Transition Cycle 1

v1.00 released 2025-09-18 09:40

New Service Requests

System Impact Study Executive Summary Report

Transition Cycle 1 Phase III

Introduction

This Phase III System Impact Study executive summary report has been prepared in accordance with the PJM Open Access Transmission Tariff Part VII, Subpart D, section 312. This report presents an executive summary of Phase III System Impact Study results for New Service Requests (projects) in Transition Cycle 1.

Preface

The Phase III System Impact Study is conducted on an aggregate basis within a New Services Request’s Cycle, and results are provided in both (i) a single Cycle summary format and (ii) an individual project-level basis. The Phase III System Impact Study Results (for both the summary and individual reports) will be publicly available on PJM’s website. Project Developers must obtain the results from the website.

In accordance with PJM Manual 14H, section 4.7, PJM takes the following actions during the Phase III System Impact Study:

  1. PJM studies each New Service Request on a summer peak, winter peak[1] and light load RTEP base case study. The case year is dependent on the new services cycle under study. PJM will identify the base case year to be used in the study of a specific cycle on its website.
  2. PJM will perform load flow, short circuit, and stability analysis during the Phase III System Impact Study.
  3. In Phase III of the Cycle, PJM will coordinate with Affected System Operators to conduct any studies required to determine the impact of a New Service Request on any Affected System.
  4. The Phase III System Impact Study results will be publicly available on PJM’s website. Project Developers and Eligible Customers must obtain the results from the website.
  5. PJM will tender draft final agreements to Project Developers or Eligible Customers.

New Services Request List

PJM received 130 New Service Requests in Transition Cycle 1, Phase III with a combined Maximum Facility Output (MFO) of 19,353.8 MW and 9,891.3 MW as Capacity Interconnection Rights (CIRs). All of these New Service Requests are listed in table below.

List of Projects Studied in Transition Cycle 1 Phase III
Project ID Project Name / POI State[2] Status Transmission Owner[3] Maxiumum Facility Output (MFO in MW) MW Energy (MWE) MW Capacity (MWC) Project Type Resource Type Facilities Study
AE1-092 Blue Jacket-Kirby 138 kV Ohio Active The Dayton Power and Light Company 206.55 206.6 96.4 Generation Interconnection Solar
AE1-114 Maryland-Lancaster 138 kV Illinois Active Commonwealth Edison Company 150.0 150.0 34.0 Generation Interconnection Wind
AE1-148 Kerr Dam-Ridge Rd 115 kV Virginia Active Virginia Electric and Power Company (Dominion Virginia Power) 90.0 90.0 54.0 Generation Interconnection Solar
AE1-172 Loretto-Wilton Center Illinois Active Commonwealth Edison Company 255.0 255.0 44.88 Generation Interconnection Wind
AE2-156 Yadkin 115 kV Virginia Active Virginia Electric and Power Company (Dominion Virginia Power) 100.0 100.0 100.0 Generation Interconnection Storage
AE2-173 McLean 345 kV Illinois Active Commonwealth Edison Company 250.0 50.0 50.0 Generation Interconnection Storage
AE2-185 Gladys DP-Stonemill Switching Station 69 kV Virginia Active Virginia Electric and Power Company (Dominion Virginia Power) 60.0 60.0 36.0 Generation Interconnection Solar
AE2-187 Shockoe DP-Chatham 69 kV Virginia Active Virginia Electric and Power Company (Dominion Virginia Power) 60.0 60.0 36.0 Generation Interconnection Solar
AE2-223 McLean 345 kV Illinois Active Commonwealth Edison Company 350.0 150.0 19.5 Generation Interconnection Wind
AE2-261 Kincaid-Pana 345 kV Illinois Active Commonwealth Edison Company 299.0 299.0 179.4 Generation Interconnection Solar
AE2-283 Gladys-Stone Mill 69 kV Virginia Active Virginia Electric and Power Company (Dominion Virginia Power) 53.0 53.0 28.0 Generation Interconnection Solar
AE2-291 Grit DP-Perth 115 kV Virginia Active Virginia Electric and Power Company (Dominion Virginia Power) 102.0 102.0 61.2 Generation Interconnection Solar
AE2-308 Three Forks-Dale 138 kV Kentucky Active East Kentucky Power Cooperative, Inc. 100.0 100.0 60.0 Generation Interconnection Solar
AE2-321 Belvidere-Marengo 138 kV Illinois Active Commonwealth Edison Company 100.0 100.0 67.0 Generation Interconnection Solar
AE2-325 Valley 138 kV Michigan Active AEP Indiana Michigan Transmission Company, Inc. 152.2 52.2 31.32 Generation Interconnection Storage
AE2-341 Sandwich-Plano 138 kV Illinois Active Commonwealth Edison Company 150.0 150.0 100.6 Generation Interconnection Solar
AF1-030 Sandwich-Plano 138 kV Illinois Active Commonwealth Edison Company 250.0 100.0 66.9 Generation Interconnection Solar
AF1-088 Sullivan 345 kV Indiana Active AEP Indiana Michigan Transmission Company, Inc. 1000.0 1000.0 1000.0 Merchant Transmission None
AF1-123 Oceana 230 kV Virginia Active Virginia Electric and Power Company (Dominion Virginia Power) 833.0 833.0 253.2 Generation Interconnection Offshore Wind
AF1-124 Oceana 230 kV Virginia Active Virginia Electric and Power Company (Dominion Virginia Power) 836.0 836.0 254.1 Generation Interconnection Offshore Wind
AF1-125 Oceana 230 kV Virginia Active Virginia Electric and Power Company (Dominion Virginia Power) 820.0 820.0 249.3 Generation Interconnection Offshore Wind
AF1-128 Chesterfield 230 kV Virginia Active Virginia Electric and Power Company (Dominion Virginia Power) 569.0 569.0 569.0 Generation Interconnection Natural Gas
AF1-161 Valley 138 kV Michigan Active AEP Indiana Michigan Transmission Company, Inc. 50.0 50.0 25.0 Generation Interconnection Storage
AF1-176 Corey 138 kV Michigan Active AEP Indiana Michigan Transmission Company, Inc. 300.0 300.0 155.682 Generation Interconnection Solar; Storage
AF1-204 Eugene 345 kV Indiana Active AEP Indiana Michigan Transmission Company, Inc. 255.0 255.0 63.75 Generation Interconnection Wind
AF1-233 Flemingsburg – Spurlock 138kV Kentucky Active East Kentucky Power Cooperative, Inc. 188.5 188.5 113.1 Generation Interconnection Solar
AF1-238 Sherman Ave - West Vineland 69 kV New Jersey Active Atlantic City Electric 50.0 50.0 20.0 Generation Interconnection Storage Not Required
AF1-240 Timblin 34.5 kV Pennsylvania Active Mid-Atlantic Interstate Transmission, LLC 15.75 15.75 11.0 Generation Interconnection Solar
AF1-280 Nelson-Lee County Illinois Active Commonwealth Edison Company 200.0 200.0 0.0 Generation Interconnection Solar
AF1-294 Jetersville-Ponton 115 kV Virginia Active Virginia Electric and Power Company (Dominion Virginia Power) 41.0 41.0 22.2 Generation Interconnection Solar
AF1-296 Garden Plain 138 kV Illinois Active Commonwealth Edison Company 190.89 190.89 33.6 Generation Interconnection Wind
AF2-008 Sullivan 345 kV Indiana Active AEP Indiana Michigan Transmission Company, Inc. 2000.0 1000.0 500.0 Merchant Transmission None
AF2-010 Union City-Titusville 115 kV Pennsylvania Active Mid-Atlantic Interstate Transmission, LLC 77.0 77.0 46.0 Generation Interconnection Solar
AF2-035 St. Johns 115 kV Virginia Active Virginia Electric and Power Company (Dominion Virginia Power) 72.0 72.0 48.0 Generation Interconnection Solar Not Required
AF2-041 Nelson-Electric Junction 345 kV Illinois Active Commonwealth Edison Company 300.0 300.0 180.0 Generation Interconnection Solar
AF2-042 Clover-Rawlings 500 kV Virginia Active Virginia Electric and Power Company (Dominion Virginia Power) 500.0 500.0 300.0 Generation Interconnection Solar
AF2-046 Tunis-Mapleton 115 kV North Carolina Active Virginia Electric and Power Company (Dominion Virginia Power) 126.0 126.0 83.7 Generation Interconnection Solar
AF2-050 Bear Rock-Johnstown 230 kV Pennsylvania Active Mid-Atlantic Interstate Transmission, LLC 150.0 50.0 30.0 Generation Interconnection Solar
AF2-068 Jay 138 kV Indiana Active AEP Indiana Michigan Transmission Company, Inc. 150.0 150.0 90.0 Generation Interconnection Solar
AF2-069 Crescent Ridge 138 kV Illinois Active Commonwealth Edison Company 87.8 8.4 1.98 Generation Interconnection Wind
AF2-080 Chinquapin-Everetts 230 kV North Carolina Active Virginia Electric and Power Company (Dominion Virginia Power) 150.0 70.0 48.5 Generation Interconnection Solar Not Required
AF2-081 Moyock 230 kV North Carolina Active Virginia Electric and Power Company (Dominion Virginia Power) 80.0 80.0 56.0 Generation Interconnection Solar
AF2-095 Davis Creek 138 kV Illinois Active Commonwealth Edison Company 144.0 144.0 86.4 Generation Interconnection Solar
AF2-111 North Clark-Spurlock 345 kV Kentucky Active East Kentucky Power Cooperative, Inc. 250.0 250.0 150.0 Generation Interconnection Solar
AF2-115 Jetersville-Ponton 115 kV Virginia Active Virginia Electric and Power Company (Dominion Virginia Power) 66.0 25.0 13.5 Generation Interconnection Solar
AF2-120 Garner-Northern Neck 115 kV Virginia Active Virginia Electric and Power Company (Dominion Virginia Power) 62.0 62.0 37.2 Generation Interconnection Solar
AF2-126 Weston 69 kV II Ohio Active American Transmission Systems, Incorporated 62.0 12.0 8.0 Generation Interconnection Solar
AF2-142 Nevada 345 kV Illinois Active Commonwealth Edison Company 300.0 150.0 90.0 Generation Interconnection Solar
AF2-143 Powerton-Nevada 345 kV Illinois Active Commonwealth Edison Company 300.0 150.0 90.0 Generation Interconnection Solar
AF2-173 Desoto 345 kV Indiana Active Indiana Michigan Power Company 340.0 140.0 84.0 Generation Interconnection Solar
AF2-177 Sorenson-DeSoto #2 345 kV Indiana Active AEP Indiana Michigan Transmission Company, Inc. 200.0 200.0 26.0 Generation Interconnection Wind
AF2-182 Nelson-Lee County 345 kV II Illinois Active Commonwealth Edison Company 500.0 300.0 0.0 Generation Interconnection Solar
AF2-199 Nelson-Electric Junction 345 kV Illinois Active Commonwealth Edison Company 400.0 100.0 60.0 Generation Interconnection Solar
AF2-200 Nelson-Electric Junction 345 kV Illinois Active Commonwealth Edison Company 600.0 200.0 120.0 Generation Interconnection Solar
AF2-222 Madisonville DP-Twitty's Creek 115 kV Virginia Active Virginia Electric and Power Company (Dominion Virginia Power) 167.0 167.0 100.0 Generation Interconnection Solar
AF2-225 McLean 345 kV Illinois Active Commonwealth Edison Company 500.0 150.0 63.0 Generation Interconnection Solar
AF2-226 Katydid Road 345 kV Illinois Active Commonwealth Edison Company 350.0 50.0 20.0 Generation Interconnection Storage
AF2-296 Madera 34.5 kV Pennsylvania Active Mid-Atlantic Interstate Transmission, LLC 20.0 20.0 12.0 Generation Interconnection Solar Not Required
AF2-297 Sedge Hill 115 kV Virginia Active Virginia Electric and Power Company (Dominion Virginia Power) 80.0 80.0 48.0 Generation Interconnection Solar
AF2-299 Fields 34.5 kV Virginia Active Virginia Electric and Power Company (Dominion Virginia Power) 18.0 18.0 10.8 Generation Interconnection Solar Not Required
AF2-307 Hope-Belvins Valley Tap 69 kV Kentucky Active East Kentucky Power Cooperative, Inc. 64.2 64.2 39.6 Generation Interconnection Solar
AF2-319 Katydid Road 345 kV Illinois Active Commonwealth Edison Company 400.0 50.0 20.0 Generation Interconnection Storage
AF2-335 Delaware-Royerton 138 kV Indiana Active AEP Indiana Michigan Transmission Company, Inc. 100.0 100.0 60.0 Generation Interconnection Solar
AF2-349 SILVER LAKE- CHERRY VALLEY 345 KV Illinois Active Commonwealth Edison Company 300.0 300.0 0.0 Generation Interconnection Solar
AF2-350 Kensington 138 kV Illinois Active Commonwealth Edison Company 100.0 100.0 60.0 Generation Interconnection Solar
AF2-358 Airey-Vienna 69 kV Maryland Active Delmarva Power and Light Company 100.0 100.0 60.0 Generation Interconnection Solar
AF2-365 Munfordville KU Tap-Horse Cave Jct. 69 kV Kentucky Active East Kentucky Power Cooperative, Inc. 50.0 50.0 30.0 Generation Interconnection Solar
AF2-370 Delaware-Royerton 138 kV Indiana Active AEP Indiana Michigan Transmission Company, Inc. 100.0 0.0 20.0 Generation Interconnection Storage
AF2-376 Timber Switch 138 kV Ohio Active Ohio Power Company 149.0 50.0 20.0 Generation Interconnection Storage
AF2-388 Keystone-Desoto 345 kV Indiana Active AEP Indiana Michigan Transmission Company, Inc. 200.0 200.0 35.2 Generation Interconnection Wind
AF2-392 Nelson-Dixon 138 kV Illinois Active Commonwealth Edison Company 199.0 199.0 35.2 Generation Interconnection Wind
AF2-396 Stinger 138 kV Michigan Active AEP Indiana Michigan Transmission Company, Inc. 200.0 200.0 200.0 Generation Interconnection Solar; Storage
AF2-404 Gladys DP-Stonemill 69 kV Virginia Active Virginia Electric and Power Company (Dominion Virginia Power) 60.0 0.0 0.0 Generation Interconnection Storage
AF2-407 Fall Creek 345 kV Indiana Active AEP Indiana Michigan Transmission Company, Inc. 300.0 300.0 300.0 Generation Interconnection Storage
AF2-441 Burnham 138kV Illinois Active Commonwealth Edison Company 200.0 200.0 80.0 Generation Interconnection Storage
AG1-008 Tunis-Mapleton 115 kV North Carolina Active Virginia Electric and Power Company (Dominion Virginia Power) 126.0 126.0 83.7 Generation Interconnection Solar
AG1-021 Jetersville-Ponton 115 kV Virginia Active Virginia Electric and Power Company (Dominion Virginia Power) 86.0 20.0 10.8 Generation Interconnection Solar
AG1-070 Bon Ayr 69 kV Kentucky Active East Kentucky Power Cooperative, Inc. 45.0 45.0 32.7 Generation Interconnection Solar
AG1-071 Bon Ayr 69 kV Kentucky Active East Kentucky Power Cooperative, Inc. 100.0 55.0 37.5 Generation Interconnection Solar
AG1-082 Ahoskie 34.5 kV North Carolina Active Virginia Electric and Power Company (Dominion Virginia Power) 20.0 20.0 12.0 Generation Interconnection Solar; Storage Not Required
AG1-090 Philipsburg 115 kV Pennsylvania Active Mid-Atlantic Interstate Transmission, LLC 95.0 95.0 30.0 Generation Interconnection Solar; Storage
AG1-098 Briery-Clover 230 kV Virginia Active Virginia Electric and Power Company (Dominion Virginia Power) 107.0 107.0 64.2 Generation Interconnection Solar
AG1-105 Mount Laurel-Barnes Junction 115 kV Virginia Active Virginia Electric and Power Company (Dominion Virginia Power) 90.0 90.0 54.0 Generation Interconnection Solar
AG1-106 Thelma 230 kV North Carolina Active Virginia Electric and Power Company (Dominion Virginia Power) 143.0 23.0 16.0 Generation Interconnection Solar Not Required
AG1-109 Valley 138 kV Michigan Active AEP Indiana Michigan Transmission Company, Inc. 50.0 0.0 25.0 Generation Interconnection Storage
AG1-118 Sugar Grove-Waterman 138kV Illinois Active Commonwealth Edison Company 300.0 300.0 180.0 Generation Interconnection Solar
AG1-124 Gladstone 138 kV Virginia Active Appalachian Power Company 90.0 90.0 53.01 Generation Interconnection Solar
AG1-127 Crego Rd 138 kV Illinois Active Commonwealth Edison Company 190.0 95.1 57.1 Generation Interconnection Solar
AG1-135 Garner-Lancaster 115 kV Virginia Active Virginia Electric and Power Company (Dominion Virginia Power) 60.0 60.0 36.0 Generation Interconnection Solar
AG1-146 Garner DP-Lancaster 115 kV Virginia Active Virginia Electric and Power Company (Dominion Virginia Power) 30.0 30.0 18.0 Generation Interconnection Solar
AG1-147 Garner DP-Lancaster 115 kV Virginia Active Virginia Electric and Power Company (Dominion Virginia Power) 100.0 70.0 42.0 Generation Interconnection Solar
AG1-153 Heritage 500 kV Virginia Active Virginia Electric and Power Company (Dominion Virginia Power) 75.0 75.0 30.0 Generation Interconnection Storage
AG1-154 Ladysmith CT 230 kV Virginia Active Virginia Electric and Power Company (Dominion Virginia Power) 50.0 50.0 20.0 Generation Interconnection Storage
AG1-166 Lone Pine 115 kV Virginia Active Virginia Electric and Power Company (Dominion Virginia Power) 20.0 20.0 6.0 Generation Interconnection Solar
AG1-167 Lone Pine 115 kV Virginia Active Virginia Electric and Power Company (Dominion Virginia Power) 35.0 15.0 4.5 Generation Interconnection Solar
AG1-168 Lone Pine 115 kV Virginia Active Virginia Electric and Power Company (Dominion Virginia Power) 50.0 15.0 4.5 Generation Interconnection Solar
AG1-226 Dequine-Eugene 345 kV Indiana Active AEP Indiana Michigan Transmission Company, Inc. 450.0 450.0 142.0 Generation Interconnection Solar
AG1-236 Lanesville-Brokaw 345 kV Illinois Active Commonwealth Edison Company 380.0 180.0 23.4 Generation Interconnection Wind
AG1-285 Chase City-Central 115 kV Virginia Active Virginia Electric and Power Company (Dominion Virginia Power) 125.0 125.0 75.0 Generation Interconnection Solar
AG1-297 Hanna-Tanners Creek 345 kV Indiana Active AEP Indiana Michigan Transmission Company, Inc. 300.0 300.0 75.0 Generation Interconnection Storage
AG1-320 Glendale-Stephensburg 69 kV Kentucky Active East Kentucky Power Cooperative, Inc. 82.0 82.0 54.8 Generation Interconnection Solar
AG1-323 Blue Jacket 138 kV Ohio Active The Dayton Power and Light Company 40.0 40.0 40.0 Generation Interconnection Solar; Storage
AG1-341 Summer Shade 161 kV Kentucky Active East Kentucky Power Cooperative, Inc. 106.0 106.0 63.6 Generation Interconnection Solar; Storage
AG1-342 Dryburg 115 kV Virginia Active Virginia Electric and Power Company (Dominion Virginia Power) 36.0 36.0 21.6 Generation Interconnection Solar
AG1-354 Summershade-Green County 161 kV Kentucky Active East Kentucky Power Cooperative, Inc. 150.0 150.0 90.0 Generation Interconnection Solar
AG1-367 DeSoto 345 kV Indiana Active Indiana Michigan Power Company 440.0 100.0 60.0 Generation Interconnection Solar
AG1-374 Blue Mound 345 kV Illinois Active Commonwealth Edison Company 300.0 300.0 180.0 Generation Interconnection Solar
AG1-375 Sorenson-Desoto 345 kV Indiana Active AEP Indiana Michigan Transmission Company, Inc. 300.0 100.0 60.0 Generation Interconnection Solar
AG1-377 Philipsburg 115 kV Pennsylvania Active Mid-Atlantic Interstate Transmission, LLC 115.0 20.0 6.0 Generation Interconnection Solar
AG1-378 Philipsburg 115 kV Pennsylvania Active Mid-Atlantic Interstate Transmission, LLC 135.0 20.0 6.0 Generation Interconnection Solar
AG1-393 Fort Pickett DP 34.5 kV Virginia Active Virginia Electric and Power Company (Dominion Virginia Power) 20.0 20.0 12.0 Generation Interconnection Solar Not Required
AG1-394 Boykins 34.5 kV Virginia Active Virginia Electric and Power Company (Dominion Virginia Power) 14.2 14.2 5.0 Generation Interconnection Solar Not Required
AG1-405 Walnut Grove-Asahi 69 kV Kentucky Active East Kentucky Power Cooperative, Inc. 57.0 57.0 34.2 Generation Interconnection Solar
AG1-406 Walnut Grove-Asahi 69 kV Kentucky Active East Kentucky Power Cooperative, Inc. 79.0 22.0 22.0 Generation Interconnection Storage
AG1-410 Maddox Creek-RP Mone 345 kV Ohio Active Ohio Power Company 300.0 300.0 180.0 Generation Interconnection Solar
AG1-411 Maddox Creek-RP Mone 345 kV Ohio Active Ohio Power Company 400.0 100.0 100.0 Generation Interconnection Storage
AG1-433 Keystone-DeSoto 345 kV Indiana Active AEP Indiana Michigan Transmission Company, Inc. 300.0 100.0 17.6 Generation Interconnection Wind
AG1-436 Olive-University Park 345 kV Indiana Active AEP Indiana Michigan Transmission Company, Inc. 250.0 125.0 75.0 Generation Interconnection Solar
AG1-447 Olive-University Park 345 kV Indiana Active AEP Indiana Michigan Transmission Company, Inc. 305.0 55.0 55.0 Generation Interconnection Storage
AG1-450 Airey-Vienna 69 kV II Maryland Active Delmarva Power and Light Company 125.0 25.0 25.0 Generation Interconnection Storage
AG1-460 Kincaid-Pana 345 kV Illinois Active Commonwealth Edison Company 329.0 30.0 12.0 Generation Interconnection Storage
AG1-462 Cordova 345 kV Illinois Active Commonwealth Edison Company 255.0 255.0 153.0 Generation Interconnection Solar
AG1-471 Up Church-Wayne County 69 kV Kentucky Active East Kentucky Power Cooperative, Inc. 54.0 54.0 32.4 Generation Interconnection Solar
AG1-494 Boxwood-Riverville 138 kV Virginia Active Appalachian Power Company 50.0 50.0 20.0 Generation Interconnection Storage
AG1-526 West Garrard 345 kV Kentucky Active East Kentucky Power Cooperative, Inc. 222.0 222.0 133.2 Generation Interconnection Solar
AG1-536 Garner-Northern Neck 115 kV Virginia Active Virginia Electric and Power Company (Dominion Virginia Power) 137.0 75.0 32.0 Generation Interconnection Storage
AG1-548 Erie South-Union City 115 kV Pennsylvania Active Mid-Atlantic Interstate Transmission, LLC 150.0 150.0 45.0 Generation Interconnection Solar; Storage
AG1-551 Parmele 34.5 kV North Carolina Active Virginia Electric and Power Company (Dominion Virginia Power) 19.99 19.99 13.1 Generation Interconnection Solar
AG1-552 Carolina 34.5 kV North Carolina Active Virginia Electric and Power Company (Dominion Virginia Power) 18.0 18.0 12.2 Generation Interconnection Solar
AG1-553 Cordova 345 kV Illinois Active Commonwealth Edison Company 260.0 260.0 0.0 Generation Interconnection Solar

Stability Clusters

Stability analysis was performed by grouping New Service Requests into clusters based on their electrical proximity in order to increase the efficiency of the stability study process. A single stability study is performed for all New Service Requests in the cluster and any reinforcement costs shall be cost allocated proportionally to all New Service Requests in the cluster.

List of Stability Clusters Studied in Transition Cycle 1 Phase III
Cluster Index Cluster Name New Service Requests Status Executive Summary
1 Cluster 1 AE2-341, AF1-030, AG1-118, AG1-127 Analysis Complete - No Issues
2 Cluster 2 AE1-114 Analysis Complete - No Issues
3 Cluster 3 AF2-350 Analysis Complete - No Issues
4 Cluster 4 AE2-321 Analysis Complete - No Issues
5 Cluster 5 AF2-226, AF2-319 Analysis Complete - No Issues
6 Cluster 6 AF2-392 Analysis Complete - No Issues
7 Cluster 7 AE2-261, AG1-236, AG1-460 Analysis Complete - No Issues
8 Cluster 8 AE1-172, AE2-173, AE2-223, AF2-225 Analysis Complete - No Issues
9 Cluster 9 AF2-069 Analysis Complete - No Issues
11 Cluster 11 AF2-441 Analysis Complete - No Issues
13 Cluster 13 AF2-142, AF2-143 Analysis Complete - No Issues
14 Cluster 14 AF2-095 Analysis Complete - No Issues
15 Cluster 15 AF2-041, AF2-199, AF2-200 Analysis Complete - No Issues
16 Cluster 16 AF1-280, AF2-182, AF2-349 Analysis Complete - No Issues
17 Cluster 17 AF1-296, AG1-462, AG1-553 Analysis Complete - No Issues
21 Cluster 21 AG1-374 Analysis Complete - No Issues
23 Cluster 23 AE1-092, AG1-323 Analysis Complete - No Issues
24 Cluster 24 AF1-233, AF2-307 Analysis Complete - No Issues
25 Cluster 25 AG1-354, AG1-471 Analysis Complete - No Issues
26 Cluster 26 AE2-308 Analysis Complete - No Issues
27 Cluster 27 AF2-111, AG1-526 Analysis Complete - No Issues
29 Cluster 29 AF1-123, AF1-124, AF1-125 Analysis Complete - Issues Found
30 Cluster 30 AF1-294, AF2-115, AG1-021, AG1-166, AG1-167, AG1-168 Analysis Complete - No Issues
31 Cluster 31 AF2-222, AG1-285 Analysis Complete - Issues Found
32 Cluster 32 AF2-120, AG1-135, AG1-146, AG1-147, AG1-536 Analysis Complete - Issues Found
33 Cluster 33 AE2-187 Analysis Complete - No Issues
34 Cluster 34 AE1-148, AE2-291, AF2-297, AG1-105, AG1-342 Analysis Complete - No Issues
35 Cluster 35 AE2-185, AE2-283, AF2-404 Analysis Complete - No Issues
37 Cluster 37 AF2-046, AG1-008 Analysis Complete - No Issues
39 Cluster 39 AF2-080, AG1-106 Analysis Complete - No Issues
42 Cluster 42 AF2-035, AG1-154 Analysis Complete - No Issues
44 Cluster 44 AF2-081 Analysis Complete - No Issues
45 Cluster 45 AF2-042, AG1-098 Analysis Complete - No Issues
46 Cluster 46 AE2-156 Analysis Complete - No Issues
47 Cluster 47 AG1-153 Analysis Complete - No Issues
48 Cluster 48 AF1-128 Analysis Complete - No Issues
52 Cluster 52 AF1-088, AF2-008 Analysis Complete - No Issues
54 Cluster 54 AG1-124, AG1-494 Analysis Complete - No Issues
55 Cluster 55 AE2-325, AF1-161, AF1-176, AF2-396, AG1-109 Analysis Complete - No Issues
56 Cluster 56 AG1-410, AG1-411 Analysis Complete - No Issues
58 Cluster 58 AG1-436, AG1-447 Analysis Complete - No Issues
59 Cluster 59 AF2-335, AF2-370 Analysis Complete - No Issues
60 Cluster 60 AF2-068 Analysis Complete - No Issues
62 Cluster 62 AF2-173, AF2-177, AF2-407, AG1-367, AG1-375 Analysis Complete - No Issues
63 Cluster 63 AF2-388, AG1-433 Analysis Complete - No Issues
64 Cluster 64 AF1-204, AG1-226 Analysis Complete - No Issues
65 Cluster 65 AG1-297 Analysis Complete - No Issues
69 Cluster 69 AF2-010, AG1-548 Analysis Complete - No Issues
70 Cluster 70 AF2-050 Analysis Complete - No Issues
71 Cluster 71 AG1-090, AG1-377, AG1-378 Analysis Complete - No Issues
72 Cluster 72 AF1-238 Analysis Complete - No Issues
74 Cluster 74 AF2-126 Analysis Complete - No Issues
75 Cluster 75 AF2-358, AG1-450 Analysis Complete - Issues Found
83 Cluster 83 AF2-365 Analysis Complete - No Issues
84 Cluster 84 AG1-341 Analysis Complete - No Issues
85 Cluster 85 AG1-320 Analysis Complete - No Issues
86 Cluster 86 AG1-070, AG1-071 Analysis Complete - No Issues
87 Cluster 87 AG1-405, AG1-406 Analysis Complete - No Issues
88 Cluster 88 AF2-376 Analysis Complete - No Issues

Executive Summary for Stability Cluster

Executive Summary:

New Service Requests (projects) in PJM Transition Cycle 1, Cluster 01 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 01 projects.

This analysis is effectively a screening study to determine whether the addition of the cluster 01 projects will meet the dynamics requirements of the NERC, ComEd and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 01 projects have been dispatched online at maximum power output, with 1.0 voltage at the terminal bus.

Cluster 01 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 140 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

  1. Steady-state operation (20 second run);
  2. Three-phase faults with normal clearing time;
  3. Three-phase bus faults with normal clearing time;
  4. Three-phase faults with three-phase delayed clearing due to a stuck breaker (GO breakers with FD Logic);
  5. Three-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure;
  6. Three-phase faults with loss of multiple-circuit tower line.

No relevant high-speed reclosing (HSR) contingencies nor single-phase bus faults were identified for this study.

For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

In the original 2027SP base case, it was found that the system becomes unstable for contingencies P1.13, P4.24, P4.29, P5.06, P5.08 and P7.03 since the units in the City of Rochelle and Mendota areas are connected to the bulk power system just through a single branch, McGirr – Dixon, during post-fault configuration. As such, it appears that local voltage collapse occurs in the weak network conditions during post-fault period. Plots from the dynamic simulations for these simulations are provided in Attachment 4.

To mitigate the instability issue, ESS H440 generating unit was turned off, and LEED (Q57), Mendota Hills (AD1-067) and AD1-013 generating units were dispatched at a reduced capacity in “Alternate Base Case” folder to satisfy the Short Term Emergency (STE) ratings of Haumesser – W. Dekalb 138 kV and McGirr Rd – Dixon 138 kV circuits, and thus secure the case for N-0 and N-1 conditions for unstable contingencies.

For all of the fault contingencies tested on the 2027 peak load case:

  1. Cluster 01 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  2. The system with Cluster 01 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
  3. Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
  4. No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

Cluster 01 projects meet the 0.95 leading and lagging PF requirement.

The IPCMD and IQCMD states in the REGCAU model of AE2-341 GEN, AF1-030 GEN, AG1-118 GEN1, AG1-118 GEN2 and AG1-127 GEN showed erratic behavior for some contingencies in which these generators have been disconnected as part of the contingency event. Since the machine is disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

Fictitious frequency response at AE2-341 generator bus tripped the queue project due to the action of instantaneous under frequency relays when faults were applied to AF1-030/AE2-341 POI. This issue is mitigated by increasing the relay pickup time for frequency relay instance 94312513 to 20 seconds to avoid fictitious frequency tripping of the unit.

Fictitious frequency response at the AF1-030 generator bus tripped the queue project due to the action of instantaneous over frequency and under frequency relays when faults were applied to AF1-030/AE2-341 POI. This issue is mitigated by increasing the relay pickup time for frequency relay instances 94359509 and 94359511 to 20 seconds to avoid fictitious frequency tripping of the units.

AF1-030 unit tripped due to an overvoltage spike following fault clearing. This was mitigated by adding a small pick-up time of 0.113 seconds to the relay instance 94359501 to resolve the overvoltage tripping.

The AC1-110 unit tripped by angle deviation relays for 3 contingencies (P4.48.3B3, P4.50.3B3 and P4.52.3B3). The AC1-111 unit tripped by angle deviation relays for 4 contingencies (P4.39.3B3, P4.44.3B3, P4.45.3B3 and P4.46.3B3). These tripping events were observed in previous stability analysis studies for AC1-109/110/111 and AF2-363/366 and therefore are not attributed to Cluster 01 stability analysis.

The DVR (Dynamic Voltage Recovery) criteria have been violated under several contingencies due to instability and unit tripping, particularly at the Mendota location, as observed in events P1.13, P4.24, P4.29, P5.06, P5.08, and P7.03. These contingencies have been simulated with reduced dispatch for several units and no DVR violation has been observed. Additional DVR violations occurred under contingencies P4.48.3B3, P4.50.3B3, and P4.52.3B3, where the tripping of the AC1-110 unit led to angle deviations. Notably, DVR violations identified at the AC1-110 generator bus terminals during contingencies P4.42.3B3 and P4.43.3B3 were not mitigated, as generation buses and points-of-interconnection (Aurora) are not valid monitoring points for assessing DVR compliance. Similarly, violations at the Aurora and Batavia buses (P4.42.3B3 and P4.53.3B3) were not addressed, given that the DVR recovery envelope was breached at only two buses per contingency—below the threshold of ten or more applicable buses required for mitigation to be considered.

No mitigations were found to be required.

Table 1: TC1 Cluster 01 Projects

Project

Fuel Type

Transmission Owner

MFO

Point of Interconnection

AE2-341

Solar

ComEd

150

Sandwich – Plano 138 kV circuit 14609

AF1-030

Solar

ComEd

100

Sandwich – Plano 138 kV circuit 14609

AG1-118

Solar

ComEd

300

Sugar Grove – Waterman 138 kV circuit 11106

AG1-127

Solar

ComEd

95.1

Crego Road 138 kV station

 

 

 

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 1, Cluster 02 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 02 projects.

This analysis is effectively a screening study to determine whether the addition of the Cluster 02 projects will meet the dynamics requirements of the NERC, ComEd and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 02 projects have been dispatched online at maximum power output, with 1.0 voltage at the terminal bus.

Cluster 02 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 45 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

  1. Steady-state operation (20 second run);
  2. Three-phase faults with normal clearing time;
  3. Three-phase bus faults with normal clearing time;
  4. Three-phase faults with three-phase delayed clearing due to a stuck breaker (GO breakers with FD Logic);
  5. Three-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure;
  6. Three-phase faults with loss of multiple-circuit tower line.

No relevant high-speed reclosing (HSR) contingencies were identified for this study.

There are no three-phase faults single-phase delayed clearing due to a stuck breaker (IPO breaker with FD Logic).

There are no three-phase faults with three-phase delayed clearing due to a stuck breaker (GO Breakers with A-contact Logic).

There are no three-phase faults with single-phase delayed clearing due to a stuck breaker (GO Breakers with FD Logic).

Stations at which the faults listed above will be applied are:

  • AE1-114 POI 138 kV
  • Lancaster TSS 119 138 kV
  • Lena TSS 180 138 kV
  • Maryland TSS 124 138 kV

The SPOG 2-51 (TSS 119 Lancaster automatic line 11904 trip schemes prevent islanding of TSS 969 Ecogrove Generation). The following assumptions were made for contingency development:

  1. TSS 969 Ecogrove Generation will be tripped when one of the following conditions are met:
  1. 138 kV line 11904 circuit breaker is open at TSS 119 Lancaster; or,
  2. 138 kV line 17121 circuit breaker is open AND either 138 kV bus tie 5-7 OR 6-7 is open at TSS 119 Lancaster.

For all simulations, the queue projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the 2027 peak load case:

  1. Cluster 02 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  2. The system with Cluster 02 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
  3. Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
  4. No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

AE1-114 meets the 0.95 leading and lagging PF requirement.

The IPCMD and IQCMD states in the REGCA model of AE1-114 GEN showed erratic behavior for some contingencies in which these generators have been disconnected as part of the contingency event. Since the machine is disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

The composite short-circuit ratio (CSCR) assessment was performed for inverter-based renewable generation units which are within one (1) substation away of Cluster 02. The CSCR results are summarized in Table 4 through Table 9 and revealed a minimum CSCR value of 3.01 for P4.18, P4.15, P4.16 and so on and a maximum CSCR value of 4.444 for P1.08, P1.06, P0.01.

Table 1: TC1 Cluster 02 Projects

 

 

 

 

 

 

 

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

02

AE1-114

Wind

ComED

150

150

34

Maryland - Lancaster 138 kV Line

 

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 1, Cluster 3 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 3 projects.

This analysis is effectively a screening study to determine whether the addition of the Cluster 3 projects will meet the dynamics requirements of the NERC, ComEd and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 3 projects have been dispatched online at maximum power output and the voltage schedule set to achieve near unity power factor at the high side of the main transformer.

Cluster 3 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 166 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

  1. Steady-state operation (20 second run);
  2. Three-phase faults with normal clearing time;
  3. Three-phase bus faults with normal clearing time;
  4. Three-phase to ground faults with three-phase delayed clearing due to a stuck breaker (GO breakers);
  5. Three-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure;
  6. Three-phase faults with loss of multiple-circuit tower line.

No relevant high speed reclosing (HSR) contingencies were identified for this study.

For all simulations, the Cluster 3 projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the 2027 peak load case:

  1. Cluster 3 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  2. The system with Cluster 3 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3%.
  3. Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
  4. No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

AF2-350 meets the 0.95 leading and lagging PF requirement.

The IPCMD and IQCMD states in the REGCA1 model of AF2-350 GEN showed erratic behavior for some contingencies in which these generators have been disconnected as part of the contingency event. Since the machine is disconnected and no active or reactive power is injected into the system these plots are ignored.

 

No mitigations were found to be required.

Table 1: TC1 Cluster 3 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

3

AF2-350

Solar

ComEd

100

100

60

Kensington 138 kV

 

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 1, Cluster 4 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 4 projects.

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 4 projects will meet the dynamics requirements of the NERC, ComEd, and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 4 projects have been dispatched online at maximum power output and the voltage schedule set to achieve near unity power factor at the high side of the main transformer.

Cluster 4 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 168 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

  1. Steady-state operation (20 second run);
  2. Three-phase faults with normal clearing time;
  3. Three-phase bus faults with normal clearing time;
  4. Three-phase to ground faults with three-phase delayed clearing due to a stuck breaker (GO breakers);
  5. Three-phase to ground faults with single-phase delayed clearing due to a stuck breaker (IPO breakers)
  6. Three-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure;
  7. Three-phase faults with loss of multiple-circuit tower line.

No relevant high speed reclosing (HSR) contingencies were identified for this study.

For all simulations, the Cluster 4 projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the 2027 peak load case:

  1. Cluster 4 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  2. The system with Cluster 4 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3%.
  3. Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
  4. No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

AE2-321 meets the 0.95 leading and lagging PF requirement.

The IPCMD and IQCMD states in the REGCA1 model of AE2-321 GEN showed erratic behavior for some contingencies in which these generators have been disconnected as part of the contingency event. Since the machine is disconnected and no active or reactive power is injected into the system, this response has no effect on the system.

AE2-321 exhibited slow reactive power recovery within the 20 second simulation window for several contingencies. This issue did not cause instability in the system. However, to reduce the reactive power settling time and eliminate the potential for the plant’s voltage controller to interact with other voltage controlling equipment in the AC system, a 5% reactive power droop was introduced to the AE2-321 plant controller.

Initial simulations showed poorly damped oscillations in AC1-111 power. The AC1-111 dynamic model was updated to the most recent (revision 1) model which uses the AC7B exciter model instead of the ESAC1A model. The updated dynamic model eliminated these oscillations.

No mitigations were found to be required.

Table 1: TC1 Cluster 4 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

4

AE2-321

Solar

ComEd

100

100

67

Belvidere – Marengo 138 kV

 

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 1, Cluster 5 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 5 projects.

This analysis is effectively a screening study to determine whether the addition of the Cluster 5 projects will meet the dynamics requirements of the NERC, ComEd and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 5 projects have been dispatched online at maximum power output and the voltage schedule set to achieve near unity power factor at the high side of the main transformer.

Cluster 5 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 107 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

  1. Steady-state operation (20 second run);
  2. Three-phase faults with normal clearing time;
  3. Three-phase bus faults with normal clearing time;
  4. Three-phase to ground faults with three-phase delayed clearing due to a stuck breaker (GO breakers);
  5. Three-phase to ground faults with single-phase delayed clearing due to a stuck breaker (IPO breakers)
  6. Three-phase faults with loss of multiple-circuit tower line.

No relevant high speed reclosing (HSR) contingencies were identified for this study.

For all simulations, the Cluster 5 projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the 2027 peak load case:

  1. Cluster 5 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  2. The system with Cluster 5 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3%.
  3. Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
  4. No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

AF2-226 and AF2-319 meet the 0.95 leading and lagging PF requirement.

The IPCMD and IQCMD states in the REGCA1 models of AF2-226 GEN and AF2-319 GEN showed erratic behavior for some contingencies in which this generator has been disconnected as part of the contingency event. Since the machine is disconnected and no active or reactive power is injected into the system, these plots are ignored.

Initial simulations showed AF2-226 and AF2-319 exhibited slow reactive power recovery within the 20 second simulation window for several contingencies. The reactive power settling time was decreased by adjusting the PPC Q/V controller PI gains for both projects (Kp = 1 from 0, Ki = 5 from 0.5). The developer confirmed that the updated controller parameters are acceptable.

Simulations showed AF2-142, AF2-143, and AE1-163 getting stuck in high voltage ride through (HVRT) mode for extended periods after fault clearance for several contingencies. This resulted in a 345 kV POI voltage of about 1.1 pu for more than 5 seconds. For AF2-142 and AF2-143, this was resolved by adjusting the HVRT threshold and deadband to 1.15 pu (from 1.1 pu) and 0.15 pu (from 0.1 pu), respectively. These parameter adjustments were confirmed by the respective project developers. For AE1-163, the dynamic model was updated to the Vestas UDM which was submitted for the AE1-163/AE2-281 necessary study as per the developer’s request.

Initial simulations showed poorly damped oscillations in AC1-111 power. The AC1-111 dynamic model was updated to the most recent (revision 1) model which uses the AC7B exciter model instead of the ESAC1A model. Revision 1 of the AC1-111 dynamic model was used in the last iteration of the AC1-111 dynamic analysis, therefore it is assumed that the AC7B model is accurate relative to what is in the field. The updated dynamic model eliminated these oscillations.

No mitigations were found to be required.

 

Table 1: TC1 Cluster 5 Projects

 

 

 

 

 

 

 

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

5

AF2-226

Storage

ComEd

50

50

20

Katydid Road 345 kV

AF2-319

Storage

ComEd

50

50

20

Katydid Road 345 kV

 

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 1, Cluster 6 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 6 projects.

This analysis is effectively a screening study to determine whether the addition of the Cluster 6 projects will meet the dynamics requirements of the NERC, ComEd and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 6 projects have been dispatched online at maximum power output and the voltage schedule set to achieve near unity power factor at the high side of the main transformer.

Cluster 6 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 103 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

  1. Steady-state operation (20 second run);
  2. Three-phase faults with normal clearing time;
  3. Three-phase bus faults with normal clearing time;
  4. Three-phase to ground faults with three-phase delayed clearing due to a stuck breaker (GO breakers);
  5. Three-phase to ground faults with single-phase delayed clearing due to a stuck breaker (IPO breakers)
  6. Three-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure;
  7. Three-phase faults with loss of multiple-circuit tower line;

No relevant high speed reclosing (HSR) contingencies were identified for this study.

For all simulations, the Cluster 6 projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the 2027 peak load case:

  1. Cluster 6 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  2. The system with Cluster 6 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3%.
  3. Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
  4. No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

AF2-392 meet the 0.95 leading and lagging PF requirement.

The IPCMD and IQCMD states in the REGCA1 models of AF2-392 showed erratic behavior for some contingencies in which this generator has been disconnected as part of the contingency event. Since the machine is disconnected and no active or reactive power is injected into the system, these plots are ignored.

AF2-392 exhibited slow reactive power recovery within the 20 second simulation window for several contingencies. This issue did not cause instability in the system.

Voltage response at O29GEN1 (Bus 276157) and O29GEN2 (Bus 276158) terminal bus tripped the generators due to the action of under voltage relays when faults were applied at Hoyle Road 138 kV (AF2-392 POI) and Nelson 138 kV. The relay pickup times for voltage relay instances 27615701 (O29GEN1, 0.45 pu, 0.26 sec), 27615702 (O29GEN1, 0.45 pu, 0.3 sec), 27615703 (O29GEN1, 0.65 pu, 0.3 sec), 27615801 (O29GEN2, 0.45 pu, 0.26 sec), 27615802 (O29GEN2, 0.45 pu, 0.3 sec) and 27615803 (O29GEN2, 0.65 pu, 0.3 sec) were set to a duration shorter than the fault duration of 20 cycles. Therefore, the relay pickup times for voltage relays were extended to 0.36667 seconds, to avoid tripping during the fault.

 

Voltage response at BROOKE Wind generator terminal bus (Bus 631215) tripped the generator due to the action of instantaneous voltage relay 63121502 (0.892 pu, 0.0 sec) when faults were applied at Nelson 345 kV. Therefore, the relay pickup times for frequency relay instance 63121502 was updated to 0.36667 seconds, to avoid tripping during the fault.

 

No mitigations were found to be required.

Table 1: TC1 Cluster 6 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

6

AF2-392

Wind

ComEd

199

199

35.2

Nelson - Dixon 138 kV

 

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 1, Cluster 07 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 07 projects.

This analysis is effectively a screening study to determine whether the addition of the cluster 07 projects will meet the dynamics requirements of the NERC, ComEd and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 07 projects have been dispatched online at maximum power output, with 1.0 voltage at the terminal bus.

Cluster 07 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 110 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

  1. Steady-state operation (20 second run).
  2. Three-phase faults with normal clearing time.
  3. Single-phase faults with stuck breaker.
  4. Three-phase faults single-phase delayed clearing due to a stuck breaker (IPO breaker with FD Logic).
  5. Three-phase faults with three-phase delayed clearing due to a stuck breaker (GO Breakers with A-contact Logic).
  6. Three-phase faults with single-phase delayed clearing due to a stuck breaker (GO Breakers with FD Logic).

No relevant high-speed reclosing (HSR) contingencies nor single-phase bus faults were identified for this study.

For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all the fault contingencies tested on the 2027 peak load case:

  1. Cluster 07 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  2. The system with Cluster 07 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
  3. Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
  4. No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

AE2-261, AG1-236, and AG1-460 meet the 0.95 leading and lagging PF requirement.

The IPCMD and IQCMD states in the REGCAU model of AE2-261, and AG1-236 showed erratic behavior for some contingencies in which these generators have been disconnected as part of the contingency event. Since the machine is disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

AG1-236 GEN exhibited slow reactive power recovery within the 20 second simulation window for several contingencies. This issue did not cause instability in the system and the models have been tuned to achieve a faster reactive power output settlement by updating Kp and Kc from REPCTA1 module in generator AG1-236.

The tripping of AD2-100 was identified in contingencies P4.68, P4.69, and P4.70, as well as during the Cluster 07 pre-project test. Therefore, it has been confirmed that the tripping of AD2-100 is not caused by the TC1 Cluster 07 queue projects. Tripping was avoided for all events by updating the undervoltage protection settings: Relay 93677405 was adjusted to 0.177 seconds (10 cycles, adding one cycle to the original P4 fault clearing time of 9 cycles).

No mitigations were found to be required.

 

Table 1: TC1 Cluster 07 Projects

 

 

 

 

 

 

 

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

07

AE2-261

Solar

ComEd

299

299

179.4

Kincaid-Pana 345 kV

AG1-460

Storage

ComEd

30

30

12

Kincaid-Pana 345 kV

AG1-236

Wind

ComEd

180

180

23.4

Lanesville- Brokaw

 

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 1, Cluster 08 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 08 projects.

This analysis is effectively a screening study to determine whether the addition of the cluster 08 projects will meet the dynamics requirements of the NERC, ComEd and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 08 projects have been dispatched online at maximum power output, with 1.0 voltage at the terminal bus.

Cluster 08 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 110 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

  1. Steady-state operation (20 second run);
  2. Three-phase faults with normal clearing time;
  3. Three-phase faults single-phase delayed clearing due to a stuck breaker (IPO breaker with FD Logic);
  4. Three-phase faults with three-phase delayed clearing due to a stuck breaker (GO breakers with FD Logic);
  5. Three-phase faults with loss of multiple-circuit tower line.

No relevant high-speed reclosing (HSR) contingencies nor single-phase bus faults were identified for this study.

There are no delayed (Zone 2) clearing faults due to dual primary relays being employed in the ComEd 345 kV transmission system.

For all of the fault contingencies tested on the 2027 peak load case:

  1. Cluster 08 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  2. The system with Cluster 08 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
  3. Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
  4. No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

AE1-172, AE2-173, AE2-223, and AF2-225 meet the 0.95 leading and lagging PF requirement.

The AE1-205 unit tripped by undervoltage relays for 4 contingencies (P4.61, P4.62, P4.63, P4.64). Contingencies P4.61, P4.62, P4.63 and P4.64 involved a three-phase stuck breaker fault at Pontiac Midpoint 345 kV clearing in 13 cycles. As per NERC Standard PRC-024 requirements, these contingencies were found to meet the corresponding NERC PRC-024 LVRT criteria. A similar tripping issue was observed in AF2-252/AF2-352 dynamic study.

AF2-225 GEN exhibited slow reactive power recovery within the 20 second simulation window for several contingencies. This issue did not cause instability in the system and the model is tuned by adjusting the Kc parameter in the plant controller (REPCA1) to 0.1 from 0 to achieve a faster reactive power output settlement. The change has been confirmed by the developer.

The IPCMD and IQCMD states in the REGCAU model of AE2-173 GEN, and AE2-223 GEN, and AF2-225 GEN showed erratic behavior for some contingencies in which these generators have been disconnected as part of the contingency event. Since the machine is disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

Fictitious post-fault overvoltage tripping at AF2-252 and AF2-352 generator buses tripped the queue projects due to the action of instantaneous over-voltage relays for contingencies P4.62 and P4.63. Therefore, the relay pickup times for voltage relay instances 96061504 and 95961504 were set to 0.0305 seconds from 0.001 to avoid fictitious voltage tripping of the units.

No mitigations were found to be required.

Table 1: TC1 Cluster 08 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

08

AE1-172

Wind

ComEd

255

255

44.88

Loretto-Wilton Center 345 kV

AE2-173

Battery Storage

ComEd

50

50

50

McLean 345 kV

AE2-223

Wind

ComEd

150

150

19.5

McLean 345 kV

AF2-225

Solar

ComEd

150

150

63

McLean 345 kV

 

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 1, Cluster 09 are listed in Table 1: TC1 Cluster 09 Projects below. This report will cover the dynamic analysis of Cluster 09 projects.

This analysis is effectively a screening study to determine whether the addition of the cluster 09 projects will meet the dynamics requirements of the NERC, ComEd and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 09 projects have been dispatched online at maximum power output, with 1.0 voltage at the terminal bus.

Cluster 09 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 79 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

  1. Steady-state operation (20 second run).
  2. Three-phase faults with normal clearing time.
  3. Three-phase bus faults with normal clearing time.
  4. Three-phase faults with three-phase delayed clearing due to a stuck breaker (GO breakers with FD Logic).
  5. Three-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure.
  6. Three-phase faults with loss of multiple-circuit tower line.

No relevant high-speed reclosing (HSR) contingencies nor single-phase bus faults were identified for this study.

For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all the fault contingencies tested on the 2027 peak load case:

  1. Cluster 09 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  2. The system with Cluster 09 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
  3. Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
  4. No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

AF2-069meets the 0.95 leading and lagging PF requirement.

The IPCMD and IQCMD states in the REGCAU model of AF2-069 showed erratic behavior for some contingencies in which these generators have been disconnected as part of the contingency event. Since the machine is disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system. These issues are not expected to occur in the field, as they are a result of modeling artifacts associated with the simulation environment and the use of generic renewable models.

AF2-069 GEN1 and GEN2 exhibited slow reactive power recovery within the 20 second simulation window for several contingencies. This issue did not cause instability in the system and the models have been tuned to achieve a faster reactive power output settlement by updating Kc to 0.1 from REPCTA1 module in both generators AF2-069 GEN 1 and AF2-069 GEN2.

High voltage spikes occurred in the simulations immediately after fault clearing for some of the contingencies studied (e.g., P4.06 and P5.13). The voltage spike is a known artifact of the WECC generic renewable models as stated in the WECC Solar Plant Dynamic Model Guidelines: “It should be noted that generic dynamic models for inverter-based generator tend to produce a short-duration (a cycle or shorter) voltage spike at fault inception and clearing. These spikes should be ignored in most cases, as they do not represent the performance of actual hardware. They are simply a consequence of the model’s limited bandwidth, integration time step, and the way current injection models interface with the network solution.”

The tripping of AD1-031 was identified during contingency P5.03 as well as during the Cluster 09 pre-project test; therefore, it has been confirmed that the tripping of AD1-031 is not caused by the TC1 Cluster 09 queue projects. Tripping was avoided for this contingency by updating the undervoltage protection settings. Instance 93405409 was adjusted to 0.5 seconds (30 cycles, adding one cycle to the original P5 fault clearing time of 29 cycles), and instance 93405408 was set to trip if terminal voltage falls below 0.65 pu for more than 0.5 seconds (30 cycles, adding several cycles to the original P5 fault clearing time of 29 cycles) .

The tripping of O29 units (O29 GEN 1 and GEN 2) was identified during contingency P5.04. It has been confirmed that this tripping is not caused by the TC1 Cluster 09 queue projects. Tripping was avoided for this contingency by updating the undervoltage protection settings. For O29 GEN 1, instance 27615703 was adjusted to 0.5 seconds (30 cycles, adding several cycles to the original P5 fault clearing time of 18 cycles). Similarly, for O29 GEN 2, instance 27615803 was updated to 0.5 seconds (30 cycles, adding several cycles to the original P5 fault clearing time of 18 cycles).

 

No mitigations were found to be required.

 

Table 1: TC1 Cluster 09 Projects

 

 

 

 

 

 

 

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

09

AF2-069

Wind

ComEd

86.8

9.3

2.2

Crescent Ridge 138kV

 

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 1, Cluster 11 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 11 projects.

This analysis is effectively a screening study to determine whether the addition of the Cluster 11 projects will meet the dynamics requirements of the NERC, ComEd and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 11 projects have been dispatched online at maximum power output, with 1.0 voltage at the terminal bus.

Cluster 11 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 129 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

  1. Steady-state operation (20 second run);
  2. Three-phase faults with normal clearing time;
  3. Three-phase bus faults with normal clearing time;
  4. Three-phase faults with three-phase delayed clearing due to a stuck breaker (GO breakers with FD Logic);
  5. Three-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure;
  6. Three-phase faults with loss of multiple-circuit tower line.

No relevant high-speed reclosing (HSR) contingencies nor single-phase bus faults were identified for this study.

For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the 2027 peak load case:

  1. Cluster 11 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  2. The system with Cluster 11 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
  3. Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
  4. No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

AF2-441 meets the 0.95 leading and lagging PF requirement.

AF2-441 GEN post fault terminal voltage was more than 1.05 p.u. for several contingencies. This issue did not cause instability in the system and the dynamic models were tuned to achieve a post fault terminal voltage less than 1.05 by adjusting Kc parameter in the REPCA1 module of AF2-441 to 0.1.

The IPCMD and IQCMD states in the REGCAU model of AF2-441 GEN, and AG1-298 GEN showed erratic behavior for some contingencies in which these generators have been disconnected as part of the contingency event. Since the machine is disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

No mitigations were found to be required.

 

Table 1: TC1 Cluster 11 Projects

 

 

 

 

 

 

 

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

11

AF2-441

Storage

ComEd

200

200

80

Burnham 138 kV

 

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 1, Cluster 13 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 13 projects.

This analysis is effectively a screening study to determine whether the addition of the Cluster 13 projects will meet the dynamics requirements of the NERC, ComEd and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 13 projects have been dispatched online at maximum power output and the voltage schedule set to achieve near unity power factor at the high side of the main transformer.

Cluster 13 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 125 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

  1. Steady-state operation (20 second run);
  2. Three-phase faults with normal clearing time;
  3. Three-phase bus faults with normal clearing time;
  4. Three-phase to ground faults with three-phase delayed clearing due to a stuck breaker (GO breakers);
  5. Three-phase to ground faults with single-phase delayed clearing due to a stuck breaker (IPO breakers);
  6. Three-phase faults with loss of multiple-circuit tower line.

No relevant high speed reclosing (HSR) contingencies were identified for this study.

For all simulations, the Cluster 13 projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the 2027 peak load case:

  1. Cluster 13 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  2. The system with Cluster 13 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3%.
  3. Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
  4. No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

AF2-142 and AF2-143 meet the 0.95 leading and lagging PF requirement.

The IPCMD and IQCMD states in the REGCA1 model of AF2-142 GEN, AF2-143 GEN, AA1-018 GEN1, AA1-018 GEN2, and AD2-038 GEN showed erratic behavior for some contingencies in which these generators have been disconnected as part of the contingency event. Since the machine is disconnected and no active or reactive power is injected into the system, these plots are ignored.

 

Voltage spikes over 1.2 pu lasting less than one cycle were observed in some contingencies at Nevada 345 kV, AF2-143 POI, and AE2-281 POI. The voltage spikes are a result of the high reactive current injection of inverter-based generation and instantaneous voltage recovery at fault clearance. Note that RMS simulation is not an accurate tool to evaluate temporary over-voltages produced by inverter-based generation.

 

Simulations showed AF2-142, AF2-143, and AE1-163 getting stuck in high voltage ride through (HVRT) mode for extended periods after fault clearance for several contingencies. This resulted in a 345 kV POI voltage of about 1.1 pu for more than 5 seconds. For AF2-142 and AF2-143, this was resolved by adjusting the HVRT threshold and deadband to 1.15 pu (from 1.1 pu) and 0.15 pu (from 0.1 pu), respectively. These parameter adjustments were confirmed by the respective project developers. For AE1-163, the dynamic model was updated to the Vestas UDM which was submitted for the AE1-163/AE2-281 necessary study as per the developer’s request.

Initial simulations showed poorly damped oscillations in AC1-111 power. The AC1-111 dynamic model was updated to the most recent (revision 1) model which uses the AC7B exciter model instead of the ESAC1A model. The updated dynamic model eliminated these oscillations.

Sensitivity studies were conducted on more severe scenarios (P4.19.3B1, P4.21.3B1, P4.53.3B3) for Powerton generator stability in the light load case. Initial simulations resulted in a numerical instability for P4.53.3B3 which was resolved by reducing generation at Elwood E.C. such that the pre-contingent loading on Elwood – Goodings Grove 345 kV circuit 11620 is at 100% of RATE A (1201 MVA). The results are stable for the contingencies studied.

No mitigations were found to be required.

 

Table 1: TC1 Cluster 13 Projects

 

 

 

 

 

 

 

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

13

AF2-142

Solar

ComEd

150

150

90

Nevada 345 kV

AF2-143

Solar

ComEd

150

150

90

Powerton – Nevada 345 kV

 

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 1, Cluster 14 are listed in              Table 1 below. This report will cover the dynamic analysis of Cluster 14 projects.

This analysis is effectively a screening study to determine whether the addition of the Cluster 14 projects will meet the dynamics requirements of the NERC, ComEd and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 14 projects have been dispatched online at maximum power output, with 1.0 voltage at the terminal bus.

Cluster 14 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 139 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

  1. Steady-state operation (20 second run);
  2. Three-phase faults with normal clearing time (and with unsuccessful high speed reclosing);
  3. Three-phase bus faults with normal clearing time;
  4. Three-phase faults with three-phase delayed clearing due to a stuck breaker (GO breakers with FD Logic);
  5. Three-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure;
  6. Three-phase faults with loss of multiple-circuit tower line (and with unsuccessful high speed reclosing).

There are no three-phase faults with three-phase delayed clearing due to a stuck breaker (GO Breakers with A-contact Logic);

For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the 2027 peak load case:

  1. Cluster 14 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  2. The system with Cluster 14 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
  3. Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
  4. No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

AF2-095 meets the 0.95 leading and lagging PF requirement.

The composite short-circuit ratio (CSCR) assessment was performed for inverter-based renewable generation units which are within one (1) substation away from AF2-095. The CSCR revealed minimum and maximum CSCR values of 3.241 for P2.01 and 5.558 for P1.03, respectively.

Nearby queues AC2-154 and AD2-060, located at the same POI (Davis Creek 138 kV) are GNETTED due to the unavailability of updated user defined models that are compatible with PSS/E 34.

The IPCMD and IQCMD states in the REGCAU models of AF2-095 showed erratic behavior for some contingencies in which these generators have been disconnected as part of the contingency event. Since the machine is disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system. 

The DVR (Dynamic Voltage Recovery) criteria have been violated under several contingencies (P2.12, P4.33.3B3 and P4.34.3B3)  at the University Park and Wilmington buses were not addressed, given that the DVR recovery envelope was breached at only one bus per contingency — below the threshold of ten or more applicable buses required for mitigation to be considered.

No mitigations were found to be required.

 

Table 1: TC1 Cluster 14 Projects

 

 

 

 

 

Cluster

Project

Fuel Type

Transmission Owner

MFO

Point of Interconnection

14

AF2-095

Solar

ComEd

144

Davis Creek TSS 86 138 kV Substation

 

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (AF2-041/AF2-199/AF2-200) in PJM Transition Cycle 1, Cluster 15 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 15 projects.

This analysis is effectively a screening study to determine whether the addition of the Cluster 15 projects will meet the dynamics requirements of the NERC, ComEd and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 15 projects have been dispatched online at maximum power output, with 1.0 voltage at the terminal bus.

Cluster 15 projects were tested for compliance with NERC, PJM, Transmission Owner, and other applicable criteria. Steady-state condition and 76 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

  1. Steady-state operation (20 second run),
  2. Three-phase faults with normal clearing time,
  3. Three-phase bus faults with normal clearing time,
  4. Three-phase faults single-phase delayed clearing due to a stuck breaker (IPO breaker with FD Logic),
  5. Three-phase faults with three-phase delayed clearing due to a stuck breaker (GO Breakers with A-contact Logic),
  6. Three-phase faults with single-phase delayed clearing due to a stuck breaker (GO Breakers with FD Logic),
  7. Three-phase faults with three-phase delayed clearing due to a stuck breaker (GO breakers with FD Logic),
  8. Three-phase faults with loss of multiple-circuit tower line.

No relevant high-speed reclosing (HSR) contingencies nor single-phase bus faults were identified for this study.

There are no delayed (Zone 2) clearing faults due to dual primary relays being employed in the ComEd 345 kV transmission system.

For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the 2027 peak load case:

  1. Cluster 15 projects were able to ride through the faults (except for faults where protective action trips a generator(s)).
  2. The system with Cluster 15 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
  3. Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
  4. No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

AF2-041, AF2-199, and AF2-200 meet the 0.95 leading and lagging PF requirement.

AF2-041 exhibited slow reactive power recovery within the 20-second simulation window for several contingencies. This issue did not result in system instability. The model was tuned to improve reactive power settling time by updating the Kp parameter to 2.0, the Ki parameter to 3.0, and setting the VCFlag to 0 in the REPCA1 module.

High voltage spikes occurred in the simulations immediately after fault clearing for some of the contingencies studied. The voltage spike is a known artifact of the WECC generic renewable models as stated in the WECC Solar Plant Dynamic Model Guidelines: “It should be noted that generic dynamic models for inverter-based generator tend to produce a short-duration (a cycle or shorter) voltage spike at fault inception and clearing. These spikes should be ignored in most cases, as they do not represent the performance of actual hardware. They are simply a consequence of the model’s limited bandwidth, integration time step, and the way current injection models interface with the network solution.”

The composite short-circuit ratio (CSCR) assessment was performed for inverter-based renewable generation units which are within one (1) substation away from AF2-041/AF2-199/AF2-500. The CSCR revealed minimum and maximum CSCR values of 3.66 for P1.17 and 5.25 for P0.01, respectively.

No mitigations were found to be required.

 

Table 1: TC1 Cluster 15 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

15

AF2-041

Solar

ComEd

300

300

180

Nelson-Electric Junction 345 kV

AF2-199

Solar

ComEd

100

100

60

Nelson-Electric Junction 345 kV

AF2-200

Solar

ComEd

200

200

120

Nelson-Electric Junction 345 kV

 

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 1, Cluster 16 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 16 projects.

This analysis is effectively a screening study to determine whether the addition of the Cluster 16 projects will meet the dynamics requirements of the NERC, ComEd and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 16 projects have been dispatched online at maximum power output and the voltage schedule set to achieve near unity power factor at the high side of the main transformer.

Cluster 16 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 112 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

  1. Steady-state operation (20 second run);
  2. Three-phase faults with normal clearing time;
  3. Three-phase bus faults with normal clearing time;
  4. Three-phase to ground faults with three-phase delayed clearing due to a stuck breaker (GO breakers);
  5. Three-phase to ground faults with single-phase delayed clearing due to a stuck breaker (IPO breakers);
  6. Three-phase faults with loss of multiple-circuit tower line;

No relevant high speed reclosing (HSR) contingencies were identified for this study.

For all simulations, the Cluster 16 projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the 2027 peak load case:

  1. Cluster 16 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  2. The system with Cluster 16 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3%.
  3. Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
  4. No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

AF1-280, AF2-182, and AF2-349 meet the 0.95 leading and lagging PF requirement.

The IPCMD and IQCMD states in the REGCA1 models of AF1-280 GEN, AF2-182 GEN, AF2-349 GEN1, and AF2-349 GEN2 showed erratic behavior for some contingencies in which this generator has been disconnected as part of the contingency event. Since the machine is disconnected and no active or reactive power is injected into the system, these plots are ignored.

Voltage response at Brooke wind generator terminal bus (631215) caused the generator terminal voltage to drop below 0.892 pu resulting in the unit being tripped instantaneously by voltage relay instance 63121502. The relay pickup time was extended to 3 seconds (PRC-024-3 compliant) to prevent the plant from tripping.

Initial simulations showed a poorly damped oscillation in voltage/reactive power at the Easy Road Type 3 Wind plant for contingency P1.02 (fault at AF1-280/AF2-182 POI on Lee County EC 345 kV circuit). Tuning the Torque controller in the Type 3 wind plant resolved the oscillation:

WTTQA1:

CON(J+11) = 0.98 (spd3, shaft speed for power p3 (pu)) from 1.2

CON(J+13) = 1.0 (spd4, shaft speed for power p4 (pu)) from 1.2

Initial simulations showed a poorly damped oscillation in AC1-111 power. The AC1-111 dynamic model was updated to the most recent (revision 1) model which uses the AC7B exciter model instead of the ESAC1A model. The updated dynamic model eliminated these oscillations.

No mitigations were found to be required.

Table 1: TC1 Cluster 16 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

16

AF1-280

Solar

ComEd

200

200

0

Nelson – Lee County 345 kV

AF2-182

Solar

ComEd

300

300

0

Nelson – Lee County 345 kV

AF2-349

Solar

ComEd

300

300

0

Silver Lake – Cherry Valley 345 kV

 

 

Executive Summary for Stability Cluster

Executive Summary

New Service Requests AF1-296, AG1-462 and AG1-553 in PJM Transition Cycle 1, Cluster 17 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 17 projects.

This analysis is effectively a screening study to determine whether the addition of the Cluster 17 projects will meet the dynamics requirements of the NERC, ComEd and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 17 projects have been dispatched online at maximum power output, with 1.0 pu voltage at the terminal bus, except AF1-296, which was allowed to have a terminal voltage of 1.027 pu.

Cluster 17 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 197 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

  1. Steady-state operation (20 second run);
  2. Three-phase faults with normal clearing time;
  3. Three-phase bus faults with normal clearing time;
  4. Three-phase faults with single-phase delayed clearing due to a stuck breaker (IPO breaker with FD Logic).
  5. Three-phase faults with three-phase delayed clearing due to a stuck breaker (GO Breakers with A-contact Logic);
  6. Three-phase faults with single-phase delayed clearing due to a stuck breaker (GO Breakers with FD Logic);
  7. Three-phase faults with three-phase delayed clearing due to a stuck breaker (GO breakers with FD Logic);
  8. Single-phase faults with stuck breaker (for MISO substations);
  9. Three-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure;
  10. Single-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure (for MISO substations);
  11. Three-phase faults with loss of multiple-circuit tower line.

No relevant high-speed reclosing (HSR) contingencies were identified for this study.

Buses at which the faults listed above were applied are:

  • Cordova E.C. TSS 940 (AG1-553/AG1-462 POI) 345 kV
  • Cordova M.E.C. 345 kV
  • Nelson TSS 155 (AE1-134/AA2-030/AA1-146 POI) 345 kV
  • E. Molin (Barstow SUB. 39 M.E.C.) 345 kV
  • Quad Cities STA. 4 345 kV
  • Garden Plain TSS 132 (AF1-296 POI) 138 kV
  • Nelson TSS 155 138 kV
  • AF2-392 TAP 138 kV
  • Sterling Steel (ESS H71) 138 kV
  • Rock Falls TSS 133 138 kV
  • Albany S.S. 138 kV & 161 kV
  • Beaver Channel 161 kV
  • York 161 kV
  • Savanna 161 kV
  • Rock Creek 161 kV
  • SUB 49 161 kV

For all simulations, the queue projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the 2027 peak load case:

  1. Cluster 17 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  2. The system with Cluster 17 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
  3. Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
  4. No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

AG1-553, AG1-462 and AF1-296 meet the 0.95 leading and lagging PF requirement.

The composite short-circuit ratio (CSCR) assessment was performed for inverter-based renewable generation units which are within one (1) substation away of Cluster 17. The CSCR results for AF1-296 are summarized in Table 7 through Table 17 and revealed a minimum and maximum CSCR values of 2.64 for P4.84 & P4.86 and 4.45 for P1.64, respectively. The CSCR results for AG1-553 and AG1-462 revealed a minimum and maximum CSCR values of 3.81 for P4.08 & P4.10 and 7.24 for P1.02 & P4.03, respectively.

Specific findings from the simulations for each of the queue projects of Cluster 17 are indicated below.

AG1-553 and AG1-462

The IPCMD and IQCMD states in the REGCA1 models of AG1-553 GEN 1&2 and AG1-462 GEN 1 showed erratic behavior for some contingencies in which AG1-553 or AG1-462 generators have been disconnected as part of the contingency event. Since the machines are disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

High voltage spikes on the terminal voltages of AG1-462 and AG1-553, occurred in the simulations immediately after fault clearing for a few of the contingencies studied (i.e. fault where spike is observed). The voltage spike is a known artifact of the WECC generic renewable models as stated in the WECC Solar Plant Dynamic Model Guidelines: “It should be noted that generic dynamic models for inverter-based generator tend to produce a short-duration (a cycle or shorter) voltage spike at fault inception and clearing. These spikes should be ignored in most cases, as they do not represent the performance of actual hardware. They are simply a consequence of the model’s limited bandwidth, integration time step, and the way current injection models interface with the network solution.”

AF1-296

For 24 contingencies out of 197, the steady state post-contingency terminal voltage of AF1-296 went slightly above 1.05 pu (Et ≈ 1.056 pu – 14 contingencies, Et ≈ 1.051 pu – 10 contingencies). This is due to the fact that the terminal voltage of AF1-296 pre-contingency is 1.027 pu.

High voltage spikes at the terminals of AF1-296 and its POI, Garden Plain 138 kV, occurred in the simulations immediately after fault clearing for some of the contingencies studied (i.e. fault where spike is observed]). As, with the WECC models, these voltage spikes are considered a consequence of the model’s limited bandwidth, integration time step and the way it interfaces with the network solution. Therefore, it is estimated that they do not represent the performance of actual equipment and can be ignored in most cases. The spike at Garden Plain is a consequence of the spike at the terminals of AF1-296.

No mitigations were found to be required. However, it is recommended that the developer of AF1-296 provides an adjusted model that allows specifying the generator’s reactive power output at levels that support initial conditions with a terminal voltage close to 1.0 pu.

 

Table 1: Cluster 17 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

17

AF1-296

Wind

ComEd

190.89

190.89

33.6

Garden Plain 138 kV

AG1-462

Solar

ComEd

255

255

153

Cordova 345 kV

AG1-553

Solar

ComEd

260

260

0

Cordova 345 kV

 

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 1, Cluster 21 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 21 projects.

This analysis is effectively a screening study to determine whether the addition of the Cluster 21 projects will meet the dynamics requirements of the NERC, ComEd and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 21 projects have been dispatched online at maximum power output, with 1.0 voltage at the terminal bus.

Cluster 21 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 39 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

  1. Steady-state operation (20 second run),
  2. Three-phase faults with normal clearing time,
  3. Three-phase faults with single-phase delayed clearing due to a stuck breaker (IPO breaker with FD Logic),
  4. Three-phase faults with three-phase delayed clearing due to a stuck breaker (GO breakers with FD Logic).

No relevant high-speed reclosing (HSR) contingencies nor single-phase bus faults were identified for this study.

There are no delayed (Zone 2) clearing faults due to dual primary relays being employed in the ComEd 345 kV transmission system.

For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the 2027 peak load case:

  1. Cluster 21 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  2. The system with Cluster 21 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
  3. Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
  4. No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

AG1-374 meets the 0.95 leading and lagging PF requirement.

 

 

 

The AE1-205 unit tripped by undervoltage relays for 4 contingencies (P4.23, P4.24, P4.25, and P4.26). Contingencies P4.23, P4.24, P4.25, and P4.26 involved a three-phase stuck breaker fault at Pontiac Midpoint 345 kV clearing in 13 cycles. As per NERC Standard PRC-024 requirements, these contingencies were found to meet the corresponding NERC PRC-024 LVRT criteria. A similar tripping issue was observed in AF2-252/AF2-352 dynamic study.

 

Fictitious post-fault overvoltage tripping at AF2-252 and AF2-352 generator buses tripped the queue projects due to the action of instantaneous over-voltage relays for contingencies P1.02, P1.03, P4.10, P4.25 and P4.26. Therefore, the relay pickup times for voltage relay instances 96061504 and 95961504 were set to 0.0305 seconds to avoid fictitious voltage tripping of the units. With this updated relay settings only P1.03 was tripping. Both relay instances have been updated to 0.035 seconds to avoid this tripping.

 

The IPCMD and IQCMD states in the REGCAU model of AG1-374 GEN showed erratic behavior for some contingencies in which these generators have been disconnected as part of the contingency event. Since the machine is disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

 

The composite short-circuit ratio (CSCR) assessment was performed for inverter-based renewable generation units which are within one (1) substation away from Cluster 21. The CSCR results are summarized in Table 8 through Table 11 and revealed a minimum and maximum CSCR values of 3.11 for P4.15, P4.16, P4.19 and P4.20 and 7.02 for P1.04, respectively.

 

No mitigations were found to be required.

Table 1: TC1 Cluster 21 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

21

AG1-374

Solar

ComEd

300

300

180

Blue Mound 345 kV

 

 

Executive Summary for Stability Cluster

Executive Summary

 

New Service Requests (projects) in PJM Transition Cycle 1, Cluster 23 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 23 projects.

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 23 projects will meet the dynamics requirements of the NERC, Dayton and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 23 projects have been dispatched online at maximum power output and the voltage schedule set to achieve near unity power factor at the high side of the main transformer. Four dispatch scenarios were considered for AG1-323, which is a hybrid solar/storage project where the aggregate machine capability exceeds MFO. The dispatch scenarios are given in the following table.

 

AG1-323 Dispatch Scenarios

Dispatch Scenario

Description

Solar Pgen (MW)

Storage Pgen (MW)

1

AG1-323 solar dispatched to maximum power output. AG1-323 storage dispatched such that the net active power injected by AG1-323 is equal to MFO at the POI.

37.77

4.63

2

AG1-323 storage dispatched such that the net active power injected by AG1-323 is equal to MFO at the POI. AG1-323 solar offline.

offline

42

3

AG1-323 Solar and Storage dispatched proportionally, prorated to the aggregate inverter MVA, such that the net active power injected by AG1-323 is equal to MFO at the POI.

19.2

22.8

4

AG1-323 Solar and Storage dispatched at maximum power output. Net active power injected by AG1-323 exceeds the requested MFO at the POI.

37.77

44.9

 

 

Cluster 23 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 193 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

       a)       Steady-state operation (20 second run);

       b)       Three-phase faults with normal clearing time;

       c)       Single-phase bus faults with normal clearing time;

       d)       Single-phase faults with stuck breaker;

       e)       Single-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure;

       f)       Single-phase faults with loss of multiple-circuit tower line.

 

No relevant high speed reclosing (HSR) contingencies were identified for this study.

 

For all simulations, the Cluster 23 projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all of the fault contingencies tested on the 2027 peak load case:

       a)       Cluster 23 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

       b)       The system with Cluster 23 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3%.

       c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d)       No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

AE1-092 and AG1-323 meet the 0.95 leading and lagging PF requirement.

 

The IPCMD and IQCMD states in the REGCA1 models of AE1-092 GEN, AG1-323_GEN1 and AG1-323_GEN2 showed erratic behavior for some contingencies in which this generator has been disconnected as part of the contingency event. Since the machine is disconnected and no active or reactive power is injected into the system, these plots are ignored.

 

No mitigations were found to be required.

 

 

Table 1: TC1 Cluster 23 Projects

 

 

 

 

 

 

 

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

23

AE1-092

Solar

Dayton

206.55

206.6

96.4

Blue Jacket – Kirby 138 kV

AG1-323

Solar

Dayton

40

40

40

Blue Jacket 138 kV

 

 

Executive Summary for Stability Cluster

Executive Summary

 

New Service Requests (projects) in PJM Transition Cycle 1, Cluster 24 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 24 projects.

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 24 projects will meet the dynamics requirements of the NERC, EKPC and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 24 projects have been dispatched online at maximum power output and the voltage schedule set to achieve near unity power factor at the high side of the main transformer.

 

Cluster 24 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 154 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

       a)       Steady-state operation (20 second run);

       b)       Three-phase faults with normal clearing time;

       c)       Single-phase bus faults with normal clearing time;

       d)       Single-phase faults with stuck breaker;

       e)       Single-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure;

       f)       Single-phase faults with loss of multiple-circuit tower line.

 

No relevant high speed reclosing (HSR) contingencies were identified for this study.

 

For all simulations, the Cluster 24 projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all of the fault contingencies tested on the 2027 peak load case:

       a)       Cluster 24 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

       b)       The system with Cluster 24 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3%.

       c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d)       No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

AF1-233 and AF2-307 meet the 0.95 leading and lagging PF requirement.

 

The IPCMD and IQCMD states in the REGCAU model of AF1-233 GEN and AF2-307 GEN showed erratic behavior for some contingencies in which these generators have been disconnected as part of the contingency event. Since the machine is disconnected and no active or reactive power is injected into the system, these plots are ignored.

 

Dynamic simulations showed that AF2-307 inverter reactive power output was being limited by the inverter controls (REECA1) below the 0.95 dynamic power factor requirement. The issue was resolved in consultation with the developer  by adjusting the inverter control parameters as follows:

•       REECA1:

o       CON(J+15) = 2 (VMAX (pu), Max. limit for voltage control) from 1.1

o       CON(J+16) = 0 (VMIN (pu), Min. limit for voltage control) from 0.9

 

AF2-111 exhibited slow reactive power recovery within the 20 second simulation window for several contingencies. This issue did not cause instability in the system.

 

No mitigations were found to be required.

 

Table 1: TC1 Cluster 24 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

24

AF1-233

Solar

EKPC

188.5

188.5

113.1

Flemingsburg – Spurlock 138kV

AF2-307

Solar

EKPC

64.2

64.2

39.6

Hope – Blevins Valley Tap 69 kV

 

 

Executive Summary for Stability Cluster

Executive Summary

 

New Service Requests (projects) in PJM Transition Cycle 1, Cluster 25 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 25 projects.

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 25 projects will meet the dynamics requirements of the NERC, EKPC and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 25 projects have been dispatched online at maximum power output, and voltage schedules set to achieve near unity power factor at the high side of the main transformer.

 

       Cluster 25 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 133 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

       a)       Steady-state operation (20 second run);

       b)       Three-phase faults with normal clearing time;

       c)       Single-phase bus faults with normal clearing time;

       d)       Single-phase faults with stuck breaker;

       e)       Single-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure;

       f)       Single-phase faults with loss of multiple-circuit tower line.

 

No relevant high speed reclosing (HSR) contingencies were identified for this study.

 

For all simulations, the Cluster 25 projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all of the fault contingencies tested on the 2027 peak load case:

       a)       Cluster 25 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

       b)       The system with Cluster 25 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3%.

       c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d)       No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

AG1-354 and AG1-471 meet the 0.95 leading and lagging PF requirement.

 

AG1-471 generator unit remained at High Voltage Ride Through mode for several  contingencies. As a result, the AG1-471 generator terminal voltage remained at approximately 1.12 pu after fault recovery which exceeds the range of 0.95 pu – 1.05 pu. This issue caused the voltage relay stage set to 1.1 pu for 10 seconds to pick up and trip AG1-471 generating unit. Modifying CON(J+1): Vup to 1.16 pu of the REECA1 model resolved the issue of AG1-471 getting stuck in HVRT mode and resolved the tripping of the unit. The AG1-471 developer confirmed that the proposed settings .

 

No mitigations were found to be required.

 

Table 1: TC1 Cluster 25 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

25

AG1-354

Solar

EKPC

150.0

150.0

90.0

Summershade - Green County 161 kV

AG1-471

Solar

EKPC

54.0

54.0

32.4

Up Church-Wayne County 69 kV

 

 

Executive Summary for Stability Cluster

Executive Summary

 

New Service Requests (projects) in PJM Transition Cycle 1, Cluster 26 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 26 projects.

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 26 projects will meet the dynamics requirements of the NERC, EKPC and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 26 projects have been dispatched online at maximum power output and the voltage schedule set to achieve near unity power factor at the high side of the main transformer.

 

Cluster 26 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 139 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

       a)       Steady-state operation (20 second run);

       b)       Three-phase faults with normal clearing time;

       c)       Single-phase bus faults with normal clearing time;

       d)       Single-phase faults with stuck breaker;

       e)       Single-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure;

       f)       Single-phase faults with loss of multiple-circuit tower line.

 

No relevant high speed reclosing (HSR) contingencies were identified for this study.

 

For all simulations, the Cluster 26 projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all of the fault contingencies tested on the 2027 peak load case:

       a)       Cluster 26 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

       b)       The system with Cluster 26 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3%.

       c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d)       No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

AE2-308 meets the 0.95 leading and lagging PF requirement.

 

ETERM of AE2-308 GEN went outside the range of 0.95 pu - 1.05 pu in post fault for several contingencies. This issue did not cause instability in the system.

 

The IPCMD and IQCMD states in the REGCA1 model of AE2-308 GEN showed erratic behavior for some contingencies in which this generator has been disconnected as part of the contingency event. Since the machine is disconnected and no active or reactive power is injected into the system, these plots are ignored.

 

Due to the breaker configuration at the AE2-308 Point of Interconnection (POI), there is a potential risk of an islanding condition in which AE2-308 could become the sole power source for the load at Three Forks if both the Fawkes and Dale circuits are lost. This scenario could occur during a stuck breaker contingency, where the breaker between the Fawkes and Dale circuits fails to operate. The AE2-308 inverter control strategy includes passive anti-islanding protection. Under this strategy, if the facility becomes islanded, the voltage and/or frequency magnitude at the inverter terminals will rapidly reach set protection thresholds, causing the inverters to trip.

 

Poorly damped oscillations in the rotor speeds and active power of the 1HAEFLING units 1 and 2 were observed for most contingencies. Select contingency was studied without TC1 projects dispatched. The oscillations persists without TC1 projects. Therefore, the issue is not a result of the addition of TC1 projects. Note that these units are using a simple GENCLS model, without an exciter or power system stabilizer.

 

No mitigations were found to be required.

 

Table 1: TC1 Cluster 26 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

26

AE2-308

Solar

EKPC

100

100

60

Three Forks - Dale 138 kV

 

 

Executive Summary for Stability Cluster

Executive Summary

 

New Service Requests (projects) in PJM Transition Cycle 1, Cluster 27 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 27 projects.

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 27 projects will meet the dynamics requirements of the NERC, EKPC and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 27 projects have been dispatched online at maximum power output and the voltage schedule set to achieve near unity power factor at the high side of the main transformer.

 

Cluster 27 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 209 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

       a)       Steady-state operation (20 second run);

       b)       Three-phase faults with normal clearing time;

       c)       Single-phase bus faults with normal clearing time;

       d)       Single-phase faults with stuck breaker;

       e)       Single-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure;

       f)       Single-phase faults with loss of multiple-circuit tower line.

 

No relevant high speed reclosing (HSR) contingencies were identified for this study.

 

For all simulations, the Cluster 27 projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all of the fault contingencies tested on the 2027 peak load case:

       a)       Cluster 27 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

       b)       The system with Cluster 27 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3%.

       c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d)       No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

AF2-111 and AG1-526 meet the 0.95 leading and lagging PF requirement.

 

The provided AF2-111 power plant controller model (REPCA1) did not include a reactive power droop on the voltage controller. It is expected to have a reactive power droop to avoid any interactions with the other plants in the AC system. This was resolved in consultation with the AF2-111 developer  by adding a 5% droop to Q/V controller in the plant controller model (REPCA1).

 

The provided AG1-526 power plant controller model (REPCA1) did not include a reactive power droop on the voltage controller. It is expected to have a reactive power droop to avoid any interactions with the other plants in the AC system. This was resolved in consultation with the AG1-526 developer  by adding a 5% droop to Q/V controller in the plant controller model (REPCA1).

 

Poorly damped oscillations in the rotor speeds and active power of the 1HAEFLING units 1 and 2 were observed for most contingencies. It was observed that the oscillations persist without TC1 projects.  Therefore, the issue is not a result of the addition of TC1 projects. Note that these units are using a simple GENCLS model, without an exciter or power system stabilizer.

 

No mitigations were found to be required.

 

 

Table 1: TC1 Cluster 27 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

27

AF2-111

Solar

EKPC

250

250

150

North Clark – Spurlock 345 kV

AG1-526

Solar

EKPC

222

222

133.2

West Gerrard 345 kV

 

 

 

Executive Summary for Stability Cluster

Executive Summary for Dynamic Stability Analysis using PSSE

New Service Requests (projects) in PJM Transition Cycle 1 Cluster 29 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 29 projects.

 

Table 1: Transition Cycle 1 Cluster 29 Projects

 

 

 

 

 

 

 

Cluster

Project

Fuel Type

Transmission Owner

MFO (MW)

MWE (MW)

MWC (MW)

Point of Interconnection

29

AF1-123

Wind

Dominion

833

833

253.2

Harper 230 kV

AF1-124

Wind

Dominion

836

836

254.1

Harper 230 kV

AF1-125

Wind

Dominion

820

820

249.3

Harper 230 kV

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 29 projects will meet the dynamics requirements of the NERC, Dominion Energy, and PJM reliability standards.

 

The load flow case finalized for Phase 2 was used as a starting point and was updated based on latest Cluster 29 data, Dominion Energy recommended transmission changes and withdrawn generation. Projects in vicinity of Cluster 29 have been dispatched online at maximum power output with near unity power factor measured at the high-side of the main substation transformer. The dynamic models for Cluster 29 projects were updated based on the latest DP2 data and include any tuning adjustments recommended during Phase 2.

 

This analysis currently was performed using the PSSE library models provided the developer.  Dominion Energy Transmission provided the models for the FACT’s devices for the AF1-123, AF1-124, and AF1-125 queue projects.

 

Cluster 29 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. 133 contingencies were studied, each with a 20 second simulation time period. The studied contingencies included:

  • Steady-state operation (30 seconds)
  • Three-phase faults with normal clearing time
  • Single-phase bus faults with normal clearing time
  • Single-phase faults with stuck breaker
  • Single-phase faults with delayed clearing at remote end
  • Single-phase faults with loss of multiple-circuit tower line.

For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

The results of the analysis were evaluated against the following recovery criteria per PJM’s Regional Transmission Planning Process and Transmission Owner criteria:

  • Cluster 29 projects were able to ride through the faults (except for faults where protective action trips a generator(s)).
  • The system with Cluster 29 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
  • Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus) and the final voltages are within the steady-state voltage ranges below per Dominion Energy’s transmission planning criteria.
    • P1 Category Contingencies:
      • 0.93 to 1.05 p.u. for 230, 115, 69 kV facilities
      • 0.93 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.01 to 1.096 p.u. for 500 kV facilities
    • P2, P4, P5, and P7 Category Contingencies:
      • 0.90 to 1.05 p.u. for 230, 115, 69 kV facilities
      • 0.90 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.00 to 1.096 p.u. for 500 kV facilities
  • No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

AF1-123, AF1-124 and AF1-125 met the 0.95 lagging and leading power factor requirements at the point of interconnect (POI) at Harpers 230 kV substation.

 

The results of the analysis identified that the addition of the AF1-123, AF1-124 and AF1-125 queue projects resulted in instability in a majority of contingencies. The following mitigation is required to maintain stability:

  • Add a second 500 kV line from the Updated Fentress to the Yadkin substations
  • Add two 230 kV gas-insulated lines (GILs) from the existing Fentress to the New Fentress substations
  • All 230 kV breakers (212822, 269T2128, 26922, 224022-1, 224022-2, 208722, W22, L122, L322, H22, SC122, SC322, SC422, SV122, and the new breakers G1 and G2 for the gas insulated lines) at Fentress 230 kV Substation require a 14 cycle clearing time
  • Dual pilot protection is required for the Fentress to AD1-033 POI 230 kV line circuit 2240

No voltage or frequency protection trips occurred for AF1-123, AF1-124 and AF1-125 queue projects using the settings provided.

 

The AF1-123, AF1-124 and AF1-125 queue projects exhibited slow active power recovery after the fault cleared and this is recovery was expected based on the model documentation provided for the OEMs’ wind turbine. The WGOWECC controller, clamps the active power at 95% for up to 5 seconds to ensure steady recovery of the system and then releases the active power to 100% to restore full operation.

 

An EMT analysis and stability analysis using a PSS/E user defined model is recommended for AF1-123, AF1-124 and AF1-125 due to the CSCR values being less than 3. A user defined model is under development by the IC and it will be evaluated as a sensitivity once the model initializes properly.

 

AE2-156 reactive power and terminal voltage recovery was not settling to a steady state value during the analysis. However, it was observed that reactive settling doesn’t violate PJM or Dominion’s criteria. The models were tuned to achieve a faster recovery in Cluster 46 Phase 2 Stability Analysis.

 

AE2-051 reactive power and terminal voltage recovery was not settling to a steady state value during the analysis. The models can be tuned to achieve a faster recovery upon request.

 

AB2-169 generator tripped for overvoltage’s above 1.25 p.u. The unit rode through when the pickup timer  was increased from 0.0 seconds to 0.0125 seconds.

 

Executive Summary for Dynamic Stability Analysis using PSCAD/EMT

 

The EMT dynamic performance analysis was revelated with the latest PSCAD models pprovided by CVOW (AF1-123, 124 & 125) generation developer.   A detailed model quality testing was performed. Below are some deficiency and corresponding update that were applied to the plant model.

 

  • CVOW initialization issues were cured by using a stiff voltage source model at POI during the initialization period and disconnected later in the simulation.
  • Pi-circuit equivalents for 66 kV IAC cables were updated to Bergeron models using best available data.
  • Onshore cable section was updated into onshore and HDD sections using best available data.
  • Earthing transformer model was included at the 66 kV delta winding of OSS transformer.
  • OSS LTC transformer taps were set to match values used for TC1 analysis.
  • Harpers STATCOM model was updated to latest OEM model.

 

Preliminary results of CVOW performance for Summer peak and Light Load system conditions for select TPL contingencies indicate the following:

 

  • Instability of the project post-fault was observed for select P1 and P6 contingencies prior to the inclusion of all proposed upgrades.
  • With the inclusion of the proposed upgrades namely the 500 kV Line 5005 between Fentress and Yadkin and two GIL circuits between new and existing Fentress 230 kV, CVOW fully recovers post-fault for a severe P4 contingency.
  • The preliminary results demonstrate the impact of the weak system strength and the improvements provided by the proposed upgrades.
  • Analysis of CVOW performance for severe P6 contingencies with the proposed upgrades is ongoing.
  • Investigation of partial nuisance tripping of CVOW post-fault is also on-going for other contingencies and system conditions.

 

CVOW Flicker

 

Preliminary analysis shows flicker issue induced by CVOW project. Preliminary flicker analysis was conducted using a range of ramp rates in the absence of data on power fluctuation in response to wind speed variation. To assess flicker impact, MEPPI evaluated multiple wind profiles, spanning from conservative scenarios to less conservative ramp rates. Results indicate that the ramp rate significantly influences the flicker observed at the POI and we violate the criteria of 1 Pst for various profiles considered. Flicker analysis was performed in PSCAD using detailed models of the CVOW project and a system equivalent at the POI.  In order to mitigate the flicker issue an addition of 300 MVAR STATCOM will need to be installed at Fentress 230 kV Substation.

 

Note:

 

TC1 Phase 3 Dynamic  Stability analysis has been completed by using library model provided in TC1 Phase 2.  For TC1 Phase 3, a PSSE User Defined Model was requested due to low SCR concerns in the area. The CVOW project developer provided a User Defined Model that did not work properly in the TC1 base case. The CVOW  project development team is actively working on getting an updated User Defined Model for the AF1-123/AF1-124/AF1-125 projects from Siemens Gamesa Renewable Energy (SGRE). This updated model was not ready at the time TC1 Phase 3 studies concluded, and CVOW will need to initiate a Necessary Study request post GIA to have the updated User Defined Model provided to PJM to perform a Dynamic Stability analysis for the AF1-123/AF1-124/AF1-125 projects.

Also, CVOW notified PJM of a change for nineteen (19) of the GSUs that are planned to be installed for the CVOW Project for Queue Position AF1-123 (OSS T1L11). Note that these 19 GSUs – installed in 19 of the 59 wind turbine generators – have been manufactured and have higher impedance values that was in the original design. Following evaluation, it has been determined that these changes in impedances to these 19 units do not affect the MFO/gross output, have very limited changes for the  losses, and the MW output at the POI will be changed, but insubstantially. The other queues AF1-124 & AF1-125 are unchanged/unaffected. This GSU change for AF1-123 will also be evaluated as part of the Necessary Study being requested above.

 

Bellow are some of the item that will be captured during post GIA Necessary study request for CVOW project.

 

  1. The User Defined Model dynamic stability analysis for AF1-123/AF1-124/AF1-125 as well as the GSU change for AF1-123.
  2. The EMT Analysis is based on PSCAD Models provided to PJM & DEV-ET on May 19th, the developers needs to confirm that these models are still valid and if updates to these models need to be made to represent changes made in the UDM please provide updated EMT models.
  3. As identified in the TC1 Phase 2 Reports and the June 2025 “EMT Generation Model Review” Report Nuisance Tripping is still occurring which can result in up to 1600 MW Tripping Off-Line.  This tripping is being initiated by the DC Protection Scheme of the WTGs, the developer needs to provide a solution to PJM & DEV-ET for this deficiency.   This solution will be evaluated in the NSA to determine if it resolves the nuisance tripping issue.  
  4. The developer needs to indicate if margin can be increased in the Over-Voltage Ride Through, Under Voltage Ride Through & Frequency Ride-Through to increase the margins from the PRC-024 & IEEE 2800 Requirements as identified in the TC1 Phase 2 Reports and the June 2025 “EMT Generation Model Review” Report.
  5. Preliminary Study Results indicate that the CVOW Project will result in a Pst Value greater than 1.  This will adversely impact Dominion’s Customers the proposed solution to this flicker issue will be to install a 300 MVAR STATCOM at Fentress Substation on the 230 kV Bus.   The developer can provide updated Ramp Rates  as part of the NSA to determine if mitigation is still required.

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 1 Cluster 30 for Phase 3 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 30 projects.

 

Table 1: Transition Cycle 1 Cluster 30 Projects

 

 

 

 

 

 

 

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

30

AF1-294

Solar

Dominion

41

41

22.2

Jetersville - Ponton 115 kV

AF2-115

Solar

Dominion

25

25

13.5

AG1-021

Solar

Dominion

20

20

10.8

AG1-166

Solar

Dominion

20

20

6

Lone Pine 115 kV

AG1-167

Solar

Dominion

15

15

4.5

AG1-168

Solar

Dominion

15

15

4.5

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 30 projects will meet the dynamics requirements of the NERC, Dominion Energy, and PJM reliability standards.

 

The load flow case for Phase 2 was used as a starting point and was updated based on latest Cluster 30 data, recommended transmission changes incorporated based on Dominion Energy Phase 2 feedback, and withdrawn generation removed. Cluster 30 projects have been dispatched online at maximum power output with near unity power factor measured at the high-side of the main substation transformer. The dynamic models for Cluster 30 projects were updated based on the latest DP2 data and include any tuning adjustments recommended during Phase 2.

 

Cluster 30 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. During the Phase 2 analysis contingencies were examined around the POIs and no violations were observed as a result of Cluster 30 projects interconnecting.  Due to this the Phase 3 analysis for Cluster 30 focused on the contingencies at Chase City that resulted in instability caused by Cluster 31 and Cluster 40 during Phase 2.  The Phase 3 analysis examined, 8 initial contingencies and 24 sensitivity contingencies were studied, each with a 30 second simulation time period. The studied contingencies included:

 

  • Three-phase faults with normal clearing time.
  • Single-phase bus faults with normal clearing time.
  • Single-phase faults with stuck breaker.

 

Instability was observed for contingencies when the Chase City to AG1-285 Tap 115 kV circuit was tripped. This outage resulted in instability due to insufficient export paths for the generation along the Farmville to Chase City 115 kV path through the radial connection.  Additionally, the Farmville to Chase City 115 kV path is prone to controller instability due to weak grid conditions determined by the composite short circuit ratio assessment.  The instability was caused by the Cluster 31 queue projects. 

 

To following mitigation was tested and all maintain stability:

  1. Adding a new 115 kV line from AG1-285 to Butcher’s Creek.
  2. Moving AF2-222 and AG1-285 to a new 230 kV line from Farmville to Finneywood.
  3. Upgrade the new AG1-285 substation to a breaker and a half scheme to accommodate 2 x 230/115 kV transformers and a 230 kV line from AG1-285 to Finneywood .

 

The Transmission Owner has elected to upgrade the new AG1-285 substation to a breaker and a half scheme to accommodate 2 x 230/115 kV transformers and a 230 kV line from AG1-285 to Finneywood as the mitigation to the instability. This mitigation is required due to the interconnection of the Cluster 31 queue projects. Cluster 30 queue projects did not cause the instability. The mitigation was further tested for all Phase 2 contingencies and no violations were observed.

 

Nearby projects were found to trip based on their protection settings. The protection trip times were increased during Phase 2 analysis and maintained during the Phase 3 analysis:

 

  • AE1-056 tripped for frequencies below 55 hz for more than 0.001 seconds and the relay pick-up time was increased to 0.034 seconds
  • AE1-056 tripped for frequencies above 65 hz for more than 0.001 seconds and the relay pick-up time was increased to 0.020834 seconds
  • AF2-222 tripped for voltages above 1.3 p.u. for more than 0.001 seconds and the relay pick-up time was increased to 0.012501 seconds

 

With the mitigation identified above, the results of the contingencies tested on the RTEP 2027 summer peak case found:

 

  • Cluster 30 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  • The system with Cluster 30 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for inter area modes and 4% for local modes.
  • Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus) and the final voltages are within the steady-state voltage ranges below per Dominion Energy’s transmission planning criteria.
    • P1 Category Contingencies:
      • 0.93 to 1.05 p.u. for 230, 115, 69 kV facilities
      • 0.93 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.01 to 1.096 p.u. for 500 kV facilities
    • P2, P4, P5, and P7 Category Contingencies:
      • 0.90 to 1.05 p.u. for 230, 115, 69 kV facilities
      • 0.90 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.00 to 1.096 p.u. for 500 kV facilities
  • No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

No mitigation was needed to connect the Cluster 30 queue projects.

Executive Summary for Stability Cluster

Executive Summary for Dynamic Stability Analysis Using PSSE

New Service Requests (projects) in PJM Transition Cycle 1 Cluster 31 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 31 projects.

 

 

Table 1: Transition Cycle 1 Cluster 31 Projects

 

 

 

 

 

 

 

Cluster

Project

Fuel Type

Transmission Owner

MFO

(MW)

MWE

(MW)

MWC

(MW)

Point of Interconnection

31

AF2-222

Solar

Dominion

167

167

100

Madisonville DP-Twitty's Creek 115 kV

AG1-285

Solar

Dominion

125

125

75

Chase City-Central 115 kV

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 31 projects will meet the dynamics requirements of the NERC, Dominion Energy, and PJM reliability standards.

 

The load flow case for Phase 2 was used as a starting point and was updated based on latest Cluster 31 data, Dominion Energy recommended transmission changes and withdrawn generation. Cluster 1 projects have been dispatched online at maximum power output with near unity power factor measured at the high-side of the main substation transformer. Two sets of modeling data were available for Cluster 31 projects for either a 115 kV Point of Interconnection (POI) or a 230 kV POI based on Phase 2 mitigation. Any tuning required for queue projects, other than AF2-222 and AG1-285, was included as the starting point for the Phase 3 analysis.

 

Cluster 31 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. 136 initial contingencies and 169 sensitivity contingencies were studied, each with a 30 second simulation time period. The studied contingencies included:

 

During the analysis, instability was observed when the Chase City to AG1-285 Tap 115 kV circuit was tripped. This outage resulted in instability due to insufficient export paths for the generation along the Farmville to Chase City 115 kV path through the radial connection.  Additionally, the Farmville to Chase City 115 kV path is prone to controller instability due to weak grid conditions determined by the composite short circuit ratio assessment. 

 

To following mitigation was tested and all maintain stability:

 

  1. Adding a new 115 kV line from AG1-285 to Butcher’s Creek.
  2. Moving AF2-222 and AG1-285 to a new 230 kV line from Farmville to Finneywood.
  3. Upgrading the new AG1-285 230 kV substation to a breaker and a half scheme to accommodate 2 x 230/115 kV AG1-285 transformers, and a 230 kV line from AG1-285 to Finneywood.

 

The Transmission Owner selected the 3rd mitigation option (N9630) which includes a new AG1-285 230 kV substation to a breaker and a half scheme to accommodate 2 x 230/115 kV AG1-285 transformers, and a 230 kV line from AG1-285 to Finneywood to mitigate the instability. This mitigation is required due to the interconnection of the Cluster 31 queue projects.

 

The Chase City to Finneywood 230 kV line and the Chase City to AG1-285 115 kV line cannot share a common tower or instability would occur for a P7 of these lines.

 

Nearby projects were found to trip based on their protection settings. The contingencies met the evaluation criteria with and without the protection enabled. The revised pickup timers were not determined to expediate Cluster 31 study completion.

 

  • AE1-056 tripped for frequencies below 55 Hz for more than 0.001 seconds
  • AE1-056 tripped for frequencies above 65 Hz for more than 0.001 seconds.
  • AF2-222 tripped for voltages above 1.3 p.u. for more than 0.001 seconds.

 

The protection settings for AE2-259 regarding frequency above 62.5 Hz for more than 0 seconds and frequencies below 56.5 Hz for more than 0 seconds are commented due to tripping of the generator during the Phase 3 analysis. The IC should be contacted to provide the maximum pickup time that the facility can withstand.  The contingencies met the evaluation criteria with and without the protection enabled. The revised pickup timers were not determined to expediate Cluster 31 study completion.

 

With the mitigation identified above, the results of the contingencies tested on the RTEP 2027 summer peak case found:

 

  • Cluster 31 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  • The system with Cluster 31 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
  • Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus) and the final voltages are within the steady-state voltage ranges below per Dominion Energy’s transmission planning criteria.
    • P1 Category Contingencies:
      • 0.93 to 1.05 p.u. for 230, 115, 69 kV facilities\
      • 0.93 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.01 to 1.096 p.u. for 500 kV facilities
    • P2, P4, P5, and P7 Category Contingencies:
      • 0.90 to 1.05 p.u. for 230, 115, 69 kV facilities
      • 0.90 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.00 to 1.096 p.u. for 500 kV facilities
  • No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

However, the AG1-285 queue project was not able to maintain voltages below 1.1 p.u during the lagging power factor assessment test.  

 

The AF2-222 queue project updated the make and model of inverter between the DP1 and DP2 data submittals. Due to this a sensitivity was performed to determine the impacts of the inverter change using the Sungrow SG4400UD-MV-US inverter provided during DP2. For the sensitivity the AF2-222 was modeled using the generator, inverter step up transformer and collector system equivalent data from DP2 to consider the inverter change.  The main station transformer and attachment line were modeled using DP1 data to consider the 115 kV POI.  Network Upgrade 3 was used for this sensitivity to determine the impacts of the inverter change after mitigating the instability.

 

The results of the sensitivity determined that AF2-222 was freezing for some contingencies using the Sungrow SG4400UD-MV-US inverter, this issue was resolved when REECA1 Vdip is changed from 0.9 p.u. to 0.8 p.u. The IC should be contacted to validate the above setting. It’s assumed the developer DP3 data submittal would include the Sungrow SG4400UD-MV-US inverters.

 

Executive Summary for Dynamic Stability Analysis Using  PSCAD/EMT

 

Model Quality Testing Report

PSCAD model for Queue project AF2-222 and AG1-285 was developed and tested individually to ensure the model was in compliance with the PJM requirements. Test summary and result of test been summarized below in table 2. it is confirmed that PSCAD model was set up properly and satisfied the PJM requirement.

 

Table 2. MQT Result for each Project

 

Test

Status

Flat Start Test 

Pass 

Voltage Step-Down 

Pass 

Voltage Step-Up 

Pass 

Frequency Step-Down, No Headroom

Pass 

Frequency Step-Down, Headroom

Pass 

Frequency Step-Up, Headroom 

Pass 

HVRT Leading

Pass 

HVRT Lagging

Pass 

LVRT Leading

Pass 

LVRT Lagging

Pass 

System Strength Test 

Pass 

Voltage Ride Through

Pass 

Phase Angle Step-Down 

Pass 

Phase Angle Step-Up 

Pass 

 

Weak Grid Assessment

This Weak Grid Assessment evaluates two projects from PJM Transition Cycle 1 (TC1) Cluster 31 for risk of voltage instability due to weak grid conditions in an EMT simulation environment.  The two projects, AF2-222 and AG1-285, were identified in the Cluster Study as having risk of undamped oscillations during a contingency condition and indicating system instability after dynamic simulation analysis in PSS/E. Three potential network upgrades were considered to resolve this instability, and Network Upgrades 2 and 3 were shown to be effective through sensitivity analysis.

This assessment, completed by INS Engineering, aims to verify the impact of Network Upgrade 2 and 3 identified in the Cluster Study, using detailed models in an EMT simulation.  Summary descriptions of each project and the two network upgrades are listed below:

 

Table 3. Summary Description of TC1 Cluster 31 Projects

 

 

 

 

Project Name

Project Type

Project Size (MW)

POI

POI Bus Number

AF2-222 Courthouse Solar

PV

167

Madisonville DP-Twitty's Creek 115 kV

959310

AG1-285 Quarter Horse Solar

PV

125

Chase City-Central 115 kV

964240

 

The following network upgrades proposed as mitigation in cluster 31 are evaluated in this weak grid assessment:

  • Network Upgrade 2: Moving AF2-222 and AG1-285 to a new 230 kV line from Farmville to Finneywood
    • Evaluated in the main body of this report
  • Network Upgrade 3: Upgrading the new AG1-285 230 kV substation to a breaker and a half scheme to accommodate 2 x 230/115 kV AG1-285 transformers, and a 230 kV line from AG1-285 to Finneywood
    • Evaluated in Appendix B
    • This option has been selected by the Transmission Owner

First, the individual project PSCAD models were evaluated for data consistency and model performance as part of the standard Model Quality Test in [2] and [3], with model updates being made where needed.  INS confirmed that the PSCAD models were set up properly and satisfied the requirements of PJM. After satisfactory configuration and performance of the individual projects were obtained, the models were integrated into a translated reduced network in PSCAD to create an overall detailed system model. 

 

For Network Upgrade 2, two representative contingency cases from the Cluster Study, considered effectively the worst case in terms of risk for weak grid instability, were simulated in the PSCAD detailed system model. For Cluster 31, the following contingency cases were chosen.

 

  • P=1.0pu, 3LG fault, 150ms, on AF2-171 POI to Farmville 230kV and loss of circuit
  • P=1.0pu, 3LG fault, 150ms, on AG1-427 to Finneywood 230kV and loss of circuit

 

Simulation results in PSCAD are summarized below.  It can be observed that both contingency cases using the detailed PSCAD system model results in a stable recovery, matching the results of the Cluster Study. 

 

Table 4. Summary of cases tested in the PSCAD system study with Network Upgrade 2

 

 

 

Case ID

Fault Description

Cluster Study Result [1]

PSCAD Study Result

Case 1.0

P=1.0pu, 3LG fault, 150ms, on AF2-171 POI to Farmville 230kV and loss of circuit

Stable

Stable

Case 2.0

P=1.0pu, 3LG fault, 150ms, on AG1-427 to Finneywood 230kV and loss of circuit

Stable

Stable

 

For Network Upgrade 3, three representative contingency cases from the Cluster Study, considered effectively the worst case in terms of risk for weak grid instability, were then simulated in the PSCAD detailed system model. Simulation results in PSCAD are summarized below.  It can be observed that all three contingency cases using the detailed PSCAD system model results in a stable recovery, matching the results of the Cluster Study. 

 

 

Table 5. Summary of cases tested in the PSCAD system study with Network Upgrade 3

 

 

 

Case ID

Fault Description

Cluster Study Result [1]

PSCAD Study Result

Case 3.1
(SP1.01)

P=1.0pu, 3LG fault, 150ms, on AF2-222 115 kV on Pamplin 115 kV circuit 154 and loss of circuit

Stable

Stable

Case 3.2
(SP1.10)

P=1.0pu, 3LG fault, 150ms, on AG1-285 POI switching station 115 kV on Chase City 115 kV circuit 1012 and loss of circuit

Stable

Stable

Case 3.3
(SP1.51)

P=1.0pu, 3LG fault, 150ms, on Finneywood 230 kV on AG1-285 – Finneywood 230 kV circuit and loss of circuit 

Stable

Stable

 

The results of this assessment show stable recovery in worst-case contingencies using either Network Upgrade 2 or 3, and support the conclusion from the Cluster Study that these proposed network upgrades mitigate the identified weak grid instability issues.

Executive Summary for Stability Cluster

Executive Summary for Dynamic Stability Analysis using PSSE

New Service Requests (projects) in PJM Transition Cycle 1 Cluster 32 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 32 projects.

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 32 projects will meet the dynamics requirements of the NERC, Dominion Energy, and PJM reliability standards.

 

 Table 1: Transition Cycle 1 Cluster 32 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO

(MW)

MWE

(MW)

MWC

(MW)

Point of Interconnection

32

AF2-120

Solar

Dominion

62

62

37.2

Garner – Northern Neck 115 kV

AG1-135

Solar

Dominion

60

60

36

Garner – Lancaster

115 kV

AG1-146

Solar

Dominion

30

30

18

Garner – Lancaster

115 kV

AG1-147

Solar

Dominion

100

70

42

Garner – Lancaster

115 kV

AG1-536

Battery

Dominion

75

75

32

Garner – Northern Neck 115 kV

 

The load flow case finalized for Phase 2 was used as a starting point and was updated based on latest Cluster 32 data, Dominion Energy recommended transmission changes and withdrawn generation. Projects in vicinity of Cluster 32 have been dispatched online at maximum power output with near unity power factor measured at the high-side of the main substation transformer. The dynamic models for Cluster 32 projects were updated based on the latest DP2 data and include any tuning adjustments recommended during Phase 2.

 

Cluster 32 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. 116 contingencies were studied, each with a 30 second simulation time period. The studied contingencies included:

 

  • Steady-state operation (30 seconds)
  • Three-phase faults with normal clearing time
  • Single-phase bus faults with normal clearing time
  • Single-phase faults with stuck breaker
  • Single-phase faults with delayed clearing at remote end
  • Single-phase faults with loss of multiple-circuit tower line.

 

The contingencies were updated based on topology changes due to any Dominion Energy recommended transmission changes or generation withdrawals.

 

For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

Instability was observed for certain contingencies resulting in the outage of the Northern Neck and AE1-155 Tap 115 kV line. The instability was mitigated by adding in a second 115 kV line from Northern Neck to AE1-155 Tap (Moon Corner). This new line would require additional breakers at Moon Corner and Northern Neck Both lines should not share a common breaker such that a breaker failure or stuck breaker could take out both Northern Neck – AE1-155 115 kV lines. Both lines should not share a common tower or structure such that a tower or structure failure could take out both lines.

 

A load flow analysis network update that reconductors the Northern Neck to Rappahannock 115 kV was considered and was not required to meet the evaluation criteria for the CL32 Stability Analysis.

 

With the addition of the second 115 kV line from Northern Neck to AE1-155 Tap, the study found that the following generators protection trips occurred. The relay pick-up settings were increased to allow the generators to ride through and should be confirmed with the generator owner.

 

  • AE2-041 tripped for voltages below 0.65 p.u. for more than 0.35 seconds and the relay pick-up time was increased to 0.4334 seconds to able to ride through the faults.
  • AF1-018 tripped for voltages below 0.65 p.u. for more than 0.35 seconds and the relay pick-up time was increased to 0.4334 seconds to able to ride through the faults.
  • AG1-038 tripped for voltages above 1.20 p.u. for more than 0.045 seconds and the relay pick-up time was increased to 0.0501 seconds to able to ride through the faults.

 

Reactive power for AF1-114 and AF2-091 does not appear to settle within the 30 seconds simulation for some contingencies. This did not violate any criteria nor create instability. AF1-114 and AF2-091 currently utilize a 4% voltage reactive droop. If a faster reactive power settling is desired in the future, then the model can be tuned to improve the reactive recovery later.

 

With the new 115 kV transmission line mitigation identified above, the results of the contingencies tested on the RTEP 2027 summer peak case found:

 

  • Cluster 32 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  • The system with Cluster 32 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for inter area modes and 4% for local modes.
  • Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus) and the final voltages are within the steady-state voltage ranges below per Dominion Energy’s transmission planning criteria.
    • P1 Category Contingencies:
      • 0.93 to 1.05 p.u. for 230, 115, 69 kV facilities
      • 0.93 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.01 to 1.096 p.u. for 500 kV facilities
    • P2, P4, P5, and P7 Category Contingencies:
      • 0.90 to 1.05 p.u. for 230, 115, 69 kV facilities
      • 0.90 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.00 to 1.096 p.u. for 500 kV facilities

 

No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

Executive Summary for Dynamic Stability Analysis using PSCAD/EMT

 

Model Quality Testing Report

 

PSCAD model for Queue project AF2-120, AG1-135, AG1-146/147 and AG1-536 was developed and tested individually to ensure the model was in compliance with the PJM requirements. Test summary and result of test been summarized below in table 2. it is confirmed that PSCAD model was set up properly and satisfied the PJM requirement.

 

Table 2. MQT Result for each project

 

Test

Status

Flat Start Test 

Pass 

Voltage Step-Down 

Pass 

Voltage Step-Up 

Pass 

Frequency Step-Down, No Headroom

Pass 

Frequency Step-Down, Headroom

Pass 

Frequency Step-Up, Headroom 

Pass 

HVRT Leading

Pass 

HVRT Lagging

Pass 

LVRT Leading

Pass 

LVRT Lagging

Pass 

System Strength Test 

Pass 

Voltage Ride Through

Pass 

Phase Angle Step-Down 

Pass 

Phase Angle Step-Up 

Pass 

 

Weak Grid Assessment

 

This Weak Grid Assessment evaluates five projects from PJM Transition Cycle 1 (TC1) Cluster 32 for risk of voltage instability due to weak grid conditions in an EMT simulation environment.  The five projects, AF2-120, AG1-135, AG1-146, AG1-147, and AG1-536, were identified in the Cluster Study as having risk of undamped oscillations in multiple contingency cases, indicating system instability after dynamic simulation analysis in PSS/E. A network upgrade, a new second 115 kV transmission line from Northern Neck to AE1-155 Tap, was recommended along with evaluation using detailed models in an EMT simulation.

This assessment, completed by INS Engineering, aims to evaluate the risk of weak grid instability and verify the effectiveness of the recommended network upgrade in EMT simulation.  A summary description of each project is listed below:

 

 

Table 3. Summary Description of TC1 Cluster 32 Projects

 

 

 

 

Project Name

Project Type

Project Size (MW)

POI

POI Bus Number

AF2-120 Cerulean Solar

PV

62

Garner – Northern Neck 115 kV

939240

AG1-135 Moon Corner

PV

60

Garner – Lancaster

115 kV

962860

AG1-146/AG1-147 Merry Point 1 and 2 Solar

PV

100

Garner – Lancaster

115 kV

962970

AG1-536 Mulberry

BESS

75

Garner – Northern Neck 115 kV

939240

 

First, the individual project PSCAD models were evaluated for data consistency and model performance as part of the standard Model Quality Tests process, model updates being made where needed.  INS confirmed that the PSCAD models were set up properly and satisfied the requirements of PJM. After satisfactory configuration and performance of the individual project models were obtained, the models were integrated into a translated reduced network in PSCAD to create an overall detailed system model. 

 

A representative contingency case from the Cluster Study, considered effectively the worst case in terms of risk for weak grid instability, was then simulated in the PSCAD detailed system model. For Cluster 32, the following contingency case was chosen.

 

  • Fault ID P1.03: Fault at AE1-155 Tap 115 kV on AE1-155 Tap – Northern Neck 115 kV circuit #1059. Fault cleared with loss of Northen Neck 115/34.5 kV Transformer #1

 

Simulation results in PSCAD are summarized below.  In Case 1a with the PSCAD detailed system model, weak grid oscillations and unstable recovery are observed without the network upgrade. With the network upgrade added in Case 1b, stable recovery is observed due to sufficient grid strength. These results are consistent with the results in the Cluster Study.

 

Table 4. Summary of cases tested in PSCAD system study

 

 

 

Case ID

Fault Description

Cluster Study Result [1]

PSCAD Study Result

Case 1a

P1.03, without network upgrade

Unstable

Unstable

Case 1b

P1.03, with network upgrade

Stable

Stable

Case 2a

P1.03, without network upgrade, modified PPC tuning

-

Stable*

* Details in Appendix B. Although a stable response was observed in this case, a detailed tuning evaluation over multiple operating conditions would be needed to verify robustness of the modified tuning.

 

As a potential alternative solution, PPC parameter were tuned to be more appropriate for weak grid conditions and this configuration was evaluated in base case P1.03, without the network upgrade – Case 2a. A stable response was observed in Case 2a, however, a detailed tuning evaluation over multiple operating conditions would be needed to verify robustness of this modified tuning.  As such, the modified tuning results in Appendix B should be considered for information only.

Based on the simulation results described above, the results of this assessment show stable recovery in the worst-case contingency when the network upgrade is included.  These results support the conclusion from the Cluster Study that the proposed network upgrade mitigates potential weak grid instability issues.

Executive Summary for Stability Cluster

Executive Summary for Dynamic Stability Analysis Using PSSE

New Service Requests (projects) in PJM Transition Cycle 1 Cluster 33 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 33 projects.

Table 1: Transition Cycle 1 Cluster 33 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

33

AE2-187

Solar

Dominion

60

60

36

Shockoe DP - Chatham 69 kV

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 33 projects will meet the dynamics requirements of the NERC, Dominion Energy, and PJM reliability standards.

 

The load flow case finalized for Phase 2 was used a starting point and was updated based on latest Cluster 33 data, Dominion Energy recommended transmission changes and withdrawn generation. Projects in vicinity of Cluster 33 have been dispatched online at maximum power output with near unity power factor measured at the high-side of the main substation transformer. The dynamic models for Cluster 33 and Cluster 35 projects were updated based on the latest DP2 data and include any tuning adjustments recommended during Phase 2.

 

Cluster 33 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. 46 contingencies were studied, each with a 30 second simulation time period. The studied contingencies included:

  • Steady-state operation (30 seconds)
  • Three-phase faults with normal clearing time
  • Single-phase bus faults with normal clearing time
  • Single-phase faults with stuck breaker
  • Single-phase faults with delayed clearing at remote end
  • Single-phase faults with loss of multiple-circuit tower line.

 

For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

AE2-187 met the 0.95 lagging and leading power factor requirements When the facility was tested at its maximum lagging reactive capability, voltages above 1.10 p.u. were observed at the inverter terminal. To ensure that the facility can provide its lagging power factor without high voltages at the inverter terminal, it is recommended that the tap on the high-side of the inverter step-up transformer be adjusted from 1.0 to 1.025 p.u. for AE2-187.

 

During phase 2 analysis some contingencies were observed to be diverged. As a result, during phase 3 analysis all generations (AC1-042, AC1-145, AE2-185, AE2-187, AE2-283, and AF2-404) have their REGCA1 Accel set to 0.7 It should be noted that this parameter does not affect the performance or recovery of the renewable model, but is used to smooth the voltage and angle calculations within PSS/E.

 

In phase 2, a number of protection trips were observed. However, for Phase 3, the latest DP2 data was incorporated for all projects after which no tripping was observed.

 

In phase 2, AE2-283 was observed to freeze for contingencies P4.01, P4.02, and P5.01, which resulted in loss of proportional and integral voltage control for voltage and tripped the generator due to terminal voltage exceeding 1.10 p.u. for more than 3 seconds. However, in phase 3 during DP2 data submission the developer had increased the AE2-283 REECA1 Vup (CON J+1) to 1.3 p.u. As a result, no freezing was observed.

 

Controller oscillations were observed at AC1-045, AE2-185, and AE2-187 during fault. After fault is cleared, the controller oscillations were no longer observed. Refer to P4.07 as an example. This did not cause instability or violate any criteria.

 

Voltages above 1.05 p.u. were observed at Altavista 69 kV. This is due to Altavista 138-69 kV load tap changer operating at 1.10 p.u. to maintain the Altavista 69 kV scheduled voltage. A significant voltage drop was observed between Altavista, Gladys Tap, Altavista DP, and Mt Airy Tap due to the amount of generation served within the Altavista 69 kV system. To ensure that that post contingency voltage is below 1.05 p.u., the Altavista 138/69 kV load tap changing transformer would need to operate at 1.0375 p.u. tap and under System Normal (P0) conditions, would produce a 0.968 p.u. voltage on the Altavista 69 kV bus, which is within Dominion’s P0 voltage levels. A voltage coordination study is recommended in the future to determine an acceptable voltage schedule for the Altavista 138/69 kV load tap changing transformer to coordinate with the generations served in the Altavista 69 kV system.

 

Oscillations in Smith Mountain and Leesville were observed. The damping ratio was calculated and found to be above the 3%, which met the damping criteria.

 

With the changes made above, all fault contingencies tested on the RTEP 2027 summer peak case:

 

  • Cluster 33 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  • The system with Cluster 33 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes in Dominion area and with damping margin of at least 3% in the AEP area.
  • Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
  • The final voltages are within the steady-state voltages specified by each Transmission Owner below
    • Dominion Energy
      • P1 Category Contingencies:
        • 0.93 to 1.05 p.u. for 230, 115, 69 kV facilities
        • 0.93 to 1.03 p.u. for 138 kV facilities due to legacy switches
        • 1.01 to 1.096 p.u. for 500 kV facilities
      • P2, P4, P5, and P7 Category Contingencies:
        • 0.90 to 1.05 p.u. for 230, 115, 69 kV facilities
        • 0.90 to 1.03 p.u. for 138 kV facilities due to legacy switches
        • 1.00 to 1.096 p.u. for 500 kV facilities
    • AEP
      • 0.92 to 1.05 p.u. for all voltage levels and each NERC Category contingencies
  • No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

No mitigations were found to be required.

 

A composite short circuit ratio (CSCR) assessment was performed and was calculated to be 1.48. All generations within Altavista 69 kV were considered due to a radially operated system. The low short circuit ratio is a weak grid concern, which could result in voltage and control instability. An Electromagnetic Transient (EMT) study is recommended.

 

Executive Summary for Dynamic Stability Analysis Using  PSCAD/EMT

 

Model Quality Testing Report

PSCAD model for Queue project AE2-187 was developed and tested to ensure the model was in compliance with the PJM requirements. Test summary and result of test been summarized below in table 2. it is confirmed that PSCAD model was set up properly and satisfied the PJM requirement.

Table 2. MQT Result for AE2-187

Test

Status

Flat Start Test 

Pass 

Voltage Step-Down 

Pass 

Voltage Step-Up 

Pass 

Frequency Step-Down, No Headroom

Pass 

Frequency Step-Down, Headroom

Pass 

Frequency Step-Up, Headroom 

Pass 

HVRT Leading

Pass 

HVRT Lagging

Pass 

LVRT Leading

Pass 

LVRT Lagging

Pass 

System Strength Test 

Pass 

Voltage Ride Through

Pass 

Phase Angle Step-Down 

Pass 

Phase Angle Step-Up 

Pass 

 

Weak Grid Assessment

This Weak Grid Assessment evaluates one project from PJM Transition Cycle 1 (TC1) Cluster 33 for risk of voltage instability due to weak grid conditions in an EMT simulation environment.  Queue project AE2-187 were identified in the Cluster Study as having potential risk of weak grid instability during contingency conditions after dynamic simulation analysis in PSS/E. System reinforcement was found to not be required, although evaluation using detailed models in an EMT simulation was recommended.

This assessment, completed by INS Engineering, aims to evaluate the risk of weak grid instability due to low short circuit ratio as identified in the Cluster Study, using detailed models in an EMT simulation.  A summary description of each project can be found below:

Table 3. Summary Description of TC1 Cluster 33 Project

Project Name

Project Type

Project Size (MW)

POI

POI Bus Number

AE2-187 (Shockoe Solar)

PV

60

Shockoe DP – Chatham 69 kV

314736

 

First, the individual project PSCAD models were evaluated for data consistency and model performance as part of the standard Model Quality Test, with model updates being made where needed.  INS confirmed that the PSCAD models were set up properly and satisfied the requirements of PJM. After satisfactory configuration and performance of the individual projects were obtained, the models were integrated into a translated reduced network in PSCAD to create an overall detailed system model. 

 

Two representative contingency cases from the Cluster Study, considered effectively the worst case in terms of risk for weak grid instability, were then simulated in the PSCAD detailed system model. For Cluster 33, the following contingency cases were chosen (all projects operating at rated power pre-fault).

  • Fault ID: P1.01: Fault at Stone Mill 69 kV on Gladys DP 69 kV and loss of circuit line #35
  • Fault ID: P1.18: Fault at Altavista 138 kV on New London (APCO) 138 kV and loss of circuit line #13

 

Simulation results in PSCAD are summarized below.  It can be observed that in case P1.01 the islanded condition results in the projects tripping, similar to the Cluster Study.  Overall system recovery as observed from the remaining 138kV network is stable.  In P1.18, stable recovery is observed in PSCAD and is consistent with the results of the Cluster Study. 

 

Table 4. Summary of cases tested in PSCAD system study

Fault ID

Fault Description

Cluster Study Result [1]

PSCAD Study Result

P1.01

Fault at Stone Mill 69 kV on Gladys DP 69 kV and loss of circuit line #35. Islanded condition in the 69 kV subnetwork. Cluster projects expected to trip.

System Stable,
Projects on 69kV trip

System Stable,
Projects on 69kV trip

P1.18

Fault at Altavista 138 kV on New London (APCO) 138 kV and loss of circuit line #13

Stable

Stable

 

The results of this weak grid assessment using PSCAD show overall stable system recovery in the two worst-case contingencies and supports the conclusion from the Cluster Study that mitigation is not required.

 

 

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 1 Cluster 34 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 34 projects.

 

Table 1: Transition Cycle 1 Cluster 34 Projects

 

 

 

 

 

 

 

Cluster

Project

Fuel Type

Transmission Owner

MFO

(MW)

MWE

(MW)

MWC

(MW)

Point of Interconnection

34

AE1-148

Solar

Dominion

90

90

54

Kerr Dam-Ridge Rd

115 kV

AE2-291

Solar

Dominion

102

102

61.2

Grit DP-Perth 115 kV

AF2-297

Solar

Dominion

80

80

48

Sedge Hill 115 kV

AG1-105

Solar

Dominion

90

90

54

Mount Laurel-Barnes Junction 115 kV

AG1-342

Solar

Dominion

36

36

21.6

Dryburg 115 kV

 

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 34 projects will meet the dynamics requirements of the NERC, Dominion Energy, and PJM reliability standards.

 

The load flow case for Phase 2 was used as a starting point and was updated based on latest Cluster 34 data, recommended transmission changes incorporated based on Dominion Energy Phase 2 feedback, and withdrawn generation removed. Cluster 34 projects have been dispatched online at maximum power output with near unity power factor measured at the high-side of the main substation transformer. The dynamic models for Cluster 34 projects were updated based on the latest DP2 data and include any tuning adjustments recommended during Phase 2.  

 

Cluster 34 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. During the Phase 2 analysis contingencies were examined around the POIs and no violations were observed as a result of Cluster 34 projects interconnecting.  Due to this the Phase 3 analysis for Cluster 34 focused on the contingencies at Chase City that resulted in instability caused by Cluster 31 and Cluster 40 during Phase 2.  The Phase 3 analysis examined 217 sensitivity contingencies, each with a 30 second simulation time period. The studied contingencies included:

 

  • Steady-state operation (30 seconds)
  • Three-phase faults with normal clearing time
  • Single-phase bus faults with normal clearing time
  • Single-phase faults with stuck breaker
  • Single-phase faults with delayed clearing at remote end
  • Three-phase faults with loss of multiple-circuit tower line

 

Instability was observed for contingencies when the Chase City to AG1-285 Tap 115 kV circuit was tripped. This outage resulted in instability due to insufficient export paths for the generation along the Farmville to Chase City 115 kV path through the radial connection.  Additionally, the Farmville to Chase City 115 kV path is prone to controller instability due to weak grid conditions determined by the composite short circuit ratio assessment.  The instability was caused by the Cluster 31 queue projects. 

  

To following mitigation was tested and all maintain stability: 

  1. Adding a new 115 kV line from AG1-285 to Butcher’s Creek. 
  2. Moving AF2-222 and AG1-285 to a new 230 kV line from Farmville to Finneywood. 
  3. Updating the new AG1-285 230 kV substation to breaker and a half scheme to accommodate 2 x 230/115 kV AG1-285 transformers, and a 230 kV line from AG1-285 to Finneywood. 

 

The Transmission Owner selected the 3rd mitigation option, which updated the new AG1-285 230 kV substation to a breaker and a half scheme to accommodate 2 x 230/115 kV AG1-285 transformers, and a 230 kV line from AG1-285 to Finneywood. to maintain stability. This mitigation is required due to the interconnection of the Cluster 31 queue projects. Cluster 34 queue projects did not cause instability.

 

The REGCA1 Accel (CON J+13) parameter was set to 0.7 to improve PSS/E network solution calculations for all IBRs located in dispatch area.

 

Voltage oscillations were observed at Altavista 69 kV. It is determined that Smith Mountain, AEP generator, is the source of this oscillation. Gnetting the Smith Mountain generators improved PSS/E network solution calculations. It is recommended for Smith Mountain dynamic model to be revised.

 

Nearby projects were found to trip based on their protection settings. The protection trip times were increased during Phase 2 analysis and maintained during the Phase 3 analysis:

  • AD2-033 tripped for overvoltage protection model for voltage above 1.4 p.u. and the time delay setting was update from 0.001 to 0.0208 seconds.
  • AE2-185 tripped for overvoltage protection model for voltage above 1.2 p.u. and the time delay setting was update from 0.001 to 0.0542 seconds.
  • AE2-187 tripped for overvoltage protection model for voltage above 1.175 p.u. and the time delay setting was update from 0.21 to 0.4042 seconds.
  • AE2-187 tripped for overvoltage protection model for voltage above 1.2 p.u. and the time delay setting was update from 0.001 to 0.3875 seconds.
  • AE2-283 tripped for underfrequency protection model for frequency below 55 Hz and the time delay settings was updated from 0.01 to 0.0167 seconds.
  • AF2-404 tripped for underfrequency protection model for frequency below 55 Hz and the time delay settings was updated from 0.01 to 0.0167 seconds.  

 

With the mitigation identified above, the results of the contingencies tested on the RTEP 2027 summer peak case found: 

 

  • Cluster 34 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  • The system with Cluster 34 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for inter area modes and 4% for local modes in Dominion area.
  • Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds,  except where protective action isolates that bus.
  • For Dominion area, the final voltages are within the steady-state voltage ranges below per Dominion Energy’s transmission planning criteria.
    • P1 Category Contingencies:
      • 0.93 to 1.05 p.u. for 230, 115, 69 kV facilities
      • 0.93 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.01 to 1.096 p.u. for 500 kV facilities
    • P2, P4, P5, and P7 Category Contingencies:
      • 0.90 to 1.05 p.u. for 230, 115, 69 kV facilities
      • 0.90 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.00 to 1.096 p.u. for 500 kV facilities
  • No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

It is recommended that future model submissions be validated with the settings proposed in this study. If model data and settings differ, then a transient stability study is recommended to validate the new model data and settings.

 

No mitigation was needed to connect the Cluster 34 queue projects. 

Executive Summary for Stability Cluster

Executive Summary for Dynamic Stability Analysis Using PSSE

New Service Requests (projects) in PJM Transition Cycle 1 Cluster 35 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 35 projects.

 

Table 1: Transition Cycle 1 Cluster 35 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO (MW)

MWE (MW)

MWC (MW)

Point of Interconnection

35

AE2-185

Solar

Dominion

60

60

36

Gladys DP – Stonemill 69 kV

AF2-404

Battery

Dominion

0

0

AE2-283

Solar

Dominion

53

53

28

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 35 projects will meet the dynamics requirements of the NERC, Dominion Energy, and PJM reliability standards.

 

The load flow case finalized for Phase 2 was used as a starting point and was updated based on latest Cluster 35 data, Dominion Energy recommended transmission changes and withdrawn generation. Projects in vicinity of Cluster 35 have been dispatched online at maximum power output with near unity power factor measured at the high-side of the main substation transformer. The dynamic models for Cluster 35 projects were updated based on the latest DP2 data and include any tuning adjustments recommended during Phase 2.

 

For Cluster 35 the dispatch of the study units was based on two scenarios.

  • Scenario 1: MFO met with solar generation and energy storage offline (solar output = 61.9 MW and storage is offline)
  • Scenario 3: MFO met with the solar generation and energy storage dispatched proportionally to their power capability (solar output = 47.44 MW and storage output = 14.56 MW)

 

Cluster 35 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. 75 contingencies were studied, each with a 30 second simulation time period. The studied contingencies included:

 

  • Steady-state operation
  • Three-phase faults with normal clearing time
  • Single-phase bus faults with normal clearing time
  • Single-phase faults with stuck breaker
  • Single-phase faults with delayed clearing at remote end
  • Three-phase faults with loss of multiple-circuit tower line.

 

For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the RTEP 2027 summer peak case:

 

  • Cluster 35 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  • The system with Cluster 35 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
  • Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus) and the final voltages are within the steady-state voltage ranges below per Dominion Energy and AEP’s transmission planning criteria.
    • Dominion Energy:
      • P1 Category Contingencies:
        • 0.93 to 1.05 p.u. for 230, 115, 69 kV facilities
        • 0.93 to 1.03 p.u. for 138 kV facilities due to legacy switches
        • 1.01 to 1.096 p.u. for 500 kV facilities
      • P2, P4, P5, and P7 Category Contingencies:
        • 0.90 to 1.05 p.u. for 230, 115, 69 kV facilities
        • 0.90 to 1.03 p.u. for 138 kV facilities due to legacy switches
        • 1.00 to 1.096 p.u. for 500 kV facilities
    • AEP:
      • 0.92 p.u. to 1.05 p.u. for all voltage levels for each NERC Category Contingency
  • No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

The results of the analysis indicated all evaluation criteria were met. The following observations were made.

 

The initial results showed that Cluster 35 generators units exhibited slow reactive power recovery for several contingencies, Power Plant Controller (PPC) freezing, divergence and low frequency controller oscillations. These issues did not cause instability, and the generating units were tuned to achieve a faster recovery with better response.

The following adjustments were required for the respective queue projects based on the analysis results:

 

  • For AE2-187 the following adjustments were made:
    • The REECA1 Vup (p.u.) (CON J+1) parameter was set to 1.15 p.u to mitigate PPC freezing
    • Generator tripped for overvoltage protection model for voltage above 1.21 p.u and the time delay setting was updated from 0.16 to 0.3 seconds to allow generator to ride through the fault

 

  • For AE2-283 the following adjustments were made:
    • The REGCA1 Accel (CON J+13) parameter was set to 0.5 to improve PSS/E network solution calculations

 

  • For AC1-122 the following adjustments were made:
    • The REPCA Ki (CON J+2) parameter was changed from 0 to 10 to improve reactive power recovery

 

During phase 3 analysis all generations near Cluster 35 (AC1-042, AC1-145, AE2-185, AE2-187, and AF2-404) have their REGCA1 Accel set to 0.7. This was implemented as part of a phase 2 observation.  It should be noted that this parameter does not affect the performance or recovery of the renewable model, but is used to smooth the voltage and angle calculations within PSS/E.

 

Voltages above 1.05 p.u. were observed at Altavista 69 kV. This is due to Altavista 138-69 kV load tap changer operating at 1.10 p.u. to maintain the Altavista 69 kV scheduled voltage. A significant voltage drop was observed between Altavista, Gladys Tap, Altavista DP, and Mt Airy Tap due to the amount of generation served within the Altavista 69 kV system. To ensure that the post contingency voltage is below 1.05 p.u., the Altavista 138/69 kV load tap changing transformer would need to operate at 1.0375 p.u. tap and under System Normal (P0) conditions, would produce a 0.968 p.u. voltage on the Altavista 69 kV bus, which is within Dominion Energy’s P0 voltage levels. A voltage coordination study is recommended in the future to determine an acceptable voltage schedule for the Altavista 138/69 kV load tap changing transformer to coordinate with the generations served in the Altavista 69 kV system.

 

AE2-185, AF2-404, AE2-283, AC1-042 and AE2-187 were observed to have controller oscillations for a few faults such as P415. This is not a concern, and IC can tune their model to eliminate this behavior.

 

AD1-131, and AF2-107’s reactive power was observed to not settle within the 30 second simulation window for various faults. This issue did not cause instability in the system and the models can be tuned to achieve a faster reactive power output settlement.

 

Low-frequency oscillations were observed for AE1-250 that were positively damped and settled in less than 15 seconds.  This issue did not cause instability in the system.

 

The AE2-185 queue project met the 0.95 lagging and leading power factor measured at the high side of main transformer.

 

The AE2-185 and AF2-404 BESS queue projects combined met the 0.95 lagging and leading power factor measured at the high side of main transformer.

 

The AE2-283 queue project met the 0.95 lagging and leading power factor measured at the high side of main transformer.

 

A voltage coordination study and Electromagnetic Transients (EMT) study around Altavista is recommended due to the findings of this analysis.  Additionally, any future projects connecting near Altavista should provide EMT models for their facility.

 

No mitigations were found to be required

 

Executive Summary for Dynamic Stability Analysis Using  PSCAD/EMT

 

Model Quality Testing Report

 

PSCAD model for Queue project AE2-185/AF2-404 and AE2-283 was developed and tested individually to ensure the model was in compliance with the PJM requirements. Test summary and result of test been summarized below in table 2. it is confirmed that PSCAD model was set up properly and satisfied the PJM requirement.

 

Table 2. MQT Result for each project

Test

Status

Flat Start Test 

Pass 

Voltage Step-Down 

Pass 

Voltage Step-Up 

Pass 

Frequency Step-Down, No Headroom

Pass 

Frequency Step-Down, Headroom

Pass 

Frequency Step-Up, Headroom 

Pass 

HVRT Leading

Pass 

HVRT Lagging

Pass 

LVRT Leading

Pass 

LVRT Lagging

Pass 

System Strength Test 

Pass 

Voltage Ride Through

Pass 

Phase Angle Step-Down 

Pass 

Phase Angle Step-Up 

Pass 

Weak Grid Assessment

 

This Weak Grid Assessment evaluates three projects from PJM Transition Cycle 1 (TC1) Cluster 35 for risk of voltage instability due to weak grid conditions in an EMT simulation environment.  The three projects, AE2-185, AF2-404, and AE2-283, were identified in the Cluster Study as having potential risk of weak grid instability during contingency conditions after dynamic simulation analysis in PSS/E. System reinforcement was found to not be required, although evaluation using detailed models in an EMT simulation was recommended.

 

This assessment, completed by INS Engineering, aims to evaluate the risk of weak grid instability due to low short circuit ratio as identified in the Cluster Study, using detailed models in an EMT simulation.  A summary description of each project can be found below:

Table 3. Summary Description of TC1 Cluster 35 Projects

Project Name

Project Type

Project Size (MW)

POI

POI Bus Number

AE2-185 / AF2-404 Pigeon Run Solar and BESS

PV + BESS

60

Gladys DP – Stonemill 69 kV

941800

AE2-283 Gladys Solar

PV

53

Gladys DP – Stonemill 69 kV

942670

 

Individual project PSCAD models were evaluated for data consistency and model performance as part of the standard Model Quality Test process,  model updates being made where needed.  INS confirmed that the PSCAD models were set up properly and satisfied the requirements of PJM. After satisfactory configuration and performance of the individual projects were obtained, the models were integrated into a translated reduced network in PSCAD to create an overall detailed system model. 

 

Two representative contingency cases from the Cluster Study, considered effectively the worst case in terms of risk for weak grid instability, were then simulated in the PSCAD detailed system model. For Cluster 35, the following contingency cases were chosen (all projects operating at rated power pre-fault).

 

  • Fault ID: P1.01: Fault at Stone Mill 69 kV on Gladys DP 69 kV and loss of circuit line #35
  • Fault ID: P1.18: Fault at Altavista 138 kV on New London (APCO) 138 kV and loss of circuit line #13

 

Simulation results in PSCAD are summarized below.  It can be observed that in case P1.01 the islanded condition results in the projects tripping, similar to the Cluster Study.  Overall system recovery as observed from the remaining 138kV network is stable.  In P1.18, stable recovery is observed in PSCAD and is consistent with the results of the Cluster Study. 

 

Table 4. Summary of cases tested in PSCAD system study

Fault ID

Fault Description

Cluster Study Result

PSCAD Study Result

P1.01

Fault at Stone Mill 69 kV on Gladys DP 69 kV and loss of circuit line #35. Islanded condition in the 69 kV subnetwork. Cluster projects expected to trip.

System Stable,
Projects on 69kV trip

System Stable,
Projects on 69kV trip

P1.18

Fault at Altavista 138 kV on New London (APCO) 138 kV and loss of circuit line #13

Stable

Stable

 

The results of this weak grid assessment using PSCAD show overall stable system recovery in the two worst-case contingencies and supports the conclusion from the Cluster Study that mitigation's are not required.

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 1 Cluster 37 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 37 projects.

 

Table 1: Transition Cycle 1 Cluster 37 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO (MW)

MWE (MW)

MWC (MW)

Point of Interconnection

37

AF2-046

Solar

Dominion

126

126

83.7

Tunis – Mapleton 115 kV

AG1-008

Solar

Dominion

126

126

83.7

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 37 projects will meet the dynamics requirements of the NERC, Dominion Energy, and PJM reliability standards.

 

The load flow scenario for the analysis was based on the Regional Transmission Expansion Plan (RTEP) 2027 summer peak case, modified to include applicable projects. Cluster 37 projects have been dispatched online at maximum power output with near unity power factor measured at the high-side of the main substation transformer.

 

Cluster 37 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. 83 contingencies were studied, each with a 20 second simulation time period. The studied contingencies included:

 

  • Steady-state operation
  • Three-phase faults with normal clearing time
  • Single-phase bus faults with normal clearing time
  • Single-phase faults with stuck breaker
  • Single-phase faults with delayed clearing at remote end
  • Three-phase faults with loss of multiple-circuit tower line

 

For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all of the fault contingencies tested on the RTEP 2027 summer peak case:

 

  • Cluster 37 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  • The system with Cluster 37 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
  • Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus) and the final voltages are within the steady-state voltage ranges below per Dominion Energy transmission planning criteria.
    • Dominion Energy:
      • P1 Category Contingencies:
        • 0.93 to 1.05 p.u. for 230, 115, 69 kV facilities
        • 0.93 to 1.03 p.u. for 138 kV facilities due to legacy switches
        • 1.01 to 1.096 p.u. for 500 kV facilities
      • P2, P4, P5, and P7 Category Contingencies:
        • 0.90 to 1.05 p.u. for 230, 115, 69 kV facilities
        • 0.90 to 1.03 p.u. for 138 kV facilities due to legacy switches
        • 1.00 to 1.096 p.u. for 500 kV facilities
  • No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

The results of the analysis indicated all evaluation criteria were met.

 

Voltages below 0.93 p.u were observed at the Boykins 115 kV, Newsoms 115 kV, Handsom DP 115 kV, Southampton 115 kV, Watkins Corner 115 kV, Franklin 115 kV, Union Camp 115 kV and Tunis 115 kV buses. This was typically observed after losing the circuit between Boykins and AF2-046 TAP 115 kV circuit and loss of Earleys to AF2-046 TAP 115 kV circuit. 

 

Voltages above 1.05 p.u were observed at Tunis 115 kV, Ahoskie 115 kV, AF2-046 TAP 115 kV, Mapleton DP 115 kV and Murphy 115 kV  due to loss of generation at AF2-046.

 

To ensure that the post-contingency voltage is within the final voltage criteria the following adjustments were needed:

 

  • 2 x 25.26 Mvar fixed shunt at Watkins 115 kV were switched on
  • 1 x 33.67 Mvar fixed shunt at Earleys 115 kV was turned off
  • Voltage schedule was updated for the generation interconnection projects in Table 2

 

A voltage coordination study is recommended to ensure that with or without a nearby capacitor bank, will produce an acceptable post-contingency voltage.

Table 2: Voltage Schedule Adjusted to Solve Voltage Violations

Bus  Number

Bus  Name

Id

Area Num

Area Name

Voltage

Schedule (p.u.)

Regulated Bus Number

POI Bus Voltage

(p.u.)

315606

AA2-053 GEN

S1

345

DVP

1.025

315606

1.0193

316140

AB2-099

1

345

DVP

1.03

316140

1.0176

316190

AA2-174 GEN

S1

345

DVP

1.025

316190

1.0193

316463

AE2-346 GEN

S1

345

DVP

1.03

316463

1.0176

918494

AA1-063A

1

345

DVP

1.02

918490

1.0189

957525

AF2-046_GEN

1

345

DVP

1.0350

957521

1.0350

961684

AG1-008_GEN

1

345

DVP

1.0350

961680

1.0350

 

System-wide high-frequency oscillations were observed during post-fault recovery caused by AA2-088. AA2-088’s REGCA1, CON(J) Tg, converter time constant was set to 0 seconds initially and was flagged by PSS/E’s data checker. After adjusting to 0.02 seconds to resolve this issue. The plant owner should review the setting.

 

AA2-088 tripped initially for 1.2 p.u. over voltage protection but rode through when the pickup timer was increased from 0 to 0.0208 seconds.

 

1HOLLOMANSOL tripped for 64 Hz over frequency protection but rode through when the pickup timer was increased from 0.02 to 0.0833 seconds.

 

Generator at Union Camp tripped for over speed due to an incorrect MVA base that was less than the Pgen value in the 2027 case. The unit rode through after updating the MVA to 43.21 from 21 MVA based on data included in an earlier case year. The plant owner should review the setting.

 

 

Reactive power for AF2-080, Union Camp, AA2-088 and AE1-035 appears to settle down beyond 20 seconds. The model could be tuned by the IC to improve settling.

 

No mitigation was required.

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 1 Cluster 39 are listed in Table 1 below. This report will cover the TC1 Phase 3 dynamic analysis of Cluster 39 projects.

 

 

Table 1: Transition Cycle 1 Cluster 39 Projects

 

 

 

 

 

 

 

Cluster

Project

Fuel Type

Transmission Owner

MFO

(MW)

MWE

(MW)

MWC

(MW)

Point of Interconnection

39

AF2-080

Solar

Dominion

150

70

48.5

Chinquapin - Everetts 230 kV

AG1-106

Solar

Dominion

323

23

16

Thelma 230 kV

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 39 projects will meet the dynamics requirements of the NERC, Dominion Energy, and PJM reliability standards.

 

The load flow case finalized for Phase 2 was used as a starting point and was updated based on latest Cluster 39 data, Dominion Energy recommended transmission changes and withdrawn generation. Projects in vicinity of Cluster 39 have been dispatched online at maximum power output with near unity power factor measured at the high-side of the main substation transformer. The dynamic models for Cluster 39 projects were updated based on the latest DP2 data and include any tuning adjustments recommended during Phase 2.

 

Cluster 39 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. 211 contingencies were studied, each with a 30 second simulation time period. The studied contingencies included:

The contingencies were updated based on topology changes due to any Dominion Energy recommended transmission changes or generation withdrawals.

 

For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all of the fault contingencies tested on the RTEP 2027 summer peak case:

 

  • Cluster 39 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  • The system with Cluster 39 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
  • Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus) and the final voltages are within the steady-state voltage ranges below per Dominion Energy’s transmission planning criteria.
    • P1 Category Contingencies:
      • 0.93 to 1.05 p.u. for 230, 115, 69 kV facilities
      • 0.93 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.01 to 1.096 p.u. for 500 kV facilities
    • P2, P4, P5, and P7 Category Contingencies:
      • 0.90 to 1.05 p.u. for 230, 115, 69 kV facilities
      • 0.90 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.00 to 1.096 p.u. for 500 kV facilities
  • No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

Oscillations were observed at the Gaston units for contingencies P4.43, P4.48, P4.52, P4.57, and P4.58. These oscillations did not met Dominion’s 4% damping criteria for local area and were observed to be pre-existing but was exacerbated by dispatched generation at Thelma.  The damping angle with changes to the generation dispatched at Thelma. The results indicate that reducing generation in the surrounding area leads to improved damping performance at Gaston and it is concluded that the oscillations at Gaston were not caused by the TC1 Cluster 39 projects.

 

The Transmission Owner has elected to upgrade the Hathaway 115 kV substation by splitting the existing 115 kV bus into two separate buses with a 115 kV line on each bus and the tie switch between line 55 and 80 was closed. Additionally, Line #1001 was opened at Battleboro, resulting in it becoming a radial line from Chestnut Substation. Contingency definitions at the Hathaway 115 kV substation were updated based on topology change, and the analysis was performed. Oscillations at Gaston continue to persist and were unaffected by the topology changes. No other violations occurred.

 

AF2-080 queue project did not meet the 0.95 lagging power factor measured at high side of the main transformer. When the facility was tested at its maximum lagging reactive capability, voltages above 1.10 p.u. were observed at the inverter terminal. To ensure that the facility can provide its lagging power factor without high voltages at the inverter terminal, it is recommended that the tap on the high side of the main transformer be adjusted from 1.0 to 1.025. An additional 5.42 Mvar is required to meet the 0.95 lagging power factor. The AF2-080 queue project met the 0.95 leading power factor measured at high side of the main transformer.

 

AG1-106 is an uprate of AB1-132 and AC1-086. The measurement point for the power factor requirements per the Interconnection Service Agreement (ISA) is at the generator terminals for AB1-132 and AC1-086.  AG1-106’s power factor requirements is measured at the high side of the station transformer.  Due to this three power factor assessments were included to bound the lagging deficiencies observed.  The following lagging deficiencies were observed for AG1-106 depending on the measurement’s points enforced for each test.

 

  • With AG1-106 online, and AB1-132 and AC1-086 offline to ensure the losses created by the AB1-132 and AC1-086 generators are not counted against AG1-106. The facility met the 0.95 lagging and leading power factor requirements measured at the high side of the main transformer.
  • With AG1-106 and AB1-132 online, AC1-086 offline to consider the shared high side of main station transformer. AB1-132’s measurement point in the ISA is not enforced in this test. The facility met the 0.95 lagging and leading power factor requirements measured at the high side of the main transformer. However, voltage violation were observed at the generator terminals with the voltage of 1.196 p.u. at AB1-132 and 1.147 p.u. at AG1-106.
  • AG1-106, AB1-132, and AC1-086 online to consider the shared high side of main station transformer. AB1-132 and AC1-086 measurement point in the ISA are not enforced in this test. The lagging power factor deficiency is 49.38 Mvar.

 

No mitigation was required.

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 1 Cluster 42 are listed in Table 1 below. This report will cover the TC1 Phase 3 dynamic analysis of Cluster 42 projects.

 

Table 1: Transition Cycle 1 Cluster 42 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

42

AF2-035

Solar

Dominion

72

72

48

St. Johns 115 kV

AG1-154

BESS

Dominion

50

50

20

Ladysmith CT 230 kV

 

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 42 projects will meet the dynamics requirements of the NERC, Dominion Energy, and PJM reliability standards.

 

The load flow case finalized for Phase 2 was used a starting point and was updated based on latest Cluster 42 data, Dominion Energy recommended transmission changes and withdrawn generation. Projects in vicinity of Cluster 42 have been dispatched online at maximum power output with near unity power factor measured at the high-side of the main substation transformer. The dynamic models for Cluster 42 projects were updated based on the latest DP2 data and include any tuning adjustments recommended during Phase 2.

 

Cluster 42 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. 117 contingencies were studied, each with a 30 second simulation time period. The studied contingencies included:

 

  • Steady-state operation
  • Three-phase faults with normal clearing time
  • Single-phase bus faults with normal clearing time
  • Single-phase faults with stuck breaker
  • Single-phase faults with delayed clearing at remote end
  • Three-phase faults with loss of multiple-circuit tower line.

 

The contingencies were updated based on topology changes due to any Dominion Energy recommended transmission changes or generation withdrawals.

 

For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all of the fault contingencies tested on the RTEP 2027 summer peak case:

 

  • Cluster 42 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  • The system with Cluster 42 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for inter area modes and 4% for local modes in Dominion area.
  • Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus)
  • No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.
  • For Dominion area, the final voltages were found to be within the steady-state voltage ranges below per Dominion Energy’s transmission planning criteria.
    • P1 Category Contingencies:
      • 0.93 to 1.05 p.u. for 230, 115, 69 kV facilities
      • 0.93 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.01 to 1.096 p.u. for 500 kV facilities
    • P2, P4, P5, and P7 Category Contingencies:
      • 0.90 to 1.05 p.u. for 230, 115, 69 kV facilities
      • 0.90 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.00 to 1.096 p.u. for 500 kV facilities

 

AF2-035 was able to meet all power factor requirements. AG1-154 met the leading power factor requirements, but did not meet the lagging requirements with a deficiency of 3.01 Mvar. The developer is requested to cure this deficiency before the project moves to the next phase.

 

The AG1-154 unit was found to have a slow reactive power response for a majority of the fault scenarios, which is most evident in scenarios P133, P410 and P439 (see Attachment 3 for plots). While this is not a criteria violation, the developer should tune this model for a faster response. Within the dynamic model for AG1-154, the REPCA parameter's Kp, Ki and Kc can be adjusted to improve the reactive power settlement.

 

A few issues that were identified in Phase 2 (Revision 1 of this report) were also tested for validity. 

  • Phase 2 analysis identified system instability for faults P412, P450 and P451. Instability is still identified in Phase 3 for faults P450 and P451 but not for P412. These faults were studied with a 26 cycle clearing time which is beyond the typical 14 cycle time for Dominion generating stations. After reducing the clearing time to 14 cycles, the instability for these faults is resolved. No mitigation is required.

 

AF2-013 was observed to freeze momentarily for faults P414, P452 and additionally trip for fault P467 in Phase 2 analysis. It was recommended that the REECA Vup parameter be increased from 1.1 to 1.2, which resolved the issues. In Phase 3 analysis the freezing is no longer observed for faults P452 and P467, but still identified for P414, and with the recommended REECA Vup adjustment, these freezing issues are resolved for all faults. Therefore, the developer is recommended to adjust the REECA Vup parameter from 1.1 to 1.2 or tune the model appropriately to prevent the identified freezing issues. 

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 1 Cluster 44 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 44 projects.

 

Table 1: Transition Cycle 1 Cluster 44 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

44

AF2-081

Solar

Dominion

80

80

56

Moyock 230 kV

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 44 projects will meet the dynamics requirements of the NERC, Dominion Energy, and PJM reliability standards.

 

The load flow case finalized for Phase 2 was used as a starting point and was updated based on latest Cluster 44 data, Dominion Energy recommended transmission changes, and withdrawn generation. Projects in vicinity of Cluster 44 has been dispatched online at maximum power output with near unity power factor measured at the high-side of the main substation transformer. The dynamic models for the Cluster 44 project was updated based on the latest DP2 data and include any tuning adjustments recommended during Phase 2.

 

Cluster 44 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. 123 contingencies were studied, each with a 20 second simulation time period. The studied contingencies included:

  • Steady-state operation (30 seconds)
  • Three-phase faults with normal clearing time
  • Single-phase bus faults with normal clearing time
  • Single-phase faults with stuck breaker
  • Single-phase faults with delayed clearing at remote end
  • Three-phase faults with loss of multiple-circuit tower line.

 

The contingencies were updated based on latest breaker topology at Moyock 230 kV substation, as provided by the Transmission Owner during the Phase 2 final review and generation withdrawals.

 

For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all of the fault contingencies tested on the RTEP 2027 summer peak case:

  • Cluster 44 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  • The system with Cluster 44 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
  • Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus) and the final voltages are within the steady-state voltage ranges below per Dominion Energy’s transmission planning criteria.
    • P1 Category Contingencies:
      • 0.93 to 1.05 p.u. for 230, 115, 69 kV facilities
      • 0.93 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.01 to 1.096 p.u. for 500 kV facilities
    • P2, P4, P5, and P7 Category Contingencies:
      • 0.90 to 1.05 p.u. for 230, 115, 69 kV facilities
      • 0.90 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.00 to 1.096 p.u. for 500 kV facilities
  • No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

AF2-081 met the 0.95 lagging and leading power factor requirements by adjusting Main Power Transformer Tap setting to 0.9 p.u for lagging test and 1.05 p.u. for leading test. Interconnection Customer confirmed per “AF2-081 Equivalent Model V34.7 - Dynamic Model Report - 02-13-25. Docx” that transformer is equipped with Load Tap changer.

 

No mitigations were found to be required.

 

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 1 Cluster 45 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 45 projects.

Table 1: Transition Cycle 1 Cluster 45 Projects

 

 

 

 

 

 

 

Cluster

Project

Fuel Type

Transmission Owner

MFO (MW)

MWE (MW)

MWC (MW)

Point of Interconnection

45

AF2-042

Solar

Dominion

500

500

300

Clover-Finneywood 500 kV

AG1-098

Solar

Dominion

107

107

64.2

Briery-Finneywood 230 kV

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 45 projects will meet the dynamics requirements of the NERC, Dominion Energy, and PJM reliability standards.

 

The load flow scenario for the analysis was based on the Regional Transmission Expansion Plan (RTEP) 2027 summer peak case, modified to include applicable projects. Cluster 45 projects have been dispatched online at maximum power output with near unity power factor measured at the high-side of the main substation transformer.

 

Cluster 45 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. 104 contingencies were studied, each with a 30 second simulation time period. The studied contingencies included:

  • Steady-state operation (30 seconds)
  • Three-phase faults with normal clearing time
  • Single-phase bus faults with normal clearing time
  • Single-phase faults with stuck breaker
  • Single-phase faults with delayed clearing at remote end
  • Three-phase faults with loss of multiple-circuit tower line

 

For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all of the fault contingencies tested on the RTEP 2027 summer peak case:

 

  • Cluster 45 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  • The system with Cluster 45 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
  • Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus) and the final voltages are within the steady-state voltage ranges below per Dominion Energy’s transmission planning criteria.
    • P1 Category Contingencies:
      • 0.93 to 1.05 p.u. for 230, 115, 69 kV facilities
      • 0.93 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.01 to 1.096 p.u. for 500 kV facilities
    • P2, P4, P5, and P7 Category Contingencies:
      • 0.90 to 1.05 p.u. for 230, 115, 69 kV facilities
      • 0.90 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.00 to 1.096 p.u. for 500 kV facilities
  • No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

The results of the analysis indicated all evaluation criteria were met.

 

The following observations were made:

 

AF2-042’s reactive power took longer than 20 seconds to settle to a steady state value  While this is not a criteria violations the model could be tuned to decrease the settling time.

Contingencies P123, P124 and P125 diverged due to the AG1-098 queue project.  This issue was resolved by updating the PSS/E Dynamic Simulation Acceleration factor from 0.5 and 0.25.

Controller oscillations were observed for AG1-098 Generators 1 & 2 during the fault on selected P4 contingencies. After the fault is cleared, no controller oscillations were observed. This did not cause instability and is not a concern.

 

AD2-202 tripped due to the overvoltage protection (1.12 p.u. in 5 seconds). When the protection model was disabled the units reached terminal voltages above 1.12 p.u. with its reactive power reaching its upper limit.  To resolve the tripping the transformer tap on the high side of the AD1-087 and AD2-202 main station transformers was changed to 1.05 p.u and by changing the two projects to control the POI voltage in the power flow case.

 

No mitigation was required.

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 1, Cluster 46 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 46 project.

 

 

Table 1: TC1 Cluster 46 Projects

 

 

 

 

 

 

 

Cluster

Project

Fuel Type

Trans. Owner

MFO (MW)

MWE (MW)

MWC (MW)

Point of Interconnection

46

AE2-156

Battery

Dominion

100

100

100

Yadkin 115 kV

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 46 projects will meet the dynamics requirements of the NERC, Dominion Energy and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2027 summer peak case, modified to include applicable projects. Cluster 46 projects have been dispatched online at maximum power output. The reactive power output for cluster 46 projects will be set near unity power factor at the high side of the station transformer before beginning the analysis

Cluster 46 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 299 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

No relevant high speed reclosing (HSR) contingencies were identified for this study.

For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the 2027 summer peak case:

  • Cluster 46 projects are able to ride through the faults (except for faults where protective action trips a generator(s)),
  • The system with Cluster 46 projects included is transiently stable and post-contingency oscillations should be positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
  • Following fault clearing, all bus voltages recover to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
  • The final voltages are within the steady-state voltage ranges below per the TOs transmission Planning Criteria:
      • P1 Category Contingencies:
        • 0.93 to 1.05 p.u. for 230, 115, 69 kV facilities
        • 0.93 to 1.03 p.u. for 138 kV facilities due to legacy switches
        • 1.01 to 1.096 p.u. for 500 kV facilities
      • P2, P4, P5, and P7 Category Contingencies:
        • 0.90 to 1.05 p.u. for 230, 138, 115, 69 kV facilities
        • 0.90 to 1.03 p.u. for 138 kV facilities due to legacy switches
        • 1.00 to 1.096 p.u. for 500 kV facilities
  • No transmission element trips, other than those either directly connected or designed to trip as a consequence of that fault.

During the model assumptions the following changes were made to the data provided by the developer.

  • REPCAU1 ICON(M) (Bus number for voltage control) to 314513
  • REPCAU1 ICON(M+1) (Monitored branch ‘FROM’)  to 941590
  • REPCAU1 ICON(M+2) (Monitored branch ‘TO’) to 314513
  • REPCAU1 CON(J+13) QMAX to 0.4764
  • REPCAU1 CON(J+14) QMIN to -0.4764
  • REPCAU1 CON(J+22) PMAX to 0.8759
  • REPCAU1 CON(J+26) droop for under-frequency to 20

 

The results of the analysis met the evaluation criteria for all contingencies.

AE2-156 exhibited the reactive power not recovering to a steady-state value, terminal voltages outside of 0.95 to 1.05 p.u. and decreasing active power for several contingencies. Although no criteria was violated, the transient stability analysis recommends modifications to AE2-156 to improve recovery and settling time. The following modifications for AE2-156 are recommended and improved recovery.

  • REECAU1 ICON M+3 (QFLAG) to 0
  • REPCAU1 ICON (M) to POI (314513)
  • REPCAU1 ICON M+4 (VC Flag) to 0

 

It is recommended that future model submissions be validated with the settings proposed in this study. If model data and settings differ, then a transient stability study is recommended to validate the new model data and settings

AD1-033’s reactive power recovery was not settling to a steady state value during the analysis.

 

AE1-072 exhibited low frequency oscillations for 0.5 seconds on selected P4 contingencies during the fault. These oscillations settled and did not cause any instability. This is not a concern.

 

AB2-169 generator tripped for overvoltage protection model1  for voltage above 1.25 p.u. for P1.21 and P1.22 contingencies the time delay settings was updated from 0.00 to 0.0125.

 

AE2-156 was turned off and the issues remained therefore it’s pre-existing. However, it was observed that reactive settling doesn’t violate any PJM or Dominion criteria and settles within a 60 second simulation. The project is currently working on an as built model submittal that can be reviewed for this behavior at a later date. 

 

No mitigations were found to be required.

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 1 Cluster 47 are listed in Table 1 below. This report will cover the TC1 Phase 3 dynamic analysis of Cluster 47 projects.

 

Table 1: Transition Cycle 1 Cluster 47 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO (MW)

MWE (MW)

MWC (MW)

Point of Interconnection

47

AG1-153

Battery

Dominion

75

75

30

Heritage 500 kV

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 47 projects will meet the dynamics requirements of the NERC, Dominion Energy, and PJM reliability standards.

 

The load flow case finalized for Phase 2 was used as a starting point and was updated based on latest Cluster 47 data, Dominion Energy recommended transmission changes and withdrawn generation. Projects in vicinity of Cluster 47 have been dispatched online at maximum power output with near unity power factor measured at the high-side of the main substation transformer. The dynamic models for Cluster 42 projects were updated based on the latest DP2 data and include any tuning adjustments recommended during Phase 2.

 

Cluster 47 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. 97 contingencies were studied, each with a 30 second simulation time period. The studied contingencies included:

 

  • Steady-state operation (30 seconds)
  • Three-phase faults with normal clearing time
  • Single-phase bus faults with normal clearing time
  • Single-phase faults with stuck breaker
  • Single-phase faults with delayed clearing at remote end
  • Three-phase faults with loss of multiple-circuit tower line.

 

The contingencies were updated based on topology changes due to any Dominion Energy recommended transmission changes or generation withdrawals.

 

For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all of the fault contingencies tested on the RTEP 2027 summer peak case:

 

 

AG1-153 queue project did not meet the power factor 0.95 lagging measured at the high side of the transformer and it is deficient by 3.85 MVAR. AG1-153 queue project met the 0.95 leading power factor requirements.

 

The result of the analysis for Cluster 47 projects met all evaluation criteria for all the contingencies. No mitigation was required. There were minor reactive drift from AG1-153 that could be tuned by developer to improve performance.

 

AE1-173:

AE1-173, a nearby generator tripped for under voltage protection for voltages under 0.64 p.u for 0.31 seconds. The unit rode through all contingencies when pickup time was increased to 0.4375 seconds. The generator owner should be contacted to confirm if the revised setting is within plants capability and/or tune the model’s recovery.

 

AB2-169:

AB2-169, nearby generator, tripped for over voltage protection for voltages over 1.25 p.u. for 0.0 seconds. The unit rode through all contingencies when pickup time was increased to 0.0125 seconds.  The generator owner should be contacted to confirm if the revised setting is within plants capability and/or tune the model’s recovery.

Executive Summary for Stability Cluster

Executive Summary

 

New Service Requests (projects) in PJM Transition Cycle 1 Cluster 48 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 48 project.

 

Table 1: Transition Cycle 1 Cluster 48 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO (MW)

MWE (MW)

MWC (MW)

Point of Interconnection

48

AF1-128

Natural Gas

Dominion

569

569

569

Chesterfield 230 kV

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 48 project will meet the dynamics requirements of the NERC, Dominion Energy, and PJM reliability standards.

 

The load flow scenario for the analysis was based on the Regional Transmission Expansion Plan (RTEP) 2027 light load case, modified to include applicable projects. Projects in vicinity of Cluster 48 have been dispatched online at maximum power output with electrically close generators dispatched near 50% of the respective units minimum reactive power output.

 

Cluster 48 were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. 126 contingencies were studied, each with a 20 second simulation time period. The studied contingencies included:

  • Steady-state operation (30 seconds)
  • Three-phase faults with normal clearing time
  • Single-phase bus faults with normal clearing time
  • Single-phase faults with stuck breaker
  • Single-phase faults with delayed clearing at remote end
  • Three-phase faults with loss of multiple-circuit tower line.

 

For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all of the fault contingencies tested on the RTEP 2027 light load case:

 

  • Cluster 48 was able to ride through the faults (except for faults where protective action trips a generator(s)),
  • The system with Cluster 48 included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes in Dominion area.
  • Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus)
  • For Dominion area, the final voltages are within the steady-state voltage ranges below per Dominion Energy’s transmission planning criteria.
    • P1 Category Contingencies:
      • 0.93 to 1.05 p.u. for 230, 115, 69 kV facilities
      • 0.93 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.01 to 1.096 p.u. for 500 kV facilities
    • P2, P4, P5, and P7 Category Contingencies:
      • 0.90 to 1.05 p.u. for 230, 115, 69 kV facilities
      • 0.90 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.00 to 1.096 p.u. for 500 kV facilities
  • No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

The transmission system being studied met the evaluation criteria. Below are some notable results.

 

AD2-074 was observed to trip on overvoltage (1.11 p.u. for 1 second and 1.2 p.u. for 0.001 second) for a number of P1 contingencies. Terminal voltage plots showed that the controller for this unit was freezing and not absorbing reactive power within the studied 20 second simulation. After reviewing the dynamic model, it was found that the REGCA model for this unit had reactive power ramp rate parameters Iqrmax and Iqrmin set to 0.02 and -0.02 p.u. respectively. These values are typically set much higher to allow the unit to respond to voltage variations quicker. Therefore, these values were increased to 100 and -100 p.u.. AD2-074 was then able to reduce the voltage post fault which prevented the unit from tripping on the 1.1 p.u. setpoint. The unit was still tripping for the 1.2 p.u. setpoint because of the low time delay (0.001 second). This time delay was increased slightly to 0.0167s. These changes enabled the unit to ride through all faults.

 

Surry units reactive response took over 20 seconds to settle for some contingencies. A longer 40 second test simulation was conducted which demonstrated that the unit settled shortly after 20 seconds shown in Figure 1 below. Slow settling is not a criteria violation and will not affect the results of the study.

 

AD1-151 reactive power was found to have some oscillations post fault that are positively damped with adequate damping ratio. This is not a criteria violation.

 

AB2-134 unit reactive power was found to not settle during the 20 second simulation. The following adjustments were made:

 

  • REPCA CON (J+1) Kp was adjusted to 1
  • REPCA CON (J+2) Ki was adjusted to 5

 

After these adjustments, the reactive power settlement improved but it did not settle within 20 seconds for some contingencies. This is not criteria violation. The developer should be requested to tune the dynamic model.

AB2-190 units reactive power was found to not settle during the 20 second simulation. The following adjustments were made:

  • PLNTBU1 CON (J+1) Kp was adjusted to 1
  • PLNTBU1 CON (J+2) Ki was adjusted to 5
  • PLNTBU1 CON (J+8) Kc was adjusted to 0.04

 

After these adjustments, the reactive power settlement improved but it did not settle within 20 seconds for some contingencies. This is not criteria violation. The developer should be requested to tune the dynamic model.

 

AG1-154 reactive power was observed to not settle during the 20 second simulation. The following adjustments were made:

 

  • REPCA CON (J+8) Kc was adjusted to 0.04

 

This adjustment improved the reactive power settlement for all contingencies.

 

No mitigation was required.

Executive Summary for Stability Cluster

Executive Summary

 

New Service Requests AF1-088 and AF2-008 in PJM Transition Cycle 1, Cluster 52 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 52 projects.

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 52 projects will meet the dynamics requirements of the NERC, AEP and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 52 projects have been dispatched online at maximum power output, with 1.0 voltage at the terminal bus.

 

Cluster 52 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 769 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

       a)       Steady-state operation (20 second run),

       b)       Three-phase faults with normal clearing time (and with unsuccessful high-speed reclosing);

       c)       Single-phase bus faults with normal clearing time,

       d)       Single-phase faults with stuck breaker,

       e)       Three-phase faults with loss of multiple-circuit tower line,

       f)       Three-phase Faults with Normal Clearing Time, Prior Outage of Rockport – Jefferson 765 kV Line,

       g)       Three-phase Faults with Normal Clearing Time, Prior Outage of Sullivan – Rockport 765kV,

       h)       Three-phase Faults with Normal Clearing Time, Prior Outage of Sullivan T-1 765-345 kV Transformer,

       i)       Three-phase Faults with Normal Clearing Time, Prior Outage of Sullivan T-2 765-345 kV Transformer,

       j)       Three-phase Faults with Normal Clearing Time, Prior Outage of Sullivan – Snyder 345 kV Line,

       k)       Three-phase Faults with Normal Clearing Time, Prior Outage of Snyder – Casey 345 kV Line,

       l)       Three-phase Faults with Normal Clearing Time, Prior Outage of Sullivan – Petersburg 345 kV Line,

       m)       Three-phase Faults with Normal Clearing Time, Prior Outage of Sullivan – Eugene 345 kV Line,

       n)       Three-phase Faults with Normal Clearing Time, Prior Outage of Sullivan – Dequine 345 kV Line,

       o)       Three-phase Faults with Normal Clearing Time, Prior Outage of Eugene – Cayuga 345 kV Line,

       p)       Three-phase Faults with Normal Clearing Time, Prior Outage of Sullivan – Dequine/Eugene Double-Circuit 345 kV Line.

 

There are no delayed (Zone 2) clearing faults due to dual primary relays being employed in the AEP 345 kV transmission system.

 

The outages of the circuits (P6 contingencies) were provided to PJM by the Transmission Owner (AEP) as potential generation curtailment scenarios.  PJM has performed analysis of these contingencies in the study. These scenarios may result in operational restrictions to the project under study.

 

For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

One of the Rockport Unit has been taken out when fault has been applied to Rockport to Jefferson 765 kV circuit .

 

For all of the fault contingencies tested on the 2027 peak load case:

       a)       Cluster 52 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

       b)       The system with Cluster 52 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.

       c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d)       No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

       e)       Since no tripping instances (protection schemes) were implemented, compliance with PRC-024 could not be tested. This does not cause instability in the system.

       f)       After the fault clears, the system shows an inverted power transient of up to 1600 MW per pole. This does not cause instability in the system.

       g)       For the scenario A: Prior Outage of Rockport – Jefferson 765 kV Line, one of the units at Rockport unit has been switched off in the basecase. For several contingencies, post fault bus voltage dropped below 0.95 per unit for Petersburg and Dequine substation.

       h)       For the scenario F: Prior Outage of Snyder – Casey 345 kV Line, P6F.55 contingency, leading to the tripping of Petersburg G2 unit.

       i)       For the scenario E, F, G, H, I, J, K: Post fault bus voltage for Rockport bus went above 1.05 for Contingencies P6.12 and P6.50.

 

A sensitivity analysis was conducted to evaluate the dynamic performance of the system following the addition of a new 345/765 kV transformer at the Jefferson substation and a new 345 kV circuit between the Jefferson and Clifty substations. The integration of the transformer did not introduce any system instability.

 

No mitigations were found to be required.

 

Table 1: TC1 Cluster 52 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

52

AF1-088

Original HVDC facility

AEP

1000

1000

1000

Sullivan 345 kV

AF2-008

Additional HVDC unit

AEP

2000

1000

500

Sullivan 345 kV

 

 

Executive Summary for Stability Cluster

Executive Summary

 

New Service Requests AG1-124 and AG1-494 in PJM Transition Cycle 1, Cluster 54 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 54 projects.

 

This analysis is effectively a screening study to determine whether the addition of the cluster 54 projects will meet the dynamics requirements of the NERC, AEP and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 54 projects have been dispatched online at maximum power output, with 1.0 voltage at the terminal bus.

 

Cluster 54 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 111 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

       a)       Steady-state operation (20 second run),

       a)       Three-phase faults with normal clearing time; (and with unsuccessful high-speed reclosing),

       b)       Single-phase bus faults with normal clearing time,

       c)       Single-phase faults with stuck breaker,

       d)       Single-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure,

       e)       Three-phase faults with loss of multiple-circuit tower line; (and with unsuccessful high-speed reclosing).

 

For all simulations, the queue projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all of the fault contingencies tested on the 2027 peak load case:

       a)       Cluster 54 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

       b)       The system with Cluster 54 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.

       c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d)       No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

AG1-124 and AG1-494 meet the 0.95 leading and lagging PF requirement.

The composite short-circuit ratio (CSCR) assessment was performed forinverter-based renewable generation units which are within one (1) substation away AG1-124 and AG1-494. CSCR results are summarized in Table 4 to Table 9 and revealed a minimum and maximum CSCR values of 3.99 for P1.16 and 6.08 for P4.21 & P4.22, respectively.

 

High voltage spikes occurred in the simulations immediately after fault clearing for some of the contingencies studied (i.e. fault where spike is observed]). The voltage spike is a known artifact of the WECC generic renewable models as stated in the WECC Solar Plant Dynamic Model Guidelines: “It should be noted that generic dynamic models for inverter-based generator tend to produce a short-duration (a cycle or shorter) voltage spike at fault inception and clearing. These spikes should be ignored in most cases, as they do not represent the performance of actual hardware. They are simply a consequence of the model’s limited bandwidth, integration time step, and the way current injection models interface with the network solution.” 

 

The IPCMD and IQCMD states in the REGCA1 model of AG1-494 GEN, and AG1-124 GEN showed erratic behavior for some contingencies in which these generators have been disconnected as part of the contingency event. Since the machine is disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

 

Non-queue project AE1-108:

 

In the previous phase (phase 2) of the dynamic simulation analysis for Cluster 54, the relay pick-up time of AE1-108, instance 93882501 (VTGTPAT) was adjusted to 0.25 seconds to prevent tripping under one contingency. For this phase of the study (phase 3) the relay pick-up time for 93882501 (VTGTPAT) of AE1-108 was restored to original setting 0.0 seconds. No trippings of this unit were observed in this study.

 

No mitigations were found to be required.

Table 1: TC1 Cluster 54 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

54

AG1-124

Solar

AEP

90

90

53.01

Gladstone 138 kV

AG1-494

Battery

AEP

50

50

20

Boxwood-Amherst 138 kV

 

 

 

Executive Summary for Stability Cluster

Executive Summary

 

New Service Requests (projects) in PJM Transition Cycle 1, Cluster 55 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 55 projects.

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 55 projects will meet the dynamics requirements of the NERC, American Electric Power (AEP), and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 55 projects have been dispatched online at maximum power output, with approximately unity power factor at the high side of the GSUs, 1.0 pu voltage at the generator terminals, and 1.0 pu voltage at the POI buses.

 

Cluster 55 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 127 contingencies were studied, each with a 20 second simulation time period (with 1.0 second initial run prior to any events). Studied faults included:

a)       Steady-state operation (Category P0);

b)       Three-phase faults with normal clearing time (Category P1);

c)       Single-phase faults with stuck breaker (Category P4);

d)       Single-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure (Category P5).

e)       Three-phase faults with normal clearing for common structure (Category P7).

 

Multiple-circuit tower line faults were identified for this study.

 

High Speed Reclosing (HSR) facilities were found in the vicinity of TC1 Cluster 55 projects.

 

For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all of the fault contingencies tested on the 2027 peak load case:

a)       Cluster 55 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

b)       The system with Cluster 55 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.

c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

d)       No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

AE2-325, AF1-161, AF1-176, AF2-396 and AG1-109 meet the 0.95 leading and lagging PF requirement.

 

Please note that AE2-325 meets its own requested MFO of the uprate portion. However, AE2-325 combined with AD2-020 does not meet the total requested MFO of 152.2 MW. There are about 1.5 MW deficiencies due to the prior queue project AD2-020.

 

AE1-170, AE2-325 and AF2-396 were tripped during the fault application closed to their POIs as a result of fictitious frequency spikes at the frequency relay monitored bus, i.e., inverter terminal bus. Therefore, frequency protection in the model was disabled for faults close to the POI of the projects due to the deficiency of PSSE frequency calculation for inverter-based generation facilities.

 

No other mitigations were found to be required for TC1 Cluster 55.

 

Table 1: TC1 Cluster 55 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

55

AE2-325

Storage

American Electric Power (AEP)

52.2 MW

52.2

MW

31.32

MW

Valley 138 kV substation

AF1-161

Storage

American Electric Power (AEP)

50

MW

50 MW

25 MW

Valley 138 kV

substation

AF1-176

Solar + Storage

American Electric Power (AEP)

300

MW

300 MW

155.684

MW

Corey 138 kV

substation

AF2-396

Solar + Storage

American Electric Power (AEP)

200

MW

200 MW

200 MW

Stinger 138 kV

substation

 

 

Executive Summary for Stability Cluster

Executive Summary

 

New Service Requests (projects) in PJM Transition Cycle 1, Cluster 56 are listed in Table 1 below . This report will cover the dynamic analysis of Cluster 56 projects.

 

This analysis is effectively a screening study to determine whether the addition of the cluster 56 projects will meet the dynamics requirements of the NERC, AEP and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 56 projects have been dispatched online at maximum power output, with 1.0 voltage at the terminal bus.

 

Cluster 56 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 34 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

       a)       Steady-state operation (20 second run),

       b)       Three-phase faults with normal clearing time; (and with unsuccessful high-speed reclosing),

       c)       Single-phase bus faults with normal clearing time,

       d)       Single-phase faults with stuck breaker,

       e)       Three-phase faults with loss of multiple-circuit tower line; (and with unsuccessful high-speed reclosing).

       

There are no delayed (Zone 2) clearing faults due to dual primary relays being employed in the AEP 345 kV transmission system.

 

For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all of the fault contingencies tested on the 2027 peak load case:

       a)       Cluster 56 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

       b)       The system with Cluster 56 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and local modes.

       c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d)       No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

AG1-410 and AG1-411 meet the 0.95 leading and lagging PF requirement.

 

The IPCMD and IQCMD states in the REGCA model of AG1-410 GEN, and AG1-411 GEN showed erratic behavior for some contingencies in which these generators have been disconnected as part of the contingency event. Since the machine is disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

 

The AG1-411 generator terminal voltage settles beyond the acceptable voltage limits after fault clearance during 17 contingencies (P1.02, P1.03, P1.04, P1.08, P1.10, P4.07, P4.08, P4.09, P4.12, P4.13, P4.14, P4.15, P4.16, P4.17, P4.18, P4.19, and P4.20). This violation has been mitigated by adjusting the following parameters in the plant controller (REPCA1) for both AG1-410 and AG1-411: Kc (the reactive current compensation gain) to 0.1 (originally set to 0.0) and VC Flag (droop flag) to 0 (originally set to 1). These changes have been confirmed by the developer and updated in the latest data package received.

 

Fictitious frequency response at AG1-410 generator bus tripped the queue project due to the action of instantaneous over-frequency relay for several contingencies. Therefore, the relay pickup time for frequency relay instance 96542509 was set to 20 seconds to avoid fictitious frequency tripping of the unit.

 

Voltage tripping was observed at the terminals of the AG1-410 generating unit after fault clearing during contingency P1.03. This issue was mitigated by adjusting Ki (Reactive power PI control integral gain) to 1.0 (originally set to 3.0) for AG1-410 in the plant controller REPCA1. The change was confirmed through correspondence with the developer.

 

No mitigations were found to be required.

 

 

Table 1: TC1 Cluster 56 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

56

AG1-410

Solar

AEP

300

300

180

Maddox Creek-RP Mone 345 kV

AG1-411

Storage

AEP

100

100

100

Maddox Creek-RP Mone 345 kV

 

 

Executive Summary for Stability Cluster

Executive Summary

 

New Service Requests (AG1-436, and AG1-447) in PJM Transition Cycle 1, Cluster 58 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 58 projects.

 

This analysis is effectively a screening study to determine whether the addition of the cluster 58 projects will meet the dynamics requirements of the NERC, AEP and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 58 projects have been dispatched online at maximum power output, with 1.0 voltage at the terminal bus.

 

Cluster 58 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 56 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

       a)       Steady-state operation (20 second run),

       a)       Three-phase faults with normal clearing time; (and with unsuccessful high-speed reclosing),

       b)       Single-phase bus faults with normal clearing time,

       c)       Single-phase faults with stuck breaker,

       d)       Three-phase faults with loss of multiple-circuit tower line; (and with unsuccessful high-speed reclosing).

 

There are no delayed (Zone 2) clearing faults due to dual primary relays being employed in the AEP 345 kV transmission system.

 

For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all of the fault contingencies tested on the 2027 peak load case:

       a)       Cluster 58 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

       b)       The system with Cluster 58 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and for local modes.

       c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d)       No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

AG1-447 and AG1-436 meet the 0.95 leading and lagging PF requirement.

 

AG1-436 GEN exhibited slow reactive power recovery within the 20 second simulation window for several contingencies. This issue was mitigated by increasing Kc value in REPCA1 dynamic model from 0 to 0.1. This change has been confirmed by the developer and included in the latest data submission.

 

AG1-447 GEN exhibited slow reactive power recovery within the 20 second simulation window for several contingencies. ETERM of AG1-447 GEN went outside the range of 0.95 pu ~1.05 pu in post fault for several contingencies. These issues were mitigated by changing VCFlag from 1 to 0, increasing Kc from 0 to 0.08, and Ki from 0.5 to 3.5 in the REPCA1 model. These changes have been confirmed by the developer in correspondence.

 

The IPCMD and IQCMD states in the REGCA1 model of AG1-447 GEN, and AG1-436 GEN showed erratic behavior for some contingencies in which these generators have been disconnected as part of the contingency event. Since the machine is disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

 

No mitigations were found to be required.

 

Table 1: TC1 Cluster 58 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

58

AG1-436

Solar

AEP

125

125

75

Olive-University Park 345 kV

AG1-447

Battery

AEP

55

55

55

Olive-University Park 345 kV

 

 

Executive Summary for Stability Cluster

Executive Summary

 

New Service Requests (projects) in PJM Transition Cycle 1, Cluster 59 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 59 projects.

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 59 projects will meet the dynamics requirements of the NERC, American Electric Power (AEP), and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 59 projects have been dispatched online at maximum power output, with approximately unity power factor at the high side of the GSUs, 1.01 pu voltage at the generator terminals, and 1.0 pu voltage at the POI buses.

 

Cluster 59 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 40 contingencies were studied, each with a 20 second simulation time period (with 1.0 second initial run prior to any events). Studied faults included:

       a)       Steady-state operation (Category P0);

       b)       Three-phase faults with normal clearing time (Category P1);

       c)       Single-phase faults with stuck breaker (Category P4);

       d)       Single-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure (Category P5).

       e)       Three-phase faults with normal clearing for common structure (Category P7).

 

Multiple-circuit tower line faults were identified for this study.

 

High Speed Reclosing (HSR) facilities were found in the vicinity of TC1 Cluster 59 projects.

 

For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all of the fault contingencies tested on the 2027 peak load case:

       a)       Cluster 59 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

       b)       The system with Cluster 59 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.

       c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d)       No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

AF2-335 and AF2-370 meet the 0.95 leading and lagging PF requirement.

 

AE1-208 was tripped during the fault application closed to their POIs as a result of fictitious frequency spikes at the frequency relay monitored bus, i.e., inverter terminal bus. Therefore, frequency protection in the model was disabled for faults close to the POI of the projects due to the deficiency of PSSE frequency calculation for inverter-based generation facilities.

 

No mitigations were found to be required for TC1 Cluster 59.

 

 

Table 1: TC1 Cluster 59 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

59

AF2-335

Solar

American Electric Power (AEP)

100 MW

100

MW

60

MW

Delaware- Royerton 138 kV

AF2-370

Storage

American Electric Power (AEP)

100 MW

0

MW

20

MW

Delaware- Royerton 138 kV

 

Executive Summary for Stability Cluster

Executive Summary

 

New Service Requests (projects) in PJM Transition Cycle 1, Cluster 60 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 60 projects.

 

This analysis is effectively a screening study to determine whether the addition of the cluster 60 projects will meet the dynamics requirements of the NERC, AEP and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 60 projects have been dispatched online at maximum power output, with 1.0 voltage at the terminal bus.

 

Cluster 60 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 125 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

       a)       Steady-state operation (20 second run),

       a)       Three-phase faults with normal clearing time; (and with unsuccessful high-speed reclosing),

       b)       Single-phase bus faults with normal clearing time,

       c)       Single-phase faults with stuck breaker,

       d)       Single-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure,

       e)       Three-phase faults with loss of multiple-circuit tower line; (and with unsuccessful high-speed reclosing).

 

For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all of the fault contingencies tested on the 2027 peak load case:

       a)       Cluster 60 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

       b)       The system with Cluster 60 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.

       c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d)       No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

AF2-068 meet the 0.95 leading and lagging PF requirement.

 

AF2-068 GEN exhibited slow reactive power recovery within the 20 second simulation window for several contingencies. This issue did not cause instability in the system and the models can be tuned to achieve a faster reactive power output settlement upon request.

 

The AG1-047 unit tripped by undervoltage relay for one contingency (P5.01). The P5.01 contingency involved a single-phase fault at 80% of line from Jay (AF2-068/AG1-017/AG1-047 POI) 138 kV on AG1-324 POI circuit with delayed (Zone 2) clearing in 60 cycles. As per NERC Standard PRC-024 requirements, the contingency was found to meet the corresponding NERC PRC-024 LVRT criteria. We solved the tripping by updating the relay instance 96203408 from 0.3 second to 1.01 seconds. Additionally, this tripping event was observed in the pre-project study and therefore is not attributed to AF2-068.

 

For P1.06 contingency AE2-318, AE2-318, AD2-163, AD2-163, AC2-195, AC1-102, AC1-074 and 08HLCRT unit have been tripped for over voltage relay settings where clearing time was 0 second for all those relay settings. Added one cycle to original pick up to prevent fictious post-fault overvoltage tripping. It should be noted that generic dynamic models for inverter-based generators tend to produce a short-duration (a cycle or shorter) voltage spike at fault inception or clearing. These spikes can be ignored in most cases as they do not represent the performance of the actual hardware. They are simply a consequence of the model’s limited bandwidth, integration time step, and the way current injection models interface with the network solution.

 

The IPCMD and IQCMD states in the REGCAU model of AF2-068 GEN showed erratic behavior for some contingencies in which these generators have been disconnected as part of the contingency event. Since the machine is disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

 

The CSCR results are summarized in Table 3 through Table 8 and revealed a minimum and maximum CSCR values of 1.99 for P4.32 and 4.14 for P1.02, respectively. 57 contingencies out of 125 contingencies have values less than 3. The lowest value is 1.99 for contingencies P1.12, P1.13, P4.24, P4.25, P4.32 and P5.05.

 

No mitigations were found to be required.

 

Table 1: TC1 Cluster 60 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

60

AF2-068

Solar

AEP

150

150

90

Jay 138 kV

 

 

Executive Summary for Stability Cluster

Executive Summary

 

New Service Requests (projects) in PJM Transition Cycle 1, Cluster 62 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 62 projects.

 

This analysis is effectively a screening study to determine whether the addition of the cluster 62 projects will meet the dynamics requirements of the NERC, AEP and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 62 projects have been dispatched online at maximum power output, with 1.0 voltage at the terminal bus.

 

Cluster 62 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 199 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

       a)       Steady-state operation (20 second run),

       a)       Three-phase faults with normal clearing time; (and with unsuccessful high-speed reclosing),

       b)       Single-phase bus faults with normal clearing time,

       c)       Single-phase faults with stuck breaker,

       d)       Three-phase faults with loss of multiple-circuit tower line; (and with unsuccessful high-speed reclosing).

 

There are no delayed (Zone 2) clearing faults due to dual primary relays being employed in the AEP 345 kV transmission system.

 

For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all of the fault contingencies tested on the 2027 peak load case:

       a)       Cluster 62 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

       b)       The system with Cluster 62 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.

       c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d)       No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

AF2-173, AF2-177, AF2-407, AG1-367 and AG1-375 meet the 0.95 leading and lagging PF requirement.

 

AF2-173 exhibited slow reactive power recovery for several contingencies. Although this issue did not cause instability in the system, the model was tuned to achieve faster reactive power output settlement. This was accomplished by adjusting the Ki parameters in the plant controller (REPCA1) for AF2-173, setting Ki to 0.15 from its original value of 0.5.

 

AF2-177 exhibited slow reactive power recovery for several contingencies. Although this issue did not cause instability in the system, the model was tuned to achieve faster reactive power output settlement. This was accomplished by adjusting the Ki parameters in the plant controller (REPCA1) for AF2-177, setting Ki to 0.15 from its original value of 0.5.

 

AG1-367 exhibited slow reactive power recovery for several contingencies. Although this issue did not cause instability in the system, the model was tuned to achieve faster reactive power output settlement. This was accomplished by adjusting the Kc parameters in the plant controller (REPCA1) for AG1-367, setting Kc to 0.1 from its original value of 0.

 

AG1-375 exhibited slow reactive power recovery for several contingencies. Although this issue did not cause instability in the system, the model was tuned to achieve faster reactive power output settlement. This was accomplished by adjusting the Kc parameters in the plant controller (REPCA1) for AG1-375, setting Kc to 0.1 from its original value of 0.

 

AF2-407 exhibited slow reactive power recovery for several contingencies. Although this issue did not cause instability in the system, the model was tuned to achieve faster reactive power output settlement. This was accomplished by adjusting the Kc, Ki and Kp parameters in the plant controller (REPCA1) for AF2-407, setting Kc to 0.15 from its original value of 0.04, setting Ki to 2 from its original value of 0.5, and setting Kp to 0.5 from its original value of 0.

 

Fictitious frequency response at AF2-407 generator bus tripped the queue project due to the action of instantaneous under-frequency and over-frequency relays when faults were applied at Fall Creek 345 kV (AF2-407 POI). Therefore, the relay pickup times for frequency relay instances 96116513 and 96116516 were set to 20 seconds to avoid fictitious frequency tripping of the unit.

 

A sensitivity analysis was conducted to evaluate the dynamic performance of the system following the addition of a new 345/765 kV transformer at the Jefferson substation and a new 345 kV circuit between the Jefferson and Clifty substations. The integration of the transformer did not introduce any system instability.

 

No mitigations were found to be required.

 

Table 1: TC1 Cluster 62 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

62

AF2-173

Solar

AEP

140

140

84

Desoto 345 kV Substation

AF2-177

Wind

AEP

200

200

26

Sorenson – Desoto #2 345 kV Line

AF2-407

Battery Storage

AEP

300

300

300

Fall Creek 345 kV Substation

AG1-367

Solar

AEP

100

100

60

DeSoto 345 kV Substation

AG1-375

Solar

AEP

100

100

100

Sorenson – Desoto #2 345 kV Line

 

Executive Summary for Stability Cluster

Executive Summary

 

New Service Requests (projects) in PJM Transition Cycle 1, Cluster 63 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 63 projects.

 

This analysis is effectively a screening study to determine whether the addition of the cluster 63 projects will meet the dynamics requirements of the NERC, AEP and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 63 projects have been dispatched online at maximum power output, with 1.0 voltage at the terminal bus.

 

Cluster 63 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 102 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

a)       Steady-state operation (20 second run),

b)       Three-phase faults with normal clearing time; (and with unsuccessful high-speed reclosing),

c)       Single-phase bus faults with normal clearing time,

d)       Single-phase faults with stuck breakers,

e)       Three-phase faults with loss of multiple-circuit tower line; (and with unsuccessful high-speed reclosing).

 

There are no delayed (Zone 2) clearing faults due to dual primary relays being employed in the AEP 345 kV transmission system.

 

For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all of the fault contingencies tested on the 2027 peak load case:

a)       Cluster 63 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

b)       The system with Cluster 63 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and for local modes.

c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

d)       No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

AG1-433 and AF2-388 meet the 0.95 leading and lagging PF requirement.

 

The IPCMD and IQCMD states in the REGCAU model of AG1-433 GEN, and AF2-388 GEN showed erratic behavior for some contingencies in which these generators have been disconnected as part of the contingency event. Since the machine is disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

 

It was observed that the terminal voltage of the AF1-119 and AF2-162 generating units after fault clearing for several contingency goes beyond the limits. This can be eliminated by adjusting the following for both AF1-119 and AF2-162 in the REPCA1 model: Kc to 0.1 (originally set to 0), Ki to 8 (originally set to 50), and Kp to 2 (originally set to 1).

 

The composite short-circuit ratio (CSCR) assessment was performed for inverter-based renewable generation units which are within one (1) substation away from Cluster 63. The CSCR results are summarized in Table 4 through Table 8 and revealed a minimum and maximum CSCR values of 3.17 for P7.13, and 4.99 for P1.09, respectively.

 

No mitigations were found to be required.

 

 

Table 1: TC1 Cluster 63 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

63

AF2-388

Wind

AEP

200 MW

200

35.2

Keystone-Desoto 345 kV

AG1-433

Wind

AEP

100 MW

100

17.6

Keystone-Desoto 345 kV

 

 

Executive Summary for Stability Cluster

Executive Summary

 

New Service Requests AF1-204 and AG1-226 in PJM Transition Cycle 1, Cluster 64 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 64 projects.

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 64 projects will meet the dynamics requirements of the NERC, AEP and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 64 projects have been dispatched online at maximum power output, with 1.0 voltage at the terminal bus.

 

Cluster 64 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 131 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

       a)       Steady-state operation (20 second run),

       a)       Three-phase faults with normal clearing time; (and with unsuccessful high-speed reclosing),

       b)       Single-phase bus faults with normal clearing time,

       c)       Single-phase faults with stuck breakers,

       d)       Three-phase faults with loss of multiple-circuit tower line; (and with unsuccessful high-speed reclosing).

 

There are no delayed (Zone 2) clearing faults due to dual primary relays being employed in the AEP 345 kV transmission system.

 

For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all of the fault contingencies tested on the 2027 peak load case:

       a)       Cluster 64 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

       b)       The system with Cluster 64 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.

       c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d)       No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

AF1-204 and AG1-226 meet the 0.95 leading and lagging PF requirement.

 

AG1-237 exhibited slow reactive power recovery for P7.04 contingency. This issue did not cause instability in the system and the models can be tuned if required to achieve a faster reactive power output settlement.

 

No mitigations were found to be required.

 

Table 1: TC1 Cluster 64 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

64

AF1-204

Wind

AEP

255

255

63.75

Eugene 345 kV

AG1-226

Solar

AEP

450

450

142

Eugene-Dequine 345 kV

 

 

Executive Summary for Stability Cluster

Executive Summary

 

New Service Requests (projects) in PJM Transition Cycle 1, Cluster 65 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 65 projects.

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 65 projects will meet the dynamics requirements of the NERC, AEP and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 65 projects have been dispatched online at maximum power output, with 1.0 voltage at the terminal bus.

 

Cluster 65 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 56 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

       a)       Steady-state operation (20 second run),

       a)       Three-phase faults with normal clearing time; (and with unsuccessful high-speed reclosing),

       b)       Single-phase faults with stuck breaker,

       c)       Three-phase faults with loss of multiple-circuit tower line; (and with unsuccessful high-speed reclosing).

 

No single-phase bus faults were identified for this study.

 

There are no delayed (Zone 2) clearing faults due to dual primary relays being employed in the AEP 345 kV transmission system.

 

For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all of the fault contingencies tested on the 2027 peak load case:

       a)       Cluster 65 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

       b)       The system with Cluster 65 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.

       c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d)       No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

AG1-297 meet the 0.95 leading and lagging PF requirement.The composite short-circuit ratio (CSCR) assessment was performed for inverter-based renewable generation units which are within one (1) substation away of Cluster 65. These nearby generating units are listed in Table 3. The CSCR results are summarized in Table 4 through Table 7 and revealed a minimum and maximum CSCR values of 5.354 for P0.01 and 3.964 for P7.02, respectively.

 

The IPCMD and IQCMD states in the REGCAU model of AG1-297 GEN10.6 showed erratic behavior for some contingencies in which these generators have been disconnected as part of the contingency event. Since the machine is disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

 

The rotor angle of East Bend Unit 2 and Lawrenceburg 2A did not achieve a flat response within the 20 second simulation window for several contingencies. This issue did not cause instability in the system. The selected contingencies were run for 35 seconds, and the rotor angle of East Bend Unit 2 and Lawrenceburg 2A achieved a flat response at the end of the 35 second simulation time-period. A pre-project test was performed for the contingencies where AG1-297 was eliminated from the case and the same angle settling issue was still observed from East Bend Unit 2 and Lawrenceburg 2A units.

 

No mitigations were found to be required.

 

Table 1: TC1 Cluster 65 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

65

AG1-297

Battery Storage

AEP

300

304.3244

304.3244

Hanna (IP&L) – Tanner’s Creek 345 kV

 

Executive Summary for Stability Cluster

PSSE Dynamic Study Analysis

 

Executive Summary

 

New Service Request projects in PJM Transition Cycle 1, Cluster 69 are listed in Table 1 below. The report covers the dynamic analysis of Cluster 69 projects.

 

The analysis is effectively a screening study to determine whether the addition of the Cluster 69 projects will meet the dynamics requirements of the NERC, First Energy (FE), and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 69 projects have been dispatched online at maximum power output, with approximately unity power factor at the high side of the GSUs, 1.02 pu voltage at the generator terminals, and 1.01 pu voltage at the AF2-010 POI bus, and 1.01 pu voltage at the AG1-548 POI bus.

 

Cluster 69 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 81 contingencies were studied, each with a 20 second simulation time period (with 1.0 second initial run prior to any events). Studied faults included:

a)  Steady-state operation (Category P0);

b)  Three-phase faults with normal clearing time (Category P1);

c)  Single-phase faults with stuck breaker (Category P4);

d)  Single phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure (Category P5).

No multiple-circuit tower line faults were identified for this study.

High Speed Reclosing (HSR) facilities were found in the vicinity of TC1 Cluster 69 projects.

 

For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance. For 75 out of 81 fault contingencies tested on the 2027 peak load case:

a)  Cluster 69 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

b)  The system with Cluster 69 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for inter-area modes and 4% for local modes.

c)  Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

d)  No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

AF2-010 was tripped during the fault application closed to their POIs as a result of fictitious frequency spikes at the frequency relay monitored bus, i.e., inverter terminal bus. Therefore, frequency protection in the model was disabled for faults close to the POI of the projects due to the deficiency of PSSE frequency calculation for inverter-based generation facilities. No more tripping issue of the AF2-010 was observed.

 

For P1.27, P4.12, P4.13, P4.14, P4.15, and P5.13, after losing 115 kV circuit from Erie South to AG1-548 POI, the results show undamped oscillations indicating system instability. The CSCR assessment shows under these fault contingencies, the CSCR values would be below 1.5 which could be considered very weak grid conditions. The PSSE dynamic analysis shows that system reinforcement is needed to resolve the undamped oscillations. Since the PSSE generic model might be not accurate at very low SC levels, an electromagnetic transient analysis with a more detailed model is required. An electromagnetic transient study was performed in TC1 Phase III.

 

PSCAD Electromagnetic Study Analysis

 

Executive Summary

 

Electromagnetic transient model quality tests were performed for the 150 MW French Creek Solar and Storage project and the Union Solar project. PSCAD models were used to perform testing and analysis to ensure compliance with PJM requirements.

 

The French Creek Solar and Storage project located in Erie County, Pennsylvania was modeled with forty-two (42) Sungrow SG4400UD-US inverters and forty-two (42) step-up transformers for the photovoltaic generation portion; eight (8) Sungrow SC4400UD-US inverters and eight (8) step-up transformers for the battery energy storage system (BESS) portion; two (2) collection systems; one (1) main power transformer; and a 1-mile (5280 ft) transmission line connected to a 115 kV tap on the Erie South to Union City transmission line.

 

The Union Solar project located in Erie County, Pennsylvania was modeled with nineteen (19) SMA SC 4600-UP inverters and nineteen (19) step-up transformers, one (1) collection system, one (1) main power transformer, and a 0.02-mile transmission line connected to the 115 kV tap on Union City to Titusville transmission line.

 

Model quality tests for the French Creek Solar and Storage project, and the Union Solar project were performed for the following scenarios:

 

•  Flat Start Test Voltage Step-Down

•  Voltage Step-Up

•  Frequency Step-Down, No Headroom

•  Frequency Step-Up/Down, Headroom (@ 80% Pmax)

•  HVRT Leading (Legacy Curve)

•  HVRT Lagging (Legacy Curve)

•  LVRT Leading (Legacy Curve)

•  LVRT Lagging (Legacy Curve)

•  Voltage Ride Through (VRT)

•  Phase Angle Step-Down

•  Phase Angle Step-Up

•  System Strength Test

 

The French Creek Solar and Storage project PSCAD model, and the Union Solar project PSCAD model, with fine tuning, both passed all the model quality tests. The undamped oscillations identified in the PSSE dynamic study are not observed in the PSCAD study with a more detailed model. It is therefore concluded that undamped oscillations under P1.27, P4.12, P4.13, P4.14, P4.15, and P5.13 can be resolved with fine tuning of the plant.

 

Table 1: TC1 Cluster 69 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

69

AF2-010

Solar

FirstEnergy (Mid-Atlantic Interstate Transmission, LLC - Penelec Zone)

77 MW

77 MW

46 MW

Union City –Titusville 115 kV

69

AG1-548

Solar + Storage

FirstEnergy (Mid-Atlantic Interstate Transmission, LLC - Penelec Zone)

150 MW

150 MW

45 MW

Erie South -Union City 115 kV

 

Executive Summary for Stability Cluster

Executive Summary

 

New Service Request project in PJM Transition Cycle 1, Cluster 70 is listed in Table 1 below. The report covers the dynamic analysis of the Cluster 70 project.

 

The analysis is effectively a screening study to determine whether the addition of the Cluster 70 project meets the dynamics requirements of the NERC, First Energy (FE), and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include the applicable project. The Cluster 70 project was dispatched online at maximum power output, with approximately unity power factor at the high side of the GSUs, 1.02 pu voltage at the generator terminals, and 1.02 pu voltage at the POI buses.

The Cluster 70 project was tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 60 contingencies were studied, each with a 20 second simulation time period (with 1.0 second initial run prior to any events). Studied faults included:

a) Steady-state operation (Category P0);

b) Three-phase faults with normal clearing time (Category P1);

c) Single-phase faults with stuck breaker (Category P4);

d) Single phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure (Category P5).

e) Single phase to ground faults with normal clearing for common structure (Category P7).

Multiple-circuit tower line faults were identified for this study.

High Speed Reclosing (HSR) facilities were found in the vicinity of the TC1 Cluster 70 project.

 

For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance. For 158 out of 160 fault contingencies tested on the 2027 peak load case:

a) The Cluster 70 project was able to ride through the faults (except for faults where protective action trips a generator(s)),

b) The system with the Cluster 70 project included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for inter-area modes and 4% for local modes.

c) Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

d) No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

No mitigation is required for the TC1 Cluster 70 project.

Table 1: TC1 Cluster 70 Project

Cluster

Project

Fuel Type

Transmission Owner

MFO (MW)

MWE (MW)

MWC (MW)

Point of Interconnection

70

AF2-050

Solar

FirstEnergy (FE) transmission system, Pennsylvania Electric Co (PENELEC) zone

150

50

30

Johnstown –Bear Rock 230 kV

 

 

Executive Summary for Stability Cluster

Executive Summary

 

New Service Request projects in PJM Transition Cycle 1, Cluster 71 are listed in Table 1 below. The report covers the dynamic analysis of the Cluster 71 projects.

The analysis is effectively a screening study to determine whether the addition of the Cluster 71 projects meet the dynamics requirements of the NERC, First Energy (FE), and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 71 projects were dispatched online at maximum power output, with approximately unity power factor at the high side of the GSUs, 1.02 pu voltage at the generator terminals, and 1.02 pu voltage at the POI bus for AG1-090, AG1-377, and AG1-378.

 

Cluster 71 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 101 contingencies were studied, each with a 20 second simulation time period (with 1.0 second initial run prior to any events). Studied faults included:

a) Steady-state operation (Category P0);

b) Three-phase faults with normal clearing time (Category P1);

c) Single-phase faults with stuck breaker (Category P4);

d) Single phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure (Category P5).

No multiple-circuit tower line faults were identified for this study.

High Speed Reclosing (HSR) facilities were found in the vicinity of TC1 Cluster 71 projects.

 

For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance. For all of the fault contingencies tested on the 2027 peak load case:

a) Cluster 71 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

b) The system with Cluster 71 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.

c) Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

d) No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

No mitigation is required for TC1 Cluster 71. 

 

 Table 1: TC1 Cluster 71 Projects 

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

71

AG1-090

Solar + Storage

FirstEnergy (FE) Transmission System, Pennsylvania Electric Company (PENELEC) zone

95 MW

95

MW

30

MW

Philipsburg 115 kV Substation

AG1-377

Solar

FirstEnergy (FE) Transmission System, Pennsylvania Electric Company (PENELEC) zone

20

MW

20 MW

6

MW

Philipsburg 115 kV Substation

AG1-378

Solar

FirstEnergy (FE) Transmission System, Pennsylvania Electric Company (PENELEC) zone

20

MW

20 MW

6

MW

Philipsburg 115 kV Substation

 

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 1, Cluster 72 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 72 projects.

This analysis is effectively a screening study to determine whether the addition of the Cluster 72 projects will meet the dynamics requirements of the NERC, Atlantic City Electric Company (AEC), and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 72 projects have been dispatched online at maximum power output, with approximately unity power factor at the high side of the GSUs, 1.02 pu voltage at the generator terminals, 1.03 pu voltage at the POI bus for AF1-238, and 1.04 pu voltage at the POI bus for AF2-025.

Cluster 72 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 136 contingencies were studied, each with a 20 second simulation time period (with 1.0 second initial run prior to any events). Studied faults included:

a)       Steady-state operation (Category P0);

b)       Three-phase faults with normal clearing time (Category P1);

c)       Single-phase faults with stuck breaker (Category P4);

d)       Single phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure (Category P5).

e)       Single phase to ground faults with normal clearing for common structure (Category P7).

No High Speed Reclosing (HSR) facilities were found in the vicinity of TC1 Cluster 72 projects.

For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the 2027 peak load case:

a)       Cluster 72 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

b)       The system with Cluster 72 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.

c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

d)       No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

AF1-238 and AF2-025 meet the 0.95 leading and lagging PF requirement.

High voltage spikes occurred in the simulations immediately after fault clearing for some of the contingencies studied. The voltage spike is a known artifact of the WECC generic renewable models as stated in the WECC Solar Plant Dynamic Model Guidelines: “It should be noted that generic dynamic models for inverter-based generator tend to produce a short-duration (a cycle or shorter) voltage spike at fault inception and clearing. These spikes should be ignored in most cases, as they do not represent the performance of actual hardware. They are simply a consequence of the model’s limited bandwidth, integration time step, and the way current injection models interface with the network solution. (source: https://www.esig.energy/wiki-main-page/dynamic-simulation-of-pv-plants/)

No mitigations were found to be required for TC1 Cluster 72.

Table 1: TC1 Cluster 72 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

72

AF1-238

Storage

Atlantic City Electric Company (AEC)

50 MW

50 MW

20 MW

Sherman Ave - West Vineland 69 kV

AF2-025

Storage

Atlantic City Electric Company (AEC)

20 MW

20 MW

8

MW

Ontario 69 kV

 

Executive Summary for Stability Cluster

Executive Summary

 

The New Service Request project in PJM Transition Cycle 1, Cluster 74 is listed in Table 1 below. The report covers the dynamic analysis of the Cluster 74 project.

 

The analysis is effectively a screening study to determine whether the addition of the Cluster 74 project meets the dynamics requirements of the NERC, First Energy (FE), and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include the applicable project. The Cluster 74 project was dispatched online at maximum power output, with approximately unity power factor at the high side of the GSUs, 1.0 pu voltage at the generator terminals, and 1.01 pu voltage at the POI bus.

 

The Cluster 74 project was tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 87 contingencies were studied, each with a 20 second simulation time period (with 1.0 second initial run prior to any events). Studied faults included:

a) Steady-state operation (Category P0);

b) Three-phase faults with normal clearing time (Category P1);

c) Single-phase faults with stuck breaker (Category P4);

d) Single phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure (Category P5).

e) Single phase faults with normal clearing on common structure (Category P7)

High Speed Reclosing (HSR) facilities were found in the vicinity of the TC1 Cluster 74 project.

For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the 2027 peak load case:

a) The Cluster 74 project is able to ride through the faults (except for faults where protective action trips a generator(s)),

b) The system with the Cluster 74 project included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.

c) Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

d) No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

AF2-126 was tripped during the fault application close to the POI as a result of fictitious frequency spikes at the frequency relay monitored bus, i.e., inverter terminal bus. Therefore, frequency protection in the model was disabled for faults close to the POI of the projects due to the deficiency of PSSE frequency calculation for inverter-based generation facilities.

No mitigation is required for TC1 Cluster 74.

 

Table 1: TC1 Cluster 74 Project 

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

74

AF2-126

Solar

FirstEnergy (FE) transmission system, West Penn Power (“WPP” in ATSI) zone

62 MW

12 MW

8 MW

Weston substation

69 kV

 

 

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 1, Cluster 75 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 75 projects.

This analysis is effectively a screening study to determine whether the addition of the Cluster 75 projects will meet the dynamics requirements of the NERC, Exelon/DPL, and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. Cluster 75 projects have been dispatched online at maximum power output, with approximately unity power factor at the high side of the GSUs, 1.02 pu voltage at the generator terminals, and 1.02 pu voltage at the POI buses.

Cluster 75 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 41 contingencies were studied, each with a 20 second simulation time period (with 1.0 second initial run prior to any events). Studied faults included:

  1. Steady-state operation (Category P0);
  2. Three-phase faults with normal clearing time (Category P1);
  3. Single-phase faults with stuck breaker (Category P4);
  4. Single phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure (Category P5).

No relevant multiple-circuit tower line faults were identified for this study.

High Speed Reclosing (HSR) facilities were found in the vicinity of TC1 Cluster 75 projects.

For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For 36 out of 41 fault contingencies tested on the 2027 peak load case:

  1. Cluster 75 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  2. The system with Cluster 75 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
  3. Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
  4. No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

AF2-358 and AG1-450 meet the 0.95 leading and lagging PF requirement.

For P1.09, P4.11, P4.12, P4.13, and P5.02, when faults are close to Vienna 69 kV while losing circuit 6709 from Vienna to AF2-358 POI, the results show undamped oscillations indicating system instability. The CSCR assessment shows under these fault contingencies, the CSCR values would be below 1.15 which could be considered very weak grid conditions. System reinforcement would be needed. Also, the generic model might be not accurate at very low SC levels, so detailed models performed under EMT simulation would be required. Thus, mitigations were found to be required for TC1 Cluster 75. PSCAD/EMT analysis will also be performed.

 

Table 1: TC1 Cluster 75 Projects

 

 

 

 

 

 

 

Cluster

Project

Fuel Type

Transmission Owner

MFO (MW)

MWE

(MW)

MWC

(MW)

Point of Interconnection

75

AF2-358

Solar

DPL

100

100

60

Airey-Vienna 69 kV

AG1-450

Storage

DPL

125

25

25

Airey-Vienna 69 kV

 

 

PSCAD Analysis Executive Summary:

Introduction

This Weak Grid Assessment evaluates two projects from PJM Transition Cycle 1 (TC1) Cluster 75 for risk of voltage instability due to weak grid conditions in an EMT simulation environment. The two projects, AF2-358 and AG1-450, were identified in the Cluster Study [1] as having risk of undamped oscillations during a contingency condition and indicating system instability after dynamic simulation analysis in PSS/E. System reinforcement as a potential mitigation was recommended along with evaluation using detailed models in an EMT simulation.

This assessment, completed by INS Engineering, aims to evaluate the risk of weak grid instability and the impact of mitigations such as system reinforcement as concluded in the Cluster Study. A summary description of each project is listed below:

Table 1. Summary Description of TC1 Cluster 75 Projects

 

 

 

 

Project Name

Project Type

Project Size (MW)

POI

POI Bus Number

AF2-358 Choptank Solar

PV

100

Airey-Vienna 69 kV

960670

AG1-450 Choptank BESS

BESS

125

Airey-Vienna 69 kV

960670

 

Conclusion:

First, the individual project PSCAD models were evaluated for data consistency and model performance

as part of the standard Model Quality Test in [2], with model updates being made where needed. INS confirmed that the PSCAD models were set up properly and satisfied the requirements of PJM. After satisfactory configuration and performance of the individual project models were obtained, the models were integrated into a translated reduced network in PSCAD to create an overall detailed system model.

 

A representative contingency case from the Cluster Study, considered effectively the worst case in terms of risk for weak grid instability, was then simulated in the PSCAD detailed system model. For Cluster 75, the following contingency case was chosen.

  • Fault ID P1.03: 3LG Fault at AF2-358 POI 69 kV on Vienna circuit (6709) resulting in loss of AF2-358 POI - Vienna circuit (6709). Projects are operating at rated power pre-fault. [1]

Simulation results in PSCAD are summarized below. It can be observed that the base case with the PSCAD detailed system model results in weak grid oscillations similar to the Cluster Study and the projects are unable to recover to pre-fault conditions after the fault clears.

Table 2. Summary of cases tested in PSCAD system study

 

 

 

Case ID

Fault Description

Cluster Study Result [1]

PSCAD Study Result

Case 1.0

P1.03, Consider as the base case

Unstable

Unstable

Case 1.1a

P1.03, modified PPC tuning, P=1.0pu, Unity PF

-

Stable

Case 1.1b

P1.03, modified PPC tuning, P=1.0pu, Lag PF

-

Stable

Case 1.1c

P1.03, modified PPC tuning, P=1.0pu, Lead PF

-

Stable*

Case 1.2a

P1.03, modified PPC tuning, P=0.75pu, Unity PF

-

Stable

Case 1.2b

P1.03, modified PPC tuning, P=0.75pu, Lag PF

-

Stable

Case 1.2c

P1.03, modified PPC tuning, P=0.75pu, Lead PF

-

Stable

Case 1.3a

P1.03, modified PPC tuning, P=0.5pu, Unity PF

-

Stable

Case 1.3b

P1.03, modified PPC tuning, P=0.5pu, Lag PF

-

Stable

Case 1.3c

P1.03, modified PPC tuning, P=0.5pu, Lead PF

-

Stable

* Only able to recover to pre-fault conditions with additional 1.5MVAr cap bank, either on 69kV POI or 34.5kV side

 

PPC parameters were tuned to be more appropriate for weak grid conditions using a generic PPC model, and this configuration was evaluated in base case P1.03, resulting in stable recovery. Nine sensitivity cases were then tested to verify robustness of the modified tuning, with all showing stable recovery except for Case 1.1c. For Case 1.1c, it was observed that although oscillations were not present, low system voltage related to the new steady-state operating point prevented full recovery to pre-fault conditions. As a result, adding a small capacitor bank of 1.5 MVAr was evaluated. It was observed that the additional reactive power support from the capacitor bank was sufficient to increase the system voltage and allow the plant to recover stably.

 

Based on the simulation results described above, it is recommended that the PPC for the Cluster 75 projects is tuned for a similar response as the modified generic PPC model tuning in this study. The full set of parameter values is listed in [2]. In addition, a small capacitor bank rated at least 1.5 MVAr and connected at either 69kV POI or on the 34.5kV side can be considered to provide additional reactive power support under contingency conditions such as P1.03.

 

Executive Summary for Stability Cluster

Executive Summary

New Service Request AF2-365 in PJM Transition Cycle 1 is listed in Table 1 below. This report will cover the dynamic analysis of AF2-365 project.

This analysis is effectively a screening study to determine whether the addition of the AF2-365 project will meet the dynamics requirements of the NERC, EKPC and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. The AF2-365 project has been dispatched online at maximum power output and the voltage schedule set to achieve near unity power factor at the high side of the main transformer.

The AF2-365 project was tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 47 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

       a) Steady-state operation (20 second run);

       b) Three-phase faults with normal clearing time;

       c) Three-phase bus faults with normal clearing time;

       d) Three-phase to ground faults with three-phase delayed clearing due to a stuck breaker;

       e)Three-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure;

       f) Three-phase faults with loss of multiple-circuit tower line.

No relevant high speed reclosing (HSR) contingencies were identified for this study.

For all simulations, the AF2-365 project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the 2027 peak load case:

       a) AF2-365 project was able to ride through the faults (except for faults where protective action trips a generator(s)),

       b) The system with AF2-365 project included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3%.

       c) Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d) No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

AF2-365 meets the 0.95 leading and lagging PF requirement.

The IPCMD and IQCMD states in the REGCA1 model of AF2-365 GEN showed erratic behavior for some contingencies in which these generators have been disconnected as part of the contingency event. Since the machine is disconnected and no active or reactive power is injected into the system these plots are ignored.

 

No mitigations were found to be required.

Table 1: TC1 AF2-365 Project

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

AF2-365

Solar

EKPC

50

50

30

Munfordville KU Tap - Horse Cave Jct 69 kV

 

 

 

 

Executive Summary for Stability Cluster

Executive Summary

 

New Service Request (project) AG1-341 in PJM Transition Cycle 1 is listed in Table 1 below. This report will cover the dynamic analysis of AG1-341.

 

This analysis is effectively a screening study to determine whether the addition of the AG1-341 will meet the dynamics requirements of the NERC, EKPC and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. AG1-341 have been dispatched online at maximum output and the voltage schedule set to achieve near unity power factor at the high side of the main transformer.

 

AG1-341 was tested for compliance with NERC, EKPC, PJM, and other applicable criteria. Steady-state condition and 233 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

       a)       Steady-state operation (20 second run);

       b)       Three-phase faults with normal clearing time;

       c)       Three-phase bus faults with normal clearing time;

       d)       Three-phase to ground faults with three-phase delayed clearing due to a stuck breaker;

       e)       Three-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure;

       f)       Three-phase faults with loss of multiple-circuit tower line.

 

No relevant high speed reclosing (HSR) contingencies were identified for this study.

 

For all simulations, the AG1-341 project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all of the fault contingencies tested on the 2027 peak load case:

       a)       AG1-341 project was able to ride through the faults (except for faults where protective action trips a generator(s)).

       b)       The system with AG1-341 project included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3%.

       c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d)       No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

AG1-341 meets the 0.95 leading and lagging PF requirement.

 

The IPCMD and IQCMD states in the REGCA1 model of AG1-341 GEN, AF1-050 GEN and AE2-071 GEN showed erratic behavior for some contingencies in which these generators have been disconnected as part of the contingency event. Since the machine is disconnected and no active or reactive power is injected into the system these plots are ignored.

 

AG1-341, AF1-050 and AE2-071 exhibited slow reactive power recovery within the 20 second simulation window for several contingencies. This issue did not cause instability in the system.

 

No mitigations were found to be required.

 

Table 1: TC1 AG1-341 Project

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

AG1-341

Solar/Storage

EKPC

106

106

63.6

Summer Shade 161 kV

 

Executive Summary for Stability Cluster

Executive Summary

New Service Request (project) AG1-320 in PJM Transition Cycle 1 is listed in Table 1 below. This report will cover the dynamic analysis of AG1-320.

This analysis is effectively a screening study to determine whether the addition of AG1-320 will meet the dynamics requirements of the NERC, EKPC and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. AG1-320 has been dispatched online at maximum power output and the voltage schedule set to achieve near unity power factor at the high side of the main transformer.

AG1-320 was tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 132 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

       a) Steady-state operation (20 second run);

       b) Three-phase faults with normal clearing time;

       c) Single-phase bus faults with normal clearing time;

       d) Single-phase faults with stuck breaker;

       e) Single-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure;

       f) Single-phase faults with loss of multiple-circuit tower line.

No relevant high speed reclosing (HSR) contingencies were identified for this study.

For all simulations, AG1-320 along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the 2027 peak load case:

       a) AG1-320 was able to ride through the faults (except for faults where protective action trips a generator(s)),

       b) The system with AG1-320 included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3%.

       c) Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d) No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

AG1-320 meets the 0.95 leading and lagging PF requirement.

The IPCMD and IQCMD states in the REGCA1 model of AG1-320 GEN showed erratic behavior for some contingencies in which these generators have been disconnected as part of the contingency event. Since the machine is disconnected and no active or reactive power is injected into the system, these plots are ignored.

 

AF1-050 exhibited slow reactive power recovery within the 20 second simulation window for several contingencies. This issue did not cause instability in the system.

No mitigations were found to be required.

 

Table 1: TC1 AG1-320 Project

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

AG1-320

Solar

EKPC

82

82

54.8

Glendale – Stephensburg 69 kV

 

 

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (projects) AG1-070 and AG1-071 in PJM Transition Cycle 1 are listed in Table 1 below. This report will cover the dynamic analysis of AG1-070 and AG1-071 projects.

This analysis is effectively a screening study to determine whether the addition of the AG1-071 and AG1-071 projects will meet the dynamics requirements of the NERC, EKPC and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. AG1-070 and AG1-071 have been dispatched online at maximum power output and the voltage schedule set to achieve near unity power factor at the high side of the main transformer.

AG1-070 and AG1-071 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 121 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

       a) Steady-state operation (20 second run);

       b) Three-phase faults with normal clearing time;

       c) Single-phase bus faults with normal clearing time;

       d) Single-phase faults with stuck breaker;

       e) Single-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure;

       f) Single-phase faults with loss of multiple-circuit tower line.

No relevant high speed reclosing (HSR) contingencies were identified for this study.

For all simulations, the AG1-070 and AG1-071 projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the 2027 peak load case:

       a) AG1-070 and AG1-071 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

       b) The system with AG1-070 and AG1-071 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3%.

       c) Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d) No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

AG1-070 and AG1-071 meet the 0.95 leading and lagging PF requirement.

The IPCMD and IQCMD states in the REGCA1 model of AG1-070 GEN and AG1-071 GEN showed erratic behavior for some contingencies in which these generators have been disconnected as part of the contingency event. Since the machine is disconnected and no active or reactive power is injected into the system, these plots are ignored.

No mitigations were found to be required.

Table 1: TC1 AG1-070/AG1-071 Projects

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

AG1-070

Solar

EKPC

45

45

32.7

Bon Ayr 69 kV

AG1-071

Solar

EKPC

55

55

37.5

Bon Ayr 69 kV

 

 

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (projects) AG1-405 and AG1-406 in PJM Transition Cycle 1 are listed in Table 1 below. This report will cover the dynamic analysis of AG1-405 and AG1-406.

This analysis is effectively a screening study to determine whether the addition of the AG1-405 and AG1-406 projects will meet the dynamics requirements of the NERC, EKPC and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. AG1-405 and AG1-406 projects have been dispatched online at maximum power output and the voltage schedule set to achieve near unity power factor at the high side of the main transformer.

AG1-405 and AG1-406 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 240 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

       a) Steady-state operation (20 second run);

       b) Three-phase faults with normal clearing time;

       c) Single-phase bus faults with normal clearing time;

       d) Single-phase faults with stuck breaker;

       e) Single-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure;

       f) Single-phase faults with loss of multiple-circuit tower line.

No relevant high speed reclosing (HSR) contingencies were identified for this study.

For all simulations, AG1-405 and AG1-406 projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the 2027 peak load case:

       a) AG1-405 and AG1-406 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

       b) The system with AG1-405 and AG1-406 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3%.

       c) Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d) No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

AG1-405 and AG1-406 projects meet the 0.95 leading and lagging PF requirement. Initial reactive power capability assessment showed the AG1-405/AG1-406 facility had a 7 MVAR reactive power deficiency due to reactive power losses between inverter terminals and the high side of the main transformer. The developer confirmed plans to install a 7 MVAR capacitor bank to resolve the deficiency (RE_ AG1-405 Model Inquiry.msg).

AG1-405 and AG1-406 exhibited slow reactive power recovery for several contingencies. This issue did not cause any instabilities in the AC system. However, to reduce reactive power settling time and to avoid potential interactions with the other plants in the AC system, a 5% reactive power droop was introduced to the Q/V controller in the power plant controller model (REPCA).

No mitigations were found to be required

 

Table 1: AG1-405/AG1-406 Projects

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

AG1-405

Solar

EKPC

57

57

34.2

Walnut Grove – Asahi 69 kV

AG1-406

BESS

EKPC

22

22

22

Walnut Grove – Asahi 69 kV

 

Executive Summary for Stability Cluster

Executive Summary

 

New Service Request (project) in PJM Transition Cycle 1, AF2-376 is listed in Table 1 below. This report will cover the dynamic analysis of AF2-376 project.

 

This analysis is effectively a screening study to determine whether the addition of the AF2-376 project will meet the dynamics requirements of the NERC, AEP and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2027 summer peak load case, modified to include applicable projects. AF2-376 project has been dispatched online at maximum power output, with 1.0 voltage at the terminal bus.

 

AF2-376 project was tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 92 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

       a)       Steady-state operation (20 second run),

       b)       Three-phase faults with normal clearing time,

       c)       Single-phase bus faults with normal clearing time,

       d)       Single-phase faults with stuck breaker,

       e)       Single-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure,

       f)       Three-phase faults with loss of multiple-circuit tower line.

 

For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all of the fault contingencies tested on the 2027 peak load case:

       a)       AF2-376 project was able to ride through the faults (except for faults where protective action trips a generator(s)),

       b)       The system with AF2-376 project included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.

       c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d)       No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

AF2-376 meet the 0.95 leading and lagging PF requirement.

 

The AE2-298 unit tripped by an undervoltage relay for one contingency (P1.09). Contingency P1.09 involved a three-phase fault at Haviland 345 kV clearing in 6 cycles. As per NERC Standard PRC-024 requirements, this relay settings were found to meet the corresponding NERC PRC-024 LVRT. Additionally, this tripping event was observed in the AE2-298 Dynamic Study and with the pre-AF2-376 scenario, therefore is not attributed to AF2-376.

 

For contingencies P5.01, P5.02 and P5.04, it was observed that active power of Timber switch unit was not recovered to pre fault value. This will not cause any instability in the system and can be mitigated upon request.

 

The IPCMD and IQCMD states in the REGCAU model of AF2-376 GEN showed erratic behavior for some contingencies in which these generators have been disconnected as part of the contingency event. Since the machine is disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

 

The CSCR results are summarized in Table 4 through Table 9 and revealed a minimum and maximum CSCR values of 1.85  for P4.25 and 4.91 for P1.04, respectively.

 

No mitigations were found to be required.

 

Table 1: TC1 AF2-376 Project

Queue

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

AF2-376

AF2-376

BESS

AEP

50.0 MW

50.0 MW

20.0

MW

Timber Switch 138 kV

 

 

Shared POIs

At PJM's discretion, New Service Requests in a Cycle at the same Point of Interconnection may be aggregated for the purposes of Phase I, Phase II, and Phase III System Impact Studies, in accordance with PJM Open Access Transmission Tariff, Part VIII, Subpart C, section 404.2.a.iii.

List of Shared POIs Studied in Transition Cycle 1 Phase III
Shared POI Name New Service Requests Aggregated
AE1-155 115 kV - Dominion AF2-120, AG1-536
AE2-185 69 kV - Dominion AE2-185, AF2-404
AE2-187 69 kV - Dominion AE2-187, AF2-403
AF1-294 115 kV - Dominion AF1-294, AF2-115, AG1-021
AF2-046 115 kV - Dominion AF2-046, AG1-008
AG1-146 115 kV - Dominion AG1-146, AG1-147
Ahoskie 34.5 kV - Dominion AG1-082, AG1-083
Airey-Vienna 69kV - DPL AF2-358, AG1-450
Belvidere - Marengo 138kV - ComEd AE2-321, AF1-048
CVOW Harpers 230 kV - Dominion AF1-123, AF1-124, AF1-125
Cordova 345 kV (ComEd) AG1-462, AG1-553
Delaware - Royerton 138kV - AEP AF2-335, AF2-370
Desoto 345kV - AEP AF2-173, AG1-367
Katydid Road 345kV (ComEd) AF2-226, AF2-319
Keystone - Desoto 345kV - AEP AF2-388, AG1-433
Kincaid Pana Tap - ComEd AE2-261, AG1-460
Lone Pine 115 kV - Dominion AG1-166, AG1-167, AG1-168, AG1-169, AG1-170
Maddox Creek - RP Mone 345kV - AEP AG1-410, AG1-411
McLean 345kV (ComEd) AE2-223, AF2-225
Nelson - Lee County 345kV - ComEd AF1-280, AF2-182
Nelson-Dixon 138kV - ComEd AF2-392, AF2-393, AF2-394
Nelson-Electric Junction 345kV - ComEd AF2-041, AF2-199, AF2-200
New AG1-405/406 69kV swyd (EKPC) AG1-405, AG1-406
Olive - University Park 345kV - AEP AG1-436, AG1-447
Philipsburg 115kV yard - Penelec AG1-090, AG1-377, AG1-378
Sandwich - Plano 138kV - ComEd AE2-341, AF1-030, AF2-329
Sorenson - Desoto 345kV - AEP AF2-177, AG1-375
Sullivan 345kV - AEP AF1-088, AF2-008
Valley 138kV - AEP AF1-161, AG1-109

CIR Claims From Deactivated Generators

The following Transition Cycle 1 Phase III projects intend to claim and transfer CIRs from deactivated capacity generation resources. PJM performed a reliability analysis of the impacts to the system capability for the proposed transfers of CIRs from the deactivated generation resources.

List of Transition Cycle 1 Phase III Projects Claiming CIRs from Deactivated Generators
Project Status Deactivated Generators
AF1-128 Active
Unit Name Status CIR Claimed POI Transfer
Chesterfield 3 Deactivated Generator 100.0 Yes
Chesterfield 4 Deactivated Generator 119.0 Yes
Chesterfield 5 Deactivated Generator 350.0 No

Cost Summary

Table below shows a summary of the total planning level cost estimates for each individual New Service Request received by PJM and studied in Transition Cycle 1 Phase III. These network upgrade costs are subject to change as a result of a facility study performed by the Interconnected Transmission Owner during the Phase III System Impact Study.

Network Cost Summary for all projects of Transition Cycle 1 Phase III
Project ID Transmission Owner Interconnection Facilities (TOIF) Physical Interconnection Network Upgrades System Reliability Network Upgrades Affected System Study Reinforcements Additional Charges Total Cost Cost Details
AE1-092 $796,612 $14,467,553 $0 $0 $0 $15,264,165
AE1-114 $0 $11,422,206 $7,522,244 $82,193 $1,237,828 $20,264,471
AE1-148 $0 $7,762,963 $6,902,292 $0 $2,426,954 $17,092,209
AE1-172 $0 $28,485,236 $12,468,541 $136,518 $2,005,307 $43,095,602
AE2-156 $3,487,508 $8,024,437 $1,733,124 $0 $0 $13,245,069
AE2-173 $0 $0 $160,381 $154,718 $2,590,088 $2,905,187
AE2-185 $0 $724,989 $2,453,903 $0 $939,177 $4,118,069
AE2-187 $0 $14,761,901 $2,429,872 $0 $0 $17,191,773
AE2-223 $0 $32,602 $4,990,729 $247,658 $1,321,269 $6,592,257
AE2-261 $0 $5,449,938 $14,188,656 $1,137,243 $997,871 $21,773,709
AE2-283 $8,300,735 $3,617,755 $1,927,647 $0 $0 $13,846,137
AE2-291 $1,091,112 $15,672,692 $5,282,175 $0 $0 $22,045,979
AE2-308 $960,000 $16,084,000 $0 $0 $0 $17,044,000
AE2-321 $779,305 $31,487,039 $0 $368,307 $0 $32,634,651
AE2-325 $193,802 $60,764 $29,905 $249,654 $0 $534,125
AE2-341 $392,212 $20,659,366 $2,555,977 $567,614 $0 $24,175,169
AF1-030 $392,212 $20,659,366 $1,701,572 $375,625 $0 $23,128,775
AF1-088 $3,945,524 $1,454,913 $86,109,849 $5,002,132 $0 $96,512,419
AF1-123 $7,308,561 $250,069,522 $249,128,481 $0 $0 $506,506,564
AF1-124 $7,308,561 $250,069,522 $250,021,531 $0 $0 $507,399,614
AF1-125 $7,308,561 $250,069,522 $243,615,499 $0 $0 $500,993,582
AF1-128 $799,374 $2,182,499 $0 $0 $0 $2,981,873
AF1-161 $503,836 $1,371,722 $14,294 $239,991 $0 $2,129,843
AF1-176 $1,095,657 $1,996,401 $23,682,596 $27,771,262 $0 $54,545,916
AF1-204 $2,204,630 $391,163 $4,646,195 $2,153,115 $0 $9,395,103
AF1-233 $1,090,000 $17,924,352 $0 $3,511,290 $0 $22,525,642
AF1-238 $0 $0 $0 $0 $0 $0
AF1-240 $293,366 $762,742 $315,639 $0 $24,999 $1,396,746
AF1-280 $0 $12,467,942 $15,708,673 $681,511 $970,966 $29,829,091
AF1-294 $0 $1,370,721 $5,614,951 $0 $956,979 $7,942,651
AF1-296 $717,375 $11,672,026 $12,404,720 $95,169 $0 $24,889,290
AF2-008 $3,207,409 $3,624,696 $86,109,849 $5,002,132 $0 $97,944,087
AF2-010 $52,291 $4,938,510 $7,287,610 $0 $962,458 $13,240,869
AF2-035 $0 $0 $14,101,897 $0 $0 $14,101,897
AF2-041 $0 $5,286,342 $168,176,697 $1,062,418 $698,350 $175,223,807
AF2-042 $2,167,703 $36,291,713 $340,130,787 $0 $0 $378,590,203
AF2-046 $909,050 $8,910,978 $113,123,215 $3,625,000 $0 $126,568,243
AF2-050 $49,831 $153,052 $9,867,005 $0 $0 $10,069,888
AF2-068 $1,750,487 $1,483,556 $0 $8,357 $0 $3,242,400
AF2-069 $0 $0 $0 $3,174 $1,259,392 $1,262,566
AF2-080 $0 $0 $20,923,633 $3,726,000 $0 $24,649,633
AF2-081 $4,133,798 $3,663,047 $1,635,340 $0 $0 $9,432,185
AF2-095 $5,112,467 $1,166,794 $4,838,684 $597,954 $0 $11,715,899
AF2-111 $0 $8,479,000 $0 $81,383 $1,416,000 $9,976,383
AF2-115 $0 $1,370,721 $3,421,907 $0 $956,979 $5,749,607
AF2-120 $1,219,290 $1,219,184 $38,365,043 $0 $0 $40,803,516
AF2-126 $58,252 $233,066 $0 $2,025 $0 $293,343
AF2-142 $0 $0 $3,178,673 $589,248 $256,082 $4,024,003
AF2-143 $0 $0 $3,145,962 $575,326 $256,082 $3,977,370
AF2-173 $0 $60,764 $2,464,619 $8,357 $193,802 $2,727,542
AF2-177 $1,199,530 $10,397,244 $2,853,760 $0 $0 $14,450,534
AF2-182 $0 $12,467,942 $23,562,909 $1,018,422 $970,966 $38,020,238
AF2-199 $0 $5,286,342 $56,062,754 $350,908 $698,350 $62,398,354
AF2-200 $0 $5,286,342 $115,190,438 $710,842 $698,350 $121,885,972
AF2-222 $1,080,391 $16,075,015 $42,923,679 $0 $0 $60,079,085
AF2-225 $0 $32,602 $3,687,698 $638,055 $1,321,269 $5,679,623
AF2-226 $0 $0 $1,345,993 $204,661 $256,082 $1,806,736
AF2-296 $238,297 $1,389,983 $0 $0 $0 $1,628,280
AF2-297 $4,540,504 $2,355,572 $7,094,464 $0 $0 $13,990,540
AF2-299 $0 $0 $0 $515,000 $0 $515,000
AF2-307 $1,799,000 $11,073,000 $0 $0 $0 $12,872,000
AF2-319 $0 $0 $1,345,993 $204,661 $256,082 $1,806,736
AF2-335 $0 $1,065,672 $0 $8,357 $155,068 $1,229,098
AF2-349 $0 $17,122,339 $1,319,935 $1,094,363 $2,000,162 $21,536,799
AF2-350 $793,922 $29,405,140 $0 $419,501 $0 $30,618,563
AF2-358 $0 $610,000 $58,631,848 $0 $1,500,000 $60,741,848
AF2-365 $2,043,000 $14,689,000 $617,704 $0 $0 $17,349,704
AF2-370 $0 $1,065,672 $0 $0 $155,068 $1,220,741
AF2-376 $193,802 $60,764 $0 $0 $0 $254,566
AF2-388 $982,483 $691,462 $2,769,596 $19,678 $0 $4,463,219
AF2-392 $797,913 $41,848,395 $15,626,198 $105,428 $0 $58,377,934
AF2-396 $2,531,657 $2,169,205 $16,292,546 $18,823,503 $0 $39,816,911
AF2-404 $0 $724,989 $0 $0 $939,177 $1,664,166
AF2-407 $2,435,538 $3,325,190 $4,519,578 $734,838 $0 $11,015,144
AF2-441 $787,345 $7,072,041 $1,516,634 $910,924 $0 $10,286,944
AG1-008 $909,050 $8,910,978 $113,123,215 $3,625,000 $0 $126,568,243
AG1-021 $0 $1,370,721 $2,737,593 $0 $956,979 $5,065,294
AG1-070 $953,500 $6,189,500 $940,667 $3,158,698 $0 $11,242,364
AG1-071 $953,500 $6,189,500 $1,149,629 $3,767,215 $0 $12,059,844
AG1-082 $0 $0 $2,851,284 $611,000 $0 $3,462,284
AG1-090 $84,934 $1,099,479 $12,820,226 $0 $1,658 $14,006,296
AG1-098 $1,090,209 $15,937,649 $17,362,631 $0 $0 $34,390,489
AG1-105 $993,766 $14,284,645 $7,874,083 $0 $0 $23,152,494
AG1-106 $0 $0 $8,127,122 $1,018,000 $0 $9,145,122
AG1-109 $503,836 $1,432,486 $14,294 $0 $0 $1,950,616
AG1-118 $0 $8,216,337 $9,409,866 $1,111,779 $1,810,470 $20,548,452
AG1-124 $1,838,092 $10,076,477 $11,159,437 $0 $0 $23,074,006
AG1-127 $0 $0 $1,184,049 $346,850 $256,082 $1,786,981
AG1-135 $1,085,295 $17,406,305 $36,335,527 $0 $0 $54,827,127
AG1-146 $503,926 $8,270,469 $25,714,848 $0 $0 $34,489,242
AG1-147 $503,926 $8,270,469 $60,001,154 $0 $0 $68,775,548
AG1-153 $4,822,863 $1,958,524 $1,736,617 $0 $0 $8,518,004
AG1-154 $1,558,655 $9,405,709 $10,895,136 $0 $0 $21,859,500
AG1-166 $650,095 $3,992,506 $2,263,939 $0 $0 $6,906,540
AG1-167 $650,095 $3,992,506 $1,697,996 $0 $0 $6,340,597
AG1-168 $650,095 $3,992,506 $1,697,996 $0 $0 $6,340,597
AG1-226 $2,930,035 $33,073,479 $14,019,658 $4,899,748 $0 $54,922,920
AG1-236 $0 $0 $9,963,959 $346,947 $268,042 $10,578,948
AG1-285 $1,077,358 $18,954,196 $29,536,510 $0 $0 $49,568,064
AG1-297 $0 $1,965,671 $7,012,206 $478,742 $414,761 $9,871,380
AG1-320 $0 $2,214,000 $0 $4,334,526 $1,591,000 $8,139,526
AG1-323 $989,115 $1,522,624 $0 $0 $0 $2,511,739
AG1-341 $1,683,000 $6,002,000 $0 $7,562,355 $0 $15,247,355
AG1-342 $0 $1,957,245 $2,017,009 $0 $2,945,911 $6,920,165
AG1-354 $0 $6,127,000 $0 $13,379,640 $1,337,000 $20,843,640
AG1-367 $0 $60,764 $1,760,469 $16,713 $82,692 $1,920,638
AG1-374 $2,382,120 $19,794,599 $8,873,193 $1,254,210 $0 $32,304,122
AG1-375 $1,199,530 $10,458,008 $1,426,881 $14,686 $193,802 $13,292,907
AG1-377 $84,934 $1,099,479 $2,699,150 $0 $1,658 $3,885,221
AG1-378 $84,934 $1,099,479 $2,699,150 $0 $1,658 $3,885,221
AG1-393 $0 $0 $0 $0 $0 $0
AG1-394 $0 $0 $240,992 $365,000 $0 $605,992
AG1-405 $1,225,000 $5,035,000 $0 $0 $0 $6,260,000
AG1-406 $1,225,000 $5,035,000 $0 $0 $0 $6,260,000
AG1-410 $1,279,780 $10,446,603 $0 $23,042 $0 $11,749,425
AG1-411 $1,279,780 $10,507,367 $0 $0 $193,802 $11,980,949
AG1-433 $982,483 $752,226 $1,384,892 $0 $193,802 $3,313,403
AG1-436 $138,247 $60,764 $0 $652,242 $0 $851,253
AG1-447 $138,247 $60,764 $0 $291,870 $0 $490,881
AG1-450 $0 $610,000 $15,760,078 $0 $1,500,000 $17,870,079
AG1-460 $0 $5,449,938 $1,423,572 $113,056 $1,253,952 $8,240,519
AG1-462 $2,663,655 $16,617,794 $16,406,951 $798,388 $0 $36,486,788
AG1-471 $718,000 $13,187,000 $0 $5,352,864 $0 $19,257,864
AG1-494 $0 $2,704,883 $8,653,167 $0 $310,137 $11,668,187
AG1-526 $1,398,000 $4,441,000 $0 $0 $0 $5,839,000
AG1-536 $1,219,290 $1,219,184 $42,589,305 $0 $0 $45,027,778
AG1-548 $54,570 $6,698,199 $14,089,575 $0 $951,097 $21,793,441
AG1-551 $181,200 $18,000,000 $0 $530,000 $0 $18,711,200
AG1-552 $181,200 $24,400,000 $0 $637,000 $0 $25,218,200
AG1-553 $2,167,424 $16,617,794 $14,840,658 $816,076 $0 $34,441,952

System Reinforcements

As part of Phase III, PJM evaluated the impact of topology changing reinforcements to mitigate the impacts driven by New Service Requests. PJM determined which reinforcements were eliminated as a result of modeling the topology changing reinforcements. PJM then grouped the topology changing and eliminated reinforcements by region and computed a discount factor to apply to reinforcements to reduce the cost of all these reinforcements down to the cost of contstructing only the topology changing reinforcements.

Regional Discount Factors for Topology Changing Upgrades
Region Topology Upgrades Eliminated Upgrades Discount Factor Details
Dominion $519,466,645 $751,704,547 40.865200%
Mid-Atlantic Area Council $0 $0 100.000000%
PJM West $203,595,627 $6,125,000 97.079448%

Details for Dominion Region


The following topology changing reinforcements within the Dominion region were modeled to mitigate the impacts driven by the new service requests in Phase III:

Table 3: Dominion Topology Changing Reinforcement(s) Modeled for Phase III
TO RTEP ID / TO ID Title Time Estimate Total Cost Estimate ($)
Dominion n7541 / dom-016

Add a third 224 MVA 230/115 kV transformer at Earleys Substation and supporting equipment.

Dec 31 2029 $22,779,395
Dominion n9138.0 / TC1-PH1-DOM-070

Wreck and rebuild 22.59 miles of Line #511 between Carson and Rawlings Substations with three (3) 1351 ACSS/TW and associated substation work.

60 to 61 Months $111,130,292
Dominion n9250.0 / TC1-PH2-DOM-044

Construct a new 22.59 mile line between Carson and Rawlings Substations.

60 to 61 Months $108,728,086
Dominion s3047.2

Install two (2) 1400 MVA 500-230 kV transformers at Vint Hill Substation and loop 500 kV line #535 and #569 into the proposed 500 kV ring bus at Vint Hill Substation.

Jun 30 2029 $0
Dominion b3800.312

Rebuild 500 kV Line #569 Loudoun - Morrisville to accommodate the new 500 kV line in the existing right-of-way.

Jun 30 2030 $0
Dominion b3800.313

Rebuild approximately 10.29 miles line segment of Line #535 (Meadow Brook to Loudoun) to accommodate the new 500 kV line in the existing ROW.

Jun 30 2030 $0
Dominion b3800.356

Build a new 500 kV line from Vint Hill to Wishing Star.

Jun 30 2030 $0
Dominion b3800.357

Build a new 500 kV line from Morrisville to Vint Hill.

Jun 30 2030 $0
Dominion b3800.354

Install terminal equipment at Wishing Star Substation to support a 5000A line to Vint Hill. Update relay settings for 500 kV Lines #546 and #590.

Jun 30 2030 $0
Dominion n8492

Wreck and rebuild the existing Yadkin to Fentress 500 kV Line #588 to share the right of way with the new Yadkin to Fentress #5005 line.

26 to 27 Months $80,172,278
Dominion n8492.1

Two Breaker Additions at Fentress Substation.

30 to 36 Months $19,945,879
Dominion n8492.2

Expand Yadkin Substation to accommodate the new 500 kV line.

15 to 16 Months $16,207,123
Dominion n9259.0

Install two 230 kV gas insulated switchgear ("GIS") bus ties for the Coastal Virginia Offshore Wind ("CVOW") project.

38 to 39 Months $25,304,902
Dominion n9267.0 / TC1-PH2-DOM-067

Construct new 10.21 mile 115 kV line between Northern Neck and Moon Corner.

45 to 46 Months $45,730,074
Dominion b4000.357

Build a new 765/500/230 kV substation called Yeat. Install (2) 765/500 kV transformers. Cut in 500 kV line Bristers-Ox and 500 kV line Meadowbrook-Vint Hill into Yeat.

Jun 01 2029 $0
Dominion b4000.356

Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 86.7 miles in Dominion section).

Jun 01 2029 $0
Dominion b4000.355

Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 69.3 miles in AEP section).

Jun 01 2029 $0
Dominion b4000.352

Cut in Line #568 Ladysmith - Possum Point into Kraken, creating new Line #568 Kraken to Possum Point.

Sep 16 2030 $0
Dominion b4000.351

Cut in Line #568 Ladysmith - Possum Point into Kraken, creating Line #9517 Ladysmith to Kraken.

Sep 16 2030 $0
Dominion b4000.350

Update relay settings at Possum Point to change the destination of 500kV line #568 from Ladysmith to Kraken.

Sep 16 2030 $0
Dominion b4000.349

Update relay settings at Ladysmith to change the destination of 500kV line #568 from Possum Point to Kraken.

Sep 16 2030 $0
Dominion b4000.348

Build a new 500/230kV substation called Kraken. The 500kV, 5000A ring bus will be set up for a redundant breaker configuration. Install (2) 1400MVA 500/230 kV transformers.

Jun 01 2029 $0
Dominion b4000.346

Cut-in 500kV line from Kraken substation into Yeat substation

Jun 01 2029 $0
Dominion b4000.345

Build a 500kV line from a new substation called Kraken to a new substation called Yeat. New conductor to have a minimum summer normal rating of 4357MVA.

Sep 16 2030 $0
Dominion b4000.344

Build a 500kV line from North Anna substation (bypassing Ladysmith Substation) to a new substation called Kraken. New conductor to have a minimum summer normal rating of 4357MVA.

Sep 16 2030 $0
Dominion b4000.342

Remove the terminal equipment and substation work required for the termination of the Morrisville-Wishing Star 500 kV line into Vint Hill.

Jul 13 2029 $0
Dominion b4000.341

Remove the 500 kV conductor previously planned to terminate into the Vint Hill 500 kV Substation and extend approximately 0.2 miles of conductor to fly-over the site.

Jul 13 2029 $0
Dominion b4000.325

Build a new 26.38mi 230kV Line from Elmont – Ladysmith on the existing 5-2 structures between the two stations. New conductor has a summer rating of 1573 MVA.

Feb 24 2029 $0
Dominion b4000.326

At Elmont substation, install/upgrade associated equipment to accommodate a 4000A line rating for the new 230kV line between Elmont - Ladysmith.

Feb 24 2029 $0
Dominion b4000.327

Upgrade/install equipment at Ladysmith Substation to 4000A. Expansion will be required to accommodate a total of three (3) new 230 kV strings of breaker and a half scheme.

Feb 24 2029 $0
Dominion n9630.0 / TC1-PH3-DOM-013

Construct a new 230 kV line from the AG1-285 substation to the Finneywood 230 kV Substation. Expand AG1-285 substation and add two (2) new 230/115 kV transformers.

Dec 31 2029 $89,468,616
Dominion b3689.2

Replace 230 kV breakers SC102, H302, H402 and 218302 at Brambleton substation with 80 kA

Mar 31 2027 $0
Dominion b4000.103

Brambleton Sub 230kV - replace 63kA breakers 217202, 2172T2183, L102, L202 with 80kA

Jun 01 2028 $0
Dominion b3800.405

Replace Brambleton 230 kV breakers 20102, 20602, 204502, 209402, 201T2045, 206T2094 with breakers rated 80 kA.

Jan 08 2031 $0
Dominion b3854.1

Replace over duty Carson 230kV circuit breakers 200272 and 24972-3 with an interrupting rating of 63 kA

May 03 2025 $0
Dominion b4000.108

Carson Sub 230kV - replace 40kA breaker 23872 with 63kA

Jul 12 2029 $0
Dominion b3800.406

Replace Gainesville 230 kV breaker 216192 with a breaker rated 80 kA.

Mar 15 2030 $0
Dominion b4000.115

Ladysmith Sub 500kV - replace 40kA breaker 574T581 with 63kA

Nov 27 2031 $0
Dominion b4000.354

Ladysmith substation breakers replacement: 574T575 and 568T581

Nov 14 2029 $0
Dominion b3853.1 / (Pending)

Replace over duty Ladysmith CT 230kV circuit breakers SX1272 and SX3472 with an interrupting rating of 63 kA

TBD $0
Dominion b4000.114

Ladysmith S1 Sub 230kV - replace 40kA breakers 25672, 209072, 256T2090, GT172, GT272, GT372, GT472, GT572 with 63kA

Jul 18 2030 $0
Dominion b3800.235

Replace 5 overdutied 230kV breakers at Loudoun substation with 80kA breakers

Oct 05 2031 $0
Dominion b3800.334

Replace four (4) overdutied 230 kV breakers at Loudoun Substation with 80 kA breakers.

Oct 05 2031 $0
Dominion b3800.407

Replace Loudoun 230 kV breakers 204552 and 217352 with breakers rated 80 kA.

Oct 05 2031 $0
Dominion b4000.119

Loudoun Cap Substation 230kV - replace 50 kA breaker SC352 with 63 kA.

Oct 31 2030 $0
Dominion b4000.128

North Anna Substation 500 kV - replace 40 kA breakers 57502, G102-1, G102-2, G202, G2T575, and XT573 with 63 kA.

Oct 13 2032 $0
Dominion b3800.408

Replace Ox 230 kV breakers 22042, 24342, 24842, 220T2063, 243T2097, 248T2013, and H342 with breakers rated 80 kA.

Apr 21 2031 $0
Dominion s2609.6

Upgrade two (2) 230 kV breakers 201342 and L142 from 50 kA to 63 kA at Ox Substation due to an insufficient breaker duty rating with the expansion in place.

Dec 15 2030 $0
Dominion s2609.9

Upgrade 230 kV Pleasant View breakers L3T203 and L3T2180 from 50 kA to 80 kA.

Sep 13 2030 $0
Dominion b4000.134

Remington Substation 230 kV - replace 40 kA and 50 kA breakers 211462, GT162, GT262, GT362, GT462, 2077T2086, 208662, H962, and H9T299 with 63 kA.

Jan 09 2031 $0
Dominion b1696

Install a breaker and a half scheme with a minimum of eight 230 kV breakers for five existing lines at Idylwood 230 kV: 20212 and 20712

TBD $0
Dominion b3800.236

Replace 2 overdutied 500kV breakers at Ox Substation with 63kA breakers.

Jan 05 2029 $0
Dominion b3800.335

Replace 1 overdutied 500kV breaker at Ox Substation with a 63kA breaker

Dec 15 2031 $0
Grand Total: $519,466,645

The following reinforcements in the Dominion region were eliminated as a result of modeling the above topology reinforcements in Phase III.

Table 4: Dominion Eliminated Reinforcement(s) Identified for Phase III
TO RTEP ID / TO ID Title Time Estimate Total Cost Estimate ($)
Dominion n7687 / dom-046

Add a 3rd 230/115 kV transformer at Sedge Hill Substation and associated breakers (230 kV and 115 kV).

Jun 01 2029 $10,595,849
Dominion n6161 / dom-039

Replace 500 kV circuit breaker H1T561 at Clifton with a higher rated device (Clifton - Ox).

Dec 31 2029 $2,634,901
Dominion n7180 / dom-199

Rebuild 7.2 miles of 230 kV Line 235 from Prince EDW to Farmville with (2) 768.2 ACSS/TW (20/7) "MAUMEE" at 250 C.

48 to 49 Months $26,768,621
Dominion n7576 / dom-281

Rebuild 7.91 miles of 230 kV Line 2083 from Birchwood to Fines with (2) 768.2 ACSS/TW (20/7) "MAUMEE" conductor 250 degrees C.

43 to 44 Months $35,735,843
Dominion n7685 / dom-283

Rebuild 4.56 miles of 230 kV Line 2157 from Fredericksburg to Cranes Corner with (2) 768.2 ACSS/TW (20/7) "MAUMEE" conductor at 250 C and replace Line Lead at Cranes Corner.

43 to 44 Months $15,674,813
Dominion n7575 / dom-286

Rebuild 6.46 mi miles of 2-545.6 ACAR (15/7) 90 MOT 230 kV Line 2083 from Fredericksburg to Fines with (2) 768.2 ACSS/TW (20/7) "MAUMEE" conductor @ 250 degrees C.

43 to 44 Months $33,559,690
Dominion n7568 / dom-369

Wreck and rebuild 6.47 miles of 230 kV transmission line 2028 between Charlottesville and Mt. Eagle with (2) 768.2 ACSS/TW (20/7) "Maumee" @ 250C and replace line lead at Mt. Eagle.

43 to 44 Months $36,802,018
Dominion n7556 / dom-461

Reconductor 3.53 miles of 115 kV Line 65 from AD2-074 Tap to AG1-146 Tap with (1) 768.2 ACSS/TW (20/70) "Maumee" conductor @ 250 degrees C

43 to 44 Months $16,493,251
Dominion n7812 / dom-397

Wreck and rebuild 7.3 miles of 138 kV Line No. 8 between AE1-108 and Bremo with (1) 768.2 ACSS/TW (20/7) "MAUMEE" conductor.

43 to 44 Months $23,887,052
Dominion n7612 / dom-015

Add a 4th 224 MVA 230/115 kV transformer at Suffolk substation and associated breakers (230 kV and 115 kV)

Dec 31 2028 $10,061,347
Dominion n7569 / dom-490

Upgrade a 3.78 mile segment of 230kV transmission line 2028 between Mt. Eagle and Grape Vine Substations at structure 2080/73.

43 to 44 Months $13,360,242
Dominion n8305 / dom-471

Reconductor 1.33 Miles of 115kV transmission line 65 from Ocran to Whitestone

42 to 43 Months $6,374,460
Dominion n8424 / dom-423

Rebuild 5.7 miles of 230 kV Line 235 from Prince EDW to Briery with (2) 768.2 ACSS/TW (20/7) "MAUMEE" conductor at 250 degrees C.

48 to 49 Months $20,782,348
Dominion n9148.0 / TC1-PH1-DOM-013

Wreck and rebuild 5.63 miles of 115 kV line between Wan and White Marsh with (1) 768.2 ACSS/TW (20/7) "MAUMEE" conductor @ 250 degrees C.

43 to 44 Months $37,993,385
Dominion n9198.0 / TC1-PH2-DOM-003

Replace Circuit Breaker 219322 and Circuit Breaker Lead at Bremo 230 kV (Bremo - Fork Union).

40 to 41 Months $2,113,879
Dominion n9203.0 / TC1-PH2-DOM-008

Wreck and rebuild 10.74 miles of line 2028 between Fork Union and Cunningham (Grape Vine) with (2) 768.2 ACSS/TW (20/7) "MAUMEE" @ 250C.

45 to 46 Months $29,539,973
Dominion n9212.0 / TC1-PH2-DOM-023

Reconductor 3.01 mi of the 115 kV line 65 from Lancaster to Ocran with 768.2 ACSS 250 C.

42 to 43 Months $9,591,162
Dominion n9218.0 / TC1-PH2-DOM-030

Reconductor 6.01 miles of 115 kV Line 65 from AG1-146 Tap to Lancaster with (1) 768.2 ACSS/TW (20/70 "Maumee" conductor @ 250 degrees C.

43 to 44 Months $27,984,346
Dominion n9221.0 / TC1-PH3-DOM-015

Replace 230 kV Breaker 29822 at Bremo with a higher-rated device (Buckingham - Bremo).

38 to 39 Months $2,057,335
Dominion n9222.0 / TC1-PH2-DOM-036

Wreck and Rebuild 6.95 miles of 115 kV Line 89 from White Marsh to Hayes with (1) 768 ACSS/TW (20/7) "Maumee" conductor @ 250 degrees C. Replace Line Lead at Hayes.

43 to 44 Months $42,356,870
Dominion n9246.0 / TC1-PH2-DOM-040

Wreck and rebuild 18.75 miles of Line 594 btwn Morrisville and Spotsylvania with (3) 1351.5 ACSR (45/7) "Dipper" at 110 degrees C and assoc substation work to achieve new rating of 4356/4356/5009 MVA.

60 to 61 Months $128,018,212
Dominion n9247.0 / TC1-PH2-DOM-041

Wreck and rebuild 14.02 miles of Line 573 btwn Spotsylvania and North Anna with (3) 1351.5 ACSR (45/7) "Dipper" at 110 degrees C and assoc substation work to achieve new rating of 4356/4356/5009 MVA.

48 Months $99,636,684
Dominion n9262.0 / TC1-PH2-DOM-061

Replace wave trap 256WT at Four River 230 kV station (Four River - St. John).

14 to 15 Months $514,454
Dominion n9263.0 / TC1-PH2-DOM-062

Wreck and Rebuild 14.83 miles of 230 kV line 256 with (2) 768.2 ACSS/TW (20/7) ""Maumee"" conductor @ 250 degrees C.

46 to 47 Months $41,037,004
Dominion n9644.0 / TC1-PH3-DOM-006

Upgrade a 2.73 mile segment of 230kV transmission line 2028 between Mt. Eagle and Grape Vine. This segment runs from Grape Vine substation to structure 2080/73.

Mar 31 2029 $8,415,380
Dominion n9376.0 / TC1-PH3-DOM-003

Wreck and Rebuild 22.98 miles of 230 kV Line 235 from Briery to AG1-098 with (2) 768.2 ACSS/TW (20/7) "MAUMEE" at 250 C.

Dec 31 2029 $69,323,785
Dominion n9643.0 / TC1-PH3-DOM-009

Replace 795 AAC 37 line lead at Farmville 115 kV.

Mar 31 2027 $391,643
Grand Total: $751,704,547

Impacted New Service Requests have a cost responsibility into the eliminated reinforcements, but these reinforcements will not be constructed. A discount factor of 40.865200% has been applied to all projects which contribute to a topology changing or eliminated reinforcement in the Dominion region.

Details for Mid-Atlantic Area Council Region


There were no eliminated reinforcements identified in the Mid-Atlantic Area Council region. Therefore, no reinforcements in the Mid-Atlantic Area Council region have been discounted.

Details for PJM West Region


The following topology changing reinforcements within the PJM West region were modeled to mitigate the impacts driven by the new service requests in Phase III:

Table 3: PJM West Topology Changing Reinforcement(s) Modeled for Phase III
TO RTEP ID / TO ID Title Time Estimate Total Cost Estimate ($)
ComEd b3775.1

Swap the NIPSCO Green Acre Tap towers from the St. John-Green Acres-Olive 345 kV line

Dec 01 2026 $0
ComEd b3811.1 / CE_PJM B3811_L11323

Expand Haumesser Road 138 kV substation as a 4 circuit breaker ring bus.

Dec 01 2028 $0
ComEd s3011 / CE_S3011

Replace 345kV straight bus at TSS 116 Goodings Grove with a gas insulated switchgear ("GIS") breaker and a half configuration.

Dec 31 2028 $0
ComEd n9195.0 / CE_NUN_STA12_345 NEW CB

Install a new 345 kV circuit breaker at Station 12 Dresden.

45 Months $3,357,627
AEP n9243.0 / AEPSERG13

Expand Jefferson 345 kV station. Install a second 765/345 kV 750 MVA transformer. Install a second Jefferson - Clifty Creek 345 kV single circuit ~0.8 miles.

55 Months $200,238,000
Grand Total: $203,595,627

The following reinforcements in the PJM West region were eliminated as a result of modeling the above topology reinforcements in Phase III.

Table 4: PJM West Eliminated Reinforcement(s) Identified for Phase III
TO RTEP ID / TO ID Title Time Estimate Total Cost Estimate ($)
AEP n4106.5 / AEPI0045c

Upgrade the 345 kV bus 2 towards Jefferson in the Clifty Creek Station

17 Months $121,000
AEP n9178.0 / AEPAPRJV007

Mitigation work on 6.5 Miles of 138 kV transmission line from Scottsville Station to Arvonia Station.

29 Months $4,759,000
AEP n9179.0 / AEPAPRJV008

Upgrade a 0.6 mile portion of the Arvonia – Bremo Bluff (VEPCO) 138 kV line.

15 Months $1,245,000
Grand Total: $6,125,000

Impacted New Service Requests have a cost responsibility into the eliminated reinforcements, but these reinforcements will not be constructed. A discount factor of 97.079448% has been applied to all projects which contribute to a topology changing or eliminated reinforcement in the PJM West region.

Steady State Thermal & Voltage Reinforcements

PJM performed generator deliverability load flow analysis for the New Service Requests in Transition Cycle 1 Phase III. Load flow analysis was performed to simulate Summer Peak, Light Load and Winter Peak[1] conditions. The table below shows all the system reinforcements identified from generator deliverability load flow analysis.

TO RTEP ID / TO ID Title Time Estimate Total Cost Estimate ($) Projects with Cost Allocation Contingent Projects Facilities Study
AEP b3775.10

Perform sag study mitigation work on Olive – University Park

Dec 01 2026
Contingent

AE1-114, AE1-172, AE2-321, AE2-341, AF1-030, AF1-280, AF1-296, AF2-041, AF2-095, AF2-142, AF2-143, AF2-182, AF2-200, AF2-349, AF2-350, AF2-392, AF2-441, AG1-118, AG1-127

N/A
AEP b3775.11 / b3775.7a

Upgrade the wavetrap at Dumont substation to increase the rating of the Stillwell-Dumont 345 kV line to match conductor rating.

Dec 01 2026
Contingent

AF2-041, AF2-441, AG1-118, AG1-374

N/A
AEP b3775.6

Perform sag study mitigation work on the Dumont-Stillwell 345 kV line

Nov 20 2026
Contingent

AF2-041, AF2-441, AG1-118, AG1-236, AG1-374

N/A
AEP b3788.1 / B3788.1

Replace limiting station elements at Kyger Creek

Nov 18 2027
Contingent

AF1-088, AF1-204, AF2-008, AF2-407, AG1-297

N/A
AEP b4000.210

Rebuild 7 miles of Otter - Johnson Mountain 138 kV line.

Jun 01 2029
Contingent

AE2-185, AE2-187, AE2-283, AE2-291, AF2-297, AG1-105

N/A
AEP b4000.211

Rebuild 6.5 miles of Johnson Mountain - New London 138 kV line

Jun 01 2029
Contingent

AE2-185, AE2-187, AE2-283, AE2-291, AF2-297, AG1-105

N/A
AEP b4000.251

Replace the wave trap and upgrade the relay at Cloverdale 765kV substation

Jun 01 2029
Contingent

AF1-088, AG1-494

N/A
AEP b4000.252

Replace the wave trap and upgrade the relay at Joshua Falls 765kV substation

Jun 01 2029
Contingent

AF1-088, AG1-494

N/A
AEP n3985 / AEPO0036a

Upgrade three Marysville Wavetraps ( 3000A)

18 to 24 Months
Contingent

AF1-176, AF2-396, AF2-441

N/A
AEP n4056.1 / AEPI0048a

Replace the (1) 3000A 765kV CB at Dumont station

18 to 24 Months
Contingent

AE1-172, AF2-349, AF2-441, AG1-118

N/A
AEP n4106.3

Extend One (1) Tower on the Jefferson - Clifty Creek (IKEC) 345 kV Circuit

12 to 18 Months
Contingent

AE2-261

N/A
AEP n5613 / AEPA0014a

Rebuild 0.9 miles of the Otter - Alta Vista 138 kV line.

Nov 21 2027
Contingent

AE2-185, AE2-187, AE2-283, AE2-291, AF2-297, AG1-105

N/A
AEP n5769.4 / AEPI0066a

Reconductor ~8.58 Miles of 345 kV transmission line from Dumont Station to Structure 39

32 Months
$31,234,000

AE1-114, AE1-172, AE2-223, AE2-341, AF1-030, AF1-296, AF2-041, AF2-095, AF2-142, AF2-143, AF2-199, AF2-200, AF2-226, AF2-319, AF2-392, AF2-441, AG1-118, AG1-236, AG1-374, AG1-462

AEP n5808 / N5808

CON Upgrade_AEP: eliminate the Eugene stuck breaker contingency. (AMIL upgrade will not be required)

May 15 2026
Contingent

AE1-172, AE2-223, AE2-261, AF1-088, AF2-041, AF2-182, AF2-225, AF2-349, AG1-118, AG1-236, AG1-374, AG1-462, AG1-553

N/A
AEP n6497.4 / AEPI0002e/f

Replace line traps on the Jefferson - Rockport 765 kV line

35 Months
$1,212,000

AF1-088, AF2-008, AG1-226

AEP n7679 / AEPI0040a

Replace 1272 AAC Jumper at Allen station

18 to 24 Months
Contingent

AF2-376

N/A
AEP n7757 / AEPI0063a

Replace Bus 1 at the Desoto 138 kV Station

17 Months
$186,000

AF2-173, AF2-177, AF2-388, AG1-367, AG1-375, AG1-433

AEP n7925.1 / AEPI0010a

Reconductor ~0.41 miles of the Sullivan – West Casey (Ameren) line

11 Months
Contingent

AE2-261, AF1-088, AF2-182, AG1-236, AG1-374, AG1-462, AG1-553

AEP n9243.0 / AEPSERG13

Expand Jefferson 345 kV station. Install a second 765/345 kV 750 MVA transformer. Install a second Jefferson - Clifty Creek 345 kV single circuit ~0.8 miles.

55 Months
$200,238,000

AE1-172, AE2-173, AE2-223, AE2-261, AF1-088, AF1-204, AF2-008, AF2-225, AG1-124, AG1-226, AG1-236, AG1-374, AG1-460, AG1-494

AE1-114, AE2-185, AE2-187, AE2-283, AE2-321, AE2-341, AF1-030, AF1-280, AF1-296, AF2-041, AF2-095, AF2-142, AF2-143, AF2-182, AF2-200, AF2-349, AF2-350, AF2-392, AF2-441, AG1-118, AG1-127, AG1-436, AG1-447, AG1-553

AEP s2793.5 / s2793

Rebuild the T-line from West Van Wert to Roller Creek

TBD
Contingent

AF2-376

N/A
ATSI n9228.0 / TC1-ATSI-002.b

Rebuild 6.6 miles of the Lallendorf-Monroe 345 kV line and install OPGW. Replace line drops and wave traps at Lallendorf.

29 Months
$38,362,639

AF1-176, AF2-396

ATSI n9322.0 / TE-AG1-S-0012a

Replace Four (4) disconnect switches, four (4) breaker leads, and one (1) meter, and reconductor two (2) transmission line drops on the Morocco 345 kV line terminal at Allen Junction.

38 Months
$1,408,997

AF1-176, AF2-396

ComEd b3775.1

Swap the NIPSCO Green Acre Tap towers from the St. John-Green Acres-Olive 345 kV line

Dec 01 2026
Contingent

AE1-114, AE1-172, AE2-173, AE2-185, AE2-187, AE2-223, AE2-261, AE2-283, AE2-321, AE2-341, AF1-030, AF1-088, AF1-204, AF1-280, AF1-296, AF2-008, AF2-041, AF2-095, AF2-142, AF2-143, AF2-182, AF2-200, AF2-225, AF2-349, AF2-350, AF2-392, AF2-441, AG1-118, AG1-124, AG1-127, AG1-226, AG1-236, AG1-374, AG1-436, AG1-447, AG1-460, AG1-494, AG1-553

N/A
ComEd b3775.3

Rebuild ComEd’s section of 345 kV double circuit in IL from St. John to Crete

Dec 01 2026
Contingent

AF2-041, AF2-200, AF2-349, AG1-118

N/A
ComEd b3775.4 / CE_B3775.4

Rebuild 345 kV double circuit extending from Crete to E. Frankfort.

Dec 01 2026
Contingent

AF2-349

N/A
ComEd b3775.5

Replace E. Frankfort 345 kV circuit breaker “9-14” with 3150A SF6 circuit breaker.

Dec 01 2026
Contingent

AE1-172, AE2-341, AF2-041, AF2-142, AF2-143, AF2-200, AF2-349, AF2-392, AF2-441, AG1-118

N/A
ComEd b3811.1 / CE_PJM B3811_L11323

Expand Haumesser Road 138 kV substation as a 4 circuit breaker ring bus.

Dec 01 2028
Contingent

AE1-114, AE1-172, AE2-173, AE2-185, AE2-187, AE2-223, AE2-261, AE2-283, AE2-321, AE2-341, AF1-030, AF1-088, AF1-204, AF1-280, AF1-296, AF2-008, AF2-041, AF2-095, AF2-142, AF2-143, AF2-182, AF2-200, AF2-225, AF2-349, AF2-350, AF2-392, AF2-441, AG1-118, AG1-124, AG1-127, AG1-226, AG1-236, AG1-374, AG1-436, AG1-447, AG1-460, AG1-494, AG1-553

N/A
ComEd b3811.2 / CE_PJM B3811_L11323

Additional Circuit Breaker at ESS H452

Dec 01 2028
Contingent

AE1-114, AF2-392

N/A
ComEd b3811.3 / CE_PJM B3811_L11323

Rebuild 3 miles of 138 kV line 11323 from Haumesser Road to the H-452 tap

Dec 01 2028
Contingent

AE1-114, AF2-392

N/A
ComEd n3515.1 / ce-017

Cherry Valley - Garden Prarie 345 kV: Line rebuild, station bus work, & Cherry Valley 345kV breaker replacement

50 Months
$84,712,245

AF2-041, AF2-199, AF2-200

ComEd n5145

Reconfigure Wilton 765kV bus

Dec 31 2025
Contingent

AE1-172, AE2-341, AF2-095, AF2-142, AF2-143, AF2-349, AF2-441, AG1-118

N/A
ComEd n5318.1 / ce-012a

Garden Prarie - Silver Lake R 345 kV: Line rebuild, station bus work & Silver Lake 345kV Breaker Replacement

60 Months
$163,968,683

AF2-041, AF2-199, AF2-200

ComEd n6639.2 / CE_NUN_L15502_4

Reconductor the Electric Junction 345 kV line 93407, perform sag mitigation on 345 kV line 93407, upgrade one 345 kV circuit breaker and associated motor operated disconnect switches.

42 Months
$146,197,759

AE1-114, AF1-280, AF1-296, AF2-041, AF2-182, AF2-199, AF2-200, AF2-392, AG1-462, AG1-553

ComEd n6840 / CE_NUN_Sta. 12 Dresden

Install a new 345kV bus tie circuit breaker at Station 12 Dresden

Dec 18 2024
Contingent

AE1-172, AE2-173, AE2-223, AE2-261, AF2-225, AG1-236, AG1-374

N/A
ComEd n7023.1 / CE_NUN_L11124.1

Reconductor the Electric Junction - Lombard line L11124 345 kV Line and perform associated station relay and protection upgrades.

36 Months
$38,797,273

AE1-114, AE2-341, AF1-030, AF1-280, AF1-296, AF2-041, AF2-182, AF2-199, AF2-200, AF2-349, AF2-392, AG1-118, AG1-127, AG1-462, AG1-553

ComEd n8162 / CE_NUN_0304.1

Perform sag mitigation on the Powerton - Tazewell 345 kV Line and replace disconnect switches at Powerton substation.

1 to 36 Months
$5,017,397

AF2-142, AF2-143, AF2-226, AF2-319

ComEd n9101.0 / CE_NUN_L18806

Mitigate sag on the Brokaw to TSS 909 Deer Creek 345 kV line L90907.

36 Months
$14,966,004

AE2-261, AG1-236, AG1-460

ComEd n9165.0 / CE_NUN_L15502.1

Perform TSS 155 Nelson Substation conductor upgrades.

36 Months
$1,220,445

AE1-114, AF1-280, AF1-296, AF2-182, AF2-392, AG1-462, AG1-553

ComEd n9166.0 / CE_NUN_L16914.1

Reconductor the McGirr Road to ESS H447 RT 138 KV line

24 Months
$605,422

AE1-114, AF2-392

ComEd n9195.0 / CE_NUN_STA12_345 NEW CB

Install a new 345 kV circuit breaker at Station 12 Dresden.

45 Months
$3,357,627

AE1-172, AE2-173, AE2-223, AE2-261, AF1-088, AF1-204, AF2-008, AF2-225, AG1-124, AG1-226, AG1-236, AG1-374, AG1-460, AG1-494

AE1-114, AE2-185, AE2-187, AE2-283, AE2-321, AE2-341, AF1-030, AF1-280, AF1-296, AF2-041, AF2-095, AF2-142, AF2-143, AF2-182, AF2-200, AF2-349, AF2-350, AF2-392, AF2-441, AG1-118, AG1-127, AG1-436, AG1-447, AG1-553

ComEd n9269.0 / CE_NUN_L11212.5

Reconductor the AD1-100 Tap - Wilton 345 kV line.

60 Months
$37,989,655

AE1-172, AE2-223, AE2-261, AF2-041, AF2-095, AF2-199, AF2-200, AF2-225, AG1-118, AG1-374, AG1-460

ComEd s3011 / CE_S3011

Replace 345kV straight bus at TSS 116 Goodings Grove with a gas insulated switchgear ("GIS") breaker and a half configuration.

Dec 31 2028
Contingent

AE1-114, AE1-172, AE2-173, AE2-185, AE2-187, AE2-223, AE2-261, AE2-283, AE2-321, AE2-341, AF1-030, AF1-088, AF1-204, AF1-280, AF1-296, AF2-008, AF2-041, AF2-095, AF2-142, AF2-143, AF2-182, AF2-200, AF2-225, AF2-349, AF2-350, AF2-392, AF2-441, AG1-118, AG1-124, AG1-127, AG1-226, AG1-236, AG1-374, AG1-436, AG1-447, AG1-460, AG1-494, AG1-553

N/A
DPL n6925 / dt22085r0001

Rebuild Edge Moor (DPL) - Linwood (PECO) 230 kV line.

36 to 48 Months
$71,680,000

AF2-358, AG1-450

Dayton b3904.1

Rebuild and reconductor 7.7 miles of 69kV line.

Jun 01 2029
Contingent

AF2-376

N/A
Dominion b3694.8

Partial wreck and rebuild 10.34 miles of 230 kV line #249 Carson-Locks to achieve a minimum summer emergency rating of 1572 MVA.

May 03 2025
Contingent

AF2-042

N/A
Dominion b3800.312

Rebuild 500 kV Line #569 Loudoun - Morrisville to accommodate the new 500 kV line in the existing right-of-way.

Jun 30 2030
Contingent

AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552

N/A
Dominion b3800.313

Rebuild approximately 10.29 miles line segment of Line #535 (Meadow Brook to Loudoun) to accommodate the new 500 kV line in the existing ROW.

Jun 30 2030
Contingent

AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552

N/A
Dominion b3800.354

Install terminal equipment at Wishing Star Substation to support a 5000A line to Vint Hill. Update relay settings for 500 kV Lines #546 and #590.

Jun 30 2030
Contingent

AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552

N/A
Dominion b3800.356

Build a new 500 kV line from Vint Hill to Wishing Star.

Jun 30 2030
Contingent

AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552

N/A
Dominion b3800.357

Build a new 500 kV line from Morrisville to Vint Hill.

Jun 30 2030
Contingent

AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552

N/A
Dominion b3800.373

Wreck and rebuild approximately 7.14 miles of 230kV line #256 from St. Johns to structure 256/108 to achieve a summer rating of 1573 MVA. Line switch 25666 at St. Johns to be upgraded to 4000A.

Jun 15 2027
Contingent

AF2-035

N/A
Dominion b3800.374

Reconductor approximately 5.30 miles of 230kV line #256 from Ladysmith CT to structure 256/107 to achieve a summer rating of 1573 MVA.

Jun 15 2027
Contingent

AF2-035

N/A
Dominion b4000.315

Reconductor 230kV Line #2003 Tyler – Poe segment. New conductor has a summer rating of 1573 MVA.

Apr 22 2030
Contingent

AF2-042, AF2-046, AF2-222, AG1-008, AG1-098, AG1-153, AG1-285

N/A
Dominion b4000.319

Reconductor 230kV Line #2002 Carson – Poe. New conductor has a summer rating of 1573 MVA.

Mar 20 2030
Contingent

AF2-042, AF2-222

N/A
Dominion b4000.320

At Carson substation, upgrade all line #2002 terminal equipment at Carson to 4000A. CCVTs will also be replaced due to aging.

Mar 20 2030
Contingent

AF2-042, AF2-222

N/A
Dominion b4000.321

At Poe substation, upgrade all line #2002 terminal equipment at Carson to 4000A. CCVTs will also be replaced due to aging.

Mar 20 2030
Contingent

AF2-042, AF2-222

N/A
Dominion b4000.325

Build a new 26.38mi 230kV Line from Elmont – Ladysmith on the existing 5-2 structures between the two stations. New conductor has a summer rating of 1573 MVA.

Feb 24 2029
Contingent

AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552

N/A
Dominion b4000.326

At Elmont substation, install/upgrade associated equipment to accommodate a 4000A line rating for the new 230kV line between Elmont - Ladysmith.

Feb 24 2029
Contingent

AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552

N/A
Dominion b4000.327

Upgrade/install equipment at Ladysmith Substation to 4000A. Expansion will be required to accommodate a total of three (3) new 230 kV strings of breaker and a half scheme.

Feb 24 2029
Contingent

AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552

N/A
Dominion b4000.341

Remove the 500 kV conductor previously planned to terminate into the Vint Hill 500 kV Substation and extend approximately 0.2 miles of conductor to fly-over the site.

Jul 13 2029
Contingent

AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552

N/A
Dominion b4000.342

Remove the terminal equipment and substation work required for the termination of the Morrisville-Wishing Star 500 kV line into Vint Hill.

Jul 13 2029
Contingent

AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552

N/A
Dominion b4000.344

Build a 500kV line from North Anna substation (bypassing Ladysmith Substation) to a new substation called Kraken. New conductor to have a minimum summer normal rating of 4357MVA.

Sep 16 2030
Contingent

AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552

N/A
Dominion b4000.345

Build a 500kV line from a new substation called Kraken to a new substation called Yeat. New conductor to have a minimum summer normal rating of 4357MVA.

Sep 16 2030
Contingent

AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552

N/A
Dominion b4000.346

Cut-in 500kV line from Kraken substation into Yeat substation

Jun 01 2029
Contingent

AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552

N/A
Dominion b4000.348

Build a new 500/230kV substation called Kraken. The 500kV, 5000A ring bus will be set up for a redundant breaker configuration. Install (2) 1400MVA 500/230 kV transformers.

Jun 01 2029
Contingent

AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552

N/A
Dominion b4000.349

Update relay settings at Ladysmith to change the destination of 500kV line #568 from Possum Point to Kraken.

Sep 16 2030
Contingent

AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552

N/A
Dominion b4000.350

Update relay settings at Possum Point to change the destination of 500kV line #568 from Ladysmith to Kraken.

Sep 16 2030
Contingent

AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552

N/A
Dominion b4000.351

Cut in Line #568 Ladysmith - Possum Point into Kraken, creating Line #9517 Ladysmith to Kraken.

Sep 16 2030
Contingent

AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552

N/A
Dominion b4000.352

Cut in Line #568 Ladysmith - Possum Point into Kraken, creating new Line #568 Kraken to Possum Point.

Sep 16 2030
Contingent

AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552

N/A
Dominion b4000.355

Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 69.3 miles in AEP section).

Jun 01 2029
Contingent

AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552

N/A
Dominion b4000.356

Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 86.7 miles in Dominion section).

Jun 01 2029
Contingent

AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552

N/A
Dominion b4000.357

Build a new 765/500/230 kV substation called Yeat. Install (2) 765/500 kV transformers. Cut in 500 kV line Bristers-Ox and 500 kV line Meadowbrook-Vint Hill into Yeat.

Jun 01 2029
Contingent

AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552

N/A
Dominion n6144 / dom-173

Rebuild DEV portion 20.5 miles 2-636 ACSR and Rebuild 17.5 miles 2-636 ACSR between 6GREENVILE T - 6EVERETS 230.0 kV substations. Rating after the upgrade: 1047/1047/1204

Nov 25 2026
Contingent

AF2-046, AF2-080, AG1-008, AG1-551

N/A
Dominion n6605 / dom-101

Wreck and rebuild 0.99 miles of line 271 between Pocaty and Landstown with (2)-768 ACSS (20/7) “MAUMEE” conductor @ 250 degrees C. Replace the line lead at Landstown.

Dec 31 2026
$6,555,756

AF1-123, AF1-124, AF1-125, AF2-081

Dominion n6618.1

Split the 115 kV Bus at Hathaway into two separate buses with a 115 kV Line on each bus and close the tie switch between Line 55 & 80.

30 to 36 Months
Contingent

AF2-046, AF2-080, AG1-008

N/A
Dominion n6872 / dom-047

Wreck and rebuild 15.05 miles of 230 kV line No. 238 between Clubhouse and AE2-033 tap with (2) 768.2 ACSS/TW (20/7) at 250C.

Dec 31 2029
$59,572,939

AF2-042, AF2-046, AF2-080, AF2-222, AG1-008, AG1-106, AG1-285

Dominion n7541 / dom-016

Add a third 224 MVA 230/115 kV transformer at Earleys Substation and supporting equipment.

Dec 31 2029
$22,779,395

AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-494, AG1-536

AG1-394, AG1-552

Dominion n7549 / dom-428

Replace Northern Neck 115/230 kV transformer #4 with a 224 MVA (260/271/295 MVA).

59 to 60 Months
$7,324,554

AF2-120, AG1-135, AG1-146, AG1-147, AG1-536

Dominion n7553 / dom-427

Replace Northern Neck 115/230 kV transformer #6 with a 224 MVA (260/271/295 MVA).

59 to 60 Months
$7,242,347

AF2-120, AG1-135, AG1-146, AG1-147, AG1-536

Dominion n7698 / dom-394

Rebuild 4.29 miles of 115 kV line 65 from AD2-074 Tap to AG1-135 Tap with single (1) 768.2 ACSS/TW (20/7) "Maumee" conductor.

43 to 44 Months
$20,146,983

AG1-146, AG1-147

Dominion n9111.0 / dom-094

Wreck and rebuild 3.3 miles of 230 kV transmission line 2092 between S. Hertford and Winfall with (2) 768.2 ACSS/TW (20/7) "MAUMEE" at 250 degrees C and replace line lead at S. Herftord and Winfall

42 to 43 Months
$7,341,167

AF2-046, AF2-080, AG1-008

Dominion n9112.0 / TC1-PH2-DOM-063

Wreck and Rebuild 12.4 miles of 230 kV line 259 with (2) 768.2 ACSS/TW (20/7) "MAUMEE" conductor @ 250 degrees C and replace line lead at Chesterfield.

46 to 47 Months
$87,030,447

AF1-123, AF1-124, AF1-125, AF2-042, AF2-046, AG1-008

Dominion n9136.0 / TC1-PH1-DOM-066

Wreck and rebuild 1.32 miles of 115 kV line from Garner to AG1-135 with 768.2 aluminum conductor steel supported trapezoidal shaped aluminum strands ("ACSS/TW") (20/7). Replace line lead at Garner DP.

42 to 43 Months
$8,145,385

AG1-135, AG1-146, AG1-147

Dominion n9138.0 / TC1-PH1-DOM-070

Wreck and rebuild 22.59 miles of Line #511 between Carson and Rawlings Substations with three (3) 1351 ACSS/TW and associated substation work.

60 to 61 Months
$111,130,292

AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-494, AG1-536

AG1-394, AG1-552

Dominion n9139.0 / TC1-PH1-DOM-073

Wreck and rebuild 37.41 miles of 500kV line 563 between Midlothian and Carson with (3) 1351.5 ACSR (45/7) "Dipper" and associated substation work.

69 to 70 Months
$245,455,768

AF1-123, AF1-124, AF1-125, AF2-042, AF2-046, AG1-008

Dominion n9143.0 / TC1-PH1-DOM-001

Upgrade 1.45 miles of 69 kV line 35 between AltaVista and Gladys Tap with single (1) 768.2 ACSS/TW (20/7) "Maumee" conductor.

20 to 21 Months
$6,315,811

AE2-185, AE2-187, AE2-283

Dominion n9145.0 / TC1-PH1-DOM-008

Reconductor 0.11 miles of 115 kV line between Garner DP and Moon Corner with single (1) 768.2 aluminum conductor steel supported trapezoidal shaped aluminum strands ("ACSS/TW") (20/7).

18 to 19 Months
$2,096,619

AG1-135, AG1-146, AG1-147

Dominion n9146.0 / TC1-PH1-DOM-004

Wreck and rebuild 1.51 miles of 115 kV Line No. 5 between Bremo and Fork Union with (1) 768.2 ACSS/TW (20/7) "MAUMEE" at 250 degrees Celsius. Replace line lead at Bremo.

42 to 43 Months
$7,535,533

AF1-123, AF1-124, AG1-124, AG1-494

Dominion n9151.0 / TC1-PH1-DOM-026

Rebuild 0.76 miles of 115 kV line 93 between Southampton and Watkins Corner with single (1) 768.2 ACSS/TW (20/7) "Maumee" conductor. Replace line lead at Watkins Corner.

42 to 43 Months
$4,174,356

AF2-046, AG1-008, AG1-394

Dominion n9153.0 / TC1-PH1-DOM-043

Wreck and rebuild 5.9 miles of 230 kV line 2128 between Fentress and Thrasher with (2) 768.2 ACSS/TW (20/7) "MAUMEE" conductor @ 250 degrees C and replace line lead at Fentress.

43 to 44 Months
$33,297,247

AE2-156, AF1-123, AF1-124, AF1-125, AF2-081

Dominion n9154.0 / TC1-PH1-DOM-025

Replace switch 9369 at Watkins Corner 115 kV (Watkins Corner - Southampton).

26 to 27 Months
$343,523

AF2-046, AG1-008, AG1-394

Dominion n9191.0 / TC1-PH1-DOM-090

Rebuild 41.13 miles of line 576 between North Anna and Midlothian with triple bundled (3) 1351.5 ACSR (45/7) "Dipper" conductor and associated substation work.

74 to 75 Months
$256,706,175

AF1-123, AF1-124, AF1-125, AF2-042, AF2-046, AG1-008

Dominion n9199.0 / TC1-PH2-DOM-004

Wreck and rebuild 1.63 miles of line 2193 between Fork Union and Bremo with (2) 768.2 ACSS/TW (20/7) "MAUMEE" @ 250C and replace line lead at Bremo.

42 to 43 Months
$7,947,612

AF1-123, AF1-124, AF1-125, AF1-294, AF2-042, AF2-115, AF2-222, AG1-021, AG1-098, AG1-285

Dominion n9200.0 / TC1-PH2-DOM-005

Rebuild 11.79 miles of line 238 between Sapony and Carson with twin bundled (2) 768.2 ACSS/TW (20/7) "Maumee" conductors.

45 to 46 Months
$38,691,326

AF2-042, AF2-046, AF2-080, AF2-222, AG1-008, AG1-106, AG1-285

Dominion n9201.0 / TC1-PH2-DOM-006

Replace wave trap at Carson 230 kV (Carson - Sapony).

14 to 15 Months
$521,941

AF2-042, AF2-046, AF2-080, AF2-222, AG1-008, AG1-106, AG1-285

Dominion n9204.0 / TC1-PH2-DOM-014

Wreck and rebuild 1.63 miles of line 238 between AE2-033 tap and Sapony with (2) 768.2 ACSS/TW (20/7) "MAUMEE" conductor.

42 to 43 Months
$6,764,273

AF2-042, AF2-046, AF2-080, AF2-222, AG1-008, AG1-106, AG1-285

Dominion n9207.0 / TC1-PH2-DOM-018

Replace 6ELMONT 230 kV to 8ELMONT 500 kV circuit 1 with larger transformer (3-480 MVA single phase transformer).

59 to 60 Months
$38,254,469

AE2-156, AF1-123, AF1-124, AF1-125, AF2-035, AF2-046, AF2-081, AF2-120, AG1-008, AG1-146, AG1-147, AG1-536

Dominion n9208.0 / TC1-PH2-DOM-020

Wreck and rebuild 6.87 miles of 115 kV Line 136 from Earleys to Ahoskie with (1) 768.2 ACSS/TW (20/7) "Maumee" conductor @ 250 degrees C. Replace Line Lead at Ahoskie.

43 to 44 Months
$25,503,905

AF2-046, AG1-008, AG1-082

AG1-394

Dominion n9213.0 / TC1-PH2-DOM-024

Reconductor 7.98 miles of 115 kV Line 136 from Tunis to Ahoskie with (1) 768.2 ACSS/TW (20/7) "Maumee" conductor @ 250 degrees C. Upgrade Line Lead at Ahoskie.

43 to 44 Months
$24,308,115

AF2-046, AG1-008

AG1-394

Dominion n9217.0 / TC1-PH2-DOM-028

Wreck and rebuild 12.73 miles of 230 kV Line 298 from Buckingham to Farmville Substations with twin bundled (2) 768 ACSS/TW (20/7) "MAUMEE" conductor.

45 to 46 Months
$40,414,822

AE1-148, AE2-291, AF1-294, AF2-042, AF2-046, AF2-115, AF2-222, AF2-297, AG1-008, AG1-021, AG1-098, AG1-105, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342

Dominion n9220.0 / TC1-PH2-DOM-033

Wreck and rebuild 15.42 miles of 230 kV Line #298 from Buckingham to Bremo Substations with twin bundled (2) 768.2 ACSS/TW (20/7) "MAUMEE" conductor.

42 to 48 Months
$44,465,922

AE1-148, AE2-291, AF1-294, AF2-042, AF2-046, AF2-115, AF2-222, AF2-297, AG1-008, AG1-021, AG1-098, AG1-105, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342

Dominion n9250.0 / TC1-PH2-DOM-044

Construct a new 22.59 mile line between Carson and Rawlings Substations.

60 to 61 Months
$108,728,086

AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-494, AG1-536

AG1-394, AG1-552

Dominion n9252.0 / TC1-PH2-DOM-047

Rebuild 3.81 miles of Line 2021 between Elizabeth City and Shawboro with double bundled (2) 768.2 ACSS/TW (20/7) "Maumee" conductor.

15 to 16 Months
$12,801,638

AF2-046, AF2-080, AG1-008

Dominion n9264.0 / TC1-PH1-DOM-080

Replace Line Lead at Surry for increased rating on Line 567 8SURRY 500 KV to 8CHCKAHM 500 KV ckt 1.

12 to 13 Months
$582,006

AF1-123, AF1-124, AF1-125, AF2-042, AF2-046, AG1-008

Dominion n9265.0 / TC1-PH2-DOM-064

Replace 230 kV wave trap 259WT at Basin 230 kV (Basin - Chesterfield B).

14 to 15 Months
$396,021

AF1-123, AF1-124, AF1-125, AF2-042, AF2-046, AG1-008

Dominion n9266.0 / TC1-PH2-DOM-065

Replace switches 25944 and 25945 at Basin 230 kV (Basin - Chesterfield B).

38 to 39 Months
$701,120

AF1-123, AF1-124, AF1-125, AF2-042, AF2-046, AG1-008

Dominion n9377.0 / TC1-PH3-DOM-004

Upgrade 0.18 miles of 230 kV line 2092 between Pembroke Creek and West Albemarle DP with twin bundled (2) 768.2 ACSS/TW (20/7) "Maumee" conductor.

Dec 31 2029
$2,651,724

AF2-046, AF2-080, AG1-008

Dominion n9378.0 / TC1-PH3-DOM-010

Replace existing 230/500 kV Carson transformer 2 with (4)-480 MVA single phase transformers.

Dec 31 2029
$37,801,301

AF1-123, AF1-124, AF1-125, AF2-042, AF2-222, AG1-098, AG1-153

Dominion n9379.0 / TC1-PH3-DOM-011

Replace existing 230/500 kV Transformer 1 at Midlothian with (4)-480 MVA Single Phase transformers.

Dec 31 2029
$37,836,293

AF1-123, AF1-124, AF1-125, AF2-042, AF2-046, AG1-008

Dominion n9380.0 / TC1-PH3-DOM-012

Replace existing Ladysmith 230/500 kV transformer 1 with four (4) 480 MVA single phase transformers.

Dec 31 2029
$37,587,605

AF2-035, AF2-120, AG1-146, AG1-147, AG1-154, AG1-536

Dominion n9646.0 / TC1-PH3-DOM-005

Upgrade 7.94 miles of 230 kV line 2092 between West Albemarle DP and South Hertford with twin bundled (2) 768.2 ACSS/TW (20/7) "Maumee" conductor. Upgrade line leads at South Hertford.

Mar 31 2029
$14,749,563

AF2-046, AF2-080, AG1-008

Dominion n9651.0 / TC1-PH2-DOM-009

Wreck and rebuild 10.05 miles of 115kV transmission line 1059 between Northern Neck and Moon Corner with (1) 768.2 ACSS/TW (20/7) "MAUMEE" conductor and replace line lead at Moon Corner.

Mar 31 2029
$28,476,954

AF2-120, AG1-135, AG1-146, AG1-147, AG1-536

Dominion n9652.0 / TC1-PH2-DOM-010

Replace Wave Trap at Northern Neck for increased rating of Line 1059 between Northern Neck and Moon Corner

Mar 01 2027
$1,065,776

AF2-120, AG1-135, AG1-146, AG1-147, AG1-536

Dominion n9653.0 / TC1-PH2-DOM-011

Replace Line Switch at Northern Neck for increased rating of Line 1059 between Northern Neck and Moon Corner

Mar 01 2027
$454,326

AF2-120, AG1-135, AG1-146, AG1-147, AG1-536

Dominion s2824

Rebuild 230 kV Line #2056 from Hornertown to Hathaway.

Dec 31 2026
Contingent

AF2-046, AG1-008, AG1-106

N/A
Dominion s3047.2

Install two (2) 1400 MVA 500-230 kV transformers at Vint Hill Substation and loop 500 kV line #535 and #569 into the proposed 500 kV ring bus at Vint Hill Substation.

Jun 30 2029
Contingent

AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552

N/A
Dominion s3222.1

Rebuild approximately 44.3 miles of 230kV Line #246 between Earleys and Suffolk to current 230kV standards. The normal rating of the line conductor will be 1573 MVA.

Dec 31 2028
Contingent

AF2-046, AF2-080, AG1-008

N/A
EKPC n7788.1 / r0071

Rebuild the AE2-071-Summer Shade 69 kV line section using 795 MCM ACSR conductor at 212 degrees F (1.7 miles)

8 to 12 Months
$2,708,000

AF2-365, AG1-070, AG1-071

NextEra b3775.2

Reconductor NEET’s section of Crete(IN/IL border)-St. John 345 kV line (6.95 miles).

May 09 2023
Contingent

AF2-041, AF2-200, AF2-349, AG1-118

N/A
OVEC b3788.2 / B3788.2

Replace limiting station elements at Kyger Creek

Jun 01 2028
Contingent

AF1-088, AF1-204, AF2-008, AF2-407, AG1-297

N/A
OVEC n7881 / OVEC0001a

Sag mitigations to bring the Dearborn – Pierce 345 kV line up to a maximum operating temperature of 311° F

38 Months
$24,006,000

AF2-173, AF2-177, AF2-388, AF2-407, AG1-297, AG1-367, AG1-375, AG1-433

PECO n9371.0 / PECO 220-85

Install OPGW on PECO portion of EDGEMR 5 230.0 kV to LINWOOD85 230.0 kV ckt 1

36 to 60 Months
$232,164

AF2-358, AG1-450

PENELEC n9115.0 / PN-AF1-F-0022

Replace substation conductor at the 115 kV tie at Shawville Substation

14 Months
$509,322

AG1-090, AG1-377, AG1-378

PENELEC n9116.0 / TC1-PN-001.d

Rebuild approximately 11 miles of the Homer City-Shelocta 230 kV line with double bundled 795 kcmil 26/7 ACSS conductor

31 Months
$39,312,233

AF2-010, AF2-050, AG1-090, AG1-377, AG1-378, AG1-548

PENELEC n9119.0 / TC1-PN-003.b

Reconductor/Rebuild the Shelocta – Keystone 230 kV Line, approximately 2.5 miles, with 1272 kcmil 45/7 ACSR 2-conductor

23 Months
$9,533,592

AF2-010, AF2-050, AG1-090, AG1-377, AG1-378, AG1-548

PENELEC n9225.0 / TC1-PN-001.e

Replace 230 kV substation conductor and line drops at Shelocta substation for the Homer City-Shelocta 230 kV line terminal

13 Months
$107,569

AF2-010, AF2-050, AG1-090, AG1-377, AG1-378, AG1-548

PENELEC s3334.1 / PN-2023-030

Replace the existing Shawville 1A Transformer

Dec 31 2026
Contingent

AF2-296, AG1-090, AG1-377, AG1-378

N/A
PENELEC s3335.1 / PN-2024-007

Replace Homer City South 345/230-23kV Transformer (Projected ISD 6/1/2027)

Jun 01 2027
Contingent

AF2-010, AG1-548

N/A

Cost Allocation details for n5769.4 / AEPI0066a


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AE1-172 8.77% $2,738,608
AE1-114 4.95% $1,545,692
AE2-223 4.17% $1,303,031
AE2-341 4.72% $1,474,423
AF1-030 3.14% $980,536
AF1-296 5.75% $1,796,511
AF2-041 7.90% $2,466,685
AF2-095 4.44% $1,386,331
AF2-143 4.05% $1,264,491
AF2-142 4.15% $1,297,117
AF2-199 2.63% $822,194
AF2-200 5.26% $1,644,388
AF2-226 2.30% $718,808
AF2-319 2.30% $718,808
AF2-392 6.39% $1,997,369
AF2-441 4.86% $1,516,634
AG1-118 8.19% $2,559,467
AG1-236 3.82% $1,193,935
AG1-374 6.27% $1,957,299
AG1-462 5.93% $1,851,670

Cost Allocation details for n6497.4 / AEPI0002e/f


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AF1-088 44.70% $541,797
AF2-008 44.70% $541,797
AG1-226 10.59% $128,407

Cost Allocation details for n7757 / AEPI0063a


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AF2-173 20.66% $38,435
AF2-177 22.00% $40,919
AF2-388 21.05% $39,154
AG1-367 14.76% $27,454
AG1-375 11.00% $20,460
AG1-433 10.53% $19,577

Cost Allocation details for n9243.0 / AEPSERG13


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AE1-172 0.21% $411,890
AE2-173 0.08% $157,788
AE2-223 0.24% $473,162
AE2-261 2.37% $4,749,045
AF1-088 42.03% $84,156,828
AF1-204 2.28% $4,569,631
AF2-008 42.03% $84,156,828
AF2-225 0.24% $473,162
AG1-124 1.62% $3,239,450
AG1-226 6.82% $13,662,239
AG1-236 0.17% $339,003
AG1-374 0.44% $879,245
AG1-460 0.24% $476,566
AG1-494 1.25% $2,493,163

Cost Allocation details for n9228.0 / TC1-ATSI-002.b


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AF1-176 59.55% $22,843,720
AF2-396 40.45% $15,518,919

Cost Allocation details for n9322.0 / TE-AG1-S-0012a


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AF1-176 59.54% $838,876
AF2-396 40.46% $570,121

Cost Allocation details for n3515.1 / ce-017


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AF2-041 50.00% $42,354,123
AF2-199 16.67% $14,119,374
AF2-200 33.33% $28,238,748

Cost Allocation details for n5318.1 / ce-012a


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AF2-041 50.00% $81,980,472
AF2-199 16.67% $27,329,404
AF2-200 33.33% $54,658,808

Cost Allocation details for n6639.2 / CE_NUN_L15502_4


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AE1-114 2.96% $4,333,722
AF1-280 9.06% $13,240,386
AF1-296 5.94% $8,676,903
AF2-041 21.49% $31,417,862
AF2-182 13.58% $19,860,480
AF2-199 7.16% $10,472,621
AF2-200 15.92% $23,272,600
AF2-392 7.36% $10,764,846
AG1-462 8.18% $11,961,925
AG1-553 8.34% $12,196,415

Cost Allocation details for n7023.1 / CE_NUN_L11124.1


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AE1-114 3.47% $1,347,650
AE2-341 2.79% $1,081,553
AF1-030 1.86% $721,036
AF1-280 5.85% $2,268,876
AF1-296 4.64% $1,800,625
AF2-041 18.52% $7,185,987
AF2-182 8.77% $3,403,314
AF2-199 6.17% $2,395,305
AF2-200 13.72% $5,322,948
AF2-349 3.40% $1,319,935
AF2-392 6.00% $2,326,344
AG1-118 9.19% $3,565,896
AG1-127 3.05% $1,184,049
AG1-462 6.22% $2,413,200
AG1-553 6.34% $2,460,556

Cost Allocation details for n8162 / CE_NUN_0304.1


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AF2-143 37.50% $1,881,471
AF2-142 37.50% $1,881,556
AF2-226 12.50% $627,185
AF2-319 12.50% $627,185

Cost Allocation details for n9101.0 / CE_NUN_L18806


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AE2-261 39.72% $5,944,195
AG1-236 56.30% $8,425,372
AG1-460 3.99% $596,436

Cost Allocation details for n9165.0 / CE_NUN_L15502.1


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AE1-114 5.35% $65,269
AF1-280 16.34% $199,410
AF1-296 10.71% $130,681
AF2-182 24.51% $299,114
AF2-392 13.28% $162,127
AG1-462 14.76% $180,156
AG1-553 15.05% $183,687

Cost Allocation details for n9166.0 / CE_NUN_L16914.1


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AE1-114 37.98% $229,910
AF2-392 62.02% $375,512

Cost Allocation details for n9195.0 / CE_NUN_STA12_345 NEW CB


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AE1-172 0.21% $6,907
AE2-173 0.08% $2,646
AE2-223 0.24% $7,934
AE2-261 2.37% $79,633
AF1-088 42.03% $1,411,157
AF1-204 2.28% $76,624
AF2-008 42.03% $1,411,157
AF2-225 0.24% $7,934
AG1-124 1.62% $54,320
AG1-226 6.82% $229,091
AG1-236 0.17% $5,684
AG1-374 0.44% $14,743
AG1-460 0.24% $7,991
AG1-494 1.25% $41,806

Cost Allocation details for n9269.0 / CE_NUN_L11212.5


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AE1-172 24.51% $9,311,061
AE2-223 8.44% $3,206,556
AE2-261 8.99% $3,415,726
AF2-041 7.30% $2,771,569
AF2-095 9.09% $3,452,353
AF2-199 2.43% $923,856
AF2-200 5.40% $2,052,947
AF2-225 8.44% $3,206,556
AG1-118 8.65% $3,284,503
AG1-374 15.85% $6,021,866
AG1-460 0.90% $342,662

Cost Allocation details for n6925 / dt22085r0001


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AF2-358 80.00% $57,344,000
AG1-450 20.00% $14,336,000

Cost Allocation details for n6605 / dom-101


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AF1-123 32.55% $2,134,024
AF1-124 32.67% $2,141,694
AF1-125 32.04% $2,100,714
AF2-081 2.74% $179,324

Cost Allocation details for n6872 / dom-047


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AF2-042 21.51% $12,812,988
AF2-046 22.73% $13,541,094
AF2-080 11.29% $6,723,564
AF2-222 7.66% $4,561,293
AG1-008 22.73% $13,541,094
AG1-106 7.68% $4,578,092
AG1-285 6.40% $3,814,814

Cost Allocation details for n7541 / dom-016


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AE1-148 0.57% $128,840
AE2-185 0.03% $7,882
AE2-187 0.03% $6,834
AE2-283 0.03% $6,948
AE2-291 0.54% $122,508
AF1-123 10.21% $2,325,482
AF1-124 10.25% $2,333,865
AF1-125 10.05% $2,289,491
AF1-294 0.41% $93,054
AF2-035 0.26% $59,773
AF2-042 28.18% $6,418,921
AF2-046 2.88% $657,163
AF2-115 0.25% $56,675
AF2-120 4.50% $1,025,552
AF2-222 3.88% $883,728
AF2-297 0.72% $163,215
AG1-008 2.88% $657,163
AG1-021 0.20% $45,331
AG1-082 0.19% $42,666
AG1-098 1.60% $365,131
AG1-105 0.68% $155,333
AG1-124 1.06% $241,895
AG1-135 4.42% $1,006,053
AG1-146 2.12% $483,744
AG1-147 4.96% $1,128,720
AG1-154 0.14% $31,481
AG1-166 0.13% $29,704
AG1-167 0.10% $22,278
AG1-168 0.10% $22,278
AG1-285 2.80% $637,323
AG1-342 0.06% $14,351
AG1-494 0.82% $186,153
AG1-536 4.96% $1,129,859

Cost Allocation details for n7549 / dom-428


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AF2-120 25.26% $1,850,537
AG1-146 8.86% $649,262
AG1-135 23.45% $1,717,897
AG1-147 20.68% $1,514,944
AG1-536 21.73% $1,591,913

Cost Allocation details for n7553 / dom-427


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AF2-120 25.27% $1,829,790
AG1-146 8.86% $642,003
AG1-135 23.45% $1,698,623
AG1-147 20.68% $1,497,932
AG1-536 21.73% $1,574,000

Cost Allocation details for n7698 / dom-394


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG1-146 30.00% $6,044,095
AG1-147 70.00% $14,102,888

Cost Allocation details for n9111.0 / dom-094


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AF2-046 37.90% $2,782,228
AF2-080 24.20% $1,776,711
AG1-008 37.90% $2,782,228

Cost Allocation details for n9112.0 / TC1-PH2-DOM-063


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AF1-123 24.38% $21,216,354
AF1-124 24.47% $21,292,518
AF1-125 24.00% $20,884,900
AF2-042 17.93% $15,607,492
AF2-046 4.61% $4,014,591
AG1-008 4.61% $4,014,591

Cost Allocation details for n9136.0 / TC1-PH1-DOM-066


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG1-146 18.75% $1,527,260
AG1-135 37.50% $3,054,519
AG1-147 43.75% $3,563,606

Cost Allocation details for n9138.0 / TC1-PH1-DOM-070


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AE1-148 0.57% $628,554
AE2-185 0.03% $38,451
AE2-187 0.03% $33,339
AE2-283 0.03% $33,895
AE2-291 0.54% $597,659
AF1-123 10.21% $11,344,969
AF1-124 10.25% $11,385,865
AF1-125 10.05% $11,169,383
AF1-294 0.41% $453,968
AF2-035 0.26% $291,606
AF2-042 28.18% $31,314,992
AF2-046 2.88% $3,206,001
AF2-115 0.25% $276,492
AF2-120 4.50% $5,003,202
AF2-222 3.88% $4,311,304
AF2-297 0.72% $796,249
AG1-008 2.88% $3,206,001
AG1-021 0.20% $221,150
AG1-082 0.19% $208,147
AG1-098 1.60% $1,781,309
AG1-105 0.68% $757,798
AG1-124 1.06% $1,180,094
AG1-135 4.42% $4,908,074
AG1-146 2.12% $2,359,965
AG1-147 4.96% $5,506,511
AG1-154 0.14% $153,582
AG1-166 0.13% $144,914
AG1-167 0.10% $108,686
AG1-168 0.10% $108,686
AG1-285 2.80% $3,109,206
AG1-342 0.06% $70,012
AG1-494 0.82% $908,158
AG1-536 4.96% $5,512,068

Cost Allocation details for n9139.0 / TC1-PH1-DOM-073


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AF1-123 25.59% $62,801,501
AF1-124 25.68% $63,027,667
AF1-125 25.19% $61,821,552
AF2-042 16.42% $40,306,135
AF2-046 3.56% $8,749,456
AG1-008 3.56% $8,749,456

Cost Allocation details for n9143.0 / TC1-PH1-DOM-001


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AE2-187 36.00% $2,273,682
AE2-185 36.00% $2,273,682
AE2-283 28.00% $1,768,447

Cost Allocation details for n9145.0 / TC1-PH1-DOM-008


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG1-146 18.75% $393,116
AG1-135 37.50% $786,232
AG1-147 43.75% $917,271

Cost Allocation details for n9146.0 / TC1-PH1-DOM-004


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AF1-123 22.17% $1,670,261
AF1-124 22.23% $1,675,225
AG1-124 30.94% $2,331,168
AG1-494 24.67% $1,858,879

Cost Allocation details for n9151.0 / TC1-PH1-DOM-026


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AF2-046 47.33% $1,975,844
AG1-008 47.33% $1,975,844
AG1-394 5.33% $222,668

Cost Allocation details for n9153.0 / TC1-PH1-DOM-043


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AE2-156 1.60% $532,572
AF1-123 32.41% $10,791,567
AF1-124 32.53% $10,830,584
AF1-125 31.90% $10,623,251
AF2-081 1.56% $519,272

Cost Allocation details for n9154.0 / TC1-PH1-DOM-025


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AF2-046 47.33% $162,599
AG1-008 47.33% $162,599
AG1-394 5.33% $18,324

Cost Allocation details for n9191.0 / TC1-PH1-DOM-090


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AF1-123 21.00% $53,907,719
AF1-124 21.07% $54,099,119
AF1-125 20.68% $53,077,275
AF2-042 24.47% $62,827,757
AF2-046 6.39% $16,397,152
AG1-008 6.39% $16,397,152

Cost Allocation details for n9199.0 / TC1-PH2-DOM-004


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AF1-123 18.64% $1,481,048
AF1-124 18.70% $1,486,238
AF1-125 18.35% $1,458,123
AF1-294 3.00% $238,032
AF2-042 15.68% $1,246,476
AF2-115 1.82% $144,731
AF2-222 11.14% $885,125
AG1-021 1.46% $115,793
AG1-098 4.73% $375,582
AG1-285 6.50% $516,464

Cost Allocation details for n9200.0 / TC1-PH2-DOM-005


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AF2-042 21.50% $8,318,848
AF2-046 22.73% $8,796,073
AF2-080 11.29% $4,367,336
AF2-222 7.65% $2,961,588
AG1-008 22.73% $8,796,073
AG1-106 7.69% $2,974,209
AG1-285 6.40% $2,477,200

Cost Allocation details for n9201.0 / TC1-PH2-DOM-006


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AF2-042 29.47% $153,825
AF2-046 16.25% $84,819
AF2-080 8.22% $42,911
AF2-222 10.49% $54,763
AG1-008 16.25% $84,819
AG1-106 10.54% $54,997
AG1-285 8.78% $45,806

Cost Allocation details for n9204.0 / TC1-PH2-DOM-014


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AF2-042 21.51% $1,454,864
AF2-046 22.73% $1,537,538
AF2-080 11.29% $763,434
AF2-222 7.66% $517,917
AG1-008 22.73% $1,537,538
AG1-106 7.68% $519,824
AG1-285 6.40% $433,157

Cost Allocation details for n9207.0 / TC1-PH2-DOM-018


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AE2-156 3.14% $1,200,552
AF1-123 25.73% $9,843,658
AF1-124 25.82% $9,879,089
AF1-125 25.33% $9,689,986
AF2-035 2.40% $919,947
AF2-046 3.34% $1,278,517
AF2-081 2.45% $936,743
AF2-120 2.18% $834,462
AG1-008 3.34% $1,278,517
AG1-146 1.08% $415,058
AG1-147 2.53% $968,497
AG1-536 2.64% $1,009,443

Cost Allocation details for n9208.0 / TC1-PH2-DOM-020


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AF2-046 46.32% $11,814,327
AG1-008 46.32% $11,814,327
AG1-082 7.35% $1,875,251

Cost Allocation details for n9213.0 / TC1-PH2-DOM-024


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AF2-046 50.00% $12,154,058
AG1-008 50.00% $12,154,058

Cost Allocation details for n9217.0 / TC1-PH2-DOM-028


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AE1-148 4.66% $1,882,945
AE2-291 2.92% $1,180,510
AF1-294 3.83% $1,546,403
AF2-042 35.22% $14,232,311
AF2-046 1.11% $446,981
AF2-115 2.33% $942,910
AF2-222 14.00% $5,658,416
AF2-297 3.96% $1,599,881
AG1-008 1.11% $446,981
AG1-021 1.87% $754,345
AG1-098 8.23% $3,325,703
AG1-105 5.09% $2,056,965
AG1-166 1.87% $754,345
AG1-167 1.40% $565,781
AG1-168 1.40% $565,781
AG1-285 9.03% $3,650,487
AG1-342 1.99% $804,077

Cost Allocation details for n9220.0 / TC1-PH2-DOM-033


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AE1-148 4.66% $2,071,550
AE2-291 2.92% $1,298,541
AF1-294 3.83% $1,701,484
AF2-042 35.22% $15,659,361
AF2-046 1.11% $491,410
AF2-115 2.33% $1,037,548
AF2-222 14.00% $6,225,961
AF2-297 3.96% $1,760,142
AG1-008 1.11% $491,410
AG1-021 1.87% $830,039
AG1-098 8.23% $3,659,167
AG1-105 5.09% $2,263,149
AG1-166 1.87% $830,039
AG1-167 1.40% $622,529
AG1-168 1.40% $622,529
AG1-285 9.03% $4,016,486
AG1-342 1.99% $884,576

Cost Allocation details for n9250.0 / TC1-PH2-DOM-044


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AE1-148 0.57% $614,967
AE2-185 0.03% $37,620
AE2-187 0.03% $32,618
AE2-283 0.03% $33,162
AE2-291 0.54% $584,740
AF1-123 10.21% $11,099,735
AF1-124 10.25% $11,139,747
AF1-125 10.05% $10,927,945
AF1-294 0.41% $444,155
AF2-035 0.26% $285,303
AF2-042 28.18% $30,638,083
AF2-046 2.88% $3,136,700
AF2-115 0.25% $270,516
AF2-120 4.50% $4,895,052
AF2-222 3.88% $4,218,110
AF2-297 0.72% $779,038
AG1-008 2.88% $3,136,700
AG1-021 0.20% $216,369
AG1-082 0.19% $203,648
AG1-098 1.60% $1,742,804
AG1-105 0.68% $741,418
AG1-124 1.06% $1,154,585
AG1-135 4.42% $4,801,981
AG1-146 2.12% $2,308,952
AG1-147 4.96% $5,387,482
AG1-154 0.14% $150,262
AG1-166 0.13% $141,782
AG1-167 0.10% $106,336
AG1-168 0.10% $106,336
AG1-285 2.80% $3,041,997
AG1-342 0.06% $68,499
AG1-494 0.82% $888,527
AG1-536 4.96% $5,392,918

Cost Allocation details for n9252.0 / TC1-PH2-DOM-047


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AF2-046 38.13% $4,881,712
AF2-080 23.73% $3,038,213
AG1-008 38.13% $4,881,712

Cost Allocation details for n9264.0 / TC1-PH1-DOM-080


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AF1-123 27.69% $161,155
AF1-124 27.79% $161,735
AF1-125 27.26% $158,640
AF2-042 11.00% $64,014
AF2-046 3.13% $18,231
AG1-008 3.13% $18,231

Cost Allocation details for n9265.0 / TC1-PH2-DOM-064


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AF1-123 20.60% $81,561
AF1-124 20.67% $81,854
AF1-125 20.28% $80,304
AF2-042 23.31% $92,294
AF2-046 7.58% $30,005
AG1-008 7.58% $30,005

Cost Allocation details for n9266.0 / TC1-PH2-DOM-065


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AF1-123 24.38% $170,920
AF1-124 24.47% $171,533
AF1-125 24.00% $168,249
AF2-042 17.93% $125,734
AF2-046 4.61% $32,342
AG1-008 4.61% $32,342

Cost Allocation details for n9377.0 / TC1-PH3-DOM-004


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AF2-046 37.90% $1,004,977
AF2-080 24.20% $641,771
AG1-008 37.90% $1,004,977

Cost Allocation details for n9378.0 / TC1-PH3-DOM-010


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AF1-123 20.89% $7,898,102
AF1-124 20.97% $7,926,605
AF1-125 20.57% $7,774,931
AF2-042 23.75% $8,977,853
AF2-222 4.87% $1,839,139
AG1-098 4.36% $1,648,056
AG1-153 4.59% $1,736,617

Cost Allocation details for n9379.0 / TC1-PH3-DOM-011


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AF1-123 19.32% $7,309,853
AF1-124 19.39% $7,335,865
AF1-125 19.02% $7,197,262
AF2-042 30.09% $11,386,412
AF2-046 6.09% $2,303,450
AG1-008 6.09% $2,303,450

Cost Allocation details for n9380.0 / TC1-PH3-DOM-012


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AF2-035 31.43% $11,814,141
AF2-120 10.97% $4,123,504
AG1-146 5.18% $1,945,994
AG1-147 12.08% $4,541,173
AG1-154 27.07% $10,174,751
AG1-536 13.27% $4,988,042

Cost Allocation details for n9646.0 / TC1-PH3-DOM-005


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AF2-046 37.90% $5,589,935
AF2-080 24.20% $3,569,693
AG1-008 37.90% $5,589,935

Cost Allocation details for n9651.0 / TC1-PH2-DOM-009


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AF2-120 20.88% $5,944,669
AG1-146 10.10% $2,876,462
AG1-135 20.20% $5,752,924
AG1-147 23.57% $6,711,745
AG1-536 25.25% $7,191,155

Cost Allocation details for n9652.0 / TC1-PH2-DOM-010


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AF2-120 20.88% $222,485
AG1-146 10.10% $107,654
AG1-135 20.20% $215,308
AG1-147 23.57% $251,193
AG1-536 25.25% $269,136

Cost Allocation details for n9653.0 / TC1-PH2-DOM-011


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AF2-120 20.88% $94,842
AG1-146 10.10% $45,892
AG1-135 20.20% $91,783
AG1-147 23.57% $107,080
AG1-536 25.25% $114,729

Cost Allocation details for n7788.1 / r0071


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AF2-365 22.81% $617,704
AG1-070 34.74% $940,667
AG1-071 42.45% $1,149,629

Cost Allocation details for n7881 / OVEC0001a


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AF2-173 10.11% $2,426,183
AF2-177 11.72% $2,812,841
AF2-388 11.37% $2,730,442
AF2-407 18.83% $4,519,578
AG1-297 29.21% $7,012,206
AG1-367 7.22% $1,733,015
AG1-375 5.86% $1,406,420
AG1-433 5.69% $1,365,315

Cost Allocation details for n9371.0 / PECO 220-85


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AF2-358 80.00% $185,731
AG1-450 20.00% $46,433

Cost Allocation details for n9115.0 / PN-AF1-F-0022


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG1-090 70.37% $358,407
AG1-377 14.82% $75,458
AG1-378 14.82% $75,458

Cost Allocation details for n9116.0 / TC1-PN-001.d


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AF2-010 14.90% $5,856,899
AF2-050 20.44% $8,035,867
AG1-090 25.20% $9,907,383
AG1-377 5.31% $2,085,966
AG1-378 5.31% $2,085,966
AG1-548 28.85% $11,340,151

Cost Allocation details for n9119.0 / TC1-PN-003.b


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AF2-010 14.84% $1,414,685
AF2-050 18.98% $1,809,150
AG1-090 26.51% $2,527,327
AG1-377 5.58% $532,018
AG1-378 5.58% $532,018
AG1-548 28.51% $2,718,394

Cost Allocation details for n9225.0 / TC1-PN-001.e


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AF2-010 14.90% $16,026
AF2-050 20.44% $21,988
AG1-090 25.20% $27,109
AG1-377 5.31% $5,708
AG1-378 5.31% $5,708
AG1-548 28.85% $31,030

Short Circuit Reinforcements

PJM performed short circuit analysis for the New Service Requests in Transition Cycle 1 Phase III. The table below shows all the system reinforcements identified from short circuit analysis.

TO RTEP ID / TO ID Title Time Estimate Total Cost Estimate ($) Projects with Cost Allocation Contingent Projects Facilities Study
Dominion b1696

Install a breaker and a half scheme with a minimum of eight 230 kV breakers for five existing lines at Idylwood 230 kV: 20212 and 20712

TBD
Contingent

AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552

N/A
Dominion b3689.2

Replace 230 kV breakers SC102, H302, H402 and 218302 at Brambleton substation with 80 kA

Mar 31 2027
Contingent

AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552

N/A
Dominion b3800.235

Replace 5 overdutied 230kV breakers at Loudoun substation with 80kA breakers

Oct 05 2031
Contingent

AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552

N/A
Dominion b3800.236

Replace 2 overdutied 500kV breakers at Ox Substation with 63kA breakers.

Jan 05 2029
Contingent

AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552

N/A
Dominion b3800.334

Replace four (4) overdutied 230 kV breakers at Loudoun Substation with 80 kA breakers.

Oct 05 2031
Contingent

AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552

N/A
Dominion b3800.335

Replace 1 overdutied 500kV breaker at Ox Substation with a 63kA breaker

Dec 15 2031
Contingent

AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552

N/A
Dominion b3800.405

Replace Brambleton 230 kV breakers 20102, 20602, 204502, 209402, 201T2045, 206T2094 with breakers rated 80 kA.

Jan 08 2031
Contingent

AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552

N/A
Dominion b3800.406

Replace Gainesville 230 kV breaker 216192 with a breaker rated 80 kA.

Mar 15 2030
Contingent

AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552

N/A
Dominion b3800.407

Replace Loudoun 230 kV breakers 204552 and 217352 with breakers rated 80 kA.

Oct 05 2031
Contingent

AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552

N/A
Dominion b3800.408

Replace Ox 230 kV breakers 22042, 24342, 24842, 220T2063, 243T2097, 248T2013, and H342 with breakers rated 80 kA.

Apr 21 2031
Contingent

AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552

N/A
Dominion b3853.1 / (Pending)

Replace over duty Ladysmith CT 230kV circuit breakers SX1272 and SX3472 with an interrupting rating of 63 kA

TBD
Contingent

AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552

N/A
Dominion b3854.1

Replace over duty Carson 230kV circuit breakers 200272 and 24972-3 with an interrupting rating of 63 kA

May 03 2025
Contingent

AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552

N/A
Dominion b4000.103

Brambleton Sub 230kV - replace 63kA breakers 217202, 2172T2183, L102, L202 with 80kA

Jun 01 2028
Contingent

AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552

N/A
Dominion b4000.108

Carson Sub 230kV - replace 40kA breaker 23872 with 63kA

Jul 12 2029
Contingent

AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552

N/A
Dominion b4000.114

Ladysmith S1 Sub 230kV - replace 40kA breakers 25672, 209072, 256T2090, GT172, GT272, GT372, GT472, GT572 with 63kA

Jul 18 2030
Contingent

AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552

N/A
Dominion b4000.115

Ladysmith Sub 500kV - replace 40kA breaker 574T581 with 63kA

Nov 27 2031
Contingent

AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552

N/A
Dominion b4000.119

Loudoun Cap Substation 230kV - replace 50 kA breaker SC352 with 63 kA.

Oct 31 2030
Contingent

AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552

N/A
Dominion b4000.128

North Anna Substation 500 kV - replace 40 kA breakers 57502, G102-1, G102-2, G202, G2T575, and XT573 with 63 kA.

Oct 13 2032
Contingent

AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552

N/A
Dominion b4000.134

Remington Substation 230 kV - replace 40 kA and 50 kA breakers 211462, GT162, GT262, GT362, GT462, 2077T2086, 208662, H962, and H9T299 with 63 kA.

Jan 09 2031
Contingent

AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552

N/A
Dominion b4000.354

Ladysmith substation breakers replacement: 574T575 and 568T581

Nov 14 2029
Contingent

AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552

N/A
Dominion n6588 / TC1-PH2-DOM-034

Replace 230 kV breaker 210512 at Yadkin 230 kV with a 63 kA breaker.

Dec 01 2028
$1,725,040

AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-494, AG1-536

AG1-394, AG1-552

Dominion s2609.6

Upgrade two (2) 230 kV breakers 201342 and L142 from 50 kA to 63 kA at Ox Substation due to an insufficient breaker duty rating with the expansion in place.

Dec 15 2030
Contingent

AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552

N/A
Dominion s2609.9

Upgrade 230 kV Pleasant View breakers L3T203 and L3T2180 from 50 kA to 80 kA.

Sep 13 2030
Contingent

AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-394, AG1-494, AG1-536, AG1-552

N/A

Cost Allocation details for n6588 / TC1-PH2-DOM-034


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AE1-148 0.57% $9,757
AE2-187 0.03% $518
AE2-185 0.03% $597
AE2-283 0.03% $526
AE2-291 0.54% $9,277
AF1-123 10.21% $176,104
AF1-124 10.25% $176,739
AF1-125 10.05% $173,379
AF1-294 0.41% $7,047
AF2-035 0.26% $4,527
AF2-042 28.18% $486,093
AF2-046 2.88% $49,766
AF2-115 0.25% $4,292
AF2-120 4.50% $77,663
AF2-222 3.88% $66,923
AF2-297 0.72% $12,360
AG1-008 2.88% $49,766
AG1-021 0.20% $3,433
AG1-082 0.19% $3,231
AG1-098 1.60% $27,651
AG1-105 0.68% $11,763
AG1-124 1.06% $18,318
AG1-146 2.12% $36,633
AG1-135 4.42% $76,186
AG1-147 4.96% $85,476
AG1-154 0.14% $2,384
AG1-166 0.13% $2,249
AG1-167 0.10% $1,687
AG1-168 0.10% $1,687
AG1-285 2.80% $48,263
AG1-342 0.06% $1,087
AG1-494 0.82% $14,097
AG1-536 4.96% $85,562

Stability Reinforcements

PJM performed stability analysis for the New Service Requests in Transition Cycle 1 Phase III. The table below shows all the system reinforcements identified from stability analysis.

TO RTEP ID / TO ID Title Time Estimate Total Cost Estimate ($) Projects with Cost Allocation Contingent Projects Facilities Study
DPL n9645.0 / (Pending)

Install 10 MVAR Cap Bank at new AF2-358 69kV Interconnection Swyd

Jun 01 2027
$2,479,762

AF2-358, AG1-450

Dominion n8492

Wreck and rebuild the existing Yadkin to Fentress 500 kV Line #588 to share the right of way with the new Yadkin to Fentress #5005 line.

26 to 27 Months
$80,172,278

AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-494, AG1-536

AG1-394, AG1-552

Dominion n8492.1

Two Breaker Additions at Fentress Substation.

30 to 36 Months
$19,945,879

AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-494, AG1-536

AG1-394, AG1-552

Dominion n8492.2

Expand Yadkin Substation to accommodate the new 500 kV line.

15 to 16 Months
$16,207,123

AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-494, AG1-536

AG1-394, AG1-552

Dominion n9259.0

Install two 230 kV gas insulated switchgear ("GIS") bus ties for the Coastal Virginia Offshore Wind ("CVOW") project.

38 to 39 Months
$25,304,902

AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-494, AG1-536

AG1-394, AG1-552

Dominion n9267.0 / TC1-PH2-DOM-067

Construct new 10.21 mile 115 kV line between Northern Neck and Moon Corner.

45 to 46 Months
$45,730,074

AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-494, AG1-536

AG1-394, AG1-552

Dominion n9630.0 / TC1-PH3-DOM-013

Construct a new 230 kV line from the AG1-285 substation to the Finneywood 230 kV Substation. Expand AG1-285 substation and add two (2) new 230/115 kV transformers.

Dec 31 2029
$89,468,616

AE1-148, AE2-185, AE2-187, AE2-283, AE2-291, AF1-123, AF1-124, AF1-125, AF1-294, AF2-035, AF2-042, AF2-046, AF2-115, AF2-120, AF2-222, AF2-297, AG1-008, AG1-021, AG1-082, AG1-098, AG1-105, AG1-124, AG1-135, AG1-146, AG1-147, AG1-154, AG1-166, AG1-167, AG1-168, AG1-285, AG1-342, AG1-494, AG1-536

AG1-394, AG1-552

Dominion n9647.0

Install a 300 MVAR STATCOM at Fentress Substation.

Mar 31 2029
$49,163,341

AF1-123, AF1-124, AF1-125

Cost Allocation details for n9645.0 / (Pending)


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AF2-358 44.44% $1,102,116
AG1-450 55.56% $1,377,646

Cost Allocation details for n8492


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AE1-148 0.57% $453,455
AE2-185 0.03% $27,740
AE2-187 0.03% $24,052
AE2-283 0.03% $24,453
AE2-291 0.54% $431,167
AF1-123 10.21% $8,184,556
AF1-124 10.25% $8,214,059
AF1-125 10.05% $8,057,883
AF1-294 0.41% $327,504
AF2-035 0.26% $210,372
AF2-042 28.18% $22,591,448
AF2-046 2.88% $2,312,892
AF2-115 0.25% $199,469
AF2-120 4.50% $3,609,440
AF2-222 3.88% $3,110,287
AF2-297 0.72% $574,435
AG1-008 2.88% $2,312,892
AG1-021 0.20% $159,543
AG1-082 0.19% $150,163
AG1-098 1.60% $1,285,083
AG1-105 0.68% $546,695
AG1-124 1.06% $851,350
AG1-135 4.42% $3,540,812
AG1-146 2.12% $1,702,540
AG1-147 4.96% $3,972,540
AG1-154 0.14% $110,798
AG1-166 0.13% $104,545
AG1-167 0.10% $78,409
AG1-168 0.10% $78,409
AG1-285 2.80% $2,243,062
AG1-342 0.06% $50,509
AG1-494 0.82% $655,169
AG1-536 4.96% $3,976,549

Cost Allocation details for n8492.1


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AE1-148 0.57% $112,814
AE2-185 0.03% $6,901
AE2-187 0.03% $5,984
AE2-283 0.03% $6,083
AE2-291 0.54% $107,269
AF1-123 10.21% $2,036,217
AF1-124 10.25% $2,043,557
AF1-125 10.05% $2,004,702
AF1-294 0.41% $81,479
AF2-035 0.26% $52,338
AF2-042 28.18% $5,620,475
AF2-046 2.88% $575,419
AF2-115 0.25% $49,625
AF2-120 4.50% $897,984
AF2-222 3.88% $773,801
AF2-297 0.72% $142,912
AG1-008 2.88% $575,419
AG1-021 0.20% $39,692
AG1-082 0.19% $37,359
AG1-098 1.60% $319,713
AG1-105 0.68% $136,011
AG1-124 1.06% $211,806
AG1-135 4.42% $880,911
AG1-146 2.12% $423,571
AG1-147 4.96% $988,319
AG1-154 0.14% $27,565
AG1-166 0.13% $26,009
AG1-167 0.10% $19,507
AG1-168 0.10% $19,507
AG1-285 2.80% $558,046
AG1-342 0.06% $12,566
AG1-494 0.82% $162,998
AG1-536 4.96% $989,317

Cost Allocation details for n8492.2


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AE1-148 0.57% $91,668
AE2-185 0.03% $5,608
AE2-187 0.03% $4,862
AE2-283 0.03% $4,943
AE2-291 0.54% $87,162
AF1-123 10.21% $1,654,538
AF1-124 10.25% $1,660,502
AF1-125 10.05% $1,628,931
AF1-294 0.41% $66,206
AF2-035 0.26% $42,528
AF2-042 28.18% $4,566,945
AF2-046 2.88% $467,560
AF2-115 0.25% $40,323
AF2-120 4.50% $729,662
AF2-222 3.88% $628,756
AF2-297 0.72% $116,124
AG1-008 2.88% $467,560
AG1-021 0.20% $32,252
AG1-082 0.19% $30,356
AG1-098 1.60% $259,784
AG1-105 0.68% $110,516
AG1-124 1.06% $172,104
AG1-135 4.42% $715,788
AG1-146 2.12% $344,175
AG1-147 4.96% $803,064
AG1-154 0.14% $22,398
AG1-166 0.13% $21,134
AG1-167 0.10% $15,851
AG1-168 0.10% $15,851
AG1-285 2.80% $453,443
AG1-342 0.06% $10,210
AG1-494 0.82% $132,445
AG1-536 4.96% $803,874

Cost Allocation details for n9259.0


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AE1-148 0.57% $143,125
AE2-185 0.03% $8,756
AE2-187 0.03% $7,591
AE2-283 0.03% $7,718
AE2-291 0.54% $136,090
AF1-123 10.21% $2,583,304
AF1-124 10.25% $2,592,616
AF1-125 10.05% $2,543,322
AF1-294 0.41% $103,371
AF2-035 0.26% $66,400
AF2-042 28.18% $7,130,574
AF2-046 2.88% $730,022
AF2-115 0.25% $62,959
AF2-120 4.50% $1,139,253
AF2-222 3.88% $981,705
AF2-297 0.72% $181,310
AG1-008 2.88% $730,022
AG1-021 0.20% $50,357
AG1-082 0.19% $47,396
AG1-098 1.60% $405,613
AG1-105 0.68% $172,554
AG1-124 1.06% $268,713
AG1-135 4.42% $1,117,592
AG1-146 2.12% $537,375
AG1-147 4.96% $1,253,859
AG1-154 0.14% $34,971
AG1-166 0.13% $32,998
AG1-167 0.10% $24,748
AG1-168 0.10% $24,748
AG1-285 2.80% $707,981
AG1-342 0.06% $15,942
AG1-494 0.82% $206,792
AG1-536 4.96% $1,255,124

Cost Allocation details for n9267.0 / TC1-PH2-DOM-067


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AE1-148 0.57% $258,650
AE2-185 0.03% $15,823
AE2-187 0.03% $13,719
AE2-283 0.03% $13,948
AE2-291 0.54% $245,937
AF1-123 10.21% $4,668,451
AF1-124 10.25% $4,685,279
AF1-125 10.05% $4,596,197
AF1-294 0.41% $186,808
AF2-035 0.26% $119,996
AF2-042 28.18% $12,886,108
AF2-046 2.88% $1,319,268
AF2-115 0.25% $113,777
AF2-120 4.50% $2,058,816
AF2-222 3.88% $1,774,100
AF2-297 0.72% $327,656
AG1-008 2.88% $1,319,268
AG1-021 0.20% $91,003
AG1-082 0.19% $85,653
AG1-098 1.60% $733,008
AG1-105 0.68% $311,834
AG1-124 1.06% $485,608
AG1-135 4.42% $2,019,671
AG1-146 2.12% $971,125
AG1-147 4.96% $2,265,927
AG1-154 0.14% $63,199
AG1-166 0.13% $59,632
AG1-167 0.10% $44,724
AG1-168 0.10% $44,724
AG1-285 2.80% $1,279,437
AG1-342 0.06% $28,810
AG1-494 0.82% $373,707
AG1-536 4.96% $2,268,214

Cost Allocation details for n9630.0 / TC1-PH3-DOM-013


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AE1-148 0.57% $506,035
AE2-185 0.03% $30,956
AE2-187 0.03% $26,841
AE2-283 0.03% $27,288
AE2-291 0.54% $481,163
AF1-123 10.21% $9,133,592
AF1-124 10.25% $9,166,516
AF1-125 10.05% $8,992,231
AF1-294 0.41% $365,480
AF2-035 0.26% $234,766
AF2-042 28.18% $25,211,029
AF2-046 2.88% $2,581,083
AF2-115 0.25% $222,598
AF2-120 4.50% $4,027,971
AF2-222 3.88% $3,470,938
AF2-297 0.72% $641,043
AG1-008 2.88% $2,581,083
AG1-021 0.20% $178,043
AG1-082 0.19% $167,575
AG1-098 1.60% $1,434,094
AG1-105 0.68% $610,087
AG1-124 1.06% $950,068
AG1-135 4.42% $3,951,385
AG1-146 2.12% $1,899,957
AG1-147 4.96% $4,433,174
AG1-154 0.14% $123,646
AG1-166 0.13% $116,667
AG1-167 0.10% $87,500
AG1-168 0.10% $87,500
AG1-285 2.80% $2,503,155
AG1-342 0.06% $56,365
AG1-494 0.82% $731,138
AG1-536 4.96% $4,437,648

Cost Allocation details for n9647.0


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AF1-123 33.47% $16,453,621
AF1-124 33.59% $16,512,878
AF1-125 32.94% $16,196,842

[1]Winter load flow analysis will be performed starting in Transition Cycle 2.

[2]State - The state in which the generator or merchant transmission facility is located.

[3]The Transmission Owner of the facility where the New Service Request project interconnects to the transmission system.

Note: Additional detail can be found in each of the individual TC1 New Service Request System Impact Study reports also available on PJM.com.