Committees & Groups

Issue Details

Wildfire Procedure

Due to reoccurring and increased wildfire risk, this issue is being brought forward to incorporate wildfire procedures into Manual 13.

Proposed Timeline

Issue initiated: 1.9.2025
Work begins: 12.5.2024
Target Completion: 1.9.2025
Actual Completion: 1.9.2025

Issue Details

Stakeholder Body Operating Committee
Facilitator Patel, Anita
Subject Matter Expert Hatch, Kevin
MRC Approval Date 2.20.2025
Problem Statement/
Issue Charge First Read
12.5.2025
Issue Catalyst PJM
Issue Status Awaiting Implementation & FERC Approval
Manual Changes Yes
  • Stakeholder Process Step

  • Completed Approved
  • Completed Education
  • Completed Interest
  • Completed Design
  • Completed Options
  • Completed Packages
  • Completed Consensus
  • Completed Review
  • Completed Completed