AH1-091 Phase II System Impact Study Report

v1.00 released 2026-06-03 17:59

Ahoskie 34.5kV

0.0 MW Capacity / 0.0 MW Energy

Introduction

AH1-091 meets the criteria for acceleration at Decision Point II (DP2) .

This Phase II System Impact Study (SIS) Report has been prepared in accordance with the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 310 for New Service Requests (projects) in Transition Cycle 2 (TC2). The Project Developer/Eligible Customer (developer) is Colice Hall Solar, LLC, and the Transmission Provider (TP) is PJM Interconnection, LLC (PJM). The interconnected Transmission Owner (TO) is Virginia Electric and Power Company (d/b/a Dominion Energy Virginia).

Preface

The Phase II System Impact Study is conducted on an aggregate basis within a New Services Request’s Cycle, and results are provided in both (i) a single Cycle summary format and (ii) an individual project-level basis. The Phase II System Impact Study Results (for both the summary and individual reports) will be publicly available on PJM’s website. Project Developers must obtain the results from the website.

In accordance with PJM Manual 14H, section 4.5, PJM takes the following actions during the Phase II System Impact Study:

  1. PJM will retool load flow results from the Phase I System Impact Study (summer peak, winter peak and light load) based on decisions made by Project Developers or Eligible Customers during Decision Point I.
  2. PJM will conduct any required voltage analyses.
  3. PJM will perform short circuit and stability analyses as required.
  4. PJM will coordinate with the Affected System to confirm which projects in the PJM Cycle will require Affected System studies. If the Affected System Operator indicates that an Affected System study is required, PJM will:
    1. Notify the Project Developer or Eligible Customer of the need for an Affected System study and the requirement to execute an Affected System study agreement with the impacted Affected System Operator, and;
    2. Include the results of the Affected System Operator’s Affected System Study in the Phase II System Impact Study results, if applicable and available.
  5. The Phase II System Impact Study Results will be publicly available on PJM’s website. Project Developers and Eligible Customers must obtain the results from the website.

The Transmission Owner takes the following actions during the Phase II System Impact Study:

  1. Verify Interconnection Facilities and Network Upgrades required to accommodate the New Service Request.
  2. Perform a Facilities Study. The Facilities Study in Phase II System Impact Study phase will be for the physical Interconnection Facilities. The Facilities Study requirements are outlined in Attachment C of this manual. The study will be conducted pursuant to Tariff, Part VII, Subpart D, section 307(A)(7) and Tariff, Part VIII, Subpart C, section 404(A)(7).

Final Agreement Requirements

This New Service Request meets the criteria for acceleration at Decision Point II (DP2).

Please note that additional requirements apply to accelerated projects at DP2 per PJM Tariff Part VII, Subpart D, section 311. Failure to meet the requirements by the close of DP2 will result in withdrawal.

Adverse Test Eligibility

This New Service Request does not meet the Adverse Study Impact Criteria and has the option to either move forward in the Cycle process or withdraw at DP2 with Readiness Deposit #1 forfeited. See adverse study impact calculation below.

This section details whether a Project Developer or Eligible Customer qualifies for the Adverse Study Impact clause outlined in the PJM OATT, Part VII, Subpart D, section 311.B and Manual 14H, section 6.2.2. In order to qualify for an Adverse Study Impact at Decision Point II, the Network Upgrade cost from Phase I to Phase II must:

  1. Increase overall by 25% or more
  2. Increases by more than $10,000 per MW (Includes Costs identified in Affected System studies)

If a New Service Request meets the criteria above and chooses to withdraw the request, PJM will refund the cumulative Readiness Deposit amounts paid at the Application Phase and at Decision Point I (RD1 and RD2, respectively).

The below calculations show the computation of this New Service Request's Adverse Study Impact

DP2 Adverse Eligibility = DP2 Adverse Cost Alloc DP1 Adverse Cost Alloc > 1.25 AND ( DP2 Adverse Cost Alloc - DP1 Adverse Cost Alloc ) Project Size > $10,000 per MW
DP2 Adverse Eligibility = $0 $0 = ∞ AND ( $0 - $0 ) 0.0 = ∞

General

The Project Developer has proposed an uprate to a planned/existing Solar facility located in the Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) zone — Hertford County, North Carolina. This project is an increase to the developer’s AB2-099/AE2-346 project(s), which will share the same Point of Interconnection. The AH1-091 project is a 0.0 MW uprate (0.0 MW Capacity uprate) to the previous project(s). The total installed facilities will have a capability of 17.0 MW with 11.9 MW of this output being recognized by PJM as Capacity.

Project Information
New Service Request Number:
AH1-091
Project Name:
Ahoskie 34.5kV
Project Developer Name:
Colice Hall Solar, LLC
State:
North Carolina
County:
Hertford
Transmission Owner:
Virginia Electric and Power Company (d/b/a Dominion Energy Virginia)
MFO:
17.0
MWE:
0.0
MWC:
0.0
Battery Storage Specification:
68.0 MWh, 4.0-hr class
Grid Charging:
Yes
Fuel Type:
Storage
Basecase Study Year:
2028

Physical Interconnection Facility Study

Not Required

A Physical Interconnection Facilities Study is not required for this project.

Point of Interconnection

AH1-091 will interconnect on the Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) distribution system at Ahoskie 34.5 kV Substation.

Cost Summary

The table below shows a summary of the total cost estimates for this New Service Request project. In Phase II SIS, the interconnected Transmission Owner has performed a facilities study for both the Transmission Owner Interconnection Facilities (TOIF) and Physical Interconnection Network Upgrades. The System Reliability Network Upgrade shown in the table are planning level cost estimates which are subject to change as a result of a facility study performed by the TO during Phase III System Impact Study.

Based on the Phase II SIS results, the AH1-091 project has the following allocation of costs for interconnection.

Cost Summary
DescriptionCost Allocated to AH1-091Cost Subject to Security*
Transmission Owner Interconnection Facilities (TOIF)$0$0
Other Scope$0$0
Option To Build Oversight$0$0
Physical Interconnection Network Upgrades
Stand Alone Network Upgrades$0$0
Network Upgrades$0$0
System Reliability Network Upgrades
Steady State Thermal & Voltage$0$0
Transient Stability$0$0
Short Circuit$0$0
Transmission Owner Analysis
SubRegional$0$0
Distribution$0$0
Affected System Reinforcements
AFS - PJM Violations$0$0
AFS - Non-PJM Violations$0$0
Total$0$0
Definitions

Transmission Owner Interconnection Facilities: Facilities that are owned, controlled, operated and maintained by the Transmission Owner on the Transmission Owner’s side of the Point of Change of Ownership to the Point of Interconnection, including any modifications, additions or upgrades made to such facilities and equipment, that are necessary to physically and electrically interconnect the Generating Facility with the Transmission System or interconnected distribution facilities.

Stand Alone Network Upgrades: Network Upgrades, which are not part of an Affected System, which a Project Developer may construct without affecting day-to-day operations (e.g. taking a transmission outage) of the Transmission System during their construction.

Network Upgrades: Modifications or additions to transmission-related facilities that are integrated with and support the Transmission Provider’s overall Transmission System for the general benefit of all users of such Transmission System. Network Upgrades have no impact or potential impact on the Transmission System until the final tie-in is complete.

Notes

Note 1: PJM Open Access Transmission Tariff (OATT), Part VII, Subpart D, section 307.5 outlines cost allocation rules. The rules are further clarified in PJM Manual 14H, section 4.2.6. PJM shall identify the New Service Requests in the Cycle contributing to the need for the required Network Upgrades within the Cycle. All New Service Requests that contribute to the need for a Network Upgrade will receive cost allocation for that upgrade pursuant to each New Service Request’s contribution to the reliability violation identified on the transmission system in accordance with PJM Manuals.

Note 2: There will be no inter-Cycle cost allocation for Interconnection Facilities or Network Upgrades identified in the System Impact Study costs identified in a Cycle; all such costs shall be allocated to New Service Requests in that Cycle.

Note 3: For Project Developers with System Reinforcements listed: If this project presents cost allocation to a System Reinforcement indicates $0, then please be aware that as changes to the interconnection process occur, such as other projects withdrawing, reducing in size, etc, the cost responsibilities can change and a cost allocation may be assigned to this project. In addition, although this project presents cost allocation to a System Reinforcement is presently $0, this project may need this system reinforcement completed to be deliverable to the PJM system. If this project desires to come into service prior to completion of the system reinforcement, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the system reinforcement is complete.

Note 4: Please see the ‘Affected Systems Studies’ section of this Phase II SIS report for details on your project’s need for an Affected Systems Study. If your project requires an Affected Systems Study, the Affected Systems impacts may not be available from the Affected System Operator at the time of the PJM Phase II SIS. Therefore, the cost in this section would not reflect any required upgrades by the Affected System until the study is completed. If your project requires an Affected Systems Study and your results are not provided for Phase II SIS, PJM anticipates providing them in the Phase III SIS per Tariff Part VII.D.312.

Security Requirement

A summary of this New Service Requests costs are summarized in the Cost Summary section, herein. Final security will be shown in the Generation Interconnection Agreement (GIA).

Transmission Owner Scope of Work

No TO Interconnection Facilities or Physical Network Upgrades are required for this project.

Transmission Owner Analysis

PJM performed a power flow analysis of the transmission system using a 2028 load flow model and the results were verified by Dominion.

 

Developer Requirements

The developer is responsible for all design and construction related activities on the developer’s side of the Point of Change in Ownership. Dominion interconnection requirements can be found here.

To the extent that these Applicable Technical Requirements and Standards may conflict with the terms and conditions of the Tariff, the Tariff shall control.

Revenue Metering and SCADA Requirements

PJM Requirements
The developer will be required to install equipment necessary to provide Revenue Metering (KWH, KVARH) and real time data (KW, KVAR) for their generating Resource. See PJM Manual 01, PJM Manual 14D, and PJM Tariff Part IX, Subpart B, Appendix 2, section 8.
Transmission Owner Requirements
The Project Developer will be required to comply with all interconnected Transmission Owner’s revenue metering requirements located at the following link: PJM - Transmission Owner Engineering & Construction Standards.

Summer Peak Analysis

The New Service Request AH1-091 was evaluated as a 0.0 MW (0.0 MW Capacity) injection in the Dominion area.

AH1-091 was evaluated as part of a plant. The plant consists of AH1-091. The total Energy output of the plant was evaluated at its maximum seasonal capability of 17.0 MW (0.0 MW under study).

Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.

The following flowgates remain after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)

Winter Peak Analysis

The New Service Request AH1-091 was evaluated as a 0.0 MW (0.0 MW Capacity) injection in the Dominion area.

AH1-091 was evaluated as part of a plant. The plant consists of AH1-091. The total Energy output of the plant was evaluated at its maximum seasonal capability of 17.0 MW (0.0 MW under study).

Note: The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for single or N-1 contingencies and multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.

The following flowgates remain after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)

Light Load Analysis

The New Service Request AH1-091 was evaluated as a 0.0 MW injection and 17.0 MW withdrawal in the Dominion area.

AH1-091 was evaluated as part of a plant. The plant consists of AH1-091. The total Energy output of the plant was evaluated at its maximum seasonal capability of 17.0 MW (10.76 MW under study).

Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.

The following flowgates remain after considering the topology reinforcements required by the cycle.

StudyAreaFacility DescriptionContingency NameContingency TypeDC|ACFinal Cycle LoadingRating (MVA)Rating TypeMVA to MitigateMW ContributionDetails
GD2CPLE/DVP
3BTLEBRO-3ROCKYMT115T 115.0 kV Ckt 1 line
DVP_P7-1: LN 2058-2181_SRT-A
TowerAC100.98 %313.0B316.08
0.92

Details for 3BTLEBRO-3ROCKYMT115T 115.0 kV Ckt 1 line l/o DVP_P7-1: LN 2058-2181_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:CPLE/DVP
Facility Description:
3BTLEBRO-3ROCKYMT115T 115.0 kV Ckt 1 line
Contingency Name:
DVP_P7-1: LN 2058-2181_SRT-A
Contingency Type:Tower
DC|AC:AC
Final Cycle Loading:100.98 %
Rating:313.0 MVA
Rating Type:B
MVA to Mitigate:316.08
MW Contribution:
0.92
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area:CPLE/DVP
Facility Description:
3BTLEBRO-3ROCKYMT115T 115.0 kV Ckt 1 line
Contingency Name:
DVP_P7-1: LN 2058-2181_SRT-A
Contingency Type:Tower
DC|AC:AC
Final Cycle Loading:97.49 %
Rating:313.0 MVA
Rating Type:B
MVA to Mitigate:305.15
MW Contribution:
0.94
Bus #Bus NameTypeMW Contribution
3147043LAWRENC
Solar/Wind Harmer
0.095
3156081AA2-088 GEN
Solar/Wind Harmer
0
316011AB1-132 GEN
Solar/Wind Harmer
0
316463AE2-346 GEN
Solar/Wind Harmer
-0.218
316065AD1-022 GEN
Solar/Wind Harmer
2.578
315732AD1-074 GEN1
Solar/Wind Harmer
0
315733AD1-074 GEN2
Solar/Wind Harmer
0
315737AD1-076 GEN
Solar/Wind Harmer
0
3145513AHOSKIE
Solar/Wind Harmer
0.247
3145513AHOSKIE
Solar/Wind Harmer
0.247
3145746EVERETS
Solar/Wind Harmer
0.68
3145746EVERETS
Solar/Wind Harmer
0.171
3145746EVERETS
Solar/Wind Harmer
0.171
3145746EVERETS
Solar/Wind Harmer
0.171
3145746EVERETS
Solar/Wind Harmer
0.171
3145746EVERETS
Solar/Wind Harmer
0.171
3145746EVERETS
Solar/Wind Harmer
0.171
3145746EVERETS
Solar/Wind Harmer
0.171
3146206CASHIE
Solar/Wind Harmer
0.168
3146206CASHIE
Solar/Wind Harmer
0.168
3146206CASHIE
Solar/Wind Harmer
0.168
3142666NORTHAMPTON
Solar/Wind Harmer
0.294
3142666NORTHAMPTON
Solar/Wind Harmer
0.294
3142666NORTHAMPTON
Solar/Wind Harmer
0.294
3142666NORTHAMPTON
Solar/Wind Harmer
0.294
3142666NORTHAMPTON
Solar/Wind Harmer
0.176
3156021HOLLOMANSOL
Solar/Wind Harmer
-0.29
315652AC1-086 GEN
Solar/Wind Harmer
11.068
316359AB2-059 GEN
Solar/Wind Harmer
0
316263AC1-034 GEN
Solar/Wind Harmer
17.985
316140AB2-099
Solar/Wind Harmer
-0.091
3130546PLYMOUTH
Solar/Wind Harmer
0.146
3145543BTLEBRO
Solar/Wind Harmer
1.27
3145543BTLEBRO
Solar/Wind Harmer
1.27
3145543BTLEBRO
Solar/Wind Harmer
1.27
3145543BTLEBRO
Solar/Wind Harmer
1.016
3145593CAROLNA
Solar/Wind Harmer
0.294
3145593CAROLNA
Solar/Wind Harmer
0.294
3145593CAROLNA
Solar/Wind Harmer
0.082
3145683EARLEYS
Solar/Wind Harmer
0.507
3145683EARLEYS
Solar/Wind Harmer
0.254
3145683EARLEYS
Solar/Wind Harmer
0.254
3145683EARLEYS
Solar/Wind Harmer
0.254
3137643SOCKMAN
Solar/Wind Harmer
1.095
3138543CONSLDL
Solar/Wind Harmer
0.747
3142053HEARTS
Solar/Wind Harmer
0.475
3145453TOT5
Solar/Wind Harmer
0.134
3145493TOT1
Solar/Wind Harmer
0.429
3145493TOT1
Solar/Wind Harmer
0.224
3145573BETHELC
Solar/Wind Harmer
0.429
3145573BETHELC
Solar/Wind Harmer
0.429
3145603CNETO
Solar/Wind Harmer
0.089
3145783HORNRTN
Solar/Wind Harmer
1.433
3145783HORNRTN
Solar/Wind Harmer
1.147
3145783HORNRTN
Solar/Wind Harmer
0.358
3145783HORNRTN
Solar/Wind Harmer
0.358
3145783HORNRTN
Solar/Wind Harmer
0.143
3145796HORNRTN
Solar/Wind Harmer
1.388
3145796HORNRTN
Solar/Wind Harmer
1.145
3145796HORNRTN
Solar/Wind Harmer
1.111
3145796HORNRTN
Solar/Wind Harmer
1.041
3145796HORNRTN
Solar/Wind Harmer
0.347
3145796HORNRTN
Solar/Wind Harmer
0.347
3145796HORNRTN
Solar/Wind Harmer
0.139
3145823KELFORD
Solar/Wind Harmer
0.4
3145823KELFORD
Solar/Wind Harmer
0.4
3145893MURPHYS
Solar/Wind Harmer
0.909
3145893MURPHYS
Solar/Wind Harmer
0.727
3145893MURPHYS
Solar/Wind Harmer
0.613
3145893MURPHYS
Solar/Wind Harmer
0.409
3145893MURPHYS
Solar/Wind Harmer
0.227
3145893MURPHYS
Solar/Wind Harmer
0.227
3145893MURPHYS
Solar/Wind Harmer
0.227
3145893MURPHYS
Solar/Wind Harmer
0.182
3145933PARMELE
Solar/Wind Harmer
0.334
3145933PARMELE
Solar/Wind Harmer
0.167
3145933PARMELE
Solar/Wind Harmer
0.167
3145963POPLR C
Solar/Wind Harmer
0.159
3145963POPLR C
Solar/Wind Harmer
0.159
3146033SCOT NK
Solar/Wind Harmer
2.185
3146043SEABORD
Solar/Wind Harmer
0.258
3146073TAR RVR
Solar/Wind Harmer
0.429
3146083TARBORO
Solar/Wind Harmer
0.429
3146083TARBORO
Solar/Wind Harmer
0.429
3146173TUNIS
Solar/Wind Harmer
0.24
3146173TUNIS
Solar/Wind Harmer
0.24
3146173TUNIS
Solar/Wind Harmer
0.24
3146173TUNIS
Solar/Wind Harmer
0.24
3146233WITAKRS
Solar/Wind Harmer
4.431
3146233WITAKRS
Solar/Wind Harmer
2.672
3146233WITAKRS
Solar/Wind Harmer
0.757
3146263WOODLND
Solar/Wind Harmer
0.265
3146263WOODLND
Solar/Wind Harmer
0.265
3146293MARTNCO
Solar/Wind Harmer
0.035
316318V4-068
Solar/Wind Harmer
0
960081AF2-299 GEN
Solar/Wind Harmer
0.763
961601AG1-000A GEN
Solar/Wind Harmer
8.329
961601AG1-000A GEN
Solar/Wind Harmer
11.488
961671AG1-007 GEN
Solar/Wind Harmer
0.806
961941AG1-037 GEN
Solar/Wind Harmer
0.141
962571AG1-106 GEN
Solar/Wind Harmer
1.414
970601AG2-382 GEN
Solar/Wind Harmer
2.353
970831AG2-522 GEN
Solar/Wind Harmer
2.539
971547AH1-271 GEN
Solar/Wind Harmer
1.344
957861AF2-080 GEN
Solar/Wind Harmer
4.335
970361AG2-238 GEN
Solar/Wind Harmer
3.112
971263AH1-091 GEN
Solar/Wind Harmer
0.917
315722AD1-056 GEN
Solar/Wind Harmer
5.718
315724AD1-057 GEN
Solar/Wind Harmer
3.145
NYPJM->LTFIMP_NY
CLTF
0.056
GibsonPJM->LTFIMP_GIBSON
CLTF
0
HAMLETPJM->LTFIMP_HAMLET
CLTF
1.631
CATAWBAPJM->LTFIMP_CATAWBA
CLTF
0.796
PRAIRIEPJM->LTFIMP_PRAIRIE
CLTF
2.343
TRIMBLEPJM->LTFIMP_TRIMBLE
CLTF
0.408
CALDErWOODPJM->LTFIMP_CALDERWOOD
CLTF
0
CHEOAHPJM->LTFIMP_CHEOAH
CLTF
0
BlueGrassPJM->LTFIMP_BlueG
CLTF
1.284
MDUPJM->LTFIMP_MDU
CLTF
0
CONTINGENCY 'DVP_P7-1: LN 2058-2181_SRT-A'
 OPEN BRANCH FROM BUS 304222 TO BUS 313845 CKT 1   /*6ROCKYMT230T 230.0 - 6HATHAWAY    230.0
 OPEN BRANCH FROM BUS 304226 TO BUS 314591 CKT 1   /*6PA-RMOUNT#4 230.0 - 6NASH        230.0
 OPEN BRANCH FROM BUS 313844 TO BUS 313845 CKT 2   /*3HATHAWAY    115.0 - 6HATHAWAY    230.0
 OPEN BRANCH FROM BUS 313845 TO BUS 314591 CKT 1   /*6HATHAWAY    230.0 - 6NASH        230.0
 OPEN BUS 304226                                   /*6PA-RMOUNT#4 230.0
 OPEN BUS 314591                                   /*6NASH        230.0
END
314554 to 304223 ckt 1

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)

Short Circuit Analysis

Analysis Complete - No Issues

Based on PJM’s TC2 Phase II Short Circuit Analysis, this project did not contribute >1% fault duty to any previously identified overdutied breakers, nor did it cause any new overdutied breakers.

Stability Analysis

PJM has reviewed this project submission and determined that a stability study is not required due to connection to a non-BES facility.

 

Reactive Power Analysis

Not Required

Reactive Power Analysis was not performed. This project is responsible for meeting all applicable power factor requirements based on the project Agreements per PJM’s Tariff, Part IX, Subpart B, App. 2, section 4.6.1.

Steady-State Voltage Analysis

Analysis Complete - No Issues

Steady State Voltage Analysis complete, no voltage issues identified.

New Service Request Dependencies

The New Service Requests below are listed in one or more dispatch for the overloads identified in this report. These projects contribute to the loading of the overloaded facilities identified in this report. The percent overload of a facility and cost allocation you may have towards a particular reinforcement could vary depending on the action of other projects. The status of each project at the time of the analysis is presented in the table. This list may change as other projects withdraw or modify their requests. This table is valid for load flow analyses only.

New Service Requests Dependencies
Project IDProject NameStatus
AB1-132Thelma 230kVIn Service
AB2-059Benson-Dunbar 115kVIn Service
AB2-099Ahoskie 34.5kVIn Service
AC1-034Heartsease DP - Mayo Dunbar 115kVEngineering & Procurement
AC1-086Thelma 230kVUnder Construction
AD1-022Cashie-Trowbridge 230 kVEngineering & Procurement
AD1-056Hornertown-Hathaway 230 kVSuspended
AD1-057Hornertown-Hathaway 230 kVSuspended
AD1-074Trowbridge 230 kVEngineering & Procurement
AD1-076Trowbridge 230 kVEngineering & Procurement
AE2-346Ahoskie 34.5 kVIn Service
AF2-080Chinquapin-Everetts 230 kVWithdrawn
AF2-299Fields 34.5 kVEngineering & Procurement
AG1-007Tar River 12.5 kVWithdrawn
AG1-037Ahoskie 34.5 kVWithdrawn
AG1-106Thelma 230 kVWithdrawn
AG2-238Earleys 230 kVActive
AG2-382Cashie 230 kVActive
AG2-522Five Forks DP - Littleton DP 115 kVActive
AH1-271Cashie 230 kVActive
V4-068Murphy's 34.5kVIn Service

Affected System - PJM Identified Violations

As part of PJM's analysis, per Tariff Part VII.G.336 & Manual 14H, Section 13, PJM evaluated the potential impacts on tie line facilities between PJM and an affected system entity, which were identified per PJM planning analysis criteria. This upgrade may be required on the affected system portion of the tie line along with cost allocation of such upgrade if applicable, in coordination with the affected system. Depending on the affected system, this project may not be contingent on upgrade based on PJM planning analysis criteria, but may be contingent on this upgrade based on the Affected System Operator's planning criteria, provided in the Affected Systems Study Section, herein.

Midcontinent Independent System Operator, Inc. (MISO)No Impact
New York Independent System Operator (NYISO)No Impact
Tennessee Valley Authority (TVA)No Impact
Louisville Gas & Electric (LG&E)No Impact
Duke Energy Carolinas (DUKE)No Impact
Duke Energy Progress – East (CPLE)No Impact
Duke Energy Progress – West (CPLW)No Impact

Affected System - Non-PJM Identified Violations

In accordance with PJM Tariff Part VII, Subpart D, section 310.A and as outlined in PJM Manual 14H, Sections 4.5 and 13, in Phase II of the Cycle, PJM provides the Affected System Operator any updates on the PJM projects that require an Affected Systems Study based on their response at DP1. New Service Requests that require an Affected Systems Study are required to enter into an Affected Systems Study Agreement with the Affected System Operator, as applicable, prior to the close of DP2 or they will be withdrawn from the Cycle.

If the Project Developer already entered into the necessary agreement and the results are available, PJM will supply them in the Phase II SIS report. See below for the status of any required Affected Systems Study. A status of “Pending” means that the study is not yet completed by the Affected System Operator. If your project requires an Affected Systems Study and your results are not provided for Phase II SIS, PJM anticipates providing them in the Phase III SIS per Tariff Part VII.D.312.

Midcontinent Independent System Operator, Inc. (MISO)Not required
New York Independent System Operator (NYISO)Not required
Tennessee Valley Authority (TVA)Not required
Louisville Gas & Electric (LG&E)Not required
Duke Energy Carolinas (DUKE)Not required
Duke Energy Progress – East (CPLE)Not required
Duke Energy Progress – West (CPLW)Not required

System Reinforcements

No cost allocated system reinforcements were identified for this project in the Phase II System Impact Study load flow analysis.

Shown below are the details of the cost allocated, contingent, eliminated, topology and potential aggregate contributor reinforcements for this project. Please refer to the System Reinforcement table above and the information below for more detail.


System Reinforcement
Type
Load Flow
TO
Dominion
RTEP ID / TO ID
(Pending)
Title
Dominion facility ratings: 379/390/449 MVA Winter | 372/384/441 MVA LL | 342/352/405 MVA Summer.
Description
Dominion facility ratings: 379/390/449 MVA Winter | 372/384/441 MVA LL | 342/352/405 MVA Summer.
Total Cost ($USD)
$0
Discounted Total Cost ($USD)
$0
Allocated Cost ($USD)
$0
Time Estimate
TBD

Note: This reinforcement is fictitious and will not be cost allocated to projects. It is listed for information purposes only.

FacilityContingency
3ROCKYMT115T-3BTLEBRO 115.0 kV Ckt 1 line(Any)
Rating SetRating TypeRating Value
LLA372.0 MVA
LLB384.0 MVA
LLC441.0 MVA
SUMA342.0 MVA
SUMB352.0 MVA
SUMC405.0 MVA
WINA379.0 MVA
WINB390.0 MVA
WINC449.0 MVA

Conversion from Impacts into Topology or Eliminated Reinforcements into Region Topology Contingent Reinforcements for AH1-091


AH1-091 Contributions into Topology or Eliminated Reinforcements:
TypeTORTEP ID / TO IDTitleTopo or ElimMW ImpactPercent AllocationCategoryAllocated Cost ($USD)
Contributions into Topology or Eliminated Reinforcement Total:$0
AH1-091 Contingent Region Topology Upgrades:
TORTEP IDTitleCategoryAllocated Cost ($USD)
Region Topology Upgrade Total:$0

Attachments

AH1-091 One Line Diagram

AH1-091 One Line Diagram.pdf
The state in which the generator or merchant transmission facility is located.
The Transmission Owner of the facility where the New Service Request project interconnects to the transmission system.
Winter load flow analysis will be performed starting in Transition Cycle 2.