AH1-564 Phase II System Impact Study Report

v1.00 released 2026-06-03 17:43

Rockford II 138 kV

150.0 MW Capacity / 150.0 MW Energy

Introduction

This Phase II System Impact Study (SIS) Report has been prepared in accordance with the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 310 for New Service Requests (projects) in Transition Cycle 2 (TC2). The Project Developer/Eligible Customer (developer) is Rockford Generation, LLC, and the Transmission Provider (TP) is PJM Interconnection, LLC (PJM). The interconnected Transmission Owner (TO) is Commonwealth Edison Company.

Preface

The Phase II System Impact Study is conducted on an aggregate basis within a New Services Request’s Cycle, and results are provided in both (i) a single Cycle summary format and (ii) an individual project-level basis. The Phase II System Impact Study Results (for both the summary and individual reports) will be publicly available on PJM’s website. Project Developers must obtain the results from the website.

In accordance with PJM Manual 14H, section 4.5, PJM takes the following actions during the Phase II System Impact Study:

  1. PJM will retool load flow results from the Phase I System Impact Study (summer peak, winter peak and light load) based on decisions made by Project Developers or Eligible Customers during Decision Point I.
  2. PJM will conduct any required voltage analyses.
  3. PJM will perform short circuit and stability analyses as required.
  4. PJM will coordinate with the Affected System to confirm which projects in the PJM Cycle will require Affected System studies. If the Affected System Operator indicates that an Affected System study is required, PJM will:
    1. Notify the Project Developer or Eligible Customer of the need for an Affected System study and the requirement to execute an Affected System study agreement with the impacted Affected System Operator, and;
    2. Include the results of the Affected System Operator’s Affected System Study in the Phase II System Impact Study results, if applicable and available.
  5. The Phase II System Impact Study Results will be publicly available on PJM’s website. Project Developers and Eligible Customers must obtain the results from the website.

The Transmission Owner takes the following actions during the Phase II System Impact Study:

  1. Verify Interconnection Facilities and Network Upgrades required to accommodate the New Service Request.
  2. Perform a Facilities Study. The Facilities Study in Phase II System Impact Study phase will be for the physical Interconnection Facilities. The Facilities Study requirements are outlined in Attachment C of this manual. The study will be conducted pursuant to Tariff, Part VII, Subpart D, section 307(A)(7) and Tariff, Part VIII, Subpart C, section 404(A)(7).

Decision Point II Requirements

At the close of Phase II System Impact Study, PJM will initiate Decision Point II (DP2). During DP2, the Project Developer will have 30 days to decide whether to proceed with their project. If the Project Developer elects to proceed, they should provide the elements defined in the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 311.A. Additional information on these elements is available in PJM Manual 14H sections 4.6, 6, and 7.

Allowable project modifications at Decision Point II are defined in PJM Open Access Transmission Tariff, Part VII, Subpart D, section 311.B. Additional information regarding allowable project modifications can be found in PJM Manual 14H, section 9.8.

Adverse Test Eligibility

This New Service Request meets the Adverse Study Impact Criteria and has the option to either move forward in the Cycle process or withdraw at DP2 with Readiness Deposits refunded. See Readiness Deposit calculation below.

This section details whether a Project Developer or Eligible Customer qualifies for the Adverse Study Impact clause outlined in the PJM OATT, Part VII, Subpart D, section 311.B and Manual 14H, section 6.2.2. In order to qualify for an Adverse Study Impact at Decision Point II, the Network Upgrade cost from Phase I to Phase II must:

  1. Increase overall by 25% or more
  2. Increases by more than $10,000 per MW (Includes Costs identified in Affected System studies)

If a New Service Request meets the criteria above and chooses to withdraw the request, PJM will refund the cumulative Readiness Deposit amounts paid at the Application Phase and at Decision Point I (RD1 and RD2, respectively).

The below calculations show the computation of this New Service Request's Adverse Study Impact

DP2 Adverse Eligibility = DP2 Adverse Cost Alloc DP1 Adverse Cost Alloc > 1.25 AND ( DP2 Adverse Cost Alloc - DP1 Adverse Cost Alloc ) Project Size > $10,000 per MW
DP2 Adverse Eligibility = $62,727,856 $500,000 = 125.46 AND ( $62,727,856 - $500,000 ) 150.0 = $414,852 per MW

General

The Project Developer has proposed an uprate to a planned/existing Natural Gas facility located in the Commonwealth Edison Company zone — Winnebago County, Illinois. This project is an increase to the developer’s AC1-114/AC2-116 project(s), which will share the same Point of Interconnection. The AH1-564 project is a 150.0 MW uprate (150.0 MW Capacity uprate) to the previous project(s). The total installed facilities will have a capability of 330.0 MW with 177.0 MW of this output being recognized by PJM as Capacity.

Project Information
New Service Request Number:
AH1-564
Project Name:
Rockford II 138 kV
Project Developer Name:
Rockford Generation, LLC
State:
Illinois
County:
Winnebago
Transmission Owner:
Commonwealth Edison Company
MFO:
330.0
MWE:
150.0
MWC:
150.0
Battery Storage Specification:
600.0 MWh, 4.0-hr class
Grid Charging:
Yes
Fuel Type:
Storage
Basecase Study Year:
2028

Physical Interconnection Facility Study

Report Available

The transmission owner has completed the Physical Interconnection Facilities Study. This report is available for download.

Point of Interconnection

AH1-564 will interconnect on the Commonwealth Edison Company transmission system at the Rockford II 138 kV Substation.

Cost Summary

The table below shows a summary of the total cost estimates for this New Service Request project. In Phase II SIS, the interconnected Transmission Owner has performed a facilities study for both the Transmission Owner Interconnection Facilities (TOIF) and Physical Interconnection Network Upgrades. The System Reliability Network Upgrade shown in the table are planning level cost estimates which are subject to change as a result of a facility study performed by the TO during Phase III System Impact Study.

Based on the Phase II SIS results, the AH1-564 project has the following allocation of costs for interconnection. The cost contribution towards Readiness Deposit #3 are also shown below.

Cost Summary
DescriptionCost Allocated to AH1-564Cost Subject to Readiness*Cost Subject to Adverse
Transmission Owner Interconnection Facilities (TOIF)$0$0$0
Other Scope$0$0$0
Option To Build Oversight$0$0$0
Physical Interconnection Network Upgrades
Stand Alone Network Upgrades$0$0$0
Network Upgrades$600,425$600,425$600,425
System Reliability Network Upgrades
Steady State Thermal & Voltage$62,091,817$62,091,817$62,091,817
Transient Stability$0$0$0
Short Circuit$0$0$0
Transmission Owner Analysis
SubRegional$0$0$0
Distribution$0$0$0
Affected System Reinforcements
AFS - PJM Violations$0$0$0
AFS - Non-PJM Violations$35,614$0$35,614
Total$62,727,856$62,692,242$62,727,856

* Contributes to calculation for Readiness Deposit #3 (RD3). See Readiness Deposit section of report for additional detail.

Definitions

Transmission Owner Interconnection Facilities: Facilities that are owned, controlled, operated and maintained by the Transmission Owner on the Transmission Owner’s side of the Point of Change of Ownership to the Point of Interconnection, including any modifications, additions or upgrades made to such facilities and equipment, that are necessary to physically and electrically interconnect the Generating Facility with the Transmission System or interconnected distribution facilities.

Stand Alone Network Upgrades: Network Upgrades, which are not part of an Affected System, which a Project Developer may construct without affecting day-to-day operations (e.g. taking a transmission outage) of the Transmission System during their construction.

Network Upgrades: Modifications or additions to transmission-related facilities that are integrated with and support the Transmission Provider’s overall Transmission System for the general benefit of all users of such Transmission System. Network Upgrades have no impact or potential impact on the Transmission System until the final tie-in is complete.

Notes

Note 1: PJM Open Access Transmission Tariff (OATT), Part VII, Subpart D, section 307.5 outlines cost allocation rules. The rules are further clarified in PJM Manual 14H, section 4.2.6. PJM shall identify the New Service Requests in the Cycle contributing to the need for the required Network Upgrades within the Cycle. All New Service Requests that contribute to the need for a Network Upgrade will receive cost allocation for that upgrade pursuant to each New Service Request’s contribution to the reliability violation identified on the transmission system in accordance with PJM Manuals.

Note 2: There will be no inter-Cycle cost allocation for Interconnection Facilities or Network Upgrades identified in the System Impact Study costs identified in a Cycle; all such costs shall be allocated to New Service Requests in that Cycle.

Note 3: For Project Developers with System Reinforcements listed: If this project presents cost allocation to a System Reinforcement indicates $0, then please be aware that as changes to the interconnection process occur, such as other projects withdrawing, reducing in size, etc, the cost responsibilities can change and a cost allocation may be assigned to this project. In addition, although this project presents cost allocation to a System Reinforcement is presently $0, this project may need this system reinforcement completed to be deliverable to the PJM system. If this project desires to come into service prior to completion of the system reinforcement, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the system reinforcement is complete.

Note 4: Please see the ‘Affected Systems Studies’ section of this Phase II SIS report for details on your project’s need for an Affected Systems Study. If your project requires an Affected Systems Study, the Affected Systems impacts may not be available from the Affected System Operator at the time of the PJM Phase II SIS. Therefore, the cost in this section would not reflect any required upgrades by the Affected System until the study is completed. If your project requires an Affected Systems Study and your results are not provided for Phase II SIS, PJM anticipates providing them in the Phase III SIS per Tariff Part VII.D.312.

Readiness Deposit

Per Tariff Part VII, Subpart D, section 311 (Decision Point II) A.1.b and PJM Manual 14H, section 6.2, Readiness Deposit #3 (RD3) are funds committed by the Project Developer or Eligible Customer based upon the applicable contribution to Network Upgrades as defined below. Readiness Deposits are not used to fund studies nor to offset Security.

During Decision Point II (DP2), the Project Developer or Eligible Customer is required to submit Readiness Deposit #3, which is calculated as 20% of cost allocation for required Phase II Network Upgrades minus Readiness Deposit #1 & Readiness Deposit #2.

Note 1: “Network Upgrades” referred to in the calculation include both (i) the Physical Interconnection Network Upgrades and (ii) the System Reliability Network Upgrades as shown in the Cost Summary table.

Note 2: Readiness Deposit #1 (RD1) = ($4,000 * Project Size (MW))

Note 3: Readiness Deposit #2 (RD2) = 10% of cost allocation for required Network Upgrades minus RD1. Readiness Deposit #2 (RD2) can be zero, but may not be a negative number.

Note 4: Readiness Deposit #3 can be zero, but may not be a negative number.

Readiness Deposit #3 Due for Project AH1-564

Readiness Deposit #3 has been calculated for the project based on the Phase II System Impact Study results and is shown in the table below. This Readiness Deposit #3 must be provided at Decision Point II through either a wire transfer or letter of credit per Manual 14H, Section 6.2.

Readiness Deposit #3 Due for AH1-564
Project ID: AH1-564
20% of cost allocation for Phase II Network Upgrades:(A) $12,538,448
Sum of Readiness Deposit #1 & Readiness Deposit #2 Received:(B) $600,000
Readiness Deposit #3 (RD3) due at DP2:(A) - (B) = $11,938,448
Note: Failure to provide an acceptable form of Readiness Deposit #3 by the end of Decision Point II will result in withdrawal and termination of the New Service Request.

For additional detail regarding Readiness Deposit Refunds, reference PJM Manual 14H, section 6.2.1. The Readiness Deposit Letter of Credit template can be found here.

Transmission Owner Scope of Work

If your project relies on Transmission Owner Interconnection Facilities, Stand Alone Network Upgrades, and/or Network Upgrades that will be constructed by another New Service Request and the other New Service Request withdraws, the scope and costs will be allocated to your project.

The total preliminary cost estimate for the Transmission Owner scope of work (including TOIF and Physical Interconnection Network Upgrades) is given in the table below. These costs do not include CIAC Tax Gross-up.

Transmission Owner Build Option
Network Upgrades
RTEP IDDescriptionDirectIndirectTotal Cost ($USD)Allocated Cost ($USD)
LaborMaterialsLaborMaterials
(Pending)

TSS194 138 KV UPGRADES TO ACCOMODATE PROJECT AH1-564

$396,417$66,534$134,096$3,378$600,425$600,425
Developer Build Option

(No Developer Build Option for this project.)

Build Option Price Comparison
Build OptionTotal CostAllocated Cost
Transmission Owner Build Option$600,425$600,425
Developer Build Option(No Developer Build Option)

Based on the scope of work for the Interconnection Facilities, it is expected to take a range of 1 to 30 month(s) after the signing of a Generator Interconnection Agreement (as this is a FERC connection) and construction kickoff call to complete the installation of the physical connection work. This assumes that there will be no environmental issues with any of the new properties associated with this project, that there will be no delays in acquiring the necessary permits for implementing the defined interconnection work, and that all system outages will be allowed when requested.

Note that the TO findings were made from a conceptual review of this project. A more detailed review of the connection facilities and their cost will be identified in a future study phase. Further note that the cost estimate data provided should be considered high level estimates since it was produced without a detailed engineering review. The Project Developer will be responsible for the actual cost of construction. TO herein reserves the right to return to any issues in this document and, upon appropriate justification, request additional monies to complete any reinforcements to the transmission systems.

Remote Terminal Work: During Phase II of the PJM interconnection process, TO’s System Protection Engineering Department will review transmission line protection as well as anti-islanding required to accommodate the new generation and interconnection substation. System Protection Engineering will determine the minimal acceptable protection requirements to reliably interconnect the proposed generating facility with the transmission system. The review is based on maintaining system reliability by reviewing TO’s protection requirements with the known transmission system configuration which includes generating facilities in the area. This review may determine that transmission line protection and communication upgrades are required at remote substations.

Notes on Cost Estimate:

  1. These estimates are order-of-magnitude estimates of the costs that ComEd would bill to the Project Developer for this interconnection. These estimates are based on a one-line electrical diagram of the project and the information provided by the Project Developer.
  2. There were no site visits performed for these estimates. There may be costs related to specific site related issues that are not identified in these estimates. The site reviews will be performed during the Facilities Study or during detailed engineering.
  3. These estimates are not a guarantee of the maximum amount payable by the Project Developer and the actual costs of ComEd's work may differ significantly from these estimates. The Project Developer will be responsible for paying actual costs of ComEd's work in accordance with the PJM Open Access Transmission Tariff.
  4. The Project Developer is responsible for all engineering, procurement, testing and construction of all equipment on the Project Developer’s side of the Point of Change in Ownership.

 

 

Transmission Owner Analysis

No Transmission Owner impacts identified.

Developer Requirements

The developer is responsible for all design and construction related activities on the developer’s side of the Point of Change in Ownership. ComEd interconnection requirements can be found here.

To the extent that these Applicable Technical Requirements and Standards may conflict with the terms and conditions of the Tariff, the Tariff shall control.

Revenue Metering and SCADA Requirements

PJM Requirements
The developer will be required to install equipment necessary to provide Revenue Metering (KWH, KVARH) and real time data (KW, KVAR) for their generating Resource. See PJM Manual 01, PJM Manual 14D, and PJM Tariff Part IX, Subpart B, Appendix 2, section 8.
Transmission Owner Requirements
The Project Developer will be required to comply with all interconnected Transmission Owner’s revenue metering requirements located at the following link: PJM - Transmission Owner Engineering & Construction Standards.

Summer Peak Analysis

The New Service Request AH1-564 was evaluated as a 150.0 MW (150.0 MW Capacity) injection in the ComEd area.

AH1-564 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 330.0 MW (150.0 MW under study).

Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.

The following flowgates remain after considering the topology reinforcements required by the cycle.

StudyAreaFacility DescriptionContingency NameContingency TypeDC|ACFinal Cycle LoadingRating (MVA)Rating TypeMVA to MitigateMW ContributionDetails
GD2CE
AF2-349 TP-SILVER LK; R 345.0 kV Ckt 1 line
COMED_P4_144-45-BT7-8___SRT-A
BreakerAC111.49 %1568.0STE1748.1
36.82
GD2CE
AF2-349 TP-SILVER LK; R 345.0 kV Ckt 1 line
COMED_P4_144-45-BT5-8___SRT-A
BreakerAC111.3 %1568.0STE1745.18
36.4
GD2CE
AF2-349 TP-SILVER LK; R 345.0 kV Ckt 1 line
COMED_P4-6_006-345-BT78___SRT-A
BreakerAC109.88 %1568.0STE1722.95
37.95
GD2CE
AF2-349 TP-SILVER LK; R 345.0 kV Ckt 1 line
COMED_P4_111-45-TR81____SRT-A
BreakerAC102.15 %1568.0STE1601.72
31.15
GD2CE
AF2-349 TP-SILVER LK; R 345.0 kV Ckt 1 line
COMED_P4_111-45-L11124__SRT-A
BreakerAC102.15 %1568.0STE1601.72
31.15
GD2CE
AF2-349 TP-SILVER LK; R 345.0 kV Ckt 1 line
COMED_P2-2_111_EJ-345B__1_SRT-A
BusAC102.15 %1568.0STE1601.72
31.15
GD2CE
AF2-349 TP-SILVER LK; R 345.0 kV Ckt 1 line
COMED_P1-2_345-L0626__B-R_SRT-A
SingleAC102.07 %1568.0STE1600.48
36.77
GD2CE
CHERRY VA; B-AF2-349 TP 345.0 kV Ckt 1 line
COMED_P4_144-45-BT7-8___SRT-A
BreakerAC107.42 %1568.0STE1684.35
36.82
GD2CE
CHERRY VA; B-AF2-349 TP 345.0 kV Ckt 1 line
COMED_P4_144-45-BT5-8___SRT-A
BreakerAC107.28 %1568.0STE1682.12
36.4
GD2CE
CHERRY VA; B-AF2-349 TP 345.0 kV Ckt 1 line
COMED_P4-6_006-345-BT78___SRT-A
BreakerAC105.77 %1568.0STE1658.52
37.95
IPDCE
ROCKFORD ;RP-SABROOKE ; R 138.0 kV Ckt 1 line
Base Case
SingleAC104.25 %310.0A323.16
150.0
GD2CE
ROCKFORD ;RP-SABROOKE ; R 138.0 kV Ckt 1 line
Base Case
SingleAC104.24 %310.0A323.14
150.0

Details for AF2-349 TP-SILVER LK; R 345.0 kV Ckt 1 line l/o COMED_P4_144-45-BT7-8___SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:CE
Facility Description:
AF2-349 TP-SILVER LK; R 345.0 kV Ckt 1 line
Contingency Name:
COMED_P4_144-45-BT7-8___SRT-A
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:111.49 %
Rating:1568.0 MVA
Rating Type:STE
MVA to Mitigate:1748.1
MW Contribution:
36.82
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area:CE
Facility Description:
AF2-349 TP-SILVER LK; R 345.0 kV Ckt 1 line
Contingency Name:
COMED_P4_144-45-BT7-8___SRT-A
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:111.43 %
Rating:1568.0 MVA
Rating Type:STE
MVA to Mitigate:1747.22
MW Contribution:
36.76
Bus #Bus NameTypeMW Contribution
274656BYRON ;1U
50/50
4.815
274657BYRON ;2U
50/50
4.679
274822ROCKFORD ;11
50/50
43.963
274823ROCKFORD ;21
50/50
43.646
274824ROCKFORD ;12
50/50
34.364
274855GSG-6 ;RU
Solar/Wind Harmer
3.013
274856ECOGROVE ;U1
Solar/Wind Harmer
6.106
274760LEE CO EC;1U
Adder
14.092
276602WESTBROOK C
Solar/Wind Harmer
1.734
276603SUBLETTE C
Solar/Wind Harmer
1.213
274850MENDOTA H;RU
Solar/Wind Harmer
2.095
274761LEE CO EC;2U
Adder
14.092
274762LEE CO EC;3U
Adder
14.092
274763LEE CO EC;4U
Adder
13.959
274764LEE CO EC;5U
Adder
14.125
274765LEE CO EC;6U
Adder
14.125
274766LEE CO EC;7U
Adder
13.926
274767LEE CO EC;8U
Adder
13.926
274872LEEDK;1U
Solar/Wind Harmer
5.695
276611AD2-172 GEN
Solar/Wind Harmer
4.632
276612AE2-035 GEN
Solar/Wind Harmer
4.632
276799AD1-013 GEN
Solar/Wind Harmer
1.781
276861AD2-134 GEN
Solar/Wind Harmer
1.457
276863AD2-134 GEN
Solar/Wind Harmer
1.457
274857EASY ROAD;U1
Solar/Wind Harmer
7.256
274858EASY ROAD;U2
Solar/Wind Harmer
7.256
938861AE1-114 GEN
Solar/Wind Harmer
12.192
946321AF1-296 GEN
Solar/Wind Harmer
9.257
946671AF1-331 GEN
Solar/Wind Harmer
0.337
959081AF2-199 GEN
Solar/Wind Harmer
5.107
959091AF2-200 GEN
Solar/Wind Harmer
10.215
960751AF2-366 GEN
Solar/Wind Harmer
2.156
962691AG1-118 GEN
Solar/Wind Harmer
17.965
962781AG1-127 GEN
Solar/Wind Harmer
7.147
970819AG2-516 GEN
Solar/Wind Harmer
23.288
971067AG2-660 GEN
Solar/Wind Harmer
1.188
971171AH1-044 GEN
Solar/Wind Harmer
10.215
971341AH1-150 GEN
Solar/Wind Harmer
10.215
971343AH1-151 GEN
Solar/Wind Harmer
10.215
971411AH1-196 GEN
Solar/Wind Harmer
63.756
971675AH1-338 GEN
Solar/Wind Harmer
14.608
971681AH1-341 GEN
Solar/Wind Harmer
21.445
276157O29GEN1
Solar/Wind Harmer
3.462
276158O29GEN2
Solar/Wind Harmer
4.553
276708O09 GEN2
Solar/Wind Harmer
3.251
276741O09 GEN1
Solar/Wind Harmer
3.251
957471AF2-041 GEN
Solar/Wind Harmer
15.322
965931AG1-462 GEN
Solar/Wind Harmer
21.963
972031AH1-564 GEN
50/50
36.821
972235AH1-702 GEN1
50/50
5.805
972236AH1-702 GEN2
50/50
5.054
972267AH1-718 GEN
Adder
4.513
971087AG2-675 GEN
Solar/Wind Harmer
3.205
990117J1214
External Queue
32.50968551635742
990407J1304
External Queue
8.001517295837402
990512J1326
External Queue
9.45048999786377
990727J1377 G
External Queue
13.989998817443848
991092J1477
External Queue
2.8669803142547607
991777J1629 G
External Queue
9.221789360046387
CBM West 1LTFEXP_CBM-W1->PJM
CBM
45.04
CBM West 2LTFEXP_CBM-W2->PJM
CBM
13.315
CBM South 1LTFEXP_CBM-S1->PJM
CBM
1.914
CBM South 2LTFEXP_CBM-S2->PJM
CBM
0.131
NYPJM->LTFIMP_NY
CLTF
0.245
WECLTFEXP_WEC->PJM
CLTF
0.771
HAMLETPJM->LTFIMP_HAMLET
CLTF
0.01
TVALTFEXP_TVA->PJM
CLTF
0.658
TRIMBLEPJM->LTFIMP_TRIMBLE
CLTF
0.142
MECLTFEXP_MEC->PJM
CLTF
9.276
BlueGrassPJM->LTFIMP_BlueG
CLTF
0.401
LAGNLTFEXP_LAGN->PJM
CLTF
2.57
SIGELTFEXP_SIGE->PJM
CLTF
0.002

Details for AF2-349 TP-SILVER LK; R 345.0 kV Ckt 1 line l/o COMED_P4_144-45-BT5-8___SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:CE
Facility Description:
AF2-349 TP-SILVER LK; R 345.0 kV Ckt 1 line
Contingency Name:
COMED_P4_144-45-BT5-8___SRT-A
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:111.3 %
Rating:1568.0 MVA
Rating Type:STE
MVA to Mitigate:1745.18
MW Contribution:
36.4
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area:CE
Facility Description:
AF2-349 TP-SILVER LK; R 345.0 kV Ckt 1 line
Contingency Name:
COMED_P4_144-45-BT5-8___SRT-A
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:111.24 %
Rating:1568.0 MVA
Rating Type:STE
MVA to Mitigate:1744.3
MW Contribution:
36.34
Bus #Bus NameTypeMW Contribution
274656BYRON ;1U
50/50
4.773
274657BYRON ;2U
50/50
4.638
274822ROCKFORD ;11
50/50
43.459
274823ROCKFORD ;21
50/50
43.146
274824ROCKFORD ;12
50/50
33.97
274855GSG-6 ;RU
Solar/Wind Harmer
3.041
274856ECOGROVE ;U1
Solar/Wind Harmer
6.052
274760LEE CO EC;1U
Adder
14.055
276602WESTBROOK C
Solar/Wind Harmer
1.75
276603SUBLETTE C
Solar/Wind Harmer
1.214
274850MENDOTA H;RU
Solar/Wind Harmer
2.114
274761LEE CO EC;2U
Adder
14.055
274762LEE CO EC;3U
Adder
14.055
274763LEE CO EC;4U
Adder
13.922
274764LEE CO EC;5U
Adder
14.088
274765LEE CO EC;6U
Adder
14.088
274766LEE CO EC;7U
Adder
13.889
274767LEE CO EC;8U
Adder
13.889
274872LEEDK;1U
Solar/Wind Harmer
5.774
276611AD2-172 GEN
Solar/Wind Harmer
4.591
276612AE2-035 GEN
Solar/Wind Harmer
4.591
276799AD1-013 GEN
Solar/Wind Harmer
1.798
276861AD2-134 GEN
Solar/Wind Harmer
1.47
276863AD2-134 GEN
Solar/Wind Harmer
1.47
274857EASY ROAD;U1
Solar/Wind Harmer
7.237
274858EASY ROAD;U2
Solar/Wind Harmer
7.237
938861AE1-114 GEN
Solar/Wind Harmer
12.132
946321AF1-296 GEN
Solar/Wind Harmer
9.281
946671AF1-331 GEN
Solar/Wind Harmer
0.341
959081AF2-199 GEN
Solar/Wind Harmer
5.475
959091AF2-200 GEN
Solar/Wind Harmer
10.951
960751AF2-366 GEN
Solar/Wind Harmer
2.181
962691AG1-118 GEN
Solar/Wind Harmer
18.362
962781AG1-127 GEN
Solar/Wind Harmer
7.228
970819AG2-516 GEN
Solar/Wind Harmer
23.055
971067AG2-660 GEN
Solar/Wind Harmer
1.273
971171AH1-044 GEN
Solar/Wind Harmer
10.951
971341AH1-150 GEN
Solar/Wind Harmer
10.951
971343AH1-151 GEN
Solar/Wind Harmer
10.951
971411AH1-196 GEN
Solar/Wind Harmer
63.057
971675AH1-338 GEN
Solar/Wind Harmer
14.744
971681AH1-341 GEN
Solar/Wind Harmer
21.364
276157O29GEN1
Solar/Wind Harmer
3.476
276158O29GEN2
Solar/Wind Harmer
4.571
276708O09 GEN2
Solar/Wind Harmer
3.264
276741O09 GEN1
Solar/Wind Harmer
3.264
957471AF2-041 GEN
Solar/Wind Harmer
16.426
965931AG1-462 GEN
Solar/Wind Harmer
22.033
972031AH1-564 GEN
50/50
36.4
972235AH1-702 GEN1
50/50
5.755
972236AH1-702 GEN2
50/50
5.01
972267AH1-718 GEN
Adder
4.537
971087AG2-675 GEN
Solar/Wind Harmer
3.215
990117J1214
External Queue
32.16032409667969
990407J1304
External Queue
7.912186622619629
990512J1326
External Queue
9.348932266235352
990727J1377 G
External Queue
13.844555854797363
991092J1477
External Queue
2.8871541023254395
991777J1629 G
External Queue
9.072366714477539
CBM West 1LTFEXP_CBM-W1->PJM
CBM
44.616
CBM West 2LTFEXP_CBM-W2->PJM
CBM
13.262
CBM South 1LTFEXP_CBM-S1->PJM
CBM
1.907
CBM South 2LTFEXP_CBM-S2->PJM
CBM
0.132
NYPJM->LTFIMP_NY
CLTF
0.244
WECLTFEXP_WEC->PJM
CLTF
0.738
HAMLETPJM->LTFIMP_HAMLET
CLTF
0.01
TVALTFEXP_TVA->PJM
CLTF
0.655
TRIMBLEPJM->LTFIMP_TRIMBLE
CLTF
0.141
MECLTFEXP_MEC->PJM
CLTF
9.249
BlueGrassPJM->LTFIMP_BlueG
CLTF
0.4
LAGNLTFEXP_LAGN->PJM
CLTF
2.561
SIGELTFEXP_SIGE->PJM
CLTF
0.002

Details for AF2-349 TP-SILVER LK; R 345.0 kV Ckt 1 line l/o COMED_P4-6_006-345-BT78___SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:CE
Facility Description:
AF2-349 TP-SILVER LK; R 345.0 kV Ckt 1 line
Contingency Name:
COMED_P4-6_006-345-BT78___SRT-A
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:109.88 %
Rating:1568.0 MVA
Rating Type:STE
MVA to Mitigate:1722.95
MW Contribution:
37.95
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area:CE
Facility Description:
AF2-349 TP-SILVER LK; R 345.0 kV Ckt 1 line
Contingency Name:
COMED_P4-6_006-345-BT78___SRT-A
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:109.83 %
Rating:1568.0 MVA
Rating Type:STE
MVA to Mitigate:1722.08
MW Contribution:
37.89
Bus #Bus NameTypeMW Contribution
274656BYRON ;1U
50/50
4.367
274657BYRON ;2U
50/50
5.244
274822ROCKFORD ;11
50/50
45.318
274823ROCKFORD ;21
50/50
44.99
274824ROCKFORD ;12
50/50
35.423
274855GSG-6 ;RU
Solar/Wind Harmer
2.98
274856ECOGROVE ;U1
Solar/Wind Harmer
6.268
274760LEE CO EC;1U
Adder
12.927
276602WESTBROOK C
Solar/Wind Harmer
1.716
276603SUBLETTE C
Solar/Wind Harmer
1.171
274850MENDOTA H;RU
Solar/Wind Harmer
2.072
274761LEE CO EC;2U
Adder
12.927
274762LEE CO EC;3U
Adder
12.927
274763LEE CO EC;4U
Adder
12.806
274764LEE CO EC;5U
Adder
12.958
274765LEE CO EC;6U
Adder
12.958
274766LEE CO EC;7U
Adder
12.775
274767LEE CO EC;8U
Adder
12.775
274872LEEDK;1U
Solar/Wind Harmer
5.712
276611AD2-172 GEN
Solar/Wind Harmer
4.755
276612AE2-035 GEN
Solar/Wind Harmer
4.755
276799AD1-013 GEN
Solar/Wind Harmer
1.763
276861AD2-134 GEN
Solar/Wind Harmer
1.441
276863AD2-134 GEN
Solar/Wind Harmer
1.441
274857EASY ROAD;U1
Solar/Wind Harmer
6.657
274858EASY ROAD;U2
Solar/Wind Harmer
6.657
938861AE1-114 GEN
Solar/Wind Harmer
12.223
946321AF1-296 GEN
Solar/Wind Harmer
8.818
946671AF1-331 GEN
Solar/Wind Harmer
0.334
959081AF2-199 GEN
Solar/Wind Harmer
4.706
959091AF2-200 GEN
Solar/Wind Harmer
9.412
960751AF2-366 GEN
Solar/Wind Harmer
2.183
962691AG1-118 GEN
Solar/Wind Harmer
18.157
962781AG1-127 GEN
Solar/Wind Harmer
7.236
970819AG2-516 GEN
Solar/Wind Harmer
24.222
971067AG2-660 GEN
Solar/Wind Harmer
1.094
971171AH1-044 GEN
Solar/Wind Harmer
9.412
971341AH1-150 GEN
Solar/Wind Harmer
9.412
971343AH1-151 GEN
Solar/Wind Harmer
9.412
971411AH1-196 GEN
Solar/Wind Harmer
64.429
971675AH1-338 GEN
Solar/Wind Harmer
14.455
971681AH1-341 GEN
Solar/Wind Harmer
21.212
276157O29GEN1
Solar/Wind Harmer
3.266
276158O29GEN2
Solar/Wind Harmer
4.296
276708O09 GEN2
Solar/Wind Harmer
3.067
276741O09 GEN1
Solar/Wind Harmer
3.067
957471AF2-041 GEN
Solar/Wind Harmer
14.118
965931AG1-462 GEN
Solar/Wind Harmer
20.81
972031AH1-564 GEN
50/50
37.955
972235AH1-702 GEN1
50/50
5.265
972236AH1-702 GEN2
50/50
5.664
972267AH1-718 GEN
Adder
4.202
971087AG2-675 GEN
Solar/Wind Harmer
3.037
990117J1214
External Queue
34.720191955566406
990407J1304
External Queue
8.583191871643066
990512J1326
External Queue
10.093079566955566
990727J1377 G
External Queue
14.965534210205078
991092J1477
External Queue
2.653498649597168
991777J1629 G
External Queue
9.970706939697266
CBM West 1LTFEXP_CBM-W1->PJM
CBM
46.344
CBM West 2LTFEXP_CBM-W2->PJM
CBM
13.042
CBM South 1LTFEXP_CBM-S1->PJM
CBM
1.876
CBM South 2LTFEXP_CBM-S2->PJM
CBM
0.126
NYPJM->LTFIMP_NY
CLTF
0.242
WECLTFEXP_WEC->PJM
CLTF
0.882
HAMLETPJM->LTFIMP_HAMLET
CLTF
0.011
TVALTFEXP_TVA->PJM
CLTF
0.645
TRIMBLEPJM->LTFIMP_TRIMBLE
CLTF
0.141
MECLTFEXP_MEC->PJM
CLTF
9.175
BlueGrassPJM->LTFIMP_BlueG
CLTF
0.4
LAGNLTFEXP_LAGN->PJM
CLTF
2.534
SIGELTFEXP_SIGE->PJM
CLTF
0.002

Details for AF2-349 TP-SILVER LK; R 345.0 kV Ckt 1 line l/o COMED_P4_111-45-TR81____SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:CE
Facility Description:
AF2-349 TP-SILVER LK; R 345.0 kV Ckt 1 line
Contingency Name:
COMED_P4_111-45-TR81____SRT-A
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:102.15 %
Rating:1568.0 MVA
Rating Type:STE
MVA to Mitigate:1601.72
MW Contribution:
31.15
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area:CE
Facility Description:
AF2-349 TP-SILVER LK; R 345.0 kV Ckt 1 line
Contingency Name:
COMED_P4_111-45-TR81____SRT-A
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:102.1 %
Rating:1568.0 MVA
Rating Type:STE
MVA to Mitigate:1601.0
MW Contribution:
31.09
Bus #Bus NameTypeMW Contribution
274656BYRON ;1U
50/50
3.625
274657BYRON ;2U
50/50
3.529
274822ROCKFORD ;11
50/50
37.189
274823ROCKFORD ;21
50/50
36.923
274824ROCKFORD ;12
50/50
29.069
274855GSG-6 ;RU
Solar/Wind Harmer
2.759
274856ECOGROVE ;U1
Solar/Wind Harmer
5.239
274760LEE CO EC;1U
Adder
12.176
276602WESTBROOK C
Solar/Wind Harmer
1.588
276603SUBLETTE C
Solar/Wind Harmer
1.156
274850MENDOTA H;RU
Solar/Wind Harmer
1.918
274761LEE CO EC;2U
Adder
12.176
274762LEE CO EC;3U
Adder
12.176
274763LEE CO EC;4U
Adder
12.061
274764LEE CO EC;5U
Adder
12.204
274765LEE CO EC;6U
Adder
12.204
274766LEE CO EC;7U
Adder
12.032
274767LEE CO EC;8U
Adder
12.032
274872LEEDK;1U
Solar/Wind Harmer
5.086
276611AD2-172 GEN
Solar/Wind Harmer
3.974
276612AE2-035 GEN
Solar/Wind Harmer
3.974
276799AD1-013 GEN
Solar/Wind Harmer
1.628
276861AD2-134 GEN
Solar/Wind Harmer
1.334
276863AD2-134 GEN
Solar/Wind Harmer
1.334
274857EASY ROAD;U1
Solar/Wind Harmer
6.27
274858EASY ROAD;U2
Solar/Wind Harmer
6.27
938861AE1-114 GEN
Solar/Wind Harmer
10.922
946321AF1-296 GEN
Solar/Wind Harmer
9.048
946671AF1-331 GEN
Solar/Wind Harmer
0.308
959081AF2-199 GEN
Solar/Wind Harmer
10.943
959091AF2-200 GEN
Solar/Wind Harmer
21.886
960751AF2-366 GEN
Solar/Wind Harmer
1.89
962691AG1-118 GEN
Solar/Wind Harmer
15.823
962781AG1-127 GEN
Solar/Wind Harmer
6.265
970819AG2-516 GEN
Solar/Wind Harmer
19.552
971067AG2-660 GEN
Solar/Wind Harmer
2.545
971171AH1-044 GEN
Solar/Wind Harmer
21.886
971341AH1-150 GEN
Solar/Wind Harmer
21.886
971343AH1-151 GEN
Solar/Wind Harmer
21.886
971411AH1-196 GEN
Solar/Wind Harmer
59.992
971675AH1-338 GEN
Solar/Wind Harmer
13.364
971681AH1-341 GEN
Solar/Wind Harmer
19.582
276157O29GEN1
Solar/Wind Harmer
3.43
276158O29GEN2
Solar/Wind Harmer
4.511
276708O09 GEN2
Solar/Wind Harmer
3.221
276741O09 GEN1
Solar/Wind Harmer
3.221
957471AF2-041 GEN
Solar/Wind Harmer
32.829
965931AG1-462 GEN
Solar/Wind Harmer
21.652
972031AH1-564 GEN
50/50
31.15
972235AH1-702 GEN1
50/50
4.371
972236AH1-702 GEN2
50/50
3.812
972267AH1-718 GEN
Adder
4.559
971087AG2-675 GEN
Solar/Wind Harmer
3.159
990117J1214
External Queue
26.119335174560547
990407J1304
External Queue
6.3769121170043945
990512J1326
External Queue
7.592830657958984
990727J1377 G
External Queue
11.233358383178711
991092J1477
External Queue
2.9201087951660156
CBM West 1LTFEXP_CBM-W1->PJM
CBM
38.735
CBM West 2LTFEXP_CBM-W2->PJM
CBM
12.92
CBM South 1LTFEXP_CBM-S1->PJM
CBM
1.923
CBM South 2LTFEXP_CBM-S2->PJM
CBM
0.238
NYPJM->LTFIMP_NY
CLTF
0.202
WECLTFEXP_WEC->PJM
CLTF
0.48
TVALTFEXP_TVA->PJM
CLTF
0.649
TRIMBLEPJM->LTFIMP_TRIMBLE
CLTF
0.105
MECLTFEXP_MEC->PJM
CLTF
8.563
BlueGrassPJM->LTFIMP_BlueG
CLTF
0.288
LAGNLTFEXP_LAGN->PJM
CLTF
2.444
SIGELTFEXP_SIGE->PJM
CLTF
0.005

Details for AF2-349 TP-SILVER LK; R 345.0 kV Ckt 1 line l/o COMED_P4_111-45-L11124__SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:CE
Facility Description:
AF2-349 TP-SILVER LK; R 345.0 kV Ckt 1 line
Contingency Name:
COMED_P4_111-45-L11124__SRT-A
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:102.15 %
Rating:1568.0 MVA
Rating Type:STE
MVA to Mitigate:1601.72
MW Contribution:
31.15
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area:CE
Facility Description:
AF2-349 TP-SILVER LK; R 345.0 kV Ckt 1 line
Contingency Name:
COMED_P4_111-45-L11124__SRT-A
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:102.1 %
Rating:1568.0 MVA
Rating Type:STE
MVA to Mitigate:1601.0
MW Contribution:
31.09
Bus #Bus NameTypeMW Contribution
274656BYRON ;1U
50/50
3.625
274657BYRON ;2U
50/50
3.529
274822ROCKFORD ;11
50/50
37.189
274823ROCKFORD ;21
50/50
36.923
274824ROCKFORD ;12
50/50
29.069
274855GSG-6 ;RU
Solar/Wind Harmer
2.759
274856ECOGROVE ;U1
Solar/Wind Harmer
5.239
274760LEE CO EC;1U
Adder
12.176
276602WESTBROOK C
Solar/Wind Harmer
1.588
276603SUBLETTE C
Solar/Wind Harmer
1.156
274850MENDOTA H;RU
Solar/Wind Harmer
1.918
274761LEE CO EC;2U
Adder
12.176
274762LEE CO EC;3U
Adder
12.176
274763LEE CO EC;4U
Adder
12.061
274764LEE CO EC;5U
Adder
12.204
274765LEE CO EC;6U
Adder
12.204
274766LEE CO EC;7U
Adder
12.032
274767LEE CO EC;8U
Adder
12.032
274872LEEDK;1U
Solar/Wind Harmer
5.086
276611AD2-172 GEN
Solar/Wind Harmer
3.974
276612AE2-035 GEN
Solar/Wind Harmer
3.974
276799AD1-013 GEN
Solar/Wind Harmer
1.628
276861AD2-134 GEN
Solar/Wind Harmer
1.334
276863AD2-134 GEN
Solar/Wind Harmer
1.334
274857EASY ROAD;U1
Solar/Wind Harmer
6.27
274858EASY ROAD;U2
Solar/Wind Harmer
6.27
938861AE1-114 GEN
Solar/Wind Harmer
10.922
946321AF1-296 GEN
Solar/Wind Harmer
9.048
946671AF1-331 GEN
Solar/Wind Harmer
0.308
959081AF2-199 GEN
Solar/Wind Harmer
10.943
959091AF2-200 GEN
Solar/Wind Harmer
21.886
960751AF2-366 GEN
Solar/Wind Harmer
1.89
962691AG1-118 GEN
Solar/Wind Harmer
15.823
962781AG1-127 GEN
Solar/Wind Harmer
6.265
970819AG2-516 GEN
Solar/Wind Harmer
19.552
971067AG2-660 GEN
Solar/Wind Harmer
2.545
971171AH1-044 GEN
Solar/Wind Harmer
21.886
971341AH1-150 GEN
Solar/Wind Harmer
21.886
971343AH1-151 GEN
Solar/Wind Harmer
21.886
971411AH1-196 GEN
Solar/Wind Harmer
59.992
971675AH1-338 GEN
Solar/Wind Harmer
13.364
971681AH1-341 GEN
Solar/Wind Harmer
19.582
276157O29GEN1
Solar/Wind Harmer
3.43
276158O29GEN2
Solar/Wind Harmer
4.511
276708O09 GEN2
Solar/Wind Harmer
3.221
276741O09 GEN1
Solar/Wind Harmer
3.221
957471AF2-041 GEN
Solar/Wind Harmer
32.829
965931AG1-462 GEN
Solar/Wind Harmer
21.652
972031AH1-564 GEN
50/50
31.15
972235AH1-702 GEN1
50/50
4.371
972236AH1-702 GEN2
50/50
3.812
972267AH1-718 GEN
Adder
4.559
971087AG2-675 GEN
Solar/Wind Harmer
3.159
990117J1214
External Queue
26.119335174560547
990407J1304
External Queue
6.3769121170043945
990512J1326
External Queue
7.592830657958984
990727J1377 G
External Queue
11.233358383178711
991092J1477
External Queue
2.9201087951660156
CBM West 1LTFEXP_CBM-W1->PJM
CBM
38.735
CBM West 2LTFEXP_CBM-W2->PJM
CBM
12.92
CBM South 1LTFEXP_CBM-S1->PJM
CBM
1.923
CBM South 2LTFEXP_CBM-S2->PJM
CBM
0.238
NYPJM->LTFIMP_NY
CLTF
0.202
WECLTFEXP_WEC->PJM
CLTF
0.48
TVALTFEXP_TVA->PJM
CLTF
0.649
TRIMBLEPJM->LTFIMP_TRIMBLE
CLTF
0.105
MECLTFEXP_MEC->PJM
CLTF
8.563
BlueGrassPJM->LTFIMP_BlueG
CLTF
0.288
LAGNLTFEXP_LAGN->PJM
CLTF
2.444
SIGELTFEXP_SIGE->PJM
CLTF
0.005

Details for AF2-349 TP-SILVER LK; R 345.0 kV Ckt 1 line l/o COMED_P2-2_111_EJ-345B__1_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:CE
Facility Description:
AF2-349 TP-SILVER LK; R 345.0 kV Ckt 1 line
Contingency Name:
COMED_P2-2_111_EJ-345B__1_SRT-A
Contingency Type:Bus
DC|AC:AC
Final Cycle Loading:102.15 %
Rating:1568.0 MVA
Rating Type:STE
MVA to Mitigate:1601.72
MW Contribution:
31.15
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area:CE
Facility Description:
AF2-349 TP-SILVER LK; R 345.0 kV Ckt 1 line
Contingency Name:
COMED_P2-2_111_EJ-345B__1_SRT-A
Contingency Type:Bus
DC|AC:AC
Final Cycle Loading:102.1 %
Rating:1568.0 MVA
Rating Type:STE
MVA to Mitigate:1600.93
MW Contribution:
31.09
Bus #Bus NameTypeMW Contribution
274656BYRON ;1U
50/50
3.625
274657BYRON ;2U
50/50
3.529
274822ROCKFORD ;11
50/50
37.189
274823ROCKFORD ;21
50/50
36.923
274824ROCKFORD ;12
50/50
29.069
274855GSG-6 ;RU
Solar/Wind Harmer
2.759
274856ECOGROVE ;U1
Solar/Wind Harmer
5.239
274760LEE CO EC;1U
Adder
12.176
276602WESTBROOK C
Solar/Wind Harmer
1.588
276603SUBLETTE C
Solar/Wind Harmer
1.156
274850MENDOTA H;RU
Solar/Wind Harmer
1.918
274761LEE CO EC;2U
Adder
12.176
274762LEE CO EC;3U
Adder
12.176
274763LEE CO EC;4U
Adder
12.061
274764LEE CO EC;5U
Adder
12.204
274765LEE CO EC;6U
Adder
12.204
274766LEE CO EC;7U
Adder
12.032
274767LEE CO EC;8U
Adder
12.032
274872LEEDK;1U
Solar/Wind Harmer
5.086
276611AD2-172 GEN
Solar/Wind Harmer
3.974
276612AE2-035 GEN
Solar/Wind Harmer
3.974
276799AD1-013 GEN
Solar/Wind Harmer
1.628
276861AD2-134 GEN
Solar/Wind Harmer
1.334
276863AD2-134 GEN
Solar/Wind Harmer
1.334
274857EASY ROAD;U1
Solar/Wind Harmer
6.27
274858EASY ROAD;U2
Solar/Wind Harmer
6.27
938861AE1-114 GEN
Solar/Wind Harmer
10.922
946321AF1-296 GEN
Solar/Wind Harmer
9.048
946671AF1-331 GEN
Solar/Wind Harmer
0.308
959081AF2-199 GEN
Solar/Wind Harmer
10.943
959091AF2-200 GEN
Solar/Wind Harmer
21.886
960751AF2-366 GEN
Solar/Wind Harmer
1.89
962691AG1-118 GEN
Solar/Wind Harmer
15.823
962781AG1-127 GEN
Solar/Wind Harmer
6.265
970819AG2-516 GEN
Solar/Wind Harmer
19.552
971067AG2-660 GEN
Solar/Wind Harmer
2.545
971171AH1-044 GEN
Solar/Wind Harmer
21.886
971341AH1-150 GEN
Solar/Wind Harmer
21.886
971343AH1-151 GEN
Solar/Wind Harmer
21.886
971411AH1-196 GEN
Solar/Wind Harmer
59.992
971675AH1-338 GEN
Solar/Wind Harmer
13.364
971681AH1-341 GEN
Solar/Wind Harmer
19.582
276157O29GEN1
Solar/Wind Harmer
3.43
276158O29GEN2
Solar/Wind Harmer
4.511
276708O09 GEN2
Solar/Wind Harmer
3.221
276741O09 GEN1
Solar/Wind Harmer
3.221
957471AF2-041 GEN
Solar/Wind Harmer
32.829
965931AG1-462 GEN
Solar/Wind Harmer
21.652
972031AH1-564 GEN
50/50
31.15
972235AH1-702 GEN1
50/50
4.371
972236AH1-702 GEN2
50/50
3.812
972267AH1-718 GEN
Adder
4.559
971087AG2-675 GEN
Solar/Wind Harmer
3.159
990117J1214
External Queue
26.119335174560547
990407J1304
External Queue
6.3769121170043945
990512J1326
External Queue
7.592830657958984
990727J1377 G
External Queue
11.233358383178711
991092J1477
External Queue
2.9201087951660156
CBM West 1LTFEXP_CBM-W1->PJM
CBM
38.735
CBM West 2LTFEXP_CBM-W2->PJM
CBM
12.92
CBM South 1LTFEXP_CBM-S1->PJM
CBM
1.923
CBM South 2LTFEXP_CBM-S2->PJM
CBM
0.238
NYPJM->LTFIMP_NY
CLTF
0.202
WECLTFEXP_WEC->PJM
CLTF
0.48
TVALTFEXP_TVA->PJM
CLTF
0.649
TRIMBLEPJM->LTFIMP_TRIMBLE
CLTF
0.105
MECLTFEXP_MEC->PJM
CLTF
8.563
BlueGrassPJM->LTFIMP_BlueG
CLTF
0.288
LAGNLTFEXP_LAGN->PJM
CLTF
2.444
SIGELTFEXP_SIGE->PJM
CLTF
0.005

Details for AF2-349 TP-SILVER LK; R 345.0 kV Ckt 1 line l/o COMED_P1-2_345-L0626__B-R_SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:CE
Facility Description:
AF2-349 TP-SILVER LK; R 345.0 kV Ckt 1 line
Contingency Name:
COMED_P1-2_345-L0626__B-R_SRT-A
Contingency Type:Single
DC|AC:AC
Final Cycle Loading:102.07 %
Rating:1568.0 MVA
Rating Type:STE
MVA to Mitigate:1600.48
MW Contribution:
36.77
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area:CE
Facility Description:
AF2-349 TP-SILVER LK; R 345.0 kV Ckt 1 line
Contingency Name:
COMED_P1-2_345-L0626__B-R_SRT-A
Contingency Type:Single
DC|AC:AC
Final Cycle Loading:102.05 %
Rating:1568.0 MVA
Rating Type:STE
MVA to Mitigate:1600.1
MW Contribution:
36.71
Bus #Bus NameTypeMW Contribution
274656BYRON ;1U
50/50
4.81
274657BYRON ;2U
50/50
4.675
274822ROCKFORD ;11
50/50
43.907
274823ROCKFORD ;21
50/50
43.591
274824ROCKFORD ;12
50/50
34.321
274855GSG-6 ;RU
Solar/Wind Harmer
0.208
274856ECOGROVE ;U1
Solar/Wind Harmer
0.295
274760LEE CO EC;1U
Adder
14.08
274850MENDOTA H;RU
Solar/Wind Harmer
0.066
274761LEE CO EC;2U
Adder
14.08
274762LEE CO EC;3U
Adder
14.08
274763LEE CO EC;4U
Adder
13.947
274764LEE CO EC;5U
Adder
14.113
274765LEE CO EC;6U
Adder
14.113
274766LEE CO EC;7U
Adder
13.914
274767LEE CO EC;8U
Adder
13.914
274872LEEDK;1U
Solar/Wind Harmer
0
276861AD2-134 GEN
Solar/Wind Harmer
0.101
276863AD2-134 GEN
Solar/Wind Harmer
0.101
274857EASY ROAD;U1
Solar/Wind Harmer
0
274858EASY ROAD;U2
Solar/Wind Harmer
0
938861AE1-114 GEN
Solar/Wind Harmer
5.873
946321AF1-296 GEN
Solar/Wind Harmer
3.463
946671AF1-331 GEN
Solar/Wind Harmer
0.599
959081AF2-199 GEN
Solar/Wind Harmer
3.569
959091AF2-200 GEN
Solar/Wind Harmer
7.138
962691AG1-118 GEN
Solar/Wind Harmer
12.515
962781AG1-127 GEN
Solar/Wind Harmer
4.983
970819AG2-516 GEN
Solar/Wind Harmer
16.227
971067AG2-660 GEN
Solar/Wind Harmer
1.19
971171AH1-044 GEN
Solar/Wind Harmer
7.138
971341AH1-150 GEN
Solar/Wind Harmer
7.138
971343AH1-151 GEN
Solar/Wind Harmer
7.138
971411AH1-196 GEN
Solar/Wind Harmer
44.459
971675AH1-338 GEN
Solar/Wind Harmer
2.206
971681AH1-341 GEN
Solar/Wind Harmer
16.043
276157O29GEN1
Solar/Wind Harmer
1.023
276158O29GEN2
Solar/Wind Harmer
0
276708O09 GEN2
Solar/Wind Harmer
0.224
276741O09 GEN1
Solar/Wind Harmer
0.224
957471AF2-041 GEN
Solar/Wind Harmer
10.707
965931AG1-462 GEN
Solar/Wind Harmer
15.306
972031AH1-564 GEN
50/50
36.775
972235AH1-702 GEN1
50/50
5.8
972236AH1-702 GEN2
50/50
5.049
972267AH1-718 GEN
Adder
4.509
971087AG2-675 GEN
Solar/Wind Harmer
3.201
990117J1214
External Queue
32.45051574707031
990407J1304
External Queue
7.987898826599121
990512J1326
External Queue
9.433289527893066
990727J1377 G
External Queue
13.973295211791992
991092J1477
External Queue
2.8681230545043945
991777J1629 G
External Queue
9.16248893737793
CBM West 1LTFEXP_CBM-W1->PJM
CBM
44.794
CBM West 2LTFEXP_CBM-W2->PJM
CBM
13.288
CBM South 1LTFEXP_CBM-S1->PJM
CBM
1.91
CBM South 2LTFEXP_CBM-S2->PJM
CBM
0.131
NYPJM->LTFIMP_NY
CLTF
0.244
WECLTFEXP_WEC->PJM
CLTF
0.749
HAMLETPJM->LTFIMP_HAMLET
CLTF
0.01
TVALTFEXP_TVA->PJM
CLTF
0.656
TRIMBLEPJM->LTFIMP_TRIMBLE
CLTF
0.141
MECLTFEXP_MEC->PJM
CLTF
9.253
BlueGrassPJM->LTFIMP_BlueG
CLTF
0.4
LAGNLTFEXP_LAGN->PJM
CLTF
2.564
SIGELTFEXP_SIGE->PJM
CLTF
0.002

Details for CHERRY VA; B-AF2-349 TP 345.0 kV Ckt 1 line l/o COMED_P4_144-45-BT7-8___SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:CE
Facility Description:
CHERRY VA; B-AF2-349 TP 345.0 kV Ckt 1 line
Contingency Name:
COMED_P4_144-45-BT7-8___SRT-A
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:107.42 %
Rating:1568.0 MVA
Rating Type:STE
MVA to Mitigate:1684.35
MW Contribution:
36.82
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area:CE
Facility Description:
CHERRY VA; B-AF2-349 TP 345.0 kV Ckt 1 line
Contingency Name:
COMED_P4_144-45-BT7-8___SRT-A
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:107.37 %
Rating:1568.0 MVA
Rating Type:STE
MVA to Mitigate:1683.52
MW Contribution:
36.76
Bus #Bus NameTypeMW Contribution
274656BYRON ;1U
50/50
4.815
274657BYRON ;2U
50/50
4.679
274822ROCKFORD ;11
50/50
43.963
274823ROCKFORD ;21
50/50
43.646
274824ROCKFORD ;12
50/50
34.364
274855GSG-6 ;RU
Solar/Wind Harmer
3.013
274856ECOGROVE ;U1
Solar/Wind Harmer
6.106
274760LEE CO EC;1U
Adder
14.092
276602WESTBROOK C
Solar/Wind Harmer
1.734
276603SUBLETTE C
Solar/Wind Harmer
1.213
274850MENDOTA H;RU
Solar/Wind Harmer
2.095
274761LEE CO EC;2U
Adder
14.092
274762LEE CO EC;3U
Adder
14.092
274763LEE CO EC;4U
Adder
13.959
274764LEE CO EC;5U
Adder
14.125
274765LEE CO EC;6U
Adder
14.125
274766LEE CO EC;7U
Adder
13.926
274767LEE CO EC;8U
Adder
13.926
274872LEEDK;1U
Solar/Wind Harmer
5.695
276611AD2-172 GEN
Solar/Wind Harmer
4.632
276612AE2-035 GEN
Solar/Wind Harmer
4.632
276799AD1-013 GEN
Solar/Wind Harmer
1.781
276861AD2-134 GEN
Solar/Wind Harmer
1.457
276863AD2-134 GEN
Solar/Wind Harmer
1.457
274857EASY ROAD;U1
Solar/Wind Harmer
7.256
274858EASY ROAD;U2
Solar/Wind Harmer
7.256
938861AE1-114 GEN
Solar/Wind Harmer
12.192
946321AF1-296 GEN
Solar/Wind Harmer
9.257
946671AF1-331 GEN
Solar/Wind Harmer
0.337
959081AF2-199 GEN
Solar/Wind Harmer
5.107
959091AF2-200 GEN
Solar/Wind Harmer
10.215
960751AF2-366 GEN
Solar/Wind Harmer
2.156
962691AG1-118 GEN
Solar/Wind Harmer
17.965
962781AG1-127 GEN
Solar/Wind Harmer
7.147
970819AG2-516 GEN
Solar/Wind Harmer
23.288
971067AG2-660 GEN
Solar/Wind Harmer
1.188
971171AH1-044 GEN
Solar/Wind Harmer
10.215
971341AH1-150 GEN
Solar/Wind Harmer
10.215
971343AH1-151 GEN
Solar/Wind Harmer
10.215
971675AH1-338 GEN
Solar/Wind Harmer
14.608
971681AH1-341 GEN
Solar/Wind Harmer
21.445
276157O29GEN1
Solar/Wind Harmer
3.462
276158O29GEN2
Solar/Wind Harmer
4.553
276708O09 GEN2
Solar/Wind Harmer
3.251
276741O09 GEN1
Solar/Wind Harmer
3.251
957471AF2-041 GEN
Solar/Wind Harmer
15.322
965931AG1-462 GEN
Solar/Wind Harmer
21.963
972031AH1-564 GEN
50/50
36.821
972235AH1-702 GEN1
50/50
5.805
972236AH1-702 GEN2
50/50
5.054
972267AH1-718 GEN
Adder
4.513
971087AG2-675 GEN
Solar/Wind Harmer
3.205
990117J1214
External Queue
32.50968551635742
990407J1304
External Queue
8.001517295837402
990512J1326
External Queue
9.45048999786377
990727J1377 G
External Queue
13.989998817443848
991092J1477
External Queue
2.8669803142547607
991777J1629 G
External Queue
9.221789360046387
CBM West 1LTFEXP_CBM-W1->PJM
CBM
45.04
CBM West 2LTFEXP_CBM-W2->PJM
CBM
13.315
CBM South 1LTFEXP_CBM-S1->PJM
CBM
1.914
CBM South 2LTFEXP_CBM-S2->PJM
CBM
0.131
NYPJM->LTFIMP_NY
CLTF
0.245
WECLTFEXP_WEC->PJM
CLTF
0.771
HAMLETPJM->LTFIMP_HAMLET
CLTF
0.01
TVALTFEXP_TVA->PJM
CLTF
0.658
TRIMBLEPJM->LTFIMP_TRIMBLE
CLTF
0.142
MECLTFEXP_MEC->PJM
CLTF
9.276
BlueGrassPJM->LTFIMP_BlueG
CLTF
0.401
LAGNLTFEXP_LAGN->PJM
CLTF
2.57
SIGELTFEXP_SIGE->PJM
CLTF
0.002

Details for CHERRY VA; B-AF2-349 TP 345.0 kV Ckt 1 line l/o COMED_P4_144-45-BT5-8___SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:CE
Facility Description:
CHERRY VA; B-AF2-349 TP 345.0 kV Ckt 1 line
Contingency Name:
COMED_P4_144-45-BT5-8___SRT-A
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:107.28 %
Rating:1568.0 MVA
Rating Type:STE
MVA to Mitigate:1682.12
MW Contribution:
36.4
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area:CE
Facility Description:
CHERRY VA; B-AF2-349 TP 345.0 kV Ckt 1 line
Contingency Name:
COMED_P4_144-45-BT5-8___SRT-A
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:107.23 %
Rating:1568.0 MVA
Rating Type:STE
MVA to Mitigate:1681.29
MW Contribution:
36.34
Bus #Bus NameTypeMW Contribution
274656BYRON ;1U
50/50
4.773
274657BYRON ;2U
50/50
4.638
274822ROCKFORD ;11
50/50
43.459
274823ROCKFORD ;21
50/50
43.146
274824ROCKFORD ;12
50/50
33.97
274855GSG-6 ;RU
Solar/Wind Harmer
3.041
274856ECOGROVE ;U1
Solar/Wind Harmer
6.052
274760LEE CO EC;1U
Adder
14.055
276602WESTBROOK C
Solar/Wind Harmer
1.75
276603SUBLETTE C
Solar/Wind Harmer
1.214
274850MENDOTA H;RU
Solar/Wind Harmer
2.114
274761LEE CO EC;2U
Adder
14.055
274762LEE CO EC;3U
Adder
14.055
274763LEE CO EC;4U
Adder
13.922
274764LEE CO EC;5U
Adder
14.088
274765LEE CO EC;6U
Adder
14.088
274766LEE CO EC;7U
Adder
13.889
274767LEE CO EC;8U
Adder
13.889
274872LEEDK;1U
Solar/Wind Harmer
5.774
276611AD2-172 GEN
Solar/Wind Harmer
4.591
276612AE2-035 GEN
Solar/Wind Harmer
4.591
276799AD1-013 GEN
Solar/Wind Harmer
1.798
276861AD2-134 GEN
Solar/Wind Harmer
1.47
276863AD2-134 GEN
Solar/Wind Harmer
1.47
274857EASY ROAD;U1
Solar/Wind Harmer
7.237
274858EASY ROAD;U2
Solar/Wind Harmer
7.237
938861AE1-114 GEN
Solar/Wind Harmer
12.132
946321AF1-296 GEN
Solar/Wind Harmer
9.281
946671AF1-331 GEN
Solar/Wind Harmer
0.341
959081AF2-199 GEN
Solar/Wind Harmer
5.475
959091AF2-200 GEN
Solar/Wind Harmer
10.951
960751AF2-366 GEN
Solar/Wind Harmer
2.181
962691AG1-118 GEN
Solar/Wind Harmer
18.362
962781AG1-127 GEN
Solar/Wind Harmer
7.228
970819AG2-516 GEN
Solar/Wind Harmer
23.055
971067AG2-660 GEN
Solar/Wind Harmer
1.273
971171AH1-044 GEN
Solar/Wind Harmer
10.951
971341AH1-150 GEN
Solar/Wind Harmer
10.951
971343AH1-151 GEN
Solar/Wind Harmer
10.951
971675AH1-338 GEN
Solar/Wind Harmer
14.744
971681AH1-341 GEN
Solar/Wind Harmer
21.364
276157O29GEN1
Solar/Wind Harmer
3.476
276158O29GEN2
Solar/Wind Harmer
4.571
276708O09 GEN2
Solar/Wind Harmer
3.264
276741O09 GEN1
Solar/Wind Harmer
3.264
957471AF2-041 GEN
Solar/Wind Harmer
16.426
965931AG1-462 GEN
Solar/Wind Harmer
22.033
972031AH1-564 GEN
50/50
36.4
972235AH1-702 GEN1
50/50
5.755
972236AH1-702 GEN2
50/50
5.01
972267AH1-718 GEN
Adder
4.537
971087AG2-675 GEN
Solar/Wind Harmer
3.215
990117J1214
External Queue
32.16032409667969
990407J1304
External Queue
7.912186622619629
990512J1326
External Queue
9.348932266235352
990727J1377 G
External Queue
13.844555854797363
991092J1477
External Queue
2.8871541023254395
991777J1629 G
External Queue
9.072366714477539
CBM West 1LTFEXP_CBM-W1->PJM
CBM
44.616
CBM West 2LTFEXP_CBM-W2->PJM
CBM
13.262
CBM South 1LTFEXP_CBM-S1->PJM
CBM
1.907
CBM South 2LTFEXP_CBM-S2->PJM
CBM
0.132
NYPJM->LTFIMP_NY
CLTF
0.244
WECLTFEXP_WEC->PJM
CLTF
0.738
HAMLETPJM->LTFIMP_HAMLET
CLTF
0.01
TVALTFEXP_TVA->PJM
CLTF
0.655
TRIMBLEPJM->LTFIMP_TRIMBLE
CLTF
0.141
MECLTFEXP_MEC->PJM
CLTF
9.249
BlueGrassPJM->LTFIMP_BlueG
CLTF
0.4
LAGNLTFEXP_LAGN->PJM
CLTF
2.561
SIGELTFEXP_SIGE->PJM
CLTF
0.002

Details for CHERRY VA; B-AF2-349 TP 345.0 kV Ckt 1 line l/o COMED_P4-6_006-345-BT78___SRT-A


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:CE
Facility Description:
CHERRY VA; B-AF2-349 TP 345.0 kV Ckt 1 line
Contingency Name:
COMED_P4-6_006-345-BT78___SRT-A
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:105.77 %
Rating:1568.0 MVA
Rating Type:STE
MVA to Mitigate:1658.52
MW Contribution:
37.95
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area:CE
Facility Description:
CHERRY VA; B-AF2-349 TP 345.0 kV Ckt 1 line
Contingency Name:
COMED_P4-6_006-345-BT78___SRT-A
Contingency Type:Breaker
DC|AC:AC
Final Cycle Loading:105.72 %
Rating:1568.0 MVA
Rating Type:STE
MVA to Mitigate:1657.7
MW Contribution:
37.89
Bus #Bus NameTypeMW Contribution
274656BYRON ;1U
50/50
4.367
274657BYRON ;2U
50/50
5.244
274822ROCKFORD ;11
50/50
45.318
274823ROCKFORD ;21
50/50
44.99
274824ROCKFORD ;12
50/50
35.423
274855GSG-6 ;RU
Solar/Wind Harmer
2.98
274856ECOGROVE ;U1
Solar/Wind Harmer
6.268
274760LEE CO EC;1U
Adder
12.927
276602WESTBROOK C
Solar/Wind Harmer
1.716
276603SUBLETTE C
Solar/Wind Harmer
1.171
274850MENDOTA H;RU
Solar/Wind Harmer
2.072
274761LEE CO EC;2U
Adder
12.927
274762LEE CO EC;3U
Adder
12.927
274763LEE CO EC;4U
Adder
12.806
274764LEE CO EC;5U
Adder
12.958
274765LEE CO EC;6U
Adder
12.958
274766LEE CO EC;7U
Adder
12.775
274767LEE CO EC;8U
Adder
12.775
274872LEEDK;1U
Solar/Wind Harmer
5.712
276611AD2-172 GEN
Solar/Wind Harmer
4.755
276612AE2-035 GEN
Solar/Wind Harmer
4.755
276799AD1-013 GEN
Solar/Wind Harmer
1.763
276861AD2-134 GEN
Solar/Wind Harmer
1.441
276863AD2-134 GEN
Solar/Wind Harmer
1.441
274857EASY ROAD;U1
Solar/Wind Harmer
6.657
274858EASY ROAD;U2
Solar/Wind Harmer
6.657
938861AE1-114 GEN
Solar/Wind Harmer
12.223
946321AF1-296 GEN
Solar/Wind Harmer
8.818
946671AF1-331 GEN
Solar/Wind Harmer
0.334
959081AF2-199 GEN
Solar/Wind Harmer
4.706
959091AF2-200 GEN
Solar/Wind Harmer
9.412
960751AF2-366 GEN
Solar/Wind Harmer
2.183
962691AG1-118 GEN
Solar/Wind Harmer
18.157
962781AG1-127 GEN
Solar/Wind Harmer
7.236
970819AG2-516 GEN
Solar/Wind Harmer
24.222
971067AG2-660 GEN
Solar/Wind Harmer
1.094
971171AH1-044 GEN
Solar/Wind Harmer
9.412
971341AH1-150 GEN
Solar/Wind Harmer
9.412
971343AH1-151 GEN
Solar/Wind Harmer
9.412
971675AH1-338 GEN
Solar/Wind Harmer
14.455
971681AH1-341 GEN
Solar/Wind Harmer
21.212
276157O29GEN1
Solar/Wind Harmer
3.266
276158O29GEN2
Solar/Wind Harmer
4.296
276708O09 GEN2
Solar/Wind Harmer
3.067
276741O09 GEN1
Solar/Wind Harmer
3.067
957471AF2-041 GEN
Solar/Wind Harmer
14.118
965931AG1-462 GEN
Solar/Wind Harmer
20.81
972031AH1-564 GEN
50/50
37.955
972235AH1-702 GEN1
50/50
5.265
972236AH1-702 GEN2
50/50
5.664
972267AH1-718 GEN
Adder
4.202
971087AG2-675 GEN
Solar/Wind Harmer
3.037
990117J1214
External Queue
34.720191955566406
990407J1304
External Queue
8.583191871643066
990512J1326
External Queue
10.093079566955566
990727J1377 G
External Queue
14.965534210205078
991092J1477
External Queue
2.653498649597168
991777J1629 G
External Queue
9.970706939697266
CBM West 1LTFEXP_CBM-W1->PJM
CBM
46.344
CBM West 2LTFEXP_CBM-W2->PJM
CBM
13.042
CBM South 1LTFEXP_CBM-S1->PJM
CBM
1.876
CBM South 2LTFEXP_CBM-S2->PJM
CBM
0.126
NYPJM->LTFIMP_NY
CLTF
0.242
WECLTFEXP_WEC->PJM
CLTF
0.882
HAMLETPJM->LTFIMP_HAMLET
CLTF
0.011
TVALTFEXP_TVA->PJM
CLTF
0.645
TRIMBLEPJM->LTFIMP_TRIMBLE
CLTF
0.141
MECLTFEXP_MEC->PJM
CLTF
9.175
BlueGrassPJM->LTFIMP_BlueG
CLTF
0.4
LAGNLTFEXP_LAGN->PJM
CLTF
2.534
SIGELTFEXP_SIGE->PJM
CLTF
0.002

Details for [AH1-564] ROCKFORD ;RP-SABROOKE ; R 138.0 kV Ckt 1 line l/o Base Case


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:CE
Facility Description:
ROCKFORD ;RP-SABROOKE ; R 138.0 kV Ckt 1 line
Contingency Name:
Base Case
Contingency Type:Single
DC|AC:AC
Final Cycle Loading:104.25 %
Rating:310.0 MVA
Rating Type:A
MVA to Mitigate:323.16
MW Contribution:
150.0
IPD Plant:AH1-564
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area:CE
Facility Description:
ROCKFORD ;RP-SABROOKE ; R 138.0 kV Ckt 1 line
Contingency Name:
Base Case
Contingency Type:Single
DC|AC:AC
Final Cycle Loading:103.99 %
Rating:310.0 MVA
Rating Type:A
MVA to Mitigate:322.36
MW Contribution:
150.0
IPD Plant:AH1-564
Bus #Bus NameTypeMW Contribution
972031AH1-564 GEN
PJM_IPD_GROUP
150

Details for ROCKFORD ;RP-SABROOKE ; R 138.0 kV Ckt 1 line l/o Base Case


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:CE
Facility Description:
ROCKFORD ;RP-SABROOKE ; R 138.0 kV Ckt 1 line
Contingency Name:
Base Case
Contingency Type:Single
DC|AC:AC
Final Cycle Loading:104.24 %
Rating:310.0 MVA
Rating Type:A
MVA to Mitigate:323.14
MW Contribution:
150.0
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area:CE
Facility Description:
ROCKFORD ;RP-SABROOKE ; R 138.0 kV Ckt 1 line
Contingency Name:
Base Case
Contingency Type:Single
DC|AC:AC
Final Cycle Loading:103.98 %
Rating:310.0 MVA
Rating Type:A
MVA to Mitigate:322.35
MW Contribution:
150.0
Bus #Bus NameTypeMW Contribution
274823ROCKFORD ;21
50/50
177.8
972031AH1-564 GEN
50/50
150
CONTINGENCY 'COMED_P4_144-45-BT7-8___SRT-A'
 TRIP BRANCH FROM BUS 270678 TO BUS 270916 CKT 1   /*BYRON    ; B 345.0 - WAYNE    ; B 345.0
 TRIP BRANCH FROM BUS 270916 TO BUS 270900 CKT 1   /*WAYNE    ; B 345.0 - TOLLWAY ; B  345.0
 TRIP BRANCH FROM BUS 275228 TO BUS 270916 CKT 1   /*WAYNE    ;1M 138.0 - WAYNE    ; B 345.0
 TRIP BRANCH FROM BUS 275228 TO BUS 272740 CKT 1   /*WAYNE    ;1M 138.0 - WAYNE    ; B 138.0
 TRIP BRANCH FROM BUS 275228 TO BUS 275328 CKT 1   /*WAYNE    ;1M 138.0 - WAYNE    ;1C  34.5
END
CONTINGENCY 'COMED_P4_144-45-BT5-8___SRT-A'
 TRIP BRANCH FROM BUS 270678 TO BUS 270916 CKT 1    /*BYRON    ; B 345.0 - WAYNE    ; B 345.0
 TRIP BRANCH FROM BUS 270916 TO BUS 270917 CKT Z1   /*WAYNE    ; B 345.0 - WAYNE    ; R 345.0
END
CONTINGENCY 'COMED_P4-6_006-345-BT78___SRT-A'
 TRIP BRANCH FROM BUS 270678 TO BUS 270679 CKT Z1   /*BYRON    ; B 345.0 - BYRON    ; R 345.0
 TRIP BRANCH FROM BUS 270678 TO BUS 270916 CKT 1    /*BYRON    ; B 345.0 - WAYNE    ; B 345.0
END
CONTINGENCY 'COMED_P4_111-45-TR81____SRT-A'
 DISCONNECT BUS 270732                             /*ELECT JCT;1B 345.0
 TRIP BRANCH FROM BUS 275182 TO BUS 270732 CKT 1   /*ELECT JCT;1M 138.0 - ELECT JCT;1B 345.0
 TRIP BRANCH FROM BUS 275182 TO BUS 271392 CKT 1   /*ELECT JCT;1M 138.0 - ELECT JCT;1B 138.0
 TRIP BRANCH FROM BUS 275182 TO BUS 275282 CKT 1   /*ELECT JCT;1M 138.0 - ELECT JCT;1C  34.5
END
CONTINGENCY 'COMED_P4_111-45-L11124__SRT-A'
 DISCONNECT BUS 270732                             /*ELECT JCT;1B 345.0
 TRIP BRANCH FROM BUS 270732 TO BUS 270814 CKT 1   /*ELECT JCT;1B 345.0 - LOMBARD  ;4B 345.0
END
CONTINGENCY 'COMED_P2-2_111_EJ-345B__1_SRT-A'
 DISCONNECT BUS 270732   /*ELECT JCT;1B 345.0
END
CONTINGENCY 'COMED_P1-2_345-L0626__B-R_SRT-A'
 TRIP BRANCH FROM BUS 270678 TO BUS 270916 CKT 1   /*BYRON    ; B 345.0 - WAYNE    ; B 345.0
END
960580 to 270883 ckt 1
270694 to 960580 ckt 1
274783 to 272433 ckt 1

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)

Winter Peak Analysis

The New Service Request AH1-564 was evaluated as a 150.0 MW (150.0 MW Capacity) injection in the ComEd area.

AH1-564 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 330.0 MW (150.0 MW under study).

Note: The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for single or N-1 contingencies and multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.

The following flowgates remain after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)

Light Load Analysis

The New Service Request AH1-564 was evaluated as a 150.0 MW injection and 150.0 MW withdrawal in the ComEd area.

AH1-564 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 330.0 MW (150.0 MW under study).

Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.

The following flowgates remain after considering the topology reinforcements required by the cycle.

StudyAreaFacility DescriptionContingency NameContingency TypeDC|ACFinal Cycle LoadingRating (MVA)Rating TypeMVA to MitigateMW ContributionDetails
GD2CE
NELSON ; B-AF2-041 TP 345.0 kV Ckt 1 line
Base Case
SingleAC100.15 %1553.0A1555.33
1.77
IPDCE
ROCKFORD ;RP-SABROOKE ; R 138.0 kV Ckt 1 line
Base Case
SingleAC135.48 %237.0A321.1
150.0

Details for NELSON ; B-AF2-041 TP 345.0 kV Ckt 1 line l/o Base Case


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:CE
Facility Description:
NELSON ; B-AF2-041 TP 345.0 kV Ckt 1 line
Contingency Name:
Base Case
Contingency Type:Single
DC|AC:AC
Final Cycle Loading:100.15 %
Rating:1553.0 MVA
Rating Type:A
MVA to Mitigate:1555.33
MW Contribution:
1.77
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area:CE
Facility Description:
NELSON ; B-AF2-041 TP 345.0 kV Ckt 1 line
Contingency Name:
Base Case
Contingency Type:Single
DC|AC:AC
Final Cycle Loading:99.81 %
Rating:1553.0 MVA
Rating Type:A
MVA to Mitigate:1550.0
MW Contribution:
1.75
Bus #Bus NameTypeMW Contribution
274856ECOGROVE ;U1
Solar/Wind Harmer
4.503
274877BISHOP HL;1U
Solar/Wind Harmer
3.499
274878BISHOP HL;2U
Solar/Wind Harmer
3.499
276603SUBLETTE C
Solar/Wind Harmer
1.962
276782AC1-033 GEN
Solar/Wind Harmer
3.529
274857EASY ROAD;U1
Solar/Wind Harmer
9.262
274858EASY ROAD;U2
Solar/Wind Harmer
9.262
938861AE1-114 GEN
Solar/Wind Harmer
16.009
946321AF1-296 GEN
Solar/Wind Harmer
23.955
970819AG2-516 GEN
Solar/Wind Harmer
5.803
971067AG2-660 GEN
50/50
Charging
23.266
971681AH1-341 GEN
Solar/Wind Harmer
12.213
276157O29GEN1
Solar/Wind Harmer
8.626
276158O29GEN2
Solar/Wind Harmer
8.626
276708O09 GEN2
Solar/Wind Harmer
8.101
276741O09 GEN1
Solar/Wind Harmer
8.101
965931AG1-462 GEN
Solar/Wind Harmer
23.946
972031AH1-564 GEN
Solar/Wind Harmer
1.766
971087AG2-675 GEN
Solar/Wind Harmer
13.659
991092J1477
External Queue
5.358128070831299
CBM West 1LTFEXP_CBM-W1->PJM
CBM
47.585
CBM West 2LTFEXP_CBM-W2->PJM
CBM
17.565
CBM South 1LTFEXP_CBM-S1->PJM
CBM
2.239
CBM South 2LTFEXP_CBM-S2->PJM
CBM
0.032
NYPJM->LTFIMP_NY
CLTF
0.399
WECLTFEXP_WEC->PJM
CLTF
0.714
HAMLETPJM->LTFIMP_HAMLET
CLTF
0.081
CATAWBAPJM->LTFIMP_CATAWBA
CLTF
0.024
TVALTFEXP_TVA->PJM
CLTF
0.794
TRIMBLEPJM->LTFIMP_TRIMBLE
CLTF
0.246
MECLTFEXP_MEC->PJM
CLTF
11.903
BlueGrassPJM->LTFIMP_BlueG
CLTF
0.708
LAGNLTFEXP_LAGN->PJM
CLTF
3.234
SIGELTFEXP_SIGE->PJM
CLTF
0
MISO WINDMISO-WIND_EXP->MISO-WIND_IMP
CLTF
470.612

Details for [AH1-564] ROCKFORD ;RP-SABROOKE ; R 138.0 kV Ckt 1 line l/o Base Case


This cycle required topology changing upgrades. After applying these topology changing upgrades to the study case, this flowgate was a Increase to the base run which does not include the topology changing upgrades.

Topology Case Flowgate

Area:CE
Facility Description:
ROCKFORD ;RP-SABROOKE ; R 138.0 kV Ckt 1 line
Contingency Name:
Base Case
Contingency Type:Single
DC|AC:AC
Final Cycle Loading:135.48 %
Rating:237.0 MVA
Rating Type:A
MVA to Mitigate:321.1
MW Contribution:
150.0
IPD Plant:AH1-564
Impact of Topology Modeling:
Increase

Base Case Flowgate

Area:CE
Facility Description:
ROCKFORD ;RP-SABROOKE ; R 138.0 kV Ckt 1 line
Contingency Name:
Base Case
Contingency Type:Single
DC|AC:AC
Final Cycle Loading:135.47 %
Rating:237.0 MVA
Rating Type:A
MVA to Mitigate:321.07
MW Contribution:
150.0
IPD Plant:AH1-564
Bus #Bus NameTypeMW Contribution
972031AH1-564 GEN
PJM_IPD_GROUP
150
270828 to 957470 ckt 1
274783 to 272433 ckt 1

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)

Short Circuit Analysis

Analysis Complete - No Issues

Based on PJM’s TC2 Phase II Short Circuit Analysis, this project did not contribute >1% fault duty to any previously identified overdutied breakers, nor did it cause any new overdutied breakers.

Please note that in TC2 Phase III, PJM will perform additional analysis including the evaluation of impacts from topology upgrades which may have potential effects on breaker duties not seen in the Phase II analysis.

Stability Analysis

Analysis Complete - No Issues

Executive Summary:

New Service Requests (projects) in PJM Transition Cycle 2, Cluster 60 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 60 projects.

This analysis is effectively a screening study to determine whether the addition of the Cluster 60 projects will meet the dynamics requirements of the NERC, ComEd and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2028 summer peak case, modified to include applicable projects. Cluster 60 projects have been dispatched online at maximum power output and the voltage schedule set to achieve near unity power factor at the high side of the main transformer.

Cluster 60 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 310 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

  1. Three-phase faults with normal clearing time;
  2. Three-phase bus faults with normal clearing time;
  3. Three-phase to ground faults with three-phase delayed clearing due to a stuck breaker (GO breakers);
  4. Three-phase to ground faults with single-phase delayed clearing due to a stuck breaker (IPO breakers)
  5. Three-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure;
  6. Three-phase faults with loss of multiple-circuit tower line.
  7. Three-phase faults with normal clearing time and a failed high speed reclose attempt.

For all simulations, the Cluster 60 projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the 2028 summer peak case:

  1. Cluster 60 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  2. The system with Cluster 60 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3%.
  3. Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
  4. No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

AG2-516, AH1-341, and AH1-564 meet the 0.95 leading and lagging PF requirements.

No mitigations were found to be required.

Table 1: TC2 Cluster 60 Projects

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

AG2-516

Solar

COMED

120

120

72

Pecatonica 138 kV

AH1-341

Solar

COMED

150

150

96.6

Stillman – Dixon 138 kV

AH1-564

Storage

COMED

330

150

150

Rockford II 138 kV

 

Reactive Power Analysis

The reactive power capability of AH1-564 meets the 0.95 leading and lagging PF requirement at the high side of the main transformer.

Steady-State Voltage Analysis

Steady State Voltage Analysis complete, no voltage issues identified.

 

New Service Request Dependencies

The New Service Requests below are listed in one or more dispatch for the overloads identified in this report. These projects contribute to the loading of the overloaded facilities identified in this report. The percent overload of a facility and cost allocation you may have towards a particular reinforcement could vary depending on the action of other projects. The status of each project at the time of the analysis is presented in the table. This list may change as other projects withdraw or modify their requests. This table is valid for load flow analyses only.

New Service Requests Dependencies
Project IDProject NameStatus
AC1-033Kewanee 138 kVIn Service
AD1-013Twombly Road 138kVEngineering & Procurement
AD2-134Shady OaksPartially in Service - Under Construction
AD2-172Lena 138kVIn Service
AE1-114Maryland-Lancaster 138 kVEngineering & Procurement
AE2-035Lena 138 kVIn Service
AF1-296Garden Plain 138 kVEngineering & Procurement
AF1-331Twombley RoadEngineering & Procurement
AF2-041Nelson-Electric Junction 345 kVEngineering & Procurement
AF2-199Nelson-Electric Junction 345 kVEngineering & Procurement
AF2-200Nelson-Electric Junction 345 kVEngineering & Procurement
AF2-366Crego Rd 138 kVEngineering & Procurement
AG1-118Sugar Grove-Waterman 138kVEngineering & Procurement
AG1-127Crego Rd 138 kVEngineering & Procurement
AG1-462Cordova 345 kVEngineering & Procurement
AG2-516Pecatonica 138kVActive
AG2-660Nelson-Electric Junction 345 kVActive
AG2-675Cordova 345 kVActive
AH1-044Nelson - Electric Junction 345 kVActive
AH1-150Nelson-Electric Junction 345 kVActive
AH1-151Nelson-Electric Junction 345 kVActive
AH1-196Silver Lake - Cherry Valley 345 kVActive
AH1-338New Sub S2354 138kVActive
AH1-341ESS-H445 3B 138kvActive
AH1-702Byron 345 kVActive
AH1-718Nelson 345 kVActive

Affected System - PJM Identified Violations

As part of PJM's analysis, per Tariff Part VII.G.336 & Manual 14H, Section 13, PJM evaluated the potential impacts on tie line facilities between PJM and an affected system entity, which were identified per PJM planning analysis criteria. This upgrade may be required on the affected system portion of the tie line along with cost allocation of such upgrade if applicable, in coordination with the affected system. Depending on the affected system, this project may not be contingent on upgrade based on PJM planning analysis criteria, but may be contingent on this upgrade based on the Affected System Operator's planning criteria, provided in the Affected Systems Study Section, herein.

Midcontinent Independent System Operator, Inc. (MISO)No Impact
New York Independent System Operator (NYISO)No Impact
Tennessee Valley Authority (TVA)No Impact
Louisville Gas & Electric (LG&E)No Impact
Duke Energy Carolinas (DUKE)No Impact
Duke Energy Progress – East (CPLE)No Impact
Duke Energy Progress – West (CPLW)No Impact

Affected System - Non-PJM Identified Violations

In accordance with PJM Tariff Part VII, Subpart D, section 310.A and as outlined in PJM Manual 14H, Sections 4.5 and 13, in Phase II of the Cycle, PJM provides the Affected System Operator any updates on the PJM projects that require an Affected Systems Study based on their response at DP1. New Service Requests that require an Affected Systems Study are required to enter into an Affected Systems Study Agreement with the Affected System Operator, as applicable, prior to the close of DP2 or they will be withdrawn from the Cycle.

If the Project Developer already entered into the necessary agreement and the results are available, PJM will supply them in the Phase II SIS report. See below for the status of any required Affected Systems Study. A status of “Pending” means that the study is not yet completed by the Affected System Operator. If your project requires an Affected Systems Study and your results are not provided for Phase II SIS, PJM anticipates providing them in the Phase III SIS per Tariff Part VII.D.312.

Midcontinent Independent System Operator, Inc. (MISO)Identified Impacts
Note: This reflects the Affected System studies results provided by the Affected System Operator. These results may be subject to adjustments based on the outcome of any studies in the remaining phases of the Affected System Operator's Generator Interconnection Process.
Impacted FacilityTransmission OwnerReinforcementCostCost Allocated to AH1-564Scenarios
  • 17REYNOLDS 765.0 - 05GRNTWN 765.0 CKT 1
NIPS Reynolds-Greentown 765 kV
NIPSCO: No mitigation required. Rating Of NIPS-
Owned
Line Portion: SN/SE=9015 MVA/9015 MVA.

AEP: No mitigation required. 8348 MVA SN/SE
$0$0
  • NIPSCO
  • Contingent
  • Wvrich 69.0 - Rochester TP 69.0 CKT 1
NIPS Wvrich - Rochester TP 69 kV
DEI: Rebuild 1 mile of 69kV with 477ACSR/VR2 @
100/120C the ratings assume that NIPSCO terminal
upgrades would not limit our T-Line rating. $1.5M

NIPSCO: DEI mitigations acceptable to remove
constraint. $0
$1,500,000$35,614
  • NIPSCO
New York Independent System Operator (NYISO)Not required
Tennessee Valley Authority (TVA)Not required
Louisville Gas & Electric (LG&E)Not required
Duke Energy Carolinas (DUKE)Not required
Duke Energy Progress – East (CPLE)Not required
Duke Energy Progress – West (CPLW)Not required

System Reinforcements

Based on the Phase II System Impact Study analysis results, this project is contingent on and may have cost responsibility for the following System Reinforcements:

AH1-564 System Reinforcements:
TORTEP IDTitleCategoryAllocated Cost ($USD)Facilities Study
ComEdn5318.1Garden Prarie - Silver Lake R 345 kV: Line rebuild, station bus work & Silver Lake 345kV Breaker ReplacementCost Allocated$34,082,582N/A
ComEdn3515.1Cherry Valley - Garden Prarie 345 kV: Line rebuild, station bus work, & Cherry Valley 345kV breaker replacementCost Allocated$27,509,235N/A
ComEdn9721.0194 Sabrooke Station ConductorCost Allocated$500,000N/A
Grand Total:$62,091,817

Shown below are the details of the cost allocated, contingent, eliminated, topology and potential aggregate contributor reinforcements for this project. Please refer to the System Reinforcement table above and the information below for more detail.


System Reinforcement: n5318.1
Type
Load Flow
TO
ComEd
RTEP ID / TO ID
n5318.1 / ce-012a
Title
Garden Prarie - Silver Lake R 345 kV: Line rebuild, station bus work & Silver Lake 345kV Breaker Replacement
Description
• Rebuild entire 345kV transmission line L.97104 from TSS 971 Prairie to TSS 138 Silver Lake (approximately 24.7 miles). • Replace static wire with OPGW that contains single-mode 48 count fiber. Install 48-ct FDP at TSS 138 Silver Lake and TSS 971 Prairie to account for new OPGW. • Upgrade the existing substation TSS138 Silver Lake by replacing existing circuit breaker 345kV BT 3-4 & associated disconnect switches and replacing the line disconnect switch for 345kV line 97104. • Upgrade relay & protection at 345kV substation TSS 138 Silver Lake to support upgrade of 345kV transmission line, 97104.
Total Cost ($USD)
$163,968,683
Discounted Total Cost ($USD)
$163,968,683
Allocated Cost ($USD)
$34,082,582
Time Estimate
60 Months

Contributor

FacilityContingency
SILVER LK; R-AF2-349 TP 345.0 kV Ckt 1 line(Any)
Rating SetRating TypeRating Value
(All)A1448.0 MVA
(All)B1863.0 MVA
(All)C2232.0 MVA
(All)STE1975.0 MVA
Cost Allocation
ProjectMW ImpactPercent AllocationAllocated Cost ($USD)
AG2-51623.3 MW13.1%$21,556,046
AG2-660 ⧉ Nelson-Electric Junction 345kV - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AG2-660, AH1-044, AH1-150, AH1-151
1.2 MW0.7%$1,099,647
AH1-044 ⧉ Nelson-Electric Junction 345kV - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AG2-660, AH1-044, AH1-150, AH1-151
10.2 MW5.8%$9,455,299
AH1-150 ⧉ Nelson-Electric Junction 345kV - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AG2-660, AH1-044, AH1-150, AH1-151
10.2 MW5.8%$9,455,299
AH1-151 ⧉ Nelson-Electric Junction 345kV - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AG2-660, AH1-044, AH1-150, AH1-151
10.2 MW5.8%$9,455,299
AH1-19663.8 MW36.0%$59,014,397
AH1-34121.4 MW12.1%$19,850,112
AH1-56436.8 MW20.8%$34,082,582

System Reinforcement: n3515.1
Type
Load Flow
TO
ComEd
RTEP ID / TO ID
n3515.1 / ce-017
Title
Cherry Valley - Garden Prarie 345 kV: Line rebuild, station bus work, & Cherry Valley 345kV breaker replacement
Description
• Rebuild entire 345kV transmission line L.15616 from TSS 156 Cherry Valley to TSS 971 Prairie (approximately 15.4 miles). • Replace static wire with dual OPGW that each contain single-mode 48 count fiber. Install two (2) 48-ct FDPs at TSS 156 Cherry Valley and TSS 971 Prairie to account for new OPGW. • Upgrade the existing substation TSS 156 Cherry Valley by upgrading existing 345kV BT 4-7 circuit breaker and associated disconnect switches. • Upgrade SCADA, relay & protection at 345kV substation TSS 156 Cherry Valley to support upgrade of 345kV L.15616.
Total Cost ($USD)
$84,712,245
Discounted Total Cost ($USD)
$84,712,245
Allocated Cost ($USD)
$27,509,235
Time Estimate
50 Months

Contributor

FacilityContingency
CHERRY VA; B-AF2-349 TP 345.0 kV Ckt 1 line(Any)
Rating SetRating TypeRating Value
(All)A1448.0 MVA
(All)B1865.0 MVA
(All)STE1975.0 MVA
Cost Allocation
ProjectMW ImpactPercent AllocationAllocated Cost ($USD)
AG2-51623.3 MW20.5%$17,398,633
AG2-660 ⧉ Nelson-Electric Junction 345kV - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AG2-660, AH1-044, AH1-150, AH1-151
1.2 MW1.0%$887,563
AH1-044 ⧉ Nelson-Electric Junction 345kV - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AG2-660, AH1-044, AH1-150, AH1-151
10.2 MW9.0%$7,631,700
AH1-150 ⧉ Nelson-Electric Junction 345kV - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AG2-660, AH1-044, AH1-150, AH1-151
10.2 MW9.0%$7,631,700
AH1-151 ⧉ Nelson-Electric Junction 345kV - ComEd: This project's cost allocation eligibility was based on the grouped impact of all New Service Requests which shared this POI within this cycle. The following project shared this POI:
AG2-660, AH1-044, AH1-150, AH1-151
10.2 MW9.0%$7,631,700
AH1-34121.4 MW18.9%$16,021,714
AH1-56436.8 MW32.5%$27,509,235

System Reinforcement: n9721.0
Type
Load Flow
TO
ComEd
RTEP ID / TO ID
n9721.0 / CE_NUN_L95201_1
Title
194 Sabrooke Station Conductor
Description
STATION CONDUCTOR UPGRADE AT RSS 194 SABROOKE LINE TERMINAL.
Total Cost ($USD)
$500,000
Discounted Total Cost ($USD)
$500,000
Allocated Cost ($USD)
$500,000
Time Estimate
12 to 16 Months

Contributor

FacilityContingency
SABROOKE ; R-ROCKFORD ;RP 138.0 kV Ckt 1 line(Any)
Rating SetRating TypeRating Value
LLA449.0 MVA
LLB519.0 MVA
SUMA449.0 MVA
SUMB519.0 MVA
SUMC713.0 MVA
SUMSTE560.0 MVA
Cost Allocation
ProjectMW ImpactPercent AllocationAllocated Cost ($USD)
AH1-564150.0 MW100.0%$500,000

System Reinforcement: n9165.0
Type
Load Flow
TO
ComEd
RTEP ID / TO ID
n9165.0 / CE_NUN_L15502.1
Title
Perform TSS 155 Nelson Substation conductor upgrades.
Description
• Update relay settings at 345kV substation TSS 155 Nelson to support upgrade of 345kV L.15502. • Replace the cables between the 345kV BT2-3 circuit breaker and the adjacent 345kV MODs on Bus 2 and Bus 3 with cables that have a minimum rating of 1966 MVA SSTE. • Upgrade TSS 155 Nelson by upgrading existing 345kV L.15502 disconnect switch and 345kV Bus 4 disconnect switches.
Total Cost ($USD)
$1,220,445
Discounted Total Cost ($USD)
$1,220,445
Allocated Cost ($USD)
$0
Time Estimate
36 Months

Potential Aggregate Contributor

Note: Based on PJM cost allocation criteria, AH1-564 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AH1-564 could receive cost allocation. Although AH1-564 may not presently have cost responsibility for this upgrade, AH1-564 is a potential Aggregate Pool Contributor.

FacilityContingency
NELSON ; B-AF2-041 TP 345.0 kV Ckt 1 line(Any)
Rating SetRating TypeRating Value
LLA1679.0 MVA
LLALDR2622.0 MVA
LLSTE2107.0 MVA
SUMA1679.0 MVA
SUMALDR2622.0 MVA
SUMB2058.0 MVA
SUMC2280.0 MVA
SUMSTE2107.0 MVA

Conversion from Impacts into Topology or Eliminated Reinforcements into Region Topology Contingent Reinforcements for AH1-564


AH1-564 Contributions into Topology or Eliminated Reinforcements:
TypeTORTEP ID / TO IDTitleTopo or ElimMW ImpactPercent AllocationCategoryAllocated Cost ($USD)
Contributions into Topology or Eliminated Reinforcement Total:$0
AH1-564 Contingent Region Topology Upgrades:
TORTEP IDTitleCategoryAllocated Cost ($USD)
Region Topology Upgrade Total:$0

Attachments

AH1-564 One Line Diagram

AH1-564 One Line Diagram.jpg
The state in which the generator or merchant transmission facility is located.
The Transmission Owner of the facility where the New Service Request project interconnects to the transmission system.
Winter load flow analysis will be performed starting in Transition Cycle 2.