AG1-039 System Impact Study Report

v1.00 released 2024-08-02 10:14

Galion 138 kV II

23.52 MW Capacity / 56.0 MW Energy

Introduction

This project is eligible for the Expedited Study process per PJM Tariff Part VII, Subpart B, section 304 and will follow the Expedited Study Process rules outlined in PJM Manual 14H, Attachment I.3.4.

Projects in the Expedited Process will receive a retooled System Impact Study report with the Transition Cycle #1 projects (AE1-AG1) removed from the base case model used for their study. This System Impact Study (SIS) report has been prepared for the AG1-039 project using the updated case model. PJM performed reliability analysis for the project based on the serial study approach using the legacy Generator Deliverability Study method outlined in Manual 14B, Attachment C.3 (Revision 51 of M14B). Summer peak and light load load flow analysis was performed. Short circuit and dynamic stability impacts were also analyzed.

The interconnected Transmission Owner (TO) for this project is American Transmission Systems, Incorporated. The TO has provided their updated TO analysis results on the lower voltage system based on their own criteria.

This System Impact Study report summarizes both the PJM and TO analysis results for your project.

Note: This updated SIS report does not include any Physical Interconnection Facilities scope or cost estimates from the TO. As this project is in the Expedited Process, a Facilities Study will be conducted by the TO (and any affected Transmission Owner(s)) for updated Physical Interconnection Facilities and System Reinforcement (Network Upgrade) costs. The Facilities Study will be issued to the Project Developers along with the Generator Interconnection Agreement (GIA) as part of the Expedited Process.

General

The developer has proposed an uprate to a planned/existing Solar generating facility located in the American Transmission Systems, Incorporated zone — Morrow County, Ohio. This project is an increase to the developer's AF2-150 project, which will share the same point of interconnection. The AG1-039 project is a 56.0 MW uprate (23.52 MW Capacity uprate) to the previous project. The total installed facilities will have a capability of 144.0 MW with 60.48 MW of this output being recognized by PJM as Capacity.

Project Information

New Service Request Number

AG1-039

Project Name

Galion 138 kV II

Developer Name

Blossom Solar, LLC

State

Ohio

County

Morrow

Transmission Owner

American Transmission Systems, Incorporated

MFO

144.0 MW

MWE

56.0 MW

MWC

23.52 MW

Fuel Type

Solar

Basecase Study Year

2024

 

Point of Interconnection

AG1-039 will interconnect with the ATSI on transmission system as an uprate to AF2-150 which is a direct connection at the Galion 138 kV substation.

Attachment 1 shows a one-line diagram of the proposed primary interconnection facilities for the AG1-039 generation project to connect to the FirstEnergy (“FE”) Transmission System.

 

Transmission Owner Analysis

FE performed an analysis of its underlying transmission <100 kV system. The AG1-039 project did not contribute to any overloads on the FE Transmission <100 kV System.

Summer Peak Analysis

The Project was evaluated as a 56.0 MW (Capacity 23.52 MW) injection in the ATSI area. Project was evaluated for compliance with applicable reliability planning criteria (PJM, NERC, NERC Regional Reliability Councils, and Transmission Owners). Potential Summer peak period network impacts were as follows:

(No impacts were found for this analysis)

Summer Potential Congestion due to Local Energy Deliverability

PJM also studied the delivery of the energy portion of this interconnection request. Any problems identified below are likely to result in operational restrictions to the project under study. The developer can proceed with network upgrades to eliminate the operational restriction at their discretion by submitting an Upgrade Request.

Note: Only the most severely overloaded conditions are listed below. There is no guarantee of full delivery of energy for this project by fixing only the conditions listed in this section.

(No impacts were found for this analysis)

Light Load Analysis

At this time light load analysis not required for this project.

Light Load Potential Congestion due to Local Energy Deliverability

At this time light load analysis not required for this project.

Short Circuit Analysis

PJM Short Circuit Analysis did not identify any new overduty breakers or >3% contribution to previously identified overduty breakers.

Stability Analysis

Generator Interconnection Request AG1-039 is for a 56 MW uprate to previous queue project AF2-150. This AG1-039 solar facility consists of additional 30 2.2 MVA SMA SC 2200 inverters. The total Maximum Facility Output (MFO) combining AG1-039 and AF2-150 is 144 MW with a total of 76 inverters connecting to the FirstEnergy (“FE”) transmission system, ATSI zone. The AG1-039 solar facility will be located in Morrow County, Ohio.

The AG1-039 generation project will directly interconnect into the existing Galion 138 kV substation via a 0.02 Miles 138 kV transmission line in the FirstEnergy (“FE”) (ATSI zone) transmission system. The Point of Interconnection (POI) will be at an ATSI installed dead-end structure at the Galion station yard.

This report describes a dynamic simulation analysis of AG1-039 as part of the overall system impact study. The load flow scenario for the analysis was based on the RTEP 2024 peak load case, modified to include applicable queue projects. AG1-039 has been dispatched online at maximum power output, with approximately unity power factor at the high side of the GSU, 1.01 pu voltage at the generator terminal, and 1.00 pu voltage at the POI bus.

AG1-039 was tested for compliance with NERC, PJM, Transmission Owner, and other applicable criteria. 127 contingencies were studied, each with a 20 second simulation time period (with 1.0 second initial run prior to any events). Studied faults included:

a)  Steady state operation (Category P0);

b)  Three phase faults with normal clearing time on the intact network (Category P1);

c)  Single phase to ground faults with delayed clearing due to a stuck breaker (Category P4);

d)  Single phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure (Category P5);

e)  Single phase to ground faults with normal clearing for common structure (Category P7).

For all 127 fault contingencies tested on the 2024 peak load case:

a)  AG1-039 was able to ride through the faults.

b)  Post-contingency oscillations were positively damped with a damping margin of at least 3%.

c)  Following fault clearing, all bus voltages recover to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

d)  No other transmission element trips, other than those either directly connected or designed to trip as a consequence of that fault.

 

No mitigation was found to be required for the project. 

Reactive Power Analysis

AG1-039 meets the PJM reactive power requirement maintaining a power factor of at least 0.95 leading to 0.95 lagging at the high side of the facility transformer. 

Steady-State Voltage Analysis

Steady State Voltage analysis is not required for this project at this time.

New Service Request Dependencies

The Projects below are listed in one or more dispatch for the overloads identified in your report. These projects contribute to the loading of the overloaded facilities identified in your report. The percent overload of a facility and cost allocation you may have towards a particular reinforcement could vary depending on the action of these earlier projects. The status of each project at the time of the analysis is presented in the table. This list may change if any earlier projects withdraw. This table is valid for load flow analyses only.

New Service Requests Dependencies
Project Project Name Status

Affected Systems

Midcontinent Independent System Operator (MISO) Not required
New York Independent System Operator (NYISO) Not required
Tennessee Valley Authority (TVA) Not required
Louisville Gas & Electric (LG&E) Not required
Duke Energy Carolinas (DUKE) Not required
Duke Energy Progress – East (CPLE) Not required
Duke Energy Progress – West (CPLW) Not required

System Reinforcements

The AG1-039 project may be responsible for a contribution to the following estimated System Reinforcement (Network Upgrade) costs as shown below. The Network Upgrades listed below are required to alleviate a reliability criteria violation identified in the Network Impact analysis that PJM has performed for this System Impact Study. No physical Interconnection Facilities costs are included in this cost table.

Note 1: PJM Open Access Transmission Tariff (OATT) Part VI, section 217.3A outlines cost allocation rules for the Expedited Process projects. These rules are further clarified in PJM Manual 14A, Attachment B.

Note 2: To Project Developers with System Reinforcements listed: If your present cost allocation to a System Reinforcement indicates $0, then please be aware that if a prior project in the Expedited Process withdraws from the cycle, the cost responsibilities can change and a cost allocation may be assigned to your project. In addition, although the cost allocation to a System Reinforcement is presently $0, your project may need this system reinforcement completed to be deliverable to the PJM system. If your project desires to possibly come into service prior to completion of the system reinforcement, you would need to request an interim deliverability study to determine if all or a portion of your project would be deliverable.

Attachments

The one line included in this refreshed System Impact Study report was originally developed prior to the Transition Date. Therefore, not all verbiage on the one line may align with the current Tariff definitions. An updated one line diagram will be provided in the Facilities Study report for the Expedited Process projects.

One-Line

AG1-039 One-Line.png