AG2-545 Phase II System Impact Study Report

v1.00 released 2026-06-03 17:54

Silver Lake 345 kV

160.0 MW Capacity / 400.0 MW Energy

Introduction

This Phase II System Impact Study (SIS) Report has been prepared in accordance with the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 310 for New Service Requests (projects) in Transition Cycle 2 (TC2). The Project Developer/Eligible Customer (developer) is Monarch Grid, LLC, and the Transmission Provider (TP) is PJM Interconnection, LLC (PJM). The interconnected Transmission Owner (TO) is Commonwealth Edison Company.

Preface

The Phase II System Impact Study is conducted on an aggregate basis within a New Services Request’s Cycle, and results are provided in both (i) a single Cycle summary format and (ii) an individual project-level basis. The Phase II System Impact Study Results (for both the summary and individual reports) will be publicly available on PJM’s website. Project Developers must obtain the results from the website.

In accordance with PJM Manual 14H, section 4.5, PJM takes the following actions during the Phase II System Impact Study:

  1. PJM will retool load flow results from the Phase I System Impact Study (summer peak, winter peak and light load) based on decisions made by Project Developers or Eligible Customers during Decision Point I.
  2. PJM will conduct any required voltage analyses.
  3. PJM will perform short circuit and stability analyses as required.
  4. PJM will coordinate with the Affected System to confirm which projects in the PJM Cycle will require Affected System studies. If the Affected System Operator indicates that an Affected System study is required, PJM will:
    1. Notify the Project Developer or Eligible Customer of the need for an Affected System study and the requirement to execute an Affected System study agreement with the impacted Affected System Operator, and;
    2. Include the results of the Affected System Operator’s Affected System Study in the Phase II System Impact Study results, if applicable and available.
  5. The Phase II System Impact Study Results will be publicly available on PJM’s website. Project Developers and Eligible Customers must obtain the results from the website.

The Transmission Owner takes the following actions during the Phase II System Impact Study:

  1. Verify Interconnection Facilities and Network Upgrades required to accommodate the New Service Request.
  2. Perform a Facilities Study. The Facilities Study in Phase II System Impact Study phase will be for the physical Interconnection Facilities. The Facilities Study requirements are outlined in Attachment C of this manual. The study will be conducted pursuant to Tariff, Part VII, Subpart D, section 307(A)(7) and Tariff, Part VIII, Subpart C, section 404(A)(7).

Decision Point II Requirements

At the close of Phase II System Impact Study, PJM will initiate Decision Point II (DP2). During DP2, the Project Developer will have 30 days to decide whether to proceed with their project. If the Project Developer elects to proceed, they should provide the elements defined in the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 311.A. Additional information on these elements is available in PJM Manual 14H sections 4.6, 6, and 7.

Allowable project modifications at Decision Point II are defined in PJM Open Access Transmission Tariff, Part VII, Subpart D, section 311.B. Additional information regarding allowable project modifications can be found in PJM Manual 14H, section 9.8.

Adverse Test Eligibility

This New Service Request does not meet the Adverse Study Impact Criteria and has the option to either move forward in the Cycle process or withdraw at DP2 with Readiness Deposit #1 forfeited. See adverse study impact calculation below.

This section details whether a Project Developer or Eligible Customer qualifies for the Adverse Study Impact clause outlined in the PJM OATT, Part VII, Subpart D, section 311.B and Manual 14H, section 6.2.2. In order to qualify for an Adverse Study Impact at Decision Point II, the Network Upgrade cost from Phase I to Phase II must:

  1. Increase overall by 25% or more
  2. Increases by more than $10,000 per MW (Includes Costs identified in Affected System studies)

If a New Service Request meets the criteria above and chooses to withdraw the request, PJM will refund the cumulative Readiness Deposit amounts paid at the Application Phase and at Decision Point I (RD1 and RD2, respectively).

The below calculations show the computation of this New Service Request's Adverse Study Impact

DP2 Adverse Eligibility = DP2 Adverse Cost Alloc DP1 Adverse Cost Alloc > 1.25 AND ( DP2 Adverse Cost Alloc - DP1 Adverse Cost Alloc ) Project Size > $10,000 per MW
DP2 Adverse Eligibility = $2,962,562 $3,750,000 = 0.79 AND ( $2,962,562 - $3,750,000 ) 400.0 = $-1,969 per MW

General

The Project Developer has proposed an uprate to a planned/existing Storage facility located in the Commonwealth Edison Company zone — McHenry County, Illinois. This project is an increase to the developer’s AG2-544 project(s), which will share the same Point of Interconnection. The AG2-545 project is a 400.0 MW uprate (160.0 MW Capacity uprate) to the previous project(s). The total installed facilities will have a capability of 400.0 MW with 240.0 MW of this output being recognized by PJM as Capacity.

Project Information
New Service Request Number:
AG2-545
Project Name:
Silver Lake 345 kV
Project Developer Name:
Monarch Grid, LLC
State:
Illinois
County:
McHenry
Transmission Owner:
Commonwealth Edison Company
MFO:
400.0
MWE:
400.0
MWC:
160.0
Battery Storage Specification:
1600.0 MWh, 4.0-hr class
Grid Charging:
Yes
Fuel Type:
Storage
Basecase Study Year:
2028

Physical Interconnection Facility Study

Report Available

The transmission owner has completed the Physical Interconnection Facilities Study. This report is available for download.

Point of Interconnection

AG2-545 will interconnect on the Commonwealth Edison Company transmission system at the Silver Lake 345 kV substation.

Cost Summary

The table below shows a summary of the total cost estimates for this New Service Request project. In Phase II SIS, the interconnected Transmission Owner has performed a facilities study for both the Transmission Owner Interconnection Facilities (TOIF) and Physical Interconnection Network Upgrades. The System Reliability Network Upgrade shown in the table are planning level cost estimates which are subject to change as a result of a facility study performed by the TO during Phase III System Impact Study.

Based on the Phase II SIS results, the AG2-545 project has the following allocation of costs for interconnection. The cost contribution towards Readiness Deposit #3 are also shown below.

Cost Summary
DescriptionCost Allocated to AG2-545Cost Subject to Readiness*Cost Subject to Adverse
Transmission Owner Interconnection Facilities (TOIF)$364,020$0$0
Other Scope$194,801$0$0
Option To Build Oversight$0$0$0
Physical Interconnection Network Upgrades
Stand Alone Network Upgrades$0$0$0
Network Upgrades$2,860,014$2,860,014$2,860,014
System Reliability Network Upgrades
Steady State Thermal & Voltage$0$0$0
Transient Stability$0$0$0
Short Circuit$0$0$0
Transmission Owner Analysis
SubRegional$0$0$0
Distribution$0$0$0
Affected System Reinforcements
AFS - PJM Violations$0$0$0
AFS - Non-PJM Violations$102,548$0$102,548
Total$3,521,383$2,860,014$2,962,562

* Contributes to calculation for Readiness Deposit #3 (RD3). See Readiness Deposit section of report for additional detail.

Definitions

Transmission Owner Interconnection Facilities: Facilities that are owned, controlled, operated and maintained by the Transmission Owner on the Transmission Owner’s side of the Point of Change of Ownership to the Point of Interconnection, including any modifications, additions or upgrades made to such facilities and equipment, that are necessary to physically and electrically interconnect the Generating Facility with the Transmission System or interconnected distribution facilities.

Stand Alone Network Upgrades: Network Upgrades, which are not part of an Affected System, which a Project Developer may construct without affecting day-to-day operations (e.g. taking a transmission outage) of the Transmission System during their construction.

Network Upgrades: Modifications or additions to transmission-related facilities that are integrated with and support the Transmission Provider’s overall Transmission System for the general benefit of all users of such Transmission System. Network Upgrades have no impact or potential impact on the Transmission System until the final tie-in is complete.

Notes

Note 1: PJM Open Access Transmission Tariff (OATT), Part VII, Subpart D, section 307.5 outlines cost allocation rules. The rules are further clarified in PJM Manual 14H, section 4.2.6. PJM shall identify the New Service Requests in the Cycle contributing to the need for the required Network Upgrades within the Cycle. All New Service Requests that contribute to the need for a Network Upgrade will receive cost allocation for that upgrade pursuant to each New Service Request’s contribution to the reliability violation identified on the transmission system in accordance with PJM Manuals.

Note 2: There will be no inter-Cycle cost allocation for Interconnection Facilities or Network Upgrades identified in the System Impact Study costs identified in a Cycle; all such costs shall be allocated to New Service Requests in that Cycle.

Note 3: For Project Developers with System Reinforcements listed: If this project presents cost allocation to a System Reinforcement indicates $0, then please be aware that as changes to the interconnection process occur, such as other projects withdrawing, reducing in size, etc, the cost responsibilities can change and a cost allocation may be assigned to this project. In addition, although this project presents cost allocation to a System Reinforcement is presently $0, this project may need this system reinforcement completed to be deliverable to the PJM system. If this project desires to come into service prior to completion of the system reinforcement, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the system reinforcement is complete.

Note 4: Please see the ‘Affected Systems Studies’ section of this Phase II SIS report for details on your project’s need for an Affected Systems Study. If your project requires an Affected Systems Study, the Affected Systems impacts may not be available from the Affected System Operator at the time of the PJM Phase II SIS. Therefore, the cost in this section would not reflect any required upgrades by the Affected System until the study is completed. If your project requires an Affected Systems Study and your results are not provided for Phase II SIS, PJM anticipates providing them in the Phase III SIS per Tariff Part VII.D.312.

Readiness Deposit

Per Tariff Part VII, Subpart D, section 311 (Decision Point II) A.1.b and PJM Manual 14H, section 6.2, Readiness Deposit #3 (RD3) are funds committed by the Project Developer or Eligible Customer based upon the applicable contribution to Network Upgrades as defined below. Readiness Deposits are not used to fund studies nor to offset Security.

During Decision Point II (DP2), the Project Developer or Eligible Customer is required to submit Readiness Deposit #3, which is calculated as 20% of cost allocation for required Phase II Network Upgrades minus Readiness Deposit #1 & Readiness Deposit #2.

Note 1: “Network Upgrades” referred to in the calculation include both (i) the Physical Interconnection Network Upgrades and (ii) the System Reliability Network Upgrades as shown in the Cost Summary table.

Note 2: Readiness Deposit #1 (RD1) = ($4,000 * Project Size (MW))

Note 3: Readiness Deposit #2 (RD2) = 10% of cost allocation for required Network Upgrades minus RD1. Readiness Deposit #2 (RD2) can be zero, but may not be a negative number.

Note 4: Readiness Deposit #3 can be zero, but may not be a negative number.

Readiness Deposit #3 Due for Project AG2-545

Readiness Deposit #3 has been calculated for the project based on the Phase II System Impact Study results and is shown in the table below. This Readiness Deposit #3 must be provided at Decision Point II through either a wire transfer or letter of credit per Manual 14H, Section 6.2.

Readiness Deposit #3 Due for AG2-545
Project ID: AG2-545
20% of cost allocation for Phase II Network Upgrades:(A) $572,003
Sum of Readiness Deposit #1 & Readiness Deposit #2 Received:(B) $1,600,000
Readiness Deposit #3 (RD3) due at DP2:(A) - (B) = $0
Note: Failure to provide an acceptable form of Readiness Deposit #3 by the end of Decision Point II will result in withdrawal and termination of the New Service Request.

For additional detail regarding Readiness Deposit Refunds, reference PJM Manual 14H, section 6.2.1. The Readiness Deposit Letter of Credit template can be found here.

Transmission Owner Scope of Work

If your project relies on Transmission Owner Interconnection Facilities, Stand Alone Network Upgrades, and/or Network Upgrades that will be constructed by another New Service Request and the other New Service Request withdraws, the scope and costs will be allocated to your project.

The total preliminary cost estimate for the Transmission Owner scope of work (including TOIF and Physical Interconnection Network Upgrades) is given in the table below. These costs do not include CIAC Tax Gross-up.

Transmission Owner Build Option
Network Upgrades
RTEP IDDescriptionDirectIndirectTotal Cost ($USD)Allocated Cost ($USD)
LaborMaterialsLaborMaterials
(Pending)

Install (2) physically diverse single-mode fiber paths (min. 48-count each) from the FDP in the TSS 138 Silver Lake control building to the customer collector substation

$77,223$2,113$12,252$126$91,714$45,857 (See Note 1)
(Pending)

TSS 138 Silver Lake, 345 kV Bus Expansion (Network Upgrades)work

$3,085,080$1,938,719$489,467$115,049$5,628,315$2,814,158 (See Note 1)
Other
RTEP IDDescriptionDirectIndirectTotal Cost ($USD)Allocated Cost ($USD)
LaborMaterialsLaborMaterials
(Pending)

Metering requirment for TSS138

$83,704$276,226$13,280$16,392$389,602$194,801 (See Note 1)
Transmission Owner Interconnection Facilities
RTEP IDDescriptionDirectIndirectTotal Cost ($USD)Allocated Cost ($USD)
LaborMaterialsLaborMaterials
(Pending)

Install one 345 kV dead-end structures and 345 kV line conductor from the dead-end structures to the Point of Interconnection

$386,325$264,712$61,293$15,709$728,039$364,020 (See Note 1)
Developer Build Option

(No Developer Build Option for this project.)

Build Option Price Comparison
Build OptionTotal CostAllocated Cost
Transmission Owner Build Option$6,837,670$3,418,835
Developer Build Option(No Developer Build Option)

Based on the scope of work for the Interconnection Facilities, it is expected to take a range of 1 to 60 month(s) after the signing of a Generator Interconnection Agreement (as this is a FERC connection) and construction kickoff call to complete the installation of the physical connection work. This assumes that there will be no environmental issues with any of the new properties associated with this project, that there will be no delays in acquiring the necessary permits for implementing the defined interconnection work, and that all system outages will be allowed when requested.

Note that the TO findings were made from a conceptual review of this project. A more detailed review of the connection facilities and their cost will be identified in a future study phase. Further note that the cost estimate data provided should be considered high level estimates since it was produced without a detailed engineering review. The Project Developer will be responsible for the actual cost of construction. TO herein reserves the right to return to any issues in this document and, upon appropriate justification, request additional monies to complete any reinforcements to the transmission systems.

Remote Terminal Work: During Phase II of the PJM interconnection process, TO’s System Protection Engineering Department will review transmission line protection as well as anti-islanding required to accommodate the new generation and interconnection substation. System Protection Engineering will determine the minimal acceptable protection requirements to reliably interconnect the proposed generating facility with the transmission system. The review is based on maintaining system reliability by reviewing TO’s protection requirements with the known transmission system configuration which includes generating facilities in the area. This review may determine that transmission line protection and communication upgrades are required at remote substations.

Note 1: A Common Use Upgrade is a Network Upgrade that is needed for the interconnection of Generating Facilities or Merchant Transmission Facilities of more than one Project Developer or Eligible Customer and which is the shared responsibility of each Project Developer or Eligible Customer. If multiple Project Developers request to connect to the same interconnection substation, the Transmission Owner will determine the cost to accommodate all the requests at the substation. The cost for the interconnection will be allocated in proportion to the number of required terminations into the substation.

Notes on Cost Estimate:

  1. These estimates are order-of-magnitude estimates of the costs that ComEd would bill to the Project Developer for this interconnection. These estimates are based on a one-line electrical diagram of the project and the information provided by the Project Developer.
  2. There were no site visits performed for these estimates. There may be costs related to specific site related issues that are not identified in these estimates. The site reviews will be performed during the Facilities Study or during detailed engineering.
  3. These estimates are not a guarantee of the maximum amount payable by the Project Developer and the actual costs of ComEd's work may differ significantly from these estimates. The Project Developer will be responsible for paying actual costs of ComEd's work in accordance with the PJM Open Access Transmission Tariff.
  4. The Project Developer is responsible for all engineering, procurement, testing and construction of all equipment on the Project Developer’s side of the Point of Change in Ownership.

 

 

Transmission Owner Analysis

No Transmission Owner impacts identified.

 

Developer Requirements

The developer is responsible for all design and construction related activities on the developer’s side of the Point of Change in Ownership. ComEd interconnection requirements can be found here.

To the extent that these Applicable Technical Requirements and Standards may conflict with the terms and conditions of the Tariff, the Tariff shall control.

Revenue Metering and SCADA Requirements

PJM Requirements
The developer will be required to install equipment necessary to provide Revenue Metering (KWH, KVARH) and real time data (KW, KVAR) for their generating Resource. See PJM Manual 01, PJM Manual 14D, and PJM Tariff Part IX, Subpart B, Appendix 2, section 8.
Transmission Owner Requirements
The Project Developer will be required to comply with all interconnected Transmission Owner’s revenue metering requirements located at the following link: PJM - Transmission Owner Engineering & Construction Standards.

Summer Peak Analysis

The New Service Request AG2-545 was evaluated as a 400.0 MW (160.0 MW Capacity) injection in the ComEd area.

AG2-545 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 400.0 MW (400.0 MW under study).

Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.

The following flowgates remain after considering the topology reinforcements required by the cycle.

StudyAreaFacility DescriptionContingency NameContingency TypeDC|ACFinal Cycle LoadingRating (MVA)Rating TypeMVA to MitigateMW ContributionDetails
IPDAEP
05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line
AP_P2-3_PE-765-237806-SB2_SRT-SL_SENS
BreakerAC218.16 %1180.0B2574.34
30.13
IPDAEP
05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line
AP_P2-3_PE-765-237806-SB1_SRT-SL_SENS
BreakerAC218.16 %1180.0B2574.34
30.13
IPDAEP
05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line
AP_P1-2_PE-765-237805-237806_SRT-A_SENS
SingleAC218.16 %1180.0B2574.34
30.13
IPDAEP
05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line
AP_P1-2_PE-765-242508-237805_SRT-A_SENS
SingleAC218.14 %1180.0B2574.07
30.13
IPDAEP
05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line
DVP_P7-1: LN 2168-555_SRT-A
TowerAC189.79 %1180.0B2239.56
25.38
IPDAEP
05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line
DVP_P7-1: LN 2114-535_SRT-A_SENS
TowerAC186.12 %1180.0B2196.19
24.54
IPDAEP
05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line
DVP_P2-2: BREMO B1_SRT-A
BusAC182.08 %1180.0B2148.53
24.32
IPDAEP
05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line
DVP_P2-2: ALTAVISTA 138KV_SRT-A
BusAC181.75 %1180.0B2144.69
24.4
IPDAEP
05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line
Base Case
SingleAC178.04 %1180.0A2100.93
24.35

Details for [AG2-545] 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line l/o AP_P2-3_PE-765-237806-SB2_SRT-SL_SENS


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Addition to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:AEP
Facility Description:
05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line
Contingency Name:
AP_P2-3_PE-765-237806-SB2_SRT-SL_SENS
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:218.16 %
Rating:1180.0 MVA
Rating Type:B
MVA to Mitigate:2574.34
MW Contribution:
30.13
IPD Plant:AG2-545
Impact of Topology Modeling:
Addition
Bus #Bus NameTypeMW Contribution
970871AG2-544 GEN
PJM_IPD_GROUP
15.065
970873AG2-545 GEN
PJM_IPD_GROUP
30.129

Details for [AG2-545] 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line l/o AP_P2-3_PE-765-237806-SB1_SRT-SL_SENS


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Addition to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:AEP
Facility Description:
05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line
Contingency Name:
AP_P2-3_PE-765-237806-SB1_SRT-SL_SENS
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:218.16 %
Rating:1180.0 MVA
Rating Type:B
MVA to Mitigate:2574.34
MW Contribution:
30.13
IPD Plant:AG2-545
Impact of Topology Modeling:
Addition
Bus #Bus NameTypeMW Contribution
970871AG2-544 GEN
PJM_IPD_GROUP
15.065
970873AG2-545 GEN
PJM_IPD_GROUP
30.129

Details for [AG2-545] 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line l/o AP_P1-2_PE-765-237805-237806_SRT-A_SENS


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Addition to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:AEP
Facility Description:
05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line
Contingency Name:
AP_P1-2_PE-765-237805-237806_SRT-A_SENS
Contingency Type:Single
DC|AC:AC
Final Cycle Loading:218.16 %
Rating:1180.0 MVA
Rating Type:B
MVA to Mitigate:2574.34
MW Contribution:
30.13
IPD Plant:AG2-545
Impact of Topology Modeling:
Addition
Bus #Bus NameTypeMW Contribution
970871AG2-544 GEN
PJM_IPD_GROUP
15.065
970873AG2-545 GEN
PJM_IPD_GROUP
30.129

Details for [AG2-545] 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line l/o AP_P1-2_PE-765-242508-237805_SRT-A_SENS


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Addition to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:AEP
Facility Description:
05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line
Contingency Name:
AP_P1-2_PE-765-242508-237805_SRT-A_SENS
Contingency Type:Single
DC|AC:AC
Final Cycle Loading:218.14 %
Rating:1180.0 MVA
Rating Type:B
MVA to Mitigate:2574.07
MW Contribution:
30.13
IPD Plant:AG2-545
Impact of Topology Modeling:
Addition
Bus #Bus NameTypeMW Contribution
970871AG2-544 GEN
PJM_IPD_GROUP
15.065
970873AG2-545 GEN
PJM_IPD_GROUP
30.129

Details for [AG2-545] 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line l/o DVP_P7-1: LN 2168-555_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Addition to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:AEP
Facility Description:
05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line
Contingency Name:
DVP_P7-1: LN 2168-555_SRT-A
Contingency Type:Tower
DC|AC:AC
Final Cycle Loading:189.79 %
Rating:1180.0 MVA
Rating Type:B
MVA to Mitigate:2239.56
MW Contribution:
25.38
IPD Plant:AG2-545
Impact of Topology Modeling:
Addition
Bus #Bus NameTypeMW Contribution
970871AG2-544 GEN
PJM_IPD_GROUP
12.69
970873AG2-545 GEN
PJM_IPD_GROUP
25.38

Details for [AG2-545] 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line l/o DVP_P7-1: LN 2114-535_SRT-A_SENS


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Addition to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:AEP
Facility Description:
05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line
Contingency Name:
DVP_P7-1: LN 2114-535_SRT-A_SENS
Contingency Type:Tower
DC|AC:AC
Final Cycle Loading:186.12 %
Rating:1180.0 MVA
Rating Type:B
MVA to Mitigate:2196.19
MW Contribution:
24.54
IPD Plant:AG2-545
Impact of Topology Modeling:
Addition
Bus #Bus NameTypeMW Contribution
970871AG2-544 GEN
PJM_IPD_GROUP
12.269
970873AG2-545 GEN
PJM_IPD_GROUP
24.539

Details for [AG2-545] 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line l/o DVP_P2-2: BREMO B1_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Addition to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:AEP
Facility Description:
05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line
Contingency Name:
DVP_P2-2: BREMO B1_SRT-A
Contingency Type:Bus
DC|AC:AC
Final Cycle Loading:182.08 %
Rating:1180.0 MVA
Rating Type:B
MVA to Mitigate:2148.53
MW Contribution:
24.32
IPD Plant:AG2-545
Impact of Topology Modeling:
Addition
Bus #Bus NameTypeMW Contribution
970871AG2-544 GEN
PJM_IPD_GROUP
12.159
970873AG2-545 GEN
PJM_IPD_GROUP
24.318

Details for [AG2-545] 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line l/o DVP_P2-2: ALTAVISTA 138KV_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Addition to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:AEP
Facility Description:
05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line
Contingency Name:
DVP_P2-2: ALTAVISTA 138KV_SRT-A
Contingency Type:Bus
DC|AC:AC
Final Cycle Loading:181.75 %
Rating:1180.0 MVA
Rating Type:B
MVA to Mitigate:2144.69
MW Contribution:
24.4
IPD Plant:AG2-545
Impact of Topology Modeling:
Addition
Bus #Bus NameTypeMW Contribution
970871AG2-544 GEN
PJM_IPD_GROUP
12.202
970873AG2-545 GEN
PJM_IPD_GROUP
24.404

Details for [AG2-545] 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line l/o Base Case


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Addition to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:AEP
Facility Description:
05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line
Contingency Name:
Base Case
Contingency Type:Single
DC|AC:AC
Final Cycle Loading:178.04 %
Rating:1180.0 MVA
Rating Type:A
MVA to Mitigate:2100.93
MW Contribution:
24.35
IPD Plant:AG2-545
Impact of Topology Modeling:
Addition
Bus #Bus NameTypeMW Contribution
970871AG2-544 GEN
PJM_IPD_GROUP
12.177
970873AG2-545 GEN
PJM_IPD_GROUP
24.354
CONTINGENCY 'AP_P2-3_PE-765-237806-SB2_SRT-SL_SENS'
 DISCONNECT BRANCH FROM BUS 237805 TO BUS 237806 CKT 1   /*01WELTON_SPR 765.0 - 01ROCKYPOINT 765.0
 REMOVE SWSHUNT FROM BUS 237806 BLOCK 1 STEP 2           /*01ROCKYPOINT 765.0
END
CONTINGENCY 'AP_P2-3_PE-765-237806-SB1_SRT-SL_SENS'
 DISCONNECT BRANCH FROM BUS 237805 TO BUS 237806 CKT 1   /*01WELTON_SPR 765.0 - 01ROCKYPOINT 765.0
 REMOVE SWSHUNT FROM BUS 237806 BLOCK 1 STEP 1           /*01ROCKYPOINT 765.0
END
CONTINGENCY 'AP_P1-2_PE-765-237805-237806_SRT-A_SENS'
 DISCONNECT BRANCH FROM BUS 237805 TO BUS 237806 CKT 1   /*01WELTON_SPR 765.0 - 01ROCKYPOINT 765.0
END
CONTINGENCY 'AP_P1-2_PE-765-242508-237805_SRT-A_SENS'
 DISCONNECT BRANCH FROM BUS 242508 TO BUS 237805 CKT 1   /*05AMOS       765.0 - 01WELTON_SPR 765.0
END
CONTINGENCY 'DVP_P7-1: LN 2168-555_SRT-A'
 OPEN BRANCH FROM BUS 314794 TO BUS 314854 CKT 1   /*6DOOMS       230.0 - 6LEXNGT1     230.0
 OPEN BRANCH FROM BUS 314907 TO BUS 314912 CKT 1   /*8DOOMS       500.0 - 8LEXNGTN     500.0
END
CONTINGENCY 'DVP_P7-1: LN 2114-535_SRT-A_SENS'
 OPEN BRANCH FROM BUS 235110 TO BUS 289543 CKT 1   /*01MDWBRK     500.0 - 05YEAT       500.0
 OPEN BRANCH FROM BUS 314085 TO BUS 314110 CKT 1   /*6REMNGCT     230.0 - 6ELK RUN     230.0
 OPEN BRANCH FROM BUS 314110 TO BUS 314125 CKT 1   /*6ELK RUN     230.0 - 6VINTHIL     230.0
 OPEN BUS 314110                                   /*6ELK RUN     230.0
END
CONTINGENCY 'DVP_P2-2: BREMO B1_SRT-A'
 OPEN BRANCH FROM BUS 313867 TO BUS 314747 CKT 1   /*6BREMODIST   230.0 - 6BREMO       230.0
 OPEN BRANCH FROM BUS 314326 TO BUS 314747 CKT 1   /*6BEARGRDN    230.0 - 6BREMO       230.0
 OPEN BRANCH FROM BUS 314326 TO BUS 314747 CKT 2   /*6BEARGRDN    230.0 - 6BREMO       230.0
 OPEN BRANCH FROM BUS 314744 TO BUS 314747 CKT 1   /*3BREMO       115.0 - 6BREMO       230.0
 OPEN BRANCH FROM BUS 970936 TO BUS 314747 CKT 1   /*AG2-583 TP   230.0 - 6BREMO       230.0
 OPEN BRANCH FROM BUS 972002 TO BUS 314747 CKT 1   /*AH1-546 TP   230.0 - 6BREMO       230.0
 OPEN BUS 314326                                   /*6BEARGRDN    230.0
 OPEN BUS 314747                                   /*6BREMO       230.0
 OPEN BUS 315191                                   /*1BEARGRDN G1  18.0
 OPEN BUS 315192                                   /*1BEARGRDN G2  18.0
 OPEN BUS 315193                                   /*1BEARGRDN S1  18.0
END
CONTINGENCY 'DVP_P2-2: ALTAVISTA 138KV_SRT-A'
 OPEN BUS 314348   /*2GRETN_1      69.0
 OPEN BUS 314667   /*4ALTVSTA     138.0
 OPEN BUS 314670   /*2ALTVSTA      69.0
 OPEN BUS 314680   /*2CHATHAM      69.0
 OPEN BUS 314685   /*2CHTM TP      69.0
 OPEN BUS 314698   /*2TAYLORS MIL  69.0
 OPEN BUS 314709   /*2GLADYS TAP   69.0
 OPEN BUS 314727   /*2CLIMAX DP    69.0
 OPEN BUS 314728   /*2CLMX TP      69.0
 OPEN BUS 314729   /*2GLADYS       69.0
 OPEN BUS 314730   /*3STONE MILL   69.0
 OPEN BUS 314731   /*2GRETNA       69.0
 OPEN BUS 314733   /*2GRNA DP      69.0
 OPEN BUS 314735   /*2ALTAVISTADP  69.0
 OPEN BUS 314736   /*2SHKO DP      69.0
 OPEN BUS 314738   /*2MT AIRY      69.0
 OPEN BUS 314739   /*2MT A TP      69.0
 OPEN BUS 316193   /*RENANTP       69.0
 OPEN BUS 316194   /*AC1-042 MAIN  69.0
 OPEN BUS 316195   /*AC1-042 COL   34.0
 OPEN BUS 316196   /*AC1-042 TERT  13.0
 OPEN BUS 316197   /*AC1-042 GEN    0.4
 OPEN BUS 316214   /*AC1-145 MAIN  69.0
 OPEN BUS 316215   /*AC1-145 COL2  34.5
 OPEN BUS 316216   /*AC1-145 COL1  34.5
 OPEN BUS 316217   /*AC1-145 GEN    0.6
END
290614 to 242515 ckt 1

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)

Winter Peak Analysis

The New Service Request AG2-545 was evaluated as a 400.0 MW (160.0 MW Capacity) injection in the ComEd area.

AG2-545 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 400.0 MW (400.0 MW under study).

Note: The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for single or N-1 contingencies and multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.

The following flowgates remain after considering the topology reinforcements required by the cycle.

StudyAreaFacility DescriptionContingency NameContingency TypeDC|ACFinal Cycle LoadingRating (MVA)Rating TypeMVA to MitigateMW ContributionDetails
IPDAEP
05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line
DVP_P1-2: LN 553_SRT-A_SENS
SingleAC191.01 %1180.0B2253.93
25.75
IPDAEP
05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line
DVP_P4-2: 542T553_SRT-W_SENS
BreakerAC188.6 %1180.0B2225.5
25.83
IPDAEP
05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line
DVP_P4-2: 553T564_SRT-W_SENS
BreakerAC187.55 %1180.0B2213.15
25.86
IPDAEP
05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line
AP_P1-2_PE-765-242508-237805_SRT-A_SENS
SingleAC182.58 %1180.0B2154.48
31.08
IPDAEP
05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line
DVP_P7-1: LN 2168-555_SRT-A
TowerAC163.16 %1180.0B1925.24
26.08
IPDAEP
05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line
DVP_P7-1: LN 2114-535_SRT-A_SENS
TowerAC161.1 %1180.0B1901.03
25.2
IPDAEP
05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line
DVP_P2-2: BREMO B1_SRT-A
BusAC157.07 %1180.0B1853.41
24.98
IPDAEP
05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line
AEP_P2-2_#10265_05LEESVI 138_1_SRT-A
BusAC156.72 %1180.0B1849.3
25.15
IPDAEP
05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line
Base Case
SingleAC152.41 %1180.0A1798.4
25.04

Details for [AG2-545] 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line l/o DVP_P1-2: LN 553_SRT-A_SENS


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Addition to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:AEP
Facility Description:
05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line
Contingency Name:
DVP_P1-2: LN 553_SRT-A_SENS
Contingency Type:Single
DC|AC:AC
Final Cycle Loading:191.01 %
Rating:1180.0 MVA
Rating Type:B
MVA to Mitigate:2253.93
MW Contribution:
25.75
IPD Plant:AG2-545
Impact of Topology Modeling:
Addition
Bus #Bus NameTypeMW Contribution
970871AG2-544 GEN
PJM_IPD_GROUP
12.877
970873AG2-545 GEN
PJM_IPD_GROUP
25.755

Details for [AG2-545] 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line l/o DVP_P4-2: 542T553_SRT-W_SENS


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Addition to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:AEP
Facility Description:
05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line
Contingency Name:
DVP_P4-2: 542T553_SRT-W_SENS
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:188.6 %
Rating:1180.0 MVA
Rating Type:B
MVA to Mitigate:2225.5
MW Contribution:
25.83
IPD Plant:AG2-545
Impact of Topology Modeling:
Addition
Bus #Bus NameTypeMW Contribution
970871AG2-544 GEN
PJM_IPD_GROUP
12.914
970873AG2-545 GEN
PJM_IPD_GROUP
25.828

Details for [AG2-545] 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line l/o DVP_P4-2: 553T564_SRT-W_SENS


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Addition to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:AEP
Facility Description:
05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line
Contingency Name:
DVP_P4-2: 553T564_SRT-W_SENS
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:187.55 %
Rating:1180.0 MVA
Rating Type:B
MVA to Mitigate:2213.15
MW Contribution:
25.86
IPD Plant:AG2-545
Impact of Topology Modeling:
Addition
Bus #Bus NameTypeMW Contribution
970871AG2-544 GEN
PJM_IPD_GROUP
12.93
970873AG2-545 GEN
PJM_IPD_GROUP
25.861

Details for [AG2-545] 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line l/o AP_P1-2_PE-765-242508-237805_SRT-A_SENS


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Addition to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:AEP
Facility Description:
05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line
Contingency Name:
AP_P1-2_PE-765-242508-237805_SRT-A_SENS
Contingency Type:Single
DC|AC:AC
Final Cycle Loading:182.58 %
Rating:1180.0 MVA
Rating Type:B
MVA to Mitigate:2154.48
MW Contribution:
31.08
IPD Plant:AG2-545
Impact of Topology Modeling:
Addition
Bus #Bus NameTypeMW Contribution
970871AG2-544 GEN
PJM_IPD_GROUP
15.538
970873AG2-545 GEN
PJM_IPD_GROUP
31.076

Details for [AG2-545] 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line l/o DVP_P7-1: LN 2168-555_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Addition to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:AEP
Facility Description:
05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line
Contingency Name:
DVP_P7-1: LN 2168-555_SRT-A
Contingency Type:Tower
DC|AC:AC
Final Cycle Loading:163.16 %
Rating:1180.0 MVA
Rating Type:B
MVA to Mitigate:1925.24
MW Contribution:
26.08
IPD Plant:AG2-545
Impact of Topology Modeling:
Addition
Bus #Bus NameTypeMW Contribution
970871AG2-544 GEN
PJM_IPD_GROUP
13.038
970873AG2-545 GEN
PJM_IPD_GROUP
26.076

Details for [AG2-545] 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line l/o DVP_P7-1: LN 2114-535_SRT-A_SENS


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Addition to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:AEP
Facility Description:
05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line
Contingency Name:
DVP_P7-1: LN 2114-535_SRT-A_SENS
Contingency Type:Tower
DC|AC:AC
Final Cycle Loading:161.1 %
Rating:1180.0 MVA
Rating Type:B
MVA to Mitigate:1901.03
MW Contribution:
25.2
IPD Plant:AG2-545
Impact of Topology Modeling:
Addition
Bus #Bus NameTypeMW Contribution
970871AG2-544 GEN
PJM_IPD_GROUP
12.599
970873AG2-545 GEN
PJM_IPD_GROUP
25.198

Details for [AG2-545] 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line l/o DVP_P2-2: BREMO B1_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Addition to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:AEP
Facility Description:
05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line
Contingency Name:
DVP_P2-2: BREMO B1_SRT-A
Contingency Type:Bus
DC|AC:AC
Final Cycle Loading:157.07 %
Rating:1180.0 MVA
Rating Type:B
MVA to Mitigate:1853.41
MW Contribution:
24.98
IPD Plant:AG2-545
Impact of Topology Modeling:
Addition
Bus #Bus NameTypeMW Contribution
970871AG2-544 GEN
PJM_IPD_GROUP
12.491
970873AG2-545 GEN
PJM_IPD_GROUP
24.981

Details for [AG2-545] 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line l/o AEP_P2-2_#10265_05LEESVI 138_1_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Addition to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:AEP
Facility Description:
05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line
Contingency Name:
AEP_P2-2_#10265_05LEESVI 138_1_SRT-A
Contingency Type:Bus
DC|AC:AC
Final Cycle Loading:156.72 %
Rating:1180.0 MVA
Rating Type:B
MVA to Mitigate:1849.3
MW Contribution:
25.15
IPD Plant:AG2-545
Impact of Topology Modeling:
Addition
Bus #Bus NameTypeMW Contribution
970871AG2-544 GEN
PJM_IPD_GROUP
12.575
970873AG2-545 GEN
PJM_IPD_GROUP
25.15

Details for [AG2-545] 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line l/o Base Case


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Addition to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:AEP
Facility Description:
05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line
Contingency Name:
Base Case
Contingency Type:Single
DC|AC:AC
Final Cycle Loading:152.41 %
Rating:1180.0 MVA
Rating Type:A
MVA to Mitigate:1798.4
MW Contribution:
25.04
IPD Plant:AG2-545
Impact of Topology Modeling:
Addition
Bus #Bus NameTypeMW Contribution
970871AG2-544 GEN
PJM_IPD_GROUP
12.52
970873AG2-545 GEN
PJM_IPD_GROUP
25.041
CONTINGENCY 'DVP_P1-2: LN 553_SRT-A_SENS'
 OPEN BRANCH FROM BUS 314910 TO BUS 313378 CKT 1   /*8CUNINGHAM   500.0 - 8VONTAY      500.0
END
CONTINGENCY 'DVP_P4-2: 542T553_SRT-W_SENS'
 OPEN BRANCH FROM BUS 313378 TO BUS 314910 CKT 1                /*8VONTAY      500.0 - 8CUNINGHAM   500.0
 OPEN BUS 315217                                                /*1CUNINGB      18.0
 OPEN BUS 315218                                                /*1CUNINGC      18.0
 SET POSTCONTRATING 3403 BRANCH FROM BUS 314910 TO BUS 314942 CKT 1 /*8CUNINGHAM   500.0 - 8FLUVANNAEAS 500.0
 SET POSTCONTRATING 3403 BRANCH FROM BUS 314910 TO BUS 314943 CKT 1 /*8CUNINGHAM   500.0 - 8FLUVANNAWES 500.0
 SET PRECONTRATING 3040 BRANCH FROM BUS 314910 TO BUS 314942 CKT 1 /*8CUNINGHAM   500.0 - 8FLUVANNAEAS 500.0
 SET PRECONTRATING 3040 BRANCH FROM BUS 314910 TO BUS 314943 CKT 1 /*8CUNINGHAM   500.0 - 8FLUVANNAWES 500.0
END
CONTINGENCY 'DVP_P4-2: 553T564_SRT-W_SENS'
 OPEN BRANCH FROM BUS 313378 TO BUS 314910 CKT 1                /*8VONTAY      500.0 - 8CUNINGHAM   500.0
 OPEN BUS 315216                                                /*1CUNINGA      18.0
 OPEN BUS 315219                                                /*1CUNINGD      22.0
 SET POSTCONTRATING 3403 BRANCH FROM BUS 314910 TO BUS 314942 CKT 1 /*8CUNINGHAM   500.0 - 8FLUVANNAEAS 500.0
 SET POSTCONTRATING 3403 BRANCH FROM BUS 314910 TO BUS 314943 CKT 1 /*8CUNINGHAM   500.0 - 8FLUVANNAWES 500.0
 SET PRECONTRATING 3040 BRANCH FROM BUS 314910 TO BUS 314942 CKT 1 /*8CUNINGHAM   500.0 - 8FLUVANNAEAS 500.0
 SET PRECONTRATING 3040 BRANCH FROM BUS 314910 TO BUS 314943 CKT 1 /*8CUNINGHAM   500.0 - 8FLUVANNAWES 500.0
END
CONTINGENCY 'AP_P1-2_PE-765-242508-237805_SRT-A_SENS'
 DISCONNECT BRANCH FROM BUS 242508 TO BUS 237805 CKT 1   /*05AMOS       765.0 - 01WELTON_SPR 765.0
END
CONTINGENCY 'DVP_P7-1: LN 2168-555_SRT-A'
 OPEN BRANCH FROM BUS 314794 TO BUS 314854 CKT 1   /*6DOOMS       230.0 - 6LEXNGT1     230.0
 OPEN BRANCH FROM BUS 314907 TO BUS 314912 CKT 1   /*8DOOMS       500.0 - 8LEXNGTN     500.0
END
CONTINGENCY 'DVP_P7-1: LN 2114-535_SRT-A_SENS'
 OPEN BRANCH FROM BUS 235110 TO BUS 289543 CKT 1   /*01MDWBRK     500.0 - 05YEAT       500.0
 OPEN BRANCH FROM BUS 314085 TO BUS 314110 CKT 1   /*6REMNGCT     230.0 - 6ELK RUN     230.0
 OPEN BRANCH FROM BUS 314110 TO BUS 314125 CKT 1   /*6ELK RUN     230.0 - 6VINTHIL     230.0
 OPEN BUS 314110                                   /*6ELK RUN     230.0
END
CONTINGENCY 'DVP_P2-2: BREMO B1_SRT-A'
 OPEN BRANCH FROM BUS 313867 TO BUS 314747 CKT 1   /*6BREMODIST   230.0 - 6BREMO       230.0
 OPEN BRANCH FROM BUS 314326 TO BUS 314747 CKT 1   /*6BEARGRDN    230.0 - 6BREMO       230.0
 OPEN BRANCH FROM BUS 314326 TO BUS 314747 CKT 2   /*6BEARGRDN    230.0 - 6BREMO       230.0
 OPEN BRANCH FROM BUS 314744 TO BUS 314747 CKT 1   /*3BREMO       115.0 - 6BREMO       230.0
 OPEN BRANCH FROM BUS 970936 TO BUS 314747 CKT 1   /*AG2-583 TP   230.0 - 6BREMO       230.0
 OPEN BRANCH FROM BUS 972002 TO BUS 314747 CKT 1   /*AH1-546 TP   230.0 - 6BREMO       230.0
 OPEN BUS 314326                                   /*6BEARGRDN    230.0
 OPEN BUS 314747                                   /*6BREMO       230.0
 OPEN BUS 315191                                   /*1BEARGRDN G1  18.0
 OPEN BUS 315192                                   /*1BEARGRDN G2  18.0
 OPEN BUS 315193                                   /*1BEARGRDN S1  18.0
END
CONTINGENCY 'AEP_P2-2_#10265_05LEESVI 138_1_SRT-A'
 OPEN BRANCH FROM BUS 242701 TO BUS 242802 CKT 1   /*05LEESVI     138.0 - 05SMITHMTN   138.0
 OPEN BRANCH FROM BUS 242701 TO BUS 247284 CKT 1   /*05LEESVI     138.0 - 05LEESVG      13.8
 OPEN BRANCH FROM BUS 242701 TO BUS 314667 CKT 1   /*05LEESVI     138.0 - 4ALTVSTA     138.0
END
290614 to 242515 ckt 1

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)

Light Load Analysis

The New Service Request AG2-545 was evaluated as a 400.0 MW injection and 400.0 MW withdrawal in the ComEd area.

AG2-545 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 400.0 MW (400.0 MW under study).

Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.

The following flowgates remain after considering the topology reinforcements required by the cycle.

StudyAreaFacility DescriptionContingency NameContingency TypeDC|ACFinal Cycle LoadingRating (MVA)Rating TypeMVA to MitigateMW ContributionDetails
IPDAEP
05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line
AEP_P1-2_#7422_16_SRT-A
SingleAC100.21 %1180.0B1182.46
34.83
IPDAEP
05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line
AEP_P4_#7422_05CLOVRD 500_EE2_SRT-A
BreakerAC100.21 %1180.0B1182.46
34.83
IPDAEP
05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line
DVP_P4-2: 56602_SRT-A
BreakerAC100.2 %1180.0B1182.35
34.83

Details for [AG2-545] 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line l/o AEP_P1-2_#7422_16_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Addition to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:AEP
Facility Description:
05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line
Contingency Name:
AEP_P1-2_#7422_16_SRT-A
Contingency Type:Single
DC|AC:AC
Final Cycle Loading:100.21 %
Rating:1180.0 MVA
Rating Type:B
MVA to Mitigate:1182.46
MW Contribution:
34.83
IPD Plant:AG2-545
Impact of Topology Modeling:
Addition
Bus #Bus NameTypeMW Contribution
970871AG2-544 GEN
PJM_IPD_GROUP
17.415
970873AG2-545 GEN
PJM_IPD_GROUP
34.83

Details for [AG2-545] 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line l/o AEP_P4_#7422_05CLOVRD 500_EE2_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Addition to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:AEP
Facility Description:
05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line
Contingency Name:
AEP_P4_#7422_05CLOVRD 500_EE2_SRT-A
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:100.21 %
Rating:1180.0 MVA
Rating Type:B
MVA to Mitigate:1182.46
MW Contribution:
34.83
IPD Plant:AG2-545
Impact of Topology Modeling:
Addition
Bus #Bus NameTypeMW Contribution
970871AG2-544 GEN
PJM_IPD_GROUP
17.415
970873AG2-545 GEN
PJM_IPD_GROUP
34.83

Details for [AG2-545] 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line l/o DVP_P4-2: 56602_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Addition to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:AEP
Facility Description:
05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line
Contingency Name:
DVP_P4-2: 56602_SRT-A
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:100.2 %
Rating:1180.0 MVA
Rating Type:B
MVA to Mitigate:1182.35
MW Contribution:
34.83
IPD Plant:AG2-545
Impact of Topology Modeling:
Addition
Bus #Bus NameTypeMW Contribution
970871AG2-544 GEN
PJM_IPD_GROUP
17.415
970873AG2-545 GEN
PJM_IPD_GROUP
34.83
CONTINGENCY 'AEP_P1-2_#7422_16_SRT-A'
 OPEN BRANCH FROM BUS 242519 TO BUS 314912 CKT 1   /*05CLOVRD     500.0 - 8LEXNGTN     500.0
END
CONTINGENCY 'AEP_P4_#7422_05CLOVRD 500_EE2_SRT-A'
 OPEN BRANCH FROM BUS 242519 TO BUS 314912 CKT 1   /*05CLOVRD     500.0 - 8LEXNGTN     500.0
END
CONTINGENCY 'DVP_P4-2: 56602_SRT-A'
 OPEN BRANCH FROM BUS 242519 TO BUS 314912 CKT 1   /*05CLOVRD     500.0 - 8LEXNGTN     500.0
 OPEN BRANCH FROM BUS 314856 TO BUS 314912 CKT 1   /*6LEXNGT2     230.0 - 8LEXNGTN     500.0
END
290614 to 242515 ckt 1

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)

Short Circuit Analysis

Analysis Complete - No Issues

Based on PJM’s TC2 Phase II Short Circuit Analysis, this project did not contribute >1% fault duty to any previously identified overdutied breakers, nor did it cause any new overdutied breakers.

Please note that in TC2 Phase III, PJM will perform additional analysis including the evaluation of impacts from topology upgrades which may have potential effects on breaker duties not seen in the Phase II analysis.

Stability Analysis

Analysis Complete - No Issues

Executive Summary:

New Service Requests (projects) in PJM Transition Cycle 2, Cluster 62 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 62 projects.

This analysis is effectively a screening study to determine whether the addition of the Cluster 62 projects will meet the dynamics requirements of the NERC, COMED and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2028 summer peak load case, modified to include applicable projects. Cluster 62 projects have been dispatched online at maximum power output and the voltage schedule set to achieve near unity power factor at the high side of the main transformer.

Cluster 62 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 352 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

  1. Three-phase faults with normal clearing time;
  2. Three-phase bus faults with normal clearing time;
  3. Three-phase to ground faults with three-phase delayed clearing due to a stuck breaker (GO breakers);
  4. Three-phase to ground faults with single-phase delayed clearing due to a stuck breaker (IPO breakers)
  5. Three-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure;
  6. Three-phase faults with loss of multiple-circuit tower line.

For all simulations, the Cluster 62 projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the 2028 peak load case:

  1. Cluster 62 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  2. The system with Cluster 62 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3%.
  3. Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
  4. No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

AG2-544 meets the 0.95 leading and lagging PF requirement.

AG2-545 meets the 0.95 leading and lagging PF requirement.

AH1-196 meets the 0.95 leading and lagging PF requirement.

 

No mitigations were found to be required for the Cluster 62 projects.

Table 1: TC2 Cluster 62 Projects

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

AG2-544

Storage

COMED

200

200

80

Silver Lake 345 kV

AG2-545

Storage

COMED

400

400

160

AH1-196

Solar

COMED

150

150

90

Prairie 345 kV

 

Reactive Power Analysis

Analysis Complete - No Issues

The reactive power capability of AG2-545 meets the 0.95 leading and lagging PF requirement at the high side of the main transformer.

Steady-State Voltage Analysis

Analysis Complete - No Issues

Steady State Voltage Analysis complete, no voltage issues identified.

New Service Request Dependencies

The New Service Requests below are listed in one or more dispatch for the overloads identified in this report. These projects contribute to the loading of the overloaded facilities identified in this report. The percent overload of a facility and cost allocation you may have towards a particular reinforcement could vary depending on the action of other projects. The status of each project at the time of the analysis is presented in the table. This list may change as other projects withdraw or modify their requests. This table is valid for load flow analyses only.

(No dependencies were identified)

Affected System - PJM Identified Violations

As part of PJM's analysis, per Tariff Part VII.G.336 & Manual 14H, Section 13, PJM evaluated the potential impacts on tie line facilities between PJM and an affected system entity, which were identified per PJM planning analysis criteria. This upgrade may be required on the affected system portion of the tie line along with cost allocation of such upgrade if applicable, in coordination with the affected system. Depending on the affected system, this project may not be contingent on upgrade based on PJM planning analysis criteria, but may be contingent on this upgrade based on the Affected System Operator's planning criteria, provided in the Affected Systems Study Section, herein.

Midcontinent Independent System Operator, Inc. (MISO)No Impact
New York Independent System Operator (NYISO)No Impact
Tennessee Valley Authority (TVA)No Impact
Louisville Gas & Electric (LG&E)No Impact
Duke Energy Carolinas (DUKE)No Impact
Duke Energy Progress – East (CPLE)No Impact
Duke Energy Progress – West (CPLW)No Impact

Affected System - Non-PJM Identified Violations

In accordance with PJM Tariff Part VII, Subpart D, section 310.A and as outlined in PJM Manual 14H, Sections 4.5 and 13, in Phase II of the Cycle, PJM provides the Affected System Operator any updates on the PJM projects that require an Affected Systems Study based on their response at DP1. New Service Requests that require an Affected Systems Study are required to enter into an Affected Systems Study Agreement with the Affected System Operator, as applicable, prior to the close of DP2 or they will be withdrawn from the Cycle.

If the Project Developer already entered into the necessary agreement and the results are available, PJM will supply them in the Phase II SIS report. See below for the status of any required Affected Systems Study. A status of “Pending” means that the study is not yet completed by the Affected System Operator. If your project requires an Affected Systems Study and your results are not provided for Phase II SIS, PJM anticipates providing them in the Phase III SIS per Tariff Part VII.D.312.

Midcontinent Independent System Operator, Inc. (MISO)Identified Impacts
Note: This reflects the Affected System studies results provided by the Affected System Operator. These results may be subject to adjustments based on the outcome of any studies in the remaining phases of the Affected System Operator's Generator Interconnection Process.
Impacted FacilityTransmission OwnerReinforcementCostCost Allocated to AG2-545Scenarios
  • 17REYNOLDS 765.0 - 05GRNTWN 765.0 CKT 1
NIPS Reynolds-Greentown 765 kV
NIPSCO: No mitigation required. Rating Of NIPS-
Owned
Line Portion: SN/SE=9015 MVA/9015 MVA.

AEP: No mitigation required. 8348 MVA SN/SE
$0$0
  • NIPSCO
  • Contingent
  • Wvrich 69.0 - Rochester TP 69.0 CKT 1
NIPS Wvrich - Rochester TP 69 kV
DEI: Rebuild 1 mile of 69kV with 477ACSR/VR2 @
100/120C the ratings assume that NIPSCO terminal
upgrades would not limit our T-Line rating. $1.5M

NIPSCO: DEI mitigations acceptable to remove
constraint. $0
$1,500,000$102,548
  • NIPSCO
New York Independent System Operator (NYISO)Not required
Tennessee Valley Authority (TVA)Not required
Louisville Gas & Electric (LG&E)Not required
Duke Energy Carolinas (DUKE)Not required
Duke Energy Progress – East (CPLE)Not required
Duke Energy Progress – West (CPLW)Not required

System Reinforcements

Based on the Phase II System Impact Study analysis results, this project is contingent on and may have cost responsibility for the following System Reinforcements:

AG2-545 System Reinforcements:
TORTEP IDTitleCategoryAllocated Cost ($USD)Facilities Study
AEPb4000.251Replace the wave trap and upgrade the relay at Cloverdale 765kV substationContingent$0N/A
AEPb4000.252Replace the wave trap and upgrade the relay at Joshua Falls 765kV substationContingent$0N/A
Grand Total:$0

Shown below are the details of the cost allocated, contingent, eliminated, topology and potential aggregate contributor reinforcements for this project. Please refer to the System Reinforcement table above and the information below for more detail.


System Reinforcement: b4000.251
Type
Load Flow
TO
AEP
RTEP ID / TO ID
b4000.251
Title
Replace the wave trap and upgrade the relay at Cloverdale 765kV substation
Description
Replace the wave trap and upgrade the relay at Cloverdale 765kV substation
Cost Information
Time Estimate
Jun 01 2029

Contingent

Note: Although AG2-545 may not presently have cost responsibility for this upgrade, AG2-545 may need this upgrade in-service to be deliverable to the PJM system. If AG2-545 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.

FacilityContingency
05JOSHUA-05CLOVRD_RJO 765.0 kV Ckt 1 line(Any)
Rating SetRating TypeRating Value
(All)A4047.0 MVA
(All)B4571.0 MVA

System Reinforcement: b4000.252
Type
Load Flow
TO
AEP
RTEP ID / TO ID
b4000.252
Title
Replace the wave trap and upgrade the relay at Joshua Falls 765kV substation
Description
Replace the wave trap and upgrade the relay at Joshua Falls 765kV substation
Cost Information
Time Estimate
Jun 01 2029

Contingent

Note: Although AG2-545 may not presently have cost responsibility for this upgrade, AG2-545 may need this upgrade in-service to be deliverable to the PJM system. If AG2-545 desires to come into service prior to completion of the upgrade, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the upgrade is complete.

FacilityContingency
05JOSHUA-05CLOVRD_RJO 765.0 kV Ckt 1 line(Any)
Rating SetRating TypeRating Value
(All)A4047.0 MVA
(All)B4571.0 MVA

Conversion from Impacts into Topology or Eliminated Reinforcements into Region Topology Contingent Reinforcements for AG2-545


AG2-545 Contributions into Topology or Eliminated Reinforcements:
TypeTORTEP ID / TO IDTitleTopo or ElimMW ImpactPercent AllocationCategoryAllocated Cost ($USD)
Contributions into Topology or Eliminated Reinforcement Total:$0
AG2-545 Contingent Region Topology Upgrades:
TORTEP IDTitleCategoryAllocated Cost ($USD)
Region Topology Upgrade Total:$0

Attachments

AG2-545 One Line Diagram

AG2-545 One Line Diagram.jpg
The state in which the generator or merchant transmission facility is located.
The Transmission Owner of the facility where the New Service Request project interconnects to the transmission system.
Winter load flow analysis will be performed starting in Transition Cycle 2.