AH1-165 Phase II System Impact Study Report

v1.00 released 2026-06-03 17:45

Will County 138 kV

0.0 MW Capacity / 72.0 MW Energy

Introduction

This Phase II System Impact Study (SIS) Report has been prepared in accordance with the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 310 for New Service Requests (projects) in Transition Cycle 2 (TC2). The Project Developer/Eligible Customer (developer) is NRG Midwest Storage LLC, and the Transmission Provider (TP) is PJM Interconnection, LLC (PJM). The interconnected Transmission Owner (TO) is Commonwealth Edison Company.

Preface

The Phase II System Impact Study is conducted on an aggregate basis within a New Services Request’s Cycle, and results are provided in both (i) a single Cycle summary format and (ii) an individual project-level basis. The Phase II System Impact Study Results (for both the summary and individual reports) will be publicly available on PJM’s website. Project Developers must obtain the results from the website.

In accordance with PJM Manual 14H, section 4.5, PJM takes the following actions during the Phase II System Impact Study:

  1. PJM will retool load flow results from the Phase I System Impact Study (summer peak, winter peak and light load) based on decisions made by Project Developers or Eligible Customers during Decision Point I.
  2. PJM will conduct any required voltage analyses.
  3. PJM will perform short circuit and stability analyses as required.
  4. PJM will coordinate with the Affected System to confirm which projects in the PJM Cycle will require Affected System studies. If the Affected System Operator indicates that an Affected System study is required, PJM will:
    1. Notify the Project Developer or Eligible Customer of the need for an Affected System study and the requirement to execute an Affected System study agreement with the impacted Affected System Operator, and;
    2. Include the results of the Affected System Operator’s Affected System Study in the Phase II System Impact Study results, if applicable and available.
  5. The Phase II System Impact Study Results will be publicly available on PJM’s website. Project Developers and Eligible Customers must obtain the results from the website.

The Transmission Owner takes the following actions during the Phase II System Impact Study:

  1. Verify Interconnection Facilities and Network Upgrades required to accommodate the New Service Request.
  2. Perform a Facilities Study. The Facilities Study in Phase II System Impact Study phase will be for the physical Interconnection Facilities. The Facilities Study requirements are outlined in Attachment C of this manual. The study will be conducted pursuant to Tariff, Part VII, Subpart D, section 307(A)(7) and Tariff, Part VIII, Subpart C, section 404(A)(7).

Decision Point II Requirements

At the close of Phase II System Impact Study, PJM will initiate Decision Point II (DP2). During DP2, the Project Developer will have 30 days to decide whether to proceed with their project. If the Project Developer elects to proceed, they should provide the elements defined in the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 311.A. Additional information on these elements is available in PJM Manual 14H sections 4.6, 6, and 7.

Allowable project modifications at Decision Point II are defined in PJM Open Access Transmission Tariff, Part VII, Subpart D, section 311.B. Additional information regarding allowable project modifications can be found in PJM Manual 14H, section 9.8.

Adverse Test Eligibility

This New Service Request does not meet the Adverse Study Impact Criteria and has the option to either move forward in the Cycle process or withdraw at DP2 with Readiness Deposit #1 forfeited. See adverse study impact calculation below.

This section details whether a Project Developer or Eligible Customer qualifies for the Adverse Study Impact clause outlined in the PJM OATT, Part VII, Subpart D, section 311.B and Manual 14H, section 6.2.2. In order to qualify for an Adverse Study Impact at Decision Point II, the Network Upgrade cost from Phase I to Phase II must:

  1. Increase overall by 25% or more
  2. Increases by more than $10,000 per MW (Includes Costs identified in Affected System studies)

If a New Service Request meets the criteria above and chooses to withdraw the request, PJM will refund the cumulative Readiness Deposit amounts paid at the Application Phase and at Decision Point I (RD1 and RD2, respectively).

The below calculations show the computation of this New Service Request's Adverse Study Impact

DP2 Adverse Eligibility = DP2 Adverse Cost Alloc DP1 Adverse Cost Alloc > 1.25 AND ( DP2 Adverse Cost Alloc - DP1 Adverse Cost Alloc ) Project Size > $10,000 per MW
DP2 Adverse Eligibility = $21,732 $2,400,000 = 0.01 AND ( $21,732 - $2,400,000 ) 72.0 = $-33,031 per MW

General

The Project Developer has proposed a Storage facility located in the Commonwealth Edison Company zone — Will County, Illinois. The installed facilities will have a total capability of 72.0 MW with 0.0 MW of this output being recognized by PJM as Capacity.

Project Information
New Service Request Number:
AH1-165
Project Name:
Will County 138 kV
Project Developer Name:
NRG Midwest Storage LLC
State:
Illinois
County:
Will
Transmission Owner:
Commonwealth Edison Company
MFO:
72.0
MWE:
72.0
MWC:
0.0
Battery Storage Specification:
72.0 MWh, 1.0-hr class
Grid Charging:
Yes
Fuel Type:
Storage
Basecase Study Year:
2028

Physical Interconnection Facility Study

Report Available

The transmission owner has completed the Physical Interconnection Facilities Study. This report is available for download.

Point of Interconnection

AH1-165 will interconnect on the Commonwealth Edison Company transmission system at the Will County 138 kV Substation.

Cost Summary

The table below shows a summary of the total cost estimates for this New Service Request project. In Phase II SIS, the interconnected Transmission Owner has performed a facilities study for both the Transmission Owner Interconnection Facilities (TOIF) and Physical Interconnection Network Upgrades. The System Reliability Network Upgrade shown in the table are planning level cost estimates which are subject to change as a result of a facility study performed by the TO during Phase III System Impact Study.

Based on the Phase II SIS results, the AH1-165 project has the following allocation of costs for interconnection. The cost contribution towards Readiness Deposit #3 are also shown below.

Cost Summary
DescriptionCost Allocated to AH1-165Cost Subject to Readiness*Cost Subject to Adverse
Transmission Owner Interconnection Facilities (TOIF)$4,880,185$0$0
Other Scope$439,942$0$0
Option To Build Oversight$0$0$0
Physical Interconnection Network Upgrades
Stand Alone Network Upgrades$0$0$0
Network Upgrades$0$0$0
System Reliability Network Upgrades
Steady State Thermal & Voltage$0$0$0
Transient Stability$0$0$0
Short Circuit$0$0$0
Transmission Owner Analysis
SubRegional$0$0$0
Distribution$0$0$0
Affected System Reinforcements
AFS - PJM Violations$0$0$0
AFS - Non-PJM Violations$21,732$0$21,732
Total$5,341,859$0$21,732

* Contributes to calculation for Readiness Deposit #3 (RD3). See Readiness Deposit section of report for additional detail.

Definitions

Transmission Owner Interconnection Facilities: Facilities that are owned, controlled, operated and maintained by the Transmission Owner on the Transmission Owner’s side of the Point of Change of Ownership to the Point of Interconnection, including any modifications, additions or upgrades made to such facilities and equipment, that are necessary to physically and electrically interconnect the Generating Facility with the Transmission System or interconnected distribution facilities.

Stand Alone Network Upgrades: Network Upgrades, which are not part of an Affected System, which a Project Developer may construct without affecting day-to-day operations (e.g. taking a transmission outage) of the Transmission System during their construction.

Network Upgrades: Modifications or additions to transmission-related facilities that are integrated with and support the Transmission Provider’s overall Transmission System for the general benefit of all users of such Transmission System. Network Upgrades have no impact or potential impact on the Transmission System until the final tie-in is complete.

Notes

Note 1: PJM Open Access Transmission Tariff (OATT), Part VII, Subpart D, section 307.5 outlines cost allocation rules. The rules are further clarified in PJM Manual 14H, section 4.2.6. PJM shall identify the New Service Requests in the Cycle contributing to the need for the required Network Upgrades within the Cycle. All New Service Requests that contribute to the need for a Network Upgrade will receive cost allocation for that upgrade pursuant to each New Service Request’s contribution to the reliability violation identified on the transmission system in accordance with PJM Manuals.

Note 2: There will be no inter-Cycle cost allocation for Interconnection Facilities or Network Upgrades identified in the System Impact Study costs identified in a Cycle; all such costs shall be allocated to New Service Requests in that Cycle.

Note 3: For Project Developers with System Reinforcements listed: If this project presents cost allocation to a System Reinforcement indicates $0, then please be aware that as changes to the interconnection process occur, such as other projects withdrawing, reducing in size, etc, the cost responsibilities can change and a cost allocation may be assigned to this project. In addition, although this project presents cost allocation to a System Reinforcement is presently $0, this project may need this system reinforcement completed to be deliverable to the PJM system. If this project desires to come into service prior to completion of the system reinforcement, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the system reinforcement is complete.

Note 4: Please see the ‘Affected Systems Studies’ section of this Phase II SIS report for details on your project’s need for an Affected Systems Study. If your project requires an Affected Systems Study, the Affected Systems impacts may not be available from the Affected System Operator at the time of the PJM Phase II SIS. Therefore, the cost in this section would not reflect any required upgrades by the Affected System until the study is completed. If your project requires an Affected Systems Study and your results are not provided for Phase II SIS, PJM anticipates providing them in the Phase III SIS per Tariff Part VII.D.312.

Readiness Deposit

Per Tariff Part VII, Subpart D, section 311 (Decision Point II) A.1.b and PJM Manual 14H, section 6.2, Readiness Deposit #3 (RD3) are funds committed by the Project Developer or Eligible Customer based upon the applicable contribution to Network Upgrades as defined below. Readiness Deposits are not used to fund studies nor to offset Security.

During Decision Point II (DP2), the Project Developer or Eligible Customer is required to submit Readiness Deposit #3, which is calculated as 20% of cost allocation for required Phase II Network Upgrades minus Readiness Deposit #1 & Readiness Deposit #2.

Note 1: “Network Upgrades” referred to in the calculation include both (i) the Physical Interconnection Network Upgrades and (ii) the System Reliability Network Upgrades as shown in the Cost Summary table.

Note 2: Readiness Deposit #1 (RD1) = ($4,000 * Project Size (MW))

Note 3: Readiness Deposit #2 (RD2) = 10% of cost allocation for required Network Upgrades minus RD1. Readiness Deposit #2 (RD2) can be zero, but may not be a negative number.

Note 4: Readiness Deposit #3 can be zero, but may not be a negative number.

Readiness Deposit #3 Due for Project AH1-165

Readiness Deposit #3 has been calculated for the project based on the Phase II System Impact Study results and is shown in the table below. This Readiness Deposit #3 must be provided at Decision Point II through either a wire transfer or letter of credit per Manual 14H, Section 6.2.

Readiness Deposit #3 Due for AH1-165
Project ID: AH1-165
20% of cost allocation for Phase II Network Upgrades:(A) $0
Sum of Readiness Deposit #1 & Readiness Deposit #2 Received:(B) $288,000
Readiness Deposit #3 (RD3) due at DP2:(A) - (B) = $0
Note: Failure to provide an acceptable form of Readiness Deposit #3 by the end of Decision Point II will result in withdrawal and termination of the New Service Request.

For additional detail regarding Readiness Deposit Refunds, reference PJM Manual 14H, section 6.2.1. The Readiness Deposit Letter of Credit template can be found here.

Transmission Owner Scope of Work

If your project relies on Transmission Owner Interconnection Facilities, Stand Alone Network Upgrades, and/or Network Upgrades that will be constructed by another New Service Request and the other New Service Request withdraws, the scope and costs will be allocated to your project.

The total preliminary cost estimate for the Transmission Owner scope of work (including TOIF and Physical Interconnection Network Upgrades) is given in the table below. These costs do not include CIAC Tax Gross-up.

Transmission Owner Build Option
Other
RTEP IDDescriptionDirectIndirectTotal Cost ($USD)Allocated Cost ($USD)
LaborMaterialsLaborMaterials
(Pending)

Install new AMI and revenue meter at STA 18 Meter

$89,927$311,825$19,676$18,514$439,942$439,942
Transmission Owner Interconnection Facilities
RTEP IDDescriptionDirectIndirectTotal Cost ($USD)Allocated Cost ($USD)
LaborMaterialsLaborMaterials
(Pending)

Upgrade STA18 138kV Substation to support interconnecting the project. Install one 138 kV dead-end structure and line conductor from the dead-end structure to the bus position in the switchyard of the interconnection substation.

$2,646,396$1,562,019$579,030$92,740$4,880,185$4,880,185
Developer Build Option

(No Developer Build Option for this project.)

Build Option Price Comparison
Build OptionTotal CostAllocated Cost
Transmission Owner Build Option$5,320,127$5,320,127
Developer Build Option(No Developer Build Option)

Based on the scope of work for the Interconnection Facilities, it is expected to take a range of 1 to 36 month(s) after the signing of a Generator Interconnection Agreement (as this is a FERC connection) and construction kickoff call to complete the installation of the physical connection work. This assumes that there will be no environmental issues with any of the new properties associated with this project, that there will be no delays in acquiring the necessary permits for implementing the defined interconnection work, and that all system outages will be allowed when requested.

Note that the TO findings were made from a conceptual review of this project. A more detailed review of the connection facilities and their cost will be identified in a future study phase. Further note that the cost estimate data provided should be considered high level estimates since it was produced without a detailed engineering review. The Project Developer will be responsible for the actual cost of construction. TO herein reserves the right to return to any issues in this document and, upon appropriate justification, request additional monies to complete any reinforcements to the transmission systems.

Remote Terminal Work: During Phase II of the PJM interconnection process, TO’s System Protection Engineering Department will review transmission line protection as well as anti-islanding required to accommodate the new generation and interconnection substation. System Protection Engineering will determine the minimal acceptable protection requirements to reliably interconnect the proposed generating facility with the transmission system. The review is based on maintaining system reliability by reviewing TO’s protection requirements with the known transmission system configuration which includes generating facilities in the area. This review may determine that transmission line protection and communication upgrades are required at remote substations.

Notes on Cost Estimate:

  1. These estimates are order-of-magnitude estimates of the costs that ComEd would bill to the Project Developer for this interconnection. These estimates are based on a one-line electrical diagram of the project and the information provided by the Project Developer.
  2. There were no site visits performed for these estimates. There may be costs related to specific site related issues that are not identified in these estimates. The site reviews will be performed during the Facilities Study or during detailed engineering.
  3. These estimates are not a guarantee of the maximum amount payable by the Project Developer and the actual costs of ComEd's work may differ significantly from these estimates. The Project Developer will be responsible for paying actual costs of ComEd's work in accordance with the PJM Open Access Transmission Tariff.
  4. The Project Developer is responsible for all engineering, procurement, testing and construction of all equipment on the Project Developer’s side of the Point of Change in Ownership.

 

 

Transmission Owner Analysis

No Transmission Owner impacts identified.

Developer Requirements

The developer is responsible for all design and construction related activities on the developer’s side of the Point of Change in Ownership. ComEd interconnection requirements can be found here.

To the extent that these Applicable Technical Requirements and Standards may conflict with the terms and conditions of the Tariff, the Tariff shall control.

Revenue Metering and SCADA Requirements

PJM Requirements
The developer will be required to install equipment necessary to provide Revenue Metering (KWH, KVARH) and real time data (KW, KVAR) for their generating Resource. See PJM Manual 01, PJM Manual 14D, and PJM Tariff Part IX, Subpart B, Appendix 2, section 8.
Transmission Owner Requirements
The Project Developer will be required to comply with all interconnected Transmission Owner’s revenue metering requirements located at the following link: PJM - Transmission Owner Engineering & Construction Standards.

Summer Peak Analysis

The New Service Request AH1-165 was evaluated as a 72.0 MW (0.0 MW Capacity) injection in the ComEd area.

AH1-165 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 72.0 MW (72.0 MW under study).

Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.

The following flowgates remain after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)

Winter Peak Analysis

The New Service Request AH1-165 was evaluated as a 72.0 MW (0.0 MW Capacity) injection in the ComEd area.

AH1-165 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 72.0 MW (72.0 MW under study).

Note: The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for single or N-1 contingencies and multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.

The following flowgates remain after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)

Light Load Analysis

The New Service Request AH1-165 was evaluated as a 72.0 MW injection and 72.0 MW withdrawal in the ComEd area.

AH1-165 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 72.0 MW (72.0 MW under study).

Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.

The following flowgates remain after considering the topology reinforcements required by the cycle.

StudyAreaFacility DescriptionContingency NameContingency TypeDC|ACFinal Cycle LoadingRating (MVA)Rating TypeMVA to MitigateMW ContributionDetails
GD2AEP
AF2-359 TP-05OLIVE 345.0 kV Ckt 1 line
AEP_P1-2_#695_1681_SRT-A
SingleAC113.5 %972.0B1103.25
7.35
GD2AEP
AF2-359 TP-05OLIVE 345.0 kV Ckt 1 line
COMED_P4_112-65-BT4-5___SRT-A
BreakerAC113.4 %972.0B1102.24
7.35
GD2AEP
AF2-359 TP-05OLIVE 345.0 kV Ckt 1 line
COMED_P4_112-65-BT3-4___SRT-A
BreakerAC113.4 %972.0B1102.24
7.35
GD2AEP
AF2-359 TP-05OLIVE 345.0 kV Ckt 1 line
765-L11215__-S_SRT-A
SingleAC113.4 %972.0B1102.23
7.35
GD2CE/NIPS
CRETE EC ;BP-17STJOHN 345.0 kV Ckt 1 line
AEP_P1-2_#695_1681_SRT-A
SingleAC110.24 %1508.0B1662.46
10.58
GD2CE/NIPS
CRETE EC ;BP-17STJOHN 345.0 kV Ckt 1 line
COMED_P4_112-65-BT4-5___SRT-A
BreakerAC110.21 %1508.0B1661.95
10.58
GD2CE/NIPS
CRETE EC ;BP-17STJOHN 345.0 kV Ckt 1 line
COMED_P4_112-65-BT3-4___SRT-A
BreakerAC110.21 %1508.0B1661.91
10.58
GD2CE/NIPS
CRETE EC ;BP-17STJOHN 345.0 kV Ckt 1 line
765-L11215__-S_SRT-A
SingleAC110.16 %1508.0B1661.16
10.58

Details for AF2-359 TP-05OLIVE 345.0 kV Ckt 1 line l/o AEP_P1-2_#695_1681_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:AEP
Facility Description:
AF2-359 TP-05OLIVE 345.0 kV Ckt 1 line
Contingency Name:
AEP_P1-2_#695_1681_SRT-A
Contingency Type:Single
DC|AC:AC
Final Cycle Loading:113.5 %
Rating:972.0 MVA
Rating Type:B
MVA to Mitigate:1103.25
MW Contribution:
7.35
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area:AEP
Facility Description:
AF2-359 TP-05OLIVE 345.0 kV Ckt 1 line
Contingency Name:
AEP_P1-2_#695_1681_SRT-A
Contingency Type:Single
DC|AC:AC
Final Cycle Loading:109.01 %
Rating:972.0 MVA
Rating Type:B
MVA to Mitigate:1059.61
MW Contribution:
7.14
Bus #Bus NameTypeMW Contribution
274676JOLIET 29;8U
50/50
28.197
274676JOLIET 29;8U
50/50
16.255
274687WILL CNTY;4U
50/50
26.029
274687WILL CNTY;4U
50/50
26.029
274861TOP CROP ;1U
Solar/Wind Harmer
6.499
274862TOP CROP ;2U
Solar/Wind Harmer
6.499
274888KELLY CRK;1U
Solar/Wind Harmer
7.356
276806AD2-047 C O1
Solar/Wind Harmer
13.686
270536AF1-215 GEN2
Solar/Wind Helper
2.044
270535AF1-215 GEN1
Solar/Wind Helper
2.044
270055AF2-134 C O1
Solar/Wind Helper
1.362
274887GEN-1.85
Solar/Wind Harmer
6.642
959351AF2-226 GEN
50/50
5.038
960281AF2-319 GEN
50/50
5.038
960591AF2-350 GEN
Solar/Wind Harmer
5.377
960681AF2-359 GEN
Solar/Wind Harmer
0
970707AG2-453 GEN
Solar/Wind Harmer
15.132
970941AG2-585 GEN
Solar/Wind Harmer
2.957
971369AH1-165 GEN
50/50
7.349
972181SS23-001
Solar/Wind Harmer
11.028
972207SS24-0001
Solar/Wind Harmer
11.552
972231SS25-0005
Solar/Wind Harmer
17.645
276843GEN-1.7
Solar/Wind Harmer
0.715
958011AF2-095 GEN
Solar/Wind Harmer
7.743
965681AG1-436 GEN
Solar/Wind Harmer
57.024
965791AG1-447 GEN
Solar/Wind Harmer
45.619
CBM West 1LTFEXP_CBM-W1->PJM
CBM
42.124
CBM West 2LTFEXP_CBM-W2->PJM
CBM
16.961
CBM South 1LTFEXP_CBM-S1->PJM
CBM
0.742
NYPJM->LTFIMP_NY
CLTF
0.949
GibsonPJM->LTFIMP_GIBSON
CLTF
0
WECLTFEXP_WEC->PJM
CLTF
2.883
HAMLETPJM->LTFIMP_HAMLET
CLTF
0.53
CATAWBAPJM->LTFIMP_CATAWBA
CLTF
0.288
TVALTFEXP_TVA->PJM
CLTF
0.405
TRIMBLEPJM->LTFIMP_TRIMBLE
CLTF
0.551
CALDErWOODPJM->LTFIMP_CALDERWOOD
CLTF
0
MECLTFEXP_MEC->PJM
CLTF
8.7
CHEOAHPJM->LTFIMP_CHEOAH
CLTF
0
BlueGrassPJM->LTFIMP_BlueG
CLTF
1.619
LAGNLTFEXP_LAGN->PJM
CLTF
2.379
MISO WINDMISO-WIND_EXP->MISO-WIND_IMP
CLTF
336.386

Details for AF2-359 TP-05OLIVE 345.0 kV Ckt 1 line l/o COMED_P4_112-65-BT4-5___SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:AEP
Facility Description:
AF2-359 TP-05OLIVE 345.0 kV Ckt 1 line
Contingency Name:
COMED_P4_112-65-BT4-5___SRT-A
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:113.4 %
Rating:972.0 MVA
Rating Type:B
MVA to Mitigate:1102.24
MW Contribution:
7.35
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area:AEP
Facility Description:
AF2-359 TP-05OLIVE 345.0 kV Ckt 1 line
Contingency Name:
COMED_P4_112-65-BT4-5___SRT-A
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:96.54 %
Rating:972.0 MVA
Rating Type:B
MVA to Mitigate:938.41
MW Contribution:
No Reportable Contribution
Bus #Bus NameTypeMW Contribution
274676JOLIET 29;8U
50/50
28.196
274676JOLIET 29;8U
50/50
16.255
274687WILL CNTY;4U
50/50
26.028
274687WILL CNTY;4U
50/50
26.028
274861TOP CROP ;1U
Solar/Wind Harmer
6.499
274862TOP CROP ;2U
Solar/Wind Harmer
6.499
274888KELLY CRK;1U
Solar/Wind Harmer
7.357
276806AD2-047 C O1
Solar/Wind Harmer
13.687
270536AF1-215 GEN2
Solar/Wind Helper
2.044
270535AF1-215 GEN1
Solar/Wind Helper
2.044
270055AF2-134 C O1
Solar/Wind Helper
1.362
274887GEN-1.85
Solar/Wind Harmer
6.642
959351AF2-226 GEN
50/50
5.038
960281AF2-319 GEN
50/50
5.038
960591AF2-350 GEN
Solar/Wind Harmer
5.377
960681AF2-359 GEN
Solar/Wind Harmer
0
970707AG2-453 GEN
Solar/Wind Harmer
15.129
970941AG2-585 GEN
Solar/Wind Harmer
2.957
971369AH1-165 GEN
50/50
7.349
972181SS23-001
Solar/Wind Harmer
11.028
972207SS24-0001
Solar/Wind Harmer
11.556
972231SS25-0005
Solar/Wind Harmer
17.645
276843GEN-1.7
Solar/Wind Harmer
0.715
958011AF2-095 GEN
Solar/Wind Harmer
7.743
965681AG1-436 GEN
Solar/Wind Harmer
57.024
965791AG1-447 GEN
Solar/Wind Harmer
45.619
CBM West 1LTFEXP_CBM-W1->PJM
CBM
42.12
CBM West 2LTFEXP_CBM-W2->PJM
CBM
16.96
CBM South 1LTFEXP_CBM-S1->PJM
CBM
0.742
NYPJM->LTFIMP_NY
CLTF
0.949
GibsonPJM->LTFIMP_GIBSON
CLTF
0
WECLTFEXP_WEC->PJM
CLTF
2.883
HAMLETPJM->LTFIMP_HAMLET
CLTF
0.53
CATAWBAPJM->LTFIMP_CATAWBA
CLTF
0.288
TVALTFEXP_TVA->PJM
CLTF
0.405
TRIMBLEPJM->LTFIMP_TRIMBLE
CLTF
0.551
CALDErWOODPJM->LTFIMP_CALDERWOOD
CLTF
0
MECLTFEXP_MEC->PJM
CLTF
8.7
CHEOAHPJM->LTFIMP_CHEOAH
CLTF
0
BlueGrassPJM->LTFIMP_BlueG
CLTF
1.619
LAGNLTFEXP_LAGN->PJM
CLTF
2.379
MISO WINDMISO-WIND_EXP->MISO-WIND_IMP
CLTF
336.359

Details for AF2-359 TP-05OLIVE 345.0 kV Ckt 1 line l/o COMED_P4_112-65-BT3-4___SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:AEP
Facility Description:
AF2-359 TP-05OLIVE 345.0 kV Ckt 1 line
Contingency Name:
COMED_P4_112-65-BT3-4___SRT-A
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:113.4 %
Rating:972.0 MVA
Rating Type:B
MVA to Mitigate:1102.24
MW Contribution:
7.35
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area:AEP
Facility Description:
AF2-359 TP-05OLIVE 345.0 kV Ckt 1 line
Contingency Name:
COMED_P4_112-65-BT3-4___SRT-A
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:96.54 %
Rating:972.0 MVA
Rating Type:B
MVA to Mitigate:938.41
MW Contribution:
No Reportable Contribution
Bus #Bus NameTypeMW Contribution
274676JOLIET 29;8U
50/50
28.196
274676JOLIET 29;8U
50/50
16.255
274687WILL CNTY;4U
50/50
26.028
274687WILL CNTY;4U
50/50
26.028
274861TOP CROP ;1U
Solar/Wind Harmer
6.499
274862TOP CROP ;2U
Solar/Wind Harmer
6.499
274888KELLY CRK;1U
Solar/Wind Harmer
7.357
276806AD2-047 C O1
Solar/Wind Harmer
13.687
270536AF1-215 GEN2
Solar/Wind Helper
2.044
270535AF1-215 GEN1
Solar/Wind Helper
2.044
270055AF2-134 C O1
Solar/Wind Helper
1.362
274887GEN-1.85
Solar/Wind Harmer
6.642
959351AF2-226 GEN
50/50
5.038
960281AF2-319 GEN
50/50
5.038
960591AF2-350 GEN
Solar/Wind Harmer
5.377
960681AF2-359 GEN
Solar/Wind Harmer
0
970707AG2-453 GEN
Solar/Wind Harmer
15.129
970941AG2-585 GEN
Solar/Wind Harmer
2.957
971369AH1-165 GEN
50/50
7.349
972181SS23-001
Solar/Wind Harmer
11.028
972207SS24-0001
Solar/Wind Harmer
11.556
972231SS25-0005
Solar/Wind Harmer
17.645
276843GEN-1.7
Solar/Wind Harmer
0.715
958011AF2-095 GEN
Solar/Wind Harmer
7.743
965681AG1-436 GEN
Solar/Wind Harmer
57.024
965791AG1-447 GEN
Solar/Wind Harmer
45.619
CBM West 1LTFEXP_CBM-W1->PJM
CBM
42.12
CBM West 2LTFEXP_CBM-W2->PJM
CBM
16.96
CBM South 1LTFEXP_CBM-S1->PJM
CBM
0.742
NYPJM->LTFIMP_NY
CLTF
0.949
GibsonPJM->LTFIMP_GIBSON
CLTF
0
WECLTFEXP_WEC->PJM
CLTF
2.883
HAMLETPJM->LTFIMP_HAMLET
CLTF
0.53
CATAWBAPJM->LTFIMP_CATAWBA
CLTF
0.288
TVALTFEXP_TVA->PJM
CLTF
0.405
TRIMBLEPJM->LTFIMP_TRIMBLE
CLTF
0.551
CALDErWOODPJM->LTFIMP_CALDERWOOD
CLTF
0
MECLTFEXP_MEC->PJM
CLTF
8.7
CHEOAHPJM->LTFIMP_CHEOAH
CLTF
0
BlueGrassPJM->LTFIMP_BlueG
CLTF
1.619
LAGNLTFEXP_LAGN->PJM
CLTF
2.379
MISO WINDMISO-WIND_EXP->MISO-WIND_IMP
CLTF
336.357

Details for AF2-359 TP-05OLIVE 345.0 kV Ckt 1 line l/o 765-L11215__-S_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:AEP
Facility Description:
AF2-359 TP-05OLIVE 345.0 kV Ckt 1 line
Contingency Name:
765-L11215__-S_SRT-A
Contingency Type:Single
DC|AC:AC
Final Cycle Loading:113.4 %
Rating:972.0 MVA
Rating Type:B
MVA to Mitigate:1102.23
MW Contribution:
7.35
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area:AEP
Facility Description:
AF2-359 TP-05OLIVE 345.0 kV Ckt 1 line
Contingency Name:
765-L11215__-S_SRT-A
Contingency Type:Single
DC|AC:AC
Final Cycle Loading:108.93 %
Rating:972.0 MVA
Rating Type:B
MVA to Mitigate:1058.78
MW Contribution:
7.14
Bus #Bus NameTypeMW Contribution
274676JOLIET 29;8U
50/50
28.197
274676JOLIET 29;8U
50/50
16.255
274687WILL CNTY;4U
50/50
26.029
274687WILL CNTY;4U
50/50
26.029
274861TOP CROP ;1U
Solar/Wind Harmer
6.499
274862TOP CROP ;2U
Solar/Wind Harmer
6.499
274888KELLY CRK;1U
Solar/Wind Harmer
7.356
276806AD2-047 C O1
Solar/Wind Harmer
13.686
270536AF1-215 GEN2
Solar/Wind Helper
2.044
270535AF1-215 GEN1
Solar/Wind Helper
2.044
270055AF2-134 C O1
Solar/Wind Helper
1.362
274887GEN-1.85
Solar/Wind Harmer
6.642
959351AF2-226 GEN
50/50
5.038
960281AF2-319 GEN
50/50
5.038
960591AF2-350 GEN
Solar/Wind Harmer
5.377
960681AF2-359 GEN
Solar/Wind Harmer
0
970707AG2-453 GEN
Solar/Wind Harmer
15.132
970941AG2-585 GEN
Solar/Wind Harmer
2.957
971369AH1-165 GEN
50/50
7.349
972181SS23-001
Solar/Wind Harmer
11.028
972207SS24-0001
Solar/Wind Harmer
11.552
972231SS25-0005
Solar/Wind Harmer
17.645
276843GEN-1.7
Solar/Wind Harmer
0.715
958011AF2-095 GEN
Solar/Wind Harmer
7.743
965681AG1-436 GEN
Solar/Wind Harmer
57.024
965791AG1-447 GEN
Solar/Wind Harmer
45.619
CBM West 1LTFEXP_CBM-W1->PJM
CBM
42.124
CBM West 2LTFEXP_CBM-W2->PJM
CBM
16.961
CBM South 1LTFEXP_CBM-S1->PJM
CBM
0.742
NYPJM->LTFIMP_NY
CLTF
0.949
GibsonPJM->LTFIMP_GIBSON
CLTF
0
WECLTFEXP_WEC->PJM
CLTF
2.883
HAMLETPJM->LTFIMP_HAMLET
CLTF
0.53
CATAWBAPJM->LTFIMP_CATAWBA
CLTF
0.288
TVALTFEXP_TVA->PJM
CLTF
0.405
TRIMBLEPJM->LTFIMP_TRIMBLE
CLTF
0.551
CALDErWOODPJM->LTFIMP_CALDERWOOD
CLTF
0
MECLTFEXP_MEC->PJM
CLTF
8.7
CHEOAHPJM->LTFIMP_CHEOAH
CLTF
0
BlueGrassPJM->LTFIMP_BlueG
CLTF
1.619
LAGNLTFEXP_LAGN->PJM
CLTF
2.379
MISO WINDMISO-WIND_EXP->MISO-WIND_IMP
CLTF
336.386

Details for CRETE EC ;BP-17STJOHN 345.0 kV Ckt 1 line l/o AEP_P1-2_#695_1681_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:CE/NIPS
Facility Description:
CRETE EC ;BP-17STJOHN 345.0 kV Ckt 1 line
Contingency Name:
AEP_P1-2_#695_1681_SRT-A
Contingency Type:Single
DC|AC:AC
Final Cycle Loading:110.24 %
Rating:1508.0 MVA
Rating Type:B
MVA to Mitigate:1662.46
MW Contribution:
10.58
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area:CE/NIPS
Facility Description:
CRETE EC ;BP-17STJOHN 345.0 kV Ckt 1 line
Contingency Name:
AEP_P1-2_#695_1681_SRT-A
Contingency Type:Single
DC|AC:AC
Final Cycle Loading:109.41 %
Rating:1508.0 MVA
Rating Type:B
MVA to Mitigate:1649.92
MW Contribution:
10.41
Bus #Bus NameTypeMW Contribution
274676JOLIET 29;8U
50/50
40.299
274676JOLIET 29;8U
50/50
23.232
274687WILL CNTY;4U
50/50
37.455
274687WILL CNTY;4U
50/50
37.455
274847GR RIDGE ;BU
Solar/Wind Harmer
8.786
274861TOP CROP ;1U
Solar/Wind Harmer
9.962
274862TOP CROP ;2U
Solar/Wind Harmer
9.962
274871GR RIDGE ;2U
Solar/Wind Harmer
9.692
276897AD1-100 C
Solar/Wind Harmer
76.528
270536AF1-215 GEN2
Solar/Wind Helper
2.074
270535AF1-215 GEN1
Solar/Wind Helper
2.074
270055AF2-134 C O1
Solar/Wind Helper
1.382
270526AF1-158 GEN
Solar/Wind Helper
2.158
939351AE1-166 GEN
Solar/Wind Harmer
0
959351AF2-226 GEN
50/50
7.722
960281AF2-319 GEN
50/50
7.722
960681AF2-359 GEN
Solar/Wind Helper
3.517
970707AG2-453 GEN
Solar/Wind Harmer
21.498
971369AH1-165 GEN
50/50
10.576
972181SS23-001
Solar/Wind Harmer
26.467
972231SS25-0005
Solar/Wind Harmer
42.346
24441505OLIV SLR
Solar/Wind Helper
0.081
941551AE2-152 GEN
Solar/Wind Harmer
0
CBM West 1LTFEXP_CBM-W1->PJM
CBM
59.953
CBM West 2LTFEXP_CBM-W2->PJM
CBM
22.889
CBM South 1LTFEXP_CBM-S1->PJM
CBM
0.843
NYPJM->LTFIMP_NY
CLTF
1.331
GibsonPJM->LTFIMP_GIBSON
CLTF
0
WECLTFEXP_WEC->PJM
CLTF
4.095
HAMLETPJM->LTFIMP_HAMLET
CLTF
0.758
CATAWBAPJM->LTFIMP_CATAWBA
CLTF
0.413
TVALTFEXP_TVA->PJM
CLTF
0.522
TRIMBLEPJM->LTFIMP_TRIMBLE
CLTF
0.826
CALDErWOODPJM->LTFIMP_CALDERWOOD
CLTF
0
MECLTFEXP_MEC->PJM
CLTF
12.286
CHEOAHPJM->LTFIMP_CHEOAH
CLTF
0
BlueGrassPJM->LTFIMP_BlueG
CLTF
2.438
LAGNLTFEXP_LAGN->PJM
CLTF
3.268
MISO WINDMISO-WIND_EXP->MISO-WIND_IMP
CLTF
480.46

Details for CRETE EC ;BP-17STJOHN 345.0 kV Ckt 1 line l/o COMED_P4_112-65-BT4-5___SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:CE/NIPS
Facility Description:
CRETE EC ;BP-17STJOHN 345.0 kV Ckt 1 line
Contingency Name:
COMED_P4_112-65-BT4-5___SRT-A
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:110.21 %
Rating:1508.0 MVA
Rating Type:B
MVA to Mitigate:1661.95
MW Contribution:
10.58
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area:CE/NIPS
Facility Description:
CRETE EC ;BP-17STJOHN 345.0 kV Ckt 1 line
Contingency Name:
COMED_P4_112-65-BT4-5___SRT-A
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:109.41 %
Rating:1508.0 MVA
Rating Type:B
MVA to Mitigate:1649.95
MW Contribution:
10.41
Bus #Bus NameTypeMW Contribution
274676JOLIET 29;8U
50/50
40.304
274676JOLIET 29;8U
50/50
23.235
274687WILL CNTY;4U
50/50
37.458
274687WILL CNTY;4U
50/50
37.458
274847GR RIDGE ;BU
Solar/Wind Harmer
8.789
274861TOP CROP ;1U
Solar/Wind Harmer
9.962
274862TOP CROP ;2U
Solar/Wind Harmer
9.962
274871GR RIDGE ;2U
Solar/Wind Harmer
9.695
276897AD1-100 C
Solar/Wind Harmer
61.582
270536AF1-215 GEN2
Solar/Wind Helper
2.074
270535AF1-215 GEN1
Solar/Wind Helper
2.074
270055AF2-134 C O1
Solar/Wind Helper
1.383
270526AF1-158 GEN
Solar/Wind Helper
2.158
939351AE1-166 GEN
Solar/Wind Harmer
0
959351AF2-226 GEN
50/50
7.722
960281AF2-319 GEN
50/50
7.722
960681AF2-359 GEN
Solar/Wind Helper
3.517
970707AG2-453 GEN
Solar/Wind Harmer
21.513
970833AG2-524 GEN
Solar/Wind Harmer
8.297
970833AG2-524 GEN
Solar/Wind Harmer
6.857
971369AH1-165 GEN
50/50
10.576
972181SS23-001
Solar/Wind Harmer
26.466
972231SS25-0005
Solar/Wind Harmer
42.346
24441505OLIV SLR
Solar/Wind Helper
0.081
941551AE2-152 GEN
Solar/Wind Harmer
0
CBM West 1LTFEXP_CBM-W1->PJM
CBM
59.974
CBM West 2LTFEXP_CBM-W2->PJM
CBM
22.892
CBM South 1LTFEXP_CBM-S1->PJM
CBM
0.843
NYPJM->LTFIMP_NY
CLTF
1.332
GibsonPJM->LTFIMP_GIBSON
CLTF
0
WECLTFEXP_WEC->PJM
CLTF
4.096
HAMLETPJM->LTFIMP_HAMLET
CLTF
0.758
CATAWBAPJM->LTFIMP_CATAWBA
CLTF
0.413
TVALTFEXP_TVA->PJM
CLTF
0.522
TRIMBLEPJM->LTFIMP_TRIMBLE
CLTF
0.826
CALDErWOODPJM->LTFIMP_CALDERWOOD
CLTF
0
MECLTFEXP_MEC->PJM
CLTF
12.289
CHEOAHPJM->LTFIMP_CHEOAH
CLTF
0
BlueGrassPJM->LTFIMP_BlueG
CLTF
2.439
LAGNLTFEXP_LAGN->PJM
CLTF
3.269
MISO WINDMISO-WIND_EXP->MISO-WIND_IMP
CLTF
480.601

Details for CRETE EC ;BP-17STJOHN 345.0 kV Ckt 1 line l/o COMED_P4_112-65-BT3-4___SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:CE/NIPS
Facility Description:
CRETE EC ;BP-17STJOHN 345.0 kV Ckt 1 line
Contingency Name:
COMED_P4_112-65-BT3-4___SRT-A
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:110.21 %
Rating:1508.0 MVA
Rating Type:B
MVA to Mitigate:1661.91
MW Contribution:
10.58
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area:CE/NIPS
Facility Description:
CRETE EC ;BP-17STJOHN 345.0 kV Ckt 1 line
Contingency Name:
COMED_P4_112-65-BT3-4___SRT-A
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:109.41 %
Rating:1508.0 MVA
Rating Type:B
MVA to Mitigate:1649.9
MW Contribution:
10.41
Bus #Bus NameTypeMW Contribution
274676JOLIET 29;8U
50/50
40.304
274676JOLIET 29;8U
50/50
23.235
274687WILL CNTY;4U
50/50
37.458
274687WILL CNTY;4U
50/50
37.458
274847GR RIDGE ;BU
Solar/Wind Harmer
8.789
274861TOP CROP ;1U
Solar/Wind Harmer
9.962
274862TOP CROP ;2U
Solar/Wind Harmer
9.962
274871GR RIDGE ;2U
Solar/Wind Harmer
9.695
276897AD1-100 C
Solar/Wind Harmer
61.583
270536AF1-215 GEN2
Solar/Wind Helper
2.074
270535AF1-215 GEN1
Solar/Wind Helper
2.074
270055AF2-134 C O1
Solar/Wind Helper
1.383
270526AF1-158 GEN
Solar/Wind Helper
2.158
939351AE1-166 GEN
Solar/Wind Harmer
0
959351AF2-226 GEN
50/50
7.722
960281AF2-319 GEN
50/50
7.722
960681AF2-359 GEN
Solar/Wind Helper
3.517
970707AG2-453 GEN
Solar/Wind Harmer
21.512
970833AG2-524 GEN
Solar/Wind Harmer
8.297
970833AG2-524 GEN
Solar/Wind Harmer
6.857
971369AH1-165 GEN
50/50
10.576
972181SS23-001
Solar/Wind Harmer
26.466
972231SS25-0005
Solar/Wind Harmer
42.346
24441505OLIV SLR
Solar/Wind Helper
0.081
941551AE2-152 GEN
Solar/Wind Harmer
0
CBM West 1LTFEXP_CBM-W1->PJM
CBM
59.972
CBM West 2LTFEXP_CBM-W2->PJM
CBM
22.892
CBM South 1LTFEXP_CBM-S1->PJM
CBM
0.843
NYPJM->LTFIMP_NY
CLTF
1.332
GibsonPJM->LTFIMP_GIBSON
CLTF
0
WECLTFEXP_WEC->PJM
CLTF
4.096
HAMLETPJM->LTFIMP_HAMLET
CLTF
0.758
CATAWBAPJM->LTFIMP_CATAWBA
CLTF
0.413
TVALTFEXP_TVA->PJM
CLTF
0.522
TRIMBLEPJM->LTFIMP_TRIMBLE
CLTF
0.826
CALDErWOODPJM->LTFIMP_CALDERWOOD
CLTF
0
MECLTFEXP_MEC->PJM
CLTF
12.289
CHEOAHPJM->LTFIMP_CHEOAH
CLTF
0
BlueGrassPJM->LTFIMP_BlueG
CLTF
2.439
LAGNLTFEXP_LAGN->PJM
CLTF
3.269
MISO WINDMISO-WIND_EXP->MISO-WIND_IMP
CLTF
480.591

Details for CRETE EC ;BP-17STJOHN 345.0 kV Ckt 1 line l/o 765-L11215__-S_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:CE/NIPS
Facility Description:
CRETE EC ;BP-17STJOHN 345.0 kV Ckt 1 line
Contingency Name:
765-L11215__-S_SRT-A
Contingency Type:Single
DC|AC:AC
Final Cycle Loading:110.16 %
Rating:1508.0 MVA
Rating Type:B
MVA to Mitigate:1661.16
MW Contribution:
10.58
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area:CE/NIPS
Facility Description:
CRETE EC ;BP-17STJOHN 345.0 kV Ckt 1 line
Contingency Name:
765-L11215__-S_SRT-A
Contingency Type:Single
DC|AC:AC
Final Cycle Loading:109.34 %
Rating:1508.0 MVA
Rating Type:B
MVA to Mitigate:1648.84
MW Contribution:
10.41
Bus #Bus NameTypeMW Contribution
274676JOLIET 29;8U
50/50
40.299
274676JOLIET 29;8U
50/50
23.232
274687WILL CNTY;4U
50/50
37.455
274687WILL CNTY;4U
50/50
37.455
274847GR RIDGE ;BU
Solar/Wind Harmer
8.786
274861TOP CROP ;1U
Solar/Wind Harmer
9.962
274862TOP CROP ;2U
Solar/Wind Harmer
9.962
274871GR RIDGE ;2U
Solar/Wind Harmer
9.692
276897AD1-100 C
Solar/Wind Harmer
76.528
270536AF1-215 GEN2
Solar/Wind Helper
2.074
270535AF1-215 GEN1
Solar/Wind Helper
2.074
270055AF2-134 C O1
Solar/Wind Helper
1.382
270526AF1-158 GEN
Solar/Wind Helper
2.158
939351AE1-166 GEN
Solar/Wind Harmer
0
959351AF2-226 GEN
50/50
7.722
960281AF2-319 GEN
50/50
7.722
960681AF2-359 GEN
Solar/Wind Helper
3.517
970707AG2-453 GEN
Solar/Wind Harmer
21.498
971369AH1-165 GEN
50/50
10.576
972181SS23-001
Solar/Wind Harmer
26.467
972231SS25-0005
Solar/Wind Harmer
42.346
24441505OLIV SLR
Solar/Wind Helper
0.081
941551AE2-152 GEN
Solar/Wind Harmer
0
CBM West 1LTFEXP_CBM-W1->PJM
CBM
59.953
CBM West 2LTFEXP_CBM-W2->PJM
CBM
22.889
CBM South 1LTFEXP_CBM-S1->PJM
CBM
0.843
NYPJM->LTFIMP_NY
CLTF
1.331
GibsonPJM->LTFIMP_GIBSON
CLTF
0
WECLTFEXP_WEC->PJM
CLTF
4.095
HAMLETPJM->LTFIMP_HAMLET
CLTF
0.758
CATAWBAPJM->LTFIMP_CATAWBA
CLTF
0.413
TVALTFEXP_TVA->PJM
CLTF
0.522
TRIMBLEPJM->LTFIMP_TRIMBLE
CLTF
0.826
CALDErWOODPJM->LTFIMP_CALDERWOOD
CLTF
0
MECLTFEXP_MEC->PJM
CLTF
12.286
CHEOAHPJM->LTFIMP_CHEOAH
CLTF
0
BlueGrassPJM->LTFIMP_BlueG
CLTF
2.438
LAGNLTFEXP_LAGN->PJM
CLTF
3.268
MISO WINDMISO-WIND_EXP->MISO-WIND_IMP
CLTF
480.46
CONTINGENCY 'AEP_P1-2_#695_1681_SRT-A'
 OPEN BRANCH FROM BUS 243206 TO BUS 290602 CKT Z1   /*05DUMONT     765.0 - 05DUMONT_RW  765.0
 OPEN BRANCH FROM BUS 270644 TO BUS 290602 CKT 1    /*WILTON   ;   765.0 - 05DUMONT_RW  765.0
END
CONTINGENCY 'COMED_P4_112-65-BT4-5___SRT-A'
 REMOVE SHUNT 1 FROM BUS 270644                    /*WILTON   ;   765.0
 TRIP BRANCH FROM BUS 270644 TO BUS 290602 CKT 1   /*WILTON   ;   765.0 - 05DUMONT_RW  765.0
 TRIP BRANCH FROM BUS 275233 TO BUS 270644 CKT 1   /*WILTON   ;4M 345.0 - WILTON   ;   765.0
 TRIP BRANCH FROM BUS 275233 TO BUS 270927 CKT 1   /*WILTON   ;4M 345.0 - WILTON   ; R 345.0
 TRIP BRANCH FROM BUS 275233 TO BUS 275333 CKT 1   /*WILTON   ;4M 345.0 - WILTON   ;4C  33.0
END
CONTINGENCY 'COMED_P4_112-65-BT3-4___SRT-A'
 REMOVE SHUNT 1 FROM BUS 270644                    /*WILTON   ;   765.0
 TRIP BRANCH FROM BUS 270644 TO BUS 290602 CKT 1   /*WILTON   ;   765.0 - 05DUMONT_RW  765.0
 TRIP BRANCH FROM BUS 275232 TO BUS 270644 CKT 1   /*WILTON   ;3M 345.0 - WILTON   ;   765.0
 TRIP BRANCH FROM BUS 275232 TO BUS 270926 CKT 1   /*WILTON   ;3M 345.0 - WILTON   ; B 345.0
 TRIP BRANCH FROM BUS 275232 TO BUS 275332 CKT 1   /*WILTON   ;3M 345.0 - WILTON   ;3C  33.0
END
CONTINGENCY '765-L11215__-S_SRT-A'
 REMOVE SHUNT 1 FROM BUS 270644                    /*WILTON   ;   765.0
 TRIP BRANCH FROM BUS 270644 TO BUS 290602 CKT 1   /*WILTON   ;   765.0 - 05DUMONT_RW  765.0
END
960680 to 243229 ckt 1
274750 to 255112 ckt 1

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

StudyAreaFacility DescriptionContingency NameContingency TypeDC|ACFinal Cycle LoadingRating (MVA)Rating TypeMVA to MitigateMW ContributionDetails
GD2AEP
05MARYSVL_RS-05MARYSV 765.0 kV Ckt Z1 line
AEP_P4_#7334_05JEFRSO 765_A2_SRT-A
BreakerAC107.83 %4142.0B4466.51
13.36
GD2AEP
05MARYSVL_RS-05MARYSV 765.0 kV Ckt Z1 line
AEP_P4_#1760_05JEFRSO 765_A_SRT-A
BreakerAC102.95 %4142.0B4264.1
13.08

Details for 05MARYSVL_RS-05MARYSV 765.0 kV Ckt Z1 line l/o AEP_P4_#7334_05JEFRSO 765_A2_SRT-A


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area:AEP
Facility Description:
05MARYSVL_RS-05MARYSV 765.0 kV Ckt Z1 line
Contingency Name:
AEP_P4_#7334_05JEFRSO 765_A2_SRT-A
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:107.83 %
Rating:4142.0 MVA
Rating Type:B
MVA to Mitigate:4466.51
MW Contribution:
13.36
Impact of Topology Modeling:
Elimination
Bus #Bus NameTypeMW Contribution
274687WILL CNTY;4U
50/50
58.304
274687WILL CNTY;4U
50/50
58.304
270471AD2-092_GEN
Solar/Wind Helper
4.535
270349AD2-093_GEN
Solar/Wind Helper
4.535
270505AE1-170 C O1
Solar/Wind Harmer
19.583
270520AE2-214 GEN
Solar/Wind Helper
5.798
270043AE2-236 GEN
Solar/Wind Harmer
7.165
270284AF1-227 GEN1
Solar/Wind Helper
5.509
270286AF1-227 GEN2
Solar/Wind Helper
2.033
270287AF1-227 GEN3
Solar/Wind Helper
2.033
270054AF2-122 C O1
Solar/Wind Helper
3.543
270459AD2-067 GEN
Solar/Wind Helper
4.885
270526AF1-158 GEN
Solar/Wind Harmer
0
944961AF1-161 GEN
50/50
11.731
945111AF1-176 GEN
Solar/Wind Harmer
23.126
945111AF1-176 GEN
Solar/Wind Harmer
28.651
946101AF1-275 GEN
Solar/Wind Helper
1.45
960681AF2-359 GEN
Solar/Wind Harmer
0
961051AF2-396 GEN
Solar/Wind Harmer
19.687
961051AF2-396 GEN
Solar/Wind Harmer
14.318
961501AF2-441 GEN
50/50
46.554
970349AG2-230 GEN
Solar/Wind Harmer
21.249
970373AG2-245 GEN
Solar/Wind Harmer
27.197
970377AG2-248 GEN
50/50
23.403
970521AG2-332 GEN
50/50
23.403
971347AH1-153 GEN
Solar/Wind Harmer
7.083
971369AH1-165 GEN
50/50
13.356
971771AH1-392 GEN
Solar/Wind Harmer
11.917
972179AH1-673 GEN
50/50
19.829
972207SS24-0001
Solar/Wind Harmer
39.041
957371AF2-031 GEN
50/50
4.667
957891AF2-083 GEN
Solar/Wind Harmer
19.544
965681AG1-436 GEN
Solar/Wind Harmer
16.66
965791AG1-447 GEN
Solar/Wind Harmer
13.328
CBM West 1LTFEXP_CBM-W1->PJM
CBM
212.629
CBM West 2LTFEXP_CBM-W2->PJM
CBM
113.026
CBM South 1LTFEXP_CBM-S1->PJM
CBM
13.518
NYPJM->LTFIMP_NY
CLTF
4.687
LGEELTFEXP_LGEE->PJM
CLTF
3.133
WECLTFEXP_WEC->PJM
CLTF
7.001
HAMLETPJM->LTFIMP_HAMLET
CLTF
2.565
CATAWBAPJM->LTFIMP_CATAWBA
CLTF
1.349
TVALTFEXP_TVA->PJM
CLTF
3.396
CALDErWOODPJM->LTFIMP_CALDERWOOD
CLTF
0
MECLTFEXP_MEC->PJM
CLTF
24.995
CHEOAHPJM->LTFIMP_CHEOAH
CLTF
0
LAGNLTFEXP_LAGN->PJM
CLTF
11.163
SIGELTFEXP_SIGE->PJM
CLTF
0.451
MISO WINDMISO-WIND_EXP->MISO-WIND_IMP
CLTF
299.821
AG2-052LTFEXP_AG2-052->PJM
LTF
0.428
AH1-155LTFEXP_AH1-155->PJM
LTF
0.642

Details for 05MARYSVL_RS-05MARYSV 765.0 kV Ckt Z1 line l/o AEP_P4_#1760_05JEFRSO 765_A_SRT-A


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area:AEP
Facility Description:
05MARYSVL_RS-05MARYSV 765.0 kV Ckt Z1 line
Contingency Name:
AEP_P4_#1760_05JEFRSO 765_A_SRT-A
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:102.95 %
Rating:4142.0 MVA
Rating Type:B
MVA to Mitigate:4264.1
MW Contribution:
13.08
Impact of Topology Modeling:
Elimination
Bus #Bus NameTypeMW Contribution
274687WILL CNTY;4U
50/50
57.11
274687WILL CNTY;4U
50/50
57.11
270449AD2-020 GEN
Solar/Wind Harmer
0
270471AD2-092_GEN
Solar/Wind Helper
4.446
270349AD2-093_GEN
Solar/Wind Helper
4.446
270505AE1-170 C O1
Solar/Wind Harmer
19.541
270520AE2-214 GEN
Solar/Wind Helper
5.609
270043AE2-236 GEN
Solar/Wind Harmer
7.17
270284AF1-227 GEN1
Solar/Wind Helper
5.376
270286AF1-227 GEN2
Solar/Wind Helper
1.984
270287AF1-227 GEN3
Solar/Wind Helper
1.984
270054AF2-122 C O1
Solar/Wind Helper
3.452
270459AD2-067 GEN
Solar/Wind Helper
4.759
270526AF1-158 GEN
Solar/Wind Harmer
0
270071AF1-092 GEN
Solar/Wind Harmer
14.769
270071AF1-092 GEN
Solar/Wind Harmer
20.587
943021AE2-325 GEN
Solar/Wind Harmer
12.221
944961AF1-161 GEN
50/50
11.706
945111AF1-176 GEN
Solar/Wind Harmer
23.076
945111AF1-176 GEN
Solar/Wind Harmer
28.59
946101AF1-275 GEN
Solar/Wind Helper
1.402
960681AF2-359 GEN
Solar/Wind Harmer
0
961051AF2-396 GEN
Solar/Wind Harmer
25.795
961051AF2-396 GEN
Solar/Wind Harmer
18.76
961501AF2-441 GEN
50/50
45.746
970349AG2-230 GEN
Solar/Wind Harmer
21.214
970373AG2-245 GEN
Solar/Wind Harmer
7.678
970377AG2-248 GEN
50/50
23.355
970521AG2-332 GEN
50/50
23.355
971347AH1-153 GEN
Solar/Wind Harmer
7.071
971369AH1-165 GEN
50/50
13.082
971771AH1-392 GEN
Solar/Wind Harmer
11.875
972179AH1-673 GEN
50/50
19.498
957371AF2-031 GEN
50/50
4.59
957891AF2-083 GEN
Solar/Wind Harmer
19.499
965681AG1-436 GEN
Solar/Wind Harmer
16.537
965791AG1-447 GEN
Solar/Wind Harmer
13.229
CBM West 1LTFEXP_CBM-W1->PJM
CBM
206.778
CBM West 2LTFEXP_CBM-W2->PJM
CBM
102.77
CBM South 1LTFEXP_CBM-S1->PJM
CBM
12.736
NYPJM->LTFIMP_NY
CLTF
4.564
LGEELTFEXP_LGEE->PJM
CLTF
3.511
WECLTFEXP_WEC->PJM
CLTF
6.81
HAMLETPJM->LTFIMP_HAMLET
CLTF
2.548
CATAWBAPJM->LTFIMP_CATAWBA
CLTF
1.347
TVALTFEXP_TVA->PJM
CLTF
3.028
CALDErWOODPJM->LTFIMP_CALDERWOOD
CLTF
0
MECLTFEXP_MEC->PJM
CLTF
23.815
CHEOAHPJM->LTFIMP_CHEOAH
CLTF
0
LAGNLTFEXP_LAGN->PJM
CLTF
10.163
SIGELTFEXP_SIGE->PJM
CLTF
0.414
MISO WINDMISO-WIND_EXP->MISO-WIND_IMP
CLTF
298.72
AG2-052LTFEXP_AG2-052->PJM
LTF
0.414
AH1-155LTFEXP_AH1-155->PJM
LTF
0.621
CONTINGENCY 'AEP_P4_#7334_05JEFRSO 765_A2_SRT-A'
 OPEN BRANCH FROM BUS 242865 TO BUS 243208 CKT 2    /*05JEFRSO     345.0 - 05JEFRSO     765.0
 OPEN BRANCH FROM BUS 242865 TO BUS 248000 CKT 1    /*05JEFRSO     345.0 - 06CLIFTY     345.0
 OPEN BRANCH FROM BUS 242924 TO BUS 290618 CKT Z1   /*05HANG R     765.0 - 05HANGRCK_RJ 765.0
 OPEN BRANCH FROM BUS 243208 TO BUS 290619 CKT Z1   /*05JEFRSO     765.0 - 05JEFFRSN_RH 765.0
 OPEN BRANCH FROM BUS 290618 TO BUS 290619 CKT 1    /*05HANGRCK_RJ 765.0 - 05JEFFRSN_RH 765.0
END
CONTINGENCY 'AEP_P4_#1760_05JEFRSO 765_A_SRT-A'
 OPEN BRANCH FROM BUS 242924 TO BUS 290618 CKT Z1   /*05HANG R     765.0 - 05HANGRCK_RJ 765.0
 OPEN BRANCH FROM BUS 243207 TO BUS 290598 CKT Z1   /*05GRNTWN     765.0 - 05GREENTW_RJ 765.0
 OPEN BRANCH FROM BUS 243208 TO BUS 290599 CKT Z1   /*05JEFRSO     765.0 - 05JEFFRSN_RG 765.0
 OPEN BRANCH FROM BUS 243208 TO BUS 290619 CKT Z1   /*05JEFRSO     765.0 - 05JEFFRSN_RH 765.0
 OPEN BRANCH FROM BUS 290598 TO BUS 290599 CKT 1    /*05GREENTW_RJ 765.0 - 05JEFFRSN_RG 765.0
 OPEN BRANCH FROM BUS 290618 TO BUS 290619 CKT 1    /*05HANGRCK_RJ 765.0 - 05JEFFRSN_RH 765.0
END
290608 to 242928 ckt Z1

Short Circuit Analysis

Analysis Complete - No Issues

Based on PJM’s TC2 Phase II Short Circuit Analysis, this project did not contribute >1% fault duty to any previously identified overdutied breakers, nor did it cause any new overdutied breakers.

Please note that in TC2 Phase III, PJM will perform additional analysis including the evaluation of impacts from topology upgrades which may have potential effects on breaker duties not seen in the Phase II analysis.

Stability Analysis

Analysis Complete - No Issues

Executive Summary:

New Service Requests (projects) in PJM Transition Cycle 2, Cluster 57 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 57 projects.

This analysis is effectively a screening study to determine whether the addition of the Cluster 57 projects will meet the dynamics requirements of the NERC, COMED and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2028 summer peak load and light load case, modified to include applicable projects. Cluster 57 projects have been dispatched online according to the scenarios, and the voltage schedule is set to achieve near unity power factor at the high side of the main transformer for the IBR projects.

Cluster 57 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 632 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

  1. Steady-state operation (20 second run);
  2. Three-phase faults with normal clearing time;
  3. Three-phase bus faults with normal clearing time;
  4. Three-phase to ground faults with three-phase delayed clearing due to a stuck breaker (GO breakers);
  5. Three-phase to ground faults with single-phase delayed clearing due to a stuck breaker (IPO breakers)
  6. Three-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure;
  7. Three-phase faults with loss of multiple-circuit tower line.

For all simulations, the Cluster 57 projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the 2028 peak load and light load cases:

  1. Cluster 57 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  2. The system with Cluster 57 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3%.
  3. Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
  4. No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

AG2-453, AG2-524, AH1-165, AH1-563, AH1-673, AH1-698 and AH1-714 meets the leading and lagging PF requirement.

Initial simulations identified slow terminal voltage and reactive power control response at AH1-165 due to the absence of reactive power droop in the voltage controller of the power plant controller model (REPCA1). This was resolved by adding a 5% droop to Q/V controller in the REPCA1 model as follows:

REPCA1:

  • CON(J+8) = 0.05 (Kc, Reactive current compensation gain (pu))

Contingencies P4.01, P4.02, P4.03, P4.04, P4.05, P4.06, P4.229, P4.230, P4.267, P4.269, P4.270 and P4.279 exhibited oscillations in the POI voltage and generator responses after 17.5s. This behavior is attributed to improperly tuned power system stabilizer model (PSS2C) in AH1-698. This issue was observed only in light load scenario. It is recommended to tune the power system stabilizer to according to the system conditions.

Table 1: TC2 Cluster 57 Projects

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

AG2-453

Solar

ComEd

280

280

196

La Salle – Plano 345 kV

AG2-524

Storage/Solar

ComEd

110

110

110

La Salle – Mazon 138 kV

AH1-165

Storage

ComEd

72

72

0

Will County 138 kV

AH1-563

Storage

ComEd

1,206

150

150

Aurora EC 138 kV

AH1-673

Storage

ComEd

85

85

85

State Line - River Energy Center 138 kV

AH1-698

Nuclear

ComEd

2,584

130

57.6

Braidwood 345 kV

AH1-714

Nuclear

ComEd

1,360

169

174.1

La Salle 345 kV

 

 

Reactive Power Analysis

Analysis Complete - No Issues

The reactive power capability of AH1-165 meets the 0.95 leading and lagging PF requirement at the high side of the main transformer.

Steady-State Voltage Analysis

 Steady State Voltage Analysis complete, no voltage issues identified.

 

New Service Request Dependencies

The New Service Requests below are listed in one or more dispatch for the overloads identified in this report. These projects contribute to the loading of the overloaded facilities identified in this report. The percent overload of a facility and cost allocation you may have towards a particular reinforcement could vary depending on the action of other projects. The status of each project at the time of the analysis is presented in the table. This list may change as other projects withdraw or modify their requests. This table is valid for load flow analyses only.

New Service Requests Dependencies
Project IDProject NameStatus
AD1-100Loretto-Wilton 345 kV & Braidwood-Davis Creek 345 kVUnder Construction
AD2-047Davis Creek 138 kVSuspended
AE1-166Loretto-Wilton 345 kV & Braidwood-Davis Creek 345 kVEngineering & Procurement
AE2-152Loretto-Wilton 345 kV & Braidwood-Davis Creek 345 kVEngineering & Procurement
AF1-158Edison-Gravel Pit 138 kVIn Service
AF1-215Olive-Reynolds 345 kVIn Service
AF2-095Davis Creek 138 kVEngineering & Procurement
AF2-134Olive-Reynolds #2 345 kVIn Service
AF2-226Katydid Road 345 kVEngineering & Procurement
AF2-319Katydid Road 345 kVEngineering & Procurement
AF2-350Kensington 138 kVEngineering & Procurement
AF2-359Olive-University Park 345 kVEngineering & Procurement
AG1-436Olive-University Park 345 kVEngineering & Procurement
AG1-447Olive-University Park 345 kVEngineering & Procurement
AG2-453Lasalle - Plano 345 kVActive
AG2-524LaSalle Station - Mazon 138 kVActive
AG2-585Kensignton 138kVActive

Affected System - PJM Identified Violations

As part of PJM's analysis, per Tariff Part VII.G.336 & Manual 14H, Section 13, PJM evaluated the potential impacts on tie line facilities between PJM and an affected system entity, which were identified per PJM planning analysis criteria. This upgrade may be required on the affected system portion of the tie line along with cost allocation of such upgrade if applicable, in coordination with the affected system. Depending on the affected system, this project may not be contingent on upgrade based on PJM planning analysis criteria, but may be contingent on this upgrade based on the Affected System Operator's planning criteria, provided in the Affected Systems Study Section, herein.

Midcontinent Independent System Operator, Inc. (MISO)Identified Impacts

No cost allocated AFS Tie Line reinforcements were identified for this project in the Phase II System Impact Study load flow analysis.


System Reinforcement
Type
Load Flow
TO
NIPS
RTEP ID / TO ID
(Pending) / NIPS_TC1_15499
Title
NIPS SN/SE ratings of 1961/2390 MVA (TC2 and beyond)
Description
NIPS SN/SE ratings of 1206/1508 MVA (pre-TC1)
Total Cost ($USD)
$0
Allocated Cost ($USD)
$0
Time Estimate
TBD

Note: This reinforcement is fictitious and will not be cost allocated to projects. It is listed for information purposes only.

FacilityContingency
17STJOHN-CRETE EC ;BP 345.0 kV Ckt 1 line(Any)
New York Independent System Operator (NYISO)No Impact
Tennessee Valley Authority (TVA)No Impact
Louisville Gas & Electric (LG&E)No Impact
Duke Energy Carolinas (DUKE)No Impact
Duke Energy Progress – East (CPLE)No Impact
Duke Energy Progress – West (CPLW)No Impact

Affected System - Non-PJM Identified Violations

In accordance with PJM Tariff Part VII, Subpart D, section 310.A and as outlined in PJM Manual 14H, Sections 4.5 and 13, in Phase II of the Cycle, PJM provides the Affected System Operator any updates on the PJM projects that require an Affected Systems Study based on their response at DP1. New Service Requests that require an Affected Systems Study are required to enter into an Affected Systems Study Agreement with the Affected System Operator, as applicable, prior to the close of DP2 or they will be withdrawn from the Cycle.

If the Project Developer already entered into the necessary agreement and the results are available, PJM will supply them in the Phase II SIS report. See below for the status of any required Affected Systems Study. A status of “Pending” means that the study is not yet completed by the Affected System Operator. If your project requires an Affected Systems Study and your results are not provided for Phase II SIS, PJM anticipates providing them in the Phase III SIS per Tariff Part VII.D.312.

Midcontinent Independent System Operator, Inc. (MISO)Identified Impacts
Note: This reflects the Affected System studies results provided by the Affected System Operator. These results may be subject to adjustments based on the outcome of any studies in the remaining phases of the Affected System Operator's Generator Interconnection Process.
Impacted FacilityTransmission OwnerReinforcementCostCost Allocated to AH1-165Scenarios
  • 17REYNOLDS 765.0 - 05GRNTWN 765.0 CKT 1
NIPS Reynolds-Greentown 765 kV
NIPSCO: No mitigation required. Rating Of NIPS-
Owned
Line Portion: SN/SE=9015 MVA/9015 MVA.

AEP: No mitigation required. 8348 MVA SN/SE
$0$0
  • NIPSCO
  • Contingent
  • Wvrich 69.0 - Rochester TP 69.0 CKT 1
NIPS Wvrich - Rochester TP 69 kV
DEI: Rebuild 1 mile of 69kV with 477ACSR/VR2 @
100/120C the ratings assume that NIPSCO terminal
upgrades would not limit our T-Line rating. $1.5M

NIPSCO: DEI mitigations acceptable to remove
constraint. $0
$1,500,000$21,732
  • NIPSCO
New York Independent System Operator (NYISO)Not required
Tennessee Valley Authority (TVA)Not required
Louisville Gas & Electric (LG&E)Not required
Duke Energy Carolinas (DUKE)Not required
Duke Energy Progress – East (CPLE)Not required
Duke Energy Progress – West (CPLW)Not required

System Reinforcements

No cost allocated system reinforcements were identified for this project in the Phase II System Impact Study load flow analysis.

Shown below are the details of the cost allocated, contingent, eliminated, topology and potential aggregate contributor reinforcements for this project. Please refer to the System Reinforcement table above and the information below for more detail.


System Reinforcement: b3878.1
Type
Load Flow
TO
AEP
RTEP ID / TO ID
b3878.1
Title
Upgrade 765 kV circuit breakers 'B' and 'B2' to 5000A 50kA breakers at Marysville Station
Description
Upgrade 765 kV circuit breakers 'B' and 'B2' to 5000A 50kA breakers at Marysville Station. In addition, the project will upgrade the existing wavetrap towards Sorenson.
Cost Information
Time Estimate
Nov 12 2027

Not Contingent

Note: AH1-165 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-165 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.

FacilityContingency
05MARYSV-05MARYSVL_RS 765.0 kV Ckt Z1 line(Any)
Rating SetRating TypeRating Value
(All)A5496.0 MVA
(All)B6667.0 MVA
(All)C6868.0 MVA

System Reinforcement: n9182.0
Type
Load Flow
TO
AEP
RTEP ID / TO ID
n9182.0 / AEPIMJMS01
Title
Rebuild Olive - AF2-359 345kV
Description
Rebuild the ~7.3 mile 345 kV line section between Olive and AF2-359 POI. The standard conductor for 345kV lines is 2-bundle 954 ACSR 45/7 RAIL.
Total Cost ($USD)
$35,000,000
Discounted Total Cost ($USD)
$35,000,000
Allocated Cost ($USD)
$0
Time Estimate
30 to 36 Months

Potential Aggregate Contributor

Note: Based on PJM cost allocation criteria, AH1-165 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AH1-165 could receive cost allocation. Although AH1-165 may not presently have cost responsibility for this upgrade, AH1-165 is a potential Aggregate Pool Contributor.

FacilityContingency
05OLIVE-AF2-359 TP 345.0 kV Ckt 1 line(Any)
Rating SetRating TypeRating Value
(All)A1410.0 MVA
(All)B1718.0 MVA

System Reinforcement
Type
Load Flow
TO
NextEra
RTEP ID / TO ID
(Pending)
Title
NextEra STE Rating of 2495 MVA
Description
None
Total Cost ($USD)
$0
Discounted Total Cost ($USD)
$0
Allocated Cost ($USD)
$0
Time Estimate
TBD

Note: This reinforcement is fictitious and will not be cost allocated to projects. It is listed for information purposes only.

FacilityContingency
17STJOHN-CRETE EC ;BP 345.0 kV Ckt 1 line(Any)
No new ratings for this Flowgate.

System Reinforcement
Type
Load Flow
TO
ComEd
RTEP ID / TO ID
(Pending)
Title
ComEd SSTE Rating of 2499 MVA
Description
None
Total Cost ($USD)
$0
Discounted Total Cost ($USD)
$0
Allocated Cost ($USD)
$0
Time Estimate
TBD

Note: This reinforcement is fictitious and will not be cost allocated to projects. It is listed for information purposes only.

FacilityContingency
17STJOHN-CRETE EC ;BP 345.0 kV Ckt 1 line(Any)
Rating SetRating TypeRating Value
(All)STE2499.0 MVA

Conversion from Impacts into Topology or Eliminated Reinforcements into Region Topology Contingent Reinforcements for AH1-165


AH1-165 Contributions into Topology or Eliminated Reinforcements:
TypeTORTEP ID / TO IDTitleTopo or ElimMW ImpactPercent AllocationCategoryAllocated Cost ($USD)
Contributions into Topology or Eliminated Reinforcement Total:$0
AH1-165 Contingent Region Topology Upgrades:
TORTEP IDTitleCategoryAllocated Cost ($USD)
Region Topology Upgrade Total:$0

Attachments

AH1-165 One Line Diagram

AH1-165 One Line Diagram.pdf
The state in which the generator or merchant transmission facility is located.
The Transmission Owner of the facility where the New Service Request project interconnects to the transmission system.
Winter load flow analysis will be performed starting in Transition Cycle 2.