Transition Cycle 2
v1.00 released 2026-06-03 19:14
New Service Requests
System Impact Study Executive Summary Report
Transition Cycle 2 — Phase II
Introduction
This Phase II System Impact Study executive summary report has been prepared in accordance with the PJM Open Access Transmission Tariff Part VII, Subpart D, section 310. This report presents an executive summary of the Phase II System Impact Study results for New Service Requests (projects) in Transition Cycle 2.
Preface
The Phase II System Impact Study is conducted on an aggregate basis within a New Services Request’s Cycle, and results are provided in both (i) a single Cycle summary format and (ii) an individual project-level basis. The Phase II System Impact Study Results (for both the summary and individual reports) will be publicly available on PJM’s website. Project Developers must obtain the results from the website.
In accordance with PJM Manual 14H, section 4.5, PJM takes the following actions during the Phase II System Impact Study:
- PJM will retool load flow results from the Phase I System Impact Study (summer peak, winter peak and light load) based on decisions made by Project Developers or Eligible Customers during Decision Point I.
- PJM will conduct any required voltage analyses.
- PJM will perform short circuit and stability analyses as required.
- PJM will coordinate with the Affected System to confirm which projects in the PJM Cycle will require Affected System studies. If the Affected System Operator indicates that an Affected System study is required, PJM will:
- Notify the Project Developer or Eligible Customer of the need for an Affected System study and the requirement to execute an Affected System study agreement with the impacted Affected System Operator, and;
- Include the results of the Affected System Operator’s Affected System Study in the Phase II System Impact Study results, if applicable and available.
- The Phase II System Impact Study Results will be publicly available on PJM’s website. Project Developers and Eligible Customers must obtain the results from the website.
New Services Request List
PJM received 270 New Service Requests in Transition Cycle 2, Phase II System Impact Study with a combined Maximum Facility Output (MFO) of 29,742.6 MW and 22,959.9 MW as Capacity Interconnection Rights (CIRs). All of these New Service Requests are listed in table below.
| Project ID | Project Name / POI |
State
|
Status |
Transmission Owner
|
Maxiumum Facility Output (MFO in MW) | MW Energy (MWE) | MW Capacity (MWC) | Project Type | Resource Type | Facilities Study |
|---|---|---|---|---|---|---|---|---|---|---|
| AG2-014 | Meadow Lake 345 kV | Indiana | Active | AEP Indiana Michigan Transmission Company, Inc. | 50.0 | 50.0 | 20.0 | Generation Interconnection | Storage | |
| AG2-016 | Oyster Creek-Whitings 34.5 kV | New Jersey | Active | Jersey Central Power & Light Company | 19.8 | 19.8 | 8.316 | Generation Interconnection | Solar | |
| AG2-029 | Forest G. Hipple-Dunton Lake 345 kV | Indiana | Active | AEP Indiana Michigan Transmission Company, Inc. | 250.0 | 250.0 | 32.5 | Generation Interconnection | Solar | |
| AG2-037 | Findlay-Clinton 23 kV | Pennsylvania | Active | Duquesne Light Company | 4.7 | 4.7 | 2.82 | Generation Interconnection | Solar | |
| AG2-049 | Van Dorn 34.5 kV | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 20.0 | 20.0 | 20.0 | Generation Interconnection | Other | |
| AG2-057 | Cardington-Liberty 69 kV II | Ohio | Active | American Transmission Systems, Incorporated | 74.0 | 10.0 | 6.0 | Generation Interconnection | Solar | |
| AG2-061 | Dana 345 kV | Illinois | Active | Commonwealth Edison Company | 200.0 | 50.0 | 20.0 | Generation Interconnection | Storage | |
| AG2-062 | William 138 kV | West Virginia | Active | Monongahela Power Company | 147.0 | 147.0 | 21.609 | Generation Interconnection | Wind | |
| AG2-068 | Heritage - Wake 500 kV | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 100.0 | 100.0 | 60.0 | Generation Interconnection | Solar | |
| AG2-069 | Heritage - Wake 500 kV | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 250.0 | 150.0 | 90.0 | Generation Interconnection | Solar | |
| AG2-072 | Rockport 765 kV | Indiana | Active | AEP Indiana Michigan Transmission Company, Inc. | 700.0 | 700.0 | 700.0 | Generation Interconnection | Natural Gas; Other | |
| AG2-073 | Crooksville 69 kV | Kentucky | Active | East Kentucky Power Cooperative, Inc. | 53.0 | 53.0 | 50.88 | Generation Interconnection | Solar | |
| AG2-074 | Meckesville Tap 69kV | Pennsylvania | Active | PPL Electric Utilities Corporation | 38.0 | 38.0 | 26.2 | Generation Interconnection | Solar | |
| AG2-077 | Clover-Rawlings 500 kV | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 700.0 | 200.0 | 120.0 | Generation Interconnection | Solar | |
| AG2-081 | Avon - Renaker 138 kV | Kentucky | Active | East Kentucky Power Cooperative, Inc. | 30.0 | 30.0 | 18.0 | Generation Interconnection | Solar | |
| AG2-082 | Nottingham 138 kV | Ohio | Active | AEP Ohio Transmission Company, Inc. | 200.0 | 200.0 | 133.4 | Generation Interconnection | Solar | |
| AG2-086 | Mt. Jackson DP-Mt. Jackson 115 kV | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 75.0 | 75.0 | 45.0 | Generation Interconnection | Solar; Storage | |
| AG2-088 | Midlothian 230 kV | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 150.0 | 150.0 | 150.0 | Generation Interconnection | Storage | |
| AG2-095 | Hopewell 34.5 kV (Circuit 313) | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 18.0 | 18.0 | 10.8 | Generation Interconnection | Solar | |
| AG2-104 | Marysville-Flatlick 765 kV | Ohio | Active | AEP Ohio Transmission Company, Inc. | 200.0 | 200.0 | 126.85 | Generation Interconnection | Solar | |
| AG2-106 | Marysville-Flatlick 765 kV | Ohio | Active | AEP Ohio Transmission Company, Inc. | 800.0 | 0.0 | 150.0 | Generation Interconnection | Storage | |
| AG2-107 | Marysville-Flatlick 765 kV | Ohio | Active | AEP Ohio Transmission Company, Inc. | 800.0 | 0.0 | 150.0 | Generation Interconnection | Storage | |
| AG2-109 | Fitchville-New London 69 kV | Ohio | Active | American Transmission Systems, Incorporated | 40.0 | 40.0 | 28.1 | Generation Interconnection | Solar | |
| AG2-114 | Dresden-Pontiac Midpoint 345 kV | Illinois | Active | Commonwealth Edison Company | 100.0 | 100.0 | 60.0 | Generation Interconnection | Solar | |
| AG2-119 | Galion-Roberts South 138 kV II | Ohio | Active | American Transmission Systems, Incorporated | 80.0 | 80.0 | 53.6 | Generation Interconnection | Solar | |
| AG2-121 | Mackeys 230 kV | North Carolina | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 140.0 | 0.0 | 0.0 | Generation Interconnection | Storage | |
| AG2-124 | Shackleford-Harmony 115 kV | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 149.9 | 0.0 | 33.34 | Generation Interconnection | Solar | |
| AG2-125 | Camden-Crystal 69 kV | Ohio | Active | The Dayton Power and Light Company | 69.9 | 0.0 | 15.44 | Generation Interconnection | Solar | |
| AG2-126 | Eugene 345 kV | Indiana | Active | AEP Indiana Michigan Transmission Company, Inc. | 150.0 | 150.0 | 90.0 | Generation Interconnection | Solar; Storage | |
| AG2-151 | Trices Lake - James River Tap 115 kV | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 100.0 | 100.0 | 60.0 | Generation Interconnection | Solar | |
| AG2-152 | Banister-Bear Skin 138 kV | Virginia | Active | Appalachian Power Company | 131.0 | 131.0 | 79.0 | Generation Interconnection | Solar | |
| AG2-163 | Dequine-Eugene 345 kV | Indiana | Active | AEP Indiana Michigan Transmission Company, Inc. | 700.0 | 250.0 | 35.0 | Generation Interconnection | Solar | |
| AG2-166 | Newville-Nottingham Tap 1 69 kV | Pennsylvania | Active | PPL Electric Utilities Corporation | 10.0 | 10.0 | 0.0 | Generation Interconnection | Solar | |
| AG2-171 | Lunenburg - Nutbush 115 kV | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 60.0 | 60.0 | 36.0 | Generation Interconnection | Solar | |
| AG2-176 | Geneva 115 kV | Pennsylvania | Active | Mid-Atlantic Interstate Transmission, LLC | 150.0 | 150.0 | 90.0 | Generation Interconnection | Solar | |
| AG2-182 | Doubs-Bismark 500 kV | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 200.0 | 200.0 | 133.3333 | Generation Interconnection | Solar | |
| AG2-184 | Harbert Metering 138 kV | Kentucky | Active | Kentucky Power Company | 210.0 | 210.0 | 126.0 | Generation Interconnection | Solar | |
| AG2-191 | Mississinewa 138 kV | Indiana | Active | American Electric Power | 30.0 | 30.0 | 18.0 | Generation Interconnection | Solar; Storage | |
| AG2-192 | Mississinewa 138 kV | Indiana | Active | American Electric Power | 19.0 | 19.0 | 11.4 | Generation Interconnection | Solar; Storage | |
| AG2-193 | Turner 34.5 kV | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 20.0 | 20.0 | 12.0 | Generation Interconnection | Solar | |
| AG2-198 | Briery - Finneywood 230 kV | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 80.0 | 80.0 | 48.0 | Generation Interconnection | Solar | |
| AG2-200 | North Warren - Russell 34.5 kV | Pennsylvania | Active | Mid-Atlantic Interstate Transmission, LLC | 17.0 | 17.0 | 10.2 | Generation Interconnection | Solar | |
| AG2-213 | Gary D.P Tap - Gary D.P 115 kV | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 80.0 | 80.0 | 48.0 | Generation Interconnection | Solar | |
| AG2-216 | East Sidney-Quincy 138 kV | Ohio | Active | The Dayton Power and Light Company | 144.0 | 0.0 | 25.92 | Generation Interconnection | Solar | |
| AG2-230 | Dumont 345 kV | Indiana | Active | AEP Indiana Michigan Transmission Company, Inc. | 150.0 | 150.0 | 90.0 | Generation Interconnection | Solar | |
| AG2-236 | Potter-Harlan 69 kV | Pennsylvania | Active | American Transmission Systems, Incorporated | 60.0 | 20.0 | 2.0 | Generation Interconnection | Solar | |
| AG2-238 | Earleys 230 kV | North Carolina | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 99.9 | 0.0 | 0.0 | Generation Interconnection | Storage | |
| AG2-240 | Old Church 34.5 kV | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 25.0 | 0.0 | 0.0 | Generation Interconnection | Storage | |
| AG2-245 | Olive - Reynolds #1 345 kV | Indiana | Active | American Electric Power | 210.0 | 210.0 | 126.0 | Generation Interconnection | Solar | |
| AG2-248 | East Elkhart - Elcona Tap 138 kV | Indiana | Active | American Electric Power | 100.0 | 100.0 | 0.0 | Generation Interconnection | Storage | |
| AG2-262 | Dryburg 115 kV | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 47.0 | 11.0 | 6.6 | Generation Interconnection | Solar | |
| AG2-270 | Clover 230 kV | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 150.0 | 150.0 | 105.0 | Generation Interconnection | Storage | |
| AG2-272 | Berry Hill 138 kV | Virginia | Active | Appalachian Power Company | 55.0 | 55.0 | 21.3 | Generation Interconnection | Storage | |
| AG2-288 | Stonewall 138 kV | Virginia | Active | The Potomac Edison Company | 150.0 | 150.0 | 150.0 | Generation Interconnection | Storage | |
| AG2-289 | Amsden - Fremont Center 69 kV | Ohio | Active | AEP Ohio Transmission Company, Inc. | 66.6 | 66.6 | 0.0 | Generation Interconnection | Storage | |
| AG2-290 | Amsden - Fremont Center 69 kV | Ohio | Active | AEP Ohio Transmission Company, Inc. | 105.0 | 38.4 | 0.0 | Generation Interconnection | Storage | |
| AG2-297 | Cumberland 230 kV | New Jersey | Active | Atlantic City Electric | 19.0 | 19.0 | 11.4 | Generation Interconnection | Solar | |
| AG2-298 | Sulphur Creek-Loretto 69 kV | Kentucky | Active | East Kentucky Power Cooperative, Inc. | 35.0 | 35.0 | 23.33 | Generation Interconnection | Solar | |
| AG2-300 | Meadow Brook 138 kV | Virginia | Active | The Potomac Edison Company | 100.0 | 100.0 | 70.0 | Generation Interconnection | Storage | |
| AG2-329 | S Berwick - Galion 345 kV | Ohio | Active | AEP Indiana Michigan Transmission Company, Inc. | 200.0 | 200.0 | 156.0 | Generation Interconnection | Storage | |
| AG2-332 | East Elkhart - Elcona Tap 138 kV | Indiana | Active | American Electric Power | 200.0 | 100.0 | 100.0 | Generation Interconnection | Storage | |
| AG2-339 | Rogers Road - Carson 500 kV | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 479.0 | 85.0 | 85.0 | Generation Interconnection | Storage | |
| AG2-341 | Ridge Road 115 kV | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 50.0 | 50.0 | 20.0 | Generation Interconnection | Storage | |
| AG2-343 | Eugene - Dequine 345 kV | Indiana | Active | AEP Indiana Michigan Transmission Company, Inc. | 100.0 | 100.0 | 78.0 | Generation Interconnection | Storage | |
| AG2-345 | Eugene - Dequine 345 kV | Indiana | Active | AEP Indiana Michigan Transmission Company, Inc. | 150.0 | 50.0 | 39.0 | Generation Interconnection | Storage | |
| AG2-356 | South Troy - Canton 34.5 kV | Pennsylvania | Active | Mid-Atlantic Interstate Transmission, LLC | 20.0 | 20.0 | 12.0 | Generation Interconnection | Solar | |
| AG2-360 | Broadford 138 kV | Virginia | Active | Appalachian Power Company | 250.0 | 250.0 | 250.0 | Generation Interconnection | Storage | |
| AG2-363 | Powerton 345 kV | Illinois | Active | Commonwealth Edison Company | 300.0 | 300.0 | 180.0 | Generation Interconnection | Solar | |
| AG2-364 | Powerton 345 kV | Illinois | Active | Commonwealth Edison Company | 200.0 | 200.0 | 120.0 | Generation Interconnection | Solar | |
| AG2-369 | Heritage - Wake 500 kV | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 86.0 | 86.0 | 51.6 | Generation Interconnection | Solar | |
| AG2-370 | Tillman 138 kV | Indiana | Active | AEP Indiana Michigan Transmission Company, Inc. | 50.0 | 50.0 | 20.0 | Generation Interconnection | Storage | |
| AG2-380 | Carville 138 kV IV | Maryland | Active | Delmarva Power and Light Company | 20.0 | 20.0 | 20.0 | Generation Interconnection | Storage | |
| AG2-382 | Cashie 230 kV | North Carolina | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 70.0 | 70.0 | 42.0 | Generation Interconnection | Solar | |
| AG2-384 | Chesterfield 230 kV | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 60.82 | 60.82 | 24.0 | Generation Interconnection | Storage | |
| AG2-401 | Losantville 345 kV | Indiana | Active | American Electric Power | 200.0 | 0.0 | 44.0 | Generation Interconnection | Solar | |
| AG2-405 | Continental 69 kV | Ohio | Active | American Electric Power | 49.9 | 0.0 | 10.98 | Generation Interconnection | Solar | |
| AG2-406 | Payne 69 kV | Ohio | Active | American Electric Power | 49.9 | 0.0 | 10.98 | Generation Interconnection | Solar | |
| AG2-411 | Statler Hill 115 kV | Pennsylvania | Active | Mid-Atlantic Interstate Transmission, LLC | 63.0 | 63.0 | 40.7 | Generation Interconnection | Solar | |
| AG2-420 | Eclipse #2 34.5 kV | Pennsylvania | Active | Mid-Atlantic Interstate Transmission, LLC | 25.0 | 25.0 | 14.0 | Generation Interconnection | Solar; Storage | |
| AG2-423 | Cherry Run - Harmony 138 kV | West Virginia | Active | Monongahela Power Company | 80.0 | 80.0 | 48.0 | Generation Interconnection | Solar | |
| AG2-424 | Summersville - Magnolia 69 kV | Kentucky | Active | East Kentucky Power Cooperative, Inc. | 63.25 | 63.25 | 34.95 | Generation Interconnection | Solar; Storage | |
| AG2-426 | Wakefield - Waverly 115 kV | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 33.5 | 33.5 | 33.5 | Generation Interconnection | Solar; Storage | |
| AG2-429 | Burma - Armstrong 138 kV | Pennsylvania | Active | Keystone Appalachian Transmission Company | 46.5 | 46.5 | 46.5 | Generation Interconnection | Solar; Storage | |
| AG2-436 | Carson - Rogers Road 500 kV | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 350.0 | 350.0 | 140.0 | Generation Interconnection | Solar | |
| AG2-440 | Twittys Creek - Madisonville 115 kV | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 75.0 | 75.0 | 45.0 | Generation Interconnection | Solar | |
| AG2-441 | Twittys Creek - Madisonville 115 kV | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 188.0 | 113.0 | 67.8 | Generation Interconnection | Solar | |
| AG2-442 | Twittys Creek - Madisonville 115 kV | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 140.0 | 140.0 | 84.0 | Generation Interconnection | Solar | |
| AG2-447 | Cedar Creek 138 kV VII | Delaware | Active | Delmarva Power and Light Company | 134.25 | 20.0 | 12.0 | Generation Interconnection | Solar | |
| AG2-448 | Cross School - Westvaco 138 kV | West Virginia | Active | The Potomac Edison Company | 50.0 | 50.0 | 30.0 | Generation Interconnection | Solar | |
| AG2-453 | Lasalle - Plano 345 kV | Illinois | Active | Commonwealth Edison Company | 280.0 | 280.0 | 196.0 | Generation Interconnection | Solar | |
| AG2-479 | Penns Tap-Richfield Tie 69 kV II | Pennsylvania | Active | PPL Electric Utilities Corporation | 20.0 | 0.0 | 4.1 | Generation Interconnection | Solar | |
| AG2-481 | Derry Tap-Derry Bus 69 kV III | Pennsylvania | Active | PPL Electric Utilities Corporation | 20.0 | 0.0 | 4.1 | Generation Interconnection | Solar | |
| AG2-484 | Mifflintown Bus-Mifflintown Tap 69 kV II | Pennsylvania | Active | PPL Electric Utilities Corporation | 20.0 | 0.0 | 4.6 | Generation Interconnection | Solar | |
| AG2-487 | Madison - Tanners Creek 138 kV | Indiana | Active | American Electric Power | 152.5 | 0.0 | 10.6 | Generation Interconnection | Solar | |
| AG2-491 | Meadow Lake 345 kV | Indiana | Active | American Electric Power | 100.0 | 100.0 | 60.0 | Generation Interconnection | Solar | |
| AG2-492 | Meadow Lake 345 kV | Indiana | Active | American Electric Power | 50.0 | 50.0 | 20.0 | Generation Interconnection | Storage | |
| AG2-516 | Pecatonica 138kV | Illinois | Active | Commonwealth Edison Company | 120.0 | 120.0 | 72.0 | Generation Interconnection | Solar | |
| AG2-518 | Tech Drive 138 kV | Virginia | Active | American Electric Power | 80.0 | 80.0 | 32.0 | Generation Interconnection | Storage | |
| AG2-519 | Royerton - Desoto 138 kV | Indiana | Active | AEP Indiana Michigan Transmission Company, Inc. | 66.5 | 66.5 | 66.5 | Generation Interconnection | Solar; Storage | |
| AG2-522 | Five Forks DP - Littleton DP 115 kV | North Carolina | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 80.0 | 80.0 | 48.0 | Generation Interconnection | Solar | |
| AG2-524 | LaSalle Station - Mazon 138 kV | Illinois | Active | Commonwealth Edison Company | 110.0 | 110.0 | 110.0 | Generation Interconnection | Solar; Storage | |
| AG2-544 | Silver Lake 345 kV | Illinois | Active | Commonwealth Edison Company | 200.0 | 200.0 | 80.0 | Generation Interconnection | Storage | |
| AG2-545 | Silver Lake 345 kV | Illinois | Active | Commonwealth Edison Company | 400.0 | 400.0 | 160.0 | Generation Interconnection | Storage | |
| AG2-548 | Corwin - Elk 138 kV | Ohio | Active | American Electric Power | 80.0 | 80.0 | 54.0 | Generation Interconnection | Solar; Storage | |
| AG2-550 | Bluff Point - Randolph 138 kV | Indiana | Active | American Electric Power | 100.0 | 100.0 | 60.0 | Generation Interconnection | Solar | |
| AG2-551 | Bluff Point - Randolph 138 kV | Indiana | Active | American Electric Power | 150.0 | 50.0 | 20.0 | Generation Interconnection | Storage | |
| AG2-561 | Glory - Glen Campbell 34.5 kV | Pennsylvania | Active | Mid-Atlantic Interstate Transmission, LLC | 20.0 | 20.0 | 12.0 | Generation Interconnection | Solar | |
| AG2-562 | Elderberry 345 kV | Indiana | Active | American Electric Power | 767.0 | 52.0 | 0.0 | Generation Interconnection | Natural Gas | |
| AG2-566 | Briery - Finneywood 230 kV | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 110.0 | 30.0 | 12.0 | Generation Interconnection | Storage | |
| AG2-568 | Stink Run - Sundial 138 kV | West Virginia | Active | American Electric Power | 80.0 | 80.0 | 48.0 | Generation Interconnection | Solar | |
| AG2-570 | Heritage - Wake 500 kV | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 400.0 | 400.0 | 100.0 | Generation Interconnection | Solar | |
| AG2-571 | Heritage - Wake 500 kV | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 500.0 | 100.0 | 40.0 | Generation Interconnection | Storage | |
| AG2-581 | Rawlings - Unity 500 kV | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 150.0 | 150.0 | 90.0 | Generation Interconnection | Solar | |
| AG2-582 | Flint Run 500 kV | West Virginia | Active | Monongahela Power Company | 2100.0 | 2100.0 | 2075.0 | Generation Interconnection | Natural Gas | |
| AG2-583 | Bremo - Cartersville 230 kV | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 115.0 | 115.0 | 69.0 | Generation Interconnection | Solar | |
| AG2-585 | Kensignton 138kV | Illinois | Active | Commonwealth Edison Company | 55.0 | 55.0 | 33.0 | Generation Interconnection | Solar | |
| AG2-616 | Churchtown - Upper Pittsgrove 138 kV | New Jersey | Active | Atlantic City Electric | 50.0 | 50.0 | 32.35 | Generation Interconnection | Solar | |
| AG2-617 | Waugh Chapel 115 kV | Maryland | Active | Baltimore Gas and Electric Company | 55.0 | 55.0 | 33.0 | Generation Interconnection | Solar | |
| AG2-618 | Morgantown Unit 1 and 2 | Maryland | Active | Potomac Electric Power Company | 110.0 | 110.0 | 71.5 | Generation Interconnection | Solar | |
| AG2-621 | Hoytdale 138 kV | Pennsylvania | Active | American Transmission Systems, Incorporated | 150.0 | 150.0 | 150.0 | Generation Interconnection | Storage | |
| AG2-625 | Pequest River-Furnace Brook Tap 34.5 kV II | New Jersey | Active | Jersey Central Power & Light Company | 19.6 | 19.6 | 8.232 | Generation Interconnection | Solar | |
| AG2-626 | Pequest River-Furnace Brook Tap 34.5 kV III | New Jersey | Active | Jersey Central Power & Light Company | 12.5 | 12.5 | 5.25 | Generation Interconnection | Solar | |
| AG2-637 | Randolph - Hodgin 138 kV | Indiana | Active | Indiana Michigan Power Company | 150.0 | 150.0 | 90.0 | Generation Interconnection | Solar | |
| AG2-657 | Kanawha River - Carbondale 138 kV | West Virginia | Active | American Electric Power | 90.0 | 90.0 | 37.8 | Generation Interconnection | Solar | |
| AG2-659 | Palmer Springs - Hawtree 115 kV | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 80.0 | 80.0 | 48.0 | Generation Interconnection | Solar | |
| AG2-660 | Nelson-Electric Junction 345 kV | Illinois | Active | Commonwealth Edison Company | 600.0 | 0.0 | 20.0 | Generation Interconnection | Storage | |
| AG2-661 | Hopewell - Colonial Trail 230 kV | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 150.0 | 0.0 | 20.0 | Generation Interconnection | Solar; Storage | |
| AG2-665 | Corwin - Elk 138 kV | Ohio | Active | American Electric Power | 160.0 | 80.0 | 54.0 | Generation Interconnection | Solar; Storage | |
| AG2-675 | Cordova 345 kV | Illinois | Active | Commonwealth Edison Company | 80.0 | 80.0 | 32.0 | Generation Interconnection | Storage | |
| AH1-004 | Avon - Renaker 138 kV | Kentucky | Active | East Kentucky Power Cooperative, Inc. | 40.0 | 40.0 | 24.0 | Generation Interconnection | Solar | |
| AH1-033 | Sligo 34.5 kV | North Carolina | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 19.5 | 19.5 | 13.0 | Generation Interconnection | Solar | |
| AH1-040 | Mackeys - Creswell 115 kV | North Carolina | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 150.0 | 150.0 | 90.0 | Generation Interconnection | Solar | |
| AH1-044 | Nelson - Electric Junction 345 kV | Illinois | Active | Commonwealth Edison Company | 800.0 | 200.0 | 120.0 | Generation Interconnection | Solar | |
| AH1-054 | Upton-Whitings 34.5 kV | New Jersey | Active | Jersey Central Power & Light Company | 8.25 | 8.25 | 3.465 | Generation Interconnection | Solar | |
| AH1-055 | Kyger Creek - Don Marquis 345 kV | Ohio | Active | Ohio Valley Electric Corporation | 220.0 | 220.0 | 154.0 | Generation Interconnection | Solar | |
| AH1-057 | Edgewood 12.47 kV | Maryland | Active | Delmarva Power and Light Company | 7.2 | 7.2 | 3.0 | Generation Interconnection | Solar | |
| AH1-059 | Sharp Road 69 kV | Ohio | Active | AEP Ohio Transmission Company, Inc. | 101.0 | 21.0 | 12.6 | Generation Interconnection | Solar | |
| AH1-060 | Cardington-Liberty 69 kV III | Ohio | Active | American Transmission Systems, Incorporated | 94.0 | 20.0 | 12.0 | Generation Interconnection | Solar | |
| AH1-071 | Midlothian 34.5 kV | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 20.0 | 20.0 | 12.0 | Generation Interconnection | Solar | |
| AH1-072 | Red Onion - VC5 69 kV | Virginia | Active | American Electric Power | 20.0 | 20.0 | 12.0 | Generation Interconnection | Solar | |
| AH1-073 | Red Onion - VC5 69 kV | Virginia | Active | American Electric Power | 40.0 | 20.0 | 12.0 | Generation Interconnection | Solar | |
| AH1-091 | Ahoskie 34.5kV | North Carolina | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 17.0 | 0.0 | 0.0 | Generation Interconnection | Storage | |
| AH1-098 | Wolf Glade-West Carroll 138 kV | Virginia | Active | American Electric Power | 40.0 | 40.0 | 24.0 | Generation Interconnection | Solar; Storage | |
| AH1-106 | Winterpock 34.5kV | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 26.0 | 26.0 | 15.6 | Generation Interconnection | Solar | |
| AH1-107 | Winterpock 34.5kV | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 26.0 | 26.0 | 15.6 | Generation Interconnection | Solar | |
| AH1-108 | Spruance NUG 230 kV | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 66.0 | 0.0 | 9.0 | Generation Interconnection | Natural Gas | |
| AH1-133 | Saltville - Tazewell 138 kV | Virginia | Active | American Electric Power | 70.0 | 70.0 | 29.4 | Generation Interconnection | Solar | |
| AH1-138 | Penniman 34.5 kV | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 20.0 | 20.0 | 8.4 | Generation Interconnection | Solar | |
| AH1-144 | Peter's Mountain 138 kV | Virginia | Active | American Electric Power | 70.0 | 70.0 | 29.4 | Generation Interconnection | Solar | |
| AH1-145 | Peter's Mountain 138 kV | Virginia | Active | American Electric Power | 150.0 | 80.0 | 80.0 | Generation Interconnection | Storage | |
| AH1-150 | Nelson-Electric Junction 345 kV | Illinois | Active | Commonwealth Edison Company | 1000.0 | 200.0 | 120.0 | Generation Interconnection | Solar | |
| AH1-151 | Nelson-Electric Junction 345 kV | Illinois | Active | Commonwealth Edison Company | 1200.0 | 200.0 | 120.0 | Generation Interconnection | Solar | |
| AH1-153 | Dumont 345 kV | Indiana | Active | AEP Indiana Michigan Transmission Company, Inc. | 200.0 | 50.0 | 30.0 | Generation Interconnection | Solar | |
| AH1-165 | Will County 138 kV | Illinois | Active | Commonwealth Edison Company | 72.0 | 72.0 | 0.0 | Generation Interconnection | Storage | |
| AH1-170 | Columbia DP 115kV | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 20.0 | 20.0 | 12.0 | Generation Interconnection | Solar | |
| AH1-188 | Pigeon Creek 138 kV | West Virginia | Active | Appalachian Power Company | 140.0 | 140.0 | 84.0 | Generation Interconnection | Solar | |
| AH1-196 | Silver Lake - Cherry Valley 345 kV | Illinois | Active | Commonwealth Edison Company | 150.0 | 150.0 | 90.0 | Generation Interconnection | Solar | |
| AH1-206 | Bethelboro 138 kV | Pennsylvania | Active | Keystone Appalachian Transmission Company | 60.0 | 60.0 | 60.0 | Generation Interconnection | Storage | |
| AH1-216 | Smithfield-Surry 230 kV | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 99.0 | 99.0 | 79.2 | Generation Interconnection | Solar; Storage | |
| AH1-221 | Heritage 500 kV | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 75.0 | 0.0 | 45.0 | Generation Interconnection | Storage | |
| AH1-223 | Poland Rd-Runway DP 230 kV | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 150.0 | 0.0 | 20.0 | Generation Interconnection | Storage | |
| AH1-227 | Flemming - Fremont 69 kV | Virginia | Active | Appalachian Power Company | 51.3 | 51.3 | 30.78 | Generation Interconnection | Solar | |
| AH1-239 | Upchurch - Zula 69 kV | Kentucky | Active | East Kentucky Power Cooperative, Inc. | 80.0 | 80.0 | 48.0 | Generation Interconnection | Solar | |
| AH1-247 | Lardin - Lake Lynn 138kV | Pennsylvania | Active | Keystone Appalachian Transmission Company | 40.0 | 40.0 | 24.0 | Generation Interconnection | Solar | |
| AH1-248 | Lardin - Lake Lynn 138kV | Pennsylvania | Active | Keystone Appalachian Transmission Company | 65.0 | 25.0 | 15.0 | Generation Interconnection | Solar | |
| AH1-249 | Lardin - Lake Lynn 138kV | Pennsylvania | Active | Keystone Appalachian Transmission Company | 145.0 | 80.0 | 80.0 | Generation Interconnection | Storage | |
| AH1-251 | Todds Tavern- Spotsylvania/Goldsdale 115kV | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 50.0 | 50.0 | 50.0 | Generation Interconnection | Storage | |
| AH1-254 | Greenland Gap 500 kV II | West Virginia | Active | Monongahela Power Company | 171.4 | 171.4 | 36.538 | Generation Interconnection | Wind | |
| AH1-257 | Broadway - Washington 34.5 kV | New Jersey | Active | Jersey Central Power & Light Company | 19.25 | 19.25 | 8.085 | Generation Interconnection | Solar | |
| AH1-258 | Belford - Keansburg 34.5 kV | New Jersey | Active | Jersey Central Power & Light Company | 19.25 | 19.25 | 8.085 | Generation Interconnection | Solar | |
| AH1-260 | New Freedom - Monroe 230 kV | New Jersey | Active | Atlantic City Electric | 300.0 | 300.0 | 300.0 | Generation Interconnection | Storage | |
| AH1-261 | Northeast - Riverside 230 kV | Maryland | Active | Baltimore Gas and Electric Company | 135.0 | 135.0 | 135.0 | Generation Interconnection | Storage | |
| AH1-263 | Chancellor 115 kV | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 200.0 | 200.0 | 200.0 | Generation Interconnection | Storage | |
| AH1-269 | Claytor 138 kV | Virginia | Active | Appalachian Power Company | 50.0 | 50.0 | 50.0 | Generation Interconnection | Storage | |
| AH1-271 | Cashie 230 kV | North Carolina | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 110.0 | 40.0 | 24.0 | Generation Interconnection | Solar | |
| AH1-272 | Argenta - Twin Branch 345 kV | Michigan | Active | AEP Indiana Michigan Transmission Company, Inc. | 185.0 | 185.0 | 123.9 | Generation Interconnection | Solar | |
| AH1-280 | Jetersville-Ponton 115 kV | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 106.0 | 20.0 | 12.0 | Generation Interconnection | Solar | |
| AH1-282 | Galion - Ohio Central 345 kV | Ohio | Active | AEP Ohio Transmission Company, Inc. | 49.9 | 49.9 | 45.9 | Generation Interconnection | Solar | |
| AH1-283 | Mount Storm-Pruntytown 500kV | Maryland | Active | The Potomac Edison Company | 200.0 | 200.0 | 120.0 | Generation Interconnection | Solar | |
| AH1-292 | Sullivan 345 kV | Indiana | Active | American Electric Power | 200.0 | 0.0 | 44.0 | Generation Interconnection | Solar | |
| AH1-302 | Olive - Reynolds 345 kV | Indiana | Active | AEP Indiana Michigan Transmission Company, Inc. | 275.0 | 75.0 | 75.0 | Generation Interconnection | Storage | |
| AH1-304 | Delaware-Van Buren 138 kV | Indiana | Active | American Electric Power | 163.0 | 0.0 | 9.8 | Generation Interconnection | Solar | |
| AH1-305 | Olive - Reynolds 345 kV | Indiana | Active | AEP Indiana Michigan Transmission Company, Inc. | 275.0 | 0.0 | 35.72 | Generation Interconnection | Solar | |
| AH1-306 | Mississinewa-Gaston 138 kV | Indiana | Active | AEP Indiana Michigan Transmission Company, Inc. | 200.0 | 0.0 | 28.8 | Generation Interconnection | Solar | |
| AH1-311 | Heartsease DP - Mayo Dunbar 115kV | North Carolina | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 75.0 | 0.0 | 2.25 | Generation Interconnection | Solar | |
| AH1-314 | East Danville 138 kV | Virginia | Active | American Electric Power | 100.0 | 100.0 | 100.0 | Generation Interconnection | Storage | |
| AH1-327 | Hardin Switch 345 kV | Ohio | Active | American Electric Power | 250.0 | 0.0 | 8.44 | Generation Interconnection | Solar | |
| AH1-328 | Blue Jacket - Kirby 138 kV | Ohio | Active | The Dayton Power and Light Company | 206.55 | 0.0 | 21.3 | Generation Interconnection | Solar | |
| AH1-334 | Lakehurst - Whitings 34.5 kV | New Jersey | Active | Jersey Central Power & Light Company | 19.25 | 19.25 | 8.085 | Generation Interconnection | Solar | |
| AH1-338 | New Sub S2354 138kV | Illinois | Active | Commonwealth Edison Company | 180.0 | 180.0 | 23.4 | Generation Interconnection | Solar | |
| AH1-341 | ESS-H445 3B 138kv | Illinois | Active | Commonwealth Edison Company | 150.0 | 150.0 | 96.6 | Generation Interconnection | Solar | |
| AH1-343 | Crystal Hill DP- Perth 115kV | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 69.0 | 69.0 | 41.4 | Generation Interconnection | Solar | |
| AH1-345 | Remington 324 34.5 kV | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 14.0 | 14.0 | 8.4 | Generation Interconnection | Solar | |
| AH1-348 | Pound 34.5 kV | Virginia | Active | American Electric Power | 10.0 | 10.0 | 6.0 | Generation Interconnection | Solar | |
| AH1-387 | Meadowbrook-Greenland Gap 500kV | West Virginia | Active | The Potomac Edison Company | 150.0 | 150.0 | 22.05 | Generation Interconnection | Wind | |
| AH1-392 | Gravel Pit-Kankakee 138 kV | Indiana | Active | American Electric Power | 90.0 | 90.0 | 60.0 | Generation Interconnection | Solar | |
| AH1-396 | Gary 24.94 kV | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 11.891 | 11.891 | 1.8 | Generation Interconnection | Solar | |
| AH1-397 | Shacklesfords 34.5 kV | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 19.67 | 19.67 | 2.97 | Generation Interconnection | Solar | |
| AH1-399 | North Doswell 12.5 kV | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 9.87 | 9.87 | 1.48 | Generation Interconnection | Solar | |
| AH1-439 | Buckingham- Farmville 230kV | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 85.0 | 85.0 | 51.0 | Generation Interconnection | Solar | |
| AH1-452 | Clementine-Clementine Jct. 25 kV | Pennsylvania | Active | Keystone Appalachian Transmission Company | 19.9 | 19.9 | 8.35 | Generation Interconnection | Solar | |
| AH1-460 | Hooversville - Scalp Level 115 kV | Pennsylvania | Active | Mid-Atlantic Interstate Transmission, LLC | 66.0 | 66.0 | 39.6 | Generation Interconnection | Solar | |
| AH1-461 | Buckhorn 138 kV | Virginia | Active | Appalachian Power Company | 80.0 | 80.0 | 80.0 | Generation Interconnection | Storage | |
| AH1-482 | Olive - Reynolds #2 345 kV | Indiana | Active | AEP Indiana Michigan Transmission Company, Inc. | 338.0 | 78.0 | 78.0 | Generation Interconnection | Storage | |
| AH1-528 | Rawlings - Unity 500 kV | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 300.8 | 300.8 | 180.0 | Generation Interconnection | Solar | |
| AH1-535 | Nagel - Cane River 230 kV | Tennessee | Active | Appalachian Power Company | 100.0 | 100.0 | 40.0 | Generation Interconnection | Solar; Storage | |
| AH1-537 | Pierce - Kyger Creek 345 kV | Ohio | Active | Ohio Valley Electric Corporation | 178.5 | 178.5 | 17.85 | Generation Interconnection | Solar | |
| AH1-541 | Chestnut 345 kV | Illinois | Active | Commonwealth Edison Company | 92.4 | 92.4 | 27.72 | Generation Interconnection | Solar; Storage | |
| AH1-542 | Crissinger-Delaware Business Park 138kV | Ohio | Active | American Transmission Systems, Incorporated | 110.0 | 110.0 | 22.0 | Generation Interconnection | Solar; Storage | |
| AH1-543 | Mulberry - Tazewell 345 kV | Illinois | Active | Commonwealth Edison Company | 157.4 | 157.4 | 31.48 | Generation Interconnection | Solar; Storage | |
| AH1-545 | Wylie Ridge-Tidd 345kV | Pennsylvania | Active | Monongahela Power Company | 200.0 | 200.0 | 20.0 | Generation Interconnection | Solar | |
| AH1-546 | Bremo - Buckingham 230 kV | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 65.0 | 65.0 | 39.0 | Generation Interconnection | Solar | |
| AH1-552 | Chalk Point 230 kV | Maryland | Active | Potomac Electric Power Company | 670.2 | 670.2 | 670.2 | Generation Interconnection | Solar; Storage | |
| AH1-563 | Aurora E.C. 138kV | Illinois | Active | Commonwealth Edison Company | 1206.0 | 150.0 | 150.0 | Generation Interconnection | Storage | |
| AH1-564 | Rockford II 138 kV | Illinois | Active | Commonwealth Edison Company | 330.0 | 150.0 | 150.0 | Generation Interconnection | Storage | |
| AH1-567 | University Park 138 kV | Illinois | Active | Commonwealth Edison Company | 328.0 | 5.0 | 5.0 | Generation Interconnection | Natural Gas | |
| AH1-570 | Millersburg 69 kV | Kentucky | Active | East Kentucky Power Cooperative, Inc. | 25.0 | 25.0 | 15.6 | Generation Interconnection | Solar | |
| AH1-571 | Millersburg 69 kV | Kentucky | Active | East Kentucky Power Cooperative, Inc. | 45.0 | 20.0 | 12.5 | Generation Interconnection | Solar | |
| AH1-580 | Nottingham 138 kV | Ohio | Active | AEP Ohio Transmission Company, Inc. | 400.0 | 200.0 | 134.0 | Generation Interconnection | Solar | |
| AH1-617 | Harbert Metering 138 kV | Kentucky | Active | Kentucky Power Company | 200.0 | 200.0 | 120.0 | Generation Interconnection | Solar | |
| AH1-637 | Oak Grove 34.5 kV | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 16.0 | 16.0 | 9.6 | Generation Interconnection | Solar | |
| AH1-641 | Churchtown - Upper Pittsgrove 138kV | New Jersey | Active | Atlantic City Electric | 65.0 | 15.0 | 7.0 | Generation Interconnection | Solar | |
| AH1-661 | Cannelville 12.47 kV | Ohio | Active | American Electric Power | 10.07 | 10.07 | 9.063 | Generation Interconnection | Other | |
| AH1-664 | Goddard-Plumville 138 kV | Kentucky | Active | East Kentucky Power Cooperative, Inc. | 100.0 | 100.0 | 66.8 | Generation Interconnection | Solar | |
| AH1-665 | Goddard-Plumsville 138 kV II | Kentucky | Active | East Kentucky Power Cooperative, Inc. | 180.0 | 80.0 | 53.5 | Generation Interconnection | Solar | |
| AH1-666 | Flemingsburg - Spurlock 138 kV | Kentucky | Active | East Kentucky Power Cooperative, Inc. | 80.0 | 80.0 | 48.0 | Generation Interconnection | Solar | |
| AH1-667 | Philipsburg-Shawville 34.5 kV | Pennsylvania | Active | Mid-Atlantic Interstate Transmission, LLC | 18.0 | 18.0 | 10.8 | Generation Interconnection | Solar | |
| AH1-672 | Farmview 138 kV | Delaware | Active | Delmarva Power and Light Company | 75.0 | 75.0 | 48.9 | Generation Interconnection | Solar | |
| AH1-673 | State Line - River Energy Center 138 kV | Illinois | Active | Commonwealth Edison Company | 85.0 | 85.0 | 85.0 | Generation Interconnection | Storage | |
| AH1-677 | Rogers Road 500 kV | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 1756.0 | 0.0 | 67.0 | Generation Interconnection | Natural Gas | |
| AH1-678 | Heritage 500 kV | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 1525.5 | 0.0 | 34.0 | Generation Interconnection | Natural Gas; Other | |
| AH1-679 | Four Rivers 230 kV | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 766.0 | 20.0 | 20.0 | Generation Interconnection | Natural Gas | |
| AH1-680 | Sammis - South Canton 345 kV | Ohio | Active | American Transmission Systems, Incorporated | 1300.0 | 1300.0 | 1300.0 | Generation Interconnection | Natural Gas | |
| AH1-681 | Cunningham 500 kV | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 1000.0 | 0.0 | 27.3 | Generation Interconnection | Natural Gas | |
| AH1-682 | Ladysmith CT 230 kV | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 190.0 | 0.0 | 21.0 | Generation Interconnection | Natural Gas | |
| AH1-683 | Ladysmith CT 230 kV | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 190.0 | 0.0 | 25.0 | Generation Interconnection | Natural Gas | |
| AH1-684 | Remington CT 230 kV | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 190.0 | 0.0 | 23.0 | Generation Interconnection | Natural Gas | |
| AH1-685 | Remington CT 230 kV | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 190.0 | 0.0 | 26.0 | Generation Interconnection | Natural Gas | |
| AH1-686 | Hanging Rock 765 kV | Ohio | Active | American Electric Power | 1364.0 | 24.0 | 21.0 | Generation Interconnection | Natural Gas | |
| AH1-687 | Bear Garden 230kV | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 682.0 | 0.0 | 51.0 | Generation Interconnection | Natural Gas | |
| AH1-691 | Ladysmith CT 230 kV | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 209.0 | 0.0 | 26.0 | Generation Interconnection | Natural Gas | |
| AH1-692 | Ladysmith CT 230 kV | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 209.0 | 0.0 | 26.0 | Generation Interconnection | Natural Gas | |
| AH1-693 | Remington CT 230 kV | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 190.0 | 0.0 | 20.0 | Generation Interconnection | Natural Gas | |
| AH1-694 | Ladysmith CT 230 kV | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 190.0 | 0.0 | 18.0 | Generation Interconnection | Natural Gas | |
| AH1-695 | Three Mile Island 230 kV | Pennsylvania | Active | Mid-Atlantic Interstate Transmission, LLC | 859.0 | 859.0 | 803.0 | Generation Interconnection | Nuclear | |
| AH1-696 | Possum Point 230kV | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 668.0 | 0.0 | 94.0 | Generation Interconnection | Natural Gas | |
| AH1-698 | Braidwood 345 kV | Illinois | Active | Commonwealth Edison Company | 2584.0 | 130.0 | 57.6 | Generation Interconnection | Nuclear | |
| AH1-699 | Wellsville 345 kV | Ohio | Active | American Transmission Systems, Incorporated | 1210.0 | 58.0 | 69.0 | Generation Interconnection | Natural Gas | |
| AH1-701 | Valero 69 kV | New Jersey | Active | Atlantic City Electric | 61.0 | 0.0 | 20.0 | Generation Interconnection | Natural Gas; Oil | |
| AH1-702 | Byron 345 kV | Illinois | Active | Commonwealth Edison Company | 2530.0 | 88.0 | 43.0 | Generation Interconnection | Nuclear | |
| AH1-703 | Bergen 230kV | New Jersey | Active | Public Service Electric and Gas Company | 670.61 | 35.61 | 51.254 | Generation Interconnection | Natural Gas | |
| AH1-704 | Hannibal 138 kV | Ohio | Active | AEP Ohio Transmission Company, Inc. | 509.0 | 24.0 | 20.0 | Generation Interconnection | Natural Gas | |
| AH1-706 | Lordstown 345 kV | Ohio | Active | American Transmission Systems, Incorporated | 970.453 | 30.453 | 23.823 | Generation Interconnection | Natural Gas | |
| AH1-710 | Salem 500kV | New Jersey | Active | Public Service Electric and Gas Company | 2650.8 | 256.8 | 228.2 | Generation Interconnection | Nuclear | |
| AH1-711 | Lemoyne 345 kV | Ohio | Active | American Transmission Systems, Incorporated | 1108.2 | 408.2 | 292.5 | Generation Interconnection | Natural Gas | |
| AH1-712 | Cunningham 500 kV | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 776.0 | 776.0 | 611.0 | Generation Interconnection | Natural Gas; Other | |
| AH1-713 | Mt. Storm 500kV | West Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 538.0 | 0.0 | 14.0 | Generation Interconnection | Coal | |
| AH1-714 | Lasalle 345 kV | Illinois | Active | Commonwealth Edison Company | 1360.0 | 169.0 | 174.1 | Generation Interconnection | Nuclear | |
| AH1-715 | Linden 138kV & 230kV | New Jersey | Active | Public Service Electric and Gas Company | 803.17 | 127.17 | 149.369 | Generation Interconnection | Natural Gas | |
| AH1-716 | Surry-Skiffes Creek 500kV | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 650.0 | 650.0 | 650.0 | Generation Interconnection | Storage | |
| AH1-718 | Nelson 345 kV | Illinois | Active | Commonwealth Edison Company | 391.0 | 11.0 | 38.0 | Generation Interconnection | Natural Gas | |
| AH1-719 | Beverly 345 kV | Ohio | Active | AEP Ohio Transmission Company, Inc. | 694.0 | 24.0 | 21.0 | Generation Interconnection | Natural Gas | |
| AH1-721 | Laurel-Cooper 161 kV | Kentucky | Active | East Kentucky Power Cooperative, Inc. | 786.0 | 786.0 | 758.9507 | Generation Interconnection | Natural Gas | |
| AH1-722 | Linden 230kV | New Jersey | Active | Public Service Electric and Gas Company | 806.4 | 130.4 | 158.1 | Generation Interconnection | Natural Gas | |
| AH1-723 | Cunningham 500 kV | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 776.0 | 776.0 | 712.0 | Generation Interconnection | Natural Gas; Other | |
| AH1-725 | Conastone 500 kV | Maryland | Active | Baltimore Gas and Electric Company | 500.0 | 500.0 | 500.0 | Generation Interconnection | Storage | |
| AH1-727 | Brambleton-Goose Creek 500kV | Virginia | Active | Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) | 425.0 | 425.0 | 425.0 | Generation Interconnection | Storage | |
| AH1-734 | South Bend 500 kV | Pennsylvania | Active | Keystone Appalachian Transmission Company | 1058.4 | 270.3 | 268.6 | Generation Interconnection | Natural Gas | |
| AH1-744 | Cheltenham 500 kV | Maryland | Active | Potomac Electric Power Company | 853.5 | 53.5 | 48.285 | Generation Interconnection | Natural Gas | |
| AH1-746 | Madera - Westover South 115 kV | Pennsylvania | Active | Mid-Atlantic Interstate Transmission, LLC | 109.9 | 0.0 | 20.0 | Generation Interconnection | Wind |
Stability Clusters
Stability analysis was performed by grouping New Service Requests into clusters based on their electrical proximity in order to increase the efficiency of the stability study process. A single stability study is performed for all New Service Requests in the cluster and any reinforcement costs shall be cost allocated proportionally to all New Service Requests in the cluster.
| Cluster Index | Cluster Name | New Service Requests | Status | Executive Summary |
|---|---|---|---|---|
| 1 | Cluster 1 | AH1-712, AH1-723 | Analysis Complete - No Issues | |
| 2 | Cluster 2 | AG2-171, AG2-213, AG2-440, AG2-441, AG2-442, AH1-280 | Analysis Complete - Issues Found | |
| 3 | Cluster 3 | AG2-151, AG2-198, AG2-566, AG2-583, AH1-170, AH1-439, AH1-546 | Analysis Complete - No Issues | |
| 4 | Cluster 4 | AG2-121, AG2-238, AG2-382, AH1-040, AH1-271 | Analysis Complete - No Issues | |
| 5 | Cluster 5 | AG2-426 | Analysis Complete - No Issues | |
| 7 | Cluster 7 | AG2-262, AG2-341, AG2-522, AG2-659, AH1-343 | Analysis Complete - No Issues | |
| 8 | Cluster 8 | AG2-077, AG2-270, AG2-581, AH1-528 | Analysis Complete - No Issues | |
| 10 | Cluster 10 | AH1-716 | Analysis Complete - No Issues | |
| 11 | Cluster 11 | AG2-086 | Analysis Complete - No Issues | |
| 12 | Cluster 12 | AG2-088, AG2-384, AH1-679 | Analysis Complete - No Issues | |
| 13 | Cluster 13 | AG2-661, AH1-216 | Analysis Complete - No Issues | |
| 15 | Cluster 15 | AH1-251, AH1-263 | Analysis Complete - No Issues | |
| 16 | Cluster 16 | AG2-182, AH1-727 | Analysis Complete - No Issues | |
| 18 | Cluster 18 | AG2-068, AG2-069, AG2-369, AG2-570, AG2-571 | Analysis Complete - No Issues | |
| 19 | Cluster 19 | AG2-339, AG2-436 | Analysis Complete - No Issues | |
| 23 | Cluster 23 | AG2-550, AG2-551, AG2-637 | Analysis Complete - No Issues | |
| 24 | Cluster 24 | AG2-152, AG2-272, AG2-518, AH1-098, AH1-144, AH1-145, AH1-269, AH1-314 | Analysis Complete - No Issues | |
| 25 | Cluster 25 | AG2-548, AG2-665 | Analysis Complete - No Issues | |
| 27 | Cluster 27 | AG2-329, AH1-282 | Analysis Complete - No Issues | |
| 28 | Cluster 28 | AG2-191, AG2-519 | Analysis Complete - No Issues | |
| 29 | Cluster 29 | AG2-360, AH1-072, AH1-073, AH1-133, AH1-188, AH1-227, AH1-535 | Analysis Complete - No Issues | |
| 31 | Cluster 31 | AG2-184, AH1-617 | Analysis Complete - No Issues | |
| 32 | Cluster 32 | AG2-082, AG2-568, AG2-657, AH1-580, AH1-686, AH1-704, AH1-719 | Analysis Complete - No Issues | |
| 33 | Cluster 33 | AG2-248, AG2-332 | Analysis Complete - No Issues | |
| 34 | Cluster 34 | AG2-289, AG2-290, AH1-059 | Analysis Complete - No Issues | |
| 35 | Cluster 35 | AH1-392 | Analysis Complete - No Issues | |
| 36 | Cluster 36 | AG2-072 | Analysis Complete - No Issues | |
| 37 | Cluster 37 | AG2-014, AG2-126, AG2-163, AG2-343, AG2-345, AG2-491, AG2-492, AH1-482 | Analysis Complete - No Issues | |
| 38 | Cluster 38 | AG2-245, AH1-302 | Analysis Complete - No Issues | |
| 39 | Cluster 39 | AG2-029, AG2-104, AG2-370 | Analysis Complete - No Issues | |
| 40 | Cluster 40 | AG2-230, AG2-562, AH1-153, AH1-272 | Analysis Complete - No Issues | |
| 41 | Cluster 41 | AH1-461 | Analysis Complete - No Issues | |
| 43 | Cluster 43 | AH1-680 | Analysis Complete - No Issues | |
| 44 | Cluster 44 | AG2-236, AG2-621, AH1-699, AH1-706 | Analysis Complete - No Issues | |
| 45 | Cluster 45 | AG2-119, AH1-542 | Analysis Complete - No Issues | |
| 48 | Cluster 48 | AH1-711 | Analysis Complete - No Issues | |
| 49 | Cluster 49 | AG2-057, AH1-060 | Analysis Complete - No Issues | |
| 50 | Cluster 50 | AG2-109 | Analysis Complete - No Issues | |
| 53 | Cluster 53 | AH1-338 | Analysis Complete - No Issues | |
| 54 | Cluster 54 | AG2-660, AG2-675, AH1-044, AH1-150, AH1-151, AH1-718 | Analysis Complete - No Issues | |
| 55 | Cluster 55 | AG2-585 | Analysis Complete - No Issues | |
| 56 | Cluster 56 | AG2-114, AH1-541 | Analysis Complete - No Issues | |
| 57 | Cluster 57 | AG2-453, AG2-524, AH1-165, AH1-563, AH1-673, AH1-698, AH1-714 | Analysis Complete - No Issues | |
| 58 | Cluster 58 | AG2-061, AG2-363, AG2-364, AH1-543 | Analysis Complete - No Issues | |
| 59 | Cluster 59 | AH1-567 | Analysis Complete - No Issues | |
| 60 | Cluster 60 | AG2-516, AH1-341, AH1-564 | Analysis Complete - No Issues | |
| 61 | Cluster 61 | AH1-702 | Analysis Complete - No Issues | |
| 62 | Cluster 62 | AG2-544, AG2-545, AH1-196 | Analysis Complete - No Issues | |
| 64 | Cluster 64 | AG2-062, AG2-448, AH1-206, AH1-247, AH1-248, AH1-249 | Analysis Complete - No Issues | |
| 66 | Cluster 66 | AG2-300, AH1-254, AH1-283, AH1-387 | Analysis Complete - No Issues | |
| 67 | Cluster 67 | AG2-288, AG2-423 | Analysis Complete - No Issues | |
| 70 | Cluster 70 | AG2-429 | Analysis Complete - No Issues | |
| 71 | Cluster 71 | AH1-545 | Analysis Complete - No Issues | |
| 72 | Cluster 72 | AH1-734 | Analysis Complete - No Issues | |
| 73 | Cluster 73 | AG2-582 | Analysis Complete - No Issues | |
| 74 | Cluster 74 | AG2-073, AG2-081, AH1-004, AH1-570, AH1-571, AH1-664, AH1-665, AH1-666 | Analysis Complete - No Issues | |
| 76 | Cluster 76 | AH1-239 | Analysis Complete - Issues Found | |
| 77 | Cluster 77 | AG2-298 | Analysis Complete - No Issues | |
| 79 | Cluster 79 | AG2-424, AH1-721 | Analysis Complete - No Issues | |
| 81 | Cluster 81 | AG2-074, AG2-479, AG2-481, AG2-484 | Analysis Complete - No Issues | |
| 82 | Cluster 82 | AG2-176, AG2-411, AH1-460 | Analysis Complete - No Issues | |
| 84 | Cluster 84 | AG2-356 | Not Required | |
| 85 | Cluster 85 | AG2-125 | Analysis Complete - No Issues | |
| 86 | Cluster 86 | AG2-380, AG2-447, AH1-672 | Analysis Complete - No Issues | |
| 87 | Cluster 87 | AG2-297, AG2-616, AH1-260, AH1-641, AH1-701 | Analysis Complete - No Issues | |
| 89 | Cluster 89 | AH1-695 | Analysis Complete - No Issues | |
| 90 | Cluster 90 | AG2-617, AH1-261, AH1-725 | Analysis Complete - No Issues | |
| 91 | Cluster 91 | AG2-618, AH1-552, AH1-744 | Analysis Complete - No Issues | |
| 93 | Cluster 93 | AH1-703, AH1-710, AH1-715, AH1-722 | Analysis Complete - No Issues | |
| 95 | Cluster 95 | AG2-106 | Analysis Complete - No Issues | |
| 96 | Cluster 96 | AG2-107 | Analysis Complete - No Issues | |
| 97 | Cluster 97 | AH1-306 | Analysis Complete - No Issues | |
| 92 | Cluster 92 | AH1-055, AH1-537 | Analysis Complete - No Issues |
CIR Claims From Deactivated Generators
The following Transition Cycle 2 projects intend to claim and transfer CIRs from deactivated capacity generation resources. PJM performed a reliability analysis of the impacts to the system capability for the proposed transfers of CIRs from the deactivated generation resources.
| Project | Status | CIR Claimed | POI Transfer | ||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| AG2-068 | Active | 60.0 | Yes |
|
|||||||||||||
| AG2-069 | Active | 90.0 | Yes |
|
|||||||||||||
| AG2-077 | Active | 120.0 | Yes |
|
|||||||||||||
| AG2-095 | Active | 10.8 | Yes |
|
|||||||||||||
| AG2-152 | Active | 79.0 | Yes |
|
|||||||||||||
| AG2-193 | Active | 12.0 | Yes |
|
|||||||||||||
| AG2-213 | Active | 48.0 | Yes |
|
|||||||||||||
| AG2-369 | Active | 51.6 | Yes |
|
|||||||||||||
| AG2-384 | Active | 24.0 | Yes |
|
|||||||||||||
| AG2-440 | Active | 45.0 | Yes |
|
|||||||||||||
| AG2-441 | Active | 67.8 | Yes |
|
|||||||||||||
| AG2-618 | Active | 71.5 | No |
|
|||||||||||||
| AH1-071 | Active | 12.0 | Yes |
|
|||||||||||||
| AH1-138 | Active | 8.4 | Yes |
|
|||||||||||||
| AH1-221 | Active | 45.0 | Yes |
|
|||||||||||||
| AH1-227 | Active | 30.78 | Yes |
|
|||||||||||||
| AH1-552 | Active | 670.2 | No |
|
|||||||||||||
| AH1-721 | Active | 116.0 | Yes |
|
Cost Summary
The table below shows a summary of the total planning level cost estimates for each individual New Service Request received by PJM and studied in Transition Cycle 2 Phase II System Impact Study. These network upgrade costs are subject to change as a result of a facility study performed by the Interconnected Transmission Owner during the Phase II System Impact Study.
| Project ID | Transmission Owner Interconnection Facilities (TOIF) | Physical Interconnection Network Upgrades | System Reliability Network Upgrades | Affected System Study Reinforcements | Additional Charges | Total Cost |
|---|---|---|---|---|---|---|
| AG2-014 | $0 | $1,780,859 | $0 | $21,125,434 | $603,891 | $23,510,184 |
| AG2-016 | $730,161 | $976,499 | $0 | $0 | $27,580 | $1,734,240 |
| AG2-029 | $1,659,783 | $31,927,955 | $0 | $65,040 | $1,117,553 | $34,770,331 |
| AG2-037 | $33,300 | $0 | $144,300 | $0 | $0 | $177,600 |
| AG2-049 | $0 | $0 | $0 | $0 | $0 | $0 |
| AG2-057 | $28,656 | $733,106 | $0 | $0 | $2,636 | $764,397 |
| AG2-061 | $0 | $511,813 | $0 | $12,124 | $0 | $523,937 |
| AG2-062 | $2,659,495 | $152,001 | $0 | $0 | $584,091 | $3,395,587 |
| AG2-068 | $1,094,345 | $13,755,464 | $0 | $143,000 | $276,414 | $15,269,223 |
| AG2-069 | $1,094,345 | $13,755,464 | $0 | $214,000 | $276,414 | $15,340,223 |
| AG2-072 | $3,195,258 | $107,970,412 | $20,391,698 | $67,900,000 | $338,434 | $199,795,802 |
| AG2-073 | $1,863,000 | $9,637,000 | $0 | $0 | $0 | $11,500,000 |
| AG2-074 | $636,546 | $1,218,744 | $0 | $0 | $0 | $1,855,290 |
| AG2-077 | $0 | $0 | $14,008,499 | $0 | $486,439 | $14,494,938 |
| AG2-081 | $845,000 | $6,285,500 | $0 | $6,394,854 | $0 | $13,525,354 |
| AG2-082 | $609,937 | $3,179,540 | $0 | $0 | $375,078 | $4,164,556 |
| AG2-086 | $0 | $30,366,362 | $0 | $0 | $0 | $30,366,362 |
| AG2-088 | $5,270,575 | $8,334,288 | $0 | $0 | $499,571 | $14,104,434 |
| AG2-095 | $0 | $0 | $0 | $0 | $0 | $0 |
| AG2-104 | $0 | $92,761 | $1,323,752 | $0 | $369,787 | $1,786,300 |
| AG2-106 | $0 | $92,761 | $1,160,359 | $0 | $232,867 | $1,485,987 |
| AG2-107 | $0 | $91,761 | $1,160,359 | $0 | $228,760 | $1,480,880 |
| AG2-109 | $1,153,439 | $14,052,335 | $509,895 | $0 | $427,497 | $16,143,166 |
| AG2-114 | $1,210,738 | $75,301,646 | $328,247 | $22,353 | $792,517 | $77,655,502 |
| AG2-119 | $736,652 | $4,631,082 | $0 | $0 | $509,013 | $5,876,747 |
| AG2-121 | $0 | $0 | $0 | $0 | $0 | $0 |
| AG2-124 | $0 | $190,117 | $0 | $0 | $0 | $190,117 |
| AG2-125 | $0 | $0 | $0 | $0 | $0 | $0 |
| AG2-126 | $1,003,988 | $9,087,740 | $0 | $12,009,282 | $1,721,443 | $23,822,453 |
| AG2-151 | $9,541,601 | $20,712,812 | $48,582 | $0 | $483,290 | $30,786,285 |
| AG2-152 | $1,252,162 | $15,980,643 | $0 | $0 | $750,157 | $17,982,962 |
| AG2-163 | $0 | $1,273,714 | $0 | $30,941 | $603,891 | $1,908,546 |
| AG2-166 | $636,546 | $1,218,744 | $0 | $0 | $0 | $1,855,290 |
| AG2-171 | $8,967,756 | $7,352,571 | $17,652,911 | $0 | $483,290 | $34,456,528 |
| AG2-176 | $755,721 | $6,907,331 | $160,187,987 | $0 | $517,642 | $168,368,681 |
| AG2-182 | $2,138,836 | $57,114,995 | $0 | $0 | $552,827 | $59,806,658 |
| AG2-184 | $571,120 | $21,611,154 | $12,996,400 | $0 | $677,024 | $35,855,699 |
| AG2-191 | $0 | $1,074,801 | $182,450 | $0 | $603,891 | $1,861,142 |
| AG2-192 | $0 | $157,768 | $117,550 | $0 | $301,946 | $577,264 |
| AG2-193 | $0 | $0 | $0 | $0 | $0 | $0 |
| AG2-198 | $849,070 | $11,907,554 | $6,057,452 | $0 | $249,786 | $19,063,862 |
| AG2-200 | $376,804 | $155,127 | $3,468,120 | $0 | $36,547 | $4,036,598 |
| AG2-213 | $9,272,482 | $5,995,888 | $23,537,260 | $0 | $483,290 | $39,288,920 |
| AG2-216 | $0 | $0 | $0 | $0 | $0 | $0 |
| AG2-230 | $829,892 | $3,290,302 | $0 | $0 | $558,776 | $4,678,970 |
| AG2-236 | $57,020 | $142,935 | $0 | $0 | $5,271 | $205,226 |
| AG2-238 | $0 | $0 | $0 | $0 | $0 | $0 |
| AG2-240 | $0 | $0 | $0 | $0 | $0 | $0 |
| AG2-245 | $849,909 | $33,314,511 | $0 | $68,689 | $1,117,553 | $35,350,662 |
| AG2-248 | $493,084 | $13,779,028 | $0 | $36,245 | $375,078 | $14,683,436 |
| AG2-262 | $0 | $0 | $0 | $0 | $0 | $0 |
| AG2-270 | $12,665,760 | $2,142,685 | $9,446,270 | $0 | $499,571 | $24,754,286 |
| AG2-272 | $986,167 | $5,906,901 | $0 | $0 | $750,157 | $7,643,225 |
| AG2-288 | $4,009,925 | $447,937 | $0 | $0 | $514,799 | $4,972,661 |
| AG2-289 | $364,638 | $6,708,740 | $0 | $1,935 | $357,462 | $7,432,774 |
| AG2-290 | $364,638 | $6,866,508 | $0 | $1,115 | $357,462 | $7,589,723 |
| AG2-297 | $614,438 | $2,824,533 | $0 | $0 | $0 | $3,438,971 |
| AG2-298 | $1,792,000 | $15,269,000 | $127,897 | $0 | $0 | $17,188,897 |
| AG2-300 | $606,945 | $3,565,166 | $0 | $0 | $514,990 | $4,687,101 |
| AG2-329 | $1,659,783 | $28,131,860 | $0 | $0 | $1,117,553 | $30,909,196 |
| AG2-332 | $493,084 | $4,373,520 | $0 | $36,245 | $978,970 | $5,881,819 |
| AG2-339 | $0 | $244,105 | $0 | $0 | $0 | $244,105 |
| AG2-341 | $4,714,199 | $3,795,171 | $659,366 | $0 | $483,290 | $9,652,026 |
| AG2-343 | $0 | $5,884,582 | $0 | $12,376 | $1,117,553 | $7,014,511 |
| AG2-345 | $0 | $157,768 | $0 | $6,188 | $603,891 | $767,847 |
| AG2-356 | $0 | $0 | $1,867,387 | $0 | $0 | $1,867,387 |
| AG2-360 | $2,206,040 | $10,686,376 | $1,155,293 | $0 | $750,157 | $14,797,866 |
| AG2-363 | $2,137,668 | $2,799,908 | $44,985,861 | $9,612,365 | $391,562 | $59,927,364 |
| AG2-364 | $2,137,668 | $2,799,908 | $29,990,798 | $6,408,237 | $391,562 | $41,728,173 |
| AG2-369 | $2,188,690 | $27,510,929 | $0 | $123,000 | $552,827 | $30,375,446 |
| AG2-370 | $0 | $3,166,854 | $0 | $0 | $603,891 | $3,770,745 |
| AG2-380 | $1,665,709 | $3,758,741 | $29,760,796 | $0 | $0 | $35,185,246 |
| AG2-382 | $2,171,760 | $13,849,668 | $0 | $0 | $249,786 | $16,271,214 |
| AG2-384 | $15,552,161 | $5,856,927 | $0 | $0 | $499,571 | $21,908,659 |
| AG2-401 | $0 | $0 | $0 | $0 | $0 | $0 |
| AG2-405 | $0 | $0 | $0 | $0 | $0 | $0 |
| AG2-406 | $0 | $0 | $0 | $0 | $0 | $0 |
| AG2-411 | $979,668 | $7,094,086 | $0 | $0 | $562,940 | $8,636,694 |
| AG2-420 | $381,016 | $102,790 | $1,337,050 | $0 | $36,547 | $1,857,403 |
| AG2-423 | $1,307,871 | $17,151,080 | $0 | $0 | $517,228 | $18,976,179 |
| AG2-424 | $1,989,000 | $9,264,000 | $4,805,372 | $0 | $0 | $16,058,372 |
| AG2-426 | $1,988,831 | $21,922,953 | $39,296,000 | $0 | $483,290 | $63,691,074 |
| AG2-429 | $1,487,522 | $19,010,009 | $63,547,134 | $0 | $521,431 | $84,566,096 |
| AG2-436 | $2,119,491 | $48,116,762 | $0 | $0 | $552,827 | $50,789,080 |
| AG2-440 | $418,486 | $10,184,099 | $35,039,080 | $0 | $225,794 | $45,867,458 |
| AG2-441 | $418,486 | $10,184,099 | $52,792,808 | $0 | $225,794 | $63,621,186 |
| AG2-442 | $1,010,704 | $22,835,450 | $65,077,754 | $0 | $483,290 | $89,407,198 |
| AG2-447 | $0 | $0 | $15,000,000 | $0 | $0 | $15,000,000 |
| AG2-448 | $1,587,454 | $23,074,066 | $0 | $0 | $517,528 | $25,179,048 |
| AG2-453 | $1,413,009 | $62,925,234 | $47,296,117 | $6,539,647 | $791,246 | $118,965,253 |
| AG2-479 | $0 | $0 | $0 | $0 | $0 | $0 |
| AG2-481 | $0 | $0 | $0 | $0 | $0 | $0 |
| AG2-484 | $0 | $0 | $0 | $0 | $0 | $0 |
| AG2-487 | $0 | $0 | $0 | $0 | $0 | $0 |
| AG2-491 | $0 | $343,288 | $0 | $42,250,869 | $301,946 | $42,896,103 |
| AG2-492 | $0 | $278,282 | $0 | $21,125,434 | $301,946 | $21,705,662 |
| AG2-516 | $461,923 | $45,037,965 | $38,954,679 | $28,036 | $444,103 | $84,926,706 |
| AG2-518 | $986,167 | $10,229,132 | $209,360 | $0 | $750,157 | $12,174,816 |
| AG2-519 | $1,657,813 | $29,158,608 | $0 | $0 | $1,354,047 | $32,170,468 |
| AG2-522 | $1,385,875 | $20,733,318 | $2,811,904 | $0 | $483,290 | $25,414,387 |
| AG2-524 | $459,203 | $37,041,344 | $17,347,544 | $1,601,218 | $442,781 | $56,892,090 |
| AG2-544 | $364,020 | $2,860,014 | $0 | $51,274 | $194,801 | $3,470,109 |
| AG2-545 | $364,020 | $2,860,014 | $0 | $102,548 | $194,801 | $3,521,383 |
| AG2-548 | $493,084 | $13,761,280 | $150,000 | $0 | $1,052,102 | $15,456,465 |
| AG2-550 | $0 | $1,225,275 | $8,380,050 | $0 | $603,891 | $10,209,216 |
| AG2-551 | $0 | $157,768 | $1,830,845 | $0 | $301,946 | $2,290,559 |
| AG2-561 | $0 | $0 | $0 | $0 | $0 | $0 |
| AG2-562 | $0 | $1,273,714 | $0 | $18,979 | $603,891 | $1,896,584 |
| AG2-566 | $849,070 | $11,907,554 | $1,219,644 | $0 | $249,786 | $14,226,054 |
| AG2-568 | $1,657,813 | $17,887,865 | $50,000 | $0 | $750,157 | $20,345,835 |
| AG2-570 | $1,624,061 | $25,335,280 | $0 | $572,000 | $276,414 | $27,807,755 |
| AG2-571 | $1,624,061 | $25,335,280 | $0 | $143,000 | $276,414 | $27,378,755 |
| AG2-581 | $2,174,919 | $56,662,561 | $569,791 | $0 | $552,827 | $59,960,098 |
| AG2-582 | $411,978 | $6,576,357 | $68,488,079 | $0 | $983,319 | $76,459,733 |
| AG2-583 | $1,063,044 | $23,029,797 | $50,309 | $0 | $499,571 | $24,642,721 |
| AG2-585 | $0 | $427,232 | $0 | $17,087 | $0 | $444,319 |
| AG2-616 | $299,960 | $11,191,475 | $0 | $0 | $0 | $11,491,435 |
| AG2-617 | $19,074,419 | $3,493,495 | $0 | $0 | $0 | $22,567,914 |
| AG2-618 | $134,199 | $5,458,484 | $0 | $0 | $0 | $5,592,683 |
| AG2-621 | $4,881,868 | $251,320 | $0 | $0 | $527,027 | $5,660,215 |
| AG2-625 | $1,094,378 | $1,073,738 | $0 | $0 | $27,740 | $2,195,856 |
| AG2-626 | $872,925 | $1,063,612 | $0 | $0 | $27,396 | $1,963,933 |
| AG2-637 | $986,167 | $20,628,547 | $10,119,105 | $0 | $750,157 | $32,483,976 |
| AG2-657 | $266,642 | $23,230,322 | $0 | $0 | $750,157 | $24,247,121 |
| AG2-659 | $884,776 | $27,520,596 | $3,221,109 | $0 | $456,444 | $32,082,925 |
| AG2-660 | $0 | $80,558 | $8,862,544 | $749,445 | $0 | $9,692,547 |
| AG2-661 | $0 | $0 | $0 | $0 | $0 | $0 |
| AG2-665 | $493,084 | $1,877,566 | $150,000 | $0 | $301,946 | $2,822,596 |
| AG2-675 | $0 | $2,056,645 | $0 | $1,015,660 | $0 | $3,072,305 |
| AH1-004 | $845,000 | $6,285,500 | $0 | $8,526,472 | $0 | $15,656,972 |
| AH1-033 | $181,200 | $3,503,266 | $0 | $0 | $0 | $3,684,466 |
| AH1-040 | $1,249,118 | $20,234,189 | $15,000,000 | $0 | $449,566 | $36,932,873 |
| AH1-044 | $0 | $80,558 | $62,336,917 | $6,492,518 | $0 | $68,909,992 |
| AH1-054 | $813,778 | $1,293,367 | $0 | $0 | $27,396 | $2,134,541 |
| AH1-055 | $2,831,484 | $32,060,082 | $13,985,198 | $0 | $1,117,553 | $49,994,317 |
| AH1-057 | $0 | $0 | $0 | $0 | $0 | $0 |
| AH1-059 | $0 | $4,013,594 | $0 | $0 | $603,891 | $4,617,485 |
| AH1-060 | $28,656 | $733,106 | $0 | $0 | $2,636 | $764,397 |
| AH1-071 | $0 | $0 | $0 | $0 | $0 | $0 |
| AH1-072 | $41,617 | $9,893,748 | $473,276 | $0 | $714,924 | $11,123,564 |
| AH1-073 | $41,617 | $9,958,754 | $473,276 | $0 | $603,891 | $11,077,538 |
| AH1-091 | $0 | $0 | $0 | $0 | $0 | $0 |
| AH1-098 | $1,298,353 | $17,267,117 | $0 | $0 | $1,354,047 | $19,919,517 |
| AH1-106 | $0 | $0 | $0 | $0 | $0 | $0 |
| AH1-107 | $0 | $0 | $0 | $0 | $0 | $0 |
| AH1-108 | $0 | $0 | $0 | $0 | $0 | $0 |
| AH1-133 | $126,981 | $18,227,186 | $0 | $0 | $750,157 | $19,104,324 |
| AH1-138 | $0 | $0 | $0 | $0 | $0 | $0 |
| AH1-144 | $838,534 | $11,933,074 | $14,290 | $0 | $750,157 | $13,536,055 |
| AH1-145 | $838,534 | $11,998,081 | $22,384 | $0 | $603,891 | $13,462,890 |
| AH1-150 | $0 | $80,558 | $62,336,917 | $6,492,518 | $0 | $68,909,992 |
| AH1-151 | $0 | $80,558 | $62,336,917 | $6,492,518 | $0 | $68,909,992 |
| AH1-153 | $829,892 | $3,448,070 | $0 | $0 | $1,162,668 | $5,440,629 |
| AH1-165 | $4,880,185 | $0 | $0 | $21,732 | $439,942 | $5,341,859 |
| AH1-170 | $0 | $16,446,668 | $0 | $0 | $0 | $16,446,668 |
| AH1-188 | $7,511,988 | $54,828,386 | $23,581,109 | $0 | $750,157 | $86,671,640 |
| AH1-196 | $0 | $252,795 | $74,856,293 | $99,847 | $0 | $75,208,935 |
| AH1-206 | $4,216,345 | $0 | $0 | $0 | $581,390 | $4,797,735 |
| AH1-216 | $1,140,974 | $26,593,928 | $0 | $0 | $499,571 | $28,234,473 |
| AH1-221 | $0 | $0 | $0 | $0 | $0 | $0 |
| AH1-223 | $0 | $0 | $0 | $0 | $0 | $0 |
| AH1-227 | $919,746 | $17,033,943 | $1,244,199 | $0 | $714,924 | $19,912,812 |
| AH1-239 | $1,905,000 | $8,774,000 | $21,639,258 | $14,440 | $0 | $32,332,698 |
| AH1-247 | $556,374 | $5,364,098 | $0 | $0 | $181,200 | $6,101,672 |
| AH1-248 | $556,374 | $5,364,098 | $0 | $0 | $181,200 | $6,101,672 |
| AH1-249 | $556,374 | $5,364,098 | $0 | $0 | $181,200 | $6,101,672 |
| AH1-251 | $1,223,282 | $21,318,662 | $0 | $0 | $483,290 | $23,025,234 |
| AH1-254 | $325,658 | $125,636 | $0 | $0 | $10,543 | $461,837 |
| AH1-257 | $857,994 | $1,155,750 | $24,750,189 | $0 | $27,396 | $26,791,329 |
| AH1-258 | $838,916 | $1,575,834 | $0 | $0 | $27,822 | $2,442,572 |
| AH1-260 | $485,734 | $24,319,043 | $0 | $0 | $0 | $24,804,777 |
| AH1-261 | $7,422,660 | $6,243,968 | $22,000,000 | $0 | $0 | $35,666,628 |
| AH1-263 | $4,333,155 | $18,009,366 | $0 | $0 | $483,290 | $22,825,811 |
| AH1-269 | $2,668,885 | $6,077,763 | $48,966 | $0 | $750,157 | $9,545,771 |
| AH1-271 | $2,171,760 | $13,849,668 | $0 | $0 | $249,786 | $16,271,214 |
| AH1-272 | $1,659,783 | $58,228,306 | $0 | $4,929,534 | $1,117,553 | $65,935,176 |
| AH1-280 | $0 | $0 | $4,444,396 | $0 | $0 | $4,444,396 |
| AH1-282 | $3,148,578 | $37,379,473 | $0 | $0 | $1,117,553 | $41,645,604 |
| AH1-283 | $3,002,558 | $35,953,058 | $0 | $0 | $964,478 | $39,920,094 |
| AH1-292 | $0 | $0 | $0 | $0 | $0 | $0 |
| AH1-302 | $0 | $1,273,714 | $0 | $29,086,695 | $603,891 | $30,964,300 |
| AH1-304 | $0 | $0 | $0 | $0 | $0 | $0 |
| AH1-305 | $0 | $0 | $0 | $0 | $0 | $0 |
| AH1-306 | $0 | $0 | $0 | $0 | $0 | $0 |
| AH1-311 | $0 | $0 | $0 | $0 | $0 | $0 |
| AH1-314 | $2,092,968 | $17,679,077 | $38,520 | $0 | $1,183,174 | $20,993,739 |
| AH1-327 | $0 | $0 | $0 | $0 | $0 | $0 |
| AH1-328 | $0 | $0 | $0 | $0 | $0 | $0 |
| AH1-334 | $878,041 | $1,033,374 | $0 | $0 | $32,051 | $1,943,466 |
| AH1-338 | $462,801 | $37,131,021 | $49,499,380 | $854,705 | $444,617 | $88,392,524 |
| AH1-341 | $461,623 | $35,675,719 | $54,393,063 | $94,403 | $443,478 | $91,068,286 |
| AH1-343 | $941,707 | $23,632,514 | $2,799,027 | $0 | $458,076 | $27,831,324 |
| AH1-345 | $0 | $0 | $0 | $0 | $0 | $0 |
| AH1-348 | $0 | $232,616 | $0 | $0 | $490,626 | $723,242 |
| AH1-387 | $3,129,272 | $37,756,968 | $0 | $0 | $987,463 | $41,873,703 |
| AH1-392 | $0 | $18,165,448 | $0 | $51,375 | $750,157 | $18,966,980 |
| AH1-396 | $0 | $0 | $1,167,335 | $0 | $0 | $1,167,335 |
| AH1-397 | $0 | $0 | $0 | $0 | $0 | $0 |
| AH1-399 | $0 | $0 | $0 | $0 | $0 | $0 |
| AH1-439 | $1,638,010 | $24,906,162 | $3,923,208 | $0 | $499,571 | $30,966,951 |
| AH1-452 | $0 | $0 | $0 | $0 | $0 | $0 |
| AH1-460 | $1,931,406 | $19,993,174 | $54,621,186 | $0 | $475,724 | $77,021,490 |
| AH1-461 | $1,049,656 | $19,612,854 | $0 | $0 | $750,157 | $21,412,667 |
| AH1-482 | $0 | $1,273,714 | $0 | $25,504,169 | $603,891 | $27,381,774 |
| AH1-528 | $2,184,196 | $51,368,471 | $1,142,613 | $0 | $552,827 | $55,248,107 |
| AH1-535 | $1,659,783 | $34,969,452 | $0 | $0 | $3,352,657 | $39,981,892 |
| AH1-537 | $0 | $34,873,818 | $9,702,716 | $0 | $1,117,553 | $45,694,087 |
| AH1-541 | $1,910,456 | $10,222,353 | $171,753 | $12,719 | $784,094 | $13,101,375 |
| AH1-542 | $1,496,938 | $14,553,811 | $0 | $0 | $508,527 | $16,559,276 |
| AH1-543 | $1,200,551 | $60,706,743 | $19,414,549 | $583,425 | $789,176 | $82,694,444 |
| AH1-545 | $2,555,819 | $31,707,604 | $0 | $0 | $843,373 | $35,106,796 |
| AH1-546 | $1,140,057 | $25,739,124 | $313,997 | $0 | $499,571 | $27,692,749 |
| AH1-552 | $134,199 | $4,728,462 | $10,000,000 | $0 | $0 | $14,862,661 |
| AH1-563 | $0 | $1,420,651 | $14,807,780 | $39,781 | $0 | $16,268,213 |
| AH1-564 | $0 | $600,425 | $62,091,817 | $35,614 | $0 | $62,727,856 |
| AH1-567 | $0 | $1,854,892 | $0 | $1,623 | $0 | $1,856,515 |
| AH1-570 | $905,500 | $5,462,500 | $0 | $0 | $0 | $6,368,000 |
| AH1-571 | $905,500 | $5,462,500 | $0 | $0 | $0 | $6,368,000 |
| AH1-580 | $609,937 | $4,747,634 | $0 | $0 | $978,970 | $6,336,540 |
| AH1-617 | $571,120 | $21,676,162 | $12,389,525 | $0 | $677,024 | $35,313,831 |
| AH1-637 | $0 | $0 | $0 | $0 | $0 | $0 |
| AH1-641 | $299,960 | $14,014,010 | $0 | $0 | $0 | $14,313,970 |
| AH1-661 | $0 | $1,230,440 | $0 | $0 | $490,626 | $1,721,066 |
| AH1-664 | $844,000 | $7,202,000 | $9,546,550 | $6,710,375 | $0 | $24,302,925 |
| AH1-665 | $844,000 | $7,202,000 | $7,637,236 | $5,368,300 | $0 | $21,051,536 |
| AH1-666 | $1,686,000 | $15,428,000 | $3,174,061 | $0 | $0 | $20,288,061 |
| AH1-667 | $404,958 | $103,456 | $494,900 | $0 | $36,547 | $1,039,861 |
| AH1-672 | $1,609,381 | $4,032,192 | $2,539,204 | $0 | $0 | $8,180,777 |
| AH1-673 | $468,238 | $38,744,562 | $0 | $31,667 | $450,775 | $39,695,242 |
| AH1-677 | $0 | $0 | $0 | $0 | $0 | $0 |
| AH1-678 | $0 | $0 | $0 | $0 | $0 | $0 |
| AH1-679 | $0 | $0 | $0 | $0 | $0 | $0 |
| AH1-680 | $2,128,099 | $27,517,041 | $1,000,000 | $0 | $680,115 | $31,325,255 |
| AH1-681 | $0 | $0 | $0 | $0 | $0 | $0 |
| AH1-682 | $0 | $0 | $0 | $0 | $0 | $0 |
| AH1-683 | $0 | $0 | $0 | $0 | $0 | $0 |
| AH1-684 | $0 | $0 | $0 | $0 | $0 | $0 |
| AH1-685 | $0 | $0 | $0 | $0 | $0 | $0 |
| AH1-686 | $0 | $2,606,993 | $0 | $0 | $982,407 | $3,589,400 |
| AH1-687 | $0 | $0 | $35,142 | $0 | $0 | $35,142 |
| AH1-691 | $0 | $0 | $0 | $0 | $0 | $0 |
| AH1-692 | $0 | $0 | $0 | $0 | $0 | $0 |
| AH1-693 | $0 | $0 | $0 | $0 | $0 | $0 |
| AH1-694 | $0 | $0 | $0 | $0 | $0 | $0 |
| AH1-695 | $406,499 | $5,478,653 | $0 | $0 | $853,848 | $6,739,000 |
| AH1-696 | $0 | $0 | $0 | $0 | $0 | $0 |
| AH1-698 | $0 | $814,361 | $0 | $38,910 | $0 | $853,271 |
| AH1-699 | $57,092 | $143,106 | $0 | $0 | $4,971 | $205,169 |
| AH1-701 | $0 | $0 | $0 | $0 | $0 | $0 |
| AH1-702 | $0 | $1,151,580 | $0 | $20,671 | $0 | $1,172,251 |
| AH1-703 | $0 | $0 | $0 | $0 | $0 | $0 |
| AH1-704 | $0 | $0 | $0 | $0 | $0 | $0 |
| AH1-706 | $57,061 | $190,637 | $0 | $0 | $5,447 | $253,145 |
| AH1-710 | $0 | $0 | $0 | $0 | $87,000 | $87,000 |
| AH1-711 | $57,092 | $47,702 | $48,873,856 | $23,198 | $5,271 | $49,007,119 |
| AH1-712 | $5,843,758 | $14,940,509 | $0 | $0 | $276,414 | $21,060,680 |
| AH1-713 | $0 | $0 | $0 | $0 | $0 | $0 |
| AH1-714 | $0 | $635,829 | $32,486,493 | $4,229,730 | $0 | $37,352,052 |
| AH1-715 | $0 | $0 | $16,576,485 | $0 | $0 | $16,576,485 |
| AH1-716 | $2,083,467 | $50,320,099 | $0 | $0 | $552,827 | $52,956,393 |
| AH1-718 | $0 | $944,946 | $0 | $2,403 | $0 | $947,349 |
| AH1-719 | $0 | $1,193,041 | $0 | $0 | $1,117,553 | $2,310,594 |
| AH1-721 | $1,600,832 | $29,826,730 | $61,055,708 | $985,560 | $0 | $93,468,831 |
| AH1-722 | $0 | $0 | $21,826,515 | $0 | $315,000 | $22,141,515 |
| AH1-723 | $5,843,758 | $14,940,509 | $0 | $0 | $276,414 | $21,060,680 |
| AH1-725 | $35,054,607 | $8,741,862 | $0 | $0 | $0 | $43,796,469 |
| AH1-727 | $2,212,720 | $56,786,817 | $0 | $0 | $552,827 | $59,552,364 |
| AH1-734 | $738,133 | $100,289 | $0 | $0 | $5,855 | $844,277 |
| AH1-744 | $0 | $0 | $0 | $0 | $0 | $0 |
| AH1-746 | $0 | $0 | $9,380,414 | $0 | $0 | $9,380,414 |
System Reinforcements
As part of the Transition Cycle 2 Phase II System Impact Study, PJM evaluated the impact of topology changing reinforcements to mitigate the impacts driven by New Service Requests. As part of the Phase II study, PJM evaluates whether any reinforcements are eliminated as a result of modeling the topology changing reinforcements. If so, PJM would group the topology changing and eliminated reinforcements by region and compute a discount factor to apply to reinforcements to reduce the cost of all these reinforcements down to the cost of constructing only the topology changing reinforcements. If no eliminated reinforcements are identified, no regional discount factor would be applied.
| Region | Topology Upgrades | Eliminated Upgrades | Discount Factor |
|---|---|---|---|
| Dominion | $145,162,000 | $0 | No Discount |
| Mid-Atlantic Area Council | $0 | $0 | No Discount |
| PJM West | $36,430,000 | $0 | No Discount |
Steady State Thermal & Voltage Reinforcements
PJM performed generator deliverability load flow analysis for the New Service Requests in Transition Cycle 2 Phase II System Impact Study. Load flow analysis was performed to simulate Summer Peak, Light Load, and Winter Peak conditions. The table below shows all the system reinforcements identified from generator deliverability load flow analysis.
| TO | RTEP ID / TO ID | Title | Time Estimate | Total Cost Estimate ($) | Projects with Cost Allocation | Contingent Projects |
|---|---|---|---|---|---|---|
| AEP | b2968 |
Upgrade existing 345kV terminal equipment at Tanners Creek station on Tanners Creek - Miami Fort 345kV line, Actual In-Service Date 12/22/2020 |
Dec 22 2020 |
|
AG2-072, AG2-660, AH1-044, AH1-150, AH1-151 |
|
| AEP | b3788.1 / B3788.1 |
Replace limiting station elements at Kyger Creek |
Apr 03 2028 |
|
AG2-072, AH1-055, AH1-537, AH1-664, AH1-665, AH1-721 |
|
| AEP | b3851.1 / B3851.1 |
Rebuild Allen-RP Mone 345kV |
Jun 01 2027 |
|
AG2-029, AG2-230, AG2-332, AG2-363, AG2-364, AG2-453, AG2-660, AH1-044, AH1-150, AH1-151, AH1-153 |
|
| AEP | b3851.2 |
Rebuild R.P. Mone – Maddox Creek 345kV line (9.4 miles). |
Jun 01 2027 |
|
AG2-029, AG2-072, AG2-332, AG2-363, AG2-364, AG2-453, AG2-660, AH1-044, AH1-150, AH1-151 |
|
| AEP | b3877.1 |
Replace station conductor and switches in the 345 kV yard at Beatty |
Feb 01 2028 |
|
AH1-664, AH1-665 |
|
| AEP | b3877.2 |
Upgrade 345 kV circuit breakers 'A' and 'A1' to 4000A 63 kA breakers at Adkins station |
Aug 01 2029 |
|
AH1-664, AH1-665 |
|
| AEP | b3878.1 |
Upgrade 765 kV circuit breakers 'B' and 'B2' to 5000A 50kA breakers at Marysville Station |
Nov 12 2027 |
|
AG2-029, AG2-072, AG2-230, AG2-248, AG2-332, AG2-363, AG2-364, AG2-453, AG2-660, AH1-044, AH1-150, AH1-151, AH1-153 |
|
| AEP | b3919.1 |
Reconfigure Maliszewski 765 kV station and establish 345 kV breaker yard |
Jun 01 2029 |
|
AG2-029, AG2-072, AG2-073, AG2-081, AG2-104, AG2-106, AG2-107, AG2-163, AG2-184, AG2-230, AG2-245, AG2-298, AG2-329, AG2-332, AG2-343, AG2-345, AG2-363, AG2-364, AG2-424, AG2-453, AG2-660, AH1-004, AH1-044, AH1-055, AH1-150, AH1-151, AH1-153, AH1-272, AH1-482, AH1-537, AH1-570, AH1-571, AH1-617, AH1-664, AH1-665, AH1-666, AH1-711, AH1-721 |
|
| AEP | b3919.5 / (Pending) |
Reconductor 4.75-miles of the existing Bokes Creek-Marysville 345 kV circuit. |
Jun 01 2029 |
|
AG2-106, AG2-107, AH1-711 |
|
| AEP | b3971.1 |
Reconductor Haviland 138 kV bus |
Jun 01 2030 |
|
AG2-370, AG2-660, AH1-044, AH1-150, AH1-151 |
|
| AEP | b3972.1 |
Sag Study and Clearance Mitigation: East Lima-Haviland |
Apr 15 2030 |
|
AG2-370 |
|
| AEP | b4000.1 |
Add two 765 kV breakers at Amos Substation to expand the breaker and a half scheme to accommodate the new Amos-Welton Spring 765 kV line (Projected ISD 6/1/2029) |
Jun 01 2029 |
|
AG2-062, AG2-072, AG2-104, AG2-106, AG2-107, AG2-184, AG2-360, AG2-363, AG2-364, AG2-411, AG2-423, AG2-448, AG2-518, AG2-582, AG2-657, AG2-660, AH1-044, AH1-144, AH1-145, AH1-150, AH1-151, AH1-269, AH1-272, AH1-460, AH1-617, AH1-711, AH1-721 |
|
| AEP | b4000.202 |
Rebuild 12.5 miles of Smith Mountain - Redeye 138 kV line |
Jun 01 2029 |
|
AG2-152 |
|
| AEP | b4000.203 |
Rebuild 17.5 miles of Redeye - Candler's Mountain 138 kV line |
Jun 01 2029 |
|
AG2-152 |
|
| AEP | b4000.204 |
Rebuild 4 miles of Candler's Mountain - Opossum Creek 138 kV line |
Jun 01 2029 |
|
AG2-152 |
|
| AEP | b4000.207 |
Leesville Station Upgrade 138 kV |
Jun 01 2029 |
|
AG2-152 |
|
| AEP | b4000.210 |
Rebuild 7 miles of Otter - Johnson Mountain 138 kV line. |
Jun 01 2029 |
|
AG2-077, AG2-152, AH1-343 |
|
| AEP | b4000.211 |
Rebuild 6.5 miles of Johnson Mountain - New London 138 kV line |
Jun 01 2029 |
|
AG2-152, AH1-343 |
|
| AEP | b4000.251 |
Replace the wave trap and upgrade the relay at Cloverdale 765kV substation |
Jun 01 2029 |
|
AG2-029, AG2-072, AG2-088, AG2-104, AG2-106, AG2-107, AG2-126, AG2-163, AG2-184, AG2-230, AG2-245, AG2-248, AG2-329, AG2-332, AG2-343, AG2-345, AG2-360, AG2-363, AG2-364, AG2-453, AG2-518, AG2-544, AG2-545, AG2-548, AG2-637, AG2-660, AG2-665, AH1-044, AH1-055, AH1-144, AH1-145, AH1-150, AH1-151, AH1-153, AH1-188, AH1-263, AH1-272, AH1-338, AH1-461, AH1-535, AH1-537, AH1-543, AH1-563, AH1-617, AH1-664, AH1-665, AH1-711, AH1-712, AH1-714, AH1-716, AH1-721, AH1-723 |
|
| AEP | b4000.252 |
Replace the wave trap and upgrade the relay at Joshua Falls 765kV substation |
Jun 01 2029 |
|
AG2-029, AG2-072, AG2-088, AG2-104, AG2-106, AG2-107, AG2-126, AG2-163, AG2-184, AG2-230, AG2-245, AG2-248, AG2-329, AG2-332, AG2-343, AG2-345, AG2-360, AG2-363, AG2-364, AG2-453, AG2-518, AG2-544, AG2-545, AG2-548, AG2-637, AG2-660, AG2-665, AH1-044, AH1-055, AH1-144, AH1-145, AH1-150, AH1-151, AH1-153, AH1-188, AH1-263, AH1-272, AH1-338, AH1-461, AH1-535, AH1-537, AH1-543, AH1-563, AH1-617, AH1-664, AH1-665, AH1-711, AH1-712, AH1-714, AH1-716, AH1-721, AH1-723 |
|
| AEP | b4000.355 |
Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 69.3 miles in AEP section). |
Jun 01 2029 |
|
AG2-068, AG2-069, AG2-072, AG2-077, AG2-081, AG2-088, AG2-151, AG2-152, AG2-171, AG2-184, AG2-198, AG2-213, AG2-270, AG2-339, AG2-341, AG2-360, AG2-369, AG2-384, AG2-436, AG2-440, AG2-441, AG2-442, AG2-522, AG2-566, AG2-570, AG2-571, AG2-581, AG2-583, AG2-659, AG2-660, AH1-004, AH1-040, AH1-044, AH1-150, AH1-151, AH1-216, AH1-263, AH1-314, AH1-343, AH1-439, AH1-528, AH1-546, AH1-617, AH1-664, AH1-665, AH1-666, AH1-677, AH1-681, AH1-682, AH1-683, AH1-687, AH1-691, AH1-692, AH1-694, AH1-712, AH1-716, AH1-721, AH1-723 |
|
| AEP | b4068.1 / AEP-TC2-18693 |
b4068: Greentown 765 kV - Teddy 765kV - Marysville 765 kV - Greenfield Line - AEP Proposal 570 |
Jun 01 2030 |
|
AG2-029, AG2-072, AG2-073, AG2-081, AG2-104, AG2-106, AG2-107, AG2-163, AG2-184, AG2-230, AG2-245, AG2-298, AG2-329, AG2-332, AG2-343, AG2-345, AG2-363, AG2-364, AG2-424, AG2-453, AG2-660, AH1-004, AH1-044, AH1-055, AH1-150, AH1-151, AH1-153, AH1-272, AH1-482, AH1-537, AH1-570, AH1-571, AH1-617, AH1-664, AH1-665, AH1-666, AH1-711, AH1-721 |
|
| AEP | n5613 / AEPA0014a |
Rebuild 0.9 miles of the Otter - Alta Vista 138 kV line. |
Nov 21 2027 |
|
AG2-077, AG2-152, AH1-343 |
|
| AEP | n7925.1 / AEPI0010a |
Reconductor ~0.41 miles of the Sullivan – West Casey (Ameren) line |
11 Months |
|
AG2-363, AG2-453 |
|
| AEP | n9182.0 / AEPIMJMS01 |
Rebuild Olive - AF2-359 345kV |
30 to 36 Months |
$35,000,000
|
AG2-363, AG2-364, AG2-453, AG2-524, AG2-660, AH1-044, AH1-150, AH1-151, AH1-196, AH1-338, AH1-341, AH1-543, AH1-714 |
|
| AEP | n9746.0 / AEP-TC2-18625 |
05HODGIN_BP 138.0 kV to 05HAYES 138.0 kV ckt 1 - Replace Conductor |
30 to 36 Months |
$100,000
|
AG2-550, AG2-551, AG2-637 |
|
| AEP | n9747.0 / AEP-TC2-18633 |
AG2-637 TP 138.0 kV to 05HODGIN_BP 138.0 kV ckt 1 - Replace conductor |
12 to 18 Months |
$100,000
|
AG2-550, AG2-551, AG2-637 |
|
| AEP | n9748.0 / AEP-TC2-18670 |
17STILLWELL 345.0 kV to 05DUMONT 345.0 kV ckt 1 - Reconductor and Replace Equipment |
36 to 48 Months |
$26,060,000
|
AG2-363, AG2-364, AG2-453, AG2-660, AH1-044, AH1-150, AH1-151, AH1-338, AH1-543, AH1-714 |
|
| AEP | n9749.0 / AEP-TC2-18677 |
05DUMONT_RW 765.0 kV to 05DUMONT 765.0 kV ckt Z1 - Replace Breaker |
36 to 42 Months |
$4,000,000
|
AG2-363, AG2-364, AG2-453, AG2-660, AH1-044, AH1-150, AH1-151, AH1-714 |
|
| AEP | n9750.0 / AEP-TC2-18699 |
AG2-548 TP 138.0 kV to 05CORWIN 138.0 kV ckt 1 - Replace Equipment |
6 to 12 Months |
$300,000
|
AG2-548, AG2-665 |
|
| AEP | n9753.0 / AEP-TC2-18751 |
05KYGER 345kV to 05SPORN 345kV ckt 1 - Replace Equipment and Sag Study |
48 to 60 Months |
$5,052,000
|
AG2-072, AH1-055, AH1-537, AH1-664, AH1-665, AH1-721 |
|
| AEP | n9761.0 / AEP-TC2-19056 |
05CLNCHR 138.0 kV to 05ABINGD 138.0 kV ckt 1 - Sag Study |
12 to 24 Months |
$180,000
|
AG2-184, AH1-227, AH1-617 |
AH1-072, AH1-073 |
| AEP | n9762.0 / AEP-TC2-19058 |
05HARBER 138.0 kV to 05SOFTSH 138.0 kV ckt 1 - Replace sub conductor |
24 to 36 Months |
$100,000
|
AG2-184, AH1-617 |
|
| AEP | n9763.0 / AEP-TC2-19060 |
05J.FERR 765.0 kV to 05CLOVRD_RJA 765.0 kV ckt 1 - Replace Wavetraps |
48 to 54 Months |
$3,300,000
|
AG2-072, AG2-184, AG2-360, AG2-363, AG2-364, AH1-617, AH1-721 |
|
| AEP | n9764.0 / AEP-TC2-19061 |
05ELKGARDNSS 138.0 kV to 05SALTV1 138.0 kV ckt 1 - Reconductor entrance span |
24 to 36 Months |
$4,000,000
|
AG2-184, AH1-072, AH1-073, AH1-227, AH1-617, AH1-721 |
AH1-535 |
| AEP | n9765.0 / AEP-TC2-19065 |
05CLNCHR 138.0 kV to 05LEBANO 138.0 kV ckt 1 - Rebuild Entrance Span |
36 to 48 Months |
$4,000,000
|
AG2-184, AH1-072, AH1-073, AH1-227, AH1-617, AH1-721 |
AH1-535 |
| AEP | n9766.0 / AEP-TC2_19067 |
05MARYSV 765.0 kV to 05MARYSVL_RM 765.0 kV ckt Z1 - Replace Wavetrap |
36 to 48 Months |
$1,100,000
|
AG2-072, AG2-104, AG2-106, AG2-107, AG2-363, AG2-364, AG2-660, AH1-044, AH1-150, AH1-151 |
|
| AEP | n9767.0 / AEP-TC2-19068 |
05KAMMER_RG 765.0 kV to 05KAMMER 765.0 kV ckt Z1 - Replace Wavetraps |
48 to 54 Months |
$4,500,000
|
AG2-072, AG2-104, AG2-106, AG2-107, AG2-363, AG2-364, AG2-660, AH1-044, AH1-150, AH1-151 |
|
| AEP | n9768.0 / AEP-TC2-19069 |
05MISSIS 138.0 kV to 05DEER CRK1 138.0 kV ckt 1 - Upgrade Risers |
24 to 30 Months |
$300,000
|
AG2-191, AG2-192 |
|
| AEP | n9769.0 / AEP-TC2-19070 |
05CLOVRD_RJA 765.0 kV to 05CLOVRD 765.0 kV ckt Z1 - Upgrade/replace CBs |
48 to 54 Months |
$25,000,000
|
AG2-072, AG2-184, AH1-617, AH1-721 |
|
| AEP | n9770.0 / AEP-TC2-19071 |
05ATKINS 138.0 kV to 05RURALR 138.0 kV ckt 1 - Sag Study |
12 to 24 Months |
$500,000
|
AG2-360 |
AH1-133 |
| AEP | n9771.0 / AEP-TC2-19073 |
05LEBANO 138.0 kV to 05ELKGARDNSS 138.0 kV ckt 1 - Rebuild/Reconductor Entrance Span |
24 to 36 Months |
$4,000,000
|
AG2-184, AH1-072, AH1-073, AH1-227, AH1-617, AH1-721 |
AH1-535 |
| AEP | n9772.0 / AEP-TC2-19074 |
05CLYTR1 138.0 kV to 05SCHRIS 138.0 kV ckt 1 - Replace Structures |
24 to 36 Months |
$270,000
|
AG2-518, AH1-144, AH1-145, AH1-269 |
|
| AEP | n9783.0 / AEP-TC2-19115 |
05BROADX 138.0 kV to 05SMYTH 138.0 - Replace station conductor |
24 to 30 Months |
$100,000
|
AG2-360 |
AH1-133 |
| AEP | n9785.0 / AEP-TC2-19160 |
Olive - 17P9700-East: Rebuild Line |
60 to 72 Months |
$215,300,000
|
AG2-363, AG2-364, AG2-453, AG2-524, AG2-660, AH1-044, AH1-150, AH1-151, AH1-196, AH1-338, AH1-341, AH1-543, AH1-714 |
|
| AEP | n9786.0 / AEP-TC2-19161 |
05MARYSVL_RM 765.0 kV to 05MALIS 765.0 kV ckt 1 - Replace Wave Traps |
24 to 36 Months |
$3,000,000
|
AG2-072, AG2-104, AG2-106, AG2-107, AG2-363, AG2-364, AG2-660, AH1-044, AH1-150, AH1-151 |
|
| AEP | s2063.4 / AEPO0001a |
Upgrade/Replace 3-345kV 1600A switches at Beatty station |
Nov 15 2022 |
|
AH1-664, AH1-665 |
|
| AEP | s2572.3 |
Rebuild ~21 miles of the 138KV line between Saltville and Tazewell stations |
Sep 02 2036 |
|
AG2-360, AH1-133, AH1-721 |
|
| AEP | s2793.5 / s2793 |
Rebuild the T-line from West Van Wert to Roller Creek |
Jul 18 2025 |
|
AG2-406 |
|
| AEP | s2887.1 / s2887 |
Construct a new brownfield, breaker and a half Glen Lyn station next to the existing station |
TBD |
|
AH1-144, AH1-145 |
|
| AEP | s2887.4 |
Extend the Glen Lyn – Morgans Cut and Glen Lyn – Hazel Hollow lines |
Apr 03 2029 |
|
AH1-144, AH1-145 |
|
| AEP | s3442.26 |
Dumont 765 kV: Replace 3000 A circuit breaker at Dumont |
Dec 01 2026 |
|
AG2-363, AG2-364, AG2-453, AG2-660, AH1-044, AH1-150, AH1-151 |
|
| AEP | s3588.1 / (Pending) |
Construct new Larrison Drive 345 kV substation |
Dec 15 2026 |
|
AG2-163, AG2-245, AG2-363, AG2-364, AG2-453, AG2-660, AH1-044, AH1-150, AH1-151, AH1-482 |
|
| AEP | s3588.2 / (Pending) |
Construct new New Prairie 345 kV substation |
Dec 15 2026 |
|
AG2-163, AG2-245, AG2-363, AG2-364, AG2-453, AG2-660, AH1-044, AH1-150, AH1-151, AH1-482 |
|
| APS | (Pending) / APS-2024-010 (Supplemental) |
Misoperation Relays: Armstrong - Kittanning 138 kV Line (Supplemental - Projected ISD 9/10/2029) |
TBD |
|
AG2-176, AG2-429 |
|
| APS | b3800.104 |
Rebuild ~15 miles of the Stonewall-Millville 138 kV line with 500 kV overbuild |
Jun 01 2030 |
|
AG2-288 |
|
| APS | b4000.10 |
Install four 250 MVAR cap banks (two on 765 and two on 500 kV side) and a +/-500 MVAR STATCOM on the 765 kV Rocky Point yard |
Jun 01 2029 |
|
AG2-062, AG2-072, AG2-104, AG2-106, AG2-107, AG2-184, AG2-360, AG2-363, AG2-364, AG2-411, AG2-423, AG2-448, AG2-518, AG2-582, AG2-657, AG2-660, AH1-044, AH1-144, AH1-145, AH1-150, AH1-151, AH1-269, AH1-272, AH1-460, AH1-617, AH1-711, AH1-721 |
|
| APS | b4000.11 |
Expand Black Oak Substation & Loop in the 502 Jct-Woodside 500 kV line (Projected ISD 6/1/2029) |
Jun 01 2029 |
|
AG2-062, AG2-072, AG2-104, AG2-106, AG2-107, AG2-184, AG2-360, AG2-363, AG2-364, AG2-411, AG2-423, AG2-448, AG2-518, AG2-582, AG2-657, AG2-660, AH1-044, AH1-144, AH1-145, AH1-150, AH1-151, AH1-269, AH1-272, AH1-460, AH1-617, AH1-711, AH1-721 |
|
| APS | b4000.2 |
Construct a new 175 miles Amos to Welton Spring 765 kV line - AEP Section of the line is 30 miles (Projected ISD 6/1/2029) |
Jun 01 2029 |
|
AG2-062, AG2-072, AG2-104, AG2-106, AG2-107, AG2-184, AG2-360, AG2-363, AG2-364, AG2-411, AG2-423, AG2-448, AG2-518, AG2-582, AG2-657, AG2-660, AH1-044, AH1-144, AH1-145, AH1-150, AH1-151, AH1-269, AH1-272, AH1-460, AH1-617, AH1-711, AH1-721 |
|
| APS | b4000.3 |
Construct a new 175 miles Amos to Welton Spring 765 kV line - APS/FE Section of the line is 145 miles (Projected ISD 6/1/2029) |
Jun 01 2029 |
|
AG2-062, AG2-072, AG2-104, AG2-106, AG2-107, AG2-184, AG2-360, AG2-363, AG2-364, AG2-411, AG2-423, AG2-448, AG2-518, AG2-582, AG2-657, AG2-660, AH1-044, AH1-144, AH1-145, AH1-150, AH1-151, AH1-269, AH1-272, AH1-460, AH1-617, AH1-711, AH1-721 |
|
| APS | b4000.4 |
Construct a new 765 kV switchyard - Welton Spring (Projected ISD 6/1/2029) |
Jun 01 2029 |
|
AG2-062, AG2-072, AG2-104, AG2-106, AG2-107, AG2-184, AG2-360, AG2-363, AG2-364, AG2-411, AG2-423, AG2-448, AG2-518, AG2-582, AG2-657, AG2-660, AH1-044, AH1-144, AH1-145, AH1-150, AH1-151, AH1-269, AH1-272, AH1-460, AH1-617, AH1-711, AH1-721 |
|
| APS | b4000.5 |
Install four 250 MVAR shunt capacitors, and a +/-500 MVAR STATCOM at Welton Spring 765 kV substation |
Jun 01 2029 |
|
AG2-062, AG2-072, AG2-104, AG2-106, AG2-107, AG2-184, AG2-360, AG2-363, AG2-364, AG2-411, AG2-423, AG2-448, AG2-518, AG2-582, AG2-657, AG2-660, AH1-044, AH1-144, AH1-145, AH1-150, AH1-151, AH1-269, AH1-272, AH1-460, AH1-617, AH1-711, AH1-721 |
|
| APS | b4000.6 |
Construct a new 86 miles Welton Spring to Rocky Point 765 kV line (Welton Spring to DVP local area, roughly 21 miles) (VA Portion) |
Jun 01 2029 |
|
AG2-062, AG2-072, AG2-104, AG2-106, AG2-107, AG2-184, AG2-360, AG2-363, AG2-364, AG2-411, AG2-423, AG2-448, AG2-518, AG2-582, AG2-657, AG2-660, AH1-044, AH1-144, AH1-145, AH1-150, AH1-151, AH1-269, AH1-272, AH1-460, AH1-617, AH1-711, AH1-721 |
|
| APS | b4000.7 |
Construct a new 86 miles Welton Spring to Rocky Point 765 kV line - in DVP local area/Millville to Lovettsville section, roughly 10.5 miles (Projected ISD 6/1/2029) |
Jun 01 2029 |
|
AG2-062, AG2-072, AG2-104, AG2-106, AG2-107, AG2-184, AG2-360, AG2-363, AG2-364, AG2-411, AG2-423, AG2-448, AG2-518, AG2-582, AG2-657, AG2-660, AH1-044, AH1-144, AH1-145, AH1-150, AH1-151, AH1-269, AH1-272, AH1-460, AH1-617, AH1-711, AH1-721 |
|
| APS | b4000.8 |
Construct a new 86 miles Welton Spring to Rocky Point 765 kV line (DVP local area to Rocky Point, roughly 4.8 miles) |
Jun 01 2029 |
|
AG2-062, AG2-072, AG2-104, AG2-106, AG2-107, AG2-184, AG2-360, AG2-363, AG2-364, AG2-411, AG2-423, AG2-448, AG2-518, AG2-582, AG2-657, AG2-660, AH1-044, AH1-144, AH1-145, AH1-150, AH1-151, AH1-269, AH1-272, AH1-460, AH1-617, AH1-711, AH1-721 |
|
| APS | b4000.9 |
Construct a new substation called Rocky Point with a 765 kV and a 500 kV yard (Projected ISD 6/1/2029) |
Jun 01 2029 |
|
AG2-062, AG2-072, AG2-104, AG2-106, AG2-107, AG2-184, AG2-360, AG2-363, AG2-364, AG2-411, AG2-423, AG2-448, AG2-518, AG2-582, AG2-657, AG2-660, AH1-044, AH1-144, AH1-145, AH1-150, AH1-151, AH1-269, AH1-272, AH1-460, AH1-617, AH1-711, AH1-721 |
|
| APS | b4002.1 |
Garrett-Garrett Tap 115 kV Line Upgrade: Rebuild approximately 1.9 miles of 115 kV line with larger conductor |
Jun 01 2029 |
|
AG2-411, AH1-460 |
|
| APS | b4002.2 |
Adjust the relay settings at Penn Mar, Garrett, and Deep Creek 115kV substations |
Jun 01 2029 |
|
AG2-411, AH1-460 |
|
| APS | b4052.5 |
Rocky Point 500 kV remote work for Dickerson (new 500 kV)-Rocky Point line |
Jun 01 2032 |
|
AG2-068, AG2-069, AG2-369, AG2-436, AG2-570, AG2-571, AH1-528, AH1-681, AH1-712, AH1-723 |
|
| APS | n6183 |
Rebuild 10.4 miles of 4/0 CU from Columbia Big Pine - Garretts Run Jct 138 kV (99 spans). Also upgrade terminal end equipment. |
26 Months |
$36,946,687
|
AG2-176, AG2-429 |
AG2-420 |
| APS | n7165.1 |
Replace T-line drops at All Dam 6 |
12 Months |
$427,516
|
AG2-176, AG2-429 |
AG2-420 |
| APS | n7165.2 |
Reconductor All Dam 6 - Kittanning 138kV line. Also upgrade terminal end equipment. |
22 Months |
$21,034,523
|
AG2-176, AG2-429 |
AG2-420 |
| APS | n7166.1 |
Replace 4/0 CU line exit at All Dam 6 Tap. |
18 Months |
$922,908
|
AG2-176, AG2-429 |
AG2-420 |
| APS | n7166.2 |
Reconductor 7.6 miles of 4/0 CU from All Dam 6 Tap to structure 84 (66 spans). Also upgrade terminal end equipment. |
23 Months |
$26,284,067
|
AG2-176, AG2-429 |
AG2-420 |
| APS | n7171.1 |
Rebuild approximately 4.0 miles of 4/0 CU on the Kiski Valley to Columbia Big Pine 138kV line. Also upgrade terminal end equipment. |
20 Months |
$15,258,720
|
AG2-176, AG2-429 |
AG2-420 |
| APS | n9717.0 / TC1-PH1-076 |
Reconductor Butler - Karns City 138 kV line. Also upgrade terminal end equipment. |
30 Months |
$51,840,579
|
AG2-176, AG2-429 |
AG2-420 |
| APS | n9733.0 / TC2-APS-015.a |
Replace 500/138 kV TR2 with (3) Single Phase 500/138 kV TRs at Flint Run. |
80 Months |
$32,119,007
|
AG2-582 |
|
| APS | n9734.0 / TC2-APS-036.a |
Upgrade/Replace (6) 138kV Substation Conductors [(2) ACSR 954 45/7 & (4) AAC 1000 37] |
15 Months |
$1,084,903
|
AG2-176 |
|
| APS | n9735.0 / TC2-APS-016.a |
Replace 500/138 kV TR1 with (3) Single Phase 500/138 kV TRs at Flint Run. |
80 Months |
$32,119,007
|
AG2-582 |
|
| APS | n9736.0 / TC2-APS-015.b |
Replace 6 138 kV Disc Switches and 5 Breaker Leads at Flint Run |
24 Months |
$1,826,164
|
AG2-582 |
|
| APS | n9737.0 / TC2-APS-016.b |
Replace 6 138 kV Disc Switches and 5 Breaker Leads at Flint Run |
24 Months |
$1,826,164
|
AG2-582 |
|
| APS | n9738.0 / TC2-APS-016.c |
Replace SCCIR 3" Pipe A-frame closest to Disc SW A-39 |
18 Months |
$597,737
|
AG2-582 |
|
| APS | s3191.1 / APS-2023-056 |
Harrison – Pruntytown 500 kV Misoperation Relays (Projected ISD by end of 2025) |
Dec 31 2024 |
|
AG2-582 |
|
| ATSI | (Pending) / ATSI-2025-004 (Supplemental) |
Lemoyne Sub Upgrades & New Greenfield-Ottawa 138kV Line (Projected ISD 6/1/2032) - s3844.1 |
TBD |
|
AH1-711 |
|
| ATSI | (Pending) / ATSI-2025-005 (Supplemental) |
Lallendorf & Allen Jct Substation Upgrades (Projected ISD 6/1/2032) - s3845.1 |
TBD |
|
AH1-272 |
|
| ATSI | b3925.2 |
Rebuild the 13.45 miles of Greenfield - Lakeview 138 kV Line from 2 x 336.4 kcmil 26/7 ACSR to 1 x 795 kcmil 26/7 ACSS |
Jun 01 2029 |
|
AG2-289, AG2-290, AG2-660, AH1-044, AH1-150, AH1-151, AH1-711 |
|
| ATSI | b3925.4 |
Rebuild the Greenfield - Beaver 138 kV corridor (32 miles) with 795 kcmil 26/7 ACSS |
Jun 01 2029 |
|
AH1-711 |
|
| ATSI | n9227.0 / TC1-ATSI-001.b |
Beaver-Lake Ave Ckt #2 345kV: Upgrade T-line drops, overhead substation conductor and TL reconductor |
37 Months |
$48,873,856
|
AH1-711 |
|
| BGE | b3780.13 |
Batavia Road to Riverside 230 kV reconductor |
Dec 31 2027 |
|
AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725 |
|
| BGE | b3780.4 |
Peach Bottom to Graceton (BGE Portion) – New 500kV Line |
Dec 31 2028 |
|
AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725 |
|
| BGE | b3780.5 |
Build Solley Road substation + Statcom (Projected ISD 12/31/2028) |
Dec 31 2028 |
|
AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725 |
|
| BGE | b3780.6 |
Build Granite substation + Statcom (Projected ISD 12/31/2028) |
Dec 31 2028 |
|
AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725 |
|
| BGE | b3780.7 |
Build new Batavia Road substation (Projected ISD 12/31/2028) |
Dec 31 2028 |
|
AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725 |
|
| BGE | b3780.8 |
Graceton 500 kV substation expansion (Projected ISD 12/31/2028) |
Dec 31 2028 |
|
AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725 |
|
| BGE | b3780.9 |
Graceton to Batavia Road 230 kV double circuit pole line (Projected ISD 12/31/2028) |
Dec 31 2028 |
|
AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725 |
|
| BGE | b3800.26 |
Build High Ridge 500 kV substation - Three bay breaker and half configuration (Projected ISD 12/31/2030) |
Dec 31 2030 |
|
AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725 |
|
| BGE | b3800.27 |
High Ridge 500 kV substation (cut into Brighton-Waugh Chapel 500 kV line) - Waugh Chapel side (Projected ISD 12/31/2030) |
Dec 31 2030 |
|
AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725 |
|
| BGE | b3800.28 |
High Ridge 500 kV substation (cut into Brighton-Waugh Chapel 500 kV line) -Brighton side (Projected ISD 12/31/2030) |
Dec 31 2030 |
|
AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725 |
|
| BGE | b3800.29 |
High Ridge termination for the North Delta-High Ridge 500 kV line (Projected ISD 12/31/2030) |
Dec 31 2030 |
|
AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725 |
|
| BGE | b3800.30 |
High Ridge - Install two 500/230 kV transformers (Projected ISD 12/31/2030) |
Dec 31 2030 |
|
AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725 |
|
| BGE | b3800.32 |
Build new North Delta-High Ridge 500 kV line - BGE Portion (Projected ISD 12/31/2030) |
Dec 31 2030 |
|
AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725 |
|
| BGE | b3800.33 |
Replace terminal equipment limitations at Brighton 500 kV - on the existing Brighton-Waugh Chapel 500 kV (5053) or new Brighton-High Ridge 500 kV. |
Dec 31 2030 |
|
AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725 |
|
| BGE | b3800.34 |
Rebuild 5012 (existing Peach Bottom-Conastone) (new Graceton-Conastone) 500 kV and cut into North Delta 500kV (Projected ISD 12/31/2030) |
Dec 31 2030 |
|
AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725 |
|
| BGE | b3800.36 |
Rebuild 5012 (existing Peach Bottom-Conastone) (new North Delta-Graceton BGE) 500 kV (Projected ISD 12/31/2030) |
Dec 31 2030 |
|
AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725 |
|
| BGE | b3800.37 |
Replace terminal equipment limitations at Conastone 500 kV - on the (existing Peach Bottom-Conastone) or (new Graceton-Conastone) 500 kV line (Projected ISD 12/31/2030) |
Dec 31 2030 |
|
AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725 |
|
| BGE | n9773.0 / |
New Upgrade for BRANDN.S 230.0 kV to SOLLEY_42 230.0 kV ckt 42 & 43 |
60 Months |
$22,000,000
|
AH1-261 |
|
| ComEd | b3811.1 / CE_PJM B3811_L11323 |
Expand Haumesser Road 138 kV substation as a 4 circuit breaker ring bus. |
Dec 01 2028 |
|
AH1-338, AH1-341 |
|
| ComEd | b3811.2 / CE_PJM B3811_L11323 |
Additional Circuit Breaker at ESS H452 |
Dec 01 2028 |
|
AH1-338, AH1-341 |
|
| ComEd | b3811.3 / CE_PJM B3811_L11323 |
Rebuild 3 miles of 138 kV line 11323 from Haumesser Road to the H-452 tap |
Dec 01 2028 |
|
AH1-338, AH1-341 |
|
| ComEd | b3915.1 |
Reconductor 345 kV lines 1202 and 1227 from Dresden to Mulberry |
Jun 01 2029 |
|
AG2-363, AG2-364, AH1-543 |
|
| ComEd | b3915.2 |
Equipment upgrades at Dresden 345 kV Substation |
Jun 01 2029 |
|
AG2-363, AG2-364, AH1-543 |
|
| ComEd | b3915.3 |
Equipment upgrades at Mulberry 345 kV Substation |
Jun 01 2029 |
|
AG2-363, AG2-364, AH1-543 |
|
| ComEd | b4006.1 |
Install 765/345 kV TR 91 and associated 765 kV and 345 kV circuit breakers at Wilton Center. |
Dec 01 2030 |
|
AG2-363, AG2-364, AG2-453, AG2-660, AH1-044, AH1-150, AH1-151, AH1-543, AH1-714 |
|
| ComEd | n3515.1 / ce-017 |
Cherry Valley - Garden Prarie 345 kV: Line rebuild, station bus work, & Cherry Valley 345kV breaker replacement |
50 Months |
$84,712,245
|
AG2-516, AG2-660, AH1-044, AH1-150, AH1-151, AH1-341, AH1-564 |
|
| ComEd | n5318.1 / ce-012a |
Garden Prarie - Silver Lake R 345 kV: Line rebuild, station bus work & Silver Lake 345kV Breaker Replacement |
60 Months |
$163,968,683
|
AG2-516, AG2-660, AH1-044, AH1-150, AH1-151, AH1-196, AH1-341, AH1-564 |
|
| ComEd | n5792 / CE_NUN_L11323 |
Rebuild Haumesser - West Dekalb 138 kV line (L11323) |
30 Months |
$10,479,841
|
AH1-338, AH1-341 |
|
| ComEd | n6260.1 / CE_NUN_8012 |
Upgrade of TSS 80 Pontiac 345kV circuit breaker BT 4-5 and 345kV station and bus conductor |
60 Months |
|
AG2-114, AH1-541 |
|
| ComEd | n6260.2 / N6260.2 |
Replace a line disconnect switch to upgrade the Pontiac - Loretto 345 kV line. |
24 Months |
$500,000
|
AG2-114, AH1-541 |
|
| ComEd | n6280 / ce-005 |
Mitigate the sag on the ComEd Powerton - Tazewell L0304 345 kV line. |
Nov 01 2026 |
|
AG2-363, AG2-364 |
|
| ComEd | n6611 / ce-007 |
The upgrades will be to reconductor the line, station conductor upgrades. |
30 Months |
|
AH1-044, AH1-150, AH1-151, AH1-338, AH1-341 |
|
| ComEd | n6639.2 / CE_NUN_L15502_4 |
Reconductor the Electric Junction 345 kV line 93407, perform sag mitigation on 345 kV line 93407, upgrade one 345 kV circuit breaker and associated motor operated disconnect switches. |
Sep 30 2029 |
|
AG2-660, AH1-044, AH1-150, AH1-151, AH1-341 |
|
| ComEd | n6779 / CE_NUN_L14609 |
Plano 138 KV re-conductor a portion of the line |
30 Months |
$5,600,000
|
AH1-338, AH1-341 |
|
| ComEd | n7023.1 / CE_NUN_L11124.1 |
Reconductor the Electric Junction - Lombard line L11124 345 kV Line and perform associated station relay and protection upgrades. |
36 Months |
$38,797,273
|
AG2-660, AH1-044, AH1-150, AH1-151, AH1-338, AH1-563 |
|
| ComEd | n9165.0 / CE_NUN_L15502.1 |
Perform TSS 155 Nelson Substation conductor upgrades. |
36 Months |
$1,220,445
|
AG2-660 |
|
| ComEd | n9166.0 / CE_NUN_L16914.1 |
Reconductor the McGirr Road to ESS H447 RT 138 KV line |
24 Months |
$605,422
|
AH1-341 |
AG2-660, AH1-044, AH1-150, AH1-151 |
| ComEd | n9172.0 / CE_NUN_L18623.2 |
Haumesser - Steward 138 kV Line Reconductor |
18 to 24 Months |
$8,500,000
|
AG2-660, AH1-044, AH1-150, AH1-151, AH1-338, AH1-341 |
|
| ComEd | n9195.0 / CE_NUN_STA12_345 NEW CB |
Install a new 345 kV circuit breaker at Station 12 Dresden. |
Dec 15 2030 |
|
AG2-114, AH1-541 |
|
| ComEd | n9269.0 / CE_NUN_L11212.5 |
Reconductor the L11212 345 kV line. |
Dec 15 2030 |
|
AG2-114, AH1-541 |
|
| ComEd | n9678.0 / CE_NUN_L11215_1 |
Mitigate the sag on L11215 |
30 Months |
$9,000,000
|
AG2-363, AG2-364, AG2-453, AG2-660, AH1-044, AH1-150, AH1-151, AH1-338, AH1-714 |
|
| ComEd | n9718.0 / CE_NUN_COLLINS_NEW CB |
New Collins New 765KV Circuit Breaker |
24 to 30 Months |
$15,500,000
|
AG2-363, AG2-364, AG2-453, AG2-660, AH1-044, AH1-150, AH1-151, AH1-714 |
|
| ComEd | n9719.0 / CE_NUN_COLLINS_TR |
Collins Station 23 New Transformer-reduces contingency events. |
24 to 30 Months |
$15,600,000
|
AG2-363, AG2-364, AG2-453, AG2-660, AH1-044, AH1-150, AH1-151, AH1-543, AH1-714 |
|
| ComEd | n9720.0 / CE_NUN_L1205-1 |
TC2 Network Upgrade- L1205 |
24 to 30 Months |
$2,800,000
|
AG2-524 |
|
| ComEd | n9721.0 / CE_NUN_L95201_1 |
194 Sabrooke Station Conductor |
12 to 16 Months |
$500,000
|
AH1-564 |
|
| ComEd | n9722.0 / CE_NUN_TSS155_TR83 |
TSS155 Nelson New Transformer |
24 to 30 Months |
$15,200,000
|
AG2-660, AH1-044, AH1-150, AH1-151 |
|
| ComEd | n9754.0 / CE_NUN_TSS 111 |
TSS 167 Plano new circuit breaker |
12 to 18 Months |
$5,000,000
|
AG2-660, AH1-044, AH1-150, AH1-151 |
|
| ComEd | n9755.0 / CE_NUN_L17705_1 |
Reconductor Sheffield - Burnham and upgrade station conductor at Burnham |
24 to 30 Months |
$14,000,000
|
AG2-363, AG2-364, AG2-453, AG2-660, AH1-044, AH1-150, AH1-151, AH1-714 |
|
| ComEd | n9784.0 / CE_L11103_2 |
L11103 Station conductor and line work |
24 to 30 Months |
$6,500,000
|
AH1-563 |
|
| ComEd | s3011 / CE_S3011 |
Replace 345kV straight bus at TSS 116 Goodings Grove with a gas insulated switchgear ("GIS") breaker and a half configuration. |
Dec 31 2029 |
|
AG2-363, AG2-364, AG2-660, AH1-044, AH1-150, AH1-151, AH1-341 |
|
| DEOK | b2831.2 |
Rebuild the Tanner Creek – Miami Fort 345kV line (DEOK portion), Actual In-service date 5/14/2021 |
May 14 2021 |
|
AG2-072, AG2-660, AH1-044, AH1-150, AH1-151 |
|
| DEOK | b3944.1 / (Pending) |
Rebuild the McGuffey to Locust 69 kV line (~1.35 miles) with 954 ACSR rail conductor and OPGW. |
May 25 2029 |
|
AG2-550, AG2-551, AG2-637 |
|
| DEOK | b4003.1 / (Pending) |
Rebuild the College Corner (AEP)-Collinsville (DEOK) 138 kV circuit. (DEOK Portion) |
Jun 01 2030 |
|
AG2-550, AG2-551, AG2-637 |
|
| DEOK | s2019 / AEP Project Resolves Overload |
AEP Project s2019 Resolves DEOK Overload |
May 26 2021 |
|
AG2-072, AG2-660, AH1-044, AH1-150, AH1-151 |
|
| DPL | (Pending) / PE-2025-008 (Supplemental) |
DPL 230 kV Supplemental Upgrades |
60 Months |
|
AH1-672, AH1-710 |
|
| DPL | b4004.1 |
Upgrade terminal equipment at Claymont substation |
May 31 2030 |
|
AH1-710 |
|
| DPL | n7042 / dt6704r0001 |
Rebuild Kent to N. Meredith Tap. |
36 to 48 Months |
$28,800,000
|
AG2-380 |
|
| DPL | n9774.0 / |
Rebuild BRIDGEVL 69.0 kV to TAYLOR 69.0 kV ckt 1 to achieve 70 MVA minimum |
36 to 60 Months |
$15,000,000
|
AG2-447 |
|
| Dayton | b3904.1 |
Rebuild and reconductor 7.7 miles of 69kV line. |
Jun 01 2029 |
|
AG2-406 |
|
| Dominion | b3692 |
Rebuild approximately 27.7-miles of 500 kV transmission line from Elmont to Chickahominy. |
TBD |
|
AG2-436, AG2-570, AG2-571, AH1-528, AH1-716 |
|
| Dominion | b3694.1 |
Convert line #29 Aquia Harbor to Possum Point to 230 kV (Extended line #2104) and swap line #2104 and converted line #29 at Aquia Harbor backbone termination. |
Sep 28 2029 |
|
AG2-436, AH1-682, AH1-683, AH1-691, AH1-692, AH1-694 |
|
| Dominion | b3694.4 |
Reconductor/rebuild approx 7.6 miles of 230 kV line #2104 Cranes Corner-Stafford. Reconductor/rebuild approx 0.34 miles of 230 kV line #2104 Stafford-Aquia Harbor. Upgrade terminal equipment. |
TBD |
|
AG2-436, AH1-682, AH1-683, AH1-691, AH1-692, AH1-694 |
|
| Dominion | b3800.300 |
Wreck/Rebuild 230kV Line #2135 segment Hollymeade Junction – Cash’s Corner using double-circuit capable 230 kV poles. (The second 230kV circuit will be wired but not have terminal ends.) |
Jun 30 2028 |
|
AH1-681, AH1-712, AH1-723 |
|
| Dominion | b3800.302 |
Upgrade Cash's Corner switches 213576 and 213579 and line leads to 4000A continuous current rating of 230kV Line #2135. |
Jun 30 2028 |
|
AH1-681, AH1-712, AH1-723 |
|
| Dominion | b4000.315 |
Reconductor 230kV Line #2003 Tyler – Poe segment. New conductor has a summer rating of 1573 MVA. |
Apr 22 2030 |
|
AG2-068, AG2-069, AG2-077, AG2-339, AG2-369, AG2-426, AG2-436, AG2-570, AG2-571, AG2-581, AH1-528 |
|
| Dominion | b4000.316 |
At Poe substation, uprate all Line #2003 terminal equipment, line leads, and bus to be rated to 4000A. |
Apr 22 2030 |
|
AG2-068, AG2-069, AG2-077, AG2-339, AG2-369, AG2-426, AG2-436, AG2-570, AG2-571, AG2-581, AH1-528 |
|
| Dominion | b4000.317 |
At Tyler substation, upgrade the necessary line terminal equipment to maintain 4000A at Tyler substation. |
Apr 22 2030 |
|
AG2-068, AG2-069, AG2-077, AG2-339, AG2-369, AG2-426, AG2-436, AG2-570, AG2-571, AG2-581, AH1-528 |
|
| Dominion | b4000.319 |
Reconductor 230kV Line #2002 Carson – Poe. New conductor has a summer rating of 1573 MVA. |
Mar 20 2030 |
|
AG2-068, AG2-069, AG2-077, AG2-270, AG2-339, AG2-369, AG2-436, AG2-440, AG2-441, AG2-442, AG2-570, AG2-571, AG2-581, AH1-528, AH1-677 |
|
| Dominion | b4000.320 |
At Carson substation, upgrade all line #2002 terminal equipment at Carson to 4000A. CCVTs will also be replaced due to aging. |
Mar 20 2030 |
|
AG2-068, AG2-069, AG2-077, AG2-270, AG2-339, AG2-369, AG2-436, AG2-440, AG2-441, AG2-442, AG2-570, AG2-571, AG2-581, AH1-528, AH1-677 |
|
| Dominion | b4000.321 |
At Poe substation, upgrade all line #2002 terminal equipment at Carson to 4000A. CCVTs will also be replaced due to aging. |
Mar 20 2030 |
|
AG2-068, AG2-069, AG2-077, AG2-270, AG2-339, AG2-369, AG2-436, AG2-440, AG2-441, AG2-442, AG2-570, AG2-571, AG2-581, AH1-528, AH1-677 |
|
| Dominion | b4000.325 |
Build a new 26.38mi 230kV Line from Elmont – Ladysmith on the existing 5-2 structures between the two stations. New conductor has a summer rating of 1573 MVA. |
Feb 24 2029 |
|
AG2-436, AG2-570, AG2-571, AH1-528, AH1-681, AH1-712, AH1-723 |
|
| Dominion | b4000.326 |
At Elmont substation, install/upgrade associated equipment to accommodate a 4000A line rating for the new 230kV line between Elmont - Ladysmith. |
Feb 24 2029 |
|
AG2-436, AG2-570, AG2-571, AH1-528, AH1-681, AH1-712, AH1-723 |
|
| Dominion | b4000.327 |
Upgrade/install equipment at Ladysmith Substation to 4000A. Expansion will be required to accommodate a total of three (3) new 230 kV strings of breaker and a half scheme. |
Feb 24 2029 |
|
AG2-436, AG2-570, AG2-571, AH1-528, AH1-681, AH1-712, AH1-723 |
|
| Dominion | b4000.334 |
Reconductor 115kV line #121 from Poe - Prince George. Specifically, line #121 will be reconductored and converted to 230kV from Poe substation to Prince George substation. |
Jan 10 2030 |
|
AG2-095, AG2-384, AG2-661, AH1-216 |
|
| Dominion | b4000.335 |
At Poe substation, install a new 230kV six breaker ultimate ring bus which will fit the station to current 230kV standards. |
Jan 10 2030 |
|
AG2-095, AG2-384, AG2-661, AH1-216 |
|
| Dominion | b4000.336 |
Build a new 230-115kV Prince George substation along the existing 115 or 230kV corridor. |
Jan 10 2030 |
|
AG2-095, AG2-384, AG2-661, AH1-216 |
|
| Dominion | b4000.341 |
Remove the 500 kV conductor previously planned to terminate into the Vint Hill 500 kV Substation and extend approximately 0.2 miles of conductor to fly-over the site. |
Jul 13 2029 |
|
AG2-068, AG2-069, AG2-072, AG2-077, AG2-081, AG2-088, AG2-151, AG2-152, AG2-171, AG2-184, AG2-198, AG2-213, AG2-270, AG2-339, AG2-341, AG2-360, AG2-369, AG2-382, AG2-384, AG2-436, AG2-440, AG2-441, AG2-442, AG2-522, AG2-566, AG2-570, AG2-571, AG2-581, AG2-583, AG2-659, AG2-660, AH1-004, AH1-040, AH1-044, AH1-150, AH1-151, AH1-170, AH1-216, AH1-263, AH1-271, AH1-314, AH1-343, AH1-439, AH1-528, AH1-546, AH1-617, AH1-664, AH1-665, AH1-666, AH1-677, AH1-681, AH1-682, AH1-683, AH1-687, AH1-691, AH1-692, AH1-694, AH1-712, AH1-716, AH1-721, AH1-723 |
|
| Dominion | b4000.342 |
Remove the terminal equipment and substation work required for the termination of the Morrisville-Wishing Star 500 kV line into Vint Hill. |
Jul 13 2029 |
|
AG2-068, AG2-069, AG2-072, AG2-077, AG2-081, AG2-088, AG2-151, AG2-152, AG2-171, AG2-184, AG2-198, AG2-213, AG2-270, AG2-339, AG2-341, AG2-360, AG2-369, AG2-382, AG2-384, AG2-436, AG2-440, AG2-441, AG2-442, AG2-522, AG2-566, AG2-570, AG2-571, AG2-581, AG2-583, AG2-659, AG2-660, AH1-004, AH1-040, AH1-044, AH1-150, AH1-151, AH1-170, AH1-216, AH1-263, AH1-271, AH1-314, AH1-343, AH1-439, AH1-528, AH1-546, AH1-617, AH1-664, AH1-665, AH1-666, AH1-677, AH1-681, AH1-682, AH1-683, AH1-687, AH1-691, AH1-692, AH1-694, AH1-712, AH1-716, AH1-721, AH1-723 |
|
| Dominion | b4000.344 |
Build a 500kV line from North Anna substation (bypassing Ladysmith Substation) to a new substation called Thornburg (formerly Kraken). New conductor to have a minimum summer normal rating of 4357MVA. |
Sep 16 2030 |
|
AG2-068, AG2-069, AG2-072, AG2-077, AG2-081, AG2-088, AG2-151, AG2-152, AG2-171, AG2-184, AG2-198, AG2-213, AG2-270, AG2-339, AG2-341, AG2-360, AG2-369, AG2-382, AG2-384, AG2-436, AG2-440, AG2-441, AG2-442, AG2-522, AG2-566, AG2-570, AG2-571, AG2-581, AG2-583, AG2-659, AG2-660, AH1-004, AH1-040, AH1-044, AH1-150, AH1-151, AH1-170, AH1-216, AH1-263, AH1-271, AH1-314, AH1-343, AH1-439, AH1-528, AH1-546, AH1-617, AH1-664, AH1-665, AH1-666, AH1-677, AH1-681, AH1-682, AH1-683, AH1-687, AH1-691, AH1-692, AH1-694, AH1-712, AH1-716, AH1-721, AH1-723 |
|
| Dominion | b4000.345 |
Build a 500kV line from a new substation called Thornburg (formerly Kraken) to a new substation called Yeat. New conductor to have a minimum summer normal rating of 4357MVA. |
Sep 16 2030 |
|
AG2-068, AG2-069, AG2-072, AG2-077, AG2-081, AG2-088, AG2-151, AG2-152, AG2-171, AG2-184, AG2-198, AG2-213, AG2-270, AG2-339, AG2-341, AG2-360, AG2-369, AG2-382, AG2-384, AG2-436, AG2-440, AG2-441, AG2-442, AG2-522, AG2-566, AG2-570, AG2-571, AG2-581, AG2-583, AG2-659, AG2-660, AH1-004, AH1-040, AH1-044, AH1-150, AH1-151, AH1-170, AH1-216, AH1-263, AH1-271, AH1-314, AH1-343, AH1-439, AH1-528, AH1-546, AH1-617, AH1-664, AH1-665, AH1-666, AH1-677, AH1-681, AH1-682, AH1-683, AH1-687, AH1-691, AH1-692, AH1-694, AH1-712, AH1-716, AH1-721, AH1-723 |
|
| Dominion | b4000.346 |
Cut-in 500kV line from Thornburg (formerly Kraken) substation into Yeat substation |
Jun 01 2029 |
|
AG2-068, AG2-069, AG2-072, AG2-077, AG2-081, AG2-088, AG2-151, AG2-152, AG2-171, AG2-184, AG2-198, AG2-213, AG2-270, AG2-339, AG2-341, AG2-360, AG2-369, AG2-382, AG2-384, AG2-436, AG2-440, AG2-441, AG2-442, AG2-522, AG2-566, AG2-570, AG2-571, AG2-581, AG2-583, AG2-659, AG2-660, AH1-004, AH1-040, AH1-044, AH1-150, AH1-151, AH1-170, AH1-216, AH1-263, AH1-271, AH1-314, AH1-343, AH1-439, AH1-528, AH1-546, AH1-617, AH1-664, AH1-665, AH1-666, AH1-677, AH1-681, AH1-682, AH1-683, AH1-687, AH1-691, AH1-692, AH1-694, AH1-712, AH1-716, AH1-721, AH1-723 |
|
| Dominion | b4000.348 |
Build a new 500/230kV substation called Thornburg (formerly Kraken). The 500kV, 5000A ring bus will be set up for a redundant breaker configuration. Install (2) 1400MVA 500/230 kV transformers. |
Jun 01 2029 |
|
AG2-068, AG2-069, AG2-072, AG2-077, AG2-081, AG2-088, AG2-151, AG2-152, AG2-171, AG2-184, AG2-198, AG2-213, AG2-270, AG2-339, AG2-341, AG2-360, AG2-369, AG2-382, AG2-384, AG2-436, AG2-440, AG2-441, AG2-442, AG2-522, AG2-566, AG2-570, AG2-571, AG2-581, AG2-583, AG2-659, AG2-660, AH1-004, AH1-040, AH1-044, AH1-150, AH1-151, AH1-170, AH1-216, AH1-263, AH1-271, AH1-314, AH1-343, AH1-439, AH1-528, AH1-546, AH1-617, AH1-664, AH1-665, AH1-666, AH1-677, AH1-681, AH1-682, AH1-683, AH1-687, AH1-691, AH1-692, AH1-694, AH1-712, AH1-716, AH1-721, AH1-723 |
|
| Dominion | b4000.349 |
Update relay settings at Ladysmith to change the destination of 500kV line #568 from Possum Point to Thornburg (formerly Kraken). |
Sep 16 2030 |
|
AG2-068, AG2-069, AG2-072, AG2-077, AG2-081, AG2-088, AG2-151, AG2-152, AG2-171, AG2-184, AG2-198, AG2-213, AG2-270, AG2-339, AG2-341, AG2-360, AG2-369, AG2-382, AG2-384, AG2-436, AG2-440, AG2-441, AG2-442, AG2-522, AG2-566, AG2-570, AG2-571, AG2-581, AG2-583, AG2-659, AG2-660, AH1-004, AH1-040, AH1-044, AH1-150, AH1-151, AH1-170, AH1-216, AH1-263, AH1-271, AH1-314, AH1-343, AH1-439, AH1-528, AH1-546, AH1-617, AH1-664, AH1-665, AH1-666, AH1-677, AH1-681, AH1-682, AH1-683, AH1-687, AH1-691, AH1-692, AH1-694, AH1-712, AH1-716, AH1-721, AH1-723 |
|
| Dominion | b4000.350 |
Update relay settings at Possum Point to change the destination of 500kV line #568 from Ladysmith to Thornburg (formerly Kraken). |
Sep 16 2030 |
|
AG2-068, AG2-069, AG2-072, AG2-077, AG2-081, AG2-088, AG2-151, AG2-152, AG2-171, AG2-184, AG2-198, AG2-213, AG2-270, AG2-339, AG2-341, AG2-360, AG2-369, AG2-382, AG2-384, AG2-436, AG2-440, AG2-441, AG2-442, AG2-522, AG2-566, AG2-570, AG2-571, AG2-581, AG2-583, AG2-659, AG2-660, AH1-004, AH1-040, AH1-044, AH1-150, AH1-151, AH1-170, AH1-216, AH1-263, AH1-271, AH1-314, AH1-343, AH1-439, AH1-528, AH1-546, AH1-617, AH1-664, AH1-665, AH1-666, AH1-677, AH1-681, AH1-682, AH1-683, AH1-687, AH1-691, AH1-692, AH1-694, AH1-712, AH1-716, AH1-721, AH1-723 |
|
| Dominion | b4000.351 |
Cut in Line #568 Ladysmith - Possum Point into Thornburg (formerly Kraken), creating Line #9517 Ladysmith to Thornburg (formerly Kraken). |
Sep 16 2030 |
|
AG2-068, AG2-069, AG2-072, AG2-077, AG2-081, AG2-088, AG2-151, AG2-152, AG2-171, AG2-184, AG2-198, AG2-213, AG2-270, AG2-339, AG2-341, AG2-360, AG2-369, AG2-382, AG2-384, AG2-436, AG2-440, AG2-441, AG2-442, AG2-522, AG2-566, AG2-570, AG2-571, AG2-581, AG2-583, AG2-659, AG2-660, AH1-004, AH1-040, AH1-044, AH1-150, AH1-151, AH1-170, AH1-216, AH1-263, AH1-271, AH1-314, AH1-343, AH1-439, AH1-528, AH1-546, AH1-617, AH1-664, AH1-665, AH1-666, AH1-677, AH1-681, AH1-682, AH1-683, AH1-687, AH1-691, AH1-692, AH1-694, AH1-712, AH1-716, AH1-721, AH1-723 |
|
| Dominion | b4000.352 |
Cut in Line #568 Ladysmith - Possum Point into Thornburg (formerly Kraken), creating new Line #568 Thornburg (formerly Kraken) to Possum Point. |
Sep 16 2030 |
|
AG2-068, AG2-069, AG2-072, AG2-077, AG2-081, AG2-088, AG2-151, AG2-152, AG2-171, AG2-184, AG2-198, AG2-213, AG2-270, AG2-339, AG2-341, AG2-360, AG2-369, AG2-382, AG2-384, AG2-436, AG2-440, AG2-441, AG2-442, AG2-522, AG2-566, AG2-570, AG2-571, AG2-581, AG2-583, AG2-659, AG2-660, AH1-004, AH1-040, AH1-044, AH1-150, AH1-151, AH1-170, AH1-216, AH1-263, AH1-271, AH1-314, AH1-343, AH1-439, AH1-528, AH1-546, AH1-617, AH1-664, AH1-665, AH1-666, AH1-677, AH1-681, AH1-682, AH1-683, AH1-687, AH1-691, AH1-692, AH1-694, AH1-712, AH1-716, AH1-721, AH1-723 |
|
| Dominion | b4000.356 |
Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 86.7 miles in Dominion section). |
Jun 01 2029 |
|
AG2-068, AG2-069, AG2-072, AG2-077, AG2-081, AG2-088, AG2-151, AG2-152, AG2-171, AG2-184, AG2-198, AG2-213, AG2-270, AG2-339, AG2-341, AG2-360, AG2-369, AG2-384, AG2-436, AG2-440, AG2-441, AG2-442, AG2-522, AG2-566, AG2-570, AG2-571, AG2-581, AG2-583, AG2-659, AG2-660, AH1-004, AH1-040, AH1-044, AH1-150, AH1-151, AH1-216, AH1-263, AH1-314, AH1-343, AH1-439, AH1-528, AH1-546, AH1-617, AH1-664, AH1-665, AH1-666, AH1-677, AH1-681, AH1-682, AH1-683, AH1-687, AH1-691, AH1-692, AH1-694, AH1-712, AH1-716, AH1-721, AH1-723 |
|
| Dominion | b4000.357 |
Build a new 765/500/230 kV substation called Yeat. Install (2) 765/500 kV transformers. Cut in 500 kV line Bristers-Ox and 500 kV line Meadowbrook-Vint Hill into Yeat. |
Jun 01 2029 |
|
AG2-068, AG2-069, AG2-072, AG2-077, AG2-081, AG2-088, AG2-151, AG2-152, AG2-171, AG2-184, AG2-198, AG2-213, AG2-270, AG2-339, AG2-341, AG2-360, AG2-369, AG2-382, AG2-384, AG2-436, AG2-440, AG2-441, AG2-442, AG2-522, AG2-566, AG2-570, AG2-571, AG2-581, AG2-583, AG2-659, AG2-660, AH1-004, AH1-040, AH1-044, AH1-150, AH1-151, AH1-170, AH1-216, AH1-263, AH1-271, AH1-314, AH1-343, AH1-439, AH1-528, AH1-546, AH1-617, AH1-664, AH1-665, AH1-666, AH1-677, AH1-681, AH1-682, AH1-683, AH1-687, AH1-691, AH1-692, AH1-694, AH1-712, AH1-716, AH1-721, AH1-723 |
|
| Dominion | b4000.360 |
Replace two switches, a wave trap and leads to upgrade all related substation equipment to 2000A at Altavista 138 kV substation. |
Dec 31 2031 |
|
AG2-152 |
|
| Dominion | b4030.1 |
Chesterfield-Basin 230 kV rebuild: Wreck and rebuild approximately 12.5 miles of Chesterfield-Basin 230 kV line. |
Jun 01 2030 |
|
AG2-068, AG2-069, AG2-077, AG2-088, AG2-436, AG2-570, AG2-571, AG2-581, AH1-528 |
|
| Dominion | b4030.10 |
Fork Union-Bremo 230 kV rebuild: Wreck and Rebuild approximately 1.74 miles of Fork Union-Bremo 230 kV line. |
Jun 01 2030 |
|
AG2-068, AG2-069, AG2-077, AG2-088, AG2-151, AG2-171, AG2-198, AG2-213, AG2-270, AG2-369, AG2-436, AG2-440, AG2-441, AG2-442, AG2-566, AG2-570, AG2-571, AG2-581, AG2-583, AH1-439, AH1-528, AH1-546, AH1-687 |
|
| Dominion | b4030.11 |
Replace all terminal equipment at Charlottesville 230 kV substation to support the new line conductor ratings of the Charlottesville-Fork Union 230 kV rebuild. |
Jun 01 2030 |
|
AG2-068, AG2-069, AG2-077, AG2-088, AG2-151, AG2-171, AG2-198, AG2-213, AG2-270, AG2-369, AG2-436, AG2-440, AG2-441, AG2-442, AG2-566, AG2-570, AG2-571, AG2-581, AG2-583, AH1-439, AH1-528, AH1-546, AH1-687 |
|
| Dominion | b4030.12 |
Replace all terminal equipment at Fork Union 230 kV substation to support the new line conductor ratings of the Charlottesville-Fork Union 230 kV rebuild. |
Jun 01 2030 |
|
AG2-068, AG2-069, AG2-077, AG2-088, AG2-151, AG2-198, AG2-213, AG2-270, AG2-369, AG2-436, AG2-440, AG2-441, AG2-442, AG2-566, AG2-570, AG2-571, AG2-581, AG2-583, AH1-439, AH1-528, AH1-546, AH1-687 |
|
| Dominion | b4030.13 |
Replace all terminal equipment at Fork Union 230 kV substation to support the new conductor ratings of the Fork Union-Bremo 230 kV rebuild. |
Jun 01 2030 |
|
AG2-068, AG2-069, AG2-077, AG2-088, AG2-151, AG2-171, AG2-198, AG2-213, AG2-270, AG2-369, AG2-436, AG2-440, AG2-441, AG2-442, AG2-566, AG2-570, AG2-571, AG2-581, AG2-583, AH1-439, AH1-528, AH1-546, AH1-687 |
|
| Dominion | b4030.14 |
Replace all terminal equipment at Bremo 230 kV substation to support the new conductor ratings of the Fork Union-Bremo 230 kV rebuild. |
Jun 01 2030 |
|
AG2-068, AG2-069, AG2-077, AG2-088, AG2-151, AG2-171, AG2-198, AG2-213, AG2-270, AG2-369, AG2-436, AG2-440, AG2-441, AG2-442, AG2-566, AG2-570, AG2-571, AG2-581, AG2-583, AH1-439, AH1-528, AH1-546, AH1-687 |
|
| Dominion | b4030.15 |
Upgrade disconnect switches at Mt. Eagle tap 230 kV substation to 4000A. |
Jun 01 2030 |
|
AG2-068, AG2-069, AG2-077, AG2-088, AG2-151, AG2-171, AG2-198, AG2-213, AG2-270, AG2-369, AG2-436, AG2-440, AG2-441, AG2-442, AG2-566, AG2-570, AG2-571, AG2-581, AG2-583, AH1-439, AH1-528, AH1-546, AH1-687 |
|
| Dominion | b4030.3 |
Basin 230 kV substation scope: Replace all terminal equipment, line leads and bus at Basin 230 kV substation to be rated to 4000A. |
Jun 01 2030 |
|
AG2-068, AG2-069, AG2-077, AG2-088, AG2-436, AG2-570, AG2-571, AG2-581, AH1-528 |
|
| Dominion | b4030.4 |
Chesterfield 230 kV substation scope: Install a new 230 kV, 80 kA 4000A circuit breaker at Chesterfield 230 kV substation. |
Jun 01 2030 |
|
AG2-068, AG2-069, AG2-077, AG2-088, AG2-436, AG2-570, AG2-571, AG2-581, AH1-528 |
|
| Dominion | b4030.9 |
Charlottesville-Fork Union 230 kV rebuild: Wreck and rebuild ~24 miles of Charlottesville-Fork Union 230 kV line.New Reinforcement |
Jun 01 2030 |
|
AG2-068, AG2-069, AG2-077, AG2-088, AG2-151, AG2-171, AG2-198, AG2-213, AG2-270, AG2-369, AG2-436, AG2-440, AG2-441, AG2-442, AG2-566, AG2-570, AG2-571, AG2-581, AG2-583, AH1-439, AH1-528, AH1-546, AH1-687 |
|
| Dominion | b4052.6 |
Aspen 500 kV remote work for Dickerson (new 500 kV) - Aspen line |
Jun 01 2032 |
|
AG2-068, AG2-069, AG2-369, AG2-436, AG2-570, AG2-571, AH1-528, AH1-681, AH1-712, AH1-723 |
|
| Dominion | b4053.10 |
Construct one new 500 kV line terminal position at the proposed Thornburg (formerly Kraken) substation. |
Jun 01 2032 |
|
AG2-068, AG2-069, AG2-077, AG2-339, AG2-369, AG2-382, AG2-436, AG2-440, AG2-441, AG2-570, AG2-571, AG2-581, AH1-040, AH1-216, AH1-271, AH1-528, AH1-681, AH1-712, AH1-716, AH1-723 |
|
| Dominion | b4053.11 |
Cut and loop line No. 5008 into Mosby substation, which will result in two 500 kV lines: line No. 5008 Morrisville-Mosby and line No. 9573 Mosby-Wishing Star. |
Jun 01 2030 |
|
AG2-068, AG2-069, AG2-072, AG2-077, AG2-081, AG2-088, AG2-151, AG2-171, AG2-184, AG2-198, AG2-213, AG2-270, AG2-339, AG2-341, AG2-360, AG2-369, AG2-384, AG2-436, AG2-440, AG2-441, AG2-442, AG2-522, AG2-566, AG2-570, AG2-571, AG2-581, AG2-583, AG2-659, AG2-660, AH1-004, AH1-044, AH1-150, AH1-151, AH1-170, AH1-263, AH1-280, AH1-314, AH1-343, AH1-396, AH1-439, AH1-528, AH1-546, AH1-617, AH1-664, AH1-665, AH1-666, AH1-677, AH1-681, AH1-682, AH1-683, AH1-687, AH1-691, AH1-692, AH1-694, AH1-712, AH1-716, AH1-721, AH1-723 |
|
| Dominion | b4053.12 |
Install two 500 kV breakers and all associated terminal equipment in the available bay adjacent to existing breaker XT590 to achieve a redundant breaker arrangement. |
Jun 01 2030 |
|
AG2-068, AG2-069, AG2-072, AG2-077, AG2-081, AG2-088, AG2-151, AG2-171, AG2-184, AG2-198, AG2-213, AG2-270, AG2-339, AG2-341, AG2-360, AG2-369, AG2-384, AG2-436, AG2-440, AG2-441, AG2-442, AG2-522, AG2-566, AG2-570, AG2-571, AG2-581, AG2-583, AG2-659, AG2-660, AH1-004, AH1-044, AH1-150, AH1-151, AH1-170, AH1-263, AH1-280, AH1-314, AH1-343, AH1-396, AH1-439, AH1-528, AH1-546, AH1-617, AH1-664, AH1-665, AH1-666, AH1-677, AH1-681, AH1-682, AH1-683, AH1-687, AH1-691, AH1-692, AH1-694, AH1-712, AH1-716, AH1-721, AH1-723 |
|
| Dominion | b4053.13 |
Construct a new 765/500 kV Vontay switching station at the crossing of 500 kV line No. 553 Cunningham-Elmont and 765 kV line Joshua Falls-Yeat. |
Jun 01 2032 |
|
AG2-068, AG2-069, AG2-072, AG2-077, AG2-081, AG2-088, AG2-151, AG2-152, AG2-171, AG2-184, AG2-198, AG2-213, AG2-270, AG2-339, AG2-341, AG2-360, AG2-369, AG2-384, AG2-436, AG2-440, AG2-441, AG2-442, AG2-522, AG2-566, AG2-570, AG2-571, AG2-581, AG2-583, AG2-659, AG2-660, AH1-004, AH1-040, AH1-044, AH1-150, AH1-151, AH1-216, AH1-314, AH1-343, AH1-439, AH1-528, AH1-546, AH1-617, AH1-664, AH1-665, AH1-666, AH1-677, AH1-681, AH1-687, AH1-712, AH1-716, AH1-721, AH1-723 |
|
| Dominion | b4053.14 |
Loop 500 kV line No. 553 into the new Vontay substation, which will result in two 500 kV lines: Cunningham-Vontay and Vontay-Elmont. |
Jun 01 2032 |
|
AG2-068, AG2-069, AG2-072, AG2-077, AG2-081, AG2-088, AG2-151, AG2-152, AG2-171, AG2-184, AG2-198, AG2-213, AG2-270, AG2-339, AG2-341, AG2-360, AG2-369, AG2-384, AG2-436, AG2-440, AG2-441, AG2-442, AG2-522, AG2-566, AG2-570, AG2-571, AG2-581, AG2-583, AG2-659, AG2-660, AH1-004, AH1-040, AH1-044, AH1-150, AH1-151, AH1-216, AH1-314, AH1-343, AH1-439, AH1-528, AH1-546, AH1-617, AH1-664, AH1-665, AH1-666, AH1-677, AH1-681, AH1-687, AH1-712, AH1-716, AH1-721, AH1-723 |
|
| Dominion | b4053.15 |
Loop 500 kV line No. 576 into the new Vontay substation, which will result in two 500 kV lines: from North Anna-Vontay and Vontay-Midlothian. |
Jun 01 2032 |
|
AG2-068, AG2-069, AG2-072, AG2-077, AG2-081, AG2-088, AG2-151, AG2-152, AG2-171, AG2-184, AG2-198, AG2-213, AG2-270, AG2-339, AG2-341, AG2-360, AG2-369, AG2-384, AG2-436, AG2-440, AG2-441, AG2-442, AG2-522, AG2-566, AG2-570, AG2-571, AG2-581, AG2-583, AG2-659, AG2-660, AH1-004, AH1-040, AH1-044, AH1-150, AH1-151, AH1-216, AH1-314, AH1-343, AH1-439, AH1-528, AH1-546, AH1-617, AH1-664, AH1-665, AH1-666, AH1-677, AH1-681, AH1-687, AH1-712, AH1-716, AH1-721, AH1-723 |
|
| Dominion | b4053.16 |
Loop 765 kV Joshua Falls-Yeat into the new Vontay substation, which will result in two 765 kV lines: from Joshua Falls-Vontay and Vontay-Yeat. |
Jun 01 2032 |
|
AG2-068, AG2-069, AG2-072, AG2-077, AG2-081, AG2-088, AG2-151, AG2-152, AG2-171, AG2-184, AG2-198, AG2-213, AG2-270, AG2-339, AG2-341, AG2-360, AG2-369, AG2-384, AG2-436, AG2-440, AG2-441, AG2-442, AG2-522, AG2-566, AG2-570, AG2-571, AG2-581, AG2-583, AG2-659, AG2-660, AH1-004, AH1-040, AH1-044, AH1-150, AH1-151, AH1-216, AH1-314, AH1-343, AH1-439, AH1-528, AH1-546, AH1-617, AH1-664, AH1-665, AH1-666, AH1-677, AH1-681, AH1-687, AH1-712, AH1-716, AH1-721, AH1-723 |
|
| Dominion | b4053.21 |
Uprate 500 kV line No. 567 associated terminal equipment at Chickahominy to 5000A standards. |
Jun 01 2032 |
|
AG2-068, AG2-069, AG2-369, AG2-436, AG2-570, AG2-571, AH1-040, AH1-528, AH1-716 |
|
| Dominion | b4053.22 |
Uprate 500 kV line No. 567 associated terminal equipment at Surry to 5000A standards. |
Jun 01 2032 |
|
AG2-068, AG2-069, AG2-369, AG2-436, AG2-570, AG2-571, AH1-040, AH1-528, AH1-716 |
|
| Dominion | b4053.28 |
Replace 500 kV circuit breakers (54265 and 553T564) and all associated equipment to line No. 553 including switches and CT with 5000A equipment at Cunningham substation. |
Jun 01 2032 |
|
AG2-068, AG2-069, AG2-072, AG2-077, AG2-081, AG2-088, AG2-151, AG2-152, AG2-171, AG2-184, AG2-198, AG2-213, AG2-270, AG2-339, AG2-341, AG2-360, AG2-369, AG2-384, AG2-436, AG2-440, AG2-441, AG2-442, AG2-522, AG2-566, AG2-570, AG2-571, AG2-581, AG2-583, AG2-659, AG2-660, AH1-004, AH1-040, AH1-044, AH1-150, AH1-151, AH1-216, AH1-314, AH1-343, AH1-439, AH1-528, AH1-546, AH1-617, AH1-664, AH1-665, AH1-666, AH1-677, AH1-681, AH1-687, AH1-712, AH1-716, AH1-721, AH1-723 |
|
| Dominion | b4053.3 |
Construct a new bipolar +/- 525 kV HVDC link connecting Heritage and Mosby substations, where the link has a capability of transmitting 3,000 MW. |
Jun 01 2032 |
|
AG2-068, AG2-069, AG2-072, AG2-077, AG2-081, AG2-088, AG2-151, AG2-171, AG2-184, AG2-198, AG2-213, AG2-270, AG2-339, AG2-341, AG2-360, AG2-369, AG2-384, AG2-436, AG2-440, AG2-441, AG2-442, AG2-522, AG2-566, AG2-570, AG2-571, AG2-581, AG2-583, AG2-659, AG2-660, AH1-004, AH1-044, AH1-150, AH1-151, AH1-170, AH1-263, AH1-280, AH1-314, AH1-343, AH1-396, AH1-439, AH1-528, AH1-546, AH1-617, AH1-664, AH1-665, AH1-666, AH1-677, AH1-681, AH1-682, AH1-683, AH1-687, AH1-691, AH1-692, AH1-694, AH1-712, AH1-716, AH1-721, AH1-723 |
|
| Dominion | b4053.4 |
Design and construct a new Voltage Source Converter (VSC) HVDC station at Heritage substation to support the new HVDC link. |
Jun 01 2032 |
|
AG2-068, AG2-069, AG2-072, AG2-077, AG2-081, AG2-088, AG2-151, AG2-171, AG2-184, AG2-198, AG2-213, AG2-270, AG2-339, AG2-341, AG2-360, AG2-369, AG2-384, AG2-436, AG2-440, AG2-441, AG2-442, AG2-522, AG2-566, AG2-570, AG2-571, AG2-581, AG2-583, AG2-659, AG2-660, AH1-004, AH1-044, AH1-150, AH1-151, AH1-170, AH1-263, AH1-280, AH1-314, AH1-343, AH1-396, AH1-439, AH1-528, AH1-546, AH1-617, AH1-664, AH1-665, AH1-666, AH1-677, AH1-681, AH1-682, AH1-683, AH1-687, AH1-691, AH1-692, AH1-694, AH1-712, AH1-716, AH1-721, AH1-723 |
|
| Dominion | b4053.5 |
Design and construct a new Voltage Source Converter (VSC) HVDC station at Mosby substation to support the new HVDC link. |
Jun 01 2032 |
|
AG2-068, AG2-069, AG2-072, AG2-077, AG2-081, AG2-088, AG2-151, AG2-171, AG2-184, AG2-198, AG2-213, AG2-270, AG2-339, AG2-341, AG2-360, AG2-369, AG2-384, AG2-436, AG2-440, AG2-441, AG2-442, AG2-522, AG2-566, AG2-570, AG2-571, AG2-581, AG2-583, AG2-659, AG2-660, AH1-004, AH1-044, AH1-150, AH1-151, AH1-170, AH1-263, AH1-280, AH1-314, AH1-343, AH1-396, AH1-439, AH1-528, AH1-546, AH1-617, AH1-664, AH1-665, AH1-666, AH1-677, AH1-681, AH1-682, AH1-683, AH1-687, AH1-691, AH1-692, AH1-694, AH1-712, AH1-716, AH1-721, AH1-723 |
|
| Dominion | b4053.8 |
Build a new 500 kV line from Elmont-Thornburg (formerly Kraken) (approximately 31 miles). |
Jun 01 2032 |
|
AG2-068, AG2-069, AG2-077, AG2-339, AG2-369, AG2-382, AG2-436, AG2-440, AG2-441, AG2-570, AG2-571, AG2-581, AH1-040, AH1-216, AH1-271, AH1-528, AH1-681, AH1-712, AH1-716, AH1-723 |
|
| Dominion | b4053.9 |
Construct one new 500 kV line terminal position at the existing Elmont substation. |
Jun 01 2032 |
|
AG2-068, AG2-069, AG2-077, AG2-339, AG2-369, AG2-382, AG2-436, AG2-440, AG2-441, AG2-570, AG2-571, AG2-581, AH1-040, AH1-216, AH1-271, AH1-528, AH1-681, AH1-712, AH1-716, AH1-723 |
|
| Dominion | n7553 / dom-427 |
Replace Northern Neck 115/230 kV transformer #6 with a 224 MVA (260/271/295 MVA). |
59 to 60 Months |
|
AG2-124 |
|
| Dominion | n7615 / dom-187 |
Wreck and rebuild 5.74 miles of 115 kV Line 44 between Myrtle and AD2-085 with (1) 768.2 ACSS/TW (20/7) "MAUMEE" conductor @ 250 Deg. C. |
30 to 36 Months |
$18,336,000
|
AG2-426 |
|
| Dominion | n9153.0 / TC1-PH1-DOM-043 |
Wreck and rebuild 5.9 miles of 230 kV line 2128 between Fentress and Thrasher with (2) 768.2 ACSS/TW (20/7) "MAUMEE" conductor @ 250 degrees C and replace line lead at Fentress. |
Jul 01 2027 |
|
AH1-040 |
|
| Dominion | n9207.0 / TC1-PH2-DOM-018 |
Replace 6ELMONT 230 kV to 8ELMONT 500 kV circuit 1 with larger transformer (3-480 MVA single phase transformer). |
Dec 31 2028 |
|
AG2-339, AG2-384, AG2-436, AG2-570, AG2-581, AH1-040, AH1-216, AH1-528 |
|
| Dominion | n9217.0 / TC1-PH2-DOM-028 |
Wreck and rebuild 12.73 miles of 230 kV Line 298 from Buckingham to Farmville Substations with twin bundled (2) 768 ACSS/TW (20/7) "MAUMEE" conductor. |
45 to 46 Months |
|
AG2-069, AG2-077, AG2-171, AG2-198, AG2-213, AG2-270, AG2-339, AG2-341, AG2-436, AG2-440, AG2-441, AG2-442, AG2-522, AG2-566, AG2-570, AG2-581, AG2-659, AH1-314, AH1-343, AH1-439, AH1-528 |
|
| Dominion | n9220.0 / TC1-PH2-DOM-033 |
Wreck and rebuild 15.49 miles of 230 kV Line #298 from Buckingham to Bremo Substations with twin bundled (2) 768.2 ACSS/TW (20/7) "MAUMEE" conductor. |
42 to 48 Months |
|
AG2-069, AG2-077, AG2-171, AG2-198, AG2-213, AG2-270, AG2-339, AG2-341, AG2-436, AG2-440, AG2-441, AG2-442, AG2-522, AG2-566, AG2-570, AG2-581, AG2-659, AH1-314, AH1-343, AH1-439, AH1-528, AH1-546 |
|
| Dominion | n9221.0 / TC1-PH3-DOM-015-TC2 |
Replace 230 kV Breaker 29822 at Bremo with a higher-rated device (Buckingham - Bremo). |
38 to 39 Months |
$2,057,335
|
AG2-077, AG2-171, AG2-198, AG2-213, AG2-270, AG2-341, AG2-440, AG2-441, AG2-442, AG2-522, AG2-566, AG2-581, AG2-659, AH1-314, AH1-343, AH1-439, AH1-528, AH1-546 |
|
| Dominion | n9378.0 / TC1-PH3-DOM-010 |
Replace existing 230/500 kV Carson transformer #1 with (4)-480 MVA single phase transformers. |
Mar 29 2029 |
|
AG2-068, AG2-069, AG2-077, AG2-270, AG2-339, AG2-436, AG2-570, AG2-581, AH1-528, AH1-677 |
|
| Dominion | n9380.0 / TC1-PH3-DOM-012 |
Replace existing Ladysmith 230/500 kV transformer 1 with four (4) 480 MVA single phase transformers. |
Dec 31 2029 |
|
AH1-683, AH1-691, AH1-692 |
|
| Dominion | n9643.0 / TC1-PH3-DOM-009-TC2 |
Replace 795 AAC 37 line lead at Farmville 115 kV. |
Mar 31 2027 |
$391,643
|
AG2-440, AG2-441, AG2-442 |
|
| Dominion | n9723.0 / TC2-PH1-DOM-0009 |
Wreck and Rebuild 0.05 miles of 115 kV Line 158 between Flat Creek and Moran DP with (1) 768.2 ACSS/TW (20/7) "MAUMEE". |
30 to 36 Months |
$160,000
|
AG2-171, AG2-213, AH1-280, AH1-396 |
|
| Dominion | n9724.0 / TC2-PH1-DOM-0011 |
Replace 795 AAC Line Lead on Line 158 at Farmville 115 kV. |
12 to 18 Months |
$400,000
|
AG2-171, AG2-213, AH1-280, AH1-396 |
|
| Dominion | n9725.0 / TC2-PH1-DOM-2012 |
Wreck and rebuild 6.55 mi of 115 kV Line 15 between Pumphouse and Poe with (1) 768.2 ACSS/TW (20/7) "Maumee" conductor @ 250 Deg. C |
30 to 36 Months |
$20,960,000
|
AG2-426 |
|
| Dominion | n9726.0 / TC2-PH1-DOM-2043 |
Wreck and rebuild 0.93 miles of 230 kV Line 2241 between Hendrick and Persons with (2) 768.2 ACSS/TW (20/7) "MAUMEE" at 250 degrees C. Dominion portion of line only. |
36 to 42 Months |
$3,534,000
|
AG2-077, AG2-151, AG2-171, AG2-198, AG2-213, AG2-270, AG2-341, AG2-440, AG2-441, AG2-442, AG2-522, AG2-566, AG2-581, AG2-583, AG2-659, AH1-343, AH1-439, AH1-528, AH1-546, AH1-687 |
|
| Dominion | n9727.0 / TC2-PH1-DOM-2091 |
Replace the existing Finneywood 230/500 kV XFRM T1 with a 3-480 MVA rated device |
42 to 48 Months |
$38,000,000
|
AG2-077, AG2-171, AG2-198, AG2-213, AG2-270, AG2-440, AG2-441, AG2-442, AG2-522, AG2-566, AG2-659, AH1-343, AH1-439 |
|
| Dominion | n9728.0 / TC2-PH1-DOM-2076 |
Replace wave trap 298 WT at Bremo 230 kV |
12 to 18 Months |
$400,000
|
AG2-077, AG2-171, AG2-198, AG2-213, AG2-270, AG2-341, AG2-440, AG2-441, AG2-442, AG2-522, AG2-566, AG2-581, AG2-659, AH1-314, AH1-343, AH1-439, AH1-528, AH1-546 |
|
| Dominion | n9729.0 / TC2-PH1-DOM-2092 |
Replace the existing Finneywood 230/500 kV XFRM T2 with a 3-480 MVA rated device |
42 to 48 Months |
$38,000,000
|
AG2-077, AG2-171, AG2-198, AG2-213, AG2-270, AG2-440, AG2-441, AG2-442, AG2-522, AG2-566, AG2-659, AH1-343, AH1-439 |
|
| Dominion | n9730.0 / TC2-PH1-DOM-2077 |
Replace switches 29824 and 29825 at Bremo 230 kV |
12 to 18 Months |
$800,000
|
AG2-077, AG2-171, AG2-198, AG2-213, AG2-270, AG2-341, AG2-440, AG2-441, AG2-442, AG2-522, AG2-566, AG2-581, AG2-659, AH1-314, AH1-343, AH1-439, AH1-528, AH1-546 |
|
| Dominion | n9731.0 / TC2-PH1-DOM-0010 |
Wreck and Rebuild 5.32 miles of 115 kV Line 158 between Farmville and Moran DP with (1) 768.2 ACSS/TW (20/7) "MAUMEE". |
30 to 36 Months |
$17,152,000
|
AG2-171, AG2-213, AH1-280, AH1-396 |
|
| Dominion | n9756.0 / TC2-PH2-DOM-009 |
Replace the existing Trowbridge 115/230 kV Transformer T2 with a new 224 MVA device |
42 to 44 Months |
$7,500,000
|
AH1-040 |
|
| Dominion | n9757.0 / TC2-PH2-DOM-005 |
Build new 230 kV line from AG1-285 to AG2-440 on single circuit monopoles. Expand the AG2-440 and AG1-285 substations. Add 2 new 224 MVA 230/115 kV XFRMs at AG2-440. |
42 to 48 Months |
$145,162,000
|
AG2-171, AG2-213, AG2-341, AG2-440, AG2-441, AG2-442, AH1-280 |
AG2-077, AG2-522, AG2-659, AH1-396 |
| Dominion | n9758.0 / TC2-PH2-DOM-008 |
Replace the existing Trowbridge 115/230 kV Transformer T1 with a new 224 MVA device |
42 to 44 Months |
$7,500,000
|
AH1-040 |
|
| Dominion | s2705 |
Wreck and rebuild approximately 12 miles of double circuit 230kV Line #252 and 115kV Line #29 from Aquia Harbour Switching Station to Possum Point. Upgrade station equipment. |
Sep 25 2029 |
|
AG2-436, AH1-682, AH1-683, AH1-691, AH1-692, AH1-694 |
|
| Dominion | s3671.5 |
Rebuild Line 238 from Carson to Clubhouse for a normal summer rating of 1573 MVA |
Dec 31 2030 |
|
AG2-068, AG2-069, AG2-077, AG2-270, AG2-369, AG2-382, AG2-440, AG2-441, AG2-442, AG2-522, AG2-570, AG2-571, AG2-581, AG2-659, AH1-040, AH1-271, AH1-528 |
|
| EKPC | n6480.1 / EKPC-tc1-r0002a |
Rebuild the Plumville-Murphysville 69 kV line section using 556 MCM ACSR conductor at 212 degrees F (9.9 miles) |
22 to 34 Months |
$14,830,000
|
AH1-664, AH1-665, AH1-666 |
|
| EKPC | n6834.1 / EKPC-tc1-r0001a |
Rebuild the 4/0 ACSR Green County-Summersville 69 kV line section (4.2 miles) using 556 MCM ACSR. |
18 to 24 Months |
$5,705,000
|
AG2-298, AG2-424, AH1-721 |
|
| EKPC | n7771.1 / r0013 |
Increase the maximum operating temperature of the Laurel County-Laurel Dam 161 kV line section 795 MCM conductor to 167 degrees F (~0.2 miles) |
9 to 12 Months |
$35,000
|
AH1-239, AH1-721 |
|
| EKPC | n7771.2 / EKPC-tc1-r0014a |
Increase the maximum operating temperature of the Laurel County-Laurel Dam 161 kV line section 795 MCM conductor to 212 degrees F (~10.55 miles) |
18 to 24 Months |
$1,010,000
|
AH1-239, AH1-721 |
|
| EKPC | n7773.1 / EKPC-tc1-r0004b |
Change the 69 kV current transformer settings associated with circuit breaker S7-654 from 600A to at least 800A. |
9 to 12 Months |
$345,000
|
AH1-721 |
|
| EKPC | n7773.4 / (Pending) |
Replace the 1200A disconnects S7-653 and S7-655 at Somerset substation with 2000A equipment. |
9 to 12 Months |
|
AH1-721 |
|
| EKPC | n8368.2 / EKPC-tc1-r0012b |
Rebuild the Cooper-Elihu 161 kV line section using 1272 MCM ACSS conductor (4.2 miles) |
16 to 27 Months |
$10,335,000
|
AH1-239, AH1-721 |
AG2-424 |
| EKPC | n8368.3 / EKPC-tc1-r0012c |
Change the Zone 3 relay setting at Elihu substation associated with the line protection to at least 545 MVA LTE rating. |
9 to 12 Months |
$10,000
|
AH1-239, AH1-721 |
AG2-424 |
| EKPC | n8368.4 / EKPC-tc1-r0012d |
Upgrade the existing 795 MCM ACSR jumpers at the Cooper substation associated with the Cooper-Elihu 161 kV line using bundled 500 MCM CU or equivalent |
9 to 12 Months |
$35,000
|
AH1-239, AH1-721 |
AG2-424 |
| EKPC | n8368.5 / EKPC-r0117d |
Cooper-Elihu 161 kV Current Transformer Upgrade |
12 to 15 Months |
|
AG2-424, AH1-239, AH1-721 |
|
| EKPC | n9687.10 / EKPC-tc2-nu053 |
Cooper 161kV breaker replacements - Breaker 1044 ELIHU |
Dec 01 2029 |
$335,000
|
AH1-239, AH1-721 |
AG2-424 |
| EKPC | n9739.0 / EKPC-tc2-nu046 |
Rebuild the AG1-471 Tap (Massingale Road)-AH1-239 Tap 69 kV line (Clinton County) (4.5 miles) using 556.5 MCM ACSR conductor. |
20 to 25 Months |
$4,215,000
|
AH1-239 |
|
| EKPC | n9740.0 / EKPC-tc2-nu024 |
Plumville-Rectorville 69 kV Line Conductor Temperature Upgrade (2.9 miles) |
12 to 16 Months |
$180,000
|
AH1-664, AH1-665 |
|
| EKPC | n9741.0 / EKPC-tc2-nu007 |
Charters-Rectorville 69 kV Line Conductor Temperature Upgrade (11.5 miles) |
12 to 21 Months |
$650,000
|
AH1-664, AH1-665 |
|
| EKPC | n9742.0 / EKPC-tc2-nu034 |
Zula Junction N.O.-AG1-471 (Massingale Road) 69 kV Line Section Rebuild (0.6 miles) |
12 to 18 Months |
$960,000
|
AH1-239, AH1-721 |
|
| EKPC | n9743.0 / EKPC-tc2-nu003 |
Cooper CCGT-Alcalde 161 kV Double-Circuit Line Addition |
22 to 36 Months |
$20,130,000
|
AG2-424, AH1-239, AH1-721 |
|
| EKPC | n9744.0 / EKPC-tc2-nu035 |
Plumville-AH1-664 Tap (North Fleming County) 138 kV Line Conductor Temperature Upgrade (8.25 miles) |
12 to 18 Months |
$760,000
|
AH1-664, AH1-665 |
|
| EKPC | n9745.0 / EKPC-tc2-nu014 |
Green County-Summersville 69 kV Line Section Rebuild #2 (266.8 MCM ACSR section) |
12 to 18 Months |
$120,000
|
AG2-424 |
|
| EKPC | n9775.0 / EKPC-tc2-nu056 |
Cooper-AH1-721 Tap (East Cooper) 161 kV Circuit #2 Rebuild (0.5 miles) |
12 to 18 Months |
$1,215,000
|
AH1-721 |
|
| EKPC | n9776.0 / EKPC-tc2-nu054 |
Cooper-AH1-721 Tap (East Cooper) 161 kV Circuit #1 Rebuild (0.5 miles) |
12 to 18 Months |
$1,215,000
|
AH1-721 |
|
| EKPC | n9777.0 / EKPC-tc2-nu055 |
Cooper-AH1-721 (East Cooper) Circuit #2 161 kV Zone 3 Setting Upgrade |
9 to 12 Months |
$10,000
|
AH1-721 |
|
| EKPC | n9778.0 / EKPC-tc2-nu047 |
Increase the Zone 3 relay setting at Somerset substation associated with the Somerset-KU Ferguson South 69 kV line section to at least 205 MVA. |
6 to 9 Months |
$10,000
|
AH1-721 |
|
| EKPC | n9779.0 / EKPC-tc2-nu048 |
Charters-Rectorville 69 kV Line Conductor Temperature Upgrade #2 (11.5 miles) |
12 to 21 Months |
$715,000
|
AH1-664, AH1-665 |
|
| EKPC | n9780.0 / EKPC-tc2-nu052 |
Cooper-Elihu 161 kV Relay Upgrade |
12 to 15 Months |
$55,000
|
AH1-239, AH1-721 |
AG2-424 |
| EKPC | n9781.0 / EKPC-tc2-nu051 |
Cooper-Elihu 161 kV Bus Conductor Upgrade |
12 to 15 Months |
$990,000
|
AH1-239, AH1-721 |
AG2-424 |
| EKPC | n9782.0 / EKPC-tc2-nu050 |
West London Tap-West London 69 kV Conductor Maximum Operating Temperature Increase |
12 to 21 Months |
$135,000
|
AH1-721 |
|
| EKPC | s3165.0 / s3165 |
Construct a new 161/13.8 kV distribution substation and associated 0.25 mile 161 kV double circuit tap line. |
Jul 26 2024 |
|
AH1-721 |
|
| EKPC | s3170.0 / s3170 |
Rebuild the 4.4 mile, Snow Tap-North Albany 69 kV line using 556.5 conductor and steel pole construction. |
Aug 04 2026 |
|
AH1-239 |
|
| EKPC | s3173.0 / S3173 |
Rebuild the 16.3 mile, Duncannon Lane Tap-West Berea 69 KV line |
Oct 05 2027 |
|
AG2-073 |
|
| LS Power | b3737.37 |
Silver Run-Hope Creek 230kV Expansion (Projected ISD 6/1/2029) |
Dec 31 2028 |
|
AH1-260, AH1-710 |
|
| OVEC | b3788.2 / B3788.2 |
Replace limiting station elements at Kyger Creek |
Jun 01 2028 |
|
AG2-072, AH1-055, AH1-537, AH1-664, AH1-665, AH1-721 |
|
| OVEC | n9759.0 / OVEC-TC2-19030 |
06KYGER 345.0 kV to 05SPORN 345.0 kV ckt 1 - Replace Equipment |
48 to 60 Months |
$38,180,000
|
AG2-072, AH1-055, AH1-537, AH1-664, AH1-665, AH1-721 |
|
| PECO | b3737.47 |
Build New North Delta 500 kV substation (Four bay breaker and half configuration) |
Oct 06 2027 |
|
AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725 |
|
| PECO | b3780.1 |
Peach Bottom North upgrades – substation work (Projected ISD 12/31/2028) |
Oct 15 2028 |
|
AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725 |
|
| PECO | b3780.14 |
Reconfigure Cooper transmission feeds by establishing new Cooper-North Delta 230 kV line and rerouting existing transmissions lines by Cooper. |
Oct 23 2028 |
|
AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725 |
|
| PECO | b3780.15 |
Cut in 5012 Peach Bottom-Conastone 500 kV line into North Delta 500/230 kV sub |
Apr 10 2028 |
|
AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725 |
|
| PECO | b3780.16 |
Terminate new Cooper-North Delta 230 kV line (Transource Scope) at North Delta 230 kV |
Oct 15 2028 |
|
AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725 |
|
| PECO | b3780.17 |
Cut in 5012 Peach Bottom-Conastone 500 kV line into North Delta 500/230 kV sub (Transource) |
May 31 2028 |
|
AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725 |
|
| PECO | b3780.2 |
Peach Bottom to Graceton (PECO Portion) – New 500kV Line |
Oct 23 2028 |
|
AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725 |
|
| PECO | b3800.31 |
Build new North Delta-High Ridge 500 kV line - PECO Portion (Projected ISD 12/1/2030) |
Dec 15 2030 |
|
AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725 |
|
| PECO | b3800.35 |
Rebuild 5012 (existing Peach Bottom-Conastone) (new North Delta-Graceton PECO) 500 kV (Projected ISD 12/1/2030) |
Apr 10 2028 |
|
AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725 |
|
| PECO | b3800.42 |
Peach Bottom 500kV North bus upgrade (Projected ISD 12/1/2030) |
Dec 01 2030 |
|
AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725 |
|
| PECO | b3800.44 |
North Delta termination for the North Delta-High Ridge 500 line (PECO work). |
Dec 15 2030 |
|
AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725 |
|
| PECO | b3800.45 |
North Delta 500 kV termination for the Rock Springs 500 kV line (5034/5014 line) (PECO work). |
Jan 31 2028 |
|
AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725 |
|
| PECO | b3800.47 |
Build new Peach Bottom South-North Delta 500 kV line (Projected ISD 12/1/2030) |
Jan 14 2030 |
|
AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725 |
|
| PECO | b3800.48 |
North Delta termination for the North Delta-High Ridge 500 line (Transource work). |
Dec 15 2030 |
|
AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725 |
|
| PECO | b3800.49 |
North Delta 500 kV termination for the Calpine generator (Calpine/Transource work). |
Oct 06 2027 |
|
AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725 |
|
| PECO | b3800.50 |
North Delta 500 kV termination for the Rock Springs 500 kV line (5034/5014 line) (Transource work). |
Jan 23 2028 |
|
AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725 |
|
| PECO | b3800.51 |
North Delta 500 kV termination for the new Peach Bottom-North Delta 500 kV line (Transource work). |
May 31 2028 |
|
AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725 |
|
| PECO | b3800.52 |
Reconfigure Peach Bottom North and South 500 kV yards (Projected ISD 12/1/2030) |
Dec 01 2030 |
|
AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725 |
|
| PECO | b3907.2 |
Rebuild Richmond - Waneeta 230 kV line |
Jun 01 2029 |
|
AG2-616, AH1-260, AH1-641, AH1-710 |
|
| PECO | b3907.3 |
Reconductor 2.12 miles of North Philadelphia to Waneeta 230 kV line including terminal equipment |
Jun 01 2029 |
|
AG2-616, AH1-260, AH1-641, AH1-710 |
|
| PECO | n9787.0 / PECO_TC2_PH2_Chichester |
New bus tie at Chichester |
36 to 48 Months |
$3,500,000
|
AG2-380, AH1-672 |
|
| PENELEC | n6817.1 |
Rebuild 24.59 miles of the Lewistown-Juniata 230kV transmission line and upgrade terminal ends |
81 Months |
$122,656,404
|
AG2-176, AH1-460 |
|
| PENELEC | n8471 |
East Sayre-North Waverly 115kV line upgrade - FirstEnergy (NYISO CY17 driven upgrade) |
Nov 01 2027 |
|
AG2-582, AH1-680 |
|
| PENELEC | s3335.1 / PN-2024-007 |
Replace Homer City South 345/230-23kV Transformer |
Jun 01 2027 |
|
AG2-176, AG2-429 |
|
| PEPCO | b3780.11 |
Brighton Statcom and Capacitor (Projected ISD 12/31/2028) |
Dec 31 2028 |
|
AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725 |
|
| PEPCO | b3800.243 |
Rebuild 7.26 miles of existing 500 kV circuit from Dickerson Station H to Ed's Ferry |
Dec 31 2030 |
|
AH1-261, AH1-552 |
|
| PEPCO | b3800.244 |
Rebuild 7.26 miles of existing 230 kV circuit from Dickerson Station H to Ed's Ferry |
Dec 31 2030 |
|
AH1-261, AH1-552 |
|
| PEPCO | b3800.245 |
Reconfigure Dickerson H 230 kV Substation and upgrade terminal equipment. |
Dec 31 2030 |
|
AH1-261, AH1-552 |
|
| PEPCO | b3800.46 |
North Delta 500 kV termination for the new Peach Bottom-North Delta 500 kV line (PECO work). |
Dec 11 2029 |
|
AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725 |
|
| PEPCO | b4052.1 |
New 500/230 kV substation (Dickerson) by cutting into the Aspen-Rocky Point 500 kV line |
Jun 01 2032 |
|
AG2-068, AG2-069, AG2-369, AG2-436, AG2-570, AG2-571, AH1-528, AH1-681, AH1-712, AH1-723 |
|
| PEPCO | b4052.10 |
Replace one stranded bus conductor, three thermal relays, two disconnect switches at Quince Orchard 230 kV substation. |
Jun 01 2032 |
|
AG2-068, AG2-069, AG2-369, AG2-436, AG2-570, AG2-571, AH1-528, AH1-681, AH1-712, AH1-723 |
|
| PEPCO | b4052.11 |
Replace Bells Mill T3 XF with new PEPCO standard 260 MVA 230/138 kV transformer. |
Jun 01 2032 |
|
AG2-068, AG2-069, AG2-369, AG2-436, AG2-570, AG2-571, AH1-528, AH1-681, AH1-712, AH1-723 |
|
| PEPCO | b4052.2 |
Install two 500/230 kV transformers connecting a new 500 kV Dickerson station and DIckeson "H" 230 kV station including 230 kV substation work. |
Jun 01 2032 |
|
AG2-068, AG2-069, AG2-369, AG2-436, AG2-570, AG2-571, AH1-528, AH1-681, AH1-712, AH1-723 |
|
| PEPCO | b4052.3 |
Rocky Point-Dickerson (new 500 kV) termination work at Dickerson 500 kV |
Jun 01 2032 |
|
AG2-068, AG2-069, AG2-369, AG2-436, AG2-570, AG2-571, AH1-528, AH1-681, AH1-712, AH1-723 |
|
| PEPCO | b4052.4 |
Aspen-Dickerson (new 500 kV) termination work at Dickerson 500 kV |
Jun 01 2032 |
|
AG2-068, AG2-069, AG2-369, AG2-436, AG2-570, AG2-571, AH1-528, AH1-681, AH1-712, AH1-723 |
|
| PEPCO | b4052.7 |
Install 3.2% 230 kV series reactor at Dickerson "H" terminal side of the Edwards Ferry-Dickerson circuit. |
Jun 01 2032 |
|
AG2-068, AG2-069, AG2-369, AG2-436, AG2-570, AG2-571, AH1-528, AH1-681, AH1-712, AH1-723 |
|
| PEPCO | b4052.8 |
Relocate Dickerson "D"-Quince Orchard 23035 to terminate at Dickerson "H" at Dickerson No. 2 tie location. |
Jun 01 2032 |
|
AG2-068, AG2-069, AG2-369, AG2-436, AG2-570, AG2-571, AH1-528, AH1-681, AH1-712, AH1-723 |
|
| PEPCO | b4052.9 |
Replace two breakers, one bushing CT, one stranded bus conductor, four disconnect switches at Brighton 500 kV substation. |
Jun 01 2032 |
|
AG2-068, AG2-069, AG2-369, AG2-436, AG2-570, AG2-571, AH1-528, AH1-681, AH1-712, AH1-723 |
|
| PEPCO | b4053.29 |
Uprate 500 kV line No. 560 terminal equipment at Burches Hill substation in PEPCO so as not to limit the conductor rating. |
Jun 01 2032 |
|
AG2-436, AG2-570, AG2-571, AH1-528, AH1-681, AH1-712, AH1-723 |
|
| PEPCO | n9760.0 / PECO_TC2_PH2 |
Relocate Dickerson D to Quince Orchard 23033 to terminate at Dickerson H |
60 Months |
$10,000,000
|
AH1-552 |
|
| PPL | n6818 |
Rebuild PPL's ~0.9 miles LEWI-JUNI 230kV Line with a summer normal rating of at least 3000 Amps. |
24 to 36 Months |
$1,900,000
|
AG2-176, AH1-460 |
|
| PPL | s0945.1 |
Rebuild the Juniata 230/69 kV Substation |
Dec 18 2025 |
|
AG2-176, AH1-460 |
|
| PSEG | n9715.0 / PSEG-TC2_PH1_LindenMinueR |
Upgrade Linden to Minue St R-2218 230 kV circuit |
30 Months |
$9,000,000
|
AH1-715, AH1-722 |
|
| PSEG | n9716.0 / PSEG-TC2_PH1_MinueSewarenR |
Upgrade Minue St to Sewaren R-2218 230kV circuit |
30 Months |
$8,332,000
|
AH1-715, AH1-722 |
|
| PSEG | n9732.0 / PSEG-TC2-PHQ_LindenGen |
Upgrade PSE&G portion of the Linden 230kV generator lead line |
24 Months |
$3,708,000
|
AH1-715, AH1-722 |
|
| PSEG | n9751.0 / PSEG-TC2_PH1_LindenMinueQ |
Upgrade Linden to Minue St Q-2348 230 kV |
30 Months |
$9,183,000
|
AH1-715, AH1-722 |
|
| PSEG | n9752.0 / PSEG-TC2_PH1_MinueSewarenQ |
Upgrade Minue St to Sewaren Q-2348 230kV circuit |
30 Months |
$8,180,000
|
AH1-715, AH1-722 |
|
Short Circuit Reinforcements
PJM performed short circuit analysis for the New Service Requests in Transition Cycle 2 Phase II System Impact Study. The table below shows all the system reinforcements identified from short circuit analysis.
| TO | RTEP ID / TO ID | Title | Time Estimate | Total Cost Estimate ($) | Projects with Cost Allocation | Contingent Projects |
|---|---|---|---|---|---|---|
| AEP | n9689.0 |
Replace 05TORREY1 breaker with a 138 kV 63 kA 3000A |
Jun 01 2028 |
$1,000,000
|
AH1-680 |
|
| AEP | s2851 / S2851 |
New Carlisle 138 kV station |
TBD |
|
AG2-562 |
|
| APS | n4854 |
Glen Falls SS: Circuit Breaker Replacements |
TBD |
|
AG2-582 |
|
| EKPC | n9687.1 |
Cooper 161kV breaker replacements - Breaker 1064 DENNY |
Dec 01 2029 |
$335,000
|
AH1-721 |
|
| EKPC | n9687.2 |
Cooper 161kV breaker replacements - Breaker 1008 XFMR |
Dec 01 2029 |
$335,000
|
AH1-721 |
|
| EKPC | n9687.3 |
Cooper 161kV breaker replacements - Breaker 1014 WOLF CR |
Dec 01 2029 |
$335,000
|
AH1-721 |
|
| EKPC | n9687.4 |
Cooper 161kV breaker replacements - Breaker 1039 BUS |
Dec 01 2029 |
$335,000
|
AH1-721 |
|
| EKPC | n9687.5 |
Cooper 161kV breaker replacement - Breaker 1054 LAUREL |
Dec 01 2029 |
$335,000
|
AH1-721 |
|
| EKPC | n9687.6 |
Cooper 161kV breaker replacements - Breaker 1079 TRANSF |
Dec 01 2029 |
$335,000
|
AH1-721 |
|
| EKPC | n9687.7 |
Cooper 161kV breaker replacements - Breaker 110G UNIT 1 |
Dec 01 2029 |
$335,000
|
AH1-721 |
|
| EKPC | n9687.8 |
Cooper 161kV breaker replacements - Breaker 210G UNIT 2 |
Dec 01 2029 |
$335,000
|
AH1-721 |
|
| EKPC | n9687.9 |
Cooper 161kV breaker replacements - Breaker 1024 LIBERTY |
Dec 01 2029 |
$335,000
|
AH1-721 |
|
Stability Reinforcements
PJM performed stability analysis for the New Service Requests in Transition Cycle 2 Phase II System Impact Study. The table below shows all the system reinforcements identified from stability analysis.
| TO | RTEP ID / TO ID | Title | Time Estimate | Total Cost Estimate ($) | Projects with Cost Allocation | Contingent Projects |
|---|---|---|---|---|---|---|
| Dominion | n9267.0 / TC1-PH2-DOM-067 |
Construct new 10.21 mile 115 kV line between Northern Neck and Moon Corner. |
45 to 46 Months |
|
AH1-397 |
|
| Dominion | n9630.0 / TC1-PH3-DOM-013 |
Construct a new 230 kV line from the AG1-285 substation to the Finneywood 230 kV Substation. Expand AG1-285 substation and add two (2) new 230/115 kV transformers. |
Dec 31 2029 |
|
AG2-077, AG2-171, AG2-198, AG2-213, AG2-270, AG2-341, AG2-440, AG2-441, AG2-442, AG2-522, AG2-566, AG2-581, AG2-659, AH1-280, AH1-396, AH1-528 |
|
| EKPC | n9688.0 / EKPC-tc2-nu049 |
AH1-239 Tap (Clinton County)-Homestead New 69 kV Line (15 miles) |
Dec 31 2028 |
$16,300,000
|
AH1-239, AH1-721 |
|
Note: Additional detail can be found in each of the individual TC2 New Service Request System Impact Study reports also available on PJM.com.