New Service Request Deposits Agreement Type Readiness Deposit Study Deposit Generating Facility $4,000 per MW is required. The MW values used in the calculation is the greater of (1) and (2) specified in the application: (1) MW energy (e.g., Maximum Facility Output) (2) MW capacity (e.g., Capacity Interconnection Rights) Study deposit required is as follows: 0 - 20MW — $75,000 > 20 - 50MW — $200,000 > 50 - 100MW — $250,000 > 100 - 250MW — $300,000 > 250 - 750MW — $350,000 > 750MW — $400,000 Merchant Transmission Facility Specifications $4,000 per MW is required. The MW values used in the calculation is the greater of (1) and (2) specified in the application: (1) MW energy (e.g., Maximum Facility Output) (2) MW capacity (e.g., Capacity Interconnection Rights) Study deposit required is as follows: 0 - 20MW — $75,000 > 20 - 50MW — $200,000 > 50 - 100MW — $250,000 > 100 - 250MW — $300,000 > 250 - 750MW — $350,000 > 750MW — $400,000 Surplus Interconnection Request $10,000 plus $100 for each MW requested provided that the maximum total deposit shall not exceed $110,000. Upgrade Application and Studies Agreement A Study Deposit in the amount of $150,000 is required.