DER Regulation Market Only Participation at NEM Customer Sites

This work is intended to address a specific issue that prohibits behind-the-meter (BTM) battery energy storage systems (BESS) participating in the Regulation Market from injecting into the distribution grid in PJM zones with Net Energy Metering (NEM). The sponsor seeks near-term allowance of injection from these BTM BESS in NEM zones solely for participation in the Regulation Market.

Proposed Timeline

Issue initiated: 12.2.2024
Work begins: 1.10.2025
Target Completion: 8.20.2025
Actual Completion: TBD

Issue Details

Stakeholder Body Distributed Resources Subcommittee
Facilitator Dropkin, Ilyana
Problem Statement/
Issue Charge First Read
11.4.2024
Issue Catalyst Intelligent Generation
Issue Status Awaiting Senior Committee Approval
Manual Changes No
Agreement Changes Open Access Transmission Tariff
  • Stakeholder Process Step

  • Completed Approved
  • Completed Education
  • Completed Interest
  • Completed Design
  • Completed Options
  • Completed Packages
  • Completed Consensus
  • In Progress Review
  • Not Started Completed