AG2-370 Phase II System Impact Study Report
v1.00 released 2026-06-03 18:06
Tillman 138 kV
20.0 MW Capacity / 50.0 MW Energy
Introduction
This Phase II System Impact Study (SIS) Report has been prepared in accordance with the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 310 for New Service Requests (projects) in Transition Cycle 2 (TC2). The Project Developer/Eligible Customer (developer) is Tillman Storage LLC, and the Transmission Provider (TP) is PJM Interconnection, LLC (PJM). The interconnected Transmission Owner (TO) is AEP Indiana Michigan Transmission Company, Inc..
Preface
The Phase II System Impact Study is conducted on an aggregate basis within a New Services Request’s Cycle, and results are provided in both (i) a single Cycle summary format and (ii) an individual project-level basis. The Phase II System Impact Study Results (for both the summary and individual reports) will be publicly available on PJM’s website. Project Developers must obtain the results from the website.
In accordance with PJM Manual 14H, section 4.5, PJM takes the following actions during the Phase II System Impact Study:
- PJM will retool load flow results from the Phase I System Impact Study (summer peak, winter peak and light load) based on decisions made by Project Developers or Eligible Customers during Decision Point I.
- PJM will conduct any required voltage analyses.
- PJM will perform short circuit and stability analyses as required.
- PJM will coordinate with the Affected System to confirm which projects in the PJM Cycle will require Affected System studies. If the Affected System Operator indicates that an Affected System study is required, PJM will:
- Notify the Project Developer or Eligible Customer of the need for an Affected System study and the requirement to execute an Affected System study agreement with the impacted Affected System Operator, and;
- Include the results of the Affected System Operator’s Affected System Study in the Phase II System Impact Study results, if applicable and available.
- The Phase II System Impact Study Results will be publicly available on PJM’s website. Project Developers and Eligible Customers must obtain the results from the website.
The Transmission Owner takes the following actions during the Phase II System Impact Study:
- Verify Interconnection Facilities and Network Upgrades required to accommodate the New Service Request.
- Perform a Facilities Study. The Facilities Study in Phase II System Impact Study phase will be for the physical Interconnection Facilities. The Facilities Study requirements are outlined in Attachment C of this manual. The study will be conducted pursuant to Tariff, Part VII, Subpart D, section 307(A)(7) and Tariff, Part VIII, Subpart C, section 404(A)(7).
Decision Point II Requirements
At the close of Phase II System Impact Study, PJM will initiate Decision Point II (DP2). During DP2, the Project Developer will have 30 days to decide whether to proceed with their project. If the Project Developer elects to proceed, they should provide the elements defined in the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 311.A. Additional information on these elements is available in PJM Manual 14H sections 4.6, 6, and 7.
Allowable project modifications at Decision Point II are defined in PJM Open Access Transmission Tariff, Part VII, Subpart D, section 311.B. Additional information regarding allowable project modifications can be found in PJM Manual 14H, section 9.8.
Adverse Test Eligibility
This New Service Request does not meet the Adverse Study Impact Criteria and has the option to either move forward in the Cycle process or withdraw at DP2 with Readiness Deposit #1 forfeited. See adverse study impact calculation below.
This section details whether a Project Developer or Eligible Customer qualifies for the Adverse Study Impact clause outlined in the PJM OATT, Part VII, Subpart D, section 311.B and Manual 14H, section 6.2.2. In order to qualify for an Adverse Study Impact at Decision Point II, the Network Upgrade cost from Phase I to Phase II must:
- Increase overall by 25% or more
- Increases by more than $10,000 per MW (Includes Costs identified in Affected System studies)
If a New Service Request meets the criteria above and chooses to withdraw the request, PJM will refund the cumulative Readiness Deposit amounts paid at the Application Phase and at Decision Point I (RD1 and RD2, respectively).
The below calculations show the computation of this New Service Request's Adverse Study Impact
General
The Project Developer has proposed a Storage facility located in the AEP Indiana Michigan Transmission Company, Inc. zone — Allen County, Indiana. The installed facilities will have a total capability of 50.0 MW with 20.0 MW of this output being recognized by PJM as Capacity.Project Information
Physical Interconnection Facility Study
The transmission owner has completed the Physical Interconnection Facilities Study. This report is available for download.
Point of Interconnection
AG2-370 will interconnect on the American Electric Power transmission system at the Tillman 138 kV Substation .
Cost Summary
The table below shows a summary of the total cost estimates for this New Service Request project. In Phase II SIS, the interconnected Transmission Owner has performed a facilities study for both the Transmission Owner Interconnection Facilities (TOIF) and Physical Interconnection Network Upgrades. The System Reliability Network Upgrade shown in the table are planning level cost estimates which are subject to change as a result of a facility study performed by the TO during Phase III System Impact Study.
Based on the Phase II SIS results, the AG2-370 project has the following allocation of costs for interconnection. The cost contribution towards Readiness Deposit #3 are also shown below.
| Cost Summary | |||
|---|---|---|---|
| Description | Cost Allocated to AG2-370 | Cost Subject to Readiness* | Cost Subject to Adverse |
| Transmission Owner Interconnection Facilities (TOIF) | $0 | $0 | $0 |
| Other Scope | $603,891 | $0 | $0 |
| Option To Build Oversight | $0 | $0 | $0 |
| Physical Interconnection Network Upgrades | |||
| Stand Alone Network Upgrades | $0 | $0 | $0 |
| Network Upgrades | $3,166,854 | $3,166,854 | $3,166,854 |
| System Reliability Network Upgrades | |||
| Steady State Thermal & Voltage | $0 | $0 | $0 |
| Transient Stability | $0 | $0 | $0 |
| Short Circuit | $0 | $0 | $0 |
| Transmission Owner Analysis | |||
| SubRegional | $0 | $0 | $0 |
| Distribution | $0 | $0 | $0 |
| Affected System Reinforcements | |||
| AFS - PJM Violations | $0 | $0 | $0 |
| AFS - Non-PJM Violations | $0 | $0 | $0 |
| Total | $3,770,745 | $3,166,854 | $3,166,854 |
* Contributes to calculation for Readiness Deposit #3 (RD3). See Readiness Deposit section of report for additional detail.
Definitions
Transmission Owner Interconnection Facilities: Facilities that are owned, controlled, operated and maintained by the Transmission Owner on the Transmission Owner’s side of the Point of Change of Ownership to the Point of Interconnection, including any modifications, additions or upgrades made to such facilities and equipment, that are necessary to physically and electrically interconnect the Generating Facility with the Transmission System or interconnected distribution facilities.
Stand Alone Network Upgrades: Network Upgrades, which are not part of an Affected System, which a Project Developer may construct without affecting day-to-day operations (e.g. taking a transmission outage) of the Transmission System during their construction.
Network Upgrades: Modifications or additions to transmission-related facilities that are integrated with and support the Transmission Provider’s overall Transmission System for the general benefit of all users of such Transmission System. Network Upgrades have no impact or potential impact on the Transmission System until the final tie-in is complete.
Notes
Note 1: PJM Open Access Transmission Tariff (OATT), Part VII, Subpart D, section 307.5 outlines cost allocation rules. The rules are further clarified in PJM Manual 14H, section 4.2.6. PJM shall identify the New Service Requests in the Cycle contributing to the need for the required Network Upgrades within the Cycle. All New Service Requests that contribute to the need for a Network Upgrade will receive cost allocation for that upgrade pursuant to each New Service Request’s contribution to the reliability violation identified on the transmission system in accordance with PJM Manuals.
Note 2: There will be no inter-Cycle cost allocation for Interconnection Facilities or Network Upgrades identified in the System Impact Study costs identified in a Cycle; all such costs shall be allocated to New Service Requests in that Cycle.
Note 3: For Project Developers with System Reinforcements listed: If this project presents cost allocation to a System Reinforcement indicates $0, then please be aware that as changes to the interconnection process occur, such as other projects withdrawing, reducing in size, etc, the cost responsibilities can change and a cost allocation may be assigned to this project. In addition, although this project presents cost allocation to a System Reinforcement is presently $0, this project may need this system reinforcement completed to be deliverable to the PJM system. If this project desires to come into service prior to completion of the system reinforcement, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the system reinforcement is complete.
Note 4: Please see the ‘Affected Systems Studies’ section of this Phase II SIS report for details on your project’s need for an Affected Systems Study. If your project requires an Affected Systems Study, the Affected Systems impacts may not be available from the Affected System Operator at the time of the PJM Phase II SIS. Therefore, the cost in this section would not reflect any required upgrades by the Affected System until the study is completed. If your project requires an Affected Systems Study and your results are not provided for Phase II SIS, PJM anticipates providing them in the Phase III SIS per Tariff Part VII.D.312.
Readiness Deposit
Per Tariff Part VII, Subpart D, section 311 (Decision Point II) A.1.b and PJM Manual 14H, section 6.2, Readiness Deposit #3 (RD3) are funds committed by the Project Developer or Eligible Customer based upon the applicable contribution to Network Upgrades as defined below. Readiness Deposits are not used to fund studies nor to offset Security.
During Decision Point II (DP2), the Project Developer or Eligible Customer is required to submit Readiness Deposit #3, which is calculated as 20% of cost allocation for required Phase II Network Upgrades minus Readiness Deposit #1 & Readiness Deposit #2.
Note 1: “Network Upgrades” referred to in the calculation include both (i) the Physical Interconnection Network Upgrades and (ii) the System Reliability Network Upgrades as shown in the Cost Summary table.
Note 2: Readiness Deposit #1 (RD1) = ($4,000 * Project Size (MW))
Note 3: Readiness Deposit #2 (RD2) = 10% of cost allocation for required Network Upgrades minus RD1. Readiness Deposit #2 (RD2) can be zero, but may not be a negative number.
Note 4: Readiness Deposit #3 can be zero, but may not be a negative number.
Readiness Deposit #3 Due for Project AG2-370
Readiness Deposit #3 has been calculated for the project based on the Phase II System Impact Study results and is shown in the table below. This Readiness Deposit #3 must be provided at Decision Point II through either a wire transfer or letter of credit per Manual 14H, Section 6.2.
Readiness Deposit #3 Due for AG2-370
For additional detail regarding Readiness Deposit Refunds, reference PJM Manual 14H, section 6.2.1. The Readiness Deposit Letter of Credit template can be found here.
Transmission Owner Scope of Work
The total preliminary cost estimate for the Transmission Owner scope of work (including TOIF and Physical Interconnection Network Upgrades) is given in the table below. These costs do not include CIAC Tax Gross-up.
Transmission Owner Build Option
| Network Upgrades | |||||||
|---|---|---|---|---|---|---|---|
| RTEP ID | Description | Direct | Indirect | Total Cost ($USD) | Allocated Cost ($USD) | ||
| Labor | Materials | Labor | Materials | ||||
| (Pending) | IMTCO will tie the proposed AG2-370 138 kV project into the existing Tillman 138 kV station by completing the following construction tasks: • Installation of (3) 138KV RCVTs with (1) three-phase 138KV RCVT structures & foundations. • Expansion of the existing Drop-In Control Module (DICM) at the Tillman 138 kV Station by 18 feet. • AEP Indiana Michigan Transmission Company Inc. will review and revise (as needed) the protective relay settings at the Tillman 138 kV Station. • AEP Indiana Michigan Transmission Company Inc. will transition existing OPGW fiber-optic shield wire from the cut-in dead ends into the Tillman 138 kV Station. • AEP Indiana Michigan Transmission Company Inc. will install 1 mile of 144 count all dielectric self supporting (ADSS) fiber-optic cable. • AEP Indiana Michigan Transmission Company Inc. will install 1 mile of 144 count all dielectric loose tube (ADLT) underground fiber-optic cable. • AEP Indiana Michigan Transmission Company Inc. will install one (1) new 8340 router at the Tillman 138 kV Station. • AEP Indiana Michigan Transmission Company Inc. will install one (1) new 1101 router at the Tillman 138 kV Station. • AEP Indiana Michigan Transmission Company Inc. will install one (1) CES relaying package at the Tillman 138 kV Station. | $1,460,089 | $931,578 | $469,558 | $305,629 | $3,166,854 | $3,166,854 |
| Other | |||||||
|---|---|---|---|---|---|---|---|
| RTEP ID | Description | Direct | Indirect | Total Cost ($USD) | Allocated Cost ($USD) | ||
| Labor | Materials | Labor | Materials | ||||
| (Pending) | • AEP Indiana Michigan Transmission Company Inc. will install one (1) metering panel with two (2) primary meters and one (1) ethernet switch in the AG2-370 Project Developer's collector Station. | $310,265 | $139,608 | $106,222 | $47,796 | $603,891 | $603,891 |
Developer Build Option
(No Developer Build Option for this project.)
| Build Option Price Comparison | |||||||
|---|---|---|---|---|---|---|---|
| Build Option | Total Cost | Allocated Cost | |||||
| Transmission Owner Build Option | $3,770,745 | $3,770,745 | |||||
| Developer Build Option | (No Developer Build Option) | ||||||
Based on the scope of work for the Interconnection Facilities, it is expected to take 15 month(s) after the signing of a Generator Interconnection Agreement (as this is a FERC connection) and construction kickoff call to complete the installation of the physical connection work. This assumes that there will be no environmental issues with any of the new properties associated with this project, that there will be no delays in acquiring the necessary permits for implementing the defined interconnection work, and that all system outages will be allowed when requested.
Note that the TO findings were made from a conceptual review of this project. A more detailed review of the connection facilities and their cost will be identified in a future study phase. Further note that the cost estimate data provided should be considered high level estimates since it was produced without a detailed engineering review. The Project Developer will be responsible for the actual cost of construction. TO herein reserves the right to return to any issues in this document and, upon appropriate justification, request additional monies to complete any reinforcements to the transmission systems.
Remote Terminal Work: During Phase II of the PJM interconnection process, TO’s System Protection Engineering Department will review transmission line protection as well as anti-islanding required to accommodate the new generation and interconnection substation. System Protection Engineering will determine the minimal acceptable protection requirements to reliably interconnect the proposed generating facility with the transmission system. The review is based on maintaining system reliability by reviewing TO’s protection requirements with the known transmission system configuration which includes generating facilities in the area. This review may determine that transmission line protection and communication upgrades are required at remote substations.
Transmission Owner Analysis
No Transmission Owner impacts identified.
Developer Requirements
The developer is responsible for all design and construction related activities on the developer’s side of the Point of Change in Ownership. AEP interconnection requirements can be found here.
To the extent that these Applicable Technical Requirements and Standards may conflict with the terms and conditions of the Tariff, the Tariff shall control.
Revenue Metering and SCADA Requirements
The developer will be required to install equipment necessary to provide Revenue Metering (KWH, KVARH) and real time data (KW, KVAR) for their generating Resource. See PJM Manual 01, PJM Manual 14D, and PJM Tariff Part IX, Subpart B, Appendix 2, section 8.Transmission Owner Requirements
The Project Developer will be required to comply with all interconnected Transmission Owner’s revenue metering requirements located at the following link: PJM - Transmission Owner Engineering & Construction Standards.
Summer Peak Analysis
The New Service Request AG2-370 was evaluated as a 50.0 MW (20.0 MW Capacity) injection in the AEP area.
AG2-370 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 50.0 MW (50.0 MW under study).
Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.
The following flowgates remain after considering the topology reinforcements required by the cycle.
| Study | Area | Facility Description | Contingency Name | Contingency Type | DC|AC | Final Cycle Loading | Rating (MVA) | Rating Type | MVA to Mitigate | MW Contribution | |
|---|---|---|---|---|---|---|---|---|---|---|---|
| GD2 | AEP | AG1-410 TP-05MADDOX 345.0 kV Ckt 1 line | AEP_P4_05MARYSV 765_A_SRT-A_SENS | Breaker | AC | 103.61 % | 1868.0 | B | 1935.5 | 2.58 | |
| GD2 | AEP | AG1-410 TP-05MADDOX 345.0 kV Ckt 1 line | AEP_P4_#8075_05MARYSV 765_A2_SRT-A_SENS | Breaker | AC | 103.47 % | 1868.0 | B | 1932.9 | 2.56 | |
| GD2 | AEP | AG1-410 TP-05MADDOX 345.0 kV Ckt 1 line | AEP_P4_#7441_05SORENS 765_J1_SRT-A | Breaker | AC | 103.36 % | 1868.0 | B | 1930.81 | 2.58 |
The following flowgates were eliminated after considering the topology reinforcements required by the cycle.
| Study | Area | Facility Description | Contingency Name | Contingency Type | DC|AC | Final Cycle Loading | Rating (MVA) | Rating Type | MVA to Mitigate | MW Contribution | |
|---|---|---|---|---|---|---|---|---|---|---|---|
| GD2 | AEP | 05ALLEN-05RPMONE 345.0 kV Ckt 1 line | AEP_P4_#7445_05MARYSV 765_B_SRT-A | Breaker | AC | 125.19 % | 1737.0 | B | 2174.62 | 2.82 | |
| GD2 | AEP | 05ALLEN-05RPMONE 345.0 kV Ckt 1 line | AEP_P4_#7441_05SORENS 765_J1_SRT-A | Breaker | AC | 120.27 % | 1737.0 | B | 2089.1 | 2.87 | |
| GD2 | AEP | 05ALLEN-05RPMONE 345.0 kV Ckt 1 line | AEP_P4_#7446_05MARYSV 765_B2_SRT-A | Breaker | AC | 118.36 % | 1737.0 | B | 2055.99 | 2.76 | |
| GD2 | AEP | 05ALLEN-05RPMONE 345.0 kV Ckt 1 line | AEP_P1-2_#7441_100545_SRT-A | Single | AC | 110.65 % | 1737.0 | B | 1922.03 | 2.87 | |
| GD2 | AEP | 05ALLEN-05RPMONE 345.0 kV Ckt 1 line | AEP_P4_#8075_05MARYSV 765_A2_SRT-A | Breaker | AC | 101.13 % | 1737.0 | B | 1756.6 | 2.4 | |
| GD2 | AEP | 05MADDOX-05E LIMA 345.0 kV Ckt 1 line | AEP_P4_#7445_05MARYSV 765_B_SRT-A | Breaker | AC | 127.07 % | 2246.0 | B | 2854.03 | 2.75 | |
| GD2 | AEP | 05MADDOX-05E LIMA 345.0 kV Ckt 1 line | AEP_P4_#7441_05SORENS 765_J1_SRT-A | Breaker | AC | 123.03 % | 2246.0 | B | 2763.26 | 2.8 | |
| GD2 | AEP | 05MADDOX-05E LIMA 345.0 kV Ckt 1 line | AEP_P4_#7446_05MARYSV 765_B2_SRT-A | Breaker | AC | 121.63 % | 2246.0 | B | 2731.77 | 2.69 | |
| GD2 | AEP | 05MADDOX-05E LIMA 345.0 kV Ckt 1 line | AEP_P1-2_#7441_100545_SRT-A | Single | AC | 111.91 % | 2246.0 | B | 2513.45 | 2.8 | |
| GD2 | AEP | 05MADDOX-05E LIMA 345.0 kV Ckt 1 line | AEP_P4_#8075_05MARYSV 765_A2_SRT-A | Breaker | AC | 108.3 % | 2246.0 | B | 2432.38 | 2.33 | |
| GD2 | AEP | 05MADDOX-05E LIMA 345.0 kV Ckt 1 line | AEP_P4_#7334_05JEFRSO 765_A2_SRT-A | Breaker | AC | 101.13 % | 2246.0 | B | 2271.27 | 2.38 | |
| GD2 | AEP | 05RPMONE-AG1-410 TP 345.0 kV Ckt 1 line | AEP_P4_#7445_05MARYSV 765_B_SRT-A | Breaker | AC | 136.53 % | 1868.0 | B | 2550.4 | 2.77 | |
| GD2 | AEP | 05RPMONE-AG1-410 TP 345.0 kV Ckt 1 line | AEP_P4_#7441_05SORENS 765_J1_SRT-A | Breaker | AC | 131.6 % | 1868.0 | B | 2458.22 | 2.81 | |
| GD2 | AEP | 05RPMONE-AG1-410 TP 345.0 kV Ckt 1 line | AEP_P4_#7446_05MARYSV 765_B2_SRT-A | Breaker | AC | 130.06 % | 1868.0 | B | 2429.61 | 2.71 | |
| GD2 | AEP | 05RPMONE-AG1-410 TP 345.0 kV Ckt 1 line | AEP_P1-2_#7441_100545_SRT-A | Single | AC | 122.25 % | 1868.0 | B | 2283.58 | 2.81 | |
| GD2 | AEP | 05RPMONE-AG1-410 TP 345.0 kV Ckt 1 line | AEP_P4_#8075_05MARYSV 765_A2_SRT-A | Breaker | AC | 114.07 % | 1868.0 | B | 2130.9 | 2.35 | |
| GD2 | AEP | 05RPMONE-AG1-410 TP 345.0 kV Ckt 1 line | AEP_P4_#7334_05JEFRSO 765_A2_SRT-A | Breaker | AC | 105.34 % | 1868.0 | B | 1967.81 | 2.4 | |
| GD2 | AEP | 05SORENS-05SORENS 345.0/765.0 kV Ckt 3 transformer | AEP_P4_#7443_05DUMONT 765_A_SRT-A | Breaker | AC | 111.31 % | 3097.0 | B | 3447.28 | 3.66 | |
| GD2 | AEP | 05SORENS-05SORENS 345.0/765.0 kV Ckt 3 transformer | AEP_P4_#7442_05SORENS 765_K2_SRT-A | Breaker | AC | 111.22 % | 3097.0 | B | 3444.48 | 3.65 | |
| GD2 | AEP | 05SORENS-05SORENS 345.0/765.0 kV Ckt 3 transformer | AEP_P4_#7444_05DUMONT 765_A2_SRT-A | Breaker | AC | 111.06 % | 3097.0 | B | 3439.41 | 3.66 | |
| GD2 | AEP | 05SORENS-05SORENS 345.0/765.0 kV Ckt 3 transformer | AEP_P1-2_#7442_200545_SRT-A | Single | AC | 103.01 % | 3097.0 | B | 3190.2 | 3.65 | |
| GD2 | AEP | 05TIMBER SW-05HAVILAND2 138.0 kV Ckt 1 line | AEP_P4_#7445_05MARYSV 765_B_SRT-A | Breaker | AC | 100.57 % | 240.0 | B | 241.36 | 4.07 | |
| GD2 | AEP | AG1-410 TP-05MADDOX 345.0 kV Ckt 1 line | AEP_P4_#7445_05MARYSV 765_B_SRT-A | Breaker | AC | 144.09 % | 1868.0 | B | 2691.58 | 2.77 | |
| GD2 | AEP | AG1-410 TP-05MADDOX 345.0 kV Ckt 1 line | AEP_P4_#7446_05MARYSV 765_B2_SRT-A | Breaker | AC | 137.58 % | 1868.0 | B | 2570.02 | 2.71 | |
| GD2 | AEP | AG1-410 TP-05MADDOX 345.0 kV Ckt 1 line | AEP_P1-2_#7441_100545_SRT-A | Single | AC | 128.82 % | 1868.0 | B | 2406.35 | 2.81 | |
| GD2 | AEP | AG1-410 TP-05MADDOX 345.0 kV Ckt 1 line | AEP_P4_#8075_05MARYSV 765_A2_SRT-A | Breaker | AC | 121.51 % | 1868.0 | B | 2269.73 | 2.35 | |
| GD2 | AEP | AG1-410 TP-05MADDOX 345.0 kV Ckt 1 line | AEP_P4_#7334_05JEFRSO 765_A2_SRT-A | Breaker | AC | 112.92 % | 1868.0 | B | 2109.31 | 2.4 | |
| GD2 | AEP | AG1-410 TP-05MADDOX 345.0 kV Ckt 1 line | AEP_P7-1_#11067___SRT-A | Tower | AC | 103.3 % | 1868.0 | B | 1929.56 | 3.58 | |
| GD2 | AEP | AG1-410 TP-05MADDOX 345.0 kV Ckt 1 line | ATSI_P7-1_TE-345-032T_SRT-A | Tower | AC | 102.98 % | 1868.0 | B | 1923.66 | 2.33 | |
| GD2 | AEP | AG1-410 TP-05MADDOX 345.0 kV Ckt 1 line | AEP_P2-2_#7222_05MALIS 765_1_SRT-A | Bus | AC | 100.16 % | 1868.0 | B | 1870.91 | 2.33 |
Winter Peak Analysis
The New Service Request AG2-370 was evaluated as a 50.0 MW (20.0 MW Capacity) injection in the AEP area.
AG2-370 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 50.0 MW (50.0 MW under study).
Note: The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for single or N-1 contingencies and multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.
The following flowgates remain after considering the topology reinforcements required by the cycle.
(No impacts were found for this analysis)
The following flowgates were eliminated after considering the topology reinforcements required by the cycle.
| Study | Area | Facility Description | Contingency Name | Contingency Type | DC|AC | Final Cycle Loading | Rating (MVA) | Rating Type | MVA to Mitigate | MW Contribution | |
|---|---|---|---|---|---|---|---|---|---|---|---|
| GD2 | AEP | 05ALLEN-05RPMONE 345.0 kV Ckt 1 line | AEP_P4_#7445_05MARYSV 765_B_SRT-A | Breaker | AC | 120.49 % | 1737.0 | B | 2092.95 | 2.76 | |
| GD2 | AEP | 05ALLEN-05RPMONE 345.0 kV Ckt 1 line | AEP_P1-2_#7441_100545_SRT-A | Single | AC | 118.4 % | 1737.0 | B | 2056.53 | 2.81 | |
| GD2 | AEP | 05ALLEN-05RPMONE 345.0 kV Ckt 1 line | AEP_P4_#7441_05SORENS 765_J1_SRT-A | Breaker | AC | 116.41 % | 1737.0 | B | 2022.06 | 2.81 | |
| GD2 | AEP | 05ALLEN-05RPMONE 345.0 kV Ckt 1 line | AEP_P4_#7446_05MARYSV 765_B2_SRT-A | Breaker | AC | 115.97 % | 1737.0 | B | 2014.34 | 2.7 | |
| GD2 | AEP | 05RPMONE-AG1-410 TP 345.0 kV Ckt 1 line | AEP_P4_#7445_05MARYSV 765_B_SRT-A | Breaker | AC | 103.66 % | 2219.0 | B | 2300.12 | 2.76 | |
| GD2 | AEP | 05RPMONE-AG1-410 TP 345.0 kV Ckt 1 line | AEP_P1-2_#7441_100545_SRT-A | Single | AC | 101.06 % | 2219.0 | B | 2242.58 | 2.81 | |
| GD2 | AEP | 05RPMONE-AG1-410 TP 345.0 kV Ckt 1 line | AEP_P4_#7441_05SORENS 765_J1_SRT-A | Breaker | AC | 100.53 % | 2219.0 | B | 2230.82 | 2.81 | |
| GD2 | AEP | 05RPMONE-AG1-410 TP 345.0 kV Ckt 1 line | AEP_P4_#7446_05MARYSV 765_B2_SRT-A | Breaker | AC | 100.04 % | 2219.0 | B | 2219.82 | 2.7 | |
| GD2 | AEP | AG1-410 TP-05MADDOX 345.0 kV Ckt 1 line | AEP_P4_#7445_05MARYSV 765_B_SRT-A | Breaker | AC | 106.03 % | 2219.0 | B | 2352.88 | 2.76 | |
| GD2 | AEP | AG1-410 TP-05MADDOX 345.0 kV Ckt 1 line | AEP_P1-2_#7441_100545_SRT-A | Single | AC | 103.21 % | 2219.0 | B | 2290.26 | 2.81 | |
| GD2 | AEP | AG1-410 TP-05MADDOX 345.0 kV Ckt 1 line | AEP_P4_#7441_05SORENS 765_J1_SRT-A | Breaker | AC | 102.89 % | 2219.0 | B | 2283.06 | 2.81 | |
| GD2 | AEP | AG1-410 TP-05MADDOX 345.0 kV Ckt 1 line | AEP_P4_#7446_05MARYSV 765_B2_SRT-A | Breaker | AC | 102.36 % | 2219.0 | B | 2271.47 | 2.7 |
Light Load Analysis
The New Service Request AG2-370 was evaluated as a 50.0 MW injection and 50.0 MW withdrawal in the AEP area.
AG2-370 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 50.0 MW (50.0 MW under study).
Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.
The following flowgates remain after considering the topology reinforcements required by the cycle.
| Study | Area | Facility Description | Contingency Name | Contingency Type | DC|AC | Final Cycle Loading | Rating (MVA) | Rating Type | MVA to Mitigate | MW Contribution | |
|---|---|---|---|---|---|---|---|---|---|---|---|
| GD2 | AEP | 05BOKESCRK-05MARYSV 345.0 kV Ckt 1 line | Base Case | Single | AC | 110.22 % | 897.0 | A | 988.66 | 3.18 |
The following flowgates were eliminated after considering the topology reinforcements required by the cycle.
| Study | Area | Facility Description | Contingency Name | Contingency Type | DC|AC | Final Cycle Loading | Rating (MVA) | Rating Type | MVA to Mitigate | MW Contribution | |
|---|---|---|---|---|---|---|---|---|---|---|---|
| GD2 | AEP | 05BOKESCRK-05MARYSV 345.0 kV Ckt 1 line | AEP_P1-2_#7441_100545_SRT-A | Single | AC | 111.71 % | 1301.0 | B | 1453.37 | 4.04 | |
| GD2 | AEP | 05E LIMA-05SW LIM 345.0 kV Ckt 1 line | AEP_P1-2_#6497_SRT-A | Single | AC | 105.4 % | 971.0 | B | 1023.39 | 2.8 | |
| GD2 | AEP | 05GUNN RD SW-05BOKESCRK 345.0 kV Ckt 1 line | Base Case | Single | AC | 102.46 % | 897.0 | A | 919.08 | 3.26 | |
| GD2 | AEP | 05GUNN RD SW-05BOKESCRK 345.0 kV Ckt 1 line | AEP_P1-2_#7441_100545_SRT-A | Single | AC | 100.53 % | 1301.0 | B | 1307.92 | 4.14 | |
| GD2 | AEP | 05HAVILAND1-05E LIMA 138.0 kV Ckt 1 line | AEP_P4_#7445_05MARYSV 765_B_SRT-A | Breaker | AC | 120.15 % | 205.0 | B | 246.3 | 5.99 | |
| GD2 | AEP | 05HAVILAND1-05E LIMA 138.0 kV Ckt 1 line | AEP_P1-2_#7441_100545_SRT-A | Single | AC | 118.36 % | 205.0 | B | 242.63 | 6.0 | |
| GD2 | AEP | 05HAVILAND1-05E LIMA 138.0 kV Ckt 1 line | AEP_P4_#7441_05SORENS 765_J1_SRT-A | Breaker | AC | 118.36 % | 205.0 | B | 242.63 | 6.0 | |
| GD2 | AEP | 05HAVILAND1-05E LIMA 138.0 kV Ckt 1 line | AEP_P4_#7446_05MARYSV 765_B2_SRT-A | Breaker | AC | 116.47 % | 205.0 | B | 238.77 | 5.97 | |
| GD2 | AEP | 05HAVILAND1-05E LIMA 138.0 kV Ckt 1 line | AEP_P1-2_#6463_16757_SRT-A | Single | AC | 115.69 % | 205.0 | B | 237.17 | 6.2 | |
| GD2 | AEP | 05HAVILAND1-05E LIMA 138.0 kV Ckt 1 line | AEP_P4_#6463_05E LIMA 345_M2_SRT-A | Breaker | AC | 115.69 % | 205.0 | B | 237.17 | 6.2 | |
| GD2 | AEP | 05HAVILAND1-05E LIMA 138.0 kV Ckt 1 line | AEP_P4_#2995_05E LIMA 345_M_SRT-A | Breaker | AC | 114.6 % | 205.0 | B | 234.92 | 6.11 | |
| GD2 | AEP | 05HAVILAND1-05E LIMA 138.0 kV Ckt 1 line | AEP_P7-1_#11010___SRT-A | Tower | AC | 110.68 % | 205.0 | B | 226.88 | 6.33 | |
| GD2 | AEP | 05HAVILAND2-05HAVILAND1 138.0 kV Ckt Z1 line | AEP_P4_#7445_05MARYSV 765_B_SRT-A | Breaker | AC | 108.33 % | 240.0 | B | 260.0 | 8.12 | |
| GD2 | AEP | 05HAVILAND2-05HAVILAND1 138.0 kV Ckt Z1 line | Base Case | Single | AC | 106.73 % | 187.0 | A | 199.59 | 7.99 | |
| GD2 | AEP | 05HAVILAND2-05HAVILAND1 138.0 kV Ckt Z1 line | AEP_P1-2_#7441_100545_SRT-A | Single | AC | 106.31 % | 240.0 | B | 255.15 | 8.13 | |
| GD2 | AEP | 05HAVILAND2-05HAVILAND1 138.0 kV Ckt Z1 line | AEP_P4_#7441_05SORENS 765_J1_SRT-A | Breaker | AC | 106.31 % | 240.0 | B | 255.15 | 8.13 | |
| GD2 | AEP | 05HAVILAND2-05HAVILAND1 138.0 kV Ckt Z1 line | AEP_P4_#7446_05MARYSV 765_B2_SRT-A | Breaker | AC | 104.92 % | 240.0 | B | 251.8 | 8.11 | |
| GD2 | AEP | 05HAVILAND2-05HAVILAND1 138.0 kV Ckt Z1 line | AEP_P1-2_#6463_16757_SRT-A | Single | AC | 103.77 % | 240.0 | B | 249.05 | 8.34 | |
| GD2 | AEP | 05HAVILAND2-05HAVILAND1 138.0 kV Ckt Z1 line | AEP_P4_#6463_05E LIMA 345_M2_SRT-A | Breaker | AC | 103.77 % | 240.0 | B | 249.05 | 8.34 | |
| GD2 | AEP | 05HAVILAND2-05HAVILAND1 138.0 kV Ckt Z1 line | AEP_P4_#2995_05E LIMA 345_M_SRT-A | Breaker | AC | 102.9 % | 240.0 | B | 246.95 | 8.27 | |
| GD2 | AEP | 05HYATT-05VASSEL 345.0 kV Ckt 1 line | AEP_P1-3_#7222_05MALIS 765_1_SRT-A | Single | AC | 101.52 % | 1409.0 | B | 1430.39 | 2.87 | |
| GD2 | AEP | 05TIMBER SW-05HAVILAND2 138.0 kV Ckt 1 line | AEP_P4_#7445_05MARYSV 765_B_SRT-A | Breaker | AC | 101.22 % | 240.0 | B | 242.93 | 10.16 |
Short Circuit Analysis
Analysis Complete - No Issues
Based on PJM’s TC2 Phase II Short Circuit Analysis, this project did not contribute >1% fault duty to any previously identified overdutied breakers, nor did it cause any new overdutied breakers.
Please note that in TC2 Phase III, PJM will perform additional analysis including the evaluation of impacts from topology upgrades which may have potential effects on breaker duties not seen in the Phase II analysis.
Stability Analysis
Analysis Complete - No Issues
Executive Summary
New Service Requests AG2-029, AG2-104 and AG2-370 in PJM Transition Cycle 2, Cluster 39 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 39 projects.
This analysis is effectively a screening study to determine whether the addition of the Cluster 39 projects will meet the dynamics requirements of the NERC, AEP and PJM reliability standards.
The load flow scenario for the analysis was based on the RTEP 2028 Summer Peak, modified to include applicable projects. Cluster 39 projects have been dispatched online at maximum power output, with 1.0 voltage at the terminal bus.
Transition Cycle 2 Cluster 39 will be tested for compliance with NERC, PJM and other applicable criteria. The contingencies will be studied with a 20 second simulation time. Contingencies to be studied include:
a. Steady-state operation (Category P0);
b. Three-phase faults with normal clearing time (and with unsuccessful high-speed reclosing) (Category P1);
c. Single-phase bus faults with normal clearing time (Category P2);
d. Single-phase faults with stuck breaker (Category P4);
e. Single-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure (Category P5);
f. Three-phase faults with loss of multiple-circuit tower line; (and with unsuccessful high-speed reclosing) (Category P7).
High Speed Reclosing (HSR) facilities were found in the vicinity of TC2 Cluster 39 projects.
Prior outage scenarios will not be considered for this study.
For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.
For all the fault contingencies tested on the 2028 Summer Peak Load case:
a) Cluster 39 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
b) The system with Cluster 39 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
c) Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
d) No transmission element tripped, other than those either directly connected or designed to trip because of that fault.
AG2-029 exhibited slow reactive power recovery within the 20-second simulation window for several contingencies. While this issue did not cause instability in the system, the plant controller model was tuned to achieve a faster reactive power output and mitigate the observed slow recovery. Specifically, the plant controller model REPCA1 was updated by updating Kp, Ki, and Kc to 0.2, 2, and 0.15, respectively, and these modifications are pending the developer’s confirmation.
AG2-104 exhibited slow reactive power recovery within the 20-second simulation window for several contingencies. While this issue did not cause instability in the system, the plant controller model was tuned to achieve a faster reactive power output and mitigate the observed slow recovery. Specifically, plant controller model PLNTBU1 was updated by updating Kc to 0.15, and this modification has been approved by the developer.
It was observed that various units tripped during P1.38 contingency due to the fault at Logtown 138. After further investigation, the trippings were attributed to T-131 wind units as listed below connecting to Logtown which was confirmed by creating a bench case with all Cluster 39 projects offline and observing the similar tripping instances.
a) TR3_G114 with ID: ‘W1’ (PSS/E Bus# 270191),
b) TR4_S_V150 with ID: ‘W1’ (PSS/E Bus# 270246),
c) TR4_N_V150 with ID: ‘W3’ (PSS/E Bus# 270247),
d) TR4_N_V136 with ID: ‘W2’ (PSS/E Bus# 247521).
After G-netting the above units, the simulation results were found to be stable. Therefore, it was concluded Cluster 39 projects do not attribute to the generator tripping instances.
In a number of contingencies, AG1-368 showed slow reactive power dynamics without imposing any instability issues.
Flatlick Generators as well as AE1-021 exhibited slow damping dynamics in P4.29-P4.34, P4.38, P4.42, and P4.46. The slow dynamics did not cause any instability issues. Additionally, the simulations were run for 40 seconds, and the system was found to be stable.
The IPCMD and IQCMD states in the REGCA1 model of AG2-029 showed erratic behavior for some contingencies in which AG2-029 has been disconnected as part of the contingency event. Since the machines are disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.
The IPCMD and IQCMD states in the REGCA1 model of AG2-104 showed erratic behavior for some contingencies in which AG2-104 has been disconnected as part of the contingency event. Since the machines are disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.
The IPCMD and IQCMD states in the REGCA1 model of AG2-370 showed erratic behavior for some contingencies in which AG2-370 has been disconnected as part of the contingency event. Since the machines are disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.
No mitigations were found to be required.
Table 1: Transition Cycle 2 Cluster 39 Projects |
|
|
|
|
Project | Fuel Type | Transmission Owner | MFO (MW) | Point of Interconnection |
AG2-029 | Solar | AEP | 250 | Dunton Lake – Forest G Hiple 345 kV |
AG2-104 | Solar | AEP | 200 | Marysville – Flatlick 765 kV |
AG2-370 | Battery | AEP | 50 | Tillman substation 138 kV |
Reactive Power Analysis
Analysis Complete - No Issues
The reactive power capability of AG2-370 meets the 0.95 leading and lagging PF requirement at the high side of the main transformer.
Steady-State Voltage Analysis
Analysis Complete - No Issues
Steady State Voltage Analysis complete, no voltage issues identified.
New Service Request Dependencies
The New Service Requests below are listed in one or more dispatch for the overloads identified in this report. These projects contribute to the loading of the overloaded facilities identified in this report. The percent overload of a facility and cost allocation you may have towards a particular reinforcement could vary depending on the action of other projects. The status of each project at the time of the analysis is presented in the table. This list may change as other projects withdraw or modify their requests. This table is valid for load flow analyses only.
| New Service Requests Dependencies | ||
|---|---|---|
| Project ID | Project Name | Status |
| AA1-018 | Powerton-Goodings Grove | In Service |
| AB2-170 | East Lima-Marysville 345kV | In Service |
| AC1-111 | Aurora 138kV | In Service |
| AC1-174 | Losantville 345kV | In Service |
| AC1-175 | Losantville 345kV | In Service |
| AC2-044 | Maddox Creek 345kV | Suspended |
| AC2-090 | Losantville 345kV | In Service |
| AC2-154 | Davis Creek 138kV | Engineering & Procurement |
| AC2-176 | Jay 138 kV | In Service |
| AD1-013 | Twombly Road 138kV | Engineering & Procurement |
| AD1-100 | Loretto-Wilton 345 kV & Braidwood-Davis Creek 345 kV | Under Construction |
| AD1-106 | North Waldo-Wild Creek 138 kV | Withdrawn |
| AD1-130 | Hardin Switch 345 kV | In Service |
| AD2-020 | Valley 138 kV | Engineering & Procurement |
| AD2-038 | Powerton-Nevada 345 kV | Under Construction |
| AD2-047 | Davis Creek 138 kV | Suspended |
| AD2-060 | Davis Creek 138kV | Engineering & Procurement |
| AD2-066 | Mazon-Crescent Ridge 138 kV | Under Construction |
| AD2-071 | Strawton-Deer Creek 138 kV | Suspended |
| AD2-079 | Capitol Ave 34.5kV | In Service |
| AD2-086 | Hardin Switch 345 kV | In Service |
| AD2-091 | Hardin Tap 345kV | Suspended |
| AD2-092 | Marysville 345kV | Withdrawn |
| AD2-093 | Marysville 345kV | Partially in Service - Under Construction |
| AD2-096 | Marysville 345kV | Suspended |
| AE1-090 | Hardin Switch 345 kV | In Service |
| AE1-091 | West Newton-Lynn 138 kV | Suspended |
| AE1-102 | Maddox Creek 345 kV | Suspended |
| AE1-113 | Mole Creek 345 kV | Under Construction |
| AE1-146 | Ebersole #2-Fostoria Central 138 kV | Under Construction |
| AE1-166 | Loretto-Wilton 345 kV & Braidwood-Davis Creek 345 kV | Engineering & Procurement |
| AE1-170 | Kenzie Creek-Colby 138 kV | Suspended |
| AE1-172 | Loretto-Wilton Center | Withdrawn |
| AE1-207 | Mississinewa-Gaston 138 kV | Suspended |
| AE1-208 | Delaware-Van Buren 138 kV | Suspended |
| AE1-209 | Desoto 345 kV | Suspended |
| AE1-210 | Desoto 345 kV | Suspended |
| AE1-245 | Haviland 138 kV | Partially in Service - Under Construction |
| AE2-072 | East Leipsic-Richland 138 kV | In Service |
| AE2-089 | Pennville-Adams 138 kV | Suspended |
| AE2-152 | Loretto-Wilton 345 kV & Braidwood-Davis Creek 345 kV | Engineering & Procurement |
| AE2-169 | Delaware-Van Buren 138 kV | Suspended |
| AE2-172 | Mississinewa-Gaston 138 kV | Suspended |
| AE2-206 | East Sidney-Quincy 138 kV | In Service |
| AE2-216 | Hardin Switch 345 kV | Suspended |
| AE2-219 | Bluff Point-Randolph 138 kV | Suspended |
| AE2-220 | Losantville 345 kV | Engineering & Procurement |
| AE2-234 | Liberty Center-Buckeye Tap 69 kV | Engineering & Procurement |
| AE2-236 | Columbia-Northeast 138 kV | Suspended |
| AE2-255 | Molecreek 345 kV | Under Construction |
| AE2-282 | East Fayette 138 kV | In Service |
| AE2-306 | Gunn Road 345 kV | Under Construction |
| AE2-323 | Twin Branch-Guardian 138 kV | Partially in Service - Under Construction |
| AE2-325 | Valley 138 kV | Withdrawn |
| AE2-341 | Sandwich-Plano 138 kV | Engineering & Procurement |
| AF1-030 | Sandwich-Plano 138 kV | Engineering & Procurement |
| AF1-078 | East Sidney-Quincy 138 kV | In Service |
| AF1-084 | Hartford-Almena 69 kV | Under Construction |
| AF1-091 | Varner - Sowers 138 kV | Engineering & Procurement |
| AF1-092 | Huntington Jct. 138 kV | Withdrawn |
| AF1-118 | Sorenson-Desoto 345 kV | Withdrawn |
| AF1-119 | Keystone-Desoto 345 kV | Engineering & Procurement |
| AF1-120 | East Fayette 2 138 kV | In Service |
| AF1-158 | Edison-Gravel Pit 138 kV | In Service |
| AF1-176 | Corey 138 kV | Engineering & Procurement |
| AF1-202 | Keystone-Desoto 345 kV | Under Construction |
| AF1-205 | Napoleon Muni 138 kV | Suspended |
| AF1-206 | East Fayette 138 kV | Engineering & Procurement |
| AF1-215 | Olive-Reynolds 345 kV | In Service |
| AF1-223 | Keystone-Desoto 345 kV | Under Construction |
| AF1-227 | Marysville – Gunn Road 345 kV | In Service |
| AF1-229 | Galion-South Berwick 345 kV | Under Construction |
| AF1-268 | Desoto-Jay 138 kV | Engineering & Procurement |
| AF1-285 | Gunn Road 345 kV | Under Construction |
| AF1-331 | Twombley Road | Engineering & Procurement |
| AF2-014 | Maddox Creek 345 kV | Under Construction |
| AF2-068 | Jay 138 kV | Engineering & Procurement |
| AF2-083 | Kenzie Creek-Stone Lake 69 kV | Under Construction |
| AF2-095 | Davis Creek 138 kV | Engineering & Procurement |
| AF2-103 | Haviland 138 kV | In Service |
| AF2-126 | Weston 69 kV II | Under Construction |
| AF2-132 | Reynolds-Olive #1 345 kV | Under Construction |
| AF2-133 | Reynolds-Olive #2 345 kV | Under Construction |
| AF2-134 | Olive-Reynolds #2 345 kV | In Service |
| AF2-142 | Nevada 345 kV | Engineering & Procurement |
| AF2-143 | Powerton-Nevada 345 kV | Engineering & Procurement |
| AF2-162 | Keystone-Desoto 345 kV | Engineering & Procurement |
| AF2-177 | Sorenson-DeSoto #2 345 kV | Engineering & Procurement |
| AF2-224 | Allen 345 kV | Engineering & Procurement |
| AF2-350 | Kensington 138 kV | Engineering & Procurement |
| AF2-359 | Olive-University Park 345 kV | Engineering & Procurement |
| AF2-366 | Crego Rd 138 kV | Engineering & Procurement |
| AF2-375 | Ebersole-Fostoria 138 kV | Engineering & Procurement |
| AF2-376 | Timber Switch 138 kV | Engineering & Procurement |
| AF2-377 | Logtown 138 kV | Engineering & Procurement |
| AF2-388 | Keystone-Desoto 345 kV | Engineering & Procurement |
| AF2-396 | Stinger 138 kV | Engineering & Procurement |
| AG1-017 | Jay 138 kV | In Service |
| AG1-047 | Jay 138 kV | Engineering & Procurement |
| AG1-118 | Sugar Grove-Waterman 138kV | Engineering & Procurement |
| AG1-127 | Crego Rd 138 kV | Engineering & Procurement |
| AG1-232 | Magley 138 kV | Engineering & Procurement |
| AG1-302 | Olive-Reynolds #1 345 kV | Under Construction |
| AG1-324 | Jay-Desoto 138 kV | Engineering & Procurement |
| AG1-349 | Olive-Reynolds #2 345 kV | Engineering & Procurement |
| AG1-365 | Allen 345 kV | Engineering & Procurement |
| AG1-366 | Allen 345 kV | Engineering & Procurement |
| AG1-368 | Tillman 138 kV | Engineering & Procurement |
| AG1-369 | Logtown 138 kV | Engineering & Procurement |
| AG1-410 | Maddox Creek-RP Mone 345 kV | Engineering & Procurement |
| AG1-411 | Maddox Creek-RP Mone 345 kV | Engineering & Procurement |
| AG1-414 | Mississinewa 138 kV | Engineering & Procurement |
| AG1-433 | Keystone-DeSoto 345 kV | Engineering & Procurement |
| AG1-436 | Olive-University Park 345 kV | Engineering & Procurement |
| AG1-447 | Olive-University Park 345 kV | Engineering & Procurement |
| AG1-478 | Wilmington 34.5 kV | Engineering & Procurement |
| AG1-554 | South Kenton 138 kV | Engineering & Procurement |
| AG2-029 | Forest G. Hipple-Dunton Lake 345 kV | Active |
| AG2-061 | Dana 345 kV | Active |
| AG2-191 | Mississinewa 138 kV | Active |
| AG2-192 | Mississinewa 138 kV | Active |
| AG2-230 | Dumont 345 kV | Active |
| AG2-245 | Olive - Reynolds #1 345 kV | Active |
| AG2-453 | Lasalle - Plano 345 kV | Active |
| AG2-519 | Royerton - Desoto 138 kV | Active |
| AG2-524 | LaSalle Station - Mazon 138 kV | Active |
| AG2-550 | Bluff Point - Randolph 138 kV | Active |
| AG2-551 | Bluff Point - Randolph 138 kV | Active |
| AG2-585 | Kensignton 138kV | Active |
| AH1-153 | Dumont 345 kV | Active |
| AH1-196 | Silver Lake - Cherry Valley 345 kV | Active |
| AH1-272 | Argenta - Twin Branch 345 kV | Active |
| AH1-338 | New Sub S2354 138kV | Active |
| AH1-392 | Gravel Pit-Kankakee 138 kV | Active |
| AH1-482 | Olive - Reynolds #2 345 kV | Active |
| AH1-543 | Mulberry - Tazewell 345 kV | Active |
| AH1-567 | University Park 138 kV | Active |
| AH1-698 | Braidwood 345 kV | Active |
| AH1-702 | Byron 345 kV | Active |
| AH1-711 | Lemoyne 345 kV | Active |
| AH1-714 | Lasalle 345 kV | Active |
| AH1-718 | Nelson 345 kV | Active |
| U2-072 | East Lima-Marysville 345kV | In Service |
| V1-011 | Haviland 138kV | In Service |
| V3-007 | Desoto-Tanners Creek #1 345kV | In Service |
| W1-056 | Ada-Dunkirk 69kV | In Service |
| X3-005 | Wildwood 12kV | In Service |
| Y3-023 | Country Side 12kV | In Service |
| Y3-024 | Bluff Point 12kV | In Service |
| Z2-115 | Deer Creek 12.47kV | In Service |
| Z2-116 | Twin Branch 12.47kV | In Service |
Affected System - PJM Identified Violations
As part of PJM's analysis, per Tariff Part VII.G.336 & Manual 14H, Section 13, PJM evaluated the potential impacts on tie line facilities between PJM and an affected system entity, which were identified per PJM planning analysis criteria. This upgrade may be required on the affected system portion of the tie line along with cost allocation of such upgrade if applicable, in coordination with the affected system. Depending on the affected system, this project may not be contingent on upgrade based on PJM planning analysis criteria, but may be contingent on this upgrade based on the Affected System Operator's planning criteria, provided in the Affected Systems Study Section, herein.
Affected System - Non-PJM Identified Violations
In accordance with PJM Tariff Part VII, Subpart D, section 310.A and as outlined in PJM Manual 14H, Sections 4.5 and 13, in Phase II of the Cycle, PJM provides the Affected System Operator any updates on the PJM projects that require an Affected Systems Study based on their response at DP1. New Service Requests that require an Affected Systems Study are required to enter into an Affected Systems Study Agreement with the Affected System Operator, as applicable, prior to the close of DP2 or they will be withdrawn from the Cycle.
If the Project Developer already entered into the necessary agreement and the results are available, PJM will supply them in the Phase II SIS report. See below for the status of any required Affected Systems Study. A status of “Pending” means that the study is not yet completed by the Affected System Operator. If your project requires an Affected Systems Study and your results are not provided for Phase II SIS, PJM anticipates providing them in the Phase III SIS per Tariff Part VII.D.312.
System Reinforcements
Based on the Phase II System Impact Study analysis results, this project is contingent on and may have cost responsibility for the following System Reinforcements:
| TO | RTEP ID | Title | Category | Allocated Cost ($USD) | Facilities Study |
|---|---|---|---|---|---|
| AEP | b3972.1 | Sag Study and Clearance Mitigation: East Lima-Haviland | Contingent | $0 | N/A |
| AEP | b3971.1 | Reconductor Haviland 138 kV bus | Contingent | $0 | N/A |
| Grand Total: | $0 | ||||
Shown below are the details of the cost allocated, contingent, eliminated, topology and potential aggregate contributor reinforcements for this project. Please refer to the System Reinforcement table above and the information below for more detail.
System Reinforcement: b4000.11
- Type
- Load Flow
- TO
- APS
- RTEP ID / TO ID
- b4000.11
- Title
- Expand Black Oak Substation & Loop in the 502 Jct-Woodside 500 kV line (Projected ISD 6/1/2029)
- Description
- Expand Black Oak Substation to accommodate the connection of the 502 Jct-Woodside 500 kV line and loop the 502 Jct-Woodside 500 kV line into the Black Oak substation by constructing ~0.85 miles of new 500 kV line into and out of Black Oak 500 kV substation
- Cost Information
- Time Estimate
- Jun 01 2029
Not ContingentTopology Changing Note 1: AG2-370 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-370 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 05HYATT-05VASSEL 345.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.1
- Type
- Load Flow
- TO
- AEP
- RTEP ID / TO ID
- b4000.1
- Title
- Add two 765 kV breakers at Amos Substation to expand the breaker and a half scheme to accommodate the new Amos-Welton Spring 765 kV line (Projected ISD 6/1/2029)
- Description
- 765kV Solution: 2024 W1 Solution - Regional Cluster Ties Doubs 500kV area to John Amos 765kV via a new 765kV line
- Cost Information
- Time Estimate
- Jun 01 2029
Not ContingentTopology Changing Note 1: AG2-370 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-370 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 05HYATT-05VASSEL 345.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.2
- Type
- Load Flow
- TO
- APS
- RTEP ID / TO ID
- b4000.2
- Title
- Construct a new 175 miles Amos to Welton Spring 765 kV line - AEP Section of the line is 30 miles (Projected ISD 6/1/2029)
- Description
- 765kV Solution: 2024 W1 Solution - Regional Cluster Ties Doubs 500kV area to John Amos 765kV via a new 765kV line
- Cost Information
- Time Estimate
- Jun 01 2029
Not ContingentTopology Changing Note 1: AG2-370 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-370 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 05HYATT-05VASSEL 345.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.3
- Type
- Load Flow
- TO
- APS
- RTEP ID / TO ID
- b4000.3
- Title
- Construct a new 175 miles Amos to Welton Spring 765 kV line - APS/FE Section of the line is 145 miles (Projected ISD 6/1/2029)
- Description
- 765kV Solution: 2024 W1 Solution - Regional Cluster Ties Doubs 500kV area to John Amos 765kV via a new 765kV line
- Cost Information
- Time Estimate
- Jun 01 2029
Not ContingentTopology Changing Note 1: AG2-370 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-370 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 05HYATT-05VASSEL 345.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.4
- Type
- Load Flow
- TO
- APS
- RTEP ID / TO ID
- b4000.4
- Title
- Construct a new 765 kV switchyard - Welton Spring (Projected ISD 6/1/2029)
- Description
- 765kV Solution: 2024 W1 Solution - Regional Cluster Ties Doubs 500kV area to John Amos 765kV via a new 765kV line
- Cost Information
- Time Estimate
- Jun 01 2029
Not ContingentTopology Changing Note 1: AG2-370 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-370 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 05HYATT-05VASSEL 345.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.5
- Type
- Load Flow
- TO
- APS
- RTEP ID / TO ID
- b4000.5
- Title
- Install four 250 MVAR shunt capacitors, and a +/-500 MVAR STATCOM at Welton Spring 765 kV substation
- Description
- 765kV Solution: 2024 W1 Solution - Regional Cluster Ties Doubs 500kV area to John Amos 765kV via a new 765kV line
- Cost Information
- Time Estimate
- Jun 01 2029
Not ContingentTopology Changing Note 1: AG2-370 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-370 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 05HYATT-05VASSEL 345.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.8
- Type
- Load Flow
- TO
- APS
- RTEP ID / TO ID
- b4000.8
- Title
- Construct a new 86 miles Welton Spring to Rocky Point 765 kV line (DVP local area to Rocky Point, roughly 4.8 miles)
- Description
- 765kV Solution: 2024 W1 Solution - Regional Cluster Ties Doubs 500kV area to John Amos 765kV via a new 765kV line
- Cost Information
- Time Estimate
- Jun 01 2029
Not ContingentTopology Changing Note 1: AG2-370 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-370 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 05HYATT-05VASSEL 345.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.9
- Type
- Load Flow
- TO
- APS
- RTEP ID / TO ID
- b4000.9
- Title
- Construct a new substation called Rocky Point with a 765 kV and a 500 kV yard (Projected ISD 6/1/2029)
- Description
- Construct a new substation called Rocky Point with a 765 kV and a 500 kV yard. Loop in the Doubs-Goose Creek 500 kV line, the Doubs-Aspen 500 kV line, and the Woodside-Goose Creek 500 kV line. Install two 765/500 kV transformer at Rocky Point substation. 765kV Solution: 2024 W1 Solution - Regional Cluster Ties Doubs 500kV area to John Amos 765kV via a new 765kV line
- Cost Information
- Time Estimate
- Jun 01 2029
Not ContingentTopology Changing Note 1: AG2-370 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-370 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 05HYATT-05VASSEL 345.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.10
- Type
- Load Flow
- TO
- APS
- RTEP ID / TO ID
- b4000.10
- Title
- Install four 250 MVAR cap banks (two on 765 and two on 500 kV side) and a +/-500 MVAR STATCOM on the 765 kV Rocky Point yard
- Description
- 765kV Solution: 2024 W1 Solution - Regional Cluster Ties Doubs 500kV area to John Amos 765kV via a new 765kV line
- Cost Information
- Time Estimate
- Jun 01 2029
Not ContingentTopology Changing Note 1: AG2-370 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-370 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 05HYATT-05VASSEL 345.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.7
- Type
- Load Flow
- TO
- APS
- RTEP ID / TO ID
- b4000.7
- Title
- Construct a new 86 miles Welton Spring to Rocky Point 765 kV line - in DVP local area/Millville to Lovettsville section, roughly 10.5 miles (Projected ISD 6/1/2029)
- Description
- 765kV Solution: 2024 W1 Solution - Regional Cluster Ties Doubs 500kV area to John Amos 765kV via a new 765kV line
- Cost Information
- Time Estimate
- Jun 01 2029
Not ContingentTopology Changing Note 1: AG2-370 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-370 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 05HYATT-05VASSEL 345.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.6
- Type
- Load Flow
- TO
- APS
- RTEP ID / TO ID
- b4000.6
- Title
- Construct a new 86 miles Welton Spring to Rocky Point 765 kV line (Welton Spring to DVP local area, roughly 21 miles) (VA Portion)
- Description
- 765kV Solution: 2024 W1 Solution - Regional Cluster Ties Doubs 500kV area to John Amos 765kV via a new 765kV line
- Cost Information
- Time Estimate
- Jun 01 2029
Not ContingentTopology Changing Note 1: AG2-370 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-370 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 05HYATT-05VASSEL 345.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4068.1
- Type
- Load Flow
- TO
- AEP
- RTEP ID / TO ID
- b4068.1 / AEP-TC2-18693
- Title
- b4068: Greentown 765 kV - Teddy 765kV - Marysville 765 kV - Greenfield Line - AEP Proposal 570
- Description
- b4068.1 through b4068.49: Affected Transmission Owners: AEP / Dayton / ATSI The objective of this project is to construct multiple transmission lines to address Ohio area violations. The total distance covered by the lines is approximately 359.54 miles. The first transmission line ranges from the existing Greentown Substation in Howard County, Indiana to the new Teddy Substation in Clark County, Ohio, the line then branches north towards the existing Marysville Substation in Union County, Ohio, and east to the existing Beatty Substation in Franklin County, Ohio, and then extends to the existing Cole Substation in Franklin County, Ohio. The second transmission line extends from the existing Adkins Substation in Pickaway County, Ohio, to the new West Millersport Substation in Fairfield County, Ohio, then continues to the existing Conesville Substation in Coshocton County, Ohio before finally extending to the existing Guernsey Substation in Guernsey County, Ohio. There is a total of five transmission lines that extend between unnamed substations (Hayden - Cole 345 kV, Hyatt - Maliszewski 345 kV [double circuit], Roberts - Kenny 138 kV, Wilson - 5th Avenue 138 kV, West Millersport-Kirk 345 kV). This project will traverse 4 counties (Howard, Grant, Blackford, Jay) in Indiana, and 13 counties (Darke, Shelby, Champaign, Clark, Madison, Franklin, Delaware, Pickaway, Fairfield, Licking, Muskingum, Coshocton, Guernsey) in Ohio. This proposal has a total of 38 components, including 16 substation upgrade components, two greenfield substation components, eight greenfield transmission line components covering approximately 336.2 miles, and 12 transmission line upgrade components covering approximately 23.34 miles. b4068.28/b4068.49 is dependent on b3919.1 Baseline completion.
- Cost Information
- Time Estimate
- Jun 01 2030
Not ContingentTopology Changing Note 1: AG2-370 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-370 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 05E LIMA-05SW LIM 345.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 05E LIMA-05MADDOX 345.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 05MARYSV-05BOKESCRK 345.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 05GUNN RD SW-05BOKESCRK 345.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 05SORENS-05SORENS 345.0/765.0 kV Ckt 3 transformer | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b3919.1
- Type
- Load Flow
- TO
- AEP
- RTEP ID / TO ID
- b3919.1
- Title
- Reconfigure Maliszewski 765 kV station and establish 345 kV breaker yard
- Description
- Reconfigure Maliszewski 765 kV station from 2 breakers to a 6 breaker ring bus. Install a new 765/345 kV transformer. Establish new 345 kV breaker yard with 3 string breaker and a half to include a line exit to Hyatt and a line exit to Corridor. Loop the existing Hyatt - West Millersport 345 kV line into the new established 345 kV yard at the Maliszewski station.
- Cost Information
- Time Estimate
- Jun 01 2029
Not ContingentTopology Changing Note 1: AG2-370 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-370 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 05E LIMA-05SW LIM 345.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 05E LIMA-05MADDOX 345.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 05MARYSV-05BOKESCRK 345.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 05GUNN RD SW-05BOKESCRK 345.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 05SORENS-05SORENS 345.0/765.0 kV Ckt 3 transformer | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b3972.1
- Type
- Load Flow
- TO
- AEP
- RTEP ID / TO ID
- b3972.1
- Title
- Sag Study and Clearance Mitigation: East Lima-Haviland
- Description
- Perform a ratings study and clearance mitigation on the ~5.55-mile section of sag derated 556.5 ACSR 26/7 DOVE conductor (East Lima-STR 28) between the East Lima-Haviland 138 kV circuit on the East Lima-West Lima 138 kV line.
- Cost Information
- Time Estimate
- Apr 15 2030
Contingent Note: Although AG2-370 may not presently have cost responsibility for this upgrade, AG2-370 may need this upgrade in-service to be deliverable to the PJM system. If AG2-370 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.
| Facility | Contingency | ||||||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 05E LIMA-05HAVILAND1 138.0 kV Ckt 1 line | (Any) |
|
System Reinforcement: b3971.1
- Type
- Load Flow
- TO
- AEP
- RTEP ID / TO ID
- b3971.1
- Title
- Reconductor Haviland 138 kV bus
- Description
- At Haviland, reconductor bus No. 1 Sub cond 500 MCM CU 37 Str toward Haviland bus No. 2 and reconductor Haviland bus No. 2 500 KCM CU, 37-Str. and 795 KCM AAC, 37-Str. toward Timber SW 138 kV.
- Cost Information
- Time Estimate
- Jun 01 2030
Contingent Note: Although AG2-370 may not presently have cost responsibility for this upgrade, AG2-370 may need this upgrade in-service to be deliverable to the PJM system. If AG2-370 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.
| Facility | Contingency | ||||||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 05HAVILAND1-05HAVILAND2 138.0 kV Ckt Z1 line | (Any) |
| |||||||||||||||||||||||||||||||
| 05HAVILAND2-05TIMBER SW 138.0 kV Ckt 1 line | (Any) |
|
System Reinforcement: b3851.2
- Type
- Load Flow
- TO
- AEP
- RTEP ID / TO ID
- b3851.2
- Title
- Rebuild R.P. Mone – Maddox Creek 345kV line (9.4 miles).
- Description
- Rebuild R.P. Mone – Maddox Creek 345kV line (9.4 miles).
- Cost Information
- Time Estimate
- Jun 01 2027
Not Contingent Note: AG2-370 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-370 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.
| Facility | Contingency | ||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 05MADDOX-AG1-410 TP 345.0 kV Ckt 1 line | (Any) |
| |||||||||||||
| 05RPMONE-AG1-410 TP 345.0 kV Ckt 1 line | (Any) |
|
System Reinforcement: b3919.5
- Type
- Load Flow
- TO
- AEP
- RTEP ID / TO ID
- b3919.5 / (Pending)
- Title
- Reconductor 4.75-miles of the existing Bokes Creek-Marysville 345 kV circuit.
- Description
- Reconductor 4.75-miles of the existing Bokes Creek-Marysville 345 kV circuit. Update the associated relay settings.
- Cost Information
- Time Estimate
- Jun 01 2029
Not Contingent Note: AG2-370 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-370 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.
| Facility | Contingency | ||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 05MARYSV-05BOKESCRK 345.0 kV Ckt 1 line | (Any) |
|
System Reinforcement: b3851.1
- Type
- Load Flow
- TO
- AEP
- RTEP ID / TO ID
- b3851.1 / B3851.1
- Title
- Rebuild Allen-RP Mone 345kV
- Description
- Rebuild Allen –R.P. Mone 345kV line (18.6 miles).
- Cost Information
- Time Estimate
- Jun 01 2027
Not Contingent Note: AG2-370 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AG2-370 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.
| Facility | Contingency | |||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 05RPMONE-05ALLEN 345.0 kV Ckt 1 line | (Any) |
|