AH1-251 Phase II System Impact Study Report
v1.00 released 2026-06-03 17:53
Todds Tavern- Spotsylvania/Goldsdale 115kV
50.0 MW Capacity / 50.0 MW Energy
Introduction
This Phase II System Impact Study (SIS) Report has been prepared in accordance with the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 310 for New Service Requests (projects) in Transition Cycle 2 (TC2). The Project Developer/Eligible Customer (developer) is Tavern Energy, LLC, and the Transmission Provider (TP) is PJM Interconnection, LLC (PJM). The interconnected Transmission Owner (TO) is Virginia Electric and Power Company (d/b/a Dominion Energy Virginia).
Preface
The Phase II System Impact Study is conducted on an aggregate basis within a New Services Request’s Cycle, and results are provided in both (i) a single Cycle summary format and (ii) an individual project-level basis. The Phase II System Impact Study Results (for both the summary and individual reports) will be publicly available on PJM’s website. Project Developers must obtain the results from the website.
In accordance with PJM Manual 14H, section 4.5, PJM takes the following actions during the Phase II System Impact Study:
- PJM will retool load flow results from the Phase I System Impact Study (summer peak, winter peak and light load) based on decisions made by Project Developers or Eligible Customers during Decision Point I.
- PJM will conduct any required voltage analyses.
- PJM will perform short circuit and stability analyses as required.
- PJM will coordinate with the Affected System to confirm which projects in the PJM Cycle will require Affected System studies. If the Affected System Operator indicates that an Affected System study is required, PJM will:
- Notify the Project Developer or Eligible Customer of the need for an Affected System study and the requirement to execute an Affected System study agreement with the impacted Affected System Operator, and;
- Include the results of the Affected System Operator’s Affected System Study in the Phase II System Impact Study results, if applicable and available.
- The Phase II System Impact Study Results will be publicly available on PJM’s website. Project Developers and Eligible Customers must obtain the results from the website.
The Transmission Owner takes the following actions during the Phase II System Impact Study:
- Verify Interconnection Facilities and Network Upgrades required to accommodate the New Service Request.
- Perform a Facilities Study. The Facilities Study in Phase II System Impact Study phase will be for the physical Interconnection Facilities. The Facilities Study requirements are outlined in Attachment C of this manual. The study will be conducted pursuant to Tariff, Part VII, Subpart D, section 307(A)(7) and Tariff, Part VIII, Subpart C, section 404(A)(7).
Decision Point II Requirements
At the close of Phase II System Impact Study, PJM will initiate Decision Point II (DP2). During DP2, the Project Developer will have 30 days to decide whether to proceed with their project. If the Project Developer elects to proceed, they should provide the elements defined in the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 311.A. Additional information on these elements is available in PJM Manual 14H sections 4.6, 6, and 7.
Allowable project modifications at Decision Point II are defined in PJM Open Access Transmission Tariff, Part VII, Subpart D, section 311.B. Additional information regarding allowable project modifications can be found in PJM Manual 14H, section 9.8.
Adverse Test Eligibility
This New Service Request meets the Adverse Study Impact Criteria and has the option to either move forward in the Cycle process or withdraw at DP2 with Readiness Deposits refunded. See Readiness Deposit calculation below.
This section details whether a Project Developer or Eligible Customer qualifies for the Adverse Study Impact clause outlined in the PJM OATT, Part VII, Subpart D, section 311.B and Manual 14H, section 6.2.2. In order to qualify for an Adverse Study Impact at Decision Point II, the Network Upgrade cost from Phase I to Phase II must:
- Increase overall by 25% or more
- Increases by more than $10,000 per MW (Includes Costs identified in Affected System studies)
If a New Service Request meets the criteria above and chooses to withdraw the request, PJM will refund the cumulative Readiness Deposit amounts paid at the Application Phase and at Decision Point I (RD1 and RD2, respectively).
The below calculations show the computation of this New Service Request's Adverse Study Impact
General
The Project Developer has proposed a Storage facility located in the Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) zone — Spotsylvania County, Virginia. The installed facilities will have a total capability of 50.0 MW with 50.0 MW of this output being recognized by PJM as Capacity.Project Information
Physical Interconnection Facility Study
The transmission owner has completed the Physical Interconnection Facilities Study. This report is available for download.
Point of Interconnection
AH1-251 will interconnect on the Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) transmission system by tapping the Todds Tavern - Spotsylvania 115 kV Line.
Cost Summary
The table below shows a summary of the total cost estimates for this New Service Request project. In Phase II SIS, the interconnected Transmission Owner has performed a facilities study for both the Transmission Owner Interconnection Facilities (TOIF) and Physical Interconnection Network Upgrades. The System Reliability Network Upgrade shown in the table are planning level cost estimates which are subject to change as a result of a facility study performed by the TO during Phase III System Impact Study.
Based on the Phase II SIS results, the AH1-251 project has the following allocation of costs for interconnection. The cost contribution towards Readiness Deposit #3 are also shown below.
| Cost Summary | |||
|---|---|---|---|
| Description | Cost Allocated to AH1-251 | Cost Subject to Readiness* | Cost Subject to Adverse |
| Transmission Owner Interconnection Facilities (TOIF) | $1,223,282 | $0 | $0 |
| Other Scope | $483,290 | $0 | $0 |
| Option To Build Oversight | $0 | $0 | $0 |
| Physical Interconnection Network Upgrades | |||
| Stand Alone Network Upgrades | $15,824,597 | $15,824,597 | $15,824,597 |
| Network Upgrades | $5,494,065 | $5,494,065 | $5,494,065 |
| System Reliability Network Upgrades | |||
| Steady State Thermal & Voltage | $0 | $0 | $0 |
| Transient Stability | $0 | $0 | $0 |
| Short Circuit | $0 | $0 | $0 |
| Transmission Owner Analysis | |||
| SubRegional | $0 | $0 | $0 |
| Distribution | $0 | $0 | $0 |
| Affected System Reinforcements | |||
| AFS - PJM Violations | $0 | $0 | $0 |
| AFS - Non-PJM Violations | $0 | $0 | $0 |
| Total | $23,025,234 | $21,318,662 | $21,318,662 |
* Contributes to calculation for Readiness Deposit #3 (RD3). See Readiness Deposit section of report for additional detail.
Definitions
Transmission Owner Interconnection Facilities: Facilities that are owned, controlled, operated and maintained by the Transmission Owner on the Transmission Owner’s side of the Point of Change of Ownership to the Point of Interconnection, including any modifications, additions or upgrades made to such facilities and equipment, that are necessary to physically and electrically interconnect the Generating Facility with the Transmission System or interconnected distribution facilities.
Stand Alone Network Upgrades: Network Upgrades, which are not part of an Affected System, which a Project Developer may construct without affecting day-to-day operations (e.g. taking a transmission outage) of the Transmission System during their construction.
Network Upgrades: Modifications or additions to transmission-related facilities that are integrated with and support the Transmission Provider’s overall Transmission System for the general benefit of all users of such Transmission System. Network Upgrades have no impact or potential impact on the Transmission System until the final tie-in is complete.
Notes
Note 1: PJM Open Access Transmission Tariff (OATT), Part VII, Subpart D, section 307.5 outlines cost allocation rules. The rules are further clarified in PJM Manual 14H, section 4.2.6. PJM shall identify the New Service Requests in the Cycle contributing to the need for the required Network Upgrades within the Cycle. All New Service Requests that contribute to the need for a Network Upgrade will receive cost allocation for that upgrade pursuant to each New Service Request’s contribution to the reliability violation identified on the transmission system in accordance with PJM Manuals.
Note 2: There will be no inter-Cycle cost allocation for Interconnection Facilities or Network Upgrades identified in the System Impact Study costs identified in a Cycle; all such costs shall be allocated to New Service Requests in that Cycle.
Note 3: For Project Developers with System Reinforcements listed: If this project presents cost allocation to a System Reinforcement indicates $0, then please be aware that as changes to the interconnection process occur, such as other projects withdrawing, reducing in size, etc, the cost responsibilities can change and a cost allocation may be assigned to this project. In addition, although this project presents cost allocation to a System Reinforcement is presently $0, this project may need this system reinforcement completed to be deliverable to the PJM system. If this project desires to come into service prior to completion of the system reinforcement, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the system reinforcement is complete.
Note 4: Please see the ‘Affected Systems Studies’ section of this Phase II SIS report for details on your project’s need for an Affected Systems Study. If your project requires an Affected Systems Study, the Affected Systems impacts may not be available from the Affected System Operator at the time of the PJM Phase II SIS. Therefore, the cost in this section would not reflect any required upgrades by the Affected System until the study is completed. If your project requires an Affected Systems Study and your results are not provided for Phase II SIS, PJM anticipates providing them in the Phase III SIS per Tariff Part VII.D.312.
Readiness Deposit
Per Tariff Part VII, Subpart D, section 311 (Decision Point II) A.1.b and PJM Manual 14H, section 6.2, Readiness Deposit #3 (RD3) are funds committed by the Project Developer or Eligible Customer based upon the applicable contribution to Network Upgrades as defined below. Readiness Deposits are not used to fund studies nor to offset Security.
During Decision Point II (DP2), the Project Developer or Eligible Customer is required to submit Readiness Deposit #3, which is calculated as 20% of cost allocation for required Phase II Network Upgrades minus Readiness Deposit #1 & Readiness Deposit #2.
Note 1: “Network Upgrades” referred to in the calculation include both (i) the Physical Interconnection Network Upgrades and (ii) the System Reliability Network Upgrades as shown in the Cost Summary table.
Note 2: Readiness Deposit #1 (RD1) = ($4,000 * Project Size (MW))
Note 3: Readiness Deposit #2 (RD2) = 10% of cost allocation for required Network Upgrades minus RD1. Readiness Deposit #2 (RD2) can be zero, but may not be a negative number.
Note 4: Readiness Deposit #3 can be zero, but may not be a negative number.
Readiness Deposit #3 Due for Project AH1-251
Readiness Deposit #3 has been calculated for the project based on the Phase II System Impact Study results and is shown in the table below. This Readiness Deposit #3 must be provided at Decision Point II through either a wire transfer or letter of credit per Manual 14H, Section 6.2.
Readiness Deposit #3 Due for AH1-251
For additional detail regarding Readiness Deposit Refunds, reference PJM Manual 14H, section 6.2.1. The Readiness Deposit Letter of Credit template can be found here.
Transmission Owner Scope of Work
The total preliminary cost estimate for the Transmission Owner scope of work (including TOIF and Physical Interconnection Network Upgrades) is given in the table below. These costs do not include CIAC Tax Gross-up.
Transmission Owner Build Option
| Network Upgrades | |||||||
|---|---|---|---|---|---|---|---|
| RTEP ID | Description | Direct | Indirect | Total Cost ($USD) | Allocated Cost ($USD) | ||
| Labor | Materials | Labor | Materials | ||||
| (Pending) | Remote end network upgrade at Spotsylvania substation | $102,705 | $54,212 | $11,463 | $4,953 | $173,333 | $173,333 |
| (Pending) | Remote end network upgrade at Chancellor substation. | $102,705 | $54,212 | $11,463 | $4,953 | $173,333 | $173,333 |
| (Pending) | This scope serves to cut in 115 kV line 198 into a new three breaker substation. | $3,522,217 | $1,177,985 | $269,305 | $177,892 | $5,147,399 | $5,147,399 |
| Other | |||||||
|---|---|---|---|---|---|---|---|
| RTEP ID | Description | Direct | Indirect | Total Cost ($USD) | Allocated Cost ($USD) | ||
| Labor | Materials | Labor | Materials | ||||
| (Pending) | This scope includes metering accuracy coupling capacitor voltage transformers (CCVT), metering accuracy current transformers (CT) and associated equipment. | $322,219 | $33,939 | $121,390 | $5,742 | $483,290 | $483,290 |
| Stand-Alone Network Upgrades | |||||||
|---|---|---|---|---|---|---|---|
| RTEP ID | Description | Direct | Indirect | Total Cost ($USD) | Allocated Cost ($USD) | ||
| Labor | Materials | Labor | Materials | ||||
| (Pending) | Build a new 115kV three breaker ring bus tapping the Todds Tavern - Spotsylvania 115 kV line. | $8,422,386 | $4,655,911 | $2,307,840 | $438,460 | $15,824,597 | $15,824,597 |
| Transmission Owner Interconnection Facilities | |||||||
|---|---|---|---|---|---|---|---|
| RTEP ID | Description | Direct | Indirect | Total Cost ($USD) | Allocated Cost ($USD) | ||
| Labor | Materials | Labor | Materials | ||||
| (Pending) | Portion of the interconnection switching station soley associated with the single feed to the generating facilities collector station including disconnect switch, conductors and connectors. | $553,770 | $505,303 | $93,600 | $70,609 | $1,223,282 | $1,223,282 |
Developer Build Option
Project Developer has the option ("Option to Build") to assume responsibility for the design, procurement and construction of Transmission Owner Interconnection Facilities and/or Stand-Alone Network Upgrades.
If Option to Build is elected, the Project Developer must fulfill additional requirements in accordance to PJM Manual 14C, section 5.1 and PJM Manual 14H, section 8.6.2.
The cost estimates for eligible facilities and Option to Build oversight are highlighted below:
| Network Upgrades | |||||||
|---|---|---|---|---|---|---|---|
| RTEP ID | Description | Direct | Indirect | Total Cost ($USD) | Allocated Cost ($USD) | ||
| Labor | Materials | Labor | Materials | ||||
| (Pending) | Remote end network upgrade at Spotsylvania substation | $102,705 | $54,212 | $11,463 | $4,953 | $173,333 | $173,333 |
| (Pending) | Remote end network upgrade at Chancellor substation. | $102,705 | $54,212 | $11,463 | $4,953 | $173,333 | $173,333 |
| (Pending) | This scope serves to cut in 115 kV line 198 into a new three breaker substation. | $3,522,217 | $1,177,985 | $269,305 | $177,892 | $5,147,399 | $5,147,399 |
| Option to Build Oversight | |||||||
|---|---|---|---|---|---|---|---|
| RTEP ID | Description | Direct | Indirect | Total Cost ($USD) | Allocated Cost ($USD) | ||
| Labor | Materials | Labor | Materials | ||||
| (Pending) | Metering Option to Build (OTB) oversight for metering accuracy CCVT's, metering accuracy CT's and associated equipment. | $31,876 | $0 | $3,557 | $0 | $35,433 | $35,433 |
| (Pending) | Option to Build (OTB) oversite for the new 115kV three breaker ring bus | $2,240,889 | $423,171 | $442,454 | $22,081 | $3,128,595 | $3,128,595 |
| (Pending) | TOIF Option to Build (OTB) oversight for the portion of the interconnection switching station which is soley associated solely with the single feed to the generating facilities including disconnect switch, conductors and connectors. | $94,446 | $0 | $10,465 | $0 | $104,911 | $104,911 |
| Build Option Price Comparison | |||||||
|---|---|---|---|---|---|---|---|
| Build Option | Total Cost | Allocated Cost | |||||
| Transmission Owner Build Option | $23,025,234 | $23,025,234 | |||||
| Developer Build Option | $8,763,004 | $8,763,004 | |||||
Based on the scope of work for the Interconnection Facilities, it is expected to take a range of 36 to 40 month(s) after the signing of a Generator Interconnection Agreement (as this is a FERC connection) and construction kickoff call to complete the installation of the physical connection work. This assumes that there will be no environmental issues with any of the new properties associated with this project, that there will be no delays in acquiring the necessary permits for implementing the defined interconnection work, and that all system outages will be allowed when requested.
Note that the TO findings were made from a conceptual review of this project. A more detailed review of the connection facilities and their cost will be identified in a future study phase. Further note that the cost estimate data provided should be considered high level estimates since it was produced without a detailed engineering review. The Project Developer will be responsible for the actual cost of construction. TO herein reserves the right to return to any issues in this document and, upon appropriate justification, request additional monies to complete any reinforcements to the transmission systems.
Remote Terminal Work: During Phase II of the PJM interconnection process, TO’s System Protection Engineering Department will review transmission line protection as well as anti-islanding required to accommodate the new generation and interconnection substation. System Protection Engineering will determine the minimal acceptable protection requirements to reliably interconnect the proposed generating facility with the transmission system. The review is based on maintaining system reliability by reviewing TO’s protection requirements with the known transmission system configuration which includes generating facilities in the area. This review may determine that transmission line protection and communication upgrades are required at remote substations.
Transmission Owner Analysis
PJM performed a power flow analysis of the transmission system using a 2028 load flow model and the results were verified by Dominion.
Developer Requirements
The developer is responsible for all design and construction related activities on the developer’s side of the Point of Change in Ownership. Dominion interconnection requirements can be found here.
To the extent that these Applicable Technical Requirements and Standards may conflict with the terms and conditions of the Tariff, the Tariff shall control.
Revenue Metering and SCADA Requirements
The developer will be required to install equipment necessary to provide Revenue Metering (KWH, KVARH) and real time data (KW, KVAR) for their generating Resource. See PJM Manual 01, PJM Manual 14D, and PJM Tariff Part IX, Subpart B, Appendix 2, section 8.Transmission Owner Requirements
The Project Developer will be required to comply with all interconnected Transmission Owner’s revenue metering requirements located at the following link: PJM - Transmission Owner Engineering & Construction Standards.
Summer Peak Analysis
The New Service Request AH1-251 was evaluated as a 50.0 MW (50.0 MW Capacity) injection in the Dominion area.
AH1-251 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 50.0 MW (50.0 MW under study).
Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.
The following flowgates remain after considering the topology reinforcements required by the cycle.
(No impacts were found for this analysis)
The following flowgates were eliminated after considering the topology reinforcements required by the cycle.
| Study | Area | Facility Description | Contingency Name | Contingency Type | DC|AC | Final Cycle Loading | Rating (MVA) | Rating Type | MVA to Mitigate | MW Contribution | |
|---|---|---|---|---|---|---|---|---|---|---|---|
| GD2 | DVP | 8CHANCE-8BRISTER 500.0 kV Ckt 1 line | DVP_P4-2: 545T594_SRT-S | Breaker | AC | 120.94 % | 3966.0 | C | 4796.52 | 14.48 | |
| GD2 | DVP | 8CHANCE-8BRISTER 500.0 kV Ckt 1 line | DVP_P1-2: LN 594_SRT-S | Single | AC | 119.54 % | 4070.2 | B | 4865.39 | 17.36 | |
| GD2 | DVP | 8CHANCE-8BRISTER 500.0 kV Ckt 1 line | DVP_P4-2: H1T594_SRT-S | Breaker | AC | 109.1 % | 5010.0 | C | 5465.85 | 17.44 | |
| GD2 | DVP | 8CHANCE-8BRISTER 500.0 kV Ckt 1 line | DVP_P4-2: SPOTS H1T594_SRT-S | Breaker | AC | 109.02 % | 5010.0 | C | 5461.82 | 17.41 | |
| GD2 | DVP | 8CHANCE-8BRISTER 500.0 kV Ckt 1 line | DVP_P4-2: 515T594_SRT-S | Breaker | AC | 109.01 % | 5010.0 | C | 5461.43 | 17.36 | |
| GD2 | DVP | 8CHANCE-8BRISTER 500.0 kV Ckt 1 line | DVP_P4-2: H1T573_SRT-S | Breaker | AC | 106.65 % | 5010.0 | C | 5342.95 | 17.45 | |
| GD2 | DVP | 8CHANCE-8BRISTER 500.0 kV Ckt 1 line | DVP_P1-2: LN 568_SRT-S | Single | AC | 105.56 % | 4070.2 | B | 4296.31 | 14.22 | |
| GD2 | DVP | 8NO ANNA-8LADYSMITH 500.0 kV Ckt 1 line | DVP_P1-2: LN 594_SRT-S | Single | AC | 132.01 % | 3220.44 | B | 4251.24 | 9.04 | |
| GD2 | DVP | 8NO ANNA-8LADYSMITH 500.0 kV Ckt 1 line | DVP_P4-2: H1T594_SRT-S | Breaker | AC | 120.22 % | 3940.0 | C | 4736.51 | 9.11 | |
| GD2 | DVP | 8NO ANNA-8LADYSMITH 500.0 kV Ckt 1 line | DVP_P4-2: 515T594_SRT-S | Breaker | AC | 119.98 % | 3940.0 | C | 4727.27 | 9.04 | |
| GD2 | DVP | 8SPOTSYL-8MORRSVL 500.0 kV Ckt 1 line | DVP_P4-2: 545T552_SRT-S | Breaker | AC | 175.64 % | 3118.0 | C | 5476.52 | 16.23 | |
| GD2 | DVP | 8SPOTSYL-8MORRSVL 500.0 kV Ckt 1 line | DVP_P1-2: LN 552_SRT-S | Single | AC | 161.05 % | 3220.44 | B | 5186.56 | 16.76 | |
| GD2 | DVP | 8SPOTSYL-8MORRSVL 500.0 kV Ckt 1 line | DVP_P4-2: H1T552_SRT-S | Breaker | AC | 147.64 % | 3940.0 | C | 5817.13 | 16.76 | |
| GD2 | DVP | 8SPOTSYL-8MORRSVL 500.0 kV Ckt 1 line | DVP_P1-2: LN 568_SRT-S | Single | AC | 146.86 % | 3220.44 | B | 4729.57 | 12.19 | |
| GD2 | DVP | 8SPOTSYL-8MORRSVL 500.0 kV Ckt 1 line | DVP_P2-2: MORRISVILLE B1_SRT-S | Bus | AC | 134.94 % | 3118.0 | C | 4207.35 | 10.96 | |
| GD2 | DVP | 8SPOTSYL-8MORRSVL 500.0 kV Ckt 1 line | DVP_P7-1: LN 2-2199_SRT-A-1 | Tower | AC | 116.02 % | 3940.0 | C | 4571.15 | 12.68 | |
| GD2 | DVP | 8SPOTSYL-8MORRSVL 500.0 kV Ckt 1 line | Base Case | Single | AC | 115.83 % | 3220.44 | A | 3730.18 | 10.96 | |
| GD2 | DVP | 8SPOTSYL-8MORRSVL 500.0 kV Ckt 1 line | DVP_P7-1: LN 2-2199_SRT-A-2 | Tower | AC | 115.74 % | 3940.0 | C | 4560.31 | 12.68 | |
| GD2 | DVP | 8SPOTSYL-8MORRSVL 500.0 kV Ckt 1 line | DVP_P2-2: GERMANNA_SRT-A | Bus | AC | 112.89 % | 3940.0 | C | 4447.98 | 11.14 |
Winter Peak Analysis
The New Service Request AH1-251 was evaluated as a 50.0 MW (50.0 MW Capacity) injection in the Dominion area.
AH1-251 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 50.0 MW (50.0 MW under study).
Note: The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for single or N-1 contingencies and multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.
The following flowgates remain after considering the topology reinforcements required by the cycle.
(No impacts were found for this analysis)
The following flowgates were eliminated after considering the topology reinforcements required by the cycle.
(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)
Light Load Analysis
The New Service Request AH1-251 was evaluated as a 50.0 MW injection and 50.0 MW withdrawal in the Dominion area.
AH1-251 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 50.0 MW (50.0 MW under study).
Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.
The following flowgates remain after considering the topology reinforcements required by the cycle.
| Study | Area | Facility Description | Contingency Name | Contingency Type | DC|AC | Final Cycle Loading | Rating (MVA) | Rating Type | MVA to Mitigate | MW Contribution | |
|---|---|---|---|---|---|---|---|---|---|---|---|
| GD2 | AEP | 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line | AEP_P4_#7422_05CLOVRD 500_EE2_SRT-A | Breaker | AC | 173.68 % | 1180.0 | B | 2049.45 | 5.86 | |
| GD2 | AEP | 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line | DVP_P4-2: 56602_SRT-A | Breaker | AC | 173.67 % | 1180.0 | B | 2049.35 | 5.86 | |
| GD2 | AEP | 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line | DVP_P4-2: 547T566_SRT-L | Breaker | AC | 173.35 % | 1180.0 | B | 2045.56 | 5.87 | |
| GD2 | AEP | 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line | AEP_P1-2_#7422_16_SRT-A | Single | AC | 171.54 % | 1180.0 | B | 2024.13 | 5.86 | |
| GD2 | AEP | 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line | AP_P2-3_PE-765-237805-SB3_SRT-SL_SENS | Breaker | AC | 138.39 % | 1180.0 | B | 1632.98 | 5.47 | |
| GD2 | AEP | 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line | AP_P2-3_PE-765-237805-SB4_SRT-SL_SENS | Breaker | AC | 138.39 % | 1180.0 | B | 1632.98 | 5.47 | |
| GD2 | AEP | 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line | AP_P1-2_PE-765-242508-237805_SRT-A_SENS | Single | AC | 136.83 % | 1180.0 | B | 1614.63 | 5.47 | |
| GD2 | AEP | 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line | AEP_P2-2_#1372_05JOSHUA 765_1_SRT-A | Bus | AC | 110.97 % | 1180.0 | B | 1309.48 | 5.11 | |
| GD2 | AEP | 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line | DVP_P7-1: LN 2114-535_SRT-A_SENS | Tower | AC | 109.71 % | 1180.0 | B | 1294.59 | 5.1 | |
| GD2 | AEP | 05CLOVRD_RJO-05JOSHUA 765.0 kV Ckt 1 line | DVP_P7-1: LN 2140-535_SRT-A_SENS | Tower | AC | 109.63 % | 1180.0 | B | 1293.65 | 5.11 |
The following flowgates were eliminated after considering the topology reinforcements required by the cycle.
(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)
Short Circuit Analysis
Analysis Complete - No Issues
Based on PJM’s TC2 Phase II Short Circuit Analysis, this project did not contribute >1% fault duty to any previously identified overdutied breakers, nor did it cause any new overdutied breakers.
Please note that in TC2 Phase III, PJM will perform additional analysis including the evaluation of impacts from topology upgrades which may have potential effects on breaker duties not seen in the Phase II analysis.
Stability Analysis
Analysis Complete - No Issues
New Service Requests (projects) in PJM Transition Cycle 2 Cluster 15 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 15 projects.
Table 1: Transition Cycle 2 Cluster 15 Projects
|
|
|
|
|
|
|
|
Cluster | Project | Fuel Type | Transmission Owner | MFO (MW) | MWE (MW) | MWC (MW) | Point of Interconnection |
15 | AH1-251 | Storage | Dominion | 50 | 50 | 50 | Todds Tavern – Spotsylvania 115 kV line |
AH1-263 | Storage | Dominion | 200 | 200 | 200 | Chancellor 115 kV substation |
The purpose of the transient stability analysis is to determine the system impact of the generation facility. This study will determine system improvements, if any, needed to reduce violations in the transient stability analysis caused by the addition of the projects in Cluster 15.
The load flow scenario for the analysis was based on the Regional Transmission Expansion Plan (RTEP) 2028 summer peak case, modified to include applicable projects. Cluster 15 projects have been dispatched online at maximum power output with near unity power factor measured at the high-side of the main substation transformer.
Cluster 15 projects were tested for compliance with NERC, PJM, Dominion Energy and other applicable criteria. 83 contingencies were studied, each with a 20 second simulation time period. The contingencies studied included:
- Steady-state operation (30 seconds)
- Three-phase faults with normal clearing time
- Single-phase bus faults with normal clearing time
- Single-phase faults with stuck breaker
- Single-phase faults placed at 80% of the line with delayed clearing at remote line end because of primary communications/relaying failure
- Single-phase faults with loss of multiple-circuit tower line.
For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.
The results of the analysis were evaluated against the following recovery criteria per PJM’s Regional Transmission Planning Process and Dominion Energy’s transmission planning criteria:
- Cluster 15 projects were able to ride through the faults (except for faults where protective action trips a generator(s)).
- The system with Cluster 15 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3%.
- Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus) and the final voltages are within the steady-state voltage ranges below per Dominion Energy’s transmission planning criteria.
- P1 Category Contingencies:
- 0.93 to 1.05 p.u. for 230, 115, 69 kV facilities
- 0.93 to 1.03 p.u. for 138 kV facilities due to legacy switches
- 1.01 to 1.096 p.u. for 500 kV facilities
- P2, P4, P5, and P7 Category Contingencies:
- 0.90 to 1.05 p.u. for 230, 115, 69 kV facilities
- 0.90 to 1.03 p.u. for 138 kV facilities due to legacy switches
- 1.00 to 1.096 p.u. for 500 kV facilities
- No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.
No mitigation is required to connect projects in TC2 Cluster 15.
Note: AC1-158 generator tripped for over voltages above 1.31 p.u. The unit rode through when the pickup timer increased from 0.014 seconds to 0.017 seconds. Generation facility owner will need to verify ride through capability.
Reactive Power Analysis
The reactive power capability of AH1-251 met the 0.95 leading and lagging power factor requirement at the high side of the main transformer.
Steady-State Voltage Analysis
Analysis Complete - No Issues
Steady State Voltage Analysis complete, no voltage issues identified.
New Service Request Dependencies
The New Service Requests below are listed in one or more dispatch for the overloads identified in this report. These projects contribute to the loading of the overloaded facilities identified in this report. The percent overload of a facility and cost allocation you may have towards a particular reinforcement could vary depending on the action of other projects. The status of each project at the time of the analysis is presented in the table. This list may change as other projects withdraw or modify their requests. This table is valid for load flow analyses only.
| New Service Requests Dependencies | ||
|---|---|---|
| Project ID | Project Name | Status |
| AA1-038 | Lexington-Low Moor 230kV | Under Construction |
| AB1-027 | Old Church 34.5 KV | In Service |
| AB2-024 | Correctional 34.5kV | In Service |
| AB2-026 | Powhatan 34.5kV | In Service |
| AB2-029 | Remington 34.5kV | In Service |
| AB2-158 | Louisa-South Anna 230kV | In Service |
| AC1-076 | Locust Grove-Paytes 115kV | In Service |
| AC1-101 | Johns Creek-Excel 138kV I | Engineering & Procurement |
| AC1-102 | Johns Creek-Excel 138kV II | Engineering & Procurement |
| AC1-118 | Westmoreland 34.5kV | In Service |
| AC1-158 | Spotsylvania 500kV | In Service |
| AC1-164 | Chickahominy 230kV | Partially in Service - Under Construction |
| AC1-191 | Elmont 115kV | Engineering & Procurement |
| AC2-137 | Elko 34.5kV | In Service |
| AC2-138 | Northern Neck 34.5kV | In Service |
| AD1-041 | Harmony Village-Shackleford 115 kV | In Service |
| AD1-063 | Harmony Village 34.5 kV | In Service |
| AD1-105 | Kings Dominion DP 115 kV | Under Construction |
| AD1-115 | Mountain Run-Mitchell 115 kV | Withdrawn |
| AD2-030 | Wan 34.5 kV | In Service |
| AD2-073 | Sanders DP 230 kV | In Service |
| AD2-074 | Garner DP-Lancaster 115 kV | Under Construction |
| AD2-179 | Morgans Cut-Glen Lyn 138kV | Withdrawn |
| AE1-074 | Winterpock 34.5 kV | Under Construction |
| AE1-075 | Powhatan 34.5 kV | In Service |
| AE1-108 | Bremo-Scottsville 138 kV | Under Construction |
| AE1-155 | Garner-Northern Neck 115 kV | In Service |
| AE1-175 | Light Foot 34.5 kV | In Service |
| AE1-190 | Harmony Village-Shackleford 115 kV | In Service |
| AE1-191 | Harmony Village-Shackleford 115 kV | In Service |
| AE1-212 | Grandview-Clifftop 138 kV | Suspended |
| AE2-005 | Harmony Village-Shackleford 115 kV | Suspended |
| AE2-092 | Kidds Store-Sherwood 115 kV | Engineering & Procurement |
| AE2-140 | Axton-Danville 138 kV | Suspended |
| AE2-160 | Kanawha River 138 kV | Engineering & Procurement |
| AE2-166 | Stockton 138 kV | Suspended |
| AE2-185 | Gladys DP-Stonemill Switching Station 69 kV | Engineering & Procurement |
| AE2-283 | Gladys-Stone Mill 69 kV | Engineering & Procurement |
| AE2-326 | Jacksons Ferry 138 kV | Engineering & Procurement |
| AF1-014 | Harmony Village-Shackleford 115 kV | Suspended |
| AF1-042 | Garner DP-Lancaster 115 kV | Engineering & Procurement |
| AF1-049 | Berry Hill 138 kV | Under Construction |
| AF1-114 | Oak Grove-Dahlgren 230 kV | Engineering & Procurement |
| AF1-130 | Inez 138 kV | Suspended |
| AF1-162 | Inez 138 kV | Engineering & Procurement |
| AF2-013 | Arnold's Corner-Dahlgren 230 kV | Engineering & Procurement |
| AF2-018 | Inez 138 kV | Engineering & Procurement |
| AF2-054 | Wan 34.5 kV | In Service |
| AF2-085 | Midlothian 34.5 kV | In Service |
| AF2-091 | Oak Grove-Dahlgren 230 kV | Engineering & Procurement |
| AF2-106 | Hazel Hollow-Glen Lyn #1 138 kV | Engineering & Procurement |
| AF2-144 | Powhatan 34.5 kV | In Service |
| AF2-382 | Hurley 69 kV | Engineering & Procurement |
| AF2-404 | Gladys DP-Stonemill 69 kV | Engineering & Procurement |
| AG1-038 | Garner DP-Lancaster 115 kV | Engineering & Procurement |
| AG1-124 | Riverville - Gladstone 138 kV | Engineering & Procurement |
| AG1-145 | Lightfoot 34.5 kV | In Service |
| AG1-152 | Remington CT 230 kV | Engineering & Procurement |
| AG1-282 | Dunnsville 34.5 kV | Withdrawn |
| AG1-469 | Gordonsville 34.5 kV | Withdrawn |
| AG1-508 | Point Lookout 69 kV | Withdrawn |
| AG1-558 | Buckner 34.5 kV | Withdrawn |
| AG1-559 | Caroline Pines 22 kV | Withdrawn |
| AG2-088 | Midlothian 230 kV | Active |
| AG2-184 | Harbert Metering 138 kV | Active |
| AG2-240 | Old Church 34.5 kV | Active |
| AG2-272 | Berry Hill 138 kV | Active |
| AG2-360 | Broadford 138 kV | Active |
| AG2-518 | Tech Drive 138 kV | Active |
| AG2-568 | Stink Run - Sundial 138 kV | Active |
| AH1-072 | Red Onion - VC5 69 kV | Active |
| AH1-073 | Red Onion - VC5 69 kV | Active |
| AH1-098 | Wolf Glade-West Carroll 138 kV | Active |
| AH1-133 | Saltville - Tazewell 138 kV | Active |
| AH1-144 | Peter's Mountain 138 kV | Active |
| AH1-145 | Peter's Mountain 138 kV | Active |
| AH1-188 | Pigeon Creek 138 kV | Active |
| AH1-227 | Flemming - Fremont 69 kV | Active |
| AH1-263 | Chancellor 115 kV | Active |
| AH1-269 | Claytor 138 kV | Active |
| AH1-348 | Pound 34.5 kV | Active |
| AH1-461 | Buckhorn 138 kV | Active |
| AH1-535 | Nagel - Cane River 230 kV | Active |
| AH1-617 | Harbert Metering 138 kV | Active |
| AH1-721 | Laurel-Cooper 161 kV | Active |
Affected System - PJM Identified Violations
As part of PJM's analysis, per Tariff Part VII.G.336 & Manual 14H, Section 13, PJM evaluated the potential impacts on tie line facilities between PJM and an affected system entity, which were identified per PJM planning analysis criteria. This upgrade may be required on the affected system portion of the tie line along with cost allocation of such upgrade if applicable, in coordination with the affected system. Depending on the affected system, this project may not be contingent on upgrade based on PJM planning analysis criteria, but may be contingent on this upgrade based on the Affected System Operator's planning criteria, provided in the Affected Systems Study Section, herein.
Affected System - Non-PJM Identified Violations
In accordance with PJM Tariff Part VII, Subpart D, section 310.A and as outlined in PJM Manual 14H, Sections 4.5 and 13, in Phase II of the Cycle, PJM provides the Affected System Operator any updates on the PJM projects that require an Affected Systems Study based on their response at DP1. New Service Requests that require an Affected Systems Study are required to enter into an Affected Systems Study Agreement with the Affected System Operator, as applicable, prior to the close of DP2 or they will be withdrawn from the Cycle.
If the Project Developer already entered into the necessary agreement and the results are available, PJM will supply them in the Phase II SIS report. See below for the status of any required Affected Systems Study. A status of “Pending” means that the study is not yet completed by the Affected System Operator. If your project requires an Affected Systems Study and your results are not provided for Phase II SIS, PJM anticipates providing them in the Phase III SIS per Tariff Part VII.D.312.
System Reinforcements
No cost allocated system reinforcements were identified for this project in the Phase II System Impact Study load flow analysis.
Shown below are the details of the cost allocated, contingent, eliminated, topology and potential aggregate contributor reinforcements for this project. Please refer to the System Reinforcement table above and the information below for more detail.
System Reinforcement: b4000.357
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.357
- Title
- Build a new 765/500/230 kV substation called Yeat. Install (2) 765/500 kV transformers. Cut in 500 kV line Bristers-Ox and 500 kV line Meadowbrook-Vint Hill into Yeat.
- Description
- Build a new 765/500/230 kV substation called Yeat. Install (2) 765/500 kV transformers. Cut in 500 kV line Bristers-Ox and 500 kV line Meadowbrook-Vint Hill into Yeat.
- Cost Information
- Time Estimate
- Jun 01 2029
Not ContingentTopology Changing Note 1: AH1-251 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-251 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 8BRISTER-8CHANCE 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8MORRSVL-8SPOTSYL 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8LADYSMITH-8NO ANNA 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.356
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.356
- Title
- Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 86.7 miles in Dominion section).
- Description
- Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 86.7 miles in Dominion section).
- Cost Information
- Time Estimate
- Jun 01 2029
Not ContingentTopology Changing Note 1: AH1-251 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-251 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 8BRISTER-8CHANCE 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8MORRSVL-8SPOTSYL 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.355
- Type
- Load Flow
- TO
- AEP
- RTEP ID / TO ID
- b4000.355
- Title
- Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 69.3 miles in AEP section).
- Description
- Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 69.3 miles in AEP section).
- Cost Information
- Time Estimate
- Jun 01 2029
Not ContingentTopology Changing Note 1: AH1-251 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-251 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 8BRISTER-8CHANCE 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8MORRSVL-8SPOTSYL 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.352
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.352
- Title
- Cut in Line #568 Ladysmith - Possum Point into Thornburg (formerly Kraken), creating new Line #568 Thornburg (formerly Kraken) to Possum Point.
- Description
- Cut in Line #568 Ladysmith - Possum Point into Thornburg (formerly Kraken), creating new Line #568 Thornburg (formerly Kraken) to Possum Point.
- Cost Information
- Time Estimate
- Sep 16 2030
Not ContingentTopology Changing Note 1: AH1-251 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-251 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 8BRISTER-8CHANCE 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8MORRSVL-8SPOTSYL 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8LADYSMITH-8NO ANNA 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.351
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.351
- Title
- Cut in Line #568 Ladysmith - Possum Point into Thornburg (formerly Kraken), creating Line #9517 Ladysmith to Thornburg (formerly Kraken).
- Description
- Cut in Line #568 Ladysmith - Possum Point into Thornburg (formerly Kraken), creating Line #9517 Ladysmith to Thornburg (formerly Kraken).
- Cost Information
- Time Estimate
- Sep 16 2030
Not ContingentTopology Changing Note 1: AH1-251 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-251 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 8BRISTER-8CHANCE 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8MORRSVL-8SPOTSYL 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8LADYSMITH-8NO ANNA 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.350
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.350
- Title
- Update relay settings at Possum Point to change the destination of 500kV line #568 from Ladysmith to Thornburg (formerly Kraken).
- Description
- Update relay settings at Possum Point to change the destination of 500kV line #568 from Ladysmith to Thornburg (formerly Kraken).
- Cost Information
- Time Estimate
- Sep 16 2030
Not ContingentTopology Changing Note 1: AH1-251 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-251 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 8BRISTER-8CHANCE 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8MORRSVL-8SPOTSYL 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8LADYSMITH-8NO ANNA 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.349
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.349
- Title
- Update relay settings at Ladysmith to change the destination of 500kV line #568 from Possum Point to Thornburg (formerly Kraken).
- Description
- Update relay settings at Ladysmith to change the destination of 500kV line #568 from Possum Point to Thornburg (formerly Kraken).
- Cost Information
- Time Estimate
- Sep 16 2030
Not ContingentTopology Changing Note 1: AH1-251 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-251 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 8BRISTER-8CHANCE 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8MORRSVL-8SPOTSYL 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8LADYSMITH-8NO ANNA 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.348
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.348
- Title
- Build a new 500/230kV substation called Thornburg (formerly Kraken). The 500kV, 5000A ring bus will be set up for a redundant breaker configuration. Install (2) 1400MVA 500/230 kV transformers.
- Description
- Build a new 500/230kV substation called Thornburg (formerly Kraken). The 500kV, 5000A ring bus will be set up for a redundant breaker configuration. Install (2) 1400MVA 500/230 kV transformers. A new redundant breaker ring will be added at Thornburg (formerly Kraken) to accommodate the new 500kV line from North Anna to Thornburg (formerly Kraken).
- Cost Information
- Time Estimate
- Jun 01 2029
Not ContingentTopology Changing Note 1: AH1-251 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-251 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 8BRISTER-8CHANCE 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8MORRSVL-8SPOTSYL 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8LADYSMITH-8NO ANNA 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.344
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.344
- Title
- Build a 500kV line from North Anna substation (bypassing Ladysmith Substation) to a new substation called Thornburg (formerly Kraken). New conductor to have a minimum summer normal rating of 4357MVA.
- Description
- Build a 500kV line from North Anna substation (bypassing Ladysmith Substation) to a new substation called Thornburg (formerly Kraken). New conductor to have a minimum summer normal rating of 4357MVA.
- Cost Information
- Time Estimate
- Sep 16 2030
Not ContingentTopology Changing Note 1: AH1-251 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-251 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 8BRISTER-8CHANCE 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8MORRSVL-8SPOTSYL 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8LADYSMITH-8NO ANNA 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.346
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.346
- Title
- Cut-in 500kV line from Thornburg (formerly Kraken) substation into Yeat substation
- Description
- Cut-in 500kV line from Thornburg (formerly Kraken) substation into Yeat substation
- Cost Information
- Time Estimate
- Jun 01 2029
Not ContingentTopology Changing Note 1: AH1-251 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-251 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 8BRISTER-8CHANCE 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8MORRSVL-8SPOTSYL 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8LADYSMITH-8NO ANNA 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.345
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.345
- Title
- Build a 500kV line from a new substation called Thornburg (formerly Kraken) to a new substation called Yeat. New conductor to have a minimum summer normal rating of 4357MVA.
- Description
- Build a 500kV line from a new substation called Thornburg (formerly Kraken) to a new substation called Yeat. New conductor to have a minimum summer normal rating of 4357MVA.
- Cost Information
- Time Estimate
- Sep 16 2030
Not ContingentTopology Changing Note 1: AH1-251 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-251 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 8BRISTER-8CHANCE 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8MORRSVL-8SPOTSYL 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8LADYSMITH-8NO ANNA 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.342
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.342
- Title
- Remove the terminal equipment and substation work required for the termination of the Morrisville-Wishing Star 500 kV line into Vint Hill.
- Description
- Remove the terminal equipment and substation work required for the termination of the Morrisville-Wishing Star 500 kV line into Vint Hill.
- Cost Information
- Time Estimate
- Jul 13 2029
Not ContingentTopology Changing Note 1: AH1-251 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-251 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 8BRISTER-8CHANCE 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8MORRSVL-8SPOTSYL 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8LADYSMITH-8NO ANNA 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.341
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4000.341
- Title
- Remove the 500 kV conductor previously planned to terminate into the Vint Hill 500 kV Substation and extend approximately 0.2 miles of conductor to fly-over the site.
- Description
- Remove the 500 kV conductor previously planned to terminate into the Vint Hill 500 kV substation and extend approximately 0.2 miles of conductor to fly-over the site.
- Cost Information
- Time Estimate
- Jul 13 2029
Not ContingentTopology Changing Note 1: AH1-251 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-251 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 8BRISTER-8CHANCE 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8MORRSVL-8SPOTSYL 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8LADYSMITH-8NO ANNA 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4000.251
- Type
- Load Flow
- TO
- AEP
- RTEP ID / TO ID
- b4000.251
- Title
- Replace the wave trap and upgrade the relay at Cloverdale 765kV substation
- Description
- Replace the wave trap and upgrade the relay at Cloverdale 765kV substation
- Cost Information
- Time Estimate
- Jun 01 2029
Not Contingent Note: AH1-251 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-251 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.
| Facility | Contingency | |||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 05JOSHUA-05CLOVRD_RJO 765.0 kV Ckt 1 line | (Any) |
|
System Reinforcement: b4000.252
- Type
- Load Flow
- TO
- AEP
- RTEP ID / TO ID
- b4000.252
- Title
- Replace the wave trap and upgrade the relay at Joshua Falls 765kV substation
- Description
- Replace the wave trap and upgrade the relay at Joshua Falls 765kV substation
- Cost Information
- Time Estimate
- Jun 01 2029
Not Contingent Note: AH1-251 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-251 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.
| Facility | Contingency | |||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 05JOSHUA-05CLOVRD_RJO 765.0 kV Ckt 1 line | (Any) |
|
System Reinforcement: b4053.5
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4053.5
- Title
- Design and construct a new Voltage Source Converter (VSC) HVDC station at Mosby substation to support the new HVDC link.
- Description
- Design and construct a new Voltage Source Converter (VSC) HVDC station at Mosby substation to support the new HVDC link.
- Cost Information
- Time Estimate
- Jun 01 2032
Not ContingentTopology Changing Note 1: AH1-251 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-251 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 8BRISTER-8CHANCE 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8MORRSVL-8SPOTSYL 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8LADYSMITH-8NO ANNA 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4053.4
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4053.4
- Title
- Design and construct a new Voltage Source Converter (VSC) HVDC station at Heritage substation to support the new HVDC link.
- Description
- Design and construct a new Voltage Source Converter (VSC) HVDC station at Heritage substation to support the new HVDC link.
- Cost Information
- Time Estimate
- Jun 01 2032
Not ContingentTopology Changing Note 1: AH1-251 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-251 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 8BRISTER-8CHANCE 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8MORRSVL-8SPOTSYL 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8LADYSMITH-8NO ANNA 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4053.3
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4053.3
- Title
- Construct a new bipolar +/- 525 kV HVDC link connecting Heritage and Mosby substations, where the link has a capability of transmitting 3,000 MW.
- Description
- Construct a new bipolar +/- 525 kV HVDC link connecting Heritage and Mosby substations, where the link has a capability of transmitting 3,000 MW. The HVDC link, approximately 185 miles in length, will be fully routed underground between the two new proposed converter stations, one at Heritage and one at Mosby.
- Cost Information
- Time Estimate
- Jun 01 2032
Not ContingentTopology Changing Note 1: AH1-251 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-251 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 8BRISTER-8CHANCE 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8MORRSVL-8SPOTSYL 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8LADYSMITH-8NO ANNA 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4053.11
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4053.11
- Title
- Cut and loop line No. 5008 into Mosby substation, which will result in two 500 kV lines: line No. 5008 Morrisville-Mosby and line No. 9573 Mosby-Wishing Star.
- Description
- Cut and loop line No. 5008 into Mosby substation, which will result in two 500 kV lines: line No. 5008 Morrisville-Mosby and line No. 9573 Mosby-Wishing Star.
- Cost Information
- Time Estimate
- Jun 01 2030
Not ContingentTopology Changing Note 1: AH1-251 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-251 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 8BRISTER-8CHANCE 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8MORRSVL-8SPOTSYL 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8LADYSMITH-8NO ANNA 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |
System Reinforcement: b4053.12
- Type
- Load Flow
- TO
- Dominion
- RTEP ID / TO ID
- b4053.12
- Title
- Install two 500 kV breakers and all associated terminal equipment in the available bay adjacent to existing breaker XT590 to achieve a redundant breaker arrangement.
- Description
- Install two 500 kV breakers and all associated terminal equipment in the available bay adjacent to existing breaker XT590 to achieve a redundant breaker arrangement. Upgrade existing terminal equipment to 500 kV, 5000A 63 kAIC standards including breaker (XT590), disconnect switches (59078, X74), leads and bus work.
- Cost Information
- Time Estimate
- Jun 01 2030
Not ContingentTopology Changing Note 1: AH1-251 contributes to the loading of an overloaded facility that is being mitigated by a planned baseline upgrade. AH1-251 is not contingent on this baseline upgrade as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade. Note 2: This topology changing reinforcement was developed by the transmission owner and modeled in PJM analysis to address cycle overload(s). A flowgate that this project contributed to was identified as requiring this topology reinforcement.
| Facility | Contingency | ||
|---|---|---|---|
| 8BRISTER-8CHANCE 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8MORRSVL-8SPOTSYL 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. | |
| 8LADYSMITH-8NO ANNA 500.0 kV Ckt 1 line | (Any) | No new ratings for this Flowgate. |