AE2-316 System Impact Study Report

v0.06 released 2023-01-26 16:12

Brookville-Squab Hollow 138 kV

41.2 MW Capacity / 90.0 MW Energy

Introduction

This System Impact Study Report (SIS) has been prepared in accordance with the PJM Open Access Transmission Tariff, 205, as well as the System Impact Study Agreement between Walden Solar PA Jefferson LLC, the Interconnection Customer (IC), and PJM Interconnection, LLC (PJM), Transmission Provider (TP). The Interconnected Transmission Owner (ITO) is Appalachian Power.

Revision 1: January 2023 - The report was revised to reflect the results of PJM's retool study. Final scope and cost estimates will be provided as part of the facilities study.

Preface

The intent of the System Impact is to determine a plan, with approximate cost and construction time estimates, to connect the subject generation interconnection project to the PJM network at a location specified by the Interconnection Customer. As a requirement for interconnection, the Interconnection Customer may be responsible for the cost of constructing: Network Upgrades, which are facility additions, or upgrades to existing facilities, that are needed to maintain the reliability of the PJM system. All facilities required for interconnection of a generation interconnection project must be designed to meet the technical specifications (on PJM web site) for the appropriate transmission owner.

In some instances an Interconnection Customer may not be responsible for 100% of the identified network upgrade cost because other transmission network uses, e.g. another generation interconnection or merchant transmission upgrade, may also contribute to the need for the same network reinforcement. The possibility of sharing the reinforcement costs with other projects may be identified in the Feasibility Study, but the actual allocation will be deferred until the System Impact Study is performed.

The System Impact study estimates do not include the feasibility, cost, or time required to obtain property rights and permits for construction of the required facilities. The project developer is responsible for the right of way, real estate, and construction permit issues. For properties currently owned by Transmission Owners, the costs may be included in the study.

General

The Interconnection Customer (IC), has proposed a generating facility located in Jefferson County, Pennsylvania. The installed facilities will have a total capability of 90.0 MW with 41.2 MW of this output being recognized by PJM as Capacity. The proposed in-service date for this project is Thursday, December 31, 2020. This study does not imply a TO commitment to this in-service date.

Project Information
Queue Number AE2-316
Project Name Brookville-Squab Hollow 138 kV
Developer Name Walden Solar PA Jefferson LLC
State Pennsylvania
County Jefferson
Transmission Owner APS
MFO 90.0 MW
MWE 90.0 MW
MWC 41.2 MW
Fuel Type Solar
Basecase Study Year 2022
Point of Interconnection

AE2-316 will interconnect with the West Penn Power transmission system by constructing a new 138 kV three-breaker ring bus substation and looping the Squab Hollow – Brookville 138 kV line into the new station.  The new substation will be located approximately 22 miles from Squab Hollow substation. The IC will be responsible for acquiring all easements, properties, and permits that may be required to construct both the new interconnection switching station and the associated facilities. The IC will also be responsible for the rough grade of the property and an access road to the proposed three-breaker ring bus site. This project will also require Non-Direct Connection upgrades at Squab Hollow, Brookville, and Armstrong substations.

 

Attachment 1 shows a one-line diagram of the proposed primary Direct Connection facilities for the AE2-316 generation project to connect to the FirstEnergy (“FE”) transmission system. Attachment 2 provides the proposed location for the point of interconnection. IC will be responsible for constructing all the facilities on its side of the POI, including the Attachment Facilities which connect the generator to the FE transmission system’s Direct Connection facilities.

 

Cost Summary

The project may be responsible for a contribution to the following costs:

Description Total Cost
Attachment Facilities $242,700
Direct Connect Facilities $6,155,700
Non-Direct Connect Facilities $1,615,400
Physical Interconnection $0
System Reinforcements $0

Note 1: PJM Open Access Transmission Tariff (OATT) section 217.3A outline cost allocation rules. The rules are further clarified in PJM Manual 14A Attachment B. The allocation of costs for a network upgrade will start with the first Queue project to cause the need for the upgrade. Later queue projects will receive cost allocation contingent on their contribution to the violation and are allocated to the queues that have not closed less than 5 years following the execution of the first Interconnection Service Agreement which identifies the need for this upgrade.

Note 2: For customers with System Reinforcements listed: If your present cost allocation to a System Reinforcement indicates $0, then please be aware that as changes to the interconnection process occur, such as prior queued projects withdrawing from the queue, reducing in size, etc, the cost responsibilities can change and a cost allocation may be assigned to your project. In addition, although your present cost allocation to a System Reinforcement is presently $0, your project may need this system reinforcement completed to be deliverable to the PJM system. If your project comes into service prior to completion of the system reinforcement, an interim deliverability study for your project will be required.

Transmission Owner Scope of Work

AE2-316 will interconnect with the West Penn Power transmission system by constructing a new 138 kV three-breaker ring bus substation and looping the Squab Hollow – Brookville 138 kV line into the new station. The new substation will be located approximately 22 miles from Squab Hollow substation. The IC will be responsible for acquiring all easements, properties, and permits that may be required to construct both the new interconnection switching station and the associated facilities. The IC will also be responsible for the rough grade of the property and an access road to the proposed three-breaker ring bus site. This project will also require Non–Direct Connection upgrades at Squab Hollow, Brookville, and Armstrong substations.

The total preliminary cost estimate is given in the table below. These costs do not include CIAC Tax Gross-up.

Attachment Facilities:
RTEP ID Description Cost Estimate
(TBD)

Build a terminal position to the new three-breaker ring bus to connect AE2-316.

$242,700
Direct Connect Facilities:
RTEP ID Description Cost Estimate
(TBD)

Build a three-breaker ring bus to connect AE2-316 generation.

$5,812,300
(TBD)

Project Management, Construction Management, Real Estate, Forestry, and Environmental.

$343,400
Non-Direct Connect Facilities:
RTEP ID Description Cost Estimate
(TBD)

Loop the Brookville-Squab Hollow 138 kV line into the proposed AE2-316 ring bus.

$447,000
(TBD)

Two (2) wideband wave traps for AE2-316 interconnect at Brookville substation.

$532,300
(TBD)

Engineering oversight of Power Producer's specification and installation of revenue metering equipment at generation facility. Support set up of Power Producer-owned metering in FE's MV90 and other systems.

$3,400
(TBD)

Anti-Islanding upgrade at Squab Hollow.

$316,400
(TBD)

Anti-Islanding upgrade at Armstrong.

$266,200
(TBD)

Estimated SCADA work at Squab Hollow & Armstrong substations to support wave trap & relay installations.

$50,100

Based on the scope of work for the interconnection facilities, it is expected to take a range of 19 to 19 month(s) after the signing of an Interconnection Construction Service Agreement (as this is a FERC connection) and construction kickoff call to complete the installation of the physical connection work. This assumes that there will be no environmental issues with any of the new properties associated with this project, that there will be no delays in acquiring the necessary permits for implementing the defined interconnection work, and that all system outages will be allowed when requested.

The schedule for any required Network Impact Reinforcements will be more clearly identified in future study phases. The estimated time to complete each of the required reinforcements is identified in the "System Reinforcements" section of the report.

Transmission Owner Analysis
Interconnection Customer Requirements

System Protection

The IC must design its Customer Facilities in accordance with all applicable standards, including the standards in FE’s “Requirements for Transmission Connected Facilities” document located at: http://www.pjm.com/planning/design-engineering/to-tech-standards/private-firstenergy.aspx. Preliminary Protection requirements will be provided as part of the Facilities Study. Detailed Protection Requirements will be provided once the project enters the construction phase.

The original one-line diagram provided by the IC depicted the correct GSU transformer winding configuration, as outlined in section 14.2.6 of FE’s “Requirements for Transmission Connected Facilities.” The GSU transformer must have a wye grounded connection on the high (utility) side and a delta connection on the low (generator) side connection.

Compliance Issues and Interconnection Customer Requirements

The proposed Customer Facilities must be designed in accordance with FE’s “Requirements for Transmission Connected Facilities” document located at: http://www.pjm.com/planning/design-engineering/to-tech-standards/private-firstenergy.aspx. In particular, the IC is responsible for the following:

  1. The purchase and installation of a fully rated 138 kV circuit breaker to protect the AE2-316 generator lead line. A single circuit breaker must be used to protect this line; if the project has several GSU transformers, the individual GSU transformer breakers cannot be used to protect this line.
  2. The purchase and installation of the minimum required FE generation interconnection relaying and control facilities. This includes over/under voltage protection, over/under frequency protection, and zero sequence voltage protection relays.
  3. The purchase and installation of supervisory control and data acquisition (“SCADA”) equipment to provide information in a compatible format to the FE Transmission System Control Center.
  4. Compliance with the FE and PJM generator power factor and voltage control requirements.
  5. The execution of a back-up service agreement to serve the customer load supplied from the AE2-316 generation project metering point when the units are out-of-service. This assumes the intent of the IC is to net the generation with the load.

The IC will also be required to meet all PJM, ReliabilityFirst, and NERC reliability criteria and operating procedures for standards compliance. For example, the IC will need to properly locate and report the over and under voltage and over and under frequency system protection elements for its units as well as the submission of the generator model and protection data required to satisfy the PJM and ReliabilityFirst audits.  Failure to comply with these requirements may result in a disconnection of service if the violation is found to compromise the reliability of the FE system.

 

Power Factor Requirements

The IC shall design its Solar Customer Facility with the ability to maintain a power factor of at least 0.95 leading (absorbing VARs) to 0.95 lagging (supplying VARs) measured at the high side of the facility substation transformer(s) connected to the FE transmission system.

 

Revenue Metering and SCADA Requirements
PJM Requirements
The Interconnection Customer will be required to install equipment necessary to provide Revenue Metering (KWH, KVARH) and real time data (KW, KVAR) for IC's generating Resource. See PJM Manuals M-01 and M14D, and PJM Tariff Section 8 of Attachment O.
Meteorological Data Reporting Requirement
The solar generation facility shall provide the Transmission Provider with site-specific meteorological data including:
  • Temperature (degrees Fahrenheit)
  • Atmospheric Pressure (hectopascals)
  • Irradiance
  • Forced outage data
Interconnection Transmission Owner Requirements
The IC will be required to comply with all Interconnected Transmission Owner's revenue metering requirements for generation interconnection customers located at the following link: PJM - Transmission Owner Engineering & Construction Standards.

PJM Transmission Network Impacts Analysis

Summer Peak Analysis

The Queue Project was evaluated as a 90.0 MW (Capacity 41.2 MW) injection in the area. Project was evaluated for compliance with applicable reliability planning criteria (PJM, NERC, NERC Regional Reliability Councils, and Transmission Owners). Potential Summer peak period network impacts were as follows:

Area Facility Description Contingency Name Contingency Type DC|AC Initial Loading Final Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Details
PENELEC 26GLADE-26WARREN 230.0 kV Ckt 1 line
200593 to 200811 ckt 1
PN-P2-3-PN-345-003A-B10
CONTINGENCY 'PN-P2-3-PN-345-003A-B10'
 DISCONNECT BRANCH FROM BUS 200826 TO BUS 200595 CKT 1   /*26HANDSMLK   345.0 - 26WAYNE      345.0
 OPEN BRANCH FROM BUS 200598 TO BUS 200595 CKT 2         /*26WAYNE      115.0 - 26WAYNE      345.0
END
Breaker DC 108.42 % 109.66 % 621.0 B 680.99 9.05 Details
PENELEC 26GLADE-26WARREN 230.0 kV Ckt 1 line
200593 to 200811 ckt 1
PN-P2-3-PN-345-003A-B45
CONTINGENCY 'PN-P2-3-PN-345-003A-B45'
 DISCONNECT BRANCH FROM BUS 200826 TO BUS 200595 CKT 1   /*26HANDSMLK   345.0 - 26WAYNE      345.0
 OPEN BRANCH FROM BUS 200598 TO BUS 200595 CKT 1         /*26WAYNE      115.0 - 26WAYNE      345.0
END
Breaker DC 108.38 % 109.62 % 621.0 B 680.74 9.04 Details
PENELEC 26KEYSTONE-STAR568 230.0/1.0 kV Ckt 3 transformer
200810 to 999428 ckt 3
PN-P2-3-PN-500-001F
CONTINGENCY 'PN-P2-3-PN-500-001F'
 DISCONNECT BRANCH FROM BUS 200011 TO BUS 200005 CKT 1          /*KEYSTONE     500.0 - CONEM-GH     500.0
 DISCONNECT BRANCH FROM BUS 200011 TO BUS 200810 TO BUS 200907 CKT 4 /*KEYSTONE     500.0 - 26KEYSTONE   230.0 - 26KEYSTN#4    20.0
 REDUCE BUS 200011 SHUNT BY 100 PERCENT                         /*KEYSTONE     500.0
END
Breaker DC 100.06 % 101.47 % 612.0 B 621.0 9.97 Details
Summer Potential Congestion due to Local Energy Deliverability

PJM also studied the delivery of the energy portion of this interconnection request. Any problems identified below are likely to result in operational restrictions to the project under study. The developer can proceed with network upgrades to eliminate the operational restriction at their discretion by submitting a Merchant Transmission Interconnection request.

Note: Only the most severely overloaded conditions are listed below. There is no guarantee of full delivery of energy for this project by fixing only the conditions listed in this section. With a Transmission Interconnection Request, a subsequent analysis will be performed which shall study all overload conditions associated with the overloaded element(s) identified.

Area Facility Description Contingency Name Contingency Type DC|AC Initial Loading Final Loading Rating (MVA) Rating Type MVA to Mitigate MW Contribution Details
PENELEC 26HOMER CT-26SHELOCTA 230.0 kV Ckt 1 line
200767 to 200795 ckt 1
ATSI_P1-2_CEI-345-719T_SRT-A
CONTINGENCY 'ATSI_P1-2_CEI-345-719T_SRT-A'
 DISCONNECT BRANCH FROM BUS 239082 TO BUS 200599 CKT 1   /*02S8-ATT     345.0 - 26ERIE W     345.0
END
OP AC 105.08 % 106.52 % 917.0 B 976.79 15.27 Details
PENELEC 26HOMER CT-26SHELOCTA 230.0 kV Ckt 1 line
200767 to 200795 ckt 1
Base Case

            
OP AC 103.88 % 105.29 % 731.0 A 769.67 11.81 Details
PENELEC 26E.TWANDA-26CANYON 230.0 kV Ckt 1 line
200675 to 200924 ckt 1
Base Case

            
OP AC 109.7 % 110.72 % 515.0 A 570.21 6.38 Details
PENELEC 26E.TWANDA-26CANYON 230.0 kV Ckt 1 line
200675 to 200924 ckt 1
PL:03:P12:001029
CONTINGENCY 'PL:03:P12:001029'
 DISCONNECT BRANCH FROM BUS 208009 TO BUS 208054 CKT 1   /*LACK         230.0 - LAEN         230.0
 DISCONNECT BUS 208054                                   /*LAEN         230.0
END
OP AC 109.63 % 110.48 % 615.0 B 679.45 6.33 Details
PENELEC 26GLADE-26WARREN 230.0 kV Ckt 1 line
200593 to 200811 ckt 1
Base Case

            
OP DC 106.96 % 108.26 % 520.0 A 562.95 7.89 Details
PENELEC 26CANYON-26N.MESHPN 230.0 kV Ckt 1 line
200924 to 200706 ckt 1
Base Case

            
OP AC 102.32 % 103.29 % 546.0 A 563.96 6.38 Details
Winter Peak Analysis

At this time winter peak analysis not required for this project.

Winter Potential Congestion due to Local Energy Deliverability

At this time winter peak analysis not required for this project.

Light Load Analysis

At this time light load analysis not required for this project.

Light Load Potential Congestion due to Local Energy Deliverability

At this time light load analysis not required for this project.

Short Circuit Analysis

PJM Short Circuit Analysis did not identify any new overduty breakers or >3% contribution to previously identified overduty breakers.

Stability Analysis

Stability Analysis complete with no violations. See complete stability report under Attachments.

Reactive Power Analysis

Reactive Power Analysis complete with all power factor requirements met. Refer to stability report under Attachments for more details.

Steady-State Voltage Analysis

Steady State Voltage analysis is not required for this queue project at this time.

Queue Dependencies

The Queue Projects below are listed in one or more dispatch for the overloads identified in your report. These projects contribute to the loading of the overloaded facilities identified in your report. The percent overload of a facility and cost allocation you may have towards a particular reinforcement could vary depending on the action of these earlier projects. The status of each project at the time of the analysis is presented in the table. This list may change as earlier projects withdraw or modify their requests. This table is valid for load flow analyses only.

Queue Number Project Name Status
AB1-092 Moshannon-East Towanda 230kV Engineering & Procurement
AB1-160 Gold-Sabinsville 115kV In Service
AC1-025 Dale Summit In Service
AD2-055 Moshannon-East Towanda 230 kV Engineering & Procurement
AD2-113 South Bend 500kV In Service
AD2-133 Eagle Valley 115kV Engineering & Procurement
AE1-123 Emlenton 34.5 kV Under Construction
AE1-128 Bedford North-Wills Mounain 115 kV Active
AE1-160 Venango 34.5 kV Engineering & Procurement
AE2-001 Nittany-Zion 46 kV Engineering & Procurement
AE2-055 Shingletown-Boalsburg 46 kV Engineering & Procurement
AE2-074 Potter 46 kV Engineering & Procurement
AE2-113 Farmers Valley-Ridgeway 115 kV Active
AE2-117 ABW Tap-Alexandria 46 kV Engineering & Procurement
AE2-118 ABW Tap-Williamsburg 46 kV Engineering & Procurement
AE2-120 Graymont-Zion 46 kV Active
AE2-121 Milesburg-Tanney Junction 46 kV Suspended
AE2-126 Dubois-Curwensville 34.5 kV Under Construction
AE2-129 Philipsburg-Clarence 34.5 kV Partially in Service - Under Construction
AE2-131 Philipsburg-Karthaus 34.5 Engineering & Procurement
AE2-139 East Towanda-Grover 230 kV Active
AE2-224 Bearrock-Johnstown 230 kV Under Construction
AE2-248 Fillmore-Thompson Farm 46 kV Engineering & Procurement
AE2-249 Bedford North-Pennsylvania Hollow 23 kV Suspended
AE2-262 Moshannon-Milesburg 230 kV Active
AE2-263 Moshannon-Milesburg 230 kV Active
AE2-264 Altoona-Raystown 230 kV Active
AE2-299 Erie East 230 kV Active
AE2-344 * Edinboro South-Venango Junction 115 kV Active
V3-030 St. Benedict-Patton 46kV In Service
Y1-033 Penn Mar-Rock Wood 115kV In Service
Z1-069 Gold-Sabinsville 115kV In Service
Z2-108 Meyersdale North 115kV In Service

* = Queue Project is after AE2-316 in queue order. Withdrawal of this project is unlikely to affect cost allocation for AE2-316.

Affected Systems
Midcontinent Independent System Operator (MISO) Not required
New York Independent System Operator (NYISO) Not required
Tennessee Valley Authority (TVA) Not required
Louisville Gas & Electric (LG&E) Not required
Duke Progress Energy (DUKE) Not required
System Reinforcements
RTEP ID Title Total Cost Time Estimate
b3017.1 Rebuild Glade to Warren 230 kV line with hi-temp conductor and substation terminal upgrades. 11.53 miles. $42,400,000 Jun 01 2025

Note: Although Queue Project AE2-316 may not have cost responsibility for this upgrade, Queue Project AE2-316 may need this upgrade in-service to be deliverable to the PJM system. If Queue Project AE2-316 comes into service prior to completion of the upgrade, Queue Project AE2-316 will need an interim study.

Description: New conductor will be 1033 ACSS. Existing conductor is 1033 ACSR. This baseline project is a ‘Pending Resolution’ baseline originally identified for generator deactivations that have since withdrawn. Some queue projects are eligible to take advantage of this project as briefed at TEAC. This upgrade is 'On Hold' until an eligible queue project has a fully executed ISA with this upgrade. Only queue projects up through AF1-074 can take advantage of this upgrade while it is in an 'on hold' status.

Flowgates Addressed by this Reinforcement:
Facility Contingency
26GLADE-26WARREN 230.0 kV Ckt 1 line (Any)
New Ratings:
Facility Rating Set Rating Type Rating Value
26GLADE-26WARREN 230.0 kV Ckt 1 line (All) A 855.0 MVA
26GLADE-26WARREN 230.0 kV Ckt 1 line (All) B 984.0 MVA
RTEP ID Title Total Cost Time Estimate
b3017.2 Glade substation terminal upgrades. Replace bus conductor, wave traps, and relaying. $50,000 Jun 01 2025

Note: Although Queue Project AE2-316 may not have cost responsibility for this upgrade, Queue Project AE2-316 may need this upgrade in-service to be deliverable to the PJM system. If Queue Project AE2-316 comes into service prior to completion of the upgrade, Queue Project AE2-316 will need an interim study.

Description: This baseline project is a ‘Pending Resolution’ baseline originally identified for generator deactivations that have since withdrawn. Some queue projects are eligible to take advantage of this project as briefed at TEAC. This upgrade is 'On Hold' until an eligible queue project has a fully executed ISA with this upgrade. Only queue projects up through AF1-074 can take advantage of this upgrade while it is in an 'on hold' status.

Flowgates Addressed by this Reinforcement:
Facility Contingency
26GLADE-26WARREN 230.0 kV Ckt 1 line (Any)
New Ratings:
Facility Rating Set Rating Type Rating Value
26GLADE-26WARREN 230.0 kV Ckt 1 line (All) A 855.0 MVA
26GLADE-26WARREN 230.0 kV Ckt 1 line (All) B 984.0 MVA
RTEP ID Title Total Cost Time Estimate
b3017.3 Warren substation terminal upgrades. Replace bus conductor, wave traps, and relaying. $50,000 Jun 01 2025

Note: Although Queue Project AE2-316 may not have cost responsibility for this upgrade, Queue Project AE2-316 may need this upgrade in-service to be deliverable to the PJM system. If Queue Project AE2-316 comes into service prior to completion of the upgrade, Queue Project AE2-316 will need an interim study.

Description: This baseline project is a ‘Pending Resolution’ baseline originally identified for generator deactivations that have since withdrawn. Some queue projects are eligible to take advantage of this project as briefed at TEAC. This upgrade is 'On Hold' until an eligible queue project has a fully executed ISA with this upgrade. Only queue projects up through AF1-074 can take advantage of this upgrade while it is in an 'on hold' status.

Flowgates Addressed by this Reinforcement:
Facility Contingency
26GLADE-26WARREN 230.0 kV Ckt 1 line (Any)
New Ratings:
Facility Rating Set Rating Type Rating Value
26GLADE-26WARREN 230.0 kV Ckt 1 line (All) A 855.0 MVA
26GLADE-26WARREN 230.0 kV Ckt 1 line (All) B 984.0 MVA
RTEP ID Title Total Cost Time Estimate
s1736 Replace the existing 351 MVA 500/230 kV transformer and install a 500kV high side breaker. (ISD 12/31/2019) $21,700,000 Dec 31 2019

Note: Although Queue Project AE2-316 may not have cost responsibility for this upgrade, Queue Project AE2-316 may need this upgrade in-service to be deliverable to the PJM system. If Queue Project AE2-316 comes into service prior to completion of the upgrade, Queue Project AE2-316 will need an interim study.

Flowgates Addressed by this Reinforcement:
Facility Contingency
26KEYSTONE-STAR568 230.0/1.0 kV Ckt 3 transformer (Any)
26KEYSTONE-STAR568 230.0/1.0 kV Ckt 3 transformer (Any)
KEYSTONE-STAR568 500.0/1.0 kV Ckt 3 transformer (Any)
New Ratings:
Facility Rating Set Rating Type Rating Value
26KEYSTONE-STAR568 230.0/1.0 kV Ckt 3 transformer (All) A 910.0 MVA
26KEYSTONE-STAR568 230.0/1.0 kV Ckt 3 transformer (All) B 1086.0 MVA
26KEYSTONE-STAR568 230.0/1.0 kV Ckt 3 transformer (All) A 910.0 MVA
26KEYSTONE-STAR568 230.0/1.0 kV Ckt 3 transformer (All) B 1086.0 MVA
KEYSTONE-STAR568 500.0/1.0 kV Ckt 3 transformer (All) A 910.0 MVA
KEYSTONE-STAR568 500.0/1.0 kV Ckt 3 transformer (All) B 1086.0 MVA
Attachments

One-Line Diagram

AE2-316 One-Line.png

Project Location

AE2-316 Project Location.png