Issue Details

Cost Allocation Issues Related to DOE Orders

This issue is exclusively intended to address the specific matter of aligning a selected cost allocation structure to the scope of any future DOE Section 202(c) Orders, in order to facilitate compensation to the resource owner for the continued operation of the resources specified in such Order.

Proposed Timeline

Issue initiated: 6.18.2025
Work begins: 7.9.2025
Target Completion: 10.23.2025
Actual Completion: TBD

Issue Details

Stakeholder Body DOE 202c Cost Allocation Senior Task Force
Facilitator Anders, David
Subject Matter Expert Morelli, Lisa K.
Problem Statement/
Issue Charge First Read
6.18.2025
Issue Catalyst PJM
Issue Status Evaluation in Progress
Manual Changes No
  • Stakeholder Process Step

  • Completed Approved
  • In Progress Education
  • Not Started Interest
  • Not Started Design
  • Not Started Options
  • Not Started Packages
  • Not Started Consensus
  • Not Started Review
  • Not Started Completed