AH1-452 Phase II System Impact Study Report
v1.00 released 2026-06-03 17:59
Clementine-Clementine Jct. 25 kV
8.35 MW Capacity / 19.9 MW Energy
Introduction
This Phase II System Impact Study (SIS) Report has been prepared in accordance with the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 310 for New Service Requests (projects) in Transition Cycle 2 (TC2). The Project Developer/Eligible Customer (developer) is IMG Solar LLC, and the Transmission Provider (TP) is PJM Interconnection, LLC (PJM). The interconnected Transmission Owner (TO) is Keystone Appalachian Transmission Company.
Preface
The Phase II System Impact Study is conducted on an aggregate basis within a New Services Request’s Cycle, and results are provided in both (i) a single Cycle summary format and (ii) an individual project-level basis. The Phase II System Impact Study Results (for both the summary and individual reports) will be publicly available on PJM’s website. Project Developers must obtain the results from the website.
In accordance with PJM Manual 14H, section 4.5, PJM takes the following actions during the Phase II System Impact Study:
- PJM will retool load flow results from the Phase I System Impact Study (summer peak, winter peak and light load) based on decisions made by Project Developers or Eligible Customers during Decision Point I.
- PJM will conduct any required voltage analyses.
- PJM will perform short circuit and stability analyses as required.
- PJM will coordinate with the Affected System to confirm which projects in the PJM Cycle will require Affected System studies. If the Affected System Operator indicates that an Affected System study is required, PJM will:
- Notify the Project Developer or Eligible Customer of the need for an Affected System study and the requirement to execute an Affected System study agreement with the impacted Affected System Operator, and;
- Include the results of the Affected System Operator’s Affected System Study in the Phase II System Impact Study results, if applicable and available.
- The Phase II System Impact Study Results will be publicly available on PJM’s website. Project Developers and Eligible Customers must obtain the results from the website.
The Transmission Owner takes the following actions during the Phase II System Impact Study:
- Verify Interconnection Facilities and Network Upgrades required to accommodate the New Service Request.
- Perform a Facilities Study. The Facilities Study in Phase II System Impact Study phase will be for the physical Interconnection Facilities. The Facilities Study requirements are outlined in Attachment C of this manual. The study will be conducted pursuant to Tariff, Part VII, Subpart D, section 307(A)(7) and Tariff, Part VIII, Subpart C, section 404(A)(7).
Decision Point II Requirements
At the close of Phase II System Impact Study, PJM will initiate Decision Point II (DP2). During DP2, the Project Developer will have 30 days to decide whether to proceed with their project. If the Project Developer elects to proceed, they should provide the elements defined in the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 311.A. Additional information on these elements is available in PJM Manual 14H sections 4.6, 6, and 7.
Allowable project modifications at Decision Point II are defined in PJM Open Access Transmission Tariff, Part VII, Subpart D, section 311.B. Additional information regarding allowable project modifications can be found in PJM Manual 14H, section 9.8.
Adverse Test Eligibility
This New Service Request does not meet the Adverse Study Impact Criteria and has the option to either move forward in the Cycle process or withdraw at DP2 with Readiness Deposit #1 forfeited. See adverse study impact calculation below.
This section details whether a Project Developer or Eligible Customer qualifies for the Adverse Study Impact clause outlined in the PJM OATT, Part VII, Subpart D, section 311.B and Manual 14H, section 6.2.2. In order to qualify for an Adverse Study Impact at Decision Point II, the Network Upgrade cost from Phase I to Phase II must:
- Increase overall by 25% or more
- Increases by more than $10,000 per MW (Includes Costs identified in Affected System studies)
If a New Service Request meets the criteria above and chooses to withdraw the request, PJM will refund the cumulative Readiness Deposit amounts paid at the Application Phase and at Decision Point I (RD1 and RD2, respectively).
The below calculations show the computation of this New Service Request's Adverse Study Impact
General
The Project Developer has proposed a Solar generating facility located in the Keystone Appalachian Transmission Company zone — Armstrong County, Pennsylvania. The installed facilities will have a total capability of 19.9 MW with 8.35 MW of this output being recognized by PJM as Capacity.Project Information
Physical Interconnection Facility Study
A Physical Interconnection Facilities Study is not required for this project.
Point of Interconnection
AH1-452 will interconnect on the Keystone Appalachian Transmission Company distribution system on the Clementine Jct to Clementine 25 kV line.
Cost Summary
The table below shows a summary of the total cost estimates for this New Service Request project. In Phase II SIS, the interconnected Transmission Owner has performed a facilities study for both the Transmission Owner Interconnection Facilities (TOIF) and Physical Interconnection Network Upgrades. The System Reliability Network Upgrade shown in the table are planning level cost estimates which are subject to change as a result of a facility study performed by the TO during Phase III System Impact Study.
Based on the Phase II SIS results, the AH1-452 project has the following allocation of costs for interconnection. The cost contribution towards Readiness Deposit #3 are also shown below.
| Cost Summary | |||
|---|---|---|---|
| Description | Cost Allocated to AH1-452 | Cost Subject to Readiness* | Cost Subject to Adverse |
| Transmission Owner Interconnection Facilities (TOIF) | $0 | $0 | $0 |
| Other Scope | $0 | $0 | $0 |
| Option To Build Oversight | $0 | $0 | $0 |
| Physical Interconnection Network Upgrades | |||
| Stand Alone Network Upgrades | $0 | $0 | $0 |
| Network Upgrades | $0 | $0 | $0 |
| System Reliability Network Upgrades | |||
| Steady State Thermal & Voltage | $0 | $0 | $0 |
| Transient Stability | $0 | $0 | $0 |
| Short Circuit | $0 | $0 | $0 |
| Transmission Owner Analysis | |||
| SubRegional | $0 | $0 | $0 |
| Distribution | $0 | $0 | $0 |
| Affected System Reinforcements | |||
| AFS - PJM Violations | $0 | $0 | $0 |
| AFS - Non-PJM Violations | $0 | $0 | $0 |
| Total | $0 | $0 | $0 |
* Contributes to calculation for Readiness Deposit #3 (RD3). See Readiness Deposit section of report for additional detail.
Definitions
Transmission Owner Interconnection Facilities: Facilities that are owned, controlled, operated and maintained by the Transmission Owner on the Transmission Owner’s side of the Point of Change of Ownership to the Point of Interconnection, including any modifications, additions or upgrades made to such facilities and equipment, that are necessary to physically and electrically interconnect the Generating Facility with the Transmission System or interconnected distribution facilities.
Stand Alone Network Upgrades: Network Upgrades, which are not part of an Affected System, which a Project Developer may construct without affecting day-to-day operations (e.g. taking a transmission outage) of the Transmission System during their construction.
Network Upgrades: Modifications or additions to transmission-related facilities that are integrated with and support the Transmission Provider’s overall Transmission System for the general benefit of all users of such Transmission System. Network Upgrades have no impact or potential impact on the Transmission System until the final tie-in is complete.
Notes
Note 1: PJM Open Access Transmission Tariff (OATT), Part VII, Subpart D, section 307.5 outlines cost allocation rules. The rules are further clarified in PJM Manual 14H, section 4.2.6. PJM shall identify the New Service Requests in the Cycle contributing to the need for the required Network Upgrades within the Cycle. All New Service Requests that contribute to the need for a Network Upgrade will receive cost allocation for that upgrade pursuant to each New Service Request’s contribution to the reliability violation identified on the transmission system in accordance with PJM Manuals.
Note 2: There will be no inter-Cycle cost allocation for Interconnection Facilities or Network Upgrades identified in the System Impact Study costs identified in a Cycle; all such costs shall be allocated to New Service Requests in that Cycle.
Note 3: For Project Developers with System Reinforcements listed: If this project presents cost allocation to a System Reinforcement indicates $0, then please be aware that as changes to the interconnection process occur, such as other projects withdrawing, reducing in size, etc, the cost responsibilities can change and a cost allocation may be assigned to this project. In addition, although this project presents cost allocation to a System Reinforcement is presently $0, this project may need this system reinforcement completed to be deliverable to the PJM system. If this project desires to come into service prior to completion of the system reinforcement, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the system reinforcement is complete.
Note 4: Please see the ‘Affected Systems Studies’ section of this Phase II SIS report for details on your project’s need for an Affected Systems Study. If your project requires an Affected Systems Study, the Affected Systems impacts may not be available from the Affected System Operator at the time of the PJM Phase II SIS. Therefore, the cost in this section would not reflect any required upgrades by the Affected System until the study is completed. If your project requires an Affected Systems Study and your results are not provided for Phase II SIS, PJM anticipates providing them in the Phase III SIS per Tariff Part VII.D.312.
Readiness Deposit
Per Tariff Part VII, Subpart D, section 311 (Decision Point II) A.1.b and PJM Manual 14H, section 6.2, Readiness Deposit #3 (RD3) are funds committed by the Project Developer or Eligible Customer based upon the applicable contribution to Network Upgrades as defined below. Readiness Deposits are not used to fund studies nor to offset Security.
During Decision Point II (DP2), the Project Developer or Eligible Customer is required to submit Readiness Deposit #3, which is calculated as 20% of cost allocation for required Phase II Network Upgrades minus Readiness Deposit #1 & Readiness Deposit #2.
Note 1: “Network Upgrades” referred to in the calculation include both (i) the Physical Interconnection Network Upgrades and (ii) the System Reliability Network Upgrades as shown in the Cost Summary table.
Note 2: Readiness Deposit #1 (RD1) = ($4,000 * Project Size (MW))
Note 3: Readiness Deposit #2 (RD2) = 10% of cost allocation for required Network Upgrades minus RD1. Readiness Deposit #2 (RD2) can be zero, but may not be a negative number.
Note 4: Readiness Deposit #3 can be zero, but may not be a negative number.
Readiness Deposit #3 Due for Project AH1-452
Readiness Deposit #3 has been calculated for the project based on the Phase II System Impact Study results and is shown in the table below. This Readiness Deposit #3 must be provided at Decision Point II through either a wire transfer or letter of credit per Manual 14H, Section 6.2.
Readiness Deposit #3 Due for AH1-452
For additional detail regarding Readiness Deposit Refunds, reference PJM Manual 14H, section 6.2.1. The Readiness Deposit Letter of Credit template can be found here.
Transmission Owner Scope of Work
This System Impact Study report does not include any physical interconnection scope or cost estimates. AH1-452 is connecting to the non-FERC jurisdictional distribution system and physical interconnection scope and costs will be provided as part of the state-level study process with the applicable entity.
Transmission Owner Analysis
FE performed an analysis of its underlying transmission system <100 kV. New Service Request Project AH1-452 did not contribute to any overloads on the FE transmission <100 kV system. For any distribution impacts, please refer to the studies conducted as part of the FirstEnergy's state-level agreement process for non-FERC jurisdictional projects.
Developer Requirements
The developer is responsible for all design and construction related activities on the developer’s side of the Point of Change in Ownership. FirstEnergy interconnection requirements can be found here.
To the extent that these Applicable Technical Requirements and Standards may conflict with the terms and conditions of the Tariff, the Tariff shall control.
Revenue Metering and SCADA Requirements
The developer will be required to install equipment necessary to provide Revenue Metering (KWH, KVARH) and real time data (KW, KVAR) for their generating Resource. See PJM Manual 01, PJM Manual 14D, and PJM Tariff Part IX, Subpart B, Appendix 2, section 8.Meteorological Data Reporting Requirement
The solar generation facility shall provide the Transmission Provider with site-specific meteorological data including:Transmission Owner Requirements
- Temperature (degrees Fahrenheit)
- Atmospheric Pressure (hectopascals)
- Irradiance
- Forced outage data
The Project Developer will be required to comply with all interconnected Transmission Owner’s revenue metering requirements located at the following link: PJM - Transmission Owner Engineering & Construction Standards.
Summer Peak Analysis
The New Service Request AH1-452 was evaluated as a 19.9 MW (8.35 MW Capacity) injection in the APS area.
AH1-452 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 19.9 MW (19.9 MW under study).
Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.
The following flowgates remain after considering the topology reinforcements required by the cycle.
| Study | Area | Facility Description | Contingency Name | Contingency Type | DC|AC | Final Cycle Loading | Rating (MVA) | Rating Type | MVA to Mitigate | MW Contribution | |
|---|---|---|---|---|---|---|---|---|---|---|---|
| GD2 | AP | 01AL&D6T-01AL 4J 138.0 kV Ckt 1 line | AP_P2-2_WP-138-054A_SRT-A | Bus | AC | 112.95 % | 151.0 | B | 170.55 | 0.98 | |
| GD2 | AP | 01AL&D6T-01AL 4J 138.0 kV Ckt 1 line | AP_P2-3_WP-138-171A_SRT-A | Breaker | AC | 112.85 % | 151.0 | B | 170.4 | 1.04 | |
| GD2 | AP | 01AL&D6T-01AL 4J 138.0 kV Ckt 1 line | ATSI_P2-3_CEI-345-041D_SRT-A | Breaker | AC | 107.4 % | 151.0 | B | 162.18 | 1.0 | |
| GD2 | AP | 01AL&D6T-01AL 4J 138.0 kV Ckt 1 line | ATSI_P2-3_CEI-345-041E_SRT-A | Breaker | AC | 107.4 % | 151.0 | B | 162.18 | 1.0 | |
| GD2 | AP | 01AL&D6T-01AL 4J 138.0 kV Ckt 1 line | AP_P1-3_WP-138-053A_SRT-A | Single | AC | 104.79 % | 151.0 | B | 158.24 | 0.56 | |
| GD2 | AP | 01COLMBGPN-01KISKIV 138.0 kV Ckt 1 line | AP_P2-3_WP-138-177_A_SRT-A | Breaker | AC | 127.29 % | 151.0 | B | 192.2 | 0.85 | |
| GD2 | AP | 01COLMBGPN-01KISKIV 138.0 kV Ckt 1 line | AP_P1-2_WP-138-087_SRT-A | Single | AC | 111.86 % | 151.0 | B | 168.91 | 0.45 | |
| GD2 | AP | 01COLMBGPN-01KISKIV 138.0 kV Ckt 1 line | AP_P1-2_WP-138-103_SRT-A | Single | AC | 102.3 % | 151.0 | B | 154.48 | 0.49 | |
| GD2 | AP | 01GAR RN-01COLMBGPN 138.0 kV Ckt 1 line | AP_P2-3_WP-138-177_A_SRT-A | Breaker | AC | 128.29 % | 151.0 | B | 193.71 | 0.85 | |
| GD2 | AP | 01GAR RN-01COLMBGPN 138.0 kV Ckt 1 line | AP_P1-2_WP-138-087_SRT-A | Single | AC | 112.51 % | 151.0 | B | 169.9 | 0.45 | |
| GD2 | AP | 01GAR RN-01COLMBGPN 138.0 kV Ckt 1 line | AP_P1-2_WP-138-103_SRT-A | Single | AC | 102.6 % | 151.0 | B | 154.93 | 0.49 | |
| GD2 | AP | 01KITTAN-01AL&D6T 138.0 kV Ckt 1 line | AP_P2-2_WP-138-054A_SRT-A | Bus | AC | 111.36 % | 151.0 | B | 168.16 | 0.98 | |
| GD2 | AP | 01KITTAN-01AL&D6T 138.0 kV Ckt 1 line | AP_P2-3_WP-138-171A_SRT-A | Breaker | AC | 111.29 % | 151.0 | B | 168.05 | 1.04 | |
| GD2 | AP | 01KITTAN-01AL&D6T 138.0 kV Ckt 1 line | ATSI_P2-3_CEI-345-041D_SRT-A | Breaker | AC | 105.95 % | 151.0 | B | 159.98 | 1.0 | |
| GD2 | AP | 01KITTAN-01AL&D6T 138.0 kV Ckt 1 line | ATSI_P2-3_CEI-345-041E_SRT-A | Breaker | AC | 105.95 % | 151.0 | B | 159.98 | 1.0 | |
| GD2 | AP | 01KITTAN-01AL&D6T 138.0 kV Ckt 1 line | AP_P1-3_WP-138-053A_SRT-A | Single | AC | 105.83 % | 151.0 | B | 159.81 | 0.56 |
The following flowgates were eliminated after considering the topology reinforcements required by the cycle.
| Study | Area | Facility Description | Contingency Name | Contingency Type | DC|AC | Final Cycle Loading | Rating (MVA) | Rating Type | MVA to Mitigate | MW Contribution | |
|---|---|---|---|---|---|---|---|---|---|---|---|
| GD2 | PENELEC | 26HOMER CT _-26HOMER CT 230.0 kV Ckt S line | PN_P2-3_PN-345-0183-304-012_SRT-A | Breaker | AC | 100.18 % | 827.0 | B | 828.5 | 1.19 | |
| GD2 | PENELEC | 26HOMER CT _-26HOMER CT 230.0 kV Ckt S line | PN_P2-3_PN-345-0183-304_SRT-A | Breaker | AC | 100.18 % | 827.0 | B | 828.5 | 1.19 | |
| GD2 | PENELEC | 26HOMER CY-26HOMER CT _ 345.0/230.0 kV Ckt S transformer | PN_P2-3_PN-345-0183-304-012_SRT-A | Breaker | AC | 100.15 % | 827.0 | B | 828.23 | 1.19 | |
| GD2 | PENELEC | 26HOMER CY-26HOMER CT _ 345.0/230.0 kV Ckt S transformer | PN_P2-3_PN-345-0183-304_SRT-A | Breaker | AC | 100.15 % | 827.0 | B | 828.23 | 1.19 |
Winter Peak Analysis
The New Service Request AH1-452 was evaluated as a 19.9 MW (8.35 MW Capacity) injection in the APS area.
AH1-452 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 19.9 MW (19.9 MW under study).
Note: The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for single or N-1 contingencies and multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.
The following flowgates remain after considering the topology reinforcements required by the cycle.
(No impacts were found for this analysis)
The following flowgates were eliminated after considering the topology reinforcements required by the cycle.
(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)
Light Load Analysis
The New Service Request AH1-452 was evaluated as a 19.9 MW injection
AH1-452 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 19.9 MW (19.9 MW under study).
Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.
The following flowgates remain after considering the topology reinforcements required by the cycle.
| Study | Area | Facility Description | Contingency Name | Contingency Type | DC|AC | Final Cycle Loading | Rating (MVA) | Rating Type | MVA to Mitigate | MW Contribution | |
|---|---|---|---|---|---|---|---|---|---|---|---|
| GD2 | PENELEC | 26HOMER CT _-26HOMER CT 230.0 kV Ckt S line | PN_P2-3_PN-230-0183-210_SRT-A | Breaker | AC | 116.4 % | 824.0 | B | 959.11 | 0.77 | |
| GD2 | PENELEC | 26HOMER CT _-26HOMER CT 230.0 kV Ckt S line | PN_P2-2_PN-230-001T_SRT-A | Bus | AC | 116.4 % | 824.0 | B | 959.11 | 0.77 | |
| GD2 | PENELEC | 26HOMER CT _-26HOMER CT 230.0 kV Ckt S line | PN_P2-3_PN-345-0183-304_SRT-A | Breaker | AC | 115.74 % | 824.0 | B | 953.68 | 0.84 | |
| GD2 | PENELEC | 26HOMER CT _-26HOMER CT 230.0 kV Ckt S line | PN_P2-3_PN-345-0183-304-012_SRT-A | Breaker | AC | 115.74 % | 824.0 | B | 953.68 | 0.84 | |
| GD2 | PENELEC | 26HOMER CT _-26HOMER CT 230.0 kV Ckt S line | Base Case | Single | AC | 115.33 % | 647.0 | A | 746.2 | 0.61 | |
| GD2 | PENELEC | 26HOMER CT _-26HOMER CT 230.0 kV Ckt S line | PN_P2-2_PN-345-001T-DRT-001_SRT-A | Bus | AC | 115.29 % | 824.0 | B | 950.01 | 0.77 | |
| GD2 | PENELEC | 26HOMER CT _-26HOMER CT 230.0 kV Ckt S line | PN_P2-2_PN-345-001T_SRT-A | Bus | AC | 115.29 % | 824.0 | B | 950.01 | 0.77 | |
| GD2 | PENELEC | 26HOMER CT _-26HOMER CT 230.0 kV Ckt S line | PN_P2-3_PN-230-0183-207_SRT-A | Breaker | AC | 114.46 % | 824.0 | B | 943.15 | 0.77 | |
| GD2 | PENELEC | 26HOMER CT _-26HOMER CT 230.0 kV Ckt S line | PN_P1-3_DRT-230-003-DRT_SRT-SL | Single | AC | 114.26 % | 824.0 | B | 941.52 | 0.77 | |
| GD2 | PENELEC | 26HOMER CT _-26HOMER CT 230.0 kV Ckt S line | PN_P2-3_PN-230-9A_SRT-A | Breaker | AC | 113.58 % | 824.0 | B | 935.91 | 0.75 | |
| GD2 | PENELEC | 26HOMER CT _-26HOMER CT 230.0 kV Ckt S line | PN_P2-3_PN-345-0183-307-DRT-010_SRT-A | Breaker | AC | 113.33 % | 824.0 | B | 933.84 | 0.85 | |
| GD2 | PENELEC | 26HOMER CY-26HOMER CT _ 345.0/230.0 kV Ckt S transformer | PN_P2-3_PN-230-0183-210_SRT-A | Breaker | AC | 116.25 % | 824.0 | B | 957.94 | 0.77 | |
| GD2 | PENELEC | 26HOMER CY-26HOMER CT _ 345.0/230.0 kV Ckt S transformer | PN_P2-2_PN-230-001T_SRT-A | Bus | AC | 116.25 % | 824.0 | B | 957.94 | 0.77 | |
| GD2 | PENELEC | 26HOMER CY-26HOMER CT _ 345.0/230.0 kV Ckt S transformer | PN_P2-3_PN-345-0183-304_SRT-A | Breaker | AC | 115.64 % | 824.0 | B | 952.84 | 0.84 | |
| GD2 | PENELEC | 26HOMER CY-26HOMER CT _ 345.0/230.0 kV Ckt S transformer | PN_P2-3_PN-345-0183-304-012_SRT-A | Breaker | AC | 115.64 % | 824.0 | B | 952.84 | 0.84 | |
| GD2 | PENELEC | 26HOMER CY-26HOMER CT _ 345.0/230.0 kV Ckt S transformer | Base Case | Single | AC | 115.28 % | 647.0 | A | 745.89 | 0.61 | |
| GD2 | PENELEC | 26HOMER CY-26HOMER CT _ 345.0/230.0 kV Ckt S transformer | PN_P2-2_PN-345-001T_SRT-A | Bus | AC | 115.18 % | 824.0 | B | 949.12 | 0.77 | |
| GD2 | PENELEC | 26HOMER CY-26HOMER CT _ 345.0/230.0 kV Ckt S transformer | PN_P2-2_PN-345-001T-DRT-001_SRT-A | Bus | AC | 115.18 % | 824.0 | B | 949.12 | 0.77 | |
| GD2 | PENELEC | 26HOMER CY-26HOMER CT _ 345.0/230.0 kV Ckt S transformer | PN_P2-3_PN-230-0183-207_SRT-A | Breaker | AC | 114.34 % | 824.0 | B | 942.12 | 0.77 | |
| GD2 | PENELEC | 26HOMER CY-26HOMER CT _ 345.0/230.0 kV Ckt S transformer | PN_P1-3_DRT-230-003-DRT_SRT-SL | Single | AC | 114.15 % | 824.0 | B | 940.63 | 0.77 | |
| GD2 | PENELEC | 26HOMER CY-26HOMER CT _ 345.0/230.0 kV Ckt S transformer | PN_P2-3_PN-230-9A_SRT-A | Breaker | AC | 113.45 % | 824.0 | B | 934.82 | 0.75 | |
| GD2 | PENELEC | 26HOMER CY-26HOMER CT _ 345.0/230.0 kV Ckt S transformer | PN_P2-3_PN-345-0183-308_SRT-A | Breaker | AC | 113.24 % | 824.0 | B | 933.07 | 0.85 |
The following flowgates were eliminated after considering the topology reinforcements required by the cycle.
| Study | Area | Facility Description | Contingency Name | Contingency Type | DC|AC | Final Cycle Loading | Rating (MVA) | Rating Type | MVA to Mitigate | MW Contribution | |
|---|---|---|---|---|---|---|---|---|---|---|---|
| GD2 | PENELEC | 26HOMER CT _-26HOMER CT 230.0 kV Ckt S line | AP_P1-2_WP-500-303T_SRT-A | Single | AC | 101.54 % | 824.0 | B | 836.72 | 0.78 | |
| GD2 | PENELEC | 26HOMER CT _-26HOMER CT 230.0 kV Ckt S line | PN_P2-2_PN-345-1185-2_SRT-A | Bus | AC | 100.48 % | 824.0 | B | 827.92 | 0.61 | |
| GD2 | PENELEC | 26HOMER CY-26HOMER CT _ 345.0/230.0 kV Ckt S transformer | AP_P1-2_WP-500-303T_SRT-A | Single | AC | 101.6 % | 824.0 | B | 837.17 | 0.78 | |
| GD2 | PENELEC | 26HOMER CY-26HOMER CT _ 345.0/230.0 kV Ckt S transformer | PN_P2-2_PN-345-1185-2_SRT-A | Bus | AC | 100.58 % | 824.0 | B | 828.75 | 0.61 |
Short Circuit Analysis
Analysis Complete - No Issues
Based on PJM’s TC2 Phase II Short Circuit Analysis, this project did not contribute >1% fault duty to any previously identified overdutied breakers, nor did it cause any new overdutied breakers.
Please note that in TC2 Phase III, PJM will perform additional analysis including the evaluation of impacts from topology upgrades which may have potential effects on breaker duties not seen in the Phase II analysis.
Stability Analysis
Not Required
PJM has reviewed this project submission and determined that a stability study is not required due to connection to a non-BES facility.
Reactive Power Analysis
Not Required
Reactive Power Analysis was not performed. This project is responsible for meeting all applicable power factor requirements based on the project Agreements per PJM’s Tariff, Part IX, Subpart B, App. 2, section 4.6.1.
Steady-State Voltage Analysis
Not Required
A steady state voltage analysis is evaluated on a project-by-project basis and depends on specific project parameters. For this project, a steady state voltage analysis is not required per PJM's Manual 14H, Section 4.5.2.
New Service Request Dependencies
The New Service Requests below are listed in one or more dispatch for the overloads identified in this report. These projects contribute to the loading of the overloaded facilities identified in this report. The percent overload of a facility and cost allocation you may have towards a particular reinforcement could vary depending on the action of other projects. The status of each project at the time of the analysis is presented in the table. This list may change as other projects withdraw or modify their requests. This table is valid for load flow analyses only.
| New Service Requests Dependencies | ||
|---|---|---|
| Project ID | Project Name | Status |
| AE2-001 | Nittany-Zion 46 kV | Suspended |
| AE2-074 | Potter 46 kV | Under Construction |
| AE2-113 | Farmers Valley-Ridgeway 115 kV | Under Construction |
| AE2-126 | Dubois-Curwensville 34.5 kV | In Service |
| AE2-139 | East Towanda-Grover 230 kV | Engineering & Procurement |
| AE2-224 | Bear Rock-Johnstown 230 kV | In Service |
| AE2-248 | Fillmore-Thompson Farm 46 kV | Suspended |
| AE2-262 | Moshannon-Milesburg 230 kV | Engineering & Procurement |
| AE2-263 | Moshannon-Milesburg 230 kV II | Engineering & Procurement |
| AE2-316 | Brookville-Squab Hollow 138 kV | Under Construction |
| AE2-344 | Edinboro South-Venango Junction 115 kV | Withdrawn |
| AF1-006 | Fairview East 34.5 kV | In Service |
| AF1-039 | Listonburg-Highpoint 24.9 kV | In Service |
| AF1-094 | Union City-Cambridge Springs 34.5 kV | Engineering & Procurement |
| AF1-098 | Four Mile Jct-Corry East 115 kV | Suspended |
| AF1-140 | Claysburg 23 kV | Engineering & Procurement |
| AF1-153 | Motion-Ridgeway 46 kV | Suspended |
| AF1-167 | West Freedom-C&K Coal 25 kV | Suspended |
| AF1-272 | Lucerne 115 kV | Engineering & Procurement |
| AF1-287 | Edinboro South 34.5 kV II | Withdrawn |
| AF1-302 | Brookville-Squab Hollow 138 kV | Under Construction |
| AF2-010 | Union City-Titusville 115 kV | Withdrawn |
| AF2-039 | Shawville-Clearfield 34.5 kV | Under Construction |
| AF2-088 | Shawville-Clearfield 34.5 kV II | Under Construction |
| AF2-130 | Cobalt Corners 34.5 kV | In Service |
| AF2-165 | Clark Summit-Emlenton 34.5 kV | In Service |
| AF2-238 | Mansfield-South Troy 34.5 kV | Engineering & Procurement |
| AF2-294 | Thompson 34.5 kV | Suspended |
| AF2-296 | Madera 34.5 kV | Engineering & Procurement |
| AG1-040 | Morgan Street-Mount Hope 34.5 kV | Engineering & Procurement |
| AG1-100 | Venango-Saegertown 34.5 kV | Engineering & Procurement |
| AG1-140 | Union City 34.5 kV | Suspended |
| AG1-193 | Utica Junction 34.5 kV | Withdrawn |
| AG1-197 | Morgan Street-Cochranton 34.5 kV | Suspended |
| AG1-198 | Union City 34.5 kV | In Service |
| AG1-253 | Erie East-Union City 34.5 kV | Suspended |
| AG1-281 | Claysburg-HCR Tap 46 kV | Engineering & Procurement |
| AG1-548 | Erie South-Union City 115 kV | Engineering & Procurement |
| AG2-176 | Geneva 115 kV | Active |
| AG2-200 | North Warren - Russell 34.5 kV | Active |
| AG2-356 | South Troy - Canton 34.5 kV | Active |
| AG2-420 | Eclipse #2 34.5 kV | Active |
| AG2-429 | Burma - Armstrong 138 kV | Active |
| AH1-667 | Philipsburg-Shawville 34.5 kV | Active |
| Y1-033 | Penn Mar-Rock Wood 115kV | In Service |
Affected System - PJM Identified Violations
As part of PJM's analysis, per Tariff Part VII.G.336 & Manual 14H, Section 13, PJM evaluated the potential impacts on tie line facilities between PJM and an affected system entity, which were identified per PJM planning analysis criteria. This upgrade may be required on the affected system portion of the tie line along with cost allocation of such upgrade if applicable, in coordination with the affected system. Depending on the affected system, this project may not be contingent on upgrade based on PJM planning analysis criteria, but may be contingent on this upgrade based on the Affected System Operator's planning criteria, provided in the Affected Systems Study Section, herein.
Affected System - Non-PJM Identified Violations
In accordance with PJM Tariff Part VII, Subpart D, section 310.A and as outlined in PJM Manual 14H, Sections 4.5 and 13, in Phase II of the Cycle, PJM provides the Affected System Operator any updates on the PJM projects that require an Affected Systems Study based on their response at DP1. New Service Requests that require an Affected Systems Study are required to enter into an Affected Systems Study Agreement with the Affected System Operator, as applicable, prior to the close of DP2 or they will be withdrawn from the Cycle.
If the Project Developer already entered into the necessary agreement and the results are available, PJM will supply them in the Phase II SIS report. See below for the status of any required Affected Systems Study. A status of “Pending” means that the study is not yet completed by the Affected System Operator. If your project requires an Affected Systems Study and your results are not provided for Phase II SIS, PJM anticipates providing them in the Phase III SIS per Tariff Part VII.D.312.
System Reinforcements
No cost allocated system reinforcements were identified for this project in the Phase II System Impact Study load flow analysis.
Shown below are the details of the cost allocated, contingent, eliminated, topology and potential aggregate contributor reinforcements for this project. Please refer to the System Reinforcement table above and the information below for more detail.
System Reinforcement: n7166.1
- Type
- Load Flow
- TO
- APS
- RTEP ID / TO ID
- n7166.1
- Title
- Replace 4/0 CU line exit at All Dam 6 Tap.
- Description
- Replace 4/0 CU line exit at All Dam 6 Tap on the 01AL&D6T - 01AL 4J
- Total Cost ($USD)
- $922,908
- Discounted Total Cost ($USD)
- $922,908
- Allocated Cost ($USD)
- $0
- Time Estimate
- 18 Months
Potential Aggregate Contributor Note: Based on PJM cost allocation criteria, AH1-452 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AH1-452 could receive cost allocation. Although AH1-452 may not presently have cost responsibility for this upgrade, AH1-452 is a potential Aggregate Pool Contributor.
| Facility | Contingency | |||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 01AL 4J-01AL&D6T 138.0 kV Ckt 1 line | (Any) |
|
System Reinforcement: n7166.2
- Type
- Load Flow
- TO
- APS
- RTEP ID / TO ID
- n7166.2
- Title
- Reconductor 7.6 miles of 4/0 CU from All Dam 6 Tap to structure 84 (66 spans). Also upgrade terminal end equipment.
- Description
- Total Cost ($USD)
- $26,284,067
- Discounted Total Cost ($USD)
- $26,284,067
- Allocated Cost ($USD)
- $0
- Time Estimate
- 23 Months
Potential Aggregate Contributor Note: Based on PJM cost allocation criteria, AH1-452 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AH1-452 could receive cost allocation. Although AH1-452 may not presently have cost responsibility for this upgrade, AH1-452 is a potential Aggregate Pool Contributor.
| Facility | Contingency | |||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 01AL 4J-01AL&D6T 138.0 kV Ckt 1 line | (Any) |
|
System Reinforcement: n7165.1
- Type
- Load Flow
- TO
- APS
- RTEP ID / TO ID
- n7165.1
- Title
- Replace T-line drops at All Dam 6
- Description
- Replace (2) T-line drops at All Dam 6
- Total Cost ($USD)
- $427,516
- Discounted Total Cost ($USD)
- $427,516
- Allocated Cost ($USD)
- $0
- Time Estimate
- 12 Months
Potential Aggregate Contributor Note: Based on PJM cost allocation criteria, AH1-452 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AH1-452 could receive cost allocation. Although AH1-452 may not presently have cost responsibility for this upgrade, AH1-452 is a potential Aggregate Pool Contributor.
| Facility | Contingency | |||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 01AL&D6T-01KITTAN 138.0 kV Ckt 1 line | (Any) |
|
System Reinforcement: n7165.2
- Type
- Load Flow
- TO
- APS
- RTEP ID / TO ID
- n7165.2
- Title
- Reconductor All Dam 6 - Kittanning 138kV line. Also upgrade terminal end equipment.
- Description
- Reconductor (Possible Rebuild) ~6 miles of the All Dam 6 - Kittanning 138kV line
- Total Cost ($USD)
- $21,034,523
- Discounted Total Cost ($USD)
- $21,034,523
- Allocated Cost ($USD)
- $0
- Time Estimate
- 22 Months
Potential Aggregate Contributor Note: Based on PJM cost allocation criteria, AH1-452 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AH1-452 could receive cost allocation. Although AH1-452 may not presently have cost responsibility for this upgrade, AH1-452 is a potential Aggregate Pool Contributor.
| Facility | Contingency | |||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 01AL&D6T-01KITTAN 138.0 kV Ckt 1 line | (Any) |
|
System Reinforcement: n6183
- Type
- Load Flow
- TO
- APS
- RTEP ID / TO ID
- n6183
- Title
- Rebuild 10.4 miles of 4/0 CU from Columbia Big Pine - Garretts Run Jct 138 kV (99 spans). Also upgrade terminal end equipment.
- Description
- Rebuild 10.4 miles of 4/0 CU from Columbia Big Pine - Garretts Run Jct 138 kV (99 spans) using 954 kcmil 45/7 STR ACSR.
- Total Cost ($USD)
- $36,946,687
- Discounted Total Cost ($USD)
- $36,946,687
- Allocated Cost ($USD)
- $0
- Time Estimate
- 26 Months
Potential Aggregate Contributor Note: Based on PJM cost allocation criteria, AH1-452 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AH1-452 could receive cost allocation. Although AH1-452 may not presently have cost responsibility for this upgrade, AH1-452 is a potential Aggregate Pool Contributor.
| Facility | Contingency | ||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 01COLMBGPN-01GAR RN 138.0 kV Ckt 1 line | (Any) |
|
System Reinforcement: n7171.1
- Type
- Load Flow
- TO
- APS
- RTEP ID / TO ID
- n7171.1
- Title
- Rebuild approximately 4.0 miles of 4/0 CU on the Kiski Valley to Columbia Big Pine 138kV line. Also upgrade terminal end equipment.
- Description
- Rebuild approximately 4.0 miles of 4/0 CU on the Kiski Valley to Columbia Big Pine 138kV line using 954 KCMIL 45/7 STR ACSR.
- Total Cost ($USD)
- $15,258,720
- Discounted Total Cost ($USD)
- $15,258,720
- Allocated Cost ($USD)
- $0
- Time Estimate
- 20 Months
Potential Aggregate Contributor Note: Based on PJM cost allocation criteria, AH1-452 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AH1-452 could receive cost allocation. Although AH1-452 may not presently have cost responsibility for this upgrade, AH1-452 is a potential Aggregate Pool Contributor.
| Facility | Contingency | |||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 01KISKIV-01COLMBGPN 138.0 kV Ckt 1 line | (Any) |
|
System Reinforcement: s3335.1
- Type
- Load Flow
- TO
- PENELEC
- RTEP ID / TO ID
- s3335.1 / PN-2024-007
- Title
- Replace Homer City South 345/230-23kV Transformer
- Description
- Replace the South 345/230-23kV Transformer and associated equipment with: - One(1) 345/230kV Transformer with three single-phase units - Replace 345 kV circuit switcher, disconnects, circuit breaker, and substation conductor Transformer Ratings: - Before Proposed Solution: 649/836/793/984 MVA (SN/SLTE/WN/WLTE) - After Proposed Solution: 913/1147/1201/1376 MVA (SN/SLTE/WN/WLTE)
- Cost Information
- Time Estimate
- Jun 01 2027
Not Contingent Note: AH1-452 contributes to the loading of an overloaded facility that is being mitigated by a planned supplemental project. AH1-452 is not contingent on this supplemental project as it does not meet the criteria for being a contingent facility or for having cost allocation for the upgrade.
| Facility | Contingency | |||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 26HOMER CT-26HOMER CT _ 230.0 kV Ckt S line | (Any) |
| ||||||||||||||||
| 26HOMER CY-26HOMER CT _ 345.0/230.0 kV Ckt S transformer | (Any) |
|