AG2-329 Phase II System Impact Study Report

v1.00 released 2026-06-03 18:45

S Berwick - Galion 345 kV

156.0 MW Capacity / 200.0 MW Energy

Introduction

This Phase II System Impact Study (SIS) Report has been prepared in accordance with the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 310 for New Service Requests (projects) in Transition Cycle 2 (TC2). The Project Developer/Eligible Customer (developer) is Wombat Solar LLC, and the Transmission Provider (TP) is PJM Interconnection, LLC (PJM). The interconnected Transmission Owner (TO) is AEP Indiana Michigan Transmission Company, Inc..

Preface

The Phase II System Impact Study is conducted on an aggregate basis within a New Services Request’s Cycle, and results are provided in both (i) a single Cycle summary format and (ii) an individual project-level basis. The Phase II System Impact Study Results (for both the summary and individual reports) will be publicly available on PJM’s website. Project Developers must obtain the results from the website.

In accordance with PJM Manual 14H, section 4.5, PJM takes the following actions during the Phase II System Impact Study:

  1. PJM will retool load flow results from the Phase I System Impact Study (summer peak, winter peak and light load) based on decisions made by Project Developers or Eligible Customers during Decision Point I.
  2. PJM will conduct any required voltage analyses.
  3. PJM will perform short circuit and stability analyses as required.
  4. PJM will coordinate with the Affected System to confirm which projects in the PJM Cycle will require Affected System studies. If the Affected System Operator indicates that an Affected System study is required, PJM will:
    1. Notify the Project Developer or Eligible Customer of the need for an Affected System study and the requirement to execute an Affected System study agreement with the impacted Affected System Operator, and;
    2. Include the results of the Affected System Operator’s Affected System Study in the Phase II System Impact Study results, if applicable and available.
  5. The Phase II System Impact Study Results will be publicly available on PJM’s website. Project Developers and Eligible Customers must obtain the results from the website.

The Transmission Owner takes the following actions during the Phase II System Impact Study:

  1. Verify Interconnection Facilities and Network Upgrades required to accommodate the New Service Request.
  2. Perform a Facilities Study. The Facilities Study in Phase II System Impact Study phase will be for the physical Interconnection Facilities. The Facilities Study requirements are outlined in Attachment C of this manual. The study will be conducted pursuant to Tariff, Part VII, Subpart D, section 307(A)(7) and Tariff, Part VIII, Subpart C, section 404(A)(7).

Decision Point II Requirements

At the close of Phase II System Impact Study, PJM will initiate Decision Point II (DP2). During DP2, the Project Developer will have 30 days to decide whether to proceed with their project. If the Project Developer elects to proceed, they should provide the elements defined in the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 311.A. Additional information on these elements is available in PJM Manual 14H sections 4.6, 6, and 7.

Allowable project modifications at Decision Point II are defined in PJM Open Access Transmission Tariff, Part VII, Subpart D, section 311.B. Additional information regarding allowable project modifications can be found in PJM Manual 14H, section 9.8.

Adverse Test Eligibility

This New Service Request meets the Adverse Study Impact Criteria and has the option to either move forward in the Cycle process or withdraw at DP2 with Readiness Deposits refunded. See Readiness Deposit calculation below.

This section details whether a Project Developer or Eligible Customer qualifies for the Adverse Study Impact clause outlined in the PJM OATT, Part VII, Subpart D, section 311.B and Manual 14H, section 6.2.2. In order to qualify for an Adverse Study Impact at Decision Point II, the Network Upgrade cost from Phase I to Phase II must:

  1. Increase overall by 25% or more
  2. Increases by more than $10,000 per MW (Includes Costs identified in Affected System studies)

If a New Service Request meets the criteria above and chooses to withdraw the request, PJM will refund the cumulative Readiness Deposit amounts paid at the Application Phase and at Decision Point I (RD1 and RD2, respectively).

The below calculations show the computation of this New Service Request's Adverse Study Impact

DP2 Adverse Eligibility = DP2 Adverse Cost Alloc DP1 Adverse Cost Alloc > 1.25 AND ( DP2 Adverse Cost Alloc - DP1 Adverse Cost Alloc ) Project Size > $10,000 per MW
DP2 Adverse Eligibility = $28,131,860 $12,526,069 = 2.25 AND ( $28,131,860 - $12,526,069 ) 200.0 = $78,029 per MW

General

The Project Developer has proposed a Storage facility located in the AEP Indiana Michigan Transmission Company, Inc. zone — Wyandot County, Ohio. The installed facilities will have a total capability of 200.0 MW with 156.0 MW of this output being recognized by PJM as Capacity.

Project Information
New Service Request Number:
AG2-329
Project Name:
S Berwick - Galion 345 kV
Project Developer Name:
Wombat Solar LLC
State:
Ohio
County:
Wyandot
Transmission Owner:
AEP Indiana Michigan Transmission Company, Inc.
MFO:
200.0
MWE:
200.0
MWC:
156.0
Battery Storage Specification:
2000.0 MWh, 10.0-hr class
Grid Charging:
Yes
Fuel Type:
Storage
Basecase Study Year:
2028

Physical Interconnection Facility Study

Report Available

The transmission owner has completed the Physical Interconnection Facilities Study. This report is available for download.

Point of Interconnection

AG2-329 will interconnect on the American Electric Power  transmission system by tapping the South Berwick - Galion 345 kV Line.

Cost Summary

The table below shows a summary of the total cost estimates for this New Service Request project. In Phase II SIS, the interconnected Transmission Owner has performed a facilities study for both the Transmission Owner Interconnection Facilities (TOIF) and Physical Interconnection Network Upgrades. The System Reliability Network Upgrade shown in the table are planning level cost estimates which are subject to change as a result of a facility study performed by the TO during Phase III System Impact Study.

Based on the Phase II SIS results, the AG2-329 project has the following allocation of costs for interconnection. The cost contribution towards Readiness Deposit #3 are also shown below.

Cost Summary
DescriptionCost Allocated to AG2-329Cost Subject to Readiness*Cost Subject to Adverse
Transmission Owner Interconnection Facilities (TOIF)$1,659,783$0$0
Other Scope$1,117,553$0$0
Option To Build Oversight$0$0$0
Physical Interconnection Network Upgrades
Stand Alone Network Upgrades$27,023,419$27,023,419$27,023,419
Network Upgrades$1,108,441$1,108,441$1,108,441
System Reliability Network Upgrades
Steady State Thermal & Voltage$0$0$0
Transient Stability$0$0$0
Short Circuit$0$0$0
Transmission Owner Analysis
SubRegional$0$0$0
Distribution$0$0$0
Affected System Reinforcements
AFS - PJM Violations$0$0$0
AFS - Non-PJM Violations$0$0$0
Total$30,909,196$28,131,860$28,131,860

* Contributes to calculation for Readiness Deposit #3 (RD3). See Readiness Deposit section of report for additional detail.

Definitions

Transmission Owner Interconnection Facilities: Facilities that are owned, controlled, operated and maintained by the Transmission Owner on the Transmission Owner’s side of the Point of Change of Ownership to the Point of Interconnection, including any modifications, additions or upgrades made to such facilities and equipment, that are necessary to physically and electrically interconnect the Generating Facility with the Transmission System or interconnected distribution facilities.

Stand Alone Network Upgrades: Network Upgrades, which are not part of an Affected System, which a Project Developer may construct without affecting day-to-day operations (e.g. taking a transmission outage) of the Transmission System during their construction.

Network Upgrades: Modifications or additions to transmission-related facilities that are integrated with and support the Transmission Provider’s overall Transmission System for the general benefit of all users of such Transmission System. Network Upgrades have no impact or potential impact on the Transmission System until the final tie-in is complete.

Notes

Note 1: PJM Open Access Transmission Tariff (OATT), Part VII, Subpart D, section 307.5 outlines cost allocation rules. The rules are further clarified in PJM Manual 14H, section 4.2.6. PJM shall identify the New Service Requests in the Cycle contributing to the need for the required Network Upgrades within the Cycle. All New Service Requests that contribute to the need for a Network Upgrade will receive cost allocation for that upgrade pursuant to each New Service Request’s contribution to the reliability violation identified on the transmission system in accordance with PJM Manuals.

Note 2: There will be no inter-Cycle cost allocation for Interconnection Facilities or Network Upgrades identified in the System Impact Study costs identified in a Cycle; all such costs shall be allocated to New Service Requests in that Cycle.

Note 3: For Project Developers with System Reinforcements listed: If this project presents cost allocation to a System Reinforcement indicates $0, then please be aware that as changes to the interconnection process occur, such as other projects withdrawing, reducing in size, etc, the cost responsibilities can change and a cost allocation may be assigned to this project. In addition, although this project presents cost allocation to a System Reinforcement is presently $0, this project may need this system reinforcement completed to be deliverable to the PJM system. If this project desires to come into service prior to completion of the system reinforcement, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the system reinforcement is complete.

Note 4: Please see the ‘Affected Systems Studies’ section of this Phase II SIS report for details on your project’s need for an Affected Systems Study. If your project requires an Affected Systems Study, the Affected Systems impacts may not be available from the Affected System Operator at the time of the PJM Phase II SIS. Therefore, the cost in this section would not reflect any required upgrades by the Affected System until the study is completed. If your project requires an Affected Systems Study and your results are not provided for Phase II SIS, PJM anticipates providing them in the Phase III SIS per Tariff Part VII.D.312.

Readiness Deposit

Per Tariff Part VII, Subpart D, section 311 (Decision Point II) A.1.b and PJM Manual 14H, section 6.2, Readiness Deposit #3 (RD3) are funds committed by the Project Developer or Eligible Customer based upon the applicable contribution to Network Upgrades as defined below. Readiness Deposits are not used to fund studies nor to offset Security.

During Decision Point II (DP2), the Project Developer or Eligible Customer is required to submit Readiness Deposit #3, which is calculated as 20% of cost allocation for required Phase II Network Upgrades minus Readiness Deposit #1 & Readiness Deposit #2.

Note 1: “Network Upgrades” referred to in the calculation include both (i) the Physical Interconnection Network Upgrades and (ii) the System Reliability Network Upgrades as shown in the Cost Summary table.

Note 2: Readiness Deposit #1 (RD1) = ($4,000 * Project Size (MW))

Note 3: Readiness Deposit #2 (RD2) = 10% of cost allocation for required Network Upgrades minus RD1. Readiness Deposit #2 (RD2) can be zero, but may not be a negative number.

Note 4: Readiness Deposit #3 can be zero, but may not be a negative number.

Readiness Deposit #3 Due for Project AG2-329

Readiness Deposit #3 has been calculated for the project based on the Phase II System Impact Study results and is shown in the table below. This Readiness Deposit #3 must be provided at Decision Point II through either a wire transfer or letter of credit per Manual 14H, Section 6.2.

Readiness Deposit #3 Due for AG2-329
Project ID: AG2-329
20% of cost allocation for Phase II Network Upgrades:(A) $5,626,372
Sum of Readiness Deposit #1 & Readiness Deposit #2 Received:(B) $1,252,607
Readiness Deposit #3 (RD3) due at DP2:(A) - (B) = $4,373,765
Note: Failure to provide an acceptable form of Readiness Deposit #3 by the end of Decision Point II will result in withdrawal and termination of the New Service Request.

For additional detail regarding Readiness Deposit Refunds, reference PJM Manual 14H, section 6.2.1. The Readiness Deposit Letter of Credit template can be found here.

Transmission Owner Scope of Work

The total preliminary cost estimate for the Transmission Owner scope of work (including TOIF and Physical Interconnection Network Upgrades) is given in the table below. These costs do not include CIAC Tax Gross-up.

Transmission Owner Build Option
Network Upgrades
RTEP IDDescriptionDirectIndirectTotal Cost ($USD)Allocated Cost ($USD)
LaborMaterialsLaborMaterials
(Pending)

AEP Ohio Transmission Company Inc. will review and revise (as needed) the protective relay settings at the South Berwick 345 kV Station.

$68,134$106,498$38,954$50,326$263,912$263,912
(Pending)

Galion – South Berwick 345 kV line will be cut and looped into the new interconnection substation.

$584,791$56,939$137,513$16,647$795,890$795,890
(Pending)

Galion Substation Protection Upgrade

$46,692$0$1,947$0$48,639$48,639
Other
RTEP IDDescriptionDirectIndirectTotal Cost ($USD)Allocated Cost ($USD)
LaborMaterialsLaborMaterials
(Pending)

Installation of a standard revenue metering package, including three (3) single phase current transformers (CT), three (3) single phase coupling capacitor voltage transformers (CCVT), associated structures and foundations, one (1) ethernet switch, and one (1) DICM-installed metering panel, for the generation lead circuit at the AG2-329 New Station 345 kV Station.

$534,797$346,663$144,903$91,190$1,117,553$1,117,553
Stand-Alone Network Upgrades
RTEP IDDescriptionDirectIndirectTotal Cost ($USD)Allocated Cost ($USD)
LaborMaterialsLaborMaterials
(Pending)

Installation of two (2) Carrier Protection panels at the AG2-329 New Station 345 kV Station. AEP Ohio Transmission Company Inc. will transition existing OPGW fiber-optic shield wire from the cut-in dead ends into the AG2-329 New 345 kV Station. AEP Ohio Transmission Company Inc. will install 1 mile of 144 count all dielectric self supporting (ADSS) fiber-optic cable. AEP Ohio Transmission Company Inc. will install 1 mile of 144 count all dielectric loose tube (ADLT) underground fiber-optic cable.

$576,141$181,045$202,086$62,618$1,021,890$1,021,890
(Pending)

A new breaker and a half station, to be operated as a three (3) circuit breaker ring bus, initially expandable to six (6) circuit breakers, AG2-329 New Station 345 kV, will be constructed along the Galion – South Berwick 345 kV transmission line to interconnect the project with the OHTCO transmission system. Installation of (3) 345KV RCVTs with (3) single-phase 345KV CCVT structures, foundations, and adapter steel. AEP Ohio Transmission Company Inc. will construct a new 345 kV breaker and a half station, to be operated as a three (3) circuit breaker ring bus, initially expandable to six (6) circuit breakers. This typical arrangement is planned to be designed to accommodate 5000A of continuous current. Installation of two 2 wavetraps. four 4 single pole, single circuit, steel tangent structure. Less than 1 mile of gravel access road. Two 2 single pole, single circuit, steel running angle structure. AEP Ohio Transmission Company Inc. will remove one 1 steel lattice structure in the Galion – South Berwick 345 kV Right of Way.

$9,781,799$11,040,827$2,431,156$2,747,747$26,001,529$26,001,529
Transmission Owner Interconnection Facilities
RTEP IDDescriptionDirectIndirectTotal Cost ($USD)Allocated Cost ($USD)
LaborMaterialsLaborMaterials
(Pending)

A 345 kV dead-end structure and foundation outside the fence of the Interconnection Substation, to terminate the Project Developer’s generator lead line. Line conductor from the dead-end structure to the bus position in the switchyard of the interconnection substation. The OHTCO Interconnection Facilities will include but are not limited to the following: • Installation of one (1) new steel, 120', single circuit, single pole dead end structure on a concrete pier foundation with an anchor bolt cage and one span of double bundle ACSR 954 (Cardinal) transmission line conductor with 7#8 Alumoweld shield wire for the generation lead circuit extending from the AG2-329 New 345 kV Station.

$737,022$584,658$188,540$149,563$1,659,783$1,659,783
Developer Build Option

Project Developer has the option ("Option to Build") to assume responsibility for the design, procurement and construction of Transmission Owner Interconnection Facilities and/or Stand-Alone Network Upgrades.

If Option to Build is elected, the Project Developer must fulfill additional requirements in accordance to PJM Manual 14C, section 5.1 and PJM Manual 14H, section 8.6.2.

The cost estimates for eligible facilities and Option to Build oversight are highlighted below:

Network Upgrades
RTEP IDDescriptionDirectIndirectTotal Cost ($USD)Allocated Cost ($USD)
LaborMaterialsLaborMaterials
(Pending)

AEP Ohio Transmission Company Inc. will review and revise (as needed) the protective relay settings at the South Berwick 345 kV Station.

$68,134$106,498$38,954$50,326$263,912$263,912
(Pending)

Galion – South Berwick 345 kV line will be cut and looped into the new interconnection substation.

$584,791$56,939$137,513$16,647$795,890$795,890
(Pending)

Galion Substation Protection Upgrade

$46,692$0$1,947$0$48,639$48,639
Option to Build Oversight
RTEP IDDescriptionDirectIndirectTotal Cost ($USD)Allocated Cost ($USD)
LaborMaterialsLaborMaterials
(Pending)

Oversight of developer design and construction of new interconnection substation

$409,606$123,028$276,344$83,002$891,980$891,980
Other
RTEP IDDescriptionDirectIndirectTotal Cost ($USD)Allocated Cost ($USD)
LaborMaterialsLaborMaterials
(Pending)

Installation of a standard revenue metering package, including three (3) single phase current transformers (CT), three (3) single phase coupling capacitor voltage transformers (CCVT), associated structures and foundations, one (1) ethernet switch, and one (1) DICM-installed metering panel, for the generation lead circuit at the AG2-329 New Station 345 kV Station.

$534,797$346,663$144,903$91,190$1,117,553$1,117,553
Build Option Price Comparison
Build OptionTotal CostAllocated Cost
Transmission Owner Build Option$30,909,196$30,909,196
Developer Build Option$3,117,974$3,117,974

Based on the scope of work for the Interconnection Facilities, it is expected to take 42 month(s) after the signing of a Generator Interconnection Agreement (as this is a FERC connection) and construction kickoff call to complete the installation of the physical connection work. This assumes that there will be no environmental issues with any of the new properties associated with this project, that there will be no delays in acquiring the necessary permits for implementing the defined interconnection work, and that all system outages will be allowed when requested.

Note that the TO findings were made from a conceptual review of this project. A more detailed review of the connection facilities and their cost will be identified in a future study phase. Further note that the cost estimate data provided should be considered high level estimates since it was produced without a detailed engineering review. The Project Developer will be responsible for the actual cost of construction. TO herein reserves the right to return to any issues in this document and, upon appropriate justification, request additional monies to complete any reinforcements to the transmission systems.

Remote Terminal Work: During Phase II of the PJM interconnection process, TO’s System Protection Engineering Department will review transmission line protection as well as anti-islanding required to accommodate the new generation and interconnection substation. System Protection Engineering will determine the minimal acceptable protection requirements to reliably interconnect the proposed generating facility with the transmission system. The review is based on maintaining system reliability by reviewing TO’s protection requirements with the known transmission system configuration which includes generating facilities in the area. This review may determine that transmission line protection and communication upgrades are required at remote substations.

Remote end work required:

 

Please note that your project interconnects directly to an AEP facility which shares a tie line with ATSI. The Transmission Owner Scope of Work above outlines the interconnection facilities required on the AEP facilities. Your project will also require upgrades at the remote end ATSI facility. The scope, cost and schedule of work required on the ATSI facilities is provided in the PJM Phase II SIS report.

Transmission Owner Analysis

Transmission Owner Identified Network Impacts to Distribution Facilities

None


Transmission Owner Identified Network Impacts to Sub-Regional Facilities

The Transmission Owner identified network impacts to Sub-Regional facilities as follows:

Overloaded ElementContingencyRating [MVA]Final Cycle Loading %Contribution [MW]
245630 05S TIFFIN 69.0 - 245713 05SENECA SS 69.0 CKT 1 AEP_P1-2_#2748_18437_SRT-A
CONTINGENCY 'AEP_P1-2_#2748_18437_SRT-A'  

  OPEN BRANCH FROM BUS 242936 TO BUS 242942 CKT 1                  / 242936 05FOSTOR 345 242942 05SBERWI 345 1

END
86.0104.55 %17.83

Transmission Owner Identified System Reinforcements on Distribution Facilities

None


Transmission Owner Identified System Reinforcements on Sub-Regional Facilities
AG2-329 Transmission Owner Identified System Reinforcements Cost Breakdown:
TORTEP ID / TO IDTitleMW ImpactPercent AllocationAllocated Cost ($USD)
AEP(Pending) / AEP-TC2-242Seneca - Tiffin: Rating Correction17.8 MW100.0%$0
Grand Total:$0
System Reinforcement
TORTEP ID / TO IDTitleTotal Cost
AEP(Pending) / AEP-TC2-242Seneca - Tiffin: Rating Correction$0

Contributor

Description: Correct light load ratings are 75 MVA normal, 91 MVA emergency

Cost Allocation
ProjectMW ImpactPercent AllocationAllocated Cost ($USD)
AG2-32917.8 MW100.0%$0

Developer Requirements

The developer is responsible for all design and construction related activities on the developer’s side of the Point of Change in Ownership. AEP interconnection requirements can be found here.

To the extent that these Applicable Technical Requirements and Standards may conflict with the terms and conditions of the Tariff, the Tariff shall control.

Revenue Metering and SCADA Requirements

PJM Requirements
The developer will be required to install equipment necessary to provide Revenue Metering (KWH, KVARH) and real time data (KW, KVAR) for their generating Resource. See PJM Manual 01, PJM Manual 14D, and PJM Tariff Part IX, Subpart B, Appendix 2, section 8.
Transmission Owner Requirements
The Project Developer will be required to comply with all interconnected Transmission Owner’s revenue metering requirements located at the following link: PJM - Transmission Owner Engineering & Construction Standards.

Summer Peak Analysis

The New Service Request AG2-329 was evaluated as a 200.0 MW (156.0 MW Capacity) injection in the AEP area.

AG2-329 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 200.0 MW (200.0 MW under study).

Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.

The following flowgates remain after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)

Winter Peak Analysis

The New Service Request AG2-329 was evaluated as a 200.0 MW (156.0 MW Capacity) injection in the AEP area.

AG2-329 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 200.0 MW (200.0 MW under study).

Note: The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for single or N-1 contingencies and multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.

The following flowgates remain after considering the topology reinforcements required by the cycle.

StudyAreaFacility DescriptionContingency NameContingency TypeDC|ACFinal Cycle LoadingRating (MVA)Rating TypeMVA to MitigateMW ContributionDetails
IPDAEP
05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line
AP_P1-2_PE-765-242508-237805_SRT-A_SENS
SingleAC179.68 %1180.0B2120.16
11.95
IPDAEP
05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line
AP_P2-3_PE-765-237805-SB4_SRT-W_SENS
BreakerAC179.67 %1180.0B2120.16
11.95
IPDAEP
05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line
AP_P2-3_PE-765-237805-SB3_SRT-W_SENS
BreakerAC179.67 %1180.0B2120.16
11.95
IPDAEP
05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line
AP_P1-2_PE-765-237805-237806_SRT-A_SENS
SingleAC179.67 %1180.0B2120.16
11.95

Details for [AG2-329] 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line l/o AP_P1-2_PE-765-242508-237805_SRT-A_SENS


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Addition to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:AEP
Facility Description:
05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line
Contingency Name:
AP_P1-2_PE-765-242508-237805_SRT-A_SENS
Contingency Type:Single
DC|AC:AC
Final Cycle Loading:179.68 %
Rating:1180.0 MVA
Rating Type:B
MVA to Mitigate:2120.16
MW Contribution:
11.95
IPD Plant:AG2-329
Impact of Topology Modeling:
Addition
Bus #Bus NameTypeMW Contribution
970515AG2-329 GEN
PJM_IPD
11.953

Details for [AG2-329] 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line l/o AP_P2-3_PE-765-237805-SB4_SRT-W_SENS


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Addition to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:AEP
Facility Description:
05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line
Contingency Name:
AP_P2-3_PE-765-237805-SB4_SRT-W_SENS
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:179.67 %
Rating:1180.0 MVA
Rating Type:B
MVA to Mitigate:2120.16
MW Contribution:
11.95
IPD Plant:AG2-329
Impact of Topology Modeling:
Addition
Bus #Bus NameTypeMW Contribution
970515AG2-329 GEN
PJM_IPD
11.953

Details for [AG2-329] 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line l/o AP_P2-3_PE-765-237805-SB3_SRT-W_SENS


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Addition to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:AEP
Facility Description:
05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line
Contingency Name:
AP_P2-3_PE-765-237805-SB3_SRT-W_SENS
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:179.67 %
Rating:1180.0 MVA
Rating Type:B
MVA to Mitigate:2120.16
MW Contribution:
11.95
IPD Plant:AG2-329
Impact of Topology Modeling:
Addition
Bus #Bus NameTypeMW Contribution
970515AG2-329 GEN
PJM_IPD
11.953

Details for [AG2-329] 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line l/o AP_P1-2_PE-765-237805-237806_SRT-A_SENS


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Addition to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:AEP
Facility Description:
05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line
Contingency Name:
AP_P1-2_PE-765-237805-237806_SRT-A_SENS
Contingency Type:Single
DC|AC:AC
Final Cycle Loading:179.67 %
Rating:1180.0 MVA
Rating Type:B
MVA to Mitigate:2120.16
MW Contribution:
11.95
IPD Plant:AG2-329
Impact of Topology Modeling:
Addition
Bus #Bus NameTypeMW Contribution
970515AG2-329 GEN
PJM_IPD
11.953
CONTINGENCY 'AP_P1-2_PE-765-242508-237805_SRT-A_SENS'
 DISCONNECT BRANCH FROM BUS 242508 TO BUS 237805 CKT 1   /*05AMOS       765.0 - 01WELTON_SPR 765.0
END
CONTINGENCY 'AP_P2-3_PE-765-237805-SB4_SRT-W_SENS'
 DISCONNECT BRANCH FROM BUS 242508 TO BUS 237805 CKT 1   /*05AMOS       765.0 - 01WELTON_SPR 765.0
 REDUCE BUS 237805 SHUNT BY 50 PERCENT                   /*01WELTON_SPR 765.0
END
CONTINGENCY 'AP_P2-3_PE-765-237805-SB3_SRT-W_SENS'
 DISCONNECT BRANCH FROM BUS 242508 TO BUS 237805 CKT 1   /*05AMOS       765.0 - 01WELTON_SPR 765.0
 REDUCE BUS 237805 SHUNT BY 50 PERCENT                   /*01WELTON_SPR 765.0
END
CONTINGENCY 'AP_P1-2_PE-765-237805-237806_SRT-A_SENS'
 DISCONNECT BRANCH FROM BUS 237805 TO BUS 237806 CKT 1   /*01WELTON_SPR 765.0 - 01ROCKYPOINT 765.0
END
290614 to 242515 ckt 1

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)

Light Load Analysis

The New Service Request AG2-329 was evaluated as a 200.0 MW injection and 200.0 MW withdrawal in the AEP area.

AG2-329 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 200.0 MW (200.0 MW under study).

Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.

The following flowgates remain after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

StudyAreaFacility DescriptionContingency NameContingency TypeDC|ACFinal Cycle LoadingRating (MVA)Rating TypeMVA to MitigateMW ContributionDetails
GD2AEP
05E LIMA-05SW LIM 345.0 kV Ckt 1 line
AEP_P1-2_#6497_SRT-A
SingleAC105.4 %971.0B1023.39
11.87

Details for 05E LIMA-05SW LIM 345.0 kV Ckt 1 line l/o AEP_P1-2_#6497_SRT-A


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area:AEP
Facility Description:
05E LIMA-05SW LIM 345.0 kV Ckt 1 line
Contingency Name:
AEP_P1-2_#6497_SRT-A
Contingency Type:Single
DC|AC:AC
Final Cycle Loading:105.4 %
Rating:971.0 MVA
Rating Type:B
MVA to Mitigate:1023.39
MW Contribution:
11.87
Impact of Topology Modeling:
Elimination
Bus #Bus NameTypeMW Contribution
24695305TIMB G C
Solar/Wind Harmer
2.45
247607V1-011 GEN
Solar/Wind Harmer
2.572
253303V4-073 C
Solar/Wind Helper
0.041
253378AE2-206_GEN
Solar/Wind Helper
4.954
253394AE2-221_GEN
Solar/Wind Helper
2.185
253398AE2-221_GEN2
Solar/Wind Helper
2.185
253383AE2-342_GEN
Solar/Wind Helper
0.783
270302AB2-170 GEN
Solar/Wind Harmer
0
270317AD1-130_GEN
Solar/Wind Harmer
0
270428AC2-015 C
Solar/Wind Harmer
0
270435AC2-044 GEN
Solar/Wind Harmer
1.747
270489AE1-102 GEN1
Solar/Wind Harmer
1.136
246936BC-WTG1
Solar/Wind Harmer
7.922
246937BC-WTG2
Solar/Wind Harmer
7.922
246938BC-WTG3
Solar/Wind Harmer
8.059
241974AD2-163_GEN2
Solar/Wind Helper
1.299
241973AD2-163_GEN1
Solar/Wind Helper
1.299
241972AD1-140 GEN
Solar/Wind Helper
3.537
241808AF1-120 C
Solar/Wind Harmer
0
241996AE2-282_GEN
Solar/Wind Harmer
0
241807AE2-176_GEN
Solar/Wind Harmer
0
241858AF1-205_GEN
Solar/Wind Harmer
1.744
270377AD1-106 GEN
Solar/Wind Harmer
0.519
270471AD2-092_GEN
Solar/Wind Helper
2.018
270349AD2-093_GEN
Solar/Wind Helper
2.018
270588AE1-091_GEN
Solar/Wind Harmer
6.227
270499AE1-146 GEN
Solar/Wind Harmer
0
270007AE1-245 C
Solar/Wind Harmer
3.61
270541AE2-072 C
Solar/Wind Harmer
0
270518AE2-148 GEN
Solar/Wind Helper
8.101
270284AF1-227 GEN1
Solar/Wind Harmer
0
270466AD2-091
50/50
13.876
270036AE2-216 BAT
50/50
15.263
270475AD2-096_GEN
50/50
Charging
3.114
270578AF1-285 GEN2
Solar/Wind Harmer
2.774
270391AF1-285 GEN3
Solar/Wind Harmer
2.774
253349AC2-067 GEN
Solar/Wind Helper
1.018
253400AC2-068 GEN
Solar/Wind Helper
0.409
270361_3
Solar/Wind Harmer
5.358
270575GUS2 35KV
Solar/Wind Harmer
5.667
276820AF1-078_GEN
Solar/Wind Helper
2.23
253406AD2-031_GEN
Solar/Wind Helper
0.776
270462AD2-086
Solar/Wind Harmer
-0.001
247522W1-056 GEN
Solar/Wind Harmer
2.66
270491AE1-102 GEN2
Solar/Wind Harmer
1.136
943851AF1-053 GEN
50/50
Charging
2.494
945411AF1-206 GEN
Solar/Wind Harmer
8.512
945641AF1-229 GEN
Solar/Wind Harmer
0
959331AF2-224 GEN
Solar/Wind Harmer
3.741
960071AF2-298 GEN
Solar/Wind Helper
1.026
960841AF2-375 GEN
Solar/Wind Harmer
0
960851AF2-376 GEN
50/50
2.877
963581AG1-207 GEN
50/50
Charging
7.901
966831AG1-554 GEN
Solar/Wind Harmer
0
970515AG2-329 GEN
50/50
11.865
970583AG2-370 GEN
50/50
2.8
972253AH1-711 GEN
50/50
24.77
270223U2-072_GEN1
Solar/Wind Harmer
5.959
270224U2-072_GEN2
Solar/Wind Harmer
5.959
270227U2-072_GEN3
Solar/Wind Harmer
5.959
270228U2-072_GEN4
Solar/Wind Harmer
5.959
270231U2-072_GEN5
Solar/Wind Harmer
5.959
957201AF2-014 GEN
Solar/Wind Harmer
0
958091AF2-103 GEN
Solar/Wind Harmer
0.188
958091AF2-103 GEN
Solar/Wind Harmer
0
958321AF2-126 GEN
Solar/Wind Harmer
0.539
965011AG1-365 GEN
Solar/Wind Harmer
3.741
965021AG1-366 GEN
Solar/Wind Harmer
3.401
965421AG1-410 GEN
Solar/Wind Harmer
24.771
965431AG1-411 GEN
50/50
15.013
990527J1329
External Queue
1.0685162544250488
CBM West 1LTFEXP_CBM-W1->PJM
CBM
28.534
NYPJM->LTFIMP_NY
CLTF
0.298
GibsonPJM->LTFIMP_GIBSON
CLTF
0
WECLTFEXP_WEC->PJM
CLTF
0.312
HAMLETPJM->LTFIMP_HAMLET
CLTF
0.768
CATAWBAPJM->LTFIMP_CATAWBA
CLTF
0.479
PRAIRIEPJM->LTFIMP_PRAIRIE
CLTF
0.853
TRIMBLEPJM->LTFIMP_TRIMBLE
CLTF
1.038
CALDErWOODPJM->LTFIMP_CALDERWOOD
CLTF
0
MECLTFEXP_MEC->PJM
CLTF
0.551
CHEOAHPJM->LTFIMP_CHEOAH
CLTF
0
BlueGrassPJM->LTFIMP_BlueG
CLTF
3.156
CONTINGENCY 'AEP_P1-2_#6497_SRT-A'
 OPEN BRANCH FROM BUS 242939 TO BUS 290984 CKT 1   /*05MARYSV     345.0 - 05BOKESCRK   345.0
END
242935 to 242945 ckt 1

Short Circuit Analysis

Analysis Complete - No Issues

Based on PJM’s TC2 Phase II Short Circuit Analysis, this project did not contribute >1% fault duty to any previously identified overdutied breakers, nor did it cause any new overdutied breakers.

Please note that in TC2 Phase III, PJM will perform additional analysis including the evaluation of impacts from topology upgrades which may have potential effects on breaker duties not seen in the Phase II analysis.

Stability Analysis

Analysis Complete - No Issues

Executive Summary

 

New Service Requests AG2-329 and AH1-282 in PJM Transition Cycle 2, Cluster 27 are listed in Error! Reference source not found. below. This report will cover the dynamic analysis of Cluster 27 projects.

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 27 projects will meet the dynamics requirements of the NERC, AEP and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2028 Summer Peak, modified to include applicable projects. Cluster 27 projects have been dispatched online at maximum power output, with 1.0 voltage at the terminal bus.

 

Transition Cycle 2 Cluster 27 will be tested for compliance with NERC, PJM and other applicable criteria. The contingencies will be studied with a 20 second simulation time. Contingencies to be studied include:

       a)       Steady-state operation (Category P0);

       b)       Three-phase faults with normal clearing time (and with unsuccessful high-speed reclosing) (Category P1);

       c)       Single-phase bus faults with normal clearing time (Category P2);

       d)       Single-phase faults with stuck breaker (Category P4);

       e)       Three-phase faults with loss of multiple-circuit tower line; (and with unsuccessful high-speed reclosing) (Category P7).

 

High Speed Reclosing (HSR) facilities were found in the vicinity of TC2 Cluster 27 projects.

 

Prior outage scenarios will not be considered for this study.

 

For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all the fault contingencies tested on the 2028 peak load case:

       a)       Cluster 27 projects were able to ride through the faults (except for faults where protective action trips a generator(s)).

       b)       The system with Cluster 27 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.

       c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d)       No transmission element tripped, other than those either directly connected or designed to trip because of that fault.

 

No mitigations were found to be required.

 

Table 1: Transition Cycle 2 Cluster 27 Projects

 

 

 

 

Project

Fuel Type

Transmission Owner

MFO (MW)

Point of Interconnection

AG2-329

Battery

AEP

200

South Berwick - Galion 345 kV

AH1-282

Solar

AEP

49.9

Galion - Ohio Central 345 kV

 

 

Reactive Power Analysis

Analysis Complete - No Issues

The reactive power capability of AG2-329 meets the 0.95 leading and lagging PF requirement at the high side of the main transformer.

Steady-State Voltage Analysis

Analysis Complete - No Issues

Steady State Voltage Analysis complete, no voltage issues identified.

New Service Request Dependencies

The New Service Requests below are listed in one or more dispatch for the overloads identified in this report. These projects contribute to the loading of the overloaded facilities identified in this report. The percent overload of a facility and cost allocation you may have towards a particular reinforcement could vary depending on the action of other projects. The status of each project at the time of the analysis is presented in the table. This list may change as other projects withdraw or modify their requests. This table is valid for load flow analyses only.

(No dependencies were identified)

Affected System - PJM Identified Violations

As part of PJM's analysis, per Tariff Part VII.G.336 & Manual 14H, Section 13, PJM evaluated the potential impacts on tie line facilities between PJM and an affected system entity, which were identified per PJM planning analysis criteria. This upgrade may be required on the affected system portion of the tie line along with cost allocation of such upgrade if applicable, in coordination with the affected system. Depending on the affected system, this project may not be contingent on upgrade based on PJM planning analysis criteria, but may be contingent on this upgrade based on the Affected System Operator's planning criteria, provided in the Affected Systems Study Section, herein.

Midcontinent Independent System Operator, Inc. (MISO)No Impact
New York Independent System Operator (NYISO)No Impact
Tennessee Valley Authority (TVA)No Impact
Louisville Gas & Electric (LG&E)No Impact
Duke Energy Carolinas (DUKE)No Impact
Duke Energy Progress – East (CPLE)No Impact
Duke Energy Progress – West (CPLW)No Impact

Affected System - Non-PJM Identified Violations

In accordance with PJM Tariff Part VII, Subpart D, section 310.A and as outlined in PJM Manual 14H, Sections 4.5 and 13, in Phase II of the Cycle, PJM provides the Affected System Operator any updates on the PJM projects that require an Affected Systems Study based on their response at DP1. New Service Requests that require an Affected Systems Study are required to enter into an Affected Systems Study Agreement with the Affected System Operator, as applicable, prior to the close of DP2 or they will be withdrawn from the Cycle.

If the Project Developer already entered into the necessary agreement and the results are available, PJM will supply them in the Phase II SIS report. See below for the status of any required Affected Systems Study. A status of “Pending” means that the study is not yet completed by the Affected System Operator. If your project requires an Affected Systems Study and your results are not provided for Phase II SIS, PJM anticipates providing them in the Phase III SIS per Tariff Part VII.D.312.

Midcontinent Independent System Operator, Inc. (MISO)Not required
New York Independent System Operator (NYISO)Not required
Tennessee Valley Authority (TVA)Not required
Louisville Gas & Electric (LG&E)Not required
Duke Energy Carolinas (DUKE)Not required
Duke Energy Progress – East (CPLE)Not required
Duke Energy Progress – West (CPLW)Not required

System Reinforcements

Based on the Phase II System Impact Study analysis results, this project is contingent on and may have cost responsibility for the following System Reinforcements:

AG2-329 System Reinforcements:
TORTEP IDTitleCategoryAllocated Cost ($USD)Facilities Study
AEPb4068.1b4068: Greentown 765 kV - Teddy 765kV - Marysville 765 kV - Greenfield Line - AEP Proposal 570Contingent$0N/A
AEPb3919.1Reconfigure Maliszewski 765 kV station and establish 345 kV breaker yardContingent$0N/A
AEPb4000.251Replace the wave trap and upgrade the relay at Cloverdale 765kV substationContingent$0N/A
AEPb4000.252Replace the wave trap and upgrade the relay at Joshua Falls 765kV substationContingent$0N/A
Grand Total:$0

Shown below are the details of the cost allocated, contingent, eliminated, topology and potential aggregate contributor reinforcements for this project. Please refer to the System Reinforcement table above and the information below for more detail.


System Reinforcement: b4068.1
Type
Load Flow
TO
AEP
RTEP ID / TO ID
b4068.1 / AEP-TC2-18693
Title
b4068: Greentown 765 kV - Teddy 765kV - Marysville 765 kV - Greenfield Line - AEP Proposal 570
Description
b4068.1 through b4068.49: Affected Transmission Owners: AEP / Dayton / ATSI The objective of this project is to construct multiple transmission lines to address Ohio area violations. The total distance covered by the lines is approximately 359.54 miles. The first transmission line ranges from the existing Greentown Substation in Howard County, Indiana to the new Teddy Substation in Clark County, Ohio, the line then branches north towards the existing Marysville Substation in Union County, Ohio, and east to the existing Beatty Substation in Franklin County, Ohio, and then extends to the existing Cole Substation in Franklin County, Ohio. The second transmission line extends from the existing Adkins Substation in Pickaway County, Ohio, to the new West Millersport Substation in Fairfield County, Ohio, then continues to the existing Conesville Substation in Coshocton County, Ohio before finally extending to the existing Guernsey Substation in Guernsey County, Ohio. There is a total of five transmission lines that extend between unnamed substations (Hayden - Cole 345 kV, Hyatt - Maliszewski 345 kV [double circuit], Roberts - Kenny 138 kV, Wilson - 5th Avenue 138 kV, West Millersport-Kirk 345 kV). This project will traverse 4 counties (Howard, Grant, Blackford, Jay) in Indiana, and 13 counties (Darke, Shelby, Champaign, Clark, Madison, Franklin, Delaware, Pickaway, Fairfield, Licking, Muskingum, Coshocton, Guernsey) in Ohio. This proposal has a total of 38 components, including 16 substation upgrade components, two greenfield substation components, eight greenfield transmission line components covering approximately 336.2 miles, and 12 transmission line upgrade components covering approximately 23.34 miles. b4068.28/b4068.49 is dependent on b3919.1 Baseline completion.
Cost Information
Time Estimate
Jun 01 2030

ContingentTopology Changing

Note 1: Although AG2-329 may not presently have cost responsibility for this upgrade, AG2-329 may need this upgrade in-service to be deliverable to the PJM system. If AG2-329 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.

Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.

FacilityContingency
05E LIMA-05SW LIM 345.0 kV Ckt 1 line(Any)
No new ratings for this Flowgate.

System Reinforcement: b3919.1
Type
Load Flow
TO
AEP
RTEP ID / TO ID
b3919.1
Title
Reconfigure Maliszewski 765 kV station and establish 345 kV breaker yard
Description
Reconfigure Maliszewski 765 kV station from 2 breakers to a 6 breaker ring bus. Install a new 765/345 kV transformer. Establish new 345 kV breaker yard with 3 string breaker and a half to include a line exit to Hyatt and a line exit to Corridor. Loop the existing Hyatt - West Millersport 345 kV line into the new established 345 kV yard at the Maliszewski station.
Cost Information
Time Estimate
Jun 01 2029

ContingentTopology Changing

Note 1: Although AG2-329 may not presently have cost responsibility for this upgrade, AG2-329 may need this upgrade in-service to be deliverable to the PJM system. If AG2-329 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.

Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.

FacilityContingency
05E LIMA-05SW LIM 345.0 kV Ckt 1 line(Any)
No new ratings for this Flowgate.

System Reinforcement: b4000.251
Type
Load Flow
TO
AEP
RTEP ID / TO ID
b4000.251
Title
Replace the wave trap and upgrade the relay at Cloverdale 765kV substation
Description
Replace the wave trap and upgrade the relay at Cloverdale 765kV substation
Cost Information
Time Estimate
Jun 01 2029

Contingent

Note: Although AG2-329 may not presently have cost responsibility for this upgrade, AG2-329 may need this upgrade in-service to be deliverable to the PJM system. If AG2-329 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.

FacilityContingency
05JOSHUA-05CLOVRD_RJO 765.0 kV Ckt 1 line(Any)
Rating SetRating TypeRating Value
(All)A4047.0 MVA
(All)B4571.0 MVA

System Reinforcement: b4000.252
Type
Load Flow
TO
AEP
RTEP ID / TO ID
b4000.252
Title
Replace the wave trap and upgrade the relay at Joshua Falls 765kV substation
Description
Replace the wave trap and upgrade the relay at Joshua Falls 765kV substation
Cost Information
Time Estimate
Jun 01 2029

Contingent

Note: Although AG2-329 may not presently have cost responsibility for this upgrade, AG2-329 may need this upgrade in-service to be deliverable to the PJM system. If AG2-329 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.

FacilityContingency
05JOSHUA-05CLOVRD_RJO 765.0 kV Ckt 1 line(Any)
Rating SetRating TypeRating Value
(All)A4047.0 MVA
(All)B4571.0 MVA

Conversion from Impacts into Topology or Eliminated Reinforcements into Region Topology Contingent Reinforcements for AG2-329


AG2-329 Contributions into Topology or Eliminated Reinforcements:
TypeTORTEP ID / TO IDTitleTopo or ElimMW ImpactPercent AllocationCategoryAllocated Cost ($USD)
Load FlowAEPb4068.1 / AEP-TC2-18693b4068: Greentown 765 kV - Teddy 765kV - Marysville 765 kV - Greenfield Line - AEP Proposal 570Topology-0.0%Contingent$0
Load FlowAEPb3919.1Reconfigure Maliszewski 765 kV station and establish 345 kV breaker yardTopology-0.0%Contingent$0
Contributions into Topology or Eliminated Reinforcement Total:$0
AG2-329 Contingent Region Topology Upgrades:
TORTEP IDTitleCategoryAllocated Cost ($USD)
Region Topology Upgrade Total:$0

Attachments

AG2-329 One Line Diagram

AG2-329 One Line Diagram.jpg
The state in which the generator or merchant transmission facility is located.
The Transmission Owner of the facility where the New Service Request project interconnects to the transmission system.
Winter load flow analysis will be performed starting in Transition Cycle 2.