Transition Cycle 2

v1.00 released 2026-06-03 19:14

New Service Requests

System Impact Study Executive Summary Report

Transition Cycle 2 — Phase II

Introduction

This Phase II System Impact Study executive summary report has been prepared in accordance with the PJM Open Access Transmission Tariff Part VII, Subpart D, section 310. This report presents an executive summary of the Phase II System Impact Study results for New Service Requests (projects) in Transition Cycle 2.

Preface

The Phase II System Impact Study is conducted on an aggregate basis within a New Services Request’s Cycle, and results are provided in both (i) a single Cycle summary format and (ii) an individual project-level basis. The Phase II System Impact Study Results (for both the summary and individual reports) will be publicly available on PJM’s website. Project Developers must obtain the results from the website.

In accordance with PJM Manual 14H, section 4.5, PJM takes the following actions during the Phase II System Impact Study:

  1. PJM will retool load flow results from the Phase I System Impact Study (summer peak, winter peak and light load) based on decisions made by Project Developers or Eligible Customers during Decision Point I.
  2. PJM will conduct any required voltage analyses.
  3. PJM will perform short circuit and stability analyses as required.
  4. PJM will coordinate with the Affected System to confirm which projects in the PJM Cycle will require Affected System studies. If the Affected System Operator indicates that an Affected System study is required, PJM will:
    1. Notify the Project Developer or Eligible Customer of the need for an Affected System study and the requirement to execute an Affected System study agreement with the impacted Affected System Operator, and;
    2. Include the results of the Affected System Operator’s Affected System Study in the Phase II System Impact Study results, if applicable and available.
  5. The Phase II System Impact Study Results will be publicly available on PJM’s website. Project Developers and Eligible Customers must obtain the results from the website.

New Services Request List

PJM received 270 New Service Requests in Transition Cycle 2, Phase II System Impact Study with a combined Maximum Facility Output (MFO) of 29,742.6 MW and 22,959.9 MW as Capacity Interconnection Rights (CIRs). All of these New Service Requests are listed in table below.

Project ID Project Name / POI
State
Status
Transmission Owner
Maxiumum Facility Output (MFO in MW) MW Energy (MWE) MW Capacity (MWC) Project Type Resource Type Facilities Study
AG2-014 Meadow Lake 345 kV Indiana Active AEP Indiana Michigan Transmission Company, Inc. 50.0 50.0 20.0 Generation Interconnection Storage
AG2-016 Oyster Creek-Whitings 34.5 kV New Jersey Active Jersey Central Power & Light Company 19.8 19.8 8.316 Generation Interconnection Solar
AG2-029 Forest G. Hipple-Dunton Lake 345 kV Indiana Active AEP Indiana Michigan Transmission Company, Inc. 250.0 250.0 32.5 Generation Interconnection Solar
AG2-037 Findlay-Clinton 23 kV Pennsylvania Active Duquesne Light Company 4.7 4.7 2.82 Generation Interconnection Solar
AG2-049 Van Dorn 34.5 kV Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 20.0 20.0 20.0 Generation Interconnection Other N/A
AG2-057 Cardington-Liberty 69 kV II Ohio Active American Transmission Systems, Incorporated 74.0 10.0 6.0 Generation Interconnection Solar
AG2-061 Dana 345 kV Illinois Active Commonwealth Edison Company 200.0 50.0 20.0 Generation Interconnection Storage
AG2-062 William 138 kV West Virginia Active Monongahela Power Company 147.0 147.0 21.609 Generation Interconnection Wind
AG2-068 Heritage - Wake 500 kV Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 100.0 100.0 60.0 Generation Interconnection Solar
AG2-069 Heritage - Wake 500 kV Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 250.0 150.0 90.0 Generation Interconnection Solar
AG2-072 Rockport 765 kV Indiana Active AEP Indiana Michigan Transmission Company, Inc. 700.0 700.0 700.0 Generation Interconnection Natural Gas; Other
AG2-073 Crooksville 69 kV Kentucky Active East Kentucky Power Cooperative, Inc. 53.0 53.0 50.88 Generation Interconnection Solar
AG2-074 Meckesville Tap 69kV Pennsylvania Active PPL Electric Utilities Corporation 38.0 38.0 26.2 Generation Interconnection Solar
AG2-077 Clover-Rawlings 500 kV Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 700.0 200.0 120.0 Generation Interconnection Solar
AG2-081 Avon - Renaker 138 kV Kentucky Active East Kentucky Power Cooperative, Inc. 30.0 30.0 18.0 Generation Interconnection Solar
AG2-082 Nottingham 138 kV Ohio Active AEP Ohio Transmission Company, Inc. 200.0 200.0 133.4 Generation Interconnection Solar
AG2-086 Mt. Jackson DP-Mt. Jackson 115 kV Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 75.0 75.0 45.0 Generation Interconnection Solar; Storage
AG2-088 Midlothian 230 kV Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 150.0 150.0 150.0 Generation Interconnection Storage
AG2-095 Hopewell 34.5 kV (Circuit 313) Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 18.0 18.0 10.8 Generation Interconnection Solar N/A
AG2-104 Marysville-Flatlick 765 kV Ohio Active AEP Ohio Transmission Company, Inc. 200.0 200.0 126.85 Generation Interconnection Solar
AG2-106 Marysville-Flatlick 765 kV Ohio Active AEP Ohio Transmission Company, Inc. 800.0 0.0 150.0 Generation Interconnection Storage
AG2-107 Marysville-Flatlick 765 kV Ohio Active AEP Ohio Transmission Company, Inc. 800.0 0.0 150.0 Generation Interconnection Storage
AG2-109 Fitchville-New London 69 kV Ohio Active American Transmission Systems, Incorporated 40.0 40.0 28.1 Generation Interconnection Solar
AG2-114 Dresden-Pontiac Midpoint 345 kV Illinois Active Commonwealth Edison Company 100.0 100.0 60.0 Generation Interconnection Solar
AG2-119 Galion-Roberts South 138 kV II Ohio Active American Transmission Systems, Incorporated 80.0 80.0 53.6 Generation Interconnection Solar
AG2-121 Mackeys 230 kV North Carolina Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 140.0 0.0 0.0 Generation Interconnection Storage N/A
AG2-124 Shackleford-Harmony 115 kV Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 149.9 0.0 33.34 Generation Interconnection Solar
AG2-125 Camden-Crystal 69 kV Ohio Active The Dayton Power and Light Company 69.9 0.0 15.44 Generation Interconnection Solar N/A
AG2-126 Eugene 345 kV Indiana Active AEP Indiana Michigan Transmission Company, Inc. 150.0 150.0 90.0 Generation Interconnection Solar; Storage
AG2-151 Trices Lake - James River Tap 115 kV Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 100.0 100.0 60.0 Generation Interconnection Solar
AG2-152 Banister-Bear Skin 138 kV Virginia Active Appalachian Power Company 131.0 131.0 79.0 Generation Interconnection Solar
AG2-163 Dequine-Eugene 345 kV Indiana Active AEP Indiana Michigan Transmission Company, Inc. 700.0 250.0 35.0 Generation Interconnection Solar
AG2-166 Newville-Nottingham Tap 1 69 kV Pennsylvania Active PPL Electric Utilities Corporation 10.0 10.0 0.0 Generation Interconnection Solar
AG2-171 Lunenburg - Nutbush 115 kV Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 60.0 60.0 36.0 Generation Interconnection Solar
AG2-176 Geneva 115 kV Pennsylvania Active Mid-Atlantic Interstate Transmission, LLC 150.0 150.0 90.0 Generation Interconnection Solar
AG2-182 Doubs-Bismark 500 kV Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 200.0 200.0 133.3333 Generation Interconnection Solar
AG2-184 Harbert Metering 138 kV Kentucky Active Kentucky Power Company 210.0 210.0 126.0 Generation Interconnection Solar
AG2-191 Mississinewa 138 kV Indiana Active American Electric Power 30.0 30.0 18.0 Generation Interconnection Solar; Storage
AG2-192 Mississinewa 138 kV Indiana Active American Electric Power 19.0 19.0 11.4 Generation Interconnection Solar; Storage
AG2-193 Turner 34.5 kV Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 20.0 20.0 12.0 Generation Interconnection Solar N/A
AG2-198 Briery - Finneywood 230 kV Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 80.0 80.0 48.0 Generation Interconnection Solar
AG2-200 North Warren - Russell 34.5 kV Pennsylvania Active Mid-Atlantic Interstate Transmission, LLC 17.0 17.0 10.2 Generation Interconnection Solar
AG2-213 Gary D.P Tap - Gary D.P 115 kV Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 80.0 80.0 48.0 Generation Interconnection Solar
AG2-216 East Sidney-Quincy 138 kV Ohio Active The Dayton Power and Light Company 144.0 0.0 25.92 Generation Interconnection Solar N/A
AG2-230 Dumont 345 kV Indiana Active AEP Indiana Michigan Transmission Company, Inc. 150.0 150.0 90.0 Generation Interconnection Solar
AG2-236 Potter-Harlan 69 kV Pennsylvania Active American Transmission Systems, Incorporated 60.0 20.0 2.0 Generation Interconnection Solar
AG2-238 Earleys 230 kV North Carolina Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 99.9 0.0 0.0 Generation Interconnection Storage N/A
AG2-240 Old Church 34.5 kV Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 25.0 0.0 0.0 Generation Interconnection Storage N/A
AG2-245 Olive - Reynolds #1 345 kV Indiana Active American Electric Power 210.0 210.0 126.0 Generation Interconnection Solar
AG2-248 East Elkhart - Elcona Tap 138 kV Indiana Active American Electric Power 100.0 100.0 0.0 Generation Interconnection Storage
AG2-262 Dryburg 115 kV Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 47.0 11.0 6.6 Generation Interconnection Solar N/A
AG2-270 Clover 230 kV Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 150.0 150.0 105.0 Generation Interconnection Storage
AG2-272 Berry Hill 138 kV Virginia Active Appalachian Power Company 55.0 55.0 21.3 Generation Interconnection Storage
AG2-288 Stonewall 138 kV Virginia Active The Potomac Edison Company 150.0 150.0 150.0 Generation Interconnection Storage
AG2-289 Amsden - Fremont Center 69 kV Ohio Active AEP Ohio Transmission Company, Inc. 66.6 66.6 0.0 Generation Interconnection Storage
AG2-290 Amsden - Fremont Center 69 kV Ohio Active AEP Ohio Transmission Company, Inc. 105.0 38.4 0.0 Generation Interconnection Storage
AG2-297 Cumberland 230 kV New Jersey Active Atlantic City Electric 19.0 19.0 11.4 Generation Interconnection Solar
AG2-298 Sulphur Creek-Loretto 69 kV Kentucky Active East Kentucky Power Cooperative, Inc. 35.0 35.0 23.33 Generation Interconnection Solar
AG2-300 Meadow Brook 138 kV Virginia Active The Potomac Edison Company 100.0 100.0 70.0 Generation Interconnection Storage
AG2-329 S Berwick - Galion 345 kV Ohio Active AEP Indiana Michigan Transmission Company, Inc. 200.0 200.0 156.0 Generation Interconnection Storage
AG2-332 East Elkhart - Elcona Tap 138 kV Indiana Active American Electric Power 200.0 100.0 100.0 Generation Interconnection Storage
AG2-339 Rogers Road - Carson 500 kV Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 479.0 85.0 85.0 Generation Interconnection Storage
AG2-341 Ridge Road 115 kV Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 50.0 50.0 20.0 Generation Interconnection Storage
AG2-343 Eugene - Dequine 345 kV Indiana Active AEP Indiana Michigan Transmission Company, Inc. 100.0 100.0 78.0 Generation Interconnection Storage
AG2-345 Eugene - Dequine 345 kV Indiana Active AEP Indiana Michigan Transmission Company, Inc. 150.0 50.0 39.0 Generation Interconnection Storage
AG2-356 South Troy - Canton 34.5 kV Pennsylvania Active Mid-Atlantic Interstate Transmission, LLC 20.0 20.0 12.0 Generation Interconnection Solar N/A
AG2-360 Broadford 138 kV Virginia Active Appalachian Power Company 250.0 250.0 250.0 Generation Interconnection Storage
AG2-363 Powerton 345 kV Illinois Active Commonwealth Edison Company 300.0 300.0 180.0 Generation Interconnection Solar
AG2-364 Powerton 345 kV Illinois Active Commonwealth Edison Company 200.0 200.0 120.0 Generation Interconnection Solar
AG2-369 Heritage - Wake 500 kV Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 86.0 86.0 51.6 Generation Interconnection Solar
AG2-370 Tillman 138 kV Indiana Active AEP Indiana Michigan Transmission Company, Inc. 50.0 50.0 20.0 Generation Interconnection Storage
AG2-380 Carville 138 kV IV Maryland Active Delmarva Power and Light Company 20.0 20.0 20.0 Generation Interconnection Storage
AG2-382 Cashie 230 kV North Carolina Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 70.0 70.0 42.0 Generation Interconnection Solar
AG2-384 Chesterfield 230 kV Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 60.82 60.82 24.0 Generation Interconnection Storage
AG2-401 Losantville 345 kV Indiana Active American Electric Power 200.0 0.0 44.0 Generation Interconnection Solar N/A
AG2-405 Continental 69 kV Ohio Active American Electric Power 49.9 0.0 10.98 Generation Interconnection Solar N/A
AG2-406 Payne 69 kV Ohio Active American Electric Power 49.9 0.0 10.98 Generation Interconnection Solar N/A
AG2-411 Statler Hill 115 kV Pennsylvania Active Mid-Atlantic Interstate Transmission, LLC 63.0 63.0 40.7 Generation Interconnection Solar
AG2-420 Eclipse #2 34.5 kV Pennsylvania Active Mid-Atlantic Interstate Transmission, LLC 25.0 25.0 14.0 Generation Interconnection Solar; Storage
AG2-423 Cherry Run - Harmony 138 kV West Virginia Active Monongahela Power Company 80.0 80.0 48.0 Generation Interconnection Solar
AG2-424 Summersville - Magnolia 69 kV Kentucky Active East Kentucky Power Cooperative, Inc. 63.25 63.25 34.95 Generation Interconnection Solar; Storage
AG2-426 Wakefield - Waverly 115 kV Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 33.5 33.5 33.5 Generation Interconnection Solar; Storage
AG2-429 Burma - Armstrong 138 kV Pennsylvania Active Keystone Appalachian Transmission Company 46.5 46.5 46.5 Generation Interconnection Solar; Storage
AG2-436 Carson - Rogers Road 500 kV Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 350.0 350.0 140.0 Generation Interconnection Solar
AG2-440 Twittys Creek - Madisonville 115 kV Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 75.0 75.0 45.0 Generation Interconnection Solar
AG2-441 Twittys Creek - Madisonville 115 kV Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 188.0 113.0 67.8 Generation Interconnection Solar
AG2-442 Twittys Creek - Madisonville 115 kV Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 140.0 140.0 84.0 Generation Interconnection Solar
AG2-447 Cedar Creek 138 kV VII Delaware Active Delmarva Power and Light Company 134.25 20.0 12.0 Generation Interconnection Solar N/A
AG2-448 Cross School - Westvaco 138 kV West Virginia Active The Potomac Edison Company 50.0 50.0 30.0 Generation Interconnection Solar
AG2-453 Lasalle - Plano 345 kV Illinois Active Commonwealth Edison Company 280.0 280.0 196.0 Generation Interconnection Solar
AG2-479 Penns Tap-Richfield Tie 69 kV II Pennsylvania Active PPL Electric Utilities Corporation 20.0 0.0 4.1 Generation Interconnection Solar
AG2-481 Derry Tap-Derry Bus 69 kV III Pennsylvania Active PPL Electric Utilities Corporation 20.0 0.0 4.1 Generation Interconnection Solar
AG2-484 Mifflintown Bus-Mifflintown Tap 69 kV II Pennsylvania Active PPL Electric Utilities Corporation 20.0 0.0 4.6 Generation Interconnection Solar
AG2-487 Madison - Tanners Creek 138 kV Indiana Active American Electric Power 152.5 0.0 10.6 Generation Interconnection Solar N/A
AG2-491 Meadow Lake 345 kV Indiana Active American Electric Power 100.0 100.0 60.0 Generation Interconnection Solar
AG2-492 Meadow Lake 345 kV Indiana Active American Electric Power 50.0 50.0 20.0 Generation Interconnection Storage
AG2-516 Pecatonica 138kV Illinois Active Commonwealth Edison Company 120.0 120.0 72.0 Generation Interconnection Solar
AG2-518 Tech Drive 138 kV Virginia Active American Electric Power 80.0 80.0 32.0 Generation Interconnection Storage
AG2-519 Royerton - Desoto 138 kV Indiana Active AEP Indiana Michigan Transmission Company, Inc. 66.5 66.5 66.5 Generation Interconnection Solar; Storage
AG2-522 Five Forks DP - Littleton DP 115 kV North Carolina Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 80.0 80.0 48.0 Generation Interconnection Solar
AG2-524 LaSalle Station - Mazon 138 kV Illinois Active Commonwealth Edison Company 110.0 110.0 110.0 Generation Interconnection Solar; Storage
AG2-544 Silver Lake 345 kV Illinois Active Commonwealth Edison Company 200.0 200.0 80.0 Generation Interconnection Storage
AG2-545 Silver Lake 345 kV Illinois Active Commonwealth Edison Company 400.0 400.0 160.0 Generation Interconnection Storage
AG2-548 Corwin - Elk 138 kV Ohio Active American Electric Power 80.0 80.0 54.0 Generation Interconnection Solar; Storage
AG2-550 Bluff Point - Randolph 138 kV Indiana Active American Electric Power 100.0 100.0 60.0 Generation Interconnection Solar
AG2-551 Bluff Point - Randolph 138 kV Indiana Active American Electric Power 150.0 50.0 20.0 Generation Interconnection Storage N/A
AG2-561 Glory - Glen Campbell 34.5 kV Pennsylvania Active Mid-Atlantic Interstate Transmission, LLC 20.0 20.0 12.0 Generation Interconnection Solar N/A
AG2-562 Elderberry 345 kV Indiana Active American Electric Power 767.0 52.0 0.0 Generation Interconnection Natural Gas
AG2-566 Briery - Finneywood 230 kV Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 110.0 30.0 12.0 Generation Interconnection Storage
AG2-568 Stink Run - Sundial 138 kV West Virginia Active American Electric Power 80.0 80.0 48.0 Generation Interconnection Solar
AG2-570 Heritage - Wake 500 kV Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 400.0 400.0 100.0 Generation Interconnection Solar
AG2-571 Heritage - Wake 500 kV Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 500.0 100.0 40.0 Generation Interconnection Storage
AG2-581 Rawlings - Unity 500 kV Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 150.0 150.0 90.0 Generation Interconnection Solar
AG2-582 Flint Run 500 kV West Virginia Active Monongahela Power Company 2100.0 2100.0 2075.0 Generation Interconnection Natural Gas
AG2-583 Bremo - Cartersville 230 kV Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 115.0 115.0 69.0 Generation Interconnection Solar
AG2-585 Kensignton 138kV Illinois Active Commonwealth Edison Company 55.0 55.0 33.0 Generation Interconnection Solar
AG2-616 Churchtown - Upper Pittsgrove 138 kV New Jersey Active Atlantic City Electric 50.0 50.0 32.35 Generation Interconnection Solar
AG2-617 Waugh Chapel 115 kV Maryland Active Baltimore Gas and Electric Company 55.0 55.0 33.0 Generation Interconnection Solar
AG2-618 Morgantown Unit 1 and 2 Maryland Active Potomac Electric Power Company 110.0 110.0 71.5 Generation Interconnection Solar
AG2-621 Hoytdale 138 kV Pennsylvania Active American Transmission Systems, Incorporated 150.0 150.0 150.0 Generation Interconnection Storage
AG2-625 Pequest River-Furnace Brook Tap 34.5 kV II New Jersey Active Jersey Central Power & Light Company 19.6 19.6 8.232 Generation Interconnection Solar
AG2-626 Pequest River-Furnace Brook Tap 34.5 kV III New Jersey Active Jersey Central Power & Light Company 12.5 12.5 5.25 Generation Interconnection Solar
AG2-637 Randolph - Hodgin 138 kV Indiana Active Indiana Michigan Power Company 150.0 150.0 90.0 Generation Interconnection Solar
AG2-657 Kanawha River - Carbondale 138 kV West Virginia Active American Electric Power 90.0 90.0 37.8 Generation Interconnection Solar
AG2-659 Palmer Springs - Hawtree 115 kV Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 80.0 80.0 48.0 Generation Interconnection Solar
AG2-660 Nelson-Electric Junction 345 kV Illinois Active Commonwealth Edison Company 600.0 0.0 20.0 Generation Interconnection Storage
AG2-661 Hopewell - Colonial Trail 230 kV Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 150.0 0.0 20.0 Generation Interconnection Solar; Storage N/A
AG2-665 Corwin - Elk 138 kV Ohio Active American Electric Power 160.0 80.0 54.0 Generation Interconnection Solar; Storage
AG2-675 Cordova 345 kV Illinois Active Commonwealth Edison Company 80.0 80.0 32.0 Generation Interconnection Storage
AH1-004 Avon - Renaker 138 kV Kentucky Active East Kentucky Power Cooperative, Inc. 40.0 40.0 24.0 Generation Interconnection Solar
AH1-033 Sligo 34.5 kV North Carolina Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 19.5 19.5 13.0 Generation Interconnection Solar
AH1-040 Mackeys - Creswell 115 kV North Carolina Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 150.0 150.0 90.0 Generation Interconnection Solar
AH1-044 Nelson - Electric Junction 345 kV Illinois Active Commonwealth Edison Company 800.0 200.0 120.0 Generation Interconnection Solar
AH1-054 Upton-Whitings 34.5 kV New Jersey Active Jersey Central Power & Light Company 8.25 8.25 3.465 Generation Interconnection Solar
AH1-055 Kyger Creek - Don Marquis 345 kV Ohio Active Ohio Valley Electric Corporation 220.0 220.0 154.0 Generation Interconnection Solar
AH1-057 Edgewood 12.47 kV Maryland Active Delmarva Power and Light Company 7.2 7.2 3.0 Generation Interconnection Solar N/A
AH1-059 Sharp Road 69 kV Ohio Active AEP Ohio Transmission Company, Inc. 101.0 21.0 12.6 Generation Interconnection Solar
AH1-060 Cardington-Liberty 69 kV III Ohio Active American Transmission Systems, Incorporated 94.0 20.0 12.0 Generation Interconnection Solar
AH1-071 Midlothian 34.5 kV Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 20.0 20.0 12.0 Generation Interconnection Solar N/A
AH1-072 Red Onion - VC5 69 kV Virginia Active American Electric Power 20.0 20.0 12.0 Generation Interconnection Solar
AH1-073 Red Onion - VC5 69 kV Virginia Active American Electric Power 40.0 20.0 12.0 Generation Interconnection Solar
AH1-091 Ahoskie 34.5kV North Carolina Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 17.0 0.0 0.0 Generation Interconnection Storage N/A
AH1-098 Wolf Glade-West Carroll 138 kV Virginia Active American Electric Power 40.0 40.0 24.0 Generation Interconnection Solar; Storage
AH1-106 Winterpock 34.5kV Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 26.0 26.0 15.6 Generation Interconnection Solar N/A
AH1-107 Winterpock 34.5kV Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 26.0 26.0 15.6 Generation Interconnection Solar N/A
AH1-108 Spruance NUG 230 kV Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 66.0 0.0 9.0 Generation Interconnection Natural Gas N/A
AH1-133 Saltville - Tazewell 138 kV Virginia Active American Electric Power 70.0 70.0 29.4 Generation Interconnection Solar
AH1-138 Penniman 34.5 kV Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 20.0 20.0 8.4 Generation Interconnection Solar N/A
AH1-144 Peter's Mountain 138 kV Virginia Active American Electric Power 70.0 70.0 29.4 Generation Interconnection Solar
AH1-145 Peter's Mountain 138 kV Virginia Active American Electric Power 150.0 80.0 80.0 Generation Interconnection Storage
AH1-150 Nelson-Electric Junction 345 kV Illinois Active Commonwealth Edison Company 1000.0 200.0 120.0 Generation Interconnection Solar
AH1-151 Nelson-Electric Junction 345 kV Illinois Active Commonwealth Edison Company 1200.0 200.0 120.0 Generation Interconnection Solar
AH1-153 Dumont 345 kV Indiana Active AEP Indiana Michigan Transmission Company, Inc. 200.0 50.0 30.0 Generation Interconnection Solar
AH1-165 Will County 138 kV Illinois Active Commonwealth Edison Company 72.0 72.0 0.0 Generation Interconnection Storage
AH1-170 Columbia DP 115kV Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 20.0 20.0 12.0 Generation Interconnection Solar
AH1-188 Pigeon Creek 138 kV West Virginia Active Appalachian Power Company 140.0 140.0 84.0 Generation Interconnection Solar
AH1-196 Silver Lake - Cherry Valley 345 kV Illinois Active Commonwealth Edison Company 150.0 150.0 90.0 Generation Interconnection Solar
AH1-206 Bethelboro 138 kV Pennsylvania Active Keystone Appalachian Transmission Company 60.0 60.0 60.0 Generation Interconnection Storage
AH1-216 Smithfield-Surry 230 kV Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 99.0 99.0 79.2 Generation Interconnection Solar; Storage
AH1-221 Heritage 500 kV Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 75.0 0.0 45.0 Generation Interconnection Storage N/A
AH1-223 Poland Rd-Runway DP 230 kV Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 150.0 0.0 20.0 Generation Interconnection Storage N/A
AH1-227 Flemming - Fremont 69 kV Virginia Active Appalachian Power Company 51.3 51.3 30.78 Generation Interconnection Solar
AH1-239 Upchurch - Zula 69 kV Kentucky Active East Kentucky Power Cooperative, Inc. 80.0 80.0 48.0 Generation Interconnection Solar
AH1-247 Lardin - Lake Lynn 138kV Pennsylvania Active Keystone Appalachian Transmission Company 40.0 40.0 24.0 Generation Interconnection Solar
AH1-248 Lardin - Lake Lynn 138kV Pennsylvania Active Keystone Appalachian Transmission Company 65.0 25.0 15.0 Generation Interconnection Solar
AH1-249 Lardin - Lake Lynn 138kV Pennsylvania Active Keystone Appalachian Transmission Company 145.0 80.0 80.0 Generation Interconnection Storage
AH1-251 Todds Tavern- Spotsylvania/Goldsdale 115kV Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 50.0 50.0 50.0 Generation Interconnection Storage
AH1-254 Greenland Gap 500 kV II West Virginia Active Monongahela Power Company 171.4 171.4 36.538 Generation Interconnection Wind
AH1-257 Broadway - Washington 34.5 kV New Jersey Active Jersey Central Power & Light Company 19.25 19.25 8.085 Generation Interconnection Solar
AH1-258 Belford - Keansburg 34.5 kV New Jersey Active Jersey Central Power & Light Company 19.25 19.25 8.085 Generation Interconnection Solar
AH1-260 New Freedom - Monroe 230 kV New Jersey Active Atlantic City Electric 300.0 300.0 300.0 Generation Interconnection Storage
AH1-261 Northeast - Riverside 230 kV Maryland Active Baltimore Gas and Electric Company 135.0 135.0 135.0 Generation Interconnection Storage
AH1-263 Chancellor 115 kV Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 200.0 200.0 200.0 Generation Interconnection Storage
AH1-269 Claytor 138 kV Virginia Active Appalachian Power Company 50.0 50.0 50.0 Generation Interconnection Storage
AH1-271 Cashie 230 kV North Carolina Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 110.0 40.0 24.0 Generation Interconnection Solar
AH1-272 Argenta - Twin Branch 345 kV Michigan Active AEP Indiana Michigan Transmission Company, Inc. 185.0 185.0 123.9 Generation Interconnection Solar
AH1-280 Jetersville-Ponton 115 kV Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 106.0 20.0 12.0 Generation Interconnection Solar N/A
AH1-282 Galion - Ohio Central 345 kV Ohio Active AEP Ohio Transmission Company, Inc. 49.9 49.9 45.9 Generation Interconnection Solar
AH1-283 Mount Storm-Pruntytown 500kV Maryland Active The Potomac Edison Company 200.0 200.0 120.0 Generation Interconnection Solar
AH1-292 Sullivan 345 kV Indiana Active American Electric Power 200.0 0.0 44.0 Generation Interconnection Solar N/A
AH1-302 Olive - Reynolds 345 kV Indiana Active AEP Indiana Michigan Transmission Company, Inc. 275.0 75.0 75.0 Generation Interconnection Storage
AH1-304 Delaware-Van Buren 138 kV Indiana Active American Electric Power 163.0 0.0 9.8 Generation Interconnection Solar N/A
AH1-305 Olive - Reynolds 345 kV Indiana Active AEP Indiana Michigan Transmission Company, Inc. 275.0 0.0 35.72 Generation Interconnection Solar N/A
AH1-306 Mississinewa-Gaston 138 kV Indiana Active AEP Indiana Michigan Transmission Company, Inc. 200.0 0.0 28.8 Generation Interconnection Solar N/A
AH1-311 Heartsease DP - Mayo Dunbar 115kV North Carolina Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 75.0 0.0 2.25 Generation Interconnection Solar N/A
AH1-314 East Danville 138 kV Virginia Active American Electric Power 100.0 100.0 100.0 Generation Interconnection Storage
AH1-327 Hardin Switch 345 kV Ohio Active American Electric Power 250.0 0.0 8.44 Generation Interconnection Solar N/A
AH1-328 Blue Jacket - Kirby 138 kV Ohio Active The Dayton Power and Light Company 206.55 0.0 21.3 Generation Interconnection Solar N/A
AH1-334 Lakehurst - Whitings 34.5 kV New Jersey Active Jersey Central Power & Light Company 19.25 19.25 8.085 Generation Interconnection Solar
AH1-338 New Sub S2354 138kV Illinois Active Commonwealth Edison Company 180.0 180.0 23.4 Generation Interconnection Solar
AH1-341 ESS-H445 3B 138kv Illinois Active Commonwealth Edison Company 150.0 150.0 96.6 Generation Interconnection Solar
AH1-343 Crystal Hill DP- Perth 115kV Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 69.0 69.0 41.4 Generation Interconnection Solar
AH1-345 Remington 324 34.5 kV Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 14.0 14.0 8.4 Generation Interconnection Solar N/A
AH1-348 Pound 34.5 kV Virginia Active American Electric Power 10.0 10.0 6.0 Generation Interconnection Solar
AH1-387 Meadowbrook-Greenland Gap 500kV West Virginia Active The Potomac Edison Company 150.0 150.0 22.05 Generation Interconnection Wind
AH1-392 Gravel Pit-Kankakee 138 kV Indiana Active American Electric Power 90.0 90.0 60.0 Generation Interconnection Solar
AH1-396 Gary 24.94 kV Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 11.891 11.891 1.8 Generation Interconnection Solar N/A
AH1-397 Shacklesfords 34.5 kV Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 19.67 19.67 2.97 Generation Interconnection Solar N/A
AH1-399 North Doswell 12.5 kV Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 9.87 9.87 1.48 Generation Interconnection Solar N/A
AH1-439 Buckingham- Farmville 230kV Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 85.0 85.0 51.0 Generation Interconnection Solar
AH1-452 Clementine-Clementine Jct. 25 kV Pennsylvania Active Keystone Appalachian Transmission Company 19.9 19.9 8.35 Generation Interconnection Solar N/A
AH1-460 Hooversville - Scalp Level 115 kV Pennsylvania Active Mid-Atlantic Interstate Transmission, LLC 66.0 66.0 39.6 Generation Interconnection Solar
AH1-461 Buckhorn 138 kV Virginia Active Appalachian Power Company 80.0 80.0 80.0 Generation Interconnection Storage
AH1-482 Olive - Reynolds #2 345 kV Indiana Active AEP Indiana Michigan Transmission Company, Inc. 338.0 78.0 78.0 Generation Interconnection Storage
AH1-528 Rawlings - Unity 500 kV Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 300.8 300.8 180.0 Generation Interconnection Solar
AH1-535 Nagel - Cane River 230 kV Tennessee Active Appalachian Power Company 100.0 100.0 40.0 Generation Interconnection Solar; Storage
AH1-537 Pierce - Kyger Creek 345 kV Ohio Active Ohio Valley Electric Corporation 178.5 178.5 17.85 Generation Interconnection Solar
AH1-541 Chestnut 345 kV Illinois Active Commonwealth Edison Company 92.4 92.4 27.72 Generation Interconnection Solar; Storage
AH1-542 Crissinger-Delaware Business Park 138kV Ohio Active American Transmission Systems, Incorporated 110.0 110.0 22.0 Generation Interconnection Solar; Storage
AH1-543 Mulberry - Tazewell 345 kV Illinois Active Commonwealth Edison Company 157.4 157.4 31.48 Generation Interconnection Solar; Storage
AH1-545 Wylie Ridge-Tidd 345kV Pennsylvania Active Monongahela Power Company 200.0 200.0 20.0 Generation Interconnection Solar
AH1-546 Bremo - Buckingham 230 kV Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 65.0 65.0 39.0 Generation Interconnection Solar
AH1-552 Chalk Point 230 kV Maryland Active Potomac Electric Power Company 670.2 670.2 670.2 Generation Interconnection Solar; Storage
AH1-563 Aurora E.C. 138kV Illinois Active Commonwealth Edison Company 1206.0 150.0 150.0 Generation Interconnection Storage
AH1-564 Rockford II 138 kV Illinois Active Commonwealth Edison Company 330.0 150.0 150.0 Generation Interconnection Storage
AH1-567 University Park 138 kV Illinois Active Commonwealth Edison Company 328.0 5.0 5.0 Generation Interconnection Natural Gas
AH1-570 Millersburg 69 kV Kentucky Active East Kentucky Power Cooperative, Inc. 25.0 25.0 15.6 Generation Interconnection Solar
AH1-571 Millersburg 69 kV Kentucky Active East Kentucky Power Cooperative, Inc. 45.0 20.0 12.5 Generation Interconnection Solar
AH1-580 Nottingham 138 kV Ohio Active AEP Ohio Transmission Company, Inc. 400.0 200.0 134.0 Generation Interconnection Solar
AH1-617 Harbert Metering 138 kV Kentucky Active Kentucky Power Company 200.0 200.0 120.0 Generation Interconnection Solar
AH1-637 Oak Grove 34.5 kV Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 16.0 16.0 9.6 Generation Interconnection Solar N/A
AH1-641 Churchtown - Upper Pittsgrove 138kV New Jersey Active Atlantic City Electric 65.0 15.0 7.0 Generation Interconnection Solar
AH1-661 Cannelville 12.47 kV Ohio Active American Electric Power 10.07 10.07 9.063 Generation Interconnection Other
AH1-664 Goddard-Plumville 138 kV Kentucky Active East Kentucky Power Cooperative, Inc. 100.0 100.0 66.8 Generation Interconnection Solar
AH1-665 Goddard-Plumsville 138 kV II Kentucky Active East Kentucky Power Cooperative, Inc. 180.0 80.0 53.5 Generation Interconnection Solar
AH1-666 Flemingsburg - Spurlock 138 kV Kentucky Active East Kentucky Power Cooperative, Inc. 80.0 80.0 48.0 Generation Interconnection Solar
AH1-667 Philipsburg-Shawville 34.5 kV Pennsylvania Active Mid-Atlantic Interstate Transmission, LLC 18.0 18.0 10.8 Generation Interconnection Solar
AH1-672 Farmview 138 kV Delaware Active Delmarva Power and Light Company 75.0 75.0 48.9 Generation Interconnection Solar
AH1-673 State Line - River Energy Center 138 kV Illinois Active Commonwealth Edison Company 85.0 85.0 85.0 Generation Interconnection Storage
AH1-677 Rogers Road 500 kV Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 1756.0 0.0 67.0 Generation Interconnection Natural Gas N/A
AH1-678 Heritage 500 kV Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 1525.5 0.0 34.0 Generation Interconnection Natural Gas; Other N/A
AH1-679 Four Rivers 230 kV Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 766.0 20.0 20.0 Generation Interconnection Natural Gas N/A
AH1-680 Sammis - South Canton 345 kV Ohio Active American Transmission Systems, Incorporated 1300.0 1300.0 1300.0 Generation Interconnection Natural Gas
AH1-681 Cunningham 500 kV Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 1000.0 0.0 27.3 Generation Interconnection Natural Gas N/A
AH1-682 Ladysmith CT 230 kV Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 190.0 0.0 21.0 Generation Interconnection Natural Gas N/A
AH1-683 Ladysmith CT 230 kV Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 190.0 0.0 25.0 Generation Interconnection Natural Gas N/A
AH1-684 Remington CT 230 kV Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 190.0 0.0 23.0 Generation Interconnection Natural Gas N/A
AH1-685 Remington CT 230 kV Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 190.0 0.0 26.0 Generation Interconnection Natural Gas N/A
AH1-686 Hanging Rock 765 kV Ohio Active American Electric Power 1364.0 24.0 21.0 Generation Interconnection Natural Gas
AH1-687 Bear Garden 230kV Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 682.0 0.0 51.0 Generation Interconnection Natural Gas N/A
AH1-691 Ladysmith CT 230 kV Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 209.0 0.0 26.0 Generation Interconnection Natural Gas N/A
AH1-692 Ladysmith CT 230 kV Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 209.0 0.0 26.0 Generation Interconnection Natural Gas N/A
AH1-693 Remington CT 230 kV Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 190.0 0.0 20.0 Generation Interconnection Natural Gas N/A
AH1-694 Ladysmith CT 230 kV Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 190.0 0.0 18.0 Generation Interconnection Natural Gas N/A
AH1-695 Three Mile Island 230 kV Pennsylvania Active Mid-Atlantic Interstate Transmission, LLC 859.0 859.0 803.0 Generation Interconnection Nuclear
AH1-696 Possum Point 230kV Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 668.0 0.0 94.0 Generation Interconnection Natural Gas N/A
AH1-698 Braidwood 345 kV Illinois Active Commonwealth Edison Company 2584.0 130.0 57.6 Generation Interconnection Nuclear
AH1-699 Wellsville 345 kV Ohio Active American Transmission Systems, Incorporated 1210.0 58.0 69.0 Generation Interconnection Natural Gas
AH1-701 Valero 69 kV New Jersey Active Atlantic City Electric 61.0 0.0 20.0 Generation Interconnection Natural Gas; Oil N/A
AH1-702 Byron 345 kV Illinois Active Commonwealth Edison Company 2530.0 88.0 43.0 Generation Interconnection Nuclear
AH1-703 Bergen 230kV New Jersey Active Public Service Electric and Gas Company 670.61 35.61 51.254 Generation Interconnection Natural Gas
AH1-704 Hannibal 138 kV Ohio Active AEP Ohio Transmission Company, Inc. 509.0 24.0 20.0 Generation Interconnection Natural Gas N/A
AH1-706 Lordstown 345 kV Ohio Active American Transmission Systems, Incorporated 970.453 30.453 23.823 Generation Interconnection Natural Gas
AH1-710 Salem 500kV New Jersey Active Public Service Electric and Gas Company 2650.8 256.8 228.2 Generation Interconnection Nuclear
AH1-711 Lemoyne 345 kV Ohio Active American Transmission Systems, Incorporated 1108.2 408.2 292.5 Generation Interconnection Natural Gas
AH1-712 Cunningham 500 kV Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 776.0 776.0 611.0 Generation Interconnection Natural Gas; Other
AH1-713 Mt. Storm 500kV West Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 538.0 0.0 14.0 Generation Interconnection Coal N/A
AH1-714 Lasalle 345 kV Illinois Active Commonwealth Edison Company 1360.0 169.0 174.1 Generation Interconnection Nuclear
AH1-715 Linden 138kV & 230kV New Jersey Active Public Service Electric and Gas Company 803.17 127.17 149.369 Generation Interconnection Natural Gas
AH1-716 Surry-Skiffes Creek 500kV Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 650.0 650.0 650.0 Generation Interconnection Storage
AH1-718 Nelson 345 kV Illinois Active Commonwealth Edison Company 391.0 11.0 38.0 Generation Interconnection Natural Gas
AH1-719 Beverly 345 kV Ohio Active AEP Ohio Transmission Company, Inc. 694.0 24.0 21.0 Generation Interconnection Natural Gas
AH1-721 Laurel-Cooper 161 kV Kentucky Active East Kentucky Power Cooperative, Inc. 786.0 786.0 758.9507 Generation Interconnection Natural Gas
AH1-722 Linden 230kV New Jersey Active Public Service Electric and Gas Company 806.4 130.4 158.1 Generation Interconnection Natural Gas
AH1-723 Cunningham 500 kV Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 776.0 776.0 712.0 Generation Interconnection Natural Gas; Other
AH1-725 Conastone 500 kV Maryland Active Baltimore Gas and Electric Company 500.0 500.0 500.0 Generation Interconnection Storage
AH1-727 Brambleton-Goose Creek 500kV Virginia Active Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) 425.0 425.0 425.0 Generation Interconnection Storage
AH1-734 South Bend 500 kV Pennsylvania Active Keystone Appalachian Transmission Company 1058.4 270.3 268.6 Generation Interconnection Natural Gas
AH1-744 Cheltenham 500 kV Maryland Active Potomac Electric Power Company 853.5 53.5 48.285 Generation Interconnection Natural Gas N/A
AH1-746 Madera - Westover South 115 kV Pennsylvania Active Mid-Atlantic Interstate Transmission, LLC 109.9 0.0 20.0 Generation Interconnection Wind N/A

Stability Clusters

Stability analysis was performed by grouping New Service Requests into clusters based on their electrical proximity in order to increase the efficiency of the stability study process. A single stability study is performed for all New Service Requests in the cluster and any reinforcement costs shall be cost allocated proportionally to all New Service Requests in the cluster.

Cluster Index Cluster Name New Service Requests Status Executive Summary
1 Cluster 1 AH1-712, AH1-723 Analysis Complete - No Issues
2 Cluster 2 AG2-171, AG2-213, AG2-440, AG2-441, AG2-442, AH1-280 Analysis Complete - Issues Found
3 Cluster 3 AG2-151, AG2-198, AG2-566, AG2-583, AH1-170, AH1-439, AH1-546 Analysis Complete - No Issues
4 Cluster 4 AG2-121, AG2-238, AG2-382, AH1-040, AH1-271 Analysis Complete - No Issues
5 Cluster 5 AG2-426 Analysis Complete - No Issues
7 Cluster 7 AG2-262, AG2-341, AG2-522, AG2-659, AH1-343 Analysis Complete - No Issues
8 Cluster 8 AG2-077, AG2-270, AG2-581, AH1-528 Analysis Complete - No Issues
10 Cluster 10 AH1-716 Analysis Complete - No Issues
11 Cluster 11 AG2-086 Analysis Complete - No Issues
12 Cluster 12 AG2-088, AG2-384, AH1-679 Analysis Complete - No Issues
13 Cluster 13 AG2-661, AH1-216 Analysis Complete - No Issues
15 Cluster 15 AH1-251, AH1-263 Analysis Complete - No Issues
16 Cluster 16 AG2-182, AH1-727 Analysis Complete - No Issues
18 Cluster 18 AG2-068, AG2-069, AG2-369, AG2-570, AG2-571 Analysis Complete - No Issues
19 Cluster 19 AG2-339, AG2-436 Analysis Complete - No Issues
23 Cluster 23 AG2-550, AG2-551, AG2-637 Analysis Complete - No Issues
24 Cluster 24 AG2-152, AG2-272, AG2-518, AH1-098, AH1-144, AH1-145, AH1-269, AH1-314 Analysis Complete - No Issues
25 Cluster 25 AG2-548, AG2-665 Analysis Complete - No Issues
27 Cluster 27 AG2-329, AH1-282 Analysis Complete - No Issues
28 Cluster 28 AG2-191, AG2-519 Analysis Complete - No Issues
29 Cluster 29 AG2-360, AH1-072, AH1-073, AH1-133, AH1-188, AH1-227, AH1-535 Analysis Complete - No Issues
31 Cluster 31 AG2-184, AH1-617 Analysis Complete - No Issues
32 Cluster 32 AG2-082, AG2-568, AG2-657, AH1-580, AH1-686, AH1-704, AH1-719 Analysis Complete - No Issues
33 Cluster 33 AG2-248, AG2-332 Analysis Complete - No Issues
34 Cluster 34 AG2-289, AG2-290, AH1-059 Analysis Complete - No Issues
35 Cluster 35 AH1-392 Analysis Complete - No Issues
36 Cluster 36 AG2-072 Analysis Complete - No Issues
37 Cluster 37 AG2-014, AG2-126, AG2-163, AG2-343, AG2-345, AG2-491, AG2-492, AH1-482 Analysis Complete - No Issues
38 Cluster 38 AG2-245, AH1-302 Analysis Complete - No Issues
39 Cluster 39 AG2-029, AG2-104, AG2-370 Analysis Complete - No Issues
40 Cluster 40 AG2-230, AG2-562, AH1-153, AH1-272 Analysis Complete - No Issues
41 Cluster 41 AH1-461 Analysis Complete - No Issues
43 Cluster 43 AH1-680 Analysis Complete - No Issues
44 Cluster 44 AG2-236, AG2-621, AH1-699, AH1-706 Analysis Complete - No Issues
45 Cluster 45 AG2-119, AH1-542 Analysis Complete - No Issues
48 Cluster 48 AH1-711 Analysis Complete - No Issues
49 Cluster 49 AG2-057, AH1-060 Analysis Complete - No Issues
50 Cluster 50 AG2-109 Analysis Complete - No Issues
53 Cluster 53 AH1-338 Analysis Complete - No Issues
54 Cluster 54 AG2-660, AG2-675, AH1-044, AH1-150, AH1-151, AH1-718 Analysis Complete - No Issues
55 Cluster 55 AG2-585 Analysis Complete - No Issues
56 Cluster 56 AG2-114, AH1-541 Analysis Complete - No Issues
57 Cluster 57 AG2-453, AG2-524, AH1-165, AH1-563, AH1-673, AH1-698, AH1-714 Analysis Complete - No Issues
58 Cluster 58 AG2-061, AG2-363, AG2-364, AH1-543 Analysis Complete - No Issues
59 Cluster 59 AH1-567 Analysis Complete - No Issues
60 Cluster 60 AG2-516, AH1-341, AH1-564 Analysis Complete - No Issues
61 Cluster 61 AH1-702 Analysis Complete - No Issues
62 Cluster 62 AG2-544, AG2-545, AH1-196 Analysis Complete - No Issues
64 Cluster 64 AG2-062, AG2-448, AH1-206, AH1-247, AH1-248, AH1-249 Analysis Complete - No Issues
66 Cluster 66 AG2-300, AH1-254, AH1-283, AH1-387 Analysis Complete - No Issues
67 Cluster 67 AG2-288, AG2-423 Analysis Complete - No Issues
70 Cluster 70 AG2-429 Analysis Complete - No Issues
71 Cluster 71 AH1-545 Analysis Complete - No Issues
72 Cluster 72 AH1-734 Analysis Complete - No Issues
73 Cluster 73 AG2-582 Analysis Complete - No Issues
74 Cluster 74 AG2-073, AG2-081, AH1-004, AH1-570, AH1-571, AH1-664, AH1-665, AH1-666 Analysis Complete - No Issues
76 Cluster 76 AH1-239 Analysis Complete - Issues Found
77 Cluster 77 AG2-298 Analysis Complete - No Issues
79 Cluster 79 AG2-424, AH1-721 Analysis Complete - No Issues
81 Cluster 81 AG2-074, AG2-479, AG2-481, AG2-484 Analysis Complete - No Issues
82 Cluster 82 AG2-176, AG2-411, AH1-460 Analysis Complete - No Issues
84 Cluster 84 AG2-356 Not Required
85 Cluster 85 AG2-125 Analysis Complete - No Issues
86 Cluster 86 AG2-380, AG2-447, AH1-672 Analysis Complete - No Issues
87 Cluster 87 AG2-297, AG2-616, AH1-260, AH1-641, AH1-701 Analysis Complete - No Issues
89 Cluster 89 AH1-695 Analysis Complete - No Issues
90 Cluster 90 AG2-617, AH1-261, AH1-725 Analysis Complete - No Issues
91 Cluster 91 AG2-618, AH1-552, AH1-744 Analysis Complete - No Issues
93 Cluster 93 AH1-703, AH1-710, AH1-715, AH1-722 Analysis Complete - No Issues
95 Cluster 95 AG2-106 Analysis Complete - No Issues
96 Cluster 96 AG2-107 Analysis Complete - No Issues
97 Cluster 97 AH1-306 Analysis Complete - No Issues
92 Cluster 92 AH1-055, AH1-537 Analysis Complete - No Issues

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 2 Cluster 01 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 1 projects.

 

Table 1: Transition Cycle 2 Cluster 1 Projects

 

 

 

 

 

 

 

 

Cluster

Project

Fuel Type

Trans. Owner

MFO (MW)

MWE

(MW)

MWC

(MW)

Point of Interconnection

1

AH1-712

Natural Gas

Dominion

776

776

611

Cunningham 500 kV

AH1-723

Natural Gas

Dominion

776

776

712

Cunningham 500 kV

 

The purpose of the transient stability analysis is to determine the system impact of the generation facility. This study will determine system improvements, if any, needed to reduce violations in the transient stability analysis caused by the addition of the projects in Cluster 1.

 

The load flow scenario for the analysis was based on the Regional Transmission Expansion Plan (RTEP) 2028 light load case, modified to include applicable projects. The Cluster 1 generators study generator(s) and the electrically close generators of the study generators were set to schedule their terminal voltage to 0.95 p.u. allowing the units Qgen to get as close to 50% of Qmin as possible while enforcing the lower limit for terminal voltages for the light load dispatch criteria.

 

The following settings were adjusted to flatstart the study case and perform dynamic simulations.  The generator owners should provide their preferred adjustment for the issues described in the summary of results.

  • AH1-712:
    • GGOV1:
      • Vmax: set to 1.001 p.u. instead of 1.00 p.u.
      • Trate: set to 470.5 MW instead of 470.0 MW.
  • AH1-723:
    • GGOV1:
      • Vmax: set to 1.001 p.u. instead of 1.00 p.u.
      • Trate: set to 470.5 MW instead of 470.0 MW.

 

Cluster 01 projects were tested for compliance with NERC, PJM, Dominion Energy and other applicable criteria. 193 contingencies were studied, each with a 20 second simulation time period. The contingencies studied included:

 

  • Steady-state operation (30 seconds)
  • Three-phase faults with normal clearing time
  • Single-phase bus faults with normal clearing time
  • Single-phase faults with stuck breaker
  • Single-phase faults with loss of multiple-circuit tower line.

 

For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

The results of the analysis were evaluated against the following recovery criteria per PJM’s Regional Transmission Planning Process and Dominion Energy’s transmission planning criteria:

 

  • Cluster 01 projects were able to ride through the faults (except for faults where protective action trips a generator(s)).
  • The system with Cluster 1 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3%.
  • Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus) and the final voltages are within the steady-state voltage ranges below per Dominion Energy’s transmission planning criteria.
    • P1 Category Contingencies:
      • 0.93 to 1.05 p.u. for 230, 115, 69 kV facilities
      • 0.93 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.01 to 1.096 p.u. for 500 kV facilities
    • P2, P4, P5, and P7 Category Contingencies:
      • 0.90 to 1.05 p.u. for 230, 115, 69 kV facilities
      • 0.90 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.00 to 1.096 p.u. for 500 kV facilities
  • No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

No mitigation was required.

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 2 Cluster 02 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 02 projects.

 

Table 1: Transition Cycle 2 Cluster 02 Projects

 

 

 

 

 

 

 

 

Cluster

Project

Fuel Type

Transmission Owner

MFO

(MW)

MWE

(MW)

MWC

(MW)

Point of Interconnection

02

AG2-171

PV

Dominion

60

60

36

Lunenburg – Nutbush 115 kV

AG2-213

PV

Dominion

80

80

48

Gary D.P. Tap and Gary D.P. 115 kV

AG2-440

PV

Dominion

75

100

45

Twittys Creek - Madisonville 115 kV

AG2-441

PV

Dominion

113

125

67.8

Twittys Creek - Madisonville 115 kV

AG2-442

PV

Dominion

140

140

84

Twittys Creek - Madisonville 115 kV

AH1-280

PV

Dominion

20

20

12

Jetersville - Ponton 115 kV

 

The purpose of the transient stability analysis is to determine the system impact of the generation facility. This study will determine system improvements, if any, needed to reduce violations in the transient stability analysis caused by the addition of the projects in Cluster 02.

 

The load flow scenario for the analysis was based on the Regional Transmission Expansion Plan (RTEP) 2028 summer peak case, modified to include applicable projects. Cluster 02 projects have been dispatched online at maximum power output with near unity power factor measured at the high-side of the main substation transformer.

 

Cluster 02 projects were tested for compliance with NERC, PJM, Dominion Energy and other applicable criteria. 242 contingencies were studied, each with a 20 second simulation time period. The contingencies studied included:

 

  • Steady-state operation (30 seconds)
  • Three-phase faults with normal clearing time
  • Single-phase bus faults with normal clearing time
  • Single-phase faults with stuck breaker
  • Single-phase faults placed at 80% of the line with delayed clearing at remote line end because of primary communications/relaying failure.
  • Single-phase faults with loss of multiple-circuit tower line.

 

For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

The results of the analysis were evaluated against the following recovery criteria per PJM’s Regional Transmission Planning Process and Dominion Energy’s transmission planning criteria:

 

  • Cluster 02 projects were able to ride through the faults (except for faults where protective action trips a generator(s)).
  • The system with Cluster 02 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3%.
  • Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus) and the final voltages are within the steady-state voltage ranges below per Dominion Energy’s transmission planning criteria.
    • P1 Category Contingencies:
      • 0.93 to 1.05 p.u. for 230, 115, 69 kV facilities
      • 0.93 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.01 to 1.096 p.u. for 500 kV facilities
    • P2, P4, P5, and P7 Category Contingencies:
      • 0.90 to 1.05 p.u. for 230, 115, 69 kV facilities
      • 0.90 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.00 to 1.096 p.u. for 500 kV facilities
  • No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

Instability and divergence were observed for contingencies when the Chase City to AG1-285 Tap 115 kV, AG1-285 – Twitty’s Creek 115 kV and Twitty’s Creek – AF2-222 115 kV circuits were tripped. This outage resulted in instability due to insufficient export paths for the generation along the Farmville to Chase City 115 kV path through the radial connection.  Additionally, the Farmville to Chase City 115 kV path is prone to controller instability due to weak grid conditions determined by the composite short circuit ratio assessment. The instability was caused by the Cluster 02 queue projects.   

 

To mitigate this issue the TO proposed the following upgrades that are tested in the Sensitivity Analysis in Section 8:

 

  • Include N9630, proposed during TC1 to resolve the instability caused by the outage of the Chase City – AG1-285 115 kV circuit.  The upgrades adds a new AG1-285 230 kV substation to a breaker and a half scheme to accommodate 2 x 230/115 kV AG1-285 transformers, and a 230 kV line from AG1-285 to Finneywood. 
  • Construct a new 17.68 mi 230 kV line from AG1-285 to AG2-440.  New line to be constructed on single circuit monopoles. Expand the AG2-440 substation to add a new 230 kV yard and two (2) new 224 MVA 230/115 kV transformers. Expand AG1-285 230 kV substation to add a new breaker and tie in a new 230 kV line to AG2-440.

 

One-line diagram were created  for the network upgrade for AG2-440 and AG1-285 substations, which should be reviewed by the TO for constructability. AG2-440’s expanded one-line diagram was based off the AG1-285 one-line the TO proposed for N9630. PJM provided and idv titled ”TC2_PH2_AG2-440_230-115_SUM.idv” to model the upgrade.

 

The AB2-060 queue projects model was replaced with the latest As built model allowing the unit to be ungnetted.  This uncovered controller freezing for P2 and P4 contingencies that tripped the Chase City – Butchers Creek 115 kV line. The issue was determined to be caused by AG2-213 REECA Vdip Con (J) set to 0.9 p.u.. This was updated to 0.8 p.u. to align with the REPCA Vfrz Con (J+5) value resolving the freezing eliminating and allowing all contingencies to meet the recovery criteria.

 

AD2-033 tripped for voltage higher than 1.4 p.u. for more than 0.001 seconds. protection pickup time was increased from 0.001 sec to 0.0167 sec.

Note: PJM will contact the project developer to verify the model tuning recommendation for non TC2 Cycle project.

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 2 Cluster 3 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 3 projects.

 

Table 1: Transition Cycle 2 Cluster 3 Projects

 

 

 

 

 

 

 

 

Cluster

Project

Fuel Type

Trans. Owner

MFO (MW)

MWE

(MW)

MWC

(MW)

Point of Interconnection

3

AG2-151

PV

Dominion

100

100

60

Trices Lake - James River Tap 115 kV

AG2-198

PV

Dominion

80

80

48

Briery - Finneywood 230 kV

AG2-566

BS

Dominion

30

30

12

Briery - Finneywood 230 kV

AG2-583

PV

Dominion

115

115

69

Bremo - Cartersville 230 kV

AH1-170

PV

Dominion

20

20

12

Columbia DP 115 kV

AH1-439

PV

Dominion

85

85

51

Buckingham - Farmville 230 kV

AH1-546

PV

Dominion

65

65

39

Bremo - Buckingham 230 kV

 

The purpose of the transient stability analysis is to determine the system impact of the generation facility. This study will determine system improvements, if any, needed to reduce violations in the transient stability analysis caused by the addition of the projects in Cluster 3.

 

The load flow scenario for the analysis was based on the Regional Transmission Expansion Plan (RTEP) 2028 summer peak case, modified to include applicable projects. The TC2 Cluster 3 projects have been dispatched online at maximum power output with near unity power factor measured at the high-side of the main substation transformer.

 

Cluster 3 projects were tested for compliance with NERC, PJM, Dominion Energy and other applicable criteria. 264 contingencies were studied, each with a 20 second simulation time period. The contingencies studied included:

 

  • Steady-state operation (30 seconds)
  • Three-phase faults with normal clearing time
  • Single-phase bus faults with normal clearing time
  • Single-phase faults with stuck breaker
  • Single-phase faults placed at 80% of the line with delayed clearing at remote line end because of primary communications/relaying failure
  • Single-phase faults with loss of multiple-circuit tower line

 

For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

The results of the analysis were evaluated against the following recovery criteria per PJM’s Regional Transmission Planning Process and Dominion Energy’s transmission planning criteria:

 

  • Cluster 3 projects were able to ride through the faults (except for faults where protective action trips a generator(s)).
  • The system with Cluster 3 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3%.
  • Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus) and the final voltages are within the steady-state voltage ranges below per Dominion Energy’s transmission planning criteria.
    • P1 Category Contingencies:
      • 0.93 to 1.05 p.u. for 230, 115, 69 kV facilities
      • 0.93 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.01 to 1.096 p.u. for 500 kV facilities
    • P2, P4, P5, and P7 Category Contingencies:
      • 0.90 to 1.05 p.u. for 230, 115, 69 kV facilities
      • 0.90 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.00 to 1.096 p.u. for 500 kV facilities
  • No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

 

AH1-546: Main Power Transformer High side to Tertiary impedance from Next Gen data (0.0033 + j0.141) does not match PSSE case (0.0033 + j0.0002). Main Power Transformer Low side to Tertiary impedance from Next Gen data (0.0033 + j0.0288) does not match PSSE case (0.0033 + j0.141). Case was set up using the PSSE case provided during DP1 Round 2 data. The IC should review the impedance and align the sav case and Next Gen data in the DP2 submittal.

 

No mitigation is required.

 

The following settings were adjusted in order to meet the evaluation criteria. The generator owners should provide their preferred adjustment for the issues described in the summary of results.

 

AG2-566 Results

No voltage-reactive droop setting was identified for AG2-566; implementation of a 4% voltage reactive droop is recommended to coordinate voltage and reactive power control with nearby generating facilities.

 

AG2-583 Results

No voltage-reactive droop setting was identified for AG2-583; implementation of a 4% voltage reactive droop is recommended to coordinate voltage and reactive power control with nearby generating facilities.

 

AH1-170 Results

AH1-170 experienced numerical convergency issues post fault for certain contingencies. Updating the REPCA RefFlag from 0 to 1 prevented any convergency issues for the generator.

 

Voltage-reactive droop setting was identified for AH1-170; implementation of a 4% voltage reactive droop is recommended to coordinate voltage and reactive power control with nearby generating facilities.

 

AH1-546 Results

No voltage-reactive droop setting was identified for AH1-546; implementation of a 4% voltage reactive droop is recommended to coordinate voltage and reactive power control with nearby generating facilities.

 

AE2-092 Results

No voltage-reactive droop setting was identified for AE2-092; Updating the REPCA VCFlag from 1 to 0 is recommended to coordinate voltage and reactive power control with nearby generating facilities.

 

Note: PJM will contact the project developer to verify the model tuning recommendation for non TC2 Cycle project.

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 2 Cluster 04 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 04 projects.

 

Table 1: Transition Cycle 2 Cluster 04 Projects

 

 

 

 

 

 

 

 

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

04

AH1-040

Solar

Dominion

150

150

90

Mackeys – Creswell 115 kV

AG2-121

Battery

Dominion

140

0

0

Mackeys 230 kV

AG2-382

Solar

Dominion

70

70

42

Cashie 230 kV

AH1-271

Solar

Dominion

40

40

24

Cashie 230 kV

AG2-238

Battery

Dominion

99.9

0

0

Earleys 230 kV

 

The purpose of the transient stability analysis is to determine the system impact of the generation facility. This study will determine system improvements, if any, needed to reduce violations in the transient stability analysis caused by the addition of the projects in TC2 Cluster 04.

 

The load flow scenario for the analysis was based on the Regional Transmission Expansion Plan (RTEP) 2028 summer peak case, modified to include applicable projects. TC2 Cluster 04 Projects have been dispatched online at maximum power output with near unity power factor measured at the high-side of the main substation transformer.

 

TC2 Cluster 04 projects were tested for compliance with NERC, PJM, Dominion Energy and other applicable criteria. 155 contingencies were studied, each with a 20 second simulation time period except for steady-state operation. The contingencies studied included:

 

  • Steady-state operation (30 second simulation)
  • Three-phase faults with normal clearing time
  • Single-phase bus faults with normal clearing time
  • Single-phase faults with a stuck breaker
  • Single-phase faults placed at 80% of the line with delayed clearing at remote line end because of primary communications/relaying failure
  • Single-phase faults with loss of multiple circuit tower

 

For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

The results of the analysis were evaluated against the following recovery criteria per PJM’s Regional Transmission Planning Process and Dominion Energy’s transmission planning criteria

The results of the analysis were evaluated against the following recovery criteria per PJM’s Regional Transmission Planning Process and Transmission Owner criteria:

 

  • TC2 Cluster 04 projects were able to ride through the faults (except for faults where protective action trips a generator(s)).
  • The system with Cluster 04 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
  • Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus) and the final voltages are within the steady-state voltage ranges below per Dominion Energy’s transmission planning criteria.
    • P1 Category Contingencies:
      • 0.93 to 1.05 p.u. for 230, 115, 69 kV facilities
      • 0.93 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.01 to 1.096 p.u. for 500 kV facilities
    • P2, P4, P5, and P7 Category Contingencies:
      • 0.90 to 1.05 p.u. for 230, 115, 69 kV facilities
      • 0.90 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.00 to 1.096 p.u. for 500 kV facilities
  • No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

No mitigation is required to connect projects in TC2 Cluster 04

 

Week grid assessment was performed for this cluster.  Composite short circuit ratio from the week grid assessment was calculated as <3. EMT analysis is recommended for the cluster.

Facility modification and model tuning is recommended. The generator owner should provide their preferred adjustments for the issues described in the summary of results:

  • AF2-110
    • Increase relay pick-up time from 0.0120 to 0.0376 seconds for the protection model tripping for voltage above 1.20 p.u. to avoid generator tripping.
  • AD2-085
    • Increase relay pick-up time from 0.017 to 0.0292 seconds for the protection model tripping for voltage above 1.20 p.u. to avoid generator tripping.
  • AE2-253
    • Increase relay pick-up time from 0.01 to 0.0167 seconds for the protection model tripping for voltage above 1.20 p.u. to avoid generator tripping.
  • AD1-022
    • AD1-022 was observed to have its reactive power not settle. Although no criteria violations occurred, the study recommends enabling voltage droop control for AD1-022 to coordinate with other generating facilities

 

Note: PJM will contact the project developer to verify the model tuning recommendation for non TC2 Cycle project.

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 2 (TC2) Cluster 5 are listed in Table 1 below. This report will cover the dynamic analysis of TC2 Cluster 5 projects.

 

Table 1: Transition Cycle 2 Cluster 5 Projects

 

 

 

 

 

 

 

 

Cluster

Project

Fuel Type

Trans. Owner

MFO (MW)

MWE

(MW)

MWC

(MW)

Point of Interconnection

5

AG2-426

Solar & Battery

Dominion

33.5

33.5

33.5

Waverly – Wakefield 115 kV

 

The purpose of the transient stability analysis is to determine the system impact of the generation facility. This study will determine system improvements, if any, needed to reduce violations in the transient stability analysis caused by the addition of the projects in TC2 Cluster 5.

 

The load flow scenario for the analysis was based on the Regional Transmission Expansion Plan (RTEP) 2028 summer peak case, modified to include applicable projects. TC2 Cluster 5 projects have been dispatched online at maximum power output with near unity power factor measured at the high-side of the main substation transformer.

 

TC2 Cluster 5 projects were tested for compliance with NERC, PJM, Dominion Energy and other applicable criteria. 191 contingencies were studied, each with a 20 second simulation time period except for steady-state operation. The contingencies studied included:

 

  • Steady-state operation (30 second simulation)
  • Three-phase faults with normal clearing time
  • Single-phase bus faults with normal clearing time
  • Single-phase faults with a stuck breaker
  • Single-phase faults placed at 80% of the line with delayed clearing at remote line end because of primary communications/relaying failure
  • Single-phase faults with loss of multiple circuit tower

 

For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

The results of the analysis were evaluated against the following recovery criteria per PJM’s Regional Transmission Planning Process and Dominion Energy’s transmission planning criteria:

  • TC2 Cluster 5 projects were able to ride through the faults (except for faults where protective action trips a generator(s)).
  • The system with TC2 Cluster 5 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3%.
  • Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus) and the final voltages are within the steady-state voltage ranges below per Dominion Energy’s transmission planning criteria.
    • P1 Category Contingencies:
      • 0.93 to 1.05 p.u. for 230, 115, 69 kV facilities
      • 0.93 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.01 to 1.096 p.u. for 500 kV facilities
    • P2, P4, P5, and P7 Category Contingencies:
      • 0.90 to 1.05 p.u. for 230, 115, 69 kV facilities
      • 0.90 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.00 to 1.096 p.u. for 500 kV facilitie
  • No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

Weak Grid Assessment results indicate weak grid concerns of CSCR of 1.862 when outaging Pump House/AE1-149 POI – Poe 115 kV. An EMT study is recommended for TC2 Cluster 5.

 

No mitigation is required to connect projects in TC2 Cluster 5.

 

Facility modification and model tuning is recommended. The generator owner should provide their preferred adjustments for the issues described in the summary of results:

 

  • AC2-079 was slow to control voltage at the POI and voltages above 1.05 p.u. were observed. The following updates were made to fix the issue:
    • REPCA1 decreased reactive power PI control proportional gain, Kp, from 6.0 to 1.0 p.u.
    • REPCA1 increased Reactive power PI control integral gain, Ki from 0.01 to 5.0 p.u.
  • AD2-085/AE2-247 reactive power was observed to not settle. Also tripped due to voltage protection. The following updates were made:
    • REECA1 increased high voltage threshold for reactive current injection, Vup, from 1.10 to 1.15 p.u.
    • REPCA1 increased reactive power PI control proportional gain, Kp, from 0.00 to 0.50 p.u.
    • VTGTPAT increased relay pick-up time from 0.017 to 0.0376 seconds for the protection model tripping for voltage above 1.20 p.u. to avoid generator tripping
  • AF1-017 reactive power was observed to not settle. Also tripped due to voltage protection. The following updates were made:
    • REGCA1 increased upper/lower limit on rate of change for reactive current, Iqrmax/Iqrmin, from +/- 0.02 to +/- 10 p.u.
    • REECA1 increased high voltage threshold for reactive current injection, Vup, from 1.10 to 1.15 p.u.
    • REPCA1 increased reactive power PI control proportional gain, Kp, from 0.00 to 0.50 p.u.
    • VTGTPAT increased relay pick-up time from 0.001 to 0.0459 seconds for the protection model tripping for voltage above 1.20 p.u. to avoid generator tripping.
  • AF2-110 tripped due to voltage protection. The following updates were made:
    • VTGTPAT increased relay pick-up time from 0.0120 to 0.0334 seconds for the protection model tripping for voltage above 1.20 p.u. to avoid generator tripping.

 

Note: PJM will contact the project developer to verify the model tuning recommendation for non TC2 Cycle project.

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 2 (TC2) Cluster 7 are listed in Table 1 below. This report will cover the dynamic analysis of TC2 Cluster 7 projects.

 

Table 1: Transition Cycle 2 Cluster 7 Projects

 

 

 

 

 

 

 

 

Cluster

Project

Fuel Type

Trans. Owner

MFO (MW)

MWE

(MW)

MWC

(MW)

Point of Interconnection

7

AG2-262

Solar

Dominion

47

11

6.6

Dryburg 115 kV

AG2-341

Battery

Dominion

50

50

20

Ridge Road 115 kV

AG2-522

Solar

Dominion

80

80

48

Five Forks DP – Littleton DP 115 kV

AG2-659

Solar

Dominion

80

80

48

Kerr Dam – Hawtree 115 kV

AH1-343

Solar

Dominion

69

69

41.4

Crystal Hill DP – Perth 115 kV

 

The purpose of the transient stability analysis is to determine the system impact of the generation facility. This study will determine system improvements, if any, needed to reduce violations in the transient stability analysis caused by the addition of the projects in TC2 Cluster 7.

 

The load flow scenario for the analysis was based on the Regional Transmission Expansion Plan (RTEP) 2028 summer peak case, modified to include applicable projects. TC2 Cluster 7 projects have been dispatched online at maximum power output with near unity power factor measured at the high-side of the main substation transformer.

 

TC2 Cluster 7 projects were tested for compliance with NERC, PJM, Dominion Energy and other applicable criteria. 411 contingencies were studied, each with a 20 second simulation time period except for steady-state operation. The contingencies studied included:

 

  • Steady-state operation (30 second simulation)
  • Three-phase faults with normal clearing time
  • Single-phase bus faults with normal clearing time
  • Single-phase faults with a stuck breaker
  • Single-phase faults placed at 80% of the line with delayed clearing at remote line end because of primary communications/relaying failure
  • Single-phase faults with loss of multiple circuit tower

 

For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

The results of the analysis were evaluated against the following recovery criteria per PJM’s Regional Transmission Planning Process and Dominion Energy’s transmission planning criteria:

 

  • TC2 Cluster 7 projects were able to ride through the faults (except for faults where protective action trips a generator(s)).
  • The system with TC2 Cluster 7 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3%.
  • Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus) and the final voltages are within the steady-state voltage ranges below per Dominion Energy’s transmission planning criteria.
    • P1 Category Contingencies:
      • 0.93 to 1.05 p.u. for 230, 115, 69 kV facilities
      • 0.93 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.01 to 1.096 p.u. for 500 kV facilities
    • P2, P4, P5, and P7 Category Contingencies:
      • 0.90 to 1.05 p.u. for 230, 115, 69 kV facilities
      • 0.90 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.00 to 1.096 p.u. for 500 kV facilities
  • No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

No mitigation is required to connect projects in TC2 Cluster 7.

 

Facility modification and model tuning is recommended. The generator owner should provide their preferred adjustments for the issues described in the summary of results:

  • AH1-343
    • AH1-343 was observed to not settle with reactive power for some contingencies. The response was improved by updating REPCA model to include 4% reactive power droop by setting VC Flag (ICON M+4) to 0 and Kc (CON J+8) to 0.04 p.u.. 
  • AB2-043
    • AB2-043 was observed to not settle with reactive power for some contingencies. The response was improved by updating REPCA Kc (CON J+8) to 0.04 to enable a 4% reactive power droop.
  • AD2-033
    • Increase relay pick-up time from 0.001 to 0.0126 seconds for the protection model tripping for voltage above 1.40 p.u. to avoid generator tripping.
  • AC1-054
    • Increase relay pick-up time from 0.2 to 0.2292 seconds for the protection model tripping for voltage above 1.25 p.u. to avoid generator tripping.
  • AC1-222
    • Increase relay pick-up time from 0 to 0.1584 seconds for the protection model tripping for frequencies above 61.8 hz to avoid generator tripping.
    • Increase relay pick-up time from 0 to 0.1709 seconds for the protection model tripping for frequencies below 57.8 hz to avoid generator tripping.
  • AC1-080
    • Increase relay pick-up time from 0.09 to 0.1501 seconds for the protection model tripping for frequencies above 63.25 hz to avoid generator tripping.
    • Increase relay pick-up time from 0.016 to 0.0834 seconds for the protection model tripping for frequencies below 57 hz to avoid generator tripping.

 

Note: PJM will contact the project developer to verify the model tuning recommendation for non TC2 Cycle project.

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 2 (TC2) Cluster 8 are listed in Table 1 below. This report will cover the dynamic analysis of TC2 Cluster 8 projects.

 

Table 1: Transition Cycle 2 Cluster 8 Projects

 

 

 

 

 

 

 

 

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

08

AG2-077

Solar

Dominion

200

200

120

Clover – Finneywood 500 kV

AG2-270

Battery

Dominion

150

150

105

Clover 230 kV

AG2-581

Solar

Dominion

150

150

90

Rawlings – Unity 500 kV

AH1-528

Solar

Dominion

300.8

300.8

180

Rawlings – Unity 500 kV

 

 

The purpose of the transient stability analysis is to determine the system impact of the generation facility. This study will determine system improvements, if any, needed to reduce violations in the transient stability analysis caused by the addition of the projects in TC2 Cluster 8.

 

The load flow scenario for the analysis was based on the Regional Transmission Expansion Plan (RTEP) 2028 summer peak case, modified to include applicable projects. TC2 Cluster 8 projects have been dispatched online at maximum power output with near unity power factor measured at the high-side of the main substation transformer.

 

TC2 Cluster 8 projects were tested for compliance with NERC, PJM, Dominion Energy and other applicable criteria. 241 contingencies were studied, each with a 20 second simulation time period except for steady-state operation. The contingencies studied included:

 

  • Steady-state operation (30 second simulation)
  • Three-phase faults with normal clearing time
  • Single-phase bus faults with normal clearing time
  • Single-phase faults with a stuck breaker
  • Single-phase faults placed at 80% of the line with delayed clearing at remote line end because of primary communications/relaying failure
  • Single-phase faults with loss of multiple circuit tower

 

For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

The results of the analysis were evaluated against the following recovery criteria per PJM’s Regional Transmission Planning Process and Dominion Energy’s transmission planning criteria:

 

  • TC2 Cluster 8 projects were able to ride through the faults (except for faults where protective action trips a generator(s)).
  • The system with TC2 Cluster 8 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3%.
  • Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus) and the final voltages are within the steady-state voltage ranges below per Dominion Energy’s transmission planning criteria.
    • P1 Category Contingencies:
      • 0.93 to 1.05 p.u. for 230, 115, 69 kV facilities
      • 0.93 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.01 to 1.096 p.u. for 500 kV facilities
    • P2, P4, P5, and P7 Category Contingencies:
      • 0.90 to 1.05 p.u. for 230, 115, 69 kV facilities
      • 0.90 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.00 to 1.096 p.u. for 500 kV facilities
  • No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

Weak Grid Assessment results indicate weak grid concerns of CSCR of 2.8676 when outaging AH1-528 POI to Rawlings 500 kV.

 

No mitigation is required to connect projects in TC2 Cluster 8.

 

Facility modification and model tuning is recommended. The generator owner should provide their preferred adjustments for the issues described in the summary of results:

 

  • AG2-077 & AF2-042
    • No voltage-reactive droop setting was identified for AG2-077 & AF2-042; implementation of a 4% voltage-reactive droop is recommended to coordinate voltage and reactive power control with nearby generating facilities.
  • AG2-581
    • No voltage-reactive droop setting was identified for AG2-581; implementation of a 4% voltage-reactive droop is recommended to coordinate voltage and reactive power control with nearby generating facilities.
  • AH1-528
    • Voltage-reactive droop setting was identified for AH1-528, but it was set to 1% voltage-reactive droop; implementation of a 4% voltage-reactive droop is recommended to coordinate voltage and reactive power control with nearby generating facilities.
  • AF2-110
    • Increase relay pick-up time from 0.0120 to 0.0334 seconds for the protection model tripping for voltage above 1.20 p.u. to avoid generator tripping.
  • AD2-085
    • Increase relay pick-up time from 0.017 to 0.0376 seconds for the protection model tripping for voltage above 1.20 p.u. to avoid generator tripping.

 

Note: PJM will contact the project developer to verify the model tuning recommendation for non TC2 Cycle project.

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 2 Cluster 10 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 10 projects.

 

Table 1: Transition Cycle 2 Cluster 10 Projects

 

 

 

 

 

 

 

 

Cluster

Project

Fuel Type

Trans. Owner

MFO (MW)

MWE

(MW)

MWC

(MW)

Point of Interconnection

10

AH1-716

Battery

Dominion

650

650

650

Surry – Skiffes Creek 500 kV

 

The purpose of the transient stability analysis is to determine the system impact of the generation facility. This study will determine system improvements, if any, needed to reduce violations in the transient stability analysis caused by the addition of the projects in Cluster 10.

 

The load flow scenario for the analysis was based on the Regional Transmission Expansion Plan (RTEP) 2028 summer peak case, modified to include applicable projects. Cluster 10 projects have been dispatched online at maximum power output with near unity power factor measured at the high-side of the main substation transformer.

 

Cluster 10 projects were tested for compliance with NERC, PJM, Dominion Energy and other applicable criteria. 99 contingencies were studied, each with a 20 second simulation time period. The contingencies studied included:

 

  • Steady-state operation (30 seconds)
  • Three-phase faults with normal clearing time
  • Single-phase bus faults with normal clearing time
  • Single-phase faults with stuck breaker
  • Single-phase faults with loss of multiple-circuit tower line.

 

For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

The results of the analysis were evaluated against the following recovery criteria per PJM’s Regional Transmission Planning Process and Dominion Energy’s transmission planning criteria:

 

  • Cluster 10 projects were able to ride through the faults (except for faults where protective action trips a generator(s)).
  • The system with Cluster 10 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3%.
  • Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus) and the final voltages are within the steady-state voltage ranges below per Dominion Energy’s transmission planning criteria.
    • P1 Category Contingencies:
      • 0.93 to 1.05 p.u. for 230, 115, 69 kV facilities
      • 0.93 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.01 to 1.096 p.u. for 500 kV facilities
    • P2, P4, P5, and P7 Category Contingencies:
      • 0.90 to 1.05 p.u. for 230, 115, 69 kV facilities
      • 0.90 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.00 to 1.096 p.u. for 500 kV facilities
  • No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

No migration was required.

 

The following settings were adjusted to meet the evaluation criteria.  The generator owners should provide their preferred adjustment for the issues described in the summary of results.

 

  • AH1-716:
    • REECA:
      • Vup: set to 1.15 p.u. instead of 1.1 p.u.
  • AF2-013:
    • REPCA:
      • Kp: set to 1 instead of 0
      • Kc: set to 0.04 instead of 0
      • Kpg: set to 1 instead of 0
      • Ddn: set to 25 instead of 0.04
      • Dup: set to 25 instead of 0.04
  • AF2-110: 1.2 p.u. protection pickup time was increased from 0.012 sec to 0.029 sec
  • AD2-085: 1.2 p.u. protection pickup time was increased from 0.017 sec to 0.029 sec
  • AC1-161: 1.4 p.u. protection pickup time was increased from 0 sec to 0.0126 sec. Note the latest as built model was used to ungnet both AC1-161 and AC2-141 queue projects which share a common POI. Both projects are undergoing the PJMs model quality review process. AC2-141’s as built model included a 210 MW MFO instead of the previous 240 MW MFO which was utilized as the modeling submittal considered the 210 MW MFO.

 

Note: PJM will contact the project developer to verify the model tuning recommendation for non TC2 Cycle project.

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 2 (TC2) Cluster 11 are listed in Table 1 below. This report will cover the dynamic analysis of TC2 Cluster 11 projects.

 

Table 1: Transition Cycle 2 Cluster 11 Projects

 

 

 

 

 

 

 

 

Cluster

Project

Fuel Type

Trans. Owner

MFO (MW)

MWE

(MW)

MWC

(MW)

Point of Interconnection

11

AG2-086

Solar and Storage

Dominion

75

75

45

Mt Jackson DP to Mt Jackson 115 KV

 

The purpose of the transient stability analysis is to determine the system impact of the generation facility. This study will determine system improvements, if any, needed to reduce violations in the transient stability analysis caused by the addition of the projects in TC2 Cluster 11.

 

The load flow scenario for the analysis was based on the Regional Transmission Expansion Plan (RTEP) 2028 summer peak case, modified to include applicable projects. TC2 Cluster 11 projects have been dispatched online at maximum power output with near unity power factor measured at the high-side of the main substation transformer.

 

TC2 Cluster 11 projects were tested for compliance with NERC, PJM, Dominion Energy and other applicable criteria. Total contingencies studied are 78, each with a 20 second simulation time period except for steady-state operation. The contingencies studied included:

 

  • Steady-state operation (30 second simulation)
  • Three-phase faults with normal clearing time
  • Single-phase bus faults with normal clearing time
  • Single-phase faults with a stuck breaker
  • Single-phase faults placed at 80% of the line with delayed clearing at remote line end because of primary communications/relaying failure
  • Single-phase faults with loss of multiple circuit tower

 

For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

The results of the analysis were evaluated against the following recovery criteria per PJM’s Regional Transmission Planning Process and Dominion Energy’s transmission planning criteria:

 

  • TC2 Cluster 11 projects were able to ride through the faults (except for faults where protective action trips a generator(s)).
  • The system with TC2 Cluster 11 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3%.
  • Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus) and the final voltages are within the steady-state voltage ranges below per Dominion Energy’s transmission planning criteria.
    • P1 Category Contingencies:
      • 0.93 to 1.05 p.u. for 230, 115, 69 kV facilities
      • 0.93 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.01 to 1.096 p.u. for 500 kV facilities
    • P2, P4, P5, and P7 Category Contingencies:
      • 0.90 to 1.05 p.u. for 230, 115, 69 kV facilities
      • 0.90 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.00 to 1.096 p.u. for 500 kV facilities
  • No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

No mitigation is required to connect projects in TC2 Cluster 11.

 

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 2 (TC2) Cluster 12 are listed in Table 1 below. This report will cover the dynamic analysis of TC2 Cluster 12 projects.

 

Table 1: Transition Cycle 2 Cluster 12 Projects

 

 

 

 

 

 

 

 

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

12

AG2-088

Battery

Dominion

150

150

150

Midlothian 230 kV Substation

AG2-384

Battery

Dominion

60

60

24

Chesterfield ‘A’ 230 kV Substation

AH1-679

Natural Gas

Dominion

766

766

716

Four Rivers 230 kV Substation

 

The purpose of the transient stability analysis is to determine the system impact of the generation facility. This study will determine system improvements, if any, needed to reduce violations in the transient stability analysis caused by the addition of the projects in TC2 Cluster 12.

 

The load flow scenario for the analysis was based on the Regional Transmission Expansion Plan (RTEP) 2028 summer peak and Light Load cases, modified to include applicable projects. TC2 Cluster 12 projects have been dispatched online at maximum real power output. The reactive power output for TC2 Cluster 12 projects was set to have near unity power factor measured at the high-side of the main substation transformer for the Summer Peak case. For the Light Load case, Dominion Energy’s Light Load Criteria was used to dispatch the TC2 Cluster 12 projects to near 50% of their minimum reactive limits. The Light Load Criteria could not be implemented for AH1-679 due to system constraints.

 

TC2 Cluster 12 projects were tested for compliance with NERC, PJM, Dominion Energy and other applicable criteria. 739 contingencies were studied, each with a 20 second simulation time period. The contingencies studied included:

 

  • No-fault steady-state operation
  • Three-phase faults with normal clearing time
  • Single-phase bus faults with normal clearing time
  • Single-phase faults with a stuck breaker
  • Single-phase faults placed at 80% of the line with delayed clearing at remote line end because of primary communications/relaying failure
  • Single-phase faults with loss of multiple circuit tower

 

For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

The results of the analysis were evaluated against the following recovery criteria per PJM’s Regional Transmission Planning Process and Dominion Energy’s transmission planning criteria:

 

  • TC2 Cluster 12 projects can ride through the faults (except for faults where protective action trips a generator(s)).
  • The system with TC2 Cluster 12 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3%.
  • Following fault clearing, all bus voltages recover to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus) and the final voltages are within the steady-state voltage ranges below per Dominion Energy’s transmission planning criteria.
    • P1 Category Contingencies:
      • 0.93 to 1.05 p.u. for 230, 115, 69 kV facilities
      • 0.93 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.01 to 1.096 p.u. for 500 kV facilities
    • P2, P4, P5, and P7 Category Contingencies:
      • 0.90 to 1.05 p.u. for 230, 115, 69 kV facilities
      • 0.90 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.00 to 1.096 p.u. for 500 kV facilities
  • No transmission element should trip, other than those either directly connected or designed to trip as a consequence of that fault.

 

TC2 Cluster 12 projects met the above criteria with some facility modifications incorporated; these modifications are provided below. No mitigation is required to connect the TC2 Cluster 12 projects.

 

Facility modification and model tuning is recommended. The generator owner should provide their preferred adjustments for the issues described in the summary of results:

  • AG2-088
    • Plant tripped for the voltage protection model 1.1 p.u. at 2 seconds while the inverter was attempting to regulate grid voltage. Please increase the tripping time to a reasonably high number considering equipment limitations.
    • Plant reactive output appears to not settle within the 20 second simulation for some fault scenarios. A 4% voltage-reactive droop setting along with a +/- 0.001 p.u. deadband is recommended to enable the plant to settle quicker.
  • AG2-384
    • The main transformer high side tap had to be adjusted to 1.025 p.u. in order to pass the power factor requirements. It is requested that future data submittals include this tap adjustment.
  • AG2-583
    • Plant reactive output appears to not settle within the 20 second simulation for some fault scenarios. A 4% voltage-reactive droop setting is recommended to enable the plant to settle quicker.
  • AD1-151/AG2-661
    • Plant controllers froze and tripped for a P5 fault scenario. It is recommended that the AD1-151 REECA1 Vup parameter be adjusted from 1.15 p.u. to 1.20 p.u. and the AG2-661 REECC1 Vup parameter be adjusted from 1.12 p.u. to 1.20 p.u. These adjustments enable the units to ride through the specific fault scenario.
    • Within the PLNTBU1 model, Kp, Ki should be reduced from 2, 50 to 0.5, 3.0, respectively. A 4% voltage-reactive droop setting is recommended to help the plant coordinate voltage regulation with other sources.
  • AF2-110
    • Plant tripped for the voltage protection model 1.2 p.u. at 0.001 seconds. Please increase the tripping time to a reasonably high number considering equipment limitations.
  • AE2-247
    • Plant tripped for the voltage protection model 1.2 p.u. at 0.017 seconds. Please increase the tripping time to a reasonably high number considering equipment limitations.
  • AE1-157
    • Plant tripped for the frequency protection model 61.8 Hz at 0.0 seconds. Please increase the tripping time to a reasonably high number considering equipment limitations.
  • AD2-074
    • Plant tripped for the frequency protection model 61.7 Hz at 0.001 seconds. Please increase the tripping time to a reasonably high number considering equipment limitations.
    • Plant tripped for the voltage protection model 1.2 p.u. at 0.001 seconds. Please increase the tripping time to a reasonably high number considering equipment limitations.
    • Plant controllers froze and tripped for a few fault scenarios. It is recommended that the REGCAU1 Iqrmax/Iqrmin values should be increased from +/- 0.02 p.u. to +/- 999 p.u. These adjustments enable the units to ride through the specific fault scenarios.
  • AD1-105
    • Plant tripped for the voltage protection model 1.2 p.u. at 0.001 seconds. Please increase the tripping time to a reasonably high number considering equipment limitations.
    • Plant tripped for the voltage protection model 1.175 p.u. at 0.2 seconds. Please increase the tripping time to a reasonably high number considering equipment limitations.
    • Plant tripped for the frequency protection model 61.7 Hz at 0.001 seconds. Please increase the tripping time to a reasonably high number considering equipment limitations.
    • Plant controllers froze and tripped for a few fault scenarios. It is recommended that the REECBU1 Vdip parameter be adjusted from 0.8 p.u. to 0.88 p.u. and the REPCA voltage reactive parameters Kp, Ki, Vfrz be adjusted from 0.01, 25, 0.7 to 4, 6, 0.88, respectively. These adjustments enable the unit to ride through the specific fault scenarios.
  • AD1-025
    • Plant reactive output appears to not settle within the 20 second simulation for some fault scenarios. A 4% voltage-reactive droop setting is recommended to enable the plant to settle quicker.
  • AC2-165
    • Plant tripped for the frequency protection model 61.8 Hz at 0.0 seconds. Please increase the tripping time to a reasonably high number considering equipment limitations.
    • Plant tripped for the frequency protection model 57.8 Hz at 0.0 seconds. Please increase the tripping time to a reasonably high number considering equipment limitations.
  • AC1-158
    • Plant tripped for the voltage protection model 1.31 p.u. at 0.014 seconds. Please increase the tripping time to a reasonably high number considering equipment limitations.

 

Note:

  • PJM will contact the project developer to verify the model tuning recommendation for non-TC2 Cycle project.
  • TO has requested additional fault to be tested at Ladysmith CT substation, which will be evaluated during Phase 3 of the analysis.

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 2 (TC2) Cluster 13 are listed in Table 1 below. This report will cover the dynamic analysis of TC2 Cluster 13 projects.

 

Table 1: Transition Cycle 2 Cluster 13 Projects

 

 

 

 

 

 

 

 

Cluster

Project

Fuel Type

Trans. Owner

MFO (MW)

MWE

(MW)

MWC

(MW)

Point of Interconnection

13

AG2-661

Battery

Dominion

150

0

20

Colonial Trail – Hopewell 230 kV

AH1-216

Solar and Battery

Dominion

99

99

79.2

Smithfield – Surry 230 kV

 

The purpose of the transient stability analysis is to determine the system impact of the generation facility. This study will determine system improvements, if any, needed to reduce violations in the transient stability analysis caused by the addition of the projects in TC2 Cluster 13.

 

The load flow scenario for the analysis was based on the Regional Transmission Expansion Plan (RTEP) 2028 summer peak case, modified to include applicable projects. TC2 Cluster 13 projects have been dispatched online at maximum power output with near unity power factor measured at the high-side of the main substation transformer.

 

TC2 Cluster 13 projects were tested for compliance with NERC, PJM, Dominion Energy and other applicable criteria. 287 contingencies were studied, each with a 20 second simulation time period except for steady-state operation. The contingencies studied included:

 

  • Steady-state operation (30 second simulation)
  • Three-phase faults with normal clearing time
  • Single-phase bus faults with normal clearing time
  • Single-phase faults with a stuck breaker
  • Single-phase faults placed at 80% of the line with delayed clearing at remote line end because of primary communications/relaying failure
  • Single-phase faults with loss of multiple circuit tower

 

For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

The results of the analysis were evaluated against the following recovery criteria per PJM’s Regional Transmission Planning Process and Dominion Energy’s transmission planning criteria:

 

  • TC2 Cluster 13 projects were able to ride through the faults (except for faults where protective action trips a generator(s)).
  • The system with TC2 Cluster 13 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3%.
  • Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus) and the final voltages are within the steady-state voltage ranges below per Dominion Energy’s transmission planning criteria.
    • P1 Category Contingencies:
      • 0.93 to 1.05 p.u. for 230, 115, 69 kV facilities
      • 0.93 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.01 to 1.096 p.u. for 500 kV facilities
    • P2, P4, P5, and P7 Category Contingencies:
      • 0.90 to 1.05 p.u. for 230, 115, 69 kV facilities
      • 0.90 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.00 to 1.096 p.u. for 500 kV facilities
  • No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

No mitigation is required to connect projects in TC2 Cluster 13 .

 

Facility modification and model tuning is recommended. The generator owner should provide their preferred adjustments for the issues described in the summary of results:

  • AF2-110
    • Increase relay pick-up time from 0.0120 to 0.0209 seconds for the protection model tripping for voltage above 1.20 p.u. to avoid generator tripping.
  • AG2-661
    • Set inverter step-up transformer tap to 1.025 p.u. (35.3625 kV) to provide more reactive power without exceeding voltages above 1.10 p.u.
    • No voltage-reactive droop setting was identified for AG2-661; implementation of a 4% voltage-reactive droop is recommended to coordinate voltage and reactive power control with nearby generating facilities.
  • AH1-216
    • Set inverter step-up transformer tap to 1.025 p.u. (35.3625 kV) to provide more reactive power without exceeding voltages above 1.10 p.u.
    • No voltage-reactive droop setting was identified for AH1-216; implementation of a 4% voltage-reactive droop is recommended to coordinate voltage and reactive power control with nearby generating facilities.
    • Controller oscillations were present during the fault and absent after fault clearing for AH1-216. The study recommends tuning the model to reduce controller oscillations during the fault.

 

Note: PJM will contact the project developer to verify the model tuning recommendation for non-TC2 Cycle project.

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 2 Cluster 15 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 15 projects.

 

Table 1: Transition Cycle 2 Cluster 15 Projects

 

 

 

 

 

 

 

 

Cluster

Project

Fuel Type

Transmission Owner

MFO (MW)

MWE (MW)

MWC (MW)

Point of Interconnection

15

AH1-251

Storage

Dominion

50

50

50

Todds Tavern – Spotsylvania 115 kV line

AH1-263

Storage

Dominion

200

200

200

Chancellor 115 kV substation

 

The purpose of the transient stability analysis is to determine the system impact of the generation facility. This study will determine system improvements, if any, needed to reduce violations in the transient stability analysis caused by the addition of the projects in Cluster 15.

 

The load flow scenario for the analysis was based on the Regional Transmission Expansion Plan (RTEP) 2028 summer peak case, modified to include applicable projects. Cluster 15 projects have been dispatched online at maximum power output with near unity power factor measured at the high-side of the main substation transformer.

 

Cluster 15 projects were tested for compliance with NERC, PJM, Dominion Energy and other applicable criteria. 83 contingencies were studied, each with a 20 second simulation time period. The contingencies studied included:

 

  • Steady-state operation (30 seconds)
  • Three-phase faults with normal clearing time
  • Single-phase bus faults with normal clearing time
  • Single-phase faults with stuck breaker
  • Single-phase faults placed at 80% of the line with delayed clearing at remote line end because of primary communications/relaying failure
  • Single-phase faults with loss of multiple-circuit tower line.

 

For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

The results of the analysis were evaluated against the following recovery criteria per PJM’s Regional Transmission Planning Process and Dominion Energy’s transmission planning criteria:

 

  • Cluster 15 projects were able to ride through the faults (except for faults where protective action trips a generator(s)).
  • The system with Cluster 15 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3%.
  • Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus) and the final voltages are within the steady-state voltage ranges below per Dominion Energy’s transmission planning criteria.
    • P1 Category Contingencies:
      • 0.93 to 1.05 p.u. for 230, 115, 69 kV facilities
      • 0.93 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.01 to 1.096 p.u. for 500 kV facilities
    • P2, P4, P5, and P7 Category Contingencies:
      • 0.90 to 1.05 p.u. for 230, 115, 69 kV facilities
      • 0.90 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.00 to 1.096 p.u. for 500 kV facilities
  • No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

No mitigation is required to connect projects in TC2 Cluster 15.

 

Note: AC1-158 generator tripped for over voltages above 1.31 p.u. The unit rode through when the pickup timer increased from 0.014 seconds to 0.017 seconds. Generation facility owner will need to verify ride through capability.

 

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 2 (TC2) Cluster 16 are listed in Table 1 below. This report will cover the dynamic analysis of TC2 Cluster 16 projects.

 

Table 1: Transition Cycle 2 Cluster 16 Projects

 

 

 

 

 

 

 

 

Cluster

Project

Fuel Type

Trans. Owner

MFO (MW)

MWE

(MW)

MWC

(MW)

Point of Interconnection

16

AG2-182

Solar

Dominion

200

200

133.3

Doubs-Bismark 500 kV

AH1-727

Storage

Dominion

425

425

425

Brambleton-Goose Creek 500kV

 

The purpose of the transient stability analysis is to determine the system impact of the generation facility. This study will determine system improvements, if any, needed to reduce violations in the transient stability analysis caused by the addition of the projects in TC2 Cluster 16.

 

The load flow scenario for the analysis was based on the Regional Transmission Expansion Plan (RTEP) 2028 summer peak case, modified to include applicable projects. TC2 Cluster 16 projects have been dispatched online at maximum power output with near unity power factor measured at the high-side of the main substation transformer.

 

TC2 Cluster 16 projects were tested for compliance with NERC, PJM, Dominion Energy and other applicable criteria. 349 contingencies were studied, each with a 20 second simulation time period except for steady-state operation. The contingencies studied included:

 

  • Steady-state operation (30 second simulation)
  • Three-phase faults with normal clearing time
  • Single-phase bus faults with normal clearing time
  • Single-phase faults with a stuck breaker
  • Single-phase faults with loss of multiple circuit tower

 

For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

The results of the analysis were evaluated against the following recovery criteria per PJM’s Regional Transmission Planning Process and Dominion Energy’s transmission planning criteria:

 

  • TC2 Cluster 16 projects were able to ride through the faults (except for faults where protective action trips a generator(s)).
  • The system with TC2 Cluster 16 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3%.
  • Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus) and the final voltages are within the steady-state voltage ranges below per Dominion Energy’s transmission planning criteria.
    • P1 Category Contingencies:
      • 0.93 to 1.05 p.u. for 230, 115, 69 kV facilities
      • 0.93 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.01 to 1.096 p.u. for 500 kV facilities
    • P2, P4, P5, and P7 Category Contingencies:
      • 0.90 to 1.05 p.u. for 230, 115, 69 kV facilities
      • 0.90 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.00 to 1.096 p.u. for 500 kV facilities
  • No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

No mitigation is required to connect projects in TC2 Cluster 16

 

Facility modification and model tuning is recommended. The generator owner should provide their preferred adjustments for the issues described in the summary of results:

 

  • AH1-725
    • The following updates are recommended to prevent overvoltage tripping from inverter freezing
      • REECC1, increased high voltage threshold for reactive current injection, Vup, from 1.10 to 1.15 p.u.
  • AG2-182
    • The following updates are recommended for reactive power to settle and resolve inverter freezing:
      • REECA1, increased high voltage threshold for reactive current injection, Vup, from 1.10 to 1.15 p.u.
      • REPCA1, increased reactive power PI control proportional gain, Kp, from 0.10 to 0.30 p.u and reactive power PI control integral gain, Ki from 0.50 to 3.0 p.u.
  • AH1-727
    • The following updates are recommended to resolve inverter freezing and overvoltage tripping
      • REECC1, increased high voltage threshold for reactive current injection, Vup, from 1.10 to 1.15 p.u.
  • AG2-582
    • A nearby generator was observed to exhibit some post-fault movements in angle and power following fault clearance for certain contingencies; however, these movements do not propagate to other generators or buses in the cluster area and therefore do not indicate a criteria violation. The applied dynamic model may require further tuning by the developer as part of plant design.

 

Note: PJM will contact the project developer to verify the model tuning recommendation for non -TC2 Cycle project.

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 2 (TC2) Cluster 18 are listed in Table 1 below. This report will cover the dynamic analysis of TC2 Cluster 18 projects.

 

Table 1: Transition Cycle 2 Cluster 18 Projects

 

 

 

 

 

 

 

 

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

 

18

 

AG2-068

Solar

Dominion

100

100

60

Heritage - Wake 500 kV

AG2-069

Solar

Dominion

250

150

90

Heritage - Wake 500 kV

AG2-369

Solar

Dominion

86

86

51.6

Heritage - Wake 500 kV

AG2-570

Solar

Dominion

400

400

100

Heritage - Wake 500 kV

AG2-571

Battery

Dominion

500

100

40

Heritage - Wake 500 kV

 

The purpose of the transient stability analysis is to determine the system impact of the generation facility. This study will determine system improvements, if any, needed to reduce violations in the transient stability analysis caused by the addition of the projects in TC2 Cluster 18.

 

The queue projects being analyzed in Cluster 18 located on an area intertie between Dominion Energy (Heritage 500 kV) and Duke Energy’s (Wake 500 kV). Contingencies examined for TC2 Cluster 18 focused on Dominion Energy equipment. Duke Energy’s is an affected system for TC2 Cluster 18, and an analysis should be performed to ensure the evaluation criteria are met for contingencies in Duke Energy’s system.

 

The load flow scenario for the analysis was based on the Regional Transmission Expansion Plan (RTEP) 2028 summer peak case, modified to include applicable projects. TC2 Cluster 18 projects have been dispatched online at maximum power output with near unity power factor measured at the high-side of the main substation transformer.

 

TC2 Cluster 18 projects were tested for compliance with NERC, PJM, Dominion Energy and other applicable criteria. 146 contingencies were studied, each with a 20 second simulation time period. The contingencies studied included:

 

  • Steady-state operation (30 seconds)
  • Three-phase faults with normal clearing time
  • Single-phase bus faults with normal clearing time
  • Single-phase faults with stuck breaker
  • Single-phase faults with loss of multiple-circuit tower line.

 

No P5 contingencies for Dominion 500 kV due to redundant relays.

 

For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

The results of the analysis were evaluated against the following recovery criteria per PJM’s Regional Transmission Planning Process and Dominion Energy’s transmission planning criteria:

 

  • TC2 Cluster 18 projects were able to ride through the faults (except for faults where protective action trips a generator(s)).
  • The system with TC2 Cluster 18 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3%.
  • Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus) and the final voltages are within the steady-state voltage ranges below per Dominion Energy’s transmission planning criteria.
    • P1 Category Contingencies:
      • 0.93 to 1.05 p.u. for 230, 115, 69 kV facilities
      • 0.93 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.01 to 1.096 p.u. for 500 kV facilities
    • P2, P4, P5, and P7 Category Contingencies:
      • 0.90 to 1.05 p.u. for 230, 115, 69 kV facilities
      • 0.90 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.00 to 1.096 p.u. for 500 kV facilities
  • No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

No mitigation is required to connect projects in TC2 Cluster 18.

 

Facility modification and model tuning is recommended. The generator owner should provide their preferred adjustments for the issues described in the summary of results:

  • AF2-110
    • Increase relay pick-up time from 0.0120 to 0.03 seconds for the protection model tripping for voltage above 1.20 p.u. to avoid generator tripping.
  • AE2-247
    • Increase relay pick-up time from 0.0120 to 0.03 seconds for the protection model tripping for voltage above 1.20 p.u. to avoid generator tripping.
  • AG2-068 and AG2-069
    • No voltage-reactive droop setting was identified for AG2-068 and AG2-069; implementation of a 4% voltage-reactive droop is recommended to coordinate voltage and reactive power control with nearby generating facilities.

 

Note: PJM will contact the project developer to verify the model tuning recommendation for non -TC2 Cycle project.

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 2 (TC2) Cluster 19 are listed in Table 1 below. This report will cover the dynamic analysis of TC2 Cluster 19 projects.

 

Table 1: Transition Cycle 2 Cluster 19 Projects

 

 

 

 

 

 

 

 

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

19

AG2-339

Battery

Dominion

394

85

85

Rogers Road – Carson 500 kV

AG2-436

Solar

Dominion

350

350

140

Rogers Road - Carson 500 kV

 

The purpose of the transient stability analysis is to determine the system impact of the generation facility. This study will determine system improvements, if any, needed to reduce violations in the transient stability analysis caused by the addition of the projects in TC2 Cluster 19.

 

The load flow scenario for the analysis was based on the Regional Transmission Expansion Plan (RTEP) 2028 summer peak case, modified to include applicable projects. TC2 Cluster 19 projects have been dispatched online at maximum power output with near unity power factor measured at the high-side of the main substation transformer.

 

TC2 Cluster 19 projects were tested for compliance with NERC, PJM, Dominion Energy and other applicable criteria. 146 contingencies were studied, each with a 20 second simulation time period. The contingencies studied included:

  • Steady-state operation (30 seconds)
  • Three-phase faults with normal clearing time
  • Single-phase bus faults with normal clearing time
  • Single-phase faults with stuck breaker
  • Single-phase faults with loss of multiple-circuit tower line.

 

No P5 contingencies for Dominion 500 kV due to redundant relays.

 

For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

The results of the analysis were evaluated against the following recovery criteria per PJM’s Regional Transmission Planning Process and Dominion Energy’s transmission planning criteria:

 

  • TC2 Cluster 19 projects were able to ride through the faults (except for faults where protective action trips a generator(s)).
  • The system with TC2 Cluster 19 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3%.
  • Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus) and the final voltages are within the steady-state voltage ranges below per Dominion Energy’s transmission planning criteria.
    • P1 Category Contingencies:
      • 0.93 to 1.05 p.u. for 230, 115, 69 kV facilities
      • 0.93 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.01 to 1.096 p.u. for 500 kV facilities
    • P2, P4, P5, and P7 Category Contingencies:
      • 0.90 to 1.05 p.u. for 230, 115, 69 kV facilities
      • 0.90 to 1.03 p.u. for 138 kV facilities due to legacy switches
      • 1.00 to 1.096 p.u. for 500 kV facilities
  • No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

 

No mitigation is required to connect projects in TC2 Cluster 19.

 

Facility modification and model tuning is recommended. The generator owner should provide their preferred adjustments for the issues described in the summary of results:

 

  • AF2-110
    • Increase relay pick-up time from 0.0120 to 0.03 seconds for the protection model tripping for voltage above 1.20 p.u. to avoid generator tripping.
  • AE2-247
    • Increase relay pick-up time from 0.0120 to 0.03 seconds for the protection model tripping for voltage above 1.20 p.u. to avoid generator tripping.
  • AG2-068 and AG2-069
    • No voltage-reactive droop setting was identified for AG2-068 and AG2-069; implementation of a 4% voltage-reactive droop is recommended to coordinate voltage and reactive power control with nearby generating facilities.

 

Note: PJM will contact the project developer to verify the model tuning recommendation for non -TC2 Cycle project.

Executive Summary for Stability Cluster

Executive Summary

 

New Service Requests AG2-550, AG2-551 and AG2-637 in PJM Transition Cycle 2, Cluster 23 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 23 projects.

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 23 projects will meet the dynamics requirements of the NERC, AEP and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2028 Summer Peak, modified to include applicable projects. Cluster 23 projects have been dispatched online at maximum power output, with 1.0 voltage at the terminal bus.

 

Transition Cycle 2 Cluster 23 will be tested for compliance with NERC, PJM and other applicable criteria. The contingencies will be studied with a 20 second simulation time. Contingencies to be studied include:

       a)       Steady-state operation (Category P0);

       b)       Three-phase faults with normal clearing time (and with unsuccessful high-speed reclosing) (Category P1);

       c)       Single-phase bus faults with normal clearing time (Category P2);

       d)       Single-phase faults with stuck breaker (Category P4);

       e)       Single-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure (Category P5);

       f)       Three-phase faults with loss of multiple-circuit tower line; (and with unsuccessful high-speed reclosing) (Category P7).

 

High Speed Reclosing (HSR) facilities were found in the vicinity of TC2 Cluster 23 projects.

 

Prior outage scenarios will not be considered for this study.

 

For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all the fault contingencies tested on the 2028 peak load case:

       a)       Cluster 23 projects were able to ride through the faults (except for faults where protective action trips a generator(s)).

       b)       The system with Cluster 23 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.

       c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d)       No transmission element tripped, other than those either directly connected or designed to trip because of that fault.

 

Fictitious frequency response at high-side of the shared MPT of AG2-550 and AG2-551 tripped the two queue projects due to the action of under-frequency relays in P1.05 and over-frequency relays in P1.06. Therefore, the frequency relay pickup times in the corresponding relay instances (i.e., 97088303 and 97088503 for P1.05 and 97088301 and 97088501 for P1.06) were set to 20 seconds to avoid fictitious frequency tripping of the unit. The system was found to be stable afterwards.

 

Fictitious frequency response at AG1-017 generator bus tripped the project due to the action of under-frequency/over-frequency relay during P1.26-P1.31 and P1.33-P1.34. Therefore, the frequency relay pickup time in the corresponding relay instance (i.e., 93359413) was set to 20 seconds to avoid fictitious frequency tripping of the unit. The system was found to be stable afterwards.

 

In P1.26 and P1.31, it was observed that AG1-047 generator bus trip because of the high voltage spikes following fault clearance. It is known that voltage spikes are a modeling limitation of WECC generic renewable models . Consequently, the pickup timer of corresponding relay instance (i.e., 96203404) has been increased to 2 cycles, and no further stability issue was observed.

 

In P4.24, AE2-219 terminal voltage experiences an overvoltage post-fault and reaches around 1.08 pu. The overvoltage at the generator terminal did not cause any instability issue.

 

The IPCMD and IQCMD states in the REGCA1 models of AG2-550 showed erratic behavior for some contingencies in which AG2-550 has been disconnected as part of the contingency event. Since the machines are disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

 

The IPCMD and IQCMD states in the REGCA1 models of AG2-551 showed erratic behavior for some contingencies in which AG2-551 has been disconnected as part of the contingency event. Since the machines are disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

 

The IPCMD and IQCMD states in the REGCA1 models of AG2-637 showed erratic behavior for some contingencies in which AG2-637 has been disconnected as part of the contingency event. Since the machines are disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

 

No mitigations were found to be required.

 

 

Table 1: Transition Cycle 2 Cluster 23 Projects

 

 

 

 

Project

Fuel Type

Transmission Owner

MFO (MW)

Point of Interconnection

AG2-550

Solar

AEP

100

Randolph - Bluff Point 138 kV

AG2-551

Battery

AEP

50

Randolph - Bluff Point 138 kV

AG2-637

Solar

AEP

150

Randolph - Hayes 138 kV

 

 

Executive Summary for Stability Cluster

Executive Summary

 

New Service Requests AG2-152, AG2-272, AG2-518, AH1-098, AH1-144, AH1-145, AH1-269 and AH1-314 in PJM Transition Cycle 2, Cluster 24 are listed in Table 1. below. This report will cover the dynamic analysis of Cluster 24 projects.

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 24 projects will meet the dynamics requirements of the NERC, AEP and PJM reliability standards.

 

Cluster 24 projects were dispatched for stability analysis according to the following scenarios:

       a)       Scenario 1: AH1-098 dispatched at full MFO injection at the POI with PV MW contribution maxed out and no/reduced MW contribution from BESS.

       b)       Scenario 2: AH1-098 dispatched at full MFO injection at the POI with BESS MW contribution maxed out, and no/reduced PV MW injection.

       c)       Scenario 3: AH1-098 dispatched at full MFO injection at the POI with PV and BESS MW contribution proportional to their capacity.

       d)       Scenario 4: AH1-098 dispatched to full capacity with PV and BESS MW injection maxed out.

 

This report describes a dynamic simulation analysis of TC2 Cluster 24 for dispatch Scenario 3 as part of the overall system impact study.

 

The load flow scenario for the analysis was based on the RTEP 2028 Summer Peak, modified to include applicable projects. Cluster 24 projects have been dispatched online at maximum power output, with 1.01 pu voltage at the terminal bus.

 

Transition Cycle 2 Cluster 24 will be tested for compliance with NERC, PJM and other applicable criteria. The contingencies will be studied with a 20 second simulation time. Contingencies to be studied include:

       a)       Steady-state operation (Category P0);

       b)       Three-phase faults with normal clearing time (and with unsuccessful high-speed reclosing) (Category P1);

       c)       Single-phase bus faults with normal clearing time (Category P2);

       d)       Single-phase faults with stuck breaker (Category P4);

       e)       Single-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure (Category P5);

       f)       Three-phase faults with loss of multiple-circuit tower line; (and with unsuccessful high-speed reclosing) (Category P7).

 

High Speed Reclosing (HSR) facilities were found in the vicinity of TC2 Cluster 24 projects.

 

Prior outage scenarios will not be considered for this study.

 

For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all the fault contingencies tested on the 2028 peak load case:

       a)       Cluster 24 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

       b)       The system with Cluster 24 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.

       c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d)       No transmission element tripped, other than those either directly connected or designed to trip because of that fault.

 

The IPCMD and IQCMD states in the REGCA1 models of all units of Cluster 24 showed erratic behavior for some contingencies in which queue project has been disconnected as part of the contingency event. Since the machines are disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

 

Tripping was observed for several contingencies (P4.081, P4.082, P5.39, and P5.48) under the initial study conditions. Upon updating the fault impedance values based on Aspen short circuit case, the tripping issues were resolved, and the system remained stable for these contingencies.

 

AH1-098 both Solar and BESS units tripped under several contingencies. Upon updating Vdip to 0.8 (Original value was 0.9) and Vup to 1.2 (Original value was 1.1) for both units resolved all tripping issue.

 

Fictitious frequency response at AH1-145 generator bus tripped the queue project for several contingencies (P1.073, P1.075 and P1.076). Therefore, the frequency relay pickup times for were set to 20 seconds to avoid fictitious frequency tripping of the unit.

 

AG2-272 generating units exhibited slow reactive power recovery within the 20 second simulation window for several contingencies. This issue did not cause instability in the system. The reactive power droop compensation was enabled and tuned by updating Kc to 0.15 (original value was 0) which resolved the slow reactive power response.

 

AH1-269 generating units exhibited slow reactive power recovery within the 20 second simulation window for several contingencies. This issue did not cause instability in the system. The reactive power droop compensation was enabled and tuned by updating Kc to 0.1 (original value was 0) which resolved the slow reactive power response.

 

AH1-314 generating units exhibited slow reactive power recovery within the 20 second simulation window for several contingencies. This issue did not cause instability in the system. The reactive power droop compensation was enabled and tuned by updating Kc to 0.1 (original value was 0) which resolved the slow reactive power response.

 

The active power for AG2-152 did not recover to the pre fault value for contingency P7.21 due inadequate reactive power response. The reactive power droop compensation gain Kc parameter was updated to 0.1 which resolved the active power recovery issue.

 

Smith Mountain generators showed positively damped oscillations which did not settle during the 20 second simulation window. The selected contingencies were run for 30 seconds, and the oscillatory signals achieved a flat response at the end of the 30 second simulation time period.

 

No mitigations were found to be required.

 

Table 1: Transition Cycle 2 Cluster 24 Queues

Table 1: Transition Cycle 2 Cluster 24 Projects

 

 

 

 

Project

Fuel Type

Transmission Owner

MFO (MW)

Point of Interconnection

AG2-152

Solar

AEP

131

Banister – Bearskin 138 kV

AG2-272

Battery

AEP

55

Berry Hill substation 138 kV

AG2-518

Battery

AEP

80

Tech Drive substation 138 kV

AH1-098

Solar/Battery

AEP

40

West Carroll – Wolf Glade 138 kV

AH1-144

Solar

AEP

70

Peter’s Mountain Substation 138 kV

AH1-145

Battery

AEP

80

Peter’s Mountain Substation 138 kV

AH1-269

Battery

AEP

50

Claytor substation 138 kV

AH1-314

Battery

AEP

100

East Danville substation 138 kV

 

 

Executive Summary for Stability Cluster

Executive Summary

 

New Service Requests AG2-548 and AG2-665 in PJM Transition Cycle 2, Cluster 25 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 25 projects.

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 25 projects will meet the dynamics requirements of the NERC, AEP and PJM reliability standards.

 

Cluster 25 projects were dispatched for stability analysis according to the following scenarios:

       a)       Scenario 1: AG2-548 and AG2-665 dispatched at full MFO injection at the POI with PV MW contribution maxed out and no/reduced MW contribution from BESS.

       b)       Scenario 2: AG2-548 and AG2-665 dispatched at full MFO injection at the POI with BESS MW contribution maxed out, and no/reduced PV MW injection.

       c)       Scenario 3: AG2-548 and AG2-665 dispatched at full MFO injection at the POI with PV and BESS MW contribution proportional to their capacity.

       d)       Scenario 4: AG2-548 and AG2-665 dispatched to full capacity with PV and BESS MW injection maxed out.

 

This report describes a dynamic simulation analysis of TC2 Cluster 25 for dispatch Scenario 3 as part of the overall system impact study.

 

The load flow scenario for the analysis was based on the RTEP 2028 Summer Peak, modified to include applicable projects. Cluster 25 projects have been dispatched online at maximum power output, with 1.0 pu voltage at the terminal bus.

 

Transition Cycle 2 cluster 25 will be tested for compliance with NERC, PJM and other applicable criteria. The contingencies will be studied with a 20 second simulation time. Contingencies to be studied include:

       a)       Steady-state operation (Category P0);

       b)       Three-phase faults with normal clearing time (and with unsuccessful high-speed reclosing) (Category P1);

       c)       Single-phase bus faults with normal clearing time (Category P2).

       d)       Single-phase faults with stuck breaker (Category P4);

       e)       Single-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure (Category P5).

 

High Speed Reclosing (HSR) facilities were found in the vicinity of TC2 cluster 25 projects.

 

Prior outage scenarios will not be considered for this study.

 

For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all the fault contingencies tested on the 2028 peak load case:

       a)       Cluster 25 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

       b)       The system with Cluster 25 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.

       c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d)       No transmission element tripped, other than those either directly connected or designed to trip because of that fault.

 

The IPCMD and IQCMD states in the REGCA1 models of AG2-548 showed erratic behavior for some contingencies in which AG2-548 has been disconnected as part of the contingency event. Since the machines are disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

 

The IPCMD and IQCMD states in the REGCA1 models of AG2-665 showed erratic behavior for some contingencies in which AG2-665 has been disconnected as part of the contingency event. Since the machines are disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

 

No mitigations were found to be required.

 

Table 1: Transition Cycle 2 Cluster 25 Projects

 

 

 

 

Project

Fuel Type

Transmission Owner

MFO (MW)

Point of Interconnection

AG2-548

Solar/Battery

AEP

80

Corwin – Elk 138 kV

AG2-665

Solar/Battery

AEP

80

Corwin – Elk 138 kV

 

 

Executive Summary for Stability Cluster

Executive Summary

 

New Service Requests AG2-329 and AH1-282 in PJM Transition Cycle 2, Cluster 27 are listed in Error! Reference source not found. below. This report will cover the dynamic analysis of Cluster 27 projects.

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 27 projects will meet the dynamics requirements of the NERC, AEP and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2028 Summer Peak, modified to include applicable projects. Cluster 27 projects have been dispatched online at maximum power output, with 1.0 voltage at the terminal bus.

 

Transition Cycle 2 Cluster 27 will be tested for compliance with NERC, PJM and other applicable criteria. The contingencies will be studied with a 20 second simulation time. Contingencies to be studied include:

       a)       Steady-state operation (Category P0);

       b)       Three-phase faults with normal clearing time (and with unsuccessful high-speed reclosing) (Category P1);

       c)       Single-phase bus faults with normal clearing time (Category P2);

       d)       Single-phase faults with stuck breaker (Category P4);

       e)       Three-phase faults with loss of multiple-circuit tower line; (and with unsuccessful high-speed reclosing) (Category P7).

 

High Speed Reclosing (HSR) facilities were found in the vicinity of TC2 Cluster 27 projects.

 

Prior outage scenarios will not be considered for this study.

 

For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all the fault contingencies tested on the 2028 peak load case:

       a)       Cluster 27 projects were able to ride through the faults (except for faults where protective action trips a generator(s)).

       b)       The system with Cluster 27 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.

       c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d)       No transmission element tripped, other than those either directly connected or designed to trip because of that fault.

 

No mitigations were found to be required.

 

Table 1: Transition Cycle 2 Cluster 27 Projects

 

 

 

 

Project

Fuel Type

Transmission Owner

MFO (MW)

Point of Interconnection

AG2-329

Battery

AEP

200

South Berwick - Galion 345 kV

AH1-282

Solar

AEP

49.9

Galion - Ohio Central 345 kV

 

 

Executive Summary for Stability Cluster

Executive Summary

 

New Service Requests AG2-191 and AG2-519 in PJM Transition Cycle 2, Cluster 28 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 28 projects.

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 28 projects will meet the dynamics requirements of the NERC, AEP and PJM reliability standards.

 

Cluster 28 projects were dispatched for stability analysis according to the following scenarios:

       a)       Scenario 1: AG1-191 and AG2-519 dispatched at full MFO injection at the POI with PV MW contribution maxed out and no/reduced MW contribution from BESS.

       b)       Scenario 2: AG1-191 and AG2-519 dispatched at full MFO injection at the POI with BESS MW contribution maxed out, and no/reduced PV MW injection.

       c)       Scenario 3: AG1-191 and AG2-519 dispatched at full MFO injection at the POI with PV and BESS MW contribution proportional to their capacity.

       d)       Scenario 4: AG1-191 and AG2-519 dispatched to full capacity with PV and BESS MW injection maxed out.

 

This report describes a dynamic simulation analysis of TC2 Cluster 28 for dispatch Scenario 3 as part of the overall system impact study.

 

The load flow scenario for the analysis was based on the RTEP 2028 Summer Peak, modified to include applicable projects. Cluster 28 projects have been dispatched online at maximum power output, with 1.01 p.u. voltage at the terminal bus.

 

Transition Cycle 2 Cluster 28 will be tested for compliance with NERC, PJM and other applicable criteria. The contingencies will be studied with a 20 second simulation time. Contingencies to be studied include:

       a)       Steady-state operation (Category P0);

       b)       Three-phase faults with normal clearing time (and with unsuccessful high-speed reclosing) (Category P1);

       c)       Single-phase bus faults with normal clearing time (Category P2);

       d)       Single-phase faults with stuck breaker (Category P4);

       e)       Single-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure (Category P5).

       f)       Three-phase faults with loss of multiple-circuit tower line; (and with unsuccessful high-speed reclosing) (Category P7).

 

High Speed Reclosing (HSR) facilities were found in the vicinity of TC2 Cluster 28 projects.

 

Prior outage scenarios will not be considered for this study.

 

For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all the fault contingencies tested on the 2028 peak load case:

       a)       Cluster 28 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

       b)       The system with Cluster 28 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.

       c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d)       No transmission element tripped, other than those either directly connected or designed to trip because of that fault.

 

The IPCMD and IQCMD states in the REGCA1 models of AG2-519 showed erratic behavior for some contingencies in which AG2-519 has been disconnected as part of the contingency event. Since the machines are disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

 

The IPCMD and IQCMD states in the REGCA1 models of AG2-191 showed erratic behavior for some contingencies in which AG2-191 has been disconnected as part of the contingency event. Since the machines are disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

 

For several contingencies AE2-297 unit has been disconnected for over voltage relay settings where clearing time was 0.001 second for that relay settings. Added two cycles to original pick up to prevent fictious post-fault overvoltage tripping. It should be noted that generic dynamic models for inverter-based generators tend to produce a short-duration (a cycle or shorter) voltage spike at fault inception or clearing. These spikes can be ignored in most cases as they do not represent the performance of the actual hardware. They are simply a consequence of the model’s limited bandwidth, integration time step, and the way current injection models interface with the network solution.

 

Fictitious frequency response at AH1-306 generator bus tripped the queue project due to    the action of instantaneous under-frequency relay for P1.24 and P1.26 contingencies. Therefore, the relay pickup times for frequency relay instance 97161309 was set to 20 seconds to avoid fictitious frequency tripping of the unit. No mitigations were found to be required.

 

 

Table 1: Transition Cycle 2 Cluster 28 Projects

 

 

 

 

Project

Fuel Type

Transmission Owner

MFO (MW)

Point of Interconnection

AG2-191

Solar/Battery

AEP

30

Mississinewa 138 kV

AG2-519

Solar/Battery

AEP

66.5

Royerton - Desoto 138 kV

 

Executive Summary for Stability Cluster

Executive Summary

 

New Service Requests AG2-360, AH1-072, AH1-073, AH1-133, AH1-188, AH1-227 and AH1-535 in PJM Transition Cycle 2, Cluster 29 are listed in Table 1. below. This report will cover the dynamic analysis of Cluster 29 projects.

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 29 projects will meet the dynamics requirements of the NERC, AEP and PJM reliability standards.

 

Cluster 29 projects were dispatched for stability analysis according to the following scenarios:

       a)       Scenario 1: AH1-535 dispatched at full MFO injection at the POI with PV MW contribution maxed out and no/reduced MW contribution from BESS.

       b)       Scenario 2: AH1-535 dispatched at full MFO injection at the POI with BESS MW contribution maxed out, and no/reduced PV MW injection.

       c)       Scenario 3: AH1-535 dispatched at full MFO injection at the POI with PV and BESS MW contribution proportional to their capacity.

       d)       Scenario 4: AH1-535 dispatched to full capacity with PV and BESS MW injection maxed out.

 

This report describes a dynamic simulation analysis of TC2 Cluster 29 for dispatch Scenario 3 as part of the overall system impact study.

 

The load flow scenario for the analysis was based on the RTEP 2028 Summer Peak, modified to include applicable projects. Cluster 29 projects have been dispatched online at maximum power output, with 1.0 voltage at the terminal bus.

 

Transition Cycle 2 Cluster 29 will be tested for compliance with NERC, PJM and other applicable criteria. The contingencies will be studied with a 20 second simulation time. Contingencies to be studied include:

       a)       Steady-state operation (Category P0);

       b)       Three-phase faults with normal clearing time (and with unsuccessful high-speed reclosing) (Category P1);

       c)       Single-phase bus faults with normal clearing time (Category P2);

       d)       Single-phase faults with stuck breaker (Category P4);

       e)       Single-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure (Category P5);

       f)       Three-phase faults with loss of multiple-circuit tower line; (and with unsuccessful high-speed reclosing) (Category P7).

 

High Speed Reclosing (HSR) facilities were found in the vicinity of TC2 Cluster 29 projects.

 

Prior outage scenarios will not be considered for this study.

 

For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all the fault contingencies tested on the 2028 peak load case:

       a)       Cluster 29 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

       b)       The system with Cluster 29 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.

       c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d)       No transmission element tripped, other than those either directly connected or designed to trip because of that fault.

 

The IPCMD and IQCMD states in the REGCA1 models of all units of Cluster 29 showed erratic behavior for some contingencies in which queue project has been disconnected as part of the contingency event. Since the machines are disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

 

Fictitious frequency response at AH1-227 generator bus tripped the queue project for several contingencies. Therefore, the frequency relay pickup times for instance 97146111 was set to 20 seconds to avoid fictitious frequency tripping of the unit.

 

High voltage spikes occurred in the simulations immediately after fault clearing for some of the contingencies studied which tripped the AC1-101 and AC1-102 units. The voltage spike is a known artifact of the WECC generic renewable models as stated in the WECC Solar Plant Dynamic Model Guidelines: “It should be noted that generic dynamic models for inverter-based generator tend to produce a short-duration (a cycle or shorter) voltage spike at fault inception and clearing. These spikes should be ignored in most cases, as they do not represent the performance of actual hardware. They are simply a consequence of the model’s limited bandwidth, integration time step, and the way current injection models interface with the network solution.”  A single cycle delay was added to the instantaneous over-voltage relays to avoid this fictitious over voltage tripping issue.

 

Similarly, under contingency P5.44, AH1-535 GEN1 tripped due to activation of its overvoltage protection. The issue was resolved by reducing its Vsched to 0.99 pu for this contingency.

 

AH1-227 generating unit exhibited slow active power recovery within the 20 second simulation window for contingency P1.11. This issue did not cause instability in the system,

 

however, the facility’s performance could be improved through model tuning, which can be evaluated in TC2 Phase 3 if active power recovery becomes a critical concern.

 

No mitigations were found to be required.

 

Table 1: Transition Cycle 2 Cluster 29 Projects

 

 

 

 

Project

Fuel Type

Transmission Owner

MFO (MW)

Point of Interconnection

AG2-360

Battery

AEP

250

Broadford substation 138 kV

AH1-072

Solar

AEP

20

Red Onion – VC5 69 kV

AH1-073

Solar

AEP

20

Red Onion – VC5 69 kV

AH1-133

Solar

AEP

70

Saltville – Tazewell 138 kV

AH1-188

Solar

AEP

140

Pigeon Creek substation 138 kV

AH1-227

Solar

AEP

51.3

Flemming - Fremont 69 kV

AH1-535

Solar/Battery

AEP

100

Nagel – Cane River 230 kV

 

 

Executive Summary for Stability Cluster

Executive Summary

 

New Service Requests AG2-184 and AH1-617 in PJM Transition Cycle 2, Cluster 31 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 31 projects.

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 31 projects will meet the dynamics requirements of the NERC, AEP and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2028 Summer Peak, modified to include applicable projects. Cluster 31 projects have been dispatched online at maximum power output, with 1.0 voltage at the terminal bus.

 

Transition Cycle 2 Cluster 31 will be tested for compliance with NERC, PJM and other applicable criteria. The contingencies will be studied with a 20 second simulation time. Contingencies to be studied include:

       a)       Steady-state operation (Category P0);

       b)       Three-phase faults with normal clearing time (and with unsuccessful high-speed reclosing) (Category P1);

       c)       Single-phase bus faults with normal clearing time (Category P2);

       d)       Single-phase faults with stuck breaker (Category P4);

       e)       Single-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure (Category P5);

       f)       Three-phase faults with loss of multiple-circuit tower line; (and with unsuccessful high-speed reclosing) (Category P7).

 

High Speed Reclosing (HSR) facilities were found in the vicinity of TC2 Cluster 31 projects.

 

Prior outage scenarios will not be considered for this study.

 

For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all the fault contingencies tested on the 2028 peak load case:

       a)       Cluster 31 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

       b)       The system with Cluster 31 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.

       c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d)       No transmission element tripped, other than those either directly connected or designed to trip because of that fault.

 

Here is a list of additional observations:

       •       AG2-184 and AH1-617 exhibited slow voltage recovery for some contingencies. Although this issue did not cause instability in the system, the model was tuned to achieve faster voltage recovery post-fault clearance. This was accomplished by adjusting Ki and Kp parameters in the plant controller (PLNTBU1) for AG2-184 and AH1-617, setting Kp to 0.15 from its original value of 0.1, and Ki to 0.35 from its original value of 0.1.

       •       CRG1H unit exhibited slow damping dynamics in several contingencies. The simulations were run for 30 seconds and were found to be stable.

       •       AC1-101 GEN 1 and AC1-102 GEN 1 experienced breaker time-out for relay instances 92623407 and 92624007, respectively. It was tested and observed that the issue is caused by numerical issues. The pick-up times for these relay instances were increased to 1 cycle to mitigate the issue.

       •       The IPCMD and IQCMD states in the REGCAU1 model of AG2-184 and AH1-617 showed erratic behavior for some contingencies in which AG2-184 and AH1-617 have been disconnected as part of the contingency event. Since the machine is disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

 

No mitigations were found to be required.

 

Table 1: Transition Cycle 2 Cluster 31 Projects

 

 

 

 

Project

Fuel Type

Transmission Owner

MFO (MW)

Point of Interconnection

AG2-184

Solar

AEP

210

Harbert Metering 138 kV

AH1-617

Solar

AEP

200

Harbert Metering 138 kV

 

 

Executive Summary for Stability Cluster

Executive Summary

 

New Service Requests AG2-082, AG2-568, AG2-657, AH1-580, AH1-686, AH1-704 and AH1-719 in PJM Transition Cycle 2, Cluster 32 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 32 projects.

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 32 projects will meet the dynamics requirements of the NERC, AEP and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2028 Summer Peak, modified to include applicable projects. Cluster 32 projects have been dispatched online at maximum power output, with 1.0 voltage at the terminal bus.

 

Transition Cycle 2 Cluster 32 will be tested for compliance with NERC, PJM and other applicable criteria. The contingencies will be studied with a 20 second simulation time. Contingencies to be studied include:

       a)       Steady-state operation (Category P0);

       b)       Three-phase faults with normal clearing time (and with unsuccessful high-speed reclosing) (Category P1);

       c)       Single-phase bus faults with normal clearing time (Category P2);

       d)       Single-phase faults with stuck breaker (Category P4);

       e)       Single-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure (Category P5);

       f)       Three-phase faults with loss of multiple-circuit tower line; (and with unsuccessful high-speed reclosing) (Category P7).

 

High Speed Reclosing (HSR) facilities were found in the vicinity of TC2 Cluster 32 projects.

 

Prior outage scenarios will not be considered for this study.

 

For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all the fault contingencies tested on the 2028 Summer Peak case:

       a)       Cluster 32 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

       b)       The system with Cluster 32 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.

       c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d)       No transmission element tripped, other than those either directly connected or designed to trip because of that fault.

 

In several contingencies, AG2-657 shows slow reactive power recovery. Although this issue did not cause instability in the system, the model was tuned to achieve satisfactory reactive power recovery. This was accomplished by adjusting Kc in the plant controller model (REPCA1) by setting Kc from 0 to 0.15. The parameters modification is pending developer’s confirmation.

 

The IPCMD and IQCMD states in the REPCA1 models of AG2-082 showed erratic behavior for some contingencies in which AG2-082 has been disconnected as part of the contingency event. Since the machines are disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

 

The IPCMD and IQCMD states in the REPCA1 models of AG2-568 showed erratic behavior for some contingencies in which AG2-568 has been disconnected as part of the contingency event. Since the machines are disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

 

The IPCMD and IQCMD states in the REPCA1 models of AG2-657 showed erratic behavior for some contingencies in which AG2-657 has been disconnected as part of the contingency event. Since the machines are disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

 

The IPCMD and IQCMD states in the REPCA1 models of AH1-580 showed erratic behavior for some contingencies in which AH1-580 has been disconnected as part of the contingency event. Since the machines are disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

 

No mitigations were found to be required.

 

Table 1: Transition Cycle 2 Cluster 32 Projects

 

 

 

 

Project

Fuel Type

Transmission Owner

MFO (MW)

Point of Interconnection

AG2-082

Solar

AEP

200

Nottingham substation 138 kV

AG2-568

Solar

AEP

80

Bim - Sundial 138 kV

AG2-657

Solar

AEP

90

Kanawha River - Carbondale 138 kV

AH1-580

Solar

AEP

200

Nottingham station 138 kV

AH1-686

Natural Gas

AEP

24

Hanging Rock substation 765 kV

AH1-704

Natural Gas

AEP

24

Hannibal substation 138 kV

AH1-719

Natural Gas

AEP

24

Beverly substation 345 kV

 

Executive Summary for Stability Cluster

Executive Summary

 

New Service Requests AG2-248 and AG2-332 in PJM Transition Cycle 2, Cluster 33 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 33 projects.

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 33 projects will meet the dynamics requirements of the NERC, AEP and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2028 Summer Peak, modified to include applicable projects. Cluster 33 projects have been dispatched online at maximum power output, with 1.01 voltage at the terminal bus.

 

Transition Cycle 2 Cluster 33 will be tested for compliance with NERC, PJM and other applicable criteria. The contingencies will be studied with a 20 second simulation time. Contingencies to be studied include:

       a)       Steady-state operation (Category P0);

       b)       Three-phase faults with normal clearing time (and with unsuccessful high-speed reclosing) (Category P1);

       c)       Single-phase bus faults with normal clearing time (Category P2).

       d)       Single-phase faults with stuck breaker (Category P4);

       e)       Single-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure (Category P5);

       f)       Three-phase faults with loss of multiple-circuit tower line; (and with unsuccessful high-speed reclosing) (Category P7).

 

High-Speed Reclosing (HSR) facilities were found in the vicinity of TC2 Cluster 33 projects.

 

Prior outage scenarios will not be considered for this study.

 

For all simulations, the queue project under study, along with the rest of the PJM system, was required to maintain synchronism and all states returning to an acceptable new condition following the disturbance.

 

For all the fault contingencies tested on the 2028 peak load case:

       a)       Cluster 33 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

       b)       The system with Cluster 33 projects included is transiently stable, and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.

       c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d)       No transmission element tripped, other than those either directly connected or designed to trip because of that fault.

 

The IPCMD and IQCMD states in the REGCA1 model of AG2-248/AG2-332 showed erratic behavior for some contingencies in which AG2-248/AG2-332 have been disconnected as part of the contingency event. Since the machine is disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system

 

No mitigations were found to be required.

 

Table 1: Transition Cycle 2 Cluster 33 Projects

 

 

 

 

Project

Fuel Type

Transmission Owner

MFO (MW)

Point of Interconnection

AG2-248

Battery

AEP

100

East Elkhart - Elcona Tap 138 kV

AG2-332

Battery

AEP

100

East Elkhart - Elcona Tap 138 kV

 

 

Executive Summary for Stability Cluster

Executive Summary

 

New Service Requests AG2-289, AG2-290, and AH1-059 in PJM Transition Cycle 2, Cluster 34 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 34 projects.

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 34 projects will meet the dynamics requirements of the NERC, AEP and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2028 Summer Peak, modified to include applicable projects. Cluster 34 projects have been dispatched online at maximum power output, with 1.0 voltage at the terminal bus.

 

Transition Cycle 2 Cluster 34 will be tested for compliance with NERC, PJM and other applicable criteria. The contingencies will be studied with a 20 second simulation time. Contingencies to be studied include:

       a)       Steady-state operation (Category P0);

       b)       Three-phase faults with normal clearing time (and with unsuccessful high-speed reclosing) (Category P1);

       c)       Single-phase bus faults with normal clearing time (Category P2);

       d)       Single-phase faults with stuck breaker (Category P4);

       e)       Single-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure (Category P5).

       f)       Three-phase faults with loss of multiple-circuit tower line; (and with unsuccessful high-speed reclosing) (Category P7).

 

High Speed Reclosing (HSR) facilities were found in the vicinity of TC2 Cluster 34 projects.

 

Prior outage scenarios will not be considered for this study.

 

For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all the fault contingencies tested on the 2028 peak load case:

       a)       Cluster 34 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

       b)       The system with Cluster 34 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.

       c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d)       No transmission element tripped, other than those either directly connected or designed to trip because of that fault.

       e)       A slight delay in reactive power recovery was observed in the AG2-290 response for some contingencies (e.g., P4.17). The generator terminal voltage and the system voltage in the area remain within acceptable ranges, and sufficient dynamic VAR support is available nearby. However, the facility’s performance could be improved through model tuning, which can be evaluated in TC2 Phase 3 if reactive power recovery becomes a critical concern.

No mitigations were found to be required.

 

Table 1: Transition Cycle 2 Cluster 34 Projects

 

 

 

 

Project

Fuel Type

Transmission Owner

MFO (MW)

Point of Interconnection

AG2-289

Battery

AEP

66.6

Amsden Switch – Fremont Center 69 kV

AG2-290

Battery

AEP

105.0

Amsden Switch – Fremont Center 69 kV

AH1-059

Solar

AEP

101.0

Sharp Road switching station 69kV

 

Executive Summary for Stability Cluster

Executive Summary

 

New Service Requests AH1-392 in PJM Transition Cycle 2, Cluster 35 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 35 projects.

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 35 projects will meet the dynamics requirements of the NERC, AEP and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2028 Summer Peak, modified to include applicable projects. Cluster 35 projects have been dispatched online at maximum power output, with 1.01 voltage at the terminal bus.

 

Transition Cycle 2 Cluster 35 will be tested for compliance with NERC, PJM and other applicable criteria. The contingencies will be studied with a 20-second simulation time. Contingencies to be studied include:

       a)       Steady-state no-fault operation (Category P0);

       b)       Three-phase faults with normal clearing time (and with unsuccessful high-speed reclosing) (Category P1);

       c)       Single-phase bus faults with normal clearing time (Category P2);

       d)       Single-phase faults with stuck breaker (Category P4);

       e)       Single-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure (Category P5);

       f)       Three-phase faults with loss of multiple-circuit tower line; (and with unsuccessful high-speed reclosing) (Category P7).

 

High-Speed Reclosing (HSR) facilities were found in the vicinity of TC2 Cluster 35 projects.

 

Prior outage scenarios will not be considered for this study.

 

For all simulations, the queue project under study, along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all the fault contingencies tested on the 2028 peak load case:

       a)        Cluster 35 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

       b)       The system with Cluster 35 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.

       c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d)       No transmission element tripped, other than those either directly connected or designed to trip because of that fault.

 

The IPCMD and IQCMD states in the REGCAU1 model of AH1-392 showed erratic behavior for some contingencies in which AH1-392 has been disconnected as part of the contingency event. Since the machine is disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

 

No mitigations were found to be required.

Table 1: Transition Cycle 2 Cluster 35 Projects

 

 

 

 

Project

Fuel Type

Transmission Owner

MFO (MW)

Point of Interconnection

AH1-392

Solar

AEP

90

Gravel Pit – Kankakee 138 kV

 

 

Executive Summary for Stability Cluster

Executive Summary

 

New Service Request AG2-072 in PJM Transition Cycle 2, Cluster 36 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 36 projects.

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 36 projects will meet the dynamics requirements of the NERC, AEP and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2028 Summer Peak, modified to include applicable projects. Cluster 36 projects have been dispatched online at maximum power output, with 1.0 voltage at the terminal bus.

 

Transition Cycle 2 Cluster 36 will be tested for compliance with NERC, PJM and other applicable criteria. The contingencies will be studied with a 20 second simulation time. Contingencies to be studied include:

       a)       Steady-state no-fault operation (Category P0);

       b)       Three-phase faults with normal clearing time (and with unsuccessful high-speed reclosing) (Category P1);

       c)       Single-phase bus faults with normal clearing time (Category P2);

       d)       Single-phase faults with stuck breaker (Category P4);

       e)       Three-phase faults with normal clearing time with prior outages of (and with unsuccessful high-speed reclosing) (Category P6) :

       f)       Three-phase Faults with Normal Clearing Time, Prior Outage of Rockport – Jefferson 765 kV Line,

       g)       Three-phase Faults with Normal Clearing Time, Prior Outage of Sullivan – Rockport 765kV,

       h)       Three-phase Faults with Normal Clearing Time, Prior Outage of Sullivan T-1 765-345 kV Transformer,

       i)       Three-phase Faults with Normal Clearing Time, Prior Outage of Sullivan T-2 765-345 kV Transformer,

       j)       Three-phase Faults with Normal Clearing Time, Prior Outage of Sullivan – Snyder 345 kV Line,

       k)       Three-phase Faults with Normal Clearing Time, Prior Outage of Snyder – Casey 345 kV Line,

       l)       Three-phase Faults with Normal Clearing Time, Prior Outage of Sullivan – Petersburg 345 kV Line,

       m)       Three-phase Faults with Normal Clearing Time, Prior Outage of Sullivan – Eugene 345 kV Line,

       n)       Three-phase Faults with Normal Clearing Time, Prior Outage of Sullivan – Dequine 345 kV Line,

       o)       Three-phase Faults with Normal Clearing Time, Prior Outage of Eugene – Cayuga 345 kV Line,

       p)       Three-phase Faults with Normal Clearing Time, Prior Outage of Sullivan – Dequine/Eugene Double-Circuit 345 kV Line.

 

High Speed Reclosing (HSR) facilities were found in the vicinity of TC2 Cluster 36 projects.

 

For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all the fault contingencies tested on the 2028 peak load case:

       a)       Cluster 36 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

       b)       The system with Cluster 36 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.

       c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d)       No transmission element tripped, other than those either directly connected or designed to trip because of that fault.

 

For prior outage scenario A (prior outage of Rockport – Jefferson 765 kV line), one of the units at Rockport unit has been switched off in the base case in accordance with Rockport emergency unit tripping (EUT) control.

 

Under prior outage scenario B (Rockport–Sullivan 765 kV line out), instability was observed for contingencies P6.B.01 and P6.B.02, resulting in the tripping of multiple units, including the queue project AG2-072 and Rockport units. Disabling the HSR scheme for these contingencies resolves the issue, with no instability observed.

 

Under prior outage scenario E (Sullivan–Snyder 345 kV line out), contingencies P6.E.03 and P6.E.07 resulted in instability and the tripping of multiple units, including the queue project AG2-072 and the Rockport units. A pre-project sensitivity was performed with AG2-072 generation offline, under which no instability was observed.

 

Under prior outage scenario F (Snyder–Casey 345 kV line out), contingencies P6.F.03 and P6.F.07 similarly resulted in instability and the tripping of multiple units, including AG2-072 and the Rockport units. A pre-project sensitivity with AG2-072 generation offline showed no instability.

 

Under prior outage scenario K (Sullivan–Dequine/Eugene double-circuit 345 kV line out), contingency P6.K.03 resulted in the tripping of the Petersburg G2 unit due to an instantaneous overvoltage relay. In addition, contingency P6.K.07 exhibited instability, leading to the tripping of multiple units, including AG2-072 and the Rockport units. A pre-project sensitivity with AG2-072 generation offline showed no instability.

 

Potential adjustments to the existing Rockport operating guidelines may be required with the interconnection of AG2-072 at Rockport 765 kV to mitigate stability issues under certain prior outage scenarios. These adjustments may include disconnecting or reducing the output of AG2-072 under those conditions.

 

Table 1: Transition Cycle 2 Cluster 36 Projects

 

 

 

 

Project

Fuel Type

Transmission Owner

MFO (MW)

Point of Interconnection

AG2-072

Natural Gas

AEP

700

Rockport 765 kV

 

Executive Summary for Stability Cluster

Executive Summary

 

New Service Requests AG2-014, AG2-126, AG2-163, AG2-343, AG2-345, AG2-491, AG2-492 and AH1-482 in PJM Transition Cycle 2, Cluster 37 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 37 projects.

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 37 projects will meet the dynamics requirements of the NERC, AEP and PJM reliability standards.

 

Cluster 37 projects were dispatched for stability analysis according to the following scenarios:

       a)       Scenario 1: AG2-126 dispatched at full MFO injection at the POI with PV MW contribution maxed out and no/reduced MW contribution from BESS.

       b)       Scenario 2: AG2-126 dispatched at full MFO injection at the POI with BESS MW contribution maxed out, and no/reduced PV MW injection.

       c)       Scenario 3: AG2-126 dispatched at full MFO injection at the POI with PV and BESS MW contribution proportional to their capacity.

       d)       Scenario 4: AG2-126 dispatched to full capacity with PV and BESS MW injection maxed out.

 

This report describes a dynamic simulation analysis of TC2 Cluster 37 for dispatch Scenario 3 as part of the overall system impact study.

 

The load flow scenario for the analysis was based on the RTEP 2028 Summer Peak, modified to include applicable projects. Cluster 37 projects have been dispatched online at maximum power output, with 1.0 voltage at the terminal bus.

 

Transition Cycle 2 Cluster 37 will be tested for compliance with NERC, PJM and other applicable criteria. The contingencies will be studied with a 20 second simulation time. Contingencies to be studied include:

       a)       Steady-state operation (Category P0);

       b)       Three-phase faults with normal clearing time (and with unsuccessful high-speed reclosing) (Category P1);

       c)       Single-phase bus faults with normal clearing time (Category P2);

       d)       Single-phase faults with stuck breaker (Category P4);

       e)       Three-phase faults with loss of multiple-circuit tower line; (and with unsuccessful high-speed reclosing) (Category P7).

 

High Speed Reclosing (HSR) facilities were found in the vicinity of TC2 cluster 37 projects.

 

There are no delayed (Zone 2) clearing faults due to dual primary relays being employed in the AEP 345 kV Nearby Queue Projects transmission system.

 

Prior outage scenarios will not be considered for this study.

 

For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all the fault contingencies tested on the 2028 peak load case:

       a)       Cluster 37 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

       b)       The system with Cluster 37 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.

       c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d)       No transmission element tripped, other than those either directly connected or designed to trip because of that fault.

 

In several contingencies, it was observed that multiple units excluding Cluster 37 projects trip due to unrealistic high terminal voltages during the fault and post-fault. Upon further analysis and observing the similar issues in the bench case with Cluster 37 projects offline, we were able to resolve the tripping instances by g-netting the following units in MISO area:

       •       17XRD2 (J968),

       •       17XRD(J1069),

       •       17HOOSIER_WF,

       •       17INXR(J913),

       •       17INXRD_J838,

       •       17CVY(J1067).

 

It may be required to coordinate with MISO to obtain an updated dynamic model for the facility—preferably a user-defined PSS®E model—for validation in TC2 Phase 3 studies.

 

Under some P1, P4, and P7 contingencies, it was observed that AF2-078 units trip as a result of the high voltage spikes following fault clearance and no further stability issues were observed. It is known that voltage spikes are a modeling limitation of WECC generic renewable models . Consequently, the pickup timer of corresponding relay instances (i.e., 9578464 and 9578484) has been increased to 0.0333 seconds.

 

Fictitious frequency response at AF1-204 generator bus tripped the queue project due to the action of instantaneous under-frequency relay under some P1 and P7 contingencies. Therefore, the relay pickup times for frequency relay instance was set to 20 seconds to avoid fictitious frequency tripping of the unit.

 

The IPCMD and IQCMD states in the REGCA1 models of AG2-014 showed erratic behavior for some contingencies in which AG2-014 has been disconnected as part of the contingency event. Since the machines are disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

 

The IPCMD and IQCMD states in the REGCA1 models of AG2-126 showed erratic behavior for some contingencies in which AG2-126 has been disconnected as part of the contingency event. Since the machines are disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

 

The IPCMD and IQCMD states in the REGCA1 models of AG2-163 showed erratic behavior for some contingencies in which AG2-163 has been disconnected as part of the contingency event. Since the machines are disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

 

The IPCMD and IQCMD states in the REGCA1 models of AG2-343 showed erratic behavior for some contingencies in which AG2-343 has been disconnected as part of the contingency event. Since the machines are disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

 

The IPCMD and IQCMD states in the REGCA1 models of AG2-345 showed erratic behavior for some contingencies in which AG2-345 has been disconnected as part of the contingency event. Since the machines are disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

 

The IPCMD and IQCMD states in the REGCA1 models of AG2-491 showed erratic behavior for some contingencies in which AG2-491 has been disconnected as part of the contingency event. Since the machines are disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

 

The IPCMD and IQCMD states in the REGCA1 models of AG2-492 showed erratic behavior for some contingencies in which AG2-492 has been disconnected as part of the contingency event. Since the machines are disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

 

The IPCMD and IQCMD states in the REGCA1 models of AH1-482 showed erratic behavior for some contingencies in which AH1-482 has been disconnected as part of the contingency event. Since the machines are disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

 

No mitigations were found to be required.

 

Table 1: Transition Cycle 2 Cluster 37 Projects

 

 

 

 

Project

Fuel Type

Transmission Owner

MFO (MW)

Point of Interconnection

AG2-014

Battery

AEP

50

Meadow Lake substation 345 kV

AG2-126

Solar/Battery

AEP

150

Eugene substation 345 kV

AG2-163

Solar

AEP

250

Dequine – Eugene 345 kV

AG2-343

Battery

AEP

100

Dequine – Eugene 345 kV

AG2-345

Battery

AEP

50

Dequine – Eugene 345 kV

AG2-491

Solar

AEP

100

Meadow Lake substation 345kV

AG2-492

Battery

AEP

50

Meadow Lake substation 345kV

AH1-482

Battery

AEP

78

Olive – Reynolds CKT #2 345kV

 

Executive Summary for Stability Cluster

Executive Summary

 

New Service Requests AG2-245 and AH1-302 in PJM Transition Cycle 2, Cluster 38 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 38 projects.

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 38 projects will meet the dynamics requirements of the NERC, AEP and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2028 Summer Peak, modified to include applicable projects. Cluster 38 projects have been dispatched online at maximum power output, with 1.0 voltage at the terminal bus.

 

Transition Cycle 2 Cluster 38 will be tested for compliance with NERC, PJM and other applicable criteria. The contingencies will be studied with a 20 second simulation time. Contingencies to be studied include:

       a)       Steady-state no fault operation (Category P0),

       b)       Three-phase faults with normal clearing time (and with unsuccessful high-speed reclosing) (Category P1),

       c)       Single-phase bus faults with normal clearing time (Category P2),

       d)       Single-phase faults with stuck breaker (Category P4),

       e)       Three-phase faults with loss of multiple-circuit tower line; (and with unsuccessful high-speed reclosing) (Category P7).

 

High Speed Reclosing (HSR) facilities were found in the vicinity of TC2 Cluster 38 projects.

 

Prior outage scenarios will not be considered for this study.

 

For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all the fault contingencies tested on the 2028 peak load case:

       a)       Cluster 38 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

       b)       The system with Cluster 38 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.

       c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d)       No transmission element tripped, other than those either directly connected or designed to trip because of that fault.

 

In several contingencies, it was observed that multiple units excluding Cluster 38 projects trip due to unrealistic high terminal voltages during the fault and post-fault. Upon further analysis and observing the similar issues in the bench case with Cluster 38 projects offline, we were able to resolve the tripping instances by g-netting the following units in MISO area:

       •       17XRD2 (J968),

       •       17XRD(J1069),

       •       17HOOSIER_WF,

       •       17INXR(J913),

       •       17INXRD_J838,

       •       17CVY(J1067).

 

It may be required to coordinate with MISO to obtain an updated dynamic model for the facility—preferably a user-defined PSS®E model—for validation in TC2 Phase 3 studies.

 

In P1.11, P1.16-P1.17, P1.26, P4.25, P7.06, and P7.13, it was observed that AF2-078 units trip as a result of the high voltage spikes following fault clearance and no further stability issues were observed. It is known that voltage spikes are a modeling limitation of WECC generic renewable models . Consequently, the pickup timer of corresponding relay instances (i.e., 9578464 and 9578484) has been increased to 0.019 seconds which aligns with the same update made in the latest stability analysis performed for AF2-078.

 

The IPCMD and IQCMD states in the REGCA1 models of AG2-245 showed erratic behavior for some contingencies in which AG2-245 has been disconnected as part of the contingency event. Since the machines are disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

 

The IPCMD and IQCMD states in the REGCA1 models of AH1-302 showed erratic behavior for some contingencies in which AH1-302 has been disconnected as part of the contingency event. Since the machines are disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

 

No mitigations were found to be required.

 

Table 1: Transition Cycle 2 Cluster 38 Projects

 

 

 

 

Project

Fuel Type

Transmission Owner

MFO (MW)

Point of Interconnection

AG2-245

Solar

AEP

210

Olive – Reynolds ckt #1 345 kV

AH1-302

Storage

AEP

75

Olive – Reynolds ckt #1 345 kV

 

 

Executive Summary for Stability Cluster

Executive Summary

 

New Service Requests AG2-029, AG2-104 and AG2-370 in PJM Transition Cycle 2, Cluster 39 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 39 projects.

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 39 projects will meet the dynamics requirements of the NERC, AEP and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2028 Summer Peak, modified to include applicable projects. Cluster 39 projects have been dispatched online at maximum power output, with 1.0 voltage at the terminal bus.

 

Transition Cycle 2 Cluster 39 will be tested for compliance with NERC, PJM and other applicable criteria. The contingencies will be studied with a 20 second simulation time. Contingencies to be studied include:

       a.       Steady-state operation (Category P0);

       b.       Three-phase faults with normal clearing time (and with unsuccessful high-speed reclosing) (Category P1);

       c.       Single-phase bus faults with normal clearing time (Category P2);

       d.       Single-phase faults with stuck breaker (Category P4);

       e.       Single-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure (Category P5);

       f.       Three-phase faults with loss of multiple-circuit tower line; (and with unsuccessful high-speed reclosing) (Category P7).

 

High Speed Reclosing (HSR) facilities were found in the vicinity of TC2 Cluster 39 projects.

 

Prior outage scenarios will not be considered for this study.

 

For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all the fault contingencies tested on the 2028 Summer Peak Load case:

       a)       Cluster 39 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

       b)       The system with Cluster 39 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.

       c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d)       No transmission element tripped, other than those either directly connected or designed to trip because of that fault.

 

AG2-029 exhibited slow reactive power recovery within the 20-second simulation window for several contingencies. While this issue did not cause instability in the system, the plant controller model was tuned to achieve a faster reactive power output and mitigate the observed slow recovery. Specifically, the plant controller model REPCA1 was updated by updating Kp, Ki, and Kc to 0.2, 2, and 0.15, respectively, and these modifications are pending the developer’s confirmation.

 

AG2-104 exhibited slow reactive power recovery within the 20-second simulation window for several contingencies. While this issue did not cause instability in the system, the plant controller model was tuned to achieve a faster reactive power output and mitigate the observed slow recovery. Specifically, plant controller model PLNTBU1 was updated by updating Kc to 0.15, and this modification has been approved by the developer.

 

It was observed that various units tripped during P1.38 contingency due to the fault at Logtown 138. After further investigation, the trippings were attributed to T-131 wind units as listed below connecting to Logtown which was confirmed by creating a bench case with all Cluster 39 projects offline and observing the similar tripping instances.

       a)       TR3_G114 with ID: ‘W1’ (PSS/E Bus# 270191),

       b)       TR4_S_V150 with ID: ‘W1’ (PSS/E Bus# 270246),

       c)       TR4_N_V150 with ID: ‘W3’ (PSS/E Bus# 270247),

       d)       TR4_N_V136 with ID: ‘W2’ (PSS/E Bus# 247521).

 

After G-netting the above units, the simulation results were found to be stable. Therefore, it was concluded Cluster 39 projects do not attribute to the generator tripping instances.

 

In a number of contingencies, AG1-368 showed slow reactive power dynamics without imposing any instability issues.

 

Flatlick Generators as well as AE1-021 exhibited slow damping dynamics in P4.29-P4.34, P4.38, P4.42, and P4.46. The slow dynamics did not cause any instability issues. Additionally, the simulations were run for 40 seconds, and the system was found to be stable.

 

The IPCMD and IQCMD states in the REGCA1 model of AG2-029 showed erratic behavior for some contingencies in which AG2-029 has been disconnected as part of the contingency event. Since the machines are disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

 

The IPCMD and IQCMD states in the REGCA1 model of AG2-104 showed erratic behavior for some contingencies in which AG2-104 has been disconnected as part of the contingency event. Since the machines are disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

 

The IPCMD and IQCMD states in the REGCA1 model of AG2-370 showed erratic behavior for some contingencies in which AG2-370 has been disconnected as part of the contingency event. Since the machines are disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

 

No mitigations were found to be required.

 

Table 1: Transition Cycle 2 Cluster 39 Projects

 

 

 

 

Project

Fuel Type

Transmission Owner

MFO (MW)

Point of Interconnection

AG2-029 

Solar 

AEP 

250 

Dunton Lake – Forest G Hiple 345 kV 

AG2-104 

Solar 

AEP 

200 

Marysville – Flatlick 765 kV 

AG2-370 

Battery 

AEP 

50 

Tillman substation 138 kV 

 

 

Executive Summary for Stability Cluster

Executive Summary

 

New Service Requests AG2-230, AG2-562, AH1-153 and AH1-272 in PJM Transition Cycle 2 Cluster 40 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 40 projects.

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 40 projects will meet the dynamics requirements of the NERC, AEP and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2028 Summer Peak, modified to include applicable projects. Cluster 40 projects have been dispatched online at maximum power output, with 1.0 voltage at the terminal bus.

 

Transition Cycle 2 Cluster 40 will be tested for compliance with NERC, PJM and other applicable criteria. The contingencies will be studied with a 20 second simulation time. Contingencies to be studied include:

       a)       Steady-state operation (Category P0);

       b)       Three-phase faults with normal clearing time (and with unsuccessful high-speed reclosing) (Category P1);

       c)       Single-phase bus faults with normal clearing time (Category P2);

       d)       Single-phase faults with stuck breaker (Category P4);

       e)       Three-phase faults with loss of multiple-Circuit tower line; (and with unsuccessful high-speed reclosing) (Category P7).

 

High Speed Reclosing (HSR) facilities were found in the vicinity of TC2 Cluster 40 projects.

 

Prior outage scenarios will not be considered for this study.

 

For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all the fault contingencies tested on the 2028 Summer Peak case:

       a)       Cluster 40 projects were able to ride through the faults (except for faults where protective action trips a generator(s)).

       b)       The system with Cluster 40 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.

       c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d)       No transmission element tripped, other than those either directly connected or designed to trip because of that fault.

 

In several contingencies, AH1-153 active power failed to recover to the pre fault level. Although this issue did not cause instability in the system, the model was tuned to achieve satisfactory active power recovery. This was accomplished by adjusting the Kp, Ki, and Kc in the plant controller model (REPCA1) by setting Kp from 3 to 5, Ki from 5 to 3, and Kc from 0 to 0.065. The parameters modification is pending developer’s confirmation.

 

The IPCMD and IQCMD states in the REGCA1 models of AG2-230 showed erratic behavior for some contingencies in which AG2-230 has been disconnected as part of the contingency event. Since the machines are disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

 

The IPCMD and IQCMD states in the REGCA1 models of AH1-153 showed erratic behavior for some contingencies in which AH1-153 has been disconnected as part of the contingency event. Since the machines are disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

 

The IPCMD and IQCMD states in the REGCA1 models of AH1-272 showed erratic behavior for some contingencies in which AH1-272 has been disconnected as part of the contingency event. Since the machines are disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

 

No mitigations were found to be required.

 

Table 1: Transition Cycle 2 Cluster 40 Projects

 

 

 

 

Project

Fuel Type

Transmission Owner

MFO (MW)

Point of Interconnection

AG2-230

Solar

AEP

150

Dumont substation 345 kV

AH1-153

Solar

AEP

50

Dumont substation 345 kV

AG2-562

Natural Gas

AEP

52

Elderberry station 345 kV

AH1-272

Solar

AEP

185

Twin Branch – Argenta 345 kV

 

 

Executive Summary for Stability Cluster

Executive Summary

 

New Service Requests AH1-461 in PJM Transition Cycle 2, Cluster 41 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 41 projects.

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 41 projects will meet the dynamics requirements of the NERC, AEP and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2028 Summer Peak, modified to include applicable projects. Cluster 41 projects have been dispatched online at maximum power output, with 1.01 pu voltage at the terminal bus.

 

Transition Cycle 2 Cluster 41 will be tested for compliance with NERC, PJM and other applicable criteria. The contingencies will be studied with a 20-second simulation time. Contingencies to be studied include:

       a)       Steady-state operation (Category P0);

       b)       Three-phase faults with normal clearing time (and with unsuccessful high-speed reclosing) (Category P1);

       c)       Single-phase bus faults with normal clearing time (Category P2);

       d)       Single-phase faults with stuck breaker (Category P4);

       e)       Single-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure (Category P5).

 

High-Speed Reclosing (HSR) facilities were found in the vicinity of TC2 Cluster 41 projects.

 

There are no three-phase faults with loss of multiple-circuit tower line (Category P7).

 

Prior outage scenarios will not be considered for this study.

 

For all simulations, the queue project under study, along with the rest of the PJM system, were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all the fault contingencies tested on the 2028 peak load case:

       a)       Cluster 41 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

       b)       The system with Cluster 41 projects included is transiently stable, and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.

       c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d)       No transmission element tripped, other than those either directly connected or designed to trip because of that fault.

 

The rotor angle of the 05CRG1H demonstrates slow rotor angle dynamics in P5.01-P5.05 and did not reach a steady-state response within the 20-second simulation window. The simulations were extended to 30 seconds, after which the rotor angle successfully stabilized.

 

The IPCMD and IQCMD states in the REGCA1 models of AH1-461 showed erratic behavior for some contingencies in which AH1-461 has been disconnected as part of the contingency event. Since the machines are disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

 

No mitigations were found to be required.

 

Table 1: Transition Cycle 2 Cluster 41 Projects

 

 

 

 

Project

Fuel Type

Transmission Owner

MFO (MW)

Point of Interconnection

AH1-461

Battery

AEP

80.0

Buckhorn 138 kV

 

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 2, Cluster 43 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 43 projects.

This analysis is effectively a screening study to determine whether the addition of the Cluster 43 projects will meet the dynamics requirements of the NERC, FirstEnergy (FE), and PJM reliability standards.

The load flow scenario for the analysis was based on the 2028 light load case, modified to include applicable projects. Cluster 43 projects have been dispatched online at maximum power output, with approximately unity power factors at the high side of the GSUs, 1.00 pu voltage at the generator terminals, and 1.01 pu voltage at the POI bus.

Cluster 43 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 53 contingencies were studied, each with a 20 second simulation time period (with 1.0 second initial run prior to any events). Studied faults included:

  1. Steady-state operation (Category P0);
  2. Three-phase faults with normal clearing time (Category P1);
  3. Single-phase faults with stuck breaker (Category P4);
  4. Single-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure (Category P5);
  5. Single-phase to ground faults with normal clearing for common structure (Category P7).

Multiple-circuit tower line faults were identified for this study.

High Speed Reclosing (HSR) facilities were found in the vicinity of TC1 Cluster 43 projects.

For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For 53 out of 53 fault contingencies tested on the 2028 light load case:

  1. Cluster 43 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  2. The system with Cluster 43 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
  3. Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
  4. No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

 

Table 1: TC2 Cluster 43 Projects

 

 

 

 

 

 

 

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

43

AH1-680

Natural Gas

FirstEnergy (FE) transmission system,

ATSI zone

1300 MW

1300 MW

1300 MW

Sammis – South Canton 345 kV

 

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 2, Cluster 44 are listed in Table 1 below. This report will cover the dynamic analysis of the Cluster 44 projects.

This analysis is effectively a screening study to determine whether the addition of the Cluster 44 projects will meet the dynamics requirements of the NERC, FE, and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2028 summer peak load case, modified to include applicable projects. Cluster 44 projects have been dispatched online at maximum power output, with approximately unity power factor at the high side of the GSUs, 1.00-1.03 pu voltage at the generator terminals, and 1.00-1.02 pu voltage at the POI buses.

Cluster 44 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 241 contingencies were studied, each with a 20 second simulation time period (with 1.0 second initial run prior to any events). Studied faults included:

  1. Steady state operation (Category P0);
  2. Three phase faults with normal clearing time on the intact network (Category P1);
  3. Single phase to ground faults with delayed clearing due to a stuck breaker (Category P4);
  4. Single phase to ground faults with delayed clearing as a result of protection failure (Category P5);
  5. Single phase to ground faults with normal clearing for common structure (Category P7).

High Speed Reclosing (HSR) facilities were found in the vicinity of TC2 Cluster 44 projects.

For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the 2028 peak load case:

  1. Cluster 44 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  2. The system with Cluster 44 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
  3. Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
  4. No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

The AG2-621 voltage relay (VTGTPAT 97100306, TP = 0.3 s) tripped during several P4 stuck-breaker contingencies (P4_1B1.73–90) with 20-cycle backup clearing. A timer setting of at least 0.35 s would be required to ride through the 20-cycle backup clearing. Based on documentation for the inverter type, the relay timer pickup was adjusted to 1.2 s. No further trips were observed after this adjustment.

The existing AE2-285 overvoltage relay (VTGTPAT 24196701, TP = 0.01 s) tripped during the P1.34 contingency (7-cycle clearing of the Maysville 138/69 kV transformer) at t = 1.129 s in both the pre-project and post-project cases. The overvoltage spike is brief and settles quickly, suggesting the trip may be a numerical simulation artifact rather than a sustained overvoltage condition. Adding 8 ms to the relay timer pickup (TP = 0.018 s) was sufficient to ride through the transient and resolve the trip.

 

Table 1: TC2 Cluster 44 Projects

 

 

 

 

 

 

 

Cluster

Project

Fuel Type

Transmission Owner

MFO (MW)

MWE (MW)

MWC (MW)

Point of Interconnection

44

AG2-236

Solar

FirstEnergy (FE) transmission system, American Transmission Systems (ATSI) zone

60.0

20.0

2.0

Potter-Harlan 69 kV

AG2-621

Storage

FirstEnergy (FE) transmission system, American Transmission Systems (ATSI) zone

150.0

150.0

150.0

Hoytdale 138 kV

AH1-699

Natural Gas

FirstEnergy (FE) transmission system, American Transmission Systems (ATSI) zone

1210.0

58.0

69.0

Wellsville 345 kV

AH1-706

Natural Gas

FirstEnergy (FE) transmission system, American Transmission Systems (ATSI) zone

970.453

30.453

23.823

Lordstown 345 kV

 

 

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 2, Cluster 45 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 45 projects.

This analysis is effectively a screening study to determine whether the addition of the Cluster 45 projects will meet the dynamics requirements of the NERC, FE-ATSI, and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2028 summer peak load case, modified to include applicable projects. Cluster 45 projects have been dispatched online at maximum power output, with approximately unity power factor at the high side of the GSUs, 1.00 pu voltage at the generator terminals, and 1.01 pu voltage at the POI buses.

Cluster 45 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 153 contingencies were studied, each with a 20 second simulation time period (with 1.0 second initial run prior to any events). Studied faults included:

  1. Steady-state operation (Category P0);
  2. Three-phase faults with normal clearing time (Category P1);
  3. Single-phase bus faults with normal clearing time (Category P2);
  4. Single-phase faults with stuck breaker (Category P4);
  5. Single phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure (Category P5).;
  6. Single-phase faults with normal clearing on common structure (Category P7).

No High Speed Reclosing (HSR) facilities were found in the vicinity of TC2 Cluster 45 projects.

For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the 2028 peak load case:

  1. Cluster 45 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  2. The system with Cluster 45 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
  3. Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
  4. No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

No mitigations were found to be required for TC2 Cluster 45.

Table 1: TC2 Cluster 45 Projects

 

 

 

 

 

 

 

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

45

AG2-119

Solar

First Energy Transmission System, ATSI zone

80 MW

80 MW

53.6 MW

Galion to Roberts South 138 kV

AH1-542

Solar & Storage

First Energy Transmission System, ATSI zone

110 MW

110 MW

22 MW

Kirby to Crissinger 138 kV

 

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 2, Cluster 48 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 48 projects.

This analysis is effectively a screening study to determine whether the addition of the Cluster 48 projects will meet the dynamics requirements of the NERC, FE, and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2028 light load case, modified to include applicable projects. Cluster 48 project has been dispatched online at maximum power output, with approximately unity power factor at the high side of the GSUs, 1.01 pu voltage at the generator terminals, and 1.01 pu voltage at the POI bus.

Cluster 48 project was tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 99 contingencies were studied, each with a 20 second simulation time period (with 1.0 second initial run prior to any events). Studied faults included:

  1. Steady state operation (Category P0);
  2. Three phase faults with normal clearing time on the intact network (Category P1);
  3. Single phase to ground faults with delayed clearing due to a stuck breaker (Category P4);
  4. Single phase to ground faults with delayed clearing as a result of protection failure (Category P5);
  5. Single phase to ground faults with normal clearing for common structure (Category P7).

High Speed Reclosing (HSR) facilities were found in the vicinity of TC2 Cluster 48 projects.

For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the 2028 light load case:

  1. Cluster 48 project was able to ride through the faults (except for faults where protective action trips a generator(s)),
  2. The system with Cluster 48 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
  3. Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
  4. No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

J1062 was tripped during the fault application closed to their POIs as a result of fictitious frequency spikes at the frequency relay monitored bus, i.e., inverter terminal bus. Therefore, frequency protection in the model was disabled for faults close to the POI of the projects due to the deficiency of PSSE frequency calculation for inverter-based generation facilities. No more tripping issue of the J1062 was observed.

No mitigations were found to be required for TC2 Cluster 48.

 

Table 1: TC2 Cluster 48 Projects

 

 

 

 

 

 

 

Cluster

Project

Fuel Type

Transmission Owner

MFO (MW)

MWE

(MW)

MWC

(MW)

Point of Interconnection

48

AH1-711

Natural Gas

FirstEnergy (FE) transmission system, American Transmission Systems, Inc. (ATSI) Zone

1108.2

408.2

292.5

Lemoyne 345 kV

 

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 2, Cluster 49 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 49 projects.

This analysis is effectively a screening study to determine whether the addition of the Cluster 49 projects will meet the dynamics requirements of the NERC, FE, and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2028 summer peak load case, modified to include applicable projects. Cluster 49 projects have been dispatched online at maximum power output, with approximately unity power factor at the high side of the GSUs, 1.00 pu voltage at the generator terminals, and 1.02 pu voltage at the POI buses.

Cluster 49 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 57 contingencies were studied, each with a 20 second simulation time period (with 1.0 second initial run prior to any events). Studied faults included:

  1. Steady state operation (Category P0);
  2. Three phase faults with normal clearing time on the intact network (Category P1);
  3. Single phase to ground faults with delayed clearing due to a stuck breaker (Category P4);
  4. Single phase to ground faults with delayed clearing as a result of protection failure (Category P5);
  5. Single phase to ground faults with normal clearing for common structure (Category P7).

No High Speed Reclosing (HSR) facilities were found in the vicinity of TC2 Cluster 49 projects.

For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the 2028 peak load case:

  1. Cluster 49 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  2. The system with Cluster 49 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
  3. Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
  4. No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

AG2-057/AH1-060 was tripped during the fault application closed to their POIs as a result of fictitious frequency spikes at the frequency relay monitored bus, i.e., inverter terminal bus from their previous queue project model AF1-122. Therefore, frequency protection in the model was disabled for faults close to the POI of the projects due to the deficiency of PSSE frequency calculation for inverter-based generation facilities. No more tripping issue of the AG2-057/AH1-060 was observed.

No mitigations were found to be required for TC2 Cluster 49.

 

 

Table 1: TC2 Cluster 49 Projects

 

 

 

 

 

 

 

Cluster

Project

Fuel Type

Transmission Owner

MFO (MW)

MWE

(MW)

MWC

(MW)

Point of Interconnection

49

AG2-057

Solar

FirstEnergy (FE) transmission system, American Transmission Systems, Inc. (ATSI) Zone

74

10

6

Cardington-Liberty 69 kV II

AH1-060

Solar

FirstEnergy (FE) transmission system, American Transmission Systems, Inc. (ATSI) Zone

94

20

12

Cardington-Liberty 69 kV III

 

 

 

Executive Summary for Stability Cluster

Executive Summary

The new Service Request (project) in PJM Transition Cycle 2, Cluster 50 is listed in Table 1 below. This report will cover the dynamic analysis of the Cluster 50 project.

This analysis is effectively a screening study to determine whether the addition of the Cluster 50 project will meet the dynamics requirements of the NERC, FirstEnergy (FE), and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2028 summer peak load case, modified to include applicable projects. The Cluster 50 project is set at maximum power output, with approximately unity power factor at the high side of the station transformer, 1.00 pu voltage at the generator terminal, and 1.02 pu voltage at the POI bus

The Cluster 50 project was tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 38 contingencies were studied, each with a 20 second simulation time period (with 1.0 second initial run prior to any events). Studied faults included:

  1. Steady-state operation (Category P0);
  2. Three-phase faults with normal clearing time (Category P1);
  3. Single-phase faults with stuck breaker (Category P4);
  4. Single phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure (Category P5).

No common tower contingencies were identified for this study.

High Speed Reclosing (HSR) facilities were not found in the vicinity of the TC2 Cluster 50 project. For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all fault contingencies tested on the 2028 peak load case:

  1. The Cluster 50 project was able to ride through the faults (except for faults where protective action trips a generator(s)),
  2. The system with the Cluster 50 project included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
  3. Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
  4. No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

No mitigation was required for TC2 Cluster 50.

 

 

Table 1: TC2 Cluster 50 Projects

 

 

 

 

 

 

 

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

50

AG2-109

Solar

FirstEnergy (FE) transmission system, American Transmission Systems, Incorporated (ATSI) zone

40 MW

40 MW

28.1 MW

Fitchville-New London 69 kV

 

Executive Summary for Stability Cluster

Executive Summary:

New Service Request (projects) in PJM Transition Cycle 2, Cluster 53 is listed in Table 1 below. This report will cover the dynamic analysis of Cluster 53 project.

This analysis is effectively a screening study to determine whether the addition of the Cluster 53 project will meet the dynamics requirements of the NERC, ComEd and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2028 summer peak load case, modified to include applicable project. Cluster 53 project has been dispatched online at maximum power output, and the voltage schedule is set to achieve near unity power factor at the high side of the main transformer.

Cluster 53 project was tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 56 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

  1. Steady-state operation (20 second run);
  2. Three-phase faults with normal clearing time;
  3. Three-phase to ground bus faults with normal clearing time;
  4. Three-phase to ground faults with delayed clearing due to a stuck breaker
  5. Three-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure;
  6. Three-phase faults with loss of multiple-circuit tower line.

For all simulations, the Cluster 53 project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the 2028 peak load case:

  1. Cluster 53 project was able to ride through the faults (except for faults where protective action trips a generator(s)),
  2. The system with Cluster 53 project included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3%.
  3. Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
  4. No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

AH1-338 meets the 0.95 leading and lagging PF requirement.

For the contingencies P4.09.3B3 and P4.10.3B3 at Steward 138 kV bus which consider the failure of the breaker between circuits 16914 and 18618, a system islanding occurs which includes all equipment at AH1-338, ESS H447, ESS 445, AF1-331, AD1-013 and ESS H440N being disconnected from the rest of the system. For the purposes of this study, all equipment within the islanding area will be tripped during these two specific contingencies.

 

Large voltage spikes were observed at fault clearing for many contingencies. These voltage spikes are known artifacts associated with generic dynamic models for inverter-based generators. These spikes should generally be disregarded as they do not represent the performance of actual hardware.

 

No mitigations were found to be required.

Table 1: TC2 Cluster 53 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

53

AH1-338

Solar

ComEd

180

180

23.4

McGirr Rd - Ritchie Road 138kV

 

Executive Summary for Stability Cluster

Executive Summary:

New Service Requests (projects) in PJM Transition Cycle 2, Cluster 54 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 54 projects.

This analysis is effectively a screening study to determine whether the addition of the Cluster 54 projects will meet the dynamics requirements of the NERC, ComEd and PJM reliability standards.

The load flow scenarios for the analysis were based on the RTEP 2028 summer peak load and light load case, modified to include applicable projects. Cluster 54 projects have been dispatched online at maximum power output and the voltage schedule is set to achieve maintain the POI voltage within the voltage schedule dead band.

Cluster 54 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 285 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

  1. Three-phase faults with normal clearing time;
  2. Three-phase bus faults with normal clearing time;
  3. Three-phase to ground faults with three-phase delayed clearing due to a stuck breaker (GO breakers);
  4. Three-phase to ground faults with single-phase delayed clearing due to a stuck breaker (IPO breakers);
  5. Three-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure;
  6. Three-phase faults with loss of multiple-circuit tower line.

For all simulations, the Cluster 54 projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the 2028 peak load and light load case:

  1. Cluster 54 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  2. The system with Cluster 54 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3%.
  3. Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
  4. No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

AG2-660, AG2-675, AH1-044, AH1-150 and AH1-151 meet the 0.95 leading and lagging PF requirement.

AH1-718 meets the 0.9 lagging and 1 leading PF requirement.

Initial studies identified slow reactive power response from AG2-675. Therefore, it is recommended to add 5% reactive power droop to the plant controller.

  • REPCA1 :

                  CON(J+8) = 0.05 (Kc Reactive current compensation gain (pu))

No mitigations were found to be required.

Table 1: TC2 Cluster 54 Projects

Project

Fuel Type

TO

MFO

MWE

MWC

Point of Interconnection

AG2-660

Storage

ComEd

600.0

0.0

20.0

Nelson – Electric Junction 345 kV

AG2-675

Storage

ComEd

335.0

80.0

32.0

Cordova 345 kV

AH1-044

Solar

ComEd

800.0

200.0

120.0

Nelson – Electric Junction 345 kV

AH1-150

Solar

ComEd

1000.0

200.0

120.0

Nelson – Electric Junction 345 kV

AH1-151

Solar

ComEd

1200.0

200.0

120.0

Nelson – Electric Junction 345 kV

AH1-718

Natural Gas

ComEd

391.0

11.0

38.0

Nelson 345 kV

 

Executive Summary for Stability Cluster

Executive Summary:

New Service Requests (projects) in PJM Transition Cycle 2, Cluster 55 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 55 projects.

This analysis is effectively a screening study to determine whether the addition of the Cluster 55 projects will meet the dynamics requirements of the NERC, ComEd and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2028 summer peak load case, modified to include applicable projects. Cluster 55 projects have been dispatched online at maximum power output, and the voltage schedule is set to achieve near unity power factor at the high side of the main transformer.

Cluster 55 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 168 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

  1. Steady-state operation;
  2. Three-phase faults with normal clearing time;
  3. Three-phase bus faults with normal clearing time;
  4. Three-phase to ground faults with three-phase delayed clearing due to a stuck breaker (GO breakers);
  5. Three-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure;
  6. Three-phase faults with loss of multiple-circuit tower line.

For all simulations, the Cluster 55 projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the 2028 peak load case:

  1. Cluster 55 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  2. The system with Cluster 55 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3%.
  3. Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
  4. No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

AG2-585 meets the 0.95 leading and lagging PF requirement.

No mitigations were found to be required.

Table 1: TC1 Cluster 55 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

55

AG2-585

Solar

ComEd

55

55

33

Kensington 138 kV

 

Executive Summary for Stability Cluster

Executive Summary:

New Service Requests (projects) in PJM Transition Cycle 2, Cluster 56 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 56 projects.

This analysis is effectively a screening study to determine whether the addition of the Cluster 56 projects will meet the dynamics requirements of the NERC, ComEd and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2028 summer peak load case, modified to include applicable projects. Cluster 56 projects have been dispatched online at maximum power output, and the voltage schedule is set to achieve near unity power factor at the high side of the main transformer.

Cluster 56 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 181 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

  1. Three-phase faults with normal clearing time;
  2. Three-phase to ground bus faults with normal clearing time;
  3. Three-phase to ground faults with three-phase delayed clearing due to a stuck breaker (GO breakers)
  4. Three-phase to ground faults with single-phase delayed clearing due to a stuck breaker (IPO breakers)
  5. Three-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure;
  6. Three-phase faults with loss of multiple-circuit tower line.

For all simulations, the Cluster 56 projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the 2028 peak load case:

  1. Cluster 56 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  2. The system with Cluster 56 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3%.
  3. Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
  4. No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

AG2-114 and AH1-541 meet the 0.95 leading and lagging PF requirement.

No mitigations were found to be required for Cluster 56 projects.

Table 1: TC2 Cluster 56 Projects

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

AG2-114

Solar

ComEd

100

100

60

Dresden-Pontiac Midpoint 345 kV

AH1-541

Storage/Solar

ComEd

92.4

92.4

27.72

Chestnut 345 kV

 

Executive Summary for Stability Cluster

Executive Summary:

New Service Requests (projects) in PJM Transition Cycle 2, Cluster 57 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 57 projects.

This analysis is effectively a screening study to determine whether the addition of the Cluster 57 projects will meet the dynamics requirements of the NERC, COMED and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2028 summer peak load and light load case, modified to include applicable projects. Cluster 57 projects have been dispatched online according to the scenarios, and the voltage schedule is set to achieve near unity power factor at the high side of the main transformer for the IBR projects.

Cluster 57 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 632 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

  1. Steady-state operation (20 second run);
  2. Three-phase faults with normal clearing time;
  3. Three-phase bus faults with normal clearing time;
  4. Three-phase to ground faults with three-phase delayed clearing due to a stuck breaker (GO breakers);
  5. Three-phase to ground faults with single-phase delayed clearing due to a stuck breaker (IPO breakers)
  6. Three-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure;
  7. Three-phase faults with loss of multiple-circuit tower line.

For all simulations, the Cluster 57 projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the 2028 peak load and light load cases:

  1. Cluster 57 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  2. The system with Cluster 57 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3%.
  3. Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
  4. No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

AG2-453, AG2-524, AH1-165, AH1-563, AH1-673, AH1-698 and AH1-714 meets the leading and lagging PF requirement.

Initial simulations identified slow terminal voltage and reactive power control response at AH1-165 due to the absence of reactive power droop in the voltage controller of the power plant controller model (REPCA1). This was resolved by adding a 5% droop to Q/V controller in the REPCA1 model as follows:

REPCA1:

  • CON(J+8) = 0.05 (Kc, Reactive current compensation gain (pu))

Contingencies P4.01, P4.02, P4.03, P4.04, P4.05, P4.06, P4.229, P4.230, P4.267, P4.269, P4.270 and P4.279 exhibited oscillations in the POI voltage and generator responses after 17.5s. This behavior is attributed to improperly tuned power system stabilizer model (PSS2C) in AH1-698. This issue was observed only in light load scenario. It is recommended to tune the power system stabilizer to according to the system conditions.

Table 1: TC2 Cluster 57 Projects

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

AG2-453

Solar

ComEd

280

280

196

La Salle – Plano 345 kV

AG2-524

Storage/Solar

ComEd

110

110

110

La Salle – Mazon 138 kV

AH1-165

Storage

ComEd

72

72

0

Will County 138 kV

AH1-563

Storage

ComEd

1,206

150

150

Aurora EC 138 kV

AH1-673

Storage

ComEd

85

85

85

State Line - River Energy Center 138 kV

AH1-698

Nuclear

ComEd

2,584

130

57.6

Braidwood 345 kV

AH1-714

Nuclear

ComEd

1,360

169

174.1

La Salle 345 kV

 

 

Executive Summary for Stability Cluster

Executive Summary:

New Service Requests (projects) in PJM Transition Cycle 2, Cluster 58 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 58 projects.

This analysis is effectively a screening study to determine whether the addition of the Cluster 58 projects will meet the dynamics requirements of the NERC, ComEd and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2028 summer peak load case, modified to include applicable projects. Cluster 58 projects have been dispatched online at maximum power output, and the voltage schedule is set to achieve near unity power factor at the high side of the main transformer.

Cluster 58 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 180 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

  1. Steady-state operation;
  2. Three-phase faults with normal clearing time;
  3. Three-phase bus faults with normal clearing time;
  4. Three-phase to ground faults with three-phase delayed clearing due to a stuck breaker (GO breakers);
  5. Three-phase to ground faults with single-phase delayed clearing due to a stuck breaker (IPO breakers);
  6. Three-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure;
  7. Three-phase faults with loss of multiple-circuit tower line.

For all simulations, the Cluster 58 projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the 2028 peak load case with mitigation implemented:

  1. Cluster 58 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  2. The system with Cluster 58 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3%.
  3. Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
  4. No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

AG2-061, AG2-363, AG2-364, and AH1-543 meet the 0.95 leading and lagging PF requirement.

Initial simulations resulted in a sustained 1.3 Hz system oscillation for all contingencies resulting in the loss of Powerton – Tazewell 345 kV circuit L0304. The oscillations violate the system damping criteria. The oscillations are present with TC2 projects out of service. therefore, the issue is a result of the addition of TC2 projects. It was attempted to mitigate the oscillation by tuning the dynamic models of incoming TC2 projects AG2-363/AG2-364 without success. It is recommended to tune the power system stabilizers on Powerton U5 & U6 to mitigate the oscillation. If tuning of the stabilizers is not possible, an alternative solution may be to add dynamic reactive power compensation at select locations in the area. Additional studies can be performed during Phase III to assess this option if required. It is recommended to perform a PSCAD study of the area with critical contingencies.

Initial simulations resulted in a rotor angle instability in the Three Rivers Unit 1 and Unit 2 for contingency P7.03 – simultaneous loss of Mulberry – Dresden circuits L1227 and L1202 with fault at Mulberry Red. The instability was observed with TC2 projects out of service. Therefore, the instability is not the result of the addition of TC2 projects. Three Rivers Unit 2 was netted during the analysis for contingency P7.03 only which resolves the instability. This scenario is being investigated by ComEd and PJM planning. It is recommended to perform a PSCAD analysis of this scenario.

Initial simulations resulted in slow reactive power settling at AH1-543. It is recommended to include a 5% reactive power droop in the power plant voltage controller.

Initial simulations resulted in slow reactive power settling at the AG2-061/AD2-038/AF2-143 facility. It is recommended to add 4% reactive power droop to AD2-038 power plant voltage controller and adjust AF2-143 reactive power droop setting to 4% in the power plant voltage controller to match AG2-061.

Table 1: TC2 Cluster 58 Projects

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

AG2-061

Storage

ComEd

200

50

20

Dana 345 kV

AG2-363

Solar

ComEd

300

300

180

Powerton 345 kV

AG2-364

Solar

ComEd

500

200

120

AH1-543

Solar and Storage

ComEd

157.4

157.4

31.48

Mulberry – Tazewell 345 kV

 

Executive Summary for Stability Cluster

Executive Summary:

New Service Requests (projects) in PJM Transition Cycle 2, Cluster 59 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 59 projects.

This analysis is effectively a screening study to determine whether the addition of the Cluster 59 projects will meet the dynamics requirements of the NERC, ComEd and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2028 summer light load case, modified to include applicable projects. Cluster 59 projects have been dispatched online at maximum power output and the voltage schedule set to the voltage schedule defined in ComEd SPOG 1-1.

Cluster 59 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 86 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

  1. Three-phase faults with normal clearing time;
  2. Three-phase bus faults with normal clearing time;
  3. Three-phase to ground faults with three-phase delayed clearing due to a stuck breaker (GO breakers);
  4. Three-phase to ground faults with single-phase delayed clearing due to a stuck breaker (IPO breakers)
  5. Three-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure;
  6. Three-phase faults with loss of multiple-circuit tower line.
  7. Three-phase faults with normal clearing time and a failed high speed reclose attempt.

For all simulations, the Cluster 59 projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the 2028 light load case:

  1. Cluster 59 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  2. The system with Cluster 59 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3%.
  3. Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
  4. No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

AH1-567 meets the 1.0 leading to 0.9 lagging PF requirement for uprated synchronous machines (< 20 MW).

 

No mitigations were found to be required for TC2 projects.

Table 1: TC2 Cluster 59 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

59

AH1-567

Natural Gas

COMED

328

5

5

University Park 138 kV

 

Executive Summary for Stability Cluster

Executive Summary:

New Service Requests (projects) in PJM Transition Cycle 2, Cluster 60 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 60 projects.

This analysis is effectively a screening study to determine whether the addition of the Cluster 60 projects will meet the dynamics requirements of the NERC, ComEd and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2028 summer peak case, modified to include applicable projects. Cluster 60 projects have been dispatched online at maximum power output and the voltage schedule set to achieve near unity power factor at the high side of the main transformer.

Cluster 60 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 310 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

  1. Three-phase faults with normal clearing time;
  2. Three-phase bus faults with normal clearing time;
  3. Three-phase to ground faults with three-phase delayed clearing due to a stuck breaker (GO breakers);
  4. Three-phase to ground faults with single-phase delayed clearing due to a stuck breaker (IPO breakers)
  5. Three-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure;
  6. Three-phase faults with loss of multiple-circuit tower line.
  7. Three-phase faults with normal clearing time and a failed high speed reclose attempt.

For all simulations, the Cluster 60 projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the 2028 summer peak case:

  1. Cluster 60 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  2. The system with Cluster 60 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3%.
  3. Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
  4. No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

AG2-516, AH1-341, and AH1-564 meet the 0.95 leading and lagging PF requirements.

No mitigations were found to be required.

Table 1: TC2 Cluster 60 Projects

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

AG2-516

Solar

COMED

120

120

72

Pecatonica 138 kV

AH1-341

Solar

COMED

150

150

96.6

Stillman – Dixon 138 kV

AH1-564

Storage

COMED

330

150

150

Rockford II 138 kV

 

Executive Summary for Stability Cluster

Executive Summary:

New Service Requests (projects) in PJM Transition Cycle 2, Cluster 61 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 61 projects.

This analysis is effectively a screening study to determine whether the addition of the Cluster 61 projects will meet the dynamics requirements of the NERC, ComEd and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2028 summer light load case, modified to include applicable projects. Cluster 61 projects have been dispatched online at maximum power output and the voltage schedule set to the schedule defined in COMED SPOG 1-1 (i.e. 354 kV).

Cluster 61 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 253 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

  1. Three-phase faults with normal clearing time;
  2. Three-phase bus faults with normal clearing time;
  3. Three-phase to ground faults with three-phase delayed clearing due to a stuck breaker (GO breakers);
  4. Three-phase to ground faults with single-phase delayed clearing due to a stuck breaker (IPO breakers)
  5. Three-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure;
  6. Three-phase faults with loss of multiple-circuit tower line.

For all simulations, the Cluster 61 projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the 2028 light load case:

  1. Cluster 61 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  2. The system with Cluster 61 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3%.
  3. Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
  4. No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

AH1-702 meets the 0.9 lagging and unity PF requirement for uprated synchronous machines.

No mitigations were found to be required for Cluster 61 projects.

Table 1: TC2 Cluster 61 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

61

AH1-702

Nuclear

COMED

2530

88

43

Byron 345 kV

 

Executive Summary for Stability Cluster

Executive Summary:

New Service Requests (projects) in PJM Transition Cycle 2, Cluster 62 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 62 projects.

This analysis is effectively a screening study to determine whether the addition of the Cluster 62 projects will meet the dynamics requirements of the NERC, COMED and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2028 summer peak load case, modified to include applicable projects. Cluster 62 projects have been dispatched online at maximum power output and the voltage schedule set to achieve near unity power factor at the high side of the main transformer.

Cluster 62 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 352 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

  1. Three-phase faults with normal clearing time;
  2. Three-phase bus faults with normal clearing time;
  3. Three-phase to ground faults with three-phase delayed clearing due to a stuck breaker (GO breakers);
  4. Three-phase to ground faults with single-phase delayed clearing due to a stuck breaker (IPO breakers)
  5. Three-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure;
  6. Three-phase faults with loss of multiple-circuit tower line.

For all simulations, the Cluster 62 projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the 2028 peak load case:

  1. Cluster 62 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  2. The system with Cluster 62 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3%.
  3. Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
  4. No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

AG2-544 meets the 0.95 leading and lagging PF requirement.

AG2-545 meets the 0.95 leading and lagging PF requirement.

AH1-196 meets the 0.95 leading and lagging PF requirement.

 

No mitigations were found to be required for the Cluster 62 projects.

Table 1: TC2 Cluster 62 Projects

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

AG2-544

Storage

COMED

200

200

80

Silver Lake 345 kV

AG2-545

Storage

COMED

400

400

160

AH1-196

Solar

COMED

150

150

90

Prairie 345 kV

 

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 2, Cluster 64 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 64 projects.

This analysis is effectively a screening study to determine whether the addition of the Cluster 64 projects will meet the dynamics requirements of the NERC, FirstEnergy (FE), and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2028 summer peak load case, modified to include applicable projects. Cluster 64 projects have been dispatched online at maximum power output, with approximately unity power factor at the high side of the GSUs, 1.0 pu voltage at the generator terminals, and 1.0 pu voltage at the POI buses.

Cluster 64 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 254 contingencies were studied, each with a 20 second simulation time period (with 1.0 second initial run prior to any events). Studied faults included:

  1. Steady-state operation (Category P0);
  2. Three phase faults with normal clearing time on the intact network (Category P1);
  3. Single phase to ground faults with delayed clearing due to a stuck breaker (Category P4);
  4. Single phase to ground faults with delayed clearing as a result of protection failure (Category P5);
  5. Single phase to ground faults with normal clearing for common structure (Category P7).

 

High Speed Reclosing (HSR) facilities were found in the vicinity of TC2 Cluster 64 projects.

For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the 2028 peak load case:

  1. Cluster 64 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  2. The system with Cluster 64 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
  3. Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
  4. No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

No mitigations were found to be required for TC2 Cluster 64.

 

Table 1: TC2 Cluster 64 Projects

 

 

 

 

 

 

 

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

64

AG2-062

Wind

FirstEnergy (FE) transmission system, Allegheny Power System (APS) zone

147.0 MW

147.0 MW

21.609 MW

William 138 kV

AG2-448

Solar

FirstEnergy (FE) transmission system, Allegheny Power System (APS) zone

50.0 MW

50.0 MW

30.0 MW

Cross School - Kitzmiller

138 kV

AH1-206

Storage

FirstEnergy (FE) transmission system, Allegheny Power System (APS) zone

60.0 MW

60.0 MW

60.0 MW

Bethelboro 138 kV

AH1-247

Solar

FirstEnergy (FE) transmission system, Allegheny Power System (APS) zone

40.0 MW

40.0 MW

24.0 MW

Lardin - Lake Lynn 138kV

AH1-248

Solar

FirstEnergy (FE) transmission system, Allegheny Power System (APS) zone

65.0 MW

25.0 MW

15.0 MW

Lardin - Lake Lynn 138kV

AH1-249

Storage

FirstEnergy (FE) transmission system, Allegheny Power System (APS) zone

145.0 MW

80.0 MW

80.0 MW

Lardin – Lake Lynn 138kV

 

Executive Summary for Stability Cluster

Executive Summary

The new Service Requests (projects) in PJM Transition Cycle 2, Cluster 66 are listed in Table 1 below. This report will cover the dynamic analysis of the Cluster 66 projects.

This analysis is effectively a screening study to determine whether the addition of the Cluster 66 projects will meet the dynamics requirements of the NERC, FirstEnergy (FE), and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2028 summer peak load case, modified to include applicable projects. The Cluster 66 projects are set at maximum power output, with approximately unity power factor at the high side of the station transformers. The voltage magnitudes at the projects’ generator terminals and POI buses are given in Table 2.

The Cluster 66 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 196 contingencies were studied, each with a 20 second simulation time period (with 1.0 second initial run prior to any events). Studied faults included:

  1. Steady-state operation (Category P0);
  2. Three-phase faults with normal clearing time (Category P1);
  3. Single-phase faults with stuck breaker (Category P4);
  4. Single phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure (Category P5);
  5. Single phase to ground faults with normal clearing for common structure (Category P7).

High Speed Reclosing (HSR) facilities were found in the vicinity of the TC2 Cluster 66 projects. For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the 2028 peak load case:

  1. The Cluster 66 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  2. The system with the Cluster 66 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
  3. Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
  4. No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

In the initial simulations, the AG2-300 generator tripped on high terminal voltage for contingencies P5.01, P5.08, P5.09, P5.10, P5.18, and P5.22. The plant is modeled with REECC1/REPCA1 controls and VTGTPAT voltage protection, with REECC1 Vup = 1.10 pu and three VTGTPAT overvoltage protection instances set at 1.11 pu / 10.0 s, 1.21 pu / 0.16 s, and 1.30 pu / 0.05 s. Based on documentation for the inverter type, the parameter Vup was adjusted to 1.20 pu, and no further trips were observed after this adjustment.

No other mitigation was required for TC2 Cluster 66. 

 

Table 1: TC2 Cluster 66 Projects

 

 

 

 

 

 

 

Cluster

Project

Fuel Type

Transmission Owner

MFO (MW)

MWE (MW)

MWC (MW)

Point of Interconnection

66

AG2-300

Storage

FirstEnergy (FE) transmission system, Allegheny Power Systems (APS) zone

100

100

70

Meadow Brook 138 kV

66

AH1-254

Wind

FirstEnergy (FE) transmission system, Allegheny Power Systems (APS) zone

171.4

171.4

36.538

Greenland Gap 500 kV II

66

AH1-283

Solar

FirstEnergy (FE) transmission system, Allegheny Power Systems (APS) zone

200

200

120

Mount Storm-Pruntytown 500kV

66

AH1-387

Wind

FirstEnergy (FE) transmission system, Allegheny Power Systems (APS) zone

150

150

22.05

Meadowbrook-Greenland Gap 500kV

 

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 2, Cluster 67 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 67 projects.

This analysis is effectively a screening study to determine whether the addition of the Cluster 67 projects will meet the dynamics requirements of the NERC, FirstEnergy (FE), and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2028 summer peak load case, modified to include applicable projects. Cluster 67 projects have been dispatched online at maximum power output, with approximately unity power factor at the high side of the GSUs, 1.00 pu voltage at the generator terminals, and 1.01 pu voltage at the POI buses.

Cluster 67 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 166 contingencies were studied, each with a 20 second simulation time period (with 0.5/1.0 second initial run prior to any events). Studied faults included:

  1. Steady-state operation (Category P0);
  2. Three phase faults with normal clearing time on the intact network (Category P1);
  3. Single phase to ground faults with delayed clearing due to a stuck breaker (Category P4);
  4. Single phase to ground faults with delayed clearing as a result of protection failure (Category P5);
  5. Single phase to ground faults with normal clearing for common structure (Category P7).

 

No High Speed Reclosing (HSR) facilities were found in the vicinity of TC2 Cluster 67 projects.

For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the 2028 peak load case:

  1. Cluster 67 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  2. The system with Cluster 67 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
  3. Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
  4. No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

AG2-288 was tripped during the fault application closed to their POIs as a result of fictitious frequency spikes at the frequency relay monitored bus. i.e., inverter terminal bus. Therefore, frequency protection in the model was disabled for faults close to the POI of the projects due to the deficiency of PSSE frequency calculation for inverter-based generation facilities. No more tripping issue of the AG2-288 was observed.

No mitigations were found to be required for TC2 Cluster 67.

 

                                             

Table 1: TC2 Cluster 67 Projects

 

 

 

 

 

 

 

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

67

AG2-288

Storage

FirstEnergy (FE) transmission system, Allegheny Power System (APS) zone

150 MW

150 MW

150 MW

Stonewall 138 kV

AG2-423

Solar

FirstEnergy (FE) transmission system, Allegheny Power System (APS) zone

80 MW

80 MW

48 MW

Cherry Run - Harmony 138 kV

 

 

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 2, Cluster 70 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 70 projects.

This analysis is effectively a screening study to determine whether the addition of the Cluster 70 projects will meet the dynamics requirements of the NERC, FirstEnergy (FE), and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2028 summer peak load case, modified to include applicable projects. Cluster 70 projects have been dispatched online at maximum power output, with approximately unity power factor at the high side of the GSUs, 1.00 pu voltage at the generator terminals, and 1.01 pu voltage at the POI buses.

Cluster 70 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 53 contingencies were studied, each with a 20 second simulation time period (with 1.0 second initial run prior to any events). Studied faults included:

  1. Steady-state operation (Category P0);
  2. Three phase faults with normal clearing time on the intact network (Category P1);
  3. Single phase to ground faults with delayed clearing due to a stuck breaker (Category P4);
  4. Single phase to ground faults with delayed clearing as a result of protection failure (Category P5);
  5. Single phase to ground faults with normal clearing for common structure (Category P7).

 

High Speed Reclosing (HSR) facilities were found in the vicinity of TC2 Cluster 70 projects.

For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the 2028 peak load case:

  1. Cluster 70 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  2. The system with Cluster 70 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
  3. Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
  4. No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

No mitigations were found to be required for TC2 Cluster 70.

 

Table 1: TC2 Cluster 70 Projects

 

 

 

 

 

 

 

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

70

AG2-429

Solar + Storage

FirstEnergy (FE) transmission system, Allegheny Power System (APS) zone

46.5 MW

46.5 MW

46.5 MW

Burma – Armstrong 138 kV

 

Executive Summary for Stability Cluster

Executive Summary

New Service Request (project) in PJM Transition Cycle 2, Cluster 71 is listed in Table 1 below. This report will cover the dynamic analysis of Cluster 71 project.

This analysis is effectively a screening study to determine whether the addition of the Cluster 71 project will meet the dynamics requirements of the NERC, FirstEnergy (FE), and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2028 summer peak load case, modified to include applicable projects. Cluster 71 project has been dispatched online at maximum power output, with approximately unity power factor at the high side of the GSUs, 1.00 pu voltage at the generator terminals, and 1.01 pu voltage at the POI bus.

Cluster 71 project was tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 185 contingencies were studied, each with a 20 second simulation time period (with 1.0 second initial run prior to any events). Studied faults included:

  1. Steady-state operation (Category P0);
  2. Three-phase faults with normal clearing time (Category P1);
  3. Single-phase faults with stuck breaker (Category P4);
  4. Single-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure (Category P5);
  5. Single-phase to ground faults with normal clearing for common structure (Category P7).

Multiple-circuit tower line faults were identified for this study.

High Speed Reclosing (HSR) facilities were found in the vicinity of TC2 Cluster 71 project.

For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the 2028 peak load case:

  1. Cluster 71 project was able to ride through the faults (except for faults where protective action trips a generator(s)),
  2. The system with Cluster 71 project included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
  3. Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
  4. No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

No mitigations were found to be required for TC2 Cluster 71.

Table 1: TC2 Cluster 71 Project

 

 

 

 

 

 

 

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

71

AH1-545

Solar

FirstEnergy (FE) transmission system,

APS zone

200 MW

200 MW

20 MW

Wylie Ridge - Tidd 345 kV

 

Executive Summary for Stability Cluster

Executive Summary

New Service Request (project) in PJM Transition Cycle 2 Cluster 72 is listed in Table 1 below. This report will cover the dynamic analysis of Cluster 72 project.

This analysis is effectively a screening study to determine whether the addition of the Cluster 72 project will meet the dynamics requirements of the NERC, FirstEnergy (FE), and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2028 light load case, modified to include applicable projects. Cluster 72 project has been dispatched online at maximum power output, with approximately unity power factor at the high side of the GSUs, 1.05 pu voltage at the generator terminals, and 1.06 pu voltage at the POI buses.

Cluster 72 project was tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 130 contingencies were studied, each with a 20 second simulation time period (with 1.0 second initial run prior to any events). Studied faults included:

  1. Steady-state operation (Category P0);
  2. Three-phase faults with normal clearing time (Category P1);
  3. Single-phase faults with stuck breaker (Category P4);
  4. Single-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure (Category P5);
  5. Single-phase to ground faults with normal clearing for common structure (Category P7).

Multiple-circuit tower line faults were identified for this study.

High Speed Reclosing (HSR) facilities were found in the vicinity of TC2 Cluster 72 project.

For all simulations, the project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the normal 2028 light load case:

  1. Cluster 72 project was able to ride through the faults (except for faults where protective action trips a generator(s)).
  2. The system with Cluster 72 project included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
  3. Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
  4. No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

No mitigations were found to be required for TC2 Cluster 72.

Table 1: TC2 Cluster 72 Project

 

 

 

 

 

 

 

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

72

AH1-734

Natural Gas

FirstEnergy (FE) transmission system, APS zone

1058.4 MW

270.3 MW

268.6 MW

South Bend 500 kV

 

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 2, Cluster 73 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 73 projects.

This analysis is effectively a screening study to determine whether the addition of the Cluster 73 projects will meet the dynamics requirements of the NERC, FE-APS, and PJM reliability standards.

The load flow scenario for the analysis was based on the 2028 light load case, modified to include applicable projects. Cluster 73 projects have been dispatched online at maximum power output, with approximately unity power factors at the high side of the GSUs, 1.00 pu voltage at the generator terminals, and 1.05 pu voltage at the POI bus.

Cluster 73 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 168 contingencies were studied, each with a 20 second simulation time period (with 1.0 second initial run prior to any events). Studied faults included:

  1. Steady-state operation (Category P0);
  2. Three-phase faults with normal clearing time (Category P1);
  3. Single-phase faults with stuck breaker (Category P4);
  4. Single-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure (Category P5);
  5. Single-phase to ground faults with normal clearing for common structure (Category P7).

Multiple-circuit tower line faults were identified for this study.

High Speed Reclosing (HSR) facilities were found in the vicinity of TC1 Cluster 73 projects.

For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the 2028 light load case:

  1. Cluster 73 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  2. The system with Cluster 73 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
  3. Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
  4. No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

No mitigations were found to be required for TC2 Cluster 73.

Table 1: TC2 Cluster 73 Projects

 

 

 

 

 

 

 

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

73

AG2-582

Natural Gas

FirstEnergy (FE) transmission system,

APS zone

2100 MW

2100 MW

2075 MW

Flint Run 500 kV

 

Executive Summary for Stability Cluster

Executive Summary

 

New Service Requests (projects) in PJM Transition Cycle 2, Cluster 74 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 74 projects.

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 74 projects will meet the dynamics requirements of the NERC, EKPC and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2028 summer peak load case, modified to include applicable projects. Cluster 74 projects have been dispatched online at maximum power output, and the voltage schedule is set to achieve near unity power factor at the high side of the main transformer.

 

Cluster 74 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 498 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

       a)       Three-phase faults with normal clearing time;

       b)       Single-phase to ground bus faults with normal clearing time;

       c)       Single-phase to ground faults with delayed clearing due to a stuck breaker

       d)       Single-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure;

       e)       Single-phase faults with loss of multiple-circuit tower line.

       f)       Three-phase faults with normal clearing time and a failed high speed reclose attempt.

 

For all simulations, the Cluster 74 projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all of the fault contingencies tested on the 2028 peak load case:

       a)       Cluster 74 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

       b)       The system with Cluster 74 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3%.

       c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d)       No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

AG2-073, AG2-081, AH1-004, AH1-570, AH1-571, AH1-664, AH1-665, and AH1-666 all meet the 0.95 leading and lagging PF requirement.

 

No mitigations are required.

 

Table 1: TC2 Cluster 74 Projects

 

 

 

 

 

 

 

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

74

 

AG2-073

Solar

EKPC

53

53

50.88

Crooksville

69 KV

AG2-081

Solar

EKPC

30

30

18

Avon - Renaker 138 kV

AH1-004

Solar

EKPC

40

40

24

AH1-570

Solar

EKPC

25

25

15.6

Headquarters - Millersburg Junction 69 kV

AH1-571

Solar

EKPC

45

20

12.5

AH1-664

Solar

EKPC

100

100

66.8

Goddard - Plumville 138 kV

AH1-665

Solar

EKPC

180

80

53.5

AH1-666

Solar

EKPC

80

80

48

Flemingsburg - Spurlock 138 kV

 

Executive Summary for Stability Cluster

Executive Summary

 

New Service Requests (projects) in PJM Transition Cycle 2, Cluster 76 are listed in Table 2 below. This report will cover the dynamic analysis of Cluster 76 projects.

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 76 projects will meet the dynamics requirements of the NERC, EKPC and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2028 summer peak load case, modified to include applicable projects. Cluster 76 projects have been dispatched online at maximum power output and the voltage schedule set to achieve near unity power factor at the high side of the main transformer.

 

Cluster 76 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 120 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

       a)       Three-phase faults with normal clearing time;

       b)       Single-phase to ground bus faults with normal clearing time;

       c)       Single-phase to ground faults with delayed clearing due to a stuck breaker;

       d)       Single-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure;

       e)       Single-phase faults with loss of multiple-circuit tower line.

       f)       Three-phase faults with normal clearing time and a failed high speed reclose attempt.

 

For all simulations, the Cluster 76 projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all of the fault contingencies tested on the 2028 peak load case:

       a)       Cluster 76 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

       b)       The system with Cluster 76 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3%.

       c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d)       No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

AH1-239 meets the 0.95 leading and lagging PF requirement.

 

The following mitigations were required:

       •       Initial simulations resulted in sustained oscillations at AH1-239 and AG1-471 for loss of the AH1-471 POI – Wayne County 69 kV circuit. The loss of AH1-471 POI – Wayne county results in AH1-239 and AG1-471 becoming radially connected to Summer Shade 69 kV at the remote end of the 69 kV circuit. The composite short circuit ratio for this scenario drops from 4.19 (system intact) to 0.46 which is extremely weak. It was determined that a network upgrade is required to strengthen the AH1-239 POI under this condition. A network upgrade was developed with EKPC which involves building 15 miles of new transmission line from the AH1-239 POI to EKPC’s existing Monticello substation (N9688.0). The new transmission line would connect at Monticello via the radial line to the Homestead distribution substation, thereby using the same breaker at Monitcello to protect the new line. With the addition of the new 69 kV line, the contingencies that caused radial connection and instability of the AH1-239 project are resolved.

       •       Initial studies identified tripping of AG1-471 and AH1-239 as a result of overvoltage relays on the inverters timing out and tripping AG1-471 and AH1-239. The overvoltages were caused by the AH1-239 inverters entering High Voltage Ride Through (HVRT) mode and remaining in this mode of operation until the units tripped. With mitigation below implemented, all instances of AH1-239 and AG1-471 tripping were resolved.

 

Table 1: AH1-239 REECA1 Model Parameters

 

 

Parameter

Original Value

New Value

Vdip

0.88

0.9

Vup

1.12

1.1

Dbd1

-0.14

-0.1

Dbd2

0.14

0.1

 

 

Table 2: TC2 Cluster 76 Projects

 

 

 

 

 

 

 

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

76

AH1-239

Solar

EKPC

80

80

48

Upchurch – Zula 69 kV

 

 

Executive Summary for Stability Cluster

Executive Summary

 

New Service Requests (projects) in PJM Transition Cycle 2, Cluster 77 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 77 projects.

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 77 projects will meet the dynamics requirements of the NERC, EKPC and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2028 summer peak load case, modified to include applicable projects. Cluster 77 projects have been dispatched online at maximum power output, and the voltage schedule is set to achieve near unity power factor at the high side of the main transformer.

 

Cluster 77 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 67 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

       a)       Steady-state operation (20 second run);

       b)       Three-phase faults with normal clearing time;

       c)       Single-phase to ground bus faults with normal clearing time;

       d)       Single-phase to ground faults with delayed clearing due to a stuck breaker

       e)       Single-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure;

       f)       Single-phase faults with loss of multiple-circuit tower line.

       g)       Three-phase faults with normal clearing time and a failed high speed reclose attempt.

 

For all simulations, the Cluster 77 projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all of the fault contingencies tested on the 2028 peak load case:

       a)       Cluster 77 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

       b)       The system with Cluster 77 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3%.

       c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d)       No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

AG2-298 meets the 0.95 leading and lagging PF requirement.

 

AG2-298 exhibited slow reactive power recovery for several contingencies. As a result, AG2-298 POI voltage has not returned to pre-fault levels following the fault clearance. This issue did not cause any instabilities in the AC system. However, to improve the reactive power settling time, the integral and proportional gain values in power plant controller model (REPCA) and electrical controller model (REECA) models were modified as below.

       o       REPCA1:

        •  CON(J+2) = 5.5 (Ki, Reactive power PI control integral gain (pu))

       o       REECA1:

        •  CON(J+17) = 1 (Kqp (pu), Reactive power regulator proportional gain)
        • CON(J+18) = 10 (Kqi (pu), Reactive power regulator integral gain)
        •  CON(J+19) = 0.5 (Kvp (pu), Voltage regulator proportional gain)
        •  CON(J+20) = 5 (Kvi (pu), Voltage regulator integral gain)

 

Table 1: TC1 Cluster 77 Projects

 

 

 

 

 

 

 

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

77

AG2-298

Solar

EKPC

35

35

23.33

Sulphur Creek - Loretto

69 kV

 

 

Executive Summary for Stability Cluster

Executive Summary

 

New Service Requests (projects) in PJM Transition Cycle 2, Cluster 79 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 79 projects.

This analysis is effectively a screening study to determine whether the addition of the Cluster 79 projects will meet the dynamics requirements of the NERC, EKPC and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2028 summer peak load and light load cases, modified to include applicable projects. Cluster 79 projects have been dispatched online at maximum power output and the voltage schedule set to achieve near unity power factor at the high side of the main transformer.

Cluster 79 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 245 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

       a)       Steady-state operation;

       b)       Three-phase faults with normal clearing time;

       c)       Single-phase to ground bus faults with normal clearing time;

       d)       Single-phase to ground faults with delayed clearing due to a stuck breaker;

       e)       Single-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure;

       f)       Single-phase faults with loss of multiple-circuit tower line.

       g)       Three-phase faults with normal clearing time and a failed high speed reclose attempt.

 

For all simulations, the Cluster 79 projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all of the fault contingencies tested on the 2028 summer peak load and light load cases:

       a)       Cluster 79 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

       b)       The system with Cluster 79 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3%.

       c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d)       No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

AG2-424 meets the 0.95 leading and lagging PF requirement.

 

AH1-721 meets the 0.95 leading and 0.90 lagging PF requirement.

 

No mitigations were found to be required.

 

Table 1: TC2 Cluster 79 Projects

 

 

 

 

 

 

 

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

79

AG2-424

Solar

Storage

EKPC

63.25

63.25

34.95

Mognolia – Summersville Tap 69 kV

AH1-721

Natural Gas

EKPC

786

786

758.9507

Laurel River Dam – Cooper 161 kV

 

Executive Summary for Stability Cluster

Executive Summary:

New Service Requests (projects) in PJM Transition Cycle 2 (TC2) Cluster 81 are listed in Table 1 below. This report will cover the dynamic analysis of TC2 Cluster 81 projects.

Table 1: Transition Cycle 2 Cluster 81 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

81

AG2-074

Solar

PPL

38

38

26.2

Meckesville Tap 69 kV

81

AG2-479

Solar

PPL

20

0

4.1

Penns Tap-Richfield Tie 69 kV

81

AG2-481

Solar

PPL

20

0

4.1

Derry Tap-Derry 69 kV

81

AG2-484

Solar

PPL

20

0

4.1

Mifflintown Bus-Mifflintown Tap 69 kV

 

The purpose of the transient stability analysis is to determine the system impact of the generation facility. This study will determine system improvements, if any, needed to reduce violations in the transient stability analysis caused by the addition of the projects in TC2 Cluster 81.

 

The load flow scenario for the analysis was based on the Regional Transmission Expansion Plan (RTEP) 2028 summer peak and light load cases, modified to include applicable projects. TC2 Cluster 81 projects have been dispatched online at maximum power output with near unity power factor measured at the high-side of the main substation transformer.

 

TC2 Cluster 81 projects were tested for compliance with NERC, PJM, PPL and other applicable criteria. 199 contingencies were studied, each with a 20 second simulation time period. The contingencies studied included:

  • Steady-state operation (20 seconds)
  • Three-phase faults with normal clearing time
  • Single-phase bus faults with normal clearing time
  • Single-phase faults with stuck breaker
  • Single-phase Faults with loss of multiple-circuit tower line

 

For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

The results of the analysis were evaluated against the following recovery criteria per PJM’s Regional Transmission Planning Process and PPL’s transmission planning criteria:

  • All generators were able to ride through the faults (except for faults where protective action trips a generator(s)),
  • The system with TC2 Cluster 81 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3%.
  • Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus) and the final voltages are within the steady-state voltage ranges below per PPL’s transmission planning criteria.
      • P1, P2, P4, P7 Category Contingencies:
        • 0.893 to 1.019 p.u. for 69 kV facilities
        • 0.92 to 1.05 p.u. for 230, 115 facilities
        • 0.97 to 1.1 p.u. for 500 kV facilities
    • No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

AG2-074 met the 0.95 leading and lagging power factor requirement at the high side of the main transformer.

 

AG2-479 met the 0.95 leading and lagging power factor requirement at the high side of the main transformer.

 

AG2-481 met the 0.95 leading and lagging power factor requirement at the high side of the main transformer.

 

AG2-484 met the 0.95 leading and lagging power factor requirement at the high side of the main transformer.

 

The CSCR assessment indicates a weak grid concern for the AG2-074 and AG2-484 projects. An EMT analysis is recommended.

 

No mitigation is required to connect projects in TC2 Cluster 81.

 

Under light load (LL) conditions, instability was observed for a P1 fault on the Sunbury–Juniata 500 kV line. This outage was examined in the power flow case and the solution diverged.  A sensitivity analysis was performed to examine the impacts of a reduced generation dispatch.  With the reduced generation dispatch the system remained stable. The TC2 Cluster 81 queue projects were turned off for both dispatches and the results remained the same.

 

The results for the light load case indicate instability can occur dependent on the dispatch conditions. However, this instability was not caused by the addition of the TC2 Cluster 81 queue projects. If stability limitations within PPL are expected under light load conditions additional dispatching instructions from the TO for case conditioning can be included in the Phase 3 analysis.  Additionally, the summer peak case conditioning should be discussed with the TO the oscillations observed are not expected.

 

Instability was observed under light load conditions for multiple P4 contingencies at the Sunbury 69 kV bus attributed to the SUNBIPCT generator model. Sensitivity analysis was conducted by updating the SUNBIPCT load flow and dynamic models to reflect the AF2 base case configuration. With the updated SUNBIPCT representation, the system remained stable. The SUNBIPCT CT unit is modelled as a 36 MW generator; however, an additional 5 MW diesel unit may have been included in the TC2 base case, potentially contributing to differences in system response. It’s recommended the SUNBIPCT generator model be reviewed further to determine the correct modelling.

 

The following model tuning is recommended. The generator owner should provide their preferred adjustments for the issues described in the summary of results:

 

  • AG2-074
    • Increase relay pick-up time from 0.16 to 0.714 seconds for the protection model tripping for frequencies below 55 Hz to avoid generator tripping.
  • AF1-040
    • Increase relay pick-up time from 0.16 to 0.3 seconds for the protection model tripping for frequencies above 62.4 Hz to avoid generator tripping.
  • AG2-484
    • Increase relay pick-up time from 0.16 to 0.2126 seconds for the protection model tripping for frequencies above 64 Hz to avoid generator tripping.
  • AF2-361
    • It is recommended that the SMA SC 2800UP-US inverters for AF2-361 have its dynamic model REECAU1 Vup (CON J+1) be updated from 1.20 to 1.22 p.u. to avoid controller freezing.
    • Increase relay pick-up time from 0.16 to 0.2584 seconds for the protection model tripping for voltages above 1.2 p.u to avoid generator tripping.
    • Increase relay pick-up time from 0.16 to 0.2334 seconds for the protection model tripping for frequencies below 62 Hz to avoid generator tripping.
  • AF2-233
    • Increase relay pick-up time from 0.017 to 0.0209 seconds for the protection model tripping for voltages above 1.3 p.u to avoid generator tripping.

 

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 2, Cluster 82 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 82 projects.

This analysis is effectively a screening study to determine whether the addition of the Cluster 82 projects will meet the dynamics requirements of the NERC, FE, and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2028 summer peak load case, modified to include applicable projects. Cluster 82 projects have been dispatched online at maximum power output, with approximately unity power factor at the high side of the GSUs, 1.00 pu voltage at the generator terminals, and 1.02 pu voltage at the POI buses.

Cluster 82 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 134 contingencies were studied, each with a 20 second simulation time period (with 1.0 second initial run prior to any events). Studied faults included:

  1. Steady state operation (Category P0);
  2. Three phase faults with normal clearing time on the intact network (Category P1);
  3. Single phase to ground faults with delayed clearing due to a stuck breaker (Category P4);
  4. Single phase to ground faults with delayed clearing as a result of protection failure (Category P5);
  5. Single phase to ground faults with normal clearing for common structure (Category P7).

High Speed Reclosing (HSR) facilities were found in the vicinity of TC2 Cluster 82 projects.

For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the 2028 peak load case:

  1. Cluster 82 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  2. The system with Cluster 82 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
  3. Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
  4. No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

AF2-001, AF2-002, and AF1-321 were tripped during the fault application closed to their POIs as a result of fictitious frequency spikes at the frequency relay monitored bus, i.e., inverter terminal bus. Therefore, frequency protection in the model was disabled for faults close to the POI of the projects due to the deficiency of PSSE frequency calculation for inverter-based generation facilities. No more tripping issue of the AF2-001, AF2-002, and AF1-321 were observed.

No mitigations were found to be required for TC2 Cluster 82.

Table 1: TC2 Cluster 82 Projects

 

 

 

 

 

 

 

Cluster

Project

Fuel Type

Transmission Owner

MFO (MW)

MWE

(MW)

MWC

(MW)

Point of Interconnection

82

AG2-411

Solar

FirstEnergy (FE) transmission system, Pennsylvania Electric Co (PENELEC) zone

63

63

40.7

Statler Hill 115 kV

AH1-460

Solar

FirstEnergy (FE) transmission system, Pennsylvania Electric Co (PENELEC) zone

66

66

39.6

Hooversville - Scalp Level 115 kV

AG2-176

Solar

FirstEnergy (FE) transmission system, Pennsylvania Electric Co (PENELEC) zone

150

150

90

Geneva 115 kV

 

Executive Summary for Stability Cluster

PJM has reviewed this project submission and determined that a stability study is not required due to connection to a non-BES facility.

 

Executive Summary for Stability Cluster

Executive Summary

 

New Service Requests (projects) in PJM Transition Cycle 2, Cluster 85 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 85 projects.

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 85 projects will meet the dynamics requirements of the NERC, Dayton and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2028 summer peak load case, modified to include applicable projects. Cluster 85 projects have been dispatched online at maximum power output, and the voltage schedule is set to achieve near unity power factor at the high side of the main transformer.

 

Cluster 85 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 97 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

       a)       Steady-state operation (20 second run);

       b)       Three-phase faults with normal clearing time;

       c)       Single-phase to ground bus faults with normal clearing time;

       d)       Single-phase to ground faults with delayed clearing due to a stuck breaker

       e)       Single-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure;

       f)       Single-phase faults with loss of multiple-circuit tower line.

 

For all simulations, the Cluster 85 projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all of the fault contingencies tested on the 2028 peak load case:

       a)       Cluster 85 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

       b)       The system with Cluster 85 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3%.

       c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d)       No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

AG2-125 meets the 0.95 leading and lagging PF requirement.

 

No mitigation were found to be required.

Table 1: TC1 Cluster 85 Projects

 

 

 

 

 

 

 

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

85

AG2-125

Solar

DAYTON

69.9

0

15.44

Camden – Crystal 69 kV

 

Executive Summary for Stability Cluster

Executive Summary:

New Service Requests (projects) in PJM Transition Cycle 2, Cluster 86 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 86 projects.

This analysis is effectively a screening study to determine whether the addition of the cluster 86 projects will meet the dynamics requirements of the NERC, DPL and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2028 summer peak load case, modified to include applicable projects. Cluster 86 projects have been dispatched online at maximum power output, with 1.0 voltage at the terminal bus.

Cluster 86 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 127 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

  1. Steady-state operation (20 second run);
  2. Three-phase faults with normal clearing time;
  3. Single-phase bus faults with normal clearing time;
  4. Single-phase faults with stuck breaker;
  5. Single-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure;

No relevant tower faults or single-phase bus faults were identified for this study.

For generator interconnection studies, Category P3 and P6 contingencies will be evaluated on an as-needed basis.

Prior outage scenarios will not be considered for this study.

Stations at which the faults listed above will be applied are:

  • Carville 138 kV (AG2-380/AF1-036/AE2-112/AD2-076 POI)
  • Wye Mills 138 kV
  • Pondtown 138 kV (AB2-032/AB2-153 POI)
  • Cedar Creek 138 kV (AG2-447/AC1-091/AC1-092/AC1-093/AC1-094/AC2 184/AC2-185 POI)
  • Cedar Creek 230 kV
  • Clayton 138 kV (W1-062 POI)
  • Farmview 138 kV (AH1-672 POI)
  • Milford 138 kV
  • South Harrington 138 kV

For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the 2028 peak load case:

  1. Cluster 86 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  2. The system with Cluster 86 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes,
  3. Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus),
  4. No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

AG2-380, AG2-447, and AH1-672 meet the 0.95 leading and lagging PF requirement.

AH1-672 exhibited slow reactive power recovery following several contingencies (P1.22 and P1.23), though system stability was not compromised. To improve performance, model tuning was conducted. In the REPCA1 model, the reactive current compensation gain, Kc, was increased from 0.0 pu to 0.07 pu. This change improved reactive power recovery.

The IPCMD and IQCMD states in the REGCA1 model of AG2-447 GEN, and AH1-672 GEN showed erratic behavior for some contingencies in which these generators have been disconnected as part of the contingency event. Since the machine is disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

For several contingencies (P1.23, P1.24, P1.25, and P4.47), the W1-062/DEMEC NUG units were tripping when dispatched at their Pmax. This behavior was also observed even after turning off all queue projects in Cluster 86, indicating that the issue is related to the W1-062/DEMEC NUG units themselves. To avoid tripping, the generator output of these units was reduced from Pmax = 52 MW to Pgen = 45 MW.

For several contingencies (e.g., P1.30), following fault clearing the system exhibits small, damped oscillations as the excitation and voltage control systems stabilize the voltage. The voltage settles to its steady-state value within a few seconds, indicating stable system behavior. These oscillations do not impact the overall stability of the system.

High voltage spikes occurred in the simulations immediately after fault clearing for some of the contingencies studied (i.e., fault where spike is observed]). The voltage spike is a known artifact of the WECC generic renewable models as stated in the WECC Solar Plant Dynamic Model Guidelines: “It should be noted that generic dynamic models for inverter-based generator tend to produce a short-duration (a cycle or shorter) voltage spike at fault inception and clearing. These spikes should be ignored in most cases, as they do not represent the performance of actual hardware. They are simply a consequence of the model’s limited bandwidth, integration time step, and the way current injection models interface with the network solution.”

No mitigations were found to be required.

Table 1: TC2 Cluster 86 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

86

AG2-380

Storage

DPL

106.00

20.00

20.00

Carville 138 kV IV Substation

AG2-447

Solar

DPL

134.25

20.00

12.00

Cedar Creek 138 kV VII Substation

AH1-672

Solar

DPL

75.00

75.00

48.90

Farmview 138 kV Substation

 

Executive Summary for Stability Cluster

Executive Summary Summer Peak Analysis:

New Service Requests (projects) in PJM Transition Cycle 2, Cluster 87 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 87 projects.

This analysis is effectively a screening study to determine whether the addition of the Cluster 87 projects will meet the dynamics requirements of the NERC, AEC, and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2028 summer peak load case, modified to include applicable projects. Cluster 87 projects have been dispatched online at maximum power output, with 1.0 pu voltage at the terminal bus.

Cluster 87 projects were tested for compliance with NERC, PJM, Transmission Owner, and other applicable criteria. A steady-state condition and 268 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

  1. Steady-state operation (20-second run);
  2. Three-phase faults with normal clearing time; (including unsuccessful high-speed reclosing);
  3. Single-phase bus faults with normal clearing time;
  4. Single-phase faults single-phase delayed clearing due to a stuck breaker;
  5. Single-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure;
  6. Single-phase faults with loss of multiple-circuit tower line (and with unsuccessful high-speed reclosing).

For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism, with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the 2028 peak load case:

  1. Cluster 87 projects were able to ride through the faults (except for faults where protective action trips a generator(s)).
  2. The system with Cluster 87 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
  3. Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
  4. No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

AG2-297, AG2-616, AH1-260, AH1-641, and AH1-701 meet the 0.95 leading and lagging PF requirement.

AH1-701 N1 exhibited slow reactive power recovery within the 20 second simulation window for several contingencies. Simulation was run for 40 seconds for these contingencies and the results show that this issue did not cause instability in the system and the models can be tuned to achieve a faster reactive power output settlement upon request.

AH1-260 GEN 1 and GEN 2 exhibited slow reactive power recovery following several contingencies, though system stability was not compromised. To improve performance, model tuning was conducted. In the REPCA1 models, the reactive power PI control integral gain and the reactive current compensation gain, Ki and Kc increased from 0.5 pu to 3 pu and 0.0 pu to 0.06 pu, respectively. These changes improved reactive power recovery.

The IPCMD and IQCMD states in the REGCA model of AG2-297, AG2-616, AH1-260 GEN 1, AH1-260 GEN 2, and AH1-641 showed erratic behavior for some contingencies in which these generators have been disconnected as part of the contingency event. Since the machine is disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

At the Dennis 230 kV bus, which is one substation away from the Columbia 230 kV bus (AG2-297 POI), voltage oscillations were observed under multiple contingencies. These oscillations are caused by the behavior of the 150 MVAr SVC at Dennis. This does not cause instability in the system.

No mitigations were found to be required.

Table 1: TC2 Cluster 87 Projects

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

AG2-297

Solar

AEC

19

19

11.4

Cumberland 230 kV Substation

AG2-616

Solar

AEC

50

50

32.35

Churchtown – Upper Pittsgrove 138 kV

AH1-260

Storage

AEC

300

300

300

New Freedom – Monroe 230 kV

AH1-641

Solar

AEC

65

15

7

Churchtown – Upper Pittsgrove 138 kV

AH1-701

Natural Gas

AEC

61

0

20

Valero 69 kV

 

Executive Summary Light Load Analysis:

New Service Requests (projects) in PJM Transition Cycle 2, Cluster 87 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 87 projects.

This analysis is effectively a screening study to determine whether the addition of the Cluster 87 projects will meet the dynamics requirements of the NERC, AEC, and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2028 light load case, modified to include applicable projects. Cluster 87 projects have been dispatched online at maximum power output, with 1.0 pu voltage at the terminal bus.

Cluster 87 projects were tested for compliance with NERC, PJM, Transmission Owner, and other applicable criteria. A steady-state condition and 268 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

  1. Steady-state operation (20-second run);
  2. Three-phase faults with normal clearing time; (including unsuccessful high-speed reclosing);
  3. Single-phase bus faults with normal clearing time;
  4. Single-phase faults single-phase delayed clearing due to a stuck breaker;
  5. Single-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure;
  6. Single-phase faults with loss of multiple-circuit tower line (and with unsuccessful high-speed reclosing).

For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism, with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the 2028 light load case:

  1. Cluster 87 projects were able to ride through the faults (except for faults where protective action trips a generator(s)).
  2. The system with Cluster 87 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
  3. Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
  4. No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

AG2-297, AG2-616, AH1-260, AH1-641, and AH1-701 meet the 0.95 leading and lagging PF requirement.

AH1-701 N1 exhibited slow reactive power recovery within the 20 second simulation window for several contingencies. Simulation was run for 40 seconds for these contingencies and the results show that this issue did not cause instability in the system and the models can be tuned to achieve a faster reactive power output settlement upon request.

AH1-260 GEN 1 and GEN 2 exhibited slow reactive power recovery following several contingencies, though system stability was not compromised. To improve performance, model tuning was conducted. In the REPCA1 models, the reactive power PI control integral gain and the reactive current compensation gain, Ki and Kc increased from 0.5 pu to 3 pu and 0.0 pu to 0.06 pu, respectively. These changes improved reactive power recovery.

The IPCMD and IQCMD states in the REGCA model of AG2-297, AG2-616, AH1-260 GEN 1, AH1-260 GEN 2, and AH1-641 showed erratic behavior for some contingencies in which these generators have been disconnected as part of the contingency event. Since the machine is disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

At the Dennis 230 kV bus, which is one substation away from the Columbia 230 kV bus (AG2-297 POI), voltage oscillations were observed under multiple contingencies. These oscillations are caused by the behavior of the 150 MVAr SVC at Dennis. This does not cause instability in the system.

High voltage spikes occurred in the simulations immediately after fault clearing for some of the contingencies studied (i.e., fault where spike is observed]). The voltage spike is a known artifact of the WECC generic renewable models as stated in the WECC Solar Plant Dynamic Model Guidelines: “It should be noted that generic dynamic models for inverter-based generator tend to produce a short-duration (a cycle or shorter) voltage spike at fault inception and clearing. These spikes should be ignored in most cases, as they do not represent the performance of actual hardware. They are simply a consequence of the model’s limited bandwidth, integration time step, and the way current injection models interface with the network solution.”

No mitigations were found to be required.

Table 1: TC2 Cluster 87 Projects

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

AG2-297

Solar

AEC

19

19

11.4

Cumberland 230 kV Substation

AG2-616

Solar

AEC

50

50

32.35

Churchtown – Upper Pittsgrove 138 kV

AH1-260

Storage

AEC

300

300

300

New Freedom – Monroe 230 kV

AH1-641

Solar

AEC

65

15

7

Churchtown – Upper Pittsgrove 138 kV

AH1-701

Natural Gas

AEC

61

0

20

Valero 69 kV

 

Executive Summary for Stability Cluster

Executive Summary

New Service Requests (projects) in PJM Transition Cycle 2, Cluster 89 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 89 projects.

This analysis is effectively a screening study to determine whether the addition of the Cluster 89 projects will meet the dynamics requirements of the NERC, FirstEnergy (FE), and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2028 light load case, modified to include applicable projects. Cluster 89 projects have been dispatched online at maximum power output, with approximately unity power factor at the high side of the GSUs, 1.02 pu voltage at the generator terminals, and 1.03 pu voltage at the POI buses.

Cluster 89 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 140 contingencies were studied, each with a 20 second simulation time period (with 1.0 second initial run prior to any events). Studied faults included:

  1. Steady-state operation (Category P0);
  2. Three phase faults with normal clearing time on the intact network (Category P1);
  3. Single phase to ground faults with delayed clearing due to a stuck breaker (Category P4);
  4. Single phase to ground faults with delayed clearing as a result of protection failure (Category P5);
  5. Single phase to ground faults with normal clearing for common structure (Category P7).

 

High Speed Reclosing (HSR) facilities were found in the vicinity of TC2 Cluster 89 projects.

For all simulations, the projects under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the 2028 light load case:

  1. Cluster 89 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  2. The system with Cluster 89 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
  3. Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
  4. No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

 

AE2-211 was tripped during the fault application closed to its POI as a result of fictitious frequency spikes at the frequency relay monitored bus, i.e., inverter terminal bus. Therefore, frequency protection in the model was disabled for faults close to the POI of the project due to the deficiency of PSSE frequency calculation for inverter-based generation facilities. No more tripping issue of the AE2-211 was observed.

 

No other mitigations were found to be required for TC2 Cluster 89.

 

 

Table 1: TC2 Cluster 89 Projects

 

 

 

 

 

 

 

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

89

AH1-695

Nuclear

FirstEnergy (FE) transmission system, Metropolitan Edison Company (ME) zone

859

MW

859

MW

803

MW

Three Mile Island

230 kV

 

Executive Summary for Stability Cluster

Executive Summary:

New Service Requests (projects) in PJM Transition Cycle 2, Cluster 90 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 90 projects.

This analysis is effectively a screening study to determine whether the addition of the Cluster 90 projects will meet the dynamics requirements of the NERC, BGE and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2028 summer peak load case, modified to include applicable projects. Cluster 90 projects have been dispatched online at maximum power output, with 1.0 pu voltage at the terminal bus.

Cluster 90 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 255 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

  1. Steady-state operation (20 second run);
  2. Three-phase faults with normal clearing time (and with unsuccessful high-speed reclosing);
  3. Single-phase bus faults with normal clearing time;
  4. Single-phase faults with stuck breaker;
  5. Single-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure;
  6. Single-phase faults with loss of multiple-circuit tower line (and with unsuccessful high-speed reclosing).

For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the 2028 peak load case:

  1. Cluster 90 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  2. The system with Cluster 90 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
  3. Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
  4. No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

AG2-617, AH1-261 and AH1-725 meet the 0.95 leading and lagging PF requirement.

AG2-617 exhibited voltage limit violations following several contingencies, although overall system stability was maintained. To improve performance, model tuning was performed. In the REPCA1 model, droop control was enabled by setting the VC flag to 0. In addition, the reactive current compensation gain, Kc, was increased from 0.04 pu to 0.2 pu. These changes kept the voltage within the acceptable range of 0.95 pu to 1.05 pu.

AH1-261 GEN exhibited slow reactive power recovery within the 20 second simulation window for several contingencies. To improve its performance, model tuning was performed. In the REPCA1 model, the integral gain, Ki, was reduced from 0.25 pu to 0.0 pu. This adjustment improved reactive power recovery.

AH1-725 GEN exhibited voltage limit violations following several contingencies, although overall system stability was maintained. To improve performance, model tuning was performed. In the REPCA1 model, droop control was enabled by setting the VC flag to 0. This adjustment kept the voltage within the acceptable range of 0.95 pu to 1.05 pu.

The IPCMD and IQCMD states in the REGCA1 models of AG2-617, AH1-261, and AH1-725 showed erratic behavior for some contingencies in which AG2-617, AH1-261, and AH1-725 have been disconnected as part of the contingency event. Since the machine is disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause system instability.

No mitigations were found to be required.

Table 1: TC2 Cluster 90 Projects

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

90

AG2-617

Solar

BGE

55

55.0

33.0

Waugh Chapel 115 kV

AH1-261

Storage

BGE

135

135.0

135.0

Northeast - Riverside 230 kV

AH1-725

Storage

BGE

500

500

500

Conastone 500 kV

 

Executive Summary for Stability Cluster

Executive Summary SP Analysis:

New Service Requests (projects) in PJM Transition Cycle 2, Cluster 91 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 91 projects.

This analysis is effectively a screening study to determine whether the addition of the Cluster 91 projects will meet the dynamics requirements of the NERC, PEPCO, and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2028 summer peak load case, modified to include applicable projects. Cluster 91 projects have been dispatched online at maximum power output, with 1.0 pu voltage at the terminal bus.

Cluster 91 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. A steady-state condition and 224 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

  1. Steady-state operation (20 second run); (and with unsuccessful high-speed reclosing),
  2. Three-phase faults with normal clearing time;
  3. Single-phase bus faults with normal clearing time;
  4. Single-phase faults with stuck breaker;
  5. Three-phase faults with loss of multiple-circuit tower line; (and with unsuccessful high-speed reclosing).

There are no delayed (Zone 2) clearing faults due to dual primary relays being employed in the PEPCO 500/230 kV transmission system.

For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism, with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the 2028 summer peak load case:

  1. Cluster 91 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  2. The system with Cluster 91 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3 % for interarea modes and 4 % for local modes.
  3. Following fault clearing, all bus voltages recovered to a minimum of 0.7 pu after 2.5 seconds (except where protective action isolates that bus).
  4. No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

AG2-618 meets the 0.95 leading and lagging PF requirement at the high side of the main transformer with the addition of a 5 MVAR customer planned capacitor bank.

AH1-552 meets the 0.95 leading and lagging PF requirement at the high side of the main transformer.

AH1-744 meets the 0.9 lagging and 1.0 leading reactive power requirements with the addition of a customer planned 30 MVAR STATCOM device.

AG2-618 exhibited slow reactive power recovery for several contingencies. This issue did not result in system instability. The model was tuned to improve the reactive power settling time by updating the Kc parameter to 0.05 and setting the VCFlag to 0 in the REPCA1 module .

High voltage spikes occurred in the simulations immediately after fault clearing for some of the contingencies studied (i.e., fault where spike is observed). The voltage spike is a known artifact of the WECC generic renewable models as stated in the WECC Solar Plant Dynamic Model Guidelines : “It should be noted that generic dynamic models for inverter-based generator tend to produce a short-duration (a cycle or shorter) voltage spike at fault inception and clearing. These spikes should be ignored in most cases, as they do not represent the performance of actual hardware. They are simply a consequence of the model’s limited bandwidth, integration time step, and the way current injection models interface with the network solution.”

The IPCMD and IQCMD states in the REGCAU model of AG2-618 and AH1-552 showed erratic behavior for some contingencies in which these generators have been disconnected as part of the contingency event. Since the machine is disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

No mitigations were found to be required.

Table 1: Transition Cycle 2 Cluster 91 Queues

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

91

AG2-618

Solar

PEPCO

110.0

110

71.5

Morgantown 230 kV Substation

AH1-744

Gas

PEPCO

853.5

53.5

48.285

Cheltenham 500 kV Line

AH1-552

Hybrid

PEPCO

670.2

670.2

670.2

Chalk Point 230 kV Line

Executive Summary LL Analysis:

New Service Requests (projects) in PJM Transition Cycle 2, Cluster 91 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 91 projects.

This analysis is effectively a screening study to determine whether the addition of the Cluster 91 projects will meet the dynamics requirements of the NERC, PEPCO, and PJM reliability standards.

The load flow scenario for the analysis was based on the RTEP 2028 light load case, modified to include applicable projects. Cluster 91 projects have been dispatched online at maximum power output, with 1.0 pu voltage at the terminal bus.

Cluster 91 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. A steady-state condition and 224 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

  1. Steady-state operation (20 second run); (and with unsuccessful high-speed reclosing),
  2. Three-phase faults with normal clearing time;
  3. Single-phase bus faults with normal clearing time;
  4. Single-phase faults with stuck breaker;
  5. Three-phase faults with loss of multiple-circuit tower line; (and with unsuccessful high-speed reclosing).

There are no delayed (Zone 2) clearing faults due to dual primary relays being employed in the PEPCO 500/230 kV transmission system.

For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism, with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the 2028 light load case:

  1. Cluster 91 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  2. The system with Cluster 91 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3 % for interarea modes and 4 % for local modes.
  3. Following fault clearing, all bus voltages recovered to a minimum of 0.7 pu after 2.5 seconds (except where protective action isolates that bus).
  4. No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

AG2-618 meets the 0.95 leading and lagging PF requirement at the high side of the main transformer with the addition of a 5 MVAR customer planned capacitor bank.

AH1-552 meets the 0.95 leading and lagging PF requirement at the high side of the main transformer.

AH1-744 meets the 0.9 lagging and 1.0 leading reactive power requirements with the addition of a customer planned 30 MVAR STATCOM device.

AG2-618 exhibited slow reactive power recovery for several contingencies. This issue did not result in system instability. The model was tuned to improve the reactive power settling time by updating the Kc parameter to 0.05 and setting the VCFlag to 0 in the REPCA1 module .

High voltage spikes occurred in the simulations immediately after fault clearing for some of the contingencies studied (i.e., fault where spike is observed). The voltage spike is a known artifact of the WECC generic renewable models as stated in the WECC Solar Plant Dynamic Model Guidelines : “It should be noted that generic dynamic models for inverter-based generator tend to produce a short-duration (a cycle or shorter) voltage spike at fault inception and clearing. These spikes should be ignored in most cases, as they do not represent the performance of actual hardware. They are simply a consequence of the model’s limited bandwidth, integration time step, and the way current injection models interface with the network solution.”

The IPCMD and IQCMD states in the REGCAU model of AG2-618 and AH1-552 showed erratic behavior for some contingencies in which these generators have been disconnected as part of the contingency event. Since the machine is disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

No mitigations were found to be required.

Table 1: Transition Cycle 2 Cluster 91 Queues

Cluster

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

91

AG2-618

Solar

PEPCO

110.0

110

71.5

Morgantown 230 kV Substation

AH1-744

Gas

PEPCO

853.5

53.5

48.285

Cheltenham 500 kV Line

AH1-552

Hybrid

PEPCO

670.2

670.2

670.2

Chalk Point 230 kV Line

 

Executive Summary for Stability Cluster

Executive Summary:

New Service Requests (projects) in PJM Transition Cycle 2, Cluster 93 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 93 projects.

This analysis is effectively a screening study to determine whether the addition of the Cluster 93 projects will meet the dynamics requirements of the NERC, PJM, and Transmission Owner reliability standards.

The load flow scenario for the analysis was based on the RTEP 2028 light load case, modified to include applicable projects. Cluster 93 projects have been dispatched online at maximum power output.

Cluster 93 projects were tested for compliance with NERC, PJM, Transmission Owner and other applicable criteria. Steady-state condition and 374 contingencies were studied, each with a 20 second simulation time period. Studied faults included:

  1. Steady-state operation (20 second run);
  2. Three-phase faults with normal clearing time; (and with unsuccessful high speed reclosing, when applicable);
  3. Single-phase bus faults with normal clearing time;
  4. Single-phase faults with stuck breaker;
  5. Single-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure;
  6. Single-phase faults with loss of multiple-circuit tower line; (and with unsuccessful high-speed reclosing, when applicable).

For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism, with all states returning to an acceptable new condition following the disturbance.

For all of the fault contingencies tested on the 2028 light load case:

  1. Cluster 93 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),
  2. The system with Cluster 93 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.
  3. Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).
  4. No transmission element tripped, other than those either directly connected or designed to trip as a consequence of that fault.

AH1-703, AH1-710, AH1-715 and AH1-722 meet the leading and lagging PF requirements.

The initial results showed that, when using the standard clearing times provided by PJM for each area, the AH1-710 units tripped due to angle deviation for three P1 contingencies and one P5 contingency involving the loss of the Salem–Hope Creek 500 kV circuit or the Hope Creek–Red Lion 500 kV circuit (P1.04, P1.15, P1.17, and P5.02). Impact study reports for prior uprates of this plant were reviewed, and it was found that shorter clearing times had been used for 500 kV circuit breakers in Salem and nearby substations for uprate H17. Accordingly, these tripping events were addressed, for those contingencies only, by adopting the clearing times used in the impact study report of the prior uprate H17.

In the initial results, the response of all generators associated with the cluster queue projects, as well as some nearby generators, exhibited undamped oscillations under several contingencies. These oscillations were observed to persist beyond 40 seconds of simulation. Further analysis indicated that they were driven by the response of the two AH1-710 units. To address this issue, the voltage regulator gain (Ka) in the excitation system models of the two AH1-710 units was reduced from 500 to 100 pu and from 800 to 100 pu, respectively.

In multiple contingencies (P1.01, P1.02, P1.14, P4.01-P4.04, P4.06, P4.08, P4.27, P4.28, P4.30 and P4.32), a well-damped oscillation is observed in the system response after approximately 15 seconds of simulation. To investigate this, the queue projects were GNETted and the contingencies were re-simulated. The results indicate that these oscillations are not related to the queue projects. Accordingly, the normal simulations for these contingencies were extended to 35 seconds, and it was confirmed that the system remains stable and these oscillations completely damp out.

In three contingencies (P1.01, P1.02, and P1.14), the active power of the two combustion turbine units of AH1-715 (GTG1 and GTG2) settles slightly above the pre-fault value (approximately 1%). Since the deviation is small, occurs in only three contingencies, and does not cause instability in either the system or the units, no further action is required. Further investigation can be conducted upon request.

 

For contingencies in which the corresponding Cluster 93 units are tripped according to the contingency definition (e.g., P1.02), the rotor angle exhibits large deviations because the machine is no longer electrically connected to the system. With electrical torque reduced to zero, the rotor accelerates freely based on its mechanical input and inertia. Consequently, the reported rotor angle drifts relative to the system reference and is not meaningful for stability evaluation.

No mitigations were found to be required.

Table 1: TC2 Cluster 93 Projects

Project

Fuel Type

Transmission Owner

MFO

MWE

MWC

Point of Interconnection

AH1-703

Gas

PSEG

670.61

35.61

51.254

Bergen 230 kV

AH1-710

Nuclear

PSEG

2650.8

256.8

228.2

Salem 500 kV

AH1-715

Gas

PSEG

803.17

127.17

149.369

Linden 230 kV & Linden 138 kV

AH1-722

Gas

PSEG

806.4

130.4

158.1

Linden 230 kV

 

Executive Summary for Stability Cluster

Executive Summary

 

New Service Request AG2-106 in PJM Transition Cycle 2, is listed in Table 1 below. This report will cover the dynamic analysis of AG2-106 project.

 

This analysis is effectively a screening study to determine whether the addition of the AG2-106 project will meet the dynamics requirements of the NERC, AEP and PJM reliability standards.

 

Since AG2-106 serves as a CIRs-only uprate to AG1-125, AG2-106 was dispatched for stability analysis according to the following scenarios:

       a)       Scenario 1: AG2-106 dispatched at full MFO injection at the POI with PV MW contribution maxed out and no/reduced MW contribution from BESS.

       b)       Scenario 2: AG2-106 dispatched at full MFO injection at the POI with BESS MW contribution maxed out, and no/reduced PV MW injection.

       c)       Scenario 3: AG2-106 dispatched at full MFO injection at the POI with PV and BESS MW contribution proportional to their capacity.

       d)       Scenario 4: AG2-106 dispatched to full capacity with PV and BESS MW injection maxed out.

 

This report describes a dynamic simulation analysis of TC2 AG2-106 for dispatch Scenario 3 as part of the overall system impact study.

 

The load flow scenario for the analysis was based on the RTEP 2028 Summer Peak, modified to include applicable project. AG2-106 project has been dispatched online at maximum power output, with 1.01 p.u. and 1.0 p.u. voltage at the terminal buses of AG2-106 GEN1 and GEN2.

 

Transition Cycle 2 AG2-106 will be tested for compliance with NERC, PJM and other applicable criteria. The contingencies will be studied with a 20 second simulation time. Contingencies to be studied include:

       a.       Steady-state operation (Category P0);

       b.       Three-phase faults with normal clearing time (and with unsuccessful high-speed reclosing) (Category P1);

       c.       Single-phase bus faults with normal clearing time (Category P2);

       d.       Single-phase faults with stuck breaker (Category P4);

       e.       Single-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure (Category P5);

       f.       Three-phase faults with loss of multiple-circuit tower line; (and with unsuccessful high-speed reclosing) (Category P7).

 

High Speed Reclosing (HSR) facilities were found in the vicinity of TC2 AG2-106 project.

 

Prior outage scenarios will not be considered for this study.

 

For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all the fault contingencies tested on the 2028 peak load case:

       a)       AG2-106 project was able to ride through the faults (except for faults where protective action trips a generator(s)),

       b)       The system with AG2-106 project included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.

       c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d)       No transmission element tripped, other than those either directly connected or designed to trip because of that fault.

 

In P1.38, multiple unit trips were observed following a fault at the Logtown 138 kV bus. Further investigation determined that all tripping events were associated with T1-131 units, listed below, which belong to a legacy wind facility:

       a)       TR3_G114 with ID: ‘W1’ (PSS/E Bus# 270191),

       b)       TR4_S_V150 with ID: ‘W1’ (PSS/E Bus# 270246),

       c)       TR4_N_V150 with ID: ‘W3’ (PSS/E Bus# 270247),

       d)       TR4_N_V136 with ID: ‘W2’ (PSS/E Bus# 247521).

 

Additional analysis indicated that these units were operating at relatively low output levels (approximately 15% of their Pmax), while the system strength in the area remained adequate. This raised concerns regarding the accuracy of the dynamic model for T1-131. Sensitivity testing using alternative generic dynamic models resulted in no observed tripping.

 

Given the limited contribution of the T1-131 units, they were subsequently g-netted, and no further issues were identified. PJM will consider the latest as-built model of T1-131 for validation in TC2 Phase 3 studies.

 

The IPCMD and IQCMD states in the REGCA1 model of AG2-106 showed erratic behavior for some contingencies in which AG2-106 has been disconnected as part of the contingency event. Since the machines are disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

 

No mitigations were found to be required.

 

Table 1: Transition Cycle 2 AG2-106 Projects

 

 

 

 

 

Project

Fuel Type

Transmission Owner

MFO

(MW)

CIR

(MW)

Point of Interconnection

AG2-106

Battery 

AEP 

0

150

Marysville – Flatlick 765 kV 

 

Executive Summary for Stability Cluster

Executive Summary

 

New Service Request AG2-107 in PJM Transition Cycle 2, is listed in Table 1 below. This report will cover the dynamic analysis of AG2-107 project.

 

This analysis is effectively a screening study to determine whether the addition of the AG2-107 project will meet the dynamics requirements of the NERC, AEP and PJM reliability standards.

 

Since AG2-107 serves as a CIRs-only uprate to AG1-126, AG2-107 was dispatched for stability analysis according to the following scenarios:

       a)       Scenario 1: AG2-107 dispatched at full MFO injection at the POI with PV MW contribution maxed out and no/reduced MW contribution from BESS.

       b)       Scenario 2: AG2-107 dispatched at full MFO injection at the POI with BESS MW contribution maxed out, and no/reduced PV MW injection.

       c)       Scenario 3: AG2-107 dispatched at full MFO injection at the POI with PV and BESS MW contribution proportional to their capacity.

       d)       Scenario 4: AG2-107 dispatched to full capacity with PV and BESS MW injection maxed out.

 

This report describes a dynamic simulation analysis of TC2 AG2-107 for dispatch Scenario 3 as part of the overall system impact study.

 

The load flow scenario for the analysis was based on the RTEP 2028 Summer Peak, modified to include applicable project. AG2-107 project has been dispatched online at maximum power output, with 1.01 p.u. voltage at the terminal bus.

 

Transition Cycle 2 AG2-107 will be tested for compliance with NERC, PJM and other applicable criteria. The contingencies will be studied with a 20 second simulation time. Contingencies to be studied include:

       a.       Steady-state operation (Category P0);

       b.       Three-phase faults with normal clearing time (and with unsuccessful high-speed reclosing) (Category P1);

       c.       Single-phase bus faults with normal clearing time (Category P2);

       d.       Single-phase faults with stuck breaker (Category P4);

       e.       Single-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure (Category P5);

       f.       Three-phase faults with loss of multiple-circuit tower line; (and with unsuccessful high-speed reclosing) (Category P7).

 

High Speed Reclosing (HSR) facilities were found in the vicinity of TC2 AG2-107 project.

 

Prior outage scenarios will not be considered for this study.

 

For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all the fault contingencies tested on the 2028 peak load case:

       a)       AG2-107 project was able to ride through the faults (except for faults where protective action trips a generator(s)),

       b)       The system with AG2-107 project included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.

       c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d)       No transmission element tripped, other than those either directly connected or designed to trip because of that fault.

 

In P1.38, multiple unit trips were observed following a fault at the Logtown 138 kV bus. Further investigation determined that all tripping events were associated with T1-131 units, listed below, which belong to a legacy wind facility:

       a)       TR3_G114 with ID: ‘W1’ (PSS/E Bus# 270191),

       b)       TR4_S_V150 with ID: ‘W1’ (PSS/E Bus# 270246),

       c)       TR4_N_V150 with ID: ‘W3’ (PSS/E Bus# 270247),

       d)       TR4_N_V136 with ID: ‘W2’ (PSS/E Bus# 247521).

 

Additional analysis indicated that these units were operating at relatively low output levels (approximately 15% of their Pmax), while the system strength in the area remained adequate. This raised concerns regarding the accuracy of the dynamic model for T1-131. Sensitivity testing using alternative generic dynamic models resulted in no observed tripping.

 

Given the limited contribution of the T1-131 units, they were subsequently g-netted, and no further issues were identified. PJM will consider the latest as-built model of T1-131 for validation in TC2 Phase 3 studies.

 

The IPCMD and IQCMD states in the REGCA1 model of AG2-107 showed erratic behavior for some contingencies in which AG2-107 has been disconnected as part of the contingency event. Since the machines are disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

 

No mitigations were found to be required.

 

Table 1: Transition Cycle 2 AG2-107 Projects

 

 

 

 

 

Project

Fuel Type

Transmission Owner

MFO

(MW)

CIR

(MW)

Point of Interconnection

AG2-107

Battery 

AEP 

0

150

Marysville – Flatlick 765 kV 

 

 

Executive Summary for Stability Cluster

Executive Summary

 

New Service Request AH1-306 in PJM Transition Cycle 2, is listed in Table 1 below. This report will cover the dynamic analysis of AH1-306 project.

 

This analysis is effectively a screening study to determine whether the addition of AH1-306 project will meet the dynamics requirements of the NERC, AEP and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2028 Summer Peak, modified to include applicable projects. AH1-306 project has been dispatched online at maximum power output, with 1.01 voltage at the terminal bus.

 

Transition Cycle 2 AH1-306 will be tested for compliance with NERC, PJM and other applicable criteria. The contingencies will be studied with a 20 second simulation time. Contingencies to be studied include:

       a)       Steady-state operation (Category P0);

       b)       Three-phase faults with normal clearing time (and with unsuccessful high-speed reclosing) (Category P1);

       c)       Single-phase bus faults with normal clearing time (Category P2);

       d)       Single-phase faults with stuck breaker (Category P4);

       e)       Single-phase faults placed at 80% of the line with delayed (Zone 2) clearing at line end remote from the fault due to primary communications/relay failure (Category P5).

       f)       Three-phase faults with loss of multiple-circuit tower line; (and with unsuccessful high-speed reclosing) (Category P7).

 

High Speed Reclosing (HSR) facilities were found in the vicinity of TC2 AH1-306 project.

 

Prior outage scenarios will not be considered for this study.

 

For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all the fault contingencies tested on the 2028 peak load case:

       a)       AH1-306 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

       b)       The system with AH1-306 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.

       c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d)       No transmission element tripped, other than those either directly connected or designed to trip because of that fault.

 

The IPCMD and IQCMD states in the REGCA1 models of AH1-306 showed erratic behavior for some contingencies in which AH1-306 has been disconnected as part of the contingency event. Since the machines are disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

 

For several contingencies AE2-297 unit has been disconnected for over voltage relay settings where clearing time was 0.001 second for that relay settings. Added two cycles to original pick up to prevent fictious post-fault overvoltage tripping. It should be noted that generic dynamic models for inverter-based generators tend to produce a short-duration (a cycle or shorter) voltage spike at fault inception or clearing. These spikes can be ignored in most cases as they do not represent the performance of the actual hardware. They are simply a consequence of the model’s limited bandwidth, integration time step, and the way current injection models interface with the network solution.

 

Fictitious frequency response at AH1-306 generator bus tripped the queue project due to the action of instantaneous under-frequency relay for P1.24 and P1.26 contingencies. Therefore, the relay pickup times for frequency relay instances 97161309 was set to 20 seconds to avoid fictitious frequency tripping of the unit.

No mitigations were found to be required.

 

Table 1: Transition Cycle 2 AH1-306 CIR Uprate Change in Model

 

 

 

 

Queue Project

Gross Outputs (MW)

Aux + Station + Fictitious Load (MW)

MFO (MW)

Inverter Change

AE1-207

161.55

3.12 MW + 0.029 MVAr

160

Original solar facility

AE2-172

40.824

0.848 MW + 0.399 MVAr

40

BESS addition

AH1-306

161.55

0.16 MW + 0.1 MVAr

0

Change in inverter type

 

 

Executive Summary for Stability Cluster

Executive Summary

 

New Service Requests AH1-055 and AH1-537 in PJM Transition Cycle 2, Cluster 92 are listed in Table 1 below. This report will cover the dynamic analysis of Cluster 92 projects.

 

This analysis is effectively a screening study to determine whether the addition of the Cluster 92 projects will meet the dynamics requirements of the NERC, OVEC and PJM reliability standards.

 

The load flow scenario for the analysis was based on the RTEP 2028 Summer Peak, modified to include applicable projects. Cluster 92 projects have been dispatched online at maximum power output, with 1.0 voltage at the terminal bus.

 

Transition Cycle 2 Cluster 92 will be tested for compliance with NERC, PJM and other applicable criteria. The contingencies will be studied with a 20 second simulation time. Contingencies to be studied include:

       a)       Steady-state operation (Category P0);

       b)       Three-phase faults with normal clearing time (Category P1);

       c)       Single-phase bus faults with normal clearing time (Category P2);

       d)       Single-phase faults with stuck breaker (Category P4);

       e)       Single-phase faults with loss of multiple-circuit tower line (Category P7).

 

High Speed Reclosing (HSR) facilities were not found in the vicinity of TC2 Cluster 92 projects.

 

Prior outage scenarios will not be considered for this study.

 

There are no delayed (Zone 2) clearing faults due to dual primary relays being employed in the OVEC 345 kV transmission system.

 

For all simulations, the queue project under study along with the rest of the PJM system were required to maintain synchronism and with all states returning to an acceptable new condition following the disturbance.

 

For all the fault contingencies tested on the 2028 peak load case:

       a)       Cluster 92 projects were able to ride through the faults (except for faults where protective action trips a generator(s)),

       b)       The system with Cluster 92 projects included is transiently stable and post-contingency oscillations were positively damped with a damping margin of at least 3% for interarea modes and 4% for local modes.

       c)       Following fault clearing, all bus voltages recovered to a minimum of 0.7 per unit after 2.5 seconds (except where protective action isolates that bus).

       d)       No transmission element tripped, other than those either directly connected or designed to trip because of that fault.

 

A slight delay in reactive power recovery was observed in the AH1-055 response for some contingencies (e.g. P1.12 among other contingencies). The generator terminal voltage and the system voltage in the area remain within acceptable ranges, and sufficient dynamic VAR support is available nearby. However, the facility’s performance could be improved through model tuning, which can be evaluated in TC2 Phase 3 if reactive power recovery becomes a critical concern.

 

The IPCMD and IQCMD states in the REGCA1 models of AH1-055 showed erratic behavior for some contingencies in which AH1-055 has been disconnected as part of the contingency event. Since the machines are disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

 

The IPCMD and IQCMD states in the REGCA1 models of AH1-537 showed erratic behavior for some contingencies in which AH1-537 has been disconnected as part of the contingency event. Since the machines are disconnected and no active or reactive power is injected into the system, this behavior is likely fictitious and a limitation of the software. This does not cause instability in the system.

 

The rotor angle of the 05AMG2 demonstrates slow rotor angle dynamics and did not reach a steady-state response within the 20-second simulation window for several contingencies. The simulations were extended to 40 seconds, after which the rotor angle successfully stabilized.

 

No mitigations were found to be required.

Table 1: Transition Cycle 2 Cluster 92 Queues

 

 

 

 

Project

Fuel Type

Transmission Owner

MFO (MW)

Point of Interconnection

AH1-055

Solar

OVEC

220

Kyger Creek - Don Marquis 345 kV

AH1-537

Solar

OVEC

178.5

Pierce - Kyger Creek 345 kV

 

 

 

  

Shared POIs

At PJM's discretion, New Service Requests in a Cycle at the same Point of Interconnection may be aggregated for the purposes of System Impact Studies, in accordance with PJM Open Access Transmission Tariff, Part VII, Subpart D, section 307.A.2.a.iii.

Shared POI Name New Service Requests Aggregated
AE2-094 500 kV - Dominion AG2-339
AF1-122 / AG2-056 / AH1-060 (ATSI) AG2-057, AH1-060
AG2-068 500 kV - Dominion AG2-068, AG2-069, AG2-369
AG2-198 230 kV - Dominion AG2-198, AG2-566
AG2-440 115 kV - Dominion AG2-440, AG2-441
AG2-570 500 kV - Dominion AG2-570, AG2-571
Cashie 230 kV - Dominion AG2-382, AH1-271
Cunningham 500 kV (Dominion) AH1-681, AH1-712, AH1-723
Deepwater - Upper Pittsgrove 138 kV - AEC AG2-616, AH1-641
Dumont 345 kV (AEP) AG2-230, AH1-153
Harbert Metering 138 kV (AEP) AG2-184, AH1-617
Ladysmith CT (Dominion) AH1-682, AH1-683, AH1-691, AH1-692, AH1-694
Meadowlake 345kV (AEP) AG2-014, AG2-491, AG2-492
Mississinewa 138kV (AEP) AG2-191, AG2-192
Nelson-Electric Junction 345kV - ComEd AG2-660, AH1-044, AH1-150, AH1-151
New AE2-045 swyd (Olive - Reynolds 345 kV) (AEP) AH1-302, AH1-305
New AE2-219 swyd (Bluff Point - Randolph 138 kV) (AEP) AG2-550, AG2-551
New AG1-125 swyd (Marysville - Flatlick 765 kV) (AEP) AG2-104, AG2-106, AG2-107
New AG1-226 swyd (Dequine - Eugene 345 kV) (AEP) AG2-163, AG2-343, AG2-345
New AG2-081 138 kV swyd (Avon - Renaker 138 kV) (EKPC) AG2-081, AH1-004
New AG2-248 swyd (East Elkhart - Elcona Tap) (AEP) AG2-248, AG2-332
New AG2-289 swyd (Amsden - Fremont Center 69 kV) (AEP) AG2-289, AG2-290
New AG2-548 swyd (Corwin -Elk 138 kV) (AEP) AG2-548, AG2-665
New AH1-072 swyd (Red Onion - VC5 69 kV) (AEP) AH1-072, AH1-073
New AH1-247 138kV swyd - APS AH1-247, AH1-248, AH1-249
New AH1-570 swyd (Headquarters - Millersburg Junction 69 kV) (EKPC) AH1-570, AH1-571
New AH1-664 swyd (Goddard - Plumville 138 kV) (EKPC) AH1-664, AH1-665
Nottingham 138 kV (AEP) AG2-082, AH1-580
Peter's Mountain 138 kV (AEP) AH1-144, AH1-145
Powerton ;B 345 kV (ComEd) AG2-363, AG2-364
Remington CT (Dominion) AH1-684, AH1-685, AH1-693
Silver Lake 345 kV (ComEd) AG2-544, AG2-545
Winterpock 230kV - Dominion AH1-106, AH1-107

CIR Claims From Deactivated Generators

The following Transition Cycle 2 projects intend to claim and transfer CIRs from deactivated capacity generation resources. PJM performed a reliability analysis of the impacts to the system capability for the proposed transfers of CIRs from the deactivated generation resources.

Project Status CIR Claimed POI Transfer Details
AG2-068 Active 60.0 Yes
Unit Name Status CIR Claimed POI Transfer
Yorktown 3 Deactivated Generator 60.0 Yes
AG2-069 Active 90.0 Yes
Unit Name Status CIR Claimed POI Transfer
Yorktown 3 Deactivated Generator 90.0 Yes
AG2-077 Active 120.0 Yes
Unit Name Status CIR Claimed POI Transfer
Yorktown 3 Deactivated Generator 120.0 Yes
AG2-095 Active 10.8 Yes
Unit Name Status CIR Claimed POI Transfer
Yorktown 3 Deactivated Generator 10.8 Yes
AG2-152 Active 79.0 Yes
Unit Name Status CIR Claimed POI Transfer
Chesterfield 6 Deactivated Generator 52.0 Yes
Yorktown 3 Deactivated Generator 27.0 Yes
AG2-193 Active 12.0 Yes
Unit Name Status CIR Claimed POI Transfer
Yorktown 3 Deactivated Generator 12.0 Yes
AG2-213 Active 48.0 Yes
Unit Name Status CIR Claimed POI Transfer
Yorktown 3 Deactivated Generator 48.0 Yes
AG2-369 Active 51.6 Yes
Unit Name Status CIR Claimed POI Transfer
Chesterfield 6 Deactivated Generator 51.6 Yes
AG2-384 Active 24.0 Yes
Unit Name Status CIR Claimed POI Transfer
Possum Point 5 Deactivated Generator 24.0 Yes
AG2-440 Active 45.0 Yes
Unit Name Status CIR Claimed POI Transfer
Yorktown 3 Deactivated Generator 45.0 Yes
AG2-441 Active 67.8 Yes
Unit Name Status CIR Claimed POI Transfer
Yorktown 3 Deactivated Generator 67.8 Yes
AG2-618 Active 71.5 No
Unit Name Status CIR Claimed POI Transfer
Morgantown Unit 1 Deactivated Generator 35.75 No
Morgantown Unit 2 Deactivated Generator 35.75 No
AH1-071 Active 12.0 Yes
Unit Name Status CIR Claimed POI Transfer
Yorktown 3 Deactivated Generator 12.0 Yes
AH1-138 Active 8.4 Yes
Unit Name Status CIR Claimed POI Transfer
Yorktown 3 Deactivated Generator 8.4 Yes
AH1-221 Active 45.0 Yes
Unit Name Status CIR Claimed POI Transfer
Possum Point 5 Deactivated Generator 45.0 Yes
AH1-227 Active 30.78 Yes
Unit Name Status CIR Claimed POI Transfer
Yorktown 3 Deactivated Generator 30.78 Yes
AH1-552 Active 670.2 No
Unit Name Status CIR Claimed POI Transfer
Chalk Point Unit 1 Deactivated Generator 333.0 No
Chalk Point Unit 2 Deactivated Generator 337.2 No
AH1-721 Active 116.0 Yes
Unit Name Status CIR Claimed POI Transfer
Cooper 1 Future Deactivation 116.0 Yes

Cost Summary

The table below shows a summary of the total planning level cost estimates for each individual New Service Request received by PJM and studied in Transition Cycle 2 Phase II System Impact Study. These network upgrade costs are subject to change as a result of a facility study performed by the Interconnected Transmission Owner during the Phase II System Impact Study.

Project ID Transmission Owner Interconnection Facilities (TOIF) Physical Interconnection Network Upgrades System Reliability Network Upgrades Affected System Study Reinforcements Additional Charges Total Cost Cost Details
AG2-014 $0 $1,780,859 $0 $21,125,434 $603,891 $23,510,184
AG2-016 $730,161 $976,499 $0 $0 $27,580 $1,734,240
AG2-029 $1,659,783 $31,927,955 $0 $65,040 $1,117,553 $34,770,331
AG2-037 $33,300 $0 $144,300 $0 $0 $177,600
AG2-049 $0 $0 $0 $0 $0 $0
AG2-057 $28,656 $733,106 $0 $0 $2,636 $764,397
AG2-061 $0 $511,813 $0 $12,124 $0 $523,937
AG2-062 $2,659,495 $152,001 $0 $0 $584,091 $3,395,587
AG2-068 $1,094,345 $13,755,464 $0 $143,000 $276,414 $15,269,223
AG2-069 $1,094,345 $13,755,464 $0 $214,000 $276,414 $15,340,223
AG2-072 $3,195,258 $107,970,412 $20,391,698 $67,900,000 $338,434 $199,795,802
AG2-073 $1,863,000 $9,637,000 $0 $0 $0 $11,500,000
AG2-074 $636,546 $1,218,744 $0 $0 $0 $1,855,290
AG2-077 $0 $0 $14,008,499 $0 $486,439 $14,494,938
AG2-081 $845,000 $6,285,500 $0 $6,394,854 $0 $13,525,354
AG2-082 $609,937 $3,179,540 $0 $0 $375,078 $4,164,556
AG2-086 $0 $30,366,362 $0 $0 $0 $30,366,362
AG2-088 $5,270,575 $8,334,288 $0 $0 $499,571 $14,104,434
AG2-095 $0 $0 $0 $0 $0 $0
AG2-104 $0 $92,761 $1,323,752 $0 $369,787 $1,786,300
AG2-106 $0 $92,761 $1,160,359 $0 $232,867 $1,485,987
AG2-107 $0 $91,761 $1,160,359 $0 $228,760 $1,480,880
AG2-109 $1,153,439 $14,052,335 $509,895 $0 $427,497 $16,143,166
AG2-114 $1,210,738 $75,301,646 $328,247 $22,353 $792,517 $77,655,502
AG2-119 $736,652 $4,631,082 $0 $0 $509,013 $5,876,747
AG2-121 $0 $0 $0 $0 $0 $0
AG2-124 $0 $190,117 $0 $0 $0 $190,117
AG2-125 $0 $0 $0 $0 $0 $0
AG2-126 $1,003,988 $9,087,740 $0 $12,009,282 $1,721,443 $23,822,453
AG2-151 $9,541,601 $20,712,812 $48,582 $0 $483,290 $30,786,285
AG2-152 $1,252,162 $15,980,643 $0 $0 $750,157 $17,982,962
AG2-163 $0 $1,273,714 $0 $30,941 $603,891 $1,908,546
AG2-166 $636,546 $1,218,744 $0 $0 $0 $1,855,290
AG2-171 $8,967,756 $7,352,571 $17,652,911 $0 $483,290 $34,456,528
AG2-176 $755,721 $6,907,331 $160,187,987 $0 $517,642 $168,368,681
AG2-182 $2,138,836 $57,114,995 $0 $0 $552,827 $59,806,658
AG2-184 $571,120 $21,611,154 $12,996,400 $0 $677,024 $35,855,699
AG2-191 $0 $1,074,801 $182,450 $0 $603,891 $1,861,142
AG2-192 $0 $157,768 $117,550 $0 $301,946 $577,264
AG2-193 $0 $0 $0 $0 $0 $0
AG2-198 $849,070 $11,907,554 $6,057,452 $0 $249,786 $19,063,862
AG2-200 $376,804 $155,127 $3,468,120 $0 $36,547 $4,036,598
AG2-213 $9,272,482 $5,995,888 $23,537,260 $0 $483,290 $39,288,920
AG2-216 $0 $0 $0 $0 $0 $0
AG2-230 $829,892 $3,290,302 $0 $0 $558,776 $4,678,970
AG2-236 $57,020 $142,935 $0 $0 $5,271 $205,226
AG2-238 $0 $0 $0 $0 $0 $0
AG2-240 $0 $0 $0 $0 $0 $0
AG2-245 $849,909 $33,314,511 $0 $68,689 $1,117,553 $35,350,662
AG2-248 $493,084 $13,779,028 $0 $36,245 $375,078 $14,683,436
AG2-262 $0 $0 $0 $0 $0 $0
AG2-270 $12,665,760 $2,142,685 $9,446,270 $0 $499,571 $24,754,286
AG2-272 $986,167 $5,906,901 $0 $0 $750,157 $7,643,225
AG2-288 $4,009,925 $447,937 $0 $0 $514,799 $4,972,661
AG2-289 $364,638 $6,708,740 $0 $1,935 $357,462 $7,432,774
AG2-290 $364,638 $6,866,508 $0 $1,115 $357,462 $7,589,723
AG2-297 $614,438 $2,824,533 $0 $0 $0 $3,438,971
AG2-298 $1,792,000 $15,269,000 $127,897 $0 $0 $17,188,897
AG2-300 $606,945 $3,565,166 $0 $0 $514,990 $4,687,101
AG2-329 $1,659,783 $28,131,860 $0 $0 $1,117,553 $30,909,196
AG2-332 $493,084 $4,373,520 $0 $36,245 $978,970 $5,881,819
AG2-339 $0 $244,105 $0 $0 $0 $244,105
AG2-341 $4,714,199 $3,795,171 $659,366 $0 $483,290 $9,652,026
AG2-343 $0 $5,884,582 $0 $12,376 $1,117,553 $7,014,511
AG2-345 $0 $157,768 $0 $6,188 $603,891 $767,847
AG2-356 $0 $0 $1,867,387 $0 $0 $1,867,387
AG2-360 $2,206,040 $10,686,376 $1,155,293 $0 $750,157 $14,797,866
AG2-363 $2,137,668 $2,799,908 $44,985,861 $9,612,365 $391,562 $59,927,364
AG2-364 $2,137,668 $2,799,908 $29,990,798 $6,408,237 $391,562 $41,728,173
AG2-369 $2,188,690 $27,510,929 $0 $123,000 $552,827 $30,375,446
AG2-370 $0 $3,166,854 $0 $0 $603,891 $3,770,745
AG2-380 $1,665,709 $3,758,741 $29,760,796 $0 $0 $35,185,246
AG2-382 $2,171,760 $13,849,668 $0 $0 $249,786 $16,271,214
AG2-384 $15,552,161 $5,856,927 $0 $0 $499,571 $21,908,659
AG2-401 $0 $0 $0 $0 $0 $0
AG2-405 $0 $0 $0 $0 $0 $0
AG2-406 $0 $0 $0 $0 $0 $0
AG2-411 $979,668 $7,094,086 $0 $0 $562,940 $8,636,694
AG2-420 $381,016 $102,790 $1,337,050 $0 $36,547 $1,857,403
AG2-423 $1,307,871 $17,151,080 $0 $0 $517,228 $18,976,179
AG2-424 $1,989,000 $9,264,000 $4,805,372 $0 $0 $16,058,372
AG2-426 $1,988,831 $21,922,953 $39,296,000 $0 $483,290 $63,691,074
AG2-429 $1,487,522 $19,010,009 $63,547,134 $0 $521,431 $84,566,096
AG2-436 $2,119,491 $48,116,762 $0 $0 $552,827 $50,789,080
AG2-440 $418,486 $10,184,099 $35,039,080 $0 $225,794 $45,867,458
AG2-441 $418,486 $10,184,099 $52,792,808 $0 $225,794 $63,621,186
AG2-442 $1,010,704 $22,835,450 $65,077,754 $0 $483,290 $89,407,198
AG2-447 $0 $0 $15,000,000 $0 $0 $15,000,000
AG2-448 $1,587,454 $23,074,066 $0 $0 $517,528 $25,179,048
AG2-453 $1,413,009 $62,925,234 $47,296,117 $6,539,647 $791,246 $118,965,253
AG2-479 $0 $0 $0 $0 $0 $0
AG2-481 $0 $0 $0 $0 $0 $0
AG2-484 $0 $0 $0 $0 $0 $0
AG2-487 $0 $0 $0 $0 $0 $0
AG2-491 $0 $343,288 $0 $42,250,869 $301,946 $42,896,103
AG2-492 $0 $278,282 $0 $21,125,434 $301,946 $21,705,662
AG2-516 $461,923 $45,037,965 $38,954,679 $28,036 $444,103 $84,926,706
AG2-518 $986,167 $10,229,132 $209,360 $0 $750,157 $12,174,816
AG2-519 $1,657,813 $29,158,608 $0 $0 $1,354,047 $32,170,468
AG2-522 $1,385,875 $20,733,318 $2,811,904 $0 $483,290 $25,414,387
AG2-524 $459,203 $37,041,344 $17,347,544 $1,601,218 $442,781 $56,892,090
AG2-544 $364,020 $2,860,014 $0 $51,274 $194,801 $3,470,109
AG2-545 $364,020 $2,860,014 $0 $102,548 $194,801 $3,521,383
AG2-548 $493,084 $13,761,280 $150,000 $0 $1,052,102 $15,456,465
AG2-550 $0 $1,225,275 $8,380,050 $0 $603,891 $10,209,216
AG2-551 $0 $157,768 $1,830,845 $0 $301,946 $2,290,559
AG2-561 $0 $0 $0 $0 $0 $0
AG2-562 $0 $1,273,714 $0 $18,979 $603,891 $1,896,584
AG2-566 $849,070 $11,907,554 $1,219,644 $0 $249,786 $14,226,054
AG2-568 $1,657,813 $17,887,865 $50,000 $0 $750,157 $20,345,835
AG2-570 $1,624,061 $25,335,280 $0 $572,000 $276,414 $27,807,755
AG2-571 $1,624,061 $25,335,280 $0 $143,000 $276,414 $27,378,755
AG2-581 $2,174,919 $56,662,561 $569,791 $0 $552,827 $59,960,098
AG2-582 $411,978 $6,576,357 $68,488,079 $0 $983,319 $76,459,733
AG2-583 $1,063,044 $23,029,797 $50,309 $0 $499,571 $24,642,721
AG2-585 $0 $427,232 $0 $17,087 $0 $444,319
AG2-616 $299,960 $11,191,475 $0 $0 $0 $11,491,435
AG2-617 $19,074,419 $3,493,495 $0 $0 $0 $22,567,914
AG2-618 $134,199 $5,458,484 $0 $0 $0 $5,592,683
AG2-621 $4,881,868 $251,320 $0 $0 $527,027 $5,660,215
AG2-625 $1,094,378 $1,073,738 $0 $0 $27,740 $2,195,856
AG2-626 $872,925 $1,063,612 $0 $0 $27,396 $1,963,933
AG2-637 $986,167 $20,628,547 $10,119,105 $0 $750,157 $32,483,976
AG2-657 $266,642 $23,230,322 $0 $0 $750,157 $24,247,121
AG2-659 $884,776 $27,520,596 $3,221,109 $0 $456,444 $32,082,925
AG2-660 $0 $80,558 $8,862,544 $749,445 $0 $9,692,547
AG2-661 $0 $0 $0 $0 $0 $0
AG2-665 $493,084 $1,877,566 $150,000 $0 $301,946 $2,822,596
AG2-675 $0 $2,056,645 $0 $1,015,660 $0 $3,072,305
AH1-004 $845,000 $6,285,500 $0 $8,526,472 $0 $15,656,972
AH1-033 $181,200 $3,503,266 $0 $0 $0 $3,684,466
AH1-040 $1,249,118 $20,234,189 $15,000,000 $0 $449,566 $36,932,873
AH1-044 $0 $80,558 $62,336,917 $6,492,518 $0 $68,909,992
AH1-054 $813,778 $1,293,367 $0 $0 $27,396 $2,134,541
AH1-055 $2,831,484 $32,060,082 $13,985,198 $0 $1,117,553 $49,994,317
AH1-057 $0 $0 $0 $0 $0 $0
AH1-059 $0 $4,013,594 $0 $0 $603,891 $4,617,485
AH1-060 $28,656 $733,106 $0 $0 $2,636 $764,397
AH1-071 $0 $0 $0 $0 $0 $0
AH1-072 $41,617 $9,893,748 $473,276 $0 $714,924 $11,123,564
AH1-073 $41,617 $9,958,754 $473,276 $0 $603,891 $11,077,538
AH1-091 $0 $0 $0 $0 $0 $0
AH1-098 $1,298,353 $17,267,117 $0 $0 $1,354,047 $19,919,517
AH1-106 $0 $0 $0 $0 $0 $0
AH1-107 $0 $0 $0 $0 $0 $0
AH1-108 $0 $0 $0 $0 $0 $0
AH1-133 $126,981 $18,227,186 $0 $0 $750,157 $19,104,324
AH1-138 $0 $0 $0 $0 $0 $0
AH1-144 $838,534 $11,933,074 $14,290 $0 $750,157 $13,536,055
AH1-145 $838,534 $11,998,081 $22,384 $0 $603,891 $13,462,890
AH1-150 $0 $80,558 $62,336,917 $6,492,518 $0 $68,909,992
AH1-151 $0 $80,558 $62,336,917 $6,492,518 $0 $68,909,992
AH1-153 $829,892 $3,448,070 $0 $0 $1,162,668 $5,440,629
AH1-165 $4,880,185 $0 $0 $21,732 $439,942 $5,341,859
AH1-170 $0 $16,446,668 $0 $0 $0 $16,446,668
AH1-188 $7,511,988 $54,828,386 $23,581,109 $0 $750,157 $86,671,640
AH1-196 $0 $252,795 $74,856,293 $99,847 $0 $75,208,935
AH1-206 $4,216,345 $0 $0 $0 $581,390 $4,797,735
AH1-216 $1,140,974 $26,593,928 $0 $0 $499,571 $28,234,473
AH1-221 $0 $0 $0 $0 $0 $0
AH1-223 $0 $0 $0 $0 $0 $0
AH1-227 $919,746 $17,033,943 $1,244,199 $0 $714,924 $19,912,812
AH1-239 $1,905,000 $8,774,000 $21,639,258 $14,440 $0 $32,332,698
AH1-247 $556,374 $5,364,098 $0 $0 $181,200 $6,101,672
AH1-248 $556,374 $5,364,098 $0 $0 $181,200 $6,101,672
AH1-249 $556,374 $5,364,098 $0 $0 $181,200 $6,101,672
AH1-251 $1,223,282 $21,318,662 $0 $0 $483,290 $23,025,234
AH1-254 $325,658 $125,636 $0 $0 $10,543 $461,837
AH1-257 $857,994 $1,155,750 $24,750,189 $0 $27,396 $26,791,329
AH1-258 $838,916 $1,575,834 $0 $0 $27,822 $2,442,572
AH1-260 $485,734 $24,319,043 $0 $0 $0 $24,804,777
AH1-261 $7,422,660 $6,243,968 $22,000,000 $0 $0 $35,666,628
AH1-263 $4,333,155 $18,009,366 $0 $0 $483,290 $22,825,811
AH1-269 $2,668,885 $6,077,763 $48,966 $0 $750,157 $9,545,771
AH1-271 $2,171,760 $13,849,668 $0 $0 $249,786 $16,271,214
AH1-272 $1,659,783 $58,228,306 $0 $4,929,534 $1,117,553 $65,935,176
AH1-280 $0 $0 $4,444,396 $0 $0 $4,444,396
AH1-282 $3,148,578 $37,379,473 $0 $0 $1,117,553 $41,645,604
AH1-283 $3,002,558 $35,953,058 $0 $0 $964,478 $39,920,094
AH1-292 $0 $0 $0 $0 $0 $0
AH1-302 $0 $1,273,714 $0 $29,086,695 $603,891 $30,964,300
AH1-304 $0 $0 $0 $0 $0 $0
AH1-305 $0 $0 $0 $0 $0 $0
AH1-306 $0 $0 $0 $0 $0 $0
AH1-311 $0 $0 $0 $0 $0 $0
AH1-314 $2,092,968 $17,679,077 $38,520 $0 $1,183,174 $20,993,739
AH1-327 $0 $0 $0 $0 $0 $0
AH1-328 $0 $0 $0 $0 $0 $0
AH1-334 $878,041 $1,033,374 $0 $0 $32,051 $1,943,466
AH1-338 $462,801 $37,131,021 $49,499,380 $854,705 $444,617 $88,392,524
AH1-341 $461,623 $35,675,719 $54,393,063 $94,403 $443,478 $91,068,286
AH1-343 $941,707 $23,632,514 $2,799,027 $0 $458,076 $27,831,324
AH1-345 $0 $0 $0 $0 $0 $0
AH1-348 $0 $232,616 $0 $0 $490,626 $723,242
AH1-387 $3,129,272 $37,756,968 $0 $0 $987,463 $41,873,703
AH1-392 $0 $18,165,448 $0 $51,375 $750,157 $18,966,980
AH1-396 $0 $0 $1,167,335 $0 $0 $1,167,335
AH1-397 $0 $0 $0 $0 $0 $0
AH1-399 $0 $0 $0 $0 $0 $0
AH1-439 $1,638,010 $24,906,162 $3,923,208 $0 $499,571 $30,966,951
AH1-452 $0 $0 $0 $0 $0 $0
AH1-460 $1,931,406 $19,993,174 $54,621,186 $0 $475,724 $77,021,490
AH1-461 $1,049,656 $19,612,854 $0 $0 $750,157 $21,412,667
AH1-482 $0 $1,273,714 $0 $25,504,169 $603,891 $27,381,774
AH1-528 $2,184,196 $51,368,471 $1,142,613 $0 $552,827 $55,248,107
AH1-535 $1,659,783 $34,969,452 $0 $0 $3,352,657 $39,981,892
AH1-537 $0 $34,873,818 $9,702,716 $0 $1,117,553 $45,694,087
AH1-541 $1,910,456 $10,222,353 $171,753 $12,719 $784,094 $13,101,375
AH1-542 $1,496,938 $14,553,811 $0 $0 $508,527 $16,559,276
AH1-543 $1,200,551 $60,706,743 $19,414,549 $583,425 $789,176 $82,694,444
AH1-545 $2,555,819 $31,707,604 $0 $0 $843,373 $35,106,796
AH1-546 $1,140,057 $25,739,124 $313,997 $0 $499,571 $27,692,749
AH1-552 $134,199 $4,728,462 $10,000,000 $0 $0 $14,862,661
AH1-563 $0 $1,420,651 $14,807,780 $39,781 $0 $16,268,213
AH1-564 $0 $600,425 $62,091,817 $35,614 $0 $62,727,856
AH1-567 $0 $1,854,892 $0 $1,623 $0 $1,856,515
AH1-570 $905,500 $5,462,500 $0 $0 $0 $6,368,000
AH1-571 $905,500 $5,462,500 $0 $0 $0 $6,368,000
AH1-580 $609,937 $4,747,634 $0 $0 $978,970 $6,336,540
AH1-617 $571,120 $21,676,162 $12,389,525 $0 $677,024 $35,313,831
AH1-637 $0 $0 $0 $0 $0 $0
AH1-641 $299,960 $14,014,010 $0 $0 $0 $14,313,970
AH1-661 $0 $1,230,440 $0 $0 $490,626 $1,721,066
AH1-664 $844,000 $7,202,000 $9,546,550 $6,710,375 $0 $24,302,925
AH1-665 $844,000 $7,202,000 $7,637,236 $5,368,300 $0 $21,051,536
AH1-666 $1,686,000 $15,428,000 $3,174,061 $0 $0 $20,288,061
AH1-667 $404,958 $103,456 $494,900 $0 $36,547 $1,039,861
AH1-672 $1,609,381 $4,032,192 $2,539,204 $0 $0 $8,180,777
AH1-673 $468,238 $38,744,562 $0 $31,667 $450,775 $39,695,242
AH1-677 $0 $0 $0 $0 $0 $0
AH1-678 $0 $0 $0 $0 $0 $0
AH1-679 $0 $0 $0 $0 $0 $0
AH1-680 $2,128,099 $27,517,041 $1,000,000 $0 $680,115 $31,325,255
AH1-681 $0 $0 $0 $0 $0 $0
AH1-682 $0 $0 $0 $0 $0 $0
AH1-683 $0 $0 $0 $0 $0 $0
AH1-684 $0 $0 $0 $0 $0 $0
AH1-685 $0 $0 $0 $0 $0 $0
AH1-686 $0 $2,606,993 $0 $0 $982,407 $3,589,400
AH1-687 $0 $0 $35,142 $0 $0 $35,142
AH1-691 $0 $0 $0 $0 $0 $0
AH1-692 $0 $0 $0 $0 $0 $0
AH1-693 $0 $0 $0 $0 $0 $0
AH1-694 $0 $0 $0 $0 $0 $0
AH1-695 $406,499 $5,478,653 $0 $0 $853,848 $6,739,000
AH1-696 $0 $0 $0 $0 $0 $0
AH1-698 $0 $814,361 $0 $38,910 $0 $853,271
AH1-699 $57,092 $143,106 $0 $0 $4,971 $205,169
AH1-701 $0 $0 $0 $0 $0 $0
AH1-702 $0 $1,151,580 $0 $20,671 $0 $1,172,251
AH1-703 $0 $0 $0 $0 $0 $0
AH1-704 $0 $0 $0 $0 $0 $0
AH1-706 $57,061 $190,637 $0 $0 $5,447 $253,145
AH1-710 $0 $0 $0 $0 $87,000 $87,000
AH1-711 $57,092 $47,702 $48,873,856 $23,198 $5,271 $49,007,119
AH1-712 $5,843,758 $14,940,509 $0 $0 $276,414 $21,060,680
AH1-713 $0 $0 $0 $0 $0 $0
AH1-714 $0 $635,829 $32,486,493 $4,229,730 $0 $37,352,052
AH1-715 $0 $0 $16,576,485 $0 $0 $16,576,485
AH1-716 $2,083,467 $50,320,099 $0 $0 $552,827 $52,956,393
AH1-718 $0 $944,946 $0 $2,403 $0 $947,349
AH1-719 $0 $1,193,041 $0 $0 $1,117,553 $2,310,594
AH1-721 $1,600,832 $29,826,730 $61,055,708 $985,560 $0 $93,468,831
AH1-722 $0 $0 $21,826,515 $0 $315,000 $22,141,515
AH1-723 $5,843,758 $14,940,509 $0 $0 $276,414 $21,060,680
AH1-725 $35,054,607 $8,741,862 $0 $0 $0 $43,796,469
AH1-727 $2,212,720 $56,786,817 $0 $0 $552,827 $59,552,364
AH1-734 $738,133 $100,289 $0 $0 $5,855 $844,277
AH1-744 $0 $0 $0 $0 $0 $0
AH1-746 $0 $0 $9,380,414 $0 $0 $9,380,414

System Reinforcements

As part of the Transition Cycle 2 Phase II System Impact Study, PJM evaluated the impact of topology changing reinforcements to mitigate the impacts driven by New Service Requests. As part of the Phase II study, PJM evaluates whether any reinforcements are eliminated as a result of modeling the topology changing reinforcements. If so, PJM would group the topology changing and eliminated reinforcements by region and compute a discount factor to apply to reinforcements to reduce the cost of all these reinforcements down to the cost of constructing only the topology changing reinforcements. If no eliminated reinforcements are identified, no regional discount factor would be applied.

Regional Discount Factors for Topology Changing Upgrades
Region Topology Upgrades Eliminated Upgrades Discount Factor Details
Dominion $145,162,000 $0 No Discount
Mid-Atlantic Area Council $0 $0 No Discount
PJM West $36,430,000 $0 No Discount

Details for Dominion Region


The following topology changing reinforcements within the Dominion region were modeled to mitigate the impacts driven by the new service requests in Transition Cycle 2 Phase II:

Table 3: Dominion Topology Changing Reinforcement(s) Modeled for Transition Cycle 2 Phase II
TO RTEP ID / TO ID Title Time Estimate Cost Eligible for Discounting ($)
Dominion n8492

Wreck and rebuild the existing Yadkin to Fentress 500 kV Line #588 to share the right of way with the new Yadkin to Fentress #5005 line.

Dec 31 2026 $0
Dominion n8492.1

Two Breaker Additions at Fentress Substation.

Dec 31 2026 $0
Dominion n8492.2

Expand Yadkin Substation to accommodate the new 500 kV line.

Dec 31 2026 $0
Dominion n9259.0

Install two 230 kV gas insulated switchgear ("GIS") bus ties at the Fentress 230 kV substation.

Jan 01 2030 $0
Dominion n9267.0 / TC1-PH2-DOM-067

Construct new 10.21 mile 115 kV line between Northern Neck and Moon Corner.

45 to 46 Months $0
Dominion b4000.357

Build a new 765/500/230 kV substation called Yeat. Install (2) 765/500 kV transformers. Cut in 500 kV line Bristers-Ox and 500 kV line Meadowbrook-Vint Hill into Yeat.

Jun 01 2029 $0
Dominion b4000.356

Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 86.7 miles in Dominion section).

Jun 01 2029 $0
Dominion b4000.352

Cut in Line #568 Ladysmith - Possum Point into Thornburg (formerly Kraken), creating new Line #568 Thornburg (formerly Kraken) to Possum Point.

Sep 16 2030 $0
Dominion b4000.351

Cut in Line #568 Ladysmith - Possum Point into Thornburg (formerly Kraken), creating Line #9517 Ladysmith to Thornburg (formerly Kraken).

Sep 16 2030 $0
Dominion b4000.350

Update relay settings at Possum Point to change the destination of 500kV line #568 from Ladysmith to Thornburg (formerly Kraken).

Sep 16 2030 $0
Dominion b4000.349

Update relay settings at Ladysmith to change the destination of 500kV line #568 from Possum Point to Thornburg (formerly Kraken).

Sep 16 2030 $0
Dominion b4000.348

Build a new 500/230kV substation called Thornburg (formerly Kraken). The 500kV, 5000A ring bus will be set up for a redundant breaker configuration. Install (2) 1400MVA 500/230 kV transformers.

Jun 01 2029 $0
Dominion b4000.346

Cut-in 500kV line from Thornburg (formerly Kraken) substation into Yeat substation

Jun 01 2029 $0
Dominion b4000.345

Build a 500kV line from a new substation called Thornburg (formerly Kraken) to a new substation called Yeat. New conductor to have a minimum summer normal rating of 4357MVA.

Sep 16 2030 $0
Dominion b4000.344

Build a 500kV line from North Anna substation (bypassing Ladysmith Substation) to a new substation called Thornburg (formerly Kraken). New conductor to have a minimum summer normal rating of 4357MVA.

Sep 16 2030 $0
Dominion b4000.342

Remove the terminal equipment and substation work required for the termination of the Morrisville-Wishing Star 500 kV line into Vint Hill.

Jul 13 2029 $0
Dominion b4000.341

Remove the 500 kV conductor previously planned to terminate into the Vint Hill 500 kV Substation and extend approximately 0.2 miles of conductor to fly-over the site.

Jul 13 2029 $0
Dominion b4000.325

Build a new 26.38mi 230kV Line from Elmont – Ladysmith on the existing 5-2 structures between the two stations. New conductor has a summer rating of 1573 MVA.

Feb 24 2029 $0
Dominion b4000.326

At Elmont substation, install/upgrade associated equipment to accommodate a 4000A line rating for the new 230kV line between Elmont - Ladysmith.

Feb 24 2029 $0
Dominion b4000.327

Upgrade/install equipment at Ladysmith Substation to 4000A. Expansion will be required to accommodate a total of three (3) new 230 kV strings of breaker and a half scheme.

Feb 24 2029 $0
Dominion n9630.0 / TC1-PH3-DOM-013

Construct a new 230 kV line from the AG1-285 substation to the Finneywood 230 kV Substation. Expand AG1-285 substation and add two (2) new 230/115 kV transformers.

Dec 31 2029 $0
Dominion b4000.334

Reconductor 115kV line #121 from Poe - Prince George. Specifically, line #121 will be reconductored and converted to 230kV from Poe substation to Prince George substation.

Jan 10 2030 $0
Dominion b4000.335

At Poe substation, install a new 230kV six breaker ultimate ring bus which will fit the station to current 230kV standards.

Jan 10 2030 $0
Dominion b4000.336

Build a new 230-115kV Prince George substation along the existing 115 or 230kV corridor.

Jan 10 2030 $0
Dominion b4053.10

Construct one new 500 kV line terminal position at the proposed Thornburg (formerly Kraken) substation.

Jun 01 2032 $0
Dominion b4053.11

Cut and loop line No. 5008 into Mosby substation, which will result in two 500 kV lines: line No. 5008 Morrisville-Mosby and line No. 9573 Mosby-Wishing Star.

Jun 01 2030 $0
Dominion b4053.12

Install two 500 kV breakers and all associated terminal equipment in the available bay adjacent to existing breaker XT590 to achieve a redundant breaker arrangement.

Jun 01 2030 $0
Dominion b4053.13

Construct a new 765/500 kV Vontay switching station at the crossing of 500 kV line No. 553 Cunningham-Elmont and 765 kV line Joshua Falls-Yeat.

Jun 01 2032 $0
Dominion b4053.14

Loop 500 kV line No. 553 into the new Vontay substation, which will result in two 500 kV lines: Cunningham-Vontay and Vontay-Elmont.

Jun 01 2032 $0
Dominion b4053.15

Loop 500 kV line No. 576 into the new Vontay substation, which will result in two 500 kV lines: from North Anna-Vontay and Vontay-Midlothian.

Jun 01 2032 $0
Dominion b4053.16

Loop 765 kV Joshua Falls-Yeat into the new Vontay substation, which will result in two 765 kV lines: from Joshua Falls-Vontay and Vontay-Yeat.

Jun 01 2032 $0
Dominion b4053.28

Replace 500 kV circuit breakers (54265 and 553T564) and all associated equipment to line No. 553 including switches and CT with 5000A equipment at Cunningham substation.

Jun 01 2032 $0
Dominion b4053.3

Construct a new bipolar +/- 525 kV HVDC link connecting Heritage and Mosby substations, where the link has a capability of transmitting 3,000 MW.

Jun 01 2032 $0
Dominion b4053.4

Design and construct a new Voltage Source Converter (VSC) HVDC station at Heritage substation to support the new HVDC link.

Jun 01 2032 $0
Dominion b4053.5

Design and construct a new Voltage Source Converter (VSC) HVDC station at Mosby substation to support the new HVDC link.

Jun 01 2032 $0
Dominion b4053.8

Build a new 500 kV line from Elmont-Thornburg (formerly Kraken) (approximately 31 miles).

Jun 01 2032 $0
Dominion b4053.9

Construct one new 500 kV line terminal position at the existing Elmont substation.

Jun 01 2032 $0
Dominion n9757.0 / TC2-PH2-DOM-005

Build new 230 kV line from AG1-285 to AG2-440 on single circuit monopoles. Expand the AG2-440 and AG1-285 substations. Add 2 new 224 MVA 230/115 kV XFRMs at AG2-440.

42 to 48 Months $145,162,000
Grand Total: $145,162,000

Impacted New Service Requests have a cost responsibility into the eliminated reinforcements, but these reinforcements will not be constructed. No eliminated reinforcements are identified, and no regional discount factor would be applied.

Details for Mid-Atlantic Area Council Region


The following topology changing reinforcements within the Mid-Atlantic Area Council region were modeled to mitigate the impacts driven by the new service requests in Transition Cycle 2 Phase II:

Table 3: Mid-Atlantic Area Council Topology Changing Reinforcement(s) Modeled for Transition Cycle 2 Phase II
TO RTEP ID / TO ID Title Time Estimate Cost Eligible for Discounting ($)
PECO b3780.2

Peach Bottom to Graceton (PECO Portion) – New 500kV Line

Oct 23 2028 $0
BGE b3780.4

Peach Bottom to Graceton (BGE Portion) – New 500kV Line

Dec 31 2028 $0
BGE b3780.7

Build new Batavia Road substation (Projected ISD 12/31/2028)

Dec 31 2028 $0
BGE b3780.8

Graceton 500 kV substation expansion (Projected ISD 12/31/2028)

Dec 31 2028 $0
BGE b3780.9

Graceton to Batavia Road 230 kV double circuit pole line (Projected ISD 12/31/2028)

Dec 31 2028 $0
BGE b3780.13

Batavia Road to Riverside 230 kV reconductor

Dec 31 2027 $0
PECO b3780.15

Cut in 5012 Peach Bottom-Conastone 500 kV line into North Delta 500/230 kV sub

Apr 10 2028 $0
PECO b3780.17

Cut in 5012 Peach Bottom-Conastone 500 kV line into North Delta 500/230 kV sub (Transource)

May 31 2028 $0
BGE b3800.34

Rebuild 5012 (existing Peach Bottom-Conastone) (new Graceton-Conastone) 500 kV and cut into North Delta 500kV (Projected ISD 12/31/2030)

Dec 31 2030 $0
PECO b3800.35

Rebuild 5012 (existing Peach Bottom-Conastone) (new North Delta-Graceton PECO) 500 kV (Projected ISD 12/1/2030)

Apr 10 2028 $0
BGE b3800.36

Rebuild 5012 (existing Peach Bottom-Conastone) (new North Delta-Graceton BGE) 500 kV (Projected ISD 12/31/2030)

Dec 31 2030 $0
PECO b3780.1

Peach Bottom North upgrades – substation work (Projected ISD 12/31/2028)

Oct 15 2028 $0
PECO b3800.52

Reconfigure Peach Bottom North and South 500 kV yards (Projected ISD 12/1/2030)

Dec 01 2030 $0
PECO b3780.14

Reconfigure Cooper transmission feeds by establishing new Cooper-North Delta 230 kV line and rerouting existing transmissions lines by Cooper.

Oct 23 2028 $0
PECO b3780.16

Terminate new Cooper-North Delta 230 kV line (Transource Scope) at North Delta 230 kV

Oct 15 2028 $0
PECO b3800.45

North Delta 500 kV termination for the Rock Springs 500 kV line (5034/5014 line) (PECO work).

Jan 31 2028 $0
PECO b3800.50

North Delta 500 kV termination for the Rock Springs 500 kV line (5034/5014 line) (Transource work).

Jan 23 2028 $0
PEPCO b3800.46

North Delta 500 kV termination for the new Peach Bottom-North Delta 500 kV line (PECO work).

Dec 11 2029 $0
PECO b3800.51

North Delta 500 kV termination for the new Peach Bottom-North Delta 500 kV line (Transource work).

May 31 2028 $0
PECO b3800.31

Build new North Delta-High Ridge 500 kV line - PECO Portion (Projected ISD 12/1/2030)

Dec 15 2030 $0
PECO b3800.44

North Delta termination for the North Delta-High Ridge 500 line (PECO work).

Dec 15 2030 $0
PECO b3800.48

North Delta termination for the North Delta-High Ridge 500 line (Transource work).

Dec 15 2030 $0
PECO b3737.47

Build New North Delta 500 kV substation (Four bay breaker and half configuration)

Oct 06 2027 $0
BGE b3800.29

High Ridge termination for the North Delta-High Ridge 500 kV line (Projected ISD 12/31/2030)

Dec 31 2030 $0
BGE b3800.32

Build new North Delta-High Ridge 500 kV line - BGE Portion (Projected ISD 12/31/2030)

Dec 31 2030 $0
BGE b3800.26

Build High Ridge 500 kV substation - Three bay breaker and half configuration (Projected ISD 12/31/2030)

Dec 31 2030 $0
BGE b3800.27

High Ridge 500 kV substation (cut into Brighton-Waugh Chapel 500 kV line) - Waugh Chapel side (Projected ISD 12/31/2030)

Dec 31 2030 $0
BGE b3800.28

High Ridge 500 kV substation (cut into Brighton-Waugh Chapel 500 kV line) -Brighton side (Projected ISD 12/31/2030)

Dec 31 2030 $0
BGE b3800.30

High Ridge - Install two 500/230 kV transformers (Projected ISD 12/31/2030)

Dec 31 2030 $0
BGE b3800.33

Replace terminal equipment limitations at Brighton 500 kV - on the existing Brighton-Waugh Chapel 500 kV (5053) or new Brighton-High Ridge 500 kV.

Dec 31 2030 $0
PECO b3800.47

Build new Peach Bottom South-North Delta 500 kV line (Projected ISD 12/1/2030)

Jan 14 2030 $0
PECO b3800.42

Peach Bottom 500kV North bus upgrade (Projected ISD 12/1/2030)

Dec 01 2030 $0
PECO b3800.49

North Delta 500 kV termination for the Calpine generator (Calpine/Transource work).

Oct 06 2027 $0
BGE b3800.37

Replace terminal equipment limitations at Conastone 500 kV - on the (existing Peach Bottom-Conastone) or (new Graceton-Conastone) 500 kV line (Projected ISD 12/31/2030)

Dec 31 2030 $0
BGE b3780.6

Build Granite substation + Statcom (Projected ISD 12/31/2028)

Dec 31 2028 $0
PEPCO b3780.11

Brighton Statcom and Capacitor (Projected ISD 12/31/2028)

Dec 31 2028 $0
BGE b3780.5

Build Solley Road substation + Statcom (Projected ISD 12/31/2028)

Dec 31 2028 $0
Grand Total: $0

Impacted New Service Requests have a cost responsibility into the eliminated reinforcements, but these reinforcements will not be constructed. No eliminated reinforcements are identified, and no regional discount factor would be applied.

Details for PJM West Region


The following topology changing reinforcements within the PJM West region were modeled to mitigate the impacts driven by the new service requests in Transition Cycle 2 Phase II:

Table 3: PJM West Topology Changing Reinforcement(s) Modeled for Transition Cycle 2 Phase II
TO RTEP ID / TO ID Title Time Estimate Cost Eligible for Discounting ($)
ITCT (Pending) / ITCT_TC1_13866

MTEP #25223/#25224 - Lulu Sub. Construct the Lulu switching station. Cut in the Lemoyne-Maple and Milan-Monroe-Morocco lines into the new station (Projected ISD 6/11/2027)

TBD $0
ComEd s3011 / CE_S3011

Replace 345kV straight bus at TSS 116 Goodings Grove with a gas insulated switchgear ("GIS") breaker and a half configuration.

Dec 31 2029 $0
AEP b4000.355

Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 69.3 miles in AEP section).

Jun 01 2029 $0
ATSI (Pending) / ATSI-2025-004 (Supplemental)

Lemoyne Sub Upgrades & New Greenfield-Ottawa 138kV Line (Projected ISD 6/1/2032) - s3844.1

TBD $0
APS b4000.11

Expand Black Oak Substation & Loop in the 502 Jct-Woodside 500 kV line (Projected ISD 6/1/2029)

Jun 01 2029 $0
AEP b4000.1

Add two 765 kV breakers at Amos Substation to expand the breaker and a half scheme to accommodate the new Amos-Welton Spring 765 kV line (Projected ISD 6/1/2029)

Jun 01 2029 $0
APS b4000.2

Construct a new 175 miles Amos to Welton Spring 765 kV line - AEP Section of the line is 30 miles (Projected ISD 6/1/2029)

Jun 01 2029 $0
APS b4000.3

Construct a new 175 miles Amos to Welton Spring 765 kV line - APS/FE Section of the line is 145 miles (Projected ISD 6/1/2029)

Jun 01 2029 $0
APS b4000.4

Construct a new 765 kV switchyard - Welton Spring (Projected ISD 6/1/2029)

Jun 01 2029 $0
APS b4000.5

Install four 250 MVAR shunt capacitors, and a +/-500 MVAR STATCOM at Welton Spring 765 kV substation

Jun 01 2029 $0
APS b4000.6

Construct a new 86 miles Welton Spring to Rocky Point 765 kV line (Welton Spring to DVP local area, roughly 21 miles) (VA Portion)

Jun 01 2029 $0
APS b4000.7

Construct a new 86 miles Welton Spring to Rocky Point 765 kV line - in DVP local area/Millville to Lovettsville section, roughly 10.5 miles (Projected ISD 6/1/2029)

Jun 01 2029 $0
APS b4000.8

Construct a new 86 miles Welton Spring to Rocky Point 765 kV line (DVP local area to Rocky Point, roughly 4.8 miles)

Jun 01 2029 $0
APS b4000.9

Construct a new substation called Rocky Point with a 765 kV and a 500 kV yard (Projected ISD 6/1/2029)

Jun 01 2029 $0
APS b4000.10

Install four 250 MVAR cap banks (two on 765 and two on 500 kV side) and a +/-500 MVAR STATCOM on the 765 kV Rocky Point yard

Jun 01 2029 $0
EKPC n9743.0 / EKPC-tc2-nu003

Cooper CCGT-Alcalde 161 kV Double-Circuit Line Addition

22 to 36 Months $20,130,000
AEP b4068.1 / AEP-TC2-18693

b4068: Greentown 765 kV - Teddy 765kV - Marysville 765 kV - Greenfield Line - AEP Proposal 570

Jun 01 2030 $0
EKPC n9688.0 / EKPC-tc2-nu049

AH1-239 Tap (Clinton County)-Homestead New 69 kV Line (15 miles)

Dec 31 2028 $16,300,000
ComEd b4006.1

Install 765/345 kV TR 91 and associated 765 kV and 345 kV circuit breakers at Wilton Center.

Dec 01 2030 $0
AEP s3588.1 / (Pending)

Construct new Larrison Drive 345 kV substation

Dec 15 2026 $0
AEP s3588.2 / (Pending)

Construct new New Prairie 345 kV substation

Dec 15 2026 $0
AEP b3919.1

Reconfigure Maliszewski 765 kV station and establish 345 kV breaker yard

Jun 01 2029 $0
Grand Total: $36,430,000

Impacted New Service Requests have a cost responsibility into the eliminated reinforcements, but these reinforcements will not be constructed. No eliminated reinforcements are identified, and no regional discount factor would be applied.

Steady State Thermal & Voltage Reinforcements

PJM performed generator deliverability load flow analysis for the New Service Requests in Transition Cycle 2 Phase II System Impact Study. Load flow analysis was performed to simulate Summer Peak, Light Load, and Winter Peak conditions. The table below shows all the system reinforcements identified from generator deliverability load flow analysis.

TO RTEP ID / TO ID Title Time Estimate Total Cost Estimate ($) Projects with Cost Allocation Contingent Projects
AEP b2968

Upgrade existing 345kV terminal equipment at Tanners Creek station on Tanners Creek - Miami Fort 345kV line, Actual In-Service Date 12/22/2020

Dec 22 2020
Contingent

AG2-072, AG2-660, AH1-044, AH1-150, AH1-151

AEP b3788.1 / B3788.1

Replace limiting station elements at Kyger Creek

Apr 03 2028
Contingent

AG2-072, AH1-055, AH1-537, AH1-664, AH1-665, AH1-721

AEP b3851.1 / B3851.1

Rebuild Allen-RP Mone 345kV

Jun 01 2027
Contingent

AG2-029, AG2-230, AG2-332, AG2-363, AG2-364, AG2-453, AG2-660, AH1-044, AH1-150, AH1-151, AH1-153

AEP b3851.2

Rebuild R.P. Mone – Maddox Creek 345kV line (9.4 miles).

Jun 01 2027
Contingent

AG2-029, AG2-072, AG2-332, AG2-363, AG2-364, AG2-453, AG2-660, AH1-044, AH1-150, AH1-151

AEP b3877.1

Replace station conductor and switches in the 345 kV yard at Beatty

Feb 01 2028
Contingent

AH1-664, AH1-665

AEP b3877.2

Upgrade 345 kV circuit breakers 'A' and 'A1' to 4000A 63 kA breakers at Adkins station

Aug 01 2029
Contingent

AH1-664, AH1-665

AEP b3878.1

Upgrade 765 kV circuit breakers 'B' and 'B2' to 5000A 50kA breakers at Marysville Station

Nov 12 2027
Contingent

AG2-029, AG2-072, AG2-230, AG2-248, AG2-332, AG2-363, AG2-364, AG2-453, AG2-660, AH1-044, AH1-150, AH1-151, AH1-153

AEP b3919.1

Reconfigure Maliszewski 765 kV station and establish 345 kV breaker yard

Jun 01 2029
Contingent

AG2-029, AG2-072, AG2-073, AG2-081, AG2-104, AG2-106, AG2-107, AG2-163, AG2-184, AG2-230, AG2-245, AG2-298, AG2-329, AG2-332, AG2-343, AG2-345, AG2-363, AG2-364, AG2-424, AG2-453, AG2-660, AH1-004, AH1-044, AH1-055, AH1-150, AH1-151, AH1-153, AH1-272, AH1-482, AH1-537, AH1-570, AH1-571, AH1-617, AH1-664, AH1-665, AH1-666, AH1-711, AH1-721

AEP b3919.5 / (Pending)

Reconductor 4.75-miles of the existing Bokes Creek-Marysville 345 kV circuit.

Jun 01 2029
Contingent

AG2-106, AG2-107, AH1-711

AEP b3971.1

Reconductor Haviland 138 kV bus

Jun 01 2030
Contingent

AG2-370, AG2-660, AH1-044, AH1-150, AH1-151

AEP b3972.1

Sag Study and Clearance Mitigation: East Lima-Haviland

Apr 15 2030
Contingent

AG2-370

AEP b4000.1

Add two 765 kV breakers at Amos Substation to expand the breaker and a half scheme to accommodate the new Amos-Welton Spring 765 kV line (Projected ISD 6/1/2029)

Jun 01 2029
Contingent

AG2-062, AG2-072, AG2-104, AG2-106, AG2-107, AG2-184, AG2-360, AG2-363, AG2-364, AG2-411, AG2-423, AG2-448, AG2-518, AG2-582, AG2-657, AG2-660, AH1-044, AH1-144, AH1-145, AH1-150, AH1-151, AH1-269, AH1-272, AH1-460, AH1-617, AH1-711, AH1-721

AEP b4000.202

Rebuild 12.5 miles of Smith Mountain - Redeye 138 kV line

Jun 01 2029
Contingent

AG2-152

AEP b4000.203

Rebuild 17.5 miles of Redeye - Candler's Mountain 138 kV line

Jun 01 2029
Contingent

AG2-152

AEP b4000.204

Rebuild 4 miles of Candler's Mountain - Opossum Creek 138 kV line

Jun 01 2029
Contingent

AG2-152

AEP b4000.207

Leesville Station Upgrade 138 kV

Jun 01 2029
Contingent

AG2-152

AEP b4000.210

Rebuild 7 miles of Otter - Johnson Mountain 138 kV line.

Jun 01 2029
Contingent

AG2-077, AG2-152, AH1-343

AEP b4000.211

Rebuild 6.5 miles of Johnson Mountain - New London 138 kV line

Jun 01 2029
Contingent

AG2-152, AH1-343

AEP b4000.251

Replace the wave trap and upgrade the relay at Cloverdale 765kV substation

Jun 01 2029
Contingent

AG2-029, AG2-072, AG2-088, AG2-104, AG2-106, AG2-107, AG2-126, AG2-163, AG2-184, AG2-230, AG2-245, AG2-248, AG2-329, AG2-332, AG2-343, AG2-345, AG2-360, AG2-363, AG2-364, AG2-453, AG2-518, AG2-544, AG2-545, AG2-548, AG2-637, AG2-660, AG2-665, AH1-044, AH1-055, AH1-144, AH1-145, AH1-150, AH1-151, AH1-153, AH1-188, AH1-263, AH1-272, AH1-338, AH1-461, AH1-535, AH1-537, AH1-543, AH1-563, AH1-617, AH1-664, AH1-665, AH1-711, AH1-712, AH1-714, AH1-716, AH1-721, AH1-723

AEP b4000.252

Replace the wave trap and upgrade the relay at Joshua Falls 765kV substation

Jun 01 2029
Contingent

AG2-029, AG2-072, AG2-088, AG2-104, AG2-106, AG2-107, AG2-126, AG2-163, AG2-184, AG2-230, AG2-245, AG2-248, AG2-329, AG2-332, AG2-343, AG2-345, AG2-360, AG2-363, AG2-364, AG2-453, AG2-518, AG2-544, AG2-545, AG2-548, AG2-637, AG2-660, AG2-665, AH1-044, AH1-055, AH1-144, AH1-145, AH1-150, AH1-151, AH1-153, AH1-188, AH1-263, AH1-272, AH1-338, AH1-461, AH1-535, AH1-537, AH1-543, AH1-563, AH1-617, AH1-664, AH1-665, AH1-711, AH1-712, AH1-714, AH1-716, AH1-721, AH1-723

AEP b4000.355

Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 69.3 miles in AEP section).

Jun 01 2029
Contingent

AG2-068, AG2-069, AG2-072, AG2-077, AG2-081, AG2-088, AG2-151, AG2-152, AG2-171, AG2-184, AG2-198, AG2-213, AG2-270, AG2-339, AG2-341, AG2-360, AG2-369, AG2-384, AG2-436, AG2-440, AG2-441, AG2-442, AG2-522, AG2-566, AG2-570, AG2-571, AG2-581, AG2-583, AG2-659, AG2-660, AH1-004, AH1-040, AH1-044, AH1-150, AH1-151, AH1-216, AH1-263, AH1-314, AH1-343, AH1-439, AH1-528, AH1-546, AH1-617, AH1-664, AH1-665, AH1-666, AH1-677, AH1-681, AH1-682, AH1-683, AH1-687, AH1-691, AH1-692, AH1-694, AH1-712, AH1-716, AH1-721, AH1-723

AEP b4068.1 / AEP-TC2-18693

b4068: Greentown 765 kV - Teddy 765kV - Marysville 765 kV - Greenfield Line - AEP Proposal 570

Jun 01 2030
Contingent

AG2-029, AG2-072, AG2-073, AG2-081, AG2-104, AG2-106, AG2-107, AG2-163, AG2-184, AG2-230, AG2-245, AG2-298, AG2-329, AG2-332, AG2-343, AG2-345, AG2-363, AG2-364, AG2-424, AG2-453, AG2-660, AH1-004, AH1-044, AH1-055, AH1-150, AH1-151, AH1-153, AH1-272, AH1-482, AH1-537, AH1-570, AH1-571, AH1-617, AH1-664, AH1-665, AH1-666, AH1-711, AH1-721

AEP n5613 / AEPA0014a

Rebuild 0.9 miles of the Otter - Alta Vista 138 kV line.

Nov 21 2027
Contingent

AG2-077, AG2-152, AH1-343

AEP n7925.1 / AEPI0010a

Reconductor ~0.41 miles of the Sullivan – West Casey (Ameren) line

11 Months
Contingent

AG2-363, AG2-453

AEP n9182.0 / AEPIMJMS01

Rebuild Olive - AF2-359 345kV

30 to 36 Months
$35,000,000

AG2-363, AG2-364, AG2-453, AG2-524, AG2-660, AH1-044, AH1-150, AH1-151, AH1-196, AH1-338, AH1-341, AH1-543, AH1-714

AEP n9746.0 / AEP-TC2-18625

05HODGIN_BP 138.0 kV to 05HAYES 138.0 kV ckt 1 - Replace Conductor

30 to 36 Months
$100,000

AG2-550, AG2-551, AG2-637

AEP n9747.0 / AEP-TC2-18633

AG2-637 TP 138.0 kV to 05HODGIN_BP 138.0 kV ckt 1 - Replace conductor

12 to 18 Months
$100,000

AG2-550, AG2-551, AG2-637

AEP n9748.0 / AEP-TC2-18670

17STILLWELL 345.0 kV to 05DUMONT 345.0 kV ckt 1 - Reconductor and Replace Equipment

36 to 48 Months
$26,060,000

AG2-363, AG2-364, AG2-453, AG2-660, AH1-044, AH1-150, AH1-151, AH1-338, AH1-543, AH1-714

AEP n9749.0 / AEP-TC2-18677

05DUMONT_RW 765.0 kV to 05DUMONT 765.0 kV ckt Z1 - Replace Breaker

36 to 42 Months
$4,000,000

AG2-363, AG2-364, AG2-453, AG2-660, AH1-044, AH1-150, AH1-151, AH1-714

AEP n9750.0 / AEP-TC2-18699

AG2-548 TP 138.0 kV to 05CORWIN 138.0 kV ckt 1 - Replace Equipment

6 to 12 Months
$300,000

AG2-548, AG2-665

AEP n9753.0 / AEP-TC2-18751

05KYGER 345kV to 05SPORN 345kV ckt 1 - Replace Equipment and Sag Study

48 to 60 Months
$5,052,000

AG2-072, AH1-055, AH1-537, AH1-664, AH1-665, AH1-721

AEP n9761.0 / AEP-TC2-19056

05CLNCHR 138.0 kV to 05ABINGD 138.0 kV ckt 1 - Sag Study

12 to 24 Months
$180,000

AG2-184, AH1-227, AH1-617

AH1-072, AH1-073

AEP n9762.0 / AEP-TC2-19058

05HARBER 138.0 kV to 05SOFTSH 138.0 kV ckt 1 - Replace sub conductor

24 to 36 Months
$100,000

AG2-184, AH1-617

AEP n9763.0 / AEP-TC2-19060

05J.FERR 765.0 kV to 05CLOVRD_RJA 765.0 kV ckt 1 - Replace Wavetraps

48 to 54 Months
$3,300,000

AG2-072, AG2-184, AG2-360, AG2-363, AG2-364, AH1-617, AH1-721

AEP n9764.0 / AEP-TC2-19061

05ELKGARDNSS 138.0 kV to 05SALTV1 138.0 kV ckt 1 - Reconductor entrance span

24 to 36 Months
$4,000,000

AG2-184, AH1-072, AH1-073, AH1-227, AH1-617, AH1-721

AH1-535

AEP n9765.0 / AEP-TC2-19065

05CLNCHR 138.0 kV to 05LEBANO 138.0 kV ckt 1 - Rebuild Entrance Span

36 to 48 Months
$4,000,000

AG2-184, AH1-072, AH1-073, AH1-227, AH1-617, AH1-721

AH1-535

AEP n9766.0 / AEP-TC2_19067

05MARYSV 765.0 kV to 05MARYSVL_RM 765.0 kV ckt Z1 - Replace Wavetrap

36 to 48 Months
$1,100,000

AG2-072, AG2-104, AG2-106, AG2-107, AG2-363, AG2-364, AG2-660, AH1-044, AH1-150, AH1-151

AEP n9767.0 / AEP-TC2-19068

05KAMMER_RG 765.0 kV to 05KAMMER 765.0 kV ckt Z1 - Replace Wavetraps

48 to 54 Months
$4,500,000

AG2-072, AG2-104, AG2-106, AG2-107, AG2-363, AG2-364, AG2-660, AH1-044, AH1-150, AH1-151

AEP n9768.0 / AEP-TC2-19069

05MISSIS 138.0 kV to 05DEER CRK1 138.0 kV ckt 1 - Upgrade Risers

24 to 30 Months
$300,000

AG2-191, AG2-192

AEP n9769.0 / AEP-TC2-19070

05CLOVRD_RJA 765.0 kV to 05CLOVRD 765.0 kV ckt Z1 - Upgrade/replace CBs

48 to 54 Months
$25,000,000

AG2-072, AG2-184, AH1-617, AH1-721

AEP n9770.0 / AEP-TC2-19071

05ATKINS 138.0 kV to 05RURALR 138.0 kV ckt 1 - Sag Study

12 to 24 Months
$500,000

AG2-360

AH1-133

AEP n9771.0 / AEP-TC2-19073

05LEBANO 138.0 kV to 05ELKGARDNSS 138.0 kV ckt 1 - Rebuild/Reconductor Entrance Span

24 to 36 Months
$4,000,000

AG2-184, AH1-072, AH1-073, AH1-227, AH1-617, AH1-721

AH1-535

AEP n9772.0 / AEP-TC2-19074

05CLYTR1 138.0 kV to 05SCHRIS 138.0 kV ckt 1 - Replace Structures

24 to 36 Months
$270,000

AG2-518, AH1-144, AH1-145, AH1-269

AEP n9783.0 / AEP-TC2-19115

05BROADX 138.0 kV to 05SMYTH 138.0 - Replace station conductor

24 to 30 Months
$100,000

AG2-360

AH1-133

AEP n9785.0 / AEP-TC2-19160

Olive - 17P9700-East: Rebuild Line

60 to 72 Months
$215,300,000

AG2-363, AG2-364, AG2-453, AG2-524, AG2-660, AH1-044, AH1-150, AH1-151, AH1-196, AH1-338, AH1-341, AH1-543, AH1-714

AEP n9786.0 / AEP-TC2-19161

05MARYSVL_RM 765.0 kV to 05MALIS 765.0 kV ckt 1 - Replace Wave Traps

24 to 36 Months
$3,000,000

AG2-072, AG2-104, AG2-106, AG2-107, AG2-363, AG2-364, AG2-660, AH1-044, AH1-150, AH1-151

AEP s2063.4 / AEPO0001a

Upgrade/Replace 3-345kV 1600A switches at Beatty station

Nov 15 2022
Contingent

AH1-664, AH1-665

AEP s2572.3

Rebuild ~21 miles of the 138KV line between Saltville and Tazewell stations

Sep 02 2036
Contingent

AG2-360, AH1-133, AH1-721

AEP s2793.5 / s2793

Rebuild the T-line from West Van Wert to Roller Creek

Jul 18 2025
Contingent

AG2-406

AEP s2887.1 / s2887

Construct a new brownfield, breaker and a half Glen Lyn station next to the existing station

TBD
Contingent

AH1-144, AH1-145

AEP s2887.4

Extend the Glen Lyn – Morgans Cut and Glen Lyn – Hazel Hollow lines

Apr 03 2029
Contingent

AH1-144, AH1-145

AEP s3442.26

Dumont 765 kV: Replace 3000 A circuit breaker at Dumont

Dec 01 2026
Contingent

AG2-363, AG2-364, AG2-453, AG2-660, AH1-044, AH1-150, AH1-151

AEP s3588.1 / (Pending)

Construct new Larrison Drive 345 kV substation

Dec 15 2026
Contingent

AG2-163, AG2-245, AG2-363, AG2-364, AG2-453, AG2-660, AH1-044, AH1-150, AH1-151, AH1-482

AEP s3588.2 / (Pending)

Construct new New Prairie 345 kV substation

Dec 15 2026
Contingent

AG2-163, AG2-245, AG2-363, AG2-364, AG2-453, AG2-660, AH1-044, AH1-150, AH1-151, AH1-482

APS (Pending) / APS-2024-010 (Supplemental)

Misoperation Relays: Armstrong - Kittanning 138 kV Line (Supplemental - Projected ISD 9/10/2029)

TBD
Contingent

AG2-176, AG2-429

APS b3800.104

Rebuild ~15 miles of the Stonewall-Millville 138 kV line with 500 kV overbuild

Jun 01 2030
Contingent

AG2-288

APS b4000.10

Install four 250 MVAR cap banks (two on 765 and two on 500 kV side) and a +/-500 MVAR STATCOM on the 765 kV Rocky Point yard

Jun 01 2029
Contingent

AG2-062, AG2-072, AG2-104, AG2-106, AG2-107, AG2-184, AG2-360, AG2-363, AG2-364, AG2-411, AG2-423, AG2-448, AG2-518, AG2-582, AG2-657, AG2-660, AH1-044, AH1-144, AH1-145, AH1-150, AH1-151, AH1-269, AH1-272, AH1-460, AH1-617, AH1-711, AH1-721

APS b4000.11

Expand Black Oak Substation & Loop in the 502 Jct-Woodside 500 kV line (Projected ISD 6/1/2029)

Jun 01 2029
Contingent

AG2-062, AG2-072, AG2-104, AG2-106, AG2-107, AG2-184, AG2-360, AG2-363, AG2-364, AG2-411, AG2-423, AG2-448, AG2-518, AG2-582, AG2-657, AG2-660, AH1-044, AH1-144, AH1-145, AH1-150, AH1-151, AH1-269, AH1-272, AH1-460, AH1-617, AH1-711, AH1-721

APS b4000.2

Construct a new 175 miles Amos to Welton Spring 765 kV line - AEP Section of the line is 30 miles (Projected ISD 6/1/2029)

Jun 01 2029
Contingent

AG2-062, AG2-072, AG2-104, AG2-106, AG2-107, AG2-184, AG2-360, AG2-363, AG2-364, AG2-411, AG2-423, AG2-448, AG2-518, AG2-582, AG2-657, AG2-660, AH1-044, AH1-144, AH1-145, AH1-150, AH1-151, AH1-269, AH1-272, AH1-460, AH1-617, AH1-711, AH1-721

APS b4000.3

Construct a new 175 miles Amos to Welton Spring 765 kV line - APS/FE Section of the line is 145 miles (Projected ISD 6/1/2029)

Jun 01 2029
Contingent

AG2-062, AG2-072, AG2-104, AG2-106, AG2-107, AG2-184, AG2-360, AG2-363, AG2-364, AG2-411, AG2-423, AG2-448, AG2-518, AG2-582, AG2-657, AG2-660, AH1-044, AH1-144, AH1-145, AH1-150, AH1-151, AH1-269, AH1-272, AH1-460, AH1-617, AH1-711, AH1-721

APS b4000.4

Construct a new 765 kV switchyard - Welton Spring (Projected ISD 6/1/2029)

Jun 01 2029
Contingent

AG2-062, AG2-072, AG2-104, AG2-106, AG2-107, AG2-184, AG2-360, AG2-363, AG2-364, AG2-411, AG2-423, AG2-448, AG2-518, AG2-582, AG2-657, AG2-660, AH1-044, AH1-144, AH1-145, AH1-150, AH1-151, AH1-269, AH1-272, AH1-460, AH1-617, AH1-711, AH1-721

APS b4000.5

Install four 250 MVAR shunt capacitors, and a +/-500 MVAR STATCOM at Welton Spring 765 kV substation

Jun 01 2029
Contingent

AG2-062, AG2-072, AG2-104, AG2-106, AG2-107, AG2-184, AG2-360, AG2-363, AG2-364, AG2-411, AG2-423, AG2-448, AG2-518, AG2-582, AG2-657, AG2-660, AH1-044, AH1-144, AH1-145, AH1-150, AH1-151, AH1-269, AH1-272, AH1-460, AH1-617, AH1-711, AH1-721

APS b4000.6

Construct a new 86 miles Welton Spring to Rocky Point 765 kV line (Welton Spring to DVP local area, roughly 21 miles) (VA Portion)

Jun 01 2029
Contingent

AG2-062, AG2-072, AG2-104, AG2-106, AG2-107, AG2-184, AG2-360, AG2-363, AG2-364, AG2-411, AG2-423, AG2-448, AG2-518, AG2-582, AG2-657, AG2-660, AH1-044, AH1-144, AH1-145, AH1-150, AH1-151, AH1-269, AH1-272, AH1-460, AH1-617, AH1-711, AH1-721

APS b4000.7

Construct a new 86 miles Welton Spring to Rocky Point 765 kV line - in DVP local area/Millville to Lovettsville section, roughly 10.5 miles (Projected ISD 6/1/2029)

Jun 01 2029
Contingent

AG2-062, AG2-072, AG2-104, AG2-106, AG2-107, AG2-184, AG2-360, AG2-363, AG2-364, AG2-411, AG2-423, AG2-448, AG2-518, AG2-582, AG2-657, AG2-660, AH1-044, AH1-144, AH1-145, AH1-150, AH1-151, AH1-269, AH1-272, AH1-460, AH1-617, AH1-711, AH1-721

APS b4000.8

Construct a new 86 miles Welton Spring to Rocky Point 765 kV line (DVP local area to Rocky Point, roughly 4.8 miles)

Jun 01 2029
Contingent

AG2-062, AG2-072, AG2-104, AG2-106, AG2-107, AG2-184, AG2-360, AG2-363, AG2-364, AG2-411, AG2-423, AG2-448, AG2-518, AG2-582, AG2-657, AG2-660, AH1-044, AH1-144, AH1-145, AH1-150, AH1-151, AH1-269, AH1-272, AH1-460, AH1-617, AH1-711, AH1-721

APS b4000.9

Construct a new substation called Rocky Point with a 765 kV and a 500 kV yard (Projected ISD 6/1/2029)

Jun 01 2029
Contingent

AG2-062, AG2-072, AG2-104, AG2-106, AG2-107, AG2-184, AG2-360, AG2-363, AG2-364, AG2-411, AG2-423, AG2-448, AG2-518, AG2-582, AG2-657, AG2-660, AH1-044, AH1-144, AH1-145, AH1-150, AH1-151, AH1-269, AH1-272, AH1-460, AH1-617, AH1-711, AH1-721

APS b4002.1

Garrett-Garrett Tap 115 kV Line Upgrade: Rebuild approximately 1.9 miles of 115 kV line with larger conductor

Jun 01 2029
Contingent

AG2-411, AH1-460

APS b4002.2

Adjust the relay settings at Penn Mar, Garrett, and Deep Creek 115kV substations

Jun 01 2029
Contingent

AG2-411, AH1-460

APS b4052.5

Rocky Point 500 kV remote work for Dickerson (new 500 kV)-Rocky Point line

Jun 01 2032
Contingent

AG2-068, AG2-069, AG2-369, AG2-436, AG2-570, AG2-571, AH1-528, AH1-681, AH1-712, AH1-723

APS n6183

Rebuild 10.4 miles of 4/0 CU from Columbia Big Pine - Garretts Run Jct 138 kV (99 spans). Also upgrade terminal end equipment.

26 Months
$36,946,687

AG2-176, AG2-429

AG2-420

APS n7165.1

Replace T-line drops at All Dam 6

12 Months
$427,516

AG2-176, AG2-429

AG2-420

APS n7165.2

Reconductor All Dam 6 - Kittanning 138kV line. Also upgrade terminal end equipment.

22 Months
$21,034,523

AG2-176, AG2-429

AG2-420

APS n7166.1

Replace 4/0 CU line exit at All Dam 6 Tap.

18 Months
$922,908

AG2-176, AG2-429

AG2-420

APS n7166.2

Reconductor 7.6 miles of 4/0 CU from All Dam 6 Tap to structure 84 (66 spans). Also upgrade terminal end equipment.

23 Months
$26,284,067

AG2-176, AG2-429

AG2-420

APS n7171.1

Rebuild approximately 4.0 miles of 4/0 CU on the Kiski Valley to Columbia Big Pine 138kV line. Also upgrade terminal end equipment.

20 Months
$15,258,720

AG2-176, AG2-429

AG2-420

APS n9717.0 / TC1-PH1-076

Reconductor Butler - Karns City 138 kV line. Also upgrade terminal end equipment.

30 Months
$51,840,579

AG2-176, AG2-429

AG2-420

APS n9733.0 / TC2-APS-015.a

Replace 500/138 kV TR2 with (3) Single Phase 500/138 kV TRs at Flint Run.

80 Months
$32,119,007

AG2-582

APS n9734.0 / TC2-APS-036.a

Upgrade/Replace (6) 138kV Substation Conductors [(2) ACSR 954 45/7 & (4) AAC 1000 37]

15 Months
$1,084,903

AG2-176

APS n9735.0 / TC2-APS-016.a

Replace 500/138 kV TR1 with (3) Single Phase 500/138 kV TRs at Flint Run.

80 Months
$32,119,007

AG2-582

APS n9736.0 / TC2-APS-015.b

Replace 6 138 kV Disc Switches and 5 Breaker Leads at Flint Run

24 Months
$1,826,164

AG2-582

APS n9737.0 / TC2-APS-016.b

Replace 6 138 kV Disc Switches and 5 Breaker Leads at Flint Run

24 Months
$1,826,164

AG2-582

APS n9738.0 / TC2-APS-016.c

Replace SCCIR 3" Pipe A-frame closest to Disc SW A-39

18 Months
$597,737

AG2-582

APS s3191.1 / APS-2023-056

Harrison – Pruntytown 500 kV Misoperation Relays (Projected ISD by end of 2025)

Dec 31 2024
Contingent

AG2-582

ATSI (Pending) / ATSI-2025-004 (Supplemental)

Lemoyne Sub Upgrades & New Greenfield-Ottawa 138kV Line (Projected ISD 6/1/2032) - s3844.1

TBD
Contingent

AH1-711

ATSI (Pending) / ATSI-2025-005 (Supplemental)

Lallendorf & Allen Jct Substation Upgrades (Projected ISD 6/1/2032) - s3845.1

TBD
Contingent

AH1-272

ATSI b3925.2

Rebuild the 13.45 miles of Greenfield - Lakeview 138 kV Line from 2 x 336.4 kcmil 26/7 ACSR to 1 x 795 kcmil 26/7 ACSS

Jun 01 2029
Contingent

AG2-289, AG2-290, AG2-660, AH1-044, AH1-150, AH1-151, AH1-711

ATSI b3925.4

Rebuild the Greenfield - Beaver 138 kV corridor (32 miles) with 795 kcmil 26/7 ACSS

Jun 01 2029
Contingent

AH1-711

ATSI n9227.0 / TC1-ATSI-001.b

Beaver-Lake Ave Ckt #2 345kV: Upgrade T-line drops, overhead substation conductor and TL reconductor

37 Months
$48,873,856

AH1-711

BGE b3780.13

Batavia Road to Riverside 230 kV reconductor

Dec 31 2027
Contingent

AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725

BGE b3780.4

Peach Bottom to Graceton (BGE Portion) – New 500kV Line

Dec 31 2028
Contingent

AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725

BGE b3780.5

Build Solley Road substation + Statcom (Projected ISD 12/31/2028)

Dec 31 2028
Contingent

AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725

BGE b3780.6

Build Granite substation + Statcom (Projected ISD 12/31/2028)

Dec 31 2028
Contingent

AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725

BGE b3780.7

Build new Batavia Road substation (Projected ISD 12/31/2028)

Dec 31 2028
Contingent

AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725

BGE b3780.8

Graceton 500 kV substation expansion (Projected ISD 12/31/2028)

Dec 31 2028
Contingent

AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725

BGE b3780.9

Graceton to Batavia Road 230 kV double circuit pole line (Projected ISD 12/31/2028)

Dec 31 2028
Contingent

AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725

BGE b3800.26

Build High Ridge 500 kV substation - Three bay breaker and half configuration (Projected ISD 12/31/2030)

Dec 31 2030
Contingent

AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725

BGE b3800.27

High Ridge 500 kV substation (cut into Brighton-Waugh Chapel 500 kV line) - Waugh Chapel side (Projected ISD 12/31/2030)

Dec 31 2030
Contingent

AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725

BGE b3800.28

High Ridge 500 kV substation (cut into Brighton-Waugh Chapel 500 kV line) -Brighton side (Projected ISD 12/31/2030)

Dec 31 2030
Contingent

AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725

BGE b3800.29

High Ridge termination for the North Delta-High Ridge 500 kV line (Projected ISD 12/31/2030)

Dec 31 2030
Contingent

AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725

BGE b3800.30

High Ridge - Install two 500/230 kV transformers (Projected ISD 12/31/2030)

Dec 31 2030
Contingent

AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725

BGE b3800.32

Build new North Delta-High Ridge 500 kV line - BGE Portion (Projected ISD 12/31/2030)

Dec 31 2030
Contingent

AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725

BGE b3800.33

Replace terminal equipment limitations at Brighton 500 kV - on the existing Brighton-Waugh Chapel 500 kV (5053) or new Brighton-High Ridge 500 kV.

Dec 31 2030
Contingent

AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725

BGE b3800.34

Rebuild 5012 (existing Peach Bottom-Conastone) (new Graceton-Conastone) 500 kV and cut into North Delta 500kV (Projected ISD 12/31/2030)

Dec 31 2030
Contingent

AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725

BGE b3800.36

Rebuild 5012 (existing Peach Bottom-Conastone) (new North Delta-Graceton BGE) 500 kV (Projected ISD 12/31/2030)

Dec 31 2030
Contingent

AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725

BGE b3800.37

Replace terminal equipment limitations at Conastone 500 kV - on the (existing Peach Bottom-Conastone) or (new Graceton-Conastone) 500 kV line (Projected ISD 12/31/2030)

Dec 31 2030
Contingent

AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725

BGE n9773.0 /

New Upgrade for BRANDN.S 230.0 kV to SOLLEY_42 230.0 kV ckt 42 & 43

60 Months
$22,000,000

AH1-261

ComEd b3811.1 / CE_PJM B3811_L11323

Expand Haumesser Road 138 kV substation as a 4 circuit breaker ring bus.

Dec 01 2028
Contingent

AH1-338, AH1-341

ComEd b3811.2 / CE_PJM B3811_L11323

Additional Circuit Breaker at ESS H452

Dec 01 2028
Contingent

AH1-338, AH1-341

ComEd b3811.3 / CE_PJM B3811_L11323

Rebuild 3 miles of 138 kV line 11323 from Haumesser Road to the H-452 tap

Dec 01 2028
Contingent

AH1-338, AH1-341

ComEd b3915.1

Reconductor 345 kV lines 1202 and 1227 from Dresden to Mulberry

Jun 01 2029
Contingent

AG2-363, AG2-364, AH1-543

ComEd b3915.2

Equipment upgrades at Dresden 345 kV Substation

Jun 01 2029
Contingent

AG2-363, AG2-364, AH1-543

ComEd b3915.3

Equipment upgrades at Mulberry 345 kV Substation

Jun 01 2029
Contingent

AG2-363, AG2-364, AH1-543

ComEd b4006.1

Install 765/345 kV TR 91 and associated 765 kV and 345 kV circuit breakers at Wilton Center.

Dec 01 2030
Contingent

AG2-363, AG2-364, AG2-453, AG2-660, AH1-044, AH1-150, AH1-151, AH1-543, AH1-714

ComEd n3515.1 / ce-017

Cherry Valley - Garden Prarie 345 kV: Line rebuild, station bus work, & Cherry Valley 345kV breaker replacement

50 Months
$84,712,245

AG2-516, AG2-660, AH1-044, AH1-150, AH1-151, AH1-341, AH1-564

ComEd n5318.1 / ce-012a

Garden Prarie - Silver Lake R 345 kV: Line rebuild, station bus work & Silver Lake 345kV Breaker Replacement

60 Months
$163,968,683

AG2-516, AG2-660, AH1-044, AH1-150, AH1-151, AH1-196, AH1-341, AH1-564

ComEd n5792 / CE_NUN_L11323

Rebuild Haumesser - West Dekalb 138 kV line (L11323)

30 Months
$10,479,841

AH1-338, AH1-341

ComEd n6260.1 / CE_NUN_8012

Upgrade of TSS 80 Pontiac 345kV circuit breaker BT 4-5 and 345kV station and bus conductor

60 Months
Contingent

AG2-114, AH1-541

ComEd n6260.2 / N6260.2

Replace a line disconnect switch to upgrade the Pontiac - Loretto 345 kV line.

24 Months
$500,000

AG2-114, AH1-541

ComEd n6280 / ce-005

Mitigate the sag on the ComEd Powerton - Tazewell L0304 345 kV line.

Nov 01 2026
Contingent

AG2-363, AG2-364

ComEd n6611 / ce-007

The upgrades will be to reconductor the line, station conductor upgrades.

30 Months
Contingent

AH1-044, AH1-150, AH1-151, AH1-338, AH1-341

ComEd n6639.2 / CE_NUN_L15502_4

Reconductor the Electric Junction 345 kV line 93407, perform sag mitigation on 345 kV line 93407, upgrade one 345 kV circuit breaker and associated motor operated disconnect switches.

Sep 30 2029
Contingent

AG2-660, AH1-044, AH1-150, AH1-151, AH1-341

ComEd n6779 / CE_NUN_L14609

Plano 138 KV re-conductor a portion of the line

30 Months
$5,600,000

AH1-338, AH1-341

ComEd n7023.1 / CE_NUN_L11124.1

Reconductor the Electric Junction - Lombard line L11124 345 kV Line and perform associated station relay and protection upgrades.

36 Months
$38,797,273

AG2-660, AH1-044, AH1-150, AH1-151, AH1-338, AH1-563

ComEd n9165.0 / CE_NUN_L15502.1

Perform TSS 155 Nelson Substation conductor upgrades.

36 Months
$1,220,445

AG2-660

ComEd n9166.0 / CE_NUN_L16914.1

Reconductor the McGirr Road to ESS H447 RT 138 KV line

24 Months
$605,422

AH1-341

AG2-660, AH1-044, AH1-150, AH1-151

ComEd n9172.0 / CE_NUN_L18623.2

Haumesser - Steward 138 kV Line Reconductor

18 to 24 Months
$8,500,000

AG2-660, AH1-044, AH1-150, AH1-151, AH1-338, AH1-341

ComEd n9195.0 / CE_NUN_STA12_345 NEW CB

Install a new 345 kV circuit breaker at Station 12 Dresden.

Dec 15 2030
Contingent

AG2-114, AH1-541

ComEd n9269.0 / CE_NUN_L11212.5

Reconductor the L11212 345 kV line.

Dec 15 2030
Contingent

AG2-114, AH1-541

ComEd n9678.0 / CE_NUN_L11215_1

Mitigate the sag on L11215

30 Months
$9,000,000

AG2-363, AG2-364, AG2-453, AG2-660, AH1-044, AH1-150, AH1-151, AH1-338, AH1-714

ComEd n9718.0 / CE_NUN_COLLINS_NEW CB

New Collins New 765KV Circuit Breaker

24 to 30 Months
$15,500,000

AG2-363, AG2-364, AG2-453, AG2-660, AH1-044, AH1-150, AH1-151, AH1-714

ComEd n9719.0 / CE_NUN_COLLINS_TR

Collins Station 23 New Transformer-reduces contingency events.

24 to 30 Months
$15,600,000

AG2-363, AG2-364, AG2-453, AG2-660, AH1-044, AH1-150, AH1-151, AH1-543, AH1-714

ComEd n9720.0 / CE_NUN_L1205-1

TC2 Network Upgrade- L1205

24 to 30 Months
$2,800,000

AG2-524

ComEd n9721.0 / CE_NUN_L95201_1

194 Sabrooke Station Conductor

12 to 16 Months
$500,000

AH1-564

ComEd n9722.0 / CE_NUN_TSS155_TR83

TSS155 Nelson New Transformer

24 to 30 Months
$15,200,000

AG2-660, AH1-044, AH1-150, AH1-151

ComEd n9754.0 / CE_NUN_TSS 111

TSS 167 Plano new circuit breaker

12 to 18 Months
$5,000,000

AG2-660, AH1-044, AH1-150, AH1-151

ComEd n9755.0 / CE_NUN_L17705_1

Reconductor Sheffield - Burnham and upgrade station conductor at Burnham

24 to 30 Months
$14,000,000

AG2-363, AG2-364, AG2-453, AG2-660, AH1-044, AH1-150, AH1-151, AH1-714

ComEd n9784.0 / CE_L11103_2

L11103 Station conductor and line work

24 to 30 Months
$6,500,000

AH1-563

ComEd s3011 / CE_S3011

Replace 345kV straight bus at TSS 116 Goodings Grove with a gas insulated switchgear ("GIS") breaker and a half configuration.

Dec 31 2029
Contingent

AG2-363, AG2-364, AG2-660, AH1-044, AH1-150, AH1-151, AH1-341

DEOK b2831.2

Rebuild the Tanner Creek – Miami Fort 345kV line (DEOK portion), Actual In-service date 5/14/2021

May 14 2021
Contingent

AG2-072, AG2-660, AH1-044, AH1-150, AH1-151

DEOK b3944.1 / (Pending)

Rebuild the McGuffey to Locust 69 kV line (~1.35 miles) with 954 ACSR rail conductor and OPGW.

May 25 2029
Contingent

AG2-550, AG2-551, AG2-637

DEOK b4003.1 / (Pending)

Rebuild the College Corner (AEP)-Collinsville (DEOK) 138 kV circuit. (DEOK Portion)

Jun 01 2030
Contingent

AG2-550, AG2-551, AG2-637

DEOK s2019 / AEP Project Resolves Overload

AEP Project s2019 Resolves DEOK Overload

May 26 2021
Contingent

AG2-072, AG2-660, AH1-044, AH1-150, AH1-151

DPL (Pending) / PE-2025-008 (Supplemental)

DPL 230 kV Supplemental Upgrades

60 Months
Contingent

AH1-672, AH1-710

DPL b4004.1

Upgrade terminal equipment at Claymont substation

May 31 2030
Contingent

AH1-710

DPL n7042 / dt6704r0001

Rebuild Kent to N. Meredith Tap.

36 to 48 Months
$28,800,000

AG2-380

DPL n9774.0 /

Rebuild BRIDGEVL 69.0 kV to TAYLOR 69.0 kV ckt 1 to achieve 70 MVA minimum

36 to 60 Months
$15,000,000

AG2-447

Dayton b3904.1

Rebuild and reconductor 7.7 miles of 69kV line.

Jun 01 2029
Contingent

AG2-406

Dominion b3692

Rebuild approximately 27.7-miles of 500 kV transmission line from Elmont to Chickahominy.

TBD
Contingent

AG2-436, AG2-570, AG2-571, AH1-528, AH1-716

Dominion b3694.1

Convert line #29 Aquia Harbor to Possum Point to 230 kV (Extended line #2104) and swap line #2104 and converted line #29 at Aquia Harbor backbone termination.

Sep 28 2029
Contingent

AG2-436, AH1-682, AH1-683, AH1-691, AH1-692, AH1-694

Dominion b3694.4

Reconductor/rebuild approx 7.6 miles of 230 kV line #2104 Cranes Corner-Stafford. Reconductor/rebuild approx 0.34 miles of 230 kV line #2104 Stafford-Aquia Harbor. Upgrade terminal equipment.

TBD
Contingent

AG2-436, AH1-682, AH1-683, AH1-691, AH1-692, AH1-694

Dominion b3800.300

Wreck/Rebuild 230kV Line #2135 segment Hollymeade Junction – Cash’s Corner using double-circuit capable 230 kV poles. (The second 230kV circuit will be wired but not have terminal ends.)

Jun 30 2028
Contingent

AH1-681, AH1-712, AH1-723

Dominion b3800.302

Upgrade Cash's Corner switches 213576 and 213579 and line leads to 4000A continuous current rating of 230kV Line #2135.

Jun 30 2028
Contingent

AH1-681, AH1-712, AH1-723

Dominion b4000.315

Reconductor 230kV Line #2003 Tyler – Poe segment. New conductor has a summer rating of 1573 MVA.

Apr 22 2030
Contingent

AG2-068, AG2-069, AG2-077, AG2-339, AG2-369, AG2-426, AG2-436, AG2-570, AG2-571, AG2-581, AH1-528

Dominion b4000.316

At Poe substation, uprate all Line #2003 terminal equipment, line leads, and bus to be rated to 4000A.

Apr 22 2030
Contingent

AG2-068, AG2-069, AG2-077, AG2-339, AG2-369, AG2-426, AG2-436, AG2-570, AG2-571, AG2-581, AH1-528

Dominion b4000.317

At Tyler substation, upgrade the necessary line terminal equipment to maintain 4000A at Tyler substation.

Apr 22 2030
Contingent

AG2-068, AG2-069, AG2-077, AG2-339, AG2-369, AG2-426, AG2-436, AG2-570, AG2-571, AG2-581, AH1-528

Dominion b4000.319

Reconductor 230kV Line #2002 Carson – Poe. New conductor has a summer rating of 1573 MVA.

Mar 20 2030
Contingent

AG2-068, AG2-069, AG2-077, AG2-270, AG2-339, AG2-369, AG2-436, AG2-440, AG2-441, AG2-442, AG2-570, AG2-571, AG2-581, AH1-528, AH1-677

Dominion b4000.320

At Carson substation, upgrade all line #2002 terminal equipment at Carson to 4000A. CCVTs will also be replaced due to aging.

Mar 20 2030
Contingent

AG2-068, AG2-069, AG2-077, AG2-270, AG2-339, AG2-369, AG2-436, AG2-440, AG2-441, AG2-442, AG2-570, AG2-571, AG2-581, AH1-528, AH1-677

Dominion b4000.321

At Poe substation, upgrade all line #2002 terminal equipment at Carson to 4000A. CCVTs will also be replaced due to aging.

Mar 20 2030
Contingent

AG2-068, AG2-069, AG2-077, AG2-270, AG2-339, AG2-369, AG2-436, AG2-440, AG2-441, AG2-442, AG2-570, AG2-571, AG2-581, AH1-528, AH1-677

Dominion b4000.325

Build a new 26.38mi 230kV Line from Elmont – Ladysmith on the existing 5-2 structures between the two stations. New conductor has a summer rating of 1573 MVA.

Feb 24 2029
Contingent

AG2-436, AG2-570, AG2-571, AH1-528, AH1-681, AH1-712, AH1-723

Dominion b4000.326

At Elmont substation, install/upgrade associated equipment to accommodate a 4000A line rating for the new 230kV line between Elmont - Ladysmith.

Feb 24 2029
Contingent

AG2-436, AG2-570, AG2-571, AH1-528, AH1-681, AH1-712, AH1-723

Dominion b4000.327

Upgrade/install equipment at Ladysmith Substation to 4000A. Expansion will be required to accommodate a total of three (3) new 230 kV strings of breaker and a half scheme.

Feb 24 2029
Contingent

AG2-436, AG2-570, AG2-571, AH1-528, AH1-681, AH1-712, AH1-723

Dominion b4000.334

Reconductor 115kV line #121 from Poe - Prince George. Specifically, line #121 will be reconductored and converted to 230kV from Poe substation to Prince George substation.

Jan 10 2030
Contingent

AG2-095, AG2-384, AG2-661, AH1-216

Dominion b4000.335

At Poe substation, install a new 230kV six breaker ultimate ring bus which will fit the station to current 230kV standards.

Jan 10 2030
Contingent

AG2-095, AG2-384, AG2-661, AH1-216

Dominion b4000.336

Build a new 230-115kV Prince George substation along the existing 115 or 230kV corridor.

Jan 10 2030
Contingent

AG2-095, AG2-384, AG2-661, AH1-216

Dominion b4000.341

Remove the 500 kV conductor previously planned to terminate into the Vint Hill 500 kV Substation and extend approximately 0.2 miles of conductor to fly-over the site.

Jul 13 2029
Contingent

AG2-068, AG2-069, AG2-072, AG2-077, AG2-081, AG2-088, AG2-151, AG2-152, AG2-171, AG2-184, AG2-198, AG2-213, AG2-270, AG2-339, AG2-341, AG2-360, AG2-369, AG2-382, AG2-384, AG2-436, AG2-440, AG2-441, AG2-442, AG2-522, AG2-566, AG2-570, AG2-571, AG2-581, AG2-583, AG2-659, AG2-660, AH1-004, AH1-040, AH1-044, AH1-150, AH1-151, AH1-170, AH1-216, AH1-263, AH1-271, AH1-314, AH1-343, AH1-439, AH1-528, AH1-546, AH1-617, AH1-664, AH1-665, AH1-666, AH1-677, AH1-681, AH1-682, AH1-683, AH1-687, AH1-691, AH1-692, AH1-694, AH1-712, AH1-716, AH1-721, AH1-723

Dominion b4000.342

Remove the terminal equipment and substation work required for the termination of the Morrisville-Wishing Star 500 kV line into Vint Hill.

Jul 13 2029
Contingent

AG2-068, AG2-069, AG2-072, AG2-077, AG2-081, AG2-088, AG2-151, AG2-152, AG2-171, AG2-184, AG2-198, AG2-213, AG2-270, AG2-339, AG2-341, AG2-360, AG2-369, AG2-382, AG2-384, AG2-436, AG2-440, AG2-441, AG2-442, AG2-522, AG2-566, AG2-570, AG2-571, AG2-581, AG2-583, AG2-659, AG2-660, AH1-004, AH1-040, AH1-044, AH1-150, AH1-151, AH1-170, AH1-216, AH1-263, AH1-271, AH1-314, AH1-343, AH1-439, AH1-528, AH1-546, AH1-617, AH1-664, AH1-665, AH1-666, AH1-677, AH1-681, AH1-682, AH1-683, AH1-687, AH1-691, AH1-692, AH1-694, AH1-712, AH1-716, AH1-721, AH1-723

Dominion b4000.344

Build a 500kV line from North Anna substation (bypassing Ladysmith Substation) to a new substation called Thornburg (formerly Kraken). New conductor to have a minimum summer normal rating of 4357MVA.

Sep 16 2030
Contingent

AG2-068, AG2-069, AG2-072, AG2-077, AG2-081, AG2-088, AG2-151, AG2-152, AG2-171, AG2-184, AG2-198, AG2-213, AG2-270, AG2-339, AG2-341, AG2-360, AG2-369, AG2-382, AG2-384, AG2-436, AG2-440, AG2-441, AG2-442, AG2-522, AG2-566, AG2-570, AG2-571, AG2-581, AG2-583, AG2-659, AG2-660, AH1-004, AH1-040, AH1-044, AH1-150, AH1-151, AH1-170, AH1-216, AH1-263, AH1-271, AH1-314, AH1-343, AH1-439, AH1-528, AH1-546, AH1-617, AH1-664, AH1-665, AH1-666, AH1-677, AH1-681, AH1-682, AH1-683, AH1-687, AH1-691, AH1-692, AH1-694, AH1-712, AH1-716, AH1-721, AH1-723

Dominion b4000.345

Build a 500kV line from a new substation called Thornburg (formerly Kraken) to a new substation called Yeat. New conductor to have a minimum summer normal rating of 4357MVA.

Sep 16 2030
Contingent

AG2-068, AG2-069, AG2-072, AG2-077, AG2-081, AG2-088, AG2-151, AG2-152, AG2-171, AG2-184, AG2-198, AG2-213, AG2-270, AG2-339, AG2-341, AG2-360, AG2-369, AG2-382, AG2-384, AG2-436, AG2-440, AG2-441, AG2-442, AG2-522, AG2-566, AG2-570, AG2-571, AG2-581, AG2-583, AG2-659, AG2-660, AH1-004, AH1-040, AH1-044, AH1-150, AH1-151, AH1-170, AH1-216, AH1-263, AH1-271, AH1-314, AH1-343, AH1-439, AH1-528, AH1-546, AH1-617, AH1-664, AH1-665, AH1-666, AH1-677, AH1-681, AH1-682, AH1-683, AH1-687, AH1-691, AH1-692, AH1-694, AH1-712, AH1-716, AH1-721, AH1-723

Dominion b4000.346

Cut-in 500kV line from Thornburg (formerly Kraken) substation into Yeat substation

Jun 01 2029
Contingent

AG2-068, AG2-069, AG2-072, AG2-077, AG2-081, AG2-088, AG2-151, AG2-152, AG2-171, AG2-184, AG2-198, AG2-213, AG2-270, AG2-339, AG2-341, AG2-360, AG2-369, AG2-382, AG2-384, AG2-436, AG2-440, AG2-441, AG2-442, AG2-522, AG2-566, AG2-570, AG2-571, AG2-581, AG2-583, AG2-659, AG2-660, AH1-004, AH1-040, AH1-044, AH1-150, AH1-151, AH1-170, AH1-216, AH1-263, AH1-271, AH1-314, AH1-343, AH1-439, AH1-528, AH1-546, AH1-617, AH1-664, AH1-665, AH1-666, AH1-677, AH1-681, AH1-682, AH1-683, AH1-687, AH1-691, AH1-692, AH1-694, AH1-712, AH1-716, AH1-721, AH1-723

Dominion b4000.348

Build a new 500/230kV substation called Thornburg (formerly Kraken). The 500kV, 5000A ring bus will be set up for a redundant breaker configuration. Install (2) 1400MVA 500/230 kV transformers.

Jun 01 2029
Contingent

AG2-068, AG2-069, AG2-072, AG2-077, AG2-081, AG2-088, AG2-151, AG2-152, AG2-171, AG2-184, AG2-198, AG2-213, AG2-270, AG2-339, AG2-341, AG2-360, AG2-369, AG2-382, AG2-384, AG2-436, AG2-440, AG2-441, AG2-442, AG2-522, AG2-566, AG2-570, AG2-571, AG2-581, AG2-583, AG2-659, AG2-660, AH1-004, AH1-040, AH1-044, AH1-150, AH1-151, AH1-170, AH1-216, AH1-263, AH1-271, AH1-314, AH1-343, AH1-439, AH1-528, AH1-546, AH1-617, AH1-664, AH1-665, AH1-666, AH1-677, AH1-681, AH1-682, AH1-683, AH1-687, AH1-691, AH1-692, AH1-694, AH1-712, AH1-716, AH1-721, AH1-723

Dominion b4000.349

Update relay settings at Ladysmith to change the destination of 500kV line #568 from Possum Point to Thornburg (formerly Kraken).

Sep 16 2030
Contingent

AG2-068, AG2-069, AG2-072, AG2-077, AG2-081, AG2-088, AG2-151, AG2-152, AG2-171, AG2-184, AG2-198, AG2-213, AG2-270, AG2-339, AG2-341, AG2-360, AG2-369, AG2-382, AG2-384, AG2-436, AG2-440, AG2-441, AG2-442, AG2-522, AG2-566, AG2-570, AG2-571, AG2-581, AG2-583, AG2-659, AG2-660, AH1-004, AH1-040, AH1-044, AH1-150, AH1-151, AH1-170, AH1-216, AH1-263, AH1-271, AH1-314, AH1-343, AH1-439, AH1-528, AH1-546, AH1-617, AH1-664, AH1-665, AH1-666, AH1-677, AH1-681, AH1-682, AH1-683, AH1-687, AH1-691, AH1-692, AH1-694, AH1-712, AH1-716, AH1-721, AH1-723

Dominion b4000.350

Update relay settings at Possum Point to change the destination of 500kV line #568 from Ladysmith to Thornburg (formerly Kraken).

Sep 16 2030
Contingent

AG2-068, AG2-069, AG2-072, AG2-077, AG2-081, AG2-088, AG2-151, AG2-152, AG2-171, AG2-184, AG2-198, AG2-213, AG2-270, AG2-339, AG2-341, AG2-360, AG2-369, AG2-382, AG2-384, AG2-436, AG2-440, AG2-441, AG2-442, AG2-522, AG2-566, AG2-570, AG2-571, AG2-581, AG2-583, AG2-659, AG2-660, AH1-004, AH1-040, AH1-044, AH1-150, AH1-151, AH1-170, AH1-216, AH1-263, AH1-271, AH1-314, AH1-343, AH1-439, AH1-528, AH1-546, AH1-617, AH1-664, AH1-665, AH1-666, AH1-677, AH1-681, AH1-682, AH1-683, AH1-687, AH1-691, AH1-692, AH1-694, AH1-712, AH1-716, AH1-721, AH1-723

Dominion b4000.351

Cut in Line #568 Ladysmith - Possum Point into Thornburg (formerly Kraken), creating Line #9517 Ladysmith to Thornburg (formerly Kraken).

Sep 16 2030
Contingent

AG2-068, AG2-069, AG2-072, AG2-077, AG2-081, AG2-088, AG2-151, AG2-152, AG2-171, AG2-184, AG2-198, AG2-213, AG2-270, AG2-339, AG2-341, AG2-360, AG2-369, AG2-382, AG2-384, AG2-436, AG2-440, AG2-441, AG2-442, AG2-522, AG2-566, AG2-570, AG2-571, AG2-581, AG2-583, AG2-659, AG2-660, AH1-004, AH1-040, AH1-044, AH1-150, AH1-151, AH1-170, AH1-216, AH1-263, AH1-271, AH1-314, AH1-343, AH1-439, AH1-528, AH1-546, AH1-617, AH1-664, AH1-665, AH1-666, AH1-677, AH1-681, AH1-682, AH1-683, AH1-687, AH1-691, AH1-692, AH1-694, AH1-712, AH1-716, AH1-721, AH1-723

Dominion b4000.352

Cut in Line #568 Ladysmith - Possum Point into Thornburg (formerly Kraken), creating new Line #568 Thornburg (formerly Kraken) to Possum Point.

Sep 16 2030
Contingent

AG2-068, AG2-069, AG2-072, AG2-077, AG2-081, AG2-088, AG2-151, AG2-152, AG2-171, AG2-184, AG2-198, AG2-213, AG2-270, AG2-339, AG2-341, AG2-360, AG2-369, AG2-382, AG2-384, AG2-436, AG2-440, AG2-441, AG2-442, AG2-522, AG2-566, AG2-570, AG2-571, AG2-581, AG2-583, AG2-659, AG2-660, AH1-004, AH1-040, AH1-044, AH1-150, AH1-151, AH1-170, AH1-216, AH1-263, AH1-271, AH1-314, AH1-343, AH1-439, AH1-528, AH1-546, AH1-617, AH1-664, AH1-665, AH1-666, AH1-677, AH1-681, AH1-682, AH1-683, AH1-687, AH1-691, AH1-692, AH1-694, AH1-712, AH1-716, AH1-721, AH1-723

Dominion b4000.356

Build a new 156 mile 765kV line from Joshua Falls – Yeat. (Roughly 86.7 miles in Dominion section).

Jun 01 2029
Contingent

AG2-068, AG2-069, AG2-072, AG2-077, AG2-081, AG2-088, AG2-151, AG2-152, AG2-171, AG2-184, AG2-198, AG2-213, AG2-270, AG2-339, AG2-341, AG2-360, AG2-369, AG2-384, AG2-436, AG2-440, AG2-441, AG2-442, AG2-522, AG2-566, AG2-570, AG2-571, AG2-581, AG2-583, AG2-659, AG2-660, AH1-004, AH1-040, AH1-044, AH1-150, AH1-151, AH1-216, AH1-263, AH1-314, AH1-343, AH1-439, AH1-528, AH1-546, AH1-617, AH1-664, AH1-665, AH1-666, AH1-677, AH1-681, AH1-682, AH1-683, AH1-687, AH1-691, AH1-692, AH1-694, AH1-712, AH1-716, AH1-721, AH1-723

Dominion b4000.357

Build a new 765/500/230 kV substation called Yeat. Install (2) 765/500 kV transformers. Cut in 500 kV line Bristers-Ox and 500 kV line Meadowbrook-Vint Hill into Yeat.

Jun 01 2029
Contingent

AG2-068, AG2-069, AG2-072, AG2-077, AG2-081, AG2-088, AG2-151, AG2-152, AG2-171, AG2-184, AG2-198, AG2-213, AG2-270, AG2-339, AG2-341, AG2-360, AG2-369, AG2-382, AG2-384, AG2-436, AG2-440, AG2-441, AG2-442, AG2-522, AG2-566, AG2-570, AG2-571, AG2-581, AG2-583, AG2-659, AG2-660, AH1-004, AH1-040, AH1-044, AH1-150, AH1-151, AH1-170, AH1-216, AH1-263, AH1-271, AH1-314, AH1-343, AH1-439, AH1-528, AH1-546, AH1-617, AH1-664, AH1-665, AH1-666, AH1-677, AH1-681, AH1-682, AH1-683, AH1-687, AH1-691, AH1-692, AH1-694, AH1-712, AH1-716, AH1-721, AH1-723

Dominion b4000.360

Replace two switches, a wave trap and leads to upgrade all related substation equipment to 2000A at Altavista 138 kV substation.

Dec 31 2031
Contingent

AG2-152

Dominion b4030.1

Chesterfield-Basin 230 kV rebuild: Wreck and rebuild approximately 12.5 miles of Chesterfield-Basin 230 kV line.

Jun 01 2030
Contingent

AG2-068, AG2-069, AG2-077, AG2-088, AG2-436, AG2-570, AG2-571, AG2-581, AH1-528

Dominion b4030.10

Fork Union-Bremo 230 kV rebuild: Wreck and Rebuild approximately 1.74 miles of Fork Union-Bremo 230 kV line.

Jun 01 2030
Contingent

AG2-068, AG2-069, AG2-077, AG2-088, AG2-151, AG2-171, AG2-198, AG2-213, AG2-270, AG2-369, AG2-436, AG2-440, AG2-441, AG2-442, AG2-566, AG2-570, AG2-571, AG2-581, AG2-583, AH1-439, AH1-528, AH1-546, AH1-687

Dominion b4030.11

Replace all terminal equipment at Charlottesville 230 kV substation to support the new line conductor ratings of the Charlottesville-Fork Union 230 kV rebuild.

Jun 01 2030
Contingent

AG2-068, AG2-069, AG2-077, AG2-088, AG2-151, AG2-171, AG2-198, AG2-213, AG2-270, AG2-369, AG2-436, AG2-440, AG2-441, AG2-442, AG2-566, AG2-570, AG2-571, AG2-581, AG2-583, AH1-439, AH1-528, AH1-546, AH1-687

Dominion b4030.12

Replace all terminal equipment at Fork Union 230 kV substation to support the new line conductor ratings of the Charlottesville-Fork Union 230 kV rebuild.

Jun 01 2030
Contingent

AG2-068, AG2-069, AG2-077, AG2-088, AG2-151, AG2-198, AG2-213, AG2-270, AG2-369, AG2-436, AG2-440, AG2-441, AG2-442, AG2-566, AG2-570, AG2-571, AG2-581, AG2-583, AH1-439, AH1-528, AH1-546, AH1-687

Dominion b4030.13

Replace all terminal equipment at Fork Union 230 kV substation to support the new conductor ratings of the Fork Union-Bremo 230 kV rebuild.

Jun 01 2030
Contingent

AG2-068, AG2-069, AG2-077, AG2-088, AG2-151, AG2-171, AG2-198, AG2-213, AG2-270, AG2-369, AG2-436, AG2-440, AG2-441, AG2-442, AG2-566, AG2-570, AG2-571, AG2-581, AG2-583, AH1-439, AH1-528, AH1-546, AH1-687

Dominion b4030.14

Replace all terminal equipment at Bremo 230 kV substation to support the new conductor ratings of the Fork Union-Bremo 230 kV rebuild.

Jun 01 2030
Contingent

AG2-068, AG2-069, AG2-077, AG2-088, AG2-151, AG2-171, AG2-198, AG2-213, AG2-270, AG2-369, AG2-436, AG2-440, AG2-441, AG2-442, AG2-566, AG2-570, AG2-571, AG2-581, AG2-583, AH1-439, AH1-528, AH1-546, AH1-687

Dominion b4030.15

Upgrade disconnect switches at Mt. Eagle tap 230 kV substation to 4000A.

Jun 01 2030
Contingent

AG2-068, AG2-069, AG2-077, AG2-088, AG2-151, AG2-171, AG2-198, AG2-213, AG2-270, AG2-369, AG2-436, AG2-440, AG2-441, AG2-442, AG2-566, AG2-570, AG2-571, AG2-581, AG2-583, AH1-439, AH1-528, AH1-546, AH1-687

Dominion b4030.3

Basin 230 kV substation scope: Replace all terminal equipment, line leads and bus at Basin 230 kV substation to be rated to 4000A.

Jun 01 2030
Contingent

AG2-068, AG2-069, AG2-077, AG2-088, AG2-436, AG2-570, AG2-571, AG2-581, AH1-528

Dominion b4030.4

Chesterfield 230 kV substation scope: Install a new 230 kV, 80 kA 4000A circuit breaker at Chesterfield 230 kV substation.

Jun 01 2030
Contingent

AG2-068, AG2-069, AG2-077, AG2-088, AG2-436, AG2-570, AG2-571, AG2-581, AH1-528

Dominion b4030.9

Charlottesville-Fork Union 230 kV rebuild: Wreck and rebuild ~24 miles of Charlottesville-Fork Union 230 kV line.New Reinforcement

Jun 01 2030
Contingent

AG2-068, AG2-069, AG2-077, AG2-088, AG2-151, AG2-171, AG2-198, AG2-213, AG2-270, AG2-369, AG2-436, AG2-440, AG2-441, AG2-442, AG2-566, AG2-570, AG2-571, AG2-581, AG2-583, AH1-439, AH1-528, AH1-546, AH1-687

Dominion b4052.6

Aspen 500 kV remote work for Dickerson (new 500 kV) - Aspen line

Jun 01 2032
Contingent

AG2-068, AG2-069, AG2-369, AG2-436, AG2-570, AG2-571, AH1-528, AH1-681, AH1-712, AH1-723

Dominion b4053.10

Construct one new 500 kV line terminal position at the proposed Thornburg (formerly Kraken) substation.

Jun 01 2032
Contingent

AG2-068, AG2-069, AG2-077, AG2-339, AG2-369, AG2-382, AG2-436, AG2-440, AG2-441, AG2-570, AG2-571, AG2-581, AH1-040, AH1-216, AH1-271, AH1-528, AH1-681, AH1-712, AH1-716, AH1-723

Dominion b4053.11

Cut and loop line No. 5008 into Mosby substation, which will result in two 500 kV lines: line No. 5008 Morrisville-Mosby and line No. 9573 Mosby-Wishing Star.

Jun 01 2030
Contingent

AG2-068, AG2-069, AG2-072, AG2-077, AG2-081, AG2-088, AG2-151, AG2-171, AG2-184, AG2-198, AG2-213, AG2-270, AG2-339, AG2-341, AG2-360, AG2-369, AG2-384, AG2-436, AG2-440, AG2-441, AG2-442, AG2-522, AG2-566, AG2-570, AG2-571, AG2-581, AG2-583, AG2-659, AG2-660, AH1-004, AH1-044, AH1-150, AH1-151, AH1-170, AH1-263, AH1-280, AH1-314, AH1-343, AH1-396, AH1-439, AH1-528, AH1-546, AH1-617, AH1-664, AH1-665, AH1-666, AH1-677, AH1-681, AH1-682, AH1-683, AH1-687, AH1-691, AH1-692, AH1-694, AH1-712, AH1-716, AH1-721, AH1-723

Dominion b4053.12

Install two 500 kV breakers and all associated terminal equipment in the available bay adjacent to existing breaker XT590 to achieve a redundant breaker arrangement.

Jun 01 2030
Contingent

AG2-068, AG2-069, AG2-072, AG2-077, AG2-081, AG2-088, AG2-151, AG2-171, AG2-184, AG2-198, AG2-213, AG2-270, AG2-339, AG2-341, AG2-360, AG2-369, AG2-384, AG2-436, AG2-440, AG2-441, AG2-442, AG2-522, AG2-566, AG2-570, AG2-571, AG2-581, AG2-583, AG2-659, AG2-660, AH1-004, AH1-044, AH1-150, AH1-151, AH1-170, AH1-263, AH1-280, AH1-314, AH1-343, AH1-396, AH1-439, AH1-528, AH1-546, AH1-617, AH1-664, AH1-665, AH1-666, AH1-677, AH1-681, AH1-682, AH1-683, AH1-687, AH1-691, AH1-692, AH1-694, AH1-712, AH1-716, AH1-721, AH1-723

Dominion b4053.13

Construct a new 765/500 kV Vontay switching station at the crossing of 500 kV line No. 553 Cunningham-Elmont and 765 kV line Joshua Falls-Yeat.

Jun 01 2032
Contingent

AG2-068, AG2-069, AG2-072, AG2-077, AG2-081, AG2-088, AG2-151, AG2-152, AG2-171, AG2-184, AG2-198, AG2-213, AG2-270, AG2-339, AG2-341, AG2-360, AG2-369, AG2-384, AG2-436, AG2-440, AG2-441, AG2-442, AG2-522, AG2-566, AG2-570, AG2-571, AG2-581, AG2-583, AG2-659, AG2-660, AH1-004, AH1-040, AH1-044, AH1-150, AH1-151, AH1-216, AH1-314, AH1-343, AH1-439, AH1-528, AH1-546, AH1-617, AH1-664, AH1-665, AH1-666, AH1-677, AH1-681, AH1-687, AH1-712, AH1-716, AH1-721, AH1-723

Dominion b4053.14

Loop 500 kV line No. 553 into the new Vontay substation, which will result in two 500 kV lines: Cunningham-Vontay and Vontay-Elmont.

Jun 01 2032
Contingent

AG2-068, AG2-069, AG2-072, AG2-077, AG2-081, AG2-088, AG2-151, AG2-152, AG2-171, AG2-184, AG2-198, AG2-213, AG2-270, AG2-339, AG2-341, AG2-360, AG2-369, AG2-384, AG2-436, AG2-440, AG2-441, AG2-442, AG2-522, AG2-566, AG2-570, AG2-571, AG2-581, AG2-583, AG2-659, AG2-660, AH1-004, AH1-040, AH1-044, AH1-150, AH1-151, AH1-216, AH1-314, AH1-343, AH1-439, AH1-528, AH1-546, AH1-617, AH1-664, AH1-665, AH1-666, AH1-677, AH1-681, AH1-687, AH1-712, AH1-716, AH1-721, AH1-723

Dominion b4053.15

Loop 500 kV line No. 576 into the new Vontay substation, which will result in two 500 kV lines: from North Anna-Vontay and Vontay-Midlothian.

Jun 01 2032
Contingent

AG2-068, AG2-069, AG2-072, AG2-077, AG2-081, AG2-088, AG2-151, AG2-152, AG2-171, AG2-184, AG2-198, AG2-213, AG2-270, AG2-339, AG2-341, AG2-360, AG2-369, AG2-384, AG2-436, AG2-440, AG2-441, AG2-442, AG2-522, AG2-566, AG2-570, AG2-571, AG2-581, AG2-583, AG2-659, AG2-660, AH1-004, AH1-040, AH1-044, AH1-150, AH1-151, AH1-216, AH1-314, AH1-343, AH1-439, AH1-528, AH1-546, AH1-617, AH1-664, AH1-665, AH1-666, AH1-677, AH1-681, AH1-687, AH1-712, AH1-716, AH1-721, AH1-723

Dominion b4053.16

Loop 765 kV Joshua Falls-Yeat into the new Vontay substation, which will result in two 765 kV lines: from Joshua Falls-Vontay and Vontay-Yeat.

Jun 01 2032
Contingent

AG2-068, AG2-069, AG2-072, AG2-077, AG2-081, AG2-088, AG2-151, AG2-152, AG2-171, AG2-184, AG2-198, AG2-213, AG2-270, AG2-339, AG2-341, AG2-360, AG2-369, AG2-384, AG2-436, AG2-440, AG2-441, AG2-442, AG2-522, AG2-566, AG2-570, AG2-571, AG2-581, AG2-583, AG2-659, AG2-660, AH1-004, AH1-040, AH1-044, AH1-150, AH1-151, AH1-216, AH1-314, AH1-343, AH1-439, AH1-528, AH1-546, AH1-617, AH1-664, AH1-665, AH1-666, AH1-677, AH1-681, AH1-687, AH1-712, AH1-716, AH1-721, AH1-723

Dominion b4053.21

Uprate 500 kV line No. 567 associated terminal equipment at Chickahominy to 5000A standards.

Jun 01 2032
Contingent

AG2-068, AG2-069, AG2-369, AG2-436, AG2-570, AG2-571, AH1-040, AH1-528, AH1-716

Dominion b4053.22

Uprate 500 kV line No. 567 associated terminal equipment at Surry to 5000A standards.

Jun 01 2032
Contingent

AG2-068, AG2-069, AG2-369, AG2-436, AG2-570, AG2-571, AH1-040, AH1-528, AH1-716

Dominion b4053.28

Replace 500 kV circuit breakers (54265 and 553T564) and all associated equipment to line No. 553 including switches and CT with 5000A equipment at Cunningham substation.

Jun 01 2032
Contingent

AG2-068, AG2-069, AG2-072, AG2-077, AG2-081, AG2-088, AG2-151, AG2-152, AG2-171, AG2-184, AG2-198, AG2-213, AG2-270, AG2-339, AG2-341, AG2-360, AG2-369, AG2-384, AG2-436, AG2-440, AG2-441, AG2-442, AG2-522, AG2-566, AG2-570, AG2-571, AG2-581, AG2-583, AG2-659, AG2-660, AH1-004, AH1-040, AH1-044, AH1-150, AH1-151, AH1-216, AH1-314, AH1-343, AH1-439, AH1-528, AH1-546, AH1-617, AH1-664, AH1-665, AH1-666, AH1-677, AH1-681, AH1-687, AH1-712, AH1-716, AH1-721, AH1-723

Dominion b4053.3

Construct a new bipolar +/- 525 kV HVDC link connecting Heritage and Mosby substations, where the link has a capability of transmitting 3,000 MW.

Jun 01 2032
Contingent

AG2-068, AG2-069, AG2-072, AG2-077, AG2-081, AG2-088, AG2-151, AG2-171, AG2-184, AG2-198, AG2-213, AG2-270, AG2-339, AG2-341, AG2-360, AG2-369, AG2-384, AG2-436, AG2-440, AG2-441, AG2-442, AG2-522, AG2-566, AG2-570, AG2-571, AG2-581, AG2-583, AG2-659, AG2-660, AH1-004, AH1-044, AH1-150, AH1-151, AH1-170, AH1-263, AH1-280, AH1-314, AH1-343, AH1-396, AH1-439, AH1-528, AH1-546, AH1-617, AH1-664, AH1-665, AH1-666, AH1-677, AH1-681, AH1-682, AH1-683, AH1-687, AH1-691, AH1-692, AH1-694, AH1-712, AH1-716, AH1-721, AH1-723

Dominion b4053.4

Design and construct a new Voltage Source Converter (VSC) HVDC station at Heritage substation to support the new HVDC link.

Jun 01 2032
Contingent

AG2-068, AG2-069, AG2-072, AG2-077, AG2-081, AG2-088, AG2-151, AG2-171, AG2-184, AG2-198, AG2-213, AG2-270, AG2-339, AG2-341, AG2-360, AG2-369, AG2-384, AG2-436, AG2-440, AG2-441, AG2-442, AG2-522, AG2-566, AG2-570, AG2-571, AG2-581, AG2-583, AG2-659, AG2-660, AH1-004, AH1-044, AH1-150, AH1-151, AH1-170, AH1-263, AH1-280, AH1-314, AH1-343, AH1-396, AH1-439, AH1-528, AH1-546, AH1-617, AH1-664, AH1-665, AH1-666, AH1-677, AH1-681, AH1-682, AH1-683, AH1-687, AH1-691, AH1-692, AH1-694, AH1-712, AH1-716, AH1-721, AH1-723

Dominion b4053.5

Design and construct a new Voltage Source Converter (VSC) HVDC station at Mosby substation to support the new HVDC link.

Jun 01 2032
Contingent

AG2-068, AG2-069, AG2-072, AG2-077, AG2-081, AG2-088, AG2-151, AG2-171, AG2-184, AG2-198, AG2-213, AG2-270, AG2-339, AG2-341, AG2-360, AG2-369, AG2-384, AG2-436, AG2-440, AG2-441, AG2-442, AG2-522, AG2-566, AG2-570, AG2-571, AG2-581, AG2-583, AG2-659, AG2-660, AH1-004, AH1-044, AH1-150, AH1-151, AH1-170, AH1-263, AH1-280, AH1-314, AH1-343, AH1-396, AH1-439, AH1-528, AH1-546, AH1-617, AH1-664, AH1-665, AH1-666, AH1-677, AH1-681, AH1-682, AH1-683, AH1-687, AH1-691, AH1-692, AH1-694, AH1-712, AH1-716, AH1-721, AH1-723

Dominion b4053.8

Build a new 500 kV line from Elmont-Thornburg (formerly Kraken) (approximately 31 miles).

Jun 01 2032
Contingent

AG2-068, AG2-069, AG2-077, AG2-339, AG2-369, AG2-382, AG2-436, AG2-440, AG2-441, AG2-570, AG2-571, AG2-581, AH1-040, AH1-216, AH1-271, AH1-528, AH1-681, AH1-712, AH1-716, AH1-723

Dominion b4053.9

Construct one new 500 kV line terminal position at the existing Elmont substation.

Jun 01 2032
Contingent

AG2-068, AG2-069, AG2-077, AG2-339, AG2-369, AG2-382, AG2-436, AG2-440, AG2-441, AG2-570, AG2-571, AG2-581, AH1-040, AH1-216, AH1-271, AH1-528, AH1-681, AH1-712, AH1-716, AH1-723

Dominion n7553 / dom-427

Replace Northern Neck 115/230 kV transformer #6 with a 224 MVA (260/271/295 MVA).

59 to 60 Months
Contingent

AG2-124

Dominion n7615 / dom-187

Wreck and rebuild 5.74 miles of 115 kV Line 44 between Myrtle and AD2-085 with (1) 768.2 ACSS/TW (20/7) "MAUMEE" conductor @ 250 Deg. C.

30 to 36 Months
$18,336,000

AG2-426

Dominion n9153.0 / TC1-PH1-DOM-043

Wreck and rebuild 5.9 miles of 230 kV line 2128 between Fentress and Thrasher with (2) 768.2 ACSS/TW (20/7) "MAUMEE" conductor @ 250 degrees C and replace line lead at Fentress.

Jul 01 2027
Contingent

AH1-040

Dominion n9207.0 / TC1-PH2-DOM-018

Replace 6ELMONT 230 kV to 8ELMONT 500 kV circuit 1 with larger transformer (3-480 MVA single phase transformer).

Dec 31 2028
Contingent

AG2-339, AG2-384, AG2-436, AG2-570, AG2-581, AH1-040, AH1-216, AH1-528

Dominion n9217.0 / TC1-PH2-DOM-028

Wreck and rebuild 12.73 miles of 230 kV Line 298 from Buckingham to Farmville Substations with twin bundled (2) 768 ACSS/TW (20/7) "MAUMEE" conductor.

45 to 46 Months
Contingent

AG2-069, AG2-077, AG2-171, AG2-198, AG2-213, AG2-270, AG2-339, AG2-341, AG2-436, AG2-440, AG2-441, AG2-442, AG2-522, AG2-566, AG2-570, AG2-581, AG2-659, AH1-314, AH1-343, AH1-439, AH1-528

Dominion n9220.0 / TC1-PH2-DOM-033

Wreck and rebuild 15.49 miles of 230 kV Line #298 from Buckingham to Bremo Substations with twin bundled (2) 768.2 ACSS/TW (20/7) "MAUMEE" conductor.

42 to 48 Months
Contingent

AG2-069, AG2-077, AG2-171, AG2-198, AG2-213, AG2-270, AG2-339, AG2-341, AG2-436, AG2-440, AG2-441, AG2-442, AG2-522, AG2-566, AG2-570, AG2-581, AG2-659, AH1-314, AH1-343, AH1-439, AH1-528, AH1-546

Dominion n9221.0 / TC1-PH3-DOM-015-TC2

Replace 230 kV Breaker 29822 at Bremo with a higher-rated device (Buckingham - Bremo).

38 to 39 Months
$2,057,335

AG2-077, AG2-171, AG2-198, AG2-213, AG2-270, AG2-341, AG2-440, AG2-441, AG2-442, AG2-522, AG2-566, AG2-581, AG2-659, AH1-314, AH1-343, AH1-439, AH1-528, AH1-546

Dominion n9378.0 / TC1-PH3-DOM-010

Replace existing 230/500 kV Carson transformer #1 with (4)-480 MVA single phase transformers.

Mar 29 2029
Contingent

AG2-068, AG2-069, AG2-077, AG2-270, AG2-339, AG2-436, AG2-570, AG2-581, AH1-528, AH1-677

Dominion n9380.0 / TC1-PH3-DOM-012

Replace existing Ladysmith 230/500 kV transformer 1 with four (4) 480 MVA single phase transformers.

Dec 31 2029
Contingent

AH1-683, AH1-691, AH1-692

Dominion n9643.0 / TC1-PH3-DOM-009-TC2

Replace 795 AAC 37 line lead at Farmville 115 kV.

Mar 31 2027
$391,643

AG2-440, AG2-441, AG2-442

Dominion n9723.0 / TC2-PH1-DOM-0009

Wreck and Rebuild 0.05 miles of 115 kV Line 158 between Flat Creek and Moran DP with (1) 768.2 ACSS/TW (20/7) "MAUMEE".

30 to 36 Months
$160,000

AG2-171, AG2-213, AH1-280, AH1-396

Dominion n9724.0 / TC2-PH1-DOM-0011

Replace 795 AAC Line Lead on Line 158 at Farmville 115 kV.

12 to 18 Months
$400,000

AG2-171, AG2-213, AH1-280, AH1-396

Dominion n9725.0 / TC2-PH1-DOM-2012

Wreck and rebuild 6.55 mi of 115 kV Line 15 between Pumphouse and Poe with (1) 768.2 ACSS/TW (20/7) "Maumee" conductor @ 250 Deg. C

30 to 36 Months
$20,960,000

AG2-426

Dominion n9726.0 / TC2-PH1-DOM-2043

Wreck and rebuild 0.93 miles of 230 kV Line 2241 between Hendrick and Persons with (2) 768.2 ACSS/TW (20/7) "MAUMEE" at 250 degrees C. Dominion portion of line only.

36 to 42 Months
$3,534,000

AG2-077, AG2-151, AG2-171, AG2-198, AG2-213, AG2-270, AG2-341, AG2-440, AG2-441, AG2-442, AG2-522, AG2-566, AG2-581, AG2-583, AG2-659, AH1-343, AH1-439, AH1-528, AH1-546, AH1-687

Dominion n9727.0 / TC2-PH1-DOM-2091

Replace the existing Finneywood 230/500 kV XFRM T1 with a 3-480 MVA rated device

42 to 48 Months
$38,000,000

AG2-077, AG2-171, AG2-198, AG2-213, AG2-270, AG2-440, AG2-441, AG2-442, AG2-522, AG2-566, AG2-659, AH1-343, AH1-439

Dominion n9728.0 / TC2-PH1-DOM-2076

Replace wave trap 298 WT at Bremo 230 kV

12 to 18 Months
$400,000

AG2-077, AG2-171, AG2-198, AG2-213, AG2-270, AG2-341, AG2-440, AG2-441, AG2-442, AG2-522, AG2-566, AG2-581, AG2-659, AH1-314, AH1-343, AH1-439, AH1-528, AH1-546

Dominion n9729.0 / TC2-PH1-DOM-2092

Replace the existing Finneywood 230/500 kV XFRM T2 with a 3-480 MVA rated device

42 to 48 Months
$38,000,000

AG2-077, AG2-171, AG2-198, AG2-213, AG2-270, AG2-440, AG2-441, AG2-442, AG2-522, AG2-566, AG2-659, AH1-343, AH1-439

Dominion n9730.0 / TC2-PH1-DOM-2077

Replace switches 29824 and 29825 at Bremo 230 kV

12 to 18 Months
$800,000

AG2-077, AG2-171, AG2-198, AG2-213, AG2-270, AG2-341, AG2-440, AG2-441, AG2-442, AG2-522, AG2-566, AG2-581, AG2-659, AH1-314, AH1-343, AH1-439, AH1-528, AH1-546

Dominion n9731.0 / TC2-PH1-DOM-0010

Wreck and Rebuild 5.32 miles of 115 kV Line 158 between Farmville and Moran DP with (1) 768.2 ACSS/TW (20/7) "MAUMEE".

30 to 36 Months
$17,152,000

AG2-171, AG2-213, AH1-280, AH1-396

Dominion n9756.0 / TC2-PH2-DOM-009

Replace the existing Trowbridge 115/230 kV Transformer T2 with a new 224 MVA device

42 to 44 Months
$7,500,000

AH1-040

Dominion n9757.0 / TC2-PH2-DOM-005

Build new 230 kV line from AG1-285 to AG2-440 on single circuit monopoles. Expand the AG2-440 and AG1-285 substations. Add 2 new 224 MVA 230/115 kV XFRMs at AG2-440.

42 to 48 Months
$145,162,000

AG2-171, AG2-213, AG2-341, AG2-440, AG2-441, AG2-442, AH1-280

AG2-077, AG2-522, AG2-659, AH1-396

Dominion n9758.0 / TC2-PH2-DOM-008

Replace the existing Trowbridge 115/230 kV Transformer T1 with a new 224 MVA device

42 to 44 Months
$7,500,000

AH1-040

Dominion s2705

Wreck and rebuild approximately 12 miles of double circuit 230kV Line #252 and 115kV Line #29 from Aquia Harbour Switching Station to Possum Point. Upgrade station equipment.

Sep 25 2029
Contingent

AG2-436, AH1-682, AH1-683, AH1-691, AH1-692, AH1-694

Dominion s3671.5

Rebuild Line 238 from Carson to Clubhouse for a normal summer rating of 1573 MVA

Dec 31 2030
Contingent

AG2-068, AG2-069, AG2-077, AG2-270, AG2-369, AG2-382, AG2-440, AG2-441, AG2-442, AG2-522, AG2-570, AG2-571, AG2-581, AG2-659, AH1-040, AH1-271, AH1-528

EKPC n6480.1 / EKPC-tc1-r0002a

Rebuild the Plumville-Murphysville 69 kV line section using 556 MCM ACSR conductor at 212 degrees F (9.9 miles)

22 to 34 Months
$14,830,000

AH1-664, AH1-665, AH1-666

EKPC n6834.1 / EKPC-tc1-r0001a

Rebuild the 4/0 ACSR Green County-Summersville 69 kV line section (4.2 miles) using 556 MCM ACSR.

18 to 24 Months
$5,705,000

AG2-298, AG2-424, AH1-721

EKPC n7771.1 / r0013

Increase the maximum operating temperature of the Laurel County-Laurel Dam 161 kV line section 795 MCM conductor to 167 degrees F (~0.2 miles)

9 to 12 Months
$35,000

AH1-239, AH1-721

EKPC n7771.2 / EKPC-tc1-r0014a

Increase the maximum operating temperature of the Laurel County-Laurel Dam 161 kV line section 795 MCM conductor to 212 degrees F (~10.55 miles)

18 to 24 Months
$1,010,000

AH1-239, AH1-721

EKPC n7773.1 / EKPC-tc1-r0004b

Change the 69 kV current transformer settings associated with circuit breaker S7-654 from 600A to at least 800A.

9 to 12 Months
$345,000

AH1-721

EKPC n7773.4 / (Pending)

Replace the 1200A disconnects S7-653 and S7-655 at Somerset substation with 2000A equipment.

9 to 12 Months
Contingent

AH1-721

EKPC n8368.2 / EKPC-tc1-r0012b

Rebuild the Cooper-Elihu 161 kV line section using 1272 MCM ACSS conductor (4.2 miles)

16 to 27 Months
$10,335,000

AH1-239, AH1-721

AG2-424

EKPC n8368.3 / EKPC-tc1-r0012c

Change the Zone 3 relay setting at Elihu substation associated with the line protection to at least 545 MVA LTE rating.

9 to 12 Months
$10,000

AH1-239, AH1-721

AG2-424

EKPC n8368.4 / EKPC-tc1-r0012d

Upgrade the existing 795 MCM ACSR jumpers at the Cooper substation associated with the Cooper-Elihu 161 kV line using bundled 500 MCM CU or equivalent

9 to 12 Months
$35,000

AH1-239, AH1-721

AG2-424

EKPC n8368.5 / EKPC-r0117d

Cooper-Elihu 161 kV Current Transformer Upgrade

12 to 15 Months
Contingent

AG2-424, AH1-239, AH1-721

EKPC n9687.10 / EKPC-tc2-nu053

Cooper 161kV breaker replacements - Breaker 1044 ELIHU

Dec 01 2029
$335,000

AH1-239, AH1-721

AG2-424

EKPC n9739.0 / EKPC-tc2-nu046

Rebuild the AG1-471 Tap (Massingale Road)-AH1-239 Tap 69 kV line (Clinton County) (4.5 miles) using 556.5 MCM ACSR conductor.

20 to 25 Months
$4,215,000

AH1-239

EKPC n9740.0 / EKPC-tc2-nu024

Plumville-Rectorville 69 kV Line Conductor Temperature Upgrade (2.9 miles)

12 to 16 Months
$180,000

AH1-664, AH1-665

EKPC n9741.0 / EKPC-tc2-nu007

Charters-Rectorville 69 kV Line Conductor Temperature Upgrade (11.5 miles)

12 to 21 Months
$650,000

AH1-664, AH1-665

EKPC n9742.0 / EKPC-tc2-nu034

Zula Junction N.O.-AG1-471 (Massingale Road) 69 kV Line Section Rebuild (0.6 miles)

12 to 18 Months
$960,000

AH1-239, AH1-721

EKPC n9743.0 / EKPC-tc2-nu003

Cooper CCGT-Alcalde 161 kV Double-Circuit Line Addition

22 to 36 Months
$20,130,000

AG2-424, AH1-239, AH1-721

EKPC n9744.0 / EKPC-tc2-nu035

Plumville-AH1-664 Tap (North Fleming County) 138 kV Line Conductor Temperature Upgrade (8.25 miles)

12 to 18 Months
$760,000

AH1-664, AH1-665

EKPC n9745.0 / EKPC-tc2-nu014

Green County-Summersville 69 kV Line Section Rebuild #2 (266.8 MCM ACSR section)

12 to 18 Months
$120,000

AG2-424

EKPC n9775.0 / EKPC-tc2-nu056

Cooper-AH1-721 Tap (East Cooper) 161 kV Circuit #2 Rebuild (0.5 miles)

12 to 18 Months
$1,215,000

AH1-721

EKPC n9776.0 / EKPC-tc2-nu054

Cooper-AH1-721 Tap (East Cooper) 161 kV Circuit #1 Rebuild (0.5 miles)

12 to 18 Months
$1,215,000

AH1-721

EKPC n9777.0 / EKPC-tc2-nu055

Cooper-AH1-721 (East Cooper) Circuit #2 161 kV Zone 3 Setting Upgrade

9 to 12 Months
$10,000

AH1-721

EKPC n9778.0 / EKPC-tc2-nu047

Increase the Zone 3 relay setting at Somerset substation associated with the Somerset-KU Ferguson South 69 kV line section to at least 205 MVA.

6 to 9 Months
$10,000

AH1-721

EKPC n9779.0 / EKPC-tc2-nu048

Charters-Rectorville 69 kV Line Conductor Temperature Upgrade #2 (11.5 miles)

12 to 21 Months
$715,000

AH1-664, AH1-665

EKPC n9780.0 / EKPC-tc2-nu052

Cooper-Elihu 161 kV Relay Upgrade

12 to 15 Months
$55,000

AH1-239, AH1-721

AG2-424

EKPC n9781.0 / EKPC-tc2-nu051

Cooper-Elihu 161 kV Bus Conductor Upgrade

12 to 15 Months
$990,000

AH1-239, AH1-721

AG2-424

EKPC n9782.0 / EKPC-tc2-nu050

West London Tap-West London 69 kV Conductor Maximum Operating Temperature Increase

12 to 21 Months
$135,000

AH1-721

EKPC s3165.0 / s3165

Construct a new 161/13.8 kV distribution substation and associated 0.25 mile 161 kV double circuit tap line.

Jul 26 2024
Contingent

AH1-721

EKPC s3170.0 / s3170

Rebuild the 4.4 mile, Snow Tap-North Albany 69 kV line using 556.5 conductor and steel pole construction.

Aug 04 2026
Contingent

AH1-239

EKPC s3173.0 / S3173

Rebuild the 16.3 mile, Duncannon Lane Tap-West Berea 69 KV line

Oct 05 2027
Contingent

AG2-073

LS Power b3737.37

Silver Run-Hope Creek 230kV Expansion (Projected ISD 6/1/2029)

Dec 31 2028
Contingent

AH1-260, AH1-710

OVEC b3788.2 / B3788.2

Replace limiting station elements at Kyger Creek

Jun 01 2028
Contingent

AG2-072, AH1-055, AH1-537, AH1-664, AH1-665, AH1-721

OVEC n9759.0 / OVEC-TC2-19030

06KYGER 345.0 kV to 05SPORN 345.0 kV ckt 1 - Replace Equipment

48 to 60 Months
$38,180,000

AG2-072, AH1-055, AH1-537, AH1-664, AH1-665, AH1-721

PECO b3737.47

Build New North Delta 500 kV substation (Four bay breaker and half configuration)

Oct 06 2027
Contingent

AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725

PECO b3780.1

Peach Bottom North upgrades – substation work (Projected ISD 12/31/2028)

Oct 15 2028
Contingent

AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725

PECO b3780.14

Reconfigure Cooper transmission feeds by establishing new Cooper-North Delta 230 kV line and rerouting existing transmissions lines by Cooper.

Oct 23 2028
Contingent

AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725

PECO b3780.15

Cut in 5012 Peach Bottom-Conastone 500 kV line into North Delta 500/230 kV sub

Apr 10 2028
Contingent

AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725

PECO b3780.16

Terminate new Cooper-North Delta 230 kV line (Transource Scope) at North Delta 230 kV

Oct 15 2028
Contingent

AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725

PECO b3780.17

Cut in 5012 Peach Bottom-Conastone 500 kV line into North Delta 500/230 kV sub (Transource)

May 31 2028
Contingent

AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725

PECO b3780.2

Peach Bottom to Graceton (PECO Portion) – New 500kV Line

Oct 23 2028
Contingent

AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725

PECO b3800.31

Build new North Delta-High Ridge 500 kV line - PECO Portion (Projected ISD 12/1/2030)

Dec 15 2030
Contingent

AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725

PECO b3800.35

Rebuild 5012 (existing Peach Bottom-Conastone) (new North Delta-Graceton PECO) 500 kV (Projected ISD 12/1/2030)

Apr 10 2028
Contingent

AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725

PECO b3800.42

Peach Bottom 500kV North bus upgrade (Projected ISD 12/1/2030)

Dec 01 2030
Contingent

AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725

PECO b3800.44

North Delta termination for the North Delta-High Ridge 500 line (PECO work).

Dec 15 2030
Contingent

AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725

PECO b3800.45

North Delta 500 kV termination for the Rock Springs 500 kV line (5034/5014 line) (PECO work).

Jan 31 2028
Contingent

AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725

PECO b3800.47

Build new Peach Bottom South-North Delta 500 kV line (Projected ISD 12/1/2030)

Jan 14 2030
Contingent

AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725

PECO b3800.48

North Delta termination for the North Delta-High Ridge 500 line (Transource work).

Dec 15 2030
Contingent

AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725

PECO b3800.49

North Delta 500 kV termination for the Calpine generator (Calpine/Transource work).

Oct 06 2027
Contingent

AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725

PECO b3800.50

North Delta 500 kV termination for the Rock Springs 500 kV line (5034/5014 line) (Transource work).

Jan 23 2028
Contingent

AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725

PECO b3800.51

North Delta 500 kV termination for the new Peach Bottom-North Delta 500 kV line (Transource work).

May 31 2028
Contingent

AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725

PECO b3800.52

Reconfigure Peach Bottom North and South 500 kV yards (Projected ISD 12/1/2030)

Dec 01 2030
Contingent

AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725

PECO b3907.2

Rebuild Richmond - Waneeta 230 kV line

Jun 01 2029
Contingent

AG2-616, AH1-260, AH1-641, AH1-710

PECO b3907.3

Reconductor 2.12 miles of North Philadelphia to Waneeta 230 kV line including terminal equipment

Jun 01 2029
Contingent

AG2-616, AH1-260, AH1-641, AH1-710

PECO n9787.0 / PECO_TC2_PH2_Chichester

New bus tie at Chichester

36 to 48 Months
$3,500,000

AG2-380, AH1-672

PENELEC n6817.1

Rebuild 24.59 miles of the Lewistown-Juniata 230kV transmission line and upgrade terminal ends

81 Months
$122,656,404

AG2-176, AH1-460

PENELEC n8471

East Sayre-North Waverly 115kV line upgrade - FirstEnergy (NYISO CY17 driven upgrade)

Nov 01 2027
Contingent

AG2-582, AH1-680

PENELEC s3335.1 / PN-2024-007

Replace Homer City South 345/230-23kV Transformer

Jun 01 2027
Contingent

AG2-176, AG2-429

PEPCO b3780.11

Brighton Statcom and Capacitor (Projected ISD 12/31/2028)

Dec 31 2028
Contingent

AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725

PEPCO b3800.243

Rebuild 7.26 miles of existing 500 kV circuit from Dickerson Station H to Ed's Ferry

Dec 31 2030
Contingent

AH1-261, AH1-552

PEPCO b3800.244

Rebuild 7.26 miles of existing 230 kV circuit from Dickerson Station H to Ed's Ferry

Dec 31 2030
Contingent

AH1-261, AH1-552

PEPCO b3800.245

Reconfigure Dickerson H 230 kV Substation and upgrade terminal equipment.

Dec 31 2030
Contingent

AH1-261, AH1-552

PEPCO b3800.46

North Delta 500 kV termination for the new Peach Bottom-North Delta 500 kV line (PECO work).

Dec 11 2029
Contingent

AG2-176, AH1-260, AH1-261, AH1-552, AH1-695, AH1-710, AH1-715, AH1-722, AH1-725

PEPCO b4052.1

New 500/230 kV substation (Dickerson) by cutting into the Aspen-Rocky Point 500 kV line

Jun 01 2032
Contingent

AG2-068, AG2-069, AG2-369, AG2-436, AG2-570, AG2-571, AH1-528, AH1-681, AH1-712, AH1-723

PEPCO b4052.10

Replace one stranded bus conductor, three thermal relays, two disconnect switches at Quince Orchard 230 kV substation.

Jun 01 2032
Contingent

AG2-068, AG2-069, AG2-369, AG2-436, AG2-570, AG2-571, AH1-528, AH1-681, AH1-712, AH1-723

PEPCO b4052.11

Replace Bells Mill T3 XF with new PEPCO standard 260 MVA 230/138 kV transformer.

Jun 01 2032
Contingent

AG2-068, AG2-069, AG2-369, AG2-436, AG2-570, AG2-571, AH1-528, AH1-681, AH1-712, AH1-723

PEPCO b4052.2

Install two 500/230 kV transformers connecting a new 500 kV Dickerson station and DIckeson "H" 230 kV station including 230 kV substation work.

Jun 01 2032
Contingent

AG2-068, AG2-069, AG2-369, AG2-436, AG2-570, AG2-571, AH1-528, AH1-681, AH1-712, AH1-723

PEPCO b4052.3

Rocky Point-Dickerson (new 500 kV) termination work at Dickerson 500 kV

Jun 01 2032
Contingent

AG2-068, AG2-069, AG2-369, AG2-436, AG2-570, AG2-571, AH1-528, AH1-681, AH1-712, AH1-723

PEPCO b4052.4

Aspen-Dickerson (new 500 kV) termination work at Dickerson 500 kV

Jun 01 2032
Contingent

AG2-068, AG2-069, AG2-369, AG2-436, AG2-570, AG2-571, AH1-528, AH1-681, AH1-712, AH1-723

PEPCO b4052.7

Install 3.2% 230 kV series reactor at Dickerson "H" terminal side of the Edwards Ferry-Dickerson circuit.

Jun 01 2032
Contingent

AG2-068, AG2-069, AG2-369, AG2-436, AG2-570, AG2-571, AH1-528, AH1-681, AH1-712, AH1-723

PEPCO b4052.8

Relocate Dickerson "D"-Quince Orchard 23035 to terminate at Dickerson "H" at Dickerson No. 2 tie location.

Jun 01 2032
Contingent

AG2-068, AG2-069, AG2-369, AG2-436, AG2-570, AG2-571, AH1-528, AH1-681, AH1-712, AH1-723

PEPCO b4052.9

Replace two breakers, one bushing CT, one stranded bus conductor, four disconnect switches at Brighton 500 kV substation.

Jun 01 2032
Contingent

AG2-068, AG2-069, AG2-369, AG2-436, AG2-570, AG2-571, AH1-528, AH1-681, AH1-712, AH1-723

PEPCO b4053.29

Uprate 500 kV line No. 560 terminal equipment at Burches Hill substation in PEPCO so as not to limit the conductor rating.

Jun 01 2032
Contingent

AG2-436, AG2-570, AG2-571, AH1-528, AH1-681, AH1-712, AH1-723

PEPCO n9760.0 / PECO_TC2_PH2

Relocate Dickerson D to Quince Orchard 23033 to terminate at Dickerson H

60 Months
$10,000,000

AH1-552

PPL n6818

Rebuild PPL's ~0.9 miles LEWI-JUNI 230kV Line with a summer normal rating of at least 3000 Amps.

24 to 36 Months
$1,900,000

AG2-176, AH1-460

PPL s0945.1

Rebuild the Juniata 230/69 kV Substation

Dec 18 2025
Contingent

AG2-176, AH1-460

PSEG n9715.0 / PSEG-TC2_PH1_LindenMinueR

Upgrade Linden to Minue St R-2218 230 kV circuit

30 Months
$9,000,000

AH1-715, AH1-722

PSEG n9716.0 / PSEG-TC2_PH1_MinueSewarenR

Upgrade Minue St to Sewaren R-2218 230kV circuit

30 Months
$8,332,000

AH1-715, AH1-722

PSEG n9732.0 / PSEG-TC2-PHQ_LindenGen

Upgrade PSE&G portion of the Linden 230kV generator lead line

24 Months
$3,708,000

AH1-715, AH1-722

PSEG n9751.0 / PSEG-TC2_PH1_LindenMinueQ

Upgrade Linden to Minue St Q-2348 230 kV

30 Months
$9,183,000

AH1-715, AH1-722

PSEG n9752.0 / PSEG-TC2_PH1_MinueSewarenQ

Upgrade Minue St to Sewaren Q-2348 230kV circuit

30 Months
$8,180,000

AH1-715, AH1-722

Cost Allocation details for n9182.0 / AEPIMJMS01


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG2-363 12.12% $4,240,898
AG2-364 8.08% $2,827,387
AG2-453 12.82% $4,487,432
AG2-524 5.78% $2,023,186
AG2-660 0.97% $337,775
AH1-044 8.30% $2,904,212
AH1-150 8.30% $2,904,212
AH1-151 8.30% $2,904,212
AH1-196 6.33% $2,216,435
AH1-338 7.54% $2,639,247
AH1-341 6.03% $2,110,047
AH1-543 6.55% $2,291,435
AH1-714 8.90% $3,113,520

Cost Allocation details for n9746.0 / AEP-TC2-18625


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG2-550 35.05% $35,049
AG2-551 11.27% $11,268
AG2-637 53.68% $53,683

Cost Allocation details for n9747.0 / AEP-TC2-18633


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG2-550 35.05% $35,049
AG2-551 11.27% $11,268
AG2-637 53.68% $53,683

Cost Allocation details for n9748.0 / AEP-TC2-18670


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG2-363 14.78% $3,852,725
AG2-364 9.86% $2,568,483
AG2-453 15.62% $4,071,071
AG2-660 1.18% $308,427
AH1-044 10.18% $2,652,559
AH1-150 10.18% $2,652,559
AH1-151 10.18% $2,652,559
AH1-338 9.26% $2,412,684
AH1-543 8.04% $2,094,513
AH1-714 10.72% $2,794,421

Cost Allocation details for n9749.0 / AEP-TC2-18677


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG2-363 16.82% $672,760
AG2-364 11.21% $448,507
AG2-453 20.16% $806,561
AG2-660 1.42% $56,620
AH1-044 12.17% $486,917
AH1-150 12.17% $486,917
AH1-151 12.17% $486,917
AH1-714 13.87% $554,803

Cost Allocation details for n9750.0 / AEP-TC2-18699


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG2-548 50.00% $150,000
AG2-665 50.00% $150,000

Cost Allocation details for n9753.0 / AEP-TC2-18751


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG2-072 20.94% $1,057,868
AH1-055 32.35% $1,634,281
AH1-537 22.44% $1,133,839
AH1-664 4.14% $209,223
AH1-665 3.31% $167,392
AH1-721 16.81% $849,398

Cost Allocation details for n9761.0 / AEP-TC2-19056


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG2-184 42.62% $76,721
AH1-227 16.78% $30,207
AH1-617 40.60% $73,071

Cost Allocation details for n9762.0 / AEP-TC2-19058


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG2-184 51.22% $51,220
AH1-617 48.78% $48,780

Cost Allocation details for n9763.0 / AEP-TC2-19060


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG2-072 24.06% $793,888
AG2-184 9.30% $306,832
AG2-360 16.83% $555,293
AG2-363 8.73% $287,968
AG2-364 5.82% $191,979
AH1-617 8.86% $292,222
AH1-721 26.42% $871,818

Cost Allocation details for n9764.0 / AEP-TC2-19061


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG2-184 25.89% $1,035,670
AH1-072 3.80% $151,863
AH1-073 3.80% $151,863
AH1-227 9.74% $389,568
AH1-617 24.66% $986,328
AH1-721 32.12% $1,284,708

Cost Allocation details for n9765.0 / AEP-TC2-19065


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG2-184 25.89% $1,035,670
AH1-072 3.80% $151,863
AH1-073 3.80% $151,863
AH1-227 9.74% $389,568
AH1-617 24.66% $986,328
AH1-721 32.12% $1,284,708

Cost Allocation details for n9766.0 / AEP-TC2_19067


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG2-072 20.70% $227,664
AG2-104 16.19% $178,073
AG2-106 14.15% $155,673
AG2-107 14.15% $155,673
AG2-363 8.46% $93,036
AG2-364 5.64% $62,022
AG2-660 0.77% $8,502
AH1-044 6.65% $73,119
AH1-150 6.65% $73,119
AH1-151 6.65% $73,119

Cost Allocation details for n9767.0 / AEP-TC2-19068


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG2-072 20.74% $933,153
AG2-104 14.67% $660,025
AG2-106 12.89% $580,123
AG2-107 12.89% $580,123
AG2-363 10.27% $462,168
AG2-364 6.85% $308,112
AG2-660 1.14% $51,376
AH1-044 6.85% $308,307
AH1-150 6.85% $308,307
AH1-151 6.85% $308,307

Cost Allocation details for n9768.0 / AEP-TC2-19069


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG2-191 60.82% $182,450
AG2-192 39.18% $117,550

Cost Allocation details for n9769.0 / AEP-TC2-19070


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG2-072 35.05% $8,763,492
AG2-184 13.55% $3,387,027
AH1-617 12.90% $3,225,746
AH1-721 38.49% $9,623,735

Cost Allocation details for n9770.0 / AEP-TC2-19071


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG2-360 100.00% $500,000

Cost Allocation details for n9771.0 / AEP-TC2-19073


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG2-184 28.32% $1,132,681
AH1-072 4.24% $169,549
AH1-073 4.24% $169,549
AH1-227 10.87% $434,856
AH1-617 26.97% $1,078,738
AH1-721 25.37% $1,014,628

Cost Allocation details for n9772.0 / AEP-TC2-19074


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG2-518 68.28% $184,360
AH1-144 5.29% $14,290
AH1-145 8.29% $22,384
AH1-269 18.14% $48,966

Cost Allocation details for n9783.0 / AEP-TC2-19115


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG2-360 100.00% $100,000

Cost Allocation details for n9785.0 / AEP-TC2-19160


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG2-363 12.06% $25,967,214
AG2-364 8.04% $17,311,476
AG2-453 12.84% $27,643,470
AG2-524 5.82% $12,524,359
AG2-660 0.97% $2,078,646
AH1-044 8.30% $17,874,602
AH1-150 8.30% $17,874,602
AH1-151 8.30% $17,874,602
AH1-196 6.33% $13,625,461
AH1-338 7.55% $16,261,765
AH1-341 6.03% $12,983,607
AH1-543 6.56% $14,125,167
AH1-714 8.90% $19,155,030

Cost Allocation details for n9786.0 / AEP-TC2-19161


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG2-072 20.70% $620,901
AG2-104 16.19% $485,654
AG2-106 14.15% $424,563
AG2-107 14.15% $424,563
AG2-363 8.46% $253,734
AG2-364 5.64% $169,150
AG2-660 0.77% $23,187
AH1-044 6.65% $199,416
AH1-150 6.65% $199,416
AH1-151 6.65% $199,416

Cost Allocation details for n6183


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG2-176 59.52% $21,988,973
AG2-429 40.48% $14,957,714

Cost Allocation details for n7165.1


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG2-176 54.78% $234,179
AG2-429 45.22% $193,337

Cost Allocation details for n7165.2


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG2-176 54.78% $11,521,986
AG2-429 45.22% $9,512,537

Cost Allocation details for n7166.1


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG2-176 54.77% $505,509
AG2-429 45.23% $417,399

Cost Allocation details for n7166.2


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG2-176 54.77% $14,396,692
AG2-429 45.23% $11,887,375

Cost Allocation details for n7171.1


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG2-176 59.52% $9,081,290
AG2-429 40.48% $6,177,430

Cost Allocation details for n9717.0 / TC1-PH1-076


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG2-176 60.65% $31,439,237
AG2-429 39.35% $20,401,342

Cost Allocation details for n9733.0 / TC2-APS-015.a


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG2-582 100.00% $32,119,007

Cost Allocation details for n9734.0 / TC2-APS-036.a


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG2-176 100.00% $1,084,903

Cost Allocation details for n9735.0 / TC2-APS-016.a


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG2-582 100.00% $32,119,007

Cost Allocation details for n9736.0 / TC2-APS-015.b


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG2-582 100.00% $1,826,164

Cost Allocation details for n9737.0 / TC2-APS-016.b


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG2-582 100.00% $1,826,164

Cost Allocation details for n9738.0 / TC2-APS-016.c


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG2-582 100.00% $597,737

Cost Allocation details for n9227.0 / TC1-ATSI-001.b


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AH1-711 100.00% $48,873,856

Cost Allocation details for n9773.0 /


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AH1-261 100.00% $22,000,000

Cost Allocation details for n3515.1 / ce-017


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG2-516 20.54% $17,398,633
AG2-660 1.05% $887,563
AH1-044 9.01% $7,631,700
AH1-150 9.01% $7,631,700
AH1-151 9.01% $7,631,700
AH1-341 18.91% $16,021,714
AH1-564 32.47% $27,509,235

Cost Allocation details for n5318.1 / ce-012a


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG2-516 13.15% $21,556,046
AG2-660 0.67% $1,099,647
AH1-044 5.77% $9,455,299
AH1-150 5.77% $9,455,299
AH1-151 5.77% $9,455,299
AH1-196 35.99% $59,014,397
AH1-341 12.11% $19,850,112
AH1-564 20.79% $34,082,582

Cost Allocation details for n5792 / CE_NUN_L11323


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AH1-338 89.33% $9,361,442
AH1-341 10.67% $1,118,399

Cost Allocation details for n6260.2 / N6260.2


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG2-114 65.65% $328,247
AH1-541 34.35% $171,753

Cost Allocation details for n6779 / CE_NUN_L14609


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AH1-338 83.87% $4,696,829
AH1-341 16.13% $903,171

Cost Allocation details for n7023.1 / CE_NUN_L11124.1


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG2-660 3.17% $1,228,492
AH1-044 19.00% $7,370,513
AH1-150 19.00% $7,370,513
AH1-151 19.00% $7,370,513
AH1-338 18.43% $7,149,463
AH1-563 21.41% $8,307,780

Cost Allocation details for n9165.0 / CE_NUN_L15502.1


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG2-660 100.00% $1,220,445

Cost Allocation details for n9166.0 / CE_NUN_L16914.1


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AH1-341 100.00% $605,422

Cost Allocation details for n9172.0 / CE_NUN_L18623.2


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG2-660 1.08% $91,803
AH1-044 6.01% $510,546
AH1-150 6.01% $510,546
AH1-151 6.01% $510,546
AH1-338 71.48% $6,075,967
AH1-341 9.42% $800,591

Cost Allocation details for n9678.0 / CE_NUN_L11215_1


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG2-363 15.13% $1,362,006
AG2-364 10.09% $908,004
AG2-453 18.14% $1,632,886
AG2-660 1.27% $114,628
AH1-044 10.95% $985,765
AH1-150 10.95% $985,765
AH1-151 10.95% $985,765
AH1-338 10.02% $901,981
AH1-714 12.48% $1,123,200

Cost Allocation details for n9718.0 / CE_NUN_COLLINS_NEW CB


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG2-363 16.80% $2,604,692
AG2-364 11.20% $1,736,502
AG2-453 19.97% $3,095,612
AG2-660 1.36% $210,639
AH1-044 11.69% $1,811,428
AH1-150 11.69% $1,811,428
AH1-151 11.69% $1,811,428
AH1-714 15.60% $2,418,271

Cost Allocation details for n9719.0 / CE_NUN_COLLINS_TR


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG2-363 17.17% $2,678,959
AG2-364 11.45% $1,785,965
AG2-453 18.78% $2,930,385
AG2-660 1.38% $214,926
AH1-044 11.85% $1,848,377
AH1-150 11.85% $1,848,377
AH1-151 11.85% $1,848,377
AH1-543 5.79% $903,434
AH1-714 9.88% $1,541,202

Cost Allocation details for n9720.0 / CE_NUN_L1205-1


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG2-524 100.00% $2,800,000

Cost Allocation details for n9721.0 / CE_NUN_L95201_1


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AH1-564 100.00% $500,000

Cost Allocation details for n9722.0 / CE_NUN_TSS155_TR83


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG2-660 3.73% $567,009
AH1-044 32.09% $4,877,664
AH1-150 32.09% $4,877,664
AH1-151 32.09% $4,877,664

Cost Allocation details for n9754.0 / CE_NUN_TSS 111


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG2-660 3.23% $161,270
AH1-044 32.26% $1,612,910
AH1-150 32.26% $1,612,910
AH1-151 32.26% $1,612,910

Cost Allocation details for n9755.0 / CE_NUN_L17705_1


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG2-363 17.93% $2,509,701
AG2-364 11.95% $1,673,211
AG2-453 18.78% $2,628,701
AG2-660 1.44% $201,590
AH1-044 12.38% $1,733,584
AH1-150 12.38% $1,733,584
AH1-151 12.38% $1,733,584
AH1-714 12.76% $1,786,046

Cost Allocation details for n9784.0 / CE_L11103_2


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AH1-563 100.00% $6,500,000

Cost Allocation details for n7042 / dt6704r0001


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG2-380 100.00% $28,800,000

Cost Allocation details for n9774.0 /


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG2-447 100.00% $15,000,000

Cost Allocation details for n7615 / dom-187


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG2-426 100.00% $18,336,000

Cost Allocation details for n9221.0 / TC1-PH3-DOM-015-TC2


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG2-077 9.78% $201,196
AG2-171 3.35% $68,920
AG2-198 6.02% $123,866
AG2-213 4.47% $91,895
AG2-270 6.12% $125,997
AG2-341 1.61% $33,027
AG2-440 4.27% $87,777
AG2-441 6.43% $132,254
AG2-442 8.35% $171,840
AG2-522 2.04% $41,934
AG2-566 2.15% $44,277
AG2-581 7.46% $153,578
AG2-659 2.26% $46,485
AH1-314 1.18% $24,329
AH1-343 1.84% $37,956
AH1-439 9.23% $189,912
AH1-528 14.97% $307,970
AH1-546 8.46% $174,120

Cost Allocation details for n9643.0 / TC1-PH3-DOM-009-TC2


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG2-440 22.87% $89,552
AG2-441 34.45% $134,926
AG2-442 42.68% $167,165

Cost Allocation details for n9723.0 / TC2-PH1-DOM-0009


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG2-171 35.03% $56,045
AG2-213 46.70% $74,727
AH1-280 11.68% $18,682
AH1-396 6.59% $10,545

Cost Allocation details for n9724.0 / TC2-PH1-DOM-0011


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG2-171 35.03% $140,113
AG2-213 46.70% $186,819
AH1-280 11.68% $46,705
AH1-396 6.59% $26,363

Cost Allocation details for n9725.0 / TC2-PH1-DOM-2012


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG2-426 100.00% $20,960,000

Cost Allocation details for n9726.0 / TC2-PH1-DOM-2043


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG2-077 12.53% $442,733
AG2-151 1.37% $48,582
AG2-171 2.75% $97,022
AG2-198 3.63% $128,145
AG2-213 3.66% $129,362
AG2-270 12.54% $443,182
AG2-341 2.66% $93,867
AG2-440 3.97% $140,410
AG2-441 5.99% $211,550
AG2-442 7.22% $255,006
AG2-522 1.96% $69,114
AG2-566 1.72% $60,956
AG2-581 9.24% $326,635
AG2-583 1.42% $50,309
AG2-659 2.25% $79,434
AH1-343 4.14% $146,168
AH1-439 2.35% $83,058
AH1-528 18.53% $655,010
AH1-546 1.08% $38,316
AH1-687 0.99% $35,142

Cost Allocation details for n9727.0 / TC2-PH1-DOM-2091


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG2-077 17.43% $6,623,610
AG2-171 4.84% $1,839,830
AG2-198 7.54% $2,866,616
AG2-213 6.46% $2,453,107
AG2-270 11.58% $4,401,769
AG2-440 8.12% $3,086,851
AG2-441 12.24% $4,650,928
AG2-442 14.72% $5,594,619
AG2-522 3.52% $1,338,203
AG2-566 1.43% $544,277
AG2-659 4.04% $1,534,050
AH1-343 3.41% $1,296,411
AH1-439 4.66% $1,769,728

Cost Allocation details for n9728.0 / TC2-PH1-DOM-2076


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG2-077 9.78% $39,118
AG2-171 3.35% $13,400
AG2-198 6.02% $24,083
AG2-213 4.47% $17,867
AG2-270 6.12% $24,497
AG2-341 1.61% $6,421
AG2-440 4.27% $17,066
AG2-441 6.43% $25,714
AG2-442 8.35% $33,410
AG2-522 2.04% $8,153
AG2-566 2.15% $8,609
AG2-581 7.46% $29,860
AG2-659 2.26% $9,038
AH1-314 1.18% $4,730
AH1-343 1.84% $7,380
AH1-439 9.23% $36,924
AH1-528 14.97% $59,878
AH1-546 8.46% $33,854

Cost Allocation details for n9729.0 / TC2-PH1-DOM-2092


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG2-077 17.43% $6,623,607
AG2-171 4.84% $1,839,802
AG2-198 7.54% $2,866,577
AG2-213 6.46% $2,453,070
AG2-270 11.58% $4,401,831
AG2-440 8.12% $3,086,951
AG2-441 12.24% $4,650,918
AG2-442 14.72% $5,594,623
AG2-522 3.52% $1,338,194
AG2-566 1.43% $544,309
AG2-659 4.04% $1,534,027
AH1-343 3.41% $1,296,353
AH1-439 4.66% $1,769,739

Cost Allocation details for n9730.0 / TC2-PH1-DOM-2077


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG2-077 9.78% $78,236
AG2-171 3.35% $26,800
AG2-198 6.02% $48,166
AG2-213 4.47% $35,734
AG2-270 6.12% $48,994
AG2-341 1.61% $12,843
AG2-440 4.27% $34,133
AG2-441 6.43% $51,427
AG2-442 8.35% $66,821
AG2-522 2.04% $16,306
AG2-566 2.15% $17,217
AG2-581 7.46% $59,719
AG2-659 2.26% $18,076
AH1-314 1.18% $9,460
AH1-343 1.84% $14,759
AH1-439 9.23% $73,848
AH1-528 14.97% $119,755
AH1-546 8.46% $67,707

Cost Allocation details for n9731.0 / TC2-PH1-DOM-0010


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG2-171 35.03% $6,008,058
AG2-213 46.70% $8,010,786
AH1-280 11.68% $2,002,728
AH1-396 6.59% $1,130,427

Cost Allocation details for n9756.0 / TC2-PH2-DOM-009


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AH1-040 100.00% $7,500,000

Cost Allocation details for n9757.0 / TC2-PH2-DOM-005


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG2-171 5.21% $7,562,919
AG2-213 6.95% $10,083,893
AG2-341 0.35% $513,207
AG2-440 19.63% $28,496,340
AG2-441 29.58% $42,935,092
AG2-442 36.64% $53,194,270
AH1-280 1.64% $2,376,280

Cost Allocation details for n9758.0 / TC2-PH2-DOM-008


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AH1-040 100.00% $7,500,000

Cost Allocation details for n6480.1 / EKPC-tc1-r0002a


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AH1-664 43.67% $6,475,522
AH1-665 34.93% $5,180,417
AH1-666 21.40% $3,174,061

Cost Allocation details for n6834.1 / EKPC-tc1-r0001a


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG2-298 2.24% $127,897
AG2-424 82.01% $4,678,715
AH1-721 15.75% $898,387

Cost Allocation details for n7771.1 / r0013


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AH1-239 0.76% $266
AH1-721 99.24% $34,734

Cost Allocation details for n7771.2 / EKPC-tc1-r0014a


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AH1-239 0.76% $7,680
AH1-721 99.24% $1,002,320

Cost Allocation details for n7773.1 / EKPC-tc1-r0004b


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AH1-721 100.00% $345,000

Cost Allocation details for n8368.2 / EKPC-tc1-r0012b


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AH1-239 1.44% $149,233
AH1-721 98.56% $10,185,767

Cost Allocation details for n8368.3 / EKPC-tc1-r0012c


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AH1-239 1.44% $144
AH1-721 98.56% $9,856

Cost Allocation details for n8368.4 / EKPC-tc1-r0012d


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AH1-239 1.44% $505
AH1-721 98.56% $34,495

Cost Allocation details for n9687.10 / EKPC-tc2-nu053


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AH1-239 1.44% $4,837
AH1-721 98.56% $330,163

Cost Allocation details for n9739.0 / EKPC-tc2-nu046


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AH1-239 100.00% $4,215,000

Cost Allocation details for n9740.0 / EKPC-tc2-nu024


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AH1-664 55.56% $100,008
AH1-665 44.44% $79,992

Cost Allocation details for n9741.0 / EKPC-tc2-nu007


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AH1-664 55.56% $361,139
AH1-665 44.44% $288,861

Cost Allocation details for n9742.0 / EKPC-tc2-nu034


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AH1-239 93.63% $898,803
AH1-721 6.37% $61,197

Cost Allocation details for n9743.0 / EKPC-tc2-nu003


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG2-424 0.03% $6,656
AH1-239 2.76% $555,851
AH1-721 97.21% $19,567,493

Cost Allocation details for n9744.0 / EKPC-tc2-nu035


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AH1-664 55.56% $422,222
AH1-665 44.44% $337,778

Cost Allocation details for n9745.0 / EKPC-tc2-nu014


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG2-424 100.00% $120,000

Cost Allocation details for n9775.0 / EKPC-tc2-nu056


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AH1-721 100.00% $1,215,000

Cost Allocation details for n9776.0 / EKPC-tc2-nu054


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AH1-721 100.00% $1,215,000

Cost Allocation details for n9777.0 / EKPC-tc2-nu055


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AH1-721 100.00% $10,000

Cost Allocation details for n9778.0 / EKPC-tc2-nu047


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AH1-721 100.00% $10,000

Cost Allocation details for n9779.0 / EKPC-tc2-nu048


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AH1-664 55.56% $397,253
AH1-665 44.44% $317,747

Cost Allocation details for n9780.0 / EKPC-tc2-nu052


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AH1-239 1.44% $794
AH1-721 98.56% $54,206

Cost Allocation details for n9781.0 / EKPC-tc2-nu051


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AH1-239 1.44% $14,295
AH1-721 98.56% $975,705

Cost Allocation details for n9782.0 / EKPC-tc2-nu050


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AH1-721 100.00% $135,000

Cost Allocation details for n9759.0 / OVEC-TC2-19030


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG2-072 20.94% $7,994,732
AH1-055 32.35% $12,350,917
AH1-537 22.44% $8,568,877
AH1-664 4.14% $1,581,182
AH1-665 3.31% $1,265,049
AH1-721 16.81% $6,419,242

Cost Allocation details for n9787.0 / PECO_TC2_PH2_Chichester


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG2-380 27.45% $960,796
AH1-672 72.55% $2,539,204

Cost Allocation details for n6817.1


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG2-176 56.15% $68,868,417
AH1-460 43.85% $53,787,987

Cost Allocation details for n9760.0 / PECO_TC2_PH2


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AH1-552 100.00% $10,000,000

Cost Allocation details for n6818


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AG2-176 56.15% $1,066,801
AH1-460 43.85% $833,199

Cost Allocation details for n9715.0 / PSEG-TC2_PH1_LindenMinueR


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AH1-715 44.54% $4,008,153
AH1-722 55.46% $4,991,847

Cost Allocation details for n9716.0 / PSEG-TC2_PH1_MinueSewarenR


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AH1-715 44.54% $3,710,659
AH1-722 55.46% $4,621,341

Cost Allocation details for n9732.0 / PSEG-TC2-PHQ_LindenGen


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AH1-715 30.34% $1,125,063
AH1-722 69.66% $2,582,937

Cost Allocation details for n9751.0 / PSEG-TC2_PH1_LindenMinueQ


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AH1-715 44.53% $4,089,648
AH1-722 55.47% $5,093,352

Cost Allocation details for n9752.0 / PSEG-TC2_PH1_MinueSewarenQ


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AH1-715 44.53% $3,642,962
AH1-722 55.47% $4,537,038

Short Circuit Reinforcements

PJM performed short circuit analysis for the New Service Requests in Transition Cycle 2 Phase II System Impact Study. The table below shows all the system reinforcements identified from short circuit analysis.

TO RTEP ID / TO ID Title Time Estimate Total Cost Estimate ($) Projects with Cost Allocation Contingent Projects
AEP n9689.0

Replace 05TORREY1 breaker with a 138 kV 63 kA 3000A

Jun 01 2028
$1,000,000

AH1-680

AEP s2851 / S2851

New Carlisle 138 kV station

TBD
Contingent

AG2-562

APS n4854

Glen Falls SS: Circuit Breaker Replacements

TBD
Contingent

AG2-582

EKPC n9687.1

Cooper 161kV breaker replacements - Breaker 1064 DENNY

Dec 01 2029
$335,000

AH1-721

EKPC n9687.2

Cooper 161kV breaker replacements - Breaker 1008 XFMR

Dec 01 2029
$335,000

AH1-721

EKPC n9687.3

Cooper 161kV breaker replacements - Breaker 1014 WOLF CR

Dec 01 2029
$335,000

AH1-721

EKPC n9687.4

Cooper 161kV breaker replacements - Breaker 1039 BUS

Dec 01 2029
$335,000

AH1-721

EKPC n9687.5

Cooper 161kV breaker replacement - Breaker 1054 LAUREL

Dec 01 2029
$335,000

AH1-721

EKPC n9687.6

Cooper 161kV breaker replacements - Breaker 1079 TRANSF

Dec 01 2029
$335,000

AH1-721

EKPC n9687.7

Cooper 161kV breaker replacements - Breaker 110G UNIT 1

Dec 01 2029
$335,000

AH1-721

EKPC n9687.8

Cooper 161kV breaker replacements - Breaker 210G UNIT 2

Dec 01 2029
$335,000

AH1-721

EKPC n9687.9

Cooper 161kV breaker replacements - Breaker 1024 LIBERTY

Dec 01 2029
$335,000

AH1-721

Cost Allocation details for n9689.0


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AH1-680 100.00% $1,000,000

Cost Allocation details for n9687.1


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AH1-721 100.00% $335,000

Cost Allocation details for n9687.2


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AH1-721 100.00% $335,000

Cost Allocation details for n9687.3


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AH1-721 100.00% $335,000

Cost Allocation details for n9687.4


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AH1-721 100.00% $335,000

Cost Allocation details for n9687.5


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AH1-721 100.00% $335,000

Cost Allocation details for n9687.6


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AH1-721 100.00% $335,000

Cost Allocation details for n9687.7


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AH1-721 100.00% $335,000

Cost Allocation details for n9687.8


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AH1-721 100.00% $335,000

Cost Allocation details for n9687.9


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AH1-721 100.00% $335,000

Stability Reinforcements

PJM performed stability analysis for the New Service Requests in Transition Cycle 2 Phase II System Impact Study. The table below shows all the system reinforcements identified from stability analysis.

TO RTEP ID / TO ID Title Time Estimate Total Cost Estimate ($) Projects with Cost Allocation Contingent Projects
Dominion n9267.0 / TC1-PH2-DOM-067

Construct new 10.21 mile 115 kV line between Northern Neck and Moon Corner.

45 to 46 Months
Contingent

AH1-397

Dominion n9630.0 / TC1-PH3-DOM-013

Construct a new 230 kV line from the AG1-285 substation to the Finneywood 230 kV Substation. Expand AG1-285 substation and add two (2) new 230/115 kV transformers.

Dec 31 2029
Contingent

AG2-077, AG2-171, AG2-198, AG2-213, AG2-270, AG2-341, AG2-440, AG2-441, AG2-442, AG2-522, AG2-566, AG2-581, AG2-659, AH1-280, AH1-396, AH1-528

EKPC n9688.0 / EKPC-tc2-nu049

AH1-239 Tap (Clinton County)-Homestead New 69 kV Line (15 miles)

Dec 31 2028
$16,300,000

AH1-239, AH1-721

Cost Allocation details for n9688.0 / EKPC-tc2-nu049


Cost Allocation
Project Percent Allocation Allocated Cost ($USD)
AH1-239 96.88% $15,791,848
AH1-721 3.12% $508,152
The state in which the generator or merchant transmission facility is located.
The Transmission Owner of the facility where the New Service Request project interconnects to the transmission system.
Winter load flow analysis will be performed starting in Transition Cycle 2.

Note: Additional detail can be found in each of the individual TC2 New Service Request System Impact Study reports also available on PJM.com.