Elwood 345 kV

120.0 MW Capacity / 60.0 MW Energy

Introduction

This System Impact Study Report (SIS) has been prepared in accordance with the PJM Open Access Transmission Tariff, 205, as well as the System Impact Study Agreement between Jackson Generation, LLC, the Interconnection Customer (IC), and PJM Interconnection, LLC (PJM), Transmission Provider (TP). The Interconnected Transmission Owner (ITO) is Commonwealth Edison Company.

Revision 0 – Issued December 2021

Revision 1 – Issued June 2022. The revised report updates the Summer Peak Analysis to include retooled load flow analysis results.

Revision 2 – Issued February 2023. The revised report updates the Transmission Owner scope of work.

 

Preface

The intent of the System Impact is to determine a plan, with approximate cost and construction time estimates, to connect the subject generation interconnection project to the PJM network at a location specified by the Interconnection Customer. As a requirement for interconnection, the Interconnection Customer may be responsible for the cost of constructing: Network Upgrades, which are facility additions, or upgrades to existing facilities, that are needed to maintain the reliability of the PJM system. All facilities required for interconnection of a generation interconnection project must be designed to meet the technical specifications (on PJM web site) for the appropriate transmission owner.

In some instances an Interconnection Customer may not be responsible for 100% of the identified network upgrade cost because other transmission network uses, e.g. another generation interconnection or merchant transmission upgrade, may also contribute to the need for the same network reinforcement. The possibility of sharing the reinforcement costs with other projects may be identified in the Feasibility Study, but the actual allocation will be deferred until the System Impact Study is performed.

The System Impact study estimates do not include the feasibility, cost, or time required to obtain property rights and permits for construction of the required facilities. The project developer is responsible for the right of way, real estate, and construction permit issues. For properties currently owned by Transmission Owners, the costs may be included in the study.

An Interconnection Customer with a proposed new Customer Facility that has a Maximum Facility Output equal to or greater than 100 MW shall install and maintain, at its expense, phasor measurement units (PMUs). See Section 8.5.3 of Appendix 2 to the Interconnection Service Agreement as well as section 4.3 of PJM Manual 14D for additional information.

General

The Interconnection Customer (IC) has proposed an uprate to a planned/existing generating facility located in Will, Illinois. This project is an increase to the Interconnection Customer's AC1-204 project, which will share the same point of interconnection. The queue position is a 60.0 MW uprate (120.0 MW Capacity uprate) to the previous project. The total installed facilities will have a capability of 1260.9 MW with 120.0 MW of this output being recognized by PJM as Capacity. The proposed in-service date for this uprate project is . This study does not imply a TO commitment to this in-service date.

Project Information

Queue Number

AD2-194

Project Name

Elwood 345 kV

Developer Name

Jackson Generation, LLC

State

Illinois

County

Will

Transmission Owner

ComEd

MFO

1260.9 MW

MWE

60.0 MW

MWC

120.0 MW

Fuel Type

Natural Gas

Basecase Study Year

2021

 

Point of Interconnection

AD2-194 will interconnect with on the ComEd transmission system via the 345kV bus at TSS 900 Elwood.

Cost Summary

The project may be responsible for a contribution to the following costs:

Description Total Cost
Attachment Facilities $0
Direct Connect Facilities $0
Non-Direct Connect Facilities $0
Physical Interconnection $350,000
System Reinforcements $19,770,779

Note 1: PJM Open Access Transmission Tariff (OATT) section 217.3A outline cost allocation rules. The rules are further clarified in PJM Manual 14A Attachment B. The allocation of costs for a network upgrade will start with the first Queue project to cause the need for the upgrade. Later queue projects will receive cost allocation contingent on their contribution to the violation and are allocated to the queues that have not closed less than 5 years following the execution of the first Interconnection Service Agreement which identifies the need for this upgrade.

Note 2: For customers with System Reinforcements listed: If your present cost allocation to a System Reinforcement indicates $0, then please be aware that as changes to the interconnection process occur, such as prior queued projects withdrawing from the queue, reducing in size, etc, the cost responsibilities can change and a cost allocation may be assigned to your project. In addition, although your present cost allocation to a System Reinforcement is presently $0, your project may need this system reinforcement completed to be deliverable to the PJM system. If your project comes into service prior to completion of the system reinforcement, an interim deliverability study for your project will be required.

Transmission Owner Scope of Work

The total preliminary cost estimate is given in the table below. These costs do not include CIAC Tax Gross-up.

Physical Interconnection
RTEP ID Description Cost Estimate
(TBD)

ComEd will need to perform project management, engineering review, drawings and system updates, relay setting changes and testing oversight and coordination to accommodate the AD2-194 interconnection.

 

$350,000

Based on the scope of work for the interconnection facilities, it is expected to take a range of 1 to 6 month(s) after the signing of an Interconnection Construction Service Agreement (as this is a FERC connection) and construction kickoff call to complete the installation of the physical connection work. This assumes that there will be no environmental issues with any of the new properties associated with this project, that there will be no delays in acquiring the necessary permits for implementing the defined interconnection work, and that all system outages will be allowed when requested.

The schedule for any required Network Impact Reinforcements will be more clearly identified in future study phases. The estimated time to complete each of the required reinforcements is identified in the "System Reinforcements" section of the report.

Transmission Owner Analysis

None.

Interconnection Customer Requirements

The Interconnection Customer is responsible for all design and construction related activities on the Interconnection Customer’s side of the Point of Interconnection. ComEd interconnection requirements can be found at https://www.pjm.com/planning/design-engineering/totech-standards/private-comed.aspx

 

To the extent that these Applicable Technical Requirements and Standards may conflict with the terms and conditions of the Tariff, the Tariff shall control.

Revenue Metering and SCADA Requirements

PJM Requirements
The Interconnection Customer will be required to install equipment necessary to provide Revenue Metering (KWH, KVARH) and real time data (KW, KVAR) for IC's generating Resource. See PJM Manuals M-01 and M14D, and PJM Tariff Section 8 of Attachment O.

Summer Peak Analysis

The Queue Project was evaluated as a 60.0 MW (Capacity 120.0 MW) injection in the area. Project was evaluated for compliance with applicable reliability planning criteria (PJM, NERC, NERC Regional Reliability Councils, and Transmission Owners). Potential Summer peak period network impacts were as follows:

Area Facility Description Contingency Name Contingency Type DC|AC Initial Loading Final Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Details
CE ELWOOD ; R-GOODINGS ;2R 345.0 kV Ckt 1 line
270737 to 270769 ckt 1
COMED_P2-2_116_GG-345B__4
CONTINGENCY 'COMED_P2-2_116_GG-345B__4'
 DISCONNECT BUS 270770   /*GOODINGS ;4B 345.0
END
Bus AC 103.96 % 106.33 % 1568.0 STE 1667.28 40.11 Details
CE ELWOOD ; B-GOODINGS ;4B 345.0 kV Ckt 1 line
270736 to 270770 ckt 1
COMED_P2-2_116_GG-345R__2
CONTINGENCY 'COMED_P2-2_116_GG-345R__2'
 DISCONNECT BUS 270769   /*GOODINGS ;2R 345.0
END
Bus AC 102.96 % 105.27 % 1568.0 STE 1650.71 39.12 Details
CE ELWOOD ; R-GOODINGS ;2R 345.0 kV Ckt 1 line
270737 to 270769 ckt 1
COMED_P4_116-45-L11613_
CONTINGENCY 'COMED_P4_116-45-L11613_'
 DISCONNECT BUS 270770                             /*GOODINGS ;4B 345.0
 TRIP BRANCH FROM BUS 270666 TO BUS 270664 CKT 1   /*BLUE ISL ;BT 345.0 - BLUE ISL ; B 345.0
 TRIP BRANCH FROM BUS 270666 TO BUS 270926 CKT 1   /*BLUE ISL ;BT 345.0 - WILTON   ; B 345.0
 TRIP BRANCH FROM BUS 270770 TO BUS 270666 CKT 1   /*GOODINGS ;4B 345.0 - BLUE ISL ;BT 345.0
END
Breaker AC 104.71 % 107.09 % 1568.0 STE 1679.11 40.09 Details
CE ELWOOD ; R-GOODINGS ;2R 345.0 kV Ckt 1 line
270737 to 270769 ckt 1
COMED_P4_116-45-TR84___
CONTINGENCY 'COMED_P4_116-45-TR84___'
 DISCONNECT BUS 270770                                          /*GOODINGS ;4B 345.0
 TRIP BRANCH FROM BUS 270770 TO BUS 271564 TO BUS 275368 CKT 1  /*GOODINGS ;4B 345.0 - GOODINGS ; B 138.0 - GOODINGS ;4C  34.5
END
Breaker AC 103.96 % 106.33 % 1568.0 STE 1667.28 40.11 Details
AEP/NIPS 17STILLWELL-05DUMONT 345.0 kV Ckt 1 line
255113 to 243219 ckt 1
AEP_P4_#2978_05DUMONT 765
CONTINGENCY 'AEP_P4_#2978_05DUMONT 765'
 OPEN BRANCH FROM BUS 243206 TO BUS 243207 CKT 1   /*05DUMONT     765.0 - 05GRNTWN     765.0
 OPEN BRANCH FROM BUS 243206 TO BUS 270644 CKT 1   /*05DUMONT     765.0 - WILTON   ;   765.0
END
Breaker AC 111.69 % 112.79 % 1409.0 B 1589.21 18.11 Details
CE ELWOOD ; B-GOODINGS ;4B 345.0 kV Ckt 1 line
270736 to 270770 ckt 1
COMED_P4_116-45-L11614_
CONTINGENCY 'COMED_P4_116-45-L11614_'
 DISCONNECT BUS 270769                             /*GOODINGS ;2R 345.0
 TRIP BRANCH FROM BUS 270667 TO BUS 270665 CKT 1   /*BLUE ISL ;RT 345.0 - BLUE ISL ; R 345.0
 TRIP BRANCH FROM BUS 270667 TO BUS 270927 CKT 1   /*BLUE ISL ;RT 345.0 - WILTON   ; R 345.0
 TRIP BRANCH FROM BUS 270769 TO BUS 270667 CKT 1   /*GOODINGS ;2R 345.0 - BLUE ISL ;RT 345.0
END
Breaker AC 103.78 % 106.1 % 1568.0 STE 1663.58 39.11 Details
CE ELWOOD ; B-GOODINGS ;4B 345.0 kV Ckt 1 line
270736 to 270770 ckt 1
COMED_P4_116-45-TR82___
CONTINGENCY 'COMED_P4_116-45-TR82___'
 DISCONNECT BUS 270769                                          /*GOODINGS ;2R 345.0
 TRIP BRANCH FROM BUS 270769 TO BUS 271565 TO BUS 275324 CKT 1  /*GOODINGS ;2R 345.0 - GOODINGS ; R 138.0 - GOODINGS ;2C  34.5
END
Breaker AC 102.96 % 105.27 % 1568.0 STE 1650.71 39.12 Details
CE ELWOOD ; R-GOODINGS ;2R 345.0 kV Ckt 1 line
270737 to 270769 ckt 1
COMED_P1-2_345-L11620_B-S
CONTINGENCY 'COMED_P1-2_345-L11620_B-S'
 TRIP BRANCH FROM BUS 270736 TO BUS 270770 CKT 1   /*ELWOOD   ; B 345.0 - GOODINGS ;4B 345.0
END
Single AC 107.1 % 109.69 % 1568.0 STE 1719.93 39.27 Details
CE ELWOOD ; R-GOODINGS ;2R 345.0 kV Ckt 1 line
270737 to 270769 ckt 1
Base Case Single AC 104.28 % 106.76 % 1201.0 A 1282.19 29.27 Details
CE ELWOOD ; B-GOODINGS ;4B 345.0 kV Ckt 1 line
270736 to 270770 ckt 1
COMED_P1-2_345-L11622_R-S
CONTINGENCY 'COMED_P1-2_345-L11622_R-S'
 TRIP BRANCH FROM BUS 270737 TO BUS 270769 CKT 1   /*ELWOOD   ; R 345.0 - GOODINGS ;2R 345.0
END
Single AC 106.26 % 108.81 % 1568.0 STE 1706.17 39.09 Details
CE ELWOOD ; B-GOODINGS ;4B 345.0 kV Ckt 1 line
270736 to 270770 ckt 1
Base Case Single AC 102.25 % 104.68 % 1201.0 A 1257.21 28.88 Details

Summer Potential Congestion due to Local Energy Deliverability

(No impacts were found for this analysis)

Winter Peak Analysis

At this time winter peak analysis not required for this project.

Winter Potential Congestion due to Local Energy Deliverability

At this time winter peak analysis not required for this project.

Light Load Analysis

At this time light load analysis not required for this project.

Light Load Potential Congestion due to Local Energy Deliverability

At this time light load analysis not required for this project.

Short Circuit Analysis

PJM Short Circuit Analysis did not identify any new overduty breakers or >3% contribution to previously identified overduty breakers.

Stability Analysis

No mitigation was found to be required due to transient stability.

Reactive Power Analysis

This project meets the power factor requirements.

Steady-State Voltage Analysis

Steady State Voltage analysis is not required for this queue project at this time.

Queue Dependencies

The Queue Projects below are listed in one or more dispatch for the overloads identified in your report. These projects contribute to the loading of the overloaded facilities identified in your report. The percent overload of a facility and cost allocation you may have towards a particular reinforcement could vary depending on the action of these earlier projects. The status of each project at the time of the analysis is presented in the table. This list may change as earlier projects withdraw or modify their requests. This table is valid for load flow analyses only.

Queue Number Project Name Status
AA1-018 Powerton-Goodings Grove In Service
AA1-040 Morris In Service
AA1-146 Nelson Under Construction
AA2-030 Nelson Under Construction
AA2-123 Marengo 34kV In Service
AB1-089 Byron-Wayne 345kV #1 Suspended
AB1-122 Kendall-Tazewell & Dresden-Mole Creek Partially in Service - Under Construction
AB2-047 Brokaw-Pontiac Midpoint In Service
AB2-191 Mendota Hills In Service
AC1-033 Kewanee 138 kV Engineering & Procurement
AC1-109 Aurora 345kV In Service
AC1-110 Aurora 138kV Partially in Service - Under Construction
AC1-111 Aurora 138kV In Service
AC1-113 Rockford In Service
AC1-114 Rockford II In Service
AC1-142A Joliet In Service
AC1-168 Kewanee-Streator Engineering & Procurement
AC1-185 Lee County In Service
AC1-204 Elwood In Service
AC1-214 Crescent Ridge In Service
AC2-115 Rockford In Service
AC2-116 Rockford II In Service
AC2-117 University Park North Engineering & Procurement
AC2-154 Davis Creek 138kV Engineering & Procurement
AD1-013 Twombly Road 138kV Engineering & Procurement
AD1-016 Marengo Suspended
AD1-031 Kewanee - E.D. Edwards 138 kV Active
AD1-067 Mendota Hills In Service
AD1-098 Dixon - McGirr 138 kV Active
AD1-100 Loretto-Wilton 345 kV & Braidwood-Davis Creek 345 kV Active
AD1-129 Belvidere 34 kV Suspended
AD1-133 Pontiac MidPoint-Dresden Active
AD2-038 Powerton Active
AD2-047 Davis Creek 138 kV Active
AD2-060 Davis Creek 138kV Engineering & Procurement
AD2-066 Mazon-Crescent Ridge 138 kV Active
AD2-102 Wempletown 345 kV Active
AD2-134 Shady Oaks Active
AD2-172 Lena 138kV Under Construction
AD2-214 * Rock Falls-Garden Plains Active
U3-031 Lincoln Generating Facility In Service
W4-086 Goose Lake 34.5kV Deactivated
X3-005 Wildwood 12kV In Service
Y3-013 Zion Energy Center In Service
Z1-106 West Chicago 34kV Deactivated
Z1-107 Joliet 34kV Deactivated
Z1-108 McHenry 34kV In Service
Z2-087 Pontiac MidPoint-Brokaw 345kV In Service

* = Queue Project is after AD2-194 in queue order. Withdrawal of this project is unlikely to affect cost allocation for AD2-194.

Affected Systems

Midcontinent Independent System Operator (MISO) Final Results - No Impacts
New York Independent System Operator (NYISO) Not required
Tennessee Valley Authority (TVA) Not required
Louisville Gas & Electric (LG&E) Not required
Duke Progress Energy (DUKE) Not required
Carolina Power & Light East (CPLE) Not required
Carolina Power & Light West (CPLW) Not required

System Reinforcements

AD2-194 Cost Breakdown:
RTEP ID Title MW Impact Percent Allocation Allocated Cost ($USD)
n5915 Elwood - Goodings B 345 kV line Reconductoring 39.1 MW 33.9% $10,448,104
n5916 Elwood - Goodings R 345 kV Line Reconductoring 39.3 MW 29.6% $9,322,676
Grand Total: $19,770,780
RTEP ID Title Total Cost Time Estimate
n4058 Sag Mitigation Work on the Stillwell - Dumont 345 kV line $1,971,000 12 - 13 Months

Note: Based on PJM cost allocation criteria, AD2-194 currently does not receive cost allocation towards this upgrade. As changes to the PJM queue process occur (such as prior queued projects withdrawing from the queue, reducing in size, etc.) AD2-194 could receive cost allocation. Although Queue Project AD2-194 may not presently have cost responsibility for this upgrade, Queue Project AD2-194 may need this upgrade in-service to be deliverable to the PJM system. If Queue Project AD2-194 comes into service prior to completion of the upgrade, Queue Project AD2-194 will need an interim study.

Description: A sag study was performed on this section of conductor. The following reinforcements were identified by the sag study and will be required to mitigate the overload: AEP will replace structure #20 with a single circuit custom steel pole structure and structure #24 with a custom steel H-frame structure on the Stillwell - Dumont 345 kV circuit. The replacements include removal of the two (2) existing lattice structures. AEP will also modify one (1) existing lattice structure, replacing a bottom swing angle bracket with a 3” tee. SE rating will be 1718 MVA limited by a Dumont wave trap. (Provided by AEP per AD1-098 FAC study).

Flowgates Addressed by this Reinforcement
Facility Contingency
05DUMONT-17STILLWELL 345.0 kV Ckt 1 line (Any)
New Ratings
Facility Rating Set Rating Type Rating Value
05DUMONT-17STILLWELL 345.0 kV Ckt 1 line (All) B 1718.0 MVA
RTEP ID Title Total Cost Time Estimate
n5915 Elwood - Goodings B 345 kV line Reconductoring $30,831,127 0 Months

AD2-194 is a Contributor

Description: The upgrade will be to Reconductor 18.1 miles of the line with 2156 kcmil ACSR (84/19) Str Bluebird conductor and replace some towers.

Flowgates Addressed by this Reinforcement
Facility Contingency
ELWOOD ; B-GOODINGS ;4B 345.0 kV Ckt 1 line (Any)
New Ratings
Facility Rating Set Rating Type Rating Value
ELWOOD ; B-GOODINGS ;4B 345.0 kV Ckt 1 line (All) A 1334.0 MVA
ELWOOD ; B-GOODINGS ;4B 345.0 kV Ckt 1 line (All) ALDR 2084.0 MVA
ELWOOD ; B-GOODINGS ;4B 345.0 kV Ckt 1 line (All) B 1726.0 MVA
ELWOOD ; B-GOODINGS ;4B 345.0 kV Ckt 1 line (All) STE 1837.0 MVA
Cost Allocation
Queue Project MW Impact Percent Allocation Allocated Cost ($USD)
AC1-204 59.0 MW 51.1% $15,769,714
AD1-133 17.3 MW 15.0% $4,613,310
AD2-194 39.1 MW 33.9% $10,448,104
RTEP ID Title Total Cost Time Estimate
n5916 Elwood - Goodings R 345 kV Line Reconductoring $31,529,018 0 Months

AD2-194 is a Contributor

Description: The upgrade will be to Reconductor 18.1 miles of the line with 2156 kcmil ACSR (84/19) Str Bluebird conductor and replace some towers.

Flowgates Addressed by this Reinforcement
Facility Contingency
ELWOOD ; R-GOODINGS ;2R 345.0 kV Ckt 1 line (Any)
New Ratings
Facility Rating Set Rating Type Rating Value
ELWOOD ; R-GOODINGS ;2R 345.0 kV Ckt 1 line (All) A 1334.0 MVA
ELWOOD ; R-GOODINGS ;2R 345.0 kV Ckt 1 line (All) ALDR 2084.0 MVA
ELWOOD ; R-GOODINGS ;2R 345.0 kV Ckt 1 line (All) B 1726.0 MVA
ELWOOD ; R-GOODINGS ;2R 345.0 kV Ckt 1 line (All) STE 1837.0 MVA
Cost Allocation
Queue Project MW Impact Percent Allocation Allocated Cost ($USD)
AC1-204 76.7 MW 57.8% $18,208,536
AD1-133 16.8 MW 12.7% $3,997,806
AD2-194 39.3 MW 29.6% $9,322,676