238,661 |
AG2-149 | 24.2 MW | 4.0% | $314,723 |
AG2-165 | 9.0 MW | 1.5% | $117,871 |
AG2-212 | 9.0 MW | 1.5% | $117,871 |
AG2-328 | 9.0 MW | 1.5% | $117,871 |
AG2-363 | 10.7 MW | 1.8% | $138,887 |
AG2-364 | 7.1 MW | 1.2% | $92,595 |
AG2-660 | 1.2 MW | 0.2% | $15,491 |
AH1-044 | 7.1 MW | 1.2% | $92,934 |
AH1-150 | 7.1 MW | 1.2% | $92,934 |
AH1-151 | 7.1 MW | 1.2% | $92,934 |
AH1-690 | 441.8 MW | 73.9% | $5,756,196 |
AH1-711 | 45.9 MW | 7.7% | $597,838 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-021.a
- Title
- Upgrade (4) circuit breakers at Beaver and Lake Ave (B:3,4,216,219)
- Description
- Upgrade (4) circuit breakers at Beaver and Lake Ave (B:3,4,216,219)
- Total Cost ($USD)
- $7,786,809
- Allocated Cost ($USD)
- $5,690,758
- Time Estimate
- 56 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02BEAVER-02LAKEAVE 345.0 kV Ckt 2 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-149 | 28.3 MW | 6.9% | $540,728 |
AG2-165 | 8.9 MW | 2.2% | $170,330 |
AG2-212 | 8.9 MW | 2.2% | $170,330 |
AG2-328 | 8.9 MW | 2.2% | $170,330 |
AH1-690 | 297.6 MW | 73.1% | $5,690,758 |
AH1-711 | 54.6 MW | 13.4% | $1,044,335 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-014.d
- Title
- Upgrade (4) circuit breakers at Beaver and Hayes (B88, B115, B3, B6)
- Description
- Upgrade (4) circuit breakers at Beaver and Hayes (B88, B115, B3, B6)
- Total Cost ($USD)
- $7,937,520
- Allocated Cost ($USD)
- $5,541,172
- Time Estimate
- 60 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02BEAVER-02HAYES 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-149 | 24.0 MW | 5.8% | $461,984 |
AG2-165 | 8.3 MW | 2.0% | $158,802 |
AG2-212 | 8.3 MW | 2.0% | $158,802 |
AG2-328 | 8.3 MW | 2.0% | $158,802 |
AG2-660 | 1.0 MW | 0.3% | $20,131 |
AH1-044 | 6.3 MW | 1.5% | $120,731 |
AH1-150 | 6.3 MW | 1.5% | $120,731 |
AH1-151 | 6.3 MW | 1.5% | $120,731 |
AH1-690 | 288.2 MW | 69.8% | $5,541,172 |
AH1-711 | 55.9 MW | 13.6% | $1,075,636 |
System Reinforcement
- Type
- Load Flow
- TO
- AEP
- RTEP ID / TO ID
- (Pending) / AEP-TC2-18733
- Title
- 05BOKESCRK 345kV to 05MARYSV 345kV ckt 1 - Reconductor
- Description
- Reconductor line between Marysville - Boke Creek 345 kV due to paper expanded line. New line will be 2-954 ACSR RAIL
- Total Cost ($USD)
- $6,810,000
- Allocated Cost ($USD)
- $4,507,618
- Time Estimate
- 48 to 52 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 05MARYSV-05BOKESCRK 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-029 | 15.4 MW | 11.7% | $794,214 |
AH1-539 | 10.6 MW | 8.0% | $547,769 |
AH1-690 | 87.6 MW | 66.2% | $4,507,618 |
AH1-711 | 18.7 MW | 14.1% | $960,398 |
System Reinforcement
- Type
- Load Flow
- TO
- AEP
- RTEP ID / TO ID
- (Pending) / AEP-TC2-18702
- Title
- 05SCOTSV 138.0 kV to AE1-108 POI 138.0 kV ckt 1 - Rebuild
- Description
- Rebuild ~0.9 miles of 138 kV line between AE1-108 and Scottsville
- Total Cost ($USD)
- $3,800,000
- Allocated Cost ($USD)
- $3,800,000
- Time Estimate
- 24 to 36 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 05SCOTSV-AE1-108 POI 138.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AH1-690 | 9.1 MW | 100.0% | $3,800,000 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-015.c
- Title
- Upgrade (2) 3000A CBs at Davis Besse and (1) 3000A CB at Lemoyne
- Description
- Upgrade (2) 3000A CBs at Davis Besse and (1) 3000A CB at Lemoyne
- Total Cost ($USD)
- $5,962,261
- Allocated Cost ($USD)
- $3,403,380
- Time Estimate
- 56 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02DAV-BE-02LEMOYN 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-029 | 19.4 MW | 4.8% | $286,099 |
AG2-149 | 26.0 MW | 6.4% | $384,270 |
AG2-165 | 9.2 MW | 2.3% | $135,685 |
AG2-212 | 9.2 MW | 2.3% | $135,685 |
AG2-328 | 9.2 MW | 2.3% | $135,685 |
AG2-515 | 20.4 MW | 5.0% | $300,872 |
AH1-690 | 230.6 MW | 57.1% | $3,403,380 |
AH1-711 | 80.0 MW | 19.8% | $1,180,584 |
System Reinforcement: n6511
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- n6511
- Title
- Reconductor the 0.8 miles of transmission line between West Fremont-Fremont [...] section of limiting conductor and provide estimates for their replacement.
- Description
- Reconductor the 0.8 miles of transmission line between West Fremont-Fremont 138 kV line. Existing transmission line conductor size 954 ACSR should be replaced with 954 ACSS AEP would need to replace their section of limiting conductor and provide estimates for their replacement.
- Total Cost ($USD)
- $4,238,484
- Allocated Cost ($USD)
- $3,347,779
- Time Estimate
- 17 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02W.FREM-05FRMNT 138.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-515 | 6.0 MW | 4.8% | $204,919 |
AH1-690 | 97.6 MW | 79.0% | $3,347,779 |
AH1-711 | 20.0 MW | 16.2% | $685,786 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-006.j
- Title
- Upgrade (6) disconnect switches at Davis Besse (D27,28,29,30,34625,37) and (5) disconnect switches at Hayes (D20,19,16,13,14)
- Description
- Upgrade (6) disconnect switches at Davis Besse (D27,28,29,30,34625,37) and (5) disconnect switches at Hayes (D20,19,16,13,14)
- Total Cost ($USD)
- $4,525,814
- Allocated Cost ($USD)
- $3,221,706
- Time Estimate
- 31 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02DAV-BE-02HAYES 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-149 | 22.4 MW | 5.2% | $235,316 |
AG2-165 | 8.1 MW | 1.9% | $84,849 |
AG2-212 | 8.1 MW | 1.9% | $84,849 |
AG2-328 | 8.1 MW | 1.9% | $84,849 |
AG2-660 | 1.0 MW | 0.2% | $10,751 |
AH1-044 | 6.1 MW | 1.4% | $64,493 |
AH1-150 | 6.1 MW | 1.4% | $64,493 |
AH1-151 | 6.1 MW | 1.4% | $64,493 |
AH1-690 | 306.6 MW | 71.2% | $3,221,706 |
AH1-711 | 58.0 MW | 13.5% | $610,013 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-021.h
- Title
- Upgrade (9) disconnect switches at Beaver and Lake Ave (D: 19,20,21,22, 212,215,217,218,220)
- Description
- Upgrade (9) disconnect switches at Beaver and Lake Ave (D: 19,20,21,22, 212,215,217,218,220)
- Total Cost ($USD)
- $3,850,794
- Allocated Cost ($USD)
- $2,814,238
- Time Estimate
- 39 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02BEAVER-02LAKEAVE 345.0 kV Ckt 2 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-149 | 28.3 MW | 6.9% | $267,405 |
AG2-165 | 8.9 MW | 2.2% | $84,233 |
AG2-212 | 8.9 MW | 2.2% | $84,233 |
AG2-328 | 8.9 MW | 2.2% | $84,233 |
AH1-690 | 297.6 MW | 73.1% | $2,814,238 |
AH1-711 | 54.6 MW | 13.4% | $516,453 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-002.m
- Title
- Upgrade (7) 3000A disconnect switches (D34545:N,S, D3454:W,E, A34673, D34561C, and 34623)and (2) B34545 impedance relays at Bayshore and Davis Besse
- Description
- Upgrade (7) 3000A disconnect switches (D34545:N,S, D3454:W,E, A34673, D34561C, and 34623)and (2) B34545 impedance relays at Bayshore and Davis Besse
- Total Cost ($USD)
- $3,544,138
- Allocated Cost ($USD)
- $2,809,622
- Time Estimate
- 42 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02BAY SH-02DAV-BE 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-029 | 18.3 MW | 3.3% | $116,491 |
AG2-149 | 24.2 MW | 4.3% | $153,617 |
AG2-165 | 9.0 MW | 1.6% | $57,533 |
AG2-212 | 9.0 MW | 1.6% | $57,533 |
AG2-328 | 9.0 MW | 1.6% | $57,533 |
AH1-690 | 441.8 MW | 79.3% | $2,809,622 |
AH1-711 | 45.9 MW | 8.2% | $291,807 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-006.g
- Title
- Upgrade B66 and B67 circuit breakers at Davis Besse substation
- Description
- Upgrade B66 and B67 circuit breakers at Davis Besse substation
- Total Cost ($USD)
- $3,893,404
- Allocated Cost ($USD)
- $2,771,525
- Time Estimate
- 56 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02DAV-BE-02HAYES 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-149 | 22.4 MW | 5.2% | $202,435 |
AG2-165 | 8.1 MW | 1.9% | $72,993 |
AG2-212 | 8.1 MW | 1.9% | $72,993 |
AG2-328 | 8.1 MW | 1.9% | $72,993 |
AG2-660 | 1.0 MW | 0.2% | $9,248 |
AH1-044 | 6.1 MW | 1.4% | $55,481 |
AH1-150 | 6.1 MW | 1.4% | $55,481 |
AH1-151 | 6.1 MW | 1.4% | $55,481 |
AH1-690 | 306.6 MW | 71.2% | $2,771,525 |
AH1-711 | 58.0 MW | 13.5% | $524,773 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-006.d
- Title
- Upgrade (2) B18 & B12 345 kV Ciruit Breakers at Hayes
- Description
- Upgrade (2) B18 & B12 345 kV Ciruit Breakers at Hayes
- Total Cost ($USD)
- $3,893,404
- Allocated Cost ($USD)
- $2,771,525
- Time Estimate
- 56 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02DAV-BE-02HAYES 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-149 | 22.4 MW | 5.2% | $202,435 |
AG2-165 | 8.1 MW | 1.9% | $72,993 |
AG2-212 | 8.1 MW | 1.9% | $72,993 |
AG2-328 | 8.1 MW | 1.9% | $72,993 |
AG2-660 | 1.0 MW | 0.2% | $9,248 |
AH1-044 | 6.1 MW | 1.4% | $55,481 |
AH1-150 | 6.1 MW | 1.4% | $55,481 |
AH1-151 | 6.1 MW | 1.4% | $55,481 |
AH1-690 | 306.6 MW | 71.2% | $2,771,525 |
AH1-711 | 58.0 MW | 13.5% | $524,773 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-014.k
- Title
- Upgrade (9) 3000A disconnect switches at Beaver and Hayes (D:74,92,93,116,4,5,7,8,11)
- Description
- Upgrade (9) 3000A disconnect switches at Beaver and Hayes (D:74,92,93,116,4,5,7,8,11)
- Total Cost ($USD)
- $3,774,791
- Allocated Cost ($USD)
- $2,768,527
- Time Estimate
- 29 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02BEAVER-02HAYES 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-149 | 24.0 MW | 6.1% | $230,820 |
AG2-165 | 8.3 MW | 2.1% | $79,342 |
AG2-212 | 8.3 MW | 2.1% | $79,342 |
AG2-328 | 8.3 MW | 2.1% | $79,342 |
AH1-690 | 288.2 MW | 73.3% | $2,768,527 |
AH1-711 | 55.9 MW | 14.2% | $537,418 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-020.a
- Title
- Upgrade B185 and B182 circuit breakers at Beaver
- Description
- Upgrade B185 and B182 circuit breakers at Beaver
- Total Cost ($USD)
- $3,893,404
- Allocated Cost ($USD)
- $2,748,721
- Time Estimate
- 56 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02BEAVER-AC2-103 TAP 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-029 | 15.9 MW | 4.1% | $158,348 |
AG2-149 | 22.5 MW | 5.7% | $223,755 |
AG2-165 | 7.8 MW | 2.0% | $77,540 |
AG2-212 | 7.8 MW | 2.0% | $77,540 |
AG2-328 | 7.8 MW | 2.0% | $77,540 |
AH1-690 | 275.9 MW | 70.6% | $2,748,721 |
AH1-711 | 53.2 MW | 13.6% | $529,961 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-015.i
- Title
- Upgrade (10) 3000A bus and line side disconnect switches at Davis Besse and Lemoyne (34624, A34604, D345:63A,63B,64D,64C,01N,01S,02W,02E)
- Description
- Upgrade (10) 3000A bus and line side disconnect switches at Davis Besse and Lemoyne (34624, A34604, D345:63A,63B,64D,64C,01N,01S,02W,02E)
- Total Cost ($USD)
- $3,952,709
- Allocated Cost ($USD)
- $2,256,287
- Time Estimate
- 29 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02DAV-BE-02LEMOYN 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-029 | 19.4 MW | 4.8% | $189,671 |
AG2-149 | 26.0 MW | 6.4% | $254,753 |
AG2-165 | 9.2 MW | 2.3% | $89,953 |
AG2-212 | 9.2 MW | 2.3% | $89,953 |
AG2-328 | 9.2 MW | 2.3% | $89,953 |
AG2-515 | 20.4 MW | 5.0% | $199,465 |
AH1-690 | 230.6 MW | 57.1% | $2,256,287 |
AH1-711 | 80.0 MW | 19.8% | $782,674 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-021.k
- Title
- Upgrade the (15) B216, B219, B3 and B4 2000 CTs at Beaver and Lake Ave
- Description
- Upgrade the (15) B216, B219, B3 and B4 2000 CTs at Beaver and Lake Ave
- Total Cost ($USD)
- $2,701,212
- Allocated Cost ($USD)
- $1,974,100
- Time Estimate
- 17 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02BEAVER-02LAKEAVE 345.0 kV Ckt 2 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-149 | 28.3 MW | 6.9% | $187,576 |
AG2-165 | 8.9 MW | 2.2% | $59,087 |
AG2-212 | 8.9 MW | 2.2% | $59,087 |
AG2-328 | 8.9 MW | 2.2% | $59,087 |
AH1-690 | 297.6 MW | 73.1% | $1,974,100 |
AH1-711 | 54.6 MW | 13.4% | $362,275 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-008.h
- Title
- Upgrade Circuit Breaker 34564 at Davis Besse
- Description
- Upgrade Circuit Breaker 34564 at Davis Besse
- Total Cost ($USD)
- $2,068,856
- Allocated Cost ($USD)
- $1,533,593
- Time Estimate
- 54 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02DAV-BE-AC2-103 TAP 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-149 | 22.2 MW | 5.7% | $117,254 |
AG2-165 | 7.9 MW | 2.0% | $41,793 |
AG2-212 | 7.9 MW | 2.0% | $41,793 |
AG2-328 | 7.9 MW | 2.0% | $41,793 |
AH1-690 | 290.3 MW | 74.1% | $1,533,593 |
AH1-711 | 55.4 MW | 14.1% | $292,630 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-008.l
- Title
- Upgrade Circuit Breaker B65 at Davis Besse
- Description
- Upgrade Circuit Breaker B65 at Davis Besse
- Total Cost ($USD)
- $2,068,856
- Allocated Cost ($USD)
- $1,533,593
- Time Estimate
- 54 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02DAV-BE-AC2-103 TAP 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-149 | 22.2 MW | 5.7% | $117,254 |
AG2-165 | 7.9 MW | 2.0% | $41,793 |
AG2-212 | 7.9 MW | 2.0% | $41,793 |
AG2-328 | 7.9 MW | 2.0% | $41,793 |
AH1-690 | 290.3 MW | 74.1% | $1,533,593 |
AH1-711 | 55.4 MW | 14.1% | $292,630 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-015.g
- Title
- Upgrade (2) B34501 and B34502 relay thermals at Lemoyne and (3) 34563 relay and meter thermals at Davis Besse
- Description
- Upgrade (2) B34501 and B34502 relay thermals at Lemoyne and (3) 34563 relay and meter thermals at Davis Besse
- Total Cost ($USD)
- $2,137,421
- Allocated Cost ($USD)
- $1,220,083
- Time Estimate
- 20 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02DAV-BE-02LEMOYN 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-029 | 19.4 MW | 4.8% | $102,564 |
AG2-149 | 26.0 MW | 6.4% | $137,758 |
AG2-165 | 9.2 MW | 2.3% | $48,642 |
AG2-212 | 9.2 MW | 2.3% | $48,642 |
AG2-328 | 9.2 MW | 2.3% | $48,642 |
AG2-515 | 20.4 MW | 5.0% | $107,860 |
AH1-690 | 230.6 MW | 57.1% | $1,220,083 |
AH1-711 | 80.0 MW | 19.8% | $423,229 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-020.b
- Title
- Upgrade (4) disconnect switches at Beaver (D186,184,181,183)
- Description
- Upgrade (4) disconnect switches at Beaver (D186,184,181,183)
- Total Cost ($USD)
- $1,699,640
- Allocated Cost ($USD)
- $1,211,059
- Time Estimate
- 25 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02BEAVER-AC2-103 TAP 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-029 | 15.9 MW | 3.9% | $66,391 |
AG2-149 | 22.1 MW | 5.4% | $92,436 |
AG2-165 | 7.9 MW | 1.9% | $32,895 |
AG2-212 | 7.9 MW | 1.9% | $32,895 |
AG2-328 | 7.9 MW | 1.9% | $32,895 |
AH1-690 | 290.0 MW | 71.3% | $1,211,059 |
AH1-711 | 55.3 MW | 13.6% | $231,070 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-015.d
- Title
- Upgrade (12) dual 1590 ACSR SCCIR at Davis Besse and Lemoyne
- Description
- Upgrade (12) dual 1590 ACSR SCCIR at Davis Besse and Lemoyne
- Total Cost ($USD)
- $2,070,983
- Allocated Cost ($USD)
- $1,182,159
- Time Estimate
- 12 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02DAV-BE-02LEMOYN 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-029 | 19.4 MW | 4.8% | $99,376 |
AG2-149 | 26.0 MW | 6.4% | $133,476 |
AG2-165 | 9.2 MW | 2.3% | $47,130 |
AG2-212 | 9.2 MW | 2.3% | $47,130 |
AG2-328 | 9.2 MW | 2.3% | $47,130 |
AG2-515 | 20.4 MW | 5.0% | $104,507 |
AH1-690 | 230.6 MW | 57.1% | $1,182,159 |
AH1-711 | 80.0 MW | 19.8% | $410,074 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-015.f
- Title
- Upgrade the B34502 CB at Lemoyne
- Description
- Upgrade the B34502 CB at Lemoyne
- Total Cost ($USD)
- $2,068,856
- Allocated Cost ($USD)
- $1,180,945
- Time Estimate
- 54 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02DAV-BE-02LEMOYN 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-029 | 19.4 MW | 4.8% | $99,274 |
AG2-149 | 26.0 MW | 6.4% | $133,338 |
AG2-165 | 9.2 MW | 2.3% | $47,082 |
AG2-212 | 9.2 MW | 2.3% | $47,082 |
AG2-328 | 9.2 MW | 2.3% | $47,082 |
AG2-515 | 20.4 MW | 5.0% | $104,400 |
AH1-690 | 230.6 MW | 57.1% | $1,180,945 |
AH1-711 | 80.0 MW | 19.8% | $409,653 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-005.a
- Title
- Upgrade (3) disconnect switches at Beaver (D:120,166,165)
- Description
- Upgrade (3) disconnect switches at Beaver (D:120,166,165)
- Total Cost ($USD)
- $1,350,788
- Allocated Cost ($USD)
- $1,056,291
- Time Estimate
- 37 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02BEAVER-02LAKEAVE 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-149 | 19.9 MW | 7.5% | $100,649 |
AH1-690 | 209.2 MW | 78.2% | $1,056,291 |
AH1-711 | 38.4 MW | 14.4% | $193,848 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-002.b
- Title
- Upgrade (3) 345kV bus and line side disconnect switches at Davis Besse substation at Davis Besse
- Description
- Upgrade (3) 345kV bus and line side disconnect switches at Davis Besse substation at Davis Besse
- Total Cost ($USD)
- $1,324,127
- Allocated Cost ($USD)
- $978,827
- Time Estimate
- 37 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02BAY SH-02DAV-BE 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-029 | 18.3 MW | 3.1% | $40,584 |
AG2-149 | 24.2 MW | 4.0% | $53,518 |
AG2-165 | 9.0 MW | 1.5% | $20,044 |
AG2-212 | 9.0 MW | 1.5% | $20,044 |
AG2-328 | 9.0 MW | 1.5% | $20,044 |
AG2-363 | 10.7 MW | 1.8% | $23,617 |
AG2-364 | 7.1 MW | 1.2% | $15,746 |
AG2-660 | 1.2 MW | 0.2% | $2,634 |
AH1-044 | 7.1 MW | 1.2% | $15,803 |
AH1-150 | 7.1 MW | 1.2% | $15,803 |
AH1-151 | 7.1 MW | 1.2% | $15,803 |
AH1-690 | 441.8 MW | 73.9% | $978,827 |
AH1-711 | 45.9 MW | 7.7% | $101,661 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-017
- Title
- Upgrade (2) 2000A bus and line side disconnect switches at Bayshore
- Description
- Upgrade (2) 2000A bus and line side disconnect switches at Bayshore
- Total Cost ($USD)
- $948,616
- Allocated Cost ($USD)
- $948,616
- Time Estimate
- 36 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02BAY SH-AH1-690 TP 345.0 kV Ckt 2 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AH1-690 | 718.0 MW | 100.0% | $948,616 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-002.f
- Title
- Upgrade (2) 345kV Wave Traps at Bayshore and (2) at Davis Besse
- Description
- Upgrade (2) 345kV Wave Traps at Bayshore and (2) at Davis Besse
- Total Cost ($USD)
- $1,215,694
- Allocated Cost ($USD)
- $898,671
- Time Estimate
- 22 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02BAY SH-02DAV-BE 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-029 | 18.3 MW | 3.1% | $37,260 |
AG2-149 | 24.2 MW | 4.0% | $49,135 |
AG2-165 | 9.0 MW | 1.5% | $18,402 |
AG2-212 | 9.0 MW | 1.5% | $18,402 |
AG2-328 | 9.0 MW | 1.5% | $18,402 |
AG2-363 | 10.7 MW | 1.8% | $21,683 |
AG2-364 | 7.1 MW | 1.2% | $14,456 |
AG2-660 | 1.2 MW | 0.2% | $2,419 |
AH1-044 | 7.1 MW | 1.2% | $14,509 |
AH1-150 | 7.1 MW | 1.2% | $14,509 |
AH1-151 | 7.1 MW | 1.2% | $14,509 |
AH1-690 | 441.8 MW | 73.9% | $898,671 |
AH1-711 | 45.9 MW | 7.7% | $93,336 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-020.g
- Title
- Upgrade (2) B185 and B182 revenue meter CTs at Beaver
- Description
- Upgrade (2) B185 and B182 revenue meter CTs at Beaver
- Total Cost ($USD)
- $1,258,596
- Allocated Cost ($USD)
- $896,798
- Time Estimate
- 21 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02BEAVER-AC2-103 TAP 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-029 | 15.9 MW | 3.9% | $49,163 |
AG2-149 | 22.1 MW | 5.4% | $68,450 |
AG2-165 | 7.9 MW | 1.9% | $24,359 |
AG2-212 | 7.9 MW | 1.9% | $24,359 |
AG2-328 | 7.9 MW | 1.9% | $24,359 |
AH1-690 | 290.0 MW | 71.3% | $896,798 |
AH1-711 | 55.3 MW | 13.6% | $171,109 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-006.e
- Title
- Upgrade (2) B12 and B18 CTs at Hayes
- Description
- Upgrade (2) B12 and B18 CTs at Hayes
- Total Cost ($USD)
- $1,258,596
- Allocated Cost ($USD)
- $895,933
- Time Estimate
- 21 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02DAV-BE-02HAYES 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-149 | 22.4 MW | 5.2% | $65,440 |
AG2-165 | 8.1 MW | 1.9% | $23,596 |
AG2-212 | 8.1 MW | 1.9% | $23,596 |
AG2-328 | 8.1 MW | 1.9% | $23,596 |
AG2-660 | 1.0 MW | 0.2% | $2,990 |
AH1-044 | 6.1 MW | 1.4% | $17,935 |
AH1-150 | 6.1 MW | 1.4% | $17,935 |
AH1-151 | 6.1 MW | 1.4% | $17,935 |
AH1-690 | 306.6 MW | 71.2% | $895,933 |
AH1-711 | 58.0 MW | 13.5% | $169,640 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-014.h
- Title
- Upgrade the B88 and B115 CTs at Beaver
- Description
- Upgrade the B88 and B115 CTs at Beaver
- Total Cost ($USD)
- $1,258,596
- Allocated Cost ($USD)
- $878,624
- Time Estimate
- 21 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02BEAVER-02HAYES 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-149 | 24.0 MW | 5.8% | $73,253 |
AG2-165 | 8.3 MW | 2.0% | $25,180 |
AG2-212 | 8.3 MW | 2.0% | $25,180 |
AG2-328 | 8.3 MW | 2.0% | $25,180 |
AG2-660 | 1.0 MW | 0.3% | $3,192 |
AH1-044 | 6.3 MW | 1.5% | $19,143 |
AH1-150 | 6.3 MW | 1.5% | $19,143 |
AH1-151 | 6.3 MW | 1.5% | $19,143 |
AH1-690 | 288.2 MW | 69.8% | $878,624 |
AH1-711 | 55.9 MW | 13.6% | $170,556 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-006.c
- Title
- Upgrade (2) Wave Traps at Davis Besse and (2) Wave Traps at Hayes
- Description
- Upgrade (2) Wave Traps at Davis Besse and (2) Wave Traps at Hayes
- Total Cost ($USD)
- $1,215,695
- Allocated Cost ($USD)
- $865,394
- Time Estimate
- 20 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02DAV-BE-02HAYES 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-149 | 22.4 MW | 5.2% | $63,209 |
AG2-165 | 8.1 MW | 1.9% | $22,792 |
AG2-212 | 8.1 MW | 1.9% | $22,792 |
AG2-328 | 8.1 MW | 1.9% | $22,792 |
AG2-660 | 1.0 MW | 0.2% | $2,888 |
AH1-044 | 6.1 MW | 1.4% | $17,324 |
AH1-150 | 6.1 MW | 1.4% | $17,324 |
AH1-151 | 6.1 MW | 1.4% | $17,324 |
AH1-690 | 306.6 MW | 71.2% | $865,394 |
AH1-711 | 58.0 MW | 13.5% | $163,858 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-002.a
- Title
- Upgrade (4) 1024.5 ACAR 24/13 sub conductors at Davis Besse
- Description
- Upgrade (4) 1024.5 ACAR 24/13 sub conductors at Davis Besse
- Total Cost ($USD)
- $1,099,401
- Allocated Cost ($USD)
- $812,704
- Time Estimate
- 14 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02BAY SH-02DAV-BE 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-029 | 18.3 MW | 3.1% | $33,696 |
AG2-149 | 24.2 MW | 4.0% | $44,435 |
AG2-165 | 9.0 MW | 1.5% | $16,642 |
AG2-212 | 9.0 MW | 1.5% | $16,642 |
AG2-328 | 9.0 MW | 1.5% | $16,642 |
AG2-363 | 10.7 MW | 1.8% | $19,609 |
AG2-364 | 7.1 MW | 1.2% | $13,073 |
AG2-660 | 1.2 MW | 0.2% | $2,187 |
AH1-044 | 7.1 MW | 1.2% | $13,121 |
AH1-150 | 7.1 MW | 1.2% | $13,121 |
AH1-151 | 7.1 MW | 1.2% | $13,121 |
AH1-690 | 441.8 MW | 73.9% | $812,704 |
AH1-711 | 45.9 MW | 7.7% | $84,407 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-002.k
- Title
- Upgrade the B34545 and 34562 (4) Meter and (2) Relay Thermals at Bayshore and Davis Besse
- Description
- Upgrade the B34545 and 34562 (4) Meter and (2) Relay Thermals at Bayshore and Davis Besse
- Total Cost ($USD)
- $998,835
- Allocated Cost ($USD)
- $738,363
- Time Estimate
- 19 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02BAY SH-02DAV-BE 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-029 | 18.3 MW | 3.1% | $30,614 |
AG2-149 | 24.2 MW | 4.0% | $40,370 |
AG2-165 | 9.0 MW | 1.5% | $15,120 |
AG2-212 | 9.0 MW | 1.5% | $15,120 |
AG2-328 | 9.0 MW | 1.5% | $15,120 |
AG2-363 | 10.7 MW | 1.8% | $17,815 |
AG2-364 | 7.1 MW | 1.2% | $11,877 |
AG2-660 | 1.2 MW | 0.2% | $1,987 |
AH1-044 | 7.1 MW | 1.2% | $11,921 |
AH1-150 | 7.1 MW | 1.2% | $11,921 |
AH1-151 | 7.1 MW | 1.2% | $11,921 |
AH1-690 | 441.8 MW | 73.9% | $738,363 |
AH1-711 | 45.9 MW | 7.7% | $76,686 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-004.a
- Title
- Upgrade D120 and D125 disconnect switches at Beaver substation
- Description
- Upgrade D120 and D125 disconnect switches at Beaver substation
- Total Cost ($USD)
- $929,516
- Allocated Cost ($USD)
- $727,201
- Time Estimate
- 22 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02BEAVER-02CARLIL 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-149 | 22.6 MW | 7.4% | $68,868 |
AH1-690 | 238.1 MW | 78.2% | $727,201 |
AH1-711 | 43.7 MW | 14.4% | $133,446 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-006.i
- Title
- Upgrade (2) 9.6 Ohms impedance relays at Hayes and (2) 12.9 Ohms impedance relays at Davis Besse
- Description
- Upgrade (2) 9.6 Ohms impedance relays at Hayes and (2) 12.9 Ohms impedance relays at Davis Besse
- Total Cost ($USD)
- $1,019,790
- Allocated Cost ($USD)
- $725,939
- Time Estimate
- 19 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02DAV-BE-02HAYES 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-149 | 22.4 MW | 5.2% | $53,023 |
AG2-165 | 8.1 MW | 1.9% | $19,119 |
AG2-212 | 8.1 MW | 1.9% | $19,119 |
AG2-328 | 8.1 MW | 1.9% | $19,119 |
AG2-660 | 1.0 MW | 0.2% | $2,422 |
AH1-044 | 6.1 MW | 1.4% | $14,532 |
AH1-150 | 6.1 MW | 1.4% | $14,532 |
AH1-151 | 6.1 MW | 1.4% | $14,532 |
AH1-690 | 306.6 MW | 71.2% | $725,939 |
AH1-711 | 58.0 MW | 13.5% | $137,453 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-008.a
- Title
- Upgrade D41 and D42 disconnect switches at Davis Besse
- Description
- Upgrade D41 and D42 disconnect switches at Davis Besse
- Total Cost ($USD)
- $967,716
- Allocated Cost ($USD)
- $717,344
- Time Estimate
- 36 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02DAV-BE-AC2-103 TAP 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-149 | 22.2 MW | 5.7% | $54,846 |
AG2-165 | 7.9 MW | 2.0% | $19,549 |
AG2-212 | 7.9 MW | 2.0% | $19,549 |
AG2-328 | 7.9 MW | 2.0% | $19,549 |
AH1-690 | 290.3 MW | 74.1% | $717,344 |
AH1-711 | 55.4 MW | 14.1% | $136,879 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-014.j
- Title
- Upgrade the B88 and B3 impedance relays at Beaver and Hayes
- Description
- Upgrade the B88 and B3 impedance relays at Beaver and Hayes
- Total Cost ($USD)
- $1,019,790
- Allocated Cost ($USD)
- $711,914
- Time Estimate
- 19 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02BEAVER-02HAYES 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-149 | 24.0 MW | 5.8% | $59,354 |
AG2-165 | 8.3 MW | 2.0% | $20,402 |
AG2-212 | 8.3 MW | 2.0% | $20,402 |
AG2-328 | 8.3 MW | 2.0% | $20,402 |
AG2-660 | 1.0 MW | 0.3% | $2,586 |
AH1-044 | 6.3 MW | 1.5% | $15,511 |
AH1-150 | 6.3 MW | 1.5% | $15,511 |
AH1-151 | 6.3 MW | 1.5% | $15,511 |
AH1-690 | 288.2 MW | 69.8% | $711,914 |
AH1-711 | 55.9 MW | 13.6% | $138,195 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-006.k
- Title
- Upgrade (1) 1590 AACSR Phase A/C line drop at Davis Besse substation and (3) Phase 3 "B-B", Phase 1&2 "C-C", and shared node to wave trap line drops at Hayes
- Description
- Upgrade (1) 1590 AACSR Phase A/C line drop at Davis Besse substation and (3) Phase 3 "B-B", Phase 1&2 "C-C", and shared node to wave trap line drops at Hayes
- Total Cost ($USD)
- $855,032
- Allocated Cost ($USD)
- $637,420
- Time Estimate
- 18 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02DAV-BE-02HAYES 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-149 | 22.4 MW | 5.4% | $46,558 |
AG2-165 | 8.1 MW | 2.0% | $16,788 |
AG2-212 | 8.1 MW | 2.0% | $16,788 |
AG2-328 | 8.1 MW | 2.0% | $16,788 |
AH1-690 | 306.6 MW | 74.5% | $637,420 |
AH1-711 | 58.0 MW | 14.1% | $120,692 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-005.b
- Title
- Upgrade (4) 954 ACSR 45/7 overhead line and line drops at Beaver Substation
- Description
- Upgrade (4) 954 ACSR 45/7 overhead line and line drops at Beaver Substation
- Total Cost ($USD)
- $809,465
- Allocated Cost ($USD)
- $635,147
- Time Estimate
- 15 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02BEAVER-02LAKEAVE 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-149 | 19.4 MW | 7.2% | $57,986 |
AH1-690 | 212.1 MW | 78.5% | $635,147 |
AH1-711 | 38.8 MW | 14.4% | $116,332 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-021.c
- Title
- Upgrade the (3) B216, B219 and B4 1500 CTs
- Description
- Upgrade the (3) B216, B219 and B4 1500 CTs
- Total Cost ($USD)
- $853,850
- Allocated Cost ($USD)
- $624,011
- Time Estimate
- 16 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02BEAVER-02LAKEAVE 345.0 kV Ckt 2 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-149 | 28.3 MW | 6.9% | $59,293 |
AG2-165 | 8.9 MW | 2.2% | $18,677 |
AG2-212 | 8.9 MW | 2.2% | $18,677 |
AG2-328 | 8.9 MW | 2.2% | $18,677 |
AH1-690 | 297.6 MW | 73.1% | $624,011 |
AH1-711 | 54.6 MW | 13.4% | $114,515 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-015.b
- Title
- Upgrade (4) L300 wavetraps at Davis Besse and Lemoyne
- Description
- Upgrade (4) L300 wavetraps at Davis Besse and Lemoyne
- Total Cost ($USD)
- $1,132,675
- Allocated Cost ($USD)
- $611,784
- Time Estimate
- 22 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02DAV-BE-02LEMOYN 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-029 | 19.4 MW | 4.5% | $51,429 |
AG2-149 | 26.0 MW | 6.1% | $69,075 |
AG2-165 | 9.2 MW | 2.2% | $24,390 |
AG2-212 | 9.2 MW | 2.2% | $24,390 |
AG2-328 | 9.2 MW | 2.2% | $24,390 |
AG2-515 | 20.4 MW | 4.8% | $54,084 |
AG2-660 | 1.2 MW | 0.3% | $3,205 |
AH1-044 | 7.3 MW | 1.7% | $19,236 |
AH1-150 | 7.3 MW | 1.7% | $19,236 |
AH1-151 | 7.3 MW | 1.7% | $19,236 |
AH1-690 | 230.6 MW | 54.0% | $611,784 |
AH1-711 | 80.0 MW | 18.7% | $212,219 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-006.h
- Title
- Upgrade B66 (1) meter and (1) relay thermals and B67 (1) meter thermal at Davis Besse substation
- Description
- Upgrade B66 (1) meter and (1) relay thermals and B67 (1) meter thermal at Davis Besse substation
- Total Cost ($USD)
- $852,462
- Allocated Cost ($USD)
- $606,826
- Time Estimate
- 19 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02DAV-BE-02HAYES 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-149 | 22.4 MW | 5.2% | $44,323 |
AG2-165 | 8.1 MW | 1.9% | $15,982 |
AG2-212 | 8.1 MW | 1.9% | $15,982 |
AG2-328 | 8.1 MW | 1.9% | $15,982 |
AG2-660 | 1.0 MW | 0.2% | $2,025 |
AH1-044 | 6.1 MW | 1.4% | $12,148 |
AH1-150 | 6.1 MW | 1.4% | $12,148 |
AH1-151 | 6.1 MW | 1.4% | $12,148 |
AH1-690 | 306.6 MW | 71.2% | $606,826 |
AH1-711 | 58.0 MW | 13.5% | $114,899 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-010
- Title
- Upgrade 4/0 CU sub conductor at FOWLES substation
- Description
- Upgrade 4/0 CU sub conductor at FOWLES substation
- Total Cost ($USD)
- $591,862
- Allocated Cost ($USD)
- $591,862
- Time Estimate
- 13 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02FWLSQ2-02PV Q2 138.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AH1-690 | 28.9 MW | 100.0% | $591,862 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-015.e
- Title
- Upgrade (2) 8.6 Ohm impedance relays at Davis Besse and (2) 7.8 Ohm impedance relays at Lemoyne
- Description
- Upgrade (2) 8.6 Ohm impedance relays at Davis Besse and (2) 7.8 Ohm impedance relays at Lemoyne
- Total Cost ($USD)
- $1,019,790
- Allocated Cost ($USD)
- $582,117
- Time Estimate
- 18 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02DAV-BE-02LEMOYN 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-029 | 19.4 MW | 4.8% | $48,935 |
AG2-149 | 26.0 MW | 6.4% | $65,726 |
AG2-165 | 9.2 MW | 2.3% | $23,208 |
AG2-212 | 9.2 MW | 2.3% | $23,208 |
AG2-328 | 9.2 MW | 2.3% | $23,208 |
AG2-515 | 20.4 MW | 5.0% | $51,461 |
AH1-690 | 230.6 MW | 57.1% | $582,117 |
AH1-711 | 80.0 MW | 19.8% | $201,928 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-008.i
- Title
- Upgrade (4) 1590 ACSR 45/7 sub conductors at Davis Besse
- Description
- Upgrade (4) 1590 ACSR 45/7 sub conductors at Davis Besse
- Total Cost ($USD)
- $756,208
- Allocated Cost ($USD)
- $560,559
- Time Estimate
- 13 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02DAV-BE-AC2-103 TAP 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-149 | 22.2 MW | 5.7% | $42,859 |
AG2-165 | 7.9 MW | 2.0% | $15,276 |
AG2-212 | 7.9 MW | 2.0% | $15,276 |
AG2-328 | 7.9 MW | 2.0% | $15,276 |
AH1-690 | 290.3 MW | 74.1% | $560,559 |
AH1-711 | 55.4 MW | 14.1% | $106,962 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-015.h
- Title
- Upgrade (12) 4.00 SPS.AL PIPE at Lemoyne
- Description
- Upgrade (12) 4.00 SPS.AL PIPE at Lemoyne
- Total Cost ($USD)
- $961,300
- Allocated Cost ($USD)
- $548,730
- Time Estimate
- 22 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02DAV-BE-02LEMOYN 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-029 | 19.4 MW | 4.8% | $46,128 |
AG2-149 | 26.0 MW | 6.4% | $61,956 |
AG2-165 | 9.2 MW | 2.3% | $21,877 |
AG2-212 | 9.2 MW | 2.3% | $21,877 |
AG2-328 | 9.2 MW | 2.3% | $21,877 |
AG2-515 | 20.4 MW | 5.0% | $48,510 |
AH1-690 | 230.6 MW | 57.1% | $548,730 |
AH1-711 | 80.0 MW | 19.8% | $190,346 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-016.b
- Title
- Upgrade the standalone CT at Ottawa
- Description
- Upgrade the standalone CT at Ottawa
- Total Cost ($USD)
- $672,402
- Allocated Cost ($USD)
- $537,901
- Time Estimate
- 20 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02LAKVEW-02OTTAWA 138.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-515 | 5.4 MW | 4.8% | $32,519 |
AH1-690 | 89.7 MW | 80.0% | $537,901 |
AH1-711 | 17.0 MW | 15.2% | $101,982 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-002.i
- Title
- Upgrade B34544 CT at BAYSHORE
- Description
- Upgrade B34544 CT at BAYSHORE
- Total Cost ($USD)
- $712,356
- Allocated Cost ($USD)
- $526,591
- Time Estimate
- 20 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02BAY SH-02DAV-BE 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-029 | 18.3 MW | 3.1% | $21,833 |
AG2-149 | 24.2 MW | 4.0% | $28,792 |
AG2-165 | 9.0 MW | 1.5% | $10,783 |
AG2-212 | 9.0 MW | 1.5% | $10,783 |
AG2-328 | 9.0 MW | 1.5% | $10,783 |
AG2-363 | 10.7 MW | 1.8% | $12,706 |
AG2-364 | 7.1 MW | 1.2% | $8,471 |
AG2-660 | 1.2 MW | 0.2% | $1,417 |
AH1-044 | 7.1 MW | 1.2% | $8,502 |
AH1-150 | 7.1 MW | 1.2% | $8,502 |
AH1-151 | 7.1 MW | 1.2% | $8,502 |
AH1-690 | 441.8 MW | 73.9% | $526,591 |
AH1-711 | 45.9 MW | 7.7% | $54,692 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-014.c
- Title
- Upgrade (2) L3000 wavetraps at Beaver and Hayes
- Description
- Upgrade (2) L3000 wavetraps at Beaver and Hayes
- Total Cost ($USD)
- $729,124
- Allocated Cost ($USD)
- $509,000
- Time Estimate
- 18 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02BEAVER-02HAYES 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-149 | 24.0 MW | 5.8% | $42,437 |
AG2-165 | 8.3 MW | 2.0% | $14,587 |
AG2-212 | 8.3 MW | 2.0% | $14,587 |
AG2-328 | 8.3 MW | 2.0% | $14,587 |
AG2-660 | 1.0 MW | 0.3% | $1,849 |
AH1-044 | 6.3 MW | 1.5% | $11,090 |
AH1-150 | 6.3 MW | 1.5% | $11,090 |
AH1-151 | 6.3 MW | 1.5% | $11,090 |
AH1-690 | 288.2 MW | 69.8% | $509,000 |
AH1-711 | 55.9 MW | 13.6% | $98,806 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-014.f
- Title
- Upgrade the B6 CT at Hayes
- Description
- Upgrade the B6 CT at Hayes
- Total Cost ($USD)
- $727,300
- Allocated Cost ($USD)
- $507,727
- Time Estimate
- 20 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02BEAVER-02HAYES 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-149 | 24.0 MW | 5.8% | $42,331 |
AG2-165 | 8.3 MW | 2.0% | $14,551 |
AG2-212 | 8.3 MW | 2.0% | $14,551 |
AG2-328 | 8.3 MW | 2.0% | $14,551 |
AG2-660 | 1.0 MW | 0.3% | $1,845 |
AH1-044 | 6.3 MW | 1.5% | $11,062 |
AH1-150 | 6.3 MW | 1.5% | $11,062 |
AH1-151 | 6.3 MW | 1.5% | $11,062 |
AH1-690 | 288.2 MW | 69.8% | $507,727 |
AH1-711 | 55.9 MW | 13.6% | $98,558 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-021.d
- Title
- Upgrade (3) 1590 line drops at Beaver and Lake Ave
- Description
- Upgrade (3) 1590 line drops at Beaver and Lake Ave
- Total Cost ($USD)
- $690,685
- Allocated Cost ($USD)
- $504,767
- Time Estimate
- 12 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02BEAVER-02LAKEAVE 345.0 kV Ckt 2 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-149 | 28.3 MW | 6.9% | $47,962 |
AG2-165 | 8.9 MW | 2.2% | $15,108 |
AG2-212 | 8.9 MW | 2.2% | $15,108 |
AG2-328 | 8.9 MW | 2.2% | $15,108 |
AH1-690 | 297.6 MW | 73.1% | $504,767 |
AH1-711 | 54.6 MW | 13.4% | $92,632 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-008.g
- Title
- Upgrade (2) Wave Traps at Davis Besse
- Description
- Upgrade (2) Wave Traps at Davis Besse
- Total Cost ($USD)
- $620,599
- Allocated Cost ($USD)
- $460,035
- Time Estimate
- 20 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02DAV-BE-AC2-103 TAP 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-149 | 22.2 MW | 5.7% | $35,173 |
AG2-165 | 7.9 MW | 2.0% | $12,537 |
AG2-212 | 7.9 MW | 2.0% | $12,537 |
AG2-328 | 7.9 MW | 2.0% | $12,537 |
AH1-690 | 290.3 MW | 74.1% | $460,035 |
AH1-711 | 55.4 MW | 14.1% | $87,781 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-020.e
- Title
- Upgrade (2) L3000 wavetraps at Beaver
- Description
- Upgrade (2) L3000 wavetraps at Beaver
- Total Cost ($USD)
- $620,600
- Allocated Cost ($USD)
- $438,140
- Time Estimate
- 18 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02BEAVER-AC2-103 TAP 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-029 | 15.9 MW | 4.1% | $25,240 |
AG2-149 | 22.5 MW | 5.7% | $35,666 |
AG2-165 | 7.8 MW | 2.0% | $12,360 |
AG2-212 | 7.8 MW | 2.0% | $12,360 |
AG2-328 | 7.8 MW | 2.0% | $12,360 |
AH1-690 | 275.9 MW | 70.6% | $438,140 |
AH1-711 | 53.2 MW | 13.6% | $84,475 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-023.a
- Title
- Upgrade (2) line drop strands, one into Greenfield and one into Lakeview
- Description
- Upgrade (2) line drop strands, one into Greenfield and one into Lakeview using single (1) 954 45/7 "Rail" ACSR
- Total Cost ($USD)
- $526,339
- Allocated Cost ($USD)
- $421,055
- Time Estimate
- 12 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02GRNFLD-02LAKVEW 138.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-515 | 5.4 MW | 4.8% | $25,455 |
AH1-690 | 89.7 MW | 80.0% | $421,055 |
AH1-711 | 17.0 MW | 15.2% | $79,829 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-016.a
- Title
- Upgrade (1) line drop into Lakeview and (1) line drop into Ottawa
- Description
- Upgrade (1) line drop into Lakeview and (1) line drop into Ottawa
- Total Cost ($USD)
- $526,339
- Allocated Cost ($USD)
- $421,055
- Time Estimate
- 13 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02LAKVEW-02OTTAWA 138.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-515 | 5.4 MW | 4.8% | $25,455 |
AH1-690 | 89.7 MW | 80.0% | $421,055 |
AH1-711 | 17.0 MW | 15.2% | $79,829 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-014.g
- Title
- Upgrade (3) 1590 AAC line drops at Beaver (line drop to WT, Phase 1&3 "B-B", and SHARED NODE TO: WT, PH 2 / 5" AL, PH 1&3)
- Description
- Upgrade (3) 1590 AAC line drops at Beaver (line drop to WT, Phase 1&3 "B-B", and SHARED NODE TO: WT, PH 2 / 5" AL, PH 1&3) using dual (2) 954 54/7 "Cardinal" ACSS
- Total Cost ($USD)
- $591,863
- Allocated Cost ($USD)
- $413,179
- Time Estimate
- 18 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02BEAVER-02HAYES 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-149 | 24.0 MW | 5.8% | $34,448 |
AG2-165 | 8.3 MW | 2.0% | $11,841 |
AG2-212 | 8.3 MW | 2.0% | $11,841 |
AG2-328 | 8.3 MW | 2.0% | $11,841 |
AG2-660 | 1.0 MW | 0.3% | $1,501 |
AH1-044 | 6.3 MW | 1.5% | $9,002 |
AH1-150 | 6.3 MW | 1.5% | $9,002 |
AH1-151 | 6.3 MW | 1.5% | $9,002 |
AH1-690 | 288.2 MW | 69.8% | $413,179 |
AH1-711 | 55.9 MW | 13.6% | $80,205 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI.023.b
- Title
- Upgrade the B242 relay thermal
- Description
- Upgrade the B242 relay thermal
- Total Cost ($USD)
- $509,895
- Allocated Cost ($USD)
- $407,901
- Time Estimate
- 18 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02GRNFLD-02LAKVEW 138.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-515 | 5.4 MW | 4.8% | $24,660 |
AH1-690 | 89.7 MW | 80.0% | $407,901 |
AH1-711 | 17.0 MW | 15.2% | $77,335 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-008.m
- Title
- Upgrade (2) B65 Meter Thermals at Davis Besse
- Description
- Upgrade (2) B65 Meter Thermals at Davis Besse
- Total Cost ($USD)
- $509,895
- Allocated Cost ($USD)
- $377,973
- Time Estimate
- 18 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02DAV-BE-AC2-103 TAP 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-149 | 22.2 MW | 5.7% | $28,899 |
AG2-165 | 7.9 MW | 2.0% | $10,300 |
AG2-212 | 7.9 MW | 2.0% | $10,300 |
AG2-328 | 7.9 MW | 2.0% | $10,300 |
AH1-690 | 290.3 MW | 74.1% | $377,973 |
AH1-711 | 55.4 MW | 14.1% | $72,122 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-008.j
- Title
- Upgrade (2) 13.03 Ohm B65 Impedance Relays at Davis Besse
- Description
- Upgrade (2) 13.03 Ohm B65 Impedance Relays at Davis Besse
- Total Cost ($USD)
- $509,895
- Allocated Cost ($USD)
- $377,973
- Time Estimate
- 18 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02DAV-BE-AC2-103 TAP 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-149 | 22.2 MW | 5.7% | $28,899 |
AG2-165 | 7.9 MW | 2.0% | $10,300 |
AG2-212 | 7.9 MW | 2.0% | $10,300 |
AG2-328 | 7.9 MW | 2.0% | $10,300 |
AH1-690 | 290.3 MW | 74.1% | $377,973 |
AH1-711 | 55.4 MW | 14.1% | $72,122 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-008.k
- Title
- Upgrade (2) 6.65 Ohm B65 Impedance Relays at Davis Besse
- Description
- Upgrade (2) 6.65 Ohm B65 Impedance Relays at Davis Besse
- Total Cost ($USD)
- $509,895
- Allocated Cost ($USD)
- $377,973
- Time Estimate
- 18 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02DAV-BE-AC2-103 TAP 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-149 | 22.2 MW | 5.7% | $28,899 |
AG2-165 | 7.9 MW | 2.0% | $10,300 |
AG2-212 | 7.9 MW | 2.0% | $10,300 |
AG2-328 | 7.9 MW | 2.0% | $10,300 |
AH1-690 | 290.3 MW | 74.1% | $377,973 |
AH1-711 | 55.4 MW | 14.1% | $72,122 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-021.f
- Title
- Upgrade the (1) B216 relay thermal at Beaver
- Description
- Upgrade the (1) B216 relay thermal at Beaver
- Total Cost ($USD)
- $509,895
- Allocated Cost ($USD)
- $372,642
- Time Estimate
- 18 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02BEAVER-02LAKEAVE 345.0 kV Ckt 2 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-149 | 28.3 MW | 6.9% | $35,408 |
AG2-165 | 8.9 MW | 2.2% | $11,153 |
AG2-212 | 8.9 MW | 2.2% | $11,153 |
AG2-328 | 8.9 MW | 2.2% | $11,153 |
AH1-690 | 297.6 MW | 73.1% | $372,642 |
AH1-711 | 54.6 MW | 13.4% | $68,385 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-021.i
- Title
- Upgrade the (2) B3 SEL411L impedance relays at Lake Ave
- Description
- Upgrade the (2) B3 SEL411L impedance relays at Lake Ave
- Total Cost ($USD)
- $509,895
- Allocated Cost ($USD)
- $372,642
- Time Estimate
- 18 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02BEAVER-02LAKEAVE 345.0 kV Ckt 2 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-149 | 28.3 MW | 6.9% | $35,408 |
AG2-165 | 8.9 MW | 2.2% | $11,153 |
AG2-212 | 8.9 MW | 2.2% | $11,153 |
AG2-328 | 8.9 MW | 2.2% | $11,153 |
AH1-690 | 297.6 MW | 73.1% | $372,642 |
AH1-711 | 54.6 MW | 13.4% | $68,385 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-021.l
- Title
- Upgrade the (2) B216 SEL411L impedance relays at Lake Ave
- Description
- Upgrade the (2) B216 SEL411L impedance relays at Lake Ave
- Total Cost ($USD)
- $509,895
- Allocated Cost ($USD)
- $372,642
- Time Estimate
- 18 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02BEAVER-02LAKEAVE 345.0 kV Ckt 2 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-149 | 28.3 MW | 6.9% | $35,408 |
AG2-165 | 8.9 MW | 2.2% | $11,153 |
AG2-212 | 8.9 MW | 2.2% | $11,153 |
AG2-328 | 8.9 MW | 2.2% | $11,153 |
AH1-690 | 297.6 MW | 73.1% | $372,642 |
AH1-711 | 54.6 MW | 13.4% | $68,385 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-020.i
- Title
- Upgrade B182 relay thermal at Beaver
- Description
- Upgrade B182 relay thermal at Beaver
- Total Cost ($USD)
- $509,895
- Allocated Cost ($USD)
- $363,320
- Time Estimate
- 19 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02BEAVER-AC2-103 TAP 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-029 | 15.9 MW | 3.9% | $19,917 |
AG2-149 | 22.1 MW | 5.4% | $27,731 |
AG2-165 | 7.9 MW | 1.9% | $9,868 |
AG2-212 | 7.9 MW | 1.9% | $9,868 |
AG2-328 | 7.9 MW | 1.9% | $9,868 |
AH1-690 | 290.0 MW | 71.3% | $363,320 |
AH1-711 | 55.3 MW | 13.6% | $69,321 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-020.f
- Title
- Upgrade (2) B182 impedance relays at Beaver (SEL-321: Z2-BU & Z2-PR)
- Description
- Upgrade (2) B182 impedance relays at Beaver (SEL-321: Z2-BU & Z2-PR)
- Total Cost ($USD)
- $509,895
- Allocated Cost ($USD)
- $363,320
- Time Estimate
- 19 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02BEAVER-AC2-103 TAP 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-029 | 15.9 MW | 3.9% | $19,917 |
AG2-149 | 22.1 MW | 5.4% | $27,731 |
AG2-165 | 7.9 MW | 1.9% | $9,868 |
AG2-212 | 7.9 MW | 1.9% | $9,868 |
AG2-328 | 7.9 MW | 1.9% | $9,868 |
AH1-690 | 290.0 MW | 71.3% | $363,320 |
AH1-711 | 55.3 MW | 13.6% | $69,321 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-020.j
- Title
- Upgrade (2) B182 impedance relays at Beaver (SEL-321: Z4-BU & Z4-PR)
- Description
- Upgrade (2) B182 impedance relays at Beaver (SEL-321: Z4-BU & Z4-PR)
- Total Cost ($USD)
- $509,895
- Allocated Cost ($USD)
- $363,320
- Time Estimate
- 19 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02BEAVER-AC2-103 TAP 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-029 | 15.9 MW | 3.9% | $19,917 |
AG2-149 | 22.1 MW | 5.4% | $27,731 |
AG2-165 | 7.9 MW | 1.9% | $9,868 |
AG2-212 | 7.9 MW | 1.9% | $9,868 |
AG2-328 | 7.9 MW | 1.9% | $9,868 |
AH1-690 | 290.0 MW | 71.3% | $363,320 |
AH1-711 | 55.3 MW | 13.6% | $69,321 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-014.i
- Title
- Upgrade the 10A B115 relay and B88 meter thermal at Beaver
- Description
- Upgrade the 10A B115 relay and B88 meter thermal at Beaver
- Total Cost ($USD)
- $509,895
- Allocated Cost ($USD)
- $355,957
- Time Estimate
- 18 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02BEAVER-02HAYES 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-149 | 24.0 MW | 5.8% | $29,677 |
AG2-165 | 8.3 MW | 2.0% | $10,201 |
AG2-212 | 8.3 MW | 2.0% | $10,201 |
AG2-328 | 8.3 MW | 2.0% | $10,201 |
AG2-660 | 1.0 MW | 0.3% | $1,293 |
AH1-044 | 6.3 MW | 1.5% | $7,756 |
AH1-150 | 6.3 MW | 1.5% | $7,756 |
AH1-151 | 6.3 MW | 1.5% | $7,756 |
AH1-690 | 288.2 MW | 69.8% | $355,957 |
AH1-711 | 55.9 MW | 13.6% | $69,097 |
System Reinforcement: n6525.2
- Type
- Load Flow
- TO
- AEP
- RTEP ID / TO ID
- n6525.2 / AEPO0026d
- Title
- Replace three Sub Cond 1590 AAC 61 Str at Fremont
- Description
- Total Cost ($USD)
- $390,000
- Allocated Cost ($USD)
- $308,043
- Time Estimate
- 18 to 24 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02W.FREM-05FRMNT 138.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-515 | 6.0 MW | 4.8% | $18,855 |
AH1-690 | 97.6 MW | 79.0% | $308,043 |
AH1-711 | 20.0 MW | 16.2% | $63,102 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-019
- Title
- Upgrade phase 2 wave trap at Galion
- Description
- Upgrade phase 2 wave trap at Galion
- Total Cost ($USD)
- $620,599
- Allocated Cost ($USD)
- $291,889
- Time Estimate
- 18 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02GALION-AG2-148 TP 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-149 | 144.6 MW | 29.8% | $184,641 |
AG2-329 | 65.6 MW | 13.5% | $83,732 |
AH1-690 | 228.6 MW | 47.0% | $291,889 |
AH1-711 | 47.3 MW | 9.7% | $60,337 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-002.j
- Title
- Upgrade (1) 1590 ACSR 45/7 sub conductor at Davis Besse
- Description
- Upgrade (1) 1590 ACSR 45/7 sub conductor at Davis Besse
- Total Cost ($USD)
- $393,871
- Allocated Cost ($USD)
- $291,159
- Time Estimate
- 13 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02BAY SH-02DAV-BE 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-029 | 18.3 MW | 3.1% | $12,072 |
AG2-149 | 24.2 MW | 4.0% | $15,919 |
AG2-165 | 9.0 MW | 1.5% | $5,962 |
AG2-212 | 9.0 MW | 1.5% | $5,962 |
AG2-328 | 9.0 MW | 1.5% | $5,962 |
AG2-363 | 10.7 MW | 1.8% | $7,025 |
AG2-364 | 7.1 MW | 1.2% | $4,684 |
AG2-660 | 1.2 MW | 0.2% | $784 |
AH1-044 | 7.1 MW | 1.2% | $4,701 |
AH1-150 | 7.1 MW | 1.2% | $4,701 |
AH1-151 | 7.1 MW | 1.2% | $4,701 |
AH1-690 | 441.8 MW | 73.9% | $291,159 |
AH1-711 | 45.9 MW | 7.7% | $30,240 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-016.d
- Title
- Upgrade 795 ACSR B6 and B145 breaker leads and shared and (2) shared node subconductors at Lakeview
- Description
- Upgrade 795 ACSR B6 and B145 breaker leads and shared and (2) shared node subconductors at Lakeview
- Total Cost ($USD)
- $337,294
- Allocated Cost ($USD)
- $269,825
- Time Estimate
- 13 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02LAKVEW-02OTTAWA 138.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-515 | 5.4 MW | 4.8% | $16,312 |
AH1-690 | 89.7 MW | 80.0% | $269,825 |
AH1-711 | 17.0 MW | 15.2% | $51,157 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-021.e
- Title
- Upgrade the (1) B219 1200 CT to PVD at Beaver
- Description
- Upgrade the (1) B219 1200 CT to PVD at Beaver
- Total Cost ($USD)
- $349,952
- Allocated Cost ($USD)
- $255,752
- Time Estimate
- 16 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02BEAVER-02LAKEAVE 345.0 kV Ckt 2 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-149 | 28.3 MW | 6.9% | $24,301 |
AG2-165 | 8.9 MW | 2.2% | $7,655 |
AG2-212 | 8.9 MW | 2.2% | $7,655 |
AG2-328 | 8.9 MW | 2.2% | $7,655 |
AH1-690 | 297.6 MW | 73.1% | $255,752 |
AH1-711 | 54.6 MW | 13.4% | $46,934 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-020.h
- Title
- Upgrade the B185 CT to PVD at Beaver
- Description
- Upgrade the B185 CT to PVD at Beaver
- Total Cost ($USD)
- $349,952
- Allocated Cost ($USD)
- $249,354
- Time Estimate
- 17 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02BEAVER-AC2-103 TAP 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-029 | 15.9 MW | 3.9% | $13,670 |
AG2-149 | 22.1 MW | 5.4% | $19,032 |
AG2-165 | 7.9 MW | 1.9% | $6,773 |
AG2-212 | 7.9 MW | 1.9% | $6,773 |
AG2-328 | 7.9 MW | 1.9% | $6,773 |
AH1-690 | 290.0 MW | 71.3% | $249,354 |
AH1-711 | 55.3 MW | 13.6% | $47,577 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-021.b
- Title
- Upgrade 1590 AAC B3, B4, B216 and B219 breaker leads at Beaver and Lake Ave
- Description
- Upgrade 1590 AAC B3, B4, B216 and B219 breaker leads at Beaver and Lake Ave
- Total Cost ($USD)
- $305,540
- Allocated Cost ($USD)
- $223,295
- Time Estimate
- 12 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02BEAVER-02LAKEAVE 345.0 kV Ckt 2 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-149 | 28.3 MW | 6.9% | $21,217 |
AG2-165 | 8.9 MW | 2.2% | $6,683 |
AG2-212 | 8.9 MW | 2.2% | $6,683 |
AG2-328 | 8.9 MW | 2.2% | $6,683 |
AH1-690 | 297.6 MW | 73.1% | $223,295 |
AH1-711 | 54.6 MW | 13.4% | $40,978 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-006.f
- Title
- Upgrade (10) 1590 ACSR sub conductor (B66 and B67 breaker leads, wave trap subconductor, Overheadline-34625) at Davis Besse and B12 breaker leads at Hayes
- Description
- Upgrade (10) 1590 ACSR sub conductor (B66 and B67 breaker leads, wave trap subconductor, Overheadline-34625) at Davis Besse and B12 breaker leads at Hayes
- Total Cost ($USD)
- $305,149
- Allocated Cost ($USD)
- $217,221
- Time Estimate
- 18 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02DAV-BE-02HAYES 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-149 | 22.4 MW | 5.2% | $15,866 |
AG2-165 | 8.1 MW | 1.9% | $5,721 |
AG2-212 | 8.1 MW | 1.9% | $5,721 |
AG2-328 | 8.1 MW | 1.9% | $5,721 |
AG2-660 | 1.0 MW | 0.2% | $725 |
AH1-044 | 6.1 MW | 1.4% | $4,348 |
AH1-150 | 6.1 MW | 1.4% | $4,348 |
AH1-151 | 6.1 MW | 1.4% | $4,348 |
AH1-690 | 306.6 MW | 71.2% | $217,221 |
AH1-711 | 58.0 MW | 13.5% | $41,130 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-004.d
- Title
- Upgrade (1) 3500 SAC 127 D120-to-B121 breaker lead at Beaver
- Description
- Upgrade (1) 3500 SAC 127 D120-to-B121 breaker lead at Beaver
- Total Cost ($USD)
- $265,209
- Allocated Cost ($USD)
- $207,485
- Time Estimate
- 12 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02BEAVER-02CARLIL 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-149 | 22.6 MW | 7.4% | $19,649 |
AH1-690 | 238.1 MW | 78.2% | $207,485 |
AH1-711 | 43.7 MW | 14.4% | $38,075 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-004.b
- Title
- Upgrade (1) 3000 SAC 169 line drop at Beaver
- Description
- Upgrade (1) 3000 SAC 169 line drop at Beaver
- Total Cost ($USD)
- $263,169
- Allocated Cost ($USD)
- $205,889
- Time Estimate
- 12 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02BEAVER-02CARLIL 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-149 | 22.6 MW | 7.4% | $19,498 |
AH1-690 | 238.1 MW | 78.2% | $205,889 |
AH1-711 | 43.7 MW | 14.4% | $37,782 |
System Reinforcement: n9674.0
- Type
- Load Flow
- TO
- AEP
- RTEP ID / TO ID
- n9674.0 / AEPO0026b
- Title
- Replace 1200 A Switch at Fremont
- Description
- Total Cost ($USD)
- $260,000
- Allocated Cost ($USD)
- $205,362
- Time Estimate
- 18 to 24 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02W.FREM-05FRMNT 138.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-515 | 6.0 MW | 4.8% | $12,570 |
AH1-690 | 97.6 MW | 79.0% | $205,362 |
AH1-711 | 20.0 MW | 16.2% | $42,068 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-006.b
- Title
- Upgrade 3500 SAC 127 OVERHEAD PIPE to disc sw. 34625 at Davis Besse and B18 breaker leads at Hayes
- Description
- Upgrade 3500 SAC 127 OVERHEAD PIPE to disc sw. 34625 at Davis Besse and B18 breaker leads at Hayes
- Total Cost ($USD)
- $284,061
- Allocated Cost ($USD)
- $202,209
- Time Estimate
- 18 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02DAV-BE-02HAYES 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-149 | 22.4 MW | 5.2% | $14,770 |
AG2-165 | 8.1 MW | 1.9% | $5,326 |
AG2-212 | 8.1 MW | 1.9% | $5,326 |
AG2-328 | 8.1 MW | 1.9% | $5,326 |
AG2-660 | 1.0 MW | 0.2% | $675 |
AH1-044 | 6.1 MW | 1.4% | $4,048 |
AH1-150 | 6.1 MW | 1.4% | $4,048 |
AH1-151 | 6.1 MW | 1.4% | $4,048 |
AH1-690 | 306.6 MW | 71.2% | $202,209 |
AH1-711 | 58.0 MW | 13.5% | $38,287 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-002.l
- Title
- Upgrade (5) 4.00 SPS AL PIPE 61 sub conductors at BAYSHORE on the Bayshore - Davis Besse 345kV line
- Description
- Upgrade (5) 4.00 SPS AL PIPE 61 sub conductors at BAYSHORE on the Bayshore - Davis Besse 345kV line
- Total Cost ($USD)
- $246,545
- Allocated Cost ($USD)
- $195,449
- Time Estimate
- 14 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02BAY SH-02DAV-BE 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-029 | 18.3 MW | 3.3% | $8,104 |
AG2-149 | 24.2 MW | 4.3% | $10,686 |
AG2-165 | 9.0 MW | 1.6% | $4,002 |
AG2-212 | 9.0 MW | 1.6% | $4,002 |
AG2-328 | 9.0 MW | 1.6% | $4,002 |
AH1-690 | 441.8 MW | 79.3% | $195,449 |
AH1-711 | 45.9 MW | 8.2% | $20,299 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-008.d
- Title
- Upgrade (2) 3500 SAC 127 line drops at Davis Besse
- Description
- Upgrade (2) 3500 SAC 127 line drops at Davis Besse
- Total Cost ($USD)
- $263,169
- Allocated Cost ($USD)
- $195,081
- Time Estimate
- 12 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02DAV-BE-AC2-103 TAP 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-149 | 22.2 MW | 5.7% | $14,915 |
AG2-165 | 7.9 MW | 2.0% | $5,316 |
AG2-212 | 7.9 MW | 2.0% | $5,316 |
AG2-328 | 7.9 MW | 2.0% | $5,316 |
AH1-690 | 290.3 MW | 74.1% | $195,081 |
AH1-711 | 55.4 MW | 14.1% | $37,224 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-008.b
- Title
- Upgrade (1) 1024 ACAR 6E550-52-1 "A" line drop at Davis Besse
- Description
- Upgrade (1) 1024 ACAR 6E550-52-1 "A" line drop at Davis Besse
- Total Cost ($USD)
- $263,169
- Allocated Cost ($USD)
- $195,081
- Time Estimate
- 12 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02DAV-BE-AC2-103 TAP 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-149 | 22.2 MW | 5.7% | $14,915 |
AG2-165 | 7.9 MW | 2.0% | $5,316 |
AG2-212 | 7.9 MW | 2.0% | $5,316 |
AG2-328 | 7.9 MW | 2.0% | $5,316 |
AH1-690 | 290.3 MW | 74.1% | $195,081 |
AH1-711 | 55.4 MW | 14.1% | $37,224 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-002.c
- Title
- Upgrade 345kV 1033.5 AAC 61 sub conductors at Davis Besse substation at Davis Besse
- Description
- Upgrade 345kV 1033.5 AAC 61 sub conductors at Davis Besse substation at Davis Besse
- Total Cost ($USD)
- $257,762
- Allocated Cost ($USD)
- $190,544
- Time Estimate
- 13 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02BAY SH-02DAV-BE 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-029 | 18.3 MW | 3.1% | $7,900 |
AG2-149 | 24.2 MW | 4.0% | $10,418 |
AG2-165 | 9.0 MW | 1.5% | $3,902 |
AG2-212 | 9.0 MW | 1.5% | $3,902 |
AG2-328 | 9.0 MW | 1.5% | $3,902 |
AG2-363 | 10.7 MW | 1.8% | $4,597 |
AG2-364 | 7.1 MW | 1.2% | $3,065 |
AG2-660 | 1.2 MW | 0.2% | $513 |
AH1-044 | 7.1 MW | 1.2% | $3,076 |
AH1-150 | 7.1 MW | 1.2% | $3,076 |
AH1-151 | 7.1 MW | 1.2% | $3,076 |
AH1-690 | 441.8 MW | 73.9% | $190,544 |
AH1-711 | 45.9 MW | 7.7% | $19,790 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-002.e
- Title
- Upgrade 345kV 3500 SAC 127 sub conductor at Davis Besse
- Description
- Upgrade 345kV 3500 SAC 127 sub conductor at Davis Besse
- Total Cost ($USD)
- $257,762
- Allocated Cost ($USD)
- $190,544
- Time Estimate
- 13 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02BAY SH-02DAV-BE 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-029 | 18.3 MW | 3.1% | $7,900 |
AG2-149 | 24.2 MW | 4.0% | $10,418 |
AG2-165 | 9.0 MW | 1.5% | $3,902 |
AG2-212 | 9.0 MW | 1.5% | $3,902 |
AG2-328 | 9.0 MW | 1.5% | $3,902 |
AG2-363 | 10.7 MW | 1.8% | $4,597 |
AG2-364 | 7.1 MW | 1.2% | $3,065 |
AG2-660 | 1.2 MW | 0.2% | $513 |
AH1-044 | 7.1 MW | 1.2% | $3,076 |
AH1-150 | 7.1 MW | 1.2% | $3,076 |
AH1-151 | 7.1 MW | 1.2% | $3,076 |
AH1-690 | 441.8 MW | 73.9% | $190,544 |
AH1-711 | 45.9 MW | 7.7% | $19,790 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-021.m
- Title
- Upgrade (8) 5.00 SPS.AL PIPE SCCIR at Beaver
- Description
- Upgrade (8) 5.00 SPS.AL PIPE SCCIR at Beaver
- Total Cost ($USD)
- $250,039
- Allocated Cost ($USD)
- $182,734
- Time Estimate
- 12 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02BEAVER-02LAKEAVE 345.0 kV Ckt 2 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-149 | 28.3 MW | 6.9% | $17,363 |
AG2-165 | 8.9 MW | 2.2% | $5,469 |
AG2-212 | 8.9 MW | 2.2% | $5,469 |
AG2-328 | 8.9 MW | 2.2% | $5,469 |
AH1-690 | 297.6 MW | 73.1% | $182,734 |
AH1-711 | 54.6 MW | 13.4% | $33,534 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI.023.c
- Title
- Upgrade the (2) B96 and (2) B7 breaker leads at Lakeview and the (1) B242 to D241 lead at Greenfield
- Description
- Upgrade the (2) B96 and (2) B7 breaker leads at Lakeview and the (1) B242 to D241 lead at Greenfield
- Total Cost ($USD)
- $218,931
- Allocated Cost ($USD)
- $175,138
- Time Estimate
- 13 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02GRNFLD-02LAKVEW 138.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-515 | 5.4 MW | 4.8% | $10,588 |
AH1-690 | 89.7 MW | 80.0% | $175,138 |
AH1-711 | 17.0 MW | 15.2% | $33,205 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-002.h
- Title
- Upgrade (8) 1590 AAC 61 sub conductor at BAYSHORE
- Description
- Upgrade (8) 1590 AAC 61 sub conductor at BAYSHORE
- Total Cost ($USD)
- $211,119
- Allocated Cost ($USD)
- $156,064
- Time Estimate
- 13 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02BAY SH-02DAV-BE 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-029 | 18.3 MW | 3.1% | $6,471 |
AG2-149 | 24.2 MW | 4.0% | $8,533 |
AG2-165 | 9.0 MW | 1.5% | $3,196 |
AG2-212 | 9.0 MW | 1.5% | $3,196 |
AG2-328 | 9.0 MW | 1.5% | $3,196 |
AG2-363 | 10.7 MW | 1.8% | $3,766 |
AG2-364 | 7.1 MW | 1.2% | $2,510 |
AG2-660 | 1.2 MW | 0.2% | $420 |
AH1-044 | 7.1 MW | 1.2% | $2,520 |
AH1-150 | 7.1 MW | 1.2% | $2,520 |
AH1-151 | 7.1 MW | 1.2% | $2,520 |
AH1-690 | 441.8 MW | 73.9% | $156,064 |
AH1-711 | 45.9 MW | 7.7% | $16,209 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-005c
- Title
- Upgrade 3500 SAC 127 B161 (2) breaker leads and (1) B121-to-D120 breaker lead at Beaver
- Description
- Upgrade 3500 SAC 127 B161 (2) breaker leads and (1) B121-to-D120 breaker lead at Beaver
- Total Cost ($USD)
- $191,109
- Allocated Cost ($USD)
- $149,954
- Time Estimate
- 11 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02BEAVER-02LAKEAVE 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-149 | 19.4 MW | 7.2% | $13,690 |
AH1-690 | 212.1 MW | 78.5% | $149,954 |
AH1-711 | 38.8 MW | 14.4% | $27,465 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-008.e
- Title
- Upgrade 3500 SAC B65 breaker leads and subconductor (D42 to wave trap) at Davis Besse
- Description
- Upgrade 3500 SAC B65 breaker leads and subconductor (D42 to wave trap) at Davis Besse
- Total Cost ($USD)
- $197,592
- Allocated Cost ($USD)
- $146,470
- Time Estimate
- 13 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02DAV-BE-AC2-103 TAP 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-149 | 22.2 MW | 5.7% | $11,199 |
AG2-165 | 7.9 MW | 2.0% | $3,992 |
AG2-212 | 7.9 MW | 2.0% | $3,992 |
AG2-328 | 7.9 MW | 2.0% | $3,992 |
AH1-690 | 290.3 MW | 74.1% | $146,470 |
AH1-711 | 55.4 MW | 14.1% | $27,948 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-020.c
- Title
- Upgrade 3000 AAC B185 and B185 breaker leads at Beaver
- Description
- Upgrade 3000 AAC B185 and B185 breaker leads at Beaver
- Total Cost ($USD)
- $187,449
- Allocated Cost ($USD)
- $133,565
- Time Estimate
- 13 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02BEAVER-AC2-103 TAP 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-029 | 15.9 MW | 3.9% | $7,322 |
AG2-149 | 22.1 MW | 5.4% | $10,195 |
AG2-165 | 7.9 MW | 1.9% | $3,628 |
AG2-212 | 7.9 MW | 1.9% | $3,628 |
AG2-328 | 7.9 MW | 1.9% | $3,628 |
AH1-690 | 290.0 MW | 71.3% | $133,565 |
AH1-711 | 55.3 MW | 13.6% | $25,484 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-021.g
- Title
- Upgrade (1) 4.00 SPS.AL PIPE at Beaver
- Description
- Upgrade (1) 4.00 SPS.AL PIPE at Beaver
- Total Cost ($USD)
- $178,089
- Allocated Cost ($USD)
- $130,151
- Time Estimate
- 12 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02BEAVER-02LAKEAVE 345.0 kV Ckt 2 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-149 | 28.3 MW | 6.9% | $12,367 |
AG2-165 | 8.9 MW | 2.2% | $3,896 |
AG2-212 | 8.9 MW | 2.2% | $3,896 |
AG2-328 | 8.9 MW | 2.2% | $3,896 |
AH1-690 | 297.6 MW | 73.1% | $130,151 |
AH1-711 | 54.6 MW | 13.4% | $23,885 |
System Reinforcement: n9669.0
- Type
- Load Flow
- TO
- AEP
- RTEP ID / TO ID
- n9669.0 / AEPO0027e
- Title
- Replace Sub cond 397.5 ACSR 26/7 at Howard
- Description
- Total Cost ($USD)
- $130,000
- Allocated Cost ($USD)
- $130,000
- Time Estimate
- 18 to 24 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 05HOWARD1-AC2-015 TAP 138.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AH1-690 | 26.1 MW | 100.0% | $130,000 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-021.j
- Title
- Upgrade (2) 2.50 SPS.AL PIPE SCCIR at Beaver
- Description
- Upgrade (2) 2.50 SPS.AL PIPE SCCIR at Beaver
- Total Cost ($USD)
- $173,391
- Allocated Cost ($USD)
- $126,718
- Time Estimate
- 12 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02BEAVER-02LAKEAVE 345.0 kV Ckt 2 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-149 | 28.3 MW | 6.9% | $12,041 |
AG2-165 | 8.9 MW | 2.2% | $3,793 |
AG2-212 | 8.9 MW | 2.2% | $3,793 |
AG2-328 | 8.9 MW | 2.2% | $3,793 |
AH1-690 | 297.6 MW | 73.1% | $126,718 |
AH1-711 | 54.6 MW | 13.4% | $23,254 |
System Reinforcement
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- (Pending) / TC2-PH1-DOM-2043
- Title
- Wreck and rebuild 0.93 miles of 230 kV Line 2241 between Hendrick and Persons with (2) 768.2 ACSS/TW (20/7) "MAUMEE" at 250 degrees C. Dominion portion of line only.
- Description
- Wreck and rebuild 0.93 miles of 230 kV Line 2241 between Hendrick and Persons with (2) 768.2 ACSS/TW (20/7) "MAUMEE" at 250 degrees C. Dominion portion of line only.
- Total Cost ($USD)
- $3,534,000
- Allocated Cost ($USD)
- $123,688
- Time Estimate
- 36 to 42 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 6PERSON230 T-AC2-100 TAP 230.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-068 | 9.2 MW | 1.1% | $39,652 |
AG2-069 | 13.8 MW | 1.7% | $59,477 |
AG2-077 | 67.9 MW | 8.3% | $292,796 |
AG2-111 | 3.5 MW | 0.4% | $15,101 |
AG2-112 | 3.7 MW | 0.4% | $15,830 |
AG2-151 | 7.2 MW | 0.9% | $31,260 |
AG2-152 | 14.7 MW | 1.8% | $63,434 |
AG2-171 | 13.1 MW | 1.6% | $56,405 |
AG2-188 | 21.4 MW | 2.6% | $92,359 |
AG2-198 | 19.5 MW | 2.4% | $83,993 |
AG2-213 | 17.4 MW | 2.1% | $75,209 |
AG2-270 | 47.1 MW | 5.8% | $203,423 |
AG2-272 | 5.3 MW | 0.7% | $23,062 |
AG2-341 | 6.5 MW | 0.8% | $27,834 |
AG2-369 | 7.9 MW | 1.0% | $34,099 |
AG2-440 | 21.4 MW | 2.6% | $92,165 |
AG2-441 | 26.7 MW | 3.3% | $115,205 |
AG2-442 | 29.9 MW | 3.7% | $129,034 |
AG2-522 | 10.0 MW | 1.2% | $43,134 |
AG2-541 | 19.1 MW | 2.3% | $82,250 |
AG2-566 | 9.3 MW | 1.1% | $39,936 |
AG2-570 | 35.7 MW | 4.4% | $154,059 |
AG2-571 | 15.5 MW | 1.9% | $67,037 |
AG2-581 | 50.2 MW | 6.1% | $216,526 |
AG2-583 | 7.5 MW | 0.9% | $32,494 |
AG2-659 | 11.3 MW | 1.4% | $48,915 |
AH1-056 | 20.7 MW | 2.5% | $89,249 |
AH1-215 | 8.7 MW | 1.1% | $37,455 |
AH1-241 | 6.9 MW | 0.8% | $29,676 |
AH1-314 | 15.6 MW | 1.9% | $67,343 |
AH1-343 | 22.0 MW | 2.7% | $94,896 |
AH1-377 | 48.3 MW | 5.9% | $208,557 |
AH1-408 | 10.5 MW | 1.3% | $45,498 |
AH1-439 | 12.3 MW | 1.5% | $53,152 |
AH1-528 | 100.6 MW | 12.3% | $434,213 |
AH1-535 | 6.0 MW | 0.7% | $25,767 |
AH1-546 | 7.3 MW | 0.9% | $31,579 |
AH1-687 | 5.2 MW | 0.6% | $22,479 |
AH1-690 | 28.7 MW | 3.5% | $123,688 |
AH1-721 | 31.5 MW | 3.8% | $135,756 |
System Reinforcement: n9675.0
- Type
- Load Flow
- TO
- AEP
- RTEP ID / TO ID
- n9675.0 / AEPO0035a
- Title
- Sag Study will be required on ACSR ~ 954 ~ 45/7, 18.3 miles line between South Berwick and Galion .
- Description
- Sag Study will be required on ACSR ~ 954 ~ 45/7, 18.3 miles line between South Berwick and Galion .The cost is expected to be 73,200.New Ratings after sag study : S/N: 1409 MVA S/E: 1887 MVA.Rebuild/Reconductor, cost : $ 36.6 million
- Total Cost ($USD)
- $229,320
- Allocated Cost ($USD)
- $107,857
- Time Estimate
- 24 to 36 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02GALION-AG2-148 TP 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-149 | 144.6 MW | 29.8% | $68,228 |
AG2-329 | 65.6 MW | 13.5% | $30,940 |
AH1-690 | 228.6 MW | 47.0% | $107,857 |
AH1-711 | 47.3 MW | 9.7% | $22,295 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-014.b
- Title
- Upgrade 3500 SAC (2) B3 and (2) B6 breaker leads at Hayes
- Description
- Upgrade 3500 SAC (2) B3 and (2) B6 breaker leads at Hayes
- Total Cost ($USD)
- $152,573
- Allocated Cost ($USD)
- $106,511
- Time Estimate
- 18 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02BEAVER-02HAYES 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-149 | 24.0 MW | 5.8% | $8,880 |
AG2-165 | 8.3 MW | 2.0% | $3,052 |
AG2-212 | 8.3 MW | 2.0% | $3,052 |
AG2-328 | 8.3 MW | 2.0% | $3,052 |
AG2-660 | 1.0 MW | 0.3% | $387 |
AH1-044 | 6.3 MW | 1.5% | $2,321 |
AH1-150 | 6.3 MW | 1.5% | $2,321 |
AH1-151 | 6.3 MW | 1.5% | $2,321 |
AH1-690 | 288.2 MW | 69.8% | $106,511 |
AH1-711 | 55.9 MW | 13.6% | $20,676 |
System Reinforcement
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- (Pending) / TC2-ATSI-014.e
- Title
- Upgrade the 1590 AAC (2) B88 and (2) B15 breaker leads at Beaver
- Description
- Upgrade the 1590 AAC (2) B88 and (2) B15 breaker leads at Beaver
- Total Cost ($USD)
- $152,573
- Allocated Cost ($USD)
- $106,511
- Time Estimate
- 18 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02BEAVER-02HAYES 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AG2-149 | 24.0 MW | 5.8% | $8,880 |
AG2-165 | 8.3 MW | 2.0% | $3,052 |
AG2-212 | 8.3 MW | 2.0% | $3,052 |
AG2-328 | 8.3 MW | 2.0% | $3,052 |
AG2-660 | 1.0 MW | 0.3% | $387 |
AH1-044 | 6.3 MW | 1.5% | $2,321 |
AH1-150 | 6.3 MW | 1.5% | $2,321 |
AH1-151 | 6.3 MW | 1.5% | $2,321 |
AH1-690 | 288.2 MW | 69.8% | $106,511 |
AH1-711 | 55.9 MW | 13.6% | $20,676 |
System Reinforcement
- Type
- Load Flow
- TO
- AEP
- RTEP ID / TO ID
- (Pending) / AEP-TC2-18731
- Title
- 05WOLFCK 138kV to 05W.WATERT 138kV ckt 1 - Replace Equipment
- Description
- At Wolf Creek Station replace 795 KCM AAC, 37-Str.
- Total Cost ($USD)
- $100,000
- Allocated Cost ($USD)
- $100,000
- Time Estimate
- 24 to 36 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 05WOLFCK-05W.WATERT 138.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AH1-690 | 15.5 MW | 100.0% | $100,000 |
System Reinforcement: n9676.0
- Type
- Load Flow
- TO
- AEP
- RTEP ID / TO ID
- n9676.0 / AEPO0033a
- Title
- Sag Study will be required on 19.2 miles line between Fostoria and Lallen [...] tudy : S/N: 1409MVA S/E: 1887MVA.Rebuild/Reconductor, cost : $ 38.4 million
- Description
- Sag Study will be required on 19.2 miles line between Fostoria and Lallendorf .The cost is expected to be 76,800.New Ratings after sag study : S/N: 1409MVA S/E: 1887MVA.Rebuild/Reconductor, cost : $ 38.4 million
- Total Cost ($USD)
- $99,840
- Allocated Cost ($USD)
- $99,840
- Time Estimate
- 24 to 36 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 02LALLENDORF-05FOSTOR 345.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AH1-690 | 788.0 MW | 100.0% | $99,840 |
System Reinforcement
- Type
- Load Flow
- TO
- AEP
- RTEP ID / TO ID
- (Pending) / AEPAPRJV002
- Title
- Perform sag study on 397 ACSR between Clifford and Boxwood (13.7 miles)
- Description
- Perform sag study on 397 ACSR between Clifford and Boxwood (13.7 miles)
- Total Cost ($USD)
- $82,200
- Allocated Cost ($USD)
- $82,200
- Time Estimate
- 24 to 36 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 05BOXWD-05CLIFFR 138.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AH1-690 | 9.1 MW | 100.0% | $82,200 |
System Reinforcement: n8383
- Type
- Load Flow
- TO
- AEP
- RTEP ID / TO ID
- n8383
- Title
- A sag study will be required on the 3.65 miles of ACSR ~ 397.5 ~ 30/7 ~ LARK~ Conductor to determine what mitigation
- Description
- A sag study will be required on the 3.65 miles of ACSR ~ 397.5 ~ 30/7 ~ LARK~ Conductor to determine what mitigation would be required (if any) to operate at the conductor's MOT. Depending on the sag study results findings, the cost for this upgrade is expected to be $60,000 (no remediation required, just sag study) and $10.0 million (complete line reconductor/rebuild).AEP will determine the new rating(s) based on the scope of work required to exceed the anticipated loading.
- Total Cost ($USD)
- $78,000
- Allocated Cost ($USD)
- $78,000
- Time Estimate
- 24 to 36 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 05CLIFFR-05COLLEEN SS 138.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AH1-690 | 9.1 MW | 100.0% | $78,000 |
System Reinforcement: n8386
- Type
- Load Flow
- TO
- AEP
- RTEP ID / TO ID
- n8386
- Title
- A sag study will be required on the ~4.0 miles of ACSR ~ 397.5 ~ 30/7 ~ LARK~ Conductor to determine what mitigation
- Description
- A sag study will be required on the ~4.0 miles of ACSR ~ 397.5 ~ 30/7 ~ LARK~ Conductor to determine what mitigation would be required (if any) to operate at the conductor's MOT. Depending on the sag study results findings, the cost for this upgrade is expected to be $60,000 (no remediation required, just sag study) and $12.0 million (complete line reconductor/rebuild).AEP will determine the new rating(s) based on the scope of work required to exceed the anticipated loading.
- Total Cost ($USD)
- $78,000
- Allocated Cost ($USD)
- $78,000
- Time Estimate
- 24 to 36 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 05COLLEEN SS-05JAMES RIVR 138.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AH1-690 | 9.1 MW | 100.0% | $78,000 |
System Reinforcement
- Type
- Load Flow
- TO
- AEP
- RTEP ID / TO ID
- (Pending) / AEPAPRJV006_2
- Title
- Sag Study 397 ACSR between James River and Soapstone ~10 miles
- Description
- Sag Study 397 ACSR between James River and Soapstone ~10 miles
- Total Cost ($USD)
- $60,000
- Allocated Cost ($USD)
- $60,000
- Time Estimate
- 24 to 36 Months
Contributor
| Facility | Contingency | |
|---|---|---|
| 05JAMES RIVR-05SOAPSTONE 138.0 kV Ckt 1 line | (Any) |
| Project | MW Impact | Percent Allocation | Allocated Cost ($USD) |
|---|---|---|---|
AH1-690 | 9.1 MW | 100.0% | $60,000 |
System Reinforcement: b3925.3
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- b3925.3
- Title
- Rebuild the 6.5 miles of Avery-Hayes 138 kV Line with 795 kcmil 26/7 ACSS conductor
- Description
- Rebuild the 6.5 miles of Avery-Hayes 138 kV Line with 795 kcmil 26/7 ACSS conductor
- Cost Information
- Time Estimate
- Jun 01 2027
Contingent Note: Although AH1-690 may not presently have cost responsibility for this upgrade, AH1-690 may need this upgrade in-service to be deliverable to the PJM system. If AH1-690 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.
| Facility | Contingency | |
|---|---|---|
| 02AVERY-02HAYES 138.0 kV Ckt 1 line | (Any) |
System Reinforcement: b3925.1
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- b3925.1
- Title
- Rebuild the 7.46 miles of Avery - Shinrock 138 kV Line with 795 kcmil 26/7 ACSS (7.46 miles)
- Description
- Rebuild the 7.46 miles of Avery - Shinrock 138 kV Line with 795 kcmil 26/7 ACSS (7.46 miles)
- Cost Information
- Time Estimate
- Dec 10 2027
Contingent Note: Although AH1-690 may not presently have cost responsibility for this upgrade, AH1-690 may need this upgrade in-service to be deliverable to the PJM system. If AH1-690 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.
| Facility | Contingency | |
|---|---|---|
| 02AVERY-02SHNROK 138.0 kV Ckt 1 line | (Any) |
System Reinforcement: b3925.4
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- b3925.4
- Title
- Rebuild the Greenfield - Beaver 138 kV corridor (32 miles) with 795 kcmil 26/7 ACSS
- Description
- Rebuild the Greenfield - Beaver 138 kV corridor (32 miles) with 795 kcmil 26/7 ACSS. This corridor encompasses multiple 138 kV lines that are constructed on common towers.
- Cost Information
- Time Estimate
- Jun 01 2029
Contingent Note: Although AH1-690 may not presently have cost responsibility for this upgrade, AH1-690 may need this upgrade in-service to be deliverable to the PJM system. If AH1-690 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.
| Facility | Contingency | |
|---|---|---|
| 02BEAVER-02NASA 138.0 kV Ckt 1 line | (Any) | |
| 02BEAVER-02OAKPOINT 138.0 kV Ckt 1 line | (Any) | |
| 02BRWELL-02FORD 138.0 kV Ckt 1 line | (Any) | |
| 02BRWELL-02N DEPT 138.0 kV Ckt 1 line | (Any) | |
| 02GRNFLD-02N DEPT 138.0 kV Ckt 1 line | (Any) | |
| 02GRNFLD-02NASA 138.0 kV Ckt 1 line | (Any) |
System Reinforcement: s3360.1
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- s3360.1
- Title
- Galion 138kV Upgrades
- Description
- - Replace 138 kV breakers B-52, B-55, B-58, B-59 and B-60 as well as circuit switchers CS-136 and CS-137. - Replace and install associated disconnect switches and protective relaying. - Replace limiting substation conductor.
- Cost Information
- Time Estimate
- Jun 01 2027
Contingent Note: Although AH1-690 may not presently have cost responsibility for this upgrade, AH1-690 may need this upgrade in-service to be deliverable to the PJM system. If AH1-690 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.
| Facility | Contingency | |
|---|---|---|
| 02GALION-02GALION 345.0/138.0 kV Ckt 3 transformer | (Any) | |
| 02GALION-02GALION 345.0/138.0 kV Ckt 4 transformer | (Any) |
System Reinforcement: s3469.1
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- s3469.1 / ATSI-2024-024
- Title
- Rebuild the double circuit Galion – Roberts North 138 kV Line and Galion – Roberts South 138 kV Line
- Description
- Rebuild the double circuit Galion – Roberts North 138 kV Line and Galion – Roberts South 138 kV Line on shared structures. - Galion: replace circuit breakers and associated disconnect switches. - Roberts: replace substation conductor https://pjm.com/-/media/committees-groups/committees/teac/2024/20241008/20241008-informational-only---atsi-local-plan-submission-of-supplemental-project-2024.ashx
- Cost Information
- Time Estimate
- Aug 27 2026
Contingent Note: Although AH1-690 may not presently have cost responsibility for this upgrade, AH1-690 may need this upgrade in-service to be deliverable to the PJM system. If AH1-690 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.
| Facility | Contingency | |
|---|---|---|
| 02DUALR+-02ROBERT 138.0 kV Ckt 1 line | (Any) |
System Reinforcement: b3925.2
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- b3925.2
- Title
- Rebuild the 13.45 miles of Greenfield - Lakeview 138 kV Line from 2 x 336.4 kcmil 26/7 ACSR to 1 x 795 kcmil 26/7 ACSS
- Description
- Rebuild the 13.45 miles of Greenfield - Lakeview 138 kV Line from 2 x 336.4 kcmil 26/7 ACSR to 1 x 795 kcmil 26/7 ACSS
- Cost Information
- Time Estimate
- Jun 01 2029
Contingent Note: Although AH1-690 may not presently have cost responsibility for this upgrade, AH1-690 may need this upgrade in-service to be deliverable to the PJM system. If AH1-690 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.
| Facility | Contingency | |
|---|---|---|
| 02GRNFLD-02LAKVEW 138.0 kV Ckt 1 line | (Any) |
System Reinforcement: b3033
- Type
- Load Flow
- TO
- ATSI
- RTEP ID / TO ID
- b3033
- Title
- Ottawa-Lakeview 138 kV Reconductor and Substation Upgrades
- Description
- Cost Information
- Time Estimate
- Oct 31 2025
Contingent Note: Although AH1-690 may not presently have cost responsibility for this upgrade, AH1-690 may need this upgrade in-service to be deliverable to the PJM system. If AH1-690 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.
| Facility | Contingency | |
|---|---|---|
| 02LAKVEW-02OTTAWA 138.0 kV Ckt 1 line | (Any) |
System Reinforcement: b3888.1
- Type
- Load Flow
- TO
- AEP
- RTEP ID / TO ID
- b3888.1
- Title
- Preform sag study and complete mitigations on the 138 kV line between East Leipsic and the AE2-072 tap (Lammer) to allow line's conductor to operate to its maximum operating temperature (MOT).
- Description
- Preform sag study and complete mitigations on the 138 kV line between East Leipsic and the AE2-072 tap (Lammer) to allow line's conductor to operate to its maximum operating temperature (MOT).
- Cost Information
- Time Estimate
- Jun 01 2029
Contingent Note: Although AH1-690 may not presently have cost responsibility for this upgrade, AH1-690 may need this upgrade in-service to be deliverable to the PJM system. If AH1-690 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.
| Facility | Contingency | |
|---|---|---|
| 05E.LEIPSIC2-AE2-072 TAP 138.0 kV Ckt 1 line | (Any) |
System Reinforcement: b4000.342
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.342
- Title
- Remove the terminal equipment and substation work required for the termination of the Morrisville-Wishing Star 500 kV line into Vint Hill.
- Description
- Remove the terminal equipment and substation work required for the termination of the Morrisville-Wishing Star 500 kV line into Vint Hill.
- Cost Information
- Time Estimate
- Jul 13 2029
Contingent Note: Although AH1-690 may not presently have cost responsibility for this upgrade, AH1-690 may need this upgrade in-service to be deliverable to the PJM system. If AH1-690 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.
| Facility | Contingency | |
|---|---|---|
| 4BREMO-AE1-108 POI 138.0 kV Ckt 1 line | (Any) |
System Reinforcement: b4000.355
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.355
- Title
- Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 69.3 miles in AEP section).
- Description
- Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 69.3 miles in AEP section).
- Cost Information
- Time Estimate
- Jun 01 2029
Contingent Note: Although AH1-690 may not presently have cost responsibility for this upgrade, AH1-690 may need this upgrade in-service to be deliverable to the PJM system. If AH1-690 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.
| Facility | Contingency | |
|---|---|---|
| 4BREMO-AE1-108 POI 138.0 kV Ckt 1 line | (Any) |
System Reinforcement: b4000.350
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.350
- Title
- Update relay settings at Possum Point to change the destination of 500kV line #568 from Ladysmith to Kraken.
- Description
- Update relay settings at Possum Point to change the destination of 500kV line #568 from Ladysmith to Kraken.
- Cost Information
- Time Estimate
- Sep 16 2030
Contingent Note: Although AH1-690 may not presently have cost responsibility for this upgrade, AH1-690 may need this upgrade in-service to be deliverable to the PJM system. If AH1-690 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.
| Facility | Contingency | |
|---|---|---|
| 4BREMO-AE1-108 POI 138.0 kV Ckt 1 line | (Any) |
System Reinforcement: b4000.348
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.348
- Title
- Build a new 500/230kV substation called Kraken. The 500kV, 5000A ring bus will be set up for a redundant breaker configuration. Install (2) 1400MVA 500/230 kV transformers.
- Description
- Build a new 500/230kV substation called Kraken. The 500kV, 5000A ring bus will be set up for a redundant breaker configuration. Install (2) 1400MVA 500/230 kV transformers. A new redundant breaker ring will be added at Kraken to accommodate the new 500kV line from North Anna to Kraken.
- Cost Information
- Time Estimate
- Jun 01 2029
Contingent Note: Although AH1-690 may not presently have cost responsibility for this upgrade, AH1-690 may need this upgrade in-service to be deliverable to the PJM system. If AH1-690 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.
| Facility | Contingency | |
|---|---|---|
| 4BREMO-AE1-108 POI 138.0 kV Ckt 1 line | (Any) |
System Reinforcement: b4000.341
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.341
- Title
- Remove the 500 kV conductor previously planned to terminate into the Vint Hill 500 kV Substation and extend approximately 0.2 miles of conductor to fly-over the site.
- Description
- Remove the 500 kV conductor previously planned to terminate into the Vint Hill 500 kV substation and extend approximately 0.2 miles of conductor to fly-over the site.
- Cost Information
- Time Estimate
- Jul 13 2029
Contingent Note: Although AH1-690 may not presently have cost responsibility for this upgrade, AH1-690 may need this upgrade in-service to be deliverable to the PJM system. If AH1-690 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.
| Facility | Contingency | |
|---|---|---|
| 4BREMO-AE1-108 POI 138.0 kV Ckt 1 line | (Any) |
System Reinforcement: b4000.327
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.327
- Title
- Upgrade/install equipment at Ladysmith Substation to 4000A. Expansion will be required to accommodate a total of three (3) new 230 kV strings of breaker and a half scheme.
- Description
- Upgrade/install equipment at Ladysmith substation to 4000A. Expansion will be required to accommodate a total of three (3) new 230kV strings of breaker and a half scheme.
- Cost Information
- Time Estimate
- Feb 24 2029
Contingent Note: Although AH1-690 may not presently have cost responsibility for this upgrade, AH1-690 may need this upgrade in-service to be deliverable to the PJM system. If AH1-690 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.
| Facility | Contingency | |
|---|---|---|
| 4BREMO-AE1-108 POI 138.0 kV Ckt 1 line | (Any) |
System Reinforcement: b4000.349
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.349
- Title
- Update relay settings at Ladysmith to change the destination of 500kV line #568 from Possum Point to Kraken.
- Description
- Update relay settings at Ladysmith to change the destination of 500kV line #568 from Possum Point to Kraken.
- Cost Information
- Time Estimate
- Sep 16 2030
Contingent Note: Although AH1-690 may not presently have cost responsibility for this upgrade, AH1-690 may need this upgrade in-service to be deliverable to the PJM system. If AH1-690 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.
| Facility | Contingency | |
|---|---|---|
| 4BREMO-AE1-108 POI 138.0 kV Ckt 1 line | (Any) |
System Reinforcement: b4000.357
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.357
- Title
- Build a new 765/500/230 kV substation called Yeat. Install (2) 765/500 kV transformers. Cut in 500 kV line Bristers-Ox and 500 kV line Meadowbrook-Vint Hill into Yeat.
- Description
- Build a new 765/500/230 kV substation called Yeat. Install (2) 765/500 kV transformers. Cut in 500 kV line Bristers-Ox and 500 kV line Meadowbrook-Vint Hill into Yeat.
- Cost Information
- Time Estimate
- Jun 01 2029
Contingent Note: Although AH1-690 may not presently have cost responsibility for this upgrade, AH1-690 may need this upgrade in-service to be deliverable to the PJM system. If AH1-690 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.
| Facility | Contingency | |
|---|---|---|
| 4BREMO-AE1-108 POI 138.0 kV Ckt 1 line | (Any) |
System Reinforcement: b4000.344
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.344
- Title
- Build a 500kV line from North Anna substation (bypassing Ladysmith Substation) to a new substation called Kraken. New conductor to have a minimum summer normal rating of 4357MVA.
- Description
- Build a 500kV line from North Anna substation (bypassing Ladysmith Substation) to a new substation called Kraken. New conductor to have a minimum summer normal rating of 4357MVA.
- Cost Information
- Time Estimate
- Sep 16 2030
Contingent Note: Although AH1-690 may not presently have cost responsibility for this upgrade, AH1-690 may need this upgrade in-service to be deliverable to the PJM system. If AH1-690 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.
| Facility | Contingency | |
|---|---|---|
| 4BREMO-AE1-108 POI 138.0 kV Ckt 1 line | (Any) |
System Reinforcement: b4000.352
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.352
- Title
- Cut in Line #568 Ladysmith - Possum Point into Kraken, creating new Line #568 Kraken to Possum Point.
- Description
- Cut in Line #568 Ladysmith - Possum Point into Kraken, creating new Line #568 Kraken to Possum Point.
- Cost Information
- Time Estimate
- Sep 16 2030
Contingent Note: Although AH1-690 may not presently have cost responsibility for this upgrade, AH1-690 may need this upgrade in-service to be deliverable to the PJM system. If AH1-690 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.
| Facility | Contingency | |
|---|---|---|
| 4BREMO-AE1-108 POI 138.0 kV Ckt 1 line | (Any) |
System Reinforcement: b4000.356
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.356
- Title
- Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 86.7 miles in Dominion section).
- Description
- Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 86.7 miles in Dominion section).
- Cost Information
- Time Estimate
- Jun 01 2029
Contingent Note: Although AH1-690 may not presently have cost responsibility for this upgrade, AH1-690 may need this upgrade in-service to be deliverable to the PJM system. If AH1-690 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.
| Facility | Contingency | |
|---|---|---|
| 4BREMO-AE1-108 POI 138.0 kV Ckt 1 line | (Any) |
System Reinforcement: b4000.346
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.346
- Title
- Cut-in 500kV line from Kraken substation into Yeat substation
- Description
- Cut-in 500kV line from Kraken substation into Yeat substation
- Cost Information
- Time Estimate
- Jun 01 2029
Contingent Note: Although AH1-690 may not presently have cost responsibility for this upgrade, AH1-690 may need this upgrade in-service to be deliverable to the PJM system. If AH1-690 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.
| Facility | Contingency | |
|---|---|---|
| 4BREMO-AE1-108 POI 138.0 kV Ckt 1 line | (Any) |
System Reinforcement: b4000.325
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.325
- Title
- Build a new 26.38mi 230kV Line from Elmont – Ladysmith on the existing 5-2 structures between the two stations. New conductor has a summer rating of 1573 MVA.
- Description
- Build a new 26.38mi 230kV Line from Elmont – Ladysmith on the existing 5-2 structures between the two stations. New conductor has a summer rating of 1573 MVA.
- Cost Information
- Time Estimate
- Feb 24 2029
Contingent Note: Although AH1-690 may not presently have cost responsibility for this upgrade, AH1-690 may need this upgrade in-service to be deliverable to the PJM system. If AH1-690 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.
| Facility | Contingency | |
|---|---|---|
| 4BREMO-AE1-108 POI 138.0 kV Ckt 1 line | (Any) |
System Reinforcement: b4000.326
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.326
- Title
- At Elmont substation, install/upgrade associated equipment to accommodate a 4000A line rating for the new 230kV line between Elmont - Ladysmith.
- Description
- At Elmont substation, install/upgrade associated equipment to accommodate a 4000A line rating for the new 230kV line between Elmont - Ladysmith.
- Cost Information
- Time Estimate
- Feb 24 2029
Contingent Note: Although AH1-690 may not presently have cost responsibility for this upgrade, AH1-690 may need this upgrade in-service to be deliverable to the PJM system. If AH1-690 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.
| Facility | Contingency | |
|---|---|---|
| 4BREMO-AE1-108 POI 138.0 kV Ckt 1 line | (Any) |
System Reinforcement: b4000.351
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.351
- Title
- Cut in Line #568 Ladysmith - Possum Point into Kraken, creating Line #9517 Ladysmith to Kraken.
- Description
- Cut in Line #568 Ladysmith - Possum Point into Kraken, creating Line #9517 Ladysmith to Kraken.
- Cost Information
- Time Estimate
- Sep 16 2030
Contingent Note: Although AH1-690 may not presently have cost responsibility for this upgrade, AH1-690 may need this upgrade in-service to be deliverable to the PJM system. If AH1-690 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.
| Facility | Contingency | |
|---|---|---|
| 4BREMO-AE1-108 POI 138.0 kV Ckt 1 line | (Any) |
System Reinforcement: b4000.345
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.345
- Title
- Build a 500kV line from a new substation called Kraken to a new substation called Yeat. New conductor to have a minimum summer normal rating of 4357MVA.
- Description
- Build a 500kV line from a new substation called Kraken to a new substation called Yeat. New conductor to have a minimum summer normal rating of 4357MVA.
- Cost Information
- Time Estimate
- Sep 16 2030
Contingent Note: Although AH1-690 may not presently have cost responsibility for this upgrade, AH1-690 may need this upgrade in-service to be deliverable to the PJM system. If AH1-690 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.
| Facility | Contingency | |
|---|---|---|
| 4BREMO-AE1-108 POI 138.0 kV Ckt 1 line | (Any) |
System Reinforcement: n8471
- Type
- Load Flow
- TO
- PENELEC
- RTEP ID / TO ID
- n8471
- Title
- East Sayre-North Waverly 115kV line upgrade - FirstEnergy (NYISO CY17 driven upgrade)
- Description
- East Sayre Substation: Replace one (1) 115 kV circuit breaker on North Waverly (NYSEG) terminal at East Sayre. Revise wiring for the North Waverly 115kV PR and BU line protection relays to utilize the redundant CT’s and trip coils on the new breaker. East Sayre – North Waverly 115kV line: Replace 3 pole wood Structure 141 due to NYSEG reconductor of East Sayre-North Waverly 115kV line. Enable load encroachment such that all protection elements will achieve the required loadability of 221/263/263/301 MVA (SN/SE/WN/WE) Note: NYISO customers Q387, Q421, Q505 require an upgrade on the East Sayre-North Waverly 115 kV line as part of the CY17 study. NYSEG will complete work at North Waverly substation and the line reconductor/rebuild. FirstEnergy will complete work at East Sayre substation. Per NYISO, the rating that must be achieved for CY17 is 176/176/176 MVA Summer Normal/LTE/STE. NYSEG confirmed the new line ratings for the NYISO side (218/251/282 MVA Summer Normal/LTE/STE; 265/291/318 MVA Winter Normal/LTE/STE), but the East Sayre terminal is still limiting. Once the scope of work and ratings at East Sayre are finalized, the expected line ratings will be updated. NYSEG uses LTE for Rate B, not STE like FirstEnergy.
- Total Cost ($USD)
- $1,417,388
- Allocated Cost ($USD)
- $0
- Time Estimate
- Nov 01 2027
Contingent Note: Based on PJM cost allocation criteria, AH1-690 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AH1-690 could receive cost allocation. Although AH1-690 may not presently have cost responsibility for this upgrade, AH1-690 may need this upgrade in-service to be deliverable to the PJM system. If AH1-690 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.
| Facility | Contingency | |
|---|---|---|
| N.WAV115-26E.SAYRE 115.0 kV Ckt 1 line | (Any) |