Critical Issue Fast Path - Large Load Additions

The PJM Board of Managers initiated the Critical Issue Fast Path (CIFP) stakeholder process by letter PDF on August 8, 2025 to address the development of reliability-focused solutions to ensure large load additions can continue to be integrated rapidly and reliably, without causing resource inadequacy, and while recognizing jurisdictional boundaries and data center relationships with existing Load Serving Entities and/or Electric Distribution Companies. The Board requested stakeholder participation in the CIFP to inform a filing with the Federal Energy Regulatory Commission by December 2025.

Chair: Michele Greening
Secretary: Matt Connolly

During the meeting, if you are experiencing issues with connectivity or teleconference, please contact Meeting Support. For registration issues, contact PJM.


Date
PJM Board Letter Regarding Implementation of Critical Issue Fast Path Process for Large Load Additions PDF
8.8.2025
Comments Submitted in Response to Board Request on Scope & PJM Request for Feedback on Initial Conceptual Proposal PDF
8.29.2025

Meeting Materials

 10.1.2025 - Critical Issue Fast Path - Large Load Additions

9.26.2025 Agenda  PDF
9.26.2025 Agenda-doc  DOC
9.29.2025 Item 01 - Draft Minutes - CIFP - Large Load Additions Stage 1 Meeting - 9.15.2025  PDF
9.29.2025 Item 01 - Draft Minutes - CIFP - Large Load Additions Stage 1 Meeting - 9.15.2025  PDF
9.26.2025 Item 02 - CIFP-LLA Work Plan  PDF
9.26.2025 Item 02 - CIFP-LLA Work Plan  PDF
9.26.2025 Item 03 - Critical Issue Fast Path - Large Load Additions - Issue Charge - Revised with Stakeholder Feedback  PDF
10.1.2025 Item 03 - Critical Issue Fast Path - Large Load Additions - Issue Charge - Revised with Stakeholder Feedback - Post Meeting  PDF
9.26.2025 Item 03 - Critical Issue Fast Path - Large Load Additions - Revised Problem Statement  PDF
10.1.2025 Item 03 - Critical Issue Fast Path - Large Load Additions - Revised Problem Statement - Post Meeting  PDF
9.26.2025 Item 04 - CIFP - LLA Updates - PJM Presentation  PDF
9.26.2025 Item 05B - CIFP - LLA Proposal Options - Advanced Power Presentation  PDF
9.26.2025 Item 05 - Critical Issue Fast Path - Large Load Additions - Options and Packages Matrix  XLS
10.2.2025 Item 05 - Critical Issue Fast Path - Large Load Additions - Options and Packages Matrix - Post Meeting  XLS
10.2.2025 Item 05 - Critical Issue Fast Path - Large Load Additions - Options and Packages Matrix - Post Meeting  XLS
9.26.2025 Item 05D - Joint Stakeholder Options - Amazon Calpine Constellation Google Microsoft Talen  PDF
9.29.2025 Item X - Informational Only - Abe Silverman - Sue Glatz Proposed Options - 10.14.2025 Presentation  PDF
9.29.2025 Item X - Informational Only - Abe Silverman - Sue Glatz Proposed Options - 10.14.2025 Presentation  PDF
9.29.2025 Item X - Informational Only - Brattle-Eolian Proposed Options for Bilateral Capacity Portfolios - 10.14.2025 Presentation  PDF

Materials submitted to PJM by PJM Members or any other stakeholder for posting on PJM.com shall not imply support or endorsement by PJM Interconnection.