Site Control Modification Clarification

PJM seeks to clarify site control modification language in Manual 14H and correct the image currently in M14H Exhibit 10 in Section 4.9.2 "Generator Interconnection into Existing TO Substation."

Proposed Timeline

Issue initiated: 1.23.2025
Work begins: 12.3.2024
Target Completion: 12.3.2024
Actual Completion: 12.3.2024

Issue Details

Stakeholder Body Planning Committee
Facilitator Carroll, Rebecca
Subject Matter Expert Thompson, Jonathan
Problem Statement/
Issue Charge First Read
11.6.2024
Issue Catalyst PJM
Issue Status Awaiting Senior Committee Approval
Manual Changes Yes
  • Stakeholder Process Step

  • Completed Approved
  • Completed Education
  • Completed Interest
  • Completed Design
  • Completed Options
  • Completed Packages
  • Completed Consensus
  • In Progress Review
  • Not Started Completed