AH1-746 Phase II System Impact Study Report

v1.00 released 2026-06-03 18:39

Madera - Westover South 115 kV

20.0 MW Capacity / 0.0 MW Energy

Introduction

This Phase II System Impact Study (SIS) Report has been prepared in accordance with the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 310 for New Service Requests (projects) in Transition Cycle 2 (TC2). The Project Developer/Eligible Customer (developer) is CPV Rogue's Wind, LLC, and the Transmission Provider (TP) is PJM Interconnection, LLC (PJM). The interconnected Transmission Owner (TO) is Mid-Atlantic Interstate Transmission, LLC.

Preface

The Phase II System Impact Study is conducted on an aggregate basis within a New Services Request’s Cycle, and results are provided in both (i) a single Cycle summary format and (ii) an individual project-level basis. The Phase II System Impact Study Results (for both the summary and individual reports) will be publicly available on PJM’s website. Project Developers must obtain the results from the website.

In accordance with PJM Manual 14H, section 4.5, PJM takes the following actions during the Phase II System Impact Study:

  1. PJM will retool load flow results from the Phase I System Impact Study (summer peak, winter peak and light load) based on decisions made by Project Developers or Eligible Customers during Decision Point I.
  2. PJM will conduct any required voltage analyses.
  3. PJM will perform short circuit and stability analyses as required.
  4. PJM will coordinate with the Affected System to confirm which projects in the PJM Cycle will require Affected System studies. If the Affected System Operator indicates that an Affected System study is required, PJM will:
    1. Notify the Project Developer or Eligible Customer of the need for an Affected System study and the requirement to execute an Affected System study agreement with the impacted Affected System Operator, and;
    2. Include the results of the Affected System Operator’s Affected System Study in the Phase II System Impact Study results, if applicable and available.
  5. The Phase II System Impact Study Results will be publicly available on PJM’s website. Project Developers and Eligible Customers must obtain the results from the website.

The Transmission Owner takes the following actions during the Phase II System Impact Study:

  1. Verify Interconnection Facilities and Network Upgrades required to accommodate the New Service Request.
  2. Perform a Facilities Study. The Facilities Study in Phase II System Impact Study phase will be for the physical Interconnection Facilities. The Facilities Study requirements are outlined in Attachment C of this manual. The study will be conducted pursuant to Tariff, Part VII, Subpart D, section 307(A)(7) and Tariff, Part VIII, Subpart C, section 404(A)(7).

Decision Point II Requirements

At the close of Phase II System Impact Study, PJM will initiate Decision Point II (DP2). During DP2, the Project Developer will have 30 days to decide whether to proceed with their project. If the Project Developer elects to proceed, they should provide the elements defined in the PJM Open Access Transmission Tariff, Part VII, Subpart D, section 311.A. Additional information on these elements is available in PJM Manual 14H sections 4.6, 6, and 7.

Allowable project modifications at Decision Point II are defined in PJM Open Access Transmission Tariff, Part VII, Subpart D, section 311.B. Additional information regarding allowable project modifications can be found in PJM Manual 14H, section 9.8.

Adverse Test Eligibility

This New Service Request meets the Adverse Study Impact Criteria and has the option to either move forward in the Cycle process or withdraw at DP2 with Readiness Deposits refunded. See Readiness Deposit calculation below.

This section details whether a Project Developer or Eligible Customer qualifies for the Adverse Study Impact clause outlined in the PJM OATT, Part VII, Subpart D, section 311.B and Manual 14H, section 6.2.2. In order to qualify for an Adverse Study Impact at Decision Point II, the Network Upgrade cost from Phase I to Phase II must:

  1. Increase overall by 25% or more
  2. Increases by more than $10,000 per MW (Includes Costs identified in Affected System studies)

If a New Service Request meets the criteria above and chooses to withdraw the request, PJM will refund the cumulative Readiness Deposit amounts paid at the Application Phase and at Decision Point I (RD1 and RD2, respectively).

The below calculations show the computation of this New Service Request's Adverse Study Impact

DP2 Adverse Eligibility = DP2 Adverse Cost Alloc DP1 Adverse Cost Alloc > 1.25 AND ( DP2 Adverse Cost Alloc - DP1 Adverse Cost Alloc ) Project Size > $10,000 per MW
DP2 Adverse Eligibility = $9,380,414 $0 = ∞ AND ( $9,380,414 - $0 ) 20.0 = $469,021 per MW

General

The Project Developer has proposed an uprate to a planned/existing Wind facility located in the Mid-Atlantic Interstate Transmission, LLC zone — Clearfield County, Pennsylvania. This project is an increase to the developer’s AF1-086 project(s), which will share the same Point of Interconnection. The AH1-746 project is a 20.0 MW Capacity only uprate to the previous project(s). The total installed facilities will have a capability of 109.9 MW with 40.54 MW of this output being recognized by PJM as Capacity.

Project Information
New Service Request Number:
AH1-746
Project Name:
Madera - Westover South 115 kV
Project Developer Name:
CPV Rogue's Wind, LLC
State:
Pennsylvania
County:
Clearfield
Transmission Owner:
Mid-Atlantic Interstate Transmission, LLC
MFO:
109.9
MWE:
0.0
MWC:
20.0
Fuel Type:
Wind
Basecase Study Year:
2028

Physical Interconnection Facility Study

Not Required

A Physical Interconnection Facilities Study is not required for this project.

Point of Interconnection

AH1-746 will interconnect on the Mid-Atlantic Interstate Transmission, LLC transmission system by tapping the Madera - Westover South 115 kV line as a CIR only uprate to AF1-086.

Cost Summary

The table below shows a summary of the total cost estimates for this New Service Request project. In Phase II SIS, the interconnected Transmission Owner has performed a facilities study for both the Transmission Owner Interconnection Facilities (TOIF) and Physical Interconnection Network Upgrades. The System Reliability Network Upgrade shown in the table are planning level cost estimates which are subject to change as a result of a facility study performed by the TO during Phase III System Impact Study.

Based on the Phase II SIS results, the AH1-746 project has the following allocation of costs for interconnection. The cost contribution towards Readiness Deposit #3 are also shown below.

Cost Summary
DescriptionCost Allocated to AH1-746Cost Subject to Readiness*Cost Subject to Adverse
Transmission Owner Interconnection Facilities (TOIF)$0$0$0
Other Scope$0$0$0
Option To Build Oversight$0$0$0
Physical Interconnection Network Upgrades
Stand Alone Network Upgrades$0$0$0
Network Upgrades$0$0$0
System Reliability Network Upgrades
Steady State Thermal & Voltage$0$0$0
Transient Stability$0$0$0
Short Circuit$0$0$0
Transmission Owner Analysis
SubRegional$9,380,414$9,380,414$9,380,414
Distribution$0$0$0
Affected System Reinforcements
AFS - PJM Violations$0$0$0
AFS - Non-PJM Violations$0$0$0
Total$9,380,414$9,380,414$9,380,414

* Contributes to calculation for Readiness Deposit #3 (RD3). See Readiness Deposit section of report for additional detail.

Definitions

Transmission Owner Interconnection Facilities: Facilities that are owned, controlled, operated and maintained by the Transmission Owner on the Transmission Owner’s side of the Point of Change of Ownership to the Point of Interconnection, including any modifications, additions or upgrades made to such facilities and equipment, that are necessary to physically and electrically interconnect the Generating Facility with the Transmission System or interconnected distribution facilities.

Stand Alone Network Upgrades: Network Upgrades, which are not part of an Affected System, which a Project Developer may construct without affecting day-to-day operations (e.g. taking a transmission outage) of the Transmission System during their construction.

Network Upgrades: Modifications or additions to transmission-related facilities that are integrated with and support the Transmission Provider’s overall Transmission System for the general benefit of all users of such Transmission System. Network Upgrades have no impact or potential impact on the Transmission System until the final tie-in is complete.

Notes

Note 1: PJM Open Access Transmission Tariff (OATT), Part VII, Subpart D, section 307.5 outlines cost allocation rules. The rules are further clarified in PJM Manual 14H, section 4.2.6. PJM shall identify the New Service Requests in the Cycle contributing to the need for the required Network Upgrades within the Cycle. All New Service Requests that contribute to the need for a Network Upgrade will receive cost allocation for that upgrade pursuant to each New Service Request’s contribution to the reliability violation identified on the transmission system in accordance with PJM Manuals.

Note 2: There will be no inter-Cycle cost allocation for Interconnection Facilities or Network Upgrades identified in the System Impact Study costs identified in a Cycle; all such costs shall be allocated to New Service Requests in that Cycle.

Note 3: For Project Developers with System Reinforcements listed: If this project presents cost allocation to a System Reinforcement indicates $0, then please be aware that as changes to the interconnection process occur, such as other projects withdrawing, reducing in size, etc, the cost responsibilities can change and a cost allocation may be assigned to this project. In addition, although this project presents cost allocation to a System Reinforcement is presently $0, this project may need this system reinforcement completed to be deliverable to the PJM system. If this project desires to come into service prior to completion of the system reinforcement, the Project Developer will need to request PJM to perform an interim study to determine if they would be deliverable for all or a portion of their output for each delivery year until the system reinforcement is complete.

Note 4: Please see the ‘Affected Systems Studies’ section of this Phase II SIS report for details on your project’s need for an Affected Systems Study. If your project requires an Affected Systems Study, the Affected Systems impacts may not be available from the Affected System Operator at the time of the PJM Phase II SIS. Therefore, the cost in this section would not reflect any required upgrades by the Affected System until the study is completed. If your project requires an Affected Systems Study and your results are not provided for Phase II SIS, PJM anticipates providing them in the Phase III SIS per Tariff Part VII.D.312.

Readiness Deposit

Per Tariff Part VII, Subpart D, section 311 (Decision Point II) A.1.b and PJM Manual 14H, section 6.2, Readiness Deposit #3 (RD3) are funds committed by the Project Developer or Eligible Customer based upon the applicable contribution to Network Upgrades as defined below. Readiness Deposits are not used to fund studies nor to offset Security.

During Decision Point II (DP2), the Project Developer or Eligible Customer is required to submit Readiness Deposit #3, which is calculated as 20% of cost allocation for required Phase II Network Upgrades minus Readiness Deposit #1 & Readiness Deposit #2.

Note 1: “Network Upgrades” referred to in the calculation include both (i) the Physical Interconnection Network Upgrades and (ii) the System Reliability Network Upgrades as shown in the Cost Summary table.

Note 2: Readiness Deposit #1 (RD1) = ($4,000 * Project Size (MW))

Note 3: Readiness Deposit #2 (RD2) = 10% of cost allocation for required Network Upgrades minus RD1. Readiness Deposit #2 (RD2) can be zero, but may not be a negative number.

Note 4: Readiness Deposit #3 can be zero, but may not be a negative number.

Readiness Deposit #3 Due for Project AH1-746

Readiness Deposit #3 has been calculated for the project based on the Phase II System Impact Study results and is shown in the table below. This Readiness Deposit #3 must be provided at Decision Point II through either a wire transfer or letter of credit per Manual 14H, Section 6.2.

Readiness Deposit #3 Due for AH1-746
Project ID: AH1-746
20% of cost allocation for Phase II Network Upgrades:(A) $1,876,083
Sum of Readiness Deposit #1 & Readiness Deposit #2 Received:(B) $80,000
Readiness Deposit #3 (RD3) due at DP2:(A) - (B) = $1,796,083
Note: Failure to provide an acceptable form of Readiness Deposit #3 by the end of Decision Point II will result in withdrawal and termination of the New Service Request.

For additional detail regarding Readiness Deposit Refunds, reference PJM Manual 14H, section 6.2.1. The Readiness Deposit Letter of Credit template can be found here.

Transmission Owner Scope of Work

No TO Interconnection Facilities or Physical Network Upgrades are required for this project.

Transmission Owner Analysis

Transmission Owner Identified Network Impacts to Distribution Facilities

None


Transmission Owner Identified Network Impacts to Sub-Regional Facilities

The Transmission Owner identified network impacts to Sub-Regional facilities as follows:

Overloaded ElementContingencyRating [MVA]Final Cycle Loading %Contribution [MW]
200524 26SPANGLER 115.0 - 200533 26SPANGLER 46.0 CKT 2 PN_P1-2_PN-115-047_SRT-A
CONTINGENCY 'PN_P1-2_PN-115-047_SRT-A'  /* GARMAN - GLORY 115KV

  DISCONNECT BRANCH FROM BUS 200801 TO BUS 200507 CKT 1            /* 26GARMAN 115 26GLORY 115

  DISCONNECT BRANCH FROM BUS 200801 TO BUS 200686 CKT 1            /* 26GARMAN 115 26GARMAN 35

END
44.0141.27 %1.9
200947 26CRRLLTWN 46.0 - 202702 26PATTON 46.0 CKT 1 PN_P1-2_PN-115-047_SRT-A
CONTINGENCY 'PN_P1-2_PN-115-047_SRT-A'  /* GARMAN - GLORY 115KV

  DISCONNECT BRANCH FROM BUS 200801 TO BUS 200507 CKT 1            /* 26GARMAN 115 26GLORY 115

  DISCONNECT BRANCH FROM BUS 200801 TO BUS 200686 CKT 1            /* 26GARMAN 115 26GARMAN 35

END
32.0109.0 %2.5

Transmission Owner Identified System Reinforcements on Distribution Facilities

None


Transmission Owner Identified System Reinforcements on Sub-Regional Facilities
AH1-746 Transmission Owner Identified System Reinforcements Cost Breakdown:
TORTEP ID / TO IDTitleMW ImpactPercent AllocationAllocated Cost ($USD)
PENELECn9801.0 / TC2-PN-L01Carrolltown - Patton 46 kV Line reconductor2.5 MW100.0%$9,380,414
Grand Total:$9,380,414
System Reinforcement
TORTEP ID / TO IDTitleTotal Cost
PENELECs3747.1Convert Spangler Substation 46 kV yard into a five-breaker ring bus. Replace 115/46 kV No. 2 Transformer.$14,200,000

Contingent

Note: Although Queue Project AH1-746 may not have cost responsibility for this upgrade, Queue Project AH1-746 may need this upgrade in-service to be deliverable to the PJM system. If Queue Project AH1-746 comes into service prior to completion of the upgrade, Queue Project AH1-746 will need an interim study.

Description: At Spangler: Convert the 46 kV yard into a five-breaker ring bus. Replace No. 2 115/46 kV transformer and install high side circuit breaker. At Garman: Replace line relaying and substation conductor At Carrolltown and Nanty Glo substations: Adjust remote end relaying Spangler No. 2 115/46 kV Transformer Ratings: Before Proposed Solution: 34 / 44 / 49 / 55 MVA (SN/SLTE/WN/WLTE) After Proposed Solution: 58 / 70 / 71 / 81 MVA (SN/SE/WN/WE)

System Reinforcement
TORTEP ID / TO IDTitleTotal Cost
PENELECn9801.0 / TC2-PN-L01Carrolltown - Patton 46 kV Line reconductor$9,380,414

Contributor

Description: Reconductor (Possible Rebuild 2.68 miles of the Ashville - Carrolltown 46 kV Line (Carolltown - Patton line section)

Cost Allocation
ProjectMW ImpactPercent AllocationAllocated Cost ($USD)
AH1-7462.5 MW100.0%$9,380,414

Developer Requirements

The developer is responsible for all design and construction related activities on the developer’s side of the Point of Change in Ownership. FirstEnergy interconnection requirements can be found here.

To the extent that these Applicable Technical Requirements and Standards may conflict with the terms and conditions of the Tariff, the Tariff shall control.

Revenue Metering and SCADA Requirements

PJM Requirements
The developer will be required to install equipment necessary to provide Revenue Metering (KWH, KVARH) and real time data (KW, KVAR) for their generating Resource. See PJM Manual 01, PJM Manual 14D, and PJM Tariff Part IX, Subpart B, Appendix 2, section 8.
Meteorological Data Reporting Requirement
The wind generation facility shall provide the Transmission Provider with site-specific meteorological data including:
  • Wind speed (meters/second) - (Required)
  • Wind direction (decimal degrees from true north) - (Required)
  • Ambient air temperature (Fahrenheit) - (Required)
  • Air Pressure (Hectopascals) - (Required)
  • Humidity (Percent) - (Accepted, not required)
Transmission Owner Requirements
The Project Developer will be required to comply with all interconnected Transmission Owner’s revenue metering requirements located at the following link: PJM - Transmission Owner Engineering & Construction Standards.

Summer Peak Analysis

The New Service Request AH1-746 was evaluated as a 0.0 MW (20.0 MW Capacity) injection in the PENELEC area.

AH1-746 was evaluated as part of a plant. The plant consists of AH1-746. The total Energy output of the plant was evaluated at its maximum seasonal capability of 109.9 MW (0.0 MW under study).

Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.

The following flowgates remain after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

StudyAreaFacility DescriptionContingency NameContingency TypeDC|ACFinal Cycle LoadingRating (MVA)Rating TypeMVA to MitigateMW ContributionDetails
GD2PENELEC/PL
26LEWISTWN-JUNI 230.0 kV Ckt 1 line
PL_10_P12_000085_SRT-A
SingleAC105.09 %618.0B649.44
2.67
GD2PENELEC/PL
26LEWISTWN-JUNI 230.0 kV Ckt 1 line
Base Case
SingleAC104.91 %493.0A517.19
2.6
GD2PENELEC/PL
26LEWISTWN-JUNI 230.0 kV Ckt 1 line
PN_P1-2_PN-115-094_A_SRT-A
SingleAC103.04 %618.0B636.77
2.88

Details for 26LEWISTWN-JUNI 230.0 kV Ckt 1 line l/o PL_10_P12_000085_SRT-A


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area:PENELEC/PL
Facility Description:
26LEWISTWN-JUNI 230.0 kV Ckt 1 line
Contingency Name:
PL_10_P12_000085_SRT-A
Contingency Type:Single
DC|AC:AC
Final Cycle Loading:105.09 %
Rating:618.0 MVA
Rating Type:B
MVA to Mitigate:649.44
MW Contribution:
2.67
Impact of Topology Modeling:
Elimination
Bus #Bus NameTypeMW Contribution
20064926PENNTECH
50/50
0.399
20066526SHAWVL 3
50/50
2.239
20066626SHAWVL 4
50/50
2.256
20071526SHAWVL 1
50/50
1.518
20072226SHAWVL 2
50/50
29.593
20079426CONEMAGH
Adder
0.907
20082826HNSMLK 1
Adder
3.367
20082926HNSMLK 2
Adder
3.367
20083026HNSMLK 3
Adder
3.367
20083126HNSMLK 4
Adder
3.367
20083226HNSMLK 5
Adder
3.367
20083726HOMER C1
Adder
44.015
20083826HOMER C2
Adder
44.149
20083926HOMER C3
Adder
46.738
20088926STNY CRK
Solar/Wind Harmer
0.108
20089026BF_G21_K23
Solar/Wind Harmer
0.029
20089126CSLMN_L13
Solar/Wind Harmer
0.028
20089226LOOKOUT
Solar/Wind Harmer
0.073
20091326SHAW-D
50/50
1.301
20092526R32
Solar/Wind Harmer
0.194
20094526CT_V3-030
Solar/Wind Harmer
0.126
20326126BLOSSBCT
Adder
1.649
20328326MANOR_T86
Adder
0.077
20334926Z1-069 C
Solar/Wind Harmer
0.414
20335026MILZ1-092
Adder
1.393
20335126GROZ1-110
Adder
1.822
20390526W1-045 C
Solar/Wind Harmer
0.08
23732901CHBRG_I12
Adder
1.108
20081226ALY HYDR
50/50
0.379
20091526CHSTN_FL
Solar/Wind Harmer
0.177
203947AF1-006 C
Solar/Wind Harmer
0.026
203948AG1-140 C
Solar/Wind Harmer
0.119
212507AE2-042_GEN
Solar/Wind Helper
0.784
203926AA2-133 GEN
Adder
1.063
20090526Q36
Solar/Wind Harmer
0.626
238219AF1-167 C
Solar/Wind Harmer
0.643
238217AF1-153 C O1
Solar/Wind Harmer
2.164
238206AE2-263_GEN
Solar/Wind Harmer
12.852
238202AE2-262_GEN
Solar/Wind Harmer
13.672
238215AE2-248 C
Solar/Wind Harmer
3.24
216419AE2-001 C
Solar/Wind Harmer
3.94
209054AE2-059 GEN
Solar/Wind Helper
0.04
209071AE2-133 GEN
Solar/Wind Helper
0.041
203980AG1-197 GEN
Solar/Wind Harmer
0.588
203860AG1-193 C
Solar/Wind Harmer
0.415
203857AF2-221 C
Solar/Wind Harmer
0.597
203843AF2-002_GEN
Solar/Wind Harmer
0.531
203841AF2-001_GEN
Solar/Wind Harmer
1.062
203839AF1-321 GEN
Solar/Wind Harmer
1.062
203962AF1-287 GEN
Solar/Wind Harmer
0.791
20120126WRREN CT
Adder
5.903
203818AF1-086 GEN
Solar/Wind Harmer
0.687
203844AF2-092 C
Solar/Wind Harmer
0.787
203813AE2-344_GEN
Solar/Wind Harmer
4.588
203961AE2-224 GEN
Solar/Wind Harmer
0
203987AE2-118 C
Solar/Wind Harmer
3.376
203804AE2-113_GEN
Solar/Wind Harmer
0
203975AE1-071-GEN
Solar/Wind Harmer
0.007
203993AD2-133_GEN1
Solar/Wind Harmer
0.62
203982AD2-062_GEN
Solar/Wind Harmer
5.215
203963AG1-253 GEN
Solar/Wind Harmer
0.189
203859AF2-294 C
Solar/Wind Harmer
0.63
209067AE2-060 GEN
Solar/Wind Helper
0.101
209137AF2-361 C
Solar/Wind Helper
1.69
946691AF1-333 GEN
Solar/Wind Helper
0.224
946731AF1-337 GEN
Solar/Wind Helper
0.224
946741AF1-338 GEN
Solar/Wind Helper
0.224
946751AF1-339 GEN
Solar/Wind Helper
0.224
959421AF2-233 GEN
Solar/Wind Helper
0.225
959431AF2-234 GEN
Solar/Wind Helper
0.45
964051AG1-259 GEN
Solar/Wind Helper
0.034
964061AG1-260 GEN
Solar/Wind Helper
0.034
200642SENECA#1
50/50
1.571
200643SENECA#2
50/50
1.467
200644SENECA#3
50/50
0.201
944781AF1-143 GEN
Solar/Wind Harmer
4.325
946071AF1-272 GEN
Solar/Wind Harmer
0
959471AF2-238 GEN
Solar/Wind Harmer
0.914
960051AF2-296 GEN
Solar/Wind Harmer
2.028
962411AG1-090 GEN
Solar/Wind Harmer
6.186
966771AG1-548 GEN
Solar/Wind Harmer
1.406
966771AG1-548 GEN
Solar/Wind Harmer
1.758
970267AG2-176 GEN
Solar/Wind Harmer
5.91
970305AG2-200 GEN
Solar/Wind Harmer
1.107
970555AG2-356 GEN
Solar/Wind Harmer
0.914
970631AG2-411 GEN
Solar/Wind Harmer
3.718
970647AG2-420 GEN
Solar/Wind Harmer
0.877
970647AG2-420 GEN
Solar/Wind Harmer
0.146
970663AG2-429 GEN
Solar/Wind Harmer
2.854
970663AG2-429 GEN
Solar/Wind Harmer
0.748
970899AG2-561 GEN
Solar/Wind Harmer
1.192
971879AH1-460 GEN
Solar/Wind Harmer
3.623
972169AH1-667 GEN
Solar/Wind Harmer
2.342
20398826ARMNA MT
Solar/Wind Harmer
0.024
941231AE2-117 GEN
Solar/Wind Harmer
3.623
941421AE2-139 GEN
Solar/Wind Harmer
0
957161AF2-010 GEN
Solar/Wind Harmer
3.249
957561AF2-050 GEN
Solar/Wind Harmer
5.014
965121AG1-377 GEN
Solar/Wind Harmer
1.237
965131AG1-378 GEN
Solar/Wind Harmer
1.237
972323AH1-746 GEN
Solar/Wind Harmer
2.667
CBM West 1LTFEXP_CBM-W1->PJM
CBM
18.775
CBM West 2LTFEXP_CBM-W2->PJM
CBM
14.623
CBM South 1LTFEXP_CBM-S1->PJM
CBM
3.9
CBM South 2LTFEXP_CBM-S2->PJM
CBM
2.011
NYPJM->LTFIMP_NY
CLTF
0.22
LGEELTFEXP_LGEE->PJM
CLTF
0.808
WECLTFEXP_WEC->PJM
CLTF
0.467
CPLELTFEXP_CPLE->PJM
CLTF
0.572
TVALTFEXP_TVA->PJM
CLTF
1.008
MECLTFEXP_MEC->PJM
CLTF
1.978
LAGNLTFEXP_LAGN->PJM
CLTF
2.043
SIGELTFEXP_SIGE->PJM
CLTF
0.061

Details for 26LEWISTWN-JUNI 230.0 kV Ckt 1 line l/o Base Case


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area:PENELEC/PL
Facility Description:
26LEWISTWN-JUNI 230.0 kV Ckt 1 line
Contingency Name:
Base Case
Contingency Type:Single
DC|AC:AC
Final Cycle Loading:104.91 %
Rating:493.0 MVA
Rating Type:A
MVA to Mitigate:517.19
MW Contribution:
2.6
Impact of Topology Modeling:
Elimination
Bus #Bus NameTypeMW Contribution
20064926PENNTECH
50/50
0.396
20066526SHAWVL 3
50/50
2.24
20066626SHAWVL 4
50/50
2.256
20071526SHAWVL 1
50/50
1.516
20072226SHAWVL 2
50/50
29.604
20079426CONEMAGH
Adder
0.855
20082826HNSMLK 1
Adder
3.125
20082926HNSMLK 2
Adder
3.125
20083026HNSMLK 3
Adder
3.125
20083126HNSMLK 4
Adder
3.125
20083226HNSMLK 5
Adder
3.125
20083726HOMER C1
Adder
40.627
20083826HOMER C2
Adder
41.24
20083926HOMER C3
Adder
43.658
20088926STNY CRK
Solar/Wind Harmer
0.102
20089026BF_G21_K23
Solar/Wind Harmer
0.027
20089126CSLMN_L13
Solar/Wind Harmer
0.027
20089226LOOKOUT
Solar/Wind Harmer
0.068
20091326SHAW-D
50/50
1.297
20092526R32
Solar/Wind Harmer
0.186
20094526CT_V3-030
Solar/Wind Harmer
0.122
20326126BLOSSBCT
Adder
1.657
20328326MANOR_T86
Adder
0.081
20334926Z1-069 C
Solar/Wind Harmer
0.407
20335026MILZ1-092
Adder
1.402
20335126GROZ1-110
Adder
1.863
20390526W1-045 C
Solar/Wind Harmer
0.082
23732901CHBRG_I12
Adder
1.154
20081226ALY HYDR
50/50
0.38
20091526CHSTN_FL
Solar/Wind Harmer
0.174
203947AF1-006 C
Solar/Wind Harmer
0.025
203948AG1-140 C
Solar/Wind Harmer
0.112
203926AA2-133 GEN
Adder
1.137
20090526Q36
Solar/Wind Harmer
0.62
238219AF1-167 C
Solar/Wind Harmer
0.602
238217AF1-153 C O1
Solar/Wind Harmer
2.146
238206AE2-263_GEN
Solar/Wind Harmer
12.898
238202AE2-262_GEN
Solar/Wind Harmer
13.722
238215AE2-248 C
Solar/Wind Harmer
3.26
216419AE2-001 C
Solar/Wind Harmer
3.964
203980AG1-197 GEN
Solar/Wind Harmer
0.548
203860AG1-193 C
Solar/Wind Harmer
0.387
203857AF2-221 C
Solar/Wind Harmer
0.567
203843AF2-002_GEN
Solar/Wind Harmer
0.502
203841AF2-001_GEN
Solar/Wind Harmer
1.004
203839AF1-321 GEN
Solar/Wind Harmer
1.004
203962AF1-287 GEN
Solar/Wind Harmer
0.739
20120126WRREN CT
Adder
5.738
203818AF1-086 GEN
Solar/Wind Harmer
0.669
203844AF2-092 C
Solar/Wind Harmer
0.756
203813AE2-344_GEN
Solar/Wind Harmer
4.286
203961AE2-224 GEN
Solar/Wind Harmer
0
203987AE2-118 C
Solar/Wind Harmer
3.374
203804AE2-113_GEN
Solar/Wind Harmer
0
203975AE1-071-GEN
Solar/Wind Harmer
0.007
203993AD2-133_GEN1
Solar/Wind Harmer
0.614
203982AD2-062_GEN
Solar/Wind Harmer
5.376
203963AG1-253 GEN
Solar/Wind Harmer
0.179
203859AF2-294 C
Solar/Wind Harmer
0.642
209067AE2-060 GEN
Solar/Wind Helper
0.091
209137AF2-361 C
Solar/Wind Helper
1.532
200642SENECA#1
50/50
1.537
200643SENECA#2
50/50
1.436
200644SENECA#3
50/50
0.197
944781AF1-143 GEN
Solar/Wind Harmer
4.066
946071AF1-272 GEN
Solar/Wind Harmer
0
959471AF2-238 GEN
Solar/Wind Harmer
0.926
960051AF2-296 GEN
Solar/Wind Harmer
2
962411AG1-090 GEN
Solar/Wind Harmer
6.151
966771AG1-548 GEN
Solar/Wind Harmer
1.321
966771AG1-548 GEN
Solar/Wind Harmer
1.651
970267AG2-176 GEN
Solar/Wind Harmer
5.502
970305AG2-200 GEN
Solar/Wind Harmer
1.076
970555AG2-356 GEN
Solar/Wind Harmer
0.926
970631AG2-411 GEN
Solar/Wind Harmer
3.524
970647AG2-420 GEN
Solar/Wind Harmer
0.82
970647AG2-420 GEN
Solar/Wind Harmer
0.137
970663AG2-429 GEN
Solar/Wind Harmer
2.669
970663AG2-429 GEN
Solar/Wind Harmer
0.7
970899AG2-561 GEN
Solar/Wind Harmer
1.136
971879AH1-460 GEN
Solar/Wind Harmer
3.434
972169AH1-667 GEN
Solar/Wind Harmer
2.335
20398826ARMNA MT
Solar/Wind Harmer
0.024
941231AE2-117 GEN
Solar/Wind Harmer
3.627
941421AE2-139 GEN
Solar/Wind Harmer
0
957161AF2-010 GEN
Solar/Wind Harmer
3.051
957561AF2-050 GEN
Solar/Wind Harmer
4.921
965121AG1-377 GEN
Solar/Wind Harmer
1.23
965131AG1-378 GEN
Solar/Wind Harmer
1.23
972323AH1-746 GEN
Solar/Wind Harmer
2.597
CBM NorthLTFEXP_CBM-N->PJM
CBM
0.997
CBM West 1LTFEXP_CBM-W1->PJM
CBM
14.271
CBM West 2LTFEXP_CBM-W2->PJM
CBM
10.938
CBM South 1LTFEXP_CBM-S1->PJM
CBM
2.904
CBM South 2LTFEXP_CBM-S2->PJM
CBM
1.452
LGEELTFEXP_LGEE->PJM
CLTF
0.606
WECLTFEXP_WEC->PJM
CLTF
0.353
CPLELTFEXP_CPLE->PJM
CLTF
0.404
TVALTFEXP_TVA->PJM
CLTF
0.749
MECLTFEXP_MEC->PJM
CLTF
1.488
LAGNLTFEXP_LAGN->PJM
CLTF
1.521
SIGELTFEXP_SIGE->PJM
CLTF
0.046

Details for 26LEWISTWN-JUNI 230.0 kV Ckt 1 line l/o PN_P1-2_PN-115-094_A_SRT-A


This cycle required topology changing upgrades. This base run flowgate was eliminated as a result of the topology changing upgrades.

Base Case Flowgate

Area:PENELEC/PL
Facility Description:
26LEWISTWN-JUNI 230.0 kV Ckt 1 line
Contingency Name:
PN_P1-2_PN-115-094_A_SRT-A
Contingency Type:Single
DC|AC:AC
Final Cycle Loading:103.04 %
Rating:618.0 MVA
Rating Type:B
MVA to Mitigate:636.77
MW Contribution:
2.88
Impact of Topology Modeling:
Elimination
Bus #Bus NameTypeMW Contribution
20064926PENNTECH
50/50
0.438
20066526SHAWVL 3
50/50
2.477
20066626SHAWVL 4
50/50
2.495
20071526SHAWVL 1
50/50
1.677
20072226SHAWVL 2
50/50
32.734
20079426CONEMAGH
Adder
0.955
20082826HNSMLK 1
Adder
3.473
20082926HNSMLK 2
Adder
3.473
20083026HNSMLK 3
Adder
3.473
20083126HNSMLK 4
Adder
3.473
20083226HNSMLK 5
Adder
3.473
20083726HOMER C1
Adder
45.578
20083826HOMER C2
Adder
46.155
20083926HOMER C3
Adder
48.861
20088926STNY CRK
Solar/Wind Harmer
0.114
20089026BF_G21_K23
Solar/Wind Harmer
0.03
20089126CSLMN_L13
Solar/Wind Harmer
0.029
20089226LOOKOUT
Solar/Wind Harmer
0.075
20091326SHAW-D
50/50
1.435
20092526R32
Solar/Wind Harmer
0.208
20094526CT_V3-030
Solar/Wind Harmer
0.135
20326126BLOSSBCT
Adder
1.871
20328326MANOR_T86
Adder
0.093
20334726NME_Y1-047
Adder
1.116
20334926Z1-069 C
Solar/Wind Harmer
0.456
20335026MILZ1-092
Adder
1.592
20335126GROZ1-110
Adder
2.107
20081226ALY HYDR
50/50
0.42
20091526CHSTN_FL
Solar/Wind Harmer
0.193
203947AF1-006 C
Solar/Wind Harmer
0.027
203948AG1-140 C
Solar/Wind Harmer
0.125
203926AA2-133 GEN
Adder
1.322
20090526Q36
Solar/Wind Harmer
0.687
238219AF1-167 C
Solar/Wind Harmer
0.669
238217AF1-153 C O1
Solar/Wind Harmer
2.376
238206AE2-263_GEN
Solar/Wind Harmer
14.253
238202AE2-262_GEN
Solar/Wind Harmer
15.162
238215AE2-248 C
Solar/Wind Harmer
3.598
216419AE2-001 C
Solar/Wind Harmer
4.375
203980AG1-197 GEN
Solar/Wind Harmer
0.607
203860AG1-193 C
Solar/Wind Harmer
0.429
203857AF2-221 C
Solar/Wind Harmer
0.631
203843AF2-002_GEN
Solar/Wind Harmer
0.559
203841AF2-001_GEN
Solar/Wind Harmer
1.118
203839AF1-321 GEN
Solar/Wind Harmer
1.118
203962AF1-287 GEN
Solar/Wind Harmer
0.818
20120126WRREN CT
Adder
6.361
203818AF1-086 GEN
Solar/Wind Harmer
0.743
203844AF2-092 C
Solar/Wind Harmer
0.84
203813AE2-344_GEN
Solar/Wind Harmer
4.744
203961AE2-224 GEN
Solar/Wind Harmer
0
203987AE2-118 C
Solar/Wind Harmer
3.735
203804AE2-113_GEN
Solar/Wind Harmer
0
203975AE1-071-GEN
Solar/Wind Harmer
0.02
203993AD2-133_GEN1
Solar/Wind Harmer
0.68
203963AG1-253 GEN
Solar/Wind Harmer
0.198
203859AF2-294 C
Solar/Wind Harmer
0.734
209067AE2-060 GEN
Solar/Wind Helper
0.084
209137AF2-361 C
Solar/Wind Helper
1.401
200917MEHOOPANY_G
Solar/Wind Harmer
0.166
200642SENECA#1
50/50
1.705
200643SENECA#2
50/50
1.592
200644SENECA#3
50/50
0.218
944781AF1-143 GEN
Solar/Wind Harmer
4.472
946071AF1-272 GEN
Solar/Wind Harmer
0
959471AF2-238 GEN
Solar/Wind Harmer
1.05
960051AF2-296 GEN
Solar/Wind Harmer
2.216
962411AG1-090 GEN
Solar/Wind Harmer
6.808
966771AG1-548 GEN
Solar/Wind Harmer
1.463
966771AG1-548 GEN
Solar/Wind Harmer
1.829
970267AG2-176 GEN
Solar/Wind Harmer
6.097
970305AG2-200 GEN
Solar/Wind Harmer
1.193
970555AG2-356 GEN
Solar/Wind Harmer
1.05
970631AG2-411 GEN
Solar/Wind Harmer
3.923
970647AG2-420 GEN
Solar/Wind Harmer
0.91
970647AG2-420 GEN
Solar/Wind Harmer
0.152
970663AG2-429 GEN
Solar/Wind Harmer
2.968
970663AG2-429 GEN
Solar/Wind Harmer
0.778
970899AG2-561 GEN
Solar/Wind Harmer
1.264
971879AH1-460 GEN
Solar/Wind Harmer
3.824
972169AH1-667 GEN
Solar/Wind Harmer
2.584
20398826ARMNA MT
Solar/Wind Harmer
0.028
941231AE2-117 GEN
Solar/Wind Harmer
4.016
941421AE2-139 GEN
Solar/Wind Harmer
0
957161AF2-010 GEN
Solar/Wind Harmer
3.38
957561AF2-050 GEN
Solar/Wind Harmer
5.458
965121AG1-377 GEN
Solar/Wind Harmer
1.362
965131AG1-378 GEN
Solar/Wind Harmer
1.362
972323AH1-746 GEN
Solar/Wind Harmer
2.883
CBM NorthLTFEXP_CBM-N->PJM
CBM
3.071
CBM West 1LTFEXP_CBM-W1->PJM
CBM
13.841
CBM West 2LTFEXP_CBM-W2->PJM
CBM
10.083
CBM South 1LTFEXP_CBM-S1->PJM
CBM
2.623
CBM South 2LTFEXP_CBM-S2->PJM
CBM
1.041
LGEELTFEXP_LGEE->PJM
CLTF
0.573
WECLTFEXP_WEC->PJM
CLTF
0.338
CPLELTFEXP_CPLE->PJM
CLTF
0.229
TVALTFEXP_TVA->PJM
CLTF
0.669
MECLTFEXP_MEC->PJM
CLTF
1.408
LAGNLTFEXP_LAGN->PJM
CLTF
1.364
SIGELTFEXP_SIGE->PJM
CLTF
0.044
CONTINGENCY 'PL_10_P12_000085_SRT-A'
 DISCONNECT BRANCH FROM BUS 200009 TO BUS 200011 CKT 1   /*JUNI         500.0 - KEYSTONE     500.0
END
CONTINGENCY 'PN_P1-2_PN-115-094_A_SRT-A'
 DISCONNECT BRANCH FROM BUS 200520 TO BUS 203971 CKT 1   /*26ROXBURY    115.0 - AE1-071-POI  115.0
END
200513 to 208004 ckt 1

Winter Peak Analysis

The New Service Request AH1-746 was evaluated as a 0.0 MW (20.0 MW Capacity) injection in the PENELEC area.

AH1-746 was evaluated as part of a plant. The plant consists of AH1-746. The total Energy output of the plant was evaluated at its maximum seasonal capability of 109.9 MW (0.0 MW under study).

Note: The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for single or N-1 contingencies and multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.

The following flowgates remain after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)

Light Load Analysis

The New Service Request AH1-746 was evaluated as a 0.0 MW injection

AH1-746 was evaluated as part of a plant. The total Energy output of the plant was evaluated at its maximum seasonal capability of 109.9 MW (0.0 MW under study).

Note: The capacity portion of Generation Interconnection Requests are evaluated for single or N-1 contingencies. The energy portion, ramped up to a percentage of its full energy output based on season and fuel-specific ramping limits, of Generation Interconnection Requests are evaluated for multiple facility (common mode) contingencies (double circuit tower line, fault with a stuck breaker, and bus fault). For additional details regarding Generator Deliverability, reference PJM Manual 14B, Attachment C, Section C.3.

The following flowgates remain after considering the topology reinforcements required by the cycle.

(No impacts were found for this analysis)

The following flowgates were eliminated after considering the topology reinforcements required by the cycle.

(No flowgates were eliminated after considering the topology reinforcements required by the cycle.)

Short Circuit Analysis

Analysis Complete - No Issues

Based on PJM’s TC2 Phase II Short Circuit Analysis, this project did not contribute >1% fault duty to any previously identified overdutied breakers, nor did it cause any new overdutied breakers.

Please note that in TC2 Phase III, PJM will perform additional analysis including the evaluation of impacts from topology upgrades which may have potential effects on breaker duties not seen in the Phase II analysis.

Stability Analysis

Not Required

PJM has reviewed this project submission and determined that a stability study is not required as this is a CIR only increase with no changes to equipment/electrical parameters (no change to MFO).

Reactive Power Analysis

Not Required

Reactive Power Analysis was not performed. This project is responsible for meeting all applicable power factor requirements based on the project Agreements per PJM’s Tariff, Part IX, Subpart B, App. 2, section 4.6.1.

Steady-State Voltage Analysis

Not Required

A steady state voltage analysis is evaluated on a project-by-project basis and depends on specific project parameters. For this project, a steady state voltage analysis is not required per PJM's Manual 14H, Section 4.5.2.

New Service Request Dependencies

The New Service Requests below are listed in one or more dispatch for the overloads identified in this report. These projects contribute to the loading of the overloaded facilities identified in this report. The percent overload of a facility and cost allocation you may have towards a particular reinforcement could vary depending on the action of other projects. The status of each project at the time of the analysis is presented in the table. This list may change as other projects withdraw or modify their requests. This table is valid for load flow analyses only.

(No dependencies were identified)

Affected System - PJM Identified Violations

As part of PJM's analysis, per Tariff Part VII.G.336 & Manual 14H, Section 13, PJM evaluated the potential impacts on tie line facilities between PJM and an affected system entity, which were identified per PJM planning analysis criteria. This upgrade may be required on the affected system portion of the tie line along with cost allocation of such upgrade if applicable, in coordination with the affected system. Depending on the affected system, this project may not be contingent on upgrade based on PJM planning analysis criteria, but may be contingent on this upgrade based on the Affected System Operator's planning criteria, provided in the Affected Systems Study Section, herein.

Midcontinent Independent System Operator, Inc. (MISO)No Impact
New York Independent System Operator (NYISO)No Impact
Tennessee Valley Authority (TVA)No Impact
Louisville Gas & Electric (LG&E)No Impact
Duke Energy Carolinas (DUKE)No Impact
Duke Energy Progress – East (CPLE)No Impact
Duke Energy Progress – West (CPLW)No Impact

Affected System - Non-PJM Identified Violations

In accordance with PJM Tariff Part VII, Subpart D, section 310.A and as outlined in PJM Manual 14H, Sections 4.5 and 13, in Phase II of the Cycle, PJM provides the Affected System Operator any updates on the PJM projects that require an Affected Systems Study based on their response at DP1. New Service Requests that require an Affected Systems Study are required to enter into an Affected Systems Study Agreement with the Affected System Operator, as applicable, prior to the close of DP2 or they will be withdrawn from the Cycle.

If the Project Developer already entered into the necessary agreement and the results are available, PJM will supply them in the Phase II SIS report. See below for the status of any required Affected Systems Study. A status of “Pending” means that the study is not yet completed by the Affected System Operator. If your project requires an Affected Systems Study and your results are not provided for Phase II SIS, PJM anticipates providing them in the Phase III SIS per Tariff Part VII.D.312.

Midcontinent Independent System Operator, Inc. (MISO)Not required
New York Independent System Operator (NYISO)Not required
Tennessee Valley Authority (TVA)Not required
Louisville Gas & Electric (LG&E)Not required
Duke Energy Carolinas (DUKE)Not required
Duke Energy Progress – East (CPLE)Not required
Duke Energy Progress – West (CPLW)Not required

System Reinforcements

No cost allocated system reinforcements were identified for this project in the Phase II System Impact Study load flow analysis.

Shown below are the details of the cost allocated, contingent, eliminated, topology and potential aggregate contributor reinforcements for this project. Please refer to the System Reinforcement table above and the information below for more detail.


System Reinforcement: s0945.1
Type
Load Flow
TO
PPL
RTEP ID / TO ID
s0945.1
Title
Rebuild the Juniata 230/69 kV Substation
Description
None
Cost Information
Time Estimate
Dec 18 2025

Not Contingent

Note: AH1-746 contributes to the loading of an overloaded facility that is being mitigated by a planned supplemental project. AH1-746 is not contingent on this supplemental project as it is already in-service.

FacilityContingency
26LEWISTWN-JUNI 230.0 kV Ckt 1 line(Any)
Rating SetRating TypeRating Value
(All)A493.0 MVA
(All)B624.0 MVA

System Reinforcement: n6818
Type
Load Flow
TO
PPL
RTEP ID / TO ID
n6818
Title
Rebuild PPL's ~0.9 miles LEWI-JUNI 230kV Line with a summer normal rating of at least 3000 Amps.
Description
The FE portion of the line is rated at 546/666 MVA SN/SE. The PPL portion is limiting, which requires n6818. Reinforcement scope no longer includes any substation scope as Juniata 230kV substation is being rebuilt under S0945.1. Actual PPL facility ratings after upgrade: 815/928 MVA SN/SE
Total Cost ($USD)
$1,900,000
Discounted Total Cost ($USD)
$1,900,000
Allocated Cost ($USD)
$0
Time Estimate
24 to 36 Months

Potential Aggregate Contributor

Note: Based on PJM cost allocation criteria, AH1-746 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AH1-746 could receive cost allocation. Although AH1-746 may not presently have cost responsibility for this upgrade, AH1-746 is a potential Aggregate Pool Contributor.

FacilityContingency
26LEWISTWN-JUNI 230.0 kV Ckt 1 line(Any)
Rating SetRating TypeRating Value
(All)A546.0 MVA
(All)B666.0 MVA

System Reinforcement: n6817.1
Type
Load Flow
TO
PENELEC
RTEP ID / TO ID
n6817.1
Title
Rebuild 24.59 miles of the Lewistown-Juniata 230kV transmission line and upgrade terminal ends
Description
Rebuild 24.59 miles of the Lewistown-Juniata 230kV transmission line and upgrade terminal ends. Expected FE facility ratings: 835/961/1051 MVA SN/SE/SLD. FE upgade n6817.1 required in addition to n6818 (Rebuild of PPL section of line). PPL ratings after n6818 are only 815/928 MVA SN/SE. Expected line ratings after n6818 & n6817.1 will be 815/928 MVA SN/SE.
Total Cost ($USD)
$122,656,404
Discounted Total Cost ($USD)
$122,656,404
Allocated Cost ($USD)
$0
Time Estimate
81 Months

Potential Aggregate Contributor

Note: Based on PJM cost allocation criteria, AH1-746 currently does not receive cost allocation towards this upgrade. As changes to the PJM process occur (such as other projects withdrawing from the cycle or reducing in size) AH1-746 could receive cost allocation. Although AH1-746 may not presently have cost responsibility for this upgrade, AH1-746 is a potential Aggregate Pool Contributor.

FacilityContingency
26LEWISTWN-JUNI 230.0 kV Ckt 1 line(Any)
Rating SetRating TypeRating Value
(All)A815.0 MVA
(All)B928.0 MVA

Conversion from Impacts into Topology or Eliminated Reinforcements into Region Topology Contingent Reinforcements for AH1-746


AH1-746 Contributions into Topology or Eliminated Reinforcements:
TypeTORTEP ID / TO IDTitleTopo or ElimMW ImpactPercent AllocationCategoryAllocated Cost ($USD)
Contributions into Topology or Eliminated Reinforcement Total:$0
AH1-746 Contingent Region Topology Upgrades:
TORTEP IDTitleCategoryAllocated Cost ($USD)
Region Topology Upgrade Total:$0

Attachments

AH1-746 One Line Diagram

AH1-746 One Line Diagram.pdf
The state in which the generator or merchant transmission facility is located.
The Transmission Owner of the facility where the New Service Request project interconnects to the transmission system.
Winter load flow analysis will be performed starting in Transition Cycle 2.