AG2-088 Phase II System Impact Study Report
v1.00 released 2026-06-03 18:01
Midlothian 230 kV
150.0 MW Capacity / 150.0 MW Energy
Introduction
This Phase II System Impact Study (SIS) Report has been prepared in accordance with the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 310 for New Service Requests (projects) in Transition Cycle 2 (TC2). The Project Developer/Eligible Customer (developer) is Hermon Energy Center, LLC, and the Transmission Provider (TP) is PJM Interconnection, LLC (PJM). The interconnected Transmission Owner (TO) is Virginia Electric and Power Company (d/b/a Dominion Energy Virginia).
Preface
The Phase II System Impact Study is conducted on an aggregate basis within a New Services Request’s Cycle, and results are provided in both (i) a single Cycle summary format and (ii) an individual project-level basis. The Phase II System Impact Study Results (for both the summary and individual reports) will be publicly available on PJM’s website. Project Developers must obtain the results from the website.
In accordance with PJM Manual 14H, section 4.5, PJM takes the following actions during the Phase II System Impact Study:
- PJM will retool load flow results from the Phase I System Impact Study (summer peak, winter peak and light load) based on decisions made by Project Developers or Eligible Customers during Decision Point I.
- PJM will conduct any required voltage analyses.
- PJM will perform short circuit and stability analyses as required.
- PJM will coordinate with the Affected System to confirm which projects in the PJM Cycle will require Affected System studies. If the Affected System Operator indicates that an Affected System study is required, PJM will:
- Notify the Project Developer or Eligible Customer of the need for an Affected System study and the requirement to execute an Affected System study agreement with the impacted Affected System Operator, and;
- Include the results of the Affected System Operator’s Affected System Study in the Phase II System Impact Study results, if applicable and available.
- The Phase II System Impact Study Results will be publicly available on PJM’s website. Project Developers and Eligible Customers must obtain the results from the website.
The Transmission Owner takes the following actions during the Phase II System Impact Study:
- Verify Interconnection Facilities and Network Upgrades required to accommodate the New Service Request.
- Perform a Facilities Study. The Facilities Study in Phase II System Impact Study phase will be for the physical Interconnection Facilities. The Facilities Study requirements are outlined in Attachment C of this manual. The study will be conducted pursuant to Tariff, Part VII, Subpart D, section 307(A)(7) and Tariff, Part VIII, Subpart C, section 404(A)(7).
Decision Point II Requirements
At the close of Phase II System Impact Study, PJM will initiate Decision Point II (DP2). During DP2, the Project Developer will have 30 days to decide whether to proceed with their project. If the Project Developer elects to proceed, they should provide the elements defined in the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 311.A. Additional information on these elements is available in PJM Manual 14H sections 4.6, 6, and 7.
Allowable project modifications at Decision Point II are defined in PJM Open Access Transmission Tariff, Part VII, Subpart D, section 311.B. Additional information regarding allowable project modifications can be found in PJM Manual 14H, section 9.8.
Adverse Test Eligibility
This New Service Request does not meet the Adverse Study Impact Criteria and has the option to either move forward in the Cycle process or withdraw at DP2 with Readiness Deposit #1 forfeited. See adverse study impact calculation below.
This section details whether a Project Developer or Eligible Customer qualifies for the Adverse Study Impact clause outlined in the PJM OATT, Part VII, Subpart D, section 311.B and Manual 14H, section 6.2.2. In order to qualify for an Adverse Study Impact at Decision Point II, the Network Upgrade cost from Phase I to Phase II must:
- Increase overall by 25% or more
- Increases by more than $10,000 per MW (Includes Costs identified in Affected System studies)
If a New Service Request meets the criteria above and chooses to withdraw the request, PJM will refund the cumulative Readiness Deposit amounts paid at the Application Phase and at Decision Point I (RD1 and RD2, respectively).
The below calculations show the computation of this New Service Request's Adverse Study Impact
General
The Project Developer has proposed a Storage facility located in the Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) zone — Chesterfield County, Virginia. The installed facilities will have a total capability of 150.0 MW with 150.0 MW of this output being recognized by PJM as Capacity.Project Information
Physical Interconnection Facility Study
The transmission owner has completed the Physical Interconnection Facilities Study. This report is available for download.
Point of Interconnection
AG2-088 will interconnect on the Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) transmission system at the Midlothian 230 kV Substation.
Cost Summary
The table below shows a summary of the total cost estimates for this New Service Request project. In Phase II SIS, the interconnected Transmission Owner has performed a facilities study for both the Transmission Owner Interconnection Facilities (TOIF) and Physical Interconnection Network Upgrades. The System Reliability Network Upgrade shown in the table are planning level cost estimates which are subject to change as a result of a facility study performed by the TO during Phase III System Impact Study.
Based on the Phase II SIS results, the AG2-088 project has the following allocation of costs for interconnection. The cost contribution towards Readiness Deposit #3 are also shown below.
| Cost Summary | |||
|---|---|---|---|
| Description | Cost Allocated to AG2-088 | Cost Subject to Readiness* | Cost Subject to Adverse |
| Transmission Owner Interconnection Facilities (TOIF) | $5,270,575 | $0 | $0 |
| Other Scope | $499,571 | $0 | $0 |
| Option To Build Oversight | $0 | $0 | $0 |
| Physical Interconnection Network Upgrades | |||
| Stand Alone Network Upgrades | $0 | $0 | $0 |
| Network Upgrades | $8,334,288 | $8,334,288 | $8,334,288 |
| System Reliability Network Upgrades | |||
| Steady State Thermal & Voltage | $0 | $0 | $0 |
| Transient Stability | $0 | $0 | $0 |
| Short Circuit | $0 | $0 | $0 |
| Transmission Owner Analysis | |||
| SubRegional | $0 | $0 | $0 |
| Distribution | $0 | $0 | $0 |
| Affected System Reinforcements | |||
| AFS - PJM Violations | $0 | $0 | $0 |
| AFS - Non-PJM Violations | $0 | $0 | $0 |
| Total | $14,104,434 | $8,334,288 | $8,334,288 |
* Contributes to calculation for Readiness Deposit #3 (RD3). See Readiness Deposit section of report for additional detail.
Definitions
Transmission Owner Interconnection Facilities: Facilities that are owned, controlled, operated and maintained by the Transmission Owner on the Transmission Owner’s side of the Point of Change of Ownership to the Point of Interconnection, including any modifications, additions or upgrades made to such facilities and equipment, that are necessary to physically and electrically interconnect the Generating Facility with the Transmission System or interconnected distribution facilities.
Stand Alone Network Upgrades: Network Upgrades, which are not part of an Affected System, which a Project Developer may construct without affecting day-to-day operations (e.g. taking a transmission outage) of the Transmission System during their construction.
Network Upgrades: Modifications or additions to transmission-related facilities that are integrated with and support the Transmission Provider’s overall Transmission System for the general benefit of all users of such Transmission System. Network Upgrades have no impact or potential impact on the Transmission System until the final tie-in is complete.
Notes
Note 1: PJM Open Access Transmission Tariff (OATT), Part VII, Subpart D, section 307.5 outlines cost allocation rules. The rules are further clarified in PJM Manual 14H, section 4.2.6. PJM shall identify the New Service Requests in the Cycle contributing to the need for the required Network Upgrades within the Cycle. All New Service Requests that contribute to the need for a Network Upgrade will receive cost allocation for that upgrade pursuant to each New Service Request’s contribution to the reliability violation identified on the transmission system in accordance with PJM Manuals.
Note 2: There will be no inter-Cycle cost allocation for Interconnection Facilities or Network Upgrades identified in the System Impact Study costs identified in a Cycle; all such costs shall be allocated to New Service Requests in that Cycle.
Note 3: For Project Developers with System Reinforcements listed: If this project presents cost allocation to a System Reinforcement indicates $0, then please be aware that as changes to the interconnection process occur, such as other projects withdrawing, reducing in size, etc, the cost responsibilities can change and a cost allocation may be assigned to this project. In addition, although this project presents cost allocation to a System Reinforcement is presently $0, this project may need this system reinforcement completed to be deliverable to the PJM system. If this project desires to come into service prior to completion of the system reinforcement, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the system reinforcement is complete.
Note 4: Please see the ‘Affected Systems Studies’ section of this Phase II SIS report for details on your project’s need for an Affected Systems Study. If your project requires an Affected Systems Study, the Affected Systems impacts may not be available from the Affected System Operator at the time of the PJM Phase II SIS. Therefore, the cost in this section would not reflect any required upgrades by the Affected System until the study is completed. If your project requires an Affected Systems Study and your results are not provided for Phase II SIS, PJM anticipates providing them in the Phase III SIS per Tariff Part VII.D.312.
Readiness Deposit
Per Tariff Part VII, Subpart D, section 311 (Decision Point II) A.1.b and PJM Manual 14H, section 6.2, Readiness Deposit #3 (RD3) are funds committed by the Project Developer or Eligible Customer based upon the applicable contribution to Network Upgrades as defined below. Readiness Deposits are not used to fund studies nor to offset Security.
During Decision Point II (DP2), the Project Developer or Eligible Customer is required to submit Readiness Deposit #3, which is calculated as 20% of cost allocation for required Phase II Network Upgrades minus Readiness Deposit #1 & Readiness Deposit #2.
Note 1: “Network Upgrades” referred to in the calculation include both (i) the Physical Interconnection Network Upgrades and (ii) the System Reliability Network Upgrades as shown in the Cost Summary table.
Note 2: Readiness Deposit #1 (RD1) = ($4,000 * Project Size (MW))
Note 3: Readiness Deposit #2 (RD2) = 10% of cost allocation for required Network Upgrades minus RD1. Readiness Deposit #2 (RD2) can be zero, but may not be a negative number.
Note 4: Readiness Deposit #3 can be zero, but may not be a negative number.
Readiness Deposit #3 Due for Project AG2-088
Readiness Deposit #3 has been calculated for the project based on the Phase II System Impact Study results and is shown in the table below. This Readiness Deposit #3 must be provided at Decision Point II through either a wire transfer or letter of credit per Manual 14H, Section 6.2.
Readiness Deposit #3 Due for AG2-088
For additional detail regarding Readiness Deposit Refunds, reference PJM Manual 14H, section 6.2.1. The Readiness Deposit Letter of Credit template can be found here.
Transmission Owner Scope of Work
The total preliminary cost estimate for the Transmission Owner scope of work (including TOIF and Physical Interconnection Network Upgrades) is given in the table below. These costs do not include CIAC Tax Gross-up.
Transmission Owner Build Option
| Network Upgrades | |||||||
|---|---|---|---|---|---|---|---|
| RTEP ID | Description | Direct | Indirect | Total Cost ($USD) | Allocated Cost ($USD) | ||
| Labor | Materials | Labor | Materials | ||||
| (Pending) | The existing Midlothian 230 kV Substation will be expanded to accommodate the new generation interconnection. | $5,309,388 | $2,057,025 | $800,579 | $167,296 | $8,334,288 | $8,334,288 |
| Other | |||||||
|---|---|---|---|---|---|---|---|
| RTEP ID | Description | Direct | Indirect | Total Cost ($USD) | Allocated Cost ($USD) | ||
| Labor | Materials | Labor | Materials | ||||
| (Pending) | Metering accuracy coupling capacitor voltage transformers (CCVT), metering accuracy current transformers (CT) and associated metering equipment. | $317,977 | $33,491 | $141,737 | $6,366 | $499,571 | $499,571 |
| Transmission Owner Interconnection Facilities | |||||||
|---|---|---|---|---|---|---|---|
| RTEP ID | Description | Direct | Indirect | Total Cost ($USD) | Allocated Cost ($USD) | ||
| Labor | Materials | Labor | Materials | ||||
| (Pending) | The portion of the interconnection switching station which is associated solely with the single feed to the generating facilities collector station. The equipment associated with the Transmission Owner Interconnection Facilities includes the disconnect switch, conductors and connectors. | $3,832,699 | $1,078,623 | $229,449 | $129,804 | $5,270,575 | $5,270,575 |
Developer Build Option
(No Developer Build Option for this project.)
| Build Option Price Comparison | |||||||
|---|---|---|---|---|---|---|---|
| Build Option | Total Cost | Allocated Cost | |||||
| Transmission Owner Build Option | $14,104,434 | $14,104,434 | |||||
| Developer Build Option | (No Developer Build Option) | ||||||
Based on the scope of work for the Interconnection Facilities, it is expected to take a range of 47 to 48 month(s) after the signing of a Generator Interconnection Agreement (as this is a FERC connection) and construction kickoff call to complete the installation of the physical connection work. This assumes that there will be no environmental issues with any of the new properties associated with this project, that there will be no delays in acquiring the necessary permits for implementing the defined interconnection work, and that all system outages will be allowed when requested.
Note that the TO findings were made from a conceptual review of this project. A more detailed review of the connection facilities and their cost will be identified in a future study phase. Further note that the cost estimate data provided should be considered high level estimates since it was produced without a detailed engineering review. The Project Developer will be responsible for the actual cost of construction. TO herein reserves the right to return to any issues in this document and, upon appropriate justification, request additional monies to complete any reinforcements to the transmission systems.
Remote Terminal Work: During Phase II of the PJM interconnection process, TO’s System Protection Engineering Department will review transmission line protection as well as anti-islanding required to accommodate the new generation and interconnection substation. System Protection Engineering will determine the minimal acceptable protection requirements to reliably interconnect the proposed generating facility with the transmission system. The review is based on maintaining system reliability by reviewing TO’s protection requirements with the known transmission system configuration which includes generating facilities in the area. This review may determine that transmission line protection and communication upgrades are required at remote substations.
Transmission Owner Analysis
PJM performed a power flow analysis of the transmission system using a 2028 load flow model and the results were verified by Dominion.
Developer Requirements
The developer is responsible for all design and construction related activities on the developer’s side of the Point of Change in Ownership. Dominion interconnection requirements can be found here.
To the extent that these Applicable Technical Requirements and Standards may conflict with the terms and conditions of the Tariff, the Tariff shall control.
Revenue Metering and SCADA Requirements
The developer will be required to install equipment necessary to provide Revenue Metering (KWH, KVARH) and real time data (KW, KVAR) for their generating Resource. See PJM Manual 01, PJM Manual 14D, and PJM Tariff Part IX, Subpart B, Appendix 2, section 8.Transmission Owner Requirements
The Project Developer will be required to comply with all interconnected Transmission Owner’s revenue metering requirements located at the following link: PJM - Transmission Owner Engineering & Construction Standards.
Summer Peak Analysis
The New Service Request AG2-088 was evaluated as a 150.0 MW (150.0 MW Capacity) injection in the Dominion area.
AG2-088 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 150.0 MW (150.0 MW under study).
Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.
The following flowgates remain after considering the topology reinforcements required by the cycle.
| Study | Area | Facility Description | Contingency Name | Contingency Type | DC|AC | Final Cycle Loading | Rating (MVA) | Rating Type | MVA to Mitigate | MW Contribution | |
|---|---|---|---|---|---|---|---|---|---|---|---|
| GD2 | DVP | 6BREMO-6BREMODIST 230.0 kV Ckt 1 line | DVP_P4-2: H6T576_SRT-A_SENS | Breaker | AC | 119.42 % | 830.0 | C | 991.21 | 18.63 | |
| GD2 | DVP | 6BREMO-6BREMODIST 230.0 kV Ckt 1 line | DVP_P4-2: H6T563_SRT-S_SENS | Breaker | AC | 119.42 % | 830.0 | C | 991.21 | 18.63 | |
| GD2 | DVP | 6BREMO-6BREMODIST 230.0 kV Ckt 1 line | DVP_P1-2: LN MIDLOTHIAN-VONTAY_SRT-A_SENS | Single | AC | 118.66 % | 678.68 | B | 805.35 | 15.74 | |
| GD2 | DVP | 6BREMO-6BREMODIST 230.0 kV Ckt 1 line | DVP_P1-2: LN 587_SRT-A-3 | Single | AC | 104.0 % | 678.68 | B | 705.83 | 10.82 | |
| GD2 | DVP | 6BREMODIST-6FORK UNION 230.0 kV Ckt 1 line | DVP_P4-2: H6T563_SRT-S_SENS | Breaker | AC | 118.86 % | 830.0 | C | 986.57 | 18.63 | |
| GD2 | DVP | 6BREMODIST-6FORK UNION 230.0 kV Ckt 1 line | DVP_P4-2: H6T576_SRT-A_SENS | Breaker | AC | 118.86 % | 830.0 | C | 986.57 | 18.63 | |
| GD2 | DVP | 6BREMODIST-6FORK UNION 230.0 kV Ckt 1 line | DVP_P1-2: LN MIDLOTHIAN-VONTAY_SRT-A_SENS | Single | AC | 117.79 % | 678.68 | B | 799.44 | 15.74 | |
| GD2 | DVP | 6BREMODIST-6FORK UNION 230.0 kV Ckt 1 line | DVP_P1-2: LN 587_SRT-A-3 | Single | AC | 103.06 % | 678.68 | B | 699.44 | 10.82 | |
| GD2 | DVP | 6FORK UNION-6GRAPEVINE 230.0 kV Ckt 1 line | DVP_P1-2: LN MIDLOTHIAN-VONTAY_SRT-A_SENS | Single | AC | 110.74 % | 678.68 | B | 751.6 | 14.63 | |
| GD2 | DVP | 6FORK UNION-6GRAPEVINE 230.0 kV Ckt 1 line | DVP_P1-2: LN 587_SRT-A-3 | Single | AC | 101.43 % | 678.68 | B | 688.38 | 10.0 | |
| GD2 | DVP | 6GRAPEVINE-6MTEAGLE 230.0 kV Ckt 1 line | DVP_P1-2: LN MIDLOTHIAN-VONTAY_SRT-A_SENS | Single | AC | 110.99 % | 661.76 | B | 734.51 | 14.63 | |
| GD2 | DVP | 6GRAPEVINE-6MTEAGLE 230.0 kV Ckt 1 line | DVP_P1-2: LN 587_SRT-A-3 | Single | AC | 101.42 % | 661.76 | B | 671.15 | 10.0 | |
| GD2 | DVP | 6MTEAGLE-6CHARLVL 230.0 kV Ckt 1 line | DVP_P1-2: LN MIDLOTHIAN-VONTAY_SRT-A_SENS | Single | AC | 107.84 % | 661.76 | B | 713.66 | 14.63 |
The following flowgates were eliminated after considering the topology reinforcements required by the cycle.
| Study | Area | Facility Description | Contingency Name | Contingency Type | DC|AC | Final Cycle Loading | Rating (MVA) | Rating Type | MVA to Mitigate | MW Contribution | |
|---|---|---|---|---|---|---|---|---|---|---|---|
| GD2 | DVP | 6BREMO-6BREMODIST 230.0 kV Ckt 1 line | DVP_P1-2: LN 576_SRT-S | Single | AC | 175.55 % | 678.68 | B | 1191.4 | 16.68 | |
| GD2 | DVP | 6BREMO-6BREMODIST 230.0 kV Ckt 1 line | DVP_P4-2: WT576_SRT-S | Breaker | AC | 173.13 % | 830.0 | C | 1436.99 | 16.67 | |
| GD2 | DVP | 6BREMO-6BREMODIST 230.0 kV Ckt 1 line | DVP_P4-2: 57602_SRT-S | Breaker | AC | 173.13 % | 830.0 | C | 1436.97 | 16.67 | |
| GD2 | DVP | 6BREMO-6BREMODIST 230.0 kV Ckt 1 line | DVP_P4-2: H6T563_SRT-S | Breaker | AC | 160.47 % | 830.0 | C | 1331.88 | 19.71 | |
| GD2 | DVP | 6BREMO-6BREMODIST 230.0 kV Ckt 1 line | DVP_P4-2: H6T576_SRT-A | Breaker | AC | 160.47 % | 830.0 | C | 1331.88 | 19.71 | |
| GD2 | DVP | 6BREMODIST-6FORK UNION 230.0 kV Ckt 1 line | DVP_P1-2: LN 576_SRT-S | Single | AC | 174.45 % | 678.68 | B | 1183.97 | 16.68 | |
| GD2 | DVP | 6BREMODIST-6FORK UNION 230.0 kV Ckt 1 line | DVP_P4-2: WT576_SRT-S | Breaker | AC | 172.24 % | 830.0 | C | 1429.6 | 16.67 | |
| GD2 | DVP | 6BREMODIST-6FORK UNION 230.0 kV Ckt 1 line | DVP_P4-2: 57602_SRT-S | Breaker | AC | 172.24 % | 830.0 | C | 1429.58 | 16.67 | |
| GD2 | DVP | 6BREMODIST-6FORK UNION 230.0 kV Ckt 1 line | DVP_P4-2: H6T563_SRT-S | Breaker | AC | 159.58 % | 830.0 | C | 1324.55 | 19.71 | |
| GD2 | DVP | 6BREMODIST-6FORK UNION 230.0 kV Ckt 1 line | DVP_P4-2: H6T576_SRT-A | Breaker | AC | 159.58 % | 830.0 | C | 1324.55 | 19.71 | |
| GD2 | DVP | 6FORK UNION-6GRAPEVINE 230.0 kV Ckt 1 line | DVP_P1-2: LN 576_SRT-S | Single | AC | 171.33 % | 678.68 | B | 1162.8 | 15.42 | |
| GD2 | DVP | 6FORK UNION-6GRAPEVINE 230.0 kV Ckt 1 line | DVP_P4-2: WT576_SRT-S | Breaker | AC | 167.37 % | 830.0 | C | 1389.21 | 15.41 | |
| GD2 | DVP | 6FORK UNION-6GRAPEVINE 230.0 kV Ckt 1 line | DVP_P4-2: 57602_SRT-S | Breaker | AC | 167.37 % | 830.0 | C | 1389.18 | 15.41 | |
| GD2 | DVP | 6FORK UNION-6GRAPEVINE 230.0 kV Ckt 1 line | DVP_P4-2: H6T563_SRT-S | Breaker | AC | 159.8 % | 830.0 | C | 1326.36 | 18.19 | |
| GD2 | DVP | 6FORK UNION-6GRAPEVINE 230.0 kV Ckt 1 line | DVP_P4-2: H6T576_SRT-A | Breaker | AC | 159.8 % | 830.0 | C | 1326.36 | 18.19 | |
| GD2 | DVP | 6GRAPEVINE-6MTEAGLE 230.0 kV Ckt 1 line | DVP_P1-2: LN 576_SRT-S | Single | AC | 173.1 % | 661.76 | B | 1145.53 | 15.42 | |
| GD2 | DVP | 6GRAPEVINE-6MTEAGLE 230.0 kV Ckt 1 line | DVP_P4-2: WT576_SRT-S | Breaker | AC | 169.58 % | 809.0 | C | 1371.94 | 15.41 | |
| GD2 | DVP | 6GRAPEVINE-6MTEAGLE 230.0 kV Ckt 1 line | DVP_P4-2: 57602_SRT-S | Breaker | AC | 169.58 % | 809.0 | C | 1371.91 | 15.41 | |
| GD2 | DVP | 6GRAPEVINE-6MTEAGLE 230.0 kV Ckt 1 line | DVP_P4-2: H6T563_SRT-S | Breaker | AC | 161.82 % | 809.0 | C | 1309.09 | 18.19 | |
| GD2 | DVP | 6GRAPEVINE-6MTEAGLE 230.0 kV Ckt 1 line | DVP_P4-2: H6T576_SRT-A | Breaker | AC | 161.82 % | 809.0 | C | 1309.09 | 18.19 | |
| GD2 | DVP | 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P4-2: 562T563_SRT-S | Breaker | AC | 123.21 % | 1265.1 | C | 1558.74 | 52.9 | |
| GD2 | DVP | 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P1-2: LN 563_SRT-S | Single | AC | 121.76 % | 1057.5 | B | 1287.59 | 52.93 | |
| GD2 | DVP | 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P4-2: 56372_SRT-S | Breaker | AC | 121.28 % | 1265.1 | C | 1534.29 | 53.02 | |
| GD2 | DVP | 6MTEAGLE-6CHARLVL 230.0 kV Ckt 1 line | DVP_P1-2: LN 576_SRT-S | Single | AC | 169.7 % | 661.76 | B | 1122.99 | 15.42 | |
| GD2 | DVP | 6MTEAGLE-6CHARLVL 230.0 kV Ckt 1 line | DVP_P4-2: WT576_SRT-S | Breaker | AC | 166.8 % | 809.0 | C | 1349.42 | 15.41 | |
| GD2 | DVP | 6MTEAGLE-6CHARLVL 230.0 kV Ckt 1 line | DVP_P4-2: 57602_SRT-S | Breaker | AC | 166.8 % | 809.0 | C | 1349.39 | 15.41 | |
| GD2 | DVP | 6MTEAGLE-6CHARLVL 230.0 kV Ckt 1 line | DVP_P4-2: H6T563_SRT-S | Breaker | AC | 159.03 % | 809.0 | C | 1286.56 | 18.19 | |
| GD2 | DVP | 6MTEAGLE-6CHARLVL 230.0 kV Ckt 1 line | DVP_P4-2: H6T576_SRT-A | Breaker | AC | 159.03 % | 809.0 | C | 1286.56 | 18.19 | |
| GD2 | DVP | 6MTEAGLE-6CHARLVL 230.0 kV Ckt 1 line | DVP_P1-2: LN 587_SRT-A-3 | Single | AC | 118.77 % | 661.76 | B | 786.0 | 10.81 | |
| GD2 | DVP | 8LADYSMITH-8POSSUM 500.0 kV Ckt 1 line | DVP_P1-2: LN 594_SRT-S | Single | AC | 118.95 % | 3220.44 | B | 3830.58 | 23.24 | |
| GD2 | DVP | 8LADYSMITH-8POSSUM 500.0 kV Ckt 1 line | DVP_P1-2: LN 573_SRT-S | Single | AC | 117.11 % | 3220.44 | B | 3771.57 | 23.34 | |
| GD2 | DVP | 8MDLTHAN-8NO ANNA 500.0 kV Ckt 1 line | DVP_P1-2: LN 574_SRT-S | Single | AC | 159.65 % | 3220.44 | B | 5141.33 | 49.09 | |
| GD2 | DVP | 8MDLTHAN-8NO ANNA 500.0 kV Ckt 1 line | DVP_P4-2: H2T574_SRT-S | Breaker | AC | 152.37 % | 3940.0 | C | 6003.22 | 49.52 | |
| GD2 | DVP | 8MDLTHAN-8NO ANNA 500.0 kV Ckt 1 line | DVP_P4-2: 557T574_SRT-S | Breaker | AC | 151.78 % | 3940.0 | C | 5980.27 | 49.57 | |
| GD2 | DVP | 8MDLTHAN-8NO ANNA 500.0 kV Ckt 1 line | DVP_P4-2: H1T574_SRT-S | Breaker | AC | 150.72 % | 3940.0 | C | 5938.23 | 49.31 | |
| GD2 | DVP | 8MDLTHAN-8NO ANNA 500.0 kV Ckt 1 line | DVP_P4-2: 574T575_SRT-S | Breaker | AC | 130.04 % | 3940.0 | C | 5123.57 | 44.66 | |
| GD2 | DVP | 8MDLTHAN-8NO ANNA 500.0 kV Ckt 1 line | DVP_P4-1: G202_SRT-S | Breaker | AC | 128.61 % | 3118.0 | C | 4010.0 | 40.51 | |
| GD2 | DVP | 8MDLTHAN-8NO ANNA 500.0 kV Ckt 1 line | DVP_P2-2: NORTH ANNA B2_SRT-S | Bus | AC | 124.42 % | 3118.0 | C | 3879.34 | 40.66 | |
| GD2 | DVP | 8MDLTHAN-8NO ANNA 500.0 kV Ckt 1 line | DVP_P2-2: NORTH ANNA B1_SRT-S | Bus | AC | 124.42 % | 3118.0 | C | 3879.34 | 40.66 | |
| GD2 | DVP | 8MDLTHAN-8NO ANNA 500.0 kV Ckt 1 line | DVP_P1-2: LN 557_SRT-S | Single | AC | 122.54 % | 3220.44 | B | 3946.36 | 43.36 | |
| GD2 | DVP | 8MDLTHAN-8NO ANNA 500.0 kV Ckt 1 line | DVP_P7-1: LN 2090-256_SRT-S | Tower | AC | 102.71 % | 3940.0 | C | 4046.64 | 42.16 | |
| GD2 | DVP | 8MDLTHAN-8NO ANNA 500.0 kV Ckt 1 line | DVP_P7-1: LN 2054-2135_SRT-A | Tower | AC | 102.49 % | 3940.0 | C | 4038.23 | 40.9 | |
| GD2 | DVP | 8MDLTHAN-8NO ANNA 500.0 kV Ckt 1 line | Base Case | Single | AC | 101.48 % | 3193.18 | A | 3240.38 | 40.66 | |
| GD2 | DVP | 8NO ANNA-8LADYSMITH 500.0 kV Ckt 1 line | DVP_P4-2: 57302_SRT-S | Breaker | AC | 149.16 % | 3118.0 | C | 4650.9 | 31.14 | |
| GD2 | DVP | 8NO ANNA-8LADYSMITH 500.0 kV Ckt 1 line | DVP_P1-2: LN 594_SRT-S | Single | AC | 132.01 % | 3220.44 | B | 4251.24 | 29.41 | |
| GD2 | DVP | 8NO ANNA-8LADYSMITH 500.0 kV Ckt 1 line | DVP_P1-2: LN 573_SRT-S | Single | AC | 129.17 % | 3220.44 | B | 4159.96 | 30.84 | |
| GD2 | DVP | 8NO ANNA-8LADYSMITH 500.0 kV Ckt 1 line | DVP_P4-2: SPOTS H1T594_SRT-S | Breaker | AC | 124.53 % | 3940.0 | C | 4906.62 | 30.71 | |
| GD2 | DVP | 8NO ANNA-8LADYSMITH 500.0 kV Ckt 1 line | DVP_P4-2: H1T594_SRT-S | Breaker | AC | 120.22 % | 3940.0 | C | 4736.51 | 29.47 | |
| GD2 | DVP | 8NO ANNA-8LADYSMITH 500.0 kV Ckt 1 line | DVP_P4-2: 515T594_SRT-S | Breaker | AC | 119.98 % | 3940.0 | C | 4727.27 | 29.41 | |
| GD2 | DVP | 8NO ANNA-8LADYSMITH 500.0 kV Ckt 1 line | DVP_P4-2: XT573_SRT-S | Breaker | AC | 118.04 % | 3940.0 | C | 4650.81 | 31.14 | |
| GD2 | DVP | 8NO ANNA-8SPOTSYL 500.0 kV Ckt 1 line | DVP_P4-2: 568T581_SRT-S | Breaker | AC | 202.01 % | 3940.0 | C | 7959.38 | 48.17 | |
| GD2 | DVP | 8NO ANNA-8SPOTSYL 500.0 kV Ckt 1 line | DVP_P4-2: 574T575_SRT-S | Breaker | AC | 166.92 % | 3940.0 | C | 6576.66 | 40.66 | |
| GD2 | DVP | 8NO ANNA-8SPOTSYL 500.0 kV Ckt 1 line | DVP_P4-2: 57502_SRT-S | Breaker | AC | 158.88 % | 3118.0 | C | 4954.02 | 33.72 | |
| GD2 | DVP | 8NO ANNA-8SPOTSYL 500.0 kV Ckt 1 line | DVP_P1-2: LN 552_SRT-S | Single | AC | 154.87 % | 3220.44 | B | 4987.58 | 35.39 | |
| GD2 | DVP | 8NO ANNA-8SPOTSYL 500.0 kV Ckt 1 line | DVP_P1-2: LN 581_SRT-S | Single | AC | 154.04 % | 3220.44 | B | 4960.85 | 35.9 | |
| GD2 | DVP | 8NO ANNA-8SPOTSYL 500.0 kV Ckt 1 line | DVP_P4-2: H1T581_SRT-S | Breaker | AC | 145.2 % | 3940.0 | C | 5721.05 | 35.83 | |
| GD2 | DVP | 8NO ANNA-8SPOTSYL 500.0 kV Ckt 1 line | DVP_P4-2: H1T552_SRT-S | Breaker | AC | 142.53 % | 3940.0 | C | 5615.56 | 35.39 | |
| GD2 | DVP | 8NO ANNA-8SPOTSYL 500.0 kV Ckt 1 line | DVP_P2-2: NORTH ANNA B1_SRT-S | Bus | AC | 126.6 % | 3118.0 | C | 3947.54 | 27.23 | |
| GD2 | DVP | 8NO ANNA-8SPOTSYL 500.0 kV Ckt 1 line | DVP_P2-2: NORTH ANNA B2_SRT-S | Bus | AC | 126.6 % | 3118.0 | C | 3947.54 | 27.23 | |
| GD2 | DVP | 8NO ANNA-8SPOTSYL 500.0 kV Ckt 1 line | DVP_P7-1: LN 11-2199_SRT-A-1 | Tower | AC | 109.64 % | 3940.0 | C | 4319.87 | 28.21 | |
| GD2 | DVP | 8NO ANNA-8SPOTSYL 500.0 kV Ckt 1 line | DVP_P7-1: LN 11-2199_SRT-A-2 | Tower | AC | 109.38 % | 3940.0 | C | 4309.68 | 28.21 | |
| GD2 | DVP | 8NO ANNA-8SPOTSYL 500.0 kV Ckt 1 line | Base Case | Single | AC | 108.67 % | 3193.18 | A | 3470.14 | 27.23 | |
| GD2 | DVP | 8SPOTSYL-8MORRSVL 500.0 kV Ckt 1 line | DVP_P4-2: 568T581_SRT-S | Breaker | AC | 203.0 % | 3940.0 | C | 7998.06 | 46.72 | |
| GD2 | DVP | 8SPOTSYL-8MORRSVL 500.0 kV Ckt 1 line | DVP_P4-2: 545T552_SRT-S | Breaker | AC | 175.64 % | 3118.0 | C | 5476.52 | 34.65 | |
| GD2 | DVP | 8SPOTSYL-8MORRSVL 500.0 kV Ckt 1 line | DVP_P4-2: 574T575_SRT-S | Breaker | AC | 168.62 % | 3940.0 | C | 6643.56 | 39.43 | |
| GD2 | DVP | 8SPOTSYL-8MORRSVL 500.0 kV Ckt 1 line | DVP_P1-2: LN 552_SRT-S | Single | AC | 161.05 % | 3220.44 | B | 5186.56 | 35.31 | |
| GD2 | DVP | 8SPOTSYL-8MORRSVL 500.0 kV Ckt 1 line | DVP_P1-2: LN 581_SRT-S | Single | AC | 156.69 % | 3220.44 | B | 5046.02 | 34.78 | |
| GD2 | DVP | 8SPOTSYL-8MORRSVL 500.0 kV Ckt 1 line | DVP_P4-2: H1T552_SRT-S | Breaker | AC | 147.64 % | 3940.0 | C | 5817.13 | 35.31 | |
| GD2 | DVP | 8SPOTSYL-8MORRSVL 500.0 kV Ckt 1 line | DVP_P4-2: H1T581_SRT-S | Breaker | AC | 147.59 % | 3940.0 | C | 5814.94 | 34.71 | |
| GD2 | DVP | 8SPOTSYL-8MORRSVL 500.0 kV Ckt 1 line | DVP_P2-2: MORRISVILLE B1_SRT-S | Bus | AC | 134.94 % | 3118.0 | C | 4207.35 | 26.73 | |
| GD2 | DVP | 8SPOTSYL-8MORRSVL 500.0 kV Ckt 1 line | DVP_P7-1: LN 2-2199_SRT-A-1 | Tower | AC | 116.02 % | 3940.0 | C | 4571.15 | 27.83 | |
| GD2 | DVP | 8SPOTSYL-8MORRSVL 500.0 kV Ckt 1 line | Base Case | Single | AC | 115.83 % | 3220.44 | A | 3730.18 | 26.73 | |
| GD2 | DVP | 8SPOTSYL-8MORRSVL 500.0 kV Ckt 1 line | DVP_P7-1: LN 2-2199_SRT-A-2 | Tower | AC | 115.74 % | 3940.0 | C | 4560.31 | 27.83 | |
| GD2 | DVP | 8SPOTSYL-8MORRSVL 500.0 kV Ckt 1 line | DVP_P2-2: GERMANNA_SRT-A | Bus | AC | 112.89 % | 3940.0 | C | 4447.98 | 27.51 |
Winter Peak Analysis
The New Service Request AG2-088 was evaluated as a 150.0 MW (150.0 MW Capacity) injection in the Dominion area.
AG2-088 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 150.0 MW (150.0 MW under study).
Note: The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for single or N-1 contingencies and multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.
The following flowgates remain after considering the topology reinforcements required by the cycle.
(No impacts were found for this analysis)
The following flowgates were eliminated after considering the topology reinforcements required by the cycle.
(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)
Light Load Analysis
The New Service Request AG2-088 was evaluated as a 150.0 MW injection and 150.0 MW withdrawal in the Dominion area.
AG2-088 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 150.0 MW (150.0 MW under study).
Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.
The following flowgates remain after considering the topology reinforcements required by the cycle.
| Study | Area | Facility Description | Contingency Name | Contingency Type | DC|AC | Final Cycle Loading | Rating (MVA) | Rating Type | MVA to Mitigate | MW Contribution | |
|---|---|---|---|---|---|---|---|---|---|---|---|
| GD2 | AEP | 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line | AEP_P4_#7422_05CLOVRD 500_EE2_SRT-A | Breaker | AC | 173.68 % | 1180.0 | B | 2049.45 | 16.82 | |
| GD2 | AEP | 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line | DVP_P4-2: 56602_SRT-A | Breaker | AC | 173.67 % | 1180.0 | B | 2049.35 | 16.82 | |
| GD2 | AEP | 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line | DVP_P4-2: 547T566_SRT-L | Breaker | AC | 173.35 % | 1180.0 | B | 2045.56 | 16.85 | |
| GD2 | AEP | 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line | AEP_P1-2_#7422_16_SRT-A | Single | AC | 171.54 % | 1180.0 | B | 2024.13 | 16.82 |
The following flowgates were eliminated after considering the topology reinforcements required by the cycle.
| Study | Area | Facility Description | Contingency Name | Contingency Type | DC|AC | Final Cycle Loading | Rating (MVA) | Rating Type | MVA to Mitigate | MW Contribution | |
|---|---|---|---|---|---|---|---|---|---|---|---|
| GD2 | DVP | 6BREMO-6BREMODIST 230.0 kV Ckt 1 line | DVP_P1-2: LN 576_SRT-L | Single | AC | 115.7 % | 830.96 | B | 961.39 | 16.37 | |
| GD2 | DVP | 6BREMO-6BREMODIST 230.0 kV Ckt 1 line | AEP_P1-2_#7422_16_SRT-A | Single | AC | 110.58 % | 830.96 | B | 918.86 | 11.15 | |
| GD2 | DVP | 6BREMODIST-6FORK UNION 230.0 kV Ckt 1 line | DVP_P1-2: LN 576_SRT-L | Single | AC | 115.51 % | 830.96 | B | 959.87 | 16.37 | |
| GD2 | DVP | 6BREMODIST-6FORK UNION 230.0 kV Ckt 1 line | AEP_P1-2_#7422_16_SRT-A | Single | AC | 110.39 % | 830.96 | B | 917.31 | 11.15 | |
| GD2 | DVP | 6CHESTF B-6BASIN 230.0 kV Ckt 1 line | DVP_P1-2: LN 563_SRT-L | Single | AC | 108.72 % | 722.86 | B | 785.91 | 13.4 | |
| GD2 | DVP | 6FORK UNION-6GRAPEVINE 230.0 kV Ckt 1 line | DVP_P1-2: LN 576_SRT-L | Single | AC | 117.38 % | 830.96 | B | 975.35 | 15.11 | |
| GD2 | DVP | 6FORK UNION-6GRAPEVINE 230.0 kV Ckt 1 line | AEP_P1-2_#7422_16_SRT-A | Single | AC | 114.63 % | 830.96 | B | 952.49 | 9.92 | |
| GD2 | DVP | 6GRAPEVINE-6MTEAGLE 230.0 kV Ckt 1 line | DVP_P1-2: LN 576_SRT-L | Single | AC | 120.16 % | 808.4 | B | 971.38 | 15.11 | |
| GD2 | DVP | 6GRAPEVINE-6MTEAGLE 230.0 kV Ckt 1 line | AEP_P1-2_#7422_16_SRT-A | Single | AC | 117.33 % | 808.4 | B | 948.5 | 9.92 | |
| GD2 | DVP | 6MTEAGLE-6CHARLVL 230.0 kV Ckt 1 line | DVP_P1-2: LN 576_SRT-L | Single | AC | 119.55 % | 808.4 | B | 966.48 | 15.11 | |
| GD2 | DVP | 6MTEAGLE-6CHARLVL 230.0 kV Ckt 1 line | AEP_P1-2_#7422_16_SRT-A | Single | AC | 116.72 % | 808.4 | B | 943.57 | 9.92 | |
| GD2 | DVP | 8NO ANNA-8SPOTSYL 500.0 kV Ckt 1 line | DVP_P4-2: 568T581_SRT-L | Breaker | AC | 105.16 % | 4628.0 | C | 4866.67 | 47.02 |
Short Circuit Analysis
Analysis Complete - No Issues
Based on PJM’s TC2 Phase II Short Circuit Analysis, this project did not contribute >1% fault duty to any previously identified overdutied breakers, nor did it cause any new overdutied breakers.
Please note that in TC2 Phase III, PJM will perform additional analysis including the evaluation of impacts from topology upgrades which may have potential effects on breaker duties not seen in the Phase II analysis.
Stability Analysis
Analysis Complete - No Issues
New Service Requests (projects) in PJM Transition Cycle 2 (TC2) Cluster 12 are listed in Table 1 below. This report will cover the dynamic analysis of TC2 Cluster 12 projects.
Table 1: Transition Cycle 2 Cluster 12 Projects
|
|
|
|
|
|
|
|
Cluster | Project | Fuel Type | Transmission Owner | MFO | MWE | MWC | Point of Interconnection |
12 | AG2-088 | Battery | Dominion | 150 | 150 | 150 | Midlothian 230 kV Substation |
AG2-384 | Battery | Dominion | 60 | 60 | 24 | Chesterfield ‘A’ 230 kV Substation | |
AH1-679 | Natural Gas | Dominion | 766 | 766 | 716 | Four Rivers 230 kV Substation |
The purpose of the transient stability analysis is to determine the system impact of the generation facility. This study will determine system improvements, if any, needed to reduce violations in the transient stability analysis caused by the addition of the projects in TC2 Cluster 12.
The load flow scenario for the analysis was based on the Regional Transmission Expansion Plan (RTEP) 2028 summer peak and Light Load cases, modified to include applicable projects. TC2 Cluster 12 projects have been dispatched online at maximum real power output. The reactive power output for TC2 Cluster 12 projects was set to have near unity power factor measured at the high-side of the main substation transformer for the Summer Peak case. For the Light Load case, Dominion Energy’s Light Load Criteria was used to dispatch the TC2 Cluster 12 projects to near 50% of their minimum reactive limits. The Light Load Criteria could not be implemented for AH1-679 due to system constraints.
TC2 Cluster 12 projects were tested for compliance with NERC, PJM, Dominion Energy and other applicable criteria. 739 contingencies were studied, each with a 20 second simulation time period. The contingencies studied included:
- No-fault steady-state operation
- Three-phase faults with normal clearing time
- Single-phase bus faults with normal clearing time
- Single-phase faults with a stuck breaker
- Single-phase faults placed at 80% of the line with delayed clearing at remote line end because of primary communications/relaying failure
- Single-phase faults with loss of multiple circuit tower
For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.
The results of the analysis were evaluated against the following recovery criteria per PJM’s Regional Transmission Planning Process and Dominion Energy’s transmission planning criteria:
- TC2 Cluster 12 projects can ride through the faults (except for faults where protective action trips a generator(s)).
- The system with TC2 Cluster 12 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3%.
- Following fault clearing, all bus voltages recover to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus) and the final voltages are within the steady-state voltage ranges below per Dominion Energy’s transmission planning criteria.
- P1 Category Contingencies:
- 0.93 to 1.05 p.u. for 230, 115, 69 kV facilities
- 0.93 to 1.03 p.u. for 138 kV facilities due to legacy switches
- 1.01 to 1.096 p.u. for 500 kV facilities
- P2, P4, P5, and P7 Category Contingencies:
- 0.90 to 1.05 p.u. for 230, 115, 69 kV facilities
- 0.90 to 1.03 p.u. for 138 kV facilities due to legacy switches
- 1.00 to 1.096 p.u. for 500 kV facilities
- No transmission element should trip, other than those either directly connected or designed to trip as a consequence of that fault.
TC2 Cluster 12 projects met the above criteria with some facility modifications incorporated; these modifications are provided below. No mitigation is required to connect the TC2 Cluster 12 projects.
Facility modification and model tuning is recommended. The generator owner should provide their preferred adjustments for the issues described in the summary of results:
- AG2-088
- Plant tripped for the voltage protection model 1.1 p.u. at 2 seconds while the inverter was attempting to regulate grid voltage. Please increase the tripping time to a reasonably high number considering equipment limitations.
- Plant reactive output appears to not settle within the 20 second simulation for some fault scenarios. A 4% voltage-reactive droop setting along with a +/- 0.001 p.u. deadband is recommended to enable the plant to settle quicker.
- AG2-384
- The main transformer high side tap had to be adjusted to 1.025 p.u. in order to pass the power factor requirements. It is requested that future data submittals include this tap adjustment.
- AG2-583
- Plant reactive output appears to not settle within the 20 second simulation for some fault scenarios. A 4% voltage-reactive droop setting is recommended to enable the plant to settle quicker.
- AD1-151/AG2-661
- Plant controllers froze and tripped for a P5 fault scenario. It is recommended that the AD1-151 REECA1 Vup parameter be adjusted from 1.15 p.u. to 1.20 p.u. and the AG2-661 REECC1 Vup parameter be adjusted from 1.12 p.u. to 1.20 p.u. These adjustments enable the units to ride through the specific fault scenario.
- Within the PLNTBU1 model, Kp, Ki should be reduced from 2, 50 to 0.5, 3.0, respectively. A 4% voltage-reactive droop setting is recommended to help the plant coordinate voltage regulation with other sources.
- AF2-110
- Plant tripped for the voltage protection model 1.2 p.u. at 0.001 seconds. Please increase the tripping time to a reasonably high number considering equipment limitations.
- AE2-247
- Plant tripped for the voltage protection model 1.2 p.u. at 0.017 seconds. Please increase the tripping time to a reasonably high number considering equipment limitations.
- AE1-157
- Plant tripped for the frequency protection model 61.8 Hz at 0.0 seconds. Please increase the tripping time to a reasonably high number considering equipment limitations.
- AD2-074
- Plant tripped for the frequency protection model 61.7 Hz at 0.001 seconds. Please increase the tripping time to a reasonably high number considering equipment limitations.
- Plant tripped for the voltage protection model 1.2 p.u. at 0.001 seconds. Please increase the tripping time to a reasonably high number considering equipment limitations.
- Plant controllers froze and tripped for a few fault scenarios. It is recommended that the REGCAU1 Iqrmax/Iqrmin values should be increased from +/- 0.02 p.u. to +/- 999 p.u. These adjustments enable the units to ride through the specific fault scenarios.
- AD1-105
- Plant tripped for the voltage protection model 1.2 p.u. at 0.001 seconds. Please increase the tripping time to a reasonably high number considering equipment limitations.
- Plant tripped for the voltage protection model 1.175 p.u. at 0.2 seconds. Please increase the tripping time to a reasonably high number considering equipment limitations.
- Plant tripped for the frequency protection model 61.7 Hz at 0.001 seconds. Please increase the tripping time to a reasonably high number considering equipment limitations.
- Plant controllers froze and tripped for a few fault scenarios. It is recommended that the REECBU1 Vdip parameter be adjusted from 0.8 p.u. to 0.88 p.u. and the REPCA voltage reactive parameters Kp, Ki, Vfrz be adjusted from 0.01, 25, 0.7 to 4, 6, 0.88, respectively. These adjustments enable the unit to ride through the specific fault scenarios.
- AD1-025
- Plant reactive output appears to not settle within the 20 second simulation for some fault scenarios. A 4% voltage-reactive droop setting is recommended to enable the plant to settle quicker.
- AC2-165
- Plant tripped for the frequency protection model 61.8 Hz at 0.0 seconds. Please increase the tripping time to a reasonably high number considering equipment limitations.
- Plant tripped for the frequency protection model 57.8 Hz at 0.0 seconds. Please increase the tripping time to a reasonably high number considering equipment limitations.
- AC1-158
- Plant tripped for the voltage protection model 1.31 p.u. at 0.014 seconds. Please increase the tripping time to a reasonably high number considering equipment limitations.
Note:
- PJM will contact the project developer to verify the model tuning recommendation for non-TC2 Cycle project.
- TO has requested additional fault to be tested at Ladysmith CT substation, which will be evaluated during Phase 3 of the analysis.
Reactive Power Analysis
The AG2-088 facility met the 0.95 leading and 0.95 lagging power factor requirements at the main transformer high side.
Steady-State Voltage Analysis
Analysis Complete - No Issues
Steady State Voltage Analysis complete, no voltage issues identified.
New Service Request Dependencies
The New Service Requests below are listed in one or more dispatch for the overloads identified in this report. These projects contribute to the loading of the overloaded facilities identified in this report. The percent overload of a facility and cost allocation you may have towards a particular reinforcement could vary depending on the action of other projects. The status of each project at the time of the analysis is presented in the table. This list may change as other projects withdraw or modify their requests. This table is valid for load flow analyses only.
| New Service Requests Dependencies | ||
|---|---|---|
| Project ID | Project Name | Status |
| AA1-038 | Lexington-Low Moor 230kV | Under Construction |
| AA1-050 | Tarboro-Everetts 230kV | In Service |
| AA1-063A | Carolina–Seaboard 115kV | In Service |
| AA1-067 | Everetts 34.5kV | In Service |
| AA1-139 | Hickory-Shawboro 230kV | In Service |
| AA2-053 | Carolina-Jackson 115kV | In Service |
| AA2-057 | Hornertown-Whitakers 115kV | In Service |
| AA2-174 | Carolina-Jackson 115kV | In Service |
| AA2-178 | Mackeys 230kV | In Service |
| AB1-027 | Old Church 34.5 KV | In Service |
| AB1-081 | Anaconda-Mayo Dunbar 115kV | In Service |
| AB1-132 | Thelma 230kV | In Service |
| AB2-022 | Elizabeth City 34.5kV | In Service |
| AB2-024 | Correctional 34.5kV | In Service |
| AB2-025 | Sapony 34.5kV | In Service |
| AB2-026 | Powhatan 34.5kV | In Service |
| AB2-029 | Remington 34.5kV | In Service |
| AB2-031 | Brink-Trego 115kV | In Service |
| AB2-040 | Brink 115kV | In Service |
| AB2-043 | Chase City 115kV | In Service |
| AB2-045 | Buckingham 34.5kV | In Service |
| AB2-059 | Benson-Dunbar 115kV | In Service |
| AB2-060 | Chase City-Lunenburg 115kV | In Service |
| AB2-077 | Buggs Island-Chase City 115kV | In Service |
| AB2-078 | Buggs Island-Chase City 115kV | In Service |
| AB2-079 | Buggs Island-Chase City 115kV | In Service |
| AB2-099 | Ahoskie 34.5kV | In Service |
| AB2-134 | Hopewell-Surry 230kV | In Service |
| AB2-158 | Louisa-South Anna 230kV | In Service |
| AB2-161 | Waverly #2 DP 115kV | In Service |
| AB2-169 | Pantago-Five Points 115kV | In Service |
| AB2-174 | Emporia-Trego 115kV | In Service |
| AB2-190 | Hopewell-Surry 230kV | In Service |
| AC1-027 | Pendleton 34.5kV | In Service |
| AC1-034 | Heartsease DP - Mayo Dunbar 115kV | Engineering & Procurement |
| AC1-036 | Twittys Creek 34.5kV | In Service |
| AC1-054 | Kerr Dam–Eatons Ferry 115 kV | In Service |
| AC1-075 | Perth-Hickory Grove 115kV | In Service |
| AC1-076 | Locust Grove-Paytes 115kV | In Service |
| AC1-086 | Thelma 230kV | Under Construction |
| AC1-098 | Dawson-South Justice 115kV | In Service |
| AC1-099 | Dawson-South Justice 115kV | In Service |
| AC1-101 | Johns Creek-Excel 138kV I | Engineering & Procurement |
| AC1-102 | Johns Creek-Excel 138kV II | Engineering & Procurement |
| AC1-105 | Halifax-Mt. Laurel 115kV | In Service |
| AC1-118 | Westmoreland 34.5kV | In Service |
| AC1-147 | Grassfield 34.5kV | In Service |
| AC1-158 | Spotsylvania 500kV | In Service |
| AC1-161 | Septa 500kV | In Service |
| AC1-164 | Chickahominy 230kV | Partially in Service - Under Construction |
| AC1-189 | Chinquapin-Everetts 230kV | Under Construction |
| AC1-191 | Elmont 115kV | Engineering & Procurement |
| AC1-208 | Cox-Whitakers 115kV | Under Construction |
| AC1-221 | Halifax-Person 230kV | In Service |
| AC1-222 | Crystal Hill-Halifax 115kV | In Service |
| AC2-012 | Grassfield-Great Bridge 115kV | In Service |
| AC2-079 | Ivor-Oak Ridge 115kV | Under Construction |
| AC2-100 | Halifax-Person 230kV | In Service |
| AC2-137 | Elko 34.5kV | In Service |
| AC2-138 | Northern Neck 34.5kV | In Service |
| AC2-141 | Septa 500kV | Engineering & Procurement |
| AC2-165 | Bremo-Powhatan 230kV | Suspended |
| AD1-022 | Cashie-Trowbridge 230 kV | Engineering & Procurement |
| AD1-025 | Hopewell-Surry 230 kV | In Service |
| AD1-033 | Fentress-Landstown 230 kV | In Service |
| AD1-041 | Harmony Village-Shackleford 115 kV | In Service |
| AD1-056 | Hornertown-Hathaway 230 kV | Suspended |
| AD1-057 | Hornertown-Hathaway 230 kV | Suspended |
| AD1-063 | Harmony Village 34.5 kV | In Service |
| AD1-074 | Trowbridge 230 kV | Engineering & Procurement |
| AD1-075 | Trowbridge 230 kV | Engineering & Procurement |
| AD1-076 | Trowbridge 230 kV | Engineering & Procurement |
| AD1-082 | Bakers Pond-Ivor 115kV | In Service |
| AD1-087 | Clover-Sedge Hill 230 kV | In Service |
| AD1-088 | Briery-Clover 230 kV | Suspended |
| AD1-105 | Kings Dominion DP 115 kV | Under Construction |
| AD1-115 | Mountain Run-Mitchell 115 kV | Withdrawn |
| AD1-144 | Kings Fork 34.5 kV | In Service |
| AD1-151 | Hopewell-Surry 230 kV | Suspended |
| AD1-152 | Clover-Sedge Hill 230 kV | In Service |
| AD2-030 | Wan 34.5 kV | In Service |
| AD2-033 | Chase City-Lunenburg 115 kV | Under Construction |
| AD2-073 | Sanders DP 230 kV | In Service |
| AD2-074 | Garner DP-Lancaster 115 kV | Under Construction |
| AD2-085 | Myrtle-Windsor DP 115kV | Engineering & Procurement |
| AD2-160 | Hickory-Moyock 230kV | In Service |
| AD2-179 | Morgans Cut-Glen Lyn 138kV | Withdrawn |
| AD2-202 | Clover-Sedge Hill 230kV | In Service |
| AE1-072 | Shawboro-Sligo 230 kV | Under Construction |
| AE1-074 | Winterpock 34.5 kV | Under Construction |
| AE1-075 | Powhatan 34.5 kV | In Service |
| AE1-103 | Holland-Union Camp 115 kV | Suspended |
| AE1-108 | Bremo-Scottsville 138 kV | Under Construction |
| AE1-149 | Disputanta-Poe 115 kV | Suspended |
| AE1-155 | Garner-Northern Neck 115 kV | In Service |
| AE1-162 | Smithfield 34.5 kV | In Service |
| AE1-173 | Carson-Suffolk 500 kV | Under Construction |
| AE1-175 | Light Foot 34.5 kV | In Service |
| AE1-190 | Harmony Village-Shackleford 115 kV | In Service |
| AE1-191 | Harmony Village-Shackleford 115 kV | In Service |
| AE1-212 | Grandview-Clifftop 138 kV | Suspended |
| AE2-005 | Harmony Village-Shackleford 115 kV | Suspended |
| AE2-027 | Harrowgate-Locks 115kV | Suspended |
| AE2-029 | Grottoes-Merck 115kV | Under Construction |
| AE2-033 | Clubhouse-Sapony 230 kV | Suspended |
| AE2-034 | Mackeys 230 kV | Partially in Service - Under Construction |
| AE2-040 | Sapony 34.5 kV | In Service |
| AE2-051 | Carson-Septa 500 kV | Engineering & Procurement |
| AE2-092 | Kidds Store-Sherwood 115 kV | Engineering & Procurement |
| AE2-094 | Carson-Rogers Road 500 kV | Engineering & Procurement |
| AE2-104 | Suffolk 115 kV | Withdrawn |
| AE2-140 | Axton-Danville 138 kV | Suspended |
| AE2-160 | Kanawha River 138 kV | Engineering & Procurement |
| AE2-166 | Stockton 138 kV | Suspended |
| AE2-183 | Rogers Road 500 kV | In Service |
| AE2-212 | Harrowgate 34 kV | Engineering & Procurement |
| AE2-253 | Hickory-Moyock 230 kV | In Service |
| AE2-259 | Curdsville-Willis Mtn 115 kV | Engineering & Procurement |
| AE2-291 | Grit DP-Perth 115 kV | Engineering & Procurement |
| AE2-326 | Jacksons Ferry 138 kV | Engineering & Procurement |
| AE2-346 | Ahoskie 34.5 kV | In Service |
| AF1-014 | Harmony Village-Shackleford 115 kV | Suspended |
| AF1-017 | Myrtle-Windsor 115 kV | Engineering & Procurement |
| AF1-032 | Suffolk 34.5 kV | In Service |
| AF1-042 | Garner DP-Lancaster 115 kV | Engineering & Procurement |
| AF1-049 | Berry Hill 138 kV | Under Construction |
| AF1-058 | Welco 34.5 kV | In Service |
| AF1-069 | Carson-Rogers Rd 500 kV | Engineering & Procurement |
| AF1-114 | Oak Grove-Dahlgren 230 kV | Engineering & Procurement |
| AF1-123 | Harper 230 kV | Under Construction |
| AF1-124 | Harper 230 kV | Partially in Service - Under Construction |
| AF1-125 | Harper 230 kV | Under Construction |
| AF1-128 | Chesterfield 230 kV | Under Construction |
| AF1-129 | Chesterfield 230 kV | Engineering & Procurement |
| AF1-130 | Inez 138 kV | Suspended |
| AF1-162 | Inez 138 kV | Engineering & Procurement |
| AF1-291 | Tyler 34.5 kV | Engineering & Procurement |
| AF1-292 | Fields 34.5kV | Under Construction |
| AF1-294 | Jetersville-Ponton 115 kV | Engineering & Procurement |
| AF2-013 | Arnold's Corner-Dahlgren 230 kV | Engineering & Procurement |
| AF2-018 | Inez 138 kV | Engineering & Procurement |
| AF2-042 | Clover-Rawlings 500 kV | Engineering & Procurement |
| AF2-043 | Suffolk 34.5 kV | In Service |
| AF2-054 | Wan 34.5 kV | In Service |
| AF2-080 | Chinquapin-Everetts 230 kV | Withdrawn |
| AF2-081 | Moyock 230 kV | Engineering & Procurement |
| AF2-085 | Midlothian 34.5 kV | In Service |
| AF2-091 | Oak Grove-Dahlgren 230 kV | Engineering & Procurement |
| AF2-106 | Hazel Hollow-Glen Lyn #1 138 kV | Engineering & Procurement |
| AF2-107 | Clifford 138 kV | Withdrawn |
| AF2-110 | Suffolk 115 kV | Withdrawn |
| AF2-115 | Jetersville-Ponton 115 kV | Engineering & Procurement |
| AF2-144 | Powhatan 34.5 kV | In Service |
| AF2-222 | Madisonville DP-Twitty's Creek 115 kV | Engineering & Procurement |
| AF2-299 | Fields 34.5 kV | Engineering & Procurement |
| AF2-382 | Hurley 69 kV | Engineering & Procurement |
| AG1-007 | Tar River 12.5 kV | Withdrawn |
| AG1-021 | Jetersville-Ponton 115 kV | Engineering & Procurement |
| AG1-037 | Ahoskie 34.5 kV | Withdrawn |
| AG1-038 | Garner DP-Lancaster 115 kV | Engineering & Procurement |
| AG1-105 | Mount Laurel-Barnes Junction 115 kV | Under Construction |
| AG1-106 | Thelma 230 kV | Withdrawn |
| AG1-145 | Lightfoot 34.5 kV | In Service |
| AG1-152 | Remington CT 230 kV | Engineering & Procurement |
| AG1-153 | Heritage 500 kV | Under Construction |
| AG1-282 | Dunnsville 34.5 kV | Withdrawn |
| AG1-285 | Chase City-Central 115 kV | Engineering & Procurement |
| AG1-342 | Dryburg 115 kV | Engineering & Procurement |
| AG1-469 | Gordonsville 34.5 kV | Withdrawn |
| AG1-508 | Point Lookout 69 kV | Withdrawn |
| AG1-532 | Fields 34.5 kV | Under Construction |
| AG1-558 | Buckner 34.5 kV | Withdrawn |
| AG1-559 | Caroline Pines 22 kV | Withdrawn |
| AG2-068 | Heritage - Wake 500 kV | Active |
| AG2-069 | Heritage - Wake 500 kV | Active |
| AG2-077 | Clover-Rawlings 500 kV | Active |
| AG2-095 | Hopewell 34.5 kV (Circuit 313) | Active |
| AG2-151 | Trices Lake - James River Tap 115 kV | Active |
| AG2-171 | Lunenburg - Nutbush 115 kV | Active |
| AG2-184 | Harbert Metering 138 kV | Active |
| AG2-198 | Briery - Finneywood 230 kV | Active |
| AG2-213 | Gary D.P Tap - Gary D.P 115 kV | Active |
| AG2-240 | Old Church 34.5 kV | Active |
| AG2-262 | Dryburg 115 kV | Active |
| AG2-270 | Clover 230 kV | Active |
| AG2-272 | Berry Hill 138 kV | Active |
| AG2-339 | Rogers Road - Carson 500 kV | Active |
| AG2-341 | Ridge Road 115 kV | Active |
| AG2-360 | Broadford 138 kV | Active |
| AG2-369 | Heritage - Wake 500 kV | Active |
| AG2-382 | Cashie 230 kV | Active |
| AG2-426 | Wakefield - Waverly 115 kV | Active |
| AG2-436 | Carson - Rogers Road 500 kV | Active |
| AG2-440 | Twittys Creek - Madisonville 115 kV | Active |
| AG2-441 | Twittys Creek - Madisonville 115 kV | Active |
| AG2-442 | Twittys Creek - Madisonville 115 kV | Active |
| AG2-518 | Tech Drive 138 kV | Active |
| AG2-522 | Five Forks DP - Littleton DP 115 kV | Active |
| AG2-566 | Briery - Finneywood 230 kV | Active |
| AG2-568 | Stink Run - Sundial 138 kV | Active |
| AG2-570 | Heritage - Wake 500 kV | Active |
| AG2-571 | Heritage - Wake 500 kV | Active |
| AG2-581 | Rawlings - Unity 500 kV | Active |
| AG2-583 | Bremo - Cartersville 230 kV | Active |
| AG2-659 | Palmer Springs - Hawtree 115 kV | Active |
| AG2-661 | Hopewell - Colonial Trail 230 kV | Active |
| AH1-033 | Sligo 34.5 kV | Active |
| AH1-040 | Mackeys - Creswell 115 kV | Active |
| AH1-071 | Midlothian 34.5 kV | Active |
| AH1-072 | Red Onion - VC5 69 kV | Active |
| AH1-073 | Red Onion - VC5 69 kV | Active |
| AH1-098 | Wolf Glade-West Carroll 138 kV | Active |
| AH1-106 | Winterpock 34.5kV | Active |
| AH1-107 | Winterpock 34.5kV | Active |
| AH1-108 | Spruance NUG 230 kV | Active |
| AH1-133 | Saltville - Tazewell 138 kV | Active |
| AH1-144 | Peter's Mountain 138 kV | Active |
| AH1-145 | Peter's Mountain 138 kV | Active |
| AH1-170 | Columbia DP 115kV | Active |
| AH1-188 | Pigeon Creek 138 kV | Active |
| AH1-216 | Smithfield-Surry 230 kV | Active |
| AH1-221 | Heritage 500 kV | Active |
| AH1-227 | Flemming - Fremont 69 kV | Active |
| AH1-251 | Todds Tavern- Spotsylvania/Goldsdale 115kV | Active |
| AH1-263 | Chancellor 115 kV | Active |
| AH1-269 | Claytor 138 kV | Active |
| AH1-271 | Cashie 230 kV | Active |
| AH1-280 | Jetersville-Ponton 115 kV | Active |
| AH1-311 | Heartsease DP - Mayo Dunbar 115kV | Active |
| AH1-343 | Crystal Hill DP- Perth 115kV | Active |
| AH1-348 | Pound 34.5 kV | Active |
| AH1-396 | Gary 24.94 kV | Active |
| AH1-439 | Buckingham- Farmville 230kV | Active |
| AH1-461 | Buckhorn 138 kV | Active |
| AH1-528 | Rawlings - Unity 500 kV | Active |
| AH1-535 | Nagel - Cane River 230 kV | Active |
| AH1-546 | Bremo - Buckingham 230 kV | Active |
| AH1-617 | Harbert Metering 138 kV | Active |
| AH1-677 | Rogers Road 500 kV | Active |
| AH1-678 | Heritage 500 kV | Active |
| AH1-687 | Bear Garden 230kV | Active |
| AH1-721 | Laurel-Cooper 161 kV | Active |
| V4-068 | Murphy's 34.5kV | In Service |
| Y1-086 | Morgans Corner | In Service |
| Z1-036 | WinFall-Chowan 230kV | In Service |
| Z2-027 | Pasquotank 34.5kV | In Service |
| Z2-044 | Whitakers 34.5kV | In Service |
Affected System - PJM Identified Violations
As part of PJM's analysis, per Tariff Part VII.G.336 & Manual 14H, Section 13, PJM evaluated the potential impacts on tie line facilities between PJM and an affected system entity, which were identified per PJM planning analysis criteria. This upgrade may be required on the affected system portion of the tie line along with cost allocation of such upgrade if applicable, in coordination with the affected system. Depending on the affected system, this project may not be contingent on upgrade based on PJM planning analysis criteria, but may be contingent on this upgrade based on the Affected System Operator's planning criteria, provided in the Affected Systems Study Section, herein.
Affected System - Non-PJM Identified Violations
In accordance with PJM Tariff Part VII, Subpart D, section 310.A and as outlined in PJM Manual 14H, Sections 4.5 and 13, in Phase II of the Cycle, PJM provides the Affected System Operator any updates on the PJM projects that require an Affected Systems Study based on their response at DP1. New Service Requests that require an Affected Systems Study are required to enter into an Affected Systems Study Agreement with the Affected System Operator, as applicable, prior to the close of DP2 or they will be withdrawn from the Cycle.
If the Project Developer already entered into the necessary agreement and the results are available, PJM will supply them in the Phase II SIS report. See below for the status of any required Affected Systems Study. A status of “Pending” means that the study is not yet completed by the Affected System Operator. If your project requires an Affected Systems Study and your results are not provided for Phase II SIS, PJM anticipates providing them in the Phase III SIS per Tariff Part VII.D.312.
System Reinforcements
Based on the Phase II System Impact Study analysis results, this project is contingent on and may have cost responsibility for the following System Reinforcements:
| TO | RTEP ID | Title | Category | Allocated Cost ($USD) | Facilities Study |
|---|---|---|---|---|---|
| Dominion | b4000.357 | Build a new 765/500/230 kV substation called Yeat. Install (2) 765/500 kV transformers. Cut in 500 kV line Bristers-Ox and 500 kV line Meadowbrook-Vint Hill into Yeat. | Contingent | $0 | N/A |
| Dominion | b4000.352 | Cut in Line #568 Ladysmith - Possum Point into Thornburg (formerly Kraken), creating new Line #568 Thornburg (formerly Kraken) to Possum Point. | Contingent | $0 | N/A |
| Dominion | b4000.351 | Cut in Line #568 Ladysmith - Possum Point into Thornburg (formerly Kraken), creating Line #9517 Ladysmith to Thornburg (formerly Kraken). | Contingent | $0 | N/A |
| Dominion | b4000.350 | Update relay settings at Possum Point to change the destination of 500kV line #568 from Ladysmith to Thornburg (formerly Kraken). | Contingent | $0 | N/A |
| Dominion | b4000.349 | Update relay settings at Ladysmith to change the destination of 500kV line #568 from Possum Point to Thornburg (formerly Kraken). | Contingent | $0 | N/A |
| Dominion | b4000.344 | Build a 500kV line from North Anna substation (bypassing Ladysmith Substation) to a new substation called Thornburg (formerly Kraken). New conductor to have a minimum summer normal rating of 4357MVA. | Contingent | $0 | N/A |
| Dominion | b4000.345 | Build a 500kV line from a new substation called Thornburg (formerly Kraken) to a new substation called Yeat. New conductor to have a minimum summer normal rating of 4357MVA. | Contingent | $0 | N/A |
| Dominion | b4000.346 | Cut-in 500kV line from Thornburg (formerly Kraken) substation into Yeat substation | Contingent | $0 | N/A |
| Dominion | b4000.348 | Build a new 500/230kV substation called Thornburg (formerly Kraken). The 500kV, 5000A ring bus will be set up for a redundant breaker configuration. Install (2) 1400MVA 500/230 kV transformers. | Contingent | $0 | N/A |
| AEP | b4000.355 | Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 69.3 miles in AEP section). | Contingent | $0 | N/A |
| Dominion | b4000.356 | Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 86.7 miles in Dominion section). | Contingent | $0 | N/A |
| Dominion | b4053.13 | Construct a new 765/500 kV Vontay switching station at the crossing of 500 kV line No. 553 Cunningham-Elmont and 765 kV line Joshua Falls-Yeat. | Contingent | $0 | N/A |
| Dominion | b4053.14 | Loop 500 kV line No. 553 into the new Vontay substation, which will result in two 500 kV lines: Cunningham-Vontay and Vontay-Elmont. | Contingent | $0 | N/A |
| Dominion | b4053.15 | Loop 500 kV line No. 576 into the new Vontay substation, which will result in two 500 kV lines: from North Anna-Vontay and Vontay-Midlothian. | Contingent | $0 | N/A |
| Dominion | b4053.16 | Loop 765 kV Joshua Falls-Yeat into the new Vontay substation, which will result in two 765 kV lines: from Joshua Falls-Vontay and Vontay-Yeat. | Contingent | $0 | N/A |
| Dominion | b4053.28 | Replace 500 kV circuit breakers (54265 and 553T564) and all associated equipment to line No. 553 including switches and CT with 5000A equipment at Cunningham substation. | Contingent | $0 | N/A |
| Dominion | b4000.341 | Remove the 500 kV conductor previously planned to terminate into the Vint Hill 500 kV Substation and extend approximately 0.2 miles of conductor to fly-over the site. | Contingent | $0 | N/A |
| Dominion | b4000.342 | Remove the terminal equipment and substation work required for the termination of the Morrisville-Wishing Star 500 kV line into Vint Hill. | Contingent | $0 | N/A |
| AEP | b4000.251 | Replace the wave trap and upgrade the relay at Cloverdale 765kV substation | Contingent | $0 | N/A |
| AEP | b4000.252 | Replace the wave trap and upgrade the relay at Joshua Falls 765kV substation | Contingent | $0 | N/A |
| Dominion | b4053.3 | Construct a new bipolar +/- 525 kV HVDC link connecting Heritage and Mosby substations, where the link has a capability of transmitting 3,000 MW. | Contingent | $0 | N/A |
| Dominion | b4053.4 | Design and construct a new Voltage Source Converter (VSC) HVDC station at Heritage substation to support the new HVDC link. | Contingent | $0 | N/A |
| Dominion | b4053.5 | Design and construct a new Voltage Source Converter (VSC) HVDC station at Mosby substation to support the new HVDC link. | Contingent | $0 | N/A |
| Dominion | b4053.11 | Cut and loop line No. 5008 into Mosby substation, which will result in two 500 kV lines: line No. 5008 Morrisville-Mosby and line No. 9573 Mosby-Wishing Star. | Contingent | $0 | N/A |
| Dominion | b4053.12 | Install two 500 kV breakers and all associated terminal equipment in the available bay adjacent to existing breaker XT590 to achieve a redundant breaker arrangement. | Contingent | $0 | N/A |
| Dominion | b4030.1 | Chesterfield-Basin 230 kV rebuild: Wreck and rebuild approximately 12.5 miles of Chesterfield-Basin 230 kV line. | Contingent | $0 | N/A |
| Dominion | b4030.4 | Chesterfield 230 kV substation scope: Install a new 230 kV, 80 kA 4000A circuit breaker at Chesterfield 230 kV substation. | Contingent | $0 | N/A |
| Dominion | b4030.3 | Basin 230 kV substation scope: Replace all terminal equipment, line leads and bus at Basin 230 kV substation to be rated to 4000A. | Contingent | $0 | N/A |
| Dominion | b4030.9 | Charlottesville-Fork Union 230 kV rebuild: Wreck and rebuild ~24 miles of Charlottesville-Fork Union 230 kV line.New Reinforcement | Contingent | $0 | N/A |
| Dominion | b4030.11 | Replace all terminal equipment at Charlottesville 230 kV substation to support the new line conductor ratings of the Charlottesville-Fork Union 230 kV rebuild. | Contingent | $0 | N/A |
| Dominion | b4030.15 | Upgrade disconnect switches at Mt. Eagle tap 230 kV substation to 4000A. | Contingent | $0 | N/A |
| Dominion | b4030.12 | Replace all terminal equipment at Fork Union 230 kV substation to support the new line conductor ratings of the Charlottesville-Fork Union 230 kV rebuild. | Contingent | $0 | N/A |
| Dominion | b4030.10 | Fork Union-Bremo 230 kV rebuild: Wreck and Rebuild approximately 1.74 miles of Fork Union-Bremo 230 kV line. | Contingent | $0 | N/A |
| Dominion | b4030.14 | Replace all terminal equipment at Bremo 230 kV substation to support the new conductor ratings of the Fork Union-Bremo 230 kV rebuild. | Contingent | $0 | N/A |
| Dominion | b4030.13 | Replace all terminal equipment at Fork Union 230 kV substation to support the new conductor ratings of the Fork Union-Bremo 230 kV rebuild. | Contingent | $0 | N/A |
| Grand Total: | $0 | ||||
Shown below are the details of the cost allocated, contingent, eliminated, topology and potential aggregate contributor reinforcements for this project. Please refer to the System Reinforcement table above and the information below for more detail.
System Reinforcement: b4000.357
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.357
- Title
- Build a new 765/500/230 kV substation called Yeat. Install (2) 765/500 kV transformers. Cut in 500 kV line Bristers-Ox and 500 kV line Meadowbrook-Vint Hill into Yeat.
- Description
- Build a new 765/500/230 kV substation called Yeat. Install (2) 765/500 kV transformers. Cut in 500 kV line Bristers-Ox and 500 kV line Meadowbrook-Vint Hill into Yeat.
- Cost Information
- Time Estimate
- Jun 01 2029
ContingentTopology Changing Note 1: Although AG2-088 may not presently have cost responsibility for this upgrade, AG2-088 may need this upgrade in-service to be deliverable to the PJM system. If AG2-088 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 8LADYSMITH-8POSSUM 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8MDLTHAN-8NO ANNA 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8MORRSVL-8SPOTSYL 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8NO ANNA-8SPOTSYL 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P4-2: 56372_SRT-S | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P1-2: LN 563_SRT-S | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P4-2: 562T563_SRT-S | No new ratings for this Flowgate. | |
| 8LADYSMITH-8NO ANNA 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.352
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.352
- Title
- Cut in Line #568 Ladysmith - Possum Point into Thornburg (formerly Kraken), creating new Line #568 Thornburg (formerly Kraken) to Possum Point.
- Description
- Cut in Line #568 Ladysmith - Possum Point into Thornburg (formerly Kraken), creating new Line #568 Thornburg (formerly Kraken) to Possum Point.
- Cost Information
- Time Estimate
- Sep 16 2030
ContingentTopology Changing Note 1: Although AG2-088 may not presently have cost responsibility for this upgrade, AG2-088 may need this upgrade in-service to be deliverable to the PJM system. If AG2-088 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 8LADYSMITH-8POSSUM 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8MDLTHAN-8NO ANNA 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8MORRSVL-8SPOTSYL 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8NO ANNA-8SPOTSYL 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P4-2: 56372_SRT-S | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P1-2: LN 563_SRT-S | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P4-2: 562T563_SRT-S | No new ratings for this Flowgate. | |
| 8LADYSMITH-8NO ANNA 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.351
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.351
- Title
- Cut in Line #568 Ladysmith - Possum Point into Thornburg (formerly Kraken), creating Line #9517 Ladysmith to Thornburg (formerly Kraken).
- Description
- Cut in Line #568 Ladysmith - Possum Point into Thornburg (formerly Kraken), creating Line #9517 Ladysmith to Thornburg (formerly Kraken).
- Cost Information
- Time Estimate
- Sep 16 2030
ContingentTopology Changing Note 1: Although AG2-088 may not presently have cost responsibility for this upgrade, AG2-088 may need this upgrade in-service to be deliverable to the PJM system. If AG2-088 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 8LADYSMITH-8POSSUM 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8MDLTHAN-8NO ANNA 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8MORRSVL-8SPOTSYL 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8NO ANNA-8SPOTSYL 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P4-2: 56372_SRT-S | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P1-2: LN 563_SRT-S | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P4-2: 562T563_SRT-S | No new ratings for this Flowgate. | |
| 8LADYSMITH-8NO ANNA 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.350
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.350
- Title
- Update relay settings at Possum Point to change the destination of 500kV line #568 from Ladysmith to Thornburg (formerly Kraken).
- Description
- Update relay settings at Possum Point to change the destination of 500kV line #568 from Ladysmith to Thornburg (formerly Kraken).
- Cost Information
- Time Estimate
- Sep 16 2030
ContingentTopology Changing Note 1: Although AG2-088 may not presently have cost responsibility for this upgrade, AG2-088 may need this upgrade in-service to be deliverable to the PJM system. If AG2-088 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 8LADYSMITH-8POSSUM 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8MDLTHAN-8NO ANNA 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8MORRSVL-8SPOTSYL 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8NO ANNA-8SPOTSYL 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P4-2: 56372_SRT-S | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P1-2: LN 563_SRT-S | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P4-2: 562T563_SRT-S | No new ratings for this Flowgate. | |
| 8LADYSMITH-8NO ANNA 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.349
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.349
- Title
- Update relay settings at Ladysmith to change the destination of 500kV line #568 from Possum Point to Thornburg (formerly Kraken).
- Description
- Update relay settings at Ladysmith to change the destination of 500kV line #568 from Possum Point to Thornburg (formerly Kraken).
- Cost Information
- Time Estimate
- Sep 16 2030
ContingentTopology Changing Note 1: Although AG2-088 may not presently have cost responsibility for this upgrade, AG2-088 may need this upgrade in-service to be deliverable to the PJM system. If AG2-088 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 8LADYSMITH-8POSSUM 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8MDLTHAN-8NO ANNA 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8MORRSVL-8SPOTSYL 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8NO ANNA-8SPOTSYL 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P4-2: 56372_SRT-S | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P1-2: LN 563_SRT-S | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P4-2: 562T563_SRT-S | No new ratings for this Flowgate. | |
| 8LADYSMITH-8NO ANNA 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.344
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.344
- Title
- Build a 500kV line from North Anna substation (bypassing Ladysmith Substation) to a new substation called Thornburg (formerly Kraken). New conductor to have a minimum summer normal rating of 4357MVA.
- Description
- Build a 500kV line from North Anna substation (bypassing Ladysmith Substation) to a new substation called Thornburg (formerly Kraken). New conductor to have a minimum summer normal rating of 4357MVA.
- Cost Information
- Time Estimate
- Sep 16 2030
ContingentTopology Changing Note 1: Although AG2-088 may not presently have cost responsibility for this upgrade, AG2-088 may need this upgrade in-service to be deliverable to the PJM system. If AG2-088 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 8LADYSMITH-8POSSUM 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8MDLTHAN-8NO ANNA 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8MORRSVL-8SPOTSYL 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8NO ANNA-8SPOTSYL 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P4-2: 56372_SRT-S | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P1-2: LN 563_SRT-S | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P4-2: 562T563_SRT-S | No new ratings for this Flowgate. | |
| 8LADYSMITH-8NO ANNA 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.345
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.345
- Title
- Build a 500kV line from a new substation called Thornburg (formerly Kraken) to a new substation called Yeat. New conductor to have a minimum summer normal rating of 4357MVA.
- Description
- Build a 500kV line from a new substation called Thornburg (formerly Kraken) to a new substation called Yeat. New conductor to have a minimum summer normal rating of 4357MVA.
- Cost Information
- Time Estimate
- Sep 16 2030
ContingentTopology Changing Note 1: Although AG2-088 may not presently have cost responsibility for this upgrade, AG2-088 may need this upgrade in-service to be deliverable to the PJM system. If AG2-088 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 8LADYSMITH-8POSSUM 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8MDLTHAN-8NO ANNA 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8MORRSVL-8SPOTSYL 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8NO ANNA-8SPOTSYL 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P4-2: 56372_SRT-S | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P1-2: LN 563_SRT-S | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P4-2: 562T563_SRT-S | No new ratings for this Flowgate. | |
| 8LADYSMITH-8NO ANNA 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.346
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.346
- Title
- Cut-in 500kV line from Thornburg (formerly Kraken) substation into Yeat substation
- Description
- Cut-in 500kV line from Thornburg (formerly Kraken) substation into Yeat substation
- Cost Information
- Time Estimate
- Jun 01 2029
ContingentTopology Changing Note 1: Although AG2-088 may not presently have cost responsibility for this upgrade, AG2-088 may need this upgrade in-service to be deliverable to the PJM system. If AG2-088 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 8LADYSMITH-8POSSUM 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8MDLTHAN-8NO ANNA 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8MORRSVL-8SPOTSYL 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8NO ANNA-8SPOTSYL 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P4-2: 56372_SRT-S | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P1-2: LN 563_SRT-S | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P4-2: 562T563_SRT-S | No new ratings for this Flowgate. | |
| 8LADYSMITH-8NO ANNA 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.348
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.348
- Title
- Build a new 500/230kV substation called Thornburg (formerly Kraken). The 500kV, 5000A ring bus will be set up for a redundant breaker configuration. Install (2) 1400MVA 500/230 kV transformers.
- Description
- Build a new 500/230kV substation called Thornburg (formerly Kraken). The 500kV, 5000A ring bus will be set up for a redundant breaker configuration. Install (2) 1400MVA 500/230 kV transformers. A new redundant breaker ring will be added at Thornburg (formerly Kraken) to accommodate the new 500kV line from North Anna to Thornburg (formerly Kraken).
- Cost Information
- Time Estimate
- Jun 01 2029
ContingentTopology Changing Note 1: Although AG2-088 may not presently have cost responsibility for this upgrade, AG2-088 may need this upgrade in-service to be deliverable to the PJM system. If AG2-088 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 8LADYSMITH-8POSSUM 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8MDLTHAN-8NO ANNA 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8MORRSVL-8SPOTSYL 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8NO ANNA-8SPOTSYL 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P4-2: 56372_SRT-S | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P1-2: LN 563_SRT-S | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P4-2: 562T563_SRT-S | No new ratings for this Flowgate. | |
| 8LADYSMITH-8NO ANNA 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.355
- Type
- Load Flow
- TO
- AEP
- RTEP ID / TO ID
- b4000.355
- Title
- Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 69.3 miles in AEP section).
- Description
- Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 69.3 miles in AEP section).
- Cost Information
- Time Estimate
- Jun 01 2029
ContingentTopology Changing Note 1: Although AG2-088 may not presently have cost responsibility for this upgrade, AG2-088 may need this upgrade in-service to be deliverable to the PJM system. If AG2-088 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 8MDLTHAN-8NO ANNA 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8MORRSVL-8SPOTSYL 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8NO ANNA-8SPOTSYL 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P4-2: 56372_SRT-S | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P1-2: LN 563_SRT-S | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P4-2: 562T563_SRT-S | No new ratings for this Flowgate. |
System Reinforcement: b4000.356
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.356
- Title
- Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 86.7 miles in Dominion section).
- Description
- Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 86.7 miles in Dominion section).
- Cost Information
- Time Estimate
- Jun 01 2029
ContingentTopology Changing Note 1: Although AG2-088 may not presently have cost responsibility for this upgrade, AG2-088 may need this upgrade in-service to be deliverable to the PJM system. If AG2-088 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 8MDLTHAN-8NO ANNA 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8MORRSVL-8SPOTSYL 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8NO ANNA-8SPOTSYL 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P4-2: 56372_SRT-S | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P1-2: LN 563_SRT-S | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P4-2: 562T563_SRT-S | No new ratings for this Flowgate. |
System Reinforcement: b4053.13
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4053.13
- Title
- Construct a new 765/500 kV Vontay switching station at the crossing of 500 kV line No. 553 Cunningham-Elmont and 765 kV line Joshua Falls-Yeat.
- Description
- Construct a new 765/500 kV Vontay switching station at the crossing of 500 kV line No. 553 Cunningham-Elmont and 765 kV line Joshua Falls-Yeat. Develop two 765 kV line terminal positions and three 500 kV line terminal positions. Install one 765/500 kV transformer, with provisions for a future second transformer.
- Cost Information
- Time Estimate
- Jun 01 2032
ContingentTopology Changing Note 1: Although AG2-088 may not presently have cost responsibility for this upgrade, AG2-088 may need this upgrade in-service to be deliverable to the PJM system. If AG2-088 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 8MDLTHAN-8NO ANNA 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P4-2: 56372_SRT-S | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P1-2: LN 563_SRT-S | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P4-2: 562T563_SRT-S | No new ratings for this Flowgate. |
System Reinforcement: b4053.14
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4053.14
- Title
- Loop 500 kV line No. 553 into the new Vontay substation, which will result in two 500 kV lines: Cunningham-Vontay and Vontay-Elmont.
- Description
- Loop 500 kV line No. 553 into the new Vontay substation, which will result in two 500 kV lines: Cunningham-Vontay and Vontay-Elmont.
- Cost Information
- Time Estimate
- Jun 01 2032
ContingentTopology Changing Note 1: Although AG2-088 may not presently have cost responsibility for this upgrade, AG2-088 may need this upgrade in-service to be deliverable to the PJM system. If AG2-088 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 8MDLTHAN-8NO ANNA 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P4-2: 56372_SRT-S | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P1-2: LN 563_SRT-S | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P4-2: 562T563_SRT-S | No new ratings for this Flowgate. |
System Reinforcement: b4053.15
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4053.15
- Title
- Loop 500 kV line No. 576 into the new Vontay substation, which will result in two 500 kV lines: from North Anna-Vontay and Vontay-Midlothian.
- Description
- Loop 500 kV line No. 576 into the new Vontay substation, which will result in two 500 kV lines: from North Anna-Vontay and Vontay-Midlothian.
- Cost Information
- Time Estimate
- Jun 01 2032
ContingentTopology Changing Note 1: Although AG2-088 may not presently have cost responsibility for this upgrade, AG2-088 may need this upgrade in-service to be deliverable to the PJM system. If AG2-088 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 8MDLTHAN-8NO ANNA 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P4-2: 56372_SRT-S | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P1-2: LN 563_SRT-S | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P4-2: 562T563_SRT-S | No new ratings for this Flowgate. |
System Reinforcement: b4053.16
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4053.16
- Title
- Loop 765 kV Joshua Falls-Yeat into the new Vontay substation, which will result in two 765 kV lines: from Joshua Falls-Vontay and Vontay-Yeat.
- Description
- Loop 765 kV Joshua Falls-Yeat into the new Vontay substation, which will result in two 765 kV lines: from Joshua Falls-Vontay and Vontay-Yeat.
- Cost Information
- Time Estimate
- Jun 01 2032
ContingentTopology Changing Note 1: Although AG2-088 may not presently have cost responsibility for this upgrade, AG2-088 may need this upgrade in-service to be deliverable to the PJM system. If AG2-088 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 8MDLTHAN-8NO ANNA 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P4-2: 56372_SRT-S | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P1-2: LN 563_SRT-S | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P4-2: 562T563_SRT-S | No new ratings for this Flowgate. |
System Reinforcement: b4053.28
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4053.28
- Title
- Replace 500 kV circuit breakers (54265 and 553T564) and all associated equipment to line No. 553 including switches and CT with 5000A equipment at Cunningham substation.
- Description
- Replace 500 kV circuit breakers (54265 and 553T564) and all associated equipment to line No. 553 including switches and CT with 5000A equipment at Cunningham substation.
- Cost Information
- Time Estimate
- Jun 01 2032
ContingentTopology Changing Note 1: Although AG2-088 may not presently have cost responsibility for this upgrade, AG2-088 may need this upgrade in-service to be deliverable to the PJM system. If AG2-088 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 8MDLTHAN-8NO ANNA 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P4-2: 56372_SRT-S | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P1-2: LN 563_SRT-S | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P4-2: 562T563_SRT-S | No new ratings for this Flowgate. |
System Reinforcement: b4000.341
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.341
- Title
- Remove the 500 kV conductor previously planned to terminate into the Vint Hill 500 kV Substation and extend approximately 0.2 miles of conductor to fly-over the site.
- Description
- Remove the 500 kV conductor previously planned to terminate into the Vint Hill 500 kV substation and extend approximately 0.2 miles of conductor to fly-over the site.
- Cost Information
- Time Estimate
- Jul 13 2029
ContingentTopology Changing Note 1: Although AG2-088 may not presently have cost responsibility for this upgrade, AG2-088 may need this upgrade in-service to be deliverable to the PJM system. If AG2-088 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 8LADYSMITH-8POSSUM 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8MDLTHAN-8NO ANNA 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8MORRSVL-8SPOTSYL 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8NO ANNA-8SPOTSYL 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P4-2: 56372_SRT-S | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P1-2: LN 563_SRT-S | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P4-2: 562T563_SRT-S | No new ratings for this Flowgate. | |
| 8LADYSMITH-8NO ANNA 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.342
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.342
- Title
- Remove the terminal equipment and substation work required for the termination of the Morrisville-Wishing Star 500 kV line into Vint Hill.
- Description
- Remove the terminal equipment and substation work required for the termination of the Morrisville-Wishing Star 500 kV line into Vint Hill.
- Cost Information
- Time Estimate
- Jul 13 2029
ContingentTopology Changing Note 1: Although AG2-088 may not presently have cost responsibility for this upgrade, AG2-088 may need this upgrade in-service to be deliverable to the PJM system. If AG2-088 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 8LADYSMITH-8POSSUM 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8MDLTHAN-8NO ANNA 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8MORRSVL-8SPOTSYL 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8NO ANNA-8SPOTSYL 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P4-2: 56372_SRT-S | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P1-2: LN 563_SRT-S | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P4-2: 562T563_SRT-S | No new ratings for this Flowgate. | |
| 8LADYSMITH-8NO ANNA 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.251
- Type
- Load Flow
- TO
- AEP
- RTEP ID / TO ID
- b4000.251
- Title
- Replace the wave trap and upgrade the relay at Cloverdale 765kV substation
- Description
- Replace the wave trap and upgrade the relay at Cloverdale 765kV substation
- Cost Information
- Time Estimate
- Jun 01 2029
Contingent Note: Although AG2-088 may not presently have cost responsibility for this upgrade, AG2-088 may need this upgrade in-service to be deliverable to the PJM system. If AG2-088 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.
| Facility | Contingency | |||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 05JOSHUA-05CLOVRD_RJO 765.0 kV Ckt 1 line | (Any) |
|
System Reinforcement: b4000.252
- Type
- Load Flow
- TO
- AEP
- RTEP ID / TO ID
- b4000.252
- Title
- Replace the wave trap and upgrade the relay at Joshua Falls 765kV substation
- Description
- Replace the wave trap and upgrade the relay at Joshua Falls 765kV substation
- Cost Information
- Time Estimate
- Jun 01 2029
Contingent Note: Although AG2-088 may not presently have cost responsibility for this upgrade, AG2-088 may need this upgrade in-service to be deliverable to the PJM system. If AG2-088 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.
| Facility | Contingency | |||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 05JOSHUA-05CLOVRD_RJO 765.0 kV Ckt 1 line | (Any) |
|
System Reinforcement: b4053.3
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4053.3
- Title
- Construct a new bipolar +/- 525 kV HVDC link connecting Heritage and Mosby substations, where the link has a capability of transmitting 3,000 MW.
- Description
- Construct a new bipolar +/- 525 kV HVDC link connecting Heritage and Mosby substations, where the link has a capability of transmitting 3,000 MW. The HVDC link, approximately 185 miles in length, will be fully routed underground between the two new proposed converter stations, one at Heritage and one at Mosby.
- Cost Information
- Time Estimate
- Jun 01 2032
ContingentTopology Changing Note 1: Although AG2-088 may not presently have cost responsibility for this upgrade, AG2-088 may need this upgrade in-service to be deliverable to the PJM system. If AG2-088 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 8LADYSMITH-8POSSUM 500.0 kV Ckt 1 line | DVP_P1-2: LN 594_SRT-S | No new ratings for this Flowgate. | |
| 8LADYSMITH-8POSSUM 500.0 kV Ckt 1 line | DVP_P1-2: LN 573_SRT-S | No new ratings for this Flowgate. | |
| 8LADYSMITH-8POSSUM 500.0 kV Ckt 1 line | DVP_P4-2: 545T594_SRT-S | No new ratings for this Flowgate. | |
| 8MDLTHAN-8NO ANNA 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8MORRSVL-8SPOTSYL 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8NO ANNA-8SPOTSYL 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P4-2: 56372_SRT-S | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P4-2: WT576_SRT-S | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P1-2: LN 576_SRT-S | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P1-2: LN 563_SRT-S | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P4-2: 57602_SRT-S | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P4-2: 562T563_SRT-S | No new ratings for this Flowgate. | |
| 8LADYSMITH-8NO ANNA 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4053.4
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4053.4
- Title
- Design and construct a new Voltage Source Converter (VSC) HVDC station at Heritage substation to support the new HVDC link.
- Description
- Design and construct a new Voltage Source Converter (VSC) HVDC station at Heritage substation to support the new HVDC link.
- Cost Information
- Time Estimate
- Jun 01 2032
ContingentTopology Changing Note 1: Although AG2-088 may not presently have cost responsibility for this upgrade, AG2-088 may need this upgrade in-service to be deliverable to the PJM system. If AG2-088 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 8LADYSMITH-8POSSUM 500.0 kV Ckt 1 line | DVP_P1-2: LN 594_SRT-S | No new ratings for this Flowgate. | |
| 8LADYSMITH-8POSSUM 500.0 kV Ckt 1 line | DVP_P1-2: LN 573_SRT-S | No new ratings for this Flowgate. | |
| 8LADYSMITH-8POSSUM 500.0 kV Ckt 1 line | DVP_P4-2: 545T594_SRT-S | No new ratings for this Flowgate. | |
| 8MDLTHAN-8NO ANNA 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8MORRSVL-8SPOTSYL 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8NO ANNA-8SPOTSYL 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P4-2: 56372_SRT-S | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P4-2: WT576_SRT-S | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P1-2: LN 576_SRT-S | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P1-2: LN 563_SRT-S | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P4-2: 57602_SRT-S | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P4-2: 562T563_SRT-S | No new ratings for this Flowgate. | |
| 8LADYSMITH-8NO ANNA 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4053.5
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4053.5
- Title
- Design and construct a new Voltage Source Converter (VSC) HVDC station at Mosby substation to support the new HVDC link.
- Description
- Design and construct a new Voltage Source Converter (VSC) HVDC station at Mosby substation to support the new HVDC link.
- Cost Information
- Time Estimate
- Jun 01 2032
ContingentTopology Changing Note 1: Although AG2-088 may not presently have cost responsibility for this upgrade, AG2-088 may need this upgrade in-service to be deliverable to the PJM system. If AG2-088 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 8LADYSMITH-8POSSUM 500.0 kV Ckt 1 line | DVP_P1-2: LN 594_SRT-S | No new ratings for this Flowgate. | |
| 8LADYSMITH-8POSSUM 500.0 kV Ckt 1 line | DVP_P1-2: LN 573_SRT-S | No new ratings for this Flowgate. | |
| 8LADYSMITH-8POSSUM 500.0 kV Ckt 1 line | DVP_P4-2: 545T594_SRT-S | No new ratings for this Flowgate. | |
| 8MDLTHAN-8NO ANNA 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8MORRSVL-8SPOTSYL 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8NO ANNA-8SPOTSYL 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P4-2: 56372_SRT-S | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P4-2: WT576_SRT-S | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P1-2: LN 576_SRT-S | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P1-2: LN 563_SRT-S | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P4-2: 57602_SRT-S | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P4-2: 562T563_SRT-S | No new ratings for this Flowgate. | |
| 8LADYSMITH-8NO ANNA 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4053.11
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4053.11
- Title
- Cut and loop line No. 5008 into Mosby substation, which will result in two 500 kV lines: line No. 5008 Morrisville-Mosby and line No. 9573 Mosby-Wishing Star.
- Description
- Cut and loop line No. 5008 into Mosby substation, which will result in two 500 kV lines: line No. 5008 Morrisville-Mosby and line No. 9573 Mosby-Wishing Star.
- Cost Information
- Time Estimate
- Jun 01 2030
ContingentTopology Changing Note 1: Although AG2-088 may not presently have cost responsibility for this upgrade, AG2-088 may need this upgrade in-service to be deliverable to the PJM system. If AG2-088 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 8LADYSMITH-8POSSUM 500.0 kV Ckt 1 line | DVP_P1-2: LN 594_SRT-S | No new ratings for this Flowgate. | |
| 8LADYSMITH-8POSSUM 500.0 kV Ckt 1 line | DVP_P1-2: LN 573_SRT-S | No new ratings for this Flowgate. | |
| 8LADYSMITH-8POSSUM 500.0 kV Ckt 1 line | DVP_P4-2: 545T594_SRT-S | No new ratings for this Flowgate. | |
| 8MDLTHAN-8NO ANNA 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8MORRSVL-8SPOTSYL 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8NO ANNA-8SPOTSYL 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P4-2: 56372_SRT-S | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P4-2: WT576_SRT-S | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P1-2: LN 576_SRT-S | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P1-2: LN 563_SRT-S | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P4-2: 57602_SRT-S | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P4-2: 562T563_SRT-S | No new ratings for this Flowgate. | |
| 8LADYSMITH-8NO ANNA 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4053.12
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4053.12
- Title
- Install two 500 kV breakers and all associated terminal equipment in the available bay adjacent to existing breaker XT590 to achieve a redundant breaker arrangement.
- Description
- Install two 500 kV breakers and all associated terminal equipment in the available bay adjacent to existing breaker XT590 to achieve a redundant breaker arrangement. Upgrade existing terminal equipment to 500 kV, 5000A 63 kAIC standards including breaker (XT590), disconnect switches (59078, X74), leads and bus work.
- Cost Information
- Time Estimate
- Jun 01 2030
ContingentTopology Changing Note 1: Although AG2-088 may not presently have cost responsibility for this upgrade, AG2-088 may need this upgrade in-service to be deliverable to the PJM system. If AG2-088 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 8LADYSMITH-8POSSUM 500.0 kV Ckt 1 line | DVP_P1-2: LN 594_SRT-S | No new ratings for this Flowgate. | |
| 8LADYSMITH-8POSSUM 500.0 kV Ckt 1 line | DVP_P1-2: LN 573_SRT-S | No new ratings for this Flowgate. | |
| 8LADYSMITH-8POSSUM 500.0 kV Ckt 1 line | DVP_P4-2: 545T594_SRT-S | No new ratings for this Flowgate. | |
| 8MDLTHAN-8NO ANNA 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8MORRSVL-8SPOTSYL 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8NO ANNA-8SPOTSYL 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P4-2: 56372_SRT-S | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P4-2: WT576_SRT-S | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P1-2: LN 576_SRT-S | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P1-2: LN 563_SRT-S | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P4-2: 57602_SRT-S | No new ratings for this Flowgate. | |
| 6MDLTHAN-8MDLTHAN 230.0/500.0 kV Ckt 1 transformer | DVP_P4-2: 562T563_SRT-S | No new ratings for this Flowgate. | |
| 8LADYSMITH-8NO ANNA 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4030.1
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4030.1
- Title
- Chesterfield-Basin 230 kV rebuild: Wreck and rebuild approximately 12.5 miles of Chesterfield-Basin 230 kV line.
- Description
- Chesterfield-Basin 230 kV rebuild: Wreck and rebuild approximately 12.5 miles of Chesterfield-Basin 230 kV line.
- Cost Information
- Time Estimate
- Jun 01 2030
Contingent Note: Although AG2-088 may not presently have cost responsibility for this upgrade, AG2-088 may need this upgrade in-service to be deliverable to the PJM system. If AG2-088 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.
| Facility | Contingency | |||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 6BASIN-6CHESTF B 230.0 kV Ckt 1 line | (Any) |
|
System Reinforcement: b4030.4
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4030.4
- Title
- Chesterfield 230 kV substation scope: Install a new 230 kV, 80 kA 4000A circuit breaker at Chesterfield 230 kV substation.
- Description
- Chesterfield 230 kV substation scope: Install a new 230 kV, 80 kA 4000A circuit breaker at Chesterfield 230 kV substation.
- Cost Information
- Time Estimate
- Jun 01 2030
Contingent Note: Although AG2-088 may not presently have cost responsibility for this upgrade, AG2-088 may need this upgrade in-service to be deliverable to the PJM system. If AG2-088 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.
| Facility | Contingency | |||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 6BASIN-6CHESTF B 230.0 kV Ckt 1 line | (Any) |
|
System Reinforcement: b4030.3
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4030.3
- Title
- Basin 230 kV substation scope: Replace all terminal equipment, line leads and bus at Basin 230 kV substation to be rated to 4000A.
- Description
- Basin 230 kV substation scope: Replace all terminal equipment, line leads and bus at Basin 230 kV substation to be rated to 4000A.
- Cost Information
- Time Estimate
- Jun 01 2030
Contingent Note: Although AG2-088 may not presently have cost responsibility for this upgrade, AG2-088 may need this upgrade in-service to be deliverable to the PJM system. If AG2-088 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.
| Facility | Contingency | |||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 6BASIN-6CHESTF B 230.0 kV Ckt 1 line | (Any) |
|
System Reinforcement: b4030.9
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4030.9
- Title
- Charlottesville-Fork Union 230 kV rebuild: Wreck and rebuild ~24 miles of Charlottesville-Fork Union 230 kV line.New Reinforcement
- Description
- Charlottesville-Fork Union 230 kV rebuild: Wreck and rebuild ~24 miles of Charlottesville-Fork Union 230 kV line.
- Cost Information
- Time Estimate
- Jun 01 2030
Contingent Note: Although AG2-088 may not presently have cost responsibility for this upgrade, AG2-088 may need this upgrade in-service to be deliverable to the PJM system. If AG2-088 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.
| Facility | Contingency | |||||||||||||||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 6CHARLVL-6MTEAGLE 230.0 kV Ckt 1 line | (Any) |
| ||||||||||||||||||||||||||||||||||||||||
| 6GRAPEVINE-6FORK UNION 230.0 kV Ckt 1 line | (Any) |
| ||||||||||||||||||||||||||||||||||||||||
| 6GRAPEVINE-6MTEAGLE 230.0 kV Ckt 1 line | (Any) |
|
System Reinforcement: b4030.11
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4030.11
- Title
- Replace all terminal equipment at Charlottesville 230 kV substation to support the new line conductor ratings of the Charlottesville-Fork Union 230 kV rebuild.
- Description
- Charlottesville 230 kV substation scope: Replace all terminal equipment at Charlottesville 230 kV substation to support the new line conductor ratings of the Charlottesville-Fork Union 230 kV rebuild.
- Cost Information
- Time Estimate
- Jun 01 2030
Contingent Note: Although AG2-088 may not presently have cost responsibility for this upgrade, AG2-088 may need this upgrade in-service to be deliverable to the PJM system. If AG2-088 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.
| Facility | Contingency | |||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 6CHARLVL-6MTEAGLE 230.0 kV Ckt 1 line | (Any) |
|
System Reinforcement: b4030.15
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4030.15
- Title
- Upgrade disconnect switches at Mt. Eagle tap 230 kV substation to 4000A.
- Description
- Mt. Eagle tap 230 kV substation scope: Upgrade disconnect switches at Mt. Eagle tap 230 kV substation to 4000A.
- Cost Information
- Time Estimate
- Jun 01 2030
Contingent Note: Although AG2-088 may not presently have cost responsibility for this upgrade, AG2-088 may need this upgrade in-service to be deliverable to the PJM system. If AG2-088 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.
| Facility | Contingency | |||||||||||||||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 6CHARLVL-6MTEAGLE 230.0 kV Ckt 1 line | (Any) |
| ||||||||||||||||||||||||||||||||||||||||
| 6GRAPEVINE-6MTEAGLE 230.0 kV Ckt 1 line | (Any) |
|
System Reinforcement: b4030.12
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4030.12
- Title
- Replace all terminal equipment at Fork Union 230 kV substation to support the new line conductor ratings of the Charlottesville-Fork Union 230 kV rebuild.
- Description
- Fork Union 230 kV substation scope: Replace all terminal equipment at Fork Union 230 kV substation to support the new line conductor ratings of the Charlottesville-Fork Union 230 kV rebuild.
- Cost Information
- Time Estimate
- Jun 01 2030
Contingent Note: Although AG2-088 may not presently have cost responsibility for this upgrade, AG2-088 may need this upgrade in-service to be deliverable to the PJM system. If AG2-088 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.
| Facility | Contingency | |||||||||||||||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 6GRAPEVINE-6FORK UNION 230.0 kV Ckt 1 line | (Any) |
|
System Reinforcement: b4030.10
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4030.10
- Title
- Fork Union-Bremo 230 kV rebuild: Wreck and Rebuild approximately 1.74 miles of Fork Union-Bremo 230 kV line.
- Description
- Fork Union-Bremo 230 kV rebuild: Wreck and Rebuild approximately 1.74 miles of Fork Union-Bremo 230 kV line.
- Cost Information
- Time Estimate
- Jun 01 2030
Contingent Note: Although AG2-088 may not presently have cost responsibility for this upgrade, AG2-088 may need this upgrade in-service to be deliverable to the PJM system. If AG2-088 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.
| Facility | Contingency | |||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 6FORK UNION-6BREMODIST 230.0 kV Ckt 1 line | (Any) |
| ||||||||||||||||||||||
| 6BREMODIST-6BREMO 230.0 kV Ckt 1 line | (Any) |
|
System Reinforcement: b4030.14
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4030.14
- Title
- Replace all terminal equipment at Bremo 230 kV substation to support the new conductor ratings of the Fork Union-Bremo 230 kV rebuild.
- Description
- Bremo 230 kV substation scope: Replace all terminal equipment at Bremo 230 kV substation to support the new conductor ratings of the Fork Union-Bremo 230 kV rebuild.
- Cost Information
- Time Estimate
- Jun 01 2030
Contingent Note: Although AG2-088 may not presently have cost responsibility for this upgrade, AG2-088 may need this upgrade in-service to be deliverable to the PJM system. If AG2-088 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.
| Facility | Contingency | |||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 6FORK UNION-6BREMODIST 230.0 kV Ckt 1 line | (Any) |
| ||||||||||||||||||||||
| 6BREMODIST-6BREMO 230.0 kV Ckt 1 line | (Any) |
|
System Reinforcement: b4030.13
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4030.13
- Title
- Replace all terminal equipment at Fork Union 230 kV substation to support the new conductor ratings of the Fork Union-Bremo 230 kV rebuild.
- Description
- Fork Union 230 kV substation scope: Replace all terminal equipment at Fork Union 230 kV substation to support the new conductor ratings of the Fork Union-Bremo 230 kV rebuild.
- Cost Information
- Time Estimate
- Jun 01 2030
Contingent Note: Although AG2-088 may not presently have cost responsibility for this upgrade, AG2-088 may need this upgrade in-service to be deliverable to the PJM system. If AG2-088 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.
| Facility | Contingency | |||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 6FORK UNION-6BREMODIST 230.0 kV Ckt 1 line | (Any) |
| ||||||||||||||||||||||
| 6BREMODIST-6BREMO 230.0 kV Ckt 1 line | (Any) |
|