Transition Cycle 1
v1.00 released 2025-09-18 09:40
New Service Requests
System Impact Study Executive Summary Report
Transition Cycle 1 Phase III
Introduction
This Phase III System Impact Study executive summary report has been prepared in accordance with the PJM Open Access Transmission Tariff Part VII, Subpart D, section 312. This report presents an executive summary of Phase III System Impact Study results for New Service Requests (projects) in Transition Cycle 1.
Preface
The Phase III System Impact Study is conducted on an aggregate basis within a New Services Request’s Cycle, and results are provided in both (i) a single Cycle summary format and (ii) an individual project-level basis. The Phase III System Impact Study Results (for both the summary and individual reports) will be publicly available on PJM’s website. Project Developers must obtain the results from the website.
In accordance with PJM Manual 14H, section 4.7, PJM takes the following actions during the Phase III System Impact Study:
- PJM studies each New Service Request on a summer peak, winter peak[1] and light load RTEP base case study. The case year is dependent on the new services cycle under study. PJM will identify the base case year to be used in the study of a specific cycle on its website.
- PJM will perform load flow, short circuit, and stability analysis during the Phase III System Impact Study.
- In Phase III of the Cycle, PJM will coordinate with Affected System Operators to conduct any studies required to determine the impact of a New Service Request on any Affected System.
- The Phase III System Impact Study results will be publicly available on PJM’s website. Project Developers and Eligible Customers must obtain the results from the website.
- PJM will tender draft final agreements to Project Developers or Eligible Customers.
New Services Request List
PJM received 130 New Service Requests in Transition Cycle 1, Phase III with a combined Maximum Facility Output (MFO) of 19,353.8 MW and 9,891.3 MW as Capacity Interconnection Rights (CIRs). All of these New Service Requests are listed in table below.
| Project ID | Project Name / POI | State[2] | Status | Transmission Owner[3] | Maxiumum Facility Output (MFO in MW) | MW Energy (MWE) | MW Capacity (MWC) | Project Type | Resource Type | Facilities Study |
|---|---|---|---|---|---|---|---|---|---|---|
| AE1-092 | Blue Jacket-Kirby 138 kV | Ohio | Active | The Dayton Power and Light Company | 206.55 | 206.6 | 96.4 | Generation Interconnection | Solar | |
| AE1-114 | Maryland-Lancaster 138 kV | Illinois | Active | Commonwealth Edison Company | 150.0 | 150.0 | 34.0 | Generation Interconnection | Wind | |
| AE1-148 | Kerr Dam-Ridge Rd 115 kV | Virginia | Active | Virginia Electric and Power Company (Dominion Virginia Power) | 90.0 | 90.0 | 54.0 | Generation Interconnection | Solar | |
| AE1-172 | Loretto-Wilton Center | Illinois | Active | Commonwealth Edison Company | 255.0 | 255.0 | 44.88 | Generation Interconnection | Wind | |
| AE2-156 | Yadkin 115 kV | Virginia | Active | Virginia Electric and Power Company (Dominion Virginia Power) | 100.0 | 100.0 | 100.0 | Generation Interconnection | Storage | |
| AE2-173 | McLean 345 kV | Illinois | Active | Commonwealth Edison Company | 250.0 | 50.0 | 50.0 | Generation Interconnection | Storage | |
| AE2-185 | Gladys DP-Stonemill Switching Station 69 kV | Virginia | Active | Virginia Electric and Power Company (Dominion Virginia Power) | 60.0 | 60.0 | 36.0 | Generation Interconnection | Solar | |
| AE2-187 | Shockoe DP-Chatham 69 kV | Virginia | Active | Virginia Electric and Power Company (Dominion Virginia Power) | 60.0 | 60.0 | 36.0 | Generation Interconnection | Solar | |
| AE2-223 | McLean 345 kV | Illinois | Active | Commonwealth Edison Company | 350.0 | 150.0 | 19.5 | Generation Interconnection | Wind | |
| AE2-261 | Kincaid-Pana 345 kV | Illinois | Active | Commonwealth Edison Company | 299.0 | 299.0 | 179.4 | Generation Interconnection | Solar | |
| AE2-283 | Gladys-Stone Mill 69 kV | Virginia | Active | Virginia Electric and Power Company (Dominion Virginia Power) | 53.0 | 53.0 | 28.0 | Generation Interconnection | Solar | |
| AE2-291 | Grit DP-Perth 115 kV | Virginia | Active | Virginia Electric and Power Company (Dominion Virginia Power) | 102.0 | 102.0 | 61.2 | Generation Interconnection | Solar | |
| AE2-308 | Three Forks-Dale 138 kV | Kentucky | Active | East Kentucky Power Cooperative, Inc. | 100.0 | 100.0 | 60.0 | Generation Interconnection | Solar | |
| AE2-321 | Belvidere-Marengo 138 kV | Illinois | Active | Commonwealth Edison Company | 100.0 | 100.0 | 67.0 | Generation Interconnection | Solar | |
| AE2-325 | Valley 138 kV | Michigan | Active | AEP Indiana Michigan Transmission Company, Inc. | 152.2 | 52.2 | 31.32 | Generation Interconnection | Storage | |
| AE2-341 | Sandwich-Plano 138 kV | Illinois | Active | Commonwealth Edison Company | 150.0 | 150.0 | 100.6 | Generation Interconnection | Solar | |
| AF1-030 | Sandwich-Plano 138 kV | Illinois | Active | Commonwealth Edison Company | 250.0 | 100.0 | 66.9 | Generation Interconnection | Solar | |
| AF1-088 | Sullivan 345 kV | Indiana | Active | AEP Indiana Michigan Transmission Company, Inc. | 1000.0 | 1000.0 | 1000.0 | Merchant Transmission | None | |
| AF1-123 | Oceana 230 kV | Virginia | Active | Virginia Electric and Power Company (Dominion Virginia Power) | 833.0 | 833.0 | 253.2 | Generation Interconnection | Offshore Wind | |
| AF1-124 | Oceana 230 kV | Virginia | Active | Virginia Electric and Power Company (Dominion Virginia Power) | 836.0 | 836.0 | 254.1 | Generation Interconnection | Offshore Wind | |
| AF1-125 | Oceana 230 kV | Virginia | Active | Virginia Electric and Power Company (Dominion Virginia Power) | 820.0 | 820.0 | 249.3 | Generation Interconnection | Offshore Wind | |
| AF1-128 | Chesterfield 230 kV | Virginia | Active | Virginia Electric and Power Company (Dominion Virginia Power) | 569.0 | 569.0 | 569.0 | Generation Interconnection | Natural Gas | |
| AF1-161 | Valley 138 kV | Michigan | Active | AEP Indiana Michigan Transmission Company, Inc. | 50.0 | 50.0 | 25.0 | Generation Interconnection | Storage | |
| AF1-176 | Corey 138 kV | Michigan | Active | AEP Indiana Michigan Transmission Company, Inc. | 300.0 | 300.0 | 155.682 | Generation Interconnection | Solar; Storage | |
| AF1-204 | Eugene 345 kV | Indiana | Active | AEP Indiana Michigan Transmission Company, Inc. | 255.0 | 255.0 | 63.75 | Generation Interconnection | Wind | |
| AF1-233 | Flemingsburg – Spurlock 138kV | Kentucky | Active | East Kentucky Power Cooperative, Inc. | 188.5 | 188.5 | 113.1 | Generation Interconnection | Solar | |
| AF1-238 | Sherman Ave - West Vineland 69 kV | New Jersey | Active | Atlantic City Electric | 50.0 | 50.0 | 20.0 | Generation Interconnection | Storage | |
| AF1-240 | Timblin 34.5 kV | Pennsylvania | Active | Mid-Atlantic Interstate Transmission, LLC | 15.75 | 15.75 | 11.0 | Generation Interconnection | Solar | |
| AF1-280 | Nelson-Lee County | Illinois | Active | Commonwealth Edison Company | 200.0 | 200.0 | 0.0 | Generation Interconnection | Solar | |
| AF1-294 | Jetersville-Ponton 115 kV | Virginia | Active | Virginia Electric and Power Company (Dominion Virginia Power) | 41.0 | 41.0 | 22.2 | Generation Interconnection | Solar | |
| AF1-296 | Garden Plain 138 kV | Illinois | Active | Commonwealth Edison Company | 190.89 | 190.89 | 33.6 | Generation Interconnection | Wind | |
| AF2-008 | Sullivan 345 kV | Indiana | Active | AEP Indiana Michigan Transmission Company, Inc. | 2000.0 | 1000.0 | 500.0 | Merchant Transmission | None | |
| AF2-010 | Union City-Titusville 115 kV | Pennsylvania | Active | Mid-Atlantic Interstate Transmission, LLC | 77.0 | 77.0 | 46.0 | Generation Interconnection | Solar | |
| AF2-035 | St. Johns 115 kV | Virginia | Active | Virginia Electric and Power Company (Dominion Virginia Power) | 72.0 | 72.0 | 48.0 | Generation Interconnection | Solar | |
| AF2-041 | Nelson-Electric Junction 345 kV | Illinois | Active | Commonwealth Edison Company | 300.0 | 300.0 | 180.0 | Generation Interconnection | Solar | |
| AF2-042 | Clover-Rawlings 500 kV | Virginia | Active | Virginia Electric and Power Company (Dominion Virginia Power) | 500.0 | 500.0 | 300.0 | Generation Interconnection | Solar | |
| AF2-046 | Tunis-Mapleton 115 kV | North Carolina | Active | Virginia Electric and Power Company (Dominion Virginia Power) | 126.0 | 126.0 | 83.7 | Generation Interconnection | Solar | |
| AF2-050 | Bear Rock-Johnstown 230 kV | Pennsylvania | Active | Mid-Atlantic Interstate Transmission, LLC | 150.0 | 50.0 | 30.0 | Generation Interconnection | Solar | |
| AF2-068 | Jay 138 kV | Indiana | Active | AEP Indiana Michigan Transmission Company, Inc. | 150.0 | 150.0 | 90.0 | Generation Interconnection | Solar | |
| AF2-069 | Crescent Ridge 138 kV | Illinois | Active | Commonwealth Edison Company | 87.8 | 8.4 | 1.98 | Generation Interconnection | Wind | |
| AF2-080 | Chinquapin-Everetts 230 kV | North Carolina | Active | Virginia Electric and Power Company (Dominion Virginia Power) | 150.0 | 70.0 | 48.5 | Generation Interconnection | Solar | |
| AF2-081 | Moyock 230 kV | North Carolina | Active | Virginia Electric and Power Company (Dominion Virginia Power) | 80.0 | 80.0 | 56.0 | Generation Interconnection | Solar | |
| AF2-095 | Davis Creek 138 kV | Illinois | Active | Commonwealth Edison Company | 144.0 | 144.0 | 86.4 | Generation Interconnection | Solar | |
| AF2-111 | North Clark-Spurlock 345 kV | Kentucky | Active | East Kentucky Power Cooperative, Inc. | 250.0 | 250.0 | 150.0 | Generation Interconnection | Solar | |
| AF2-115 | Jetersville-Ponton 115 kV | Virginia | Active | Virginia Electric and Power Company (Dominion Virginia Power) | 66.0 | 25.0 | 13.5 | Generation Interconnection | Solar | |
| AF2-120 | Garner-Northern Neck 115 kV | Virginia | Active | Virginia Electric and Power Company (Dominion Virginia Power) | 62.0 | 62.0 | 37.2 | Generation Interconnection | Solar | |
| AF2-126 | Weston 69 kV II | Ohio | Active | American Transmission Systems, Incorporated | 62.0 | 12.0 | 8.0 | Generation Interconnection | Solar | |
| AF2-142 | Nevada 345 kV | Illinois | Active | Commonwealth Edison Company | 300.0 | 150.0 | 90.0 | Generation Interconnection | Solar | |
| AF2-143 | Powerton-Nevada 345 kV | Illinois | Active | Commonwealth Edison Company | 300.0 | 150.0 | 90.0 | Generation Interconnection | Solar | |
| AF2-173 | Desoto 345 kV | Indiana | Active | Indiana Michigan Power Company | 340.0 | 140.0 | 84.0 | Generation Interconnection | Solar | |
| AF2-177 | Sorenson-DeSoto #2 345 kV | Indiana | Active | AEP Indiana Michigan Transmission Company, Inc. | 200.0 | 200.0 | 26.0 | Generation Interconnection | Wind | |
| AF2-182 | Nelson-Lee County 345 kV II | Illinois | Active | Commonwealth Edison Company | 500.0 | 300.0 | 0.0 | Generation Interconnection | Solar | |
| AF2-199 | Nelson-Electric Junction 345 kV | Illinois | Active | Commonwealth Edison Company | 400.0 | 100.0 | 60.0 | Generation Interconnection | Solar | |
| AF2-200 | Nelson-Electric Junction 345 kV | Illinois | Active | Commonwealth Edison Company | 600.0 | 200.0 | 120.0 | Generation Interconnection | Solar | |
| AF2-222 | Madisonville DP-Twitty's Creek 115 kV | Virginia | Active | Virginia Electric and Power Company (Dominion Virginia Power) | 167.0 | 167.0 | 100.0 | Generation Interconnection | Solar | |
| AF2-225 | McLean 345 kV | Illinois | Active | Commonwealth Edison Company | 500.0 | 150.0 | 63.0 | Generation Interconnection | Solar | |
| AF2-226 | Katydid Road 345 kV | Illinois | Active | Commonwealth Edison Company | 350.0 | 50.0 | 20.0 | Generation Interconnection | Storage | |
| AF2-296 | Madera 34.5 kV | Pennsylvania | Active | Mid-Atlantic Interstate Transmission, LLC | 20.0 | 20.0 | 12.0 | Generation Interconnection | Solar | |
| AF2-297 | Sedge Hill 115 kV | Virginia | Active | Virginia Electric and Power Company (Dominion Virginia Power) | 80.0 | 80.0 | 48.0 | Generation Interconnection | Solar | |
| AF2-299 | Fields 34.5 kV | Virginia | Active | Virginia Electric and Power Company (Dominion Virginia Power) | 18.0 | 18.0 | 10.8 | Generation Interconnection | Solar | |
| AF2-307 | Hope-Belvins Valley Tap 69 kV | Kentucky | Active | East Kentucky Power Cooperative, Inc. | 64.2 | 64.2 | 39.6 | Generation Interconnection | Solar | |
| AF2-319 | Katydid Road 345 kV | Illinois | Active | Commonwealth Edison Company | 400.0 | 50.0 | 20.0 | Generation Interconnection | Storage | |
| AF2-335 | Delaware-Royerton 138 kV | Indiana | Active | AEP Indiana Michigan Transmission Company, Inc. | 100.0 | 100.0 | 60.0 | Generation Interconnection | Solar | |
| AF2-349 | SILVER LAKE- CHERRY VALLEY 345 KV | Illinois | Active | Commonwealth Edison Company | 300.0 | 300.0 | 0.0 | Generation Interconnection | Solar | |
| AF2-350 | Kensington 138 kV | Illinois | Active | Commonwealth Edison Company | 100.0 | 100.0 | 60.0 | Generation Interconnection | Solar | |
| AF2-358 | Airey-Vienna 69 kV | Maryland | Active | Delmarva Power and Light Company | 100.0 | 100.0 | 60.0 | Generation Interconnection | Solar | |
| AF2-365 | Munfordville KU Tap-Horse Cave Jct. 69 kV | Kentucky | Active | East Kentucky Power Cooperative, Inc. | 50.0 | 50.0 | 30.0 | Generation Interconnection | Solar | |
| AF2-370 | Delaware-Royerton 138 kV | Indiana | Active | AEP Indiana Michigan Transmission Company, Inc. | 100.0 | 0.0 | 20.0 | Generation Interconnection | Storage | |
| AF2-376 | Timber Switch 138 kV | Ohio | Active | Ohio Power Company | 149.0 | 50.0 | 20.0 | Generation Interconnection | Storage | |
| AF2-388 | Keystone-Desoto 345 kV | Indiana | Active | AEP Indiana Michigan Transmission Company, Inc. | 200.0 | 200.0 | 35.2 | Generation Interconnection | Wind | |
| AF2-392 | Nelson-Dixon 138 kV | Illinois | Active | Commonwealth Edison Company | 199.0 | 199.0 | 35.2 | Generation Interconnection | Wind | |
| AF2-396 | Stinger 138 kV | Michigan | Active | AEP Indiana Michigan Transmission Company, Inc. | 200.0 | 200.0 | 200.0 | Generation Interconnection | Solar; Storage | |
| AF2-404 | Gladys DP-Stonemill 69 kV | Virginia | Active | Virginia Electric and Power Company (Dominion Virginia Power) | 60.0 | 0.0 | 0.0 | Generation Interconnection | Storage | |
| AF2-407 | Fall Creek 345 kV | Indiana | Active | AEP Indiana Michigan Transmission Company, Inc. | 300.0 | 300.0 | 300.0 | Generation Interconnection | Storage | |
| AF2-441 | Burnham 138kV | Illinois | Active | Commonwealth Edison Company | 200.0 | 200.0 | 80.0 | Generation Interconnection | Storage | |
| AG1-008 | Tunis-Mapleton 115 kV | North Carolina | Active | Virginia Electric and Power Company (Dominion Virginia Power) | 126.0 | 126.0 | 83.7 | Generation Interconnection | Solar | |
| AG1-021 | Jetersville-Ponton 115 kV | Virginia | Active | Virginia Electric and Power Company (Dominion Virginia Power) | 86.0 | 20.0 | 10.8 | Generation Interconnection | Solar | |
| AG1-070 | Bon Ayr 69 kV | Kentucky | Active | East Kentucky Power Cooperative, Inc. | 45.0 | 45.0 | 32.7 | Generation Interconnection | Solar | |
| AG1-071 | Bon Ayr 69 kV | Kentucky | Active | East Kentucky Power Cooperative, Inc. | 100.0 | 55.0 | 37.5 | Generation Interconnection | Solar | |
| AG1-082 | Ahoskie 34.5 kV | North Carolina | Active | Virginia Electric and Power Company (Dominion Virginia Power) | 20.0 | 20.0 | 12.0 | Generation Interconnection | Solar; Storage | |
| AG1-090 | Philipsburg 115 kV | Pennsylvania | Active | Mid-Atlantic Interstate Transmission, LLC | 95.0 | 95.0 | 30.0 | Generation Interconnection | Solar; Storage | |
| AG1-098 | Briery-Clover 230 kV | Virginia | Active | Virginia Electric and Power Company (Dominion Virginia Power) | 107.0 | 107.0 | 64.2 | Generation Interconnection | Solar | |
| AG1-105 | Mount Laurel-Barnes Junction 115 kV | Virginia | Active | Virginia Electric and Power Company (Dominion Virginia Power) | 90.0 | 90.0 | 54.0 | Generation Interconnection | Solar | |
| AG1-106 | Thelma 230 kV | North Carolina | Active | Virginia Electric and Power Company (Dominion Virginia Power) | 143.0 | 23.0 | 16.0 | Generation Interconnection | Solar | |
| AG1-109 | Valley 138 kV | Michigan | Active | AEP Indiana Michigan Transmission Company, Inc. | 50.0 | 0.0 | 25.0 | Generation Interconnection | Storage | |
| AG1-118 | Sugar Grove-Waterman 138kV | Illinois | Active | Commonwealth Edison Company | 300.0 | 300.0 | 180.0 | Generation Interconnection | Solar | |
| AG1-124 | Gladstone 138 kV | Virginia | Active | Appalachian Power Company | 90.0 | 90.0 | 53.01 | Generation Interconnection | Solar | |
| AG1-127 | Crego Rd 138 kV | Illinois | Active | Commonwealth Edison Company | 190.0 | 95.1 | 57.1 | Generation Interconnection | Solar | |
| AG1-135 | Garner-Lancaster 115 kV | Virginia | Active | Virginia Electric and Power Company (Dominion Virginia Power) | 60.0 | 60.0 | 36.0 | Generation Interconnection | Solar | |
| AG1-146 | Garner DP-Lancaster 115 kV | Virginia | Active | Virginia Electric and Power Company (Dominion Virginia Power) | 30.0 | 30.0 | 18.0 | Generation Interconnection | Solar | |
| AG1-147 | Garner DP-Lancaster 115 kV | Virginia | Active | Virginia Electric and Power Company (Dominion Virginia Power) | 100.0 | 70.0 | 42.0 | Generation Interconnection | Solar | |
| AG1-153 | Heritage 500 kV | Virginia | Active | Virginia Electric and Power Company (Dominion Virginia Power) | 75.0 | 75.0 | 30.0 | Generation Interconnection | Storage | |
| AG1-154 | Ladysmith CT 230 kV | Virginia | Active | Virginia Electric and Power Company (Dominion Virginia Power) | 50.0 | 50.0 | 20.0 | Generation Interconnection | Storage | |
| AG1-166 | Lone Pine 115 kV | Virginia | Active | Virginia Electric and Power Company (Dominion Virginia Power) | 20.0 | 20.0 | 6.0 | Generation Interconnection | Solar | |
| AG1-167 | Lone Pine 115 kV | Virginia | Active | Virginia Electric and Power Company (Dominion Virginia Power) | 35.0 | 15.0 | 4.5 | Generation Interconnection | Solar | |
| AG1-168 | Lone Pine 115 kV | Virginia | Active | Virginia Electric and Power Company (Dominion Virginia Power) | 50.0 | 15.0 | 4.5 | Generation Interconnection | Solar | |
| AG1-226 | Dequine-Eugene 345 kV | Indiana | Active | AEP Indiana Michigan Transmission Company, Inc. | 450.0 | 450.0 | 142.0 | Generation Interconnection | Solar | |
| AG1-236 | Lanesville-Brokaw 345 kV | Illinois | Active | Commonwealth Edison Company | 380.0 | 180.0 | 23.4 | Generation Interconnection | Wind | |
| AG1-285 | Chase City-Central 115 kV | Virginia | Active | Virginia Electric and Power Company (Dominion Virginia Power) | 125.0 | 125.0 | 75.0 | Generation Interconnection | Solar | |
| AG1-297 | Hanna-Tanners Creek 345 kV | Indiana | Active | AEP Indiana Michigan Transmission Company, Inc. | 300.0 | 300.0 | 75.0 | Generation Interconnection | Storage | |
| AG1-320 | Glendale-Stephensburg 69 kV | Kentucky | Active | East Kentucky Power Cooperative, Inc. | 82.0 | 82.0 | 54.8 | Generation Interconnection | Solar | |
| AG1-323 | Blue Jacket 138 kV | Ohio | Active | The Dayton Power and Light Company | 40.0 | 40.0 | 40.0 | Generation Interconnection | Solar; Storage | |
| AG1-341 | Summer Shade 161 kV | Kentucky | Active | East Kentucky Power Cooperative, Inc. | 106.0 | 106.0 | 63.6 | Generation Interconnection | Solar; Storage | |
| AG1-342 | Dryburg 115 kV | Virginia | Active | Virginia Electric and Power Company (Dominion Virginia Power) | 36.0 | 36.0 | 21.6 | Generation Interconnection | Solar | |
| AG1-354 | Summershade-Green County 161 kV | Kentucky | Active | East Kentucky Power Cooperative, Inc. | 150.0 | 150.0 | 90.0 | Generation Interconnection | Solar | |
| AG1-367 | DeSoto 345 kV | Indiana | Active | Indiana Michigan Power Company | 440.0 | 100.0 | 60.0 | Generation Interconnection | Solar | |
| AG1-374 | Blue Mound 345 kV | Illinois | Active | Commonwealth Edison Company | 300.0 | 300.0 | 180.0 | Generation Interconnection | Solar | |
| AG1-375 | Sorenson-Desoto 345 kV | Indiana | Active | AEP Indiana Michigan Transmission Company, Inc. | 300.0 | 100.0 | 60.0 | Generation Interconnection | Solar | |
| AG1-377 | Philipsburg 115 kV | Pennsylvania | Active | Mid-Atlantic Interstate Transmission, LLC | 115.0 | 20.0 | 6.0 | Generation Interconnection | Solar | |
| AG1-378 | Philipsburg 115 kV | Pennsylvania | Active | Mid-Atlantic Interstate Transmission, LLC | 135.0 | 20.0 | 6.0 | Generation Interconnection | Solar | |
| AG1-393 | Fort Pickett DP 34.5 kV | Virginia | Active | Virginia Electric and Power Company (Dominion Virginia Power) | 20.0 | 20.0 | 12.0 | Generation Interconnection | Solar | |
| AG1-394 | Boykins 34.5 kV | Virginia | Active | Virginia Electric and Power Company (Dominion Virginia Power) | 14.2 | 14.2 | 5.0 | Generation Interconnection | Solar | |
| AG1-405 | Walnut Grove-Asahi 69 kV | Kentucky | Active | East Kentucky Power Cooperative, Inc. | 57.0 | 57.0 | 34.2 | Generation Interconnection | Solar | |
| AG1-406 | Walnut Grove-Asahi 69 kV | Kentucky | Active | East Kentucky Power Cooperative, Inc. | 79.0 | 22.0 | 22.0 | Generation Interconnection | Storage | |
| AG1-410 | Maddox Creek-RP Mone 345 kV | Ohio | Active | Ohio Power Company | 300.0 | 300.0 | 180.0 | Generation Interconnection | Solar | |
| AG1-411 | Maddox Creek-RP Mone 345 kV | Ohio | Active | Ohio Power Company | 400.0 | 100.0 | 100.0 | Generation Interconnection | Storage | |
| AG1-433 | Keystone-DeSoto 345 kV | Indiana | Active | AEP Indiana Michigan Transmission Company, Inc. | 300.0 | 100.0 | 17.6 | Generation Interconnection | Wind | |
| AG1-436 | Olive-University Park 345 kV | Indiana | Active | AEP Indiana Michigan Transmission Company, Inc. | 250.0 | 125.0 | 75.0 | Generation Interconnection | Solar | |
| AG1-447 | Olive-University Park 345 kV | Indiana | Active | AEP Indiana Michigan Transmission Company, Inc. | 305.0 | 55.0 | 55.0 | Generation Interconnection | Storage | |
| AG1-450 | Airey-Vienna 69 kV II | Maryland | Active | Delmarva Power and Light Company | 125.0 | 25.0 | 25.0 | Generation Interconnection | Storage | |
| AG1-460 | Kincaid-Pana 345 kV | Illinois | Active | Commonwealth Edison Company | 329.0 | 30.0 | 12.0 | Generation Interconnection | Storage | |
| AG1-462 | Cordova 345 kV | Illinois | Active | Commonwealth Edison Company | 255.0 | 255.0 | 153.0 | Generation Interconnection | Solar | |
| AG1-471 | Up Church-Wayne County 69 kV | Kentucky | Active | East Kentucky Power Cooperative, Inc. | 54.0 | 54.0 | 32.4 | Generation Interconnection | Solar | |
| AG1-494 | Boxwood-Riverville 138 kV | Virginia | Active | Appalachian Power Company | 50.0 | 50.0 | 20.0 | Generation Interconnection | Storage | |
| AG1-526 | West Garrard 345 kV | Kentucky | Active | East Kentucky Power Cooperative, Inc. | 222.0 | 222.0 | 133.2 | Generation Interconnection | Solar | |
| AG1-536 | Garner-Northern Neck 115 kV | Virginia | Active | Virginia Electric and Power Company (Dominion Virginia Power) | 137.0 | 75.0 | 32.0 | Generation Interconnection | Storage | |
| AG1-548 | Erie South-Union City 115 kV | Pennsylvania | Active | Mid-Atlantic Interstate Transmission, LLC | 150.0 | 150.0 | 45.0 | Generation Interconnection | Solar; Storage | |
| AG1-551 | Parmele 34.5 kV | North Carolina | Active | Virginia Electric and Power Company (Dominion Virginia Power) | 19.99 | 19.99 | 13.1 | Generation Interconnection | Solar | |
| AG1-552 | Carolina 34.5 kV | North Carolina | Active | Virginia Electric and Power Company (Dominion Virginia Power) | 18.0 | 18.0 | 12.2 | Generation Interconnection | Solar | |
| AG1-553 | Cordova 345 kV | Illinois | Active | Commonwealth Edison Company | 260.0 | 260.0 | 0.0 | Generation Interconnection | Solar |
Stability Clusters
Stability analysis was performed by grouping New Service Requests into clusters based on their electrical proximity in order to increase the efficiency of the stability study process. A single stability study is performed for all New Service Requests in the cluster and any reinforcement costs shall be cost allocated proportionally to all New Service Requests in the cluster.
| Cluster Index | Cluster Name | New Service Requests | Status | Executive Summary |
|---|---|---|---|---|
| 1 | Cluster 1 | AE2-341, AF1-030, AG1-118, AG1-127 | Analysis Complete - No Issues | |
| 2 | Cluster 2 | AE1-114 | Analysis Complete - No Issues | |
| 3 | Cluster 3 | AF2-350 | Analysis Complete - No Issues | |
| 4 | Cluster 4 | AE2-321 | Analysis Complete - No Issues | |
| 5 | Cluster 5 | AF2-226, AF2-319 | Analysis Complete - No Issues | |
| 6 | Cluster 6 | AF2-392 | Analysis Complete - No Issues | |
| 7 | Cluster 7 | AE2-261, AG1-236, AG1-460 | Analysis Complete - No Issues | |
| 8 | Cluster 8 | AE1-172, AE2-173, AE2-223, AF2-225 | Analysis Complete - No Issues | |
| 9 | Cluster 9 | AF2-069 | Analysis Complete - No Issues | |
| 11 | Cluster 11 | AF2-441 | Analysis Complete - No Issues | |
| 13 | Cluster 13 | AF2-142, AF2-143 | Analysis Complete - No Issues | |
| 14 | Cluster 14 | AF2-095 | Analysis Complete - No Issues | |
| 15 | Cluster 15 | AF2-041, AF2-199, AF2-200 | Analysis Complete - No Issues | |
| 16 | Cluster 16 | AF1-280, AF2-182, AF2-349 | Analysis Complete - No Issues | |
| 17 | Cluster 17 | AF1-296, AG1-462, AG1-553 | Analysis Complete - No Issues | |
| 21 | Cluster 21 | AG1-374 | Analysis Complete - No Issues | |
| 23 | Cluster 23 | AE1-092, AG1-323 | Analysis Complete - No Issues | |
| 24 | Cluster 24 | AF1-233, AF2-307 | Analysis Complete - No Issues | |
| 25 | Cluster 25 | AG1-354, AG1-471 | Analysis Complete - No Issues | |
| 26 | Cluster 26 | AE2-308 | Analysis Complete - No Issues | |
| 27 | Cluster 27 | AF2-111, AG1-526 | Analysis Complete - No Issues | |
| 29 | Cluster 29 | AF1-123, AF1-124, AF1-125 | Analysis Complete - Issues Found | |
| 30 | Cluster 30 | AF1-294, AF2-115, AG1-021, AG1-166, AG1-167, AG1-168 | Analysis Complete - No Issues | |
| 31 | Cluster 31 | AF2-222, AG1-285 | Analysis Complete - Issues Found | |
| 32 | Cluster 32 | AF2-120, AG1-135, AG1-146, AG1-147, AG1-536 | Analysis Complete - Issues Found | |
| 33 | Cluster 33 | AE2-187 | Analysis Complete - No Issues | |
| 34 | Cluster 34 | AE1-148, AE2-291, AF2-297, AG1-105, AG1-342 | Analysis Complete - No Issues | |
| 35 | Cluster 35 | AE2-185, AE2-283, AF2-404 | Analysis Complete - No Issues | |
| 37 | Cluster 37 | AF2-046, AG1-008 | Analysis Complete - No Issues | |
| 39 | Cluster 39 | AF2-080, AG1-106 | Analysis Complete - No Issues | |
| 42 | Cluster 42 | AF2-035, AG1-154 | Analysis Complete - No Issues | |
| 44 | Cluster 44 | AF2-081 | Analysis Complete - No Issues | |
| 45 | Cluster 45 | AF2-042, AG1-098 | Analysis Complete - No Issues | |
| 46 | Cluster 46 | AE2-156 | Analysis Complete - No Issues | |
| 47 | Cluster 47 | AG1-153 | Analysis Complete - No Issues | |
| 48 | Cluster 48 | AF1-128 | Analysis Complete - No Issues | |
| 52 | Cluster 52 | AF1-088, AF2-008 | Analysis Complete - No Issues | |
| 54 | Cluster 54 | AG1-124, AG1-494 | Analysis Complete - No Issues | |
| 55 | Cluster 55 | AE2-325, AF1-161, AF1-176, AF2-396, AG1-109 | Analysis Complete - No Issues | |
| 56 | Cluster 56 | AG1-410, AG1-411 | Analysis Complete - No Issues | |
| 58 | Cluster 58 | AG1-436, AG1-447 | Analysis Complete - No Issues | |
| 59 | Cluster 59 | AF2-335, AF2-370 | Analysis Complete - No Issues | |
| 60 | Cluster 60 | AF2-068 | Analysis Complete - No Issues | |
| 62 | Cluster 62 | AF2-173, AF2-177, AF2-407, AG1-367, AG1-375 | Analysis Complete - No Issues | |
| 63 | Cluster 63 | AF2-388, AG1-433 | Analysis Complete - No Issues | |
| 64 | Cluster 64 | AF1-204, AG1-226 | Analysis Complete - No Issues | |
| 65 | Cluster 65 | AG1-297 | Analysis Complete - No Issues | |
| 69 | Cluster 69 | AF2-010, AG1-548 | Analysis Complete - No Issues | |
| 70 | Cluster 70 | AF2-050 | Analysis Complete - No Issues | |
| 71 | Cluster 71 | AG1-090, AG1-377, AG1-378 | Analysis Complete - No Issues | |
| 72 | Cluster 72 | AF1-238 | Analysis Complete - No Issues | |
| 74 | Cluster 74 | AF2-126 | Analysis Complete - No Issues | |
| 75 | Cluster 75 | AF2-358, AG1-450 | Analysis Complete - Issues Found | |
| 83 | Cluster 83 | AF2-365 | Analysis Complete - No Issues | |
| 84 | Cluster 84 | AG1-341 | Analysis Complete - No Issues | |
| 85 | Cluster 85 | AG1-320 | Analysis Complete - No Issues | |
| 86 | Cluster 86 | AG1-070, AG1-071 | Analysis Complete - No Issues | |
| 87 | Cluster 87 | AG1-405, AG1-406 | Analysis Complete - No Issues | |
| 88 | Cluster 88 | AF2-376 | Analysis Complete - No Issues |
CIR Claims From Deactivated Generators
The following Transition Cycle 1 Phase III projects intend to claim and transfer CIRs from deactivated capacity generation resources. PJM performed a reliability analysis of the impacts to the system capability for the proposed transfers of CIRs from the deactivated generation resources.
| Project | Status | Deactivated Generators | ||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| AF1-128 | Active |
|
Cost Summary
Table below shows a summary of the total planning level cost estimates for each individual New Service Request received by PJM and studied in Transition Cycle 1 Phase III. These network upgrade costs are subject to change as a result of a facility study performed by the Interconnected Transmission Owner during the Phase III System Impact Study.
| Project ID | Transmission Owner Interconnection Facilities (TOIF) | Physical Interconnection Network Upgrades | System Reliability Network Upgrades | Affected System Study Reinforcements | Additional Charges | Total Cost |
|---|---|---|---|---|---|---|
| AE1-092 | $796,612 | $14,467,553 | $0 | $0 | $0 | $15,264,165 |
| AE1-114 | $0 | $11,422,206 | $7,522,244 | $82,193 | $1,237,828 | $20,264,471 |
| AE1-148 | $0 | $7,762,963 | $6,902,292 | $0 | $2,426,954 | $17,092,209 |
| AE1-172 | $0 | $28,485,236 | $12,468,541 | $136,518 | $2,005,307 | $43,095,602 |
| AE2-156 | $3,487,508 | $8,024,437 | $1,733,124 | $0 | $0 | $13,245,069 |
| AE2-173 | $0 | $0 | $160,381 | $154,718 | $2,590,088 | $2,905,187 |
| AE2-185 | $0 | $724,989 | $2,453,903 | $0 | $939,177 | $4,118,069 |
| AE2-187 | $0 | $14,761,901 | $2,429,872 | $0 | $0 | $17,191,773 |
| AE2-223 | $0 | $32,602 | $4,990,729 | $247,658 | $1,321,269 | $6,592,257 |
| AE2-261 | $0 | $5,449,938 | $14,188,656 | $1,137,243 | $997,871 | $21,773,709 |
| AE2-283 | $8,300,735 | $3,617,755 | $1,927,647 | $0 | $0 | $13,846,137 |
| AE2-291 | $1,091,112 | $15,672,692 | $5,282,175 | $0 | $0 | $22,045,979 |
| AE2-308 | $960,000 | $16,084,000 | $0 | $0 | $0 | $17,044,000 |
| AE2-321 | $779,305 | $31,487,039 | $0 | $368,307 | $0 | $32,634,651 |
| AE2-325 | $193,802 | $60,764 | $29,905 | $249,654 | $0 | $534,125 |
| AE2-341 | $392,212 | $20,659,366 | $2,555,977 | $567,614 | $0 | $24,175,169 |
| AF1-030 | $392,212 | $20,659,366 | $1,701,572 | $375,625 | $0 | $23,128,775 |
| AF1-088 | $3,945,524 | $1,454,913 | $86,109,849 | $5,002,132 | $0 | $96,512,419 |
| AF1-123 | $7,308,561 | $250,069,522 | $249,128,481 | $0 | $0 | $506,506,564 |
| AF1-124 | $7,308,561 | $250,069,522 | $250,021,531 | $0 | $0 | $507,399,614 |
| AF1-125 | $7,308,561 | $250,069,522 | $243,615,499 | $0 | $0 | $500,993,582 |
| AF1-128 | $799,374 | $2,182,499 | $0 | $0 | $0 | $2,981,873 |
| AF1-161 | $503,836 | $1,371,722 | $14,294 | $239,991 | $0 | $2,129,843 |
| AF1-176 | $1,095,657 | $1,996,401 | $23,682,596 | $27,771,262 | $0 | $54,545,916 |
| AF1-204 | $2,204,630 | $391,163 | $4,646,195 | $2,153,115 | $0 | $9,395,103 |
| AF1-233 | $1,090,000 | $17,924,352 | $0 | $3,511,290 | $0 | $22,525,642 |
| AF1-238 | $0 | $0 | $0 | $0 | $0 | $0 |
| AF1-240 | $293,366 | $762,742 | $315,639 | $0 | $24,999 | $1,396,746 |
| AF1-280 | $0 | $12,467,942 | $15,708,673 | $681,511 | $970,966 | $29,829,091 |
| AF1-294 | $0 | $1,370,721 | $5,614,951 | $0 | $956,979 | $7,942,651 |
| AF1-296 | $717,375 | $11,672,026 | $12,404,720 | $95,169 | $0 | $24,889,290 |
| AF2-008 | $3,207,409 | $3,624,696 | $86,109,849 | $5,002,132 | $0 | $97,944,087 |
| AF2-010 | $52,291 | $4,938,510 | $7,287,610 | $0 | $962,458 | $13,240,869 |
| AF2-035 | $0 | $0 | $14,101,897 | $0 | $0 | $14,101,897 |
| AF2-041 | $0 | $5,286,342 | $168,176,697 | $1,062,418 | $698,350 | $175,223,807 |
| AF2-042 | $2,167,703 | $36,291,713 | $340,130,787 | $0 | $0 | $378,590,203 |
| AF2-046 | $909,050 | $8,910,978 | $113,123,215 | $3,625,000 | $0 | $126,568,243 |
| AF2-050 | $49,831 | $153,052 | $9,867,005 | $0 | $0 | $10,069,888 |
| AF2-068 | $1,750,487 | $1,483,556 | $0 | $8,357 | $0 | $3,242,400 |
| AF2-069 | $0 | $0 | $0 | $3,174 | $1,259,392 | $1,262,566 |
| AF2-080 | $0 | $0 | $20,923,633 | $3,726,000 | $0 | $24,649,633 |
| AF2-081 | $4,133,798 | $3,663,047 | $1,635,340 | $0 | $0 | $9,432,185 |
| AF2-095 | $5,112,467 | $1,166,794 | $4,838,684 | $597,954 | $0 | $11,715,899 |
| AF2-111 | $0 | $8,479,000 | $0 | $81,383 | $1,416,000 | $9,976,383 |
| AF2-115 | $0 | $1,370,721 | $3,421,907 | $0 | $956,979 | $5,749,607 |
| AF2-120 | $1,219,290 | $1,219,184 | $38,365,043 | $0 | $0 | $40,803,516 |
| AF2-126 | $58,252 | $233,066 | $0 | $2,025 | $0 | $293,343 |
| AF2-142 | $0 | $0 | $3,178,673 | $589,248 | $256,082 | $4,024,003 |
| AF2-143 | $0 | $0 | $3,145,962 | $575,326 | $256,082 | $3,977,370 |
| AF2-173 | $0 | $60,764 | $2,464,619 | $8,357 | $193,802 | $2,727,542 |
| AF2-177 | $1,199,530 | $10,397,244 | $2,853,760 | $0 | $0 | $14,450,534 |
| AF2-182 | $0 | $12,467,942 | $23,562,909 | $1,018,422 | $970,966 | $38,020,238 |
| AF2-199 | $0 | $5,286,342 | $56,062,754 | $350,908 | $698,350 | $62,398,354 |
| AF2-200 | $0 | $5,286,342 | $115,190,438 | $710,842 | $698,350 | $121,885,972 |
| AF2-222 | $1,080,391 | $16,075,015 | $42,923,679 | $0 | $0 | $60,079,085 |
| AF2-225 | $0 | $32,602 | $3,687,698 | $638,055 | $1,321,269 | $5,679,623 |
| AF2-226 | $0 | $0 | $1,345,993 | $204,661 | $256,082 | $1,806,736 |
| AF2-296 | $238,297 | $1,389,983 | $0 | $0 | $0 | $1,628,280 |
| AF2-297 | $4,540,504 | $2,355,572 | $7,094,464 | $0 | $0 | $13,990,540 |
| AF2-299 | $0 | $0 | $0 | $515,000 | $0 | $515,000 |
| AF2-307 | $1,799,000 | $11,073,000 | $0 | $0 | $0 | $12,872,000 |
| AF2-319 | $0 | $0 | $1,345,993 | $204,661 | $256,082 | $1,806,736 |
| AF2-335 | $0 | $1,065,672 | $0 | $8,357 | $155,068 | $1,229,098 |
| AF2-349 | $0 | $17,122,339 | $1,319,935 | $1,094,363 | $2,000,162 | $21,536,799 |
| AF2-350 | $793,922 | $29,405,140 | $0 | $419,501 | $0 | $30,618,563 |
| AF2-358 | $0 | $610,000 | $58,631,848 | $0 | $1,500,000 | $60,741,848 |
| AF2-365 | $2,043,000 | $14,689,000 | $617,704 | $0 | $0 | $17,349,704 |
| AF2-370 | $0 | $1,065,672 | $0 | $0 | $155,068 | $1,220,741 |
| AF2-376 | $193,802 | $60,764 | $0 | $0 | $0 | $254,566 |
| AF2-388 | $982,483 | $691,462 | $2,769,596 | $19,678 | $0 | $4,463,219 |
| AF2-392 | $797,913 | $41,848,395 | $15,626,198 | $105,428 | $0 | $58,377,934 |
| AF2-396 | $2,531,657 | $2,169,205 | $16,292,546 | $18,823,503 | $0 | $39,816,911 |
| AF2-404 | $0 | $724,989 | $0 | $0 | $939,177 | $1,664,166 |
| AF2-407 | $2,435,538 | $3,325,190 | $4,519,578 | $734,838 | $0 | $11,015,144 |
| AF2-441 | $787,345 | $7,072,041 | $1,516,634 | $910,924 | $0 | $10,286,944 |
| AG1-008 | $909,050 | $8,910,978 | $113,123,215 | $3,625,000 | $0 | $126,568,243 |
| AG1-021 | $0 | $1,370,721 | $2,737,593 | $0 | $956,979 | $5,065,294 |
| AG1-070 | $953,500 | $6,189,500 | $940,667 | $3,158,698 | $0 | $11,242,364 |
| AG1-071 | $953,500 | $6,189,500 | $1,149,629 | $3,767,215 | $0 | $12,059,844 |
| AG1-082 | $0 | $0 | $2,851,284 | $611,000 | $0 | $3,462,284 |
| AG1-090 | $84,934 | $1,099,479 | $12,820,226 | $0 | $1,658 | $14,006,296 |
| AG1-098 | $1,090,209 | $15,937,649 | $17,362,631 | $0 | $0 | $34,390,489 |
| AG1-105 | $993,766 | $14,284,645 | $7,874,083 | $0 | $0 | $23,152,494 |
| AG1-106 | $0 | $0 | $8,127,122 | $1,018,000 | $0 | $9,145,122 |
| AG1-109 | $503,836 | $1,432,486 | $14,294 | $0 | $0 | $1,950,616 |
| AG1-118 | $0 | $8,216,337 | $9,409,866 | $1,111,779 | $1,810,470 | $20,548,452 |
| AG1-124 | $1,838,092 | $10,076,477 | $11,159,437 | $0 | $0 | $23,074,006 |
| AG1-127 | $0 | $0 | $1,184,049 | $346,850 | $256,082 | $1,786,981 |
| AG1-135 | $1,085,295 | $17,406,305 | $36,335,527 | $0 | $0 | $54,827,127 |
| AG1-146 | $503,926 | $8,270,469 | $25,714,848 | $0 | $0 | $34,489,242 |
| AG1-147 | $503,926 | $8,270,469 | $60,001,154 | $0 | $0 | $68,775,548 |
| AG1-153 | $4,822,863 | $1,958,524 | $1,736,617 | $0 | $0 | $8,518,004 |
| AG1-154 | $1,558,655 | $9,405,709 | $10,895,136 | $0 | $0 | $21,859,500 |
| AG1-166 | $650,095 | $3,992,506 | $2,263,939 | $0 | $0 | $6,906,540 |
| AG1-167 | $650,095 | $3,992,506 | $1,697,996 | $0 | $0 | $6,340,597 |
| AG1-168 | $650,095 | $3,992,506 | $1,697,996 | $0 | $0 | $6,340,597 |
| AG1-226 | $2,930,035 | $33,073,479 | $14,019,658 | $4,899,748 | $0 | $54,922,920 |
| AG1-236 | $0 | $0 | $9,963,959 | $346,947 | $268,042 | $10,578,948 |
| AG1-285 | $1,077,358 | $18,954,196 | $29,536,510 | $0 | $0 | $49,568,064 |
| AG1-297 | $0 | $1,965,671 | $7,012,206 | $478,742 | $414,761 | $9,871,380 |
| AG1-320 | $0 | $2,214,000 | $0 | $4,334,526 | $1,591,000 | $8,139,526 |
| AG1-323 | $989,115 | $1,522,624 | $0 | $0 | $0 | $2,511,739 |
| AG1-341 | $1,683,000 | $6,002,000 | $0 | $7,562,355 | $0 | $15,247,355 |
| AG1-342 | $0 | $1,957,245 | $2,017,009 | $0 | $2,945,911 | $6,920,165 |
| AG1-354 | $0 | $6,127,000 | $0 | $13,379,640 | $1,337,000 | $20,843,640 |
| AG1-367 | $0 | $60,764 | $1,760,469 | $16,713 | $82,692 | $1,920,638 |
| AG1-374 | $2,382,120 | $19,794,599 | $8,873,193 | $1,254,210 | $0 | $32,304,122 |
| AG1-375 | $1,199,530 | $10,458,008 | $1,426,881 | $14,686 | $193,802 | $13,292,907 |
| AG1-377 | $84,934 | $1,099,479 | $2,699,150 | $0 | $1,658 | $3,885,221 |
| AG1-378 | $84,934 | $1,099,479 | $2,699,150 | $0 | $1,658 | $3,885,221 |
| AG1-393 | $0 | $0 | $0 | $0 | $0 | $0 |
| AG1-394 | $0 | $0 | $240,992 | $365,000 | $0 | $605,992 |
| AG1-405 | $1,225,000 | $5,035,000 | $0 | $0 | $0 | $6,260,000 |
| AG1-406 | $1,225,000 | $5,035,000 | $0 | $0 | $0 | $6,260,000 |
| AG1-410 | $1,279,780 | $10,446,603 | $0 | $23,042 | $0 | $11,749,425 |
| AG1-411 | $1,279,780 | $10,507,367 | $0 | $0 | $193,802 | $11,980,949 |
| AG1-433 | $982,483 | $752,226 | $1,384,892 | $0 | $193,802 | $3,313,403 |
| AG1-436 | $138,247 | $60,764 | $0 | $652,242 | $0 | $851,253 |
| AG1-447 | $138,247 | $60,764 | $0 | $291,870 | $0 | $490,881 |
| AG1-450 | $0 | $610,000 | $15,760,078 | $0 | $1,500,000 | $17,870,079 |
| AG1-460 | $0 | $5,449,938 | $1,423,572 | $113,056 | $1,253,952 | $8,240,519 |
| AG1-462 | $2,663,655 | $16,617,794 | $16,406,951 | $798,388 | $0 | $36,486,788 |
| AG1-471 | $718,000 | $13,187,000 | $0 | $5,352,864 | $0 | $19,257,864 |
| AG1-494 | $0 | $2,704,883 | $8,653,167 | $0 | $310,137 | $11,668,187 |
| AG1-526 | $1,398,000 | $4,441,000 | $0 | $0 | $0 | $5,839,000 |
| AG1-536 | $1,219,290 | $1,219,184 | $42,589,305 | $0 | $0 | $45,027,778 |
| AG1-548 | $54,570 | $6,698,199 | $14,089,575 | $0 | $951,097 | $21,793,441 |
| AG1-551 | $181,200 | $18,000,000 | $0 | $530,000 | $0 | $18,711,200 |
| AG1-552 | $181,200 | $24,400,000 | $0 | $637,000 | $0 | $25,218,200 |
| AG1-553 | $2,167,424 | $16,617,794 | $14,840,658 | $816,076 | $0 | $34,441,952 |
System Reinforcements
As part of Phase III, PJM evaluated the impact of topology changing reinforcements to mitigate the impacts driven by New Service Requests. PJM determined which reinforcements were eliminated as a result of modeling the topology changing reinforcements. PJM then grouped the topology changing and eliminated reinforcements by region and computed a discount factor to apply to reinforcements to reduce the cost of all these reinforcements down to the cost of contstructing only the topology changing reinforcements.
| Region | Topology Upgrades | Eliminated Upgrades | Discount Factor |
|---|---|---|---|
| Dominion | $519,466,645 | $751,704,547 | 40.865200% |
| Mid-Atlantic Area Council | $0 | $0 | 100.000000% |
| PJM West | $203,595,627 | $6,125,000 | 97.079448% |
Steady State Thermal & Voltage Reinforcements
PJM performed generator deliverability load flow analysis for the New Service Requests in Transition Cycle 1 Phase III. Load flow analysis was performed to simulate Summer Peak, Light Load and Winter Peak[1] conditions. The table below shows all the system reinforcements identified from generator deliverability load flow analysis.
| TO | RTEP ID / TO ID | Title | Time Estimate | Total Cost Estimate ($) | Projects with Cost Allocation | Contingent Projects |
|---|---|---|---|---|---|---|
| AEP | b3775.10 |
Perform sag study mitigation work on Olive – University Park |
Dec 01 2026 |
|
AE1-114, AE1-172, AE2-321, AE2-341, AF1-030, AF1-280, AF1-296, AF2-041, AF2-095, AF2-142, AF2-143, AF2-182, AF2-200, AF2-349, AF2-350, AF2-392, AF2-441, AG1-118, AG1-127 |
|
| AEP | b3775.11 / b3775.7a |
Upgrade the wavetrap at Dumont substation to increase the rating of the Stillwell-Dumont 345 kV line to match conductor rating. |
Dec 01 2026 |
|
AF2-041, AF2-441, AG1-118, AG1-374 |
|
| AEP | b3775.6 |
Perform sag study mitigation work on the Dumont-Stillwell 345 kV line |
Nov 20 2026 |
|
AF2-041, AF2-441, AG1-118, AG1-236, AG1-374 |
|
| AEP | b3788.1 / B3788.1 |
Replace limiting station elements at Kyger Creek |
Nov 18 2027 |
|
AF1-088, AF1-204, AF2-008, AF2-407, AG1-297 |
|
| AEP | b4000.210 |
Rebuild 7 miles of Otter - Johnson Mountain 138 kV line. |
Jun 01 2029 |
|
AE2-185, AE2-187, AE2-283, AE2-291, AF2-297, AG1-105 |
|
| AEP | b4000.211 |
Rebuild 6.5 miles of Johnson Mountain - New London 138 kV line |
Jun 01 2029 |
|
AE2-185, AE2-187, AE2-283, AE2-291, AF2-297, AG1-105 |
|
| AEP | b4000.251 |
Replace the wave trap and upgrade the relay at Cloverdale 765kV substation |
Jun 01 2029 |
|
AF1-088, AG1-494 |
|
| AEP | b4000.252 |
Replace the wave trap and upgrade the relay at Joshua Falls 765kV substation |
Jun 01 2029 |
|
AF1-088, AG1-494 |
|
| AEP | n3985 / AEPO0036a |
Upgrade three Marysville Wavetraps ( 3000A) |
18 to 24 Months |
|
AF1-176, AF2-396, AF2-441 |
|
| AEP | n4056.1 / AEPI0048a |
Replace the (1) 3000A 765kV CB at Dumont station |
18 to 24 Months |
|
AE1-172, AF2-349, AF2-441, AG1-118 |
|
| AEP | n4106.3 |
Extend One (1) Tower on the Jefferson - Clifty Creek (IKEC) 345 kV Circuit |
12 to 18 Months |
|
AE2-261 |
|
| AEP | n5613 / AEPA0014a |
Rebuild 0.9 miles of the Otter - Alta Vista 138 kV line. |
Nov 21 2027 |
|
AE2-185, AE2-187, AE2-283, AE2-291, AF2-297, AG1-105 |
|
| AEP | n5769.4 / AEPI0066a |
Reconductor ~8.58 Miles of 345 kV transmission line from Dumont Station to Structure 39 |
32 Months |
$31,234,000
|
AE1-114, AE1-172, AE2-223, AE2-341, AF1-030, AF1-296, AF2-041, AF2-095, AF2-142, AF2-143, AF2-199, AF2-200, AF2-226, AF2-319, AF2-392, AF2-441, AG1-118, AG1-236, AG1-374, AG1-462 |
|
| AEP | n5808 / N5808 |
CON Upgrade_AEP: eliminate the Eugene stuck breaker contingency. (AMIL upgrade will not be required) |
May 15 2026 |
|
AE1-172, AE2-223, AE2-261, AF1-088, AF2-041, AF2-182, AF2-225, AF2-349, AG1-118, AG1-236, AG1-374, AG1-462, AG1-553 |
|
| AEP | n6497.4 / AEPI0002e/f |
Replace line traps on the Jefferson - Rockport 765 kV line |
35 Months |
$1,212,000
|
AF1-088, AF2-008, AG1-226 |
|
| AEP | n7679 / AEPI0040a |
Replace 1272 AAC Jumper at Allen station |
18 to 24 Months |
|
AF2-376 |
|
| AEP | n7757 / AEPI0063a |
Replace Bus 1 at the Desoto 138 kV Station |
17 Months |
$186,000
|
AF2-173, AF2-177, AF2-388, AG1-367, AG1-375, AG1-433 |
|
| AEP | n7925.1 / AEPI0010a |
Reconductor ~0.41 miles of the Sullivan – West Casey (Ameren) line |
11 Months |
|
AE2-261, AF1-088, AF2-182, AG1-236, AG1-374, AG1-462, AG1-553 |
|
| AEP | n9243.0 / AEPSERG13 |
Expand Jefferson 345 kV station. Install a second 765/345 kV 750 MVA transformer. Install a second Jefferson - Clifty Creek 345 kV single circuit ~0.8 miles. |
55 Months |
$200,238,000
|
AE1-172, AE2-173, AE2-223, AE2-261, AF1-088, AF1-204, AF2-008, AF2-225, AG1-124, AG1-226, AG1-236, AG1-374, AG1-460, AG1-494 |
AE1-114, AE2-185, AE2-187, AE2-283, AE2-321, AE2-341, AF1-030, AF1-280, AF1-296, AF2-041, AF2-095, AF2-142, AF2-143, AF2-182, AF2-200, AF2-349, AF2-350, AF2-392, AF2-441, AG1-118, AG1-127, AG1-436, AG1-447, AG1-553 |
| AEP | s2793.5 / s2793 |
Rebuild the T-line from West Van Wert to Roller Creek |
TBD |
|
AF2-376 |
|
| ATSI | n9228.0 / TC1-ATSI-002.b |
Rebuild 6.6 miles of the Lallendorf-Monroe 345 kV line and install OPGW. Replace line drops and wave traps at Lallendorf. |
29 Months |
$38,362,639
|
AF1-176, AF2-396 |
|
| ATSI | n9322.0 / TE-AG1-S-0012a |
Replace Four (4) disconnect switches, four (4) breaker leads, and one (1) meter, and reconductor two (2) transmission line drops on the Morocco 345 kV line terminal at Allen Junction. |
38 Months |
$1,408,997
|
AF1-176, AF2-396 |
|
| ComEd | b3775.1 |
Swap the NIPSCO Green Acre Tap towers from the St. John-Green Acres-Olive 345 kV line |
Dec 01 2026 |
|
AE1-114, AE1-172, AE2-173, AE2-185, AE2-187, AE2-223, AE2-261, AE2-283, AE2-321, AE2-341, AF1-030, AF1-088, AF1-204, AF1-280, AF1-296, AF2-008, AF2-041, AF2-095, AF2-142, AF2-143, AF2-182, AF2-200, AF2-225, AF2-349, AF2-350, AF2-392, AF2-441, AG1-118, AG1-124, AG1-127, AG1-226, AG1-236, AG1-374, AG1-436, AG1-447, AG1-460, AG1-494, AG1-553 |
|
| ComEd | b3775.3 |
Rebuild ComEd’s section of 345 kV double circuit in IL from St. John to Crete |
Dec 01 2026 |
|
AF2-041, AF2-200, AF2-349, AG1-118 |
|
| ComEd | b3775.4 / CE_B3775.4 |
Rebuild 345 kV double circuit extending from Crete to E. Frankfort. |
Dec 01 2026 |
|
AF2-349 |
|
| ComEd | b3775.5 |
Replace E. Frankfort 345 kV circuit breaker “9-14” with 3150A SF6 circuit breaker. |
Dec 01 2026 |
|
AE1-172, AE2-341, AF2-041, AF2-142, AF2-143, AF2-200, AF2-349, AF2-392, AF2-441, AG1-118 |
|
| ComEd | b3811.1 / CE_PJM B3811_L11323 |
Expand Haumesser Road 138 kV substation as a 4 circuit breaker ring bus. |
Dec 01 2028 |
|
AE1-114, AE1-172, AE2-173, AE2-185, AE2-187, AE2-223, AE2-261, AE2-283, AE2-321, AE2-341, AF1-030, AF1-088, AF1-204, AF1-280, AF1-296, AF2-008, AF2-041, AF2-095, AF2-142, AF2-143, AF2-182, AF2-200, AF2-225, AF2-349, AF2-350, AF2-392, AF2-441, AG1-118, AG1-124, AG1-127, AG1-226, AG1-236, AG1-374, AG1-436, AG1-447, AG1-460, AG1-494, AG1-553 |
|
| ComEd | b3811.2 / CE_PJM B3811_L11323 |
Additional Circuit Breaker at ESS H452 |
Dec 01 2028 |
|
AE1-114, AF2-392 |
|
| ComEd | b3811.3 / CE_PJM B3811_L11323 |
Rebuild 3 miles of 138 kV line 11323 from Haumesser Road to the H-452 tap |
Dec 01 2028 |
|
AE1-114, AF2-392 |
|
| ComEd | n3515.1 / ce-017 |
Cherry Valley - Garden Prarie 345 kV: Line rebuild, station bus work, & Cherry Valley 345kV breaker replacement |
50 Months |
$84,712,245
|
AF2-041, AF2-199, AF2-200 |
|
| ComEd | n5145 |
Reconfigure Wilton 765kV bus |
Dec 31 2025 |
|
AE1-172, AE2-341, AF2-095, AF2-142, AF2-143, AF2-349, AF2-441, AG1-118 |
|
| ComEd | n5318.1 / ce-012a |
Garden Prarie - Silver Lake R 345 kV: Line rebuild, station bus work & Silver Lake 345kV Breaker Replacement |
60 Months |
$163,968,683
|
AF2-041, AF2-199, AF2-200 |
|
| ComEd | n6639.2 / CE_NUN_L15502_4 |
Reconductor the Electric Junction 345 kV line 93407, perform sag mitigation on 345 kV line 93407, upgrade one 345 kV circuit breaker and associated motor operated disconnect switches. |
42 Months |
$146,197,759
|
AE1-114, AF1-280, AF1-296, AF2-041, AF2-182, AF2-199, AF2-200, AF2-392, AG1-462, AG1-553 |
|
| ComEd | n6840 / CE_NUN_Sta. 12 Dresden |
Install a new 345kV bus tie circuit breaker at Station 12 Dresden |
Dec 18 2024 |
|
AE1-172, AE2-173, AE2-223, AE2-261, AF2-225, AG1-236, AG1-374 |
|
| ComEd | n7023.1 / CE_NUN_L11124.1 |
Reconductor the Electric Junction - Lombard line L11124 345 kV Line and perform associated station relay and protection upgrades. |
36 Months |
$38,797,273
|
AE1-114, AE2-341, AF1-030, AF1-280, AF1-296, AF2-041, AF2-182, AF2-199, AF2-200, AF2-349, AF2-392, AG1-118, AG1-127, AG1-462, AG1-553 |
|
| ComEd | n8162 / CE_NUN_0304.1 |
Perform sag mitigation on the Powerton - Tazewell 345 kV Line and replace disconnect switches at Powerton substation. |
1 to 36 Months |
$5,017,397
|
AF2-142, AF2-143, AF2-226, AF2-319 |
|
| ComEd | n9101.0 / CE_NUN_L18806 |
Mitigate sag on the Brokaw to TSS 909 Deer Creek 345 kV line L90907. |
36 Months |
$14,966,004
|
AE2-261, AG1-236, AG1-460 |
|
| ComEd | n9165.0 / CE_NUN_L15502.1 |
Perform TSS 155 Nelson Substation conductor upgrades. |
36 Months |
$1,220,445
|
AE1-114, AF1-280, AF1-296, AF2-182, AF2-392, AG1-462, AG1-553 |
|
| ComEd | n9166.0 / CE_NUN_L16914.1 |
Reconductor the McGirr Road to ESS H447 RT 138 KV line |
24 Months |
$605,422
|
AE1-114, AF2-392 |
|
| ComEd | n9195.0 / CE_NUN_STA12_345 NEW CB |
Install a new 345 kV circuit breaker at Station 12 Dresden. |
45 Months |
$3,357,627
|
AE1-172, AE2-173, AE2-223, AE2-261, AF1-088, AF1-204, AF2-008, AF2-225, AG1-124, AG1-226, AG1-236, AG1-374, AG1-460, AG1-494 |
AE1-114, AE2-185, AE2-187, AE2-283, AE2-321, AE2-341, AF1-030, AF1-280, AF1-296, AF2-041, AF2-095, AF2-142, AF2-143, AF2-182, AF2-200, AF2-349, AF2-350, AF2-392, AF2-441, AG1-118, AG1-127, AG1-436, AG1-447, AG1-553 |
| ComEd | n9269.0 / CE_NUN_L11212.5 |
Reconductor the AD1-100 Tap - Wilton 345 kV line. |
60 Months |
$37,989,655
|
AE1-172, AE2-223, AE2-261, AF2-041, AF2-095, AF2-199, AF2-200, AF2-225, AG1-118, AG1-374, AG1-460 |
|
| ComEd | s3011 / CE_S3011 |
Replace 345kV straight bus at TSS 116 Goodings Grove with a gas insulated switchgear ("GIS") breaker and a half configuration. |
Dec 31 2028 |
|
AE1-114, AE1-172, AE2-173, AE2-185, AE2-187, AE2-223, AE2-261, AE2-283, AE2-321, AE2-341, AF1-030, AF1-088, AF1-204, AF1-280, AF1-296, AF2-008, AF2-041, AF2-095, AF2-142, AF2-143, AF2-182, AF2-200, AF2-225, AF2-349, AF2-350, AF2-392, AF2-441, AG1-118, AG1-124, AG1-127, AG1-226, AG1-236, AG1-374, AG1-436, AG1-447, AG1-460, AG1-494, AG1-553 |
|
| DPL | n6925 / dt22085r0001 |
Rebuild Edge Moor (DPL) - Linwood (PECO) 230 kV line. |
36 to 48 Months |
$71,680,000
|
AF2-358, AG1-450 |
|
| Dayton | b3904.1 |
Rebuild and reconductor 7.7 miles of 69kV line. |
Jun 01 2029 |
|
AF2-376 |
|
| Dominion | b3694.8 |
Partial wreck and rebuild 10.34 miles of 230 kV line #249 Carson-Locks to achieve a minimum summer emergency rating of 1572 MVA. |
May 03 2025 |
|
AF2-042 |
|
| Dominion | b3800.312 |
Rebuild 500 kV Line #569 Loudoun - Morrisville to accommodate the new 500 kV line in the existing right-of-way. |
Jun 30 2030 |
|
AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552 |
|
| Dominion | b3800.313 |
Rebuild approximately 10.29 miles line segment of Line #535 (Meadow Brook to Loudoun) to accommodate the new 500 kV line in the existing ROW. |
Jun 30 2030 |
|
AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552 |
|
| Dominion | b3800.354 |
Install terminal equipment at Wishing Star Substation to support a 5000A line to Vint Hill. Update relay settings for 500 kV Lines #546 and #590. |
Jun 30 2030 |
|
AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552 |
|
| Dominion | b3800.356 |
Build a new 500 kV line from Vint Hill to Wishing Star. |
Jun 30 2030 |
|
AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552 |
|
| Dominion | b3800.357 |
Build a new 500 kV line from Morrisville to Vint Hill. |
Jun 30 2030 |
|
AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552 |
|
| Dominion | b3800.373 |
Wreck and rebuild approximately 7.14 miles of 230kV line #256 from St. Johns to structure 256/108 to achieve a summer rating of 1573 MVA. Line switch 25666 at St. Johns to be upgraded to 4000A. |
Jun 15 2027 |
|
AF2-035 |
|
| Dominion | b3800.374 |
Reconductor approximately 5.30 miles of 230kV line #256 from Ladysmith CT to structure 256/107 to achieve a summer rating of 1573 MVA. |
Jun 15 2027 |
|
AF2-035 |
|
| Dominion | b4000.315 |
Reconductor 230kV Line #2003 Tyler – Poe segment. New conductor has a summer rating of 1573 MVA. |
Apr 22 2030 |
|
AF2-042, AF2-046, AF2-222, AG1-008, AG1-098, AG1-153, AG1-285 |
|
| Dominion | b4000.319 |
Reconductor 230kV Line #2002 Carson – Poe. New conductor has a summer rating of 1573 MVA. |
Mar 20 2030 |
|
AF2-042, AF2-222 |
|
| Dominion | b4000.320 |
At Carson substation, upgrade all line #2002 terminal equipment at Carson to 4000A. CCVTs will also be replaced due to aging. |
Mar 20 2030 |
|
AF2-042, AF2-222 |
|
| Dominion | b4000.321 |
At Poe substation, upgrade all line #2002 terminal equipment at Carson to 4000A. CCVTs will also be replaced due to aging. |
Mar 20 2030 |
|
AF2-042, AF2-222 |
|
| Dominion | b4000.325 |
Build a new 26.38mi 230kV Line from Elmont – Ladysmith on the existing 5-2 structures between the two stations. New conductor has a summer rating of 1573 MVA. |
Feb 24 2029 |
|
AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552 |
|
| Dominion | b4000.326 |
At Elmont substation, install/upgrade associated equipment to accommodate a 4000A line rating for the new 230kV line between Elmont - Ladysmith. |
Feb 24 2029 |
|
AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552 |
|
| Dominion | b4000.327 |
Upgrade/install equipment at Ladysmith Substation to 4000A. Expansion will be required to accommodate a total of three (3) new 230 kV strings of breaker and a half scheme. |
Feb 24 2029 |
|
AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552 |
|
| Dominion | b4000.341 |
Remove the 500 kV conductor previously planned to terminate into the Vint Hill 500 kV Substation and extend approximately 0.2 miles of conductor to fly-over the site. |
Jul 13 2029 |
|
AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552 |
|
| Dominion | b4000.342 |
Remove the terminal equipment and substation work required for the termination of the Morrisville-Wishing Star 500 kV line into Vint Hill. |
Jul 13 2029 |
|
AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552 |
|
| Dominion | b4000.344 |
Build a 500kV line from North Anna substation (bypassing Ladysmith Substation) to a new substation called Kraken. New conductor to have a minimum summer normal rating of 4357MVA. |
Sep 16 2030 |
|
AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552 |
|
| Dominion | b4000.345 |
Build a 500kV line from a new substation called Kraken to a new substation called Yeat. New conductor to have a minimum summer normal rating of 4357MVA. |
Sep 16 2030 |
|
AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552 |
|
| Dominion | b4000.346 |
Cut-in 500kV line from Kraken substation into Yeat substation |
Jun 01 2029 |
|
AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552 |
|
| Dominion | b4000.348 |
Build a new 500/230kV substation called Kraken. The 500kV, 5000A ring bus will be set up for a redundant breaker configuration. Install (2) 1400MVA 500/230 kV transformers. |
Jun 01 2029 |
|
AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552 |
|
| Dominion | b4000.349 |
Update relay settings at Ladysmith to change the destination of 500kV line #568 from Possum Point to Kraken. |
Sep 16 2030 |
|
AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552 |
|
| Dominion | b4000.350 |
Update relay settings at Possum Point to change the destination of 500kV line #568 from Ladysmith to Kraken. |
Sep 16 2030 |
|
AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552 |
|
| Dominion | b4000.351 |
Cut in Line #568 Ladysmith - Possum Point into Kraken, creating Line #9517 Ladysmith to Kraken. |
Sep 16 2030 |
|
AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552 |
|
| Dominion | b4000.352 |
Cut in Line #568 Ladysmith - Possum Point into Kraken, creating new Line #568 Kraken to Possum Point. |
Sep 16 2030 |
|
AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552 |
|
| Dominion | b4000.355 |
Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 69.3 miles in AEP section). |
Jun 01 2029 |
|
AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552 |
|
| Dominion | b4000.356 |
Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 86.7 miles in Dominion section). |
Jun 01 2029 |
|
AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552 |
|
| Dominion | b4000.357 |
Build a new 765/500/230 kV substation called Yeat. Install (2) 765/500 kV transformers. Cut in 500 kV line Bristers-Ox and 500 kV line Meadowbrook-Vint Hill into Yeat. |
Jun 01 2029 |
|
AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552 |
|
| Dominion | n6144 / dom-173 |
Rebuild DEV portion 20.5 miles 2-636 ACSR and Rebuild 17.5 miles 2-636 ACSR between 6GREENVILE T - 6EVERETS 230.0 kV substations. Rating after the upgrade: 1047/1047/1204 |
Nov 25 2026 |
|
AF2-046, AF2-080, AG1-008, AG1-551 |
|
| Dominion | n6605 / dom-101 |
Wreck and rebuild 0.99 miles of line 271 between Pocaty and Landstown with (2)-768 ACSS (20/7) “MAUMEE” conductor @ 250 degrees C. Replace the line lead at Landstown. |
Dec 31 2026 |
$6,555,756
|
AF1-123, AF1-124, AF1-125, AF2-081 |
|
| Dominion | n6618.1 |
Split the 115 kV Bus at Hathaway into two separate buses with a 115 kV Line on each bus and close the tie switch between Line 55 & 80. |
30 to 36 Months |
|
AF2-046, AF2-080, AG1-008 |
|
| Dominion | n6872 / dom-047 |
Wreck and rebuild 15.05 miles of 230 kV line No. 238 between Clubhouse and AE2-033 tap with (2) 768.2 ACSS/TW (20/7) at 250C. |
Dec 31 2029 |
$59,572,939
|
AF2-042, AF2-046, AF2-080, AF2-222, AG1-008, AG1-106, AG1-285 |
|
| Dominion | n7541 / dom-016 |
Add a third 224 MVA 230/115 kV transformer at Earleys Substation and supporting equipment. |
Dec 31 2029 |
$22,779,395
|
AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-494, AG1-536 |
AG1-394, AG1-552 |
| Dominion | n7549 / dom-428 |
Replace Northern Neck 115/230 kV transformer #4 with a 224 MVA (260/271/295 MVA). |
59 to 60 Months |
$7,324,554
|
AF2-120, AG1-135, AG1-146, AG1-147, AG1-536 |
|
| Dominion | n7553 / dom-427 |
Replace Northern Neck 115/230 kV transformer #6 with a 224 MVA (260/271/295 MVA). |
59 to 60 Months |
$7,242,347
|
AF2-120, AG1-135, AG1-146, AG1-147, AG1-536 |
|
| Dominion | n7698 / dom-394 |
Rebuild 4.29 miles of 115 kV line 65 from AD2-074 Tap to AG1-135 Tap with single (1) 768.2 ACSS/TW (20/7) "Maumee" conductor. |
43 to 44 Months |
$20,146,983
|
AG1-146, AG1-147 |
|
| Dominion | n9111.0 / dom-094 |
Wreck and rebuild 3.3 miles of 230 kV transmission line 2092 between S. Hertford and Winfall with (2) 768.2 ACSS/TW (20/7) "MAUMEE" at 250 degrees C and replace line lead at S. Herftord and Winfall |
42 to 43 Months |
$7,341,167
|
AF2-046, AF2-080, AG1-008 |
|
| Dominion | n9112.0 / TC1-PH2-DOM-063 |
Wreck and Rebuild 12.4 miles of 230 kV line 259 with (2) 768.2 ACSS/TW (20/7) "MAUMEE" conductor @ 250 degrees C and replace line lead at Chesterfield. |
46 to 47 Months |
$87,030,447
|
AF1-123, AF1-124, AF1-125, AF2-042, AF2-046, AG1-008 |
|
| Dominion | n9136.0 / TC1-PH1-DOM-066 |
Wreck and rebuild 1.32 miles of 115 kV line from Garner to AG1-135 with 768.2 aluminum conductor steel supported trapezoidal shaped aluminum strands ("ACSS/TW") (20/7). Replace line lead at Garner DP. |
42 to 43 Months |
$8,145,385
|
AG1-135, AG1-146, AG1-147 |
|
| Dominion | n9138.0 / TC1-PH1-DOM-070 |
Wreck and rebuild 22.59 miles of Line #511 between Carson and Rawlings Substations with three (3) 1351 ACSS/TW and associated substation work. |
60 to 61 Months |
$111,130,292
|
AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-494, AG1-536 |
AG1-394, AG1-552 |
| Dominion | n9139.0 / TC1-PH1-DOM-073 |
Wreck and rebuild 37.41 miles of 500kV line 563 between Midlothian and Carson with (3) 1351.5 ACSR (45/7) "Dipper" and associated substation work. |
69 to 70 Months |
$245,455,768
|
AF1-123, AF1-124, AF1-125, AF2-042, AF2-046, AG1-008 |
|
| Dominion | n9143.0 / TC1-PH1-DOM-001 |
Upgrade 1.45 miles of 69 kV line 35 between AltaVista and Gladys Tap with single (1) 768.2 ACSS/TW (20/7) "Maumee" conductor. |
20 to 21 Months |
$6,315,811
|
AE2-185, AE2-187, AE2-283 |
|
| Dominion | n9145.0 / TC1-PH1-DOM-008 |
Reconductor 0.11 miles of 115 kV line between Garner DP and Moon Corner with single (1) 768.2 aluminum conductor steel supported trapezoidal shaped aluminum strands ("ACSS/TW") (20/7). |
18 to 19 Months |
$2,096,619
|
AG1-135, AG1-146, AG1-147 |
|
| Dominion | n9146.0 / TC1-PH1-DOM-004 |
Wreck and rebuild 1.51 miles of 115 kV Line No. 5 between Bremo and Fork Union with (1) 768.2 ACSS/TW (20/7) "MAUMEE" at 250 degrees Celsius. Replace line lead at Bremo. |
42 to 43 Months |
$7,535,533
|
AF1-123, AF1-124, AG1-124, AG1-494 |
|
| Dominion | n9151.0 / TC1-PH1-DOM-026 |
Rebuild 0.76 miles of 115 kV line 93 between Southampton and Watkins Corner with single (1) 768.2 ACSS/TW (20/7) "Maumee" conductor. Replace line lead at Watkins Corner. |
42 to 43 Months |
$4,174,356
|
AF2-046, AG1-008, AG1-394 |
|
| Dominion | n9153.0 / TC1-PH1-DOM-043 |
Wreck and rebuild 5.9 miles of 230 kV line 2128 between Fentress and Thrasher with (2) 768.2 ACSS/TW (20/7) "MAUMEE" conductor @ 250 degrees C and replace line lead at Fentress. |
43 to 44 Months |
$33,297,247
|
AE2-156, AF1-123, AF1-124, AF1-125, AF2-081 |
|
| Dominion | n9154.0 / TC1-PH1-DOM-025 |
Replace switch 9369 at Watkins Corner 115 kV (Watkins Corner - Southampton). |
26 to 27 Months |
$343,523
|
AF2-046, AG1-008, AG1-394 |
|
| Dominion | n9191.0 / TC1-PH1-DOM-090 |
Rebuild 41.13 miles of line 576 between North Anna and Midlothian with triple bundled (3) 1351.5 ACSR (45/7) "Dipper" conductor and associated substation work. |
74 to 75 Months |
$256,706,175
|
AF1-123, AF1-124, AF1-125, AF2-042, AF2-046, AG1-008 |
|
| Dominion | n9199.0 / TC1-PH2-DOM-004 |
Wreck and rebuild 1.63 miles of line 2193 between Fork Union and Bremo with (2) 768.2 ACSS/TW (20/7) "MAUMEE" @ 250C and replace line lead at Bremo. |
42 to 43 Months |
$7,947,612
|
AF1-123, AF1-124, AF1-125, AF1-294, AF2-042, AF2-115, AF2-222, AG1-021, AG1-098, AG1-285 |
|
| Dominion | n9200.0 / TC1-PH2-DOM-005 |
Rebuild 11.79 miles of line 238 between Sapony and Carson with twin bundled (2) 768.2 ACSS/TW (20/7) "Maumee" conductors. |
45 to 46 Months |
$38,691,326
|
AF2-042, AF2-046, AF2-080, AF2-222, AG1-008, AG1-106, AG1-285 |
|
| Dominion | n9201.0 / TC1-PH2-DOM-006 |
Replace wave trap at Carson 230 kV (Carson - Sapony). |
14 to 15 Months |
$521,941
|
AF2-042, AF2-046, AF2-080, AF2-222, AG1-008, AG1-106, AG1-285 |
|
| Dominion | n9204.0 / TC1-PH2-DOM-014 |
Wreck and rebuild 1.63 miles of line 238 between AE2-033 tap and Sapony with (2) 768.2 ACSS/TW (20/7) "MAUMEE" conductor. |
42 to 43 Months |
$6,764,273
|
AF2-042, AF2-046, AF2-080, AF2-222, AG1-008, AG1-106, AG1-285 |
|
| Dominion | n9207.0 / TC1-PH2-DOM-018 |
Replace 6ELMONT 230 kV to 8ELMONT 500 kV circuit 1 with larger transformer (3-480 MVA single phase transformer). |
59 to 60 Months |
$38,254,469
|
AE2-156, AF1-123, AF1-124, AF1-125, AF2-035, AF2-046, AF2-081, AF2-120, AG1-008, AG1-146, AG1-147, AG1-536 |
|
| Dominion | n9208.0 / TC1-PH2-DOM-020 |
Wreck and rebuild 6.87 miles of 115 kV Line 136 from Earleys to Ahoskie with (1) 768.2 ACSS/TW (20/7) "Maumee" conductor @ 250 degrees C. Replace Line Lead at Ahoskie. |
43 to 44 Months |
$25,503,905
|
AF2-046, AG1-008, AG1-082 |
AG1-394 |
| Dominion | n9213.0 / TC1-PH2-DOM-024 |
Reconductor 7.98 miles of 115 kV Line 136 from Tunis to Ahoskie with (1) 768.2 ACSS/TW (20/7) "Maumee" conductor @ 250 degrees C. Upgrade Line Lead at Ahoskie. |
43 to 44 Months |
$24,308,115
|
AF2-046, AG1-008 |
AG1-394 |
| Dominion | n9217.0 / TC1-PH2-DOM-028 |
Wreck and rebuild 12.73 miles of 230 kV Line 298 from Buckingham to Farmville Substations with twin bundled (2) 768 ACSS/TW (20/7) "MAUMEE" conductor. |
45 to 46 Months |
$40,414,822
|
AE1-148, AE2-291, AF1-294, AF2-042, AF2-046, AF2-115, AF2-222, AF2-297, AG1-008, AG1-021, AG1-098, AG1-105, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342 |
|
| Dominion | n9220.0 / TC1-PH2-DOM-033 |
Wreck and rebuild 15.42 miles of 230 kV Line #298 from Buckingham to Bremo Substations with twin bundled (2) 768.2 ACSS/TW (20/7) "MAUMEE" conductor. |
42 to 48 Months |
$44,465,922
|
AE1-148, AE2-291, AF1-294, AF2-042, AF2-046, AF2-115, AF2-222, AF2-297, AG1-008, AG1-021, AG1-098, AG1-105, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342 |
|
| Dominion | n9250.0 / TC1-PH2-DOM-044 |
Construct a new 22.59 mile line between Carson and Rawlings Substations. |
60 to 61 Months |
$108,728,086
|
AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-494, AG1-536 |
AG1-394, AG1-552 |
| Dominion | n9252.0 / TC1-PH2-DOM-047 |
Rebuild 3.81 miles of Line 2021 between Elizabeth City and Shawboro with double bundled (2) 768.2 ACSS/TW (20/7) "Maumee" conductor. |
15 to 16 Months |
$12,801,638
|
AF2-046, AF2-080, AG1-008 |
|
| Dominion | n9264.0 / TC1-PH1-DOM-080 |
Replace Line Lead at Surry for increased rating on Line 567 8SURRY 500 KV to 8CHCKAHM 500 KV ckt 1. |
12 to 13 Months |
$582,006
|
AF1-123, AF1-124, AF1-125, AF2-042, AF2-046, AG1-008 |
|
| Dominion | n9265.0 / TC1-PH2-DOM-064 |
Replace 230 kV wave trap 259WT at Basin 230 kV (Basin - Chesterfield B). |
14 to 15 Months |
$396,021
|
AF1-123, AF1-124, AF1-125, AF2-042, AF2-046, AG1-008 |
|
| Dominion | n9266.0 / TC1-PH2-DOM-065 |
Replace switches 25944 and 25945 at Basin 230 kV (Basin - Chesterfield B). |
38 to 39 Months |
$701,120
|
AF1-123, AF1-124, AF1-125, AF2-042, AF2-046, AG1-008 |
|
| Dominion | n9377.0 / TC1-PH3-DOM-004 |
Upgrade 0.18 miles of 230 kV line 2092 between Pembroke Creek and West Albemarle DP with twin bundled (2) 768.2 ACSS/TW (20/7) "Maumee" conductor. |
Dec 31 2029 |
$2,651,724
|
AF2-046, AF2-080, AG1-008 |
|
| Dominion | n9378.0 / TC1-PH3-DOM-010 |
Replace existing 230/500 kV Carson transformer 2 with (4)-480 MVA single phase transformers. |
Dec 31 2029 |
$37,801,301
|
AF1-123, AF1-124, AF1-125, AF2-042, AF2-222, AG1-098, AG1-153 |
|
| Dominion | n9379.0 / TC1-PH3-DOM-011 |
Replace existing 230/500 kV Transformer 1 at Midlothian with (4)-480 MVA Single Phase transformers. |
Dec 31 2029 |
$37,836,293
|
AF1-123, AF1-124, AF1-125, AF2-042, AF2-046, AG1-008 |
|
| Dominion | n9380.0 / TC1-PH3-DOM-012 |
Replace existing Ladysmith 230/500 kV transformer 1 with four (4) 480 MVA single phase transformers. |
Dec 31 2029 |
$37,587,605
|
AF2-035, AF2-120, AG1-146, AG1-147, AG1-154, AG1-536 |
|
| Dominion | n9646.0 / TC1-PH3-DOM-005 |
Upgrade 7.94 miles of 230 kV line 2092 between West Albemarle DP and South Hertford with twin bundled (2) 768.2 ACSS/TW (20/7) "Maumee" conductor. Upgrade line leads at South Hertford. |
Mar 31 2029 |
$14,749,563
|
AF2-046, AF2-080, AG1-008 |
|
| Dominion | n9651.0 / TC1-PH2-DOM-009 |
Wreck and rebuild 10.05 miles of 115kV transmission line 1059 between Northern Neck and Moon Corner with (1) 768.2 ACSS/TW (20/7) "MAUMEE" conductor and replace line lead at Moon Corner. |
Mar 31 2029 |
$28,476,954
|
AF2-120, AG1-135, AG1-146, AG1-147, AG1-536 |
|
| Dominion | n9652.0 / TC1-PH2-DOM-010 |
Replace Wave Trap at Northern Neck for increased rating of Line 1059 between Northern Neck and Moon Corner |
Mar 01 2027 |
$1,065,776
|
AF2-120, AG1-135, AG1-146, AG1-147, AG1-536 |
|
| Dominion | n9653.0 / TC1-PH2-DOM-011 |
Replace Line Switch at Northern Neck for increased rating of Line 1059 between Northern Neck and Moon Corner |
Mar 01 2027 |
$454,326
|
AF2-120, AG1-135, AG1-146, AG1-147, AG1-536 |
|
| Dominion | s2824 |
Rebuild 230 kV Line #2056 from Hornertown to Hathaway. |
Dec 31 2026 |
|
AF2-046, AG1-008, AG1-106 |
|
| Dominion | s3047.2 |
Install two (2) 1400 MVA 500-230 kV transformers at Vint Hill Substation and loop 500 kV line #535 and #569 into the proposed 500 kV ring bus at Vint Hill Substation. |
Jun 30 2029 |
|
AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552 |
|
| Dominion | s3222.1 |
Rebuild approximately 44.3 miles of 230kV Line #246 between Earleys and Suffolk to current 230kV standards. The normal rating of the line conductor will be 1573 MVA. |
Dec 31 2028 |
|
AF2-046, AF2-080, AG1-008 |
|
| EKPC | n7788.1 / r0071 |
Rebuild the AE2-071-Summer Shade 69 kV line section using 795 MCM ACSR conductor at 212 degrees F (1.7 miles) |
8 to 12 Months |
$2,708,000
|
AF2-365, AG1-070, AG1-071 |
|
| NextEra | b3775.2 |
Reconductor NEET’s section of Crete(IN/IL border)-St. John 345 kV line (6.95 miles). |
May 09 2023 |
|
AF2-041, AF2-200, AF2-349, AG1-118 |
|
| OVEC | b3788.2 / B3788.2 |
Replace limiting station elements at Kyger Creek |
Jun 01 2028 |
|
AF1-088, AF1-204, AF2-008, AF2-407, AG1-297 |
|
| OVEC | n7881 / OVEC0001a |
Sag mitigations to bring the Dearborn – Pierce 345 kV line up to a maximum operating temperature of 311° F |
38 Months |
$24,006,000
|
AF2-173, AF2-177, AF2-388, AF2-407, AG1-297, AG1-367, AG1-375, AG1-433 |
|
| PECO | n9371.0 / PECO 220-85 |
Install OPGW on PECO portion of EDGEMR 5 230.0 kV to LINWOOD85 230.0 kV ckt 1 |
36 to 60 Months |
$232,164
|
AF2-358, AG1-450 |
|
| PENELEC | n9115.0 / PN-AF1-F-0022 |
Replace substation conductor at the 115 kV tie at Shawville Substation |
14 Months |
$509,322
|
AG1-090, AG1-377, AG1-378 |
|
| PENELEC | n9116.0 / TC1-PN-001.d |
Rebuild approximately 11 miles of the Homer City-Shelocta 230 kV line with double bundled 795 kcmil 26/7 ACSS conductor |
31 Months |
$39,312,233
|
AF2-010, AF2-050, AG1-090, AG1-377, AG1-378, AG1-548 |
|
| PENELEC | n9119.0 / TC1-PN-003.b |
Reconductor/Rebuild the Shelocta – Keystone 230 kV Line, approximately 2.5 miles, with 1272 kcmil 45/7 ACSR 2-conductor |
23 Months |
$9,533,592
|
AF2-010, AF2-050, AG1-090, AG1-377, AG1-378, AG1-548 |
|
| PENELEC | n9225.0 / TC1-PN-001.e |
Replace 230 kV substation conductor and line drops at Shelocta substation for the Homer City-Shelocta 230 kV line terminal |
13 Months |
$107,569
|
AF2-010, AF2-050, AG1-090, AG1-377, AG1-378, AG1-548 |
|
| PENELEC | s3334.1 / PN-2023-030 |
Replace the existing Shawville 1A Transformer |
Dec 31 2026 |
|
AF2-296, AG1-090, AG1-377, AG1-378 |
|
| PENELEC | s3335.1 / PN-2024-007 |
Replace Homer City South 345/230-23kV Transformer (Projected ISD 6/1/2027) |
Jun 01 2027 |
|
AF2-010, AG1-548 |
Short Circuit Reinforcements
PJM performed short circuit analysis for the New Service Requests in Transition Cycle 1 Phase III. The table below shows all the system reinforcements identified from short circuit analysis.
| TO | RTEP ID / TO ID | Title | Time Estimate | Total Cost Estimate ($) | Projects with Cost Allocation | Contingent Projects |
|---|---|---|---|---|---|---|
| Dominion | b1696 |
Install a breaker and a half scheme with a minimum of eight 230 kV breakers for five existing lines at Idylwood 230 kV: 20212 and 20712 |
TBD |
|
AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552 |
|
| Dominion | b3689.2 |
Replace 230 kV breakers SC102, H302, H402 and 218302 at Brambleton substation with 80 kA |
Mar 31 2027 |
|
AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552 |
|
| Dominion | b3800.235 |
Replace 5 overdutied 230kV breakers at Loudoun substation with 80kA breakers |
Oct 05 2031 |
|
AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552 |
|
| Dominion | b3800.236 |
Replace 2 overdutied 500kV breakers at Ox Substation with 63kA breakers. |
Jan 05 2029 |
|
AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552 |
|
| Dominion | b3800.334 |
Replace four (4) overdutied 230 kV breakers at Loudoun Substation with 80 kA breakers. |
Oct 05 2031 |
|
AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552 |
|
| Dominion | b3800.335 |
Replace 1 overdutied 500kV breaker at Ox Substation with a 63kA breaker |
Dec 15 2031 |
|
AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552 |
|
| Dominion | b3800.405 |
Replace Brambleton 230 kV breakers 20102, 20602, 204502, 209402, 201T2045, 206T2094 with breakers rated 80 kA. |
Jan 08 2031 |
|
AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552 |
|
| Dominion | b3800.406 |
Replace Gainesville 230 kV breaker 216192 with a breaker rated 80 kA. |
Mar 15 2030 |
|
AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552 |
|
| Dominion | b3800.407 |
Replace Loudoun 230 kV breakers 204552 and 217352 with breakers rated 80 kA. |
Oct 05 2031 |
|
AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552 |
|
| Dominion | b3800.408 |
Replace Ox 230 kV breakers 22042, 24342, 24842, 220T2063, 243T2097, 248T2013, and H342 with breakers rated 80 kA. |
Apr 21 2031 |
|
AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552 |
|
| Dominion | b3853.1 / (Pending) |
Replace over duty Ladysmith CT 230kV circuit breakers SX1272 and SX3472 with an interrupting rating of 63 kA |
TBD |
|
AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552 |
|
| Dominion | b3854.1 |
Replace over duty Carson 230kV circuit breakers 200272 and 24972-3 with an interrupting rating of 63 kA |
May 03 2025 |
|
AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552 |
|
| Dominion | b4000.103 |
Brambleton Sub 230kV - replace 63kA breakers 217202, 2172T2183, L102, L202 with 80kA |
Jun 01 2028 |
|
AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552 |
|
| Dominion | b4000.108 |
Carson Sub 230kV - replace 40kA breaker 23872 with 63kA |
Jul 12 2029 |
|
AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552 |
|
| Dominion | b4000.114 |
Ladysmith S1 Sub 230kV - replace 40kA breakers 25672, 209072, 256T2090, GT172, GT272, GT372, GT472, GT572 with 63kA |
Jul 18 2030 |
|
AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552 |
|
| Dominion | b4000.115 |
Ladysmith Sub 500kV - replace 40kA breaker 574T581 with 63kA |
Nov 27 2031 |
|
AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552 |
|
| Dominion | b4000.119 |
Loudoun Cap Substation 230kV - replace 50 kA breaker SC352 with 63 kA. |
Oct 31 2030 |
|
AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552 |
|
| Dominion | b4000.128 |
North Anna Substation 500 kV - replace 40 kA breakers 57502, G102-1, G102-2, G202, G2T575, and XT573 with 63 kA. |
Oct 13 2032 |
|
AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552 |
|
| Dominion | b4000.134 |
Remington Substation 230 kV - replace 40 kA and 50 kA breakers 211462, GT162, GT262, GT362, GT462, 2077T2086, 208662, H962, and H9T299 with 63 kA. |
Jan 09 2031 |
|
AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552 |
|
| Dominion | b4000.354 |
Ladysmith substation breakers replacement: 574T575 and 568T581 |
Nov 14 2029 |
|
AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552 |
|
| Dominion | n6588 / TC1-PH2-DOM-034 |
Replace 230 kV breaker 210512 at Yadkin 230 kV with a 63 kA breaker. |
Dec 01 2028 |
$1,725,040
|
AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-494, AG1-536 |
AG1-394, AG1-552 |
| Dominion | s2609.6 |
Upgrade two (2) 230 kV breakers 201342 and L142 from 50 kA to 63 kA at Ox Substation due to an insufficient breaker duty rating with the expansion in place. |
Dec 15 2030 |
|
AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552 |
|
| Dominion | s2609.9 |
Upgrade 230 kV Pleasant View breakers L3T203 and L3T2180 from 50 kA to 80 kA. |
Sep 13 2030 |
|
AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552 |
Stability Reinforcements
PJM performed stability analysis for the New Service Requests in Transition Cycle 1 Phase III. The table below shows all the system reinforcements identified from stability analysis.
| TO | RTEP ID / TO ID | Title | Time Estimate | Total Cost Estimate ($) | Projects with Cost Allocation | Contingent Projects |
|---|---|---|---|---|---|---|
| DPL | n9645.0 / (Pending) |
Install 10 MVAR Cap Bank at new AF2-358 69kV Interconnection Swyd |
Jun 01 2027 |
$2,479,762
|
AF2-358, AG1-450 |
|
| Dominion | n8492 |
Wreck and rebuild the existing Yadkin to Fentress 500 kV Line #588 to share the right of way with the new Yadkin to Fentress #5005 line. |
26 to 27 Months |
$80,172,278
|
AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-494, AG1-536 |
AG1-394, AG1-552 |
| Dominion | n8492.1 |
Two Breaker Additions at Fentress Substation. |
30 to 36 Months |
$19,945,879
|
AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-494, AG1-536 |
AG1-394, AG1-552 |
| Dominion | n8492.2 |
Expand Yadkin Substation to accommodate the new 500 kV line. |
15 to 16 Months |
$16,207,123
|
AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-494, AG1-536 |
AG1-394, AG1-552 |
| Dominion | n9259.0 |
Install two 230 kV gas insulated switchgear ("GIS") bus ties for the Coastal Virginia Offshore Wind ("CVOW") project. |
38 to 39 Months |
$25,304,902
|
AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-494, AG1-536 |
AG1-394, AG1-552 |
| Dominion | n9267.0 / TC1-PH2-DOM-067 |
Construct new 10.21 mile 115 kV line between Northern Neck and Moon Corner. |
45 to 46 Months |
$45,730,074
|
AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-494, AG1-536 |
AG1-394, AG1-552 |
| Dominion | n9630.0 / TC1-PH3-DOM-013 |
Construct a new 230 kV line from the AG1-285 substation to the Finneywood 230 kV Substation. Expand AG1-285 substation and add two (2) new 230/115 kV transformers. |
Dec 31 2029 |
$89,468,616
|
AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-494, AG1-536 |
AG1-394, AG1-552 |
| Dominion | n9647.0 |
Install a 300 MVAR STATCOM at Fentress Substation. |
Mar 31 2029 |
$49,163,341
|
AF1-123, AF1-124, AF1-125 |
|
[1]Winter load flow analysis will be performed starting in Transition Cycle 2.
[2]State - The state in which the generator or merchant transmission facility is located.
[3]The Transmission Owner of the facility where the New Service Request project interconnects to the transmission system.
Note: Additional detail can be found in each of the individual TC1 New Service Request System Impact Study reports also available on PJM.com.