AG2-109 Phase II System Impact Study Report

v1.00 released 2026-06-03 17:59

Fitchville-New London 69 kV

28.1 MW Capacity / 40.0 MW Energy

Introduction

This Phase II System Impact Study (SIS) Report has been prepared in accordance with the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 310 for New Service Requests (projects) in Transition Cycle 2 (TC2). The Project Developer/Eligible Customer (developer) is Rosemary Solar, LLC, and the Transmission Provider (TP) is PJM Interconnection, LLC (PJM). The interconnected Transmission Owner (TO) is American Transmission Systems, Incorporated.

Preface

The Phase II System Impact Study is conducted on an aggregate basis within a New Services Request’s Cycle, and results are provided in both (i) a single Cycle summary format and (ii) an individual project-level basis. The Phase II System Impact Study Results (for both the summary and individual reports) will be publicly available on PJM’s website. Project Developers must obtain the results from the website.

In accordance with PJM Manual 14H, section 4.5, PJM takes the following actions during the Phase II System Impact Study:

  1. PJM will retool load flow results from the Phase I System Impact Study (summer peak, winter peak and light load) based on decisions made by Project Developers or Eligible Customers during Decision Point I.
  2. PJM will conduct any required voltage analyses.
  3. PJM will perform short circuit and stability analyses as required.
  4. PJM will coordinate with the Affected System to confirm which projects in the PJM Cycle will require Affected System studies. If the Affected System Operator indicates that an Affected System study is required, PJM will:
    1. Notify the Project Developer or Eligible Customer of the need for an Affected System study and the requirement to execute an Affected System study agreement with the impacted Affected System Operator, and;
    2. Include the results of the Affected System Operator’s Affected System Study in the Phase II System Impact Study results, if applicable and available.
  5. The Phase II System Impact Study Results will be publicly available on PJM’s website. Project Developers and Eligible Customers must obtain the results from the website.

The Transmission Owner takes the following actions during the Phase II System Impact Study:

  1. Verify Interconnection Facilities and Network Upgrades required to accommodate the New Service Request.
  2. Perform a Facilities Study. The Facilities Study in Phase II System Impact Study phase will be for the physical Interconnection Facilities. The Facilities Study requirements are outlined in Attachment C of this manual. The study will be conducted pursuant to Tariff, Part VII, Subpart D, section 307(A)(7) and Tariff, Part VIII, Subpart C, section 404(A)(7).

Decision Point II Requirements

At the close of Phase II System Impact Study, PJM will initiate Decision Point II (DP2). During DP2, the Project Developer will have 30 days to decide whether to proceed with their project. If the Project Developer elects to proceed, they should provide the elements defined in the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 311.A. Additional information on these elements is available in PJM Manual 14H sections 4.6, 6, and 7.

Allowable project modifications at Decision Point II are defined in PJM Open Access Transmission Tariff, Part VII, Subpart D, section 311.B. Additional information regarding allowable project modifications can be found in PJM Manual 14H, section 9.8.

Adverse Test Eligibility

This New Service Request does not meet the Adverse Study Impact Criteria and has the option to either move forward in the Cycle process or withdraw at DP2 with Readiness Deposit #1 forfeited. See adverse study impact calculation below.

This section details whether a Project Developer or Eligible Customer qualifies for the Adverse Study Impact clause outlined in the PJM OATT, Part VII, Subpart D, section 311.B and Manual 14H, section 6.2.2. In order to qualify for an Adverse Study Impact at Decision Point II, the Network Upgrade cost from Phase I to Phase II must:

  1. Increase overall by 25% or more
  2. Increases by more than $10,000 per MW (Includes Costs identified in Affected System studies)

If a New Service Request meets the criteria above and chooses to withdraw the request, PJM will refund the cumulative Readiness Deposit amounts paid at the Application Phase and at Decision Point I (RD1 and RD2, respectively).

The below calculations show the computation of this New Service Request's Adverse Study Impact

DP2 Adverse Eligibility = DP2 Adverse Cost Alloc DP1 Adverse Cost Alloc > 1.25 AND ( DP2 Adverse Cost Alloc - DP1 Adverse Cost Alloc ) Project Size > $10,000 per MW
DP2 Adverse Eligibility = $14,562,230 $12,413,263 = 1.17 AND ( $14,562,230 - $12,413,263 ) 40.0 = $53,724 per MW

General

The Project Developer has proposed a Solar generating facility located in the American Transmission Systems, Incorporated zone — Huron County, Ohio. The installed facilities will have a total capability of 40.0 MW with 28.1 MW of this output being recognized by PJM as Capacity.

Project Information
New Service Request Number:
AG2-109
Project Name:
Fitchville-New London 69 kV
Project Developer Name:
Rosemary Solar, LLC
State:
Ohio
County:
Huron
Transmission Owner:
American Transmission Systems, Incorporated
MFO:
40.0
MWE:
40.0
MWC:
28.1
Fuel Type:
Solar
Basecase Study Year:
2028

Physical Interconnection Facility Study

Report Available

The transmission owner has completed the Physical Interconnection Facilities Study. This report is available for download.

Point of Interconnection

AG2-109 will interconnect on the American Transmission Systems, Incorporated transmission system by tapping the Hanville to Wellington 69 kV line between Fitchville and New London. 

Cost Summary

The table below shows a summary of the total cost estimates for this New Service Request project. In Phase II SIS, the interconnected Transmission Owner has performed a facilities study for both the Transmission Owner Interconnection Facilities (TOIF) and Physical Interconnection Network Upgrades. The System Reliability Network Upgrade shown in the table are planning level cost estimates which are subject to change as a result of a facility study performed by the TO during Phase III System Impact Study.

Based on the Phase II SIS results, the AG2-109 project has the following allocation of costs for interconnection. The cost contribution towards Readiness Deposit #3 are also shown below.

Cost Summary
DescriptionCost Allocated to AG2-109Cost Subject to Readiness*Cost Subject to Adverse
Transmission Owner Interconnection Facilities (TOIF)$1,153,439$0$0
Other Scope$427,497$0$0
Option To Build Oversight$0$0$0
Physical Interconnection Network Upgrades
Stand Alone Network Upgrades$11,545,887$11,545,887$11,545,887
Network Upgrades$2,506,448$2,506,448$2,506,448
System Reliability Network Upgrades
Steady State Thermal & Voltage$0$0$0
Transient Stability$0$0$0
Short Circuit$0$0$0
Transmission Owner Analysis
SubRegional$509,895$509,895$509,895
Distribution$0$0$0
Affected System Reinforcements
AFS - PJM Violations$0$0$0
AFS - Non-PJM Violations$0$0$0
Total$16,143,166$14,562,230$14,562,230

* Contributes to calculation for Readiness Deposit #3 (RD3). See Readiness Deposit section of report for additional detail.

Definitions

Transmission Owner Interconnection Facilities: Facilities that are owned, controlled, operated and maintained by the Transmission Owner on the Transmission Owner’s side of the Point of Change of Ownership to the Point of Interconnection, including any modifications, additions or upgrades made to such facilities and equipment, that are necessary to physically and electrically interconnect the Generating Facility with the Transmission System or interconnected distribution facilities.

Stand Alone Network Upgrades: Network Upgrades, which are not part of an Affected System, which a Project Developer may construct without affecting day-to-day operations (e.g. taking a transmission outage) of the Transmission System during their construction.

Network Upgrades: Modifications or additions to transmission-related facilities that are integrated with and support the Transmission Provider’s overall Transmission System for the general benefit of all users of such Transmission System. Network Upgrades have no impact or potential impact on the Transmission System until the final tie-in is complete.

Notes

Note 1: PJM Open Access Transmission Tariff (OATT), Part VII, Subpart D, section 307.5 outlines cost allocation rules. The rules are further clarified in PJM Manual 14H, section 4.2.6. PJM shall identify the New Service Requests in the Cycle contributing to the need for the required Network Upgrades within the Cycle. All New Service Requests that contribute to the need for a Network Upgrade will receive cost allocation for that upgrade pursuant to each New Service Request’s contribution to the reliability violation identified on the transmission system in accordance with PJM Manuals.

Note 2: There will be no inter-Cycle cost allocation for Interconnection Facilities or Network Upgrades identified in the System Impact Study costs identified in a Cycle; all such costs shall be allocated to New Service Requests in that Cycle.

Note 3: For Project Developers with System Reinforcements listed: If this project presents cost allocation to a System Reinforcement indicates $0, then please be aware that as changes to the interconnection process occur, such as other projects withdrawing, reducing in size, etc, the cost responsibilities can change and a cost allocation may be assigned to this project. In addition, although this project presents cost allocation to a System Reinforcement is presently $0, this project may need this system reinforcement completed to be deliverable to the PJM system. If this project desires to come into service prior to completion of the system reinforcement, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the system reinforcement is complete.

Note 4: Please see the ‘Affected Systems Studies’ section of this Phase II SIS report for details on your project’s need for an Affected Systems Study. If your project requires an Affected Systems Study, the Affected Systems impacts may not be available from the Affected System Operator at the time of the PJM Phase II SIS. Therefore, the cost in this section would not reflect any required upgrades by the Affected System until the study is completed. If your project requires an Affected Systems Study and your results are not provided for Phase II SIS, PJM anticipates providing them in the Phase III SIS per Tariff Part VII.D.312.

Readiness Deposit

Per Tariff Part VII, Subpart D, section 311 (Decision Point II) A.1.b and PJM Manual 14H, section 6.2, Readiness Deposit #3 (RD3) are funds committed by the Project Developer or Eligible Customer based upon the applicable contribution to Network Upgrades as defined below. Readiness Deposits are not used to fund studies nor to offset Security.

During Decision Point II (DP2), the Project Developer or Eligible Customer is required to submit Readiness Deposit #3, which is calculated as 20% of cost allocation for required Phase II Network Upgrades minus Readiness Deposit #1 & Readiness Deposit #2.

Note 1: “Network Upgrades” referred to in the calculation include both (i) the Physical Interconnection Network Upgrades and (ii) the System Reliability Network Upgrades as shown in the Cost Summary table.

Note 2: Readiness Deposit #1 (RD1) = ($4,000 * Project Size (MW))

Note 3: Readiness Deposit #2 (RD2) = 10% of cost allocation for required Network Upgrades minus RD1. Readiness Deposit #2 (RD2) can be zero, but may not be a negative number.

Note 4: Readiness Deposit #3 can be zero, but may not be a negative number.

Readiness Deposit #3 Due for Project AG2-109

Readiness Deposit #3 has been calculated for the project based on the Phase II System Impact Study results and is shown in the table below. This Readiness Deposit #3 must be provided at Decision Point II through either a wire transfer or letter of credit per Manual 14H, Section 6.2.

Readiness Deposit #3 Due for AG2-109
Project ID: AG2-109
20% of cost allocation for Phase II Network Upgrades:(A) $2,912,446
Sum of Readiness Deposit #1 & Readiness Deposit #2 Received:(B) $1,241,326
Readiness Deposit #3 (RD3) due at DP2:(A) - (B) = $1,671,120
Note: Failure to provide an acceptable form of Readiness Deposit #3 by the end of Decision Point II will result in withdrawal and termination of the New Service Request.

For additional detail regarding Readiness Deposit Refunds, reference PJM Manual 14H, section 6.2.1. The Readiness Deposit Letter of Credit template can be found here.

Transmission Owner Scope of Work

The total preliminary cost estimate for the Transmission Owner scope of work (including TOIF and Physical Interconnection Network Upgrades) is given in the table below. These costs do not include CIAC Tax Gross-up.

Transmission Owner Build Option
Network Upgrades
RTEP IDDescriptionDirectIndirectTotal Cost ($USD)Allocated Cost ($USD)
LaborMaterialsLaborMaterials
(Pending)

Cut the existing 69 kV line and Loop in the new Interconnection substation.

$754,250$51,831$31,433$5,094$842,608$842,608
(Pending)

Install new UPLC Carrier Sets, Wave Traps, Line Tuners, and revise relay settings at New London substation.

$384,359$133,343$16,018$2,694$536,414$536,414
(Pending)

Fitchville substation nameplate update due to line name change.

$4,016$2,493$167$50$6,726$6,726
(Pending)

Install new UPLC Carrier Sets, Wave Traps, Line Tuners, relays, and revise relay settings at Wellington Substation.

$789,300$195,856$32,894$3,956$1,022,006$1,022,006
(Pending)

Revise relay settings at Hanville substation as required.

$47,385$0$1,975$0$49,360$49,360
(Pending)

Review and update relay settings at Carriage substation.

$47,360$0$1,974$0$49,334$49,334
Other
RTEP IDDescriptionDirectIndirectTotal Cost ($USD)Allocated Cost ($USD)
LaborMaterialsLaborMaterials
(Pending)

Install 69 kV revenue metering within new Interconnection substation.

$298,519$114,230$12,441$2,307$427,497$427,497
Stand-Alone Network Upgrades
RTEP IDDescriptionDirectIndirectTotal Cost ($USD)Allocated Cost ($USD)
LaborMaterialsLaborMaterials
(Pending)

Construct a new 69 kV 3-breaker ring bus Interconnection substation.

$7,160,091$2,820,731$298,397$59,208$10,338,427$10,338,427
(Pending)

Install/Test approximately 0.12 miles of new 48F/SM OPGW fiber cable from the new AG2-109 substation PCE to a splice point at STR 209A on the Hanville to Wellington OPGW cable installed by a different project. Underground ADSS will be utilized for this entire run to the existing splice point.

$538,640$20,504$22,448$414$582,006$582,006
(Pending)

Design, installation, and testing/commissioning for MPLS equipment for SCADA transport at AG2-109 Substation. Assumed SCADA work is included in this cost.

$367,689$126,949$15,323$2,564$512,525$512,525
(Pending)

Two (2) in-sub fiber builds to serve as OPGW tail ends to the Hanville - Wellington 69kV line with existing OPGW. Estimated (2) in-sub fiber builds for relaying protection from AG2-109 Substation control house to the AG2-109 PCO.

$103,347$5,171$4,307$104$112,929$112,929
Transmission Owner Interconnection Facilities
RTEP IDDescriptionDirectIndirectTotal Cost ($USD)Allocated Cost ($USD)
LaborMaterialsLaborMaterials
(Pending)

Integrate Interconnection Facilities protection and controls to the Transmission Owner system.

$47,385$0$1,975$0$49,360$49,360
(Pending)

Install line terminal equipment within the AG2-109 Interconnection substation. Install one span from AG2-109 Interconnection Substation to the Project Developer-owned dead-end structure outside of FE substation fence.

$742,546$322,364$30,946$8,223$1,104,079$1,104,079
Developer Build Option

Project Developer has the option ("Option to Build") to assume responsibility for the design, procurement and construction of Transmission Owner Interconnection Facilities and/or Stand-Alone Network Upgrades.

If Option to Build is elected, the Project Developer must fulfill additional requirements in accordance to PJM Manual 14C, section 5.1 and PJM Manual 14H, section 8.6.2.

The cost estimates for eligible facilities and Option to Build oversight are highlighted below:

Network Upgrades
RTEP IDDescriptionDirectIndirectTotal Cost ($USD)Allocated Cost ($USD)
LaborMaterialsLaborMaterials
(Pending)

Cut the existing 69 kV line and Loop in the new Interconnection substation.

$754,250$51,831$31,433$5,094$842,608$842,608
(Pending)

Install new UPLC Carrier Sets, Wave Traps, Line Tuners, and revise relay settings at New London substation.

$384,359$133,343$16,018$2,694$536,414$536,414
(Pending)

Fitchville substation nameplate update due to line name change.

$4,016$2,493$167$50$6,726$6,726
(Pending)

Install new UPLC Carrier Sets, Wave Traps, Line Tuners, relays, and revise relay settings at Wellington Substation.

$789,300$195,856$32,894$3,956$1,022,006$1,022,006
(Pending)

Revise relay settings at Hanville substation as required.

$47,385$0$1,975$0$49,360$49,360
(Pending)

Review and update relay settings at Carriage substation.

$47,360$0$1,974$0$49,334$49,334
Option to Build Oversight
RTEP IDDescriptionDirectIndirectTotal Cost ($USD)Allocated Cost ($USD)
LaborMaterialsLaborMaterials
(Pending)

Transmission Owner oversight of developer design and construction of new interconnection substation.

$1,022,593$0$42,617$0$1,065,210$1,065,210
Other
RTEP IDDescriptionDirectIndirectTotal Cost ($USD)Allocated Cost ($USD)
LaborMaterialsLaborMaterials
(Pending)

Install 69 kV revenue metering within new Interconnection substation.

$298,519$114,230$12,441$2,307$427,497$427,497
Stand-Alone Network Upgrades
RTEP IDDescriptionDirectIndirectTotal Cost ($USD)Allocated Cost ($USD)
LaborMaterialsLaborMaterials
(Pending)

Install/Test approximately 0.12 miles of new 48F/SM OPGW fiber cable from the new AG2-109 substation PCE to a splice point at STR 209A on the Hanville to Wellington OPGW cable installed by a different project. Underground ADSS will be utilized for this entire run to the existing splice point.

$538,640$20,504$22,448$414$582,006$582,006
(Pending)

Install (1) security system and camera system. Install (1) indoor security AC cabinet. Install (1) network fiber termination rack.

$1,635,351$255,640$68,153$5,164$1,964,308$1,964,308
Transmission Owner Interconnection Facilities
RTEP IDDescriptionDirectIndirectTotal Cost ($USD)Allocated Cost ($USD)
LaborMaterialsLaborMaterials
(Pending)

Integrate Interconnection Facilities protection and controls to the Transmission Owner system.

$47,385$0$1,975$0$49,360$49,360
Build Option Price Comparison
Build OptionTotal CostAllocated Cost
Transmission Owner Build Option$15,633,271$15,633,271
Developer Build Option$6,594,829$6,594,829

Based on the scope of work for the Interconnection Facilities, it is expected to take 36 month(s) after the signing of a Generator Interconnection Agreement (as this is a FERC connection) and construction kickoff call to complete the installation of the physical connection work. This assumes that there will be no environmental issues with any of the new properties associated with this project, that there will be no delays in acquiring the necessary permits for implementing the defined interconnection work, and that all system outages will be allowed when requested.

Note that the TO findings were made from a conceptual review of this project. A more detailed review of the connection facilities and their cost will be identified in a future study phase. Further note that the cost estimate data provided should be considered high level estimates since it was produced without a detailed engineering review. The Project Developer will be responsible for the actual cost of construction. TO herein reserves the right to return to any issues in this document and, upon appropriate justification, request additional monies to complete any reinforcements to the transmission systems.

Remote Terminal Work: During Phase II of the PJM interconnection process, TO’s System Protection Engineering Department will review transmission line protection as well as anti-islanding required to accommodate the new generation and interconnection substation. System Protection Engineering will determine the minimal acceptable protection requirements to reliably interconnect the proposed generating facility with the transmission system. The review is based on maintaining system reliability by reviewing TO’s protection requirements with the known transmission system configuration which includes generating facilities in the area. This review may determine that transmission line protection and communication upgrades are required at remote substations.

Transmission Owner Analysis

Transmission Owner Identified Network Impacts to Distribution Facilities

None


Transmission Owner Identified Network Impacts to Sub-Regional Facilities

The Transmission Owner identified network impacts to Sub-Regional facilities as follows:

Overloaded ElementContingencyRating [MVA]Final Cycle Loading %Contribution [MW]
239713 02NOVA 69.0 - 239167 02WELLNG 69.0 CKT 1 ATSI_P1-2_OEC-345-809_SRT-A
CONTINGENCY 'ATSI_P1-2_OEC-345-809_SRT-A'  /* LINE 02HAYES TO 02BEAVER 345 CK 1

  DISCONNECT BRANCH FROM BUS 239289 TO BUS 238569 CKT 1            /* 02HAYES 345 02BEAVER 345

END
33.0124.39 %10.03

Transmission Owner Identified System Reinforcements on Distribution Facilities

None


Transmission Owner Identified System Reinforcements on Sub-Regional Facilities
AG2-109 Transmission Owner Identified System Reinforcements Cost Breakdown:
TORTEP ID / TO IDTitleMW ImpactPercent AllocationAllocated Cost ($USD)
ATSIn9804.0 / TC2-ATSI-L02Upgrade (1) 4A overcurrent relay for breaker B41 at Wellington10.0 MW100.0%$509,895
Grand Total:$509,895
System Reinforcement
TORTEP ID / TO IDTitleTotal Cost
ATSIn9804.0 / TC2-ATSI-L02Upgrade (1) 4A overcurrent relay for breaker B41 at Wellington$509,895

Contributor

Description: Upgrade (1) 4A overcurrent relay for breaker B41 at Wellington New ratings to be 55/69/80 MVA Next Limiting Element: Current Transformer

Cost Allocation
ProjectMW ImpactPercent AllocationAllocated Cost ($USD)
AG2-10910.0 MW100.0%$509,895

Developer Requirements

The developer is responsible for all design and construction related activities on the developer’s side of the Point of Change in Ownership. FirstEnergy interconnection requirements can be found here.

To the extent that these Applicable Technical Requirements and Standards may conflict with the terms and conditions of the Tariff, the Tariff shall control.

Revenue Metering and SCADA Requirements

PJM Requirements
The developer will be required to install equipment necessary to provide Revenue Metering (KWH, KVARH) and real time data (KW, KVAR) for their generating Resource. See PJM Manual 01, PJM Manual 14D, and PJM Tariff Part IX, Subpart B, Appendix 2, section 8.
Meteorological Data Reporting Requirement
The solar generation facility shall provide the Transmission Provider with site-specific meteorological data including:
  • Temperature (degrees Fahrenheit)
  • Atmospheric Pressure (hectopascals)
  • Irradiance
  • Forced outage data
Transmission Owner Requirements
The Project Developer will be required to comply with all interconnected Transmission Owner’s revenue metering requirements located at the following link: PJM - Transmission Owner Engineering & Construction Standards.

Summer Peak Analysis

The New Service Request AG2-109 was evaluated as a 40.0 MW (28.1 MW Capacity) injection in the ATSI area.

AG2-109 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 40.0 MW (40.0 MW under study).

Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.

The following flowgates remain after considering the topology reinforcements required by the cycle.

StudyAreaFacility DescriptionContingency NameContingency TypeDC|ACFinal Cycle LoadingRating (MVA)Rating TypeMVA to MitigateMW ContributionDetails
GD2ATSI
02BEAVER-02LAKEAVE 345.0 kV Ckt 2 line
ATSI_P2-3_OEC-345-002_SRT-A
BreakerAC112.58 %1878.0B2114.26
3.77

Details for 02BEAVER-02LAKEAVE 345.0 kV Ckt 2 line l/o ATSI_P2-3_OEC-345-002_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Decrease to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:ATSI
Facility Description:
02BEAVER-02LAKEAVE 345.0 kV Ckt 2 line
Contingency Name:
ATSI_P2-3_OEC-345-002_SRT-A
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:112.58 %
Rating:1878.0 MVA
Rating Type:B
MVA to Mitigate:2114.26
MW Contribution:
3.77
Impact of Topology Modeling:
Decrease

Base Case Flowgate

Area:ATSI
Facility Description:
02BEAVER-02LAKEAVE 345.0 kV Ckt 2 line
Contingency Name:
ATSI_P2-3_OEC-345-002_SRT-A
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:156.06 %
Rating:1878.0 MVA
Rating Type:B
MVA to Mitigate:2930.9
MW Contribution:
3.9
Bus #Bus NameTypeMW Contribution
23856402BAYSG1
50/50
1.455
23860102FRMENG 1
50/50
1.798
23860202FRMENG 2
50/50
1.798
23860302FRMENG 3
50/50
3.65
23867002DVBSG1
50/50
12.603
23906402RICHG1
Adder
1.43
23917202WLORG-3
50/50
1.941
23917302WLORG-4
50/50
1.898
23917402WLORG-5
50/50
1.908
23920202STRYCT
Adder
1.949
23929302BS-PKR
50/50
2.564
247620Y3-023
Adder
0.245
247643Z2-116 C
Solar/Wind Harmer
0.036
20094526CT_V3-030
Solar/Wind Helper
0.225
20334926Z1-069 C
Solar/Wind Helper
0.787
24191202EL_AA1-006
Adder
0.352
24441205WTRV SLR C
Solar/Wind Harmer
0.079
274723RIVER EC ;12
Adder
7.743
274724RIVER EC ;11
Adder
7.651
274752CRETE EC ;2U
Adder
2.129
274753CRETE EC ;3U
Adder
2.129
274754CRETE EC ;4U
Adder
2.129
20091526CHSTN_FL
Solar/Wind Helper
0.266
24695305TIMB G C
Solar/Wind Harmer
1.933
24189802OREGON_CT1
50/50
2.75
24189902OREGON_CT2
50/50
2.692
24190002OREGON_ST1
50/50
3.625
247607V1-011 GEN
Solar/Wind Harmer
2.419
23857102WLORG-A
Adder
8.069
23857202WLORG-B
Adder
8.313
247521TR3_G114
Solar/Wind Harmer
1.865
254304AE2-114 C
Solar/Wind Helper
0.137
254305AE2-115 C
Solar/Wind Helper
0.137
235058AG1-386 C
Solar/Wind Helper
0.2
241982AE2-343 S C
Solar/Wind Helper
0.143
203946AE2-131 C
Solar/Wind Helper
0.238
203947AF1-006 C
Solar/Wind Helper
0.508
203952AE2-129 C
Solar/Wind Helper
0.238
203954AE2-126 C
Solar/Wind Helper
0.264
270191TR4_S_V150
Solar/Wind Harmer
1.664
23906502RICHG2&3
Adder
1.428
23906502RICHG2&3
Adder
1.428
20090526Q36
Solar/Wind Helper
0.497
940863AE2-074 GEN
Solar/Wind Helper
0.276
203979AG1-198 GEN
Solar/Wind Helper
0.256
203846AF2-130 C
Solar/Wind Helper
0.312
203835AF1-098 GEN
Solar/Wind Helper
1.743
203830AF1-094 GEN
Solar/Wind Helper
0.426
203818AF1-086 GEN
Solar/Wind Helper
0.851
203854AF2-039 C
Solar/Wind Helper
0.167
203855AF2-088 C
Solar/Wind Helper
0.081
203804AE2-113_GEN
Solar/Wind Helper
1.068
203993AD2-133_GEN1
Solar/Wind Helper
0.497
270302AB2-170 GEN
Solar/Wind Harmer
4.551
270317AD1-130_GEN
Solar/Wind Harmer
1.74
241886AC2-103 GEN2
Solar/Wind Harmer
17.897
241885AC2-103 GEN1
Solar/Wind Harmer
17.897
241801AE1-079 GEN
Solar/Wind Helper
0.16
270404AC1-167 GEN
Solar/Wind Harmer
0.737
270428AC2-015 C
Solar/Wind Harmer
5.2
241847AF2-150_GEN
Solar/Wind Harmer
2.695
270435AC2-044 GEN
Solar/Wind Harmer
1.202
270489AE1-102 GEN1
Solar/Wind Harmer
0.781
246936BC-WTG1
Solar/Wind Harmer
2.35
246937BC-WTG2
Solar/Wind Harmer
2.35
246938BC-WTG3
Solar/Wind Harmer
2.391
241808AF1-120 C
Solar/Wind Harmer
1.304
241996AE2-282_GEN
Solar/Wind Harmer
2.339
241813AF1-122_GEN
Solar/Wind Harmer
2.879
241960AC2-195 GEN
Solar/Wind Harmer
1.397
241832AE2-181_GEN
Solar/Wind Harmer
2.119
241967AE2-285_GEN
Solar/Wind Helper
0.41
241997AF1-093 GEN
Solar/Wind Helper
0.157
241807AE2-176_GEN
Solar/Wind Harmer
7.207
241840AF1-064_GEN
Solar/Wind Harmer
1.536
241858AF1-205_GEN
Solar/Wind Harmer
5.982
270297AD1-101 GEN
Solar/Wind Harmer
1.496
270377AD1-106 GEN
Solar/Wind Harmer
3.053
270258AD1-119 GEN
Solar/Wind Harmer
1.322
270449AD2-020 GEN
Solar/Wind Harmer
1.557
241985AE1-237 GEN
Solar/Wind Helper
0.159
270216AD2-079_GEN
Solar/Wind Harmer
0.315
270588AE1-091_GEN
Solar/Wind Harmer
7.73
270499AE1-146 GEN
Solar/Wind Harmer
2.797
270505AE1-170 C O1
Solar/Wind Harmer
8.128
270007AE1-245 C
Solar/Wind Harmer
3.305
270541AE2-072 C
Solar/Wind Harmer
4.762
270043AE2-236 GEN
Solar/Wind Harmer
2.674
270063AE2-323 C
Solar/Wind Harmer
1.163
270536AF1-215 GEN2
Solar/Wind Harmer
1.98
270535AF1-215 GEN1
Solar/Wind Harmer
1.98
270055AF2-134 C O1
Solar/Wind Harmer
1.32
254303AC2-168 GEN
Solar/Wind Helper
0.091
203853AF1-134 C O1
Solar/Wind Helper
0.245
270578AF1-285 GEN2
Solar/Wind Harmer
0.233
270578AF1-285 GEN2
Solar/Wind Harmer
0.606
270391AF1-285 GEN3
Solar/Wind Harmer
0.233
270391AF1-285 GEN3
Solar/Wind Harmer
0.606
270361_3
Solar/Wind Harmer
10.197
270575GUS2 35KV
Solar/Wind Harmer
12.013
270526AF1-158 GEN
Solar/Wind Harmer
2.256
270462AD2-086
Solar/Wind Harmer
3.781
270485AE1-090_GEN
Solar/Wind Harmer
0.329
270071AF1-092 GEN
Solar/Wind Harmer
6.649
270044AE2-322 C
Solar/Wind Harmer
0.894
23917102WLORG-2
50/50
1.88
274751CRETE EC ;1U
Adder
2.129
241966AE1-183 GEN
Solar/Wind Helper
0.157
24639705ELKHART HY
Adder
0.081
247522W1-056 GEN
Solar/Wind Harmer
1.879
270491AE1-102 GEN2
Solar/Wind Harmer
0.781
942221AE2-234 GEN
Solar/Wind Harmer
1.509
942801AE2-298 GEN
Solar/Wind Harmer
0.922
942871AE2-306 GEN
Solar/Wind Harmer
0.454
943021AE2-325 GEN
Solar/Wind Harmer
2.023
944161AF1-084 GEN
Solar/Wind Harmer
1.246
944231AF1-091 GEN
Solar/Wind Harmer
12.113
945111AF1-176 GEN
Solar/Wind Harmer
9.687
945111AF1-176 GEN
Solar/Wind Harmer
3.07
945411AF1-206 GEN
Solar/Wind Harmer
8.76
945641AF1-229 GEN
Solar/Wind Harmer
3.889
946071AF1-272 GEN
Solar/Wind Helper
1.261
946381AF1-302 GEN
Solar/Wind Helper
0.128
959331AF2-224 GEN
Solar/Wind Harmer
5.26
960681AF2-359 GEN
Solar/Wind Harmer
1.782
960841AF2-375 GEN
Solar/Wind Harmer
4.495
961051AF2-396 GEN
Solar/Wind Harmer
8.744
961051AF2-396 GEN
Solar/Wind Harmer
4.067
961961AG1-039 GEN
Solar/Wind Harmer
1.859
961971AG1-040 GEN
Solar/Wind Helper
0.442
962101AG1-054 GEN
Solar/Wind Helper
0.393
962511AG1-100 GEN
Solar/Wind Helper
0.454
963791AG1-232 GEN
Solar/Wind Harmer
6.482
966831AG1-554 GEN
Solar/Wind Harmer
0.826
970031AG2-029 GEN
Solar/Wind Harmer
13.191
970065AG2-057 GEN
Solar/Wind Harmer
0.45
970179AG2-119 GEN
Solar/Wind Harmer
4.027
970349AG2-230 GEN
Solar/Wind Harmer
7.078
970373AG2-245 GEN
Solar/Wind Harmer
9.365
971201AH1-060 GEN
Solar/Wind Harmer
0.9
971347AH1-153 GEN
Solar/Wind Harmer
2.359
971549AH1-272 GEN
Solar/Wind Harmer
12.854
971567AH1-282 GEN
Solar/Wind Harmer
3.214
971771AH1-392 GEN
Solar/Wind Harmer
4.593
972181SS23-001
Solar/Wind Harmer
2.584
972231SS25-0005
Solar/Wind Harmer
4.134
972253AH1-711 GEN
Adder
53.07
20398826ARMNA MT
Solar/Wind Helper
0.785
24441505OLIV SLR
Solar/Wind Harmer
0.066
270223U2-072_GEN1
Solar/Wind Harmer
0.989
270224U2-072_GEN2
Solar/Wind Harmer
0.989
270227U2-072_GEN3
Solar/Wind Harmer
0.989
270228U2-072_GEN4
Solar/Wind Harmer
0.989
270231U2-072_GEN5
Solar/Wind Harmer
0.989
270246TR4_N_V150
Solar/Wind Harmer
0.472
270247TR4_N_V136
Solar/Wind Harmer
0.472
957071AF2-004 GEN
50/50
15.111
957111AF2-005 GEN
Adder
1.302
957201AF2-014 GEN
Solar/Wind Harmer
2.725
957891AF2-083 GEN
Solar/Wind Harmer
8.1
958091AF2-103 GEN
Solar/Wind Harmer
0.099
958321AF2-126 GEN
Solar/Wind Harmer
1.652
965011AG1-365 GEN
Solar/Wind Harmer
5.26
965021AG1-366 GEN
Solar/Wind Harmer
1.223
965041AG1-368 GEN
Solar/Wind Harmer
5.565
965051AG1-369 GEN
Solar/Wind Harmer
2.771
965421AG1-410 GEN
Solar/Wind Harmer
17.81
965681AG1-436 GEN
Solar/Wind Harmer
5.896
965791AG1-447 GEN
Solar/Wind Harmer
3.017
966311AG1-500 GEN
50/50
176.524
966321AG1-501 GEN
Adder
1.627
970159AG2-109 GEN
Solar/Wind Harmer
3.775
990142J1224
External Queue
14.317364692687988
990527J1329
External Queue
1.9586000442504883
991177J1571 G
External Queue
16.711238861083984
991182J1586 G
External Queue
26.50733757019043
CBM West 1LTFEXP_CBM-W1->PJM
CBM
90.951
CBM West 2LTFEXP_CBM-W2->PJM
CBM
34.551
CBM South 1LTFEXP_CBM-S1->PJM
CBM
7.496
CBM South 2LTFEXP_CBM-S2->PJM
CBM
1.326
NYPJM->LTFIMP_NY
CLTF
2.203
LGEELTFEXP_LGEE->PJM
CLTF
1.76
WECLTFEXP_WEC->PJM
CLTF
1.522
CPLELTFEXP_CPLE->PJM
CLTF
0.089
TVALTFEXP_TVA->PJM
CLTF
1.871
MECLTFEXP_MEC->PJM
CLTF
5.849
LAGNLTFEXP_LAGN->PJM
CLTF
4.213
SIGELTFEXP_SIGE->PJM
CLTF
0.148
AG2-052LTFEXP_AG2-052->PJM
LTF
0.098
AH1-155LTFEXP_AH1-155->PJM
LTF
0.147
CONTINGENCY 'ATSI_P2-3_OEC-345-002_SRT-A'
 DISCONNECT BRANCH FROM BUS 238569 TO BUS 238607 CKT 1   /*02BEAVER     345.0 - 02CARLIL     345.0
 DISCONNECT BRANCH FROM BUS 238569 TO BUS 239725 CKT 1   /*02BEAVER     345.0 - 02LAKEAVE    345.0
END
238569 to 239725 ckt 2

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

StudyAreaFacility DescriptionContingency NameContingency TypeDC|ACFinal Cycle LoadingRating (MVA)Rating TypeMVA to MitigateMW ContributionDetails
GD2AP
01KAMMER-01 502 J 500.0 kV Ckt 1 line
AP_P1-3_MP-765-501T_SRT-A
SingleAC102.51 %3729.0B3822.68
2.81
GD2AEP/AP
05KAMMER-01KAMMER 765.0/500.0 kV Ckt 1 transformer
AP_P1-3_MP-765-501T_SRT-A
SingleAC103.35 %3792.0B3919.06
2.81

Details for 01KAMMER-01 502 J 500.0 kV Ckt 1 line l/o AP_P1-3_MP-765-501T_SRT-A


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area:AP
Facility Description:
01KAMMER-01 502 J 500.0 kV Ckt 1 line
Contingency Name:
AP_P1-3_MP-765-501T_SRT-A
Contingency Type:Single
DC|AC:AC
Final Cycle Loading:102.51 %
Rating:3729.0 MVA
Rating Type:B
MVA to Mitigate:3822.68
MW Contribution:
2.81
Impact of Topology Modeling:
Elimination
Bus #Bus NameTypeMW Contribution
23906402RICHG1
Adder
1.118
23920202STRYCT
Adder
1.272
23929302BS-PKR
Adder
1.285
24690905MDL-1G C
Solar/Wind Harmer
0
24691005MDL-2G C
Solar/Wind Harmer
0
24697605MDL-3G C
Solar/Wind Harmer
0
24728505AND G1
Adder
3.321
24728605AND G2
Adder
3.321
24728705AND G3
Adder
6.945
24728805RICHG1
Adder
3.364
24728905RICHG2
Adder
3.364
24729505KEY G4
Adder
6.029
247620Y3-023
Adder
0.426
247621Y3-024
Adder
0.22
247642Z2-115 C
Solar/Wind Harmer
0.003
23546401DTGZ2-030
Solar/Wind Helper
0.079
23585401KL_K28_T16
Solar/Wind Helper
1.286
23750701CROSSCHOOL
Solar/Wind Helper
1.305
23751201ROTHROCK
Solar/Wind Helper
0.726
25196708WSDLE6
Adder
7.715
25196808ZIMRHP
Adder
66.312
25306009OHH W.
Adder
2.688
25322209TAIT E
Adder
8.971
25322209TAIT E
Adder
9.177
25326109MON D
Adder
1.25
25326309TAIT D
Adder
1.031
270119AB2-067 GEN1
50/50
8.122
270120AB2-067 GEN2
50/50
8.122
274675JOLIET 29;7U
Adder
27.038
274675JOLIET 29;7U
Adder
26.073
274676JOLIET 29;8U
Adder
27.038
274676JOLIET 29;8U
Adder
26.073
274682WAUKEGAN ;7U
Adder
15.667
274682WAUKEGAN ;7U
Adder
15.667
274683WAUKEGAN ;8U
Adder
18.36
274683WAUKEGAN ;8U
Adder
15.477
274687WILL CNTY;4U
Adder
24.642
274687WILL CNTY;4U
Adder
24.642
274693ROCKY RD ;1P
Adder
9.616
274695ROCKY RD ;2P
Adder
9.711
274696ROCKY RD ;4P
Adder
9.94
274697ROCKY RD ;3P
Adder
2.638
274723RIVER EC ;12
Adder
15.96
274724RIVER EC ;11
Adder
15.773
274728ELWOOD EC;5P
Adder
14.48
274729ELWOOD EC;1P
Adder
14.48
274730ELWOOD EC;6P
Adder
14.48
274731ELWOOD EC;2P
Adder
14.48
274732ELWOOD EC;7P
Adder
14.48
274733ELWOOD EC;3P
Adder
14.48
274734ELWOOD EC;8P
Adder
14.48
274735ELWOOD EC;4P
Adder
14.48
274736ELWOOD EC;9P
Adder
14.48
274752CRETE EC ;2U
Adder
7.348
274753CRETE EC ;3U
Adder
7.348
274754CRETE EC ;4U
Adder
7.348
274771LINCOLN ;2U
Adder
7.511
274772LINCOLN ;3U
Adder
7.511
274773LINCOLN ;4U
Adder
7.511
274774LINCOLN ;5U
Adder
7.511
274775LINCOLN ;6U
Adder
7.511
274776LINCOLN ;7U
Adder
7.511
274777LINCOLN ;8U
Adder
7.511
274822ROCKFORD ;11
Adder
16.895
274823ROCKFORD ;21
Adder
12.596
274826FISK ;BP
Adder
9.691
274827FISK ;RP
Adder
6.868
274847GR RIDGE ;BU
Solar/Wind Harmer
0
274855GSG-6 ;RU
Solar/Wind Harmer
0.22
274861TOP CROP ;1U
Solar/Wind Harmer
0
274862TOP CROP ;2U
Solar/Wind Harmer
0.824
274871GR RIDGE ;2U
Solar/Wind Harmer
0
274879MINONK ;1U
Solar/Wind Harmer
0.253
274888KELLY CRK;1U
Solar/Wind Harmer
0.36
23562501BACKB
Solar/Wind Helper
0.891
25326509SID D
Adder
1.291
24318805MLG1
50/50
12.144
25196408WSDLE3
Adder
7.822
23777801MSM_W1-116
Solar/Wind Helper
0.099
23777901MDS_W4-102
Solar/Wind Helper
0.155
235020AA1-095 C
Solar/Wind Helper
0.046
24318905MLG2
50/50
8.017
25194408D.CRK1
Adder
6.694
25194508D.CRK3
Adder
1.252
25194608D.CRK4
Adder
1.455
25194608D.CRK4
Adder
1.455
25196008MFTGT1
Adder
1.208
25196008MFTGT1
Adder
1.17
25196108MFTGT2
Adder
1.236
25196108MFTGT2
Adder
1.331
25196208WSDLE1
Adder
7.735
25196308WSDLE2
Adder
7.754
25196508WSDLE4
Adder
7.521
25196608WSDLE5
Adder
7.599
274674JOLIET 9 ;6U
Adder
13.562
274674JOLIET 9 ;6U
Adder
13.562
274828WAUKEGAN ;BP
Adder
9.624
24379505HDWTR1G C
Solar/Wind Harmer
0
24385905FR-11G C
Solar/Wind Harmer
0
24386205FR-12G C
Solar/Wind Harmer
0
24386405FR-21G C
Solar/Wind Harmer
0
24386605FR-22G C
Solar/Wind Harmer
0
24387305FR-4G C
Solar/Wind Harmer
0
24695305TIMB G C
Solar/Wind Harmer
0.567
24699105WLD G1 C
Solar/Wind Harmer
0
24725505WLD G2 C
Solar/Wind Harmer
0
247607V1-011 GEN
Solar/Wind Harmer
0
247521TR3_G114
Solar/Wind Harmer
0.243
226910AB2-157 C
Solar/Wind Helper
0.013
237025AB1-124 C
Solar/Wind Helper
0.142
237030AB1-096 C
Solar/Wind Helper
0.058
237038AE2-054 C
Solar/Wind Helper
0.237
237048AF1-022 C
Solar/Wind Helper
0.157
252510AF1-249 C
Solar/Wind Harmer
0.047
270122AB2-093 CT
50/50
4.163
270201AC2-176 GEN
Solar/Wind Harmer
0
3141196NOKESVL
Solar/Wind Helper
0.912
316411AF1-147_GEN1
Solar/Wind Helper
0.785
316415AF1-147_GEN2
Solar/Wind Helper
0.785
25183208HLCRTG
Solar/Wind Harmer
0
23906502RICHG2&3
Adder
1.119
23906502RICHG2&3
Adder
1.119
23751101LEADS_P59
Solar/Wind Helper
1.931
235062AE1-101 C1
Solar/Wind Helper
1.442
274850MENDOTA H;RU
Solar/Wind Harmer
0.07
238185AF2-356 C
Solar/Wind Helper
2.305
237080AD1-060 GEN
Solar/Wind Helper
0.298
235067AD1-061 GEN
Solar/Wind Helper
0.388
237001AB1-127_GEN
Solar/Wind Helper
0.384
237002AB1-128_GEN
Solar/Wind Helper
0.385
238175AF1-290_GEN
Solar/Wind Helper
0.138
238221AF1-254 C O1
Solar/Wind Helper
0.239
238120AE2-309 GEN
Solar/Wind Helper
0.458
238169AE2-226 GEN1
Solar/Wind Helper
0.618
238170AE2-226 GEN2
Solar/Wind Helper
0.618
274872LEEDK;1U
Solar/Wind Harmer
0
926823AC1-168 GEN
Solar/Wind Harmer
1.023
276776AD2-060 GEN
Solar/Wind Harmer
0.659
276806AD2-047 C O1
Solar/Wind Harmer
3.499
276901AD2-066 C O1
Solar/Wind Harmer
0
276893AG1-478 C
Solar/Wind Harmer
0.41
238108AE1-109 GEN1
Solar/Wind Helper
0.099
238109AE1-109 GEN2
Solar/Wind Helper
0.099
238110AE1-109 GEN3
Solar/Wind Helper
0.099
237085AD2-009_GEN
Solar/Wind Helper
1.434
276897AD1-100 C
Solar/Wind Harmer
15.406
235054AD2-180 GEN
Solar/Wind Helper
1.764
237061AD1-155 GEN
Solar/Wind Helper
1.557
235531U2-073 GEN
Solar/Wind Helper
2.87
237006AB1-125 GEN
Solar/Wind Helper
0.107
23779801AA1-109
Solar/Wind Helper
0.168
23583801GRNGAP
Solar/Wind Helper
4.94
226929AD2-058 GEN
Solar/Wind Helper
0.087
253333AC1-068 GEN
Solar/Wind Harmer
0.008
253325AC1-069 GEN
Solar/Wind Harmer
0.008
270180AB1-006 GEN1
Solar/Wind Harmer
0
253394AE2-221_GEN
Solar/Wind Harmer
0
253398AE2-221_GEN2
Solar/Wind Harmer
0
252507AC2-088 GEN
Solar/Wind Harmer
0.275
252509AD1-136 GEN
Solar/Wind Harmer
0.031
252516AE2-318_GEN
Solar/Wind Harmer
6.92
252519AF1-045_GEN
Solar/Wind Harmer
3.223
276872AE1-163_GEN1
Solar/Wind Harmer
0
276876AE1-163_GEN2
Solar/Wind Harmer
0
276882AE2-255 GEN
Solar/Wind Harmer
0.708
276868AE1-113 GEN
Solar/Wind Harmer
1.213
253316AC1-085 GEN3
Solar/Wind Harmer
0
253317AC1-085 GEN4
Solar/Wind Harmer
0
274744AC1-111 GEN8
Adder
4.899
274745AC1-111 GEN9
Adder
4.899
274746AC1-111 G10
Adder
4.899
276861AD2-134 GEN
Solar/Wind Harmer
0.107
276863AD2-134 GEN
Solar/Wind Harmer
0.107
241955AC1-078 GEN
Solar/Wind Harmer
-0.001
270166AC1-044 GEN3
50/50
8.122
270302AB2-170 GEN
Solar/Wind Harmer
0
270317AD1-130_GEN
Solar/Wind Harmer
0
270263AC1-001 GEN
Solar/Wind Harmer
0.659
238127S14_GEN_2
Solar/Wind Helper
0.716
238126S14_GEN_1
Solar/Wind Helper
0.716
238117U2-030
Solar/Wind Helper
0.296
238118U2-030_1
Solar/Wind Helper
0.296
270209AC1-174_GEN
Solar/Wind Harmer
0
270291AC1-194 GEN
Solar/Wind Harmer
0
270428AC2-015 C
Solar/Wind Harmer
0
270435AC2-044 GEN
Solar/Wind Harmer
0.861
270489AE1-102 GEN1
Solar/Wind Harmer
0.884
246936BC-WTG1
Solar/Wind Harmer
0.274
246937BC-WTG2
Solar/Wind Harmer
0.274
246938BC-WTG3
Solar/Wind Harmer
0.245
270432AC2-029 GEN
Solar/Wind Harmer
3.082
270273AD2-016 GEN
Solar/Wind Harmer
0.693
270269AC2-059
Solar/Wind Harmer
0
241972AD1-140 GEN
Solar/Wind Harmer
0.749
270340AC2-060 GEN
Solar/Wind Harmer
0.001
270367AC2-061_GEN
Solar/Wind Harmer
0
270437AC2-090 C
Solar/Wind Harmer
0
241813AF1-122_GEN
Solar/Wind Harmer
3.228
241858AF1-205_GEN
Solar/Wind Harmer
2.535
270377AD1-106 GEN
Solar/Wind Harmer
2.656
270383AD1-128 GEN
Solar/Wind Harmer
0
270449AD2-020 GEN
Solar/Wind Harmer
0
276903AD2-071 C
Solar/Wind Harmer
6.96
276805AD2-038 GEN
Solar/Wind Harmer
0
270471AD2-092_GEN
Solar/Wind Harmer
0.001
270349AD2-093_GEN
Solar/Wind Harmer
0.001
270588AE1-091_GEN
Solar/Wind Harmer
5.409
270499AE1-146 GEN
Solar/Wind Harmer
0.022
270505AE1-170 C O1
Solar/Wind Harmer
6.751
270594AE1-207 GEN
Solar/Wind Harmer
7.026
270032AE2-172
Solar/Wind Harmer
4.182
270599AE1-208 GEN
Solar/Wind Harmer
5.805
270031AE2-169
Solar/Wind Harmer
3.483
270007AE1-245 C
Solar/Wind Harmer
0
270541AE2-072 C
Solar/Wind Harmer
0
270024AE2-089 GEN
Solar/Wind Harmer
0.001
270518AE2-148 GEN
Solar/Wind Harmer
0.581
270520AE2-214 GEN
Solar/Wind Harmer
0
270543AE2-219 C
Solar/Wind Harmer
4.436
270043AE2-236 GEN
Solar/Wind Harmer
4.212
270322AE2-290 GEN
Solar/Wind Harmer
6.558
270356AE2-297 GEN
Solar/Wind Harmer
0
270063AE2-323 C
Solar/Wind Harmer
0
270536AF1-215 GEN2
Solar/Wind Harmer
0
270535AF1-215 GEN1
Solar/Wind Harmer
0
270055AF2-134 C O1
Solar/Wind Harmer
0
270284AF1-227 GEN1
Solar/Wind Harmer
-0.001
270054AF2-122 C O1
Solar/Wind Harmer
0
270466AD2-091
50/50
6.112
270036AE2-216 BAT
50/50
6.723
270475AD2-096_GEN
50/50
6.627
270051AF1-062 GEN
50/50
11.187
270459AD2-067 GEN
Solar/Wind Harmer
0
270578AF1-285 GEN2
Solar/Wind Harmer
0.496
270391AF1-285 GEN3
Solar/Wind Harmer
0.496
270186AC1-089 GEN
Solar/Wind Harmer
0
270361_3
Solar/Wind Harmer
4.488
270575GUS2 35KV
Solar/Wind Harmer
4.488
253370AE2-315 SEC1
Adder
1.874
253370AE2-315 SEC1
Adder
1.874
253370AE2-315 SEC1
Adder
1.874
253371AE2-315 SEC2
Adder
1.772
253371AE2-315 SEC2
Adder
1.772
253372AE2-315 SEC3
Adder
1.772
253372AE2-315 SEC3
Adder
1.772
270526AF1-158 GEN
Solar/Wind Harmer
0
253406AD2-031_GEN
Solar/Wind Harmer
0.473
270462AD2-086
Solar/Wind Harmer
0
270071AF1-092 GEN
Solar/Wind Harmer
12.47
270004AE1-209 GEN
Solar/Wind Harmer
1.364
270005AE1-210 C O1
Solar/Wind Harmer
1.364
274751CRETE EC ;1U
Adder
7.348
274770LINCOLN ;1U
Adder
7.511
274863CRW1-WTG
Solar/Wind Harmer
0
274864CRW2-WTG
Solar/Wind Harmer
0
3138216PACIFIC
Solar/Wind Helper
0.039
316095T157 G97
Solar/Wind Helper
1.326
316097T157 G90
Solar/Wind Helper
1.326
926881AC1-175 GEN
Solar/Wind Harmer
0
943121AE2-341 GEN
Solar/Wind Harmer
10.254
945421AF1-207 GEN
Solar/Wind Harmer
0
946031AF1-268 GEN
Solar/Wind Harmer
5.999
946171AF1-282 GEN
Solar/Wind Harmer
6.309
946181AF1-283 GEN
Solar/Wind Harmer
8.202
946581AF1-322 GEN
Solar/Wind Harmer
-0.001
946671AF1-331 GEN
Solar/Wind Harmer
0.643
958481AF2-142 GEN
Solar/Wind Harmer
9.155
958491AF2-143 GEN
Solar/Wind Harmer
9.115
959081AF2-199 GEN
Solar/Wind Harmer
6.016
959091AF2-200 GEN
Solar/Wind Harmer
12.032
962581AG1-107 GEN
Solar/Wind Harmer
0.001
962691AG1-118 GEN
Solar/Wind Harmer
18.2
962781AG1-127 GEN
Solar/Wind Harmer
5.767
966841AG1-555 GEN
Solar/Wind Harmer
0.693
970169AG2-114 GEN
Solar/Wind Harmer
6.047
970241AG2-163 GEN
Solar/Wind Harmer
3.524
970289AG2-191 GEN
Solar/Wind Harmer
1.191
970289AG2-191 GEN
Solar/Wind Harmer
0.689
970291AG2-192 GEN
Solar/Wind Harmer
0.815
970291AG2-192 GEN
Solar/Wind Harmer
0.376
970569AG2-363 GEN
Solar/Wind Harmer
18.043
970571AG2-364 GEN
Solar/Wind Harmer
12.028
970613AG2-401 GEN
Solar/Wind Harmer
4.595
970773AG2-487 GEN
Solar/Wind Harmer
1.088
970781AG2-491 GEN
Solar/Wind Harmer
6.168
970825AG2-519 GEN
Solar/Wind Harmer
4.738
970825AG2-519 GEN
Solar/Wind Harmer
2.233
970879AG2-548 GEN
Solar/Wind Harmer
4.544
970879AG2-548 GEN
Solar/Wind Harmer
1.033
971067AG2-660 GEN
Solar/Wind Harmer
2.005
971073AG2-665 GEN
Solar/Wind Harmer
4.544
971073AG2-665 GEN
Solar/Wind Harmer
1.033
971171AH1-044 GEN
Solar/Wind Harmer
12.032
971341AH1-150 GEN
Solar/Wind Harmer
12.032
971343AH1-151 GEN
Solar/Wind Harmer
12.032
971411AH1-196 GEN
Solar/Wind Harmer
9.046
971613AH1-306 GEN
Solar/Wind Harmer
3.011
971675AH1-338 GEN
Solar/Wind Harmer
2.352
227287AC2-120 GEN
Solar/Wind Helper
0.303
270240V3-007_GEN2
Solar/Wind Harmer
0
939401AE1-172 GEN
Solar/Wind Harmer
4.563
957471AF2-041 GEN
Solar/Wind Harmer
18.048
963741AG1-226 GEN
Solar/Wind Harmer
14.298
963841AG1-237 GEN
Solar/Wind Harmer
2.634
964991AG1-363 GEN
Solar/Wind Helper
4.464
971997AH1-543 GEN
Solar/Wind Harmer
3.181
24639705ELKHART HY
Adder
0.142
247536S-71 GEN
Solar/Wind Harmer
0.254
270491AE1-102 GEN2
Solar/Wind Harmer
0.884
274887GEN-1.85
Solar/Wind Harmer
0.16
938701AE1-092 GEN
Solar/Wind Harmer
11.951
939351AE1-166 GEN
Solar/Wind Harmer
0
942081AE2-220 GEN
Solar/Wind Harmer
0
942221AE2-234 GEN
Solar/Wind Harmer
2.589
942861AE2-305 GEN
Solar/Wind Harmer
5.722
943021AE2-325 GEN
Solar/Wind Harmer
3.355
943591AF1-030 GEN
Solar/Wind Harmer
6.819
943851AF1-053 GEN
Solar/Wind Harmer
1.956
943861AF1-054 GEN
Solar/Wind Harmer
2.824
944231AF1-091 GEN
Solar/Wind Harmer
15.173
944531AF1-118 GEN
Solar/Wind Harmer
29.147
944541AF1-119 GEN
Solar/Wind Harmer
0.429
945111AF1-176 GEN
Solar/Wind Harmer
11.479
945111AF1-176 GEN
Solar/Wind Harmer
5.214
945371AF1-202 GEN
Solar/Wind Harmer
0
945411AF1-206 GEN
Solar/Wind Harmer
0
945581AF1-223 GEN
Solar/Wind Harmer
0
945631AF1-228 GEN
Solar/Wind Harmer
0.001
945641AF1-229 GEN
Solar/Wind Harmer
0.001
958861AF2-177 GEN
Solar/Wind Harmer
2.778
958961AF2-187 GEN
Solar/Wind Harmer
0
959141AF2-205 GEN
Solar/Wind Harmer
0
959331AF2-224 GEN
Solar/Wind Harmer
4.665
960591AF2-350 GEN
Solar/Wind Harmer
6.175
960681AF2-359 GEN
Solar/Wind Harmer
0
960841AF2-375 GEN
Solar/Wind Harmer
0
960971AF2-388 GEN
Solar/Wind Harmer
3.772
961051AF2-396 GEN
Solar/Wind Harmer
12.859
961051AF2-396 GEN
Solar/Wind Harmer
8.573
961821AG1-024 GEN
Solar/Wind Harmer
4.743
961921AG1-034 GEN
Solar/Wind Harmer
7.115
962031AG1-047 GEN
Solar/Wind Harmer
0
962761AG1-125 GEN
Solar/Wind Harmer
30.582
962771AG1-126 GEN
Solar/Wind Harmer
30.582
963791AG1-232 GEN
Solar/Wind Harmer
8.828
970031AG2-029 GEN
Solar/Wind Harmer
3.529
970065AG2-057 GEN
Solar/Wind Harmer
0.721
970073AG2-061 GEN
Solar/Wind Harmer
2.026
970109AG2-082 GEN
Solar/Wind Harmer
14.58
970149AG2-104 GEN
Solar/Wind Harmer
16.515
970153AG2-106 GEN
Solar/Wind Harmer
19.529
970155AG2-107 GEN
Solar/Wind Harmer
19.529
970179AG2-119 GEN
Solar/Wind Harmer
6.495
970191AG2-125 GEN
Solar/Wind Harmer
1.674
970329AG2-216 GEN
Solar/Wind Harmer
3
970349AG2-230 GEN
Solar/Wind Harmer
9.656
970373AG2-245 GEN
Solar/Wind Harmer
13.225
970621AG2-405 GEN
Solar/Wind Harmer
1.233
970623AG2-406 GEN
Solar/Wind Harmer
1.223
970707AG2-453 GEN
Solar/Wind Harmer
20.139
970833AG2-524 GEN
Solar/Wind Harmer
6.754
970833AG2-524 GEN
Solar/Wind Harmer
4.502
970883AG2-550 GEN
Solar/Wind Harmer
6.337
970885AG2-551 GEN
Solar/Wind Harmer
2.112
970941AG2-585 GEN
Solar/Wind Harmer
3.396
971029AG2-637 GEN
Solar/Wind Harmer
9.493
971199AH1-059 GEN
Solar/Wind Harmer
1.506
971201AH1-060 GEN
Solar/Wind Harmer
1.441
971347AH1-153 GEN
Solar/Wind Harmer
3.219
971549AH1-272 GEN
Solar/Wind Harmer
13.254
971567AH1-282 GEN
Solar/Wind Harmer
5.363
971605AH1-302 GEN
Solar/Wind Harmer
7.778
971609AH1-304 GEN
Solar/Wind Harmer
1.034
971611AH1-305 GEN
Solar/Wind Harmer
3.704
971653AH1-327 GEN
Solar/Wind Harmer
1.032
971655AH1-328 GEN
Solar/Wind Harmer
2.641
971771AH1-392 GEN
Solar/Wind Harmer
6.414
971917AH1-482 GEN
Solar/Wind Harmer
8.126
971995AH1-542 GEN
Solar/Wind Harmer
2.725
972037AH1-567 GEN1
Adder
0.162
972038AH1-567 GEN2
Adder
0.323
972063AH1-580 GEN
Solar/Wind Harmer
14.646
972159AH1-661 GEN
Adder
0.989
972227AH1-698 GEN1
Adder
2.307
972228AH1-698 GEN2
Adder
3.276
972239AH1-704 GEN
50/50
3.142
972253AH1-711 GEN
Adder
28.904
972259AH1-714 GEN
Adder
16.858
972269AH1-719 GEN
Adder
2.204
270246TR4_N_V150
Solar/Wind Harmer
0.043
270247TR4_N_V136
Solar/Wind Harmer
0.043
276843GEN-1.7
Solar/Wind Harmer
0.2
940581AE2-045 GEN
Solar/Wind Harmer
0
940611AE2-048 GEN
Solar/Wind Harmer
16.742
941391AE2-136 GEN
Solar/Wind Harmer
9.431
941551AE2-152 GEN
Solar/Wind Harmer
0
942051AE2-217 GEN
Solar/Wind Harmer
13.26
957201AF2-014 GEN
Solar/Wind Harmer
0
957741AF2-068 GEN
Solar/Wind Harmer
9.527
957841AF2-078 GEN
Solar/Wind Harmer
0
957891AF2-083 GEN
Solar/Wind Harmer
10.714
958011AF2-095 GEN
Solar/Wind Harmer
8.892
958321AF2-126 GEN
Solar/Wind Harmer
0.855
958381AF2-132 GEN
Solar/Wind Harmer
0.001
958391AF2-133 GEN
Solar/Wind Harmer
0.001
964401AG1-302 GEN
Solar/Wind Harmer
0.001
964611AG1-324 GEN
Solar/Wind Harmer
0.476
964611AG1-324 GEN
Solar/Wind Harmer
2.473
964861AG1-349 GEN
Solar/Wind Harmer
0.001
965011AG1-365 GEN
Solar/Wind Harmer
6.664
965021AG1-366 GEN
Solar/Wind Harmer
2.221
965041AG1-368 GEN
Solar/Wind Harmer
6.675
965051AG1-369 GEN
Solar/Wind Harmer
3.345
965421AG1-410 GEN
Solar/Wind Harmer
20.356
965651AG1-433 GEN
Solar/Wind Harmer
1.886
965681AG1-436 GEN
Solar/Wind Harmer
7.938
965791AG1-447 GEN
Solar/Wind Harmer
5.821
970159AG2-109 GEN
Solar/Wind Harmer
2.815
274811UNIV PK N;7U
Adder
4.45
274812UNIV PK N;8U
Adder
4.45
274814UNIV PK N;0U
Adder
4.489
276691AA1-018 GEN1
Solar/Wind Harmer
0.992
276694AA1-018 GEN2
Solar/Wind Harmer
0
238147AE2-230_GEN1
Solar/Wind Helper
0.439
238148AE2-230_GEN2
Solar/Wind Helper
0.439
238149AF1-291A_GEN
Solar/Wind Helper
0.125
238152AF2-075_GEN
Solar/Wind Helper
0.627
235063AE1-101 C2
Solar/Wind Helper
1.442
274805UNIV PK N;1U
Adder
4.46
274807UNIV PK N;3U
Adder
4.479
274808UNIV PK N;4U
Adder
4.43
274800UNIV PARK;3U
Adder
5.159
274801UNIV PARK;4U
Adder
5.159
274802UNIV PARK;5U
Adder
5.164
274803UNIV PARK;6U
Adder
5.164
CBM West 1LTFEXP_CBM-W1->PJM
CBM
124.933
CBM West 2LTFEXP_CBM-W2->PJM
CBM
91.648
CBM South 1LTFEXP_CBM-S1->PJM
CBM
22.848
CBM South 2LTFEXP_CBM-S2->PJM
CBM
4.294
NYPJM->LTFIMP_NY
CLTF
3.843
LGEELTFEXP_LGEE->PJM
CLTF
5.521
WECLTFEXP_WEC->PJM
CLTF
3.283
TVALTFEXP_TVA->PJM
CLTF
5.655
MECLTFEXP_MEC->PJM
CLTF
13.416
LAGNLTFEXP_LAGN->PJM
CLTF
11.693
SIGELTFEXP_SIGE->PJM
CLTF
0.416
AG2-052LTFEXP_AG2-052->PJM
LTF
0.207
AH1-155LTFEXP_AH1-155->PJM
LTF
0.31

Details for 05KAMMER-01KAMMER 765.0/500.0 kV Ckt 1 transformer l/o AP_P1-3_MP-765-501T_SRT-A


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area:AEP/AP
Facility Description:
05KAMMER-01KAMMER 765.0/500.0 kV Ckt 1 transformer
Contingency Name:
AP_P1-3_MP-765-501T_SRT-A
Contingency Type:Single
DC|AC:AC
Final Cycle Loading:103.35 %
Rating:3792.0 MVA
Rating Type:B
MVA to Mitigate:3919.06
MW Contribution:
2.81
Impact of Topology Modeling:
Elimination
Bus #Bus NameTypeMW Contribution
23906402RICHG1
Adder
1.118
23920202STRYCT
Adder
1.272
23929302BS-PKR
Adder
1.285
24690905MDL-1G C
Solar/Wind Harmer
0
24691005MDL-2G C
Solar/Wind Harmer
0
24697605MDL-3G C
Solar/Wind Harmer
0
24728505AND G1
Adder
3.321
24728605AND G2
Adder
3.321
24728705AND G3
Adder
6.945
24728805RICHG1
Adder
3.364
24728905RICHG2
Adder
3.364
24729505KEY G4
Adder
6.029
247620Y3-023
Adder
0.426
247621Y3-024
Adder
0.22
247642Z2-115 C
Solar/Wind Harmer
0.003
23546401DTGZ2-030
Solar/Wind Helper
0.079
23585401KL_K28_T16
Solar/Wind Helper
1.286
23750701CROSSCHOOL
Solar/Wind Helper
1.305
23751201ROTHROCK
Solar/Wind Helper
0.726
25196708WSDLE6
Adder
7.715
25196808ZIMRHP
Adder
66.312
25306009OHH W.
Adder
2.688
25322209TAIT E
Adder
8.971
25322209TAIT E
Adder
9.177
25326109MON D
Adder
1.25
25326309TAIT D
Adder
1.031
270119AB2-067 GEN1
50/50
8.122
270120AB2-067 GEN2
50/50
8.122
274675JOLIET 29;7U
Adder
27.038
274675JOLIET 29;7U
Adder
26.073
274676JOLIET 29;8U
Adder
27.038
274676JOLIET 29;8U
Adder
26.073
274682WAUKEGAN ;7U
Adder
15.667
274682WAUKEGAN ;7U
Adder
15.667
274683WAUKEGAN ;8U
Adder
18.36
274683WAUKEGAN ;8U
Adder
15.477
274687WILL CNTY;4U
Adder
24.642
274687WILL CNTY;4U
Adder
24.642
274693ROCKY RD ;1P
Adder
9.616
274695ROCKY RD ;2P
Adder
9.711
274696ROCKY RD ;4P
Adder
9.94
274697ROCKY RD ;3P
Adder
2.638
274723RIVER EC ;12
Adder
15.96
274724RIVER EC ;11
Adder
15.773
274728ELWOOD EC;5P
Adder
14.48
274729ELWOOD EC;1P
Adder
14.48
274730ELWOOD EC;6P
Adder
14.48
274731ELWOOD EC;2P
Adder
14.48
274732ELWOOD EC;7P
Adder
14.48
274733ELWOOD EC;3P
Adder
14.48
274734ELWOOD EC;8P
Adder
14.48
274735ELWOOD EC;4P
Adder
14.48
274736ELWOOD EC;9P
Adder
14.48
274752CRETE EC ;2U
Adder
7.348
274753CRETE EC ;3U
Adder
7.348
274754CRETE EC ;4U
Adder
7.348
274771LINCOLN ;2U
Adder
7.511
274772LINCOLN ;3U
Adder
7.511
274773LINCOLN ;4U
Adder
7.511
274774LINCOLN ;5U
Adder
7.511
274775LINCOLN ;6U
Adder
7.511
274776LINCOLN ;7U
Adder
7.511
274777LINCOLN ;8U
Adder
7.511
274822ROCKFORD ;11
Adder
16.895
274823ROCKFORD ;21
Adder
12.596
274826FISK ;BP
Adder
9.691
274827FISK ;RP
Adder
6.868
274847GR RIDGE ;BU
Solar/Wind Harmer
0
274855GSG-6 ;RU
Solar/Wind Harmer
0.22
274861TOP CROP ;1U
Solar/Wind Harmer
0
274862TOP CROP ;2U
Solar/Wind Harmer
0.824
274871GR RIDGE ;2U
Solar/Wind Harmer
0
274879MINONK ;1U
Solar/Wind Harmer
0.253
274888KELLY CRK;1U
Solar/Wind Harmer
0.36
23562501BACKB
Solar/Wind Helper
0.891
25326509SID D
Adder
1.291
24318805MLG1
50/50
12.144
25196408WSDLE3
Adder
7.822
23777801MSM_W1-116
Solar/Wind Helper
0.099
23777901MDS_W4-102
Solar/Wind Helper
0.155
235020AA1-095 C
Solar/Wind Helper
0.046
24318905MLG2
50/50
8.017
25194408D.CRK1
Adder
6.694
25194508D.CRK3
Adder
1.252
25194608D.CRK4
Adder
1.455
25194608D.CRK4
Adder
1.455
25196008MFTGT1
Adder
1.208
25196008MFTGT1
Adder
1.17
25196108MFTGT2
Adder
1.236
25196108MFTGT2
Adder
1.331
25196208WSDLE1
Adder
7.735
25196308WSDLE2
Adder
7.754
25196508WSDLE4
Adder
7.521
25196608WSDLE5
Adder
7.599
274674JOLIET 9 ;6U
Adder
13.562
274674JOLIET 9 ;6U
Adder
13.562
274828WAUKEGAN ;BP
Adder
9.624
24379505HDWTR1G C
Solar/Wind Harmer
0
24385905FR-11G C
Solar/Wind Harmer
0
24386205FR-12G C
Solar/Wind Harmer
0
24386405FR-21G C
Solar/Wind Harmer
0
24386605FR-22G C
Solar/Wind Harmer
0
24387305FR-4G C
Solar/Wind Harmer
0
24695305TIMB G C
Solar/Wind Harmer
0.567
24699105WLD G1 C
Solar/Wind Harmer
0
24725505WLD G2 C
Solar/Wind Harmer
0
247607V1-011 GEN
Solar/Wind Harmer
0
247521TR3_G114
Solar/Wind Harmer
0.243
226910AB2-157 C
Solar/Wind Helper
0.013
237025AB1-124 C
Solar/Wind Helper
0.142
237030AB1-096 C
Solar/Wind Helper
0.058
237038AE2-054 C
Solar/Wind Helper
0.237
237048AF1-022 C
Solar/Wind Helper
0.157
252510AF1-249 C
Solar/Wind Harmer
0.047
270122AB2-093 CT
50/50
4.163
270201AC2-176 GEN
Solar/Wind Harmer
0
3141196NOKESVL
Solar/Wind Helper
0.912
316411AF1-147_GEN1
Solar/Wind Helper
0.785
316415AF1-147_GEN2
Solar/Wind Helper
0.785
25183208HLCRTG
Solar/Wind Harmer
0
23906502RICHG2&3
Adder
1.119
23906502RICHG2&3
Adder
1.119
23751101LEADS_P59
Solar/Wind Helper
1.931
235062AE1-101 C1
Solar/Wind Helper
1.442
274850MENDOTA H;RU
Solar/Wind Harmer
0.07
238185AF2-356 C
Solar/Wind Helper
2.305
237080AD1-060 GEN
Solar/Wind Helper
0.298
235067AD1-061 GEN
Solar/Wind Helper
0.388
237001AB1-127_GEN
Solar/Wind Helper
0.384
237002AB1-128_GEN
Solar/Wind Helper
0.385
238175AF1-290_GEN
Solar/Wind Helper
0.138
238221AF1-254 C O1
Solar/Wind Helper
0.239
238120AE2-309 GEN
Solar/Wind Helper
0.458
238169AE2-226 GEN1
Solar/Wind Helper
0.618
238170AE2-226 GEN2
Solar/Wind Helper
0.618
274872LEEDK;1U
Solar/Wind Harmer
0
926823AC1-168 GEN
Solar/Wind Harmer
1.023
276776AD2-060 GEN
Solar/Wind Harmer
0.659
276806AD2-047 C O1
Solar/Wind Harmer
3.499
276901AD2-066 C O1
Solar/Wind Harmer
0
276893AG1-478 C
Solar/Wind Harmer
0.41
238108AE1-109 GEN1
Solar/Wind Helper
0.099
238109AE1-109 GEN2
Solar/Wind Helper
0.099
238110AE1-109 GEN3
Solar/Wind Helper
0.099
237085AD2-009_GEN
Solar/Wind Helper
1.434
276897AD1-100 C
Solar/Wind Harmer
15.406
235054AD2-180 GEN
Solar/Wind Helper
1.764
237061AD1-155 GEN
Solar/Wind Helper
1.557
235531U2-073 GEN
Solar/Wind Helper
2.87
237006AB1-125 GEN
Solar/Wind Helper
0.107
23779801AA1-109
Solar/Wind Helper
0.168
23583801GRNGAP
Solar/Wind Helper
4.94
226929AD2-058 GEN
Solar/Wind Helper
0.087
253333AC1-068 GEN
Solar/Wind Harmer
0.008
253325AC1-069 GEN
Solar/Wind Harmer
0.008
270180AB1-006 GEN1
Solar/Wind Harmer
0
253394AE2-221_GEN
Solar/Wind Harmer
0
253398AE2-221_GEN2
Solar/Wind Harmer
0
252507AC2-088 GEN
Solar/Wind Harmer
0.275
252509AD1-136 GEN
Solar/Wind Harmer
0.031
252516AE2-318_GEN
Solar/Wind Harmer
6.92
252519AF1-045_GEN
Solar/Wind Harmer
3.223
276872AE1-163_GEN1
Solar/Wind Harmer
0
276876AE1-163_GEN2
Solar/Wind Harmer
0
276882AE2-255 GEN
Solar/Wind Harmer
0.708
276868AE1-113 GEN
Solar/Wind Harmer
1.213
253316AC1-085 GEN3
Solar/Wind Harmer
0
253317AC1-085 GEN4
Solar/Wind Harmer
0
274744AC1-111 GEN8
Adder
4.899
274745AC1-111 GEN9
Adder
4.899
274746AC1-111 G10
Adder
4.899
276861AD2-134 GEN
Solar/Wind Harmer
0.107
276863AD2-134 GEN
Solar/Wind Harmer
0.107
241955AC1-078 GEN
Solar/Wind Harmer
-0.001
270166AC1-044 GEN3
50/50
8.122
270302AB2-170 GEN
Solar/Wind Harmer
0
270317AD1-130_GEN
Solar/Wind Harmer
0
270263AC1-001 GEN
Solar/Wind Harmer
0.659
238127S14_GEN_2
Solar/Wind Helper
0.716
238126S14_GEN_1
Solar/Wind Helper
0.716
238117U2-030
Solar/Wind Helper
0.296
238118U2-030_1
Solar/Wind Helper
0.296
270209AC1-174_GEN
Solar/Wind Harmer
0
270291AC1-194 GEN
Solar/Wind Harmer
0
270428AC2-015 C
Solar/Wind Harmer
0
270435AC2-044 GEN
Solar/Wind Harmer
0.861
270489AE1-102 GEN1
Solar/Wind Harmer
0.884
246936BC-WTG1
Solar/Wind Harmer
0.274
246937BC-WTG2
Solar/Wind Harmer
0.274
246938BC-WTG3
Solar/Wind Harmer
0.245
270432AC2-029 GEN
Solar/Wind Harmer
3.082
270273AD2-016 GEN
Solar/Wind Harmer
0.693
270269AC2-059
Solar/Wind Harmer
0
241972AD1-140 GEN
Solar/Wind Harmer
0.749
270340AC2-060 GEN
Solar/Wind Harmer
0.001
270367AC2-061_GEN
Solar/Wind Harmer
0
270437AC2-090 C
Solar/Wind Harmer
0
241813AF1-122_GEN
Solar/Wind Harmer
3.228
241858AF1-205_GEN
Solar/Wind Harmer
2.535
270377AD1-106 GEN
Solar/Wind Harmer
2.656
270383AD1-128 GEN
Solar/Wind Harmer
0
270449AD2-020 GEN
Solar/Wind Harmer
0
276903AD2-071 C
Solar/Wind Harmer
6.96
276805AD2-038 GEN
Solar/Wind Harmer
0
270471AD2-092_GEN
Solar/Wind Harmer
0.001
270349AD2-093_GEN
Solar/Wind Harmer
0.001
270588AE1-091_GEN
Solar/Wind Harmer
5.409
270499AE1-146 GEN
Solar/Wind Harmer
0.022
270505AE1-170 C O1
Solar/Wind Harmer
6.751
270594AE1-207 GEN
Solar/Wind Harmer
7.026
270032AE2-172
Solar/Wind Harmer
4.182
270599AE1-208 GEN
Solar/Wind Harmer
5.805
270031AE2-169
Solar/Wind Harmer
3.483
270007AE1-245 C
Solar/Wind Harmer
0
270541AE2-072 C
Solar/Wind Harmer
0
270024AE2-089 GEN
Solar/Wind Harmer
0.001
270518AE2-148 GEN
Solar/Wind Harmer
0.581
270520AE2-214 GEN
Solar/Wind Harmer
0
270543AE2-219 C
Solar/Wind Harmer
4.436
270043AE2-236 GEN
Solar/Wind Harmer
4.212
270322AE2-290 GEN
Solar/Wind Harmer
6.558
270356AE2-297 GEN
Solar/Wind Harmer
0
270063AE2-323 C
Solar/Wind Harmer
0
270536AF1-215 GEN2
Solar/Wind Harmer
0
270535AF1-215 GEN1
Solar/Wind Harmer
0
270055AF2-134 C O1
Solar/Wind Harmer
0
270284AF1-227 GEN1
Solar/Wind Harmer
-0.001
270054AF2-122 C O1
Solar/Wind Harmer
0
270466AD2-091
50/50
6.112
270036AE2-216 BAT
50/50
6.723
270475AD2-096_GEN
50/50
6.627
270051AF1-062 GEN
50/50
11.187
270459AD2-067 GEN
Solar/Wind Harmer
0
270578AF1-285 GEN2
Solar/Wind Harmer
0.496
270391AF1-285 GEN3
Solar/Wind Harmer
0.496
270186AC1-089 GEN
Solar/Wind Harmer
0
270361_3
Solar/Wind Harmer
4.488
270575GUS2 35KV
Solar/Wind Harmer
4.488
253370AE2-315 SEC1
Adder
1.874
253370AE2-315 SEC1
Adder
1.874
253370AE2-315 SEC1
Adder
1.874
253371AE2-315 SEC2
Adder
1.772
253371AE2-315 SEC2
Adder
1.772
253372AE2-315 SEC3
Adder
1.772
253372AE2-315 SEC3
Adder
1.772
270526AF1-158 GEN
Solar/Wind Harmer
0
253406AD2-031_GEN
Solar/Wind Harmer
0.473
270462AD2-086
Solar/Wind Harmer
0
270071AF1-092 GEN
Solar/Wind Harmer
12.47
270004AE1-209 GEN
Solar/Wind Harmer
1.364
270005AE1-210 C O1
Solar/Wind Harmer
1.364
274751CRETE EC ;1U
Adder
7.348
274770LINCOLN ;1U
Adder
7.511
274863CRW1-WTG
Solar/Wind Harmer
0
274864CRW2-WTG
Solar/Wind Harmer
0
3138216PACIFIC
Solar/Wind Helper
0.039
316095T157 G97
Solar/Wind Helper
1.326
316097T157 G90
Solar/Wind Helper
1.326
926881AC1-175 GEN
Solar/Wind Harmer
0
943121AE2-341 GEN
Solar/Wind Harmer
10.254
945421AF1-207 GEN
Solar/Wind Harmer
0
946031AF1-268 GEN
Solar/Wind Harmer
5.999
946171AF1-282 GEN
Solar/Wind Harmer
6.309
946181AF1-283 GEN
Solar/Wind Harmer
8.202
946581AF1-322 GEN
Solar/Wind Harmer
-0.001
946671AF1-331 GEN
Solar/Wind Harmer
0.643
958481AF2-142 GEN
Solar/Wind Harmer
9.155
958491AF2-143 GEN
Solar/Wind Harmer
9.115
959081AF2-199 GEN
Solar/Wind Harmer
6.016
959091AF2-200 GEN
Solar/Wind Harmer
12.032
962581AG1-107 GEN
Solar/Wind Harmer
0.001
962691AG1-118 GEN
Solar/Wind Harmer
18.2
962781AG1-127 GEN
Solar/Wind Harmer
5.767
966841AG1-555 GEN
Solar/Wind Harmer
0.693
970169AG2-114 GEN
Solar/Wind Harmer
6.047
970241AG2-163 GEN
Solar/Wind Harmer
3.524
970289AG2-191 GEN
Solar/Wind Harmer
1.191
970289AG2-191 GEN
Solar/Wind Harmer
0.689
970291AG2-192 GEN
Solar/Wind Harmer
0.815
970291AG2-192 GEN
Solar/Wind Harmer
0.376
970569AG2-363 GEN
Solar/Wind Harmer
18.043
970571AG2-364 GEN
Solar/Wind Harmer
12.028
970613AG2-401 GEN
Solar/Wind Harmer
4.595
970773AG2-487 GEN
Solar/Wind Harmer
1.088
970781AG2-491 GEN
Solar/Wind Harmer
6.168
970825AG2-519 GEN
Solar/Wind Harmer
4.738
970825AG2-519 GEN
Solar/Wind Harmer
2.233
970879AG2-548 GEN
Solar/Wind Harmer
4.544
970879AG2-548 GEN
Solar/Wind Harmer
1.033
971067AG2-660 GEN
Solar/Wind Harmer
2.005
971073AG2-665 GEN
Solar/Wind Harmer
4.544
971073AG2-665 GEN
Solar/Wind Harmer
1.033
971171AH1-044 GEN
Solar/Wind Harmer
12.032
971341AH1-150 GEN
Solar/Wind Harmer
12.032
971343AH1-151 GEN
Solar/Wind Harmer
12.032
971411AH1-196 GEN
Solar/Wind Harmer
9.046
971613AH1-306 GEN
Solar/Wind Harmer
3.011
971675AH1-338 GEN
Solar/Wind Harmer
2.352
227287AC2-120 GEN
Solar/Wind Helper
0.303
270240V3-007_GEN2
Solar/Wind Harmer
0
939401AE1-172 GEN
Solar/Wind Harmer
4.563
957471AF2-041 GEN
Solar/Wind Harmer
18.048
963741AG1-226 GEN
Solar/Wind Harmer
14.298
963841AG1-237 GEN
Solar/Wind Harmer
2.634
964991AG1-363 GEN
Solar/Wind Helper
4.464
971997AH1-543 GEN
Solar/Wind Harmer
3.181
24639705ELKHART HY
Adder
0.142
247536S-71 GEN
Solar/Wind Harmer
0.254
270491AE1-102 GEN2
Solar/Wind Harmer
0.884
274887GEN-1.85
Solar/Wind Harmer
0.16
938701AE1-092 GEN
Solar/Wind Harmer
11.951
939351AE1-166 GEN
Solar/Wind Harmer
0
942081AE2-220 GEN
Solar/Wind Harmer
0
942221AE2-234 GEN
Solar/Wind Harmer
2.589
942861AE2-305 GEN
Solar/Wind Harmer
5.722
943021AE2-325 GEN
Solar/Wind Harmer
3.355
943591AF1-030 GEN
Solar/Wind Harmer
6.819
943851AF1-053 GEN
Solar/Wind Harmer
1.956
943861AF1-054 GEN
Solar/Wind Harmer
2.824
944231AF1-091 GEN
Solar/Wind Harmer
15.173
944531AF1-118 GEN
Solar/Wind Harmer
29.147
944541AF1-119 GEN
Solar/Wind Harmer
0.429
945111AF1-176 GEN
Solar/Wind Harmer
11.479
945111AF1-176 GEN
Solar/Wind Harmer
5.214
945371AF1-202 GEN
Solar/Wind Harmer
0
945411AF1-206 GEN
Solar/Wind Harmer
0
945581AF1-223 GEN
Solar/Wind Harmer
0
945631AF1-228 GEN
Solar/Wind Harmer
0.001
945641AF1-229 GEN
Solar/Wind Harmer
0.001
958861AF2-177 GEN
Solar/Wind Harmer
2.778
958961AF2-187 GEN
Solar/Wind Harmer
0
959141AF2-205 GEN
Solar/Wind Harmer
0
959331AF2-224 GEN
Solar/Wind Harmer
4.665
960591AF2-350 GEN
Solar/Wind Harmer
6.175
960681AF2-359 GEN
Solar/Wind Harmer
0
960841AF2-375 GEN
Solar/Wind Harmer
0
960971AF2-388 GEN
Solar/Wind Harmer
3.772
961051AF2-396 GEN
Solar/Wind Harmer
12.859
961051AF2-396 GEN
Solar/Wind Harmer
8.573
961821AG1-024 GEN
Solar/Wind Harmer
4.743
961921AG1-034 GEN
Solar/Wind Harmer
7.115
962031AG1-047 GEN
Solar/Wind Harmer
0
962761AG1-125 GEN
Solar/Wind Harmer
30.582
962771AG1-126 GEN
Solar/Wind Harmer
30.582
963791AG1-232 GEN
Solar/Wind Harmer
8.828
970031AG2-029 GEN
Solar/Wind Harmer
3.529
970065AG2-057 GEN
Solar/Wind Harmer
0.721
970073AG2-061 GEN
Solar/Wind Harmer
2.026
970109AG2-082 GEN
Solar/Wind Harmer
14.58
970149AG2-104 GEN
Solar/Wind Harmer
16.515
970153AG2-106 GEN
Solar/Wind Harmer
19.529
970155AG2-107 GEN
Solar/Wind Harmer
19.529
970179AG2-119 GEN
Solar/Wind Harmer
6.495
970191AG2-125 GEN
Solar/Wind Harmer
1.674
970329AG2-216 GEN
Solar/Wind Harmer
3
970349AG2-230 GEN
Solar/Wind Harmer
9.656
970373AG2-245 GEN
Solar/Wind Harmer
13.225
970621AG2-405 GEN
Solar/Wind Harmer
1.233
970623AG2-406 GEN
Solar/Wind Harmer
1.223
970707AG2-453 GEN
Solar/Wind Harmer
20.139
970833AG2-524 GEN
Solar/Wind Harmer
6.754
970833AG2-524 GEN
Solar/Wind Harmer
4.502
970883AG2-550 GEN
Solar/Wind Harmer
6.337
970885AG2-551 GEN
Solar/Wind Harmer
2.112
970941AG2-585 GEN
Solar/Wind Harmer
3.396
971029AG2-637 GEN
Solar/Wind Harmer
9.493
971199AH1-059 GEN
Solar/Wind Harmer
1.506
971201AH1-060 GEN
Solar/Wind Harmer
1.441
971347AH1-153 GEN
Solar/Wind Harmer
3.219
971549AH1-272 GEN
Solar/Wind Harmer
13.254
971567AH1-282 GEN
Solar/Wind Harmer
5.363
971605AH1-302 GEN
Solar/Wind Harmer
7.778
971609AH1-304 GEN
Solar/Wind Harmer
1.034
971611AH1-305 GEN
Solar/Wind Harmer
3.704
971653AH1-327 GEN
Solar/Wind Harmer
1.032
971655AH1-328 GEN
Solar/Wind Harmer
2.641
971771AH1-392 GEN
Solar/Wind Harmer
6.414
971917AH1-482 GEN
Solar/Wind Harmer
8.126
971995AH1-542 GEN
Solar/Wind Harmer
2.725
972037AH1-567 GEN1
Adder
0.162
972038AH1-567 GEN2
Adder
0.323
972063AH1-580 GEN
Solar/Wind Harmer
14.646
972159AH1-661 GEN
Adder
0.989
972227AH1-698 GEN1
Adder
2.307
972228AH1-698 GEN2
Adder
3.276
972239AH1-704 GEN
50/50
3.142
972253AH1-711 GEN
Adder
28.904
972259AH1-714 GEN
Adder
16.858
972269AH1-719 GEN
Adder
2.204
270246TR4_N_V150
Solar/Wind Harmer
0.043
270247TR4_N_V136
Solar/Wind Harmer
0.043
276843GEN-1.7
Solar/Wind Harmer
0.2
940581AE2-045 GEN
Solar/Wind Harmer
0
940611AE2-048 GEN
Solar/Wind Harmer
16.742
941391AE2-136 GEN
Solar/Wind Harmer
9.431
941551AE2-152 GEN
Solar/Wind Harmer
0
942051AE2-217 GEN
Solar/Wind Harmer
13.26
957201AF2-014 GEN
Solar/Wind Harmer
0
957741AF2-068 GEN
Solar/Wind Harmer
9.527
957841AF2-078 GEN
Solar/Wind Harmer
0
957891AF2-083 GEN
Solar/Wind Harmer
10.714
958011AF2-095 GEN
Solar/Wind Harmer
8.892
958321AF2-126 GEN
Solar/Wind Harmer
0.855
958381AF2-132 GEN
Solar/Wind Harmer
0.001
958391AF2-133 GEN
Solar/Wind Harmer
0.001
964401AG1-302 GEN
Solar/Wind Harmer
0.001
964611AG1-324 GEN
Solar/Wind Harmer
0.476
964611AG1-324 GEN
Solar/Wind Harmer
2.473
964861AG1-349 GEN
Solar/Wind Harmer
0.001
965011AG1-365 GEN
Solar/Wind Harmer
6.664
965021AG1-366 GEN
Solar/Wind Harmer
2.221
965041AG1-368 GEN
Solar/Wind Harmer
6.675
965051AG1-369 GEN
Solar/Wind Harmer
3.345
965421AG1-410 GEN
Solar/Wind Harmer
20.356
965651AG1-433 GEN
Solar/Wind Harmer
1.886
965681AG1-436 GEN
Solar/Wind Harmer
7.938
965791AG1-447 GEN
Solar/Wind Harmer
5.821
970159AG2-109 GEN
Solar/Wind Harmer
2.815
274811UNIV PK N;7U
Adder
4.45
274812UNIV PK N;8U
Adder
4.45
274814UNIV PK N;0U
Adder
4.489
276691AA1-018 GEN1
Solar/Wind Harmer
0.992
276694AA1-018 GEN2
Solar/Wind Harmer
0
238147AE2-230_GEN1
Solar/Wind Helper
0.439
238148AE2-230_GEN2
Solar/Wind Helper
0.439
238149AF1-291A_GEN
Solar/Wind Helper
0.125
238152AF2-075_GEN
Solar/Wind Helper
0.627
235063AE1-101 C2
Solar/Wind Helper
1.442
274805UNIV PK N;1U
Adder
4.46
274807UNIV PK N;3U
Adder
4.479
274808UNIV PK N;4U
Adder
4.43
274800UNIV PARK;3U
Adder
5.159
274801UNIV PARK;4U
Adder
5.159
274802UNIV PARK;5U
Adder
5.164
274803UNIV PARK;6U
Adder
5.164
CBM West 1LTFEXP_CBM-W1->PJM
CBM
124.933
CBM West 2LTFEXP_CBM-W2->PJM
CBM
91.648
CBM South 1LTFEXP_CBM-S1->PJM
CBM
22.848
CBM South 2LTFEXP_CBM-S2->PJM
CBM
4.294
NYPJM->LTFIMP_NY
CLTF
3.843
LGEELTFEXP_LGEE->PJM
CLTF
5.521
WECLTFEXP_WEC->PJM
CLTF
3.283
TVALTFEXP_TVA->PJM
CLTF
5.655
MECLTFEXP_MEC->PJM
CLTF
13.416
LAGNLTFEXP_LAGN->PJM
CLTF
11.693
SIGELTFEXP_SIGE->PJM
CLTF
0.416
AG2-052LTFEXP_AG2-052->PJM
LTF
0.207
AH1-155LTFEXP_AH1-155->PJM
LTF
0.31
CONTINGENCY 'AP_P1-3_MP-765-501T_SRT-A'
 DISCONNECT BRANCH FROM BUS 235102 TO BUS 242920 CKT 5   /*01BELMNT     500.0 - 05BELMON     765.0
 DISCONNECT BRANCH FROM BUS 242920 TO BUS 242516 CKT 1   /*05BELMON     765.0 - 05MOUNTN     765.0
 DISCONNECT BRANCH FROM BUS 242920 TO BUS 242925 CKT 1   /*05BELMON     765.0 - 05KAMMER     765.0
 DISCONNECT BUS 242920                                   /*05BELMON     765.0
END
235117 to 235111 ckt 1
242925 to 235117 ckt 1

Winter Peak Analysis

The New Service Request AG2-109 was evaluated as a 40.0 MW (28.1 MW Capacity) injection in the ATSI area.

AG2-109 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 40.0 MW (40.0 MW under study).

Note: The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for single or N-1 contingencies and multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.

The following flowgates remain after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)

Light Load Analysis

The New Service Request AG2-109 was evaluated as a 40.0 MW injection

AG2-109 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 40.0 MW (40.0 MW under study).

Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.

The following flowgates remain after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)

Short Circuit Analysis

Analysis Complete - No Issues

Based on PJM’s TC2 Phase II Short Circuit Analysis, this project did not contribute >1% fault duty to any previously identified overdutied breakers, nor did it cause any new overdutied breakers.

Please note that in TC2 Phase III, PJM will perform additional analysis including the evaluation of impacts from topology upgrades which may have potential effects on breaker duties not seen in the Phase II analysis.

Stability Analysis

Analysis Complete - No Issues

Executive Summary

The new Service Request (project) in PJM Transition Cycle 2, Cluster 50 is listed in Table 1 below. This report will cover the dynamic analysis of the Cluster 50 project.

This analysis is effectively a screening study to determine whether the addition of the Cluster 50 project will meet the dynamics requirements of the NERC, FirstEnergy (FE), and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2028 summer peak load case, modified to include applicable projects. The Cluster 50 project is set at maximum power output, with approximately unity power factor at the high side of the station transformer, 1.00 pu voltage at the generator terminal, and 1.02 pu voltage at the POI bus

The Cluster 50 project was tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 38 contingencies were studied, each with a 20 second simulation time period (with 1.0 second initial run prior to any events). Studied faults included:

  1. Steady-state operation (Category P0);
  2. Three-phase faults with normal clearing time (Category P1);
  3. Single-phase faults with stuck breaker (Category P4);
  4. Single phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure (Category P5).

No common tower contingencies were identified for this study.

High Speed Reclosing (HSR) facilities were not found in the vicinity of the TC2 Cluster 50 project. For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all fault contingencies tested on the 2028 peak load case:

  1. The Cluster 50 project was able to ride through the faults (except for faults where protective action trips a generator(s)),
  2. The system with the Cluster 50 project included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
  3. Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
  4. No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

No mitigation was required for TC2 Cluster 50.

 

 

Table 1: TC2 Cluster 50 Projects

 

 

 

 

 

 

 

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

50

AG2-109

Solar

FirstEnergy (FE) transmission system, American Transmission Systems, Incorporated (ATSI) zone

40 MW

40 MW

28.1 MW

Fitchville-New London 69 kV

 

Reactive Power Analysis

The reactive power capability of AG2-109 meets the 0.95 leading and lagging PF requirement at the high side of the main transformer.

Steady-State Voltage Analysis

Not Required

A steady state voltage analysis is evaluated on a project-by-project basis and depends on specific project parameters. For this project, a steady state voltage analysis is not required per PJM's Manual 14H, Section 4.5.2.

New Service Request Dependencies

The New Service Requests below are listed in one or more dispatch for the overloads identified in this report. These projects contribute to the loading of the overloaded facilities identified in this report. The percent overload of a facility and cost allocation you may have towards a particular reinforcement could vary depending on the action of other projects. The status of each project at the time of the analysis is presented in the table. This list may change as other projects withdraw or modify their requests. This table is valid for load flow analyses only.

New Service Requests Dependencies
Project IDProject NameStatus
AB2-170East Lima-Marysville 345kVIn Service
AC1-167Platter Creek 69kVUnder Construction
AC2-015Chatfield-Howard 138kVPartially in Service - Under Construction
AC2-044Maddox Creek 345kVSuspended
AC2-103Beaver-Davis Besse 345 kV IEngineering & Procurement
AC2-168Clinton 23kVIn Service
AC2-195Galion-Roberts South 138 kVPartially in Service - Under Construction
AD1-101Continental 69 kVIn Service
AD1-106North Waldo-Wild Creek 138 kVWithdrawn
AD1-119Payne 69 kVIn Service
AD1-130Hardin Switch 345 kVIn Service
AD2-020Valley 138 kVEngineering & Procurement
AD2-079Capitol Ave 34.5kVIn Service
AD2-086Hardin Switch 345 kVIn Service
AD2-133Eagle Valley 115kVIn Service
AE1-079Maysville-Sharon 69 kVUnder Construction
AE1-090Hardin Switch 345 kVIn Service
AE1-091West Newton-Lynn 138 kVSuspended
AE1-102Maddox Creek 345 kVSuspended
AE1-146Ebersole #2-Fostoria Central 138 kVUnder Construction
AE1-170Kenzie Creek-Colby 138 kVSuspended
AE1-183Maysville-McDowell 69 kVUnder Construction
AE1-237Andover (Maysville) 69kV IUnder Construction
AE1-245Haviland 138 kVPartially in Service - Under Construction
AE2-072East Leipsic-Richland 138 kVIn Service
AE2-074Potter 46 kVUnder Construction
AE2-113Farmers Valley-Ridgeway 115 kVUnder Construction
AE2-114Midland 23 kV IIn Service
AE2-115Midland 23 kV IIIn Service
AE2-126Dubois-Curwensville 34.5 kVIn Service
AE2-129Philipsburg-Clarence 34.5 kVIn Service
AE2-131Philipsburg-Karthaus 34.5Under Construction
AE2-176Groton 138 kV SolarIn Service
AE2-181Snyder 69kVIn Service
AE2-234Liberty Center-Buckeye Tap 69 kVEngineering & Procurement
AE2-236Columbia-Northeast 138 kVSuspended
AE2-282East Fayette 138 kVIn Service
AE2-285Maysville 69 kVUnder Construction
AE2-298Cavett Switch - West Van Wert 69 kVWithdrawn
AE2-306Gunn Road 345 kVUnder Construction
AE2-322Platter Creek 69kVUnder Construction
AE2-323Twin Branch-Guardian 138 kVPartially in Service - Under Construction
AE2-325Valley 138 kVWithdrawn
AE2-343Andover (Maysville) 69 kV IIUnder Construction
AF1-006Fairview East 34.5 kVIn Service
AF1-064Weston 69 kVUnder Construction
AF1-084Hartford-Almena 69 kVUnder Construction
AF1-086Madera-Westover South 115 kVPartially in Service - Under Construction
AF1-091Varner - Sowers 138 kVEngineering & Procurement
AF1-092Huntington Jct. 138 kVWithdrawn
AF1-093Henderson-Stoneboro 69 kVUnder Construction
AF1-094Union City-Cambridge Springs 34.5 kVEngineering & Procurement
AF1-098Four Mile Jct-Corry East 115 kVSuspended
AF1-120East Fayette 2 138 kVIn Service
AF1-122Cardington-Liberty 69 kVSuspended
AF1-134Philipsburg-Madera 34.5 kVUnder Construction
AF1-158Edison-Gravel Pit 138 kVIn Service
AF1-176Corey 138 kVEngineering & Procurement
AF1-205Napoleon Muni 138 kVSuspended
AF1-206East Fayette 138 kVEngineering & Procurement
AF1-215Olive-Reynolds 345 kVIn Service
AF1-229Galion-South Berwick 345 kVUnder Construction
AF1-272Lucerne 115 kVEngineering & Procurement
AF1-285Gunn Road 345 kVUnder Construction
AF1-302Brookville-Squab Hollow 138 kVUnder Construction
AF2-004Beaver 345 kVEngineering & Procurement
AF2-005Beaver 138 kVEngineering & Procurement
AF2-014Maddox Creek 345 kVUnder Construction
AF2-039Shawville-Clearfield 34.5 kVUnder Construction
AF2-083Kenzie Creek-Stone Lake 69 kVUnder Construction
AF2-088Shawville-Clearfield 34.5 kV IIUnder Construction
AF2-103Haviland 138 kVIn Service
AF2-126Weston 69 kV IIUnder Construction
AF2-130Cobalt Corners 34.5 kVIn Service
AF2-134Olive-Reynolds #2 345 kVIn Service
AF2-150Galion 138 kVUnder Construction
AF2-224Allen 345 kVEngineering & Procurement
AF2-359Olive-University Park 345 kVEngineering & Procurement
AF2-375Ebersole-Fostoria 138 kVEngineering & Procurement
AF2-396Stinger 138 kVEngineering & Procurement
AG1-039Galion 138 kV IIUnder Construction
AG1-040Morgan Street-Mount Hope 34.5 kVEngineering & Procurement
AG1-054Potter-Harlan 69 kVEngineering & Procurement
AG1-100Venango-Saegertown 34.5 kVEngineering & Procurement
AG1-198Union City 34.5 kVIn Service
AG1-232Magley 138 kVEngineering & Procurement
AG1-365Allen 345 kVEngineering & Procurement
AG1-366Allen 345 kVEngineering & Procurement
AG1-368Tillman 138 kVEngineering & Procurement
AG1-369Logtown 138 kVEngineering & Procurement
AG1-386Smith-Francis Junction 25 kVIn Service
AG1-410Maddox Creek-RP Mone 345 kVEngineering & Procurement
AG1-436Olive-University Park 345 kVEngineering & Procurement
AG1-447Olive-University Park 345 kVEngineering & Procurement
AG1-500Beaver 345 kVEngineering & Procurement
AG1-501Beaver 138 kVEngineering & Procurement
AG1-554South Kenton 138 kVEngineering & Procurement
AG2-029Forest G. Hipple-Dunton Lake 345 kVActive
AG2-057Cardington-Liberty 69 kV IIActive
AG2-119Galion-Roberts South 138 kV IIActive
AG2-230Dumont 345 kVActive
AG2-245Olive - Reynolds #1 345 kVActive
AH1-060Cardington-Liberty 69 kV IIIActive
AH1-153Dumont 345 kVActive
AH1-272Argenta - Twin Branch 345 kVActive
AH1-282Galion - Ohio Central 345 kVActive
AH1-392Gravel Pit-Kankakee 138 kVActive
AH1-711Lemoyne 345 kVActive
U2-072East Lima-Marysville 345kVIn Service
V1-011Haviland 138kVIn Service
W1-056Ada-Dunkirk 69kVIn Service
Y3-023Country Side 12kVIn Service
Z2-116Twin Branch 12.47kVIn Service

Affected System - PJM Identified Violations

As part of PJM's analysis, per Tariff Part VII.G.336 & Manual 14H, Section 13, PJM evaluated the potential impacts on tie line facilities between PJM and an affected system entity, which were identified per PJM planning analysis criteria. This upgrade may be required on the affected system portion of the tie line along with cost allocation of such upgrade if applicable, in coordination with the affected system. Depending on the affected system, this project may not be contingent on upgrade based on PJM planning analysis criteria, but may be contingent on this upgrade based on the Affected System Operator's planning criteria, provided in the Affected Systems Study Section, herein.

Midcontinent Independent System Operator, Inc. (MISO)No Impact
New York Independent System Operator (NYISO)No Impact
Tennessee Valley Authority (TVA)No Impact
Louisville Gas & Electric (LG&E)No Impact
Duke Energy Carolinas (DUKE)No Impact
Duke Energy Progress – East (CPLE)No Impact
Duke Energy Progress – West (CPLW)No Impact

Affected System - Non-PJM Identified Violations

In accordance with PJM Tariff Part VII, Subpart D, section 310.A and as outlined in PJM Manual 14H, Sections 4.5 and 13, in Phase II of the Cycle, PJM provides the Affected System Operator any updates on the PJM projects that require an Affected Systems Study based on their response at DP1. New Service Requests that require an Affected Systems Study are required to enter into an Affected Systems Study Agreement with the Affected System Operator, as applicable, prior to the close of DP2 or they will be withdrawn from the Cycle.

If the Project Developer already entered into the necessary agreement and the results are available, PJM will supply them in the Phase II SIS report. See below for the status of any required Affected Systems Study. A status of “Pending” means that the study is not yet completed by the Affected System Operator. If your project requires an Affected Systems Study and your results are not provided for Phase II SIS, PJM anticipates providing them in the Phase III SIS per Tariff Part VII.D.312.

Midcontinent Independent System Operator, Inc. (MISO)Not required
New York Independent System Operator (NYISO)Not required
Tennessee Valley Authority (TVA)Not required
Louisville Gas & Electric (LG&E)Not required
Duke Energy Carolinas (DUKE)Not required
Duke Energy Progress – East (CPLE)Not required
Duke Energy Progress – West (CPLW)Not required

System Reinforcements

No cost allocated system reinforcements were identified for this project in the Phase II System Impact Study load flow analysis.

Shown below are the details of the cost allocated, contingent, eliminated, topology and potential aggregate contributor reinforcements for this project. Please refer to the System Reinforcement table above and the information below for more detail.


System Reinforcement: b4000.11
Type
Load Flow
TO
APS
RTEP ID / TO ID
b4000.11
Title
Expand Black Oak Substation & Loop in the 502 Jct-Woodside 500 kV line (Projected ISD 6/1/2029)
Description
Expand Black Oak Substation to accommodate the connection of the 502 Jct-Woodside 500 kV line and loop the 502 Jct-Woodside 500 kV line into the Black Oak substation by constructing ~0.85 miles of new 500 kV line into and out of Black Oak 500 kV substation
Cost Information
Time Estimate
Jun 01 2029

Not ContingentTopology Changing

Note 1: AG2-109 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-109 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.

FacilityContingency
01 502 J-01KAMMER 500.0 kV Ckt 1 line(Any)
No new ratings for this Flowgate.
01KAMMER-05KAMMER 500.0/765.0 kV Ckt 1 transformer(Any)
No new ratings for this Flowgate.
02BEAVER-02LAKEAVE 345.0 kV Ckt 2 line(Any)
No new ratings for this Flowgate.

System Reinforcement: b4000.1
Type
Load Flow
TO
AEP
RTEP ID / TO ID
b4000.1
Title
Add two 765 kV breakers at Amos Substation to expand the breaker and a half scheme to accommodate the new Amos-Welton Spring 765 kV line (Projected ISD 6/1/2029)
Description
765kV Solution: 2024 W1 Solution - Regional Cluster Ties Doubs 500kV area to John Amos 765kV via a new 765kV line
Cost Information
Time Estimate
Jun 01 2029

Not ContingentTopology Changing

Note 1: AG2-109 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-109 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.

FacilityContingency
01 502 J-01KAMMER 500.0 kV Ckt 1 line(Any)
No new ratings for this Flowgate.
01KAMMER-05KAMMER 500.0/765.0 kV Ckt 1 transformer(Any)
No new ratings for this Flowgate.
02BEAVER-02LAKEAVE 345.0 kV Ckt 2 line(Any)
No new ratings for this Flowgate.

System Reinforcement: b4000.2
Type
Load Flow
TO
APS
RTEP ID / TO ID
b4000.2
Title
Construct a new 175 miles Amos to Welton Spring 765 kV line - AEP Section of the line is 30 miles (Projected ISD 6/1/2029)
Description
765kV Solution: 2024 W1 Solution - Regional Cluster Ties Doubs 500kV area to John Amos 765kV via a new 765kV line
Cost Information
Time Estimate
Jun 01 2029

Not ContingentTopology Changing

Note 1: AG2-109 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-109 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.

FacilityContingency
01 502 J-01KAMMER 500.0 kV Ckt 1 line(Any)
No new ratings for this Flowgate.
01KAMMER-05KAMMER 500.0/765.0 kV Ckt 1 transformer(Any)
No new ratings for this Flowgate.
02BEAVER-02LAKEAVE 345.0 kV Ckt 2 line(Any)
No new ratings for this Flowgate.

System Reinforcement: b4000.3
Type
Load Flow
TO
APS
RTEP ID / TO ID
b4000.3
Title
Construct a new 175 miles Amos to Welton Spring 765 kV line - APS/FE Section of the line is 145 miles (Projected ISD 6/1/2029)
Description
765kV Solution: 2024 W1 Solution - Regional Cluster Ties Doubs 500kV area to John Amos 765kV via a new 765kV line
Cost Information
Time Estimate
Jun 01 2029

Not ContingentTopology Changing

Note 1: AG2-109 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-109 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.

FacilityContingency
01 502 J-01KAMMER 500.0 kV Ckt 1 line(Any)
No new ratings for this Flowgate.
01KAMMER-05KAMMER 500.0/765.0 kV Ckt 1 transformer(Any)
No new ratings for this Flowgate.
02BEAVER-02LAKEAVE 345.0 kV Ckt 2 line(Any)
No new ratings for this Flowgate.

System Reinforcement: b4000.4
Type
Load Flow
TO
APS
RTEP ID / TO ID
b4000.4
Title
Construct a new 765 kV switchyard - Welton Spring (Projected ISD 6/1/2029)
Description
765kV Solution: 2024 W1 Solution - Regional Cluster Ties Doubs 500kV area to John Amos 765kV via a new 765kV line
Cost Information
Time Estimate
Jun 01 2029

Not ContingentTopology Changing

Note 1: AG2-109 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-109 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.

FacilityContingency
01 502 J-01KAMMER 500.0 kV Ckt 1 line(Any)
No new ratings for this Flowgate.
01KAMMER-05KAMMER 500.0/765.0 kV Ckt 1 transformer(Any)
No new ratings for this Flowgate.
02BEAVER-02LAKEAVE 345.0 kV Ckt 2 line(Any)
No new ratings for this Flowgate.

System Reinforcement: b4000.5
Type
Load Flow
TO
APS
RTEP ID / TO ID
b4000.5
Title
Install four 250 MVAR shunt capacitors, and a +/-500 MVAR STATCOM at Welton Spring 765 kV substation
Description
765kV Solution: 2024 W1 Solution - Regional Cluster Ties Doubs 500kV area to John Amos 765kV via a new 765kV line
Cost Information
Time Estimate
Jun 01 2029

Not ContingentTopology Changing

Note 1: AG2-109 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-109 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.

FacilityContingency
01 502 J-01KAMMER 500.0 kV Ckt 1 line(Any)
No new ratings for this Flowgate.
01KAMMER-05KAMMER 500.0/765.0 kV Ckt 1 transformer(Any)
No new ratings for this Flowgate.
02BEAVER-02LAKEAVE 345.0 kV Ckt 2 line(Any)
No new ratings for this Flowgate.

System Reinforcement: b4000.6
Type
Load Flow
TO
APS
RTEP ID / TO ID
b4000.6
Title
Construct a new 86 miles Welton Spring to Rocky Point 765 kV line (Welton Spring to DVP local area, roughly 21 miles) (VA Portion)
Description
765kV Solution: 2024 W1 Solution - Regional Cluster Ties Doubs 500kV area to John Amos 765kV via a new 765kV line
Cost Information
Time Estimate
Jun 01 2029

Not ContingentTopology Changing

Note 1: AG2-109 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-109 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.

FacilityContingency
01 502 J-01KAMMER 500.0 kV Ckt 1 line(Any)
No new ratings for this Flowgate.
01KAMMER-05KAMMER 500.0/765.0 kV Ckt 1 transformer(Any)
No new ratings for this Flowgate.
02BEAVER-02LAKEAVE 345.0 kV Ckt 2 line(Any)
No new ratings for this Flowgate.

System Reinforcement: b4000.7
Type
Load Flow
TO
APS
RTEP ID / TO ID
b4000.7
Title
Construct a new 86 miles Welton Spring to Rocky Point 765 kV line - in DVP local area/Millville to Lovettsville section, roughly 10.5 miles (Projected ISD 6/1/2029)
Description
765kV Solution: 2024 W1 Solution - Regional Cluster Ties Doubs 500kV area to John Amos 765kV via a new 765kV line
Cost Information
Time Estimate
Jun 01 2029

Not ContingentTopology Changing

Note 1: AG2-109 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-109 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.

FacilityContingency
01 502 J-01KAMMER 500.0 kV Ckt 1 line(Any)
No new ratings for this Flowgate.
01KAMMER-05KAMMER 500.0/765.0 kV Ckt 1 transformer(Any)
No new ratings for this Flowgate.
02BEAVER-02LAKEAVE 345.0 kV Ckt 2 line(Any)
No new ratings for this Flowgate.

System Reinforcement: b4000.8
Type
Load Flow
TO
APS
RTEP ID / TO ID
b4000.8
Title
Construct a new 86 miles Welton Spring to Rocky Point 765 kV line (DVP local area to Rocky Point, roughly 4.8 miles)
Description
765kV Solution: 2024 W1 Solution - Regional Cluster Ties Doubs 500kV area to John Amos 765kV via a new 765kV line
Cost Information
Time Estimate
Jun 01 2029

Not ContingentTopology Changing

Note 1: AG2-109 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-109 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.

FacilityContingency
01 502 J-01KAMMER 500.0 kV Ckt 1 line(Any)
No new ratings for this Flowgate.
01KAMMER-05KAMMER 500.0/765.0 kV Ckt 1 transformer(Any)
No new ratings for this Flowgate.
02BEAVER-02LAKEAVE 345.0 kV Ckt 2 line(Any)
No new ratings for this Flowgate.

System Reinforcement: b4000.9
Type
Load Flow
TO
APS
RTEP ID / TO ID
b4000.9
Title
Construct a new substation called Rocky Point with a 765 kV and a 500 kV yard (Projected ISD 6/1/2029)
Description
Construct a new substation called Rocky Point with a 765 kV and a 500 kV yard. Loop in the Doubs-Goose Creek 500 kV line, the Doubs-Aspen 500 kV line, and the Woodside-Goose Creek 500 kV line. Install two 765/500 kV transformer at Rocky Point substation. 765kV Solution: 2024 W1 Solution - Regional Cluster Ties Doubs 500kV area to John Amos 765kV via a new 765kV line
Cost Information
Time Estimate
Jun 01 2029

Not ContingentTopology Changing

Note 1: AG2-109 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-109 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.

FacilityContingency
01 502 J-01KAMMER 500.0 kV Ckt 1 line(Any)
No new ratings for this Flowgate.
01KAMMER-05KAMMER 500.0/765.0 kV Ckt 1 transformer(Any)
No new ratings for this Flowgate.
02BEAVER-02LAKEAVE 345.0 kV Ckt 2 line(Any)
No new ratings for this Flowgate.

System Reinforcement: b4000.10
Type
Load Flow
TO
APS
RTEP ID / TO ID
b4000.10
Title
Install four 250 MVAR cap banks (two on 765 and two on 500 kV side) and a +/-500 MVAR STATCOM on the 765 kV Rocky Point yard
Description
765kV Solution: 2024 W1 Solution - Regional Cluster Ties Doubs 500kV area to John Amos 765kV via a new 765kV line
Cost Information
Time Estimate
Jun 01 2029

Not ContingentTopology Changing

Note 1: AG2-109 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-109 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.

FacilityContingency
01 502 J-01KAMMER 500.0 kV Ckt 1 line(Any)
No new ratings for this Flowgate.
01KAMMER-05KAMMER 500.0/765.0 kV Ckt 1 transformer(Any)
No new ratings for this Flowgate.
02BEAVER-02LAKEAVE 345.0 kV Ckt 2 line(Any)
No new ratings for this Flowgate.

System Reinforcement: b4068.1
Type
Load Flow
TO
AEP
RTEP ID / TO ID
b4068.1 / AEP-TC2-18693
Title
b4068: Greentown 765 kV - Teddy 765kV - Marysville 765 kV - Greenfield Line - AEP Proposal 570
Description
b4068.1 through b4068.49: Affected Transmission Owners: AEP / Dayton / ATSI The objective of this project is to construct multiple transmission lines to address Ohio area violations. The total distance covered by the lines is approximately 359.54 miles. The first transmission line ranges from the existing Greentown Substation in Howard County, Indiana to the new Teddy Substation in Clark County, Ohio, the line then branches north towards the existing Marysville Substation in Union County, Ohio, and east to the existing Beatty Substation in Franklin County, Ohio, and then extends to the existing Cole Substation in Franklin County, Ohio. The second transmission line extends from the existing Adkins Substation in Pickaway County, Ohio, to the new West Millersport Substation in Fairfield County, Ohio, then continues to the existing Conesville Substation in Coshocton County, Ohio before finally extending to the existing Guernsey Substation in Guernsey County, Ohio. There is a total of five transmission lines that extend between unnamed substations (Hayden - Cole 345 kV, Hyatt - Maliszewski 345 kV [double circuit], Roberts - Kenny 138 kV, Wilson - 5th Avenue 138 kV, West Millersport-Kirk 345 kV). This project will traverse 4 counties (Howard, Grant, Blackford, Jay) in Indiana, and 13 counties (Darke, Shelby, Champaign, Clark, Madison, Franklin, Delaware, Pickaway, Fairfield, Licking, Muskingum, Coshocton, Guernsey) in Ohio. This proposal has a total of 38 components, including 16 substation upgrade components, two greenfield substation components, eight greenfield transmission line components covering approximately 336.2 miles, and 12 transmission line upgrade components covering approximately 23.34 miles. b4068.28/b4068.49 is dependent on b3919.1 Baseline completion.
Cost Information
Time Estimate
Jun 01 2030

Not ContingentTopology Changing

Note 1: AG2-109 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-109 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.

FacilityContingency
02BEAVER-02LAKEAVE 345.0 kV Ckt 2 line(Any)
No new ratings for this Flowgate.

System Reinforcement: b3919.1
Type
Load Flow
TO
AEP
RTEP ID / TO ID
b3919.1
Title
Reconfigure Maliszewski 765 kV station and establish 345 kV breaker yard
Description
Reconfigure Maliszewski 765 kV station from 2 breakers to a 6 breaker ring bus. Install a new 765/345 kV transformer. Establish new 345 kV breaker yard with 3 string breaker and a half to include a line exit to Hyatt and a line exit to Corridor. Loop the existing Hyatt - West Millersport 345 kV line into the new established 345 kV yard at the Maliszewski station.
Cost Information
Time Estimate
Jun 01 2029

Not ContingentTopology Changing

Note 1: AG2-109 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-109 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.

FacilityContingency
02BEAVER-02LAKEAVE 345.0 kV Ckt 2 line(Any)
No new ratings for this Flowgate.

System Reinforcement: n9227.0
Type
Load Flow
TO
ATSI
RTEP ID / TO ID
n9227.0 / TC1-ATSI-001.b
Title
Beaver-Lake Ave Ckt #2 345kV: Upgrade T-line drops, overhead substation conductor and TL reconductor
Description
Reconductor (possible rebuild) of 8.12 miles of dual transmission line and (2) single conductor line drops at Beaver on the Beaver-Lake Ave Ckt #2 345 kV line using triple (3) 1113 54/19 ""Finch"" ACSS"
Total Cost ($USD)
$48,873,856
Discounted Total Cost ($USD)
$48,873,856
Allocated Cost ($USD)
$0
Time Estimate
37 Months

Potential Aggregate Contributor

Note: Based on PJM cost allocation criteria, AG2-109 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AG2-109 could receive cost allocation. Although AG2-109 may not presently have cost responsibility for this upgrade, AG2-109 is a potential Aggregate Pool Contributor.

FacilityContingency
02BEAVER-02LAKEAVE 345.0 kV Ckt 2 line(Any)
Rating SetRating TypeRating Value
(All)A1868.0 MVA
(All)B2249.0 MVA
(All)C2375.0 MVA

Conversion from Impacts into Topology or Eliminated Reinforcements into Region Topology Contingent Reinforcements for AG2-109


AG2-109 Contributions into Topology or Eliminated Reinforcements:
TypeTORTEP ID / TO IDTitleTopo or ElimMW ImpactPercent AllocationCategoryAllocated Cost ($USD)
Contributions into Topology or Eliminated Reinforcement Total:$0
AG2-109 Contingent Region Topology Upgrades:
TORTEP IDTitleCategoryAllocated Cost ($USD)
Region Topology Upgrade Total:$0

Attachments

AG2-109 One Line Diagram

AG2-109 One Line Diagram.pdf
The state in which the generator or merchant transmission facility is located.
The Transmission Owner of the facility where the New Service Request project interconnects to the transmission system.
Winter load flow analysis will be performed starting in Transition Cycle 2.