AH1-098 Phase II System Impact Study Report
v1.00 released 2026-06-03 18:41
Wolf Glade-West Carroll 138 kV
24.0 MW Capacity / 40.0 MW Energy
Introduction
This Phase II System Impact Study (SIS) Report has been prepared in accordance with the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 310 for New Service Requests (projects) in Transition Cycle 2 (TC2). The Project Developer/Eligible Customer (developer) is Pine Branch Solar, LLC, and the Transmission Provider (TP) is PJM Interconnection, LLC (PJM). The interconnected Transmission Owner (TO) is American Electric Power.
Preface
The Phase II System Impact Study is conducted on an aggregate basis within a New Services Request’s Cycle, and results are provided in both (i) a single Cycle summary format and (ii) an individual project-level basis. The Phase II System Impact Study Results (for both the summary and individual reports) will be publicly available on PJM’s website. Project Developers must obtain the results from the website.
In accordance with PJM Manual 14H, section 4.5, PJM takes the following actions during the Phase II System Impact Study:
- PJM will retool load flow results from the Phase I System Impact Study (summer peak, winter peak and light load) based on decisions made by Project Developers or Eligible Customers during Decision Point I.
- PJM will conduct any required voltage analyses.
- PJM will perform short circuit and stability analyses as required.
- PJM will coordinate with the Affected System to confirm which projects in the PJM Cycle will require Affected System studies. If the Affected System Operator indicates that an Affected System study is required, PJM will:
- Notify the Project Developer or Eligible Customer of the need for an Affected System study and the requirement to execute an Affected System study agreement with the impacted Affected System Operator, and;
- Include the results of the Affected System Operator’s Affected System Study in the Phase II System Impact Study results, if applicable and available.
- The Phase II System Impact Study Results will be publicly available on PJM’s website. Project Developers and Eligible Customers must obtain the results from the website.
The Transmission Owner takes the following actions during the Phase II System Impact Study:
- Verify Interconnection Facilities and Network Upgrades required to accommodate the New Service Request.
- Perform a Facilities Study. The Facilities Study in Phase II System Impact Study phase will be for the physical Interconnection Facilities. The Facilities Study requirements are outlined in Attachment C of this manual. The study will be conducted pursuant to Tariff, Part VII, Subpart D, section 307(A)(7) and Tariff, Part VIII, Subpart C, section 404(A)(7).
Decision Point II Requirements
At the close of Phase II System Impact Study, PJM will initiate Decision Point II (DP2). During DP2, the Project Developer will have 30 days to decide whether to proceed with their project. If the Project Developer elects to proceed, they should provide the elements defined in the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 311.A. Additional information on these elements is available in PJM Manual 14H sections 4.6, 6, and 7.
Allowable project modifications at Decision Point II are defined in PJM Open Access Transmission Tariff, Part VII, Subpart D, section 311.B. Additional information regarding allowable project modifications can be found in PJM Manual 14H, section 9.8.
Adverse Test Eligibility
This New Service Request does not meet the Adverse Study Impact Criteria and has the option to either move forward in the Cycle process or withdraw at DP2 with Readiness Deposit #1 forfeited. See adverse study impact calculation below.
This section details whether a Project Developer or Eligible Customer qualifies for the Adverse Study Impact clause outlined in the PJM OATT, Part VII, Subpart D, section 311.B and Manual 14H, section 6.2.2. In order to qualify for an Adverse Study Impact at Decision Point II, the Network Upgrade cost from Phase I to Phase II must:
- Increase overall by 25% or more
- Increases by more than $10,000 per MW (Includes Costs identified in Affected System studies)
If a New Service Request meets the criteria above and chooses to withdraw the request, PJM will refund the cumulative Readiness Deposit amounts paid at the Application Phase and at Decision Point I (RD1 and RD2, respectively).
The below calculations show the computation of this New Service Request's Adverse Study Impact
General
The Project Developer has proposed a Solar/Storage generating facility located in the American Electric Power zone — Carroll County, Virginia. The installed facilities will have a total capability of 40.0 MW with 24.0 MW of this output being recognized by PJM as Capacity.Project Information
Physical Interconnection Facility Study
The transmission owner has completed the Physical Interconnection Facilities Study. This report is available for download.
Point of Interconnection
AH1-098 will interconnect on the American Electric Power transmission system by tapping the Wolf Glade - West Carroll 138 kV Line.
Cost Summary
The table below shows a summary of the total cost estimates for this New Service Request project. In Phase II SIS, the interconnected Transmission Owner has performed a facilities study for both the Transmission Owner Interconnection Facilities (TOIF) and Physical Interconnection Network Upgrades. The System Reliability Network Upgrade shown in the table are planning level cost estimates which are subject to change as a result of a facility study performed by the TO during Phase III System Impact Study.
Based on the Phase II SIS results, the AH1-098 project has the following allocation of costs for interconnection. The cost contribution towards Readiness Deposit #3 are also shown below.
| Cost Summary | |||
|---|---|---|---|
| Description | Cost Allocated to AH1-098 | Cost Subject to Readiness* | Cost Subject to Adverse |
| Transmission Owner Interconnection Facilities (TOIF) | $1,298,353 | $0 | $0 |
| Other Scope | $1,354,047 | $0 | $0 |
| Option To Build Oversight | $0 | $0 | $0 |
| Physical Interconnection Network Upgrades | |||
| Stand Alone Network Upgrades | $15,130,471 | $15,130,471 | $15,130,471 |
| Network Upgrades | $2,136,646 | $2,136,646 | $2,136,646 |
| System Reliability Network Upgrades | |||
| Steady State Thermal & Voltage | $0 | $0 | $0 |
| Transient Stability | $0 | $0 | $0 |
| Short Circuit | $0 | $0 | $0 |
| Transmission Owner Analysis | |||
| SubRegional | $0 | $0 | $0 |
| Distribution | $0 | $0 | $0 |
| Affected System Reinforcements | |||
| AFS - PJM Violations | $0 | $0 | $0 |
| AFS - Non-PJM Violations | $0 | $0 | $0 |
| Total | $19,919,517 | $17,267,117 | $17,267,117 |
* Contributes to calculation for Readiness Deposit #3 (RD3). See Readiness Deposit section of report for additional detail.
Definitions
Transmission Owner Interconnection Facilities: Facilities that are owned, controlled, operated and maintained by the Transmission Owner on the Transmission Owner’s side of the Point of Change of Ownership to the Point of Interconnection, including any modifications, additions or upgrades made to such facilities and equipment, that are necessary to physically and electrically interconnect the Generating Facility with the Transmission System or interconnected distribution facilities.
Stand Alone Network Upgrades: Network Upgrades, which are not part of an Affected System, which a Project Developer may construct without affecting day-to-day operations (e.g. taking a transmission outage) of the Transmission System during their construction.
Network Upgrades: Modifications or additions to transmission-related facilities that are integrated with and support the Transmission Provider’s overall Transmission System for the general benefit of all users of such Transmission System. Network Upgrades have no impact or potential impact on the Transmission System until the final tie-in is complete.
Notes
Note 1: PJM Open Access Transmission Tariff (OATT), Part VII, Subpart D, section 307.5 outlines cost allocation rules. The rules are further clarified in PJM Manual 14H, section 4.2.6. PJM shall identify the New Service Requests in the Cycle contributing to the need for the required Network Upgrades within the Cycle. All New Service Requests that contribute to the need for a Network Upgrade will receive cost allocation for that upgrade pursuant to each New Service Request’s contribution to the reliability violation identified on the transmission system in accordance with PJM Manuals.
Note 2: There will be no inter-Cycle cost allocation for Interconnection Facilities or Network Upgrades identified in the System Impact Study costs identified in a Cycle; all such costs shall be allocated to New Service Requests in that Cycle.
Note 3: For Project Developers with System Reinforcements listed: If this project presents cost allocation to a System Reinforcement indicates $0, then please be aware that as changes to the interconnection process occur, such as other projects withdrawing, reducing in size, etc, the cost responsibilities can change and a cost allocation may be assigned to this project. In addition, although this project presents cost allocation to a System Reinforcement is presently $0, this project may need this system reinforcement completed to be deliverable to the PJM system. If this project desires to come into service prior to completion of the system reinforcement, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the system reinforcement is complete.
Note 4: Please see the ‘Affected Systems Studies’ section of this Phase II SIS report for details on your project’s need for an Affected Systems Study. If your project requires an Affected Systems Study, the Affected Systems impacts may not be available from the Affected System Operator at the time of the PJM Phase II SIS. Therefore, the cost in this section would not reflect any required upgrades by the Affected System until the study is completed. If your project requires an Affected Systems Study and your results are not provided for Phase II SIS, PJM anticipates providing them in the Phase III SIS per Tariff Part VII.D.312.
Readiness Deposit
Per Tariff Part VII, Subpart D, section 311 (Decision Point II) A.1.b and PJM Manual 14H, section 6.2, Readiness Deposit #3 (RD3) are funds committed by the Project Developer or Eligible Customer based upon the applicable contribution to Network Upgrades as defined below. Readiness Deposits are not used to fund studies nor to offset Security.
During Decision Point II (DP2), the Project Developer or Eligible Customer is required to submit Readiness Deposit #3, which is calculated as 20% of cost allocation for required Phase II Network Upgrades minus Readiness Deposit #1 & Readiness Deposit #2.
Note 1: “Network Upgrades” referred to in the calculation include both (i) the Physical Interconnection Network Upgrades and (ii) the System Reliability Network Upgrades as shown in the Cost Summary table.
Note 2: Readiness Deposit #1 (RD1) = ($4,000 * Project Size (MW))
Note 3: Readiness Deposit #2 (RD2) = 10% of cost allocation for required Network Upgrades minus RD1. Readiness Deposit #2 (RD2) can be zero, but may not be a negative number.
Note 4: Readiness Deposit #3 can be zero, but may not be a negative number.
Readiness Deposit #3 Due for Project AH1-098
Readiness Deposit #3 has been calculated for the project based on the Phase II System Impact Study results and is shown in the table below. This Readiness Deposit #3 must be provided at Decision Point II through either a wire transfer or letter of credit per Manual 14H, Section 6.2.
Readiness Deposit #3 Due for AH1-098
For additional detail regarding Readiness Deposit Refunds, reference PJM Manual 14H, section 6.2.1. The Readiness Deposit Letter of Credit template can be found here.
Transmission Owner Scope of Work
The total preliminary cost estimate for the Transmission Owner scope of work (including TOIF and Physical Interconnection Network Upgrades) is given in the table below. These costs do not include CIAC Tax Gross-up.
Transmission Owner Build Option
| Network Upgrades | |||||||
|---|---|---|---|---|---|---|---|
| RTEP ID | Description | Direct | Indirect | Total Cost ($USD) | Allocated Cost ($USD) | ||
| Labor | Materials | Labor | Materials | ||||
| (Pending) | WOLF GLADE - WEST CARROLL 138 kV line will be cut and looped into the new interconnection substation. | $902,404 | $622,166 | $238,803 | $187,751 | $1,951,124 | $1,951,124 |
| (Pending) | Appalachian Power Company will review and revise (as needed) the protective relay settings at the WOLF GLADE 138 kV Station. | $44,758 | $12,003 | $28,387 | $7,613 | $92,761 | $92,761 |
| (Pending) | Appalachian Power Company will review and revise (as needed) the protective relay settings at the WOLF GLADE 138 kV Station. | $44,758 | $12,003 | $28,387 | $7,613 | $92,761 | $92,761 |
| Other | |||||||
|---|---|---|---|---|---|---|---|
| RTEP ID | Description | Direct | Indirect | Total Cost ($USD) | Allocated Cost ($USD) | ||
| Labor | Materials | Labor | Materials | ||||
| (Pending) | Installation of a standard revenue metering package, including three (3) single phase current transformers (CT), three (3) single phase voltage transformers (VT), associated structures and foundations, one (1) ethernet switch, and one (1) DICM-installed metering panel, for the generation lead circuit at the AH1-098 New Station 138 kV Station. Appalachian Power Company will install one (1) metering panel with two (2) primary meters and one (1) ethernet switch in the AH1-098 Project Developer's collector Station. | $682,520 | $351,292 | $213,076 | $107,159 | $1,354,047 | $1,354,047 |
| Stand-Alone Network Upgrades | |||||||
|---|---|---|---|---|---|---|---|
| RTEP ID | Description | Direct | Indirect | Total Cost ($USD) | Allocated Cost ($USD) | ||
| Labor | Materials | Labor | Materials | ||||
| (Pending) | A new breaker and a half substation (initially populated with 3 breakers and operated as a ring bus), AH1-098 New 138 kV station (name TBD), will be constructed along the WOLF GLADE - WEST CARROLL 138 kV transmission line to interconnect the project with the APCO transmission system. Appalachian Power Company will construct a new 138 kV breaker and a half station, to be operated as a three (3) circuit breaker ring bus, initially expandable to six (6) circuit breakers. This typical arrangement is planned to be designed to accommodate 3000A of continuous current. Installation of (3) 138KV RCVTs with (1) three-phase 138KV RCVT structures & foundations. Installation of one 1 wavetrap. 2 mile of gravel access road. | $8,157,029 | $3,692,995 | $1,804,203 | $955,436 | $14,609,663 | $14,609,663 |
| (Pending) | Installation of Carrier Protection at the AH1-098 New Station 138 kV Station. Appalachian Power Company will transition existing OPGW fiber-optic shield wire from the cut-in dead ends into the AH1-098 New Station 138 kV Station | $300,193 | $76,107 | $115,281 | $29,227 | $520,808 | $520,808 |
| Transmission Owner Interconnection Facilities | |||||||
|---|---|---|---|---|---|---|---|
| RTEP ID | Description | Direct | Indirect | Total Cost ($USD) | Allocated Cost ($USD) | ||
| Labor | Materials | Labor | Materials | ||||
| (Pending) | A 138 kV dead-end structure and foundation outside the fence of the Interconnection Substation, to terminate the Project Developers generator lead line. Line conductor from the dead-end structure to the bus position in the switchyard of the interconnection substation. The APCO Interconnection Facilities will include but are not limited to the following: Installation of one (1) new steel, single circuit, single pole dead end structure and one span of ACSR 556 (Dove) transmission line conductor with 7#8 Alumoweld shield wire for the generation lead circuit extending from the AH1-098 New Station 138 kV Station. | $725,198 | $298,448 | $191,596 | $83,111 | $1,298,353 | $1,298,353 |
Developer Build Option
Project Developer has the option ("Option to Build") to assume responsibility for the design, procurement and construction of Transmission Owner Interconnection Facilities and/or Stand-Alone Network Upgrades.
If Option to Build is elected, the Project Developer must fulfill additional requirements in accordance to PJM Manual 14C, section 5.1 and PJM Manual 14H, section 8.6.2.
The cost estimates for eligible facilities and Option to Build oversight are highlighted below:
| Network Upgrades | |||||||
|---|---|---|---|---|---|---|---|
| RTEP ID | Description | Direct | Indirect | Total Cost ($USD) | Allocated Cost ($USD) | ||
| Labor | Materials | Labor | Materials | ||||
| (Pending) | WOLF GLADE - WEST CARROLL 138 kV line will be cut and looped into the new interconnection substation. | $902,404 | $622,166 | $238,803 | $187,751 | $1,951,124 | $1,951,124 |
| (Pending) | Appalachian Power Company will review and revise (as needed) the protective relay settings at the WOLF GLADE 138 kV Station. | $44,758 | $12,003 | $28,387 | $7,613 | $92,761 | $92,761 |
| (Pending) | Appalachian Power Company will review and revise (as needed) the protective relay settings at the WOLF GLADE 138 kV Station. | $44,758 | $12,003 | $28,387 | $7,613 | $92,761 | $92,761 |
| Option to Build Oversight | |||||||
|---|---|---|---|---|---|---|---|
| RTEP ID | Description | Direct | Indirect | Total Cost ($USD) | Allocated Cost ($USD) | ||
| Labor | Materials | Labor | Materials | ||||
| (Pending) | Oversight of developer design and construction of new interconnection substation | $244,623 | $83,373 | $182,825 | $62,310 | $573,131 | $573,131 |
| Other | |||||||
|---|---|---|---|---|---|---|---|
| RTEP ID | Description | Direct | Indirect | Total Cost ($USD) | Allocated Cost ($USD) | ||
| Labor | Materials | Labor | Materials | ||||
| (Pending) | Installation of a standard revenue metering package, including three (3) single phase current transformers (CT), three (3) single phase voltage transformers (VT), associated structures and foundations, one (1) ethernet switch, and one (1) DICM-installed metering panel, for the generation lead circuit at the AH1-098 New Station 138 kV Station. Appalachian Power Company will install one (1) metering panel with two (2) primary meters and one (1) ethernet switch in the AH1-098 Project Developer's collector Station. | $682,520 | $351,292 | $213,076 | $107,159 | $1,354,047 | $1,354,047 |
| Build Option Price Comparison | |||||||
|---|---|---|---|---|---|---|---|
| Build Option | Total Cost | Allocated Cost | |||||
| Transmission Owner Build Option | $19,919,517 | $19,919,517 | |||||
| Developer Build Option | $4,063,824 | $4,063,824 | |||||
Based on the scope of work for the Interconnection Facilities, it is expected to take 30 month(s) after the signing of a Generator Interconnection Agreement (as this is a FERC connection) and construction kickoff call to complete the installation of the physical connection work. This assumes that there will be no environmental issues with any of the new properties associated with this project, that there will be no delays in acquiring the necessary permits for implementing the defined interconnection work, and that all system outages will be allowed when requested.
Note that the TO findings were made from a conceptual review of this project. A more detailed review of the connection facilities and their cost will be identified in a future study phase. Further note that the cost estimate data provided should be considered high level estimates since it was produced without a detailed engineering review. The Project Developer will be responsible for the actual cost of construction. TO herein reserves the right to return to any issues in this document and, upon appropriate justification, request additional monies to complete any reinforcements to the transmission systems.
Remote Terminal Work: During Phase II of the PJM interconnection process, TO’s System Protection Engineering Department will review transmission line protection as well as anti-islanding required to accommodate the new generation and interconnection substation. System Protection Engineering will determine the minimal acceptable protection requirements to reliably interconnect the proposed generating facility with the transmission system. The review is based on maintaining system reliability by reviewing TO’s protection requirements with the known transmission system configuration which includes generating facilities in the area. This review may determine that transmission line protection and communication upgrades are required at remote substations.
Transmission Owner Analysis
No Transmission Owner impacts identified.
Developer Requirements
The developer is responsible for all design and construction related activities on the developer’s side of the Point of Change in Ownership. AEP interconnection requirements can be found here.
To the extent that these Applicable Technical Requirements and Standards may conflict with the terms and conditions of the Tariff, the Tariff shall control.
Revenue Metering and SCADA Requirements
The developer will be required to install equipment necessary to provide Revenue Metering (KWH, KVARH) and real time data (KW, KVAR) for their generating Resource. See PJM Manual 01, PJM Manual 14D, and PJM Tariff Part IX, Subpart B, Appendix 2, section 8.Meteorological Data Reporting Requirement
The solar generation facility shall provide the Transmission Provider with site-specific meteorological data including:Transmission Owner Requirements
- Temperature (degrees Fahrenheit)
- Atmospheric Pressure (hectopascals)
- Irradiance
- Forced outage data
The Project Developer will be required to comply with all interconnected Transmission Owner’s revenue metering requirements located at the following link: PJM - Transmission Owner Engineering & Construction Standards.
Summer Peak Analysis
The New Service Request AH1-098 was evaluated as a 40.0 MW (24.0 MW Capacity) injection in the AEP area.
AH1-098 was evaluated as part of a plant. The plant consists of AH1-098. The total Energy output of the plant was evaluated at its maximum seasonal capability of 40.0 MW (40.0 MW under study).
Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.
The following flowgates remain after considering the topology reinforcements required by the cycle.
| Study | Area | Facility Description | Contingency Name | Contingency Type | DC|AC | Final Cycle Loading | Rating (MVA) | Rating Type | MVA to Mitigate | MW Contribution | |
|---|---|---|---|---|---|---|---|---|---|---|---|
| GD2 | AEP | 05CLOVRD_RJA-05CLOVRD 765.0 kV Ckt Z1 line | AP_P2-3_PE-765-237806-SB1_SRT-SL_SENS | Breaker | AC | 103.15 % | 5523.0 | B | 5696.85 | 7.59 | |
| GD2 | AEP | 05CLOVRD_RJA-05CLOVRD 765.0 kV Ckt Z1 line | AP_P2-3_PE-765-237806-SB2_SRT-SL_SENS | Breaker | AC | 103.15 % | 5523.0 | B | 5696.85 | 7.59 | |
| GD2 | AEP | 05CLOVRD_RJA-05CLOVRD 765.0 kV Ckt Z1 line | AP_P2-3_PE-765-237805-SB6_SRT-SL_SENS | Breaker | AC | 103.14 % | 5523.0 | B | 5696.46 | 7.59 | |
| GD2 | AEP | 05CLOVRD_RJA-05CLOVRD 765.0 kV Ckt Z1 line | AP_P2-3_PE-765-237805-SB5_SRT-SL_SENS | Breaker | AC | 103.14 % | 5523.0 | B | 5696.46 | 7.59 | |
| GD2 | AEP | 05CLOVRD_RJA-05CLOVRD 765.0 kV Ckt Z1 line | AP_P2-3_PE-765-237805-SB3_SRT-SL_SENS | Breaker | AC | 103.14 % | 5523.0 | B | 5696.16 | 7.59 | |
| GD2 | AEP | 05CLOVRD_RJA-05CLOVRD 765.0 kV Ckt Z1 line | AP_P1-2_PE-765-237805-237806_SRT-A_SENS | Single | AC | 102.09 % | 5523.0 | B | 5638.63 | 5.3 | |
| GD2 | AEP | 05CLOVRD_RJA-05CLOVRD 765.0 kV Ckt Z1 line | AP_P1-2_PE-765-242508-237805_SRT-A_SENS | Single | AC | 102.08 % | 5523.0 | B | 5637.94 | 5.3 | |
| GD2 | AEP | 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line | AP_P2-3_PE-765-237806-SB2_SRT-SL_SENS | Breaker | AC | 300.71 % | 1180.0 | B | 3548.35 | 5.7 | |
| GD2 | AEP | 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line | AP_P2-3_PE-765-237806-SB1_SRT-SL_SENS | Breaker | AC | 300.71 % | 1180.0 | B | 3548.35 | 5.7 | |
| GD2 | AEP | 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line | AP_P2-3_PE-765-237805-SB6_SRT-SL_SENS | Breaker | AC | 300.69 % | 1180.0 | B | 3548.19 | 5.7 | |
| GD2 | AEP | 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line | AP_P2-3_PE-765-237805-SB5_SRT-SL_SENS | Breaker | AC | 300.69 % | 1180.0 | B | 3548.19 | 5.7 | |
| GD2 | AEP | 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line | AP_P2-3_PE-765-237805-SB3_SRT-SL_SENS | Breaker | AC | 300.69 % | 1180.0 | B | 3548.09 | 5.7 | |
| GD2 | AEP | 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line | AP_P1-2_PE-765-237805-237806_SRT-A_SENS | Single | AC | 286.57 % | 1180.0 | B | 3381.47 | 3.97 | |
| GD2 | AEP | 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line | AP_P1-2_PE-765-242508-237805_SRT-A_SENS | Single | AC | 286.54 % | 1180.0 | B | 3381.22 | 3.97 | |
| GD2 | AEP | 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line | DVP_P7-1: LN 2168-555_SRT-A | Tower | AC | 253.24 % | 1180.0 | B | 2988.23 | 5.61 | |
| GD2 | AEP | 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line | AEP_P7-1_#17030___SRT-A | Tower | AC | 241.49 % | 1180.0 | B | 2849.63 | 5.57 | |
| GD2 | AEP | 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line | PECO_P2-2_PHILLIPS-BUS_SRT-A/* $ DELCO $ PECO_P2-2_PHILLIPS-BUS $ B | Bus | AC | 237.35 % | 1180.0 | B | 2800.7 | 5.34 | |
| GD2 | AEP | 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line | AEP_P2-2_#10265_05LEESVI 138_1_SRT-A | Bus | AC | 236.49 % | 1180.0 | B | 2790.61 | 5.39 | |
| GD2 | AEP | 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line | Base Case | Single | AC | 222.44 % | 1180.0 | A | 2624.74 | 3.73 | |
| GD2 | AEP | 05J.FERR-05CLOVRD_RJA 765.0 kV Ckt 1 line | AP_P2-3_PE-765-237806-SB1_SRT-SL_SENS | Breaker | AC | 124.63 % | 4571.0 | B | 5696.85 | 7.59 | |
| GD2 | AEP | 05J.FERR-05CLOVRD_RJA 765.0 kV Ckt 1 line | AP_P2-3_PE-765-237806-SB2_SRT-SL_SENS | Breaker | AC | 124.63 % | 4571.0 | B | 5696.85 | 7.59 | |
| GD2 | AEP | 05J.FERR-05CLOVRD_RJA 765.0 kV Ckt 1 line | AP_P2-3_PE-765-237805-SB6_SRT-SL_SENS | Breaker | AC | 124.62 % | 4571.0 | B | 5696.46 | 7.59 | |
| GD2 | AEP | 05J.FERR-05CLOVRD_RJA 765.0 kV Ckt 1 line | AP_P2-3_PE-765-237805-SB5_SRT-SL_SENS | Breaker | AC | 124.62 % | 4571.0 | B | 5696.46 | 7.59 | |
| GD2 | AEP | 05J.FERR-05CLOVRD_RJA 765.0 kV Ckt 1 line | AP_P2-3_PE-765-237805-SB4_SRT-SL_SENS | Breaker | AC | 124.62 % | 4571.0 | B | 5696.16 | 7.59 | |
| GD2 | AEP | 05J.FERR-05CLOVRD_RJA 765.0 kV Ckt 1 line | AP_P1-2_PE-765-237805-237806_SRT-A_SENS | Single | AC | 123.36 % | 4571.0 | B | 5638.63 | 5.3 | |
| GD2 | AEP | 05J.FERR-05CLOVRD_RJA 765.0 kV Ckt 1 line | AP_P1-2_PE-765-242508-237805_SRT-A_SENS | Single | AC | 123.34 % | 4571.0 | B | 5637.94 | 5.3 |
The following flowgates were eliminated after considering the topology reinforcements required by the cycle.
| Study | Area | Facility Description | Contingency Name | Contingency Type | DC|AC | Final Cycle Loading | Rating (MVA) | Rating Type | MVA to Mitigate | MW Contribution | |
|---|---|---|---|---|---|---|---|---|---|---|---|
| GD2 | AEP | 05CLOV17_XFL-05CLOVRD 345.0 kV Ckt 17 line | AEP_P4_#7421_05CLOVRD 765_BB2_SRT-A | Breaker | AC | 107.18 % | 2320.0 | B | 2486.65 | 3.31 | |
| GD2 | AEP | 05CLOV17_XFL-05CLOVRD 345.0 kV Ckt 17 line | AEP_P1-3_#7421_05CLOVRD 765_14_SRT-A | Single | AC | 104.78 % | 2320.0 | B | 2430.97 | 2.31 | |
| GD2 | AEP/DVP | 05CLOVRD-8LEXNGTN 500.0 kV Ckt 1 line | AP_P1-3_MP-765-501T_SRT-A | Single | AC | 118.13 % | 3393.4 | B | 4008.49 | 5.17 | |
| GD2 | AEP/DVP | 05CLOVRD-8LEXNGTN 500.0 kV Ckt 1 line | AP_P2-3_MP-500-020_SRT-SL | Breaker | AC | 115.66 % | 3610.0 | B | 4175.28 | 7.43 | |
| GD2 | AEP/DVP | 05CLOVRD-8LEXNGTN 500.0 kV Ckt 1 line | AP_P2-3_MP-500-021_SRT-SL | Breaker | AC | 115.4 % | 3610.0 | B | 4165.98 | 7.42 | |
| GD2 | AEP/DVP | 05CLOVRD-8LEXNGTN 500.0 kV Ckt 1 line | AEP_P4_#37_05MOUNTN 765_B1_SRT-A | Breaker | AC | 115.26 % | 3610.0 | B | 4160.96 | 7.42 | |
| GD2 | AEP/DVP | 05CLOVRD-8LEXNGTN 500.0 kV Ckt 1 line | AEP_P4_#2942_05KAMMER 765_PP_SRT-A | Breaker | AC | 114.94 % | 3610.0 | B | 4149.41 | 7.42 | |
| GD2 | AEP | 05MOUNTN-05BELMON 765.0 kV Ckt 1 line | AEP_P4_#8075_05MARYSV 765_A2_SRT-A | Breaker | AC | 119.32 % | 5523.0 | B | 6590.12 | 5.29 | |
| GD2 | AEP | 05MOUNTN-05BELMON 765.0 kV Ckt 1 line | AEP_P1-2_#17217_SRT-A | Single | AC | 116.4 % | 5523.0 | B | 6428.58 | 3.63 | |
| GD2 | AEP | 05MOUNTN-05BELMON 765.0 kV Ckt 1 line | AEP_P4_#7445_05MARYSV 765_B_SRT-A | Breaker | AC | 111.96 % | 5523.0 | B | 6183.32 | 5.71 | |
| GD2 | AEP | 05MOUNTN-05BELMON 765.0 kV Ckt 1 line | Base Case | Single | AC | 109.18 % | 4558.0 | A | 4976.63 | 3.39 | |
| GD2 | AEP | 05MOUNTN-05BELMON 765.0 kV Ckt 1 line | AEP_P4_#7422_05CLOVRD 500_EE2_SRT-A | Breaker | AC | 108.41 % | 5523.0 | B | 5987.66 | 6.62 | |
| GD2 | AEP | 05MOUNTN-05BELMON 765.0 kV Ckt 1 line | AEP_P2-2_#7222_05MALIS 765_1_SRT-A | Bus | AC | 107.46 % | 5523.0 | B | 5935.05 | 5.09 | |
| GD2 | AEP | 05MOUNTN-05BELMON 765.0 kV Ckt 1 line | AEP_P1-2_#7422_16_SRT-A | Single | AC | 106.76 % | 5523.0 | B | 5896.19 | 4.62 | |
| GD2 | AEP | 05MOUNTN-05BELMON 765.0 kV Ckt 1 line | AEP_P7-1_#10944___SRT-A | Tower | AC | 105.86 % | 5523.0 | B | 5846.6 | 5.47 | |
| GD2 | AEP | 05MOUNTN-05BELMON 765.0 kV Ckt 1 line | AEP_P7-1_#10856___SRT-A | Tower | AC | 101.88 % | 5523.0 | B | 5626.94 | 5.52 | |
| GD2 | DVP | 8BATH CO-8VALLEY SC 500.0 kV Ckt 1 line | DVP_P1-2: LN 555_SRT-A | Single | AC | 112.06 % | 3220.44 | B | 3608.77 | 3.38 | |
| GD2 | DVP | 8BATH CO-8VALLEY SC 500.0 kV Ckt 1 line | DVP_P7-1: LN 2168-555_SRT-A | Tower | AC | 104.87 % | 3940.0 | C | 4131.96 | 5.46 | |
| GD2 | DVP | 8VALLEY SC-8VALLEY 500.0 kV Ckt 1 line | DVP_P1-2: LN 555_SRT-A | Single | AC | 111.74 % | 3220.44 | B | 3598.36 | 3.38 | |
| GD2 | DVP | 8VALLEY SC-8VALLEY 500.0 kV Ckt 1 line | DVP_P7-1: LN 2168-555_SRT-A | Tower | AC | 104.6 % | 3940.0 | C | 4121.29 | 5.46 |
Winter Peak Analysis
The New Service Request AH1-098 was evaluated as a 40.0 MW (24.0 MW Capacity) injection in the AEP area.
AH1-098 was evaluated as part of a plant. The plant consists of AH1-098. The total Energy output of the plant was evaluated at its maximum seasonal capability of 40.0 MW (40.0 MW under study).
Note: The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for single or N-1 contingencies and multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.
The following flowgates remain after considering the topology reinforcements required by the cycle.
| Study | Area | Facility Description | Contingency Name | Contingency Type | DC|AC | Final Cycle Loading | Rating (MVA) | Rating Type | MVA to Mitigate | MW Contribution | |
|---|---|---|---|---|---|---|---|---|---|---|---|
| GD2 | AEP | 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line | DVP_P1-2: LN 553_SRT-A_SENS | Single | AC | 220.41 % | 1180.0 | B | 2600.84 | 0.32 | |
| GD2 | AEP | 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line | DVP_P4-2: 542T553_SRT-W_SENS | Breaker | AC | 218.08 % | 1180.0 | B | 2573.38 | 0.32 | |
| GD2 | AEP | 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line | DVP_P4-2: 553T564_SRT-W_SENS | Breaker | AC | 217.06 % | 1180.0 | B | 2561.3 | 0.32 | |
| GD2 | AEP | 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line | AP_P1-2_PE-765-242508-237805_SRT-A_SENS | Single | AC | 215.66 % | 1180.0 | B | 2544.77 | 0.34 | |
| GD2 | AEP | 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line | DVP_P7-1: LN 2168-555_SRT-A | Tower | AC | 194.03 % | 1180.0 | B | 2289.58 | 0.33 | |
| GD2 | AEP | 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line | DVP_P7-1: LN 2114-535_SRT-A_SENS | Tower | AC | 190.04 % | 1180.0 | B | 2242.41 | 0.31 | |
| GD2 | AEP | 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line | PECO_P2-2_PHILLIPS-BUS_SRT-A/* $ DELCO $ PECO_P2-2_PHILLIPS-BUS $ B | Bus | AC | 186.82 % | 1180.0 | B | 2204.47 | 0.31 | |
| GD2 | AEP | 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line | DVP_P2-2: BREMO B1_SRT-A | Bus | AC | 186.02 % | 1180.0 | B | 2194.98 | 0.31 | |
| GD2 | AEP | 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line | Base Case | Single | AC | 180.89 % | 1180.0 | A | 2134.53 | 0.31 |
The following flowgates were eliminated after considering the topology reinforcements required by the cycle.
(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)
Light Load Analysis
The New Service Request AH1-098 was evaluated as a 40.0 MW injection and 20.0 MW withdrawal in the AEP area.
AH1-098 was evaluated as part of a plant. The plant consists of AH1-098. The total Energy output of the plant was evaluated at its maximum seasonal capability of 40.0 MW (57.14 MW under study).
Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.
The following flowgates remain after considering the topology reinforcements required by the cycle.
| Study | Area | Facility Description | Contingency Name | Contingency Type | DC|AC | Final Cycle Loading | Rating (MVA) | Rating Type | MVA to Mitigate | MW Contribution | |
|---|---|---|---|---|---|---|---|---|---|---|---|
| GD2 | AEP | 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line | AEP_P4_#7422_05CLOVRD 500_EE2_SRT-A | Breaker | AC | 173.68 % | 1180.0 | B | 2049.45 | 8.7 | |
| GD2 | AEP | 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line | DVP_P4-2: 56602_SRT-A | Breaker | AC | 173.67 % | 1180.0 | B | 2049.35 | 8.7 | |
| GD2 | AEP | 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line | DVP_P4-2: 547T566_SRT-L | Breaker | AC | 173.35 % | 1180.0 | B | 2045.56 | 8.7 | |
| GD2 | AEP | 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line | AP_P2-3_PE-765-237805-SB3_SRT-SL_SENS | Breaker | AC | 138.39 % | 1180.0 | B | 1632.98 | 6.96 | |
| GD2 | AEP | 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line | AP_P2-3_PE-765-237805-SB4_SRT-SL_SENS | Breaker | AC | 138.39 % | 1180.0 | B | 1632.98 | 6.96 | |
| GD2 | AEP | 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line | AEP_P2-2_#1372_05JOSHUA 765_1_SRT-A | Bus | AC | 110.97 % | 1180.0 | B | 1309.48 | 6.75 | |
| GD2 | AEP | 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line | AEP_P7-1_#17030___SRT-A | Tower | AC | 110.49 % | 1180.0 | B | 1303.74 | 6.77 | |
| GD2 | AEP | 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line | AEP_P7-1_#17029___SRT-A | Tower | AC | 110.3 % | 1180.0 | B | 1301.52 | 6.77 | |
| GD2 | AEP | 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line | AEP_P2-2_#10310_05REUSENS1 138_1_SRT-A | Bus | AC | 109.1 % | 1180.0 | B | 1287.39 | 6.67 |
The following flowgates were eliminated after considering the topology reinforcements required by the cycle.
(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)
Short Circuit Analysis
Analysis Complete - No Issues
Based on PJM’s TC2 Phase II Short Circuit Analysis, this project did not contribute >1% fault duty to any previously identified overdutied breakers, nor did it cause any new overdutied breakers.
Please note that in TC2 Phase III, PJM will perform additional analysis including the evaluation of impacts from topology upgrades which may have potential effects on breaker duties not seen in the Phase II analysis.
Stability Analysis
Analysis Complete - No Issues
Executive Summary
New Service Requests AG2-152, AG2-272, AG2-518, AH1-098, AH1-144, AH1-145, AH1-269 and AH1-314 in PJM Transition Cycle 2, Cluster 24 are listed in Table 1. below. This report will cover the dynamic analysis of Cluster 24 projects.
This analysis is effectively a screening study to determine whether the addition of the Cluster 24 projects will meet the dynamics requirements of the NERC, AEP and PJM reliability standards.
Cluster 24 projects were dispatched for stability analysis according to the following scenarios:
a) Scenario 1: AH1-098 dispatched at full MFO injection at the POI with PV MW contribution maxed out and no/reduced MW contribution from BESS.
b) Scenario 2: AH1-098 dispatched at full MFO injection at the POI with BESS MW contribution maxed out, and no/reduced PV MW injection.
c) Scenario 3: AH1-098 dispatched at full MFO injection at the POI with PV and BESS MW contribution proportional to their capacity.
d) Scenario 4: AH1-098 dispatched to full capacity with PV and BESS MW injection maxed out.
This report describes a dynamic simulation analysis of TC2 Cluster 24 for dispatch Scenario 3 as part of the overall system impact study.
The load flow scenario for the analysis was based on the RTEP 2028 Summer Peak, modified to include applicable projects. Cluster 24 projects have been dispatched online at maximum power output, with 1.01 pu voltage at the terminal bus.
Transition Cycle 2 Cluster 24 will be tested for compliance with NERC, PJM and other applicable criteria. The contingencies will be studied with a 20 second simulation time. Contingencies to be studied include:
a) Steady-state operation (Category P0);
b) Three-phase faults with normal clearing time (and with unsuccessful high-speed reclosing) (Category P1);
c) Single-phase bus faults with normal clearing time (Category P2);
d) Single-phase faults with stuck breaker (Category P4);
e) Single-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure (Category P5);
f) Three-phase faults with loss of multiple-circuit tower line; (and with unsuccessful high-speed reclosing) (Category P7).
High Speed Reclosing (HSR) facilities were found in the vicinity of TC2 Cluster 24 projects.
Prior outage scenarios will not be considered for this study.
For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.
For all the fault contingencies tested on the 2028 peak load case:
a) Cluster 24 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
b) The system with Cluster 24 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
c) Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
d) No transmission element tripped, other than those either directly connected or designed to trip because of that fault.
The IPCMD and IQCMD states in the REGCA1 models of all units of Cluster 24 showed erratic behavior for some contingencies in which queue project has been disconnected as part of the contingency event. Since the machines are disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.
Tripping was observed for several contingencies (P4.081, P4.082, P5.39, and P5.48) under the initial study conditions. Upon updating the fault impedance values based on Aspen short circuit case, the tripping issues were resolved, and the system remained stable for these contingencies.
AH1-098 both Solar and BESS units tripped under several contingencies. Upon updating Vdip to 0.8 (Original value was 0.9) and Vup to 1.2 (Original value was 1.1) for both units resolved all tripping issue.
Fictitious frequency response at AH1-145 generator bus tripped the queue project for several contingencies (P1.073, P1.075 and P1.076). Therefore, the frequency relay pickup times for were set to 20 seconds to avoid fictitious frequency tripping of the unit.
AG2-272 generating units exhibited slow reactive power recovery within the 20 second simulation window for several contingencies. This issue did not cause instability in the system. The reactive power droop compensation was enabled and tuned by updating Kc to 0.15 (original value was 0) which resolved the slow reactive power response.
AH1-269 generating units exhibited slow reactive power recovery within the 20 second simulation window for several contingencies. This issue did not cause instability in the system. The reactive power droop compensation was enabled and tuned by updating Kc to 0.1 (original value was 0) which resolved the slow reactive power response.
AH1-314 generating units exhibited slow reactive power recovery within the 20 second simulation window for several contingencies. This issue did not cause instability in the system. The reactive power droop compensation was enabled and tuned by updating Kc to 0.1 (original value was 0) which resolved the slow reactive power response.
The active power for AG2-152 did not recover to the pre fault value for contingency P7.21 due inadequate reactive power response. The reactive power droop compensation gain Kc parameter was updated to 0.1 which resolved the active power recovery issue.
Smith Mountain generators showed positively damped oscillations which did not settle during the 20 second simulation window. The selected contingencies were run for 30 seconds, and the oscillatory signals achieved a flat response at the end of the 30 second simulation time period.
No mitigations were found to be required.
Table 1: Transition Cycle 2 Cluster 24 Queues
Table 1: Transition Cycle 2 Cluster 24 Projects |
|
|
|
|
Project | Fuel Type | Transmission Owner | MFO (MW) | Point of Interconnection |
AG2-152 | Solar | AEP | 131 | Banister – Bearskin 138 kV |
AG2-272 | Battery | AEP | 55 | Berry Hill substation 138 kV |
AG2-518 | Battery | AEP | 80 | Tech Drive substation 138 kV |
AH1-098 | Solar/Battery | AEP | 40 | West Carroll – Wolf Glade 138 kV |
AH1-144 | Solar | AEP | 70 | Peter’s Mountain Substation 138 kV |
AH1-145 | Battery | AEP | 80 | Peter’s Mountain Substation 138 kV |
AH1-269 | Battery | AEP | 50 | Claytor substation 138 kV |
AH1-314 | Battery | AEP | 100 | East Danville substation 138 kV |
Reactive Power Analysis
Analysis Complete - No Issues
The reactive power capability of AH1-098 meets the 0.95 leading and lagging PF requirement at the high side of the main transformer.
Steady-State Voltage Analysis
Analysis Complete - No Issues
Steady State Voltage Analysis complete, no voltage issues identified.
New Service Request Dependencies
The New Service Requests below are listed in one or more dispatch for the overloads identified in this report. These projects contribute to the loading of the overloaded facilities identified in this report. The percent overload of a facility and cost allocation you may have towards a particular reinforcement could vary depending on the action of other projects. The status of each project at the time of the analysis is presented in the table. This list may change as other projects withdraw or modify their requests. This table is valid for load flow analyses only.
| New Service Requests Dependencies | ||
|---|---|---|
| Project ID | Project Name | Status |
| AA1-018 | Powerton-Goodings Grove | In Service |
| AA1-038 | Lexington-Low Moor 230kV | Under Construction |
| AB1-006 | Meadow Lake 345kV | In Service |
| AB1-027 | Old Church 34.5 KV | In Service |
| AB2-024 | Correctional 34.5kV | In Service |
| AB2-026 | Powhatan 34.5kV | In Service |
| AB2-029 | Remington 34.5kV | In Service |
| AB2-045 | Buckingham 34.5kV | In Service |
| AB2-070 | Mt. Pulaski-Brokaw | In Service |
| AB2-134 | Hopewell-Surry 230kV | In Service |
| AB2-157 | Prince George's County 12kV | In Service |
| AB2-158 | Louisa-South Anna 230kV | In Service |
| AB2-161 | Waverly #2 DP 115kV | In Service |
| AB2-190 | Hopewell-Surry 230kV | In Service |
| AC1-001 | Delano 138kV | In Service |
| AC1-027 | Pendleton 34.5kV | In Service |
| AC1-033 | Kewanee 138 kV | In Service |
| AC1-042 | Altavista-Mt. Airy 69kV | In Service |
| AC1-053 | Lanesville-Brokaw | In Service |
| AC1-068 | Atlanta 69kV I | In Service |
| AC1-069 | Atlanta 69kV II | In Service |
| AC1-074 | Jacksonville-Renaker 138kV I | In Service |
| AC1-075 | Perth-Hickory Grove 115kV | In Service |
| AC1-076 | Locust Grove-Paytes 115kV | In Service |
| AC1-082 | Ravenswood-Hemlock 69kV | Partially in Service - Under Construction |
| AC1-085 | Stuart-Clinton 345kV | In Service |
| AC1-089 | Hillsboro-Wildcat 138kV | In Service |
| AC1-101 | Johns Creek-Excel 138kV I | Engineering & Procurement |
| AC1-102 | Johns Creek-Excel 138kV II | Engineering & Procurement |
| AC1-111 | Aurora 138kV | In Service |
| AC1-118 | Westmoreland 34.5kV | In Service |
| AC1-122 | Smith Mountain-Candler's Mountain 138kV | In Service |
| AC1-145 | Gretna DP 69 kV | In Service |
| AC1-147 | Grassfield 34.5kV | In Service |
| AC1-158 | Spotsylvania 500kV | In Service |
| AC1-161 | Septa 500kV | In Service |
| AC1-164 | Chickahominy 230kV | Partially in Service - Under Construction |
| AC1-168 | Kewanee-Streator | Suspended |
| AC1-174 | Losantville 345kV | In Service |
| AC1-175 | Losantville 345kV | In Service |
| AC1-188 | Rio-Lick 138kV | Engineering & Procurement |
| AC1-191 | Elmont 115kV | Engineering & Procurement |
| AC1-194 | Elk 138kV | Engineering & Procurement |
| AC1-214 | Crescent Ridge | In Service |
| AC2-012 | Grassfield-Great Bridge 115kV | In Service |
| AC2-029 | Circleville 138kV | Suspended |
| AC2-059 | Biers Run-Circleville 138kV | In Service |
| AC2-060 | Buckskin 69kV | In Service |
| AC2-061 | Hillsboro-Clinton 138kV | In Service |
| AC2-075 | Jacksonville-Renaker 138 kV | In Service |
| AC2-088 | S. Bethel-Brown 69kV | In Service |
| AC2-090 | Losantville 345kV | In Service |
| AC2-111 | College Corner 138kV | Engineering & Procurement |
| AC2-120 | Ripley 69kV | In Service |
| AC2-123 | Jacksons Ferry 138kV | In Service |
| AC2-137 | Elko 34.5kV | In Service |
| AC2-138 | Northern Neck 34.5kV | In Service |
| AC2-141 | Septa 500kV | Engineering & Procurement |
| AC2-157 | Sullivan 345 kV | Partially in Service - Under Construction |
| AC2-176 | Jay 138 kV | In Service |
| AD1-025 | Hopewell-Surry 230 kV | In Service |
| AD1-033 | Fentress-Landstown 230 kV | In Service |
| AD1-041 | Harmony Village-Shackleford 115 kV | In Service |
| AD1-063 | Harmony Village 34.5 kV | In Service |
| AD1-082 | Bakers Pond-Ivor 115kV | In Service |
| AD1-100 | Loretto-Wilton 345 kV & Braidwood-Davis Creek 345 kV | Under Construction |
| AD1-105 | Kings Dominion DP 115 kV | Under Construction |
| AD1-115 | Mountain Run-Mitchell 115 kV | Withdrawn |
| AD1-128 | Modoc-Delaware 138 kV | In Service |
| AD1-136 | South Bethel-Brown 69 kV | In Service |
| AD1-140 | Greene-Clark 138 kV | Engineering & Procurement |
| AD1-144 | Kings Fork 34.5 kV | In Service |
| AD1-155 | Meadow Brook-Strasburg 138 kV | In Service |
| AD2-016 | Biers Run-Circleville 138 kV | In Service |
| AD2-030 | Wan 34.5 kV | In Service |
| AD2-031 | Martinsville-Wilmington 69 kV | In Service |
| AD2-038 | Powerton-Nevada 345 kV | Under Construction |
| AD2-047 | Davis Creek 138 kV | Suspended |
| AD2-048 | Cynthia-Headquarters 69 kV | Under Construction |
| AD2-058 | St. Barnabas 13 kV | In Service |
| AD2-060 | Davis Creek 138kV | Engineering & Procurement |
| AD2-066 | Mazon-Crescent Ridge 138 kV | Under Construction |
| AD2-071 | Strawton-Deer Creek 138 kV | Suspended |
| AD2-073 | Sanders DP 230 kV | In Service |
| AD2-074 | Garner DP-Lancaster 115 kV | Under Construction |
| AD2-100 | Kincaid-Pana 345 kV | Suspended |
| AD2-131 | Kincaid-Pana 345kV | Suspended |
| AD2-134 | Shady Oaks | Partially in Service - Under Construction |
| AD2-172 | Lena 138kV | In Service |
| AD2-179 | Morgans Cut-Glen Lyn 138kV | Withdrawn |
| AE1-074 | Winterpock 34.5 kV | Under Construction |
| AE1-075 | Powhatan 34.5 kV | In Service |
| AE1-100 | Axton 138 kV | In Service |
| AE1-108 | Bremo-Scottsville 138 kV | Under Construction |
| AE1-113 | Mole Creek 345 kV | Under Construction |
| AE1-114 | Maryland-Lancaster 138 kV | Engineering & Procurement |
| AE1-143 | Marion County 161 kV | Under Construction |
| AE1-155 | Garner-Northern Neck 115 kV | In Service |
| AE1-162 | Smithfield 34.5 kV | In Service |
| AE1-163 | Powerton-Nevada 345 kV | Under Construction |
| AE1-166 | Loretto-Wilton 345 kV & Braidwood-Davis Creek 345 kV | Engineering & Procurement |
| AE1-170 | Kenzie Creek-Colby 138 kV | Suspended |
| AE1-172 | Loretto-Wilton Center | Withdrawn |
| AE1-175 | Light Foot 34.5 kV | In Service |
| AE1-176 | Roanoke-Vinton 12 kV (Niagara Hydro) | In Service |
| AE1-190 | Harmony Village-Shackleford 115 kV | In Service |
| AE1-191 | Harmony Village-Shackleford 115 kV | In Service |
| AE1-205 | McLean 345 kV | Engineering & Procurement |
| AE1-207 | Mississinewa-Gaston 138 kV | Suspended |
| AE1-208 | Delaware-Van Buren 138 kV | Suspended |
| AE1-209 | Desoto 345 kV | Suspended |
| AE1-210 | Desoto 345 kV | Suspended |
| AE1-212 | Grandview-Clifftop 138 kV | Suspended |
| AE2-005 | Harmony Village-Shackleford 115 kV | Suspended |
| AE2-027 | Harrowgate-Locks 115kV | Suspended |
| AE2-029 | Grottoes-Merck 115kV | Under Construction |
| AE2-035 | Lena 138 kV | In Service |
| AE2-045 | Olive-Reynolds 345 kV | Engineering & Procurement |
| AE2-071 | Patton Rd-Summer Shade 69 kV | In Service |
| AE2-089 | Pennville-Adams 138 kV | Suspended |
| AE2-092 | Kidds Store-Sherwood 115 kV | Engineering & Procurement |
| AE2-140 | Axton-Danville 138 kV | Suspended |
| AE2-152 | Loretto-Wilton 345 kV & Braidwood-Davis Creek 345 kV | Engineering & Procurement |
| AE2-160 | Kanawha River 138 kV | Engineering & Procurement |
| AE2-166 | Stockton 138 kV | Suspended |
| AE2-169 | Delaware-Van Buren 138 kV | Suspended |
| AE2-172 | Mississinewa-Gaston 138 kV | Suspended |
| AE2-185 | Gladys DP-Stonemill Switching Station 69 kV | Engineering & Procurement |
| AE2-212 | Harrowgate 34 kV | Engineering & Procurement |
| AE2-219 | Bluff Point-Randolph 138 kV | Suspended |
| AE2-220 | Losantville 345 kV | Engineering & Procurement |
| AE2-221 | Clinton-Stuart 345 kV | Under Construction |
| AE2-223 | McLean 345 kV | Engineering & Procurement |
| AE2-226 | Millville-Old Chapel 138 kV | Engineering & Procurement |
| AE2-230 | Bartonsville-Meadow Brook 138 kV | In Service |
| AE2-234 | Liberty Center-Buckeye Tap 69 kV | Engineering & Procurement |
| AE2-236 | Columbia-Northeast 138 kV | Suspended |
| AE2-254 | Garrard County-Tommy-Gooch 69 kV | In Service |
| AE2-255 | Molecreek 345 kV | Under Construction |
| AE2-261 | Kincaid-Pana 345 kV | Engineering & Procurement |
| AE2-267 | Woodsdale 345 kV | Engineering & Procurement |
| AE2-283 | Gladys-Stone Mill 69 kV | Engineering & Procurement |
| AE2-297 | Madison-Tanners Creek 138 kV | In Service |
| AE2-308 | Three Forks-Dale 138 kV | Engineering & Procurement |
| AE2-315 | Yankee Tap 69 kV | In Service |
| AE2-318 | Ford-Cedarville 138 kV | Suspended |
| AE2-326 | Jacksons Ferry 138 kV | Engineering & Procurement |
| AE2-339 | Avon 138 kV | Under Construction |
| AE2-341 | Sandwich-Plano 138 kV | Engineering & Procurement |
| AF1-014 | Harmony Village-Shackleford 115 kV | Suspended |
| AF1-030 | Sandwich-Plano 138 kV | Engineering & Procurement |
| AF1-038 | Sewellton Jct-Webbs Crossroads 69 kV | Under Construction |
| AF1-042 | Garner DP-Lancaster 115 kV | Engineering & Procurement |
| AF1-045 | Cedarville-Ford 138 kV | Suspended |
| AF1-049 | Berry Hill 138 kV | Under Construction |
| AF1-050 | Summer Shade - Green County 161 kV | Engineering & Procurement |
| AF1-071 | College Corner 138 kV | Engineering & Procurement |
| AF1-083 | Green County-Saloma 161 kV | Engineering & Procurement |
| AF1-090 | Kincaid-Pana | Engineering & Procurement |
| AF1-092 | Huntington Jct. 138 kV | Withdrawn |
| AF1-114 | Oak Grove-Dahlgren 230 kV | Engineering & Procurement |
| AF1-118 | Sorenson-Desoto 345 kV | Withdrawn |
| AF1-119 | Keystone-Desoto 345 kV | Engineering & Procurement |
| AF1-130 | Inez 138 kV | Suspended |
| AF1-147 | Poland Rd-Runway DP 230kV | Partially in Service - Under Construction |
| AF1-158 | Edison-Gravel Pit 138 kV | In Service |
| AF1-162 | Inez 138 kV | Engineering & Procurement |
| AF1-176 | Corey 138 kV | Engineering & Procurement |
| AF1-202 | Keystone-Desoto 345 kV | Under Construction |
| AF1-203 | Patton Rd-Summer Shade 69 kV | In Service |
| AF1-204 | Eugene 345 kV | Engineering & Procurement |
| AF1-207 | Reynolds-Olive #1 345 kV | Engineering & Procurement |
| AF1-215 | Olive-Reynolds 345 kV | In Service |
| AF1-223 | Keystone-Desoto 345 kV | Under Construction |
| AF1-233 | Flemingsburg – Spurlock 138kV | Engineering & Procurement |
| AF1-249 | Nickel 12.47 kV | In Service |
| AF1-268 | Desoto-Jay 138 kV | Engineering & Procurement |
| AF1-282 | Stuart-Clinton 345 kV | Engineering & Procurement |
| AF1-283 | Stuart-Clinton 345 kV | Engineering & Procurement |
| AF1-291 | Tyler 34.5 kV | Engineering & Procurement |
| AF1-291A | Bartonsville-Meadow Brook 138 kV | In Service |
| AF1-296 | Garden Plain 138 kV | Engineering & Procurement |
| AF1-322 | Meadow Lake 345 kV | Under Construction |
| AF1-331 | Twombley Road | Engineering & Procurement |
| AF2-013 | Arnold's Corner-Dahlgren 230 kV | Engineering & Procurement |
| AF2-018 | Inez 138 kV | Engineering & Procurement |
| AF2-032 | Kincaid 345 kV | Withdrawn |
| AF2-041 | Nelson-Electric Junction 345 kV | Engineering & Procurement |
| AF2-048 | Rio-Lick 138 kV | Engineering & Procurement |
| AF2-054 | Wan 34.5 kV | In Service |
| AF2-068 | Jay 138 kV | Engineering & Procurement |
| AF2-075 | Bartonsville-Meadow Brook 138 kV III | In Service |
| AF2-077 | White Marsh 34.5 kV | In Service |
| AF2-078 | Reynolds-Olive #1 345 kV | Engineering & Procurement |
| AF2-083 | Kenzie Creek-Stone Lake 69 kV | Under Construction |
| AF2-085 | Midlothian 34.5 kV | In Service |
| AF2-091 | Oak Grove-Dahlgren 230 kV | Engineering & Procurement |
| AF2-095 | Davis Creek 138 kV | Engineering & Procurement |
| AF2-106 | Hazel Hollow-Glen Lyn #1 138 kV | Engineering & Procurement |
| AF2-111 | North Clark-Spurlock 345 kV | Engineering & Procurement |
| AF2-132 | Reynolds-Olive #1 345 kV | Under Construction |
| AF2-133 | Reynolds-Olive #2 345 kV | Under Construction |
| AF2-134 | Olive-Reynolds #2 345 kV | In Service |
| AF2-142 | Nevada 345 kV | Engineering & Procurement |
| AF2-143 | Powerton-Nevada 345 kV | Engineering & Procurement |
| AF2-144 | Powhatan 34.5 kV | In Service |
| AF2-177 | Sorenson-DeSoto #2 345 kV | Engineering & Procurement |
| AF2-199 | Nelson-Electric Junction 345 kV | Engineering & Procurement |
| AF2-200 | Nelson-Electric Junction 345 kV | Engineering & Procurement |
| AF2-205 | Olive-Reynolds #2 345 kV | Engineering & Procurement |
| AF2-225 | McLean 345 kV | Engineering & Procurement |
| AF2-252 | Blue Mound 345 kV | Engineering & Procurement |
| AF2-291 | Sporn South-Leon 138 kV | Engineering & Procurement |
| AF2-350 | Kensington 138 kV | Engineering & Procurement |
| AF2-352 | Blue Mound 345 kV | Engineering & Procurement |
| AF2-359 | Olive-University Park 345 kV | Engineering & Procurement |
| AF2-382 | Hurley 69 kV | Engineering & Procurement |
| AF2-388 | Keystone-Desoto 345 kV | Engineering & Procurement |
| AF2-404 | Gladys DP-Stonemill 69 kV | Engineering & Procurement |
| AF2-440 | Hillsboro-Middleboro 138 kV | Under Construction |
| AG1-038 | Garner DP-Lancaster 115 kV | Engineering & Procurement |
| AG1-047 | Jay 138 kV | Engineering & Procurement |
| AG1-066 | Bonnyman 69 kV | Engineering & Procurement |
| AG1-107 | Hillsboro-Middleboro 138 kV | Under Construction |
| AG1-118 | Sugar Grove-Waterman 138kV | Engineering & Procurement |
| AG1-124 | Riverville - Gladstone 138 kV | Engineering & Procurement |
| AG1-127 | Crego Rd 138 kV | Engineering & Procurement |
| AG1-145 | Lightfoot 34.5 kV | In Service |
| AG1-152 | Remington CT 230 kV | Engineering & Procurement |
| AG1-226 | Dequine-Eugene 345 kV | Engineering & Procurement |
| AG1-232 | Magley 138 kV | Engineering & Procurement |
| AG1-237 | Dequine-Eugene 345 kV | Engineering & Procurement |
| AG1-282 | Dunnsville 34.5 kV | Withdrawn |
| AG1-302 | Olive-Reynolds #1 345 kV | Under Construction |
| AG1-320 | Hodgenville-Stephensburg 69 kV | Engineering & Procurement |
| AG1-324 | Jay-Desoto 138 kV | Engineering & Procurement |
| AG1-341 | Summer Shade 161 kV | Engineering & Procurement |
| AG1-349 | Olive-Reynolds #2 345 kV | Engineering & Procurement |
| AG1-354 | Summershade-Green County 161 kV | Engineering & Procurement |
| AG1-374 | Blue Mound 345 kV | Engineering & Procurement |
| AG1-433 | Keystone-DeSoto 345 kV | Engineering & Procurement |
| AG1-436 | Olive-University Park 345 kV | Engineering & Procurement |
| AG1-447 | Olive-University Park 345 kV | Engineering & Procurement |
| AG1-460 | Kincaid-Pana 345 kV | Engineering & Procurement |
| AG1-462 | Cordova 345 kV | Engineering & Procurement |
| AG1-469 | Gordonsville 34.5 kV | Withdrawn |
| AG1-471 | Up Church-Wayne County 69 kV | Engineering & Procurement |
| AG1-478 | Wilmington 34.5 kV | Engineering & Procurement |
| AG1-508 | Point Lookout 69 kV | Withdrawn |
| AG1-555 | Dequine 345 kV | Engineering & Procurement |
| AG1-558 | Buckner 34.5 kV | Withdrawn |
| AG1-559 | Caroline Pines 22 kV | Withdrawn |
| AG2-061 | Dana 345 kV | Active |
| AG2-072 | Rockport 765 kV | Active |
| AG2-073 | Crooksville 69 kV | Active |
| AG2-081 | Avon - Renaker 138 kV | Active |
| AG2-088 | Midlothian 230 kV | Active |
| AG2-114 | Dresden-Pontiac Midpoint 345 kV | Active |
| AG2-125 | Camden-Crystal 69 kV | Active |
| AG2-126 | Eugene 345 kV | Active |
| AG2-163 | Dequine-Eugene 345 kV | Active |
| AG2-184 | Harbert Metering 138 kV | Active |
| AG2-191 | Mississinewa 138 kV | Active |
| AG2-192 | Mississinewa 138 kV | Active |
| AG2-230 | Dumont 345 kV | Active |
| AG2-240 | Old Church 34.5 kV | Active |
| AG2-245 | Olive - Reynolds #1 345 kV | Active |
| AG2-272 | Berry Hill 138 kV | Active |
| AG2-298 | Sulphur Creek-Loretto 69 kV | Active |
| AG2-360 | Broadford 138 kV | Active |
| AG2-363 | Powerton 345 kV | Active |
| AG2-364 | Powerton 345 kV | Active |
| AG2-401 | Losantville 345 kV | Active |
| AG2-424 | Summersville - Magnolia 69 kV | Active |
| AG2-453 | Lasalle - Plano 345 kV | Active |
| AG2-487 | Madison - Tanners Creek 138 kV | Active |
| AG2-491 | Meadow Lake 345 kV | Active |
| AG2-516 | Pecatonica 138kV | Active |
| AG2-518 | Tech Drive 138 kV | Active |
| AG2-519 | Royerton - Desoto 138 kV | Active |
| AG2-524 | LaSalle Station - Mazon 138 kV | Active |
| AG2-548 | Corwin - Elk 138 kV | Active |
| AG2-550 | Bluff Point - Randolph 138 kV | Active |
| AG2-551 | Bluff Point - Randolph 138 kV | Active |
| AG2-568 | Stink Run - Sundial 138 kV | Active |
| AG2-585 | Kensignton 138kV | Active |
| AG2-637 | Randolph - Hodgin 138 kV | Active |
| AG2-657 | Kanawha River - Carbondale 138 kV | Active |
| AG2-660 | Nelson-Electric Junction 345 kV | Active |
| AG2-665 | Corwin - Elk 138 kV | Active |
| AG2-675 | Cordova 345 kV | Active |
| AH1-004 | Avon - Renaker 138 kV | Active |
| AH1-044 | Nelson - Electric Junction 345 kV | Active |
| AH1-055 | Kyger Creek - Don Marquis 345 kV | Active |
| AH1-072 | Red Onion - VC5 69 kV | Active |
| AH1-073 | Red Onion - VC5 69 kV | Active |
| AH1-133 | Saltville - Tazewell 138 kV | Active |
| AH1-144 | Peter's Mountain 138 kV | Active |
| AH1-145 | Peter's Mountain 138 kV | Active |
| AH1-150 | Nelson-Electric Junction 345 kV | Active |
| AH1-151 | Nelson-Electric Junction 345 kV | Active |
| AH1-153 | Dumont 345 kV | Active |
| AH1-188 | Pigeon Creek 138 kV | Active |
| AH1-196 | Silver Lake - Cherry Valley 345 kV | Active |
| AH1-227 | Flemming - Fremont 69 kV | Active |
| AH1-239 | Upchurch - Zula 69 kV | Active |
| AH1-251 | Todds Tavern- Spotsylvania/Goldsdale 115kV | Active |
| AH1-263 | Chancellor 115 kV | Active |
| AH1-269 | Claytor 138 kV | Active |
| AH1-292 | Sullivan 345 kV | Active |
| AH1-302 | Olive - Reynolds 345 kV | Active |
| AH1-304 | Delaware-Van Buren 138 kV | Active |
| AH1-305 | Olive - Reynolds 345 kV | Active |
| AH1-306 | Mississinewa-Gaston 138 kV | Active |
| AH1-338 | New Sub S2354 138kV | Active |
| AH1-341 | ESS-H445 3B 138kv | Active |
| AH1-348 | Pound 34.5 kV | Active |
| AH1-392 | Gravel Pit-Kankakee 138 kV | Active |
| AH1-461 | Buckhorn 138 kV | Active |
| AH1-482 | Olive - Reynolds #2 345 kV | Active |
| AH1-535 | Nagel - Cane River 230 kV | Active |
| AH1-537 | Pierce - Kyger Creek 345 kV | Active |
| AH1-541 | Chestnut 345 kV | Active |
| AH1-543 | Mulberry - Tazewell 345 kV | Active |
| AH1-570 | Millersburg 69 kV | Active |
| AH1-571 | Millersburg 69 kV | Active |
| AH1-617 | Harbert Metering 138 kV | Active |
| AH1-664 | Goddard-Plumville 138 kV | Active |
| AH1-665 | Goddard-Plumsville 138 kV II | Active |
| AH1-666 | Flemingsburg - Spurlock 138 kV | Active |
| AH1-686 | Hanging Rock 765 kV | Active |
| AH1-702 | Byron 345 kV | Active |
| AH1-714 | Lasalle 345 kV | Active |
| AH1-718 | Nelson 345 kV | Active |
| AH1-721 | Laurel-Cooper 161 kV | Active |
| V3-007 | Desoto-Tanners Creek #1 345kV | In Service |
| W2-048 | Brokaw-Lanesville | In Service |
| W4-005 | Blue Mound-Latham | In Service |
| X2-022 | Brokaw-Lanesville | In Service |
| Y1-049 | Wurno 34.5kV | In Service |
| Z2-087 | Pontiac MidPoint-Brokaw 345kV | In Service |
| Z2-115 | Deer Creek 12.47kV | In Service |
Affected System - PJM Identified Violations
As part of PJM's analysis, per Tariff Part VII.G.336 & Manual 14H, Section 13, PJM evaluated the potential impacts on tie line facilities between PJM and an affected system entity, which were identified per PJM planning analysis criteria. This upgrade may be required on the affected system portion of the tie line along with cost allocation of such upgrade if applicable, in coordination with the affected system. Depending on the affected system, this project may not be contingent on upgrade based on PJM planning analysis criteria, but may be contingent on this upgrade based on the Affected System Operator's planning criteria, provided in the Affected Systems Study Section, herein.
Affected System - Non-PJM Identified Violations
In accordance with PJM Tariff Part VII, Subpart D, section 310.A and as outlined in PJM Manual 14H, Sections 4.5 and 13, in Phase II of the Cycle, PJM provides the Affected System Operator any updates on the PJM projects that require an Affected Systems Study based on their response at DP1. New Service Requests that require an Affected Systems Study are required to enter into an Affected Systems Study Agreement with the Affected System Operator, as applicable, prior to the close of DP2 or they will be withdrawn from the Cycle.
If the Project Developer already entered into the necessary agreement and the results are available, PJM will supply them in the Phase II SIS report. See below for the status of any required Affected Systems Study. A status of “Pending” means that the study is not yet completed by the Affected System Operator. If your project requires an Affected Systems Study and your results are not provided for Phase II SIS, PJM anticipates providing them in the Phase III SIS per Tariff Part VII.D.312.
System Reinforcements
No cost allocated system reinforcements were identified for this project in the Phase II System Impact Study load flow analysis.
Shown below are the details of the cost allocated, contingent, eliminated, topology and potential aggregate contributor reinforcements for this project. Please refer to the System Reinforcement table above and the information below for more detail.
System Reinforcement: b4000.10
- Type
- Load Flow
- TO
- APS
- RTEP ID / TO ID
- b4000.10
- Title
- Install four 250 MVAR cap banks (two on 765 and two on 500 kV side) and a +/-500 MVAR STATCOM on the 765 kV Rocky Point yard
- Description
- 765kV Solution: 2024 W1 Solution - Regional Cluster Ties Doubs 500kV area to John Amos 765kV via a new 765kV line
- Cost Information
- Time Estimate
- Jun 01 2029
Not ContingentTopology Changing Note 1: AH1-098 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-098 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 05MOUNTN-05BELMON 765.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 05CLOVRD-05CLOV17_XFL 345.0 kV Ckt 17 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.9
- Type
- Load Flow
- TO
- APS
- RTEP ID / TO ID
- b4000.9
- Title
- Construct a new substation called Rocky Point with a 765 kV and a 500 kV yard (Projected ISD 6/1/2029)
- Description
- Construct a new substation called Rocky Point with a 765 kV and a 500 kV yard. Loop in the Doubs-Goose Creek 500 kV line, the Doubs-Aspen 500 kV line, and the Woodside-Goose Creek 500 kV line. Install two 765/500 kV transformer at Rocky Point substation. 765kV Solution: 2024 W1 Solution - Regional Cluster Ties Doubs 500kV area to John Amos 765kV via a new 765kV line
- Cost Information
- Time Estimate
- Jun 01 2029
Not ContingentTopology Changing Note 1: AH1-098 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-098 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 05MOUNTN-05BELMON 765.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 05CLOVRD-05CLOV17_XFL 345.0 kV Ckt 17 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.8
- Type
- Load Flow
- TO
- APS
- RTEP ID / TO ID
- b4000.8
- Title
- Construct a new 86 miles Welton Spring to Rocky Point 765 kV line (DVP local area to Rocky Point, roughly 4.8 miles)
- Description
- 765kV Solution: 2024 W1 Solution - Regional Cluster Ties Doubs 500kV area to John Amos 765kV via a new 765kV line
- Cost Information
- Time Estimate
- Jun 01 2029
Not ContingentTopology Changing Note 1: AH1-098 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-098 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 05MOUNTN-05BELMON 765.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 05CLOVRD-05CLOV17_XFL 345.0 kV Ckt 17 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.7
- Type
- Load Flow
- TO
- APS
- RTEP ID / TO ID
- b4000.7
- Title
- Construct a new 86 miles Welton Spring to Rocky Point 765 kV line - in DVP local area/Millville to Lovettsville section, roughly 10.5 miles (Projected ISD 6/1/2029)
- Description
- 765kV Solution: 2024 W1 Solution - Regional Cluster Ties Doubs 500kV area to John Amos 765kV via a new 765kV line
- Cost Information
- Time Estimate
- Jun 01 2029
Not ContingentTopology Changing Note 1: AH1-098 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-098 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 05MOUNTN-05BELMON 765.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 05CLOVRD-05CLOV17_XFL 345.0 kV Ckt 17 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.6
- Type
- Load Flow
- TO
- APS
- RTEP ID / TO ID
- b4000.6
- Title
- Construct a new 86 miles Welton Spring to Rocky Point 765 kV line (Welton Spring to DVP local area, roughly 21 miles) (VA Portion)
- Description
- 765kV Solution: 2024 W1 Solution - Regional Cluster Ties Doubs 500kV area to John Amos 765kV via a new 765kV line
- Cost Information
- Time Estimate
- Jun 01 2029
Not ContingentTopology Changing Note 1: AH1-098 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-098 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 05MOUNTN-05BELMON 765.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 05CLOVRD-05CLOV17_XFL 345.0 kV Ckt 17 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.5
- Type
- Load Flow
- TO
- APS
- RTEP ID / TO ID
- b4000.5
- Title
- Install four 250 MVAR shunt capacitors, and a +/-500 MVAR STATCOM at Welton Spring 765 kV substation
- Description
- 765kV Solution: 2024 W1 Solution - Regional Cluster Ties Doubs 500kV area to John Amos 765kV via a new 765kV line
- Cost Information
- Time Estimate
- Jun 01 2029
Not ContingentTopology Changing Note 1: AH1-098 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-098 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 05MOUNTN-05BELMON 765.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 05CLOVRD-05CLOV17_XFL 345.0 kV Ckt 17 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.4
- Type
- Load Flow
- TO
- APS
- RTEP ID / TO ID
- b4000.4
- Title
- Construct a new 765 kV switchyard - Welton Spring (Projected ISD 6/1/2029)
- Description
- 765kV Solution: 2024 W1 Solution - Regional Cluster Ties Doubs 500kV area to John Amos 765kV via a new 765kV line
- Cost Information
- Time Estimate
- Jun 01 2029
Not ContingentTopology Changing Note 1: AH1-098 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-098 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 05MOUNTN-05BELMON 765.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 05CLOVRD-05CLOV17_XFL 345.0 kV Ckt 17 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.3
- Type
- Load Flow
- TO
- APS
- RTEP ID / TO ID
- b4000.3
- Title
- Construct a new 175 miles Amos to Welton Spring 765 kV line - APS/FE Section of the line is 145 miles (Projected ISD 6/1/2029)
- Description
- 765kV Solution: 2024 W1 Solution - Regional Cluster Ties Doubs 500kV area to John Amos 765kV via a new 765kV line
- Cost Information
- Time Estimate
- Jun 01 2029
Not ContingentTopology Changing Note 1: AH1-098 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-098 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 05MOUNTN-05BELMON 765.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 05CLOVRD-05CLOV17_XFL 345.0 kV Ckt 17 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.2
- Type
- Load Flow
- TO
- APS
- RTEP ID / TO ID
- b4000.2
- Title
- Construct a new 175 miles Amos to Welton Spring 765 kV line - AEP Section of the line is 30 miles (Projected ISD 6/1/2029)
- Description
- 765kV Solution: 2024 W1 Solution - Regional Cluster Ties Doubs 500kV area to John Amos 765kV via a new 765kV line
- Cost Information
- Time Estimate
- Jun 01 2029
Not ContingentTopology Changing Note 1: AH1-098 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-098 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 05MOUNTN-05BELMON 765.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 05CLOVRD-05CLOV17_XFL 345.0 kV Ckt 17 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.1
- Type
- Load Flow
- TO
- AEP
- RTEP ID / TO ID
- b4000.1
- Title
- Add two 765 kV breakers at Amos Substation to expand the breaker and a half scheme to accommodate the new Amos-Welton Spring 765 kV line (Projected ISD 6/1/2029)
- Description
- 765kV Solution: 2024 W1 Solution - Regional Cluster Ties Doubs 500kV area to John Amos 765kV via a new 765kV line
- Cost Information
- Time Estimate
- Jun 01 2029
Not ContingentTopology Changing Note 1: AH1-098 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-098 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 05MOUNTN-05BELMON 765.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 05CLOVRD-05CLOV17_XFL 345.0 kV Ckt 17 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.11
- Type
- Load Flow
- TO
- APS
- RTEP ID / TO ID
- b4000.11
- Title
- Expand Black Oak Substation & Loop in the 502 Jct-Woodside 500 kV line (Projected ISD 6/1/2029)
- Description
- Expand Black Oak Substation to accommodate the connection of the 502 Jct-Woodside 500 kV line and loop the 502 Jct-Woodside 500 kV line into the Black Oak substation by constructing ~0.85 miles of new 500 kV line into and out of Black Oak 500 kV substation
- Cost Information
- Time Estimate
- Jun 01 2029
Not ContingentTopology Changing Note 1: AH1-098 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-098 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 05MOUNTN-05BELMON 765.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 05CLOVRD-05CLOV17_XFL 345.0 kV Ckt 17 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.357
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.357
- Title
- Build a new 765/500/230 kV substation called Yeat. Install (2) 765/500 kV transformers. Cut in 500 kV line Bristers-Ox and 500 kV line Meadowbrook-Vint Hill into Yeat.
- Description
- Build a new 765/500/230 kV substation called Yeat. Install (2) 765/500 kV transformers. Cut in 500 kV line Bristers-Ox and 500 kV line Meadowbrook-Vint Hill into Yeat.
- Cost Information
- Time Estimate
- Jun 01 2029
Not ContingentTopology Changing Note 1: AH1-098 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-098 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 8VALLEY-8VALLEY SC 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8BATH CO-8VALLEY SC 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 05CLOVRD-8LEXNGTN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.356
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.356
- Title
- Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 86.7 miles in Dominion section).
- Description
- Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 86.7 miles in Dominion section).
- Cost Information
- Time Estimate
- Jun 01 2029
Not ContingentTopology Changing Note 1: AH1-098 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-098 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 8VALLEY-8VALLEY SC 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8BATH CO-8VALLEY SC 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 05CLOVRD-8LEXNGTN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.355
- Type
- Load Flow
- TO
- AEP
- RTEP ID / TO ID
- b4000.355
- Title
- Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 69.3 miles in AEP section).
- Description
- Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 69.3 miles in AEP section).
- Cost Information
- Time Estimate
- Jun 01 2029
Not ContingentTopology Changing Note 1: AH1-098 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-098 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 8VALLEY-8VALLEY SC 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8BATH CO-8VALLEY SC 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 05CLOVRD-8LEXNGTN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4053.13
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4053.13
- Title
- Construct a new 765/500 kV Vontay switching station at the crossing of 500 kV line No. 553 Cunningham-Elmont and 765 kV line Joshua Falls-Yeat.
- Description
- Construct a new 765/500 kV Vontay switching station at the crossing of 500 kV line No. 553 Cunningham-Elmont and 765 kV line Joshua Falls-Yeat. Develop two 765 kV line terminal positions and three 500 kV line terminal positions. Install one 765/500 kV transformer, with provisions for a future second transformer.
- Cost Information
- Time Estimate
- Jun 01 2032
Not ContingentTopology Changing Note 1: AH1-098 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-098 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 05CLOVRD-8LEXNGTN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4053.14
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4053.14
- Title
- Loop 500 kV line No. 553 into the new Vontay substation, which will result in two 500 kV lines: Cunningham-Vontay and Vontay-Elmont.
- Description
- Loop 500 kV line No. 553 into the new Vontay substation, which will result in two 500 kV lines: Cunningham-Vontay and Vontay-Elmont.
- Cost Information
- Time Estimate
- Jun 01 2032
Not ContingentTopology Changing Note 1: AH1-098 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-098 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 05CLOVRD-8LEXNGTN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4053.16
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4053.16
- Title
- Loop 765 kV Joshua Falls-Yeat into the new Vontay substation, which will result in two 765 kV lines: from Joshua Falls-Vontay and Vontay-Yeat.
- Description
- Loop 765 kV Joshua Falls-Yeat into the new Vontay substation, which will result in two 765 kV lines: from Joshua Falls-Vontay and Vontay-Yeat.
- Cost Information
- Time Estimate
- Jun 01 2032
Not ContingentTopology Changing Note 1: AH1-098 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-098 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 05CLOVRD-8LEXNGTN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4053.15
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4053.15
- Title
- Loop 500 kV line No. 576 into the new Vontay substation, which will result in two 500 kV lines: from North Anna-Vontay and Vontay-Midlothian.
- Description
- Loop 500 kV line No. 576 into the new Vontay substation, which will result in two 500 kV lines: from North Anna-Vontay and Vontay-Midlothian.
- Cost Information
- Time Estimate
- Jun 01 2032
Not ContingentTopology Changing Note 1: AH1-098 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-098 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 05CLOVRD-8LEXNGTN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4053.28
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4053.28
- Title
- Replace 500 kV circuit breakers (54265 and 553T564) and all associated equipment to line No. 553 including switches and CT with 5000A equipment at Cunningham substation.
- Description
- Replace 500 kV circuit breakers (54265 and 553T564) and all associated equipment to line No. 553 including switches and CT with 5000A equipment at Cunningham substation.
- Cost Information
- Time Estimate
- Jun 01 2032
Not ContingentTopology Changing Note 1: AH1-098 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-098 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 05CLOVRD-8LEXNGTN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.352
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.352
- Title
- Cut in Line #568 Ladysmith - Possum Point into Thornburg (formerly Kraken), creating new Line #568 Thornburg (formerly Kraken) to Possum Point.
- Description
- Cut in Line #568 Ladysmith - Possum Point into Thornburg (formerly Kraken), creating new Line #568 Thornburg (formerly Kraken) to Possum Point.
- Cost Information
- Time Estimate
- Sep 16 2030
Not ContingentTopology Changing Note 1: AH1-098 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-098 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 8VALLEY-8VALLEY SC 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8BATH CO-8VALLEY SC 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 05CLOVRD-8LEXNGTN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.351
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.351
- Title
- Cut in Line #568 Ladysmith - Possum Point into Thornburg (formerly Kraken), creating Line #9517 Ladysmith to Thornburg (formerly Kraken).
- Description
- Cut in Line #568 Ladysmith - Possum Point into Thornburg (formerly Kraken), creating Line #9517 Ladysmith to Thornburg (formerly Kraken).
- Cost Information
- Time Estimate
- Sep 16 2030
Not ContingentTopology Changing Note 1: AH1-098 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-098 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 8VALLEY-8VALLEY SC 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8BATH CO-8VALLEY SC 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 05CLOVRD-8LEXNGTN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.350
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.350
- Title
- Update relay settings at Possum Point to change the destination of 500kV line #568 from Ladysmith to Thornburg (formerly Kraken).
- Description
- Update relay settings at Possum Point to change the destination of 500kV line #568 from Ladysmith to Thornburg (formerly Kraken).
- Cost Information
- Time Estimate
- Sep 16 2030
Not ContingentTopology Changing Note 1: AH1-098 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-098 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 8VALLEY-8VALLEY SC 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8BATH CO-8VALLEY SC 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 05CLOVRD-8LEXNGTN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.349
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.349
- Title
- Update relay settings at Ladysmith to change the destination of 500kV line #568 from Possum Point to Thornburg (formerly Kraken).
- Description
- Update relay settings at Ladysmith to change the destination of 500kV line #568 from Possum Point to Thornburg (formerly Kraken).
- Cost Information
- Time Estimate
- Sep 16 2030
Not ContingentTopology Changing Note 1: AH1-098 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-098 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 8VALLEY-8VALLEY SC 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8BATH CO-8VALLEY SC 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 05CLOVRD-8LEXNGTN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.348
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.348
- Title
- Build a new 500/230kV substation called Thornburg (formerly Kraken). The 500kV, 5000A ring bus will be set up for a redundant breaker configuration. Install (2) 1400MVA 500/230 kV transformers.
- Description
- Build a new 500/230kV substation called Thornburg (formerly Kraken). The 500kV, 5000A ring bus will be set up for a redundant breaker configuration. Install (2) 1400MVA 500/230 kV transformers. A new redundant breaker ring will be added at Thornburg (formerly Kraken) to accommodate the new 500kV line from North Anna to Thornburg (formerly Kraken).
- Cost Information
- Time Estimate
- Jun 01 2029
Not ContingentTopology Changing Note 1: AH1-098 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-098 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 8VALLEY-8VALLEY SC 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8BATH CO-8VALLEY SC 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 05CLOVRD-8LEXNGTN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.346
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.346
- Title
- Cut-in 500kV line from Thornburg (formerly Kraken) substation into Yeat substation
- Description
- Cut-in 500kV line from Thornburg (formerly Kraken) substation into Yeat substation
- Cost Information
- Time Estimate
- Jun 01 2029
Not ContingentTopology Changing Note 1: AH1-098 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-098 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 8VALLEY-8VALLEY SC 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8BATH CO-8VALLEY SC 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 05CLOVRD-8LEXNGTN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.345
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.345
- Title
- Build a 500kV line from a new substation called Thornburg (formerly Kraken) to a new substation called Yeat. New conductor to have a minimum summer normal rating of 4357MVA.
- Description
- Build a 500kV line from a new substation called Thornburg (formerly Kraken) to a new substation called Yeat. New conductor to have a minimum summer normal rating of 4357MVA.
- Cost Information
- Time Estimate
- Sep 16 2030
Not ContingentTopology Changing Note 1: AH1-098 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-098 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 8VALLEY-8VALLEY SC 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8BATH CO-8VALLEY SC 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 05CLOVRD-8LEXNGTN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.344
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.344
- Title
- Build a 500kV line from North Anna substation (bypassing Ladysmith Substation) to a new substation called Thornburg (formerly Kraken). New conductor to have a minimum summer normal rating of 4357MVA.
- Description
- Build a 500kV line from North Anna substation (bypassing Ladysmith Substation) to a new substation called Thornburg (formerly Kraken). New conductor to have a minimum summer normal rating of 4357MVA.
- Cost Information
- Time Estimate
- Sep 16 2030
Not ContingentTopology Changing Note 1: AH1-098 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-098 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 8VALLEY-8VALLEY SC 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8BATH CO-8VALLEY SC 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 05CLOVRD-8LEXNGTN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.342
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.342
- Title
- Remove the terminal equipment and substation work required for the termination of the Morrisville-Wishing Star 500 kV line into Vint Hill.
- Description
- Remove the terminal equipment and substation work required for the termination of the Morrisville-Wishing Star 500 kV line into Vint Hill.
- Cost Information
- Time Estimate
- Jul 13 2029
Not ContingentTopology Changing Note 1: AH1-098 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-098 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 8VALLEY-8VALLEY SC 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8BATH CO-8VALLEY SC 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 05CLOVRD-8LEXNGTN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.341
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.341
- Title
- Remove the 500 kV conductor previously planned to terminate into the Vint Hill 500 kV Substation and extend approximately 0.2 miles of conductor to fly-over the site.
- Description
- Remove the 500 kV conductor previously planned to terminate into the Vint Hill 500 kV substation and extend approximately 0.2 miles of conductor to fly-over the site.
- Cost Information
- Time Estimate
- Jul 13 2029
Not ContingentTopology Changing Note 1: AH1-098 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-098 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 8VALLEY-8VALLEY SC 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8BATH CO-8VALLEY SC 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 05CLOVRD-8LEXNGTN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: n9769.0
- Type
- Load Flow
- TO
- AEP
- RTEP ID / TO ID
- n9769.0 / AEP-TC2-19070
- Title
- 05CLOVRD_RJA 765.0 kV to 05CLOVRD 765.0 kV ckt Z1 - Upgrade/replace CBs
- Description
- Upgrade/replace Cloverdale 765 kV, 4000 A CBs "CC" and "CC2" to 5000 A
- Total Cost ($USD)
- $25,000,000
- Discounted Total Cost ($USD)
- $25,000,000
- Allocated Cost ($USD)
- $0
- Time Estimate
- 48 to 54 Months
Potential Aggregate Contributor Note: Based on PJM cost allocation criteria, AH1-098 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AH1-098 could receive cost allocation. Although AH1-098 may not presently have cost responsibility for this upgrade, AH1-098 is a potential Aggregate Pool Contributor.
| Facility | Contingency | |||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 05CLOVRD-05CLOVRD_RJA 765.0 kV Ckt Z1 line | (Any) |
|
System Reinforcement: b4000.252
- Type
- Load Flow
- TO
- AEP
- RTEP ID / TO ID
- b4000.252
- Title
- Replace the wave trap and upgrade the relay at Joshua Falls 765kV substation
- Description
- Replace the wave trap and upgrade the relay at Joshua Falls 765kV substation
- Cost Information
- Time Estimate
- Jun 01 2029
Not Contingent Note: AH1-098 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-098 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.
| Facility | Contingency | |||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 05JOSHUA-05CLOVRD_RJO 765.0 kV Ckt 1 line | (Any) |
|
System Reinforcement: b4000.251
- Type
- Load Flow
- TO
- AEP
- RTEP ID / TO ID
- b4000.251
- Title
- Replace the wave trap and upgrade the relay at Cloverdale 765kV substation
- Description
- Replace the wave trap and upgrade the relay at Cloverdale 765kV substation
- Cost Information
- Time Estimate
- Jun 01 2029
Not Contingent Note: AH1-098 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-098 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.
| Facility | Contingency | |||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 05JOSHUA-05CLOVRD_RJO 765.0 kV Ckt 1 line | (Any) |
|
System Reinforcement: n9763.0
- Type
- Load Flow
- TO
- AEP
- RTEP ID / TO ID
- n9763.0 / AEP-TC2-19060
- Title
- 05J.FERR 765.0 kV to 05CLOVRD_RJA 765.0 kV ckt 1 - Replace Wavetraps
- Description
- Replace wave trap on 765 kV Cloverdale line. Replace/upgrade CB's B and B2 with 5000A CBs.
- Total Cost ($USD)
- $3,300,000
- Discounted Total Cost ($USD)
- $3,300,000
- Allocated Cost ($USD)
- $0
- Time Estimate
- 48 to 54 Months
Potential Aggregate Contributor Note: Based on PJM cost allocation criteria, AH1-098 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AH1-098 could receive cost allocation. Although AH1-098 may not presently have cost responsibility for this upgrade, AH1-098 is a potential Aggregate Pool Contributor.
| Facility | Contingency | |||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 05J.FERR-05CLOVRD_RJA 765.0 kV Ckt 1 line | (Any) |
|
System Reinforcement: b4053.3
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4053.3
- Title
- Construct a new bipolar +/- 525 kV HVDC link connecting Heritage and Mosby substations, where the link has a capability of transmitting 3,000 MW.
- Description
- Construct a new bipolar +/- 525 kV HVDC link connecting Heritage and Mosby substations, where the link has a capability of transmitting 3,000 MW. The HVDC link, approximately 185 miles in length, will be fully routed underground between the two new proposed converter stations, one at Heritage and one at Mosby.
- Cost Information
- Time Estimate
- Jun 01 2032
Not ContingentTopology Changing Note 1: AH1-098 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-098 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 8VALLEY-8VALLEY SC 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8BATH CO-8VALLEY SC 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 05CLOVRD-8LEXNGTN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4053.4
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4053.4
- Title
- Design and construct a new Voltage Source Converter (VSC) HVDC station at Heritage substation to support the new HVDC link.
- Description
- Design and construct a new Voltage Source Converter (VSC) HVDC station at Heritage substation to support the new HVDC link.
- Cost Information
- Time Estimate
- Jun 01 2032
Not ContingentTopology Changing Note 1: AH1-098 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-098 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 8VALLEY-8VALLEY SC 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8BATH CO-8VALLEY SC 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 05CLOVRD-8LEXNGTN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4053.5
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4053.5
- Title
- Design and construct a new Voltage Source Converter (VSC) HVDC station at Mosby substation to support the new HVDC link.
- Description
- Design and construct a new Voltage Source Converter (VSC) HVDC station at Mosby substation to support the new HVDC link.
- Cost Information
- Time Estimate
- Jun 01 2032
Not ContingentTopology Changing Note 1: AH1-098 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-098 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 8VALLEY-8VALLEY SC 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8BATH CO-8VALLEY SC 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 05CLOVRD-8LEXNGTN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4053.12
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4053.12
- Title
- Install two 500 kV breakers and all associated terminal equipment in the available bay adjacent to existing breaker XT590 to achieve a redundant breaker arrangement.
- Description
- Install two 500 kV breakers and all associated terminal equipment in the available bay adjacent to existing breaker XT590 to achieve a redundant breaker arrangement. Upgrade existing terminal equipment to 500 kV, 5000A 63 kAIC standards including breaker (XT590), disconnect switches (59078, X74), leads and bus work.
- Cost Information
- Time Estimate
- Jun 01 2030
Not ContingentTopology Changing Note 1: AH1-098 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-098 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 8VALLEY-8VALLEY SC 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8BATH CO-8VALLEY SC 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 05CLOVRD-8LEXNGTN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4053.11
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4053.11
- Title
- Cut and loop line No. 5008 into Mosby substation, which will result in two 500 kV lines: line No. 5008 Morrisville-Mosby and line No. 9573 Mosby-Wishing Star.
- Description
- Cut and loop line No. 5008 into Mosby substation, which will result in two 500 kV lines: line No. 5008 Morrisville-Mosby and line No. 9573 Mosby-Wishing Star.
- Cost Information
- Time Estimate
- Jun 01 2030
Not ContingentTopology Changing Note 1: AH1-098 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-098 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 8VALLEY-8VALLEY SC 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8BATH CO-8VALLEY SC 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 05CLOVRD-8LEXNGTN 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |