Redacted Public Proposals for Current and Closed Windows


Proposal ID Target Zone(s) Analysis Type Flowgates Comments
441 Dominion End of Life Criteria DOM-O5 Rebuild 500 kV Line #514 Goose Creek – Doubs(FE)

Proposal ID Target Zone(s) Analysis Type Flowgates Comments
574 ComEd Winter Generation Deliverability GD-W252, GD-W253, GD-W257, GD-W258 Install two (2) 765 kV circuit breakers at Wilton Center substation and move the Collins line exit to a new bus position
640 Dominion Summer N-1 & N-1-1 Themal, Gen Deliv Violations N1-ST46, GD-S5, GD-S7, N2-ST69, N2-ST70, N2-ST71 Increase the maximum operating temperature of 230 kV line 227
800 Dominion Summer N-1 & N-1-1 Themal, Gen Deliv Violations N1-ST46, GD-S5, GD-S7, N2-ST69, N2-ST70, N2-ST71 Reconductor 230 kV Line 227 between Pleasant View Junction and Beaumeade
418 Dominion Summer N-1 & N-1-1 Themal, Gen Deliv Violations N1-ST46, GD-S5, GD-S7, N2-ST69, N2-ST70, N2-ST71 Rebuild 230 kV Line 227 Cochran Mill DP - Pleasant View Junction and reconductor Pleasant View Junction - Beaumeade and Cochran Mill DP - Belmont
626 DPL Summer & Winter Generation Deliverablity  GD-S537, GD-S538, GD-W441, GD-W442 Install a series reactor on the Silverside-Darley 69 kV line
820 DPL Summer & Winter Generation Deliverablity  GD-S537, GD-S538, GD-W441, GD-W442 Install a SmartWire device in series with the Silverside-Darley 69 kV line
673 DPL Summer & Winter Generation Deliverablity  GD-S537, GD-S538, GD-W441, GD-W442 Reconductor Silverside-Darley and Darley-Naamans 69 kV lines and upgrade terminal equipment
174 DPL Summer & Winter Generation Deliverablity  GD-S537, GD-S538, GD-W441, GD-W442 Build a new 69 kV line Edge Moor-Claymont
36 DPL Summer & Winter Generation Deliverablity  GD-S537, GD-S538, GD-W441, GD-W442 Build a new substation near Linwood Substation (PECO), build a in 230 kV line to Edge Moor and tap the Chichester-Linwood 230 kV Line (PECO).
522 DPL Summer & Winter Generation Deliverablity  GD-S537, GD-S538, GD-W441, GD-W442 Build new 230 kV line Edge Moor-Chichester
637 DPL Summer & Winter Generation Deliverablity  GD-S537, GD-S538, GD-W441, GD-W442 Build new substation near Linwood Substation (PECO), build a new 230 kV line to Harmony, and tap the Chichester-Linwood 230 kV Line (PECO).
839 DPL Summer & Winter Generation Deliverablity  GD-S537, GD-S538, GD-W441, GD-W442 Build a new 230 kV line Harmony-Chichester
702 APS Summer & Winter N-1-1 Voltage Violations  N2-SVM1, N2-SVM2, N2-SVM3, N2-SVM4, N2-SVM5, N2-SVM6, N2-SVM7, N2-SVM8, N2-SVM9, N2-SVM10, N2-SVM11, N2-SVM12, N2-SVM13, N2-WVM1, N2-WVM2, N2-WVM3, N2-WVM4, N2-WVM5, N2-WVM6, N2-WVD1, N2-WVD2, N2-WVD3, N2-WVD4, N2-WVD5, N2-WVD6, N2-WVD7, N2-WVD8, N2-WVD9, N2-WVD10 Reconfigure Stonewall 138 kV substation to a six-breaker breaker-and-a-half layout and install two (2) 36 MVAR capacitors
620 APS Summer & Winter N-1-1 Voltage Violations  N2-SVM1, N2-SVM2, N2-SVM3, N2-SVM4, N2-SVM5, N2-SVM6, N2-SVM7, N2-SVM8, N2-SVM9, N2-SVM10, N2-SVM11, N2-SVM12, N2-SVM13, N2-WVM1, N2-WVM2, N2-WVM3, N2-WVM4, N2-WVM5, N2-WVM6, N2-WVD1, N2-WVD2, N2-WVD3, N2-WVD4, N2-WVD5, N2-WVD6, N2-WVD7, N2-WVD8, N2-WVD9, N2-WVD10 Reconfigure Hampshire 138 kV switching station to a networked ring bus. Install one (1) 34.6 MVAR capacitor at Inwood
788 APS Summer & Winter N-1-1 Voltage Violations N2-SVM1, N2-SVM2, N2-SVM3, N2-SVM4, N2-SVM5, N2-SVM6, N2-SVM7, N2-SVM8, N2-SVM9, N2-SVM10, N2-SVM11, N2-SVM12, N2-SVM13, N2-WVM1, N2-WVM2, N2-WVM3, N2-WVM4, N2-WVM5, N2-WVM6, N2-WVD1, N2-WVD2, N2-WVD3, N2-WVD4, N2-WVD5, N2-WVD6, N2-WVD7, N2-WVD8, N2-WVD9, N2-WVD10 Build a new 500/138 kV station (Woodside) tapping Doubs-Bismark 500 kV, Stonewall-Feagan’s Mill 138 kV and Stonewall-Inwood 138 kV lines

Proposal ID Target Zone(s) Analysis Type Congestion Driver Major Component/Project Description
469 MetEd Market Efficiency ME-1 Install a SmartWires Device on the Lincoln - Hunterstown 115 kV line
293 MetEd Market Efficiency ME-1 Build a 4 position 115 kV ring bus (Meade) at Lincoln Tap Substation
398 MISO Market Efficiency ME-7 Build new 345 kV transmission line from the existing Meadow Lake station to a new 345 kV switching station called “Pike Creek".
249 MISO Market Efficiency ME-7 Install a 50 MW 4-hour battery at the existing Trail Creek 138 kV station.
129 MISO Market Efficiency ME-7 Build a new 138 kV Kuchar station on the Bosserman-Liquid Carbonics 138 kV line. Extend a new 138 kV single circuit transmission line from the Kuchar Station to the existing Luchtman Station.
436 MISO Market Efficiency ME-7 Build a new Toto 345 kV Switching Station and interconnect the existing Olive - Reynolds #1, Olive - Reynolds #2, and Schahfer - Burr Oak 345 kV transmission lines
481 MISO Market Efficiency ME-7 Reconductor Michigan City-Trail Creek-Bosserman (6.7 mile and 4.0 mile) and Maple – LNG 138 kV (7.8 mile) circuits.
322 AMIL Market Efficiency ME-6 Build a new 345 kV line between the Palmyra and Herleman Substations and rebuild the existing Palmyra – Marblehead 161 kV line and a Marblehead – Herleman 138 kV line. 
506 AMIL Market Efficiency ME-6 Build a new 345 kV line between the Maywood and Herleman Substations and rebuild the existing Palmyra – Marblehead 161 kV line and a Marblehead – Herleman 138 kV line.
775 MISO Market Efficiency ME-2 Decouple part of multi-bundled conductor on a portion of Monroe-Wayne 345 kV line and re-utilize the adjacent Monroe-Coventry line. 
078 MISO Market Efficiency ME-2 Decouple part of multi-bundled conductor on a portion of Monroe-Wayne 345 kV line. 
782 MISO Market Efficiency ME-2 Upgrade the Monroe-Wayne 1&2 345 kV line rating by replacing switches at the 345 kV Wayne Station. 
830 MetEd Market Efficiency ME-1 Build a 500/115 kV substation on Hunterstown-Conastone 500 kV line near Littlestown, PA. and build a 115 kV line from new station to Germantown station. 
616 MetEd Market Efficiency ME-1 Build a 500/230 kV substation on Hunterstown-Conastone 500 kV line near Wentz, MD., build a 230 kV line from new substation to Carroll substation, install a 500/230 kV transformer Peach Bottom station, and build a Peach Bottom-Graceton 230 kV line.
593 MetEd Market Efficiency ME-1 Build a 500/115 kV substation on Hunterstown-Conastone 500 kV line near Littlestown, PA., build a 115 kV line from new substation to Germantown substation, install a 500/230 kV transformer at Peach Bottom, and build a Peach Bottom-Graceton 230 kV line.
387 MetEd Market Efficiency ME-1 Build a 500-230 kV substation on Hunterstown-Conastone 500 kV line near Wentz, MD. and build a 230 kV line from new substation to Carroll substation.
413 MetEd Market Efficiency ME-1 Build a 115 kV line from Hunterstown to Lincoln stations and install a 10 MW 2-hour battery at Lincoln.
402 MetEd Market Efficiency ME-1 Build a 115 kV line from Hunterstown to Lincoln stations and install a 25 MW 2-hour battery at Lincoln.
960 MetEd Market Efficiency ME-1 Build a 115 kV line from Hunterstown to Lincoln substations.
868 MetEd Market Efficiency ME-1 Build a 500 kV switchyard on the PEBO-DELT 500 kV line and install a new 115 kV ring bus at the Orrtanna tap point of the METED Hunterstown – Orrtanna – Lincoln 115 kV line.
453 MetEd Market Efficiency ME-1 Install a 25 MW 4-hour battery at Lincoln 115 kV station.
201 MetEd Market Efficiency ME-1 Install a 25 MW 2-hour battery at Lincoln 115 kV station.
892 MetEd Market Efficiency ME-1 Install a 50 MW 2-hour battery at Lincoln 115 kV station.
647 MetEd Market Efficiency ME-1 Install a 115 kV ring bus at the Orrtanna tap point of the METED Hunterstown – Orrtanna – Lincoln 115 kV line, build an Otter Creek 500/230 kV station, and rebuild 1.3 miles of Manor – Graceton 230 kV line.
511 MetEd Market Efficiency ME-1 Install a 115 kV ring bus at the Orrtanna tap point of the METED Hunterstown – Orrtanna – Lincoln 115 kV line and build an Otter Creek 500/230 kV substation.
007 MetEd Market Efficiency ME-1 Install a 115 kV ring bus at the Orrtanna tap point of the METED Hunterstown – Orrtanna – Lincoln 115 kV line.
034 MetEd Market Efficiency ME-1 Rebuild the Hunterstown – Lincoln - Germantown 115 kV and Germantown - Carrol 138 kV lines as double circuit 230 kV line.
622 MetEd Market Efficiency ME-1 Rebuild the Hunterstown - Lincoln 115 kV line.
021 MetEd Market Efficiency ME-1 Rebuild the Hunterstown-Lincoln 115 kV line, build a Peach Bottom - Graceton 230 kV circuit, upgrade the existing Face Rock 115/69 kV transformers and circuit switching at Rice and Ringgold 230 kV stations.
389 MetEd Market Efficiency ME-1 Rebuild the Hunterstown-Lincoln 115 kV line, add a Peach Bottom 500/230 kV transformer, and add a Peach Bottom-Graceton 230 kV line.
357 MetEd Market Efficiency ME-1 Build a 500/230 kV substation on the Delta - Peach Bottom 500 kV line, build a 230 kV line from the new station to Graceton, build a 230 kV switching station on the Carroll - Mt. Airy 230 kV line, and build a 230 kV line from the new station to Hunterstown.
847 MetEd Market Efficiency ME-1 Build a 500/230 kV substation on the Delta - Peach Bottom 500 kV line, build a 230 kV line from the new station to Graceton and reconductor the Hunterstown - Lincoln 115 kV line.

Proposal ID Proposing Entity Target Zone(s) Analysis Type FG# Major Component/Project Description
1A DEOK DEOK Summer N-1 Load Drop N1-SLD1 Add redundant relaying to Port Union 138kV Bus 2 to eliminate the contingency driving the reliability criteria violation.
2A Dominion Dominion Summer N-1 High Voltage N1-SVH1, N1-SVH2 This is an operational solution that will remotely open Davis TX#1 breaker L122, immediately following the breaker-failure event (2036T2142) at Radnor Substation thus resolving the post contingency high voltage.
2B Dominion Dominion Summer N-1 High Voltage N1-SVH1, N1-SVH2 Move the existing 230/69kV TX#4 to the vacant 230/69kV TX#2 spot at Davis Substation.
2C Dominion Dominion Summer N-1 High Voltage N1-SVH1, N1-SVH2 Move spare 230/69kV transformer from Jefferson Street Substation to the vacant Transformer #2 bay at Davis Substation.
2D Dominion Dominion Summer N-1 High Voltage N1-SVH1, N1-SVH2 Construct a 230kV four (4) breaker GIS ring bus in Davis Substation and terminate existing Line 2037 and Line 2121. 
2E Dominion Dominion Summer N-1 High Voltage N1-SVH1, N1-SVH2 Install a 50 MVAR fixed shunt reactor at Davis Substation on the 69kV bus.
2F Dominion Dominion Summer N-1 High Voltage N1-SVH1, N1-SVH2 A new substation called Cloverleaf with a 230kV variable shunt reactor with a new 230kV underground line roughly 300 ft extending from Cloverleaf Substation to Davis substation terminating at the 230kV bus.

AEP

Date
2017_1-8B - Maddox-Southwest_Lima_345kV PDF
3.1.2018

Duquesne

Date
2017_1-4A - Cheswick-Plum_138kV PDF
3.1.2018

Exelon

Date
2017_1-9D - Edge_Moor-Chichester_230kV PDF
3.1.2018
2017_1-9E - Edge_Moor-Linwood_230kV PDF
3.1.2018
2017_1-9F - Edge_Moor-Post_230kV PDF
 3.1.2018
2017_1-9G - Edge_Moor-New_PECO_sub_230kV PDF
 3.1.2018
2017_1-9H - Harmony-Linwood_230kV PDF
 3.1.2018
2017_1-9I - Harmony-Chichester_230kV PDF
 3.1.2018
2017_1-9J - Harmony-Clay_230kV PDF
3.1.2018
2017_1-9N - Edge_Moor-Pedrick_230kV PDF
3.1.2018

First Energy

Date
2017_1-10F - Bunola_Substation_138kV PDF 
3.1.2018

Nextera

Date
2017_1-5A - Lamberts_Run_500-138kV_Sub PDF
3.1.2018
2017_1-5B - Miracle_138kV_Series Reactor PDF
 3.1.2018
2017_1-5C - Miracle_138kV_Reconductor PDF
 3.1.2018

NTD

Date
2017_1-2A - Glade_Run-Waldo_Run_138kV PDF
3.1.2018
2017_1-2B - Logans_Ferry-Pucketa_138kV PDF
 3.1.2018
2017_1-2C - Logans_Ferry-Pucketa_138kV PDF
 3.1.2018
2017_1-2D - Logans_Ferry-Thorn_Run_345kV PDF
 3.1.2018
2017_1-2E - Twelvemile_345kV_Sub PDF
 3.1.2018

PSEG

Date
2017_1-3A - Beaver_Run-Logans_Ferry_500kV PDF
 3.1.2018

Transource

Date
2017_1-7A - Barking_Road-Wright_Road_138 kV PDF
3.1.2018
2017_1-7B - Anson_Station_345kV PDF
3.1.2018
2017_1-7C - Sycolin_Creek_230kV PDF
3.1.2018
2017_1-7D - York-Coyote_345kV PDF
3.1.2018
2017_1-7E - Narrow_Run-Waldo_Run_500 kV PDF
 3.1.2018
2017_1-7F - Tanners_Creek-Miami_Fort_345kV PDF
3.1.2018
2017_1-7G - Upper_Harmony-McCalmont_138kV PDF
3.1.2018

Dominion

Date
1-8Q - Palmyra 500kV Capacitor PDF
2.27.2017

Nipsco

Date
1-9A - Bosserman Reconductor PDF
2.25.2017
1-9B - Thayer Morrison 138kV PDF 
2.28.2017

Nextera

Date
1-10A - Spring Hill 500-230kV PDF 
2.28.2017
1-10B - Rolling Prairie 345-138kV PDF 
2.28.2017
1-10C - Rowland-Perryman 230kV PDF
2.28.2017
1-10D - Rowland-Perryman 230kV Pylesville 500-230kV PDF
2.28.2017
1-10E - Perryman-Rowland-Pylesville 230kV Pylesville 500-230kV PDF
 2.28.2017

AEP-Nipsco

Date
1-12D - Olive-Liquid Carbonics 138kV PDF
3.2.2017

Transource

Date
1-13A - Baldwin Road-Raphael Road 230kV PDF
2.28.2017
1-13B - Conastone-Dulaney Valley 230kV PDF 
2.28.2017
1-13C - Conastone-Long Green 230kV PDF
 2.28.2017
1-13D - Conastone-Long Green-Raphael Road 230kV PDF
 2.28.2017
1-13E - Hereford-Dulaney Valley 230kV PDF
 2.28.2017
1-13F - Love Run-Perryman 230kV PDF
2.28.2017
1-13H - York Coyote 345kV PDF
2.28.2017

DATC

Date
1-14A - Furnace Run-Perryman PDF
2.28.2017

PPL-ATXI East

Date
1-15A -  Conastone-Graceton-Bagley with Conastone-Baldwin 230kV PDF
2.28.2017
1-15B -  Conastone-Graceton-Bagley with Peach Bottom-Otter Point 230kV PDF
2.28.2017

PSEG

Date
1-16A - Peach Bottom-Otter Point 230kV PDF
2.28.2017
1-16B - PeachBottom-Raphael Road 230kV PDF
3.1.2017
1-16C - Conastone-Raphael Road 230kV PDF
3.1.2017
1-16D - Conastone-Northeast 230kV PDF
3.1.2017
1-16E - Peach Bottom-Northeast 230kV PDF
 3.1.2017

Exelon

Date
1-17A - AEP-Public-Cottage Grove PDF
2.28.2017
1-17B - Meadow Lake-Pike Creek 345kV PDF
 2.28.2017

NTD

Date
1-18A - Baltimore 2 PDF
3.1.2017
1-18B - Baltimore 3 PDF
3.1.2017
1-18C - Baltimore 5 PDF
 3.1.2017
1-18D - Baltimore 6 PDF
 3.1.2017
1-18F - Conastone-Fitzhugh Run PDF
 3.1.2017
1-18G - Fells Creek PDF
 3.1.2017
1-18H - Green Ridge 230kV PDF
 3.1.2017
1-18I - Green Ridge 500kV PDF
 3.1.2017
1-18J - Hunterstown-GreenValley PDF
 3.1.2017
1-18K - James Creek PDF
 3.1.2017
1-18L - Limestone Ridge PDF
 3.1.2017
1-18M - Marysville-Miami_Spring Run-Crown PDF
 3.1.2017
1-18N - Marysville-Miami PDF
 3.1.2017
1-18O - Smith Branch PDF
 3.1.2017
1-18P - Spring Run-Crown PDF
 3.1.2017
1-18Q - Trexler Run-Harwood PDF
 3.1.2017
1-18R - Turkey Creek PDF
 3.1.2017
1-18S - Coffee Creek PDF
 3.1.2017

ITC

Date
1-20A - Peach Bottom-Old Post 230kV PDF
3.2.2017
1-20B - Conastone-Raphael 230kV PDF
3.2.2017
1-20C - Conastone-Northeast 230kV PDF
3.2.2017
1-20D - Conastone-Old Post 230kV PDF
3.2.2017
1-20E - Peach Bottom-Pyle-Fallston-Old Post 230kV PDF
 3.2.2017
1-20F - Conastone-Pyle-Fallston-Old Post 230kV PDF
3.2.2017
1-20G - Peach Bottom-Northeast 230kV PDF
3.2.2017
1-20H - Peach Bottom-OldPost 230kV+Battery PDF
3.2.2017
1-20I - Peach Bottom-Pyle-Fallston-OldPost 230kV+battery PDF
3.2.2017


Date
DEOK / AEP Competitive Cluster Independent Constructability Review White Paper PDF
1.11.2017

Redacted Public Greenfield Proposals

Transource

Date
2016_2-3B - Version Homer City-Two Lick Creek PDF
10.17.2016
2016_2-3C - Russ 345_138 kV Station PDF
10.17.2016
2016_2-3D - Upper Harmony-McCalmont 138 PDF 10.17.2016
2016_2-3E - Williams Grove 115 PDF 10.17.2016
2016_2-3F - York-Coyote 345 PDF 10.17.2016

Nextera

Date
2016_2-6A - Salem345-138kV PDF
10.17.2016
2016_2-6B - DE 345 KV Trans PDF
10.17.2016

AEP

Date
2016_2-7I - Dequine-Meadow Lake 345 PDF
10.17.2016
2016_2-7M - Eugene-Dequine 345 kV SGL 2 PDF
10.17.2016
2016_2-7P - Eugene-Meadow Lake 345 kV SGL PDF 10.17.2016

Northeast Transmission Development

Date
2016_2-9A PDF
10.17.2016
2016_2-9B PDF
10.17.2016
2016_2-9C PDF
10.17.2016
2016_2-9D PDF 10.17.2016
2016_2-9F PDF 10.17.2016
2016_2-9G PDF 10.17.2016
2016_2-9I PDF 10.17.2016
2016_2-9J PDF 10.17.2016
2016_2-9O PDF 10.17.2016
2016_2-9P PDF 10.17.2016
2016_2-9Q PDF 10.17.2016
2016_2-9R PDF 10.17.2016
2016_2-9S PDF 10.17.2016
2016_2-9T PDF 10.17.2016
2016_2-9V PDF 10.17.2016

Mid-Atlantic MCN

Date
2016_2-10B PDF
10.17.2016

PSEG

Date
2016_2-11C - Vectren Eugene to Meadow Lake 345kV PDF
10.17.2016
2016_2-11D - Vectren Ghent to East Bend 345kV PDF
10.17.2016
2016_2-11E - Vectren Clifty Creek to East Bend 345kV PDF 10.17.2016

PPL

Date
2016_2-13F - PPL - Public Redacted Version - Clifty_Madison PDF
10.17.2016
2016_2-13G - PPL - Public Redacted Version - Dequine_New_Line PDF
10.17.2016
2016_2-13I - PPL - Public Redacted Version - TodhunterRockiesExp PDF 10.17.2016
2016_2-13J - PPL - Public Redacted Version - Nickel_Warren PDF 10.17.2016



AEP

Date
2-3A PDF
10.30.2015
2-3C PDF
10.28.2015
2-3D PDF 
10.28.2015
2-3E-3F PDF
10.28.2015
2-3G-3H PDF
10.28.2015
2-3I PDF 
10.30.2015
2-3J PDF 
10.30.2015

Northeast Transmission Development

Date
2-2A-2I PDF
10.28.2015


Dominion

Date
2015_1-1C - Carson-Rogers Rd 500kV PDF
9.8.2015
2015_1-1D - Carson-Rawlings 500kV PDF 
9.8.2015
2015_1-1E - Rogers Road-Maclins 500kV Ln and Maclins-Clubhouse 230kV PDF
9.8.2015
2015_1-1F - Rawlings-Purdy 230kV PDF
9.8.2015

AEP

Date
2015_1-2D - Clinch River-Keen Mountain PDF 
9.11.2015
2015_1-2E - Clinch River-Beaver Creek PDF 
9.11.2015
2015_1-2G - Dequine-Meadow Lake 345 Ckt3 PDF
9.10.2015
2015_1-2L - Herlan-Blue Racer 138kV PDF
9.11.2015

Transource

Date
2015_1-5A - Anson 345 kV Station PDF
9.8.2015
2015_1-5B - Burma-Piney 115kV PDF 
9.8.2015
2015_1-5C - Cambria 500 115 kV Station Project PDF
9.8.2015
2015_1-5D - Carlisle Pike-Fayetteville 138kV PDF 
9.8.2015
2015_1-5E - Carlisle Pike-Rice Project PDF
9.8.2015
2015_1-5F - Carson Rawlings 500 kV Project PDF 
9.8.2015
2015_1-5G - Tanners Creek-Miami Fort PDF 
9.8.2015

Nextera

Date
2015_1-6A - Rogers Road to Pleasant Shade & Carson to Rawlings PDF
9.8.2015
2015_1-6B - Carson to Rawlings PDF 
9.8.2015
2015_1-6C - Carson to Rogers Road PDF 
9.8.2015

PSEG

Date
2015_1-7A - Dequine to Meadow 345kV PDF
9.8.2015
2015_1-7B - Englishtown to East Windsor 230kV PDF 
9.8.2015
2015_1-7C - Englishtown 500 230kV PDF
9.8.2015
2015_1-7D - Brunswick-Wake 500230 kV New Line Clubhouse 230kV PDF
9.8.2015
2015_1-7E - Beaver to Black River 138kV PDF 
9.8.2015
2015_1-7F - Beaver to Lake Ave 138kV PDF 
9.8.2015
2015_1-7G - Station Beaver 138 69kV to New Station Sheffield 138kV PDF
9.8.2015
2015_1-7H - Guyandotte to Tams Mountain 138kV PDF 
9.8.2015
2015_1-7I - Matt Funk-Kanawha River 345 138kV PDF 
9.8.2015
2015_1-7J - Crossland to Elwood 138kV PDF
9.8.2015
2015_1-7K - Dowling to Bowling Green 5 138kV PDF 
9.8.2015

Northeast Transmission Development

Date
2015_1-8A-AD PDF
9.8.2015

ITC

Date
2015_1-9A-E PDF
9.8.2015


Transource

Date
2014_2B-1A - Cumberland Tap 1 PDF
3.17.2015
2014_2B-1B - Cumberland Tap 3 PDF
3.17.2015

Northeast Transmission Development

Date
2014_2B-3A PDF
3.17.2015
2014_2B-3B PDF
3.17.2015
2014_2B-3C PDF
3.17.2015
2014_2B-3D PDF 
3.17.2015
2014_2B-3E PDF 
3.17.2015
2014_2B-3F PDF 
3.17.2015

PPL/First Energy

Date
2014_2B-4A - Allen Williams Grove PDF
3.17.2015


Date
Independent Cost Review White Paper PDF
5.6.2016

Long-Term Public Redacted Proposals

Window closed on 2.27.2015

PPL

Date
201415_1-2C - AP South PDF
3.24.2015

AEP

Date
201415_1-4A - Gavin Kyger PDF
3.24.2015
201415_1-4H - Dequine-Meadow Lake 345 PDF
3.24.2015

Dominion

Date
201415_1-6D - Palmyra 500kV PDF
3.24.2015

Transource

Date
201415_1-7A - Axton EastDanville 230kV PDF
3.24.2015
201415_1-7B - Meadowbrook Doubs PDF 
3.24.2015
201415_1-7C - Meadowbrook Doubs 500kV PDF
3.24.2015

Dominion/Transource

Date
201415_1-8A - Joshua Falls Palmyra 765kV PDF
3.24.2015
201415_1-8B - Joshua Falls Palmyra 500kV PDF
3.24.2015
201415_1-8C - Axton Clover 765kV PDF 
3.24.2015
201415_1-8D - Axton Clover 500kV PDF 
3.24.2015
201415_1-8E - Joshua Falls to Farmville Single 230 kV PDF
3.24.2015
201415_1-8F - Joshua Falls to Farmville Double 230 kV PDF
3.24.2015

Dominion High Voltage

Date
201415_1-9A - Southern PA PDF
3.24.2015

ComEd

Date
201415_1-10C - Loretto Wilton Center PDF
3.24.2015

PECO

Date
201415_1-11A - Proposal 1 PDF
9.15.2015
201415_1-11B - Proposal 2 PDF
9.15.2015
201415_1-11C - Proposal 3 PDF
9.15.2015
201415_1-11D - Proposal 4 PDF
9.15.2015

DATC

Date
201415_1-14A - AP South PDF
3.24.2015
201415_1-14B - Germantown Fairview PDF
3.24.2015
201415_1-14C - Kentucky Substation PDF 
3.24.2015

GridAmerica

Date
201415_1-15A - NJMEP PDF
3.24.2015

Nipsco

Date
201415_1-16A - Wilton Center Reynolds Gwynneville PDF
3.24.2015
201415_1-16B - Pontiac Reynolds PDF 
3.24.2015

NextEra

Date
201415_1-17A - 1A PDF
3.24.2015
201415_1-17B - 1B PDF
3.24.2015
201415_1-17C - NextEra - 1C PDF
3.24.2015
201415_1-17D - 1D PDF
3.24.2015
201415_1-17E- 2A PDF
3.24.2015
201415_1-17F- 2B PDF
3.24.2015
201415_1-17G - 2C PDF
3.24.2015

First Energy

Date
201415_1-18E - AP South PDF
3.24.2015

Northeast Transmission Development

Date
201415_1-19A PDF
3.24.2015
201415_1-19B PDF
3.24.2015
201415_1-19C PDF
3.24.2015
201415_1-19D PDF
3.24.2015
201415_1-19E PDF
3.24.2015
201415_1-19F PDF
3.24.2015
201415_1-19G PDF
3.24.2015
201415_1-19H PDF
3.24.2015
201415_1-19I PDF
3.24.2015

ITC

Date
201415_1-20A - 3-1 PDF
3.24.2015
201415_1-20B - 3-3 PDF
3.24.2015
201415_1-20C - 3-4 PDF 
3.24.2015
201415_1-20D - 3-5 PDF 
3.24.2015
201415_1-20E - 3-6 PDF 
3.24.2015
201415_1-20F - 3-7 PDF 
3.24.2015
201415_1-20G - 3-9 PDF 
3.24.2015
201415_1-20H - 3-10 PDF
3.24.2015
201415_1-20I - 3-11 PDF 
3.24.2015
201415_1-20J - 3-1 PDF 
3.24.2015
201415_1-20K - 3-9 PDF 
3.24.2015
201415_1-20L - 3-1 PDF 
3.24.2015
201415_1-20M - 3-1 PDF 
3.24.2015
201415_1-20N - 3-9 PDF 
3.24.2015
201415_1-20O - 3-9 PDF 
3.24.2015

PSEG

Date
201415_1-21A - Eagle Point to Penrose 230kV PDF
3.24.2015
201415_1-21B - Gloucester Cuthbert 230kV PDF 
3.24.2015
201415_1-21C - Miami Fort to Willey 138kV PDF 
3.24.2015
201415_1-21D -Milford Cool Spring 230kV PDF 
3.24.2015
201415_1-21E - Reconductor Red Lion Cedar Creek PDF
3.24.2015
201415_1-21F - Red Lion Cedar Creek 230kV PDF 
3.24.2015

Ameren

Date
201415_1-22A - AP South & AEP - DOM Congestion PDF
3.24.2015
201415_1-22B - AP South & AEP - DOM Congestion PDF
3.24.2015
201415_1-22C - Taneytown - Carroll PDF 
3.24.2015
201415_1-22D - Miami Ft Willey PDF 
3.24.2015
201415_1-22E - Miami Ft Willey PDF 
3.24.2015
201415_1-22F - Miami Ft Willey PDF 
3.24.2015


PPL/First Energy

Date
2014 2A-1A - Allen Williams Grove PDF
2.17.2015

Transource

Date
2014 2A-2A - Cumberland Tap 1 PDF
2.17.2015
2014 2A-2A - Cumberland Tap 3 PDF
2.17.2015

Northeast Transmission Development

Date
2014 2A-3A - Dogwood Run PDF
2.17.2015


AEP

Date
2014_2-2K - Boone Area PDF
1.14.2015
2014_2-2Q - Belva - Clendenin 138kV PDF
1.14.2015
2014_2-2R - Therofare - Ivydale 138kV PDF
1.14.2015
2014_2-2S - Therofare - 138kV Tap PDF
1.14.2015
2014_2-2U - Skin Fork Area Improvements PDF 
1.14.2015
2014 2-2W - Bellaire-Glencoe-Herlan 138 kV PDF
1.14.2015
2014_2-2Y - Colfax-Drewrys PDF
1.14.2015

Transource

Date
2014_2-3A - Cumberland Tap PDF
12.16.2014
2014_2-3B - Sewaren Tap PDF
12.16.2014

First Energy

Date
2014_2-4E - Allen 230-115 kV PDF
12.16.2014

PECO

Date
2014_2-5A - Proposal 1 PDF 
1.14.2015
2014_2-5B - Proposal 2 PDF
1.14.2015

ITC Mid Atlantic

Date
2014_2-6A - Emilie to Mercer PDF
12.16.2014
2014_2-6B - Gordonsville Fairground Remington - Pratts PDF
1.12.2015

Northeast Transmission Development

Date
2014_2-7A - Cedar Plains PDF
12.16.2014
2014_2-7B - Dogwood Run PDF
12.16.2014
2014_2-7C - South Fork PDF
12.16.2014
2014_2-7D - Pratts PDF 
1.12.2015
2014_2-7E - Pratts PDF 
1.12.2015
2014_2-7F - Pratts PDF 
1.12.2015
2014_2-7G - Pratts PDF
1.12.2015
2014_2-7H - Pratts PDF 
1.12.2015
2014_2-7I - Pratts PDF
1.12.2015
2014_2-7J - Pratts PDF 
1.12.2015
2014_2-7K - Pratts PDF 
1.12.2015

Comed

Date
2014_2-8E - Schauff Road to Rock Falls PDF
12.16.2014

Nextera Energy Transmission

Date
2014_2-10A - DOM 5A PDF
1.14.2015
2014_2-10B - DOM 5B PDF
1.14.2015

NIPSCO

Date
2014_2-12A - Oglesby Pontiac Reynolds PDF
12.16.2014

Dominion/First Energy

Date
2014_2-13A - Pratts PDF
1.12.2015
2014_2-13B - Pratts PDF
1.12.2015
2014_2-13C - Pratts PDF
1.12.2015
2014_2-13D - Pratts PDF
2.23.2015

Ameren

Date
2014_2-14A - Option 1 - Pratts PDF
1.14.2015
2014_2-14B - Option 2 - Pratts PDF
1.14.2015
2014_2-14C - Option 3 - Pratts PDF
1.14.2015


Duke Energy
Date
2014-1-1B - Miami Fort to Willey New Branch PDF
9.30.2014
AEP
Date
2014-1-2G - Clinch River-Keen Mountain PDF
9.30.2014
2014-1-2H - Clinch River-Beaver Creek PDF
9.30.2014
2014-1-2L - Kyger Creek - Gavin 345-138 PDF
9.30.2014
Transource
Date
2014-1-3A - Brooke County PDF
9.30.2014
2014-1-3B - Lorain PDF
9.30.2014
2014-1-3C - Lorain Juniper PDF
9.30.2014
2014-1-3D - Lockwood Road-Stryker PDF
9.30.2014
2014-1-3E - Bryan-Stryker PDF
9.30.2014
2014-1-3F - Fremont-Hayes PDF
9.30.2014
2014-1-3G - West Fremont Hayes PDF
9.30.2014
2014-1-3H - Southwest Ohio PDF
9.30.2014
2014-1-3I - Montour PDF
9.30.2014
2014-1-3J - Crescent PDF
9.30.2014
2014-1-3K - Dresden PDF
9.30.2014
2014-1-3L - South Philly PDF
9.30.2014
Dominion High Voltage Mid-Atlantic
Date
2014-1-4C - Sunbury Susquehanna Montour Columbia Frackville PDF
9.30.2014
PPL
Date
2014-1-7A - AE 1 PDF
9.30.2014
2014-1-7B - AE 2 PDF
9.30.2014
2014-1-7C - AE 3 PDF
9.30.2014
2014-1-7D - AE 4 PDF
9.30.2014
2014-1-7E - AEP 1 PDF
9.30.2014
2014-1-7F - AEP 2 PDF
9.30.2014
2014-1-7G - FE 1 PDF
9.30.2014
2014-1-7H - FE 2 PDF
9.30.2014
2014-1-7K - PPL 3 PDF
9.30.2014
2014-1-7L - PPL 4 PDF
9.30.2014
2014-1-7M - PPL 5A PDF
9.30.2014
2014-1-7N - PPL 5B PDF
9.30.2014
2014-1-7O - PPL 6 PDF
9.30.2014
2014-1-7P - Project Compass PDF
9.30.2014
ITC
Date
2014-1-11A - 1-1 PDF
9.30.2014
2014-1-11B - 1-2 PDF
9.30.2014
2014-1-11C - 1-3 PDF
9.30.2014
2014-1-11D - 1-4 PDF
9.30.2014
2014-1-11E - 1-5 PDF
9.30.2014
2014-1-11F - 1-6 PDF
9.30.2014
PHI
Date
2014-1-12A - DPL PDF
9.30.2014
Nextera
Date
2014-1-13A - Meshoppen to Lackawanna PDF
9.30.2014
2014-1-13B - Montour to Sunbury PDF
9.30.2014
Northeast Transmission Development
Date
2014-1-14A - Crows Run PDF
9.30.2014
2014-1-14B - Delco to Eddystone PDF
9.30.2014
2014-1-14C - Garrison Run PDF
9.30.2014
2014-1-14D - Kammer To Holloway PDF
9.30.2014
2014-1-14E & E1 - Montour To Furman PDF
9.30.2014
2014-1-14F - Paddys Run PDF
9.30.2014
2014-1-14G - Tidd To Windsor PDF
9.30.2014
2014-1-14H & H1 - Clinch River to West Fork PDF
9.30.2014
2014-1-14I - BL England to Cardiff PDF
9.30.2014
2014-1-14J and J1 - Swisher Hill PDF
9.30.2014
2014-1-14K - Lake Avenue to Case PDF
9.30.2014
PSEG
Date
2014-1-15A - B.L. England to Cardiff 138kV PDF
9.30.2014
2014-1-15B - B.L. England to Cardiff 230kV PDF
9.30.2014
2014-1-15C - Dennis to B.L. England to Cardiff 230kV PDF
9.30.2014
2014-1-15D - Eagle Point to Penrose 230kV PDF
9.30.2014
2014-1-15E - Gloucester to Cuthbert Blvd 230kV PDF
9.30.2014
2014-1-15F - Kyger Creek - New Station 345kV PDF
9.30.2014


Window Information
Redacted Problem Statement
Artificial Island Projects Stability Test Results Summary (Public Non CEII)

August 12, 2014 Supplemental Request: Letter | FAQ PDF  
PJM Letter to Chief Judge Wagner PDF
 

Window closed on 06.28.2013

Supplemental Responses

Dominion High Voltage (2013-1-1A)
Date
2013-1-1A - Public PDF
9.19.2014
2013-1-1A - Public - SVC Milestone Dates & Gantt Chart PDF
9.19.2014
Dominion High Voltage (2013-1-1C)
 
2013-1-1C - Public PDF
9.19.2014
2013-1-1C - Public - 500 kV Line Milestone Dates & Gantt Chart PDF
9.19.2014
Transource (2013-1-2B)
 
2013-1-2B - Public - Final Response PDF
9.25.2014

Northeast Transmission Development (2013-1-5A)

 
2013-1-5A - Public - Finalist Letter to PJM PDF
9.19.2014
2013-1-5A - Public - Exhibit 1 - Cost Cap Legal Terms PDF
9.19.2014
2013-1-5A - Public - Exhibit 2 PDF
9.19.2014
2013-1-5A - Public - Exhibit 3 PDF
9.19.2014
2013-1-5A - Public - Exhibit 4 PDF
9.19.2014

PSEG (2013-1-7K)

 
2013-1-7K - Public - Supplemental Proposal Request Submittal Final PDF
9.19.2014
Notice PDF
9.24.2014

Redacted Public Proposals

Virginia Electric and Power Company
Date
Dominion - Proposal 1 PDF
7.24.2013
Dominion - Proposal 2 PDF
7.24.2013
Transource
 
Proposal 1 Salem to Cedar Creek Report & Attachment PDF
7.24.2013
Proposal 2 Salem to North Cedar Creek Report & Attachment PDF
7.24.2013
Proposal 3 Salem to Red Lion Report & Attachment PDF
7.24.2013
Proposal 4 New Freedom to Lumberton to Smithburg Report & Attachment PDF
7.24.2013
FirstEnergy Corporation
 
Report PDF
7.24.2013
Pepco Holdings, Inc and Exelon Corporation
 
Joint Stability Solution Proposal PDF
7.24.2013
LS Power
 
230kV PDF
7.24.2013
500kV PDF
7.24.2013
Atlantic Grid Holdings LLC
 
Atlantic Wind - Garden State Reliability Project - Artificial Island Intertie PDF
7.24.2013
PSE&G
 
Proposal PDF
7.24.2013

Constructability Reports
Date
Constructability Analysis for the Dominion 1A Project PDF 
12.12.2014
Permitting Analysis for the Finalist Line Projects PDF
10.9.2014
SVC Options for Artificial Island, Orchard & New Freedom PDF
6.11.2014
Delmarva Peninsula Lines Constructability Analysis PDF
5.23.2014
Red Lion Constructability Analysis PDF
5.23.2014